cm training
TRANSCRIPT
-
8/7/2019 Cm Training
1/166
1
Essentials of Project and
Construction ManagementLand is Life
Korea Land Corporation(KLC)
In association withHill International, Inc.
Hill International, Inc.
Strictly
Confidential
-
8/7/2019 Cm Training
2/166
2
THE PROJECT
Session 1
-
8/7/2019 Cm Training
3/166
3
The Project
A Discrete, Planned Undertaking
having
A Defined Scope
A Start and a Finish
The Project Approach Has
Evolved to be a Management
Buzzword
Origins in the EPC Industry
-
8/7/2019 Cm Training
4/166
4
The Project
Traditionally EPC industry was loose conglomerate of
designers, financiers, builders, suppliers, contractors, etc.
Complexity, computerization, and failures brought forwardthe need for a Project Approach
The ProjectApproach has now become the rule rather than
the exception
Project Management concept has evolved, defined as
The management of an organized set of activities towards
defined objectives using limited resources applying
specialized management structures and techniques.
-
8/7/2019 Cm Training
5/166
5
The Project Life Cycle
-
8/7/2019 Cm Training
6/166
6
The Project Life Cycle
All projects exhibit similar life cycles
Four primary seasons
Concept
Development
Implementation
Termination/Completion
-
8/7/2019 Cm Training
7/166
7
The Project Life Cycle
Concept Development Implementation Termination
L
e
v
e
l
o
f
E
f
f
o
r
t
-
8/7/2019 Cm Training
8/166
8
The Project Life Cycle
Gather data
Identify need
Establish
goals, objective
basic economics,
feasibility stake holders
risk level
strategy
potential team
Guesstimate Resources
Identify Alternatives
Present proposal
Obtain Approval for nextphase
Concept Phase
-
8/7/2019 Cm Training
9/166
9
The Project Life Cycle
Appoint Key Team
Members Conduct Studies
Develop ScopeBaseline
end product(s)
quality standards
resources
activities
Establish
master plan budget, cash flow
WBS
policies andprocedures
Assess risks
confirm justification
Present project brief
Obtain approval to
proceed
Development Phase
-
8/7/2019 Cm Training
10/166
10
The Project Life Cycle
Set Up Organization
Communications
Motivate Team
Detail Technical Req.'s
Establish Work packages
InformationControl Systems
Procure Goods and Services Execute Work Packages
Direct/Monitor/Forecast/Control:
Scope
Quality Time
Cost
Resolve Problems
Implementation Phase
-
8/7/2019 Cm Training
11/166
11
The Project Life Cycle
Finalize Products Review and Accept
Final Settlements
Transfer Product Responsibility
Evaluate Project
Document Results
Release/Redirect resources
Reassign Project Team
Termination Phase
-
8/7/2019 Cm Training
12/166
12
The Project Organization
-
8/7/2019 Cm Training
13/166
13
The Project Organization
Various Forms of Project Organizational
Structures
Project-Based
Functional/Division-Based
Pure Matrix
Modified Matrix
-
8/7/2019 Cm Training
14/166
14
The Project Organization
The Project-Based Organization
Design
Engineering
Procurement
Construction
Project 1Oil Refinery
Design
Engineering
Procurement
Construction
Project 2Office Building
Design
Engineering
Procurement
Construction
Project 3Hotel
The Big Cheese
-
8/7/2019 Cm Training
15/166
15
The Project Organization
The Project-Based Organization
Advantages:Focus is on delivering the PROJECT
Better interface between Project Team
members
Teamwork
Better Communication Flow
One Stop Shopping for Management
-
8/7/2019 Cm Training
16/166
16
The Project Organization
The Project-Based Organization
Disadvantages: Corporate Goals not always priority
Tunnel Vision
Redundant Staffing
Lack of Consistency, Procedures amongdifferent projects
-
8/7/2019 Cm Training
17/166
17
The Project Organization
The Fu ti l r iz ti
Pr ct Y
Phas 3
Pr ct X
Phas 1
Mark ti
ivisi
Pr ct X
Phas 3
Pr cti
Ivisi
Pr ct Z
Acc ti
ivisi
The i heese
-
8/7/2019 Cm Training
18/166
18
The Project Organization
The Functional Organization
Advantages:Consistency in Particular Disciplines/Areas
Corporate Goals are considered
Cross-utilization of Staff
-
8/7/2019 Cm Training
19/166
19
The Project Organization
The Functional Organization
Disadvantages:Lack of focus on the PROJECT
No independent central coordinator for
managing the projectCorporate/Division Politics often dictate
Projects often suffer from inadequate or
untimely staffing
-
8/7/2019 Cm Training
20/166
20
The Project Organization
Pur M trix r i ti
Refi er
r ject
H tel
r ject
Office
Buil i
i eeri
i i i
r ucti
i i i
ccounting
Di i ion
TheBig heese
-
8/7/2019 Cm Training
21/166
21
The Project Organization
The Pure Matrix Organization
Advantages:Best of both worlds
Balance between corporate/division needs and
those of individual projects
Central coordinator(s)/Project Manager(s)
Ideal for multi-project organizations
-
8/7/2019 Cm Training
22/166
22
The Project Organization
The Pure Matrix Organization
Disadvantages:Conflicts for resources among projects
Smaller projects suffer
Some staffing inefficiencies
-
8/7/2019 Cm Training
23/166
23
The Project Organization
ModifiedMatri r anization
Refi er
Pr ect
ffice
Bu il i
i eeri
ivisi
Pr ucti
ivisi
Acc un ting
Divisi n
Marketing Pr ect
X
TheBig heese
-
8/7/2019 Cm Training
24/166
24
The Project Organization
The Modified Matrix Organization
Advantages:
Tailor-made organization
Balance between corporate/division needs
and those of individual projects
Central coordinator(s)/Project Manager(s)
Ideal for multi-project organizations
Provision for Special or small projects
-
8/7/2019 Cm Training
25/166
25
The Project Organization
The Modified Matrix Organization
Disadvantages:Better suited for managing multiple projects
Some staffing inefficiencies
-
8/7/2019 Cm Training
26/166
26
The ProjectTeam
-
8/7/2019 Cm Training
27/166
27
The ProjectTeam
Purpose of the Project Team
To effectively implement the objectives of the
Project within a set of restraints
Objectives can include Quality, Efficiency,
Environmental, Public FactorsRestraints are usually Cost, Schedule, Impact
on Environment, Impact on Public
-
8/7/2019 Cm Training
28/166
28
The ProjectTeam
Qualities of an Effective Project Team
Technical Qualifications Interpersonal Factors
Effective Organization
Effective
Communication
Adequate Authority and
Responsibility
KNOWTHE JOBTEAMWORK
PLAN, PLAN, PLAN
KNOWWHAT GOES ON
ABILITYTO GETTHE
JOB DONE
-
8/7/2019 Cm Training
29/166
29
The ProjectTeam
Typi al roject Team r anization Chart
Planning
Envir nmental
G vt Relati ns
ther
perati ns
Design/
Engineering
Pr ucti n/
Fabricati n
Construction/Installation
Commissioning
Cost
Schedule
Contracts/Legal
Qualit
Control
Document
Con trol
Project
Controls
Project Manager
wner/C lient
-
8/7/2019 Cm Training
30/166
30
The ProjectTeam
ACTIVE
Maintains Day toDay Control
Conflict with Project
Manager
Better Product ?
PASSIVE
Not involved in Dayto Day Affairs
Sets Overall
Direction
Lack of Control ?
The OwnerThe Owner
-
8/7/2019 Cm Training
31/166
31
The ProjectTeam
The Project ManagerThe Project Manager
The Conductor of the Project
Orchestra
Facilitator, Liaison, Go-Between
Responsibility = < Authority
Right Combination ofTechnical andInterpersonal Skills
-
8/7/2019 Cm Training
32/166
32
The ProjectTeam
Project ControlsProject Controls
Critical Tools of the Project Manager
Cost/ScheduleControl/Contracts/Legal
Quality Control
Document Control
Provide the Checks and Balances for the
Project
The Police
-
8/7/2019 Cm Training
33/166
33
The ProjectTeam
Other Project Team MembersOther Project Team Members
Design/Engineering Construction/Installation
Commissioning/Closeout
Operations
Ancillary Bodies
-
8/7/2019 Cm Training
34/166
34
PROGRAM, PROJECT, CONSTRUCTION
MANAGEMENTAND OVERSIGHT
Session 2
-
8/7/2019 Cm Training
35/166
35
What is Project Management?
Project Management for Design/
Construction can be defined as:
the process of professionalmanagement applied to the planning,
design and construction of a project
from inception to completion for the
purpose of controlling time, scope,cost and quality.
-
8/7/2019 Cm Training
36/166
36
What is Project Management?
The 4 core elements:
ScopeManagement
QualityManagement
TimeManagement
CostMana ement
-
8/7/2019 Cm Training
37/166
37
What Is Project Management ?
CORE 1
SCOPE MANAGEMENT:
Defining objectives
Determine activities necessary to achieve the
objectives
Monitor and control scope vs. objectives Quantify the resources
Manage (inevitable) changes
-
8/7/2019 Cm Training
38/166
38
What Is Project Management ?
CORE 2
QUALITY MANAGEMENT:
Establish the standards of qualityrequired to meet the investment
objectives;
Then manage the project to meet
these standards using Quality
Assurance and Quality Control.
-
8/7/2019 Cm Training
39/166
39
What is Project Management ?
CORE 3
TIME MANAGEMENT:
Plan the activities
Schedule the activities
Monitor and control actual Resolve impacts to
schedule/time
-
8/7/2019 Cm Training
40/166
40
What is Project Management ?
CORE 4
COST MANAGEMENT:
Define investment
Prepare estimates
Establish budgets
Control actual vs. budget
-
8/7/2019 Cm Training
41/166
41
What is Project Management ?
Project Management requires special skills to
achieve the four core elements
Managing People
Effective Communications
Resource Management
Risk Management
Technical Knowledge
-
8/7/2019 Cm Training
42/166
42
What is Project Management ?
Managing People - because people are at the center of theproject;
Communications - providing leadership and direction;obtaining feedback and then adjusting actions to match actualevents;
Resource Management- obtaining the necessary resourcesand commitments in the most efficient manner;
Risk Management- avoiding or minimizing risks to projectsuccess by identifying quantifying the risk, allocating the riskto the project and managing it;
TechnicalKnowledge - because you cant manage what youdont understand.
-
8/7/2019 Cm Training
43/166
43
What is Project Management ?
What Brought About Project Management?
The traditional separation of
Owner, Designer,
Contractor often caused conflicts because each
has different objectives;
Increased complexity of modern projects;
Owners desires for faster completion - time
equals money:
-
8/7/2019 Cm Training
44/166
44
What is Project Management ?
What Brought About Project Management?
(continued)
Increased cost of resources Development of management
skills, tools and systems that could
be adapted to construction; Effective management found
to increase productivity
-
8/7/2019 Cm Training
45/166
45
What is Project Management ?
What are the Benefits of Project Management?
Better planning of projects
More productive use of resources
Better control of risk
Improved communications and teamwork
MORE SUCCESSFUL PROJECTS!
On Time - Within Budget - Right Quality
-
8/7/2019 Cm Training
46/166
-
8/7/2019 Cm Training
47/166
47
What is Project Management ?
Why So Many Different Delivery Methods?
Different Needs ofOwners
Different Capabilities ofOwners
Nature and Complexity of Project
Amount ofTime for Project
-
8/7/2019 Cm Training
48/166
48
What is Project Management ?
However, no matter what method you use,
every construction project requires the following:
Plan What You Want
Design What You Plan
Build the Design
MANAGEMENTOF THE ENTIRE PROCESS
-
8/7/2019 Cm Training
49/166
49
Traditional Approach
Planning DesignAdvertise
&AwardConstruction
Occupancy
Start-up
A rch itect/
En g ineer
S ubco ntr ac to r s
Gener a l
C o n tr ac to r
O w ne r
-
8/7/2019 Cm Training
50/166
50
Traditional Approach
Project Phases in sequence
Contractor does not participate in design
Complete design before construction
Owner must manage entire process
A/E and General Contractor independent
Owner has maximum control
-
8/7/2019 Cm Training
51/166
51
Clerk ofWorks/ A/E Administration
Planning DesignAdvertise
&AwardConstruction
Occupancy
Start-up
A rc h i t e c t -
E n g i n e e r
S u b c o n t r a c t o rV e n d o r s
G e n e r a l
C o n t r a c t o r
O w n e r
-
8/7/2019 Cm Training
52/166
52
Clerk ofWorks/ A/E Administration
Similar to traditional approach.
Difference is expanded role ofA/E
A/E performs basic administration,
inspection during construction
Owner manages all other aspects
-
8/7/2019 Cm Training
53/166
53
Design/Build
Planning Design
ConstructionOccupancy
Start-up
D e s ig n e r s S u b c o n t r a c t o r
V e n d o r s
D e s ig n - u i ld
C o n t r a c t o r
w n e r
-
8/7/2019 Cm Training
54/166
54
Design/Build
Single firm responsible for design andconstruction
Owner defines performance, D-B Contractordetermines design
Owner has less control, less responsibility
Design often controlled by construction, not
independent Usually faster than traditional
Allows construction expertise into design
-
8/7/2019 Cm Training
55/166
55
Project/Construction Management
Planning DesignAdvertise
&AwardConstruction
Occupancy
Start-up
Planning Design
Award Construction
Award Construction
Award Construction Occupancy
Start-up
OR
-
8/7/2019 Cm Training
56/166
56
Project/Construction Management
ArchitectEngineer
Trade
Contractor
Trade
Contractor
TradeContractor
rojectConstruction
Manager
wner
ArchitectEngineer
Subcontractor
GeneralContractor
ConstructionManager
OwnerOR
-
8/7/2019 Cm Training
57/166
57
Project/Construction Management
CM is Owners agent and performs manyresponsibilities forOwner
CM role is to manage design and/or construction
All contracts with Owner
Brings construction expertise to design
Permits fast-track projects
Allows multiple prime trade contractors, or onegeneral contractor with subcontractors.
-
8/7/2019 Cm Training
58/166
58
Program Management
Project A
Project B
Project C
-
8/7/2019 Cm Training
59/166
59
Program Management
Project "A " Project "
" Project "C"
Pro gr am
M a n a ger
A /E G .C C /M A /E G .C A / S G .C
w ner
Project "A" Projec t " "
Project"C"
A/E G.C C/M A.E G.C
A.E G.C
Program
Manager
wner
-
8/7/2019 Cm Training
60/166
60
Program Management
Management of multipleprojects
Single Management firm Provides consistent standards,
controls and reporting on allprojects
Effective management ofproject interfaces
-
8/7/2019 Cm Training
61/166
61
Project Management Oversight
(PMO)
Pr j
t " "
Pr j t " "Pr j t "A"
PM
sult t
Ar it t
E
i
r
G r l
tr
t r
Ar it t
E
i
rs
tr t rs/
Subcontr ctors
Proj ct/
onstruction
M nagers
Designer Subcontractor
Design- uil
ontractor
wner
-
8/7/2019 Cm Training
62/166
62
Project Management Oversight
(PMO) PMO is independent consultant toOwner
PMO focus is top management
PMO surveys, evaluates, reports on all aspects:
planning, design, construction
No direct responsibility to manage project
Can work with any other project delivery methods
Good at identifying potential problems, facilitating
resolutions Most effective for large projects
Most often used by Top management or funding agenciesnot directly involved, e.g. Banks, Governments
-
8/7/2019 Cm Training
63/166
63
Comparison of Delivery MethodsTraditional Clerk of Works
A/E
Administration
Design-
Build
Program Project/
Construction
Management
Project
Management
Oversight
Principal
Advantages
-Owner has
greatest control
-Designcomplete before
construction-Most commonsystem, familiar
to Owners, manycontract forms
available-Can be cheaper
because lessconsultants
-Similar to
traditional
-A/E assistsOwner to
manage, whichreduces Ownersresponsibility,
staff
-Fastest-
allows fast-
track-Owner deals
with 1 entity-Lessresponsibility
on Owner,less staff
-Lessadversarial
-Combinesconstructionexpertise intodesign
-Applies
management
expertise to project-PM/CM is
independent-focusis on projectssuccess
-Bringsconstruction
expertise to design-Allows fast-
tracking and multi-contracting-Gives Owner awide, flexible
range of services toselect-Less adversarial-Owner has lessresponsibility, less
staff-Independent
inspection and
quality control
Independent,
experienced
consultant to helpidentify, solve
problems-Keeps topmanagement
informed,involved
-Inexpensive
(1%)
-Assists allparties to
establish effectivecontrols,
reporting
-
8/7/2019 Cm Training
64/166
64
Comparison of Delivery Methods
Traditional Clerk of
Works A.EAdministra
tion
Design-Build Program
Project/Construction
Mana ement
Project
ManagementOversight
Principal
Dis-
advantages
-Slowest-Moreresponsibility on
Owner, requireslarger staff-Price not knowntill designcomplete-Most adversarial-competing
interests-No constructioninput to design-Difficult forlarge, multi-contractor projects
-Similar totraditional-Does not
provide fullmana ement
-A/Esinterestscan bebiased todesign
-Less controlby Owner-Limited
access todesign team-Design oftensubordinated toconstruction-Requirescareful
planning byOwner-Not as manyfirms who cando D.B
-Owner hasless control-Adds costs of
PM/CM
-May raisepotentialconflict with
Owner staff-Not alwayscost effectiveon smallerprojects
-
8/7/2019 Cm Training
65/166
65
Planning for the
Success of t
he Project
Session 3Session 3
-
8/7/2019 Cm Training
66/166
66
Planning is Essential
for aS
uccessful Project Planning defines and quantifies the
measure of success
Through planning, the project team defineshow it will organize to achieve this success
Planning defines and develops the tools that
are needed to manage to success Planning defines the risks and establishes
the measures to avoid or manage the risks
-
8/7/2019 Cm Training
67/166
67
Why Do We Need to Plan?
Studies and case histories have shown
planning to be the single most important
factor for successful projects Planning is done at the very start, when we
have the most control
Enables the project team to apply thebenefits of experience
Anticipates problems and their solutions
-
8/7/2019 Cm Training
68/166
68
Types of Planning
First step of planning is to identify the
project mission:
What is the project ?
Who is the project for (the market) ?
Why is the project being built ?
(short and long term projection)
-
8/7/2019 Cm Training
69/166
69
Three Types of Planning
Strategic planning
Operational planning / construction masterplan
Project scheduling
-
8/7/2019 Cm Training
70/166
70
Strategic Planning
High level selection of the
project objectives
Target investment level Projected date of
completion
Desired marketpenetration
-
8/7/2019 Cm Training
71/166
71
Operational Planning/Construction
Master Plan Analysis of available construction resources
within the company
The impact of the new projecton existing work load
Identification of the
required resources andwhere to be acquired
O l Pl /C
-
8/7/2019 Cm Training
72/166
72
Operational Planning/Construction
Master Plan (continued)
Organize and control major work activities
to meet project goals
Project budget/estimate Resource plan (people, material, systems)
Project schedule
Procurement plan (subcontracting, etc.)
-
8/7/2019 Cm Training
73/166
73
Elements to Effective Planning
of Construction Projects
Hills experience has shown seven (7) elements to
be necessary to construction project plans
(1) Clear Definition of Project Goals and Objectives
(2) Well Defined Project Organization
(3) ComprehensiveWork Breakdown Structure (WBS)
(4) AWritten Project Management Plan (PMP)
(5) Development of the NecessaryT
ools and Systems forManaging the Project
(6) AMaster Schedule
(7) An Effective Risk Management Program
-
8/7/2019 Cm Training
74/166
74
Project Goals & Objectives
(1) Clear Definition of the Project Goals
and Objectives
Project Goals and Objectives include:The desired function or output
The desired cost or investment
The desired duration to complete
The desired quality
-
8/7/2019 Cm Training
75/166
75
Project Goals & Objectives(continued)
The Goals and objectives define the
value(s) for the project The project values define the balance
between cost, schedule, quality and
function
-
8/7/2019 Cm Training
76/166
76
Project Organization
(2) Well Defined Project Organization Organizing the Project team early permits pro-active management and
establishes proper relationships of work and responsibilities.
The project Organization should define the members of the project
team and outside parties affecting the project, for example:
ProjectTeam Outside Parties
- Owner - Banks and Financing
- Operator - Insurers
- Designers - Surety/Bonding
- Contractors - Government and Regulatory
- Project Manager
- Consultants
-
8/7/2019 Cm Training
77/166
77
Project Organization
The Project Organization defines the roles
and responsibilities of the project team:
This includes: Scopes ofWork (SOW)
Responsibility/approval authority
Reporting and communication matrix Interfaces between the project team members
-
8/7/2019 Cm Training
78/166
78
Work Breakdown Structure
(3) Comprehensive Work Breakdown
Structure (WBS)
Definition: A tree of activities which organizes,defines and graphically displays the total work to
be accomplished in order to achieve the final
objectives of a project. Each level of the WBS
represents an increasing detailed definition of theproject activities. The WBS is a system for
subdividing a project into manageable work
packages.
-
8/7/2019 Cm Training
79/166
79
Work Breakdown Structure(continued)
Purpose ofWBS:
(1)Organizes the work into detailed packages
(2)Assures that all necessary activities areidentified and organized
(3)Shows relationships of work packages
(4)Defines how the cost and schedule are to be
developed and integrated
(5)Assigns responsibility for all project work
-
8/7/2019 Cm Training
80/166
80
Work Breakdown Structure(continued)
What
Can a WBS
Do For You
Break the Scope
of Work Down
Into Know Tasks
Provide Resource
Planning Information
for Manager
Identify End Products
and
Deliverables
Allow Development
of Integrated
Costs and Schedules
Track Cost
and
Schedule
Assign Responsibility
for Work
Performance
-
8/7/2019 Cm Training
81/166
81
Work Breakdown Structure(continued)
Work Breakdown Structure Example
AAB01
Design
AAB
Houses
AAA01
Design
AAA
Apartments
AA
Housing Complex
ABA
Below Grade
ABB
Levels 1-20
AB
Office Complex
AC
Retail Complex
Project ANew Center
-
8/7/2019 Cm Training
82/166
82
Project Management Plan
(4) AWritten Project Management Plan
(PMP)
A written document designed to cover allproject activities through project
completion.
Written by the Project Management Team Updated throughout project as elements of
the project change
-
8/7/2019 Cm Training
83/166
83
Project Management Plan (continued)
Example: Table of Contents of one of Hills PMP Manuals:
PART 1 Preliminary Design1 Introduction2 Summary
3 Objectives, Goal and C onstraints4 Assumptions/Anticipated Conditions5 O rganisation and Staffing6 Preliminary D esign Program7 Permit Requirement8 Project Control
9 AppendicesPART 2 FINAL DESIGN & CONSTRUCTION PHASE1 Assumptions/Anticipated Conditions2 Final Design & Construction Phase3 Scope of P rofessional Services4 Project Organisation & M anagement
-
8/7/2019 Cm Training
84/166
84
Tools & Systems
(5) Development of the Necessary Tools and Systems forManaging the Project
The Essential Tools for Managing the Project Cover:
Scope
Cost
Quality
Schedule
Documentation/Communication
-
8/7/2019 Cm Training
85/166
85
Tools & Systems
Scope (1) Design documents - drawings, specifications,conceptual, schematic, design development,
construction documents
(2) Contract Packaging
(3) ChangeOrder Management
(4) Configuration Management
(5) As-built documentation - drawings, warranties,
O&M Manuals
-
8/7/2019 Cm Training
86/166
86
Tools & Systems(continued)
Cost 1) Target Investment2) Budgets
3) Estimates4) Cost Control
5) Accounting
6) Commitments
7) Changes
8) Forecasting and Trending
-
8/7/2019 Cm Training
87/166
87
Tools & Systems (continued)
Quality 1) Quality Standards2) Quality Assurance Program
3) Regulatory Requirements e.g. CTMA
4) Quality Control and Inspection
5) Change Control6) Non-Conformance and Corrections
7) Record-keeping
Schedule 1) Planning2) Master Schedule
3) Detailed Schedules4) Elemental Schedules - Design, Construction,
Procurement, other
5) Updating and Reporting
6) Variation and Impact Evaluations
7) RiskAnalysis
-
8/7/2019 Cm Training
88/166
88
Tools & Systems (continued)
Communication/Documentation
1) Document Management
2) Logs and Reports e.g. - submittals, RFIs, ChangeOrders3) Management Information System
4) Meetings
5) Procedures Manual
6) Approval and Reporting Matrices
-
8/7/2019 Cm Training
89/166
89
MasterSchedule
(6) A Master Schedule
Summary of all major activities to achieve project
completion
Defines overall time for project and the duration
for each major activity
Confirms the feasibility of the overall project
duration Defines major milestones
Identifies major interfaces with outside entities
-
8/7/2019 Cm Training
90/166
90
Risk Management Program
(7) An Effective Risk Management Program
Purpose of Risk Management Program:
Identify and evaluate risks to project To plan how to handle and manage each risk
To implement the plan and to monitor all potential
risks
Identification and Evaluation of Risks should cover: technical risks
cost, financial & Schedule
political, governmental and regulatory
-
8/7/2019 Cm Training
91/166
91
Risk Management Program(continued)
Plan How to Handle and Manage Each Risk
Techniques for risk management
Avoid the riskby taking measures to eliminate the risk:
e.g. pre-qualification of contractors Reduce the risk- by taking measure to continually re-evaluate the
risk and developing fall back positions:
e.g. contingency planning and allowances
Retain the risk- accept the consequences if the risk occurs
Transfer the risk- sharing or completely transferring the risk toanother party.
e.g. specifying the risk in the construction contract and making the
contractor responsible
e.g. obtaining insurance to protect if the risk occurs
e.g. performance bonds.
Creating and Implementing
-
8/7/2019 Cm Training
92/166
92
g p g
PM/CMTools
Session 4
Creating and Implementing
-
8/7/2019 Cm Training
93/166
93
g p g
PM/CMTools
Successful management is like magic, its easy
if you have the tools. All you need are:
Work Break Down Structure (WBS)
Design/Scope Management
Cost management
Schedule
Quality control
Document control
Field management control
Creating and Implementing
-
8/7/2019 Cm Training
94/166
94
g p g
PM/CMTools
Work Break Down Structure (WBS)
Task-oriented family tree which organizes,
defines and graphically displays project Descending levels represent detailed
definition of the objectives
Relates elements of work to each other andend product
Creating and Implementing
-
8/7/2019 Cm Training
95/166
95
g p g
PM/CMTools
WBS (continued)
The WBS allows for the following:
Estimates, costs, budget, schedule can beestablished from detail level (bottom-up)
The total program can be described as a
summation of subdivided elements/tasks Potential problems are detected at low level
early enough to be pro-active
Creating and Implementing
-
8/7/2019 Cm Training
96/166
96
g p g
PM/CMTools
Work Breakdo n tructure Exam le
B102 ite
ork
B103 Concrete
B104
asonry
B105 etals
B106Wood&Plasitic
B107 Thermal& ! oisture Protec
B108 Doors&Windo"
s
B109 Finishes
B110 # ecialities
B111 Equi # ment
B112 Furnishings
B113 # ecial construction
B114 Con$
eying ystem
B115 ! echanical
B116 Electrical
B102-16Construction Trates
B1011 Conce # t Design
B1012 Design De$
elo# ment
B1013
chematic
B1014 Construction Dra
ings
B101DE% I & N
B1Villa 1
AAB2Villa 2
AABVillas
AAAAppartmens
AAHousing Complex
ABABelo
' rade
ABBLe
$
els 1-20
ABOffice Complex
AC hopping all
Project ANe
Center
Creating and Implementing
-
8/7/2019 Cm Training
97/166
97
g p g
PM/CMTools
Design/Scope Management
At each level of design a validation
estimate needs to be conducted andif higher than budget re-design
Value engineering to be part of
design team during all design
stages Design to be frozen prior to
contractor award
Creating and Implementing
-
8/7/2019 Cm Training
98/166
98
g p g
PM/CMTools
Design/Scope Management (continued)
A common danger for cost overruns arises throughscope
creepsand changes after the design has been frozen and
released to the contractor. These changes need to betraceable and tightly controlled.
Changes after design is frozen must be:
Estimated separately
Analyzed for schedule impact
Approved by Management
Negotiated and settled with contractor ASAP
Creating and Implementing
-
8/7/2019 Cm Training
99/166
99
g p g
PM/CMTools
What is Cost Management?
Cost management is a function which
includes the processes that are requiredto maintain effective financial control
of projects:
Estimating, Budgeting and Cost control
Scheduling, Evaluating and Monitoring Analyzing and Adjusting
Reporting
Creating and Implementing
-
8/7/2019 Cm Training
100/166
100
g p g
PM/CMTools
Estimating
Methods of estimating:
Detailed bottom-up estimateConceptual judgmental estimate
Parametric historical cost parameters
Firm Quotes from potential vendors
Creating and Implementing
-
8/7/2019 Cm Training
101/166
101
g p g
PM/CMTools
Estimating (continued)
The estimating effort should be continuous
on the project. Recommended levels are: Conceptual estimate
Schematic Estimate
Design Development estimate
Construction drawing estimate
Field Changes and Change Order Estimates
Creating and Implementing
-
8/7/2019 Cm Training
102/166
102
PM/CMTools
Estimating (continued)
A contingency provision is to be included in
the various estimates, due to the percentageof accuracy available at each level of design
Concept/Feasibility 25%-40%
Obtain project Funding 15%-25% Capital cost/budget 10%-15%
Definitive/In field 7%-5%
Creating and Implementing
-
8/7/2019 Cm Training
103/166
103
PM/CMTools
Estimating (continued)
By establishing a contingency the project
team has the ability to manage problemsand changes without alarming higher
management.
Contingency usage monitoring is a goodindication on the performance of the project
team by Management.
Creating and Implementing
-
8/7/2019 Cm Training
104/166
104
PM/CMTools
Budgeting
The project budget sets a realistic projection for
material, labor, subcontractor and indirect costs on thetotal project.
A poor estimate/budget leads to an unrealistic budget
causing cost overruns and loss of control.
The project budget is the baseline for cost control
Creating and Implementing
-
8/7/2019 Cm Training
105/166
105
PM/CMTools
Budgeting (continued)
At the capital stage the budget has to be
frozen and serves as baseline with costs andfuture commitments.
Budget breakdown in accordance with the
WBS
Contingency usage is tracked and managed
Creating and Implementing
-
8/7/2019 Cm Training
106/166
106
PM/CMTools
Schedule
In construction projects there are usually two
schedules: Owners schedule - macro schedule stressing the
strategic planning goals including design
Contractors schedule - fully detailed operational
schedule covering all the construction work
activities within the owners end date
Creating and Implementing
-
8/7/2019 Cm Training
107/166
107
PM/CMTools
Schedule (continued)
Two scheduling methods
Bar Charts
Logic-diagram-based schedules
Both have advantages and disadvantages
and are sometimes interchangeable
Creating and Implementing
/C l
-
8/7/2019 Cm Training
108/166
108
PM/CMTools
Schedule (continued)
Bar charts
Advantages:
Inexpensive and simple to prepare
Easy to read and update
Disadvantages: Inability to show enough detail to cover all Activities onlarge projects
Do not show the interrelation of activities
Creating and Implementing
-
8/7/2019 Cm Training
109/166
109
PM/CMTools
Schedule (continued)
Logic-diagram-based schedules
AdvantagesReveals interdependence of activities
Calculates project completion dates
Enables what if analysesHighlights critical activities
Evaluates performance
Creating and Implementing
-
8/7/2019 Cm Training
110/166
110
PM/CMTools
Schedule (continued)
The logic diagramed basedschedule is the right tool as the
project schedule
Provides the ability to organize
schedule at the lowest level ofWBS
Creating and Implementing
-
8/7/2019 Cm Training
111/166
111
PM/CMTools
Schedule (continued)
Contractor schedule can be used to
electronically update the Owners schedulebased on approved completion for each
period
The ability to cost load the schedule andproduce earned value analysis
Allows management of project float
Creating and Implementing
-
8/7/2019 Cm Training
112/166
112
PM/CMTools
Quality Control
Conformance to requirements
Doing it right the first time
Fitness for the purpose
Creating and Implementing
-
8/7/2019 Cm Training
113/166
113
PM/CMTools
Quality Control Plan includes
Quality assurance
Quality Control
Quality Management
Creating and Implementing
-
8/7/2019 Cm Training
114/166
114
PM/CMTools
Quality Control Plan - Quality Assurance
QA procedures
Quality Systems Verification
Identify& analyze issue
Audits/observation
Rework reporting
Corrective action
Training
Creating and Implementing
-
8/7/2019 Cm Training
115/166
115
PM/CMTools
Quality Control Plan - Quality Control
Tests/inspection plan
Design/technical reviews
Fabrication & installation inspection
Material control and inspection
Calibration control
Contractor & subcontractor control
Creating and Implementing
-
8/7/2019 Cm Training
116/166
116
PM/CMTools
Quality Control Plan - Quality Management
Quality based client relations
Quality skills training Project execution strategy
Work process improvement
Obstacle identification & removal
Project information feedback
Creating and Implementing
-
8/7/2019 Cm Training
117/166
117
PM/CMTools
Document Control
Integrated system based on the WBS for all
documents of the project. Organized filling facilitates team to work
Engineering drawing tracking
Correspondence tracking One stop shop for historical data
Creating and Implementing
-
8/7/2019 Cm Training
118/166
118
PM/CMTools
Field Management Control
All field changes initiated by owner must be
approved in writing by the PM/CM; noverbal authorization
Contractor field change request must be
approved by PM/CM prior to initiation To avoid disputes all field changes should
be negotiated bi-monthly
Creating and Implementing
/ l
-
8/7/2019 Cm Training
119/166
119
PM/CMTools
OPEN DOOR POLICY
Communication failure can
neutralize all tools, no matter
how well they are established
Common reasons are:
negative mode, not accepting
other peoples ideas, impatient,assuming others have the same
information, reacting without
analyzing the facts
-
8/7/2019 Cm Training
120/166
120
Th
e Project Manager
Session 5
Th P j M
-
8/7/2019 Cm Training
121/166
121
The Project Manager
What Makes a Successful Project Manager?
Must cross organizational boundaries
Must develop the Project Team into a cohesivegroup
Combination of technical, administrative and
people skills
Must create environment which motivatespeople to deliver a quality project
Th P j M
-
8/7/2019 Cm Training
122/166
122
The Project Manager
Project Managers Directive:
Accomplish what cannot be done;
Predict the Unknown;Develop a Plan to Address it;
Implement the Plan
With People who do not report to you
And with resources which you cant control
In an unreasonable time frame
And for an unreasonable budget
Th P j t M
-
8/7/2019 Cm Training
123/166
123
The Project Manager
Functional/Matrix Organization Balance of Power
Project
Organization
Functional
Organization
Project Manager Influence
Functional Manager Influence
Balance of
Power/
Influence
in Decision
Making
Strong Matrix Weak Matrix
Th P j t M
-
8/7/2019 Cm Training
124/166
124
The Project Manager
Skills of the Ideal Project Manager (1)
Team-Building
Empathy
Motivation
Leadership
Sets Examples
Energetic Big Picture Vision
Delegates
Ethics/Morals
Th P j t M
-
8/7/2019 Cm Training
125/166
125
The Project Manager
Skills of the Ideal Project Manager (2)
Communication
Listening
Understanding
Persuasion
Planning/Organizing
Flexibility Common Sense
Positive Approach
Goal-Setting
Th P j t M
-
8/7/2019 Cm Training
126/166
126
The Project Manager
Skills of the Ideal Project Manager (3)
Problem Solving Skills
Analyzing and Problem Solving
Negotiating
Conflict Management
Removing Obstacles
Creativity
T
echnical Skills Expertise/Experience/Credibility
Current Knowledge
Technical Problem Solving
Th P j t M
-
8/7/2019 Cm Training
127/166
127
The Project Manager
Skills of the Ideal Project Manager (4)
Coping Skills
Persistence
Patience
Crisis Handling
Stress Management
Estimation/SchedulingAdministration
Computer Skills
Th P j t M
-
8/7/2019 Cm Training
128/166
128
The Project Manager
Responsibilities of the Project Manager (1)Organize, coordinate and direct the Project
Resolve Conflicts between team members
Lead the Project Team in developing the PMP, the
Quality Assurance Guidelines, Design Standards and
Requirements, etc.
Communicate project goals and objectives to the
Project Team
Ensure requirements ofOwner are met
Th P j t M
-
8/7/2019 Cm Training
129/166
129
The Project Manager
Responsibilities of the Project Manager (2)
Lead the Project in:
Acquiring Resources
Selecting Team Members
Developing user requirements
Defining Scope and Quality
Defining Budgets
Determining Schedules
Maintain control to assure the project is completed in
accordance with the requirements set forth
The Project Manager
-
8/7/2019 Cm Training
130/166
130
The Project Manager
Responsibilities of the Project Manager (3)
Report project status on a regular basis
Ensure the completeness and adequacy of project
records and documentation Ensure that appropriate QA/QC procedures are set
in place and applied
Specify testing requirements and ensure
appropriate tests are carried out so that the projectmeets design requirements
Maintain successful ongoing operations and
maintenance
The Project Manager
-
8/7/2019 Cm Training
131/166
131
The Project Manager
Must be an Effective
Communicator Most of the working hours of a
Project Manager will be spent in
some type of communicatoractivity
Conferences, meetings, writing,
memoranda, issuing and reading
reports, communicating with team
members, communicating withmanagement, talking to
customers/clients, talking with
contractors, subcontractors, and
suppliers
R i i A T bl d P j t
-
8/7/2019 Cm Training
132/166
132
Reviving A Troubled Project
Session 6
R i i T bl d P j t
-
8/7/2019 Cm Training
133/166
133
Reviving a Troubled Project
I. WARNING SIGNS
II. FINDING THE REASONS
III. DETERMINING ALTERNATIVES
IV. IMPLEMENTING THE REVIVAL PLAN
V. REACTION AND FEEDBACK
Ad d l d
-
8/7/2019 Cm Training
134/166
134
AdvancedTools and
Techniques in ConstructionManagement
-
8/7/2019 Cm Training
135/166
135
Value Engineering
Value Engineering
-
8/7/2019 Cm Training
136/166
136
Value Engineering
Studies have shown $4.40 of
savings for every $1.00 spent onValue Engineering
Value Engineering can achieve 10-
20% cost savings while
maintaining value objectives
VE Potential Cost Savings
Value Engineering
-
8/7/2019 Cm Training
137/166
137
Value Engineering
Resultant VE Cost Savings over Project Life
Potential
for
Savings
from
Value
Engineering
Time
Schematic
Design
Design
Development
ContractDocuments
Construction
-
8/7/2019 Cm Training
138/166
138
Partnering
Partnering
-
8/7/2019 Cm Training
139/166
139
Partnering
New term based on old concept
Established 1988 by Army Corps of Engineers
Each of the contractual parties respects the rightsand responsibilities of the other(s)
Recognizes that every contract has an implied
good faith covenant
Does not change the terms of the signed contract
Partnering
-
8/7/2019 Cm Training
140/166
140
Partnering
Army Corps of Engineers Definition
...the creation of a relationship between Owner and Contractor
that promotes achievement of mutual and beneficial goals.
Construction Industry Institute Definition ...a long term commitment between two or more organizations for
the purpose of achieving specific business objectives by
maximizing the effectiveness of each participants resources. The
relationship is based upon trust, dedication to common goals and
understanding each others individual expectations and values.
Expected benefits include improved efficiencies and cost
effectiveness, increased opportunity for innovation and continuous
improvement of quality products and services.
Eliminate Us vs.. Them attitude.
Partnering
-
8/7/2019 Cm Training
141/166
141
Partnering
Keys to Success
Concept
Begin early in process
Establish mutual recognizance
Select Independent facilitator
Commitment from Corporate Management Continuously evaluate
Properly allocate risk
Partnering Workshop
-
8/7/2019 Cm Training
142/166
142
PartneringWorkshop
Partnering Workshop
Signed Charter to Guide the Partnership
Written Mission Statement and Objectives Specific Program to Measure Objectives
Action Plan for Key Problems
Establish Dispute Resolution Process
Address Individual Roles and Concerns
Team Evaluation Process with Facilitator
Partnering
-
8/7/2019 Cm Training
143/166
143
Partnering
Goals of Partnering
On Time Completion
Completion within
Owner and Contractor budgets
Deliver required quality or better
Establish realistic, achievable schedule
Reduce paperwork
Avoid litigation or arbitration
Eliminate lost/unproductive time
Eliminate accidents
Partnering
-
8/7/2019 Cm Training
144/166
144
Partnering
Benefits of Partnering
Owner
Reduced Exposure to Litigation
Better Quality
Lower Risk of Cost Overruns and Delays
Contractor
Reduced Exposure to Litigation
Increased Productivity
Lower Risk of Cost Overruns and Delays
Partnering
-
8/7/2019 Cm Training
145/166
145
Partnering
Essential Elements of Partnering
Recapitulation
Commitment Equity
Trust
Communication
FOR EXAMPLE
-
8/7/2019 Cm Training
146/166
CLARKLEISURE HILLS
RESIDENCE & RESORT COMPLEX
DEVELOPMENT PLAN
Our Approach & Process
Things to Know
The Key Factor
Management StructureThe Palm Jebel Ali / The Palm Jumeriah/ The world Islands
Hil l is managing design and construction of Palm Islands, two man-made,palm-shaped islands in Dubai, UAE. The first is land, Palm Jumeirah, willinclude 2,400 homes, 30 hotels, aquatic themed entertainment and touristattractions. The larger island, Palm Jebel Ali, will include 3,200 homes, 40hetels and commercial as well as retail properties.
HILL
Hill International
The Project Team
-
8/7/2019 Cm Training
147/166
- -
-
- Masterplan - /// - - VE -
- Proposal E aluation- Technical E aluation- Cost E aluation- -
-
-
-
-
The Conductor ofthe Project Orchestra
Facilitator, Liaison,Go-Between
Responsibility = < Authority
RightCombination ofTechnicalandInterpersonal Skills
The ProjectTeam
-
The Project
-
8/7/2019 Cm Training
148/166
Hill International + Hill Korea
Hill International + Hill Korea CM
(,,,, )
- ,, ,
(Value Engineering),
,,,,
, ,
,
,, (O&M)
The Project
-
AdvancedTools andTechniquesin Construction Management
-
8/7/2019 Cm Training
149/166
in Construction Management
- (I)
( /) ( /)
(QPMS) (QPMS)
VE VE
O&M (Operation & Maintenance)O&M (Operation & Maintenance)
AdvancedTools andTechniquesin Construction Management
-
8/7/2019 Cm Training
150/166
-
- - - / - / - / - -
- - Nego
- - - - - - - -
- - - -
- / / - Quality Control
in Construction Management
- (II)
AdvancedTools andTechniquesin Construction Management
-
8/7/2019 Cm Training
151/166
1) 2)
1)
1) Master Schedule 2)
1)
2)
3) VE ()4)
1) P.Q 2) Nego3)
1) 2) 3)
1) 2) 3)
1) 2) 3) 4)
1) 2)
3) (O&M Manual )
in Construction Management
-
Design/ Build
-
8/7/2019 Cm Training
152/166
Design/ Build
70%
100%
.
(20/80 : 20% 80% )
/ /
, , ,
, , ,
(, , )
,
,
Life Cycle Cost, Facility Management System
Creating andImplementing
PM/CM Tools
-
8/7/2019 Cm Training
153/166
PM/CMTools
: ,
(/ / / )
(/ ISO/ / )
PQ ()
/
(/, / )
, , , , /
Creating andImplementing
PM/CM Tools
-
8/7/2019 Cm Training
154/166
/ /
/
(/ / / etc)
/
Procurement
/ / / / /
/
(/ / / / / )
PM/CMTools
Creating andImplementing
PM/CM Tools
-
8/7/2019 Cm Training
155/166
Master Schedule Mile Stone
/ Long Lead Item
/
EVMS SYSTEM
(/ :
Earned Value Management System)
4 / /
Point
,
,
Fast Track
Fast Track
Long-Lead Item
Fast Track
Schedule Two scheduling methods
Bar Charts Logic-diagram-based schedules
Both have advantages and
Disadvantages and are sometimesinterchangeable
PM/CMTools
Creating andImplementing
PM/CM Tools
-
8/7/2019 Cm Training
156/166
/
AS-Built ,
, Sample, Spare Part List, O&M Manual
(, ,
,
, )
System
A/S SYSTEM
SYS
Feed-Back System
A/S SYSTEM
Zone
/ Data
/ System
System (Operation & Maintenance SYS)
FMS (Facility Management System)
, ,
, , / , , ,
, (Total Cost) /
LCC (Life Cycle Cost: )
PM/CMTools
Creating andImplementing
PM/CM Tools
-
8/7/2019 Cm Training
157/166
PM/CMTools
Successful management is like magic,Its easy if you have the tools.
All you need are
PM & CM
Design/Scope Management
Cost management
Schedule
Quality control
Document control
Field management control
Creating andImplement PM/CMTools
-
8/7/2019 Cm Training
158/166
OPEN DOOR POLICY Communication failure can
neutralize all tools, nomatter how well they areestablished
Common reasons are:
negative mode, not
accepting other peoplesideas, impatient, assumingothers have the sameinformation, reactingwithout analyzing the facts
PM/ CM PM/ CM
[Professional Ethic]
(Engineering Ethic)
()
(Workmanship]
////
-
8/7/2019 Cm Training
159/166
THE KEY FACTOR
-
8/7/2019 Cm Training
160/166
THE TECHNICAL BIG FIVE
1. Risk Management
2. Project Procedures
3. Project Control ystems
4. uality Management
5.HSE Management
-
8/7/2019 Cm Training
161/166
THE COMMERCIAL BIG TWO
Often undertaken in cooperation and coordination ith the Cost
Consultant and the Employers Representati e are the follo ing
T o further PROGRAMMANAGEMENT elements:
6. Contract Packaging, Drafting and Management
7. Claims Avoidance orManagement
-
8/7/2019 Cm Training
162/166
-
8/7/2019 Cm Training
163/166
Profile of Project Director
-
8/7/2019 Cm Training
164/166
Name : Mr.Albert Cabellon (Nationality: USA)
Current position: Project manager,Hill International,Philippines
Education: California Polytechnic State University,San Luis Obispo (B.Sc. InArchitecture)
Career Highlight: 30 years in Project Management, Ne to n,High-rise Mixed-useDevelopment,Hospitality,Shopping Centers
Projects:
- UAE: 60story x 9buildings Mixed-use Development (Hotel, Residental,Office to ers)(US$2.5 billion)/ PM
- USA: 700 unit Condominium To ers, t o 40 story to er(US$300Million)/
PMInternational Cruise Terminal,San Francisco / PMT o 5-star Hotel and Golf Resorts,717Acres (US$120Million)/5 PMMega scale Po er Center(Shopping Malls)/Ne To n Development /
-
8/7/2019 Cm Training
165/166
165
-
8/7/2019 Cm Training
166/166