automated people mover (apm) - granicus
TRANSCRIPT
1
Automated People Mover (APM)Landside Access Modernization Program (LAMP)
Board of Airport Commissioners (BOAC) – Update #1November 1, 2018
2
Automated People Mover (APM)
Agenda• APM DBFOM Project
Project Overview Design and Construction Status Vehicle Manufacturing and Assembly Status Overall Project Schedule Financial Summary Inclusivity and Workforce Development
Performance Project Management Focus
4
Automated People Mover (APM)
Design and Construction Status• Commercial Close April 2018
• Financial Close June 2018
• NTP 1 issued in July 2018
• Design Progress 33%
• NTP 2 forecast in December 2018
• Construction – Utility Relocations and Demolition (after NTP 2)
• M&SF Clearing & Grubbing Starts Jan 2019, Grading Feb. 2019
• West CTA, East CTA & ITF W Station Foundations Start July 2019
5
Automated People Mover (APM)
Vehicle Manufacturing & Assembly Status
• Bombardier - INNOVIA APM 300(44 cars)
• Exterior - End Cap, Skirts, Windows approved
• Delivery Plan a) Mfg & Assembly in Mexicob) Testing in Canada
• Preliminary Design Audit - Dec 2018
• 1st Vehicle at LAX - Dec 2020
7
Automated People Mover (APM)
Project Progress (through Sept 2018)
11.4% Complete
Source: LINXS September, 2018 LTA Report
8
Automated People Mover (APM)
Design & Construction Period Cash Flow
Excludes TO-001, O&M Costs, and Contingency
10
Automated People Mover (APM)
LAWA Payment Summary
Payment Type Total # of Payments Total $ # of Payments
Made Paid $
Milestone Payments 6 $1,009,749,091
Additional D&C Payments 4 $21,520,825 1* $2,152,083
Approved Task Orders –1 (Allowances) 6 $13,950,000
Approved Change Orders - 0 0 $0
Total $1,045,219,916 $2,152,083
*1st Payment Issued on October 30, 2018
D&C Capital Cost SplitLAWA Payments $1,045,219,916
LINXS Financing $939,444,730
Total D&C $1,984,664,646
11
Automated People Mover (APM)
Change Management
• Change Orders• Request for Change Proposals
o Partneringo Parking Structure P3 Internal Circulation
• AllowancesItem Budget Authorized Committed
Streetscape, Landscape, Public Realm $6,000,000 $6,000,000 $0
Hazmat $3,700,000 $3,700,000 $0
Art Accommodations $15,000,000 $15,000,000 $0
Guideway Modifications $118,450,000 $13,950,000* $13,950,000*
*TO-001
JA
12
Automated People Mover (APM)
Inclusivity & Workforce Development – Design SummaryBUSINESS INCLUSION REQUIREMENTS
Item SBE LBE LSBE DVBE
DESIGN (Total Budget $136,248,420)
Requirement 22%$29,974,652
8%$10,899,874
3%$4,087,453
3%$4,087,453
$ Committed17%
$23,720,183 24%
$33,375,929 13%
$17,574,237 2%
$2,412,241
$ Paid to Date* $1,683,073 $3,553,405 $ 1,339,769 $65,168
Source: LINXS September, 2018 monthly report * Paid to Date amounts through June 2018
*Total Design Paid to Date $14,304,936
AE
13
Automated People Mover (APM)
Inclusivity & Workforce Development - ActualsWORKFORCE INCLUSION REQUIREMENTS
Item Local HireConstruction
Requirement 30% of total workers
Actual Percentages 36% of total workers
Local Hires / Total Workers 60 / 168
Total Wages Earned $1,787,254
As validated by PLA Administrator – 10/26/18
14
Automated People Mover (APM)
Project Management Focus
• PMO• Partnering• Baseline Schedule
Approval• Vehicle Manufacturing• Interface Coordination• Construction Impacts
within the CTA