CSEM01 - wk8 - Software Planning 1
Software Planning
CSEM01
SE Evolution & Management
Anne Comer
Helen Edwards
CSEM01 - wk8 - Software Planning 2
• Concerned with activities involved in ensuring that software is delivered on time and on schedule and in accordance with the requirements of the organisations developing and procuring the software
• Project management is needed because software development is always subject to budget and schedule constraints that are set by the organisation developing the software
Software project management
CSEM01 - wk8 - Software Planning 3
• Proposal writing• Project planning and scheduling• Project costing• Project monitoring and reviews• Personnel selection and evaluation• Report writing and presentations
Management activities
CSEM01 - wk8 - Software Planning 4
• These activities are not peculiar to software management
• Many techniques of engineering project management are equally applicable to software project management
• Technically complex engineering systems tend to suffer from the same problems as software systems
Management commonalities
CSEM01 - wk8 - Software Planning 5
Project staffing• May not be possible to appoint the ideal people to
work on a project– Project budget may not allow for the use of highly-
paid staff– Staff with the appropriate experience may not be
available– An organisation may wish to develop employee skills
on a software project
• Managers have to work within these constraints, especially when there are shortages of skilled IT staff
CSEM01 - wk8 - Software Planning 6
Project planning• Probably the most time-consuming project
management activity• Continuous activity from initial concept through
to system delivery. Plans must be regularly revised as new information becomes available
• Various different types of plan may be developed to support the main software project plan (mainly concerned with schedule and budget)
CSEM01 - wk8 - Software Planning 7
Project plan structure• Scope the problem
• Decompose the problem
• Estimate function and effort
• Risk analysis
• Work breakdown
• Project schedule
• Monitoring and reporting mechanisms
CSEM01 - wk8 - Software Planning 8
Activity organization• Activities in a project should be organised to
produce tangible outputs for management to judge progress
• Milestones are the end-point of a process activity• Deliverables are project results delivered to
customers• The waterfall process allows for the
straightforward definition of progress milestones
CSEM01 - wk8 - Software Planning 9
Milestones in the RE process
Evaluationreport
Prototypedevelopment
Requirementsdefinition
Requirementsanalysis
Feasibilityreport
Feasibilitystudy
Architecturaldesign
Designstudy
Requirementsspecification
Requirementsspecification
ACTIVITIES
MILESTONES
CSEM01 - wk8 - Software Planning 10
Project scheduling• Split project into tasks and estimate time and
resources required to complete each task• Organise tasks concurrently to make optimal
use of workforce• Minimise task dependencies to avoid delays
caused by one task waiting for another to complete
• Dependent on project managers intuition and experience
CSEM01 - wk8 - Software Planning 11
The project scheduling process
Estimate resourcesfor activities
Identify activitydependencies
Identifyactivities
Allocate peopleto activities
Create projectcharts
Softwarerequirements
Activity chartsand bar charts
CSEM01 - wk8 - Software Planning 12
Scheduling problems• Estimating the difficulty of problems and hence the
cost of developing a solution is hard• Productivity is not proportional to the number of
people working on a task• Adding people to a late project makes it later
because of communication overheads• The unexpected always happens. Always allow
contingency in planning
CSEM01 - wk8 - Software Planning 13
Bar charts and activity networks• Graphical notations used to illustrate the
project schedule• Show project breakdown into tasks. Tasks
should not be too small. They should take about a week or two
• Activity charts show task dependencies and the the critical path
• Bar charts show schedule against calendar time
CSEM01 - wk8 - Software Planning 14
Task durations and dependencies
Task Duration (days) DependenciesT1 8T2 15T3 15 T1 (M1)T4 10T5 10 T2, T4 (M2)T6 5 T1, T2 (M3)T7 20 T1 (M1)T8 25 T4 (M5)T9 15 T3, T6 (M4)T10 15 T5, T7 (M7)T11 7 T9 (M6)T12 10 T11 (M8)
CSEM01 - wk8 - Software Planning 15
Activity network
start
T2
M3T6
Finish
T10
M7T5
T7
M2T4
M5
T8
4/7/99
8 days
14/7/99 15 days
4/8/99
15 days
25/8/99
7 days
5/9/99
10 days
19/9/99
15 days
11/8/99
25 days
10 days
20 days
5 days25/7/99
15 days
25/7/99
18/7/99
10 days
T1
M1 T3T9
M6
T11
M8
T12
M4
CSEM01 - wk8 - Software Planning 16
Activity timeline4/7 11/7 18/7 25/7 1/8 8/8 15/8 22/8 29/8 5/9 12/9 19/9
T4
T1T2
M1
T7T3
M5T8
M3
M2T6
T5M4
T9
M7T10
M6
T11M8
T12
Start
Finish
CSEM01 - wk8 - Software Planning 17
Staff allocation4/7 11/7 18/7 25/ 1/8 8/8 15/8 22/8 29/8 5/9 12/9 19/9
T4
T8 T11
T12
T1
T3
T9
T2
T6 T10
T7
T5
Fred
Jane
Anne
Mary
Jim
CSEM01 - wk8 - Software Planning 18
The risk management process
• Risk identification– Identify project, product and business risks
• Risk analysis– Assess the likelihood and consequences of these
risks
• Risk planning– Draw up plans to avoid or minimise the effects of the
risk
• Risk monitoring– Monitor the risks throughout the project
CSEM01 - wk8 - Software Planning 19
Risk identification
• Technology risks
• People risks
• Organisational risks
• Requirements risks
• Estimation risks
CSEM01 - wk8 - Software Planning 20
Risk analysis
• Assess probability and seriousness of each risk
• Probability may be very low, low, moderate, high or very high
• Risk effects might be catastrophic, serious, tolerable or insignificant
CSEM01 - wk8 - Software Planning 21
Risk Analysis & Planning
RISK PROB-
ABILITY
EFFECTS STRATEGY
Key staff are ill at critical
times
Moderate Serious Reorganise team so that there is more overlap of
work
Changes to requirements
that need major rework
Low Serious Derive traceability information to assess change
impact
Organisation restructured High Serious Prepare briefing document to show the importance
of the work being done and the negative impact of
any further change
Time required to develop
the s/w is underestimated
High Serious Reorganise work schedule and discuss the range
of alternatives with the client
Size of s/w is
underestimated
High Tolerable See above
Rate of fault finding and fix
is underestimated
Moderate Tolerable See above
CSEM01 - wk8 - Software Planning 22
Risk monitoring
• Assess each identified risks regularly to decide whether or not it is becoming less or more probable
• Also assess whether the effects of the risk have changed
• Each key risk should be discussed at management progress meetings
CSEM01 - wk8 - Software Planning 23
Key points• Good project management is essential for project
success• Managers have diverse roles but their most
significant activities are planning, estimating and scheduling
• Planning and estimating are iterative processes which continue throughout the course of a project
CSEM01 - wk8 - Software Planning 24
• A project milestone is a predictable state where some formal report of progress is presented to management.
• Risk management is concerned with identifying risks which may affect the project and planning to ensure that these risks do not develop into major threats
Key points