cth pd pim 2 (june 2016 presentation) - madison, wisconsin · • 2012 –2014 – cth m & s...

10
Public Involvement Meeting #2 CTH PD, McKee Road (Meriter Way – Maple Grove Drive) June 9, 2016

Upload: others

Post on 06-Aug-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: CTH PD PIM 2 (June 2016 Presentation) - Madison, Wisconsin · • 2012 –2014 – CTH M & S • 2017 –2019 ... WI Ironman, Epic UGM) ... Microsoft PowerPoint - CTH PD PIM 2 (June

Public In

volvem

ent M

eetin

g #2

CTH PD, M

cKee

 Roa

d(M

erite

rWay –Map

le Grove Driv

e)

June

 9, 201

6

Page 2: CTH PD PIM 2 (June 2016 Presentation) - Madison, Wisconsin · • 2012 –2014 – CTH M & S • 2017 –2019 ... WI Ironman, Epic UGM) ... Microsoft PowerPoint - CTH PD PIM 2 (June
Page 3: CTH PD PIM 2 (June 2016 Presentation) - Madison, Wisconsin · • 2012 –2014 – CTH M & S • 2017 –2019 ... WI Ironman, Epic UGM) ... Microsoft PowerPoint - CTH PD PIM 2 (June

6/9/2016

1

Project Overview

CTH PD Project Corridor:2017 Construction Year$13.9 million Estimated Cost

CTH M Project Corridor:2017‐2019 Construction Year

CTH M Project Corridor Schedule• 2010 – 2011

– Pleasant View Rd / Valley View Rd

• 2012 – 2014– CTH M & S

• 2017 – 2019– CTH PD 

• 2017 – 2019– Mid Town Rd

Project Purpose & Need• Poor Pavement Condition

• Congestion (Corridor & Intersections)

• Substandard Bike/Pedestrian Accommodations

• Substandard Sight Distance and Steep Grades

• Deficient Operations at Intersections

Page 4: CTH PD PIM 2 (June 2016 Presentation) - Madison, Wisconsin · • 2012 –2014 – CTH M & S • 2017 –2019 ... WI Ironman, Epic UGM) ... Microsoft PowerPoint - CTH PD PIM 2 (June

6/9/2016

2

Proposed ImprovementsReconstruct Pavement

Meriter Way – High Point Road

High Point Road – Maple Grove Drive

Proposed ImprovementsIncrease Sight Distance and Reduce Vertical Grades

11’

Proposed ImprovementsIce Age National Scenic Trail & Ice Age Junction Path

Page 5: CTH PD PIM 2 (June 2016 Presentation) - Madison, Wisconsin · • 2012 –2014 – CTH M & S • 2017 –2019 ... WI Ironman, Epic UGM) ... Microsoft PowerPoint - CTH PD PIM 2 (June

6/9/2016

3

Proposed ImprovementsHigh Point Road Intersection

– High Point Additional Lane• Future Southbound Dual Left Turn

– Median for Refuge & Safety

– CTH PD Left Turn Lanes• Extend Eastbound

• Add Westbound

– Replace Traffic Signals• Countdown Timers

– Bus Pads

– Realigned Parking Lot Driveway

Proposed ImprovementsMuir Field / Country Grove Intersection

– Muir Field / Country Grove Left Turn Lanes• Add Northbound & Southbound

– Box Culvert Extension• Badger Mill Creek

– CTH PD Left Turn Lanes• Add Westbound & Eastbound

– New Traffic Signals• Countdown Timers

– Bus Pads and Pull‐Outs

– Median for Refuge & Safety

– Crosswalks• All Legs of Intersection

Proposed ImprovementsJ‐Turn Access between Muir Field and Silverton Trail 

Page 6: CTH PD PIM 2 (June 2016 Presentation) - Madison, Wisconsin · • 2012 –2014 – CTH M & S • 2017 –2019 ... WI Ironman, Epic UGM) ... Microsoft PowerPoint - CTH PD PIM 2 (June

6/9/2016

4

Proposed ImprovementsMaple Grove Drive Intersection

– Maple Grove Additional Lane• Southbound Through Lane

– Modify Traffic Signals• Countdown Timers

• Future Accommodation of NB Lt Turn Arrow

• Future Accommodation of EB Lt Turn Arrow

– Bus Pads

Proposed ImprovementsIce Age Trail & Ice Age Junction Path Bridge Structure over CTH PD

Cannonball Path over Madison Beltline

CTH PD (Looking West)

Proposed ImprovementsDrainage / Storm Water

– Badger Mill Creek Storm Detention

– Storm Sewer System 

Utility– Sanitary Sewer

– Water Main

– Street Lighting

– American Transmission Company

– Madison Gas & Electric

Real Estate Acquisition– Right‐of‐Way

– Temporary Easements 

– Permanent Easements

Page 7: CTH PD PIM 2 (June 2016 Presentation) - Madison, Wisconsin · • 2012 –2014 – CTH M & S • 2017 –2019 ... WI Ironman, Epic UGM) ... Microsoft PowerPoint - CTH PD PIM 2 (June

6/9/2016

5

Proposed ImprovementsTraffic Control & Construction Staging

– One Lane Each Direction with Turn Lanes

– Temporary Pavement Widening & Crossovers

– Temporary Traffic Signals

– Temporary Pedestrian Accommodations

– Limit Closures of Intersection for Construction 

– Access to Business and Residential Properties

– Ice Age Trail & Ice Age Junction Path Detour

– Overnight Detour for Structure Construction 

– Special Events (PGA Champions Golf Tournament, WI Ironman, Epic UGM) 

Project Schedule

• 2016

– Complete Environmental Study

– Purchase of Right‐of‐Way

– Begin Utility Relocations

– Finalize Plans

• 2017

– Hold 3rd Public Involvement Meeting

– Complete Utility Relocations

– Construction (April to October)

Project Website & NotificationsProject Website Information & Subscribe to Email Updates:

http://www.cityofmadison.com/engineering/projects/county-highway-pd

EmailUpdates

Page 8: CTH PD PIM 2 (June 2016 Presentation) - Madison, Wisconsin · • 2012 –2014 – CTH M & S • 2017 –2019 ... WI Ironman, Epic UGM) ... Microsoft PowerPoint - CTH PD PIM 2 (June

6/9/2016

6

Comments & FeedbackPlease Complete and Return the Comment Form by July 1, 2016

Questions or Comments?Project Contacts:

Chris Petykowski, P.E. Pam Dunphy, P.E.City of Madison Engineering Dane County, Dept of Public Works

608‐267‐8678 608‐266‐4036

[email protected] [email protected]

Mike Bakalars, P.E. Aaron Steger, P.E.KL Engineering, Inc. KL Engineering, Inc.

608‐663‐1218 608‐663‐1218

[email protected] [email protected]

Page 9: CTH PD PIM 2 (June 2016 Presentation) - Madison, Wisconsin · • 2012 –2014 – CTH M & S • 2017 –2019 ... WI Ironman, Epic UGM) ... Microsoft PowerPoint - CTH PD PIM 2 (June

G:\Madison\15002-000\PUBLIC INVOLVEMENT\PIM 2\CTH PD PIM 2 Comment Form.Docx

PUBLIC INFORMATION MEETING #2 COMMENT FORM

City of Madison, McKee Road (Meriter Way – Maple Grove Drive)

CTH PD, Dane County Please use this page to record any comments or questions you may have regarding this project. Comments may be left in the comment box at today’s meeting, emailed to either [email protected] or [email protected] or mailed to the address on the back of this sheet by July 1, 2016. Name: Address: Telephone: Email: COMMENTS:

Page 10: CTH PD PIM 2 (June 2016 Presentation) - Madison, Wisconsin · • 2012 –2014 – CTH M & S • 2017 –2019 ... WI Ironman, Epic UGM) ... Microsoft PowerPoint - CTH PD PIM 2 (June

G:\Madison\15002-000\PUBLIC INVOLVEMENT\PIM 2\CTH PD PIM 2 Comment Form.Docx

RETURN ADDRESS _________________________________ _________________________________ _________________________________

KL Engineering, Inc. ATTN: Mike Bakalars, P.E. 5950 Seminole Centre Court Suite 200 Madison, WI 53711