    Code of Construction PracticePart B: Site Specific RequirementsVictoria Embankment Foreshore - Revised 3 February 2014

    Doc Ref: APP104.16

    Folder1803 February 2014

    Thames Tideway TunnelThames Water Utilities Limited

    Application for Development ConsentApplication Reference Number: WWO10001

  • 8/13/2019 Code of Construction Practice Part B: Site Specic Requirements Victoria Embankment Foreshore - Revised 3 February 2014

    2/12

    DCO-DT-000-ZZZZZ-071902 I February 2014

    Code of Construction Practice

    Part B: Site-specificrequirements

    Victoria Embankment Foreshore

  • 8/13/2019 Code of Construction Practice Part B: Site Specic Requirements Victoria Embankment Foreshore - Revised 3 February 2014

    3/12

    Code of Construction Practice Part B

    This page intentionally left blank

  • 8/13/2019 Code of Construction Practice Part B: Site Specic Requirements Victoria Embankment Foreshore - Revised 3 February 2014

    4/12

    Code of Construction Practice Part B i

    Thames Tideway Tunnel

    Code of Construction Practice Part B

    Victoria Embankment Foreshore

    List of contents

    Page number

    1 Introduction ...................................................................................................... 12 General requirements ...................................................................................... 23 Communications and community/stakeholder liaison ................................. 24 Site operation ................................................................................................... 25 Public access, highway and river transport .................................................. 36 Noise and vibration .......................................................................................... 47 Air quality.......................................................................................................... 58 Water resources ............................................................................................... 59 Land quality ...................................................................................................... 510 Waste management and resource use ........................................................... 511 Ecology (aquatic and terrestrial) .................................................................... 612 Historic environment ....................................................................................... 613 Other ................................................................................................................. 6

    List of figures

    Page number

    Figure 1.1 Victoria Embankment Foreshore: Site context and location plan............... 2

  • 8/13/2019 Code of Construction Practice Part B: Site Specic Requirements Victoria Embankment Foreshore - Revised 3 February 2014

    5/12

    Code of Construction Practice Part B ii

    This page intentionally left blank

  • 8/13/2019 Code of Construction Practice Part B: Site Specic Requirements Victoria Embankment Foreshore - Revised 3 February 2014

    6/12

    Victoria Embankment Foreshore

    Code of Construction Practice Part B 1

    1 Introduction

    1.1.1 All works described in this document are to be managed and performed tomeet the health and safety vision of Zero Incidents, Zero Harm, Zero

    Compromisefor the Thames Tideway Tunnel project (the project).

    1.1.2 The Code of Construction Practice(CoCP) comprises two parts:

    a. Part A: General requirements. These measures are applicableproject wide.

    b. Part B: Site-specific requirements. These are site-specific measureswhere deviations from the general requirements are indicated inPart A.

    1.1.3 This document forms the CoCPPart B for the project works at the VictoriaEmbankment Foreshore site and sets out detailed site-specific measures

    including working hours, site set-up and servicing arrangements, takinginto account environmental matters and consultations with WestminsterCity Council and other stakeholders.

    1.1.4 For ease of reference, this document sets out site-specific issues anddeviations from Part A; therefore where no site-specific measures arespecified, reference should be made to Part A.

    1.1.5 A plan showing the location of the site is shown inFigure 1.1 overleaf.

  • 8/13/2019 Code of Construction Practice Part B: Site Specic Requirements Victoria Embankment Foreshore - Revised 3 February 2014

    7/12

    Victoria Embankment Foreshore

    Code of Construction Practice Part B 2

    Figure 1.1 Victoria Embankment Foreshore: Site context and location plan

    Note: For detailed limits of land to be acquired or used, refer to the drawings in the Book of Plans.

    2 General requirements2.1.1 As per the CoCPPart A.

    3 Communications and community/stakeholderliaison

    3.1.1 As per the CoCPPart A.

    4 Site operation

    Topic Site-specific requirement

    Working hours The following working hours shall apply to this site:

    a. standard

    b. continuous during construction of the RegentStreet connection tunnel.

    When other types of working hours (CoCPPart A,

    Table 4.1) are required, these will be subject to

    consent from the local authority under Section 61 ofthe Control of Pollution Act 1974.

  • 8/13/2019 Code of Construction Practice Part B: Site Specic Requirements Victoria Embankment Foreshore - Revised 3 February 2014

    8/12

    Victoria Embankment Foreshore

    Code of Construction Practice Part B 3

    Topic Site-specific requirement

    Site layout Temporary in-river construction works shall belimited within the authorised navigation channel.The detailed proposals shall be agreed with the Port

    of London Authority and the Environment Agency(relevant protective provisions) and the MarineManagement Organisation (Deemed Marine Licenceconditions) and subject to any additional requiredlicenses, navigational risk assessments andconsents.

    Site security/hoardingrequirements

    The hoarding shall incorporate suitable art work andviewing windows, as defined in CoCPPart A para.4.3.4a and b.

    The hoarding on the western boundary shall be3.6m.

    The local authority shall approve the externalappearance of the hoarding.

    River works As per the CoCPPart A.

    Other items The contractor shall produce a site-specific lightingmanagement plan. The lighting scheme shallminimise impacts on terrestrial and aquatic ecologyand include the use of low level directional lighting,where possible, while providing safe workingconditions.

    5 Public access, highway and river transport

    Topic Site-specific requirement

    Site access and gates Entry to the site will be from Victoria Embankmentwith left turn into the site. Exit will be left turn outtravelling south.

    Traffic management Site areas shall be designed to maintain two-waytraffic flow along Victoria Embankment.

    Two lanes shall be maintained on bothcarriageways, except for short periods during utilitydiversions where only one lane on the westboundcarriageway shall remain open.

    Prior to suspending any coach parking spaces,alternative spaces shall be provided. The spacesshall be reinstated on completion of the works unlessagreed with the highway authority. It is proposedthat, subject to obtaining the relevant highwayconsents, the coach parking spaces would be

    relocated to Albert Embankment (A3036) betweenTinworth Street and Black Prince Road, Millbank

  • 8/13/2019 Code of Construction Practice Part B: Site Specic Requirements Victoria Embankment Foreshore - Revised 3 February 2014

    9/12

    Victoria Embankment Foreshore

    Code of Construction Practice Part B 4

    Topic Site-specific requirement

    (A3212) between Thorney Street and AtterburyStreet, or Lambeth Palace Road (A3036) to the northof Lambeth Road (A3203)/Lambeth Bridge(A3203)/Albert Embankment (A3036)/LambethPalace Road (A3036) roundabout.

    The minimum width of the retained traffic lanes alongVictoria Embankment shall be 3m in each directionfor one outer lane and 3.25m for a second inner lane(where applicable). A suitable safety barrier shall beinstalled between opposing direction lanes.

    The extent and duration of working areas extendinginto traffic lanes shall be minimised. Traffic barriersshall be moved as construction progresses asTransport for London requires minimum land-take

    within the highway.

    Event restrictions Event restrictions are to be confirmed in consultationwith the local authority and Transport for London.

    The contractor shall liaise with the City of LondonCorporation, Westminster City Council and Transportfor London event planning teams with regard to theLondon Marathon and other major events whenproducing the traffic management plan and trafficmanagement schemes to ensure that appropriatemeasures are in place.

    River transport Access to the existing Embankment Pier shall bemaintained for both pedestrians and vessel services.The contractor shall liaise with London RiverServices (Transport for London).

    Other Clear signage shall be provided for the diversion ofthe Thames Path.

    6 Noise and vibration

    Topic Site-specific requirement

    Control measures

    The noise and vibrationcontrol measures shall bedetailed (and may be modifiedor added to) in Section 61consent applications to thelocal authority.

    A 2.4m noise barrier shall be installed on thenorthern and southern boundaries of the temporarycofferdam to screen receptors on the tidal Thames.

    Barges shall only be loaded and unloaded duringstandard working hours.

    Except for the anchor piles, the contractor shallconstruct the cofferdam using push piling unless thisis determined to be impossible. The first 'anchor'piles shall be installed at a location as far away fromthe closest sensitive receptors, including the

  • 8/13/2019 Code of Construction Practice Part B: Site Specic Requirements Victoria Embankment Foreshore - Revised 3 February 2014

    10/12

    Victoria Embankment Foreshore

    Code of Construction Practice Part B 5

    Topic Site-specific requirement

    Hispaniola and the Tattershall Castle as possible.

    Where push piling is determined to be impossible,this shall be demonstrated by the contractor, who

    shall make an application to the local authority for analternative piling method through the Section 61dispensation process (see Appendix A, Section A.1in the CoCPPart A) or through contingencymeasures and arrangements if included in theoriginal Section 61 consent.

    Other N/A

    7 Air quality

    Topic Site-specific requirement

    Vehicle and plant emissions As per the CoCPPart A.

    Dust emissions/control As per the CoCPPart A.

    Odour As per the CoCPPart A.

    Other N/A

    8 Water resources

    Topic Site-specific requirement

    Control of pollution: surfacewater/groundwater

    As per the CoCPPart A.

    Control on abstraction As per the CoCPPart A.

    Ground treatment As per the CoCPPart A.

    Other N/A

    9 Land quality

    Topic Site-specific requirement

    Site works As per the CoCPPart A.

    Site-specific issues/mitigation As per the CoCPPart A.

    10 Waste management and resource use

    Topic Site-specific requirementExcavated material As per the CoCPPart A.

  • 8/13/2019 Code of Construction Practice Part B: Site Specic Requirements Victoria Embankment Foreshore - Revised 3 February 2014

    11/12

    Victoria Embankment Foreshore

    Code of Construction Practice Part B 6

    Topic Site-specific requirement

    Resource usage As per the CoCPPart A.

    Other N/A

    11 Ecology (aquatic and terrestrial)

    Topic Site-specific requirement

    Protection of habitats A membrane shall be installed between the riverbedand any temporary back fill material to preventcontamination of habitat and preserve potentialarchaeology.

    Areas of foreshore used for temporary works shallbe restored to a similar condition with similar

    materials as prior to the works.

    Protection of trees The specifications for replacement trees shall beagreed with Transport for London including species,size, source, pit design and finish.

    Other N/A

    12 Historic environment

    Topic Site-specific requirementOther Intrusive structural investigations shall be carried out

    on the listed river wall beyond the area of proposedfabric removal.

    Existing granite blocks shall be used to join the newand old sections of the river wall.

    The sturgeon lamp stands shall be removed; thecontractor shall seek to reuse them in accordancewith the procedures set out in the HeritageStatement.

    13 Other

    Topic Site-specific requirement

    Other As per the CoCPPart A.

  • 8/13/2019 Code of Construction Practice Part B: Site Specic Requirements Victoria Embankment Foreshore - Revised 3 February 2014

    12/12

    Copyright notice

    All rights reserved.

    Any plans, drawings, designs and materials (materials) submitted

    by Thames Water Utilities Limited (Thames Water) as part of this

    application for Development Consent to the Planning Inspectorate

    are protected by copyright. You may only use this material(including making copies of it) in order to (a) inspect those plans,

    drawings, designs and materials at a more convenient time or

    place; or (b) to facilitate the exercise of a right to participate in the

    pre-examination or examination stages of the application which

    is available under the Planning Act 2008 and related regulations.

    Use for any other purpose is prohibited and further copies must

    not be made without the prior written consent of Thames Water.

    Thames Water Utilities Limited

    Clearwater Court, Vastern Road, Reading RG1 8DB

    The Thames Water logo and Thames Tideway Tunnel logo

    are Thames Water Utilities Limited. All rights reserved.

    Copyright Thames Water Utilities Limited February 2014.