chapter 2 ibs integrated building system

Upload: mohd-afzal

Post on 07-Jul-2018

228 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/18/2019 chapter 2 IBS integrated building system

    1/34

    TECHNOLOGY OF

    IBSBFP40603 – INDUSTRIALISED BUILDING SYSTEMS (IBS)

  • 8/18/2019 chapter 2 IBS integrated building system

    2/34

    CONTENT

    • Types of IBS

    •Precast Concrete Framing, Panel and BoxSystem

    •Formwork Systems

    •Prefabricated Steel Framing Systems

    •Prefabricated Timber Framing Systems

    •Blockwork Systems

    • Innovative

    • Facilities and infrastructures

  • 8/18/2019 chapter 2 IBS integrated building system

    3/34

    Learning outcome:

    • Identify and understand the components type of IBS such as

    Precast Concrete Framing, Panel and Box system; Formwork

    System, Steel Framing System; Prefabricated TimberFraming System; Blockwork System and Innovative.

  • 8/18/2019 chapter 2 IBS integrated building system

    4/34

    INTRODUCTION

    • Earliest classifications of IBS were a) frame or post andbeam system; b) panel system; and c) box system (Junid,

    1986).

    Column and beam - main

    structure member (support

    all the building weight)

    Walls - light and easy

    to install

    Concrete panels - flooring

    Loads are distributed through largefloor and wall panels where walls

    support the building weight.

    Applicable to buildings which require

    large number of walls-apartment

    house, hotel and hospital.

    Not suitable to buildings with large

    spans or many stories

    Three-dimensional modules

    or boxes for fabrication of

    habitable units that are

    capable of withstanding load

    from various directions due to

    their internal stability

  • 8/18/2019 chapter 2 IBS integrated building system

    5/34

    INTRODUCTION

    • Classification of IBS developed by the CIDB:

    IBS Types

    Precast concrete

    framing, panel

    and box system

    Formwork

    systemBlockwork

    system

    Prefabricated

    steel framing

    system

    Prefabricated

    timber framing

    system

    Innovative

    product system

  • 8/18/2019 chapter 2 IBS integrated building system

    6/34

    1) Precast concrete

    framing, panel and box

    systemThe most common group of IBS

    products is the pre-cast concrete

    elements, such as, pre-cast

    concrete column, beams, slabs,

    walls, “3-D” components(examples, balconies, staircases,

    toilets, lift chamber, refuse

    chambers), lightweight pre-cast

    concrete, as well as permanentconcrete formwork

  • 8/18/2019 chapter 2 IBS integrated building system

    7/34

  • 8/18/2019 chapter 2 IBS integrated building system

    8/34

    Preparing M&E for precast wall panel

  • 8/18/2019 chapter 2 IBS integrated building system

    9/34

    2) Formwork system

    • Considered as one of the “low-level” or the “least

    prefabricated” IBS, as they generally involve site casting

    • High quality finishes, fast construction with less site labour and

    material requirement.

    • These include tunnel forms, tilt-up systems, beams and

    columns moulding forms, and permanent steel formwork

    (metal decks).

    • Onsite fabrication - the walls and complete building are cast

    on-site, using specially designed and reusable formwork

    moulds.

    • The formwork may be made from plastic, steel etc.

    • The claim to prefabrication lies in the manufacture of the

    moulds, into which the concrete is poured.

  • 8/18/2019 chapter 2 IBS integrated building system

    10/34

  • 8/18/2019 chapter 2 IBS integrated building system

    11/34

  • 8/18/2019 chapter 2 IBS integrated building system

    12/34

    Video: Ajiya IBS Green (Enduroframe)

  • 8/18/2019 chapter 2 IBS integrated building system

    13/34

    4) Prefabricated timber

    framing system

    Products - timber building

    frames and timber roof trusses.While the latter are more

    popular, timber building frame

    systems also have its own niche

    market: offering interestingdesign from simple dwelling

    units to buildings requiring high

    aesthetical values such as

    chalets for resorts

  • 8/18/2019 chapter 2 IBS integrated building system

    14/34

    5) Blockwork system

    • Interlocking concrete

    masonry units (CMU) and

    lightweight concrete blocks.

    • Simplify the traditional

    brick-laying tasks

    • Usually, the block is

    designed as a load bearingwall system, in which the

    bricklaying work does not

    require mortar (dry system),

    and the component caneasily be installed like a

    ‘Lego’ system.

  • 8/18/2019 chapter 2 IBS integrated building system

    15/34

  • 8/18/2019 chapter 2 IBS integrated building system

    16/34

  • 8/18/2019 chapter 2 IBS integrated building system

    17/34

  • 8/18/2019 chapter 2 IBS integrated building system

    18/34

    6) Innovative

    This category refers to the various pre-fabricated materials that

    have entered the market, which include gypsum, wood wool,polymer, fibreglass, glass and aluminium-based IBS components.

  • 8/18/2019 chapter 2 IBS integrated building system

    19/34

    FB: IBS Concrete panels Sdn Bhd

  • 8/18/2019 chapter 2 IBS integrated building system

    20/34

  • 8/18/2019 chapter 2 IBS integrated building system

    21/34

    IBS FACILITIES AND INFRASTUCTURE

    1) Producing the components within controlled environment whether offsite or on-site;

    2)Delivery of component to the construction site or workplace; and

    3) Installation of components and ancillary site works.

    Typical Industrialised Building System (IBS) Construction Process (Adapted from Hamid, 2010)

    Production

    facility

    Transportation

    Equipment

    at site

  • 8/18/2019 chapter 2 IBS integrated building system

    22/34

    1) Production facility

    • Plant -

    • Equipment

    • Skilled worker

    • Management resources

    >> initial capital investment is relatively expensive - such huge

    investment can only be breakeven if there is sufficiently high

    demand for the products. On the other hand, a temporary

    casting yard or factory can be established at the project site in

    order to minimized the transportation costs (Peng, 1986)

  • 8/18/2019 chapter 2 IBS integrated building system

    23/34

    Precast concrete fabrication yard

    Batching plantOverhead crane

    Precast concrete mould &

    casting bed

  • 8/18/2019 chapter 2 IBS integrated building system

    24/34

    Precast concrete fabrication yard

    Skilled worker

  • 8/18/2019 chapter 2 IBS integrated building system

    25/34

    Precast concrete fabrication yard

  • 8/18/2019 chapter 2 IBS integrated building system

    26/34

    Storage facility

    Blockwork manufacturing

    Forklift

    QA/QC

  • 8/18/2019 chapter 2 IBS integrated building system

    27/34

    Blockwork manufacturing (automatic)

  • 8/18/2019 chapter 2 IBS integrated building system

    28/34

    Prefabricated steel framing factory

  • 8/18/2019 chapter 2 IBS integrated building system

    29/34

    Prefabricated timber framing factory

  • 8/18/2019 chapter 2 IBS integrated building system

    30/34

    2) Transportation

    • Large truck, lorry

    • It is found that casting a large panel system can reduce

    labour cost up to 30 percent. However, these cost savings

    are partly offset by the transportation costs. Thetransportation of large panels is also subject to the road

    department and relevant authorities (Peng, 1986)

  • 8/18/2019 chapter 2 IBS integrated building system

    31/34

  • 8/18/2019 chapter 2 IBS integrated building system

    32/34

    3) Equipment at site

    • For the purpose of erecting and assembling pre-cast panel

    into their position, heavy crane is required especially for

    multi-story building.

    •Crane, other equipment and tool

  • 8/18/2019 chapter 2 IBS integrated building system

    33/34

  • 8/18/2019 chapter 2 IBS integrated building system

    34/34

    References

    • Thanoon et al, THE ESSENTIAL CHARACTERISTICS OF

    INDUSTRIALISED BUILDING SYSTEM, International

    Conference on Industrialised Building Systems, Kuala

    Lumpur, Malaysia, 10-11 September, 2003