GRP PROGRAM CONSTRUCTION PROGRESS SJRA Board of Directors Meeting March 28, 2013 GRP Review Committee Meeting March 26, 2013

Upload: san-jacinto-river-authority

Post on 31-May-2015

805 views

Category:

News & Politics


1 download

DESCRIPTION

San Jacinto River Authority Groundwater Reduction Program water line construction progress, The Woodlands, Conroe, Lake Conroe, Montgomery County, Texas

TRANSCRIPT

Page 1: GRP Program Water Line Construction Progress

GRP PROGRAM CONSTRUCTION PROGRESS

SJRA Board of Directors

MeetingMarch 28,

2013

GRP Review Committee Meeting March 26,

2013

Page 2: GRP Program Water Line Construction Progress

SURFACE WATER FACILITY CONSTRUCTION ADMINISTRATION

Project Data Thru 02/28/2013 - Early Work Package 3

Project Budget: $191,000,000.00

Contracted Amount: $90,331,558.00

Change Orders: $0.00

Estimate to Complete: $191,000,000.00

Amount Invoiced: $16,591,685.62

Budget Remaining: $174,408,314.38

Percent In-Place Work: 18.40%

Completion Date: June 1, 2015

Page 3: GRP Program Water Line Construction Progress

Placement of 75 feet long precast concrete bridge girders

RAW WATER INTAKE AND PUMP STATION

March 06, 2013

Page 4: GRP Program Water Line Construction Progress

Placement of 75 feet long precast concrete bridge girders

RAW WATER INTAKE AND PUMP STATION

March 06, 2013

Page 5: GRP Program Water Line Construction Progress

Overview of precast concrete girders – Dam to Bent 3

RAW WATER INTAKE AND PUMP STATION

March 15, 2013

Page 6: GRP Program Water Line Construction Progress

Metal decking installation at Raw Water Intake bridge

RAW WATER INTAKE AND PUMP STATION

March 12, 2013

Page 7: GRP Program Water Line Construction Progress

Grade-beam installation at Raw Water Intake building structure

RAW WATER INTAKE AND PUMP STATION

March 15, 2013

Page 8: GRP Program Water Line Construction Progress

HIGH SERVICE PUMP STATION

Flowable fill installation beneath Pump Room

March 04, 2013

Page 9: GRP Program Water Line Construction Progress

HIGH SERVICE PUMP STATION

Plumbing installation at Pump Room

March 13, 2013

Page 10: GRP Program Water Line Construction Progress

GROUND STORAGE TANKS

February progress photo at GST2

February 15, 2013

Page 11: GRP Program Water Line Construction Progress

GROUND STORAGE TANKS

Rebar installation at GST2

March 01, 2013

Page 12: GRP Program Water Line Construction Progress

GROUND STORAGE TANKS

Concrete placement at GST2 – 625 CYDS

March 06, 2013

Page 13: GRP Program Water Line Construction Progress

February progress photo at Granulated Activated Carbon Building

WATER TREATMENT PLANT

February 01, 2013

Page 14: GRP Program Water Line Construction Progress

Process piping installation at Granulated Activated Carbon Building

WATER TREATMENT PLANT

March 15, 2013

Page 15: GRP Program Water Line Construction Progress

Process piping installation at Granulated Activated Carbon Building

WATER TREATMENT PLANT

March 13, 2013

Page 16: GRP Program Water Line Construction Progress

February progress photo at Membrane Building

WATER TREATMENT PLANT

February 08, 2013

Page 17: GRP Program Water Line Construction Progress

Lower trench drain foundation for the Membrane Building

WATER TREATMENT PLANT

March 11, 2013

Page 18: GRP Program Water Line Construction Progress

Mass excavation and seal slabs for the Pre-Treatment Structure

WATER TREATMENT PLANT

March 15, 2013