banebranchen - den danske · pdf file→ 10 extra trains per direction ... strategic level...
TRANSCRIPT
New Line Copenhagen-Ringsted
- 60 km electificated railway
- Speed up to 250 kph
- ~ 90 bridges, 220 constr.’s
- 3.300.000 m3 earthworks
- > 900 utilities replaced
- > 1200 expropriations
→ 10 extra trains per direction
→ Shorter trip time
→ Better punctuality
- Fully TSI-compliance!
Project vision
”We will construct the New Line Copenhagen-
Ringsted to a European Best-in-Class standard
through purchasing in a competitive market and
by leveraging economies of scale and
by using state-of-the-art technology in the life
cycle perspective”
- Learning how it was done best!
Projects contribution to “The future railway”
– More Design-and-build contracts
– Succesfull contract negotiations
– Incentives
- Underlined in McKinsey budget analysis
Influences BDK readiness!!
Organizational levels, planned
Strategic Level
BDK’s project director and managers (management group)
Tactic Level
BDK’s project management and suppliers project management
Operational Level
Consultants, contractors, suppliers
Client
Organizational levels, daily business
Strategic Level
BDK’s project director and managers (management group)
Tactic Level
BDK’s project management and suppliers project management
Operational Level
Consultants, contractors, suppliers
Client
Organization NLCR
Project Board
Project Director
Construction
Safety management
Secretariat
Finance and Plan
Change Board
Contractors, consultants, suppliers
PM
Urban
PM
North
PM
West
PM
South
PM
Rail
Safety
– Use of Danish Railway Norms and Standards
– Use of TSI
– Cross-acceptance
Safety fencing in Germany, Hamburg-Berlin
Safety fencing at platforms
Why 3D-models?
– Tender phase
o - time consuming and expensive for the tenderers
o + better understanding of the project – risk minimizing/better
price
– After contracting
o Risk (overview of methods and work procedures)
o Time / logistics
o Amounts (handling of claims/extra works)
o Executing (machine controlling, control measurements, spoil
areas)
o As built (documentation of amounts etc. for maintenance)
Banedanmark’s 3D-models Tender material
Spoil area
Ground water
level
Clearance for
roads
Road surface
Retaining
wall
Clearance for rail
Bridge profile
Control of construction works (QA, specific element)
Supervision Testing Transfer to
O&M
CAD-3Dm CAD manager
As-built DB Project support/CAD
Maintenance manual
Component list and
”Mangelliste” fulfilled
Maintenance org + skills (education)
”Hand over” to
Teknisk drift BDK Project manager
BDK as-built archive
SI-DB Safety manager
Hazard log – safety requirements
Safety related application
conditions
Central Hazard Log Safety in O&M
Information
– Neighbour letters
– Newsletters / Homepage
– Traffic info
– Info meetings
– Announcments
– Press
– Signs
– ”Open project”
Lessons learned
- Errors acceptable, but not to repeated to often!!
• Norms for 250 kph (e.g. transition zones)
• Road traffic (regulations) during construction works
• As-is existing constructions/installations/registrations
• Ground water not as predicted
• Drainage and fees
• 3. part works (utility replacements)
• Validation of detailed design (also CSM in general)
• NLCR-organization proactive, framework often reactive
• Extended time schedule (e.g. construction sites)