chinook full report
TRANSCRIPT
-
8/6/2019 Chinook Full Report
1/28
REPORT BY THE COMPTROLLER AND AUDITOR GENERAL | HC 512 Session 2007-2008 | 4 June 2008
Ministry of Defence
Chinook Mk3 Helicopters
-
8/6/2019 Chinook Full Report
2/28
The National Audit Oice scrutinises
public spending on behal o
Parliament. The Comptroller and
Auditor General, Tim Burr, is anOicer o the House o Commons.
He is the head o the National Audit
Oice which employs some 850 sta.
He and the National Audit Oice are
totally independent o Government.
He certiies the accounts o all
Government departments and a wide
range o other public sector bodies;
and he has statutory authority to report
to Parliament on the economy,
eiciency and eectiveness with
which departments and other bodieshave used their resources. Our work
saves the taxpayer millions o pounds
every year: at least 9 or every
1 spent running the Oice.
-
8/6/2019 Chinook Full Report
3/28
LONDON: The Stationery Ofce
7.70
Ordered by theHouse o Commons
to be printed on 2 June 2008
Ministry of Defence
Chinook Mk3 Helicopters
REPORT BY THE COMPTROLLER AND AUDITOR GENERAL | HC 512 Session 2007-2008 | 4 June 2008
-
8/6/2019 Chinook Full Report
4/28
This report has been prepared under Section 6o the National Audit Act 1983 or presentationto the House o Commons in accordance withSection 9 o the Act.
Tim Burr
Comptroller and Auditor GeneralNational Audit Ofce
30 May 2008
The National Audit Ofcestudy team consisted o:
Dan Jenkins and Stewart Lingard, under thedirection o Tim Banfeld
This report can be ound on the National Audit
Ofce web site at www.nao.org.uk
For urther inormation about theNational Audit Ofce please contact:
National Audit OfcePress Ofce157-197 Buckingham Palace RoadVictoriaLondonSW1W 9SP
Tel: 020 7798 7400
Email: [email protected]
National Audit Ofce 2008
-
8/6/2019 Chinook Full Report
5/28
sUMMAry 4
PArt one
Probles with the original procreent 7
PArt tWo
Developent of soltions 10
PArt tHree
manageent of the Reversion project 14
APPenDices
1 Std ethodolog 18
2 The united States Ar 20Chinoo helicopters
3 Battlefield Helicopters: Coittee of 21Pblic Acconts Conclsions andRecoendations concerning Chinoom3 and Treasr minte response
4 united kingdo militar Airworthiness 23 e principles
Photographs courtesy o Qinetiq Group PLC
CONTENTS
-
8/6/2019 Chinook Full Report
6/28
SummARy
4 CHINOOk mk3 HELICOPTERS
1 The Ministry o Deence (the Department) operates
a leet o 40 Chinook Mk2/2a helicopters, primarily in
support o Army and special operations. In 1995 theDepartment ordered 14 Chinook Mk2a helicopters
rom Boeing o which six were retained as Mk2a and
have lown satisactorily since they were delivered.
The other eight, however, were modiied as Mk3 to meet
a longstanding requirement or dedicated helicopters
or special operations. Those eight Chinook Mk3
helicopters cost some 259 million and the Department
took delivery o them rom Boeing in December 2001.
Although Boeing met its contractual obligations, the
avionics sotware ell short o United Kingdom military
airworthiness standards and the helicopters have not
lown on operations.
2 In 2004, the Committee o Public Accounts
described the original procurement o the Chinook Mk3
Helicopter as one o the worst examples o equipment
procurement that it had seen. This report ollows on
rom the Committees concerns and examines whether
the Department has taken appropriate steps to make the
eight Chinook Mk3s operational. Our methodology is set
out at Appendix 1.
-
8/6/2019 Chinook Full Report
7/28
SummARy
5CHINOOk mk3 HELICOPTERS
The decision making process
3 There was no immediate solution on how the
Chinook Mk3 helicopters could be made operational.
In September 2004 the Department identiied a Fix
to Field project as the best value or money solution.This project involved replacing or modiying the cockpit
display and other systems, which would deliver more
capable helicopters or special operations. It would also
reduce shortalls in helicopter lit by reeing up Mk2/2a
helicopters that had been modiied to deliver the special
operations capability in the interim.
4 The Department began a preparation phase or the
Fix to Field solution in September 2004, and the project
was estimated to deliver in-service helicopters in 2008.
In the end it took 30 months or the Department and
Boeing to agree an aordable programme o work.Although the preparation phase was protracted, it did
result in a robust business case with which to take the
project orward. The inal estimate or the in-service date
was 2011-12 with a predicted cost o 215 million.
Change o strategy the generalshortage o helicopters
5 The delay in making these Chinooks airworthy
contributed to the overall shortall in helicopter lit
and meant that the Department had a smaller Chinookleet rom which to provide capability in Aghanistan.
Assuming an appropriate level o pilots and logistic
support, additional Chinook lying hours could have
been used to carry out operations with greater lexibility
including more non-essential military tasks in support o
the international mission in Aghanistan.
6 In July 2006 the Department announced that the
number o troops stationed in Aghanistan would be
increased rom 3,500 to 4,000 and in January 2007 the
number was increased to 7,700. As a matter o urgency,
the Department began to search or ways to increasesigniicantly the levels o helicopter capability available
to commanders in operational theatres, especially in
Aghanistan. The Chinook is the most capable support
helicopter in the adverse hot and high conditions o
Aghanistan. In March 2007 the Department thereore
decided to make the eight Mk3 Chinooks available or
operations as soon as possible. The Fix to Field project
was cancelled in avour o converting (or reverting) the
Mk3 to the Mk2/2a standard. The Department estimated
that the Reversion project would make them available or
operations two years earlier than the Fix to Field project.
In March 2007 the Department also purchased six Merlinhelicopters or use in Iraq.
7 The need or more helicopters in Aghanistan and
elsewhere was recognised and the decision to cancel
the Fix to Field project and revert the Chinook Mk3 was
undertaken quickly. The timescale imperative meant
that the Department undertook limited analysis o the
operational beneits and drawbacks, and the costs andrisks o this decision. However, detailed Business Cases
were subsequently prepared and approved in accordance
with the Departments regular approvals processes beore
the main contract was signed in December 2007.
8 The Department and Boeing are conident that the
Reversion project can deliver the additional operational
capability by 2009-10. They have, or example, adopted
ast track procurement arrangements and, building on the
earlier investment in the Fix to Field project, developed
a saety management plan, agreed by Boeing, which is
expected to deliver an airworthy helicopter. In March 2007,the cost o Reversion was estimated at 53 million.
The Department acknowledged at that time that the
estimate was immature and had been produced quickly.
By the time the Department had developed a mature
estimate in November 2007, the cost estimate had
risen to 90.1 million (an increase o 70 per cent).
This excludes 22.5 million o speciic equipment
required or Aghanistan unded by the Treasury rom
the Contingency Reserve.
9 Since 2002, the Department has met the needs or
demanding very low light special operations by usingChinook Mk2/2a helicopters modiied with a Night
Enhancement Package. The ergonomics o the modiied
cockpit are imperect and, while the Department is
content that the modiied Chinook Mk2/2a helicopters are
sae to ly, it accepts that there are saety and operating
risks associated with the Night Enhancement Package.
The Department has partially mitigated these risks. As part
o the latest equipment planning round the Department has
earmarked unding to introduce an enhanced partial digital
cockpit across the entire Chinook leet to address these
concerns, maintain commonality and increase operational
lexibility. The Department expects the enhanced Chinooks
or special operations to start to enter service early in the
next decade, sooner than under the Fix to Field project.
The ull special operations capability, using the Chinook
Mk3 helicopters at uel tanks, will be met but later
than planned under the Fix to Field project. The costs o
the project are commercially sensitive as negotiations are
on going.
-
8/6/2019 Chinook Full Report
8/28
SummARy
6 CHINOOk mk3 HELICOPTERS
Conclusions
10 Our conclusions on the progress o the project are:
n The Departments progress up to the point o
committing to reversion in March 2007 on the
Chinooks and how they could be made operational
was protracted. As a result the shortage o helicopters
to support operations has been exacerbated.
n Had the Department progressed the Fix to Field
project more quickly the Reversion project would
have been unnecessary.
n The Departments decision to revert the Chinook
Mk3 helicopters will make them available, to meet
the overriding priority or additional helicopter
lit, two years earlier than would have been the
case under the Fix to Field project and will result
in a largely common cockpit across the leet with
consequent improvements in operational lexibility.
The Department expects this will also result in a
lower level o support costs.
n Although the Department has met the needs or
special operations by adapting Chinook Mk2/2a
helicopters the solution has been sub-optional.
n Early in the next decade, to solve the risks
associated with the cockpit ergonomics o the Night
Enhancement Package, the Department plans to
introduce an enhanced partially digital cockpit
across the Chinook leet, which will enable the
prosecution o special operations with greater
lexibility and less operational risk.
n The timescale imperative meant that the March 2007
decision to revert the Chinook Mk3 helicopters,
whilst inormed by a high level consideration o
options, was not based on the level o detailed
analysis that we would usually expect to see or
an investment o this magnitude. The project hassubsequently passed through the Departments
regular approvals process.
n The total costs associated with the Chinook Mk3
helicopters rom their initial procurement through
to completion o the Reversion project will be some
422 million (Figure 1) some 85 million less than
the Fix to Field project. This igure does not however
include urther expenditure required to sustain the
Night Enhancement Package which is currently
being negotiated with industry and is thereore
commercially sensitive.
1 Estiated costs of procring the eight Chinoos,
aing the operational and sstaining thespecial operations capabilit
Source: National Audit Office analysis of Ministry of Defence data
NOTES
1 Estiated costs and In-service date of Fix to Field post capabilit andcost redction exercise and re-bid in 2006-07.
2 Sstainent costs for the Night Enhanceent Pacage arecoerciall confidential ntil a contract is let.
fx fld c rv c( mll)1 ( mll)
Total expenditre on m3s 474.56 389.41
Total expenditre on Night 32.3 32.3 + X2Enhanceent Pacagefor m2/2a
Total expenditre 506.86
Expected In-service Dates 2011-12 2009-10
-
8/6/2019 Chinook Full Report
9/28
PART ONE
7CHINOOk mk3 HELICOPTERS
1.1 The Chinook helicopter is a highly capable
and versatile support helicopter that can operate in
environments ranging rom cold weather arcticconditions to desert warare operations. Chinook
helicopters are manuactured by The Boeing Company
(Boeing) in the United States and are used in the
United Kingdom primarily in support o Army and special
operations. The Ministry o Deence (the Department)
operates the second largest leet o Chinook helicopters
ater the United States Army with a total o 40 helicopters
(see Appendix 2 or details about the United States
Armys leet). Currently the Chinook is the Departments
most capable support helicopter, able to operate all year
round in the adverse high altitude and hot conditions in
Aghanistan whilst carrying an operationally useul load.Figure 2 provides more inormation about the United
Kingdoms Chinook leet.
Airworthiness issues
1.2 In 1995 the Department ordered 14 Chinook Mk2a
helicopters rom Boeing o which six were retained as
Mk2a and have lown satisactorily since they were
delivered. The other eight, however, were upgraded to
a Mk3 standard. The Mk3 helicopters were itted with
specialist equipment and larger (at) uel tanks to extend
their range (Figure 3 overlea). The at tanks avoid the needto carry uel inside the helicopter thereby allowing more
personnel and equipment to be carried on long range
missions. The Chinook Mk3 helicopters eatured unique
cockpit avionics which, relecting aordability constraints,
were a hybrid o analogue and digital systems.
1.3 The Chinook Mk3 helicopters have not lown on
operations because the Department reused to grant the
helicopters an airworthiness certiicate. Although Boeing
met its contractual obligations the avionics sotware
could not be shown to meet United Kingdom standards.
The helicopters can ly but are restricted to lying on
cloudless days above 500 eet where the pilot cannavigate via landmarks. In 2004, the Committee o Public
Accounts report1 described the procurement o the
Chinook MK3 Helicopter as one o the worst examples o
equipment procurement that it had seen. The Committees
conclusions and recommendations are listed in
Appendix 3. The helicopters cost some 259 million
and had a projected in-service date o January 2002.
The Department took delivery o the helicopters rom
Boeing in December 2001.
Problems with theoriginal procurement
2 ke facts abot the united kingdos Chinoo
helicopter fleet
Source: National Audit Office
n Each Chinoo helicopter can carr p to 55 troops,ten tonnes of cargo or two Land Rovers in the cabin, whilsta variet of additional loads can be carried externall.
n The have seen service in the Fallands, Northern Ireland,kwait, Bosnia, Sierra Leone, Iraq and Afghanistan.
n The Chinoo m2 and m2a helicopters crrentl haveot-of-service dates of 2015 and 2025 respectivelalthogh the Departent expects to extend these to 2040.
n Chinoos are operated b the Joint Helicopter Coandwhich brings together the battlefield helicopters of the RoalNav, Ar and Roal Air Force. As well as the Chinoo,
the Joint Helicopter Coand operates a frther sevenhelicopter tpes, in total over 250 helicopters.
n The united kingdos fleet of Chinoos are flown b threeRoal Air Force operational sqadrons (No 7, No 18 andNo 27) which are based at RAF Odiha in Hapshire.
n A frther eight Chinoo m3 helicopters were held instorage at the Departents Boscobe Down facilit bt arenow being wored pon as part of the Reversion project.
1 Committee o Public Accounts, Ministry o Deence: Battleield Helicopters, Eighth Report 2004-05 (HC 386).
-
8/6/2019 Chinook Full Report
10/28
PART ONE
8 CHINOOk mk3 HELICOPTERS
1.4 Since their delivery to the United Kingdom in
2001, the Chinook Mk3 helicopters have been kept
in climate controlled, de-humidiied aircrat shelters
at the Departments acility at Boscombe Down.
The helicopters are inspected once a week and moved
out o the shelters every two years or more detailed
inspections to be perormed. These activities have so
ar cost the Department an estimated 560,000.
1.5 By the time the airworthiness issues with the ChinookMk3 helicopters became apparent, emerging legislation
and operational requirements meant that the helicopters
would need to be modiied beore they could be deployed
on operations. In early 2003 the use o light recorders
(Black Boxes) and Health and Usage Monitoring Systems
on all aircrat lying in the United Kingdom was mandated.
As well as being important to understand air accidents,
these monitoring systems are also used to enable analysis
o lying hours, aircrat atigue and maintenance schedules.
The need or improved deensive systems and night vision
capability urther challenged the Department which was
already limited by the unding available to address theairworthiness and modiication issues.
1.6 In order to meet the Departments airworthiness
standards, (Appendix 4), analysis and testing o the
sotware source code or the Mk3 cockpit was required
to reduce the possibility o unoreseen system and saety
problems during light. The Department had ailed
to speciy access to the source code in the original
procurement and thereore had no leverage with which
to negotiate with Boeing or release o the source code.
Boeing and its sub-contractors, or their part, in seeking
to protect their intellectual property rights, resisted theDepartments requests or access to the source code.
Even i it had been able to access the source code, the
Department estimated that it might take up to two years
to analyse the source code with no guarantee that the
code would be written in a way which might make it
comprehensible or analysis purposes.
3 The Chinoo m2/2a and m3 helicopters
Source: Ministry of Defence and Qinetiq Group PLC
chk Mk2/2a chk Mk3
EnhancedEngines
Larger FatFel Tans
-
8/6/2019 Chinook Full Report
11/28
PART ONE
9CHINOOk mk3 HELICOPTERS
1.7 When aced with similar diiculties accessing
source code to prove airworthiness on other United States
aircrat with digital cockpits, such as the C17 aircrat, the
Department has accepted data and assumptions provided
by United States authorities and lies these aircrat within
the United States Air Force operating limits. In other casesthe Department has sought to overcome airworthiness data
issues by looking at similar systems on other aircrat. At the
time United States Chinooks were not itted with digital
cockpits and the Department investigated whether there
was suicient commonality with the digital cockpit that
Boeing had itted to Chinook helicopters used by the Royal
Netherlands Air Force to enable the preparation o an
appropriate saety case. This turned out not to be the case.
1.8 A 2004 report prepared by experts in the Department
supported these judgements and concluded that the
unique nature o the Mk3 cockpit and the lack o evidenceprovided by Boeing meant that it would have been diicult
to recommend anything other than stringent restrictions on
the operation o the aircrat. The Director o United States
Army Aviation concurred with this view and said that given
the standards operated by the United Kingdom authorities,
the Department took the right course o action in not
granting an airworthiness certiicate to the Mk3 helicopters.
1.9 In 2002 the Department equipped eight o the
Chinook Mk2/2a leet to meet requirements or special
operations. The delay in making the Chinook Mk3
helicopters airworthy contributed to the overall shortallin helicopter lit and meant that the Department had a
smaller Chinook leet to provide capability in Aghanistan.
Assuming an appropriate level o pilots and logistic
support, additional Chinook lying hours could have
been used to carry out operations with greater lexibility
including more non-essential military tasks in support o
the international mission in Aghanistan.
-
8/6/2019 Chinook Full Report
12/28
10 CHINOOk mk3 HELICOPTERS
PART TWO
2.1 This Part examines how the Department developed
a Fix to Field solution to enable the helicopters to ly
on operations; and the Departments eventual change inapproach which involved cancelling the Fix to Field project
and reverting the Mk3 helicopters to the Mk2/2a standard.
Analysis o options
2.2 In 2002 the Department began work on various
options or how it might proceed with the Chinooks.
The analysis considered whether the requirement or
eight Chinooks or special operations was still necessary
and generated a range o ully appraised options which
included assessing the impact o each on both support
helicopters and the special operations capability.In parallel the Department explored the scope to sell the
helicopters but was unable to ind a suitable buyer.
2.3 By February 2004, the Department had analysed
twelve options, o which eight were rejected because they
either did not meet requirements or special operations,
had late in-service dates, or because o poor cost-
eectiveness. In June 2004, the Department decided
to undertake urther analysis o our options which are
summarised in Figure 4.
2.4 In September 2004 the Department decided toexplore urther a Fix to Field solution which involved
the replacement or modiication o the cockpit display
systems, the communications systems and uel quantity
gauging, together with the integration o special
operations equipment and a comprehensive Deensive
Aids Suite. Although this option was the most expensive
(at 149 million) the Department assessed that it oered
the best value or money solution: it would reduce
shortalls in both standard helicopter lit (by reeing up
the eight Mk2/2a helicopters currently used or special
operations) and would meet the requirement or dedicated
special operation helicopters.
2.5 To provide additional assurance, the Department
commissioned ERA Technology, QinetiQ and the Deence
Scientiic Advisory Council to examine the easibility othe Fix to Field option. Each conirmed that the solution
was technically easible, had a sound approach to
airworthiness and would enable the Chinook Mk3 to be
declared an operationally eective helicopter to be used
on special operations.
Development o the Fix to Field project
2.6 In September 2004, the Department began a
preparation phase, initially expected to last eight months,
to ully develop the technical solution, the underpinning
initial saety case and an in-service support plan toestablish a irm price. The Departments expectation was
that the irst helicopters would be available in 2008 and
the total cost o the project, including the price o the
Boeing contract, would be 163 million. In the end it
took 30 months or the Department to agree an aordable
programme o work with Boeing. There were two main
reasons or the delay:
n It took longer than expected to agree on a
programme o work with Boeing. A detailed work
project in which all parties could have conidence
was not agreed by the Department and Boeingssenior management until April 2005. This meant the
preparation phase was extended to July 2006.
n In March 2006 Boeing submitted a proposal which
was 105 million more than the Department
had budgeted or and considered aordable.
In subsequent negotiations the Department, working
closely with Boeing, sought to reduce the price, in
part by trading non-essential elements o capability
whilst maintaining the minimum capability required
to meet the needs o special operations. This process
took until November 2006.
Development o solutions
-
8/6/2019 Chinook Full Report
13/28
PART TWO
11CHINOOk mk3 HELICOPTERS
2.7 The delays to the preparation phase meant that the
in-service date o the Chinook Mk3 helicopters slipped
to 2011-12 and the total costs, including the price o the
Boeing contract, rose to 215 million. These costs include
the estimated cost o the preparation phase which had
increased rom 13.25 million to 23.5 million.
2.8 Although the preparation phase or the Fix to Field
project was protracted, the resultant project was well
planned, technically mature, and aordable and wasstill assessed by the Department as oering the most
cost eective solution to meet the special operations
requirement. In particular:
n Steps were taken to minimise the technical risks to
the project. For example, Boeing selected Thales
Limited to provide its Top-Deck digital cockpit
which is rom the same amily as the cockpit itted to
the Departments own A400M transport aircrat and
the Nimrod MRA4.
n The Department worked closely with Boeing
and QinetiQ (the independent saety assessor
working or the Department) to ensure that earlier
airworthiness problems would not be repeated.
Boeing personnel were trained in United Kingdom
saety regulations and worked with the Department
to develop a saety management plan. Arrangements
were made so that QinetiQ could provide direct
advice to Boeing on generic saety issues to assist
them in the development o the airworthiness case.In November 2006, QinetiQ reported that the Fix
to Field project would meet saety requirements
and that airworthiness certiication would almost
certainly be given at the end o the project.
n A Gateway review by the Oice o Government
Commerce conducted in December 2006 and a
review (Red Team) led by the United States Army
Director o Army Aviation concluded that the Fix to
Field project was a high quality project which would
succeed in delivering the required capability.
4 In Jne 2004 the Departent decided to exaine for options in detail
Source: National Audit Office analysis of Ministry of Defence data
op
Do nothing
Do ini
Fix to Field
Sell m3 andrel on Spportand AphibiosBattlefield Rotorcraft
Dal
Rn the existing odified mk2/2a helicoptersto the end of their operational life; asse thatno additional fnding is available to sstain thespecific eqipent. use the mk3 as spares for themk2/2a fleet. Asse that no soltion is availablethrogh the Spport and Aphibios BattlefieldRotorcraft Project1.
Contine to se the odified mk2/2a helicopters,asse that fnding is ade available to sstain thespecific eqipent to its ot of service date. use them3 as spares for the m2/2a fleet.
mini odifications reqired to pgrade the m3helicopter to ensre that it is at least as capable asthe odified m2/2a helicopters.
maintain the odified mk2/2a helicopters ntilthe entr in to service of the ftre Spport andAphibios Battlefield Rotorcraft helicopter,odified for se on special operations. Sell theChinoo m3 helicopters.
c savg mll
21
62
149
62
rul h Dpam aal
Redces effectiveness, b nearl20 per cent.
Onl aintains the crrentcapabilit for a short period of tieand redces the effectiveness b10 per cent when the Spport andAphibios Battlefield Rotorcrafthelicopter reaches its in-service date.
Increases effectiveness b26 per cent and allows the retrnof the 8 m2/2a helicopters to theSpport Helicopter fleet.
Althogh it appears to be cheaperthan Fix to Field it does notinclde the procreent of thehelicopters which wold provide theftre capabilit.
NOTE
1 In 2005 the Spport and Aphibios Battlefield Rotorcraft Prograe was absorbed within the Departents Ftre Rotorcraft Capabilit Prograewhich ais to provide a coherent ftre prograe for all tpes of helicopter.
-
8/6/2019 Chinook Full Report
14/28
PART TWO
12 CHINOOk mk3 HELICOPTERS
Change o strategy
2.9 From mid 2006 the Department began to urgently
search or ways to quickly and signiicantly increase the
levels o helicopter capability available to commanders in
operational theatres. The imperative was made acute bythe increased tempo o war ighting and reconstruction
operations in Aghanistan and by the wider geographical
distribution o United Kingdom orces. The threat rom
road-side bombs also increased and alternatives
were sought to moving troops and materiel by road.
In July 2006 the Department announced that the number
o troops stationed in Aghanistan would be increased
rom 3,500 to 4,000. In January 2007 the number was
urther increased to 7,700.
2.10 In early 2007, in response to the increased troop
levels, the Department examined a range o options(Figure 5) to increase the helicopter capacity available to
support United Kingdom orces in Aghanistan. As a result
in March 2007 the Department decided it was imperative
to make the eight Mk3 Chinook helicopters available or
operations in Aghanistan as soon as possible. The Joint
Helicopter Command judged that it had suicient
aircrew to cover the increase, although it could mean
the guidelines setting out the amount o time Armed
Forces personnel are required to be away rom home on
operational duty (the harmony guidelines) would be
urther stretched.
2.11 The Fix to Field project was thereore cancelled
in avour o a project known as the Chinook Mk3
Reversion to convert the helicopters to a similar
standard as the Mk2/2a Chinook helicopters. Converting
the helicopters involves removing the existing Mk3
hybrid digital/analogue cockpit and replacing it with the
analogue cockpit itted to the Mk2/2a, itting a health
and usage monitoring system, United Kingdom speciic
communications equipment and deensive systems.
2.12 The Department estimated that the Reversion project
would deliver an extra eight Chinook helicopters rom
2009-10 (some two years earlier than Fix to Field)
and with lower technical risk. The Director o United
States Army Aviation agreed with the Departments
assessment that, given the United Kingdom airworthinessrequirements, reversion to the Mk2/2a cockpit standard
would be the quickest way to bring the Mk3 into service.
5 ke options to increase helicopter capacit
in Afghanistan
Source: National Audit Office analysis of Ministry of Defence data
n B bag chk m h u. The globalshortage of Chinoos eant that, despite strenos effortsb the Departent, none were available either to bor loan. For exaple, the united States Ar told s itwas approxiatel 100 Chinoos short of their overall
reqireent of 489 helicopters.n B mdg xg hlp to enable their se in the
hot and high conditions of Afghanistan. For exaple, newrotor blades have been fitted to Sea king helicopters at acost of 5.25 illion.
n B aqug h p upp hlp. Inmarch 2007 the Departent prchased six merlinhelicopters which had been ordered b the Roal DanishAir Force for 198 illion (of which 48 illion was spenton spare parts and new rotor blades to provide enhancedperforance). The merlin helicopters are ndergoing aconversion project to eet united kingdo reqireentsand are being eqipped with a odern defensive aids
site. The initial operating capabilit was achieved ontie in march 2008, the fll operating capabilit is ontrac for Jl 2008. merlin helicopters have replaced theSea king helicopters in Iraq, which have been redeploedto Afghanistan.
n B alg maa aagm to enable orefling hors to be achieved. The Departent, woringclosel with Boeing and the Defence Aviation RepairAgenc has increased the nber of fling hors achievedb the Chinoo fleet fro 12,000 hors in 2005-06 to13,000 in 2006-07.
-
8/6/2019 Chinook Full Report
15/28
PART TWO
13CHINOOk mk3 HELICOPTERS
2.13 The decision to cancel the Fix to Field project
and revert the Chinook Mk3 helicopters was undertaken
quickly. The timescales meant that the Department only
undertook limited analysis o the operational beneits
and drawbacks, and the costs and risks o this decision.
In particular, we note that:
n There was recognition within the Department and
more widely that additional helicopter assets were
needed in Aghanistan. The capability o Chinook in
the demanding operational conditions o Aghanistan
was a key actor in consideration o the options to
provide more helicopter assets.
n The timescale imperative meant that the March 2007
decision to revert the Chinook Mk3 helicopters was
not based on the level o detailed analysis that we
would usually expect to see or an investment o
this magnitude. However, detailed BusinessCases were subsequently prepared and approved
by the Departments Investment Approvals
Board in accordance with the normal approvals
processes beore the main contract was signed in
December 2007.
n Boeing was not consulted beore the initial decision
was made about the potential cost o the project or
whether there were any alternatives to Reversion
which could make the Chinook Mk3 helicopters
available or operations earlier.
n In July 2007, the Departments Investment ApprovalBoard, the senior committee o the Ministry o
Deence with responsibility or investment decisions,
approved a business case or the reversion o the
Chinooks as the only viable option to deliver
additional Chinook helicopter capability within the
appropriate timescale. In early August the Chairman
o the IAB noted the Boards disappointment that
the paper submitted had not included a more
robust explanation o the operational imperative or
providing additional Chinook aircrat in the battleield
support role within two to three years.
n At the time the decision was taken, the Department
acknowledged that risks associated with the long
term delivery o special operations capability
remained to be addressed and has since earmarked
unding to introduce an enhanced partial digital
cockpit across the entire Chinook leet to address
these concerns.
-
8/6/2019 Chinook Full Report
16/28
14 CHINOOk mk3 HELICOPTERS
PART THREE
3.1 The Reversion project aims to deliver the eight
Chinook Mk3 helicopters to a standard such that they
can be deployable to Aghanistan in 2009-10. This Partexamines how the Department aims to deliver the
Reversion project to time; the consequences o
the Reversion project or longer term helicopter
capability; and the overall costs o making the Mk3
helicopters operational.
Timetable
3.2 The Department and Boeing are conident that the
Reversion project can deliver the additional operational
capability quickly with one helicopter delivered to
operational commanders by the end o 2009 and the
remainder by May 2010. Their conidence is based upon
the adoption o a ast track timetable, a comprehensive
approach to ensuring airworthiness and commercial
incentives (Figure 6 provides details). The Department is
conident that the project is currently on track to deliver to
time and cost.
Cost o Reversion
3.3 In March 2007, the cost o Reversion was estimated
at 53 million. The Department acknowledged at the
time that the estimate was immature and had been
produced quickly. It had not been agreed with industry
and elements such as risk and theatre-entry equipment
had not been included. By the time the Department had
developed a mature estimate in November 2007, the cost
estimate had risen to 90.1 million, or 112.6 million
including modiications made speciically or operations in
Aghanistan. In December 2007, the Department agreed
with the Treasury that it would be able to re-claim the
cost o modiications rom the contingency reserve or
expenditure on military operations in Iraq and Aghanistan.
Long term consequences
Capability3.4 In order to ly operations in very low light the
modiied Chinook Mk2/2a (paragraph 1.9) were itted
with specialist equipment, called the Night Enhancement
Package, which included items such as navigation units,
thermal imagers, moving map displays and night vision
goggles. The Package was installed in 2002 as a short
term modiication to meet operational requirements in
Aghanistan and used bolt-on equipment that was not
ully integrated into the cockpit in order to accelerate its
entry into service. The cockpit ergonomics are imperect
because some components o the Package are placed in
positions in the cockpit that lead to increased workload on
the aircrew when lying (see Figure 7). Senior sta in the
Joint Helicopter Command also told us that the saety issues
surrounding the Night Enhancement Package were among
its top concerns.
3.5 The modiied Chinook Mk2/2a helicopters were
released to service as sae to ly, by the Assistant Chie
o the Air Sta, on the basis that the saety and operating
risks associated with the ergonomic aspects o the Night
Enhancement Package were outweighed by the increased
operational risk i the Chinook Mk2/2a helicopters were
to operate without the Night Enhancement Package and
could be mitigated by training procedures and time
bounding the risks.
3.6 In originally issuing the clearance or the modiied
Chinook Mk2/2a in 2003, the Assistant Chie o the Air
Sta received assurances that the Department would
develop a unded project in order to mitigate the air saety
risks associated with the Night Enhancement Package.
Management o theReversion project
-
8/6/2019 Chinook Full Report
17/28
PART THREE
15CHINOOk mk3 HELICOPTERS
6 Wh the Departent and Boeing are confident that the Reversion project can deliver operational capabilit qicl
Source: National Audit Office analysis of Ministry of Defence data
n The adoption of a parallel approach to design, installationand testing. For exaple, trial installation wor has begn
now that sfficient atre design inforation is available.The Departent estiates that this will deliver the helicopterssix onths earlier than adopting a ore traditionalseqential process.
n Boeing has a strong trac record in the design and deliver ofChinoo helicopters. It is the Design Athorit for the Chinooand provides throgh life sppor t for the united kingdosm2/2a fleet.
n To aintain their engineering resorces and enable the toqicl start p the new project, Boeing has preserved itstea of personnel dring the gap between cancellation of Fixto Field and the start of the Reversion project to enable it tobild on the Fix to Field preparation phase wor. Boeing tolds that the were fll coitted to the Reversion project.
n Boeing has categorised the m3 Reversion project as aprestigios Focs project, sall onl assigned to highonetar projects worth over $500 illion (250 illion).
n Boeing has engaged QinetiQ to condct the trial installationon the first two helicopters and installation of the reainingsix. QinetiQ has been integrall involved with the m3helicopters and has a good nderstanding of the aircraft andassociated safet and airworthiness isses.
n To help develop good woring practices and to bild strongcollaborative relationships, e representatives fro the
Departent, Boeing and QinetiQ have ndertaen jointtraining, notabl on Boeings prograe anageent corse.
n The Departent agreed a 62 illion contract with Boeingto deliver the Chinoos. The contract inclded a tie-basedincentive fee agreeent to encorage earl deliver.The contract rewards Boeing for earl deliver of threeilestones, the final design review, deliver of the firstaircraft and deliver of the seventh aircraft.
n Learning fro its original procreent difficlties, theDepartent has ade it a contractal reqireent thatBoeing satisf the reqireents of the Departents safetanageent plan which incldes the acceptance of safetcritical software. Ris redction activities will also bendertaen earlier in the procreent ccle, inclding designanalsis, to identif and resolve an design safet isses.
n Airworthiness riss are lower becase the helicopters arebeing reverted to a siilar standard to the existing m2/2afleet for which safet inforation is available and theDepartent has appointed a dedicated safet anager.
7 The Chinoo m2/m2a Night Enhanceent Pacage
Source: Ministry of Defence
L had pl kp rgh had pl kp
Pilots NightEnhanceent
PacageDispla
Co-Pilots NightEnhanceent PacageDispla (Obscres theforward view)
-
8/6/2019 Chinook Full Report
18/28
PART THREE
16 CHINOOk mk3 HELICOPTERS
3.7 The cancellation o the Fix to Field project meant
that another way had to be ound to address these risks
and as a result the Assistant Chie o the Air Sta stated, in
March 2007, that without urther unding, the clearance
to continue using the Night Enhancement Package could
not be assured. The Department acknowledged that therisks associated with the Night Enhancement Package
still needed to be addressed and subsequently earmarked
unding and started a project which it is conident will
address these risks earlier than the Fix to Field project.
3.8 This project will introduce an enhanced partial
digital cockpit across the entire Chinook leet to maintain
commonality and operational lexibility. The ull special
operations capability, using the Chinook Mk3 helicopters
at uel tanks, will be met but later than planned under
the Fix to Field project. The costs o the project are
commercially sensitive as negotiations are on going.
Training
3.9 The Chinook Mk3 Reversion project will introduce a
largely common cockpit coniguration across the Chinook
leet, which would not have been achieved under the Fix
to Field project. This will reduce the burden on pilot and
crew training, although speciic training on the use o the
Night Enhancement Package will continue to be required.
The Department is managing a number o issues to ensure
the reverted Chinook Mk3 helicopters are successully
integrated in to the Chinook leet including:
n Increasing the number o aircrew by 40 and
engineers by 60 personnel, and running concurrent
courses or both air and ground instruction, where
previously they had been consecutive. In doing so
there has been no requirement or additional training
sta to deliver the increased output, but it does mean
there will be greater demands placed on them.
n The Department is conident that it should be
possible to qualiy crews to operate Mk2/2a and Mk3
helicopters under a single all Marks qualiication
since the aim o the Mk3 Reversion project is to
mirror as closely as possible the cockpit and controls
o the Mk2/2a, thus producing a common cockpitacross all Chinook helicopter variants and
allowing any appropriately trained pilot to ly
any Chinook helicopter.
n Common training or both the Chinook Mk3 and
Chinook Mk2/2a helicopters which takes into
account the dierent light handling characteristics
due to the larger uel tanks which are inherent to the
design o Chinook Mk3.
n Current training light simulators do not match
the requirements or lying the current Chinook
helicopters. To mitigate this risk, the Department willmodiy the existing Chinook light simulators beore
the end o 2009.
Delivery costs
3.10 Figure 8 shows that the costs associated with the
Chinook Mk3 helicopters rom their initial procurement
through to completion o the Reversion project will
be some 422 million. The costs take into account the
original purchase price o the Chinooks, the procurement
costs or the Night Enhancement Package and thecosts o storing and maintaining the Mk3 helicopters at
Boscombe Down.
3.11 For comparison purposes Figure 8 also includes the
costs o the Fix to Field project. It shows that the total cost
o the Fix to Field project would have been 507 million,
some 85 million more than the Reversion project.
However, the reversion costs do not include urther
expenditure required to sustain the Night Equipment
Package which is currently being negotiated with industry
and are thereore commercially sensitive.
-
8/6/2019 Chinook Full Report
19/28
PART THREE
17CHINOOk mk3 HELICOPTERS
3.12 Although the Fix to Field project would have
ultimately met the requirement or special operations
missions it would not have met the timescale imperative
to provide more Chinook capacity to operations in
Aghanistan. The Reversion project will provide an
increase in Chinook helicopters two years earlier.
3.13 Cancellation o the Fix to Field project also meant
some inancial losses or industry. Thales Limited, or
example, invested in the development o the Fix to Field
solution in order to shorten the delivery timescales and
incurred a small inancial loss when the project did not
proceed. Boeing lost any proit it may have made through
the preparation phase o the contract.
8 Estiated costs of procring the eight Chinoo m3 helicopters and aing the operational and sstaining the
special operations capabilit
Source: National Audit Office analysis of Ministry of Defence data
Ma xpdu m
Original procreent
Reversion project, inclding Afghan theatre specific eqipent
Expenditre on Fix to Field before cancellation2
Fix to Field
Storage, inspection and aintenance of eight helicopters at Boscobe Down
tal xpdu Mk3
Night Enhanceent Pacage installed in eight helicopters in 2001
Sstainent and Integration of the Night Enhanceent Pacage for eight helicopters
tal xpdu
Expected In-service Dates
fx fld c
( mll)1
259
215
0.56
474.56
32.3
506.86
2011-12
rv c
( mll)259
112.6
17.25
0.56
389.41
32.3
X3
2009-10
NOTES
1 Estiated costs and In-service date of Fix to Field post capabilit and cost redction exercise and re-bid in 2006-07.
2 The Departent told s that soe of the activities arising fro the preparation phase cold be sed on the Reversion and other projects althogh the extentof this has not been qantified.
3 Costs are coerciall confidential ntil a contract is let.
-
8/6/2019 Chinook Full Report
20/28
18 CHINOOk mk3 HELICOPTERS
Study methodology
1 This Appendix sets out the scope o our examination
o the Chinook Mk3 and the methodologies we used in
the course o our study.
We examined the ollowing areas:
n Whether concerns arising rom earlier reports by the
National Audit Oice2 and the Committee o Public
Accounts3 have been addressed.
n The steps the Department has taken to make the
eight Chinook Mk3 helicopters ully operational
since 2001, including the Fix to Field project and the
Reversion project.
n Whether decisions to make the helicopters
operational have been taken expeditiously and based
on sound advice.
n How the Department has managed shortalls in
special operations capability due to the lack o
availability o the Chinook MK3s.
n The arrangements the Department has in place to
ensure that the helicopters, when delivered under the
Reversion project, will be airworthy or operations,
and that other risks have been minimised.
n The costs o making the Chinooks operational and
how these have been controlled.
We undertook a series o interviews:
2 We carried out a series o interviews with
Departmental sta rom:
n The Departments Deence Equipment and Support
organisation responsible or the management o the
Chinook Mk3 and its associated ielding projects.
n The Directorate o Equipment Capability (Air and
Littoral Manoeuvre) in order to ully understand the
original planning, requirements and procurement othe Chinook Mk3 along with the development o the
subsequent ielding projects.
n Joint Helicopter Command personnel at
Headquarters Land Command in Wilton to gain
an understanding o how the aircrat are used and
how the introduction o the Mk3 may aect the
availability and operational perormance o the
Chinook leets.
n Chinook aircrew rom 7, 18 and 27 Squadron RAF
along with ground crew and station personnel at
RAF Odiham. We gained awareness o the day today challenges associated with the Chinook aircrat
along with the challenges aced by the station
personnel in direct support o the Chinook leet.
We examined Departmental documents:
3 We examined Departmental documents including:
n Post-project appraisals o the original Chinook Mk3
procurement.
n Papers prepared or, and approvals made by, the
Departments Investment Approvals Board.
n Technical and economic appraisals o the Fix to Field
and Reversion projects.
n Airworthiness standards.
n Other relevant inormation such as guidance
and manuals.
APPENDIX ONE
2 National Audit Oice: Ministry of Defence: Battlefield Helicopters, HC 486 Session 2003-2004: 7 April 2004.3 Committee o Public Accounts: Ministry of Defence: Battlefield Helicopters, Eighth Report 2004-05 (HC 386).
-
8/6/2019 Chinook Full Report
21/28
19CHINOOk mk3 HELICOPTERS
We discussed the Chinook Mk3projects with industrial providersand experts and observed theChinooks at Boscombe Down
4 We interviewed representatives rom industrial
providers:
n Boeing was the main contractor or the original
procurement and the Fix to Field project and is
the main contractor or the Reversion project.
We interviewed representatives o the company
responsible or Chinooks at their Philadelphia actory
in the United States.
n QinetiQ are contracted by the Department to provideindependent advice on airworthiness and saety.
We interviewed representatives at Boscombe Down.
n Thales was to provide the helicopter cockpit or the
Fix to Field project. We interviewed representatives
in London.
5 We observed the Chinook Mk3 helicopters in their
storage acilities at Boscombe Down and interviewed
those responsible or their maintenance and inspection.
We interviewed the United StatesDirector o Army Aviation
n We met with the United States Director o Army
Aviation in the United States in order to provide
greater insight to the use o Chinook helicopters by
the United States Army and Special Forces.
Summary o the stakeholderswithin the Department and otherorganisations which we visited
Deence Equipment and Support
Director General Helicopters
Director Future Rotor Crat Capability
Chinook Integrated Project Team
Chinook Future Heavy Lit Project Team
Ministry o Deence
Directorate Equipment Capability
(Air and Littoral Manoeuvre)
Director General Scrutiny and Analysis
Deence Science Technology Laboratory
Directorate Special Forces
Royal Air Force
Headquarters Joint Helicopter Command
RAF Odiham
IndustryThe Boeing Company
QinetiQ
Thales Limited
United States Army
Director o Army Aviation
APPENDIX ONE
-
8/6/2019 Chinook Full Report
22/28
20 CHINOOk mk3 HELICOPTERS
The United States ArmyChinook helicopters
1 The United States army currently operates our
dierent versions o the Chinook Helicopter.
2 The Chinook D model which is similar to the United
Kingdom Chinook Mk2/2a and the Chinook E model a
Special Forces variant o the D model, similar to the United
Kingdom Chinook Mk3 but with a ully analogue cockpit.
An upgrade project is currently converting the D helicopters
rom analogue to digital cockpits and upgrading the already
digital E model helicopters to the F and G model Chinooks,
which will become the basis or the US Armys leet o
standard and Special Forces helicopters.
3 The United States Army will buy Chinooks orm the
Boeing until approximately 2019, on the current delivery
schedule, to meet their overall requirement o 489 aircrat.The acquisition project involves a combination o
remanuacturing a total o 393 CH-47D and CH-47E
model Chinooks into CH47F and G models with an
additional new buy o 120 CH-47F.
4 The United States operational requirement or
Chinooks in the Aghanistan theatre
n Each o the our Combat Aviation Brigades brings its
CH-47 company o 12 aircrat, however;
n Operation Enduring Freedom requires an additional
1215 Chinook aircrat above that provided by the
Combat Aviation Brigades; this augmentation is
generally supported by a National Guard unit.
APPENDIX TWO
9 The united States Ars crrent and planned fleet
of Chinoo helicopters
Source: United States Army
Aalgu ckp Dgal ckp tal
Reglar Ar 371 x CH 47D 35 x CH 47F 406
160th Special 15 x mH 47E 40 x mH 47G 55OperationsAircraft Regient
-
8/6/2019 Chinook Full Report
23/28
21CHINOOk mk3 HELICOPTERS
APPENDIX THREE
Battleield Helicopters:Committee o Public
Accounts Conclusionsand Recommendationsconcerning Chinook Mk3and Treasury Minute response
cmm Publ Aulu ad mmda
The Departent has boght eightChinoo m3 helicopters whichhave not entered service andwhich it cannot se.
The Departent was nable tosa who was responsible forthe flawed procreent of theChinoo m3.
tau Mu p
The Departent agrees that there were significant probles with the acqisition of the Chinoo m3helicopter. major changes, nder the Sart Acqisition initiative, have been incorporated into theDepartents woring practices to ensre that these probles wold not occr now. Areas thathave been addressed inclde a ore rigoros prioritisation of the reqireent, clear gidelines onresponsibilities, iproved militar Aircraft Release procedres and a rigoros project review andassrance process. In the Reqireents manageent process essential eleents are identifiedas ke user Reqireents. In particlar, the developent of prioritised, hierarchical reqireentsdocents and a thorogh process to trac these reqireents throgh contracts into a deliveredcapabilit is a e sccess of Sart Acqisition. In parallel, it has also been recognised that thetrading of perforance, cost and tie is necessar to balance the desire to provide everthing thata Cstoer wants against affordabilit in order to ensre best vale for one.
Crrent processes also reqire that significant ris redction activit taes place prior to the aininvestent decision. Perforance, Tie and Cost riss are considered and no coitent is ade
to a project ntil an acceptable level of atrit and ris is attained. ke staeholders in theseprocesses inclde the Integrated Project Tea, Cstoer and Indstr.
The Departent agrees with the Coittees conclsion on appointing a single point ofaccontabilit for projects. All eqipent projects have a noinated individal responsible foroverseeing all aspects of the project to ensre that riss are anaged and that the fll benefitsof the project are achieved. This individal is answerable for the introdction of capabilit intoservice and the coherent and integrated deliver of eqipent; training and personnel; logistics;infrastrctre; concepts; doctrine and other coponents of ilitar capabilit.
For each eqipent and bsiness change project which involves sbstantial change, significantcoplexit and/or deanding integration across bondaries, the Departent has appointed aSenior Responsible Owner with responsibilities and reporting arrangeents set ot in foral tersof reference. For all other eqipent acqisition projects, the appropriate Director of Eqipent
Capabilit has been designated as the single point of accontabilit for ensring the deliver of allcoponents of ilitar capabilit inherent in an eqipent investent decision. The Chinoo m3procreent however, predates the adoption in the Departent of both Senior Responsible Ownerand single point of accontabilit constrcts.
A e part of the Senior Responsible Owner and single point of accontabilit role is to resolveconflicting priorities and deands in order to achieve the reqired benefits against e strategicpriorities and within tie, cost and perforance paraeters. With the increasing coplexit andintegration of eqipent projects, the role of the Senior Responsible Owner and single point ofaccontabilit will be vital in ensring effective deliver of new ilitar capabilit to the front line.
-
8/6/2019 Chinook Full Report
24/28
22 CHINOOk mk3 HELICOPTERS
tau Mu p
The Departent agrees that there have been significant probles with the acqisition of theChinoo m 3 helicopter and options for the ftre of the aircraft are being prsed.
Crrent indications are that odifing the aircraft to provide the reqired capabilit and to eetthe militar Aircraft Release reqireent will offer the best vale for one soltion and addressthe shortfall in battlefield helicopter lift capabilit, as highlighted in the National Adit OfficeReport. The option to sell the aircraft reains open pending satisfactor copletion of this technicaland indstrial preparator wor.
The vale of the Chinoo m3 aircraft has been written down at present to a vale eqivalent todisposal or se as spares, bt this is becase of prdent acconting practice, and is not a reflectionof ftre intent.
cmm Publ Aulu ad mmda
The Departent shold deterinewhether there is an beneficial
se that can be ade of theChinoo m3.
APPENDIX THREE
-
8/6/2019 Chinook Full Report
25/28
23CHINOOk mk3 HELICOPTERS
APPENDIX FOuR
United KingdomMilitary Airworthiness key principles
1 Airworthiness is essentially a technical attribute o
materiel; it is concerned with airborne saety aspects that
are dependent on the design o a particular aircrat type.The ormal deinition o airworthiness is:
n The ability o an aircrat, or other airborne equipment
or system to operate without signiicant hazard to
aircrew, ground crew passengers or to the general
public over which such airborne systems are lown.
2 Airworthiness characteristics stem rom the design
o a particular aircrat and thereore determine not only
the coniguration o the aircrat, but also the requirements
and limits o both its maintenance and operation.
The granting o Airworthiness Authority to areas within
the Deence Equipment and Support organisation limitstheir ability to change either the design or the operating
or maintenance requirements which are derived rom the
design o the aircrat.
3 Additionally, Aircrat Operating Authorities, in
the case o the Chinook, Commander Joint Helicopter
Command, have the responsibility to preserve the
airworthiness o individual aircrat by ensuring that
their personnel operate and maintain aircrat within the
requirements and limits speciied in the Release to service
and Aircrat Document Set. This responsibility is explicitly
stated in the authority to operate aircrat delegated romthe Secretary o State through the Chies o Sta and hence
through to Aircrat Operating Authorities.
4 The authority to operate and regulate United Kingdom
military aircrat is vested in Secretary o State. The Secretary
o State requires all aircrat, associated equipment and
sotware to be designed, constructed, maintained and
operated in such a manner that they are airworthy.
5 The Secretary o State requires that the airworthiness
arrangements or military aircrat should be at least as
eective as those or civil aircrat contained in the AirNavigation Order, which sets out the regulations to which
all civilian air traic in the United Kingdom must adhere,
and should comply with the Health and Saety at Work
Act where relevant. This is particularly important in roles
that are paralleled in civil operations, such as where
passengers are carried.
6 The Departments Aviation Regulatory and Saety
Board, chaired by the Assistant Chie o the Air Sta, sets
out the Military Airworthiness Regulations in Joint Service
Publication 553.
7 Joint Service Publication 553 describes the Saety
Management System or the management o airworthiness
o UK Military Aircrat. The Saety Management System
deines the planning, organising, implementing and
controlling o airworthiness management activities.
It covers policy aspects o the management o design,
procurement maintenance and operation o military
aircrat that aect airworthiness, and, where appropriate
delineates responsibilities. Within the project Saety
Management System, the Saety Case provides the
objective justiication or the airworthiness o an aircrat
and is thus the on-going basis o aircrat releases.
The Release to Service
8 The Release to Service is central to the management
o airworthiness or any given aircrat. A Release to
Service is only authorised ollowing the presentation o a
robust, independently assessed Saety Case or any new
aircrat and subsequent modiication. It disseminates the
authorised limits, procedures and operating inormation
to the personnel (aircrew and engineers) who operate the
aircrat. The content o the Release to Service is divided
into seven sections (Figure 10 overlea).
-
8/6/2019 Chinook Full Report
26/28
24 CHINOOk mk3 HELICOPTERS
10 manageent of Release to Service
Source: Ministry of Defence
Pa A Awh ad Dum Maagm. This partcovers the sections related to the airworthiness and athorisation
fnctions of the Release together with sections that are foranageent of the aircraft or general Release docentation.
Pa B Aa Dg ad Hadlg Lma.This partcovers the inforation to aircrew, for liitations that are basic tofling the aircraft withot external stores or other role eqipentfitted. Ths it covers ites sch as: Speed, Altitde, manoevres,Environent Conditions, and Tae-off & Landing.
Pa c sm Lma ad ca. This part covers theliitation aspects of operating the aircraft that are applicable tothe aircraft sstes, rather than fling the aircraft. Ths it coversites sch as: Engine, Fel Sste, Electrical Sste, Atopilot,Conications, and Radar.
Pa D rl Lma ad ca. This part covers the
liitations that are sortie dependent; i.e. var between flights,rather than related to the role of the basic aircraft. Ths itcovers ites sch as: Athorised Stores Configrations; StoresCarriage, Release and Jettison Liits; Passenger and FreightLiits; Winch Operations; Air-Drop etc. There are an possiblesection headings that fit into this Part, bt the tend to sb-divideaccording to the tpe of aircraft, for exaple, Fast Jets, Transportand Spport and Helicopters.
Pa e Maagm tmpa ima. Clearancesinclded in this section are to be of a geninel transitor natre:
for exaple, the clearance of a Special Trial Fit for a shortdration trial after which it will be reoved; or inclded within thispart throgh operational necessit as a teporar aendent,pending its inclsion in the appropriate part at the next foralaendent of the Release to Service. All sch inforation stbe spported b a safet case. This section a also be sed toprolgate other rgent inforation to aircrew pending foralaendent of aircrew pblications (for exaple, operating datain spport of a new clearance).
Pa f claa wh Lmd evd. The prpose of Part F isto record where inforation has been inclded within the Releaseto Service that has not been derived fro a fll sbstantiatedsafet case; sch clearances are tered Clearances with LiitedEvidence. Sch clearances are norall sbject to periodic
review, freqent aendent, and soe a be applicable onlto certain ars, operating nits or even individal airfraes.Following a periodic review or change to sch clearance, theapplicabilit and validit of the Clearance a change.
Pa G Aud tal. This part covers the Adit trail fnctionreqired to ensre airworthiness, and will be all the eleents ofthe whole aircraft Safet Case. It is a record of all the Safet Casedata that has been sed in copiling the Release and providesjstification for all eleents of the Release content.
APPENDIX FOuR
Printed in the UK or the Stationery Oice Limited
on behal o the Controller o Her Majestys Stationery Oice
5820992 06/08 77240
-
8/6/2019 Chinook Full Report
27/28
Design and Production byNAO Marketing & Communications Team
DP Re: 8353VE
This report has been printed on ConsortRoyal Silk and is produced rom acombination o ECF (Elemental ChlorineFree) and TCF (Totally Chlorine Free) woodpulp that is ully recyclable and sourcedrom careully managed and renewedcommercial orests. The range ismanuactured within a mill which isregistered under the BS EN ISO 9001accreditation, which provides the higheststandard o quality assurance.
-
8/6/2019 Chinook Full Report
28/28
Pblished b TSO (The Stationer Office) and available fro:
olwww.tso.co./booshop
Mal, tlph, fax & e-malTSOPO Box 29, Norwich, NR3 1GNTelephone orders/General enqiries: 0870 600 5522Order throgh the Parliaentar HotlineLo-call 0845 7 023474
Fax orders: 0870 600 5533E-ail: [email protected] 0870 240 3701
tso shp16 Arthr Street, Belfast BT1 4GD028 9023 8451 Fax 028 9023 540171 Lothian Road, Edinbrgh EH3 9AZ0870 606 5566 Fax 0870 606 5588
th Palama Bkhp12 Bridge Street, Parliaent Sqare,London SW1A 2JX
Telephone orders/General enqiries 020 7219 3890Fax Orders 020 7219 3866Eail [email protected] booshop Parliaent
ISBN 978-0-10-295414-2
ChinookMk3Helicop
ters
AreportbytheCom
ptrollerandAuditorGeneral
TheStatio
7.70