Chronological progress of the construction phase:
March 2015 - May 2015 - Completion Report
Installation of silt fence & trees protection
Trees Removal
Removal of top soil to prepare the foundation
Excavation & materials removal
Retaining walls excavation & backfill
Backfilling and compaction
Fire fighting pond
Water storm drainage
June 2015 - Dec 2015 - Completion Report
100% of the perimeter of the concrete walls for first level
100% of walls foaming of lower level concrete
Elevator Pit is complete
CONSTRUCTION IS CURRENTLY ON HOLD DUE TO WINTER AND WILL RESUME BACK IN SPRING 2016
The actual spent as of
Dec 2015 towards the
construction of
Masjid Noor-UL-Haram
is $2.1M which is part
of the $13.5M of the
total cost of project
for phase 1