  • 8/10/2019 BG-Progressing Summary 4-12-2014

    1/1

    ID Task Name Start Finish DurationQuantity

    achieved

    Total

    QuantityRemarks Complete

    4/9/2014 7/9/2014 14/9/2014 21/9/2014

    4 5 6 7 8 9 10 1 1 12 1 3 14 1 5 16 1 7 18 1 9 20 2 1 22 2 3 24 2 5

    1 CONSTRUCTION OF PARKING, BANSRA GALI 4/9/2014 24/12/2014 112.0 d. - - - 66.0%

    2 Drains Terrace-1 8/9/2014 29/9/2014 22.0 d. 365 RFT 365 RFT Curb stones remaining 81.0%

    3 Drains Terrace-2 10/9/2014 23/9/2014 14.0 d. 200 RFT 200 RFT Curb stones in progress 80.0%

    6 Earth Reinforcement T-1 5/9/2014 24/9/2014 20.0 d. 92 RFT 92 RFT Completed 100.0%

    7 Earth Reinforcement T-2 7/9/2014 22/9/2014 16.0 d. 172 RFT 172 RFT Completed 100.0%

    8 Coffee Shop T-2 8/9/2014 23/10/2014 46.0 d. - - Fixtures a nd finishing remaining 70.0%

    9 Gazebo T-2 8/9/2014 18/10/2014 41.0 d. - - Floors, fixtures and finishing remaining 64.4%

    10 Gazebo T-1 15/9/2014 25/10/2014 41.0 d. - - Floors, fixtures and finishing remaining 56.9%

    9 Water Tank T-1 4/9/2014 18/9/2014 15.0 d. - - Completed 100.0%

    10 Septic Tank 1/10/2014 13/10/2014 13.0 d. - - Completed 100.0%

    11 Pavement T-1 21/9/2014 15/12/2014 86.0 d. - 20000 sqft. Stone pavement in progress. Grassing remaining 10.0%

    12 Pavement T-2 24/9/2014 5/12/2014 73.0 d. - 10000 sqft About 10% stone flooring & 90% Grassing remainnig 85.0%

    13 Exit Road 4/9/2014 27/9/2014 24.0 d. 750 RFT 750 RFT JRCP completed. Filling of joints remaining 96.8%

    14 Common Road 12/9/2014 22/9/2014 11.0 d. 250 RFT 250 RFT JRCP completed. Filling of joints remaining 96.0%

    15 Entrance Road 28/9/2014 7/10/2014 10.0 d. 525 RFT 525 RFT JRCP completed. Filling of joints remaining 96.0%

    16 Toilets T-1 28/9/2014 25/10/2014 28.0 d. - - Phenolic paneling, stone flooring & fixtures remaining 75.2%

    17 Toilets T-2 15/10/2014 4/11/2014 21.0 d. - - Phenolic paneling & fixtures remaining 80.0%

    18 Paragola T-2 25/9/2014 10/10/2014 16.0 d. - - Stone flooring & chemical treatment of timber remaining 80.0%

    19 Control Room 20/9/2014 11/10/2014 22.0 d. - - Stone flooring & chemical treatment of timber remaining 60.0%

    20 Gaurd Room T-1 25/9/2014 5/10/2014 11.0 d. - - Stone flooring & chemical treatment of timber remaining 72.7%

    21 Gaurd Room T-2 5/10/2014 18/10/2014 14.0 d. - - Stone flooring & chemical treatment of timber remaining 80.0%

    22 Entrance Booth 14/10/2014 24/10/2014 11.0 d. - - Stone flooring, fixtures & chemical treatment of timber remaining 50.0%

    23 Exit Booth 24/10/2014 3/11/2014 11.0 d. - - Stone flooring, fixtures & chemical treatment of timber remaining 45.0%

    24 Walking Track 6/9/2014 16/9/2014 11.0 d. 250 RFT 250 RFT Concreting & stone flooring remaining 30.0%

    25 Wooden Railing 5/10/2014 15/12/2014 72.0 d. 700 RFT 700 RFT - 81.3%

    26 Wooden Railing T-1 18/10/2014 15/12/2014 59.0 d. 500 RFT 500 RFT 50% fixing &90% chemical treatment remaining 61.9%

    27 Wooden Railing T-2 5/10/2014 4/12/2014 61.0 d. 200 RFT 200 RFT Completed 100.0%

    28 Retaining Wall 6/9/2014 24/12/2014 110.0 d. - - 20% remaining 80.0%

    29 M ain En tr anc eGa te 25/ 11/ 2014 20/ 12/ 2014 26. 0d. - - Foundation completed. 12.0%

    30 Procurement Items 20/9/2014 10/11/2014 52. 0d. - - 80% Eq uip me nt pro cu red and del iv er ed at si te 48.8%

    31 Electrical & IT Equipment 20/9/2014 25/10/2014 36.0 d. - - 2 0% t ra ns po rt at io n an d 10 0 % In st al la ti on , te st in g an d co mm is si on in g 8 4. 3%

    32 Main Boards & Distribution Boards 20/9/2014 25/10/2014 36.0 d. - - Inst allation, testing and commissioning remaining 80. 0%

    33 Transformer 22/9/2014 15/10/2014 24.0 d. - - No action so far 0.0%

    34 AMF/ATS for 60 KV DG Set 30/9/2014 25/10/2014 26.0 d. - - No action so far 0.0%

    35 Sanitary F ixing & Fixtures 20/10/2014 10/11/2014 22.0 d. - - 40%procurement/transporta tion ;insta l la tion inp rogress;testing&commission ing rema ining 50 .5%