BHARUCH CIVIL ENGINEERS FORUM
Organises
A PRESENTATION ON
TECHNICAL ISSUES INVOLVED IN WEIR CUM CAUSEWAY ON RIVER NARMADA TO ARREST SALINITY DUE TO BACK (SEA) WATERS and AUGMENTING SURFACE TRANSPORTATION FACILITY BETWEEN BHARUCH & ANKLESHWAR By MK BAROT, Member BCEF Thursday, 17th July, 2003
MOTIVES AND OBJECTIVES OF BCEF
UNLIKE THE “BIG BROTHER” ROLE, BCEF AIMS TO EXTEND A HELPING HAND WITH FUTURISTIC VISION TO LOCAL ADMINISTRATION FOR BETTERMENT OF CIVIC LIFE IN THE REGION.
TAPPING OF TECHNICAL RESOURCES.
TO CREAT ENVIRONMENT CONSCIOUSNESS & QUALITY AWARENESS IN CONSTRUCTION FIELD.
TO SET UP RURAL DEVELOPMENT CELL
CONDUCTING BRAIN STORMING TECHNICAL SESSIONS
MAJOR CAUSE OF CONCERN FOR CITIZENS OF BHARUCH AND ANKLESHWAR
NATURE’S FURY : SALINITY INGRESS – Water-rich region reduced to water-scarce
region.
WATER WOES : ACTUTE DRINKING WATER PROBLEM.
GRINDING HALT : SUDDEN SHUTDOWN OF PLANT. MISSING LINK BETWEEN TWIN CITIES :
STRATEGICALLY IMPORTANT CENTURY OLD GOLDEN BRIDGE HAS OUTLIVED ITS USEFUL LIFE.
SALINITY : BRUNT OF DOUBLE EDGE SWORD FACED BY
THE REGION.
MANAGING FINITE SUPPLY OF NATURE’S BOUNTY :
LIMITED INCOMING WATER AFTER UPCOMING OF DAM AND INCREASED RATE OF SALINITY ON ACCOUNT OF GLOBAL GEOLOGICAL CHANGES.
AS PER THE INFORMATION COLLECTED FROM CENTRAL WATER COMMISSION OFFICE – RATE OF FLOW IN NARMADA RIVER NEAR GADURESHWAR IS AROUND 180 Cu.M/ Sec. I.e. 15552 MLD.
POUND OF FLESH :RIPEARIAN RIGHTS OF THE REGION TO BE REVIEWED.
SWEET WATER REQUIREMENT :
1 ANKLESHWAR GIDC 100 MLD
2 PANOLI GIDC 100 MLD
3 JHAGADIA GIDC 075 MLD
4 ANKLESHWAR CITY 025 MLD
5 BHARUCH CITY 035 MLD
6 GNFC 100 MLD
7 NTPC 075 MLD
8 GPEC 075 MLD
9 VIDEOCONE 075 MLD
10 IPCL 075 MLD
11 BIRLA COPPER 075 MLD
12 GACL 075 MLD
13 INDL. AT DAHEJ 120 MLD
14 TOTAL 1000 MLD
MISSING LINK : EXISTING CONDITION OF SURFACE
TRANSPORTATION BETWEEN TWIN CITIES ? IN HOT WATER ??
120 YEAR OLD GOLDEN BRIDGE : HIGH TIME TO FIND OUT SUBSTITUTE OF HERITAGE
STRUCTURE DUE TODETRIORATED FOUNDATION CONDITION
NEED OF THE DAY : WIDE SPREAD INDUSTRIAL GROWTH RESULTED IN
TO INCREASED TRAFFIC VOLUME CALLS FOR A FULL PROOF LINK.
A PANEL DISCUSSION ON AUGMENTATION IN CONNECTIVITY BETWEEN BHARUCH & ANKLESHWAR STRENGTHENING OF GOLDEN BRIDGE OR NEW BRIDGE ?
Sunday, 30th September, 2001
Organised By BHARUCH CIVIL ENGINEERS FORUM
ABSTRACTS OF CONCLUDING REMARKS
120 YEAR OLD GOLDEN BRIDGE TO BE TREATED AS MONUMENT AND SHOULD BE PRESERVED AS HERITAGE STRUCTURE
TECHNICAL INVESTIGATION TO BE CARRIED OUT FOR ASCERTAINING THE CONDITION OF BRIDGE FOUNDATION
WEIR CUM CAUSEWAY : - TO SOLVE PROBLEM OF POTABLE WATER BY ARRESTING SALINITY DUE TO SEA WATER - TO IMPROVE EXISTING SURFACE TRANSPORTATION FACILITY
RIVER SIDE DEVELOPMENT AS A RECREATIONAL SPOT WHICH WILL HELP IN GENERATING FUND FOR PROJECT
NECESSITY OF WEIR CUM CAUSEWAY ON RIVER
RETIREMENT OF THE CENTURY OLD BRIDGE
CATERING THE NEED OF INCREASED TRAFFIC VOLUME
TO ARREST THE SALINITY INGRESS IN RIVER WATER DUE TO BACK FLOW FROM SEA
CREATION OF SWEET WATER RESERVOIR ESPECIALLY IN VIEW OF THE LIMITED QUANTITY OF INCOMING WATER DUE TO SARDAR SAROVAR PROJECT
INTRODUCTION OF WEIR CUM CAUSEWAY
WEIR : WEIR IS AN IMPERVIOUS BARRIER ACROSS A RIVER TO RAISE THE WATER LEVEL ON ITS UPSTREAM AND TO ARREST BACKWARD FLOW OF WATER FROM DOWN STREAM
CAUSEWAY : A CAUSEWAY IS SMALL SUBMERSIBLE BRIDGE. IT IS ALSO KNOWN AS AN IRISH CAUSEWAY OR DIP
TYPES OF CAUSEWAY : 1 LOW LEVEL CAUSEWAY (LLC) - Without Opening 2 HIGH LEVEL CAUSEWAY (HLC) - With Opening
REQUISITE CONDITIONS FOR WEIR CUM CAUSEWAY
DEPTH OF WATER : SEASONAL FLOW OF WATER SHOULD BE VERY LESS
HIGHEST FLOOD DISCHARGE : FLOW IN THE STREAM SHOULD NOT BE FOR MORE THAN 8 TO 10 DAYS IN A YEAR AND FOR ABOUT 4 TO 5 HOURS DURING THESE DAYS
NORMAL FLOOD DISCHARGE : IT SHOULD NOT BE MORE THAN 40 % OF HIGHEST
FLOOD DISCHARGE
SALIENT & BROWNIE POINTS WEIR CUM CAUSEWAY ACROSS RIVER NARMADA
+ INDUSTRIAL DEVELOPMENT :UNINTRUPETED & SUSTAINED INDUSTRIAL GROWTH.
+ AGRICULTURAL DEVELOPMENT :OPTIMUM UTILIZATION OF LAND FOR IRRIGATION.
+ FISHERIES FRIENDLY PROPOSAL :DISCHARGE OF SWEET WATER ON DOWNSTREAM OF
WEIR SHALL BE SAME AS EARLIER.
+ DEVELOPMENT OF BOATING, RECREATIONAL & NAVIGATIONAL FACILITIES
ADVANTAGES OF WEIR CUM CAUSEWAY - 1
+FOREMOST & BEST WAY OF CONSERVATION OF PRECIOUS NATURAL RESOURCE
+CAN BE USED AS A MEANS OF SURFACE TRANSPORTATION
+ARREST SALINITY DUE TO BACK FLOW FROM SEA WATER
+CREATION OF RESERVOIR FOR PRESERVATION OF SWEET WATER
+PRESERVATION OF UNDERGROUND (SUB SOIL ) SWEET WATER
ADVANTAGES OF WEIR CUM CAUSEWAY - 2
+RISE OF WATER TABLE OF SURROUNDING REGION WHICH WILL, IN TURN, REDUCE THE PUMPING COST
+DEVELOPMENT OF FISHERIES WHICH CAN GENERATE SELF- EMPLOYMENT OPPORTUNITIES
+DEVELOPMENT OF BOATING & RECREATIONAL FACILITIES
+OPTIMIZATION OF RIPARIAN RIGHTS
+CAN BE USED FOR NAVIGATIONAL PURPOSE
SPECIFIC ADVANTAGES OF SELECTING SITE OF CAUSEWAY NEAR GOLDEN BRIDGE
+ ROAD LINK ON BOTH THE ENDS AVAILABLE.
+ MINIMUM RIVER TRAINING WORKS REQUIRED.
+ WILL NOT AFFECT FISHERMAN’S BUSINESS.
+ SERVES DUAL PURPOSE OF SURFACE TRANSPORTATION AS WELL AS ARRESTS SALINITY
+ PICKNIC SPOT CAN BE CREATED ADJOING TO GOLDEN BRIDGE : A HERITAGE MONUMENT.
SHORTCOMING OF WCC AS COMPARED TO BRIDGE
MUCH COSTLIER OPTION (Both Initial Project Cost as well as Maintenance Cost )
RIVER TRAINING WORKS
SILTING PROBLEM IN BASIN
HIGH COST OF DREDGING
HIGH MAINTENANCE COST DUE TO LIKELY DAMAGES DURING FLOODS
SERVICES RENDERED BY :
CONSTRUCTION AGENCY : M/s LARSEN & TOUBRO LIMITED ECC CONSTRUCTION GROUP
DESIGN CONSULTANT : M/s MULTI MEDIA CONSULTANT
PROJECT MANAGEMENT CONSULTANT : M/s DALAL CONSULTANT
PROJECT ENGINEER - IN- CHARGE : Mr. PC SHAH, CITY ENGINEER, SMC
OVERALL COORDINATION : HAJIRA AREA INDUSTRIES ASSOCIATION
TECHNICAL PROFILE OF WCC at SURAT - 1
1LENGTH OF THE WEIR( The Portion Without Gate & With Gate )
In all 580 Meters
2 WIDTH OF THE CREST10 Meters having6 Meters RL
3 FRL( Up to the top of the gate ) 5 Meters
4 WATER STORAGE CAPACITY310 Lacs Cubicmetersi.e. 6822 Million gallons
5GATES ( SEAL LEVEL ) - SELF OPERATIVE 150 Meters Length
Such 16 Nos.
6 FLOOD GATES AT BOTH ENDS10 x 5.2 Meters each of14 Meter Height
7 RL OF RIVERBED ( - ) 1.9 Meters
TECHNICAL PROFILE OF WCC at SURAT- 2
8 DESIGNED DISCHARGE 24000 Cusec
9 LENGTH OF RESERVOIR30 Kms.Area : 18 Square Kms
10CAUSEWAY DIMENSIONS Total Top Width - 10 Meter
3.5 Meter Wide x 2 Lanes
11FOOTPATHDIVIDER/CURB
1 x 1.80 Meter1.20 Meter
12 CONSUMPTION OF CEMENT- CONCRETE 86,000 Cubic Meters
13 CONSUMPTION OF CEMENT6,24,000 Bags i.e. 31,200 MTs
14 CONSUMPTION OF STEEL 1100 MTs
TECHNICAL PROFILE OF WCC at SURAT- 3
15PROTECTION WORKSAPRON BLOCK - 1.5 x 1.5 x 0.9 Meter size
7300 Nos. of 5 MT weight each
16 RIPARIAN RIGHT OF SMC 300 Cusec
17 TOTAL COST OF LIGHTING & ILLUMINATION Rs. 16 Lacs
18 CAUSEWAY UTILIZATION PERIODMore than 10 Months in a year
19 TOP LEVEL OF CAUSEWAY 6.00 RL
20 TOP RL OF HIGH TIDE LEVEL 4.00 RL
21 TOP RESERVOIR LEVEL 5.00 RL
FAVOURABLE CONDITIONS FOR CONCEIVING SURAT PROJECT
1 ACUTE SHORTAGE OF WATER FOR CATERING THE NEEDS OF SURAT CITY
2 HIGHLY DEVELOPED INDUSTRIAL ZONE WHICH CALLS FOR RELIABLE & PERENNIAL WATER SUPPLY
3 DRAWING OF WATER FROM UKAI / KAKARAPAR CANAL - HIGHLY COSTLY AFFAIR
4 TOTAL WATER SUPPLY DISRUPTED DURING CANAL MAINTENANCE WORK EVERY YEAR
5 TOPOGRAPHY AND SUBSOIL CONDITIONS
6 HIGH & FIRM EMBANKMENTS WITH MINIMUM BED WIDTH OF RIVER SECTION
MAJOR CONTRIBUTING INDUSTRIAL GIANTS
RELIANCE INDUSTRIES LTD
ESSAR GUJARAT LIMITED
NATIONAL THERMAL POWER CORPORATION LTD.
OIL & NATURAL GAS COMMISSION
INDIAN OIL CORPORATION
RAMA NEWS PRINT & PAPER LIMITED
GUJARAT INDUSTRIAL DEVELOPMENT CORPORATION
CYANIDES & CHEMICALS COMPANY
LARSEN & TOUBRO LIMITED
GAS AUTHORITY OF INDIA LIMITED
THE GOVERNING FACTORS FOR COST ECONOMICS AND FUND RAISING FOR IMPLEMENTATION OF WCC PROJECT ON RIVER NARMADA
LENGTH OF CAUSEWAY : Approx. 1400 Meters ( 580 Meters)
ESTIMATED COST: Approx. 125 Crores ( 35 Crores )
FUND RAISING : Contribution is expected from approx. 5-7 major Industrial sectors (10 mega Industrial units ) Like GNFC, IPCL, ONGC, GIDC, NTPC, Torrent, Birla Copper
ALMOST EVERY INDUSTRY HAS THEIR PERMANENT WATER SUPPLY SCHEME ON NARMADA RIVER ITSELF
THE TOP PRIORITY OF OUR PROJECT IS SURFACE TRANSPORTATION AS WELL AS PRESERVATION OF SWEET WATER.
RAISING OF FUND FOR CIVIC PROJECT
1) ISSUE OF NON CONVERTIBLE BONDS JOINTLY BY LOCAL CIVIC BODY AND FORMING –
" BHARUCH –ANKLESHWAR DEVELOPMENT BOARD"
2) GOVERNMENT SHOULD OWN THE PROJECT AND EXECUTE WITH EITHER WITH THE HELP FROM WORLD BANK OR ON BOT BASIS
3) CONTRIBUTION FROM THE INDUSTRIES LOCATED IN THE REGION
4) DEVELOPMENT OF RIVER SIDE BANKS AS A PICNIC SPOT
5) REVENUE TO BE GENERATED FROM FISHERIES BUSINESS
SALIENT FEATURES OF NCB ISSUED BY AHMEDABAD MUNICIPAL CORPORATION FOR RAISING OF FUND FOR CIVIC PROJECTA) NON CONVERTIBLE BONDS ISSUED IN THE YEAR 1998. Fund Raised : Rs. 100 Crores. Duration : 7 Years Nature of Bond : Public Bond. Rate of Interest : 14 %.
B) TAX FREE NON CONVERTIBLE BONDS TO BE ISSUED IN MARCH 2002.
Fund to be Raised : Rs. 100 Crores. Duration : 10 Years.Nature of Bond : Premium Tax Free & shall be open to only
Selected Financial Institutions.Price of the Bond : Rs. 1.0 lac per Bond. Rate of Interest : 9.09 %.Status of Bond : Prerequisite clearance for NCB has been
acquired from Central as well as State Government. Purpose : Finance generated by the bond would be used for projects like bridges, fly overs, water supply & sewerage, roads etc.