cormac engineering zambia limited
DESCRIPTION
Cormac Engineering Zambia Limited. The Finance and Construction of 12 Airports For The Republic of Zambia. Cormac Engineering Zambia Limited. Cormac Engineering Zambia Limited. E ndorsed by African Regional High Commissions: Leadership and Consultation ; - PowerPoint PPT PresentationTRANSCRIPT
Cormac Engineering Zambia Limited
The Finance and Construction of 12 Airports
For The Republic of Zambia
Presented by Steve PearsonProgramme Director
Page 1 of 19
Presented by Steve Pearson Programme Director
Cormac Engineering Zambia Limited
Page 2 of 19
Presented by Steve Pearson Programme Director
Endorsed by African Regional High Commissions:
Leadership and Consultation; Providing High Tier Management in Infrastructure Development. Setting the standards for Quality and Technology Development.
High Quality Engineering Expert Implementation; Value Added construction solutions. Long lasting environmental and humanitarian benefits.
Sharing your Vision in Partnership; We will develop solutions to achieve your objectives.
Cormac Engineering Zambia Limited
Page 3 of 19
Our Accolades:
Cormac Limited understands the infrastructure requirements of African countries
Customer focused and we aim to exceed all expectations
Adaptive approach to development phasing and requirements
Provision of economies of scale to benefit project and programme implementation.
Cormac Engineering Zambia Limited
Presented by Steve Pearson Programme Director Page 4 of 19
Client: Metropolitan Washington Airports AuthorityPresident Ronald Reagan International AirportContract Period: April 2011 – March 2012Contract Value: £8.7 million
===========================================================
Client: Sierra Leone Airport Authority Lungi International Airport Contract Period: April 2010 – April 2011Contract Value: £8 million
Portfolio Examples
Cormac Engineering Zambia Limited
Presented by Steve Pearson Programme Director
Page 5 of 19
Client: Namibia Airports Company (NAC)Hosea Kutako International AirportContract Period: September 2012 - July 2013Contract Value: US $ 3.5 million
======================================================
Client: Ilembe ConsortiumKing Shaka International AirportContract Period: Jun 2006 - Apr 2010Contract Value: $ 45million
Portfolio Examples
Cormac Engineering Zambia Limited
Presented by Steve Pearson Programme Director Page 6 of 19
Airports Team
Cormac Engineering Zambia Limited
Presented by Steve Pearson Programme Director Page 7 of 19
Outline of AerodromesAerodromes Nakonde Cat 3 International Choma Cat 4 International Kitwe Cat 4 Domestic Chingola Cat 4 Domestic Mufulira Cat 4 Domestic Luanshya Cat 4 Domestic Samfya Cat 3 Domestic Zambezi Cat 4 Domestic Kabwe Cat 4 Domestic Katete Cat 4 Domestic Petauke Cat 3 Domestic Kalabo Cat 3 Domestic
Cormac Engineering Zambia Limited
Presented by Steve Pearson Programme Director Page 8 of 19
Presented by Steve Pearson Programme Director
List of Services and Deliverables
Engineering & Design Phase Topological And Geotechnical Survey Boundary Security Construction Drawings Airfield Pavement Design Construction
Drawings Service Pavement Design Construction
Drawings Car Park Ticket Revenue Design Drawings Airfield Ground Lighting Design Drawings Capacity Assessments Airport Master Plan Development
Cormac Engineering Zambia Limited
Page 9 of 19
List of Services and DeliverablesConstructConstruction of Runways, Taxiways, ApronsLighting, Signage, SafetyAirport Access RoadsCar Parks
Cormac Engineering Zambia Limited
Construction Phase 1 - Overview Implementation of Boundary Security Implementation of Runway, Taxiway and
RESA Pavements Implementation of Apron Pavements Implementation of Car Park Pavements &
Ticket Systems Implementation of Access Road
Pavements Implementation of Airfield Ground
Lighting Implementation of Airfield Signage
Presented by Steve Pearson Programme Director Page 10 of 19
Presented by Steve Pearson Programme Director
List of Services and DeliverablesConstructConstruction of Runways, Taxiways, ApronsLighting, Signage, SafetyAirport Access RoadsCar Parks
Cormac Engineering Zambia Limited
Construction Phase 1 - Airfield Pavements
Asphalt Pavements at ~ 3ft depth:
Runways: Total 22.4 Km Asphalt Taxiways: Total 1.8 Km Asphalt RESAs: Total 72,000 m2 Asphalt RESAs: Total 28,800 m2 Non-Asphalt
Concrete Pavements at ~ 3.5 ft depth:
Aprons: Total 230,958 m2 ConcretePage 11 of 19
Presented by Steve Pearson Programme Director
List of Services and DeliverablesConstructConstruction of Runways, Taxiways, ApronsLighting, Signage, SafetyAirport Access RoadsCar Parks
Cormac Engineering Zambia Limited
Construction Phase 1 - Service Facilities
Asphalt Pavements:
Car Parks: Total 133,650 m2 Access Roads: Total 20.98 Km
Car Parking Systems: 4 Parking systems each comprising: 2 Automated Entrance 2 Automated Exit 2 Automated Payment Machines
Page 12 of 19
Presented by Steve Pearson Programme Director
Terminal, Tower, Fuel Farm Areas – Phase 2 Terminal Design and Construction ATC Tower Design and Construction Mechanical Systems Fit out Electrical Distribution HVAC Lighting and Signage Baggage Handling Security Screening Immigration and Transit Areas Arrivals and Departure areas / lounges Fuel Farms and Fire Fighting Facilities
Building Facilities
Cormac Engineering Zambia Limited
Page 13 of 19
Presented by Steve Pearson Programme Director
Communications
Communications Systems – Phase 2 ATC VHF Communication Systems Ground Management Communications Crash Fire Rescue Communications Intercom and Public Address Systems Digital Voice Switch Systems
Cormac Engineering Zambia Limited
Page 14 of 19
Presented by Steve Pearson Programme Director
Surveillance
Surveillance Systems – Phase 2 Time Reference Systems Meteorological Systems Record and Replay Systems Time Stamping Systems
Cormac Engineering Zambia Limited
Page 15 of 19
Presented by Steve Pearson Programme Director
Navigation
Navigation Systems – Phase 3 VHF Omnidirectional Range System
(VOR) Instrument Landing Systems (ILS) Approach Lighting Runway Centre Line Lighting
Cormac Engineering Zambia Limited
Page 16 of 19
Presented by Steve Pearson Programme Director
Commercial:
Engineering Design and Construction Phase 1: Financed Programme dependant on
arrangement Two Year Six Month Programme to completion Programme Price $143, 278, 742 US Dollars Programme Down Payment of 30%
Runway Price (per Km) $2, 600 000 or < 20m Kw
Cormac Engineering Zambia Limited
Page 17 of 19
Presented by Steve Pearson Programme Director
Conclusions:
Dependable Airport Expertise Proven Airport Programmes Flexible approach to Client’s needs Tailored solutions Cost-effective phased approach
Cormac Engineering Zambia Limited
Page 18 of 19
Presented by Steve Pearson Programme Director
Thank you for your valuable
time!
Any Questions?
Cormac Engineering Zambia Limited
Page 19 of 19