Constructability ReviewContract Documents

Construction

Robert Z. Fisher, PESr. Construction Manager, Parsons

Event Date

Page 2: Constructability Review Contract Documents Construction Robert Z. Fisher, PE Sr. Construction Manager, Parsons Event Date

Constructability ReviewPurpose: Improve the total quality of construction

bid package. Leverage the experience and knowledge

of construction professionals gained through:

Fixing problems caused by the unknown Fixing problems caused by mistakes

What is the Goal??? Prevent Problems

or Fix Problems

Resource: Constructability Guide Book

Page 3: Constructability Review Contract Documents Construction Robert Z. Fisher, PE Sr. Construction Manager, Parsons Event Date

Constructability Reviews Constructability Review Team

(CRT) Budgeted for and Assembled by PM The project complexity will determine

makeup of team. Could be 1 person. Could be 5.

Levels of review for project types are outlined in the Guidebook.

Construction Resources: District Construction Engineer Area Engineer Project Engineer/Supervisor Consultant Construction Professionals

Page 4: Constructability Review Contract Documents Construction Robert Z. Fisher, PE Sr. Construction Manager, Parsons Event Date

Constructability Review As the Utility Coordinators

Always coordinate with PM Initial CRT Engagement

Utility Coordination Checklist Item 2.03 Perfect Opportunity for Utility

Coordinator to collaborate with Construction

Expands understanding/goals of project

Establishes good lines of communication

Other Benefits?

Page 5: Constructability Review Contract Documents Construction Robert Z. Fisher, PE Sr. Construction Manager, Parsons Event Date

Constructability Review Initial Field Visit

Investigate Field Conditions

Good overview of site

ID Challenge Areas ID Parcels that

might pose challenges

Any information is good information at this stage.

Page 6: Constructability Review Contract Documents Construction Robert Z. Fisher, PE Sr. Construction Manager, Parsons Event Date

Constructability Review

Initial Field Visit with Construction ID the less

obvious clues trenches depressions valve boxes

Page 7: Constructability Review Contract Documents Construction Robert Z. Fisher, PE Sr. Construction Manager, Parsons Event Date

Constructability Review

Initial Field Visit with Construction ID the less

obvious clues manhole lids Whose is this? Maybe Maybe Not! VERIFY

Page 8: Constructability Review Contract Documents Construction Robert Z. Fisher, PE Sr. Construction Manager, Parsons Event Date

Constructability Review

Initial Field Visit with Construction ID less obvious

clues Overhead ID Power Phone, Cable,

Internet Other??? Signals, ITS ???

Page 9: Constructability Review Contract Documents Construction Robert Z. Fisher, PE Sr. Construction Manager, Parsons Event Date

Constructability Review

Initial Field Visit with Construction ID less obvious

clues Utility “CAMO”

Page 10: Constructability Review Contract Documents Construction Robert Z. Fisher, PE Sr. Construction Manager, Parsons Event Date

Constructability Review

Initial Field Visit with Construction ID less obvious

clues Utility “CAMO”

Page 11: Constructability Review Contract Documents Construction Robert Z. Fisher, PE Sr. Construction Manager, Parsons Event Date

Constructability Review

Initial Field Visit with Construction ID less obvious

clues Utility “CAMO”

Page 12: Constructability Review Contract Documents Construction Robert Z. Fisher, PE Sr. Construction Manager, Parsons Event Date

Constructability Review

Initial Field Visit with Construction MORE obvious

clues Really???

Page 13: Constructability Review Contract Documents Construction Robert Z. Fisher, PE Sr. Construction Manager, Parsons Event Date

Constructability Reviews Further CRT Engagement

Stage 2 of Design Checklist Item 5.11: Conflict Analysis Constructability Review can focus on

known conflicts Recommend possible solutions ID Critical Path Utility Issues

Utility Coordinator should consult with construction ANYTIME there is a question or potential issue.

Page 14: Constructability Review Contract Documents Construction Robert Z. Fisher, PE Sr. Construction Manager, Parsons Event Date

Constructability Reviews Further CRT Engagement

Stage 3 of Design Checklist Item 8.02 and 8.05.

Combine if possible as last Constructability Review

Confirms issues have been addressed through:

Design alterations to avoid conflicts Well coordinated utility relocation plans

Confirms ID of Critical Path Utility Issues

Page 15: Constructability Review Contract Documents Construction Robert Z. Fisher, PE Sr. Construction Manager, Parsons Event Date

Constructability Review Summary

Well executed review included in process from beginning to letting

Aids in developing: Improved total quality of construction

documents Lower change order costs Less delay/claims Higher quality end product

Potential Benefits to Utilities/INDOT Simpler, cost effective relocations Eliminate need to relocate

Page 16: Constructability Review Contract Documents Construction Robert Z. Fisher, PE Sr. Construction Manager, Parsons Event Date

Contract Information Book Proposal Page Schedule of Pay

Items Recurring Plan

Details Special Provisions

Contract Documents

Page 17: Constructability Review Contract Documents Construction Robert Z. Fisher, PE Sr. Construction Manager, Parsons Event Date

Construction Documents

PLANS

Contract Documents

Page 18: Constructability Review Contract Documents Construction Robert Z. Fisher, PE Sr. Construction Manager, Parsons Event Date

CIB specifies applicable SS edition.

Note: Some Special Provisions REVISE the SS.

Section 105.04 Some legal mumbo

jumbo you don’t need to build the job. Right?

Contract Documents

Page 19: Constructability Review Contract Documents Construction Robert Z. Fisher, PE Sr. Construction Manager, Parsons Event Date

Section 105.04

Illustrates importance of being clear and consistent!!!

Contract Documents

Page 20: Constructability Review Contract Documents Construction Robert Z. Fisher, PE Sr. Construction Manager, Parsons Event Date

Construction DocumentsRecurring Special

Provision: 107-R-169

Always check for and use current version posted on INDOT website.

Adaptable. Covers most situations.

Uncommon Utility situations may require Unique Special Provision (USP)

USP must be clear and defendable Consult INDOT Utility Section!!!

For added clarity….list relocations first

UC is responsible to be sure the information shown here matches the relocation plans/documents.

Page 21: Constructability Review Contract Documents Construction Robert Z. Fisher, PE Sr. Construction Manager, Parsons Event Date

Construction DocumentsExample Special Provision

It is OK to add email addresses here.

Does all of this information agree with all of the other construction documents???•Plans, Special Provisions, Utility Agreements, Relocation Plans, etc.

IT SHOULD IF UC DID THEIR JOB!

Page 22: Constructability Review Contract Documents Construction Robert Z. Fisher, PE Sr. Construction Manager, Parsons Event Date

Construction DocumentsExample Special Provision

BAD WORDS

Are these dates and durations accurately reflected in Gantt Chart? Have you, as UC, followed up regularly with Utility to confirm?

Page 23: Constructability Review Contract Documents Construction Robert Z. Fisher, PE Sr. Construction Manager, Parsons Event Date

Construction (Post Letting) We made the letting We have a low bidder The contract is awarded Utility Coordination is OVER! It’s construction’s problem

now….

Wrong!

Page 24: Constructability Review Contract Documents Construction Robert Z. Fisher, PE Sr. Construction Manager, Parsons Event Date

Construction (Post Letting) Utility Coordination will take

place until the relocations are complete! Pre-construction Conference

Generally first time all parties meet Field Staff Contractors Designers Utilities Others

All have different responsibilities UC will be proactive in making sure Utilities

engage!!!

Page 25: Constructability Review Contract Documents Construction Robert Z. Fisher, PE Sr. Construction Manager, Parsons Event Date

Construction (Post Letting) Utility Coordination

All jobs have some form of progress meetings Utility Coordinator should attend until a point where

coordination efforts are no longer needed. If proactively communicating with utilities and field

staff: Coordinator is not there to learn what is going on but should be educating others as to what is current, what is coming, and what is complete!

Page 26: Constructability Review Contract Documents Construction Robert Z. Fisher, PE Sr. Construction Manager, Parsons Event Date

Construction (Post Letting) Typical Project

Survey Clearing right-of-way Contract documents contain information

regarding status of utilities and how relocation work relates to Survey and Clearing R/W

It benefits everyone (INDOT, Contractors, Utilities, Public) to work together to progress the work to complete projects on time and on budget.

Page 27: Constructability Review Contract Documents Construction Robert Z. Fisher, PE Sr. Construction Manager, Parsons Event Date

Construction (Post Letting) Shop Drawings

Example: Mechanically Stabilized Earth (MSE) Retaining Walls.

Vendor Systems vary. What is shown in the plans is typically

less than what is submitted in Shop Drawings.

Lengths and Elevations of Leveling Pads vary slightly from plans. Can effect Underground Utilities.

Page 28: Constructability Review Contract Documents Construction Robert Z. Fisher, PE Sr. Construction Manager, Parsons Event Date

Mislocation Scenario:

PE/S calls you and says they found a water service line that is 15’ away from where it was shown on the plans and is in conflict with a new curb inlet. Contractor moved on to other pipe and structure work but said he needs to complete this within a week to stay on schedule. Water company has had other relocation work and is non-reimbursable.

What are our options? What do we do? (Open Discussion)

Page 29: Constructability Review Contract Documents Construction Robert Z. Fisher, PE Sr. Construction Manager, Parsons Event Date

Mis-relocation Same Kind of Scenario:

PE/S calls you and says a water service line was relocated 15’ away from where it was shown on the approved relocation plans and is in conflict with a new curb inlet. Contractor moved on to other pipe and structure work but said he needs to complete this within a week to stay on schedule. Water company has had other relocation work and is reimbursable.

What are our options? What do we do? (Open Discussion)

Page 30: Constructability Review Contract Documents Construction Robert Z. Fisher, PE Sr. Construction Manager, Parsons Event Date

Mis-Coordination (Uh Oh) Scenario:

PE/S calls you and says a water service line was relocated to the line and elevation on the approved relocation plans but is was cut when the contractor excavated the new ditch.

This WILL be a thing of the past. Very typical example of past problems. This is why drawings of significant detail

and constructability reviews are so important.

Discussion

Page 31: Constructability Review Contract Documents Construction Robert Z. Fisher, PE Sr. Construction Manager, Parsons Event Date

Constructability ReviewContract Documents

Construction

QUESTIONS?Thanks!