case studies: field qa/qc monitoring of subsurface bos 100
TRANSCRIPT
Battelle PresentationApril 10, 2018
Nathan Lichti (Vertex Environmental Inc.) – PresenterBruce Tunnicliffe (Vertex Environmental Inc.)Mike Mazzarese (AST Environmental Inc.)
Case Studies: Field QA/QC Monitoring of Subsurface BOS 100® Injections
• Introduction• Background
• BOS 100® Amendment• Delivery Approach• Field Monitoring
• Case Studies• Dry Cleaner Case Study • Industrial Site Case Study
• Conclusions
Introduction – Agenda
• Nathan Lichti, B.A.Sc., P.Eng.• Environmental Engineer• University of Waterloo, Canada
• Vertex Environmental Inc.• Environmental Contractor• Remediation services across Canada• Approved Installer for Trap & Treat®
products in Canada
Introduction – Vertex
Background – Delivery & Field Monitoring
Background – Amendment Overview
• BOS 100® • Consists of GAC impregnated
with metallic iron
• Mechanisms:• “Trap” the contamination
within the GAC matrix• “Treat” the contamination
via reductive dechlorination within the GAC matrix
• Applications:• Treatment of chlorinated
solvents• Overburden or bedrock• Plume or barrier applications
Mixing BOS 100® in the field
CONTAMINANTS
ACTIVATED CARBON
PORES
Activated Carbonadsorbs contaminants
Background – Delivery Equipment
INJECTION TRAILER
INTERLOCKING INTERVALS OF AMENDMENT
DIRECT PUSH RIG
DECOMMISSION WITH BENTONITE
TOP‐DOWN INJECTION ROD
SETUP
INJECTION TIP SELECTION IS IMPORTANT
Background – Injection Grid
Iterative Injection Grid – ISCO
TEMPORARYIP LOCATIONSINJECTION #1INJECTION #2INJECTION #3INJECTION #4
Single Application Injection Grid – Trap & Treat®
DELIVERY CRITICAL FOR SINGLE APPLICATION
AMENDMENTS
TemporaryIP LocationsINJECTION #1
TREATMENT AREA
TREATMENT AREA
PROPERTY BOUNDARY
Background – Monitoring Matrix
• Flowrate • Pressure Signatures
Injection Parameters Monitoring Wells
• Hydraulic influence• Geochemistry influence• Daylighting / Surfacing
• Soil cores• High resolution sampling /
characterization
Direct Push Rig Laboratory Analysis
• Soil and groundwater• Amendment concentrations
Real‐Tim
e Da
taInterim
Data
MULTIPLE LINES OF EVIDENCE ARE CRUCIAL
IDENTIFY KEY MONITORING PARAMETERS PRIOR TO
INJECTION
Case Study #1Dry Cleaner Site
Site Background• Ongoing dry cleaner operations• Former excavations (2002)• cVOCs in groundwater and soil
Remedial Objective• Generic groundwater/soil standards
Obstacles• Delivery around former excavations• Short time‐frame
Case Study #1 – Active Dry Cleaner Site
Site Map Conceptual Site Model
ACTIVE DRY
CLEANER UNIT
FORMER EXCAVATIONS
DENSE SILTY CLAY TILL WITH SAND SEAMS
WATER TABLE(~8 ft bgs)
FILL
TARGET TREATMENT
ZONE
PCE GW PLUME
FORMER EXCAVATIONS
GW FLOW DIRECTION
Case Study #1 – Active Dry Cleaner Site
Pre‐Injection WorkStep 1) Remedial Design Characterization (RDC)• 4 BHs around/within former excavations• Re‐allocated vertical injection loadingsStep 2) Finalize Injection Plan• Injection of 5,200 lbs of BOS 100®• Temporary grid of 64 IPs on 5 ft spacingStep 3) Identify Key Monitoring Parameters• Injection Pressures / Signatures• Monitoring Well Influence• Confirmatory Soil Cores
Case Study #1 – Active Dry Cleaner Site
WS01
EXTERIOR INJECTION GRID
INTERIOR INJECTION GRID
Case Study #1 – Active Dry Cleaner Site
RECORD INJECTION PARAMETERS AT
INJECTION TRAILER
RECORD INFLUENCE AT
ADJACENT WELLS
COLLECT CONFIRMATORY SOIL CORES
Case Study #1 – Active Dry Cleaner Site
Injection Parameters• Flowrate
• Positive displacement pump (constant 34 GPM)• 10 to 20 GAL of BOS 100® slurry per shot
• Injection Pressure• Within former excavations fill:
• 275 psi (avg peak pressure)• Within native clay till:
• 350 psi (avg peak pressure)
InjectionParameters
Monitoring Wells
Direct PushVerificatio
n
LaboratoryAnalysis
Real‐
Time
Interim
Case Study #1 – Active Dry Cleaner Site
0
50
100
150
200
250
300
350
400
00:00 00:05 00:10 00:15 00:20 00:25 00:30 00:35
Injection Pressure
(psi)
Time(mm:ss)
Pressure Signature(IP17 @ 19 ft)
CLAY TILL FRACTURE AT 325 PSI
INJ START INJ END
15 GAL SHOT OF BOS 100® IN NATIVE
CLAY TILL
Case Study #1 – Active Dry Cleaner Site
STABLE INJECTION PRESSURE ~280 PSI
0
50
100
150
200
250
300
350
400
00:00 00:05 00:10 00:15 00:20 00:25 00:30 00:35
Injection Pressure
(psi)
Time(mm:ss)
Pressure Signature(IP17 @ 11 ft)
STABLE INJECTION PRESSURE ~230 PSI
INJ END
15 GAL SHOT OF BOS 100® IN FORMER EXCAVATION FILL
INJ START
Case Study #1 – Active Dry Cleaner Site
0
50
100
150
200
250
300
350
400
00:05 00:10 00:15 00:20 00:25 00:30 00:35 00:40 00:45 00:50 00:55
Injection Pressure
(psi)
Time(mm:ss)
Pressure Signature(IP19 @ 15 ft)
RAPID DROP IN PRESSURE
INJ END
20 GAL SHOT OF BOS 100® IN NATIVE
CLAY TILL
INJ START
Case Study #1 – Active Dry Cleaner Site
CLAY TILL FRACTURE AT 390 PSI
STABLE INJECTION PRESSURE ~375 PSI
Case Study #1 – Active Dry Cleaner Site
Pressure Signatures Summary
Benefits Limitations
• Data available real‐time in Injection Trailer• Establish expected pressure signatures during pilot‐
test (for each geology)• Use pressure signatures real‐time to assess delivery
patterns and flag variations for further investigation
• Soil heterogeneities (i.e. sand seams in clay layer) can raise false flags
• Pressure signatures will indicate that “something” is happening but may need other lines of evidence to understand (i.e., soil cores, monitoring wells)
InjectionParameters
Monitoring Wells
Direct PushVerification
LaboratoryAnalysis
Real‐
Time
Interim
Confirmatory Soil Cores – Edge of Former Excavation
0 to 5 ft
5 to 10 ft
10 to 15 ft
None
8’‐0” (fill)8’‐5” (fill)9’‐0” (sand)9’‐2” (clay)
11’‐6” (clay)12’‐8” (sand)12’‐11” (clay)14’‐6” (sand)
15’‐8” (sand)17’‐1” (clay)17’‐3” (clay)18’‐8” (clay)19’‐2” (sand)
Case Study #1 – Active Dry Cleaner Site
InjectionParameters
Monitoring Wells
Direct PushVerification
LaboratoryAnalysis
Real‐
Time
Interim
15 to 20 ft
BOS 100® Seam in Sand @ 9’‐0”
BOS 100® Seam in Clay @ 12’‐11”
BOS 100® Seam in Sand @ 19’‐2”
Case Study #1 – Active Dry Cleaner Site
Confirmatory Soil Cores – Edge of Former Excavation
Confirmatory Soil Cores – North of Excavation
0 to 5 ft
5 to 10 ft
10 to 15 ft
15 to 20 ft
None
6’‐1” (sand)7’‐6” (clay)8’‐0” (sand)8’‐3” (clay)8’‐10” (clay)9’‐1” (sand)9’‐3” (clay)9’‐7” (sand)10’‐0” (clay)
10‐8” (sand)11’‐8” (clay)13’‐0” (sand)13’‐4” (clay)14’‐0” (sand)
15’‐10” (clay)
Case Study #1 – Active Dry Cleaner Site
BOS 100® RE‐ALLOCATED TO TARGET 16 – 20 ft
InjectionParameters
Monitoring Wells
Direct PushVerification
LaboratoryAnalysis
Real‐
Time
Interim
Interim
InjectionParameters
Monitoring Wells
Direct PushVerification
LaboratoryAnalysis
Real‐
Time
BOS 100® Seams in Sandy Clay @ 9’‐0” to 9’‐6”
Case Study #1 – Active Dry Cleaner Site
Confirmatory Soil Cores – North of Excavation
Case Study #1 – Active Dry Cleaner Site
Soil Core Summary
Benefits Limitations
• Critical evidence for confirming delivery within each unique geologic units
• Useful tool to investigate pressure signature flags
• Time & budget to complete• Not real‐time data
InjectionParameters
Monitoring Wells
Direct PushVerification
LaboratoryAnalysis
Real‐
Time
Interim
Monitoring Well Influence• Hydraulic Influence
• Observed at all wells within injection zone
• Influence ranging from 1.9 to 9.7 ft• Geochemistry Influence
• Avg ORP = ‐182 mV (pre‐injection)• Avg ORP = ‐320 mV (post‐injection)
Case Study #1 – Active Dry Cleaner Site
WS01ΔWLMAX = 1.9 ftΔORP = ‐132 mV
VMW1ΔWLMAX = 9.7 ftΔORP = ‐227 mV
VMW2ΔWLMAX = 4.4 ftΔORP = ‐141 mV
WS02ΔWLMAX = 3.1 ftΔORP = ‐48 mV
WS04ΔWLMAX = 1.8 ftΔORP = +13 mV
InjectionParameters
Monitoring Wells
Direct PushVerification
LaboratoryAnalysis
Real‐
Time
Interim
Case Study #1 – Active Dry Cleaner Site
Monitoring Well Influence
Benefits Limitations
• Real‐time data• Confirm delivery and radius of influence (ROI)
assumptions• Monitor downgradient receptors and property
boundaries• Make adjustments to injection program based on
real‐time MW responses
• Relies on existing well network (which may be inadequate)
• Well screens often straddle multiple geological layers
InjectionParameters
Monitoring Wells
Direct PushVerification
LaboratoryAnalysis
Real‐
Time
Interim
Case Study #1 – Active Dry Cleaner Site
Project Summary• Remedial Design Characterization
• Identified new soil impact outside excavations• Re‐allocation of vertical injection loadings
• Key Monitoring Parameters• Injection pressures utilized to flag intervals with unexpected signatures• Soil cores utilized to confirm BOS 100® delivery/ROI assumptions, and identify zones for re‐application• Monitoring well evidence for delivery/ROI assumptions, and that amendments stayed within the target zone
(no offsite migration)• Analytical Results
• Initial cVOCs GW results >90% decrease (initial “Trap”)• Subsequent GW samples and soil cores to be collected by Consultant
Case Study #2Industrial Site with Inflexible Remediation Deadline
Site Background• Site being sold; full remediation required as condition of
sale• Timeline for remediation was inflexible
Contaminant Situation• Two separate areas of cVOCs
Remedial Objective• Generic groundwater standards
Obstacles• Short timeframe for remediation (<5 months)• Creek adjacent to Site – non‐mobile amendment needed
Case Study #2 – Industrial Site with Inflexible Deadline
Case Study #2 – Industrial Site with Inflexible Deadline
AEC‐1
Case Study #2 – Industrial Site with Inflexible Deadline
CREEK
AEC‐2
Case Study #2 – Industrial Site with Inflexible Deadline
Pre‐Injection WorkStep 1) Remedial Design Characterization• Fill in data gapsStep 2) Develop Pilot & Full‐Scale Injection Plan• Injection of 5,400 lbs of BOS 100®• Grid of 135 IPs on 5 to 7.5 ft spacing• 14 day injection programStep 3) Identify Key Monitoring Parameters• Monitoring Wells & Preferential Pathways• Interim Groundwater Monitoring
Case Study #2 – Industrial Site with Inflexible Deadline
Conceptual Site Model
Case Study #2 – Industrial Site with Inflexible DeadlineSite Map
AEC1
INJECTION GRID
AEC2
INJECTION GRID
ASPHALT
FILL
LIMESTONE BEDROCK
WATER TABLE(~13 ft bgs)
PROPERTY BOUNDARY
SILTY SAND LAYER
CREEK
TARGET TREATMENT
ZONE
Monitoring Well Influence in AEC1• Hydraulic Influence
• Observed at all wells within injection zone
• Influence ranging from 9.4 to 13.4 ft• Geochemistry Influence
• Avg ORP = +97 mV (pre‐injection)• Avg ORP = ‐100 mV (post‐injection)
• Preferential Pathways• No influence in creek• No surfacing along creek bank
Case Study #2 – Industrial Site with Inflexible Deadline
InjectionParameters
Monitoring Wells
Direct PushVerification
LaboratoryAnalysis
Real‐
Time
Interim
MW206‐16ΔWLMAX = 13.3 ftΔORP = ‐208 mV
MW205‐16ΔWLMAX = 13.4 ftΔORP = ‐74 mV
MW115‐15ΔWLMAX = 9.4 ftΔORP = ‐270 mV
Case Study #2 – Industrial Site with Inflexible Deadline
AEC1Monitoring Well Influence in AEC1• Hydraulic Influence
• Observed at all wells within injection zone
• Influence ranging from 9.4 to 13.4 ft• Geochemistry Influence
• Avg ORP = +97 mV (pre‐injection)• Avg ORP = ‐100 mV (post‐injection)
• Preferential Pathways• No influence in creek• No surfacing along creek bank
InjectionParameters
Monitoring Wells
Direct PushVerification
LaboratoryAnalysis
Real‐
Time
Interim
Monitoring Well Influence in AEC2• Hydraulic Influence
• Observed at all wells within injection zone
• Influence ranging from 3.6 to 12 ft• Geochemistry Influence
• Avg ORP = +15 mV (pre‐injection)• Avg ORP = ‐122 mV (post‐injection)
MW201‐16ΔWLMAX = 6.4 ftΔORP = ‐438 mV
MW204‐16dΔWLMAX = 9.9 ftΔORP = +107 mV
MW110‐15ΔWLMAX = 4.2 ftΔORP = ‐246 mV
Case Study #2 – Industrial Site with Inflexible Deadline
AEC2
MW204‐16sΔWLMAX = 8.7 ftΔORP = ‐26 mV
MW116‐15ΔWLMAX = 8.7 ftΔORP = ‐182 mV
MW107‐15ΔWLMAX = 7.4 ftΔORP = ‐102 mV
BH1 (MW)ΔWLMAX = 12 ftΔORP = ‐142 mV
InjectionParameters
Monitoring Wells
Direct PushVerification
LaboratoryAnalysis
Real‐
Time
Interim
Monitoring Wells and Preferential Pathways
Benefits Limitations
• Real‐time data• Confirm delivery and radius of influence (ROI)
assumptions• Monitor downgradient receptors and property
boundaries• Make adjustments to injection program based on
real‐time MW responses
• Relies on existing well network (which may be inadequate)
• Well screens often straddle multiple geological layers
Case Study #2 – Industrial Site with Inflexible Deadline
InjectionParameters
Monitoring Wells
Direct PushVerification
LaboratoryAnalysis
Real‐
Time
Interim
Interim Monitoring Timeline• <5 months from Project Award
to Real‐Estate transaction
Case Study #2 – Industrial Site with Inflexible Deadline
FEB MAR APR MAY JUN
FEB 24, 2017PROJECT AWARD
MAR 29 ‐ 30PILOT TEST(2 INJ DAYS)
INTERIM SAMPLING #1
MAR. 25
APR. 24 ‐MAY 5FULL‐SCALE(10 INJ DAYS)
JUL
INTERIM SAMPLING #2
APR. 17
INTERIM SAMPLING #3
APR. 28
INTERIM SAMPLING #4
MAY 12
INTERIM SAMPLING #5
JUN 13
MAY 18 ‐ 19CONTINGENCY(2 INJ DAYS)
JUN 30, 2017REAL ESTATETRANSACTION
InjectionParameters
Monitoring Wells
Direct PushVerification
LaboratoryAnalysis
Real‐
Time
Interim
Case Study #2 – Industrial Site with Inflexible Deadline
0
50
100
150
200
250
25‐M
ar‐17
1‐Ap
r‐17
8‐Ap
r‐17
15‐Apr‐17
22‐Apr‐17
29‐Apr‐17
6‐May‐17
13‐M
ay‐17
20‐M
ay‐17
27‐M
ay‐17
3‐Jun‐17
10‐Ju
n‐17
17‐Ju
n‐17
1,1‐DCE
Con
centratio
n(ug/L)
AEC1: 1,1‐DCE Groundwater Results
MW205‐16
MW206‐16
MOECC Standard = 17 ug/L
PILOT‐TESTINJECTION
FULL‐SCALE INJECTION
CONTINGENCY INJECTION
1,1‐DCE SPIKE
0.0
2.0
4.0
6.0
8.0
10.0
25‐M
ar‐17
1‐Ap
r‐17
8‐Ap
r‐17
15‐Apr‐17
22‐Apr‐17
29‐Apr‐17
6‐May‐17
13‐M
ay‐17
20‐M
ay‐17
27‐M
ay‐17
3‐Jun‐17
10‐Ju
n‐17
17‐Ju
n‐17
VC Con
centratio
n(ug/L)
AEC2: Vinyl Chloride Groundwater Results
MW116‐15MW201‐16MW110‐15MOECC Standard = 1.7 ug/L
Case Study #2 – Industrial Site with Inflexible Deadline
PILOT‐TESTINJECTION
FULL‐SCALE INJECTION
CONTINGENCY INJECTION
CONTINGENCY DAYS NEEDED IN AEC2
Interim Monitoring Events
Benefits Limitations
• Provides progress updates on delivery (“Trap”)• Leads to adjustments of horizontal or vertical
injection spacings and loadings• Most useful on projects where there are multiple
phases to the injection program (i.e., Pilot, Full, Contingency)
• Time & budget to complete• Relies on existing well network (which may be
inadequate)• Not real‐time data
Case Study #2 – Industrial Site with Inflexible Deadline
InjectionParameters
Monitoring Wells
Direct PushVerification
LaboratoryAnalysis
Real‐
Time
Interim
Case Study #2 – Industrial Site with Inflexible Deadline
Project Summary• Key Monitoring Parameters
• MWs provided evidence for delivery/ROI• MWs indicated no offsite migration of amendments• Interim monitoring identified need for re‐allocation in
AEC1, and contingency injection in AEC2• Analytical Results
• Site remediation completed on time• Remedial objective achieved
• Real‐Estate transaction successful
Closing Thoughts for Successful Injections
Stage Description Scope(Approx. Cost)
Pre‐Injection Remedial Design Characterization drilling and sampling Fill‐in soil data gaps(drill rig + analytical costs)
Pilot‐Test Assess design assumptions (drilling, delivery, ROI) ~10% of Full‐Scale(extra MOB cost)
Full‐Scale
Identify “Key Monitoring Parameters” for site:• Monitoring Wells and Preferential Pathways• Pressure Signatures• Soil Cores• Interim Sampling
Use “Key Monitoring Parameters” to make in‐field adjustments
Field Delivery Monitoring(field labour costs)(field labour costs)(drill rig costs)
(analytical costs)
Thank You for Your Time
Nathan Lichti (Vertex Environmental Inc.)[email protected]
Bruce Tunnicliffe (Vertex Environmental Inc.)[email protected]
Mike Mazzarese (AST Environmental Inc.)[email protected]
Questions