december 10, 1999

40
CNWRA PROGRAM MANAGER'S PERIODIC REPORT ON ACTIVITIES OF THE CENTER FOR NUCLEAR WASTE REGULATORY ANALYSES For the Fiscal Reporting Period October 23, 1999 - November 19,1999 PMPR No. FY2000-2 December 10, 1999

Upload: others

Post on 22-Feb-2022

5 views

Category:

Documents


0 download

TRANSCRIPT

CNWRA PROGRAM MANAGER'S PERIODIC REPORT ON ACTIVITIES OF THE

CENTER FOR NUCLEAR WASTE REGULATORY ANALYSES

For the Fiscal Reporting Period

October 23, 1999 - November 19,1999

PMPR No. FY2000-2

December 10, 1999

TABLE OF CONTENTS

Section Page

T A B L E S .......................................................................... iv ABBREV IATION S .................................................................. v EXECUTIVE SUMMARY-PERIOD 2 ................................................. xi

1 TECH N ICA L ................................................................ 1 1.1 CNW RA Operations (COPS) ............................................. 1 1.2 External Quality Assurance (EQA) ......................................... 2 1.3 Igneous A ctivity (IA ) .................................................... 3 1.4 Structural Deformation and Seismicity (SDS) ................................ 3 1.5 Evolution of the Near-Field Environment (ENFE) ............................. 4 1.6 Container Life and Source Term (CLST) .................................... 5 1.7 Thermal Effects on Flow (TEF) ........................................... 7 1.8 Repository Design and Thermal-Mechanical Effects (RDTME) .................. 8 1.9 Total System Performance Assessment and Integration (TSPAI) .................. 8 1.10 Activities Related to Development of the NRC High-Level Waste

Regulations (A RDR) .................................................... 9 1.11 Unsaturated and Saturated Flow Under Isothermal Conditions (USFIC) ........... 10 1.12 Radionuclide Transport (RT) ............................................. 10 1.13 Review of the Draft Environmental Impact Statement (DEIS) ................... 11 1.14 Public O utreach ....................................................... 11 1.15 Development of the Yucca Mountain Review Plan (YMRP) .................... 11 1.16 Tank Waste Remediation Systems (TWRS) ................................. 12 1.17 Dry Transfer System (DTS) .............................................. 12 1.18 Centralized Interim Storage Facility (CISF) ................................. 13 1.19 Private Fuel Storage Facility (PFSF) ....................................... 13

2 M ANAGEM ENT ISSUES ..................................................... 13

3 M AJOR PROBLEM S ........................................................ 13

4 SUMMARY OF SCHEDULE CHANGES ........................................ 13

5 SUMMARY OF FINANCIAL STATUS .......................................... 13

APPENDIX-Planned and Actual Costs, and Cost Variances Period 2-FY2000

iii

TABLES

Table Page

1 CNWRA Core Staff-Current Profile and Hiring Plan (Period 2) ...................... 17

2 CNWRA Core Staff-Summary by Area of Concentration (Period 2) ................... 18

3 Summary of Schedule Changes (Period 2) ......................................... 19

4 D eliverables (Period 2) ........................................................ 20

5 Financial Status (Period 2) ..................................................... 21

6 Private Fuel Storage Facility License Fee Cost Recovery Status (Period 2) ............... 22

iv

ABBREVIATIONS

ID 2D 3D AA AAI AC ACD ACF

ACNW ACRS ACS ADAMS

AECL AES AMR AWF AGU AI ALTS AML AMR ANS ANSI AO AP APB AR ARDR

ASCE ASCII

ASLB ASME

ASTM

ASU ATDTS

BDCF BEG BFD BM BMF BTP CAI CAM CAR CCDF

CCL CCM CD-R

One-Dimensional Two-Dimensional Three-Dimensional Atomic Absorption Average Annual Infiltration Acceptance Criteria Advanced Conceptual Design Alumina (in excess of alkali feldspar), Calcium Oxide, Ferromagnesian Oxide Advisory Committee on Nuclear Waste Advanced Computer Review System American Chemical Society Agencywide Documents Access and Management System Atomic Energy of Canada Limited Atomic Emission Spectrometry Analysis Model Report Antler Wash Fault American Geophysical Union Administrative Item Apache Leap Test Site Areal Mass Loading Analysis and Model Report American Nuclear Society American National Standards Institute Annotated Outline Administrative Procedure Acid-Producing Bacteria Assessment Report Activities Related to Development of the NRC High-Level Waste Regulations American Society of Civil Engineers American Standard Code for Information Interchange Atomic Safety and Licensing Board American Society of Mechanical Engineers American Society for Testing and Materials Arizona State University Automated Technical Data Tracking System Biosphere Dose Conversion Factor Bureau of Economic Geology Basis for Design Bare Mountain Bare Mountain Fault Branch Technical Position Color Alteration Index Corrosion Allowance Material Corrective Action Request Complementary Cumulative Distribution Function Commitment Control Log Constant Capacitance Model CDROM Recordable

CDF CDOCS

CDROM CDTS CEB CEC

CFD CFR CHn CIAC CISF CLST CM CNWRA

COl COPS CPP CQAM CRG CRM CRWMS

CSCS

CSH CSPE

DAS DBE DC DCAA DCB DCF DCM D&D DECOVALEX

DEIS DEM DF DFCSS

DIE

DIMNS

DKM DLG DLM DNAG DNFSB DOE

V

Cumulative Distribution Function Consolidated DOCument Management System Compact Disk Read Only Memory Commission Decision Tracking System Center for Environmental Biotechnology Commission of the European Communities Computational Fluid Dynamics Code of Federal Regulation Calico Hills Nonwelded Tuff Computer Incident Advisory Capability Centralized Interim Storage Facility Container Life and Source Term Configuration Management Center for Nuclear Waste Regulatory Analyses Conflict of Interest CNWRA Operations Cyclic Potentiodynamic Polarization CNWRA Quality Assurance Manual Center Review Group Corrosion Resistant Material Civilian Radioactive Waste Management System Constrained Stochastic Climate Simulator Calcium Silicate Hydrate Corrosion Science and Process Engineering Data Acquisition System Design Basis Event Division of Contracts Defense Contract Audit Agency Double Cantilever Beam Dose Conversion Factor Dual Continuum Model Decommissioning and Decontamination DEvelopment of COupled Models and Their VALidation Against EXperiments in Nuclear Waste Isolation Draft Environmental Impact Statement Digital Elevation Model Dilution Factor Division of Fuel Cycle Safety and Safeguards Determination of Importance Evaluation Division of Industrial and Medical Nuclear Safety Dual Permeability Model Digital Line Graph Diffuse Layer Model Decade of North American Geology Defense Nuclear Facilities Safety Board U.S. Department of Energy

ABBREVIATIONS (cont'd)

DOE-DP

DOE-RU

DRA DST DTED DTS DWM DWPF EA EBS ECM ECRB

EDA II EDO

EDX EIS EM EMPA ENE ENFE

EnPA ENS EPA EPR

EPRI EQA EROS ESF ESP EW EWDP EXAFS

FCRG FDSHA

FEHM FEM FEPs FFRDC

FFT FOC FTE FTP FY FYTD GDF GEM

U.S. Department of Energy Defense Program U.S. Department of Energy Regulatory Unit Division of Regulatory Applications Drift Scale Test Digital Terrain Elevation Data Dry Transfer System Division of Waste Management Defense Waste Processing Facility Environmental Assessment Engineered Barrier System/Subsystem Equivalent Continuum Model Enhanced Characterization of Repository Block Enhanced Design Alternative II Office of the Executive Director for Operations Energy-Dispersive X-Ray Spectroscopy Environmental Impact Statement Element Manager Electron MicroProbe Analysis East-NorthEast Evolution of the Near-Field Environment Energy Policy Act of 1992 European Nuclear Society U.S. Environmental Protection Agency Electrochemical Potentiokinetic Reactivation Electric Power Research Institute External Quality Assurance Earth Resource Observation System Exploratory Studies Facility Environmental Simulation Program East-West Early Warning Drilling Project Extended X-Ray Absorption Fine Structure Format and Content Regulatory Guide Fault Displacement and Seismic Hazard Analysis Finite Element Heat and Mass Transfer Finite Element Method Features, Events, and Processes Federally Funded Research and Development Center Fast Fourier Transform Field Operations Center Full-Time Equivalent File Transfer Protocol Fiscal Year Fiscal Year-To-Date Ghost Dance Fault General Electrochemical Migration

vi

GEOTRAP GEOlogic Transport of RAdionuclides Predictions

GERT General Employee Radiological Training

GET General Employee Training GFM Geological Framework Model GHGC GeoHydrology and GeoChemistry GIA Generalized Importance Analysis GIS Geographic Information System GLGP Geology and GeoPhysics GMS Goundwater Modeling System GPS Global Positioning System GROA Geologic Repository Operations Area GSA Geologic Society of America GTFE Great Tolbachik Fissure Eruption GUI Graphics User Interface GWB Geochemist' s WorkBench GWSI GroundWater System Integration GWTI" GroundWater Travel Time HE Hydrogen Embrittlement HLW High-Level Waste HRTEM High-Resolution Transmission Electron

Microscopy HTML HyperText Markup Language IA Igneous Activity IBM International Business Machines ICP Inductively Coupled Plasma ICPP Idaho Chemical Processing Plant ICRP International Commission on

Radiological Protection IDLH Immediately Dangerous to Life and

Health IHLRWMC International High-Level Radioactive

Waste Management Conference and Exposition

IM Intermediate Milestone IME Industrial Mobilization Exception IMS Information Management Systems INEEL Idaho National Engineering and

Environmental Laboratory INETER Instituto Nicaraguense de Estudios

TERritoriales INTEC Idaho National Technology and

Engineering Center I/O Input/Output IP Inspection Procedure IPA Iterative Performance Assessment IR&D Internal Research & Development IRIS Interim Records Information System IRM Office of Information Resources

Management IRSR Issue Resolution Status Report ISA Integrated Safety Analysis ISFSI Independent Spent Fuel Storage

Installation ISI Integrated Sublssue

ABBREVIATIONS (cont'd)

ISM IUGG

IVM JC JPL JRC KESA KTI LA LAAO LAN LANL LARP LAW LBNL LBT LHS LITC

LLC LLNL

LLW LMAES

LSA LSS LWR M Ma MAI MAP MAT MC METRA MGDS MH MIC MINC MIT MM M&O MOU MPC MRS MSS MTU NAS NAWG NCR NEA NEI NFS NIOSH NIR

Integrated Site Model International Union of Geodesy and Geophysics Interactive Volume Modeling Job Code Jet Propulsion Laboratory Joint Roughness Coefficient Key Elements of Subsystem Abstraction Key Technical Issue License Application License Application Annotated Outline Local Area Network Los Alamos National Laboratory License Application Review Plan Low-Activity Waste Lawrence Berkeley National Laboratory Large Block Test Latin Hypercube Sampling Lockheed Information Technology Company Limited Liability Company Lawrence Livermore National Laboratory Low-Level Waste Lockheed Martin Advanced Environmental Systems Liquid Scintillation Analyzer Licensing Support System Light Water Reactor Molar Million Years Ago Mean Annual Infiltration Mean Annual Precipitation Mean Annual Temperature Monte Carlo Mass and Energy TRAnsport Mined Geologic Disposal System Mechanical-Hydrological Microbially Influenced Corrosion Multiple INteracting Continua Massachusetts Institute of Technology Major Milestone Management and Operations Memorandum Of Understanding Multi-Purpose Canister Monitored Retrievable Storage MultiSpectral Scanner Metric Tonnes of Uranium National Academy of Sciences Natural Analogue Working Group NonConformance Report Nuclear Energy Agency Nuclear Energy Institute Network File Server National Institutes Of Safety and Health Near-InfraRed

NIST

NMSS

NNE NNW NOAA

NRC NS NTS NUREG NWPA NWTRB OBES OCRWM

OECD

OGC OITS OMB OPS

ORR ORS OWFN PA PAAG

PC PC/TCP

PCT PDF PDR PEL PEM PER PEST PFA PFD PFDHA

PFS PFSF PHA PI PMDA

PMPR PMR PMT PNNL PO PPE

vii

National Institute of Standards and Technology Office of Nuclear Material Safety and Safeguards North-NorthEast North-NorthWest National Oceanographic and Atmospheric Administration Nuclear Regulatory Commission North-South Nevada Test Site NRC Technical Report Designation Nuclear Waste Policy Act, as amended Nuclear Waste Technical Review Board Office of Basic Energy Sciences Office of Civilian Radioactive Waste Management Organisation for Economic Co-operation and Development Office of General Counsel Open-Item Tracking System Office of Management and Budget Operations Plans for the Repository Program Operations Readiness Review Overall Review Strategy One White Flint North Performance Assessment Performance Assessment Advisory Group Personal Computer Personal Computer/Transmission Control Protocol Product Consistency Test Probability Distribution Function Public Document Room Permissible Exposure Limit Program Element Manager Prelicensing Evaluation Report Parameter ESTimation PerFluoroAlkoxy Probabilistic Fault Displacement Probabilistic Fault Displacement HAzard Private Fuel Storage Private Fuel Storage Facility Preliminary Hazard Analysis Principal Investigator Program Management, Policy Development and Analysis Staff Program Manager's Periodic Report Process Model Report Photo-Multiplier Tube Pacific Northwest National Laboratory Project Officer Prepassivated Platinum Electrode

ABBREVIATIONS (cont'd)

PRA PRT PSAG PSHA PSI PTFE PTn PUF PVHA

PVHView

PVM PWR QA QAP QRAM

RAI RASA RDCO

RDTME

REE REECO

RES RFP RH RM RSRG RT RTS SAIC

SAP SAR SCA SCC SCCEX

SCE SCFF SCM SCP SCR SDMP SDP SDS SECY

SELM SEM SER SFPO

Probabilistic Risk Assessment Peer Review Team Probabilistic System Assessment Group Probabilistic Seismic Hazard Analyses Process Safety Institute PolyTetraFluoroEthylene Paintbrush Nonwelded Tuff Pressurized Unsaturated Flow Probabilistic Volcanic Hazards Assessment Probability of Volcanic Hazards View Parallel Virtual Machine Pressurized Water Reactor Quality Assurance Quality Assurance Procedure Quality Requirements Application Matrix Request for Additional Information Regional Aquifer System Analysis Repository Design, Construction, and Operations Repository Design and ThermalMechanical Effects Rare Earth Element Reynolds Electrical and Engineering COmpany, Inc. Office of Nuclear Regulatory Research Request For Proposal Relative Humidity Review Method Real Space Renormalization Group Radionuclide Transport Radwaste Treatment System Science Application International Corporation Standards Approval Package Safety Analysis Report Site Characterization Analysis Stress Corrosion Cracking Substantially Complete Containment EXample Standard Calomel Electrode Southern Crater Flat Fault Surface Complexation Models Site Characterization Plan Software Change Report Site Decommissioning Management Plan Software Development Plan Structural Deformation and Seismicity Secretary of the Commission, Office of the (NRC) Spectral ELement Method Scanning Electron Microscopy Safety Evaluation Report Spent Fuel Project Office

SFVF SGI SGML

SHE SHT SKI S-L SLAR SNF SNL SOW SR SRB SRBS

SRD SRS SRSASF

SS SSSA SSC SSW STEM

STP SUFLAT

SVF SwRI SZ TA TAN TBD TBM TCP/IP

TDEM TEDE TEF TEM TFE TH THC THMC

T-L TLM TM TMH TMI-2 TMS

TOP TP

viii

San Francisco Volcanic Field Silicon Graphics Inc. Standard Generalized Markup Language Standard Hydrogen Electrode Single Heater Test Swedish Nuclear Power Inspectorate Short Transverse-Longitudinal Side Looking Airborne Radar Spent Nuclear Fuel Sandia National Laboratories Statement Of Work Site Recommendation Sulfate-Reducing Bacteria Shafts, Ramps, Boreholes, and Their Seals Software Requirements Description Savannah River Site Savannah River Site AluminumBased Spent Fuel Stainless Steel Soil Science Society of America Structures, Systems, and Components South-Southwest Scanning Transmission Electron Microscopy Staff Technical Position Stochastic Analyses of Unsaturated FLow And Transport Springerville Volcanic Field Southwest Research Institute Saturated Zone Technical Assistance Test Area North To Be Determined Tunnel Boring Machine Transmission Control Protocol/ Internet Protocol Time-Domain Electro-Magnetic Total Effective Dose Equivalent Thermal Effects on Flow Transmission Electron Microscopy TetraFluoroEthylene Thermal-Hydrologic Thermal-Hydrologic-Chemical Thermal-Hydrologic-MechanicalChemical Transverse-Longitudinal Triple-Layer Model Thermal-Mechanical Thermal-Mechanical-Hydrological Three Mile Island Unit 2 The Minerals, Metals, and Materials Society Technical Operating Procedure Technical Position

ABBREVIATIONS (cont'd)

TPA TPI TR2 TRG TSAR TSPA TSPA-VA

TSPAI

TSw-Chnv

TVD TWFN TWINS

TWRS UA UACH

UCLA UDEC UK UNLV UNM UR U.S. USDA USFIC

USGS UTM UZ VA VCS VF VSIP WAN WAPDEG WBS WFO WGB WIPP WNYNSC

WOL WP WSRC

WSS WTSO WVDP WVNS WWW XAFS XPS

XRD Y2K YM YMP YMR YMRP YMSCO

YTD

X-Ray Diffractometry Year 2000 Yucca Mountain Yucca Mountain Project Yucca Mountain Region Yucca Mountain Review Plan Yucca Mountain Site Characterization Office Year-To-Date

ix

Total-system Performance Assessment Time Period of Regulatory Interest DOE Seismic Topical Report No. 2 Technical Review Group Topical Safety Analysis Report Total System Performance Assessment Total System Performance AssessmentViability Assessment Total System Performance Assessment and Integration Topopah Spring Welded-Calico Hills Nonvitric Total Variation Diminishing Two White Flint North Tank Waste Information Network System Tank Waste Remediation System University of Arizona Universidad Aut6noma de Chihuahua University of California, Los Angeles Universal Distinct Element Code United Kingdom University of Nevada, Las Vegas University of New Mexico Uranium Recovery United States U.S. Department of Agriculture Unsaturated and Saturated Flow Under Isothermal Conditions U.S. Geological Survey Universal Transverse Mercator Unsaturated Zone Viability Assessment Version Control System Vitrification Facility Vertical Slice Implementation Plan Wide Area Network WAste Package DEGradation Work Breakdown Structure Work For Others Western Great Basin Waste Isolation Pilot Plant Western New York Nuclear Service Center Wedge-Opening Loading Waste Package Westinghouse Savannah River Company Waste Solidification Systems Washington Technical Support Office West Valley Demonstration Project West Valley Nuclear Services World Wide Web X-Ray Adsorption Fine Structure X-Ray Photoelectron Spectroscopy

EXECUTIVE SUMMARY-PERIOD 1

In the Division of Waste Management (DWM) Job Code (JC), the Center for Nuclear Waste Regulatory Analyses (CNWRA) staff transmitted External Peer Review of the Total-system Performance Assessment Version 3.2 Code-Letter Report and Draft Environmental Impact Statement Evaluative Review Comments. The staff produced papers and posters for presentation at various technical meetings. These papers have been or will be submitted for acceptance in recognized technical journals. Staff also participated in workshops, symposia, and other technical meetings.

The DWM JC year-to-date (YTD) cost variance was - 11.3 percent. Spending fell slightly from the last period, but again exceeded spending estimates for the period.

In the TankWaste Remediation System JC, staff pursued activities in the various subtasks, and they attended several design review meetings. The YTD cost variance was 24.2 percent. Spending declined from the previous period, but the cumulative variance is expected to decrease as new activities begin.

In the Dry Transfer System (DTS) JC, staff continued developing the DTS draft safety evaluation report (SER), using CNWRA and Southwest Research Institute (SwRI) staffs and one consultant. The YTD cost variance was 7.9 percent, down sharply from the first period as a result of intensive work on the SER. Spending increased significantly since the last period, and is expected to remain fairly steady as the staff prepares the draft SER.

In the Centralized Interim Storage Facility (CISF) JC, staff pursued the review of the U.S. Department of Energy response to the Spent Fuel Project Office request for additional information on the HI-STAR and HI-STORM topical report for high seismic risk sites. The YTD cost variance for the CISF was 43.1 percent. Spending remained constant from last period, but it may increase significantly after the NRC comments on the draft assessment report are received at the CNWRA.

In the Private Fuel Storage Facility (PFSF) JC, staff, in addition to visiting the site at Utah, participated in the Nuclear Regulatory Commission (NRC) and PFSF meeting at Salt Lake City, Utah, on revised seismic design and worked interactively with the NRC staff to prepare the public release version of the site-specific portion of the PFSF SER. The YTD cost variance was 26.6 percent. Spending rose significantly from last period, and it is expected to be generally consistent with estimated spending for the following period.

xi

CNWRA PROGRAM MANAGER'S PERIODIC REPORT ON ACTIVITIES OF THE

CENTER FOR NUCLEAR WASTE REGULATORY ANALYSES

TITLE: Center for Nuclear Waste Regulatory Analyses (CNWRA)

CONTRACTOR: Southwest Research Institute (SwRI) 6220 Culebra Road, San Antonio, Texas, 78238-5166

CONTRACT NO: NRC-02-97-009

JOB CODES: D1035, J5164, J5206, J5226

NRC CNWRA PROGRAM MANAGER: John J. Linehan, (301) 415-7780

NRC CNWRA DEPUTY PROGRAM MANAGER: Deborah A. DeMarco, (301) 415-7804

CNWRA PRESIDENT: Wesley C. Patrick, (210) 522-5158

ESTIMATED BUDGET: $87,611,477

PERIOD OF PERFORMANCE: 09/27/97-09/27/02

PERIOD OF THIS REPORT: 10/23/99-11/19/99

1 TECHNICAL

1.1 CNWRA Operations (COPS)

In addition to a wide range of day-to-day activities, accomplishments in the management and planning area included (i) participating in an NRC/CNWRA Management Meeting and NRC CRG meeting at TWFN; (ii) submitting a list of FY1999 milestones postponed into FY2000; (iii) reconciling the FY1999 award fee pool and estimates for FY2000 carryover monies; (iv) preparing for the NRC Annual Review of CNWRA, December 7-9, 1999, in San Antonio, Texas; (v) addressing COI-related topics among the NRC, SwRI, and CNWRA management staffs; and (vi) participating in weekly HLW Management Board meetings.

The status of CNWRA staffing is indicated in table 1. During period 2, CNWRA management continued to evaluate the demand for additional staff and the need for recruiting potential candidates. A geohydrologist will start work at the CNWRA in period 3. An operational health physicist is scheduled to join the staff in period 5, and a performance assessment modeler is expected to begin working at the CNWRA in period 6.

Computer system support activities encompassed (i) upgrading the desktop computers for basic system standardization and Y2K compliance; (ii) updating all software for Y2K compliance; (iii) pursuing installation of hardware and software for the CNWRA Security System (firewall) and an automated tape backup system; (iv) participating, as requested, in

1

the monthly NRC/CNWRA Computer Coordination meeting; and (v) maintaining LAN operations.

QA activities included (i) working to achieve closure of the CARs from the FY1999 CNWRA QA Audit (two of the four CARs have been closed); (ii) conducting surveillances, issuing nonconformance reports and corrective action requests, as required, and working with cognizant staff in response to these reports; (iii) supporting the application of configuration control for CNWRA scientific and engineering software ready for release as has been accomplished with variants of the TPA code; (iv) preventing organizational COI through SwRI RFP reviews; (v) performing QA verification checks on each CNWRA deliverable; (vi) providing QA indoctrination for new CNWRA staff members and consultants; and (vii) distributing the revised CNWRA Quality Assurance Procedure-016, Procurement Control, to key CNWRA staff members.

In the next period, the CNWRA staff expect to (i) participate in the NRC Annual Review of CNWRA ; (ii) present a summary of the Five-Year Strategic Plan at the annual review; (iii) be part of another NRC/CNWRA Management Meeting in connection with the annual review; (iv) evaluate the requirement for hiring additional core staff; (v) update LAN configurations, including installation of the revised CNWRA firewall and a new automated tape backup system; and (vi) provide CNWRA LAN operation and maintenance support.

In addition, the staff will (i) start implementation of the QA-related procurement procedure, (ii) put under configuration control the TPA Version 3.3 Code, (iii) continue to address other activities relating to the CARs identified at the annual CNWRA QA audit, (iv) perform scheduled and unscheduled QA surveillances, (v) conduct QA indoctrinations for new CNWRA staff and consultants, (vi) review SwRI RFPs for potential COI, (vii) perform QA verification checks on each CNWRA outgoing deliverable, and (viii) receive the QA survey forms that were sent to CNWRA subcontractors.

1.2 External Quality Assurance (EQA)

During this period, accomplishments in the EQA area included (i) developing the NRC report on the OCRWM ISM observation audit, which occurred October 11-15, 1999; (ii) preparing for and participating in the WP PMR OCRWM audit on November 8-12, 1999, and writing portions of that observation report; (iii) preparing for and participating in the OCRWM Biosphere PMR audit, which took place November 15-19, 1999; (iv) holding discussions with NRC staff to prepare for another round of NRC observation audits in January and February of 2000; and (v) reviewing lessons learned from the first two observation audits and arriving at a useful NRC electronic template that can be used by CNWRA and SwRI QA staffs.

In the next period, the CNWRA staff expect to (i) submit the Observation Report on the DOE YM ISM audit, (ii) complete the input to the NRC observation audit report for the WP PMR audit and convey same, (iii) complete the input to the NRC observation audit report for the Biosphere PMR audit and submit this report, and (iv) provide CNWRA input to the NRC on future observation audits and participate in the regularly scheduled DOE/NRC QA Management Meetings.

2

1.3 Igneous Activity (IA)

Staff attended and made presentations at the USGS workshop on probabilistic risk assessment for geologic hazards. The goals of this workshop were to (i) bring together experts in probabilistic hazard and risk assessment methodologies for earthquakes, floods, landslides, and volcanoes; (ii) increase awareness of the tools used to assess hazard and risk across disciplines; and (iii) determine if a common framework for assessing risks from different geologic hazards can be developed. Staff attended primarily to assess how the volcanic hazard models developed at the CNWRA for the proposed HLW repository at YM compare with hazard models developed in other disciplines by the USGS and others.

Work continued this period on the analysis of geophysical data collected at the Cerro Negro volcano, Nicaragua, during field work conducted shortly after the August eruption of this small-volume basaltic cinder cone. Staff visited the Rosensteil School of Marine and Atmospheric Sciences to learn techniques for numerical modeling of 3D deformation, which was observed during basaltic dike injection during the 1999 Cerro Negro eruption. Preliminary modeling of the Cerro Negro fracture system indicates that surface deformation occurred with dike injection to a depth of <100 m. Modeling of Cerro Negro transient electromagnetic data is continuing at the University of Southern Maine.

Physical analog experiments for magma-repository interactions continued this period. These experiments are conducted to evaluate the rate and extent of flow if basaltic magma enters a repository drift. These experiments aim to evaluate the current DOE TSPA assumption of limited flow into a drift. Several low volatile (golden syrup) and volatile-rich (gum-resin-acetone) experiments were conducted successfully during this period. Work focused on development of an equation of state for the gum-resin-acetone mixture to better quantify the analogy with basaltic magma.

Staff gave two invited lectures at Idaho State University this period. These lectures presented risk assessment methodologies at Cerro Negro volcano, Nicaragua, and how volcanic risks are being evaluated and compared with other risks in the YMRP. Staff also began preparations for the NRC Annual Review of the CNWRA and the Fall AGU meeting.

In the next period, staff will (i) make presentations at the NRC Annual Review of the CNWRA, (ii) complete preparations for presentations at the Fall AGU meeting, (iii) continue to analyze and model data from the August activity at the Cerro Negro volcano, and (iv) conduct analog experiments of magma-repository interactions that evaluate the response of a high-volatile content system during sudden decompression and fragmentation.

1.4 Structural Deformation and Seismicity (SDS)

The EarthVision geologic model that will be used as input for hydrologic modeling of the SZ, and the accompanying CNWRA report are being reviewed.

Staff continued an analysis of the field data on faults and fractures recently collected in the Volcanic Tablelands of California. The deformation of the Tablelands serves as an analog for deformation at YM. Results of the analysis will be used in resolving uncertainties in

3

orientation and distribution of fracture sets at YM and in the review and evaluation of the faulting models proposed in the DOE PSHA expert elicitation.

Staff continued development of the Strain Distribution and Tectonic Setting of Yucca Mountain and Crater Flat-Journal Article. This article will evaluate the geological relationships in Crater Flat and present a 3D model of the fault system at Bare Mountain. Alternatives of the model will be used to evaluate sensitivities of the potential seismic hazard at YM.

Paleomagnetic measurements of 136 samples from southern Crater Flat and the Volcanic Tablelands were completed during this period. Analysis of the data will be accomplished during the next several periods.

Staff finished and placed in review an AI report on the portability of SEISM 1.1. This report documents the completion of all SEISM 1.1 activities, including archiving the software.

In the next period, staff will (i) make presentations at the NRC Annual Review of the CNWRA; (ii) modify and add to the 3DStress software leading to Version 2.0, following completion of the TOP-018 requirements; and (iii) continue work on two milestones (the Strain Distribution and the Tectonic Setting Yucca Mountain and Crater Flat-Journal Article and Resolve Selective Field Relationships for the Three-Dimensional Structural Model of Amargosa Desert for Input to the USFIC-CNWRA Report).

1.5 Evolution of the Near-Field Environment (ENFE)

Staff completed the author-final draft of an analysis of ENFE-relevant content in the DOE database of FEPs, focusing on inclusiveness and FEPs screening.

NRC and CNWRA staffs continued a review of the DOE Disposal Criticality Analysis Methodology Topical Report. Staff attended a meeting at Bettis Atomic Power Laboratory, West Mifflin, Pennsylvania, with technical staff from the DOE Naval Nuclear Propulsion Program.

Staff participated in the NRC/CNWRA workshop on the third laboratory-scale heater test held at TWFN. A work plan to model coupled THC processes in the laboratory tests was developed and presented.

A poster titled Hydrothermal or Deuteric Alteration of Tuffs at the Paiute Ridge Intrusive Complex, Nevada, was presented at the Annual Meeting of the GSA in Denver, Colorado. Manuscripts and presentation material were prepared for two papers to be presented at the upcoming Materials Research Society Fall Meeting in Boston, Massachusetts. The papers are Thermodynamic Interpretations of Chemical Analyses of Unsaturated Zone Water from Yucca Mountain, Nevada, and Natural Analogs and Performance Assessment for Geologic Disposal of Nuclear Waste.

Staff continued development of the MULTIFLO code, focusing on release of Version 1.2. Staff also began revisions to the MULTIFLO User's Manual.

4

In addition to an assessment of the potential radiolysis effects on the near-field environment-inside and outside the WP--on the basis of the EDA II design, staff pursued the development of a webpage for the Pefia Blanca natural analog site. A draft of the webpage contents was sent to NRC staff.

Staff prepared presentations for the NRC Annual Review of the CNWRA.

In the next period, staff will (i) submit the report on FEPs Database Analysis; (ii) present results of ENFE activities at the Materials Research Society Fall Meeting in Boston, Massachusetts; (iii) begin SER on the DOE Disposal Criticality Analysis Methodology Topical Report; and (iv) participate in the NRC Annual Review of the CNWRA, December 7-9, 1999 in San Antonio, Texas.

1.6 Container Life and Source Term (CLST)

Staff continued to evaluate the applicability of repassivation and corrosion potentials as adequate electrochemical parameters to predict the long-term, localized corrosion of corrosion-resistant container materials through prolonged corrosion testing. Potentiostatic and open-circuit tests continued, conducted in chloride-containing solutions at 95 'C using Alloy 825 specimens with attached crevice-forming devices. The total test times reached 1,514 and 1,368 days, respectively. In addition, for the past several months, three creviced Alloy 22 specimens have been tested at 95 'C in a 4 M NaC1 solution at pH 8.0. Two of these specimens are being tested at 300 and 400 mVsCE, and the third at the open-circuit potential in an air-saturated solution. The time-dependent changes in the corrosion potential are monitored in the test under open-circuit conditions.

Staff measured the passive corrosion rates of welded Alloy 22 specimens in slightly alkaline (pH 8.2) and acidic (pH 2.7) chloride solutions at 95 'C. Having begun tests to measure the passive corrosion rate of welded specimens in highly alkaline solutions (pH 11.0), results obtained to date indicate that the passive dissolution rate of the welded material is similar to that measured for the base metal. Staff began modeling the passive behavior of Ni-Cr-Mo alloys using a modified version of the point-defect model to provide a solid mechanistic interpretation to the experimentally measured long-term passive corrosion rates.

Staff continued the SCC testing of Alloy 22 and type 316L SS in hot chloride-containing solutions. Fatigue precracked, wedge-loaded DCB specimens of each material were tested in a deaerated 5 percent NaCl solution, acidified to pH 2.7 by the addition of HCI, and heated to 90 'C to duplicate experimental conditions used at the LLNL. No cracking of the two alloys was observed under these conditions for a cumulative test time of 51 wk. In addition, no crack growth was observed on Alloy 22 specimens exposed to a more aggressive environment, 40 percent MgCI2 solution at 110 'C under open-circuit potential conditions. In contrast, significant crack growth was observed in type 316L SS specimens after a short exposure period in MgC12 solutions (both 30 and 40 percent) at 110 'C. Tests of type 316L SS specimens conducted at various applied potentials in 30 percent MgC12 solution at 110 'C showed that the crack growth rate decreases with decreasing potential. It appears that no SCC propagation would occur below the repassivation potential. Staff are planning more tests to confirm whether the repassivation potential may be used as a

5

threshold criterion for precracked specimens as was demonstrated previously for smooth specimens in slow strain rate tests.

Staff prepared a paper containing the results obtained in all these studies on Alloy 22 for presentation at the NACE Corrosion/2000 conference. This paper is currently under programmatic review.

Staff also attended a workshop on life prediction of engineered structures subject to corrosion that was sponsored by the ASTM in Kansas City, Missouri. They made a presentation at this workshop showing how experimental results were used in the TPA code to predict corrosion lifetimes of WP materials. Included in the presentation were examples of the effects of Ni base alloy selection (Alloy 825 vs 625 vs 22) as well as fabrication effects on the localized and uniform corrosion resistance and, consequently, predicted life times of WPs. Staff are preparing a trip report describing the presentation.

Staff evaluated the effects of environmental variables on the corrosion behavior of Ti-grade 7 (identified by the DOE as a possible candidate material for drip shield construction). Long-term tests continued to confirm the high resistance of these alloys to localized corrosion. The galvanic coupling of Ti to carbon steel is also being examined because carbon steel components may be used for ground support, which may lead to conditions favorable for hydrogen embrittlement. Limited crevice corrosion testing continued at temperatures greater than 100 'C to examine the effects of temperature on the critical potentials for the localized corrosion of Ti. Given the high resistance of Ti alloys to localized corrosion, staff conducted measurements of the passive dissolution rate. In addition, welded specimens are being evaluated to examine the possible detrimental effects of weldments on corrosion resistance. A paper to be presented at the NACE Corrosion/2000 conference detailing the results obtained to date is currently being finalized, incorporating technical and programmatic reviews comments.

Another paper for presentation at the NACE Corrosion/2000 conference is being finalized for submission. The topic of the paper is Localized Corrosion Behavior of Zircaloy-4, and it is based on collaborative work conducted by NRC and CNWRA staffs.

Staff pursued testing glass wasteforms using the standard EA glass and two simulated waste glasses (DWPF Blend 1 and WVNS Reference 6) using the ASTM PCT, Method B. Long-term tests on these three glasses are conducted in deionized water and concentrated FeC12 and FeC13 solutions (0.25 and 0.0025 M), with solution replacements twice a week for the first 12 wk using PFA TFE-flourocarbon vessels. A 1-wk solution replacement interval has begun. Twenty-eight solution replacements have been made and the leachates analyzed using ICP to determine the effect of iron cations on the dissolution rate of the reference glasses. This effect is important for assessing the influence of steel corrosion products on glass degradation. In addition, staff used PUF test equipment to study the dissolution behavior of simulated wasteforms under repository conditions. Long-term tests exceeding 6 mo are planned.

Staff continued evaluating the suitability of corrosion potential and chemistry (Cl concentration and pH) sensors for heat transfer conditions as part of a performance confirmation test evaluation program. Results during elevated temperature exposure indicate that the chloride and pH electrodes show promise, though the reference electrode

6

shows some variability with time and solution chemistry. Examination began of the effects of episodic dryout and rewetting on the performance of these electrodes. Based on limited testing, the pH and chloride electrodes seem to perform reasonably. The choice of a suitable reference electrode is still problematic. The results obtained to date were presented at an NRC/CNWRA workshop on the third laboratory-scale heater test at TWFN.

In the next period, staff will (i) participate in the NRC Annual Review of the CNWRA; (ii) pursue long-term corrosion testing of Alloys 825 and C-22 together with SCC tests using Alloy C-22 and type 316L SS along with the Ti-grade 7 test program, including examination of localized corrosion of welded specimens; (iii) examine the effect of preoxidation on the passive film and subsequent corrosion behavior of Zircaloy-4; (iv) evaluate sensor designs to be used in the simulated drift experiments; (v) perform additional glass-dissolution tests; and (vi) begin an investigation of the internal WP environment in coordination with other CNWRA staff associated with the ENFE and TEF KTIs. In addition, technical and programmatic reviews will be completed on the various papers submitted for presentation at the Corrosion/2000 conference and for subsequent publication.

1.7 Thermal Effects on Flow (TEF)

The NRC/CNWRA workshop on the third laboratory-scale heater test was held November 9, 1999, at TWFN. CNWRA representatives from the TEF, ENFE, and CLST KTIs led discussions on test design, test objectives, and details of instrumentation. NRC staff attending the workshop provided valuable input on the design of the experiment that addressed important objectives. Alpine miner muck from the lower lithophysal unit of the Topopah Spring Tuff in the ECRB is being prepared for the experiment.

Staff completed preliminary calculations of temperature and RH inside a backfilled drift and in fractured rock adjacent to the drift wall. These calculations were made available to colleagues in the ENFE KTI. In addition, one TEF KTI staff member attended the Ninth Thermal Workshop held at SNL in Albuquerque, New Mexico. He submitted a trip report summarizing discussions regarding the DST and concerns regarding heat and moisture loss through the thermal bulkhead.

Laboratory investigation is ongoing of an artificial fracture to determine whether or not a capillary threshold for dripping exists for preferential "finger" flow along a fracture at the drift wall boundary. Preliminary TH simulations of the DST in 3D are progressing to investigate the effects of moisture and heat loss through the thermal bulkhead on the development of refluxing above the heated drift. Simulations of mountain-scale and driftscale TH are continuing to look at the effects of repository edge cooling and preclosure ventilation.

In the next period, staff plan to (i) make presentations at the NRC Annual Review of the CNWRA; (ii) provide results of capillary diversion in an artificial fracture at the Fall Meeting of the AGU; and (iii) continue 3D modeling of the DST and 2D modeling of TH at the drift and mountain scales.

7

1.8 Repository Design and Thermal-Mechanical Effects (RDTME)

The ABAQUS code modeling of WPs continued to investigate the thermal stress of WPs and assess the WP responses when subjected to the impact of falling rocks at various times considering the long-term effect of corrosion on WPs. This analysis will develop a reasonable failure criterion for use in the SEISMO module to assess the effect of rockfalls on WP integrity.

Staff began a discontinuous analysis using the UDEC code to assess the stability of emplacement drifts under the newly proposed EDA II. The analysis focused on the effect of data input uncertainties on rock-mass behavior surrounding the emplacement drifts. The data under consideration include both mechanical and strength properties. The effect of lithophysae also will be included in the analysis in the future. In addition, staff pursued efforts to examine rockfall potential using the Key Block Theory considering thermal stress and seismic loads.

Development activities related to the ISA prediction tool began. During this reporting period, activities focused on (i) identifying computer codes suitable for conducting various aspects of the analysis and (ii) becoming familiar with the ISA process so that appropriate acceptance criteria and review methods can be developed for review of the DOE ISA in the LA. Modeling work started on one subtask of the DECOVALEX mI Program. This subtask is part of Task 2 (Drift Scale Test at the Yucca Mountain) of the DECOVALEX III Program.

One RDTME staff member attended the Ninth Thermal Workshop held at SNL in Albuquerque, New Mexico. Staff participated in the Appendix 7 Meeting on QA Classification and ISA Approach held in Las Vegas, Nevada, November 16, 1999, and the Appendix 7 Meeting on Ground Control held in Las Vegas, Nevada, November 17-18, 1999.

In the next period, staff plan to (i) make presentations at the NRC Annual Review of the CNWRA; (ii) investigate rock mass behavior under heated conditions on both repository and drift scales with an emphasis on long-term degradation of rock mass material properties and strengths using the new EDA II design; (iii) conduct rockfall simulations; (iv) use the ABAQUS code to model WPs; (v) model the TMH coupled effects for the DECOVALEX III Program; (vi) participate in the NRC Annual Review of the CNWRA; and (vii) attend the DECOVALEX III Task Force Meeting to be held in Barcelona, Spain, December 13-15, 1999.

1.9 Total System Performance Assessment and Integration (TSPAI)

Staff continued testing the TPA Version 3.3 code and preparing documents for software configuration control. The CNWRA and the NRC PA staffs finalized the prioritization of the TPA Version 4.0 code process-level changes proposed by staff associated with the various KTIs. The CNWRA PA staff proposed additional system-level changes. Also, the CNWRA staff began developing the SRD for the TPA Version 4.0 code. In support of SRD development, staff conducted feasibility studies using the TPA code to identify code changes needed to accommodate the DOE new repository and WP designs.

8

The report, External Peer Review of the Total-system Performance Assessment Version 3.2 Code, was submitted. The report compiles the independent reports from each of the eight external peer reviewers and summarizes their findings on the suitability of the TPA Version 3.2 code as a tool for reviewing the DOE TSPA-LA. Staff will use the comments of the external reviewers to guide the development of future versions of the TPA code.

The CNWRA and NRC staffs continued revising Input to TSPAI IRSR, Revision 2-Letter Report based on new guidance received from the NRC for a systematic, logical, and easyto-read style of presentation. The draft version of the section on transparency and traceability in the performance assessment was completed, provided to the NRC staff for review, and submitted for incorporation into the TSPAI IRSR.

Staff made two presentations at the ANS Winter Meeting, held November 14-19, 1999, in Long Beach, California. Staff also traveled to Rockville, Maryland, to attend the 114th

ACNW Meeting and discuss with subcontractor staff the development of a post-processor for the systematic presentation of TPA output. Other activities during this period include preparation of papers for the NRC-approved presentations at the Waste Management 2000 Conference to be held February 28-March 2, 2000, in Tucson, Arizona, and the European Safety and Reliability Conference (ESREL2000) scheduled for May 15-17, 2000, in Edinburgh, Scotland, United Kingdom.

Four papers were submitted during this period for NRC programmatic review. Two of these papers will be published in the proceedings of the Scientific Basis for Nuclear Waste Management Symposium scheduled for November 29-December 3, 1999, in Boston, Massachusetts. The other two will be submitted for publication in the Nuclear Engineering and Design journal.

In the next period, the staff will focus on (i) participating in the NRC Annual Review of the CNWRA on December 7-9, 1999, at San Antonio, Texas; (ii) completing Input to TSPAI IRSR, Revision 2-Letter Report; (iii) finalizing testing and documentation documents for the TPA Version 3.3 code; (iv) discussing with staff in other KTIs changes to be implemented in the TPA Version 4.0 code and preparing the associated SRD and SDP; (v) preparing papers for conferences; and (vi) beginning work on the strategic plan for review of the TSPA-SR. Two PA staff will join the CNWRA in the January-February timeframe; active recruitment for the two remaining PA positions will be postponed until later in the year.

1.10 Activities Related to Development of the NRC High-Level Waste Regulations (ARDR)

Staff continued writing responses to public comments on the 10 CFR Part 63 proposed rule. They also continued consideration of potential changes to the Statements of Consideration and this proposed rule based on review of the comments.

In the next period, emphasis will be placed on (i) participating in the NRC Annual Review of the CNWRA on December 7-9, 1999 at San Antonio, Texas; (ii) completing draft responses to the NRC comments on the proposed 10 CFR Part 63 and the identification of potential changes to the proposed rule and the Statements of Consideration that result from the responses to public comments; and (iii) conducting analyses supporting these responses

9

to public comments needed for the upcoming deliverable, Analyses Supporting Responses to Public Comments on Draft HLW Rulemaking.

1.11 Unsaturated and Saturated Flow Under Isothermal Conditions (USFIC)

Staff pursued watershed modeling, using existing data and recent confirmatory field observations of soil cover and bedrock lithology, in an effort to investigate the alternative conceptual model of high, focused infiltration in the upper watershed caused by focusing of runoff into channels and the thin alluvial cover in those channels.

Staff also continued modeling analyses to assess the importance of well-screen length, dispersivity, source mixing, and plume geometries on dilution of contaminants in pumping wells. Because and DOE is likely to take credit for well-bore dilution, these analyses will allow staff to rank the importance of various controlling factors and focus review efforts accordingly.

SZ flow modeling was used to test the alternative conceptual model of enhanced permeability along fault zones and reduced permeability across fault zones. Inclusion of such characteristics in the flow model resulted in improved model calibration. In a parallel effort, reduction of YM well data continued in the ongoing review of aquifer permeability and the potential for increased permeability along faults.

Staff continued to review pertinent DOE reports, literature, meeting transcripts, and data. One staff member attended a meeting in Beatty, Nevada, on the development of the USGS Death Valley Regional Groundwater Flow.Model.

In the next period, USFIC activities will include (i) delivery of a presentation at the NRC Annual Review of the CNWRA on December 7-9, 1999 in San Antonio, Texas; (ii) participation in the AGU Fall Meeting, December 13-17, 1999, in San Francisco, California; (iii) review of DOE models for seepage and dripping in underground cavities; (iv) analysis of processes affecting deep percolation; (v) analysis of YM well data; and (vi) continued use of a site-scale model for SZ flow to investigate alternative conceptual models for flow.

1.12 Radionuclide Transport (RT)

Staff presented an invited paper, Role of Radionuclide Sorption in High-Level Waste Performance Assessment: Approaches for the Abstraction of Detailed Models, at the Soil Science Society of America Annual Meeting held October 31-November 5, 1999, in Salt Lake City, Utah. Staff completed the manuscript, Technetium-99 Chemistry in Reducing Groundwaters: Implications for the Performance of a Proposed High-Level Nuclear Waste Repository at Yucca Mountain, Nevada, for presentation at the Materials Research Society Annual Meeting to be held in Boston, Massachusetts, November 29-December 3, 1999. Staff prepared presentation materials for the NRC Annual Review of the CNWRA to be held December 7-9, 1999, in San Antonio, Texas.

Experiments continued on the sorption behavior of Tc and coprecipitation for Np and calcite. The effect of calcite growth rate on Np coprecipitation, as controlled by supersaturation with respect to calcite, is being studied. XAFS spectra were collected at

10

Brookhaven National Laboratory for investigating mechanisms for uranyl sorption onto montmorillonite and clinoptilolite. Analyzed samples include ion-exchanged and surfaceadsorbed uranyl ion with clinoptilolite and montmorillonite, reacted at pH 3 and 6, respectively.

Staff participated in the November sampling event for the Nye County EWDP wells. Samples from well NC-EWDP-3S were collected from the 408 ft and 500 ft sampling ports and were analyzed for temperature, pH, conductivity, oxidation-reduction potential, and alkalinity. The samples are being processed for further chemical analyses.

In the next period, staff will (i) make a presentation at the NRC Annual Review of the CNWRA, (ii) work with staff associated with the TSPAI KTI to implement proposed sorption response surfaces for the TPA Version 4.0 code, (iii) continue to revise reports on ion exchange and surface complexation, and (iv) pursue sorption experiments on alluvium minerals.

1.13 Review of the Draft Environmental Impact Statement (DEIS)

Staff and external consultants completed review of the DOE DEIS for the proposed repository and submitted Draft Environmental Impact Statement Evaluative Review Comments. The CNWRA staff participated in public meetings in Caliente, Nevada, and attended a DEIS briefing to the ACNW.

In the next period, the staff and external consultants will work with the NRC staff to finalize DEIS comments for submission to the Commission.

1.14 Public Outreach

Discussions continued with a risk communications expert about conducting a 1- or 2-day course at the CNWRA. Although a date for this course still has not been established, staff believes it can be conducted by the end of period 5.

In the next period, efforts will continue to establish a schedule and agenda for the short course on risk communications.

1.15 Development of the Yucca Mountain Review Plan (YMRP)

YMRP development continued in collaboration with the NRC staff. KTI and ISI staff leads continued preparation of the model abstraction portions of the plan, and some ISI sections completed the internal CNWRA review process. Staff proceeded on the preclosure and QA portions of the plan. The CNWRA project manager participated in a presentation to the ACNW on YMRP development. An Annotated Yucca Mountain Review Plan Outline was prepared for submittal as an IM during the next period.

In the next period, staff will continue development of Revision 0 of the YMRP, focusing on completion of the postclosure safety sections. The CNWRA project manager will participate in meetings with NRC staff and management at TWFN. Development of the preclosure safety and administrative and programmatic portions of the YMRP will also continue. The CNWRA will draft a white paper that proposes options for the integration

11

of the IRSR and the YMRP structures. The CNWRA will also identify activities that should be conducted under YMRP development rather than under the KTIs to address an existing resource imbalance. The Annotated Yucca Mountain Review Plan outline will be submitted.

1.16 Tank Waste Remediation System (TWRS)

In subtask 1.2, staff started work on the technical review report on Ultrafilters. Also, staff is reformatting the Survey of Solidification Technologies report to NUREG/CR format and awaiting copyright permissions for figures and tables from authors and publishers.

In subtask 1.4, staff started work on the classification and categorization of process safety issues.

In subtask 1.6, staff continued development of a spreadsheet model of the pretreatment process, based on mass-balance considerations using reported waste feed envelope compositions and reported or assumed concentration factors or decontamination factors. A preliminary version was sent.

In subtask 2.1, CNWRA staff attended a topical meeting on Cs storage vessel cooling and seismic probabilistic risk analysis and a design review meeting on low activity waste and high-level waste melter design. CNWRA staff attended a design review meeting on pretreatment ion exchange systems and equipment. Trip reports on these meetings have been transmitted. Staff provided comments to the NRC on the Management of Risks Posed by Explosive Hazards Present at the River Protection Project-Waste Treatment Plant on October 13, 1999. On November 11, 1999, staff provided response to BNFL Inc. comments on the CNWRA document, Review of BNFL Inc. Design Safety Features Deliverable: Hydrogen Control in High-Level Waste Storage Tanks. Staff started review of the BNFL Inc. document entitled Summary of ISM Cycle 1 Results and Identification of Preliminary Design Basis Events. As agreed with the NRC, initial comments will be provided as an AI on November 24, 1999, and final comments by December 21, 1999, after incorporating new information provided by BNFL Inc. at a topical meeting on November 30, 1999.

In the next period, in subtask 1.2, staff will continue work on reformatting the Survey of Solidification Technologies report and the technical review report on Ultrafilters. In subtask 1.4, staff will continue the classification and categorization of process safety issues. In subtask 1.6, development of a spreadsheet model for the TWRS waste pretreatment will progress. In subtask 2.1, staff will review the document, Summary of ISM Cycle 1 Results and Identification of Preliminary Design Basis Events. In addition, staff plan to attend a topical meeting on November 30, 1999, and a design review meeting on December 7-8, 1999.

1.17 Dry Transfer System (DTS)

Development of the DTS draft SER progressed during this period, making use of the CNWRA and SwRI staffs and a consultant. Significant progress was made developing this draft SER. It will be delivered as Safety Evaluation Report of Dry Transfer System Topical Safety Analysis Report-Draft during the next reporting period.

12

In the next period, the staff will complete development of the draft SER.

1.18 Centralized Interim Storage Facility (CISF)

Staff continued reviewing the DOE response to the SFPO first round RAI on the HI-STAR and HI-STORM topical report for high seismic sites. Further, staff began developing the second round RAI.

In the next period, the staff will continue reviewing and evaluating the DOE response to the SFPO first round RAI on the HI-STAR and HI-STORM topical report for high seismic risk

sites. The development of the second round RAI will also be ongoing.

1.19 Private Fuel Storage Facility (PFSF)

Three PFSF staff members visited the site in Utah and participated in the NRC/PFSF

meeting at Salt Lake City, Utah, on revised seismic design. Two PFSF staff members also

attended a meeting with the Air Force staff at Hill Air Force Base to discuss aircraft accident issues. The staff worked interactively with the NRC staff to prepare the public release version of the site-specific portion of the PFSF SER. They also worked on various contentions.

In the next period, the staff plans to continue working interactively with the NRC staff to

prepare the public release version of the site-specific portion of the PFSF SER, review and

evaluate the revised seismic design reports, and assist the NRC staff on ASLB hearing activities.

2 MANAGEMENT ISSUES

None to report.

3 MAJOR PROBLEMS

None to report.

4 SUMMARY OF SCHEDULE CHANGES

Schedule changes for IMs are included in table 3. Completed deliverables are noted in table 4.

5 SUMMARY OF FINANCIAL STATUS

Table 5 summarizes the CNWRA financial status in the context of authorized funds. Total

commitments are $368,227. The appendix lists planned and actual costs to date, as well as variances

between these, without allowance for fee, on both a per-period and a cumulative basis. These data

do not include commitments. Pertinent financial information is provided for the DWM JC, including

COPS, EQA, DEIS, Public Outreach, YMRP, and ten KTIs, TWRS JC, DTS JC, CISF JC, and PFSF

JC. The planned costs per period are based on the revised spending plans contained in the FY2000 OPS conveyed to the NRC.

13

Period 2 FY2000 CNWRA composite expenditures rose a modest 0.14 percent from last period, and this aggregate of all JCs was overspent by $143,786 or -6.7 percent. Since the previous period, spending rose in the DTS and PFSF JCs, but fell in the DWM, TWRS, and CISF JCs. With the exception of the DWM JC, all other JCs have a positive cumulative variance in period 2.

Expenditures on SwRI labor, consultants, and subcontractors as a proportion of composite spending on all JCs were 19.4 percent. Expense of consultants and subcontractors as a fraction of composite spending on all JCs was 12.1 percent. The CNWRA continues the judicious employment of consultants and subcontractors in the conduct of CNWRA work.

As shown in table 1, the CNWRA has 56 staff members. The available pool of approved consultants and subcontractors is 85.

This FYTD, no capital or sensitive equipment was purchased with NRC funds (other than overhead, general and administrative expenses, and fees).

The DWM JC was overspent by $209,240 or - 11.3 percent. Overall expenditures decreased about 1.4 percent from the previous period as costs rose in the IA, TSPA, and USFIC KTIs as well as the EQA and YMRP, but declined in COPS and the SDS, ENFE, CLST, TEF, RDTME, ARDR, and RT KTIs as well as the DEIS and Public Outreach. With the exception of EQA, Public Outreach, and YMRP, DEIS, COPS, and all ten KTIs have a negative cumulative variance in period 2. In various meetings with NRC senior management staff and other interested parties, CNWRA senior management staff continue to discuss current and expected levels of spending, recruitment efforts for core staff, and effective engagement of consultants and subcontractors. The CNWRA revised its award fee pool and estimate of carryover monies.

The cost variance for COPS was -30.4 percent: -35.7 percent for the Management, Planning, and Computer Support subtask (158) and -2.8 percent for the QA subtask (159). The negative variance in subtask 158 resulted primarily from delayed payment to consultants and subcontractors for FY1999, increased travel and time related to staff professional development, staff travel and time for an NRC/CNWRA Management Meeting, and late payment of costs related to the development and submittal of OPS. In the next period, spending in subtask 158 is expected to decline, but may still exceed the estimated amount. CNWRA management will monitor expenditures to ensure that

the cognizant NRC PEM for COPS is provided sufficient notice concerning expected negative variances from estimated spending in the next couple of periods. In subtask 159, spending decreased in period 2 relative to last period because of a temporary slowdown in the QA surveillance schedule and reduced consultant costs.

The cumulative cost variance for EQA was 34.5 percent. Spending this period exceeded the planned amount because of heavier activities in the field and preparation for additional NRC observation audit teams in the year 2000. In the third period of the FY, spending in subtask 331 is expected to continue near the period 2 level as the two observation audit reports are written and transmitted to the NRC.

The cost variance for the IA KTI was -25.0 percent. This overspending continues to be driven by payment of outstanding charges from FY1999. FY2000 expenditures for external labor will be controlled during the second quarter to bring expenditures within anticipated costs.

14

The cost variance for the SDS KTI was -5.4 percent. The overspending decreased significantly this period and continues to be driven by commitments incurred last FY.

The cost variance for the ENFE KTI was -45.8 percent. Although this variance is a decrease in percentage terms from period 1, the absolute value of the variance increased substantially during this period. This variance is likely to persist until activity under the YMRP increases.

The cost variance for the CLST KTI was -30.4 percent. Per period spending and cumulative variance are down, and, once the startup phase is completed, project spending will be brought in line with budgeted funds during the second quarter.

The cost variance for the TEF KTI was -6.6 percent. This variance is significantly lower than that of the previous period, and will be reduced further during the next period. The FY2000 total expenditures are expected to converge to the FY2000 allocation.

The cost variance for the RDTME KTI was -2.1 percent. FY2000 total expenditures are anticipated to converge to the planned amount.

The cost variance for the TSPAI KTI was -38.1 percent. Spending increased from the first period of FY2000 because of additional work on the modifications to Revision 2 of the TSPAI IRSR. The spending is expected to decrease in the next period following completion of the IRSR and staff vacations during the winter holidays.

The cost variance for the ARDR KTI was - 1.1 percent. Spending should continue at the same pace during the next period to complete the responses to the public comments on 10 CFR Part 63.

The cost variance for the USFIC KTI was -3.4 percent. This small negative variance resulted from an increase in activities relative to period 1. Future costs are likely to be somewhat above planned as a new hydrologist starts work during period 3. Appropriate reduction in use of external labor will be used to bring the project into convergence with the budget.

The cost variance for the RT KTI was -54.0 percent. This represents a significant decrease in the period cost variance from period 1, but the cumulative continued to increase significantly. Costs for consultants and subcontractors from FY1999 posted to this account during period 1 of FY2000 and travel costs are responsible for this variance. The cost variance should be reduced as activities increase related to YMRP development.

The cost variance for review of the DEIS was -31.3 percent. This variance was the result of the concentrated effort by CNWRA staff and external consultants to complete their reviews of the DEIS. The variance is expected to continue to increase through the next period as consultant billings are paid, but spending will then decrease substantially as DEIS review activity slows. This project is ultimately expected to have net underspending, because the level of required travel and consultant support for public meetings is expected to be less than was envisioned in the original statement of work.

The cost variance for Public Outreach was 83.7 percent. This amount understates the actual variance because labor that should have been charged to the DEIS project was inadvertently charged to this account. A transfer of labor will be processed to correct this error. Significant spending is not expected until periods 5 and 6.

15

Although costs more than doubled relative to period 1, the cumulative cost variance for development of the YMRP was 65.4 percent. The large variance is partially due to priority given by the project manager to review of the YM DEIS. The CNWRA is identifying work that can appropriately be shifted to YMRP development from the KTI structure.

The cost variance for the TWRS project was 24.2 percent. The variance will decline when new activities accelerate.

The cost variance for the DTS project was 7.9 percent. This cost variance is considerably less than that of the previous period. The FY2000 total expenditures are expected to converge to the FY2000 allocation.

The cost variance for the CISF project was 43.1 percent. This cost variance is due to lack of assignment from the NRC and lagging charges from a consultant.

The cost variance for the PFSF project was 26.6 percent. This cost variance is because of delay in receiving the final seismic design reports, aircraft crash hazard report, and other submittals from the applicant that have caused rescheduling of the delivery date of the PFSF SER supplement.

16

Table 1. CNWRA Core Staff-Current Profile and Hiring Plan* (Period 2)

Positions Open

Expertise/Experience Current No. Professional Staff FY2000

ADMINISTRATION 4 H.GARCIA, W.PATRICK. J.RUSSELL B.SAGAR

CHEMICAL PROCESSING 2 V.JAIN, D.DARUWALLA ENGNG./PHYS. CHEM.

CODE ANALYSIS/DEVELOPMENT 2 RJANETZKE, R.MARTIN

DATA MANAGEMENT/PROCESSING, I P.MALDONADO INCLUDING FINANCIAL

DOSE/RISK/HAZARD ANALYSIS 0 1

ELECTROCHEMISTRY I G.CRAGNOLINO

ENGINEERING 2 R.CHEN, G.OFOEGBU GEOLOGY/GEOLOGICAL ENGNG.

ENVIRONMENTAL SCIENCES I P.LaPLANTE

GEOCHEMISTRY 8 P.BERTETI], LBROWNING, W.MURPHY, R.PABALAN, EPEARCY, J.PRIKRYL. D.TURNER, M.NUGENT

GEOHYDROLOGY/HYDROGEOLOGY 5 D.FARRELL, R.FEDORS, R.GREEN, M.HILL, 2 J.WINTERLE

GEOLOGY 3 P.LAFEMINA, L.McKAGUE, M.MIKIAS

HYDROLOGIC TRANSPORT 3 A.ARMSTRONG, D.HUGHSON, S.PAINTER

INFORMATION MANAGEMENT 0 1 SYSTEMS

MATERIAL SCIENCES 5 S.BROSSIA, D.DUNN, O.MOGHISSI, Y-M.PAN, I N.SRIDHAR

MECHANICAL, I D.GUTE INCLUDING DESIGN & FABRICATION

MINING ENGINEERING 1 S-M.HSIUNG

NUCLEAR ENGINEERING 1 M.SMITH

OPERATIONAL HEALTH PHYSICS I J.WELDY I

PERFORMANCE ASSESSMENT 3 S.MOHANTY, O.PENSADO-RODRIGUEZ, 2 G.WITIMEYER

QUALITY ASSURANCE I B.MABRITO

RADIOISOTOPE GEOCHEMISTRY I D.PICKET"

ROCK MECHANICS, 3 A.CHOWDHURY, A.GHOSH, B.DASGUPTA INCLUDING CIVILJSTRUC. ENGNG.

SOURCE-TERM/SPENT FUEL DEGRAD. I L.YANG

STRUCTURAL GEOLOGY/ 3 D.FERRILL, D.SIMS, J.STAMATAKOS SEISMO-TECTONICS

SYSTEMS ENGINEERING I P.MACKIN

VOLCANOLOGY/IGNEOUS 2 C.CONNOR, B.HILL PROCESSES

TOTAL 56 8

* See staffing plan for details

17

Table 2. CNWRA Core Staff-Summary by Area of Concentration (Period 2)

Positions

Area of Concentration Actual Planned Open

ADMINISTRATION, QUALITY ASSURANCE, AND 6 7 1 INFORMATION MANAGEMENT

GEOCHEMISTRY 9 9 0

HYDROLOGY/CLIMATOLOGY 8 9 1

MATERIAL SCIENCES 7 9 2

MECHANICAL, CHEMICAL, NUCLEAR, AND SYSTEMS 5 5 0 ENGINEERING

PERFORMANCE ASSESSMENT 6 10 4

ROCK MECHANICS, MINING, AND GEOLOGICAL 6 6 0 ENGINEERING

STRUCTURAL GEOLOGY, TECTONICS, AND VOLCANISM 9 9 0

TOTAL 56 64 I 8

18

Table 3. Summary of Schedule Changes (Period 2)

MILESTONE ORIGINAL REVISED

NUMBER TYPE DESCRIPTION DATE DATE RATIONALE FOR CHANGE

01402.158.075 IM Update CNWRA Computer Security 05/30/2000 New milestone added to supplement OPS

Plan FY2000.

01402.471.020 IM Strain Distribution and the Tectonic 12/13/1999 01/24/2000 Higher priority work including input to

Setting of Yucca Mountain and YMRP, preparation for annual review, and

Crater Flat-Journal Article response to licensing contentions for PSFS (Utah).

01402.771.030 IM Analyses Supporting Responses to 01/30/2000 02/25/2000 Date of 01/30/2000 in Period I PMPR was

Public Comments on Draft HLW incorrect; 02/25/2000 date reflects the need to

Rulemaking give priority to completing the rulemaking package before documenting the supporting technical work.

01402.951.014 IM Yucca Mountain Review Plan 07/14/2000 New milestone added to supplement OPS

Revision 1 Preclosure Section- FY2000. Draft

01402.952.014 IM Yucca Mountain Review Plan 07/14/2000 New milestone added to supplement OPS

Revision I Postclosure Section- FY2000. Draft

01402.953.014 IM Yucca Mountain Review Plan 07/14/2000 New milestone added to supplement OPS

Revision I Administrative and FY2000. Other Sections-Draft

01403.201.010 IM CNWRA Review (Final) "ISM 12/21/1999 New milestone added to include review of a

Cycle I Results and Identification of BNFL Inc. submittal.

Preliminary DBEs"

Table 4. Deliverables (Period 2)

ORIGINAL ACTUAL

MILESTONE COMPLETION REVISED # OF COMPLETION REASON

NUMBER TYPE DESCRIPTION DATE DATE REVISIONS DATE (IF DELAYED)

01402.761.080 IM External Review of TPA 3.2 Code- 10/29/1999 10/28/1999

_ Letter Report

01402.931.010 IM Draft Environmental Impact Statement 11/15/1999 11/15/1999

I Evaluative Review Comments

0) 0

Table 5. Financial Status (Period 2)

Funds Funds Funds Project Names Authorized Costed to Date Uncosted Commitments

COPS 3,795,302 3,750,253 45,048 33,580

EQA 73,112 31,716 41,395 1,962

IA 1,601.120 1.587,691 13,429 24,464

SDS 1.981,275 1,942,771 38,504 33,607

ENFE 1,895.049 1,905,134 (10,085) 106,381

CLST 2.135,233 2,130,995 4,238 7,987

TEF 1,420.941 1,383,539 37,402 19,864

RDTME 1,528,914 1,463,543 65,370 24,739

TSPAI 3,796,839 3,781,875 14,964 39,828

ARDR 418,024 406,216 11,809 4,260

USFIC 2,443.833 2,362,432 81,401 9,209

RT 1,396,689 1,399,970 (3,281) 16,212

DEIS 216,470 190,097 26,373 625

PO 25,080 2,752 22,328 0

YMRP 355,230 81,240 273,990 0

DWM Costs 23,083,109 22,420,225 662,884

DWM Award Fee 1,196.006 849,751 346,255

DWM Base Fee 923,324 874,417 48,907

TOTAL DWM 25,202.439 24,144,393 1,058,046 322,719

TWRS Costs 1,610,314 1,590,209 20,105 2,896

TWRS Award Fee 93,654 77,449 16,205

TWRS Base Fee 64,413 64,114 298

TOTAL TWRS 1,768,381 1,731,772 36,609 2,896

DTS Costs 515,500 464,450 51,050 0

DTS Award Fee 23.323 14,293 9,030

DTS Base Fee 20,620 18,308 2,312

TOTAL DTS 559,443 497,051 62,392 0

CISF Costs 376,720 356,843 19,877 0

CISF Award Fee 24.338 19.124 5,214

CISF Base Fee 15,069 14,179 890

TOTAL CISF 416,127 390,146 25,981 0

PFSF Costs 606,340 481,290 125,050 42,612

PFSF Award Fee 26.581 11,737 14,844

PFSF Base Fee 24,254 18,193 6,061

TOTAL PFSF 657,175 511,220 145,956 42,612

Grand Total 28,603,565 27,274,582 1,328,983 368,227

21

Note: All authorized funds have been allocated through modification #131. Funds costed to date for each award fee program

represent the award fee for FY 1998 and interim for FY 1999. Funds uncosted for each award fee program represent the award fee reserved from the last authorizations based on the Operations Plans for FYI 999.

I Note: All authorized funds have been allocated through modification #13 1. Funds costed to date for each award fee program

Table 6. Private Fuel Storage Facility License Fee Cost Recovery Status (Period 2)

LICENSE FEE COST RECOVERY STATUS

JOB CODE: J5226

TITLE:

PERIOD:

Private Fuel Storage Facility

October 23, 1999-November 19, 1999

Notes: Costs include 4 percent actual base fee plus FY1998 award fee in the amount of $6,827.

Costs include FY 1999 interim award fee in the amount of $4,910.

1")

TAC OR INSPECTION

TASK DOCKET IDENTIFICATION PERIOD CUMULATIVE COSTS

NUMBER FACILITY NAME NUMBER NUMBER COSTS CONTRACT TO DATE

01405.041 Private Fuel Storage 72-22 L22462 $32,451.52 $510,129.41

Facility

APPENDIX Planned and Actual Costs,

and Cost Variances Period 2-FY2000

CNWRA COMPOSITE

TOTAL ESTIMATE COST

ITEM 01 02 03 04 05 06 07 08 09 10 11 12 13 Total

Est 1,083,678 1,070,856 916,344 931,128 1,088,180 1,035,964 1,029,712 1,029,912 1,201,753 1,201,198 1,200,811 1,052,648 1,028,995 2,154,534

ActPd Cost 1,148,341 1,149,979 0 0 0 0 0 0 0 0 0 0 0 2,298,320

Variance, $ (64,663) (79,123) 0 0 0 0 0 0 0 0 0 0 0 (143,786)

Variance, % -6.0% -7.4% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% -6.7%

Est 1,083,678 2,154,534 3,070,878 4,002,006 5,090,186 6,126,150 7,155,862 8,185,774 9,387,527 10,588,725 11,789,536 12,842,184 13,871,179

ActFY Cumul 1,148,341 2,298,320 0 0 0 0 0 0 0 0 0 0 0

% Complete 8.3% 16.6% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

Cumul Var, $ (64,663) (143,786) 0 0 0 0 0 0 0 0 0 0 0

Cumul Var, % -6.00% -6.7% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

DIVISION OF WASTE MANAGEMENT (DWM)

01402.000 ITEM 01 02 03 04 05 06 07 08 09 10 11 12 13 Total

EstPd Cost 932,008 927,059 810,641 845,713 986,474 938,239 938,144 938,250 1,110,632 1,110,767 1,110,602 962,027 938,087 1,859,067

ActPd Cost 1,041,326 1,026,980 0 0 0 0 0 0 0 0 0 0 0 2,068,307

Variance, $ (109,318) (99,921) 0 0 0 0 0 0 0 0 0 0 0 (209,240)

Variance, % -11.7% -10.8% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% -11.3%

Est 932,008 1,859,067 2,669,708 3,515,421 4,501,895 5,440,134 6,378,278 7,316,528 8,427,160 9,537,927 10,648,529 11,610,556 12,548,643

ActFY Cumul 1,041,326 2,068,307 0 0 0 0 0 0 0 0 0 0 0

% Complete 8.3% 16.5% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

Cumul Var, $ (109,318) (209,240) 0 0 0 0 0 0 0 0 0 0 0

Cumul Var, % -11.7% -11.3% 0.0% 0,0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

CNWRA OPERATIONS (COPS)

01402.150

ITEM 01 02 03 04 05 06 07 08 09 10 11 12 13 Total

Est Pd Cost 134,053 134,054 112,122 112,125 134,829 134,833 134,829 134,835 194,873 194,882 194,871 158,588 134,828 268,107

Act Pd Cost 176,208 173,297 0 0 0 0 0 0 0 0 0 0 0 349,506

Variance, $ (42,155) (39,243) 0 0 0 0 0 0 0 0 0 0 0 (81,399)

Variance, % -31.4% -29.3% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% -30.4%

EstFY Cumul 134,053 268,107 380,229 492,354 627,183 762,016 896,845 1,031,680 1,226,553 1,421,435 1,616,306 1,774,894 1,909,722

Act FY Cumul 176,208 349,506 0 0 0 0 0 0 0 0 0 0 0

% Complete 9.2% 18.3% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

Cumul Var, $ (42,155) (81,399) 0 0 0 0 0 0 0 0 0 0 0

Cumul Var, % -31.4% -30.4% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

EXTERNAL QUALITY ASSURANCE (EQA)

EX VHNA QALIT ASSRACE(EA

ITEM 01 02 03 04 05 06 07 08 09 10 11 12 13 Total

Est Pd Cost 24,213 24,213 20,826 20,828 24,213 24,215 24,212 24,216 27,428 27,434 27,426 24,216 24,206 48,426

Act Pd Cost 7,139 24,577 0 0 0 0 0 0 0 0 0 0 0 31,716

Variance, $ 17,074 (364) 0 0 0 0 0 0 0 0 0 0 0 16,710

Variance, % 70.5% -1.5% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 34.5%

Est FY Cumul 24,213 48,426 69,252 90,080 114,293 138,508 162,720 186,936 214,364 241,798 269,224 293,440 317,646

Act FY Cumul 7,139 31,716 0 0 0 0 0 0 0 0 0 0 0

% Complete 2.2% 10.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

Cumul Var, $ 17,074 16,710 0 0 0 0 0 0 0 0 0 0 0

Cumul Var, % 70.5% 34.5% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

IGNEOUS ACTIVITY (IA)

01402.460

ITEM 01 02 03 04 05 06 07 08 09 10 11 12 13 Total

Est Pd Cost 36,787 36,787 30,456 30,461 36,785 36,790 36,782 36,790 42,368 42,377 42,366 36,791 36,774 73,574

Act Pd Cost 45,721 46,276 0 0 0 0 0 0 0 0 0 0 0 91,997

Variance, $ (8,934) (9,489) 0 0 0 0 0 0 0 0 0 0 0 (18,423)

Variance, % -24.3% -25.8% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% -25.0%

Est FY Cumul 36,787 73,574 104,030 134,491 171,276 208,066 244,848 281,638 324,006 366,383 408,749 445,540 482,314

Act FY Cumul 45,721 91,997 0 0 0 0 0 0 0 0 0 0 0

% Complete 9.5% 19.1% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

Cumul Var, $ (8,934) (18,423) 0 0 0 0 0 0 0 0 0 0 0

Cumul Var, % -24.3% -25.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

STRUCTURAL DEFORMATION AND SEISMICITY (SDS)

01402.470

ITEM 01 02 03 04 05 06 07 08 09 10 11 12 13 Total

Est Pd Cost 51,038 51,040 42,932 42,938 51,035 51,041 51,034 51,044 58,686 58,699 58,685 51,046 51,029 102,078

Act Pd Cost 60,861 46,731 0 0 0 0 0 0 0 0 0 0 0 107,593

Variance, $ (9,823) 4,309 0 0 0 0 0 0 0 0 0 0 0 (5,515)

Variance, % -19.2% 8.4% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% -5.4%

Est FY Cumul 51,038 102,078 145,010 187,948 238,983 290,024 341,058 392,102 450,788 509,487 568,172 619,218 670,247

Act FY Cumul 60,861 107,593 0 0 0 0 0 0 0 0 0 0 0

% Complete 9.1% 16.1% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

Cumul Var, $ (9,823) (5,515) 0 0 0 0 0 0 0 0 0 0 0

C'u-mul Var. % -19.2% -5.4% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

EVOLUTION OF THE NEAR-FIELD ENVIRONMENT (ENFE)

EVOLUTIONOF THE NER-FEDEVRNET(N

ITEM 01 02 03 04 05 06 07 08 09 10 11 12 13 Total

Est Pd Cost 64,477 64,478 54,913 54,915 64,475 64,478 64,474 64,478 73,858 73,866 73,856 64,482 64,467 128,955

Act Pd Cost 102,508 85.494 0 0 0 0 0 0 0 0 0 0 0 188,003

Variance, $ (38,031) (21.016) 0 0 0 0 0 0 0 0 0 0 0 (59,048)

Variance, % -59.0% -32.6% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% -45.8%

Est FY Cumul 64,477 128,955 183,868 238,783 303,258 367,736 432,210 496,688 570,546 644,412 718,268 782,750 847,217

Act FY Cumul 102,508 188,003 0 0 0 0 0 0 0 0 0 0 0

% Complete 12.1% 22.2% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

Cumul Var, $ (38,031) (59,048) 0 0 0 0 0 0 0 0 0 0 0

Cumul Var, % -59.0% -45.8% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

CONTAINER LIFE AND SOURCE TERM (CLST)

01402.570

ITEM 01 02 03 04 05 06 07 08 09 10 11 12 13 Total

Est Pd Cost 87,167 87,169 73,583 73,587 87,166 87,170 87,166 87,171 100,372 100,379 100,370 87,172 87,167 174,336

Act Pd Cost 117,352 110,042 0 0 0 0 0 0 0 0 0 0 0 227,394.

Variance, $ (30,185) (22,873) 0 0 0 0 0 0 0 0 0 0 0 (53,058)

Variance, % -34.6% -26.2% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% -30.4%

Est FY Cumul 87,167 174,336 247,919 321,506 408,672 495,842 583,008 670,179 770,551 870,930 971,300 1,058,472 1,145,639

Act FY Cumul 117,352 227,394 0 0 0 0 0 0 0 0 0 0 0

% Complete 10.2% 19.8% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

Cumul Var, $ (30,185) (53,058) 0 0 0 0 0 0 0 0 0 0 0

Cumul Var, % -34.6% -30.4% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

THERMAL EFFECTS ON FLOW (TEF)

01402.660

ITEM 01 02 03 04 05 06 07 08 09 10 11 12 13 Total

Est Pd Cost 41,829 41,830 38,373 38,378 45,013 45,018 45,012 45,019 51,276 51,283 51,273 45,020 45,910 83,659

Act Pd Cost 48,680 40,466 0 0 0 0 0 0 0 0 0 0 0 89,145

Variance, $ (6,851) 1,364 0 0 0 0 0 0 0 0 0 0 0 (5,486)

Variance, % -16.4% 3.3% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% -6.6%

Est FY Cumul 41,829 83,659 122,032 160,410 205,423 250,441 295,453 340,472 391,748 443,031 494,304 539,324 584,334

Act FY Cumul 48,680 89,145 0 0 0 0 0 0 0 0 0 0 0

% Complete 8.3% 15.3% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

Cumul Var, $ (6,851) (5,486) 0 0 0 0 0 0 0 0 0 0 0

Cumul Var. % -16.4% -6.6% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

t

o.,,~nrrrrre mnnSAC

U IVU'..UU

ITEM 01 02 03 04 05 06 07 08 09 10 11 12 13 Total

Est Pd Cost 69,482 69,483 58,857 80,786 91,405 91,411 91,405 91,412 101,982 101,990 101,980 91,414 91,400 138,965

Act Pd Cost 75,511 66,349 0 0 0 0 0 0 0 0 0 0 0 141,860

Variance, $ (6,029) 3,134 0 0 0 0 0 0 0 0 0 0 0 (2,895)

Variance, % -8.7% 4.5% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% -2.1%

Est FY Cumul 69,482 138,965 197,822 278,608 370,013 461,424 552,829 644,241 746,223 848,213 950,193 1,041,607 1,133,007

Act FY Cumul 75,511 141,860 0 0 0 0 0 0 0 0 0 0 0

% Complete 6.7% 12.5% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

Cumul Var, $ (6,029) (2,895) 0 0 0 0 0 0 0 0 0 0 0

Cumul Var, % -8.7% -2.1% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

TOTAL SYSTEM PERFORMANCE ASSESSMENT AND INTEGRATION (TSPAI)

01402.760

ITEM 01 02 03 04 05 06 07 08 09 10 11 12 13 Total

Est Pd Cost 118,702 113,734 98,060 109,681 131,276 131,286 131,275 131,287 149,616 149,632 149,612 131,292 131,275 232,436

Act Pd Cost 155,162 165,856 0 0 0 0 0 0 0 0 0 0 0 321,018

Variance, $ (36,460) (52,122) 0 0 0 0 0 0 0 0 0 0 0 (88,582)

Variance, % -30.7% -45.8% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% -38.1%

Est FY Cumul 118,702 232,436 330,496 440,177 571,453 702,739 834,014 965,301 1,114,917 1,264,549 1,414,161 1,545,453 1,676,728

Act FY Cumul 155,162 321,018 0 0 0 0 0 0 0 0 0 0 0

% Complete 9.3% 19.1% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

Cumul Var, $ (36,460) (88,582) 0 0 0 0 0 0 0 0 0 0 0

Cumul Var, % -30.7% -38.1% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

ACTIVITIES RELATED TO DEVELOPMENT OF THE NRC HIGH-LEVEL WASTE REGULATIONS TECHNICAL ASSISTANCE (ARDR)

01402.770

ITEM 01 02 03 04 05 06 07 08 09 10 11 12 13 Total

Est Pd Cost 13,246 13,247 10,677 12,028 14,893 14,900 14,893 14,900 16,930 16,937 16,929 14,900 14,893 26,493

Act Pd Cost 14,423 12,352 0 0 0 0 0 0 0 0 0 0 0 26,775

Variance,$ (1,177) 895 0 0 0 0 0 0 0 0 0 0 0 (282)

Variance, % -8.9% 6.8% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% -1.1%

Est FY Cumul 13,246 26,493 37,170 49,198 64,091 78,991 93,884 108,784 125,714 142,651 159,580 174,480 189,373

Act FY Cumul 14,423 26,775 0 0 0 0 0 0 0 0 0 0 0

% Complete 7.6% 14.1% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

Cumul Var, $ (1,177) (282) 0 0 0 0 0 0 0 0 0 0 0

CumuI Var. o -8.9% -1.1% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% .00% 0.0% 0.0% 0.0%

REPOSITORUY DEIG:I~N AIND I ITHERrL-VI=•rLnM14IkL M::FrrE I ý %n I l

UNSATURATED AND SATURATED FLOW UNDER ISOTHERMAL CONDITIONS (USFIC)

01402.880

ITEM 01 02 03 04 05 06 07 08 09 10 11 12 13 Total

Est Pd Cost 76,565 76,570 77,509 77,520 89,532 89,546 89,532 89,546 101,785 101,800 101,783 89,549 89,528 153,135

Act Pd Cost 71,447 86,963 0 0 0 0 0 0 0 0 0 0 0 158,410

Variance, $ 5,118 (10,393) 0 0 0 0 0 0 0 0 0 0 0 (5,275)

Variance, % 6.7% -13.6% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% -3.4%

Est FY Cumul 76,565 153,135 230,644 308,164 397,696 487,242 576,774 666,320 768,105 869,905 971,688 1,061,237 1,150,765

Act FY Cumul 71,447 158,410 0 0 0 0 0 0 0 0 0 0 0

% Complete 6.2% 13,8% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

Cumul Var, $ 5,118 (5,275) 0 0 0 0 0 0 0 0 0 0 0

Cumul Var, % 6.7% -3.4% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

RADIONUCLIDE TRANSPORT (RT)

01402.870

ITEM 01 02 03 04 05 06 07 08 09 10 11 12 13 Total

Est Pd Cost 40,573 40,575 35,306 35,311 40,568 40,576 40,566 40,577 46,193 46,206 46,193 40,580 40,565 81,148

Act Pd Cost 73,142 51,836 0 0 0 0 0 0 0 0 0 0 0 124,979

Variance, $ (32,569) (11,261) 0 0 0 0 0 0 0 0 0 0 0 (43,831).,

Variance, % -80.3% -27.8% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% -54.0%

Est FY Cumul 40,573 81,148 116,454 151,765 192,333 232,909 273,475 314,052 360,245 406,451 452,644 493,224 533,789

Act FY Cumul 73,142 124,979 0 0 0 0 0 0 0 0 0 0 0

% Complete 13.7% 23.4% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

Cumul Var, $ (32,569) (43,831) 0 0 0 0 0 0 0 0 0 0 0

Cumul Var, % -80.3% -54.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

REVIEW OF THE YUCCA MOUNTAIN DRAFT ENVIRONMENTAL IMPACT STATEMENT (DEIS)

01402.930

ITEM 01 02 03 04 05 06 07 08 09 10 11 12 13 Total

Est Pd Cost 47,968 47,969 48,321 48,442 48,319 0 0 0 0 0 0 0 . 0 95,937

Act Pd Cost 68,045 57,873 0 0 0 0 0 0 0 0 0 0 0 125,918

Variance, $ (20,077) (9,904) 0 0 0 0 0 0 0 0 0 0 0 (29,981)

Variance, % -41.9% -20.6% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% -31.3%

Est FY Cumul 47,968 95,937 144,258 192,700 241,019 241,019 241,019 241,019 241,019 241,019 241,019 241,019 241,019

Act FY Cumul 68,045 125,918 0 0 0 0 0 0 0 0 0 0 0

% Complete 28.2% 52.2% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

Cumul Var, $ (20,077) (29,981) 0 0 0 0 0 0 0 0 0 0 0

Cumul Var. % _ -41.9% - -31.3% - 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% - 0.0% 0.0% 0.0% 0.0%

PUBLIC OUTREACH

A1AA•9 OAA•

ITEM 01 02 03 04 05 06 07 08 09 10 11 12 13 Total

Est Pd Cost 8,437 8,438 6,898 6,900 8,673 8,676 8,673 8,676 10,090 10,094 10,090 8,677 8,668 16,875

Act Pd Cost 0 2,752 0 0 0 0 0 0 0 0 0 0 0 2,752

Variance, $ 8,437 5,686 0 0 0 0 0 0 0 0 0 0 0 14,123

Variance, % 100.0% 67.4% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 83.7%

Est FY Cumul 8,437 16,875 23,773 30,673 39,346 48,022 56,695 65,371 75,461 85,555 95,645 104,322 112,990

Act FY Cumul 0 2,752 0 0 0 0 0 0 0 0 0 0 0

% Complete 0.0% 2.4% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

Cumul Var, $ 8,437 14,123 0 0 0 0 0 0 0 0 0 0 0

Cumul Var, % 100.0% 83.7% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

DEVELOPMENT OF THE YUCCA MOUNTAIN REVIEW PLAN (YMRP)

01402.950

ITEM 01 02 03 04 05 06 07 08 09 10 11 12 13 Total

Est Pd Cost 117,471 117,472 101,808 101,813 118,292 118,299 118,291 118,299 135,175 135,188 135,168 118,300 118,277 234,943

Act Pd Cost 25,126 56,114 0 0 0 0 0 0 0 0 0 0 0 81,240

Variance, $ 92,345 61,358 0 0 0 0 0 0 0 0 0 0 0 153,703

Variance, % 78.6% 52.2% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 65.4%

Est FY Cumul 117,471 234,943 336,751 438,564 556,856 675,155 793,446 911,745 1,046,920 1,182,108 1,317,276 1,435,576 1,553,853

Act FY Cumul 25,126 81,240 0 0 0 0 0 0 0 0 0 0 0

% Complete 1.6% 5.2% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

Cumul Var, $ 92,345 153,703 0 0 0 0 0 0 0 0 0 0 0

Cumul Var, % 78.6% 65.4% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

TANK WASTE REMEDIATION SYSTEM (TWRS)

01403.000

ITEM 01 02 03 04 05 06 07 08 09 10 11 12 13 Total

Est Pd Cost 60,928 60,930 51,298 51,308 60,923 62,495 60,917 60,937 69,072 69,094 69,069 60,938 60,905 121,858

Act Pd Cost 48,460 43,899 0 0 0 0 0 0 0 0 0 0 0 92,358

Variance, $ 12,468 17,031 0 0 0 0 0 0 0 0 0 0 0 29,500

Variance, % 20.5% 28.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 24.2%

Est FY Cumul 60,928 121,858 173,156 224,464 285,387 347,882 408,799 469,736 538,808 607,902 676,971 737,909 798,814

Act FY Cumul 48,460 92,358 0 0 0 0 0 0 0 0 0 0 0

% Complete 6.1% 11.6% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

Cumul Var, $ 12,468 29,500 0 0 0 0 0 0 0 0 0 0 0

Cumul Var, % 20.5% 24.2% 0.0% 0.0% 0.0% 00.0% .0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% -______

DRY TRANSFER SYSTEM (DTS)

AIAO,'I 000

ITEM 01 02 03 04 05 06 07 08 09 10 11 12 13 Total

Est Pd Cost 37,856 37,789 28,660 8,149 10,132 4,571 0 0 0 0 0 0 0 75,645

Act Pd Cost 28,512 41,142 0 0 0 0 0 0 0 0 0 0 0 69,654

Variance, $ 9,344 (3,353) 0 0 0 0 0 0 0 0 0 0 0 5,991

Variance, % 24.7% -8.9% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 7.9%

Est FYCumul 37,856 75,645 104,305 112,454 122,586 127,157 127,157 127,157 127,157 127,157 127,157 127,157 127,157

Act FY Cumul 28,512 69,654 0 0 0 0 0 0 0 0 0 0 0

% Complete 22.4% 54.8% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

Cumul Var, $ 9,344 5,991 0 0 0 0 0 0 0 0 0 0 0

Cumul Var, % 24.7% 7.9% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

CENTRALIZED INTERIM STORAGE FACILITY (CISF)

01405.030

ITEM 01 02 03 04 05 06 07 08 09 10 11 12 13 Total

Est Pd Cost 12,299 11,379 9,378 9,380 11.378 11,380 11,378 11,446 12,771 12,052 11,862 10,404 11,074 23,678

Act Pd Cost 6,754 6.715 0 0 0 0 0 0 0 0 0 0 0 13,469

Variance, $ 5,545 4,664 0 0 0 0 0 0 0 0 0 0 0 10,209

Variance, % 45.1% 41.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 43.1%

Est FY Cumul 12,299 23,678 33,056 42,436 53,814 65,194 76,572 88,018 100,789 112,841 124,703 135,107 146,181

Act FY Cumul 6,754 13,469 0 0 0 0 0 0 0 0 0 0 0

% Complete 4.6% 9.2% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

Cumul Var, $ 5,545 10,209 0 0 0 0 0 0 0 0 0 0 0

Cumul Var, % 45.1% 43.1% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

PRIVATE FUEL STORAGE FACILITY (PFSF)

01405.040

ITEM 01 02 03 04 05 06 07 08 09 10 11 12 13 Total

Est Pd Cost 40,587 33,699 16,367 16,578 19,273 19,279 19,273 19,279 9,278 9,285 9,278 19,279 18%929 74,286

Act Pd Cost 23,289 31,243 0 0 0 0 0 0 0 0 0 0 0 54,532

Variance, $ 17,298 2,456 0 0 0 0 0 0 0 0 0 0 0 19,754

Variance, % 42.6% 7.3% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 26.6%

Est FY Cumul 40,587 74,286 90,653 107,231 126,504 145,783 165,056 184,335 193,613 202,898 212,176 231,455 250,384

Act FY Cumul 23,289 54,532 0 0 0 0 0 0 0 0 0 0 0

% Complete 9.3% 21.8% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

Cumul Var, $ 17,298 19,754 0 0 0 0 0 0 0 0 0 0 0

Cumul Var, % 42.6% 26.6% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

MKT 101

2HD fiB FFormatted F.tmIte

Aw

4¾ 4 MO / 7

alad-/7'cd /1;1-1/1o 77'