cm training

Upload: jmgwoo

Post on 08-Apr-2018

229 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/7/2019 Cm Training

    1/166

    1

    Essentials of Project and

    Construction ManagementLand is Life

    Korea Land Corporation(KLC)

    In association withHill International, Inc.

    Hill International, Inc.

    Strictly

    Confidential

  • 8/7/2019 Cm Training

    2/166

    2

    THE PROJECT

    Session 1

  • 8/7/2019 Cm Training

    3/166

    3

    The Project

    A Discrete, Planned Undertaking

    having

    A Defined Scope

    A Start and a Finish

    The Project Approach Has

    Evolved to be a Management

    Buzzword

    Origins in the EPC Industry

  • 8/7/2019 Cm Training

    4/166

    4

    The Project

    Traditionally EPC industry was loose conglomerate of

    designers, financiers, builders, suppliers, contractors, etc.

    Complexity, computerization, and failures brought forwardthe need for a Project Approach

    The ProjectApproach has now become the rule rather than

    the exception

    Project Management concept has evolved, defined as

    The management of an organized set of activities towards

    defined objectives using limited resources applying

    specialized management structures and techniques.

  • 8/7/2019 Cm Training

    5/166

    5

    The Project Life Cycle

  • 8/7/2019 Cm Training

    6/166

    6

    The Project Life Cycle

    All projects exhibit similar life cycles

    Four primary seasons

    Concept

    Development

    Implementation

    Termination/Completion

  • 8/7/2019 Cm Training

    7/166

    7

    The Project Life Cycle

    Concept Development Implementation Termination

    L

    e

    v

    e

    l

    o

    f

    E

    f

    f

    o

    r

    t

  • 8/7/2019 Cm Training

    8/166

    8

    The Project Life Cycle

    Gather data

    Identify need

    Establish

    goals, objective

    basic economics,

    feasibility stake holders

    risk level

    strategy

    potential team

    Guesstimate Resources

    Identify Alternatives

    Present proposal

    Obtain Approval for nextphase

    Concept Phase

  • 8/7/2019 Cm Training

    9/166

    9

    The Project Life Cycle

    Appoint Key Team

    Members Conduct Studies

    Develop ScopeBaseline

    end product(s)

    quality standards

    resources

    activities

    Establish

    master plan budget, cash flow

    WBS

    policies andprocedures

    Assess risks

    confirm justification

    Present project brief

    Obtain approval to

    proceed

    Development Phase

  • 8/7/2019 Cm Training

    10/166

    10

    The Project Life Cycle

    Set Up Organization

    Communications

    Motivate Team

    Detail Technical Req.'s

    Establish Work packages

    InformationControl Systems

    Procure Goods and Services Execute Work Packages

    Direct/Monitor/Forecast/Control:

    Scope

    Quality Time

    Cost

    Resolve Problems

    Implementation Phase

  • 8/7/2019 Cm Training

    11/166

    11

    The Project Life Cycle

    Finalize Products Review and Accept

    Final Settlements

    Transfer Product Responsibility

    Evaluate Project

    Document Results

    Release/Redirect resources

    Reassign Project Team

    Termination Phase

  • 8/7/2019 Cm Training

    12/166

    12

    The Project Organization

  • 8/7/2019 Cm Training

    13/166

    13

    The Project Organization

    Various Forms of Project Organizational

    Structures

    Project-Based

    Functional/Division-Based

    Pure Matrix

    Modified Matrix

  • 8/7/2019 Cm Training

    14/166

    14

    The Project Organization

    The Project-Based Organization

    Design

    Engineering

    Procurement

    Construction

    Project 1Oil Refinery

    Design

    Engineering

    Procurement

    Construction

    Project 2Office Building

    Design

    Engineering

    Procurement

    Construction

    Project 3Hotel

    The Big Cheese

  • 8/7/2019 Cm Training

    15/166

    15

    The Project Organization

    The Project-Based Organization

    Advantages:Focus is on delivering the PROJECT

    Better interface between Project Team

    members

    Teamwork

    Better Communication Flow

    One Stop Shopping for Management

  • 8/7/2019 Cm Training

    16/166

    16

    The Project Organization

    The Project-Based Organization

    Disadvantages: Corporate Goals not always priority

    Tunnel Vision

    Redundant Staffing

    Lack of Consistency, Procedures amongdifferent projects

  • 8/7/2019 Cm Training

    17/166

    17

    The Project Organization

    The Fu ti l r iz ti

    Pr ct Y

    Phas 3

    Pr ct X

    Phas 1

    Mark ti

    ivisi

    Pr ct X

    Phas 3

    Pr cti

    Ivisi

    Pr ct Z

    Acc ti

    ivisi

    The i heese

  • 8/7/2019 Cm Training

    18/166

    18

    The Project Organization

    The Functional Organization

    Advantages:Consistency in Particular Disciplines/Areas

    Corporate Goals are considered

    Cross-utilization of Staff

  • 8/7/2019 Cm Training

    19/166

    19

    The Project Organization

    The Functional Organization

    Disadvantages:Lack of focus on the PROJECT

    No independent central coordinator for

    managing the projectCorporate/Division Politics often dictate

    Projects often suffer from inadequate or

    untimely staffing

  • 8/7/2019 Cm Training

    20/166

    20

    The Project Organization

    Pur M trix r i ti

    Refi er

    r ject

    H tel

    r ject

    Office

    Buil i

    i eeri

    i i i

    r ucti

    i i i

    ccounting

    Di i ion

    TheBig heese

  • 8/7/2019 Cm Training

    21/166

    21

    The Project Organization

    The Pure Matrix Organization

    Advantages:Best of both worlds

    Balance between corporate/division needs and

    those of individual projects

    Central coordinator(s)/Project Manager(s)

    Ideal for multi-project organizations

  • 8/7/2019 Cm Training

    22/166

    22

    The Project Organization

    The Pure Matrix Organization

    Disadvantages:Conflicts for resources among projects

    Smaller projects suffer

    Some staffing inefficiencies

  • 8/7/2019 Cm Training

    23/166

    23

    The Project Organization

    ModifiedMatri r anization

    Refi er

    Pr ect

    ffice

    Bu il i

    i eeri

    ivisi

    Pr ucti

    ivisi

    Acc un ting

    Divisi n

    Marketing Pr ect

    X

    TheBig heese

  • 8/7/2019 Cm Training

    24/166

    24

    The Project Organization

    The Modified Matrix Organization

    Advantages:

    Tailor-made organization

    Balance between corporate/division needs

    and those of individual projects

    Central coordinator(s)/Project Manager(s)

    Ideal for multi-project organizations

    Provision for Special or small projects

  • 8/7/2019 Cm Training

    25/166

    25

    The Project Organization

    The Modified Matrix Organization

    Disadvantages:Better suited for managing multiple projects

    Some staffing inefficiencies

  • 8/7/2019 Cm Training

    26/166

    26

    The ProjectTeam

  • 8/7/2019 Cm Training

    27/166

    27

    The ProjectTeam

    Purpose of the Project Team

    To effectively implement the objectives of the

    Project within a set of restraints

    Objectives can include Quality, Efficiency,

    Environmental, Public FactorsRestraints are usually Cost, Schedule, Impact

    on Environment, Impact on Public

  • 8/7/2019 Cm Training

    28/166

    28

    The ProjectTeam

    Qualities of an Effective Project Team

    Technical Qualifications Interpersonal Factors

    Effective Organization

    Effective

    Communication

    Adequate Authority and

    Responsibility

    KNOWTHE JOBTEAMWORK

    PLAN, PLAN, PLAN

    KNOWWHAT GOES ON

    ABILITYTO GETTHE

    JOB DONE

  • 8/7/2019 Cm Training

    29/166

    29

    The ProjectTeam

    Typi al roject Team r anization Chart

    Planning

    Envir nmental

    G vt Relati ns

    ther

    perati ns

    Design/

    Engineering

    Pr ucti n/

    Fabricati n

    Construction/Installation

    Commissioning

    Cost

    Schedule

    Contracts/Legal

    Qualit

    Control

    Document

    Con trol

    Project

    Controls

    Project Manager

    wner/C lient

  • 8/7/2019 Cm Training

    30/166

    30

    The ProjectTeam

    ACTIVE

    Maintains Day toDay Control

    Conflict with Project

    Manager

    Better Product ?

    PASSIVE

    Not involved in Dayto Day Affairs

    Sets Overall

    Direction

    Lack of Control ?

    The OwnerThe Owner

  • 8/7/2019 Cm Training

    31/166

    31

    The ProjectTeam

    The Project ManagerThe Project Manager

    The Conductor of the Project

    Orchestra

    Facilitator, Liaison, Go-Between

    Responsibility = < Authority

    Right Combination ofTechnical andInterpersonal Skills

  • 8/7/2019 Cm Training

    32/166

    32

    The ProjectTeam

    Project ControlsProject Controls

    Critical Tools of the Project Manager

    Cost/ScheduleControl/Contracts/Legal

    Quality Control

    Document Control

    Provide the Checks and Balances for the

    Project

    The Police

  • 8/7/2019 Cm Training

    33/166

    33

    The ProjectTeam

    Other Project Team MembersOther Project Team Members

    Design/Engineering Construction/Installation

    Commissioning/Closeout

    Operations

    Ancillary Bodies

  • 8/7/2019 Cm Training

    34/166

    34

    PROGRAM, PROJECT, CONSTRUCTION

    MANAGEMENTAND OVERSIGHT

    Session 2

  • 8/7/2019 Cm Training

    35/166

    35

    What is Project Management?

    Project Management for Design/

    Construction can be defined as:

    the process of professionalmanagement applied to the planning,

    design and construction of a project

    from inception to completion for the

    purpose of controlling time, scope,cost and quality.

  • 8/7/2019 Cm Training

    36/166

    36

    What is Project Management?

    The 4 core elements:

    ScopeManagement

    QualityManagement

    TimeManagement

    CostMana ement

  • 8/7/2019 Cm Training

    37/166

    37

    What Is Project Management ?

    CORE 1

    SCOPE MANAGEMENT:

    Defining objectives

    Determine activities necessary to achieve the

    objectives

    Monitor and control scope vs. objectives Quantify the resources

    Manage (inevitable) changes

  • 8/7/2019 Cm Training

    38/166

    38

    What Is Project Management ?

    CORE 2

    QUALITY MANAGEMENT:

    Establish the standards of qualityrequired to meet the investment

    objectives;

    Then manage the project to meet

    these standards using Quality

    Assurance and Quality Control.

  • 8/7/2019 Cm Training

    39/166

    39

    What is Project Management ?

    CORE 3

    TIME MANAGEMENT:

    Plan the activities

    Schedule the activities

    Monitor and control actual Resolve impacts to

    schedule/time

  • 8/7/2019 Cm Training

    40/166

    40

    What is Project Management ?

    CORE 4

    COST MANAGEMENT:

    Define investment

    Prepare estimates

    Establish budgets

    Control actual vs. budget

  • 8/7/2019 Cm Training

    41/166

    41

    What is Project Management ?

    Project Management requires special skills to

    achieve the four core elements

    Managing People

    Effective Communications

    Resource Management

    Risk Management

    Technical Knowledge

  • 8/7/2019 Cm Training

    42/166

    42

    What is Project Management ?

    Managing People - because people are at the center of theproject;

    Communications - providing leadership and direction;obtaining feedback and then adjusting actions to match actualevents;

    Resource Management- obtaining the necessary resourcesand commitments in the most efficient manner;

    Risk Management- avoiding or minimizing risks to projectsuccess by identifying quantifying the risk, allocating the riskto the project and managing it;

    TechnicalKnowledge - because you cant manage what youdont understand.

  • 8/7/2019 Cm Training

    43/166

    43

    What is Project Management ?

    What Brought About Project Management?

    The traditional separation of

    Owner, Designer,

    Contractor often caused conflicts because each

    has different objectives;

    Increased complexity of modern projects;

    Owners desires for faster completion - time

    equals money:

  • 8/7/2019 Cm Training

    44/166

    44

    What is Project Management ?

    What Brought About Project Management?

    (continued)

    Increased cost of resources Development of management

    skills, tools and systems that could

    be adapted to construction; Effective management found

    to increase productivity

  • 8/7/2019 Cm Training

    45/166

    45

    What is Project Management ?

    What are the Benefits of Project Management?

    Better planning of projects

    More productive use of resources

    Better control of risk

    Improved communications and teamwork

    MORE SUCCESSFUL PROJECTS!

    On Time - Within Budget - Right Quality

  • 8/7/2019 Cm Training

    46/166

  • 8/7/2019 Cm Training

    47/166

    47

    What is Project Management ?

    Why So Many Different Delivery Methods?

    Different Needs ofOwners

    Different Capabilities ofOwners

    Nature and Complexity of Project

    Amount ofTime for Project

  • 8/7/2019 Cm Training

    48/166

    48

    What is Project Management ?

    However, no matter what method you use,

    every construction project requires the following:

    Plan What You Want

    Design What You Plan

    Build the Design

    MANAGEMENTOF THE ENTIRE PROCESS

  • 8/7/2019 Cm Training

    49/166

    49

    Traditional Approach

    Planning DesignAdvertise

    &AwardConstruction

    Occupancy

    Start-up

    A rch itect/

    En g ineer

    S ubco ntr ac to r s

    Gener a l

    C o n tr ac to r

    O w ne r

  • 8/7/2019 Cm Training

    50/166

    50

    Traditional Approach

    Project Phases in sequence

    Contractor does not participate in design

    Complete design before construction

    Owner must manage entire process

    A/E and General Contractor independent

    Owner has maximum control

  • 8/7/2019 Cm Training

    51/166

    51

    Clerk ofWorks/ A/E Administration

    Planning DesignAdvertise

    &AwardConstruction

    Occupancy

    Start-up

    A rc h i t e c t -

    E n g i n e e r

    S u b c o n t r a c t o rV e n d o r s

    G e n e r a l

    C o n t r a c t o r

    O w n e r

  • 8/7/2019 Cm Training

    52/166

    52

    Clerk ofWorks/ A/E Administration

    Similar to traditional approach.

    Difference is expanded role ofA/E

    A/E performs basic administration,

    inspection during construction

    Owner manages all other aspects

  • 8/7/2019 Cm Training

    53/166

    53

    Design/Build

    Planning Design

    ConstructionOccupancy

    Start-up

    D e s ig n e r s S u b c o n t r a c t o r

    V e n d o r s

    D e s ig n - u i ld

    C o n t r a c t o r

    w n e r

  • 8/7/2019 Cm Training

    54/166

    54

    Design/Build

    Single firm responsible for design andconstruction

    Owner defines performance, D-B Contractordetermines design

    Owner has less control, less responsibility

    Design often controlled by construction, not

    independent Usually faster than traditional

    Allows construction expertise into design

  • 8/7/2019 Cm Training

    55/166

    55

    Project/Construction Management

    Planning DesignAdvertise

    &AwardConstruction

    Occupancy

    Start-up

    Planning Design

    Award Construction

    Award Construction

    Award Construction Occupancy

    Start-up

    OR

  • 8/7/2019 Cm Training

    56/166

    56

    Project/Construction Management

    ArchitectEngineer

    Trade

    Contractor

    Trade

    Contractor

    TradeContractor

    rojectConstruction

    Manager

    wner

    ArchitectEngineer

    Subcontractor

    GeneralContractor

    ConstructionManager

    OwnerOR

  • 8/7/2019 Cm Training

    57/166

    57

    Project/Construction Management

    CM is Owners agent and performs manyresponsibilities forOwner

    CM role is to manage design and/or construction

    All contracts with Owner

    Brings construction expertise to design

    Permits fast-track projects

    Allows multiple prime trade contractors, or onegeneral contractor with subcontractors.

  • 8/7/2019 Cm Training

    58/166

    58

    Program Management

    Project A

    Project B

    Project C

  • 8/7/2019 Cm Training

    59/166

    59

    Program Management

    Project "A " Project "

    " Project "C"

    Pro gr am

    M a n a ger

    A /E G .C C /M A /E G .C A / S G .C

    w ner

    Project "A" Projec t " "

    Project"C"

    A/E G.C C/M A.E G.C

    A.E G.C

    Program

    Manager

    wner

  • 8/7/2019 Cm Training

    60/166

    60

    Program Management

    Management of multipleprojects

    Single Management firm Provides consistent standards,

    controls and reporting on allprojects

    Effective management ofproject interfaces

  • 8/7/2019 Cm Training

    61/166

    61

    Project Management Oversight

    (PMO)

    Pr j

    t " "

    Pr j t " "Pr j t "A"

    PM

    sult t

    Ar it t

    E

    i

    r

    G r l

    tr

    t r

    Ar it t

    E

    i

    rs

    tr t rs/

    Subcontr ctors

    Proj ct/

    onstruction

    M nagers

    Designer Subcontractor

    Design- uil

    ontractor

    wner

  • 8/7/2019 Cm Training

    62/166

    62

    Project Management Oversight

    (PMO) PMO is independent consultant toOwner

    PMO focus is top management

    PMO surveys, evaluates, reports on all aspects:

    planning, design, construction

    No direct responsibility to manage project

    Can work with any other project delivery methods

    Good at identifying potential problems, facilitating

    resolutions Most effective for large projects

    Most often used by Top management or funding agenciesnot directly involved, e.g. Banks, Governments

  • 8/7/2019 Cm Training

    63/166

    63

    Comparison of Delivery MethodsTraditional Clerk of Works

    A/E

    Administration

    Design-

    Build

    Program Project/

    Construction

    Management

    Project

    Management

    Oversight

    Principal

    Advantages

    -Owner has

    greatest control

    -Designcomplete before

    construction-Most commonsystem, familiar

    to Owners, manycontract forms

    available-Can be cheaper

    because lessconsultants

    -Similar to

    traditional

    -A/E assistsOwner to

    manage, whichreduces Ownersresponsibility,

    staff

    -Fastest-

    allows fast-

    track-Owner deals

    with 1 entity-Lessresponsibility

    on Owner,less staff

    -Lessadversarial

    -Combinesconstructionexpertise intodesign

    -Applies

    management

    expertise to project-PM/CM is

    independent-focusis on projectssuccess

    -Bringsconstruction

    expertise to design-Allows fast-

    tracking and multi-contracting-Gives Owner awide, flexible

    range of services toselect-Less adversarial-Owner has lessresponsibility, less

    staff-Independent

    inspection and

    quality control

    Independent,

    experienced

    consultant to helpidentify, solve

    problems-Keeps topmanagement

    informed,involved

    -Inexpensive

    (1%)

    -Assists allparties to

    establish effectivecontrols,

    reporting

  • 8/7/2019 Cm Training

    64/166

    64

    Comparison of Delivery Methods

    Traditional Clerk of

    Works A.EAdministra

    tion

    Design-Build Program

    Project/Construction

    Mana ement

    Project

    ManagementOversight

    Principal

    Dis-

    advantages

    -Slowest-Moreresponsibility on

    Owner, requireslarger staff-Price not knowntill designcomplete-Most adversarial-competing

    interests-No constructioninput to design-Difficult forlarge, multi-contractor projects

    -Similar totraditional-Does not

    provide fullmana ement

    -A/Esinterestscan bebiased todesign

    -Less controlby Owner-Limited

    access todesign team-Design oftensubordinated toconstruction-Requirescareful

    planning byOwner-Not as manyfirms who cando D.B

    -Owner hasless control-Adds costs of

    PM/CM

    -May raisepotentialconflict with

    Owner staff-Not alwayscost effectiveon smallerprojects

  • 8/7/2019 Cm Training

    65/166

    65

    Planning for the

    Success of t

    he Project

    Session 3Session 3

  • 8/7/2019 Cm Training

    66/166

    66

    Planning is Essential

    for aS

    uccessful Project Planning defines and quantifies the

    measure of success

    Through planning, the project team defineshow it will organize to achieve this success

    Planning defines and develops the tools that

    are needed to manage to success Planning defines the risks and establishes

    the measures to avoid or manage the risks

  • 8/7/2019 Cm Training

    67/166

    67

    Why Do We Need to Plan?

    Studies and case histories have shown

    planning to be the single most important

    factor for successful projects Planning is done at the very start, when we

    have the most control

    Enables the project team to apply thebenefits of experience

    Anticipates problems and their solutions

  • 8/7/2019 Cm Training

    68/166

    68

    Types of Planning

    First step of planning is to identify the

    project mission:

    What is the project ?

    Who is the project for (the market) ?

    Why is the project being built ?

    (short and long term projection)

  • 8/7/2019 Cm Training

    69/166

    69

    Three Types of Planning

    Strategic planning

    Operational planning / construction masterplan

    Project scheduling

  • 8/7/2019 Cm Training

    70/166

    70

    Strategic Planning

    High level selection of the

    project objectives

    Target investment level Projected date of

    completion

    Desired marketpenetration

  • 8/7/2019 Cm Training

    71/166

    71

    Operational Planning/Construction

    Master Plan Analysis of available construction resources

    within the company

    The impact of the new projecton existing work load

    Identification of the

    required resources andwhere to be acquired

    O l Pl /C

  • 8/7/2019 Cm Training

    72/166

    72

    Operational Planning/Construction

    Master Plan (continued)

    Organize and control major work activities

    to meet project goals

    Project budget/estimate Resource plan (people, material, systems)

    Project schedule

    Procurement plan (subcontracting, etc.)

  • 8/7/2019 Cm Training

    73/166

    73

    Elements to Effective Planning

    of Construction Projects

    Hills experience has shown seven (7) elements to

    be necessary to construction project plans

    (1) Clear Definition of Project Goals and Objectives

    (2) Well Defined Project Organization

    (3) ComprehensiveWork Breakdown Structure (WBS)

    (4) AWritten Project Management Plan (PMP)

    (5) Development of the NecessaryT

    ools and Systems forManaging the Project

    (6) AMaster Schedule

    (7) An Effective Risk Management Program

  • 8/7/2019 Cm Training

    74/166

    74

    Project Goals & Objectives

    (1) Clear Definition of the Project Goals

    and Objectives

    Project Goals and Objectives include:The desired function or output

    The desired cost or investment

    The desired duration to complete

    The desired quality

  • 8/7/2019 Cm Training

    75/166

    75

    Project Goals & Objectives(continued)

    The Goals and objectives define the

    value(s) for the project The project values define the balance

    between cost, schedule, quality and

    function

  • 8/7/2019 Cm Training

    76/166

    76

    Project Organization

    (2) Well Defined Project Organization Organizing the Project team early permits pro-active management and

    establishes proper relationships of work and responsibilities.

    The project Organization should define the members of the project

    team and outside parties affecting the project, for example:

    ProjectTeam Outside Parties

    - Owner - Banks and Financing

    - Operator - Insurers

    - Designers - Surety/Bonding

    - Contractors - Government and Regulatory

    - Project Manager

    - Consultants

  • 8/7/2019 Cm Training

    77/166

    77

    Project Organization

    The Project Organization defines the roles

    and responsibilities of the project team:

    This includes: Scopes ofWork (SOW)

    Responsibility/approval authority

    Reporting and communication matrix Interfaces between the project team members

  • 8/7/2019 Cm Training

    78/166

    78

    Work Breakdown Structure

    (3) Comprehensive Work Breakdown

    Structure (WBS)

    Definition: A tree of activities which organizes,defines and graphically displays the total work to

    be accomplished in order to achieve the final

    objectives of a project. Each level of the WBS

    represents an increasing detailed definition of theproject activities. The WBS is a system for

    subdividing a project into manageable work

    packages.

  • 8/7/2019 Cm Training

    79/166

    79

    Work Breakdown Structure(continued)

    Purpose ofWBS:

    (1)Organizes the work into detailed packages

    (2)Assures that all necessary activities areidentified and organized

    (3)Shows relationships of work packages

    (4)Defines how the cost and schedule are to be

    developed and integrated

    (5)Assigns responsibility for all project work

  • 8/7/2019 Cm Training

    80/166

    80

    Work Breakdown Structure(continued)

    What

    Can a WBS

    Do For You

    Break the Scope

    of Work Down

    Into Know Tasks

    Provide Resource

    Planning Information

    for Manager

    Identify End Products

    and

    Deliverables

    Allow Development

    of Integrated

    Costs and Schedules

    Track Cost

    and

    Schedule

    Assign Responsibility

    for Work

    Performance

  • 8/7/2019 Cm Training

    81/166

    81

    Work Breakdown Structure(continued)

    Work Breakdown Structure Example

    AAB01

    Design

    AAB

    Houses

    AAA01

    Design

    AAA

    Apartments

    AA

    Housing Complex

    ABA

    Below Grade

    ABB

    Levels 1-20

    AB

    Office Complex

    AC

    Retail Complex

    Project ANew Center

  • 8/7/2019 Cm Training

    82/166

    82

    Project Management Plan

    (4) AWritten Project Management Plan

    (PMP)

    A written document designed to cover allproject activities through project

    completion.

    Written by the Project Management Team Updated throughout project as elements of

    the project change

  • 8/7/2019 Cm Training

    83/166

    83

    Project Management Plan (continued)

    Example: Table of Contents of one of Hills PMP Manuals:

    PART 1 Preliminary Design1 Introduction2 Summary

    3 Objectives, Goal and C onstraints4 Assumptions/Anticipated Conditions5 O rganisation and Staffing6 Preliminary D esign Program7 Permit Requirement8 Project Control

    9 AppendicesPART 2 FINAL DESIGN & CONSTRUCTION PHASE1 Assumptions/Anticipated Conditions2 Final Design & Construction Phase3 Scope of P rofessional Services4 Project Organisation & M anagement

  • 8/7/2019 Cm Training

    84/166

    84

    Tools & Systems

    (5) Development of the Necessary Tools and Systems forManaging the Project

    The Essential Tools for Managing the Project Cover:

    Scope

    Cost

    Quality

    Schedule

    Documentation/Communication

  • 8/7/2019 Cm Training

    85/166

    85

    Tools & Systems

    Scope (1) Design documents - drawings, specifications,conceptual, schematic, design development,

    construction documents

    (2) Contract Packaging

    (3) ChangeOrder Management

    (4) Configuration Management

    (5) As-built documentation - drawings, warranties,

    O&M Manuals

  • 8/7/2019 Cm Training

    86/166

    86

    Tools & Systems(continued)

    Cost 1) Target Investment2) Budgets

    3) Estimates4) Cost Control

    5) Accounting

    6) Commitments

    7) Changes

    8) Forecasting and Trending

  • 8/7/2019 Cm Training

    87/166

    87

    Tools & Systems (continued)

    Quality 1) Quality Standards2) Quality Assurance Program

    3) Regulatory Requirements e.g. CTMA

    4) Quality Control and Inspection

    5) Change Control6) Non-Conformance and Corrections

    7) Record-keeping

    Schedule 1) Planning2) Master Schedule

    3) Detailed Schedules4) Elemental Schedules - Design, Construction,

    Procurement, other

    5) Updating and Reporting

    6) Variation and Impact Evaluations

    7) RiskAnalysis

  • 8/7/2019 Cm Training

    88/166

    88

    Tools & Systems (continued)

    Communication/Documentation

    1) Document Management

    2) Logs and Reports e.g. - submittals, RFIs, ChangeOrders3) Management Information System

    4) Meetings

    5) Procedures Manual

    6) Approval and Reporting Matrices

  • 8/7/2019 Cm Training

    89/166

    89

    MasterSchedule

    (6) A Master Schedule

    Summary of all major activities to achieve project

    completion

    Defines overall time for project and the duration

    for each major activity

    Confirms the feasibility of the overall project

    duration Defines major milestones

    Identifies major interfaces with outside entities

  • 8/7/2019 Cm Training

    90/166

    90

    Risk Management Program

    (7) An Effective Risk Management Program

    Purpose of Risk Management Program:

    Identify and evaluate risks to project To plan how to handle and manage each risk

    To implement the plan and to monitor all potential

    risks

    Identification and Evaluation of Risks should cover: technical risks

    cost, financial & Schedule

    political, governmental and regulatory

  • 8/7/2019 Cm Training

    91/166

    91

    Risk Management Program(continued)

    Plan How to Handle and Manage Each Risk

    Techniques for risk management

    Avoid the riskby taking measures to eliminate the risk:

    e.g. pre-qualification of contractors Reduce the risk- by taking measure to continually re-evaluate the

    risk and developing fall back positions:

    e.g. contingency planning and allowances

    Retain the risk- accept the consequences if the risk occurs

    Transfer the risk- sharing or completely transferring the risk toanother party.

    e.g. specifying the risk in the construction contract and making the

    contractor responsible

    e.g. obtaining insurance to protect if the risk occurs

    e.g. performance bonds.

    Creating and Implementing

  • 8/7/2019 Cm Training

    92/166

    92

    g p g

    PM/CMTools

    Session 4

    Creating and Implementing

  • 8/7/2019 Cm Training

    93/166

    93

    g p g

    PM/CMTools

    Successful management is like magic, its easy

    if you have the tools. All you need are:

    Work Break Down Structure (WBS)

    Design/Scope Management

    Cost management

    Schedule

    Quality control

    Document control

    Field management control

    Creating and Implementing

  • 8/7/2019 Cm Training

    94/166

    94

    g p g

    PM/CMTools

    Work Break Down Structure (WBS)

    Task-oriented family tree which organizes,

    defines and graphically displays project Descending levels represent detailed

    definition of the objectives

    Relates elements of work to each other andend product

    Creating and Implementing

  • 8/7/2019 Cm Training

    95/166

    95

    g p g

    PM/CMTools

    WBS (continued)

    The WBS allows for the following:

    Estimates, costs, budget, schedule can beestablished from detail level (bottom-up)

    The total program can be described as a

    summation of subdivided elements/tasks Potential problems are detected at low level

    early enough to be pro-active

    Creating and Implementing

  • 8/7/2019 Cm Training

    96/166

    96

    g p g

    PM/CMTools

    Work Breakdo n tructure Exam le

    B102 ite

    ork

    B103 Concrete

    B104

    asonry

    B105 etals

    B106Wood&Plasitic

    B107 Thermal& ! oisture Protec

    B108 Doors&Windo"

    s

    B109 Finishes

    B110 # ecialities

    B111 Equi # ment

    B112 Furnishings

    B113 # ecial construction

    B114 Con$

    eying ystem

    B115 ! echanical

    B116 Electrical

    B102-16Construction Trates

    B1011 Conce # t Design

    B1012 Design De$

    elo# ment

    B1013

    chematic

    B1014 Construction Dra

    ings

    B101DE% I & N

    B1Villa 1

    AAB2Villa 2

    AABVillas

    AAAAppartmens

    AAHousing Complex

    ABABelo

    ' rade

    ABBLe

    $

    els 1-20

    ABOffice Complex

    AC hopping all

    Project ANe

    Center

    Creating and Implementing

  • 8/7/2019 Cm Training

    97/166

    97

    g p g

    PM/CMTools

    Design/Scope Management

    At each level of design a validation

    estimate needs to be conducted andif higher than budget re-design

    Value engineering to be part of

    design team during all design

    stages Design to be frozen prior to

    contractor award

    Creating and Implementing

  • 8/7/2019 Cm Training

    98/166

    98

    g p g

    PM/CMTools

    Design/Scope Management (continued)

    A common danger for cost overruns arises throughscope

    creepsand changes after the design has been frozen and

    released to the contractor. These changes need to betraceable and tightly controlled.

    Changes after design is frozen must be:

    Estimated separately

    Analyzed for schedule impact

    Approved by Management

    Negotiated and settled with contractor ASAP

    Creating and Implementing

  • 8/7/2019 Cm Training

    99/166

    99

    g p g

    PM/CMTools

    What is Cost Management?

    Cost management is a function which

    includes the processes that are requiredto maintain effective financial control

    of projects:

    Estimating, Budgeting and Cost control

    Scheduling, Evaluating and Monitoring Analyzing and Adjusting

    Reporting

    Creating and Implementing

  • 8/7/2019 Cm Training

    100/166

    100

    g p g

    PM/CMTools

    Estimating

    Methods of estimating:

    Detailed bottom-up estimateConceptual judgmental estimate

    Parametric historical cost parameters

    Firm Quotes from potential vendors

    Creating and Implementing

  • 8/7/2019 Cm Training

    101/166

    101

    g p g

    PM/CMTools

    Estimating (continued)

    The estimating effort should be continuous

    on the project. Recommended levels are: Conceptual estimate

    Schematic Estimate

    Design Development estimate

    Construction drawing estimate

    Field Changes and Change Order Estimates

    Creating and Implementing

  • 8/7/2019 Cm Training

    102/166

    102

    PM/CMTools

    Estimating (continued)

    A contingency provision is to be included in

    the various estimates, due to the percentageof accuracy available at each level of design

    Concept/Feasibility 25%-40%

    Obtain project Funding 15%-25% Capital cost/budget 10%-15%

    Definitive/In field 7%-5%

    Creating and Implementing

  • 8/7/2019 Cm Training

    103/166

    103

    PM/CMTools

    Estimating (continued)

    By establishing a contingency the project

    team has the ability to manage problemsand changes without alarming higher

    management.

    Contingency usage monitoring is a goodindication on the performance of the project

    team by Management.

    Creating and Implementing

  • 8/7/2019 Cm Training

    104/166

    104

    PM/CMTools

    Budgeting

    The project budget sets a realistic projection for

    material, labor, subcontractor and indirect costs on thetotal project.

    A poor estimate/budget leads to an unrealistic budget

    causing cost overruns and loss of control.

    The project budget is the baseline for cost control

    Creating and Implementing

  • 8/7/2019 Cm Training

    105/166

    105

    PM/CMTools

    Budgeting (continued)

    At the capital stage the budget has to be

    frozen and serves as baseline with costs andfuture commitments.

    Budget breakdown in accordance with the

    WBS

    Contingency usage is tracked and managed

    Creating and Implementing

  • 8/7/2019 Cm Training

    106/166

    106

    PM/CMTools

    Schedule

    In construction projects there are usually two

    schedules: Owners schedule - macro schedule stressing the

    strategic planning goals including design

    Contractors schedule - fully detailed operational

    schedule covering all the construction work

    activities within the owners end date

    Creating and Implementing

  • 8/7/2019 Cm Training

    107/166

    107

    PM/CMTools

    Schedule (continued)

    Two scheduling methods

    Bar Charts

    Logic-diagram-based schedules

    Both have advantages and disadvantages

    and are sometimes interchangeable

    Creating and Implementing

    /C l

  • 8/7/2019 Cm Training

    108/166

    108

    PM/CMTools

    Schedule (continued)

    Bar charts

    Advantages:

    Inexpensive and simple to prepare

    Easy to read and update

    Disadvantages: Inability to show enough detail to cover all Activities onlarge projects

    Do not show the interrelation of activities

    Creating and Implementing

  • 8/7/2019 Cm Training

    109/166

    109

    PM/CMTools

    Schedule (continued)

    Logic-diagram-based schedules

    AdvantagesReveals interdependence of activities

    Calculates project completion dates

    Enables what if analysesHighlights critical activities

    Evaluates performance

    Creating and Implementing

  • 8/7/2019 Cm Training

    110/166

    110

    PM/CMTools

    Schedule (continued)

    The logic diagramed basedschedule is the right tool as the

    project schedule

    Provides the ability to organize

    schedule at the lowest level ofWBS

    Creating and Implementing

  • 8/7/2019 Cm Training

    111/166

    111

    PM/CMTools

    Schedule (continued)

    Contractor schedule can be used to

    electronically update the Owners schedulebased on approved completion for each

    period

    The ability to cost load the schedule andproduce earned value analysis

    Allows management of project float

    Creating and Implementing

  • 8/7/2019 Cm Training

    112/166

    112

    PM/CMTools

    Quality Control

    Conformance to requirements

    Doing it right the first time

    Fitness for the purpose

    Creating and Implementing

  • 8/7/2019 Cm Training

    113/166

    113

    PM/CMTools

    Quality Control Plan includes

    Quality assurance

    Quality Control

    Quality Management

    Creating and Implementing

  • 8/7/2019 Cm Training

    114/166

    114

    PM/CMTools

    Quality Control Plan - Quality Assurance

    QA procedures

    Quality Systems Verification

    Identify& analyze issue

    Audits/observation

    Rework reporting

    Corrective action

    Training

    Creating and Implementing

  • 8/7/2019 Cm Training

    115/166

    115

    PM/CMTools

    Quality Control Plan - Quality Control

    Tests/inspection plan

    Design/technical reviews

    Fabrication & installation inspection

    Material control and inspection

    Calibration control

    Contractor & subcontractor control

    Creating and Implementing

  • 8/7/2019 Cm Training

    116/166

    116

    PM/CMTools

    Quality Control Plan - Quality Management

    Quality based client relations

    Quality skills training Project execution strategy

    Work process improvement

    Obstacle identification & removal

    Project information feedback

    Creating and Implementing

  • 8/7/2019 Cm Training

    117/166

    117

    PM/CMTools

    Document Control

    Integrated system based on the WBS for all

    documents of the project. Organized filling facilitates team to work

    Engineering drawing tracking

    Correspondence tracking One stop shop for historical data

    Creating and Implementing

  • 8/7/2019 Cm Training

    118/166

    118

    PM/CMTools

    Field Management Control

    All field changes initiated by owner must be

    approved in writing by the PM/CM; noverbal authorization

    Contractor field change request must be

    approved by PM/CM prior to initiation To avoid disputes all field changes should

    be negotiated bi-monthly

    Creating and Implementing

    / l

  • 8/7/2019 Cm Training

    119/166

    119

    PM/CMTools

    OPEN DOOR POLICY

    Communication failure can

    neutralize all tools, no matter

    how well they are established

    Common reasons are:

    negative mode, not accepting

    other peoples ideas, impatient,assuming others have the same

    information, reacting without

    analyzing the facts

  • 8/7/2019 Cm Training

    120/166

    120

    Th

    e Project Manager

    Session 5

    Th P j M

  • 8/7/2019 Cm Training

    121/166

    121

    The Project Manager

    What Makes a Successful Project Manager?

    Must cross organizational boundaries

    Must develop the Project Team into a cohesivegroup

    Combination of technical, administrative and

    people skills

    Must create environment which motivatespeople to deliver a quality project

    Th P j M

  • 8/7/2019 Cm Training

    122/166

    122

    The Project Manager

    Project Managers Directive:

    Accomplish what cannot be done;

    Predict the Unknown;Develop a Plan to Address it;

    Implement the Plan

    With People who do not report to you

    And with resources which you cant control

    In an unreasonable time frame

    And for an unreasonable budget

    Th P j t M

  • 8/7/2019 Cm Training

    123/166

    123

    The Project Manager

    Functional/Matrix Organization Balance of Power

    Project

    Organization

    Functional

    Organization

    Project Manager Influence

    Functional Manager Influence

    Balance of

    Power/

    Influence

    in Decision

    Making

    Strong Matrix Weak Matrix

    Th P j t M

  • 8/7/2019 Cm Training

    124/166

    124

    The Project Manager

    Skills of the Ideal Project Manager (1)

    Team-Building

    Empathy

    Motivation

    Leadership

    Sets Examples

    Energetic Big Picture Vision

    Delegates

    Ethics/Morals

    Th P j t M

  • 8/7/2019 Cm Training

    125/166

    125

    The Project Manager

    Skills of the Ideal Project Manager (2)

    Communication

    Listening

    Understanding

    Persuasion

    Planning/Organizing

    Flexibility Common Sense

    Positive Approach

    Goal-Setting

    Th P j t M

  • 8/7/2019 Cm Training

    126/166

    126

    The Project Manager

    Skills of the Ideal Project Manager (3)

    Problem Solving Skills

    Analyzing and Problem Solving

    Negotiating

    Conflict Management

    Removing Obstacles

    Creativity

    T

    echnical Skills Expertise/Experience/Credibility

    Current Knowledge

    Technical Problem Solving

    Th P j t M

  • 8/7/2019 Cm Training

    127/166

    127

    The Project Manager

    Skills of the Ideal Project Manager (4)

    Coping Skills

    Persistence

    Patience

    Crisis Handling

    Stress Management

    Estimation/SchedulingAdministration

    Computer Skills

    Th P j t M

  • 8/7/2019 Cm Training

    128/166

    128

    The Project Manager

    Responsibilities of the Project Manager (1)Organize, coordinate and direct the Project

    Resolve Conflicts between team members

    Lead the Project Team in developing the PMP, the

    Quality Assurance Guidelines, Design Standards and

    Requirements, etc.

    Communicate project goals and objectives to the

    Project Team

    Ensure requirements ofOwner are met

    Th P j t M

  • 8/7/2019 Cm Training

    129/166

    129

    The Project Manager

    Responsibilities of the Project Manager (2)

    Lead the Project in:

    Acquiring Resources

    Selecting Team Members

    Developing user requirements

    Defining Scope and Quality

    Defining Budgets

    Determining Schedules

    Maintain control to assure the project is completed in

    accordance with the requirements set forth

    The Project Manager

  • 8/7/2019 Cm Training

    130/166

    130

    The Project Manager

    Responsibilities of the Project Manager (3)

    Report project status on a regular basis

    Ensure the completeness and adequacy of project

    records and documentation Ensure that appropriate QA/QC procedures are set

    in place and applied

    Specify testing requirements and ensure

    appropriate tests are carried out so that the projectmeets design requirements

    Maintain successful ongoing operations and

    maintenance

    The Project Manager

  • 8/7/2019 Cm Training

    131/166

    131

    The Project Manager

    Must be an Effective

    Communicator Most of the working hours of a

    Project Manager will be spent in

    some type of communicatoractivity

    Conferences, meetings, writing,

    memoranda, issuing and reading

    reports, communicating with team

    members, communicating withmanagement, talking to

    customers/clients, talking with

    contractors, subcontractors, and

    suppliers

    R i i A T bl d P j t

  • 8/7/2019 Cm Training

    132/166

    132

    Reviving A Troubled Project

    Session 6

    R i i T bl d P j t

  • 8/7/2019 Cm Training

    133/166

    133

    Reviving a Troubled Project

    I. WARNING SIGNS

    II. FINDING THE REASONS

    III. DETERMINING ALTERNATIVES

    IV. IMPLEMENTING THE REVIVAL PLAN

    V. REACTION AND FEEDBACK

    Ad d l d

  • 8/7/2019 Cm Training

    134/166

    134

    AdvancedTools and

    Techniques in ConstructionManagement

  • 8/7/2019 Cm Training

    135/166

    135

    Value Engineering

    Value Engineering

  • 8/7/2019 Cm Training

    136/166

    136

    Value Engineering

    Studies have shown $4.40 of

    savings for every $1.00 spent onValue Engineering

    Value Engineering can achieve 10-

    20% cost savings while

    maintaining value objectives

    VE Potential Cost Savings

    Value Engineering

  • 8/7/2019 Cm Training

    137/166

    137

    Value Engineering

    Resultant VE Cost Savings over Project Life

    Potential

    for

    Savings

    from

    Value

    Engineering

    Time

    Schematic

    Design

    Design

    Development

    ContractDocuments

    Construction

  • 8/7/2019 Cm Training

    138/166

    138

    Partnering

    Partnering

  • 8/7/2019 Cm Training

    139/166

    139

    Partnering

    New term based on old concept

    Established 1988 by Army Corps of Engineers

    Each of the contractual parties respects the rightsand responsibilities of the other(s)

    Recognizes that every contract has an implied

    good faith covenant

    Does not change the terms of the signed contract

    Partnering

  • 8/7/2019 Cm Training

    140/166

    140

    Partnering

    Army Corps of Engineers Definition

    ...the creation of a relationship between Owner and Contractor

    that promotes achievement of mutual and beneficial goals.

    Construction Industry Institute Definition ...a long term commitment between two or more organizations for

    the purpose of achieving specific business objectives by

    maximizing the effectiveness of each participants resources. The

    relationship is based upon trust, dedication to common goals and

    understanding each others individual expectations and values.

    Expected benefits include improved efficiencies and cost

    effectiveness, increased opportunity for innovation and continuous

    improvement of quality products and services.

    Eliminate Us vs.. Them attitude.

    Partnering

  • 8/7/2019 Cm Training

    141/166

    141

    Partnering

    Keys to Success

    Concept

    Begin early in process

    Establish mutual recognizance

    Select Independent facilitator

    Commitment from Corporate Management Continuously evaluate

    Properly allocate risk

    Partnering Workshop

  • 8/7/2019 Cm Training

    142/166

    142

    PartneringWorkshop

    Partnering Workshop

    Signed Charter to Guide the Partnership

    Written Mission Statement and Objectives Specific Program to Measure Objectives

    Action Plan for Key Problems

    Establish Dispute Resolution Process

    Address Individual Roles and Concerns

    Team Evaluation Process with Facilitator

    Partnering

  • 8/7/2019 Cm Training

    143/166

    143

    Partnering

    Goals of Partnering

    On Time Completion

    Completion within

    Owner and Contractor budgets

    Deliver required quality or better

    Establish realistic, achievable schedule

    Reduce paperwork

    Avoid litigation or arbitration

    Eliminate lost/unproductive time

    Eliminate accidents

    Partnering

  • 8/7/2019 Cm Training

    144/166

    144

    Partnering

    Benefits of Partnering

    Owner

    Reduced Exposure to Litigation

    Better Quality

    Lower Risk of Cost Overruns and Delays

    Contractor

    Reduced Exposure to Litigation

    Increased Productivity

    Lower Risk of Cost Overruns and Delays

    Partnering

  • 8/7/2019 Cm Training

    145/166

    145

    Partnering

    Essential Elements of Partnering

    Recapitulation

    Commitment Equity

    Trust

    Communication

    FOR EXAMPLE

  • 8/7/2019 Cm Training

    146/166

    CLARKLEISURE HILLS

    RESIDENCE & RESORT COMPLEX

    DEVELOPMENT PLAN

    Our Approach & Process

    Things to Know

    The Key Factor

    Management StructureThe Palm Jebel Ali / The Palm Jumeriah/ The world Islands

    Hil l is managing design and construction of Palm Islands, two man-made,palm-shaped islands in Dubai, UAE. The first is land, Palm Jumeirah, willinclude 2,400 homes, 30 hotels, aquatic themed entertainment and touristattractions. The larger island, Palm Jebel Ali, will include 3,200 homes, 40hetels and commercial as well as retail properties.

    HILL

    Hill International

    The Project Team

  • 8/7/2019 Cm Training

    147/166

    - -

    -

    - Masterplan - /// - - VE -

    - Proposal E aluation- Technical E aluation- Cost E aluation- -

    -

    -

    -

    -

    The Conductor ofthe Project Orchestra

    Facilitator, Liaison,Go-Between

    Responsibility = < Authority

    RightCombination ofTechnicalandInterpersonal Skills

    The ProjectTeam

    -

    The Project

  • 8/7/2019 Cm Training

    148/166

    Hill International + Hill Korea

    Hill International + Hill Korea CM

    (,,,, )

    - ,, ,

    (Value Engineering),

    ,,,,

    , ,

    ,

    ,, (O&M)

    The Project

    -

    AdvancedTools andTechniquesin Construction Management

  • 8/7/2019 Cm Training

    149/166

    in Construction Management

    - (I)

    ( /) ( /)

    (QPMS) (QPMS)

    VE VE

    O&M (Operation & Maintenance)O&M (Operation & Maintenance)

    AdvancedTools andTechniquesin Construction Management

  • 8/7/2019 Cm Training

    150/166

    -

    - - - / - / - / - -

    - - Nego

    - - - - - - - -

    - - - -

    - / / - Quality Control

    in Construction Management

    - (II)

    AdvancedTools andTechniquesin Construction Management

  • 8/7/2019 Cm Training

    151/166

    1) 2)

    1)

    1) Master Schedule 2)

    1)

    2)

    3) VE ()4)

    1) P.Q 2) Nego3)

    1) 2) 3)

    1) 2) 3)

    1) 2) 3) 4)

    1) 2)

    3) (O&M Manual )

    in Construction Management

    -

    Design/ Build

  • 8/7/2019 Cm Training

    152/166

    Design/ Build

    70%

    100%

    .

    (20/80 : 20% 80% )

    / /

    , , ,

    , , ,

    (, , )

    ,

    ,

    Life Cycle Cost, Facility Management System

    Creating andImplementing

    PM/CM Tools

  • 8/7/2019 Cm Training

    153/166

    PM/CMTools

    : ,

    (/ / / )

    (/ ISO/ / )

    PQ ()

    /

    (/, / )

    , , , , /

    Creating andImplementing

    PM/CM Tools

  • 8/7/2019 Cm Training

    154/166

    / /

    /

    (/ / / etc)

    /

    Procurement

    / / / / /

    /

    (/ / / / / )

    PM/CMTools

    Creating andImplementing

    PM/CM Tools

  • 8/7/2019 Cm Training

    155/166

    Master Schedule Mile Stone

    / Long Lead Item

    /

    EVMS SYSTEM

    (/ :

    Earned Value Management System)

    4 / /

    Point

    ,

    ,

    Fast Track

    Fast Track

    Long-Lead Item

    Fast Track

    Schedule Two scheduling methods

    Bar Charts Logic-diagram-based schedules

    Both have advantages and

    Disadvantages and are sometimesinterchangeable

    PM/CMTools

    Creating andImplementing

    PM/CM Tools

  • 8/7/2019 Cm Training

    156/166

    /

    AS-Built ,

    , Sample, Spare Part List, O&M Manual

    (, ,

    ,

    , )

    System

    A/S SYSTEM

    SYS

    Feed-Back System

    A/S SYSTEM

    Zone

    / Data

    / System

    System (Operation & Maintenance SYS)

    FMS (Facility Management System)

    , ,

    , , / , , ,

    , (Total Cost) /

    LCC (Life Cycle Cost: )

    PM/CMTools

    Creating andImplementing

    PM/CM Tools

  • 8/7/2019 Cm Training

    157/166

    PM/CMTools

    Successful management is like magic,Its easy if you have the tools.

    All you need are

    PM & CM

    Design/Scope Management

    Cost management

    Schedule

    Quality control

    Document control

    Field management control

    Creating andImplement PM/CMTools

  • 8/7/2019 Cm Training

    158/166

    OPEN DOOR POLICY Communication failure can

    neutralize all tools, nomatter how well they areestablished

    Common reasons are:

    negative mode, not

    accepting other peoplesideas, impatient, assumingothers have the sameinformation, reactingwithout analyzing the facts

    PM/ CM PM/ CM

    [Professional Ethic]

    (Engineering Ethic)

    ()

    (Workmanship]

    ////

  • 8/7/2019 Cm Training

    159/166

    THE KEY FACTOR

  • 8/7/2019 Cm Training

    160/166

    THE TECHNICAL BIG FIVE

    1. Risk Management

    2. Project Procedures

    3. Project Control ystems

    4. uality Management

    5.HSE Management

  • 8/7/2019 Cm Training

    161/166

    THE COMMERCIAL BIG TWO

    Often undertaken in cooperation and coordination ith the Cost

    Consultant and the Employers Representati e are the follo ing

    T o further PROGRAMMANAGEMENT elements:

    6. Contract Packaging, Drafting and Management

    7. Claims Avoidance orManagement

  • 8/7/2019 Cm Training

    162/166

  • 8/7/2019 Cm Training

    163/166

    Profile of Project Director

  • 8/7/2019 Cm Training

    164/166

    Name : Mr.Albert Cabellon (Nationality: USA)

    Current position: Project manager,Hill International,Philippines

    Education: California Polytechnic State University,San Luis Obispo (B.Sc. InArchitecture)

    Career Highlight: 30 years in Project Management, Ne to n,High-rise Mixed-useDevelopment,Hospitality,Shopping Centers

    Projects:

    - UAE: 60story x 9buildings Mixed-use Development (Hotel, Residental,Office to ers)(US$2.5 billion)/ PM

    - USA: 700 unit Condominium To ers, t o 40 story to er(US$300Million)/

    PMInternational Cruise Terminal,San Francisco / PMT o 5-star Hotel and Golf Resorts,717Acres (US$120Million)/5 PMMega scale Po er Center(Shopping Malls)/Ne To n Development /

  • 8/7/2019 Cm Training

    165/166

    165

  • 8/7/2019 Cm Training

    166/166