bill palazzi, palazzi rail - the automatic train protection (atp) program
TRANSCRIPT
ATP / ETCS in SydneyInvesting in technology to improve commuter
safety and service reliability
Bill Palazzi, palazzirailTechnical Manager, TfNSW Advanced Train
Control Systems Program
11 August 2014
Drivers of the current ATP
programme
• Waterfall Rail
Accident and Report
of the Special
Commission of
Inquiry
• Safety benefit for
customers
• Enabler for future
capacity
improvements
The ATP journey thus far …
3
DATE ACTIVITIES
2006 • Recommendation that RailCorp implement an ATP system
2008 • ETCS Level 1 Pilot Trial Complete
2010 • Funding approved for first ATP Package
2011 • Contract for supply of first package awarded to Alstom
• ATP works begin on Main North Line
2012 • Contract for installation of equipment on Oscar trains awarded to Alstom
• RailCorp System Testing 1
• Consolidated Train Operating System (TOS) rollout
2013 • RailCorp System Testing 2
2014 /
2015
• Oscar Fleet Rollout
• Tangara Fleet Rollout
Why reconsider the approach to
ATP deployment?
5
• To align with the direction set out in Sydney’s Rail Future
• The current funding approval only deals with part of the network.
• It would also be desirable to leverage off the investment in ATP for performance improvements as well as safety.
• Need to provide for higher performance at train frequencies of 20 per hour on key corridors. Advanced systems will be a key component in achieving this.
• Need for replacement of large, life expired signalling installations.
• Technology has changed – ETCS Level 2 is now a reality.
6
Objective of any Rail Systems
initiative
• Any strategy for rail systems must align with the vision
for Sydney’s Rail Future and contribute to TfNSW’s
Strategic Business Requirements:
– Safety – enhance and maintain safety for passengers, staff and
others
– Cost – reduced project, operational and maintenance costs
– Capacity – optimise the capacity of the network, to meet service
requirements
– Carbon – move towards intelligent systems that optimise train
movements to reduce energy consumption
– Customer Satisfaction – improve reliability, provide a platform
to support initiatives such as consolidated control.
7
System Options
Existing (train stops)
Intermittent ATP +
Resignal
Intermittent ATP Overlay
Continuous ATP Overlay
System defined by existing signalling. ATP simply takes
the place of trainstops.
Existing system is optimised to achieve full benefits of
ATP – for example, removal of overlaps, removal of
signals possible (if in-cab).
Continuous ATP +
In-Cab + moving block
Continuous ATP +
In-Cab + ATO + moving
block
Continuous ATP +
In-Cab + ATO + moving
block + ATR / ATS
Moving block results in minimal trackside equipment (no track circuits required).
Control of trains by
driver. SPAD protection is
reactive (trainstops).
Driver drives, but speed
profile enforced by the system. Authority
from lineside signals.
Driver may be present but automatic
operation is possible, to
limits enforced by
ATP.
Driver drives, but speed
profile enforced by the system. Authority
from lineside or in-cab.
Driver may be present but automatic
operation is possible, plus
dynamic regulation of
trains.
Continuous ATP +
Resignal
Continuous ATP +
In-Cab + ATO + Resignal
Continuous ATP +
In-Cab + ATO + virtual blocks
Continuous ATP +
In-Cab + virtual blocks
Fixed blocks remain, but are augmented using virtual
blocks to provide increased capacity.
Continuous ATP +
In-Cab + ATO + virtual
blocks + ATR /ATS
Continuous ATP +
In-Cab + ATO + Resignal +
ATR /ATS
Scope of existing ATP project
Scope of proposed L2 trial
To be implemented on NWRL
Variants of ETCS L1
Variants of ETCS L2
Variants of ETCS L3 /
CBTC
Note: ‘In-Cab’ refers to in-cab signalling
Increasing Automation
Sim
ple
r Si
gnal
ling
Existing
Signalling
in Sydney
Ideal, long
term target
8
Long term vision for systems
Real-time
service data to
passengers
Trains operate
when scheduled.
Automatic Train Operation provides
increased capacity and smoother
travelAdditional capacity provides
opportunities for freight.
Safety ensured by on-board
Automatic Train Protection
Energy use is
optimised
Capacity
maximised
through moving
block systems
Reduced trackside
infrastructure, increased
worker safety
Costs reduced through
standardisation and automation.
Effective management of
incidents to allow the network
to keep operating.
Systems are easily
upgraded with no
operational impact.Self healing
systems minimise
impacts of failure.
Anticipated benefits from moving to
cab signalling
Strategic Business
Requirement
Advanced Train Control Systems Contribution
Safety • SPAD protection
• Overspeed protection
• Maintenance worker safety
Cost Simplified trackside infrastructure leads to
• Lower capital costs
• Lower operational and maintenance costs
Capacity • Consistency in train behaviour
• Reduced platform re-occupation times
• Increased capacity
Carbon • Optimised energy consumption for trains
• Reduced energy consumption by trackside infrastructure
Customer Satisfaction • Higher performance / higher reliability services
• Lower operational impact during project work
• Reduced journey times
9
Simplified trackside infrastructure
13
ETCS Level 2 requires:
• Train detection (track
circuits or axle counters)
• Balises (for odometry
correction)
• Point machines and
detection
Cab signalling
14
Benefits will include:
• Lower capital costs – typically put at 40% or less of the equivalent
conventional arrangement
• Lower maintenance costs
• Less need for workers to be trackside = higher levels of safety
The difference this could make …
15
Top signalling failure categories , Oct – Dec 2011
Not required with
cab signalling
Potential to use axle
counters to provide
higher reliability
braking distance overlapsighting
Emergency braking applied by trainstop if necessary, to stop train within overlap
Line speed
Stopped
Normal operation at service braking, to stop at red signal
Train must clear this overlap before the first red signal will change to yellow
One clear block(= braking distance)
Track blocks regulate train separation but also
demonstrate train integrity
Minimum separation between following trains
Increasing capacity
16
Traditional signalling with trainstops
ATP Level 2 (Continuous ATP)
braking distance
Line speed
Stopped
ATP enforces normal operation at service braking, to ensure
train stops at block point
ATP
Train must move to next block before following
train’s movement authority can be extended
Data radio communication to
trains
Signals removed, blocks represented in on-board system
Block point
ATP
overlapone clear block‘Sighting distance’ eliminated by continuous
update via radio
Minimum separation between following trains
Minimum separation between
following trains
Reducing platform reoccupation
times
17
• Modelling suggests that re-spacing of
blocks through core areas can reduce
platform reoccupation times by over
15 seconds
Source – David Morton, Siemens,
presentation to WCRR 2013 Sydney
Closely spaced blocks
at the rear of the
platform, to provide an
updated movement
authority to the
following train as soon
as possible.
Direction of travel
Outcomes from modelling work
18
Operational
target – 24tph
Modelling of ETCS L1 for
Sydney – max. 22tph
Modelling of ETCS L2 for
Sydney – max. 24tph
ThamesLink target for
L2 w.ATO – 24tph
Outcome of Line Capacity Study
with ATP/ATO – max. 26tph
Notional outcome –
30tph
No clear view on timing of a
high capacity version of L3
Examples exist worldwide of
capacity 30tph and above
Capacity limit under a
moving block system likely
to be as a result of corridor
and alignment parameters
Modelling of ETCS L2 in
Brisbane (90 sec dwell)
Area controlled by
Sydney Interlocking
Area controlled by North
Sydney Interlocking
Area controlled
by Strathfield
Interlocking
19
Upcoming asset renewals
Possible approach to deployment
20
Train control location
Interlocking location
Trackside interface location
Signal
Track circuit boundary
Trainstop
Point machine
Main cables
Local cables
New equipment deployed in parallel with existing signalling.
Change-over to new system once equipment is proven, processes are established and staff are trained.
Train control location
Interlocking location
Trackside interface location
New cabling to connect to existing
point machines
Axle counter headExisting signalling equipment shown in blackNew signalling equipment shown in red
Block lengths optimised for new
configuration
Passive balise
Grade of Automation
Type of Train
Operation
Sets Train in Motion
Stopping Train
Door Closure
Operation in event of
Disruption
GoA1ETCS L2
With DriverDriver Driver Driver Driver
GoA2ETCS L2 &
ATOWith Driver
Automatic Automatic Driver Driver
GoA3 Driverless Automatic AutomaticTrain
AttendantTrain
Attendant
GoA4Unattended
Train Operation
Automatic Automatic Automatic Automatic
Grades of Automation
21
Work on ATO with ETCS L2 is currently focussed on GoA2
Optimisation of energy
consumption with ATO
22
Source – David Morton, Siemens,
presentation to WCRR 2013 Sydney
• There are four driving phases: acceleration, cruising, coasting and
braking.
• The ATO algorithm optimizes the cruising and coasting phases.
Optimisation of energy
consumption with ATO
23
Source – UNISIG specification for ATO
with ETCS
Non-optimised
approach to a
station
Optimisation of energy
consumption with ATO
24
Source – UNISIG specification for ATO
with ETCS
Energy-optimised
approach to a station.
Estimates of the energy
saving possible range
between 10 and 40%.
DTRS and ETCS Level 2
26
– Capability to support ETCS L2 From the DTRS contract:
“The minimum requirements must be capable of delivering, subject to
necessary future BTS augmentation, all requirements for ETCS Level 2
ATP circuit switched data between Radio Block Centres.”
Capacity to support ETCS L2 Do we need to increase the number of transceivers in any BTSs?
Should we move to GPRS?
– Coverage to support ETCS L2Do we need to provide additional BTSs?
Summary
• In response to the release of Sydney's Rail Future, TfNSW is taking
the opportunity to revisit the ATP and systems strategy for Sydney,
with a focus on the strategic business requirements of Safety, Cost,
Capacity, Carbon and Customer Satisfaction.
• Adopting cab signalling using ETCS Level 2 presents an
opportunity for substantial benefits to the Sydney network.
• There is a fair bit of water to go under the bridge yet, but some of
the issues and strategies discussed in this presentation may form
part of the ultimate solution.
27