december 18, 2007 tptf early delivery systems status daryl cote
TRANSCRIPT
December 18, 2007
TPTF
Early Delivery SystemsStatus
Daryl Cote
2TPTF12/17/2007 2
EDS Status Update
2007 2008
SCED R5.1 SCED R5.3: RT ICCP SCED R5.4: LMP Post
Sep Oct Nov Dec Jan Feb
SCED R5.2
ICCP Fail-over / P2P
R3: SE / Telemetry Criteria (SE Tuning)
R4: NOMCR / Network Model verification
E1 R2
E2 R3
E2 R4
E3 R5
E3 R6 LFC R6.1: ACE
E3 R7 CRR R7.1
E4 R9 R9
6-month LMP Posting
SE Verification
RT ICCP
NOMCR Checkout Network Model Verification
EDS 1 Exit Criteria % of MPs
% of Points
Comments
MPs have completed PtP checkout and topology review for all submitted Nodal points (MP5)
95%(95%)
99%(99%)
XTend having link problems, RCEC completed 1st phase. Adding Magic Valley (Q1 ‘08) and College Station (Jan ’08) – approximately 1000 points.
ERCOT has completed local failover testing with each MP (MP6) 87%(84%)
n/a Tenaska, AEP QSE in 12/07, BTU and Xtend in 01/08.
ERCOT has completed Alarm Processing Configuration and testing
n/a 10% Alarm processing testing will be phased by category and systems availability.
ERCOT has completed all PtP process documentation to support checkout for new construction / future changes to telemetry
95% n/a Final process handoff and transition to Operations will occur by year end.
Outstanding ICCP issues <= 3% per MP (MP5) 100%(80%)
n/a Overall error rate ~1%. 9 MPs are at a 0% error rate. 15 MPs tested are at or below 1% error rate.
Quality Code Retesting (MP5) 100%(92%)
n/a 36 of 36 MPs regression tested with quality code fix.
Reporting
Legend: % in parentheses are from the 11/26 TPTF update
3TPTF12/17/2007 3
Alarm Processing Approach – Expected Delivery Schedule
Implementation• EDS 1 by 12/15• EDS 2 by 1/15• EDS 3 by 2/15
MPs• OnCor• CenterPoint• Reliant• Luminant
Participants will perform limit testing and work with ERCOT to verify procedures.
# Category Name Definition EDSPro
cedure
s Cre
ated
Teste
d by
Ops Support
Teste
d by
Operat
ors
Teste
d by
MPs
1 Frequency DeviationWhen frequency deviation is above the RRS recovery limits 3 xWhen RRS is deployed partially and frequency deviation above RRS limit 3 x
If the real time frequency is above defined threshold 3 x
When reserve capacity is below Operator specified limits 3 xWhen un-deployed regulation-up is below Operator entered threshold 3When un-deployed regulation-down is below Operator entered threshold 3When telemetered HSL is higher than Net Dependable Capability 3
When difference between HASL and total energy req < Operator threshold 3When the difference between HDL sum and total energy req < Operator threshold 3If scheduled LAAR and RT LAAR are differed by threshold 3 xNeed to send selected alarms to MIS 3
System Operating Limits When SOL is more than 95% of the limit specified 2 xSCADA and SE Overloads When MVA line or trans flow > 98% dynamic emer rating or 100% normal rating 2
When RT flow close to 95% of SPS triggering condition 2 xIf real time status of SPS goes disabled, alarms shall be generated 2When 345Kv bus voltages are outside specified limits 2 xWhen 138/69 Kv bus voltages are outside specified limits 2 x
4 Resource Control Errors When RE (Resource Error) is outside the limits defined by the Operator 3 x
Forced line/transformer outages for 345Kv 2 x
Forced Bus outages for 345Kv 2 x
Planned line/transformer outages for 345Kv 2 x
Planned Bus outages for 345Kv 2 xSwitching Device Status When 345Kv/unit breakers change status 1 x Start 12/17
Forced line/transformer outages for 138/69Kv 2 x
Forced Bus outages for 138/69Kv 2 x
Planned line/transformer outages for 138/69Kv 2 x
Planned Bus outages for 138/69Kv 2 x
When 138Kv/unit breakers change status 1 x Start 12/17When 69Kv/unit breakers change status 1 x Start 12/17
Forced Outage Detector When FOD detects Forced unit outages 2 xPlanned Outage When FOD detects Planned unit outages 2 x
ICCP Link 1 x
TCM, Dynamic Ratings, SE, NSA, PI 2
LFC, SCED, VSAT, TSAT, FOD 3System Status Generate system alarms for, Site Failover, EMS failover, MMS failover 3 x
EMS Security For unauthorized logins to EMS system 2
Application Status8
Switching Device Status
7
6
Forced Outage Detector
Planned Outage
SPS3
Voltage Limits
Forced Outage Detector
5Planned Outage
2 Ancillary Service Capacity
1 Frequency Deviation
4TPTF12/17/2007 4
R4: NOMCR / Network Model verification
Release 3 – State Estimator and Telemetry
2007 2008
SCED R5.1 SCED R5.3: RT ICCP SCED R5.4: LMP Post
Sep Oct Nov Dec Jan Feb
SCED R5.2
ICCP Fail-over / P2P
R3: SE / Telemetry Criteria (SE Tuning)
E1 R2
E2 R3
E2 R4
E3 R5
E3 R6 LFC R6.1: ACE
E3 R7 CRR R7.1
E4 R9 R9
6-month LMP Posting
SE Verification
RT ICCP
NOMCR Checkout Network Model Verification
EDS 2 Release 3 Exit Criteria % Complete
Comments
TSP/QSE data points reasonably conform to Telemetry Performance criteria
40% SCADA Mappings for Generation in progress – see next slide324 unobservable points (communicated to TSPs) + ~170 loads to be mapped by ERCOT; polarity correction with one TSPQuality of MW and GMW provided by QSEs remains at ~40%
ERCOT Operations have operating procedures in place to address performance issues
30%(30%)
8 of 27 procedures have been updated. The remaining will be completed when Release 3 processes are verified.
Network Security Analysis functions are verified and ERCOT Operations have procedures in place to manage
76%(76%)
SE STAT is 95% tested; Contingency Analysis is 95% tested; Dynamic Ratings is 30% tested; RTMONI is 90% tested.
ERCOT SE is tuned and meets performance criteria 50%(9%)
See detailed slide for SE Convergence rates over time.MW/MVar tolerance is 50, SE convergence varies.
Load Modeling restructured, load adaptation and bus load forecast verified
50%(25%)
Schedules have been successfully load and have been verified. Load Adaptation cannot be tested until a bug is fixed.
EDW reports correctly post to MIS and can be accessed 0% SE and Performance Report Schedule is being re-planned.
EDW reports have been verified within ERCOT and by MPs 0% Telemetry and State Estimator standards in stakeholder process.
Reporting
Legend: % in parentheses are from the 11/26 TPTF update
5TPTF12/17/2007 5
EDS 2 – Generation Verification Status
Verifying the following: Breaker Status Combine-cycle Configuration High Emergency Limit High Sustained Limit Low Emergency Limit Low Sustained Limit Plant Auxiliary Load Resource Status
‘Complete’ indicates ERCOT mapping is complete and does not reflect data quality
6TPTF12/17/2007 6
Release 3 – State Estimator Convergence Rate Status
Convergence Rate
0.0010.0020.0030.0040.0050.0060.0070.0080.0090.00
100.00
Novem
ber 2
6th
Novem
ber 2
7th
Novem
ber 2
8th
Novem
ber 2
9th
Novem
ber 3
0th
Decem
ber 1
st
Decem
ber 2
nd
Decem
ber 3
rd
Decem
ber 4
th
Decem
ber 5
th
Decem
ber 6
th
Decem
ber 7
th
Decem
ber 8
th
Decem
ber 9
th
Decem
ber 1
0th
Decem
ber 1
1th
Decem
ber 1
2th
Convergence
Co
nve
rgen
ce P
erce
nta
ge
0
50
100
150
200
250
300
350
To
lera
nce
Convergence Rate (%) Tolerance
No Convergence due to System Problems
7TPTF12/17/2007 7
EDS 2 – State Estimator and Telemetry Criteria
Telemetry Criteria Status Comment
Data Quality (MW/MVar Tolerance) At 50 Standard is 15 MV/MVar
Telemetry Availability tbd Need EDW Report
Critically Important Telemetry tbd Need EDS Report
Availability for Critically Important Telemetry tbd Need EDW Report
Requests for Redundant Telemetry tbd Need Critical Measurement functionality
State Estimator Criteria Status Comment
SE Convergence Stable at 50MW variance when application is running (e.g. not down due to hardware or database loads)
Transmission Element SE Accuracy tbd Need EDW Report
Critical Transmission Element SE Accuracy tbd Need EDW Report
Critical Bus Voltage Accuracy tbd Need EDW Report
SCADA Measurement Accuracy tbd Need EDW Report
Status of SE and Telemetry Criteria
8TPTF12/17/2007 8
Observability Status
Observability Status
Oncor 147 104 Y Y N N N N 12/31/2007 Initial response receivedAEP 134 134 Y Y N N N N tbd Initial response. Sent e-mailTexas New Mexico Power 22 22 Y Y N N N N 12/15/2007 Questions resolved.STEC 16 4 Y Y N N N N 12/15/2007 Questions resolved.Rayburn Country Electric 15 15 Y Y N N N N 12/15/2007 Initial response receivedLCRA 15 15 Y Y Y N N N 12/10/2007 Questions resolved.Brownsville 11 11 Y Y N N N N 12/15/2007 Resent dataCenterPoint Energy 11 11 Y Y N N N N 12/15/2007 Initial response. Sent e-mailBrazos 10 8 Y Y Y N N N 12/15/2007 Initial response received
Total Points 381 32485%
Observability Status147
134
22 16 15 15 11 11 10
104
134
22
415 15 11 11 8
0
20
40
60
80
100
120
140
160
TSP
Po
ints
(N
o.)
Number of points
Revised number of points
Status as of 12/14
9TPTF12/17/2007 9
Release 4 – NMMS / NOMCR
2007 2008
SCED R5.1 SCED R5.3: RT ICCP SCED R5.4: LMP Post
Sep Oct Nov Dec Jan Feb
SCED R5.2
ICCP Fail-over / P2P
R3: SE / Telemetry Criteria (SE Tuning)
R4: NOMCR / Network Model verification
E1 R2
E2 R3
E2 R4
E3 R5
E3 R6 LFC R6.1: ACE
E3 R7 CRR R7.1
R9
6-month LMP Posting
SE Verification
RT ICCP
NOMCR Checkout Network Model Verification
EDS 2 Release 4 Entry Criteria % Complete
Comments
NMMS Phase 2A has completed FAT Testing 0% Planned release of NMMS 2A on January 2, 2008
MIS/NMMS link has completed ITest and is installed in EDS 47%(25%)
9 of 17 TSPs have successfully connected through Citrix to notepad (not all the way to NMMS)
NMMS is installed in EDS 0% Hardware build in progress
EMS Nodal Importer has completed ITest and is installed in EDS 0% EMS 4 FAT end scheduled for 2/15; will not migrate to EDS until MMS importer also available
NMMS database has been successfully loaded with:•ERCOT NOM database; ICCP modeling point database; Ownership / operatorship data
0% Currently working with TSPs/MPs (and ERCOT working groups) on data information for loading. Waiting on NMMS 2A delivery to install and configure data
NMMS database is placed under full change control 0% Once data is loaded and verified by MPs, DB will be under ERCOT change control.
Reporting
Any direct communication with John Hall or John Webb should be sent to [email protected] effective immediately
Legend: % in parentheses are from the last update
10TPTF12/17/2007 10
Release 5 - SCED
2007 2008
SCED R5.1 SCED R5.3: RT ICCP SCED R5.4: LMP Post
Sep Oct Nov Dec Jan Feb
SCED R5.2
ICCP Fail-over / P2P
R3: SE / Telemetry Criteria (SE Tuning)
R4: NOMCR / Network Model verification
E1 R2
E2 R3
E2 R4
E3 R5
E3 R6 LFC R6.1: ACE
E3 R7 CRR R7.1
E4 R9 R9
6-month LMP Posting
SE Verification
RT ICCP
NOMCR Checkout Network Model Verification
EDS 3 Release 5 Exit Criteria % Complete
Comments
QSEs w/ Resources able to submit COP & TPO for entire portfolio
100% •Known issues with Output Schedules and Performance issues (root cause analysis done on performance issues and passed to teams)
SCED Inputs verified: HRL, LRL, SURAMP, SDRAMP, HDL, LDL; GTBD, ICCP
40%(40%)
See next slide
SCED Outputs verified: QSE’s ability to receive Resource Base Points and LMPs via ICCP
10%(10%)
Verifications began November 1st. A number of QSEs have reported receiving Base Points and LMPs – ERCOT reviewing SCADA mapping.
Base Point and LMP calculation verified for Resources with Offer Curves or Output Schedules
0% Verifications to begin in January.
Reports 50%(0%)
Reports related to SCED are available in draft form on MIS and nodal.ercot.com
LMPs verified for Reasonability and posted to MIS for Market Participant review 0%
See next slide
Reporting
Legend: % in parentheses are from the 10/22 TPTF update
11TPTF12/17/2007 11
SCED Issues
1. EMS Hardware insufficient for user base and functionality– INF prioritized production hardware for EMS – will use for EMS 3B
2. SCADA mapping resulted in all Combined Cycles MW telemetry levels set to 0– Corrected in SCADA load on Friday 12/14; still needs to be verified
3. Interface table for Constraint Names incorrect so SCED is not able to process constraint names & shift factors
4. MPs sending Incorrect values for CC configuration causes SCED failure– Working with EMS team to implement data check and MPs to send valid
configuration values5. MPs sending HSL < LSL resulting in SCED failure
– Working with MPs to resolve and adding validation in EMS to set LSL = HSL when telemeter HSL<LSL
6. MPs sending resource status of off when actual telemeter MW output is > 0– SCED sets basepoint = 0
7. MPs sending invalid resource status (e.g. 050)– SCED ignores the unit
8. DC TIE Telemetry missing and DC Tie calculation not working– Adding telemetry and EMS team resolving calculation function
Joint effort between ERCOT and MPs to resolve most of these will enable reasonableness declaration
12TPTF12/17/2007 12
Release 6 - LFC
2007 2008
R5.3 SCED R5.4: LMP Post
Jan Feb Mar Apr May Jun
R4: NOMCR / Network Model verificationE2 R4
E3 R5
E3 R6 R6.1: ACE
E3 R7 R7.1
E4 R9
6-month LMP Posting
EDS 3 Release 6.1 Entry Criteria % Complete
Comments
ICCP and the Generation Subsystem (LFC, RLC and Resource Qualification Testing) has passed FAT and completed acceptable portions of the ITEST.
0% EMS 3B FAT expected to complete 12/21 (revised from 12/7)
ERCOT has validated that the RLC outputs and Emergency Base Point calculator values are calculated in the ERCOT Nodal system as expected per the Nodal EMS Design documents.
0% Same as above
QSEs with Resources have submitted the 6.1 test form to ERCOT
0% ERCOT expects to distribute the form on January 2. QSEs complete the form and send it back to ERCOT 2 business days before their scheduled 6.1 testing date.
Legend: % in parentheses are from the 10/22 TPTF update
R6.2: QSE Testing R6.3: TST
R7.2 R7.3 R7.4
Any direct correspondence with Brain Davison should be directed to [email protected] effective immediately
13TPTF12/17/2007 13
EDS 3 – LFC Testing Schedule
14TPTF12/17/2007 14
EDS 3 – LFC Testing Schedule
15TPTF12/17/2007 15
Release 7 - CRR
• Kick-off meeting scheduled for January 18th from 1-3pm– http://www.ercot.com/calendar/2008/01/20080118-EDS3.html
• Working on 7.0 activities– Discrepancies between CRR Account Holder forms and emails
to eds3 indicating intention to participate• See next slide
• Planning to present an updated version of CRR handbook to TPTF at the January 21-23rd meeting. Updated version available at http://nodal.ercot.com/docs/pd/eds/index.html#oth
16TPTF12/17/2007 16
Release 7 - Participants
17TPTF12/17/2007 17
EDS 4 – Release 9.1
• MMS, EIP, and INT teams working aggressively to support a January 15th start of Release 9.1– Will schedule support calls similar to SCED– Might have to start with QSEs desiring to use Web Services first
if ERCOT developed UI not available by January 15th • Scheduled a Release 9.1 kick-off WebEx for Thursday 12/20
from 9-11 am: http://www.ercot.com/calendar/2007/12/20071220-EDS4.html
• Significant number of QSEs have missed deadline to submitted intent emails to [email protected].– See next slide
18TPTF12/17/2007 18
EDS 4 Release 9
• QSEs expected for EDS4, but not yet registered
– Affordable Power Plan– Alcoa Power Marketing– Alliance Power Company– Ambit Energy– Ambridge Energy– Amigo Energy– Andeler Corporation– APN Starfirst– APNA Holding– Aquila – Barclays Bank– Bear Energy– Blu Power of Texas– Brilliant Energy
– Cargill Power Markets– Citadel Energy Products– Clearview Electric– ConocoPhillips Company– Constellation NewEnergy– DPI Energy– Duke Energy Ohio– Eagle Energy Partners– Econnergy Energy Company– Electric Now– First Choice Power– Formosa Utility Venture– Freedom Power– Fulcrum Power Service– Glacial Energy– Himalaya Power
19TPTF12/17/2007 19
EDS4 Release 9
• QSEs expected for EDS4, but not yet registered (continued)
– Integrys Energy Services– JP Morgan Ventures Energy
Corporation– Just Energy Texas– Kansas City Power and Light– Keystone Energy Partners– Lehman Brothers Commodity Services– Liberty Power– Merrill Lynch Commodities– Mirant Energy Trading– National Power Company– North American Energy Credit and
Clearing Delivery– NRG– ONPAC Energy– PEPCO Energy Services– Pre Buy Electric– Repower
– Scurry County Wind– Sitara Energy– Spark Energy– Stream Gas and Electric– Tara Energy– Texas Retail Energy– Texas Star Energy– Texpo Energy– Topaz Power Management– Trieagle Energy Supply– Urban Energy Source– Viasyn– WCW International– Xtend Energy
20TPTF12/17/2007 20
Questions?