Smart City Challenge Demonstration Quarterly Report: 2018 4th Quarter (October 2018 – December 2018) 1
Smart Columbus Quarterly Progress Report
4th Quarter of 2018
Contents
Award Information ................................................................................................................................................................. 2
Report Information ................................................................................................................................................................. 2
Project Scope ............................................................................................................................................................................. 2
Items of Note ............................................................................................................................................................................. 2
Financial Status ........................................................................................................................................................................ 3
Invoices Submitted ................................................................................................................................................................. 8
Schedule Update..................................................................................................................................................................... 11
Key Activities / Accomplishments .................................................................................................................................. 15
Leveraged Partner Resources Status Summary ........................................................................................................ 31
Schedule Update..................................................................................................................................................................... 32
Risk Status ................................................................................................................................................................................ 33
Issues/Concerns/ Other ..................................................................................................................................................... 34
Smart City Challenge Demonstration Quarterly Report: 2018 4th Quarter (October 2018 – December 2018) 2
Quarterly Progress Report
Award Information
Title Award # Awardee
Smart City Challenge Demonstration
DTFH6116H00013 City of Columbus
Report Information
Date Submitted Submitted To Period Covered by Report
January 30, 2019
Sarah Tarpgaard
Kate Hartman
October 2018 – December 2018
Project Scope
Scope Statement
The Smart City Challenge Demonstration intends to improve the access of residents of Columbus through alleviating transportation challenges. To accomplish this task, Smart Columbus will develop intelligent transportation solutions using engineering systems of planning, design, implementation/deployment, and demonstration. The projects that Smart Columbus is demonstrating are divided into the themes below:
Smart Columbus Operating System Enabling Technologies
o Connected Vehicle Environment Enhanced Human Services
o Multi-Modal Trip Planning Application/Common Payment System o Smart Mobility Hubs o Mobility Assistance o Prenatal Trip Assistance o Event Parking Management
Emerging Technologies o Connected Electric Automated Vehicles o Truck Platooning
Items of Note
Conducted Operating System Public Webinar on 10/10/2018
Conducted Smart Mobility Hubs System Requirements Public Webinar on 10/24/2018
Conducted CVE System Requirements Public Webinar on 11/5/2018
Conducted Prenatal Trip Assistance ConOps Public Webinar on 11/14/2018
Conducted EPM System Requirements Public Webinar on 11/15/2018
Conducted CPS System Requirements Public Webinar on 11/28/2018
Smart City Challenge Demonstration Quarterly Report: 2018 4th Quarter (October 2018 – December 2018) 3
Financial Status
Task Financial Summary: August 30, 2016 – March 31, 2018*
*Total different from previously reported amount due to an inadvertent formula error. Task Financial Summary is as was reported in January 2018 – March 2018 Quarterly Report.
Task Financial Summary: April 1, 2018 – Current
Budget Costs To Date Remaining Budget Costs to Date Remaining Budget Costs To Date Remaining
1 Program Management $4,086,645.00 $2,686,147.92 $1,400,497.08 $8,000,000.00 $0.00 $8,000,000.00 $12,086,645.00 $2,686,147.92 $9,400,497.08
2 Communications and Outreach $3,369,998.00 $731,538.52 $2,638,459.48 $0.00 $0.00 $0.00 $3,369,998.00 $731,538.52 $2,638,459.48
3
Enabling Technologies
(Integration) $2,813,720.00 $100.00 $2,813,620.00 $0.00 $0.00 $0.00 $2,813,720.00 $100.00 $2,813,620.00
3a
Connected Columbus
Transportation Network
(CCTN) $17,130,004.00 $351,492.49 $16,778,511.51 $0.00 $0.00 $0.00 $17,130,004.00 $351,492.49 $16,778,511.51
3b Integrated Data Exchange (IDE) $3,077,209.00 $1,219,156.51 $1,858,052.49 $8,000,000.00 $11,613.57 $7,988,386.43 $11,077,209.00 $1,230,770.08 $9,846,438.92
4a Residential District $2,739,632.00 $370,653.69 $2,368,978.31 $0.00 $0.00 $0.00 $2,739,632.00 $370,653.69 $2,368,978.31
4b Commercial District $925,375.00 $127,261.52 $798,113.48 $3,000,000.00 $0.00 $3,000,000.00 $3,925,375.00 $127,261.52 $3,798,113.48
4c Logistics $4,908,384.00 $201,235.44 $4,707,148.56 $0.00 $0.00 $0.00 $4,908,384.00 $201,235.44 $4,707,148.56
4d Downtown District $949,033.00 $274,395.59 $674,637.41 $0.00 $0.00 $0.00 $949,033.00 $274,395.59 $674,637.41
$40,000,000.00 $5,961,981.68 $34,038,018.32 $19,000,000.00 $11,613.57 $18,988,386.43 $59,000,000.00 $5,973,595.25 $53,026,404.75
Task Financial Summary
Task
Federal Share Cost Share Total
Totals
Budget Costs To Date Remaining Budget Costs To Date Remaining Budget Costs to Date Remaining Budget Costs to Date Remaining Budget Costs To Date Remaining
$3,520,163 $1,013,279 $2,506,884 $0 $0 $0 $0 $0 $0 $0 $0 $0 $3,520,163 $1,013,279 $2,506,884
$1,369,348 $177,045 $1,192,303 $0 $0 $0 $0 $0 $0 $0 $0 $0 $1,369,348 $177,045 $1,192,303
$167,000 $25,573 $141,427 $0 $0 $0 $0 $0 $0 $0 $0 $0 $167,000 $25,573 $141,427
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
$100,000 $0 $100,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $100,000 $0 $100,000
$3,240,989 $0 $3,240,989 $2,759,011 $0 $2,759,011 $0 $0 $0 $4,000,000 $0 $4,000,000 $10,000,000 $0 $10,000,000
$840,000 $0 $840,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $840,000 $0 $840,000
$0 $0 $0 $700,989 $0 $700,989 $0 $0 $0 $0 $0 $0 $700,989 $0 $700,989
$65,000 $8,000 $57,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $65,000 $8,000 $57,000
$500,000 $0 $500,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $500,000 $0 $500,000
$450,000 $0 $450,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $450,000 $0 $450,000
$2,187,500 $0 $2,187,500 $0 $0 $0 $910,310 $0 $910,310 $0 $0 $0 $3,097,810 $0 $3,097,810
$0 $0 $0 $0 $0 $0 $2,127,000 $0 $2,127,000 $0 $0 $0 $2,127,000 $0 $2,127,000
$14,060,937 $5,378,079 $8,682,858 $2,100,000 $886,016 $1,213,984 $0 $0 $0 $0 $0 $0 $16,160,937 $6,264,095 $9,896,842
$10,400,000 $2,918,741 $7,481,259 $0 $0 $0 $2,261,690 $437,239 $1,824,451 $0 $0 $0 $12,661,690 $3,355,980 $9,305,710
$0 $0 $0 $0 $0 $0 $1,701,000 $0 $1,701,000 $0 $0 $0 $1,701,000 $0 $1,701,000
$663,000 $0 $663,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $663,000 $0 $663,000
$1,000,000 $0 $1,000,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $1,000,000 $0 $1,000,000
$260,000 $46,100 $213,900 $0 $0 $0 $0 $0 $0 $0 $0 $0 $260,000 $46,100 $213,900
$100,000 $7,992 $92,008 $300,000 $0 $300,000 $0 $0 $0 $0 $0 $0 $400,000 $7,992 $392,008
$1,076,063 $854,070 $221,993 $2,140,000 $172,143 $1,967,857 $0 $0 $0 $0 $0 $0 $3,216,063 $1,026,213 $2,189,850
$40,000,000 $10,428,880 $29,571,120 $8,000,000 $1,058,158 $6,941,842 $7,000,000 $437,239 $6,562,761 $4,000,000 $0 $4,000,000 $59,000,000 $11,924,277 $47,075,723
Communications & Outreach
MMTPA/CPS
Indirect Costs
General Program Management: City Travel
General Program Management: City Equipment
General Program Management: City Supplies
CITY LABOR
OTHER DIRECT COSTS
Direct Labor
Smart Columbus Operating System
Connected Vehicle Environment (CVE)
Task Financial Summary -- April 1, 2018 -- Current
Task
Federal Share Franklin County - Cost Share TotalODOT - Cost ShareCity of Columbus - Cost Share
Totals
Smart Mobility Hubs
Mobility Assistance
Prenatal Trip Assistance
Event Parking Management
Truck Platooning
Procured Miscellaneous Service
Procured Communications Services (Engage)
Systems Engineeering Expertise (ALE)
Procured Technical Services (CV Applications)
Procured Technical Services (Prenatal Trip)
Procured Information Technology Services (MMTPA/CPS)
Procured Information Technology Services (SCOS Only)
Procured Technical Services (Consulted Support Services/Program Manager)
General Program Management: Subconsultants
Connected Electric Vehicles
Smart City Challenge Demonstration Quarterly Report: 2018 4th Quarter (October 2018 – December 2018) 4
Costs Incurred vs Budgeted Costs
Costs Incurred vs. Budgeted Costs
FEDERAL SHARE COST SHARE TOTAL Current Quarter Cumulative
Current Quarter Cumulative
Current Quarter Cumulative
Costs Incurred $1,873,070 $10,428,880 $651,306 $1,495,397 $2,524,376 $11,924,277
Budgeted $2,133,867 $40,000,000 $914,514 $19,000,000 $3,048,381 $59,000,000
Difference $260,796 $29,571,120 $263,209 $17,504,603 $524,005 $47,075,723
Costs Incurred vs Obligated Federal Funding
Cost Share Contributors
Costs Incurred to Date
Obligated Funding to Date
Remaining Obligated Funding to Date
Funding Subject to Availability
$19,571,120
$10,000,000
Cumulative
Costs Incurred vs. Obligated Federal Funding
FEDERAL SHARE
$10,428,880
$30,000,000
CONTRIBUTOR BUDGETED
CURRENT
QUARTER CUMULATIVE REMAINING
City of Columbus $8,000,000 $533,330 $1,058,158 $6,941,842
ODOT $7,000,000 $117,976 $437,239 $6,562,761
Franklin County $4,000,000 $0 $0 $4,000,000
TOTAL $19,000,000 $651,306 $1,495,397 $17,504,603
Cost Share Contribution
Smart City Challenge Demonstration Quarterly Report: 2018 4th Quarter (October 2018 – December 2018) 5
Direct Labor Hours Worked
Budget vs Cost to Date Summary
Note: Graph reflects budget adjustment effective April 2018 and all USDOT approved expenses (federal and cost share).
Name TITLE/Job Classification
Current
Quarter Cumulative
Mandy Bishop Program Manager 235.00 1757.50
Ryan Bollo Project Manager 258.50 3111.00
Randy Bowman Deputy Program Manager 0.00 1516.00
Brandi Braun Communications 134.00 1475.00
Aparna Dial Program Manager 0.00 587.00
Abbie L. Green Fiscal Assistant I 442.50 2559.25
Kevin McSweeney Management Analyst II 0.00 463.00
Jeff Ortega Communications 0.00 267.50
Kevin Retta Student Intern 0.00 1429.00
Sonja Summer Student Intern 251.00 2266.50
Brandi A. Vance Management Analyst I 354.50 2579.40
Andrew Wolpert Deputy Program Manager 479.00 3628.00
Jodie Bare Deputy Program Manager 476.00 2092.00
Alyssa Chenault Communications Manager 462.00 1110.00
3092.50 24841.15TOTAL
Smart City Challenge Demonstration Quarterly Report: 2018 4th Quarter (October 2018 – December 2018) 6
Costs Incurred by Cost Element
Estimated Cost to Complete
Current Quarter Cumulative Current Quarter Cumulative Current Quarter Cumulative
City of Columbus
Direct Labor $127,378 $1,013,279 $0 $0 $127,378 $1,013,279
Fringe Benefits and Insurance Costs $22,578 $177,045 $0 $0 $22,578 $177,045
Travel $2,041 $25,573 $0 $0 $2,041 $25,573
Subcontractor Costs - HNTB* $0 $5,242,347 $434,783 $886,016 $434,783 $6,128,362
Subcontractor Costs - Engage $0 $854,070 $98,547 $172,143 $98,547 $1,026,213
Subcontractor Costs - Proteon $162,908 $567,503 $0 $0 $162,908 $567,503
Subcontractor Costs - A.L.E. $10,160 $46,100 $0 $0 $10,160 $46,100
Subcontractor Costs - Battelle $20,570 $59,418 $0 $0 $20,570 $59,418
Subcontractor Costs - Pillar $1,434,518 $2,291,819 $0 $0 $1,434,518 $2,291,819
Subcontractor Costs - Michael Baker $76,925 $135,733 $0 $0 $76,925 $135,733
Subcontractor Costs - AbleLink $7,992 $7,992 $0 $0 $7,992 $7,992
Other Direct Costs - Mobility Assistance $8,000 $8,000 $0 $0 $8,000 $8,000
Ohio DOT $0 $0 $117,976 $437,239 $117,976 $437,239
Franklin County $0 $0 $0 $0 $0 $0
TOTAL $1,873,070 $10,428,880 $651,306 $1,495,397 $2,524,376 $11,924,277
Costs Incurred by Cost Element
TOTALFEDERAL SHARE COST SHARE
*Does not include $89,231.24 in USDOT Disallowed expenses
COST ELEMENT
Original Total
Budget Costs To Date Remaining
Estimated
Changes Needed
to Budget
Estimated Cost
to Complete
Project
$3,520,163 $1,013,279 $2,506,884 $0 $2,506,884
$1,369,348 $177,045 $1,192,303 $0 $1,192,303
$167,000 $25,573 $141,427 $0 $141,427
$0 $0 $0 $0 $0
$0 $0 $0 $0 $0
$0 $0 $0 $0 $0
$100,000 $0 $100,000 $0 $100,000
$10,000,000 $0 $10,000,000 $0 $10,000,000
$840,000 $0 $840,000 $0 $840,000
$700,989 $0 $700,989 $0 $700,989
$65,000 $8,000 $57,000 $0 $57,000
$500,000 $0 $500,000 $0 $500,000
$450,000 $0 $450,000 $0 $450,000
$3,097,810 $0 $3,097,810 $0 $3,097,810
$2,127,000 $0 $2,127,000 $0 $2,127,000
$16,160,937 $6,264,095 $9,896,842 $0 $9,896,842
$12,661,690 $3,355,980 $9,305,710 $0 $9,305,710
$1,701,000 $0 $1,701,000 $0 $1,701,000
$663,000 $0 $663,000 $0 $663,000
$1,000,000 $0 $1,000,000 $0 $1,000,000
$260,000 $46,100 $213,900 $0 $213,900
$400,000 $7,992 $392,008 $0 $392,008
$3,216,063 $1,026,213 $2,189,850 $0 $2,189,850
$59,000,000 $11,924,277 $47,075,723 $0 $47,075,723
Procured Communications Services (Engage)
Totals
Procured Information Technology Services (MMTPA/CPS)
Procured Technical Services (Prenatal Trip)
Procured Technical Services (CV Applications)
Systems Engineeering Expertise (ALE)
Procured Miscellaneous Service
Connected Electric Vehicles
Truck Platooning
GENERAL PROGRAM MANAGEMENT: SUBCONSULTANTS
Procured Technical Services (Consulted Support Services/Program Manager)
Procured Information Technology Services (SCOS Only)
Event Parking Management
Smart Mobility Hubs
OTHER DIRECT COSTS
General Program Management: City Travel
General Program Management: City Equipment
General Program Management: City Supplies
Communications & Outreach
Smart Columbus Operating System
Connected Vehicle Environment (CVE)
MMTPA/CPS
Mobility Assistance
Prenatal Trip Assistance
Estimated Cost to Complete Project
CITY LABOR
Direct Labor
Indirect Costs
Smart City Challenge Demonstration Quarterly Report: 2018 4th Quarter (October 2018 – December 2018) 7
DBE Update
Company
Original
Contract
Amount
Modification/
Additional
Amounts
Total Contract
Amount
Amount Paid
To Date
Minimum
DBE Goal DBE Spend
DBE
Spend %
(DBE
Spend /
Invoiced
Amount)
1 HNTB $400,000 $6,400,000 $6,800,000 $6,217,594 15.00% $15,715 0.25%
2 Engage $125,000 $1,029,035 $1,154,035 $1,026,213 15.00% $916,589 89.32%
3 Proteon $18,500 $648,204 $666,704 $567,503 15.00% $0 0.00%
4 A.L.E. $19,300 $238,010 $257,310 $46,100 15.00% $46,100 100.00%
5 Battelle $287,083 $0 $287,083 $59,418 15.00% $0 0.00%
6 Pillar $2,500,000 $2,500,000 $5,000,000 $2,291,819 15.00% $0 0.00%
7 Michael Baker $789,413 $0 $789,413 $135,733 15.00% $0 0.00%
8 AbleLink $29,970 $0 $29,970 $7,992 15.00% $0 0.00%
$4,169,267 $10,815,249 $14,984,516 $10,352,372 15.00% $978,404 9.45%
DBE Update
Totals
Smart City Challenge Demonstration Quarterly Report: 2018 4th Quarter (October 2018 – December 2018) 8
Invoices Submitted Invoice # $ Amount Date Notes/Comments
1 $200,506.41 5/18/2017 Second submission for original rejected amount. Payment received 5/30/17.
2 $574,229.54 6/6/2017 This request was submitted for 574,229.54 but was approved for 574,299.54. The difference will be included on the next submission. Payment received 6/16/17.
3 $689,328.87 5/25/2017 Payment received 8/22/17
4 $995,460.20 12/6/2017 Payment received 12/10/17
5 $51,840.25 1/16/2018 Payment received 1/19/18
6 $78,020.87 1/16/2018 Payment received 1/20/18
7 $55,446.22 1/16/2018 Payment received 1/20/18
8 $47,591.10 1/16/2018 Payment received 1/20/18
9 $276,018.94 1/17/2018 Payment received 1/20/18
10 $40,470.50 1/18/2018 Payment received 1/20/18
11 $261,784.60 2/14/2018 Payment received 2/20/18
12 $36,978.30 2/16/2018 Payment received 2/20/18
13 $570,836.47 2/16/2018 Payment received 2/20/18
14 $47,742.51 3/15/2018 Payment received 3/19/18
15 $45,248.00 3/15/2018 Payment received 3/19/18
16 $15,528.47 3/19/2018 Payment received 3/19/18
17 $45,688.50 3/26/2018 Payment received 4/2/18
18 $48,099.08 3/26/2018 Payment received 4/2/18
19 $30,211.75 5/11/2018 Payment received 5/16/18
20 $277,393.03 5/14/2018 Payment received 5/17/18
21 $46,148.12 5/14/2018 Payment received 5/17/18
22 $234,593.30 6/20/2018 Payment received 7/3/18
23 $47,527.50 6/20/2018 Payment received 7/3/18
24 $286,953.82 6/20/2018 Payment received 7/3/18
25 $26,347.50 6/20/2018 Payment received 7/3/18
26 $134,418.51 6/20/2018 Payment received 7/3/18
27 $39,158.81 6/20/2018 Payment received 7/3/18
28 $315,703.43 6/20/2018 Payment received 7/3/18
29 $23,442.50 6/20/2018 Payment received 7/3/18
30 $173,252.87 6/20/2018 Payment received 7/3/18
Smart City Challenge Demonstration Quarterly Report: 2018 4th Quarter (October 2018 – December 2018) 9
Invoice # $ Amount Date Notes/Comments
31 $15,064.44 7/1/2018 Payment Received 10/17/18
32 $23,752.50 7/1/2018 Payment Received 10/17/18
33 $211,984.87 7/1/2018 Payment Received 10/17/18
34 $288,613.65 7/1/2018 Payment Received 10/17/18
35 $54,150.52 7/1/2018 Payment Received 10/17/18
36 $53,376.50 7/1/2018 Payment Received 10/17/18
37 $18,500.00 7/1/2018 Payment Received 10/17/18
38 $11,500.00 7/1/2018 Payment Received 10/17/18
39 $11,750.00 7/1/2018 Payment Received 10/17/18
40 $20,250.00 7/1/2018 Payment Received 10/17/18
41 $19,750.00 8/14/2018 Payment Received 10/17/18
42 $20,300.00 8/14/2018 Payment Received 10/17/18
43 $8,685.00 8/14/2018 Payment Received 10/17/18
44 $6,948.00 8/14/2018 Payment Received 10/17/18
45 $2,026.50 8/14/2018 Payment Received 10/17/18
46 $1,640.50 8/14/2018 Payment Received 10/17/18
47 $1,760.00 8/14/2018 Payment Received 10/17/18
48 $2,720.00 8/14/2018 Payment Received 10/17/18
49 $2,960.00 8/14/2018 Payment Received 10/17/18
50 $2,320.00 8/14/2018 Payment Received 10/17/18
51 $20,300.00 8/14/2018 Payment Received 10/17/18
52 $24,700.00 8/14/2018 Payment Received 10/17/18
53 $29,100.00 8/14/2018 Payment Received 10/17/18
54 $29,100.00 8/14/2018 Payment Received 10/17/18
55R $29,100.00 8/14/2018 Payment Received 10/17/18
56 $37,900.00 8/14/2018 Payment Received 10/17/18
57 $30,200.00 8/14/2018 Payment Received 10/17/18
58 $13,433.90 8/14/2018 Payment Received 10/17/18
59 $5,868.59 8/14/2018 Payment Received 10/17/18
60 $46,332.32 8/14/2018 Payment Received 10/17/18
61 $38,533.52 8/14/2018 Payment Received 12/4/18
62 $44,538.54 8/14/2018 Payment Received 12/4/18
63 $20,080.00 8/14/2018 Payment Received 12/4/18
64 $20,080.00 8/14/2018 Payment Received 12/4/18
65 $20,080.00 8/14/2018 Payment Received 12/4/18
66 $2,800.00 8/14/2018 Payment Received 12/4/18
Smart City Challenge Demonstration Quarterly Report: 2018 4th Quarter (October 2018 – December 2018) 10
Invoice # $ Amount Date Notes/Comments
67 $2,960.00 8/14/2018 Payment Received 12/4/18
68 $178,049.59 8/14/2018 Payment Received 12/4/18
69 $269,833.70 8/14/2018 Payment Received 12/4/18
70 $7,214.23 8/14/2018 Payment Received 12/4/18
71 $228,967.31 8/14/2018 Payment Received 12/4/18
72 $7,734.00 8/14/2018 This request was submitted for $16,308.98 but was approved for $7,734.00. Payment received 12/20/18.
73 $25,972.32 8/14/2018 This request was submitted for $27,972.32 but was approved for $25,972.32. Payment received 12/20/18.
Federal Financial Report
Status
1. See signed copy of the Federal Financial Report.
Smart City Challenge Demonstration Quarterly Report: 2018 4th Quarter (October 2018 – December 2018) 11
Schedule Update
Key Deliverables Completed Current Quarter
Task Name and Deliverable Due Date Status
Task A: Project Management
Quarterly Progress Report for 2018 Q3 10/30/2018 Final Delivered
Quarterly Progress Report for 2018 Q3 - Revised 11/21/2018 Final Delivered
Quarterly Schedule Update 11/30/2018 Final Delivered
Task B: Systems Engineering Approach Due Date Status
Smart Mobility Hubs SyRS – Draft 10/3/2018 Draft Delivered
Operating System – Public Webinar 10/10/2018 Final Delivered
Prenatal Trip Assistance RFP – Public Advertisement 10/10/2018 Final Delivered
Truck Platooning Trade Study – Final 10/11/2018 Final Delivered
Connected Electric Autonomous Vehicle RFI – Public Advertisement
10/11/2018 Final Delivered
Truck Platooning Trade Study – Revised Final 10/11/2018 Final Delivered
Common Payment System SyRS – Draft 10/22/2018 Draft Delivered
Smart Mobility Hubs SyRS – Public Webinar 10/24/2018 Final Delivered
Connected Vehicle Environment SyRS – Public Webinar 11/5/2018 Final Delivered
Prenatal Trip Assistance ConOps – Public Webinar 11/14/2018 Final Delivered
Event Parking Management SyRS – Public Webinar 11/15/2018 Final Delivered
Smart Mobility Hubs SyRS – Final 11/16/2018 Final Delivered
Mobility Assistance Test Plan – Draft 11/27/2018 Draft Delivered
Common Payment System SyRS – Public Webinar 11/28/2018 Final Delivered
Connected Vehicle Environment SyRS – Final 11/30/2018 Final Delivered
Common Payment System RFP – USDOT Review 12/2/2018 Draft Delivered
Common Payment System RFP – Public Advertisement 12/10/2018 Final Delivered
Event Parking Management SyRS – Final 12/11/2018 Final Delivered
Common Payment System SyRS – Final 12/19/2018 Final Delivered
Connected Electric Autonomous Vehicle RFP – USDOT Review 12/17/2018 Draft Delivered
Smart Mobility Hubs ICD – Draft 12/29/2018 Draft Delivered
Smart City Challenge Demonstration Quarterly Report: 2018 4th Quarter (October 2018 – December 2018) 12
Task Name and Deliverable Due Date Status
Task D: Data Privacy Requirements
Data Privacy Plan – Public Webinar 10/10/2018 Final Delivered
Data Privacy Plan – Draft Quarterly Update 12/28/2018 Draft Delivered
Task E: Data Management and Support for Independent Evaluation
Data Management Plan – Public Webinar 10/10/2018 Final Delivered
Data Management Plan – Draft Quarterly Update 12/28/2018 Draft Delivered
Task F: Safety Management and Safety Assurance
Safety Management Plan – Draft 11/30/2018 Draft Delivered
Task G: Communications and Outreach
Communication and Outreach Plan – Revised Draft 10/16/2018 Draft Delivered
Marketing & Communications Support RFP - Public Advertisement 11/26/2018 Final Delivered
Smart City Challenge Demonstration Quarterly Report: 2018 4th Quarter (October 2018 – December 2018) 13
Key Deliverables to be Delivered Next Quarter
Task Name and Deliverable Due Date Status
Task A: Project Management
Quarterly Progress Report for 2018 Q4 1/30/2019 Final Delivered
Quarterly Schedule Update 3/29/2019 In Revision 60%
Task B: Systems Engineering Approach Due Date Status
Connected Vehicle Environment Request for Subcontractor Approval of RSU Consultant – USDOT Review
1/7/2019 Draft Delivered
Connected Vehicle Environment Request for Subcontractor Approval of OBU Consultant – USDOT Review
1/10/2019 Draft Delivered
Connected Electric Autonomous Vehicle RFP – Public Advertisement
1/17/2019 Final Delivered
Mobility Assistance Test Plan – Final 1/18/2019 Final Delivered
Request for Subcontractor Approval (QBS) – USDOT Review 1/28/2019 Draft Delivered
System Architecture and Standards Plan – Draft 2/1/2019 Draft Delivered
Event Parking Management ICD – Draft 2/11/2019 In Progress 80%
Smart Mobility Hubs ICD – Final 2/15/2019 In Progress 60%
Connected Vehicle Environment ICD – Draft 2/22/2019 In Progress 60%
Connected Vehicle Environment Installation Plans – USDOT Review 2/27/2019 In Progress 60%
Mobility Assistance O&M Plan – Draft 3/5/2019 Not Initiated
Event Parking Management ICD – Public Webinar 3/6/2019 In Progress 50%
Smart Mobility Hubs Installation Plan – USDOT Review 3/12/2019 In Progress 50%
System Architecture and Standards Plan – Final 3/15/2019 Not Initiated
Connected Vehicle Environment ICD – Public Webinar 3/18/2019 In Progress 40%
Event Parking Management ICD – Final 3/27/2019 Not Initiated
Task C: Performance Measurement
Performance Measurement Plan – Revised Draft 2/1/2019 In Progress 95%
Performance Measurement Plan – Public Webinar 3/11/2019 In Progress 50%
Task D: Data Privacy Requirements
Data Privacy Plan – Final 2/8/2019 In Revision 90%
Data Privacy Plan – Revised Final 3/25/2019 Not Initiated
Smart City Challenge Demonstration Quarterly Report: 2018 4th Quarter (October 2018 – December 2018) 14
Task Name and Deliverable Due Date Status
Task E: Data Management and Support for Independent Evaluation
Data Management Plan –Final 1/29/2019 Final Delivered
Data Management Plan – Revised Final 2/26/2019 Not Initiated
Task G: Communications and Outreach
Communication and Outreach Plan – Quarterly Update 3/29/2019 Not Initiated
Smart City Challenge Demonstration Quarterly Report: 2018 4th Quarter (October 2018 – December 2018) 15
Key Activities / Accomplishments
Program-Level Accomplishments for Current Quarter
Q4 Task Accomplishment Date
1.
A: Project Management
Project Coordination meetings to discuss accomplishments and issues -Discussed activities accomplished the previous day, coordinate phone calls, meetings, deliverables, and planned the next two days
Daily
2. Conducted Weekly USDOT/Smart Columbus Status Update Meeting
Tuesdays 10/2/2018 – 12/18/2018
3. Conducted Program Management Office Monthly Meetings
10/10/2018, 10/24/2018, 11/8/2018, 11/21/2018, 12/19/2018
4. Submitted Final Quarterly Report for Q3 2018 10/30/2018
5. Conducted EMPO Meeting 11/1/2018, 12/6/2018
6. Submitted Revised Final Quarterly Report for Q3 2018
11/21/2018
7. Submitted Quarterly Schedule Update 11/30/2018
8. C: Performance Measurement
Participated in Bi-Weekly USDOT CV Pilot Perf Measures / IE / Human Use roundtable meetings
10/9/2018, 11/6/2018, 12/4/2018, 12/18/2018
9.
D: Data Privacy Requirements
Conducted Data Privacy Plan Public Webinar for USDOT 10/10/2018
10. Participated in webinar for Transportation Data Privacy 11/13/2018
11. Submitted Draft Update (Iteration 3) of Data Privacy Plan 12/28/2018
12. E: Data Management and Support for Independent Evaluation
Conducted Data Management Plan Public Webinar for USDOT 10/10/2018
13. Conducted Bi-Weekly Meeting with Independent Evaluator
12/13/2018, 12/27/2018
14. Submitted Draft Update (Iteration 3) of Data Management Plan 12/28/2018
15.
F: Safety Management and Safety Assurance
Submitted Draft Safety Management Plan 11/30/2018
Smart City Challenge Demonstration Quarterly Report: 2018 4th Quarter (October 2018 – December 2018) 16
Q4 Task Accomplishment Date
16.
G: Communications and Outreach
Submitted Revised Draft Communication and Outreach Plan to USDOT
10/16/2018
17.
Provide graphic design services and support to deliver two scheduled webinars: Operating System and Smart Mobility Hubs
Oct 2018
18.
Provided on-call graphics services for engineering submittals including upcoming webinars and PMP documentation
Oct 2018
19.
Participated in work sessions and led tactic development for engaging end-users related to the CEAV, MMTPA/CPS, SMH, EPM, CVE and PTA projects
Oct 2018
20.
In conjunction with PMO, drafted, edited, proofed and provided graphic design support for communications plans for CVE, CEAV, DATP, PTA, MMTPA/CPS, SMH, MAPCD and EPM.
Oct 2018
21. Released RFP for Marketing & Communications Support
11/26/2018
22.
Facilitated engagement activities and stakeholder meetings for PTA. Drafted grassroots engagement and adoption plans for EPM, CVE, MMTPA/CPS and SMH.
Nov 2018
23.
Provide graphic design services and support to deliver one scheduled webinar: Prenatal Trip Assistance
Nov 2018
24. Refined 2019 communications program plans based on PMO feedback.
Nov 2018
25. Facilitated engagement activities and stakeholder meetings for PTA.
Dec 2018
26.
Provided on-call graphics services for the Operating System including a goals map, refinements to the primary portfolio graphic and creation of an end-user worksheet
Dec 2018
Smart City Challenge Demonstration Quarterly Report: 2018 4th Quarter (October 2018 – December 2018) 17
Program-Level Plans for Next Quarter
Q1 Task Accomplishment Date
1.
A: Project Management
Program Coordination meetings to discuss accomplishments and issues.
Daily
2. Conduct Weekly USDOT Status Update Meetings
Tuesdays 1/1/2019 – 3/26/2019
3. Conduct Program Management Office Bi-Weekly Meetings
Wednesdays 1/2/2019 – 3/27/2019
4. Conduct EPMO Meeting
1/23/2019, 2/27/2019, 3/27/2019
5. Submit Final Quarterly Report for Q4 2018 1/30/2019
6. Submit Quarterly Update for Project Management Plan Q1 2019
7. Submit Quarterly Schedule Update to USDOT 3/29/2019
8. B: Systems Engineering Approach
Submit Draft System Architecture and Standards Plan 2/1/2019
9. Submit Final System Architecture and Standards Plan 3/15/2019
10.
C: Performance Measurement
Participate in Bi-Weekly USDOT CV Pilot Perf Measures / IE / Human Use Roundtable Meetings
Tuesdays
1/1/2019 – 3/26/2019
11. Submit Revised Draft Performance Measurement Plan 2/1/2019
12. Conduct Performance Measurement Plan Public Webinar for USDOT
3/11/2018
13. D: Data Privacy Requirements
Submit Final Data Privacy Plan to USDOT 2/8/2019
14. Submit Revised Final Data Privacy Plan to USDOT 3/25/2019
15.
E: Data Management and Support for Independent Evaluation
Work on Independent Evaluation Support Plan Q1 2019
16. Conduct Bi-Weekly Meeting with Independent Evaluator
Thursdays
1/10/2019 – 3/21/2019
17. Submit Final Data Management Plan to USDOT 1/29/2019
18. Submit Revised Final Data Management Plan to USDOT 2/26/2019
Smart City Challenge Demonstration Quarterly Report: 2018 4th Quarter (October 2018 – December 2018) 18
Q1 Task Accomplishment Date
19.
F: Safety Management and Safety Assurance
Conduct Safety Management Plan Public Webinar for USDOT
TBD
20.
G: Communications and Outreach
Provide graphic design services and support to deliver one scheduled webinar: Connected Electric Autonomous Vehicles project
Q1 2019
21. Continue development of PTA launch materials and risk mitigation plans
Q1 2019
22. Perform MMTPA grassroots engagement tactics Q1 2019
23. Finalize plans and tactics for CEAV and EPM launches Q1 2019
24. Support PMO development of grassroots engagement activities toward CVE end-user adoption and risk mitigation
Q1 2019
25. Provide on-call graphics services to support engineering submittals
Q1 2019
26. Facilitate engagement activities as needed to support user need validation
Q1 2019
Table of Events Attended and Upcoming Events
Date Event
N/A N/A
N/A N/A
*Gray for events completed, white for upcoming events
Smart City Challenge Demonstration Quarterly Report: 2018 4th Quarter (October 2018 – December 2018) 19
Project-Level Accomplishments for Current Quarter
Q4 Project Accomplishment Date
1.
Smart Columbus Operating System
Conducted daily Standing Scrum Meetings for Sprint 34 for Platform Framework and discussed status, blockers, and stories.
10/1/2018 – 12/31/2018
2.
Conducted Sprint 34 Review and Retrospective meetings. -Upgraded CKAN Data Platform and migrated existing data to the upgraded environment; Made Jupyter public facing when ready to engage beta testers; Created automated code base so system will be deployed and verified independently; Created data story page to support COTA map; Began preparation to activate Kylo data platform to replace CKAN; Provisioned technology tools for data platform 2.0 (Kylo)
10/2/2018
3.
Conducted Planning session for Sprint 35 Platform Framework meeting. -Determined the sprint goals and the Development Team answered the questions: number of points to deliver within the sprint, who owned each item, and clarification from the product owner.
10/2/2018
4.
Conducted daily Standing Scrum Meetings for Sprint 35 for Platform Framework and discussed status, blockers, and stories.
10/3/2018 – 10/16/2018
5. Conducted Bi-Weekly Update Meetings with USDOT
Fridays 10/5/2018 – 12/28/2018
6. Conducted Public Webinar for USDOT 10/10/2018
7.
Conducted Monthly Data Technical Working Group Meeting -Worked to solve technical issues regarding: open sourcing, risks, community engagement, and sphere. Worked to solve policy issues regarding: Data Privacy and Data Management Plans and provided guidance on policies identified in Policy Roadmap
10/15/2018, 11/15/2018, 12/13/2018
8.
Conducted Sprint 35 Retrospective meeting.
-Scrum team reviewed internal work flows and potential process for improvement and approach to implement those improvements into the next sprints.
10/16/2018
Smart City Challenge Demonstration Quarterly Report: 2018 4th Quarter (October 2018 – December 2018) 20
Q4 Project Accomplishment Date
9.
Smart Columbus Operating System
Conducted Weekly Architecture and Demo Presentations -Demonstrated progress and worked to plan future sprints.
Tuesdays 10/16/2018 – 12/18/2018
10.
Conducted daily Standing Scrum Meetings for Sprint 36 for Platform Framework and discussed status, blockers, and stories.
10/17/2018 – 10/30/2018
11.
Conducted Sprint 36 Retrospective meeting.
-Scrum team reviewed internal work flows and potential process for improvement and approach to implement those improvements into the next sprints.
10/30/2018
12.
Conducted Review Demo Presentation for Sprints 35 & 36 -Worked improve provisions for elasticsearch and activemq, transition from CKAN to Kylo, and prepare for provisions for Kylo; Worked to add search abilities for datasets and review metadata prior to download through KPI support and Data Lake UI; Worked to harden and stabilize the real-time location of COTA bus and to productionize Kafka; Worked to add provision Hadoop and to harden and stabilize the OS from the developers perspective; Worked to prepare for beta testers
10/30/2018
13.
Conducted daily Standing Scrum Meetings for Sprint 37 for Platform Framework and discussed status, blockers, and stories.
10/31/2018 – 11/13/2018
14.
Conducted Sprint 37 Retrospective meeting.
-Scrum team reviewed internal work flows and potential process for improvement and approach to implement those improvements into the next sprints.
11/13/2018
15.
Conducted daily Standing Scrum Meetings for Sprint 38 for Platform Framework and discussed status, blockers, and stories.
11/14/2018 – 11/27/2018
16.
Conducted Sprint 38 Retrospective meeting.
-Scrum team reviewed internal work flows and potential process for improvement and approach to implement those improvements into the next sprints.
11/27/2018
Smart City Challenge Demonstration Quarterly Report: 2018 4th Quarter (October 2018 – December 2018) 21
Q4 Project Accomplishment Date
17.
Smart Columbus Operating System
Conducted Review Demo Presentation for Sprints 37 & 38
-Worked to prepare for MMTPA; Worked on provisions for Kylo; Worked to add search abilities for datasets and review metadata prior to download through Data Lake UI and CEAV Data Integration; Worked to add provision for Hadoop, Setup KDC infrastructure with HDP, add part 2 of COTA map, and DPP/DMP Prep; Worked to add alerting and monitoring, production support, and hardening and stability for OS developers; Worked to prepare for Open Source
11/27/2018
18.
Conducted daily Standing Scrum Meetings for Sprint 39 for Platform Framework and discussed status, blockers, and stories.
11/28/2018 – 12/11/2018
19.
Conducted Sprint 39 Retrospective meeting.
-Scrum team reviewed internal work flows and potential process for improvement and approach to implement those improvements into the next sprints.
12/11/2018
20.
Conducted daily Standing Scrum Meetings for Sprint 40 for Platform Framework and discussed status, blockers, and stories.
12/12/2018 – 12/25/2018
21.
Conducted Review Demo Presentation for Sprints 39 & 40
-Worked to inject CEAV data and Lime Surveys into Kubernetes; Worked to reverse DNS lookup of KDC, configure an LDAP service account for NiFi to Kylo and for Discovery API to Kylo, connect Kylo/Nifi to Hive, replace mockylo with Kylo; Worked to make graphs available in Grafana, configure Grafana to use LDAP, configure Joomla to use LDAP, configure Elixir apps with smaller Docker image; Worked on updating policy roadmap; Worked on recommendations for community engagements practices for the technical working groups
12/18/2018
Smart City Challenge Demonstration Quarterly Report: 2018 4th Quarter (October 2018 – December 2018) 22
Q4 Project Accomplishment Date
22. Smart Columbus Operating System
Conducted Sprint 40 Retrospective meeting.
-Scrum team reviewed internal work flows and potential process for improvement and approach to implement those improvements into the next sprints.
12/25/2018
23.
Conducted daily Standing Scrum Meetings for Sprint 41 for Platform Framework and discussed status, blockers, and stories.
12/26/2018 – 12/31/2018
24.
Connected Vehicle Environment
Conducted Weekly Meetings -Discussed schedule, deliverables, upcoming webinars, and ongoing coordination with COTA and Franklin County along with other City departments.
Thursdays
10/4/2018 – 12/27/2018
25.
Antaira Technologies meeting with DriveOhio - Discussed and reviewed managed Layer 2 and Layer 3 network switches and abilities for an IPV4 and IVP6 environment
10/18/2018
26. Participated in Bi-Weekly CV Pilot Technical Roundtable Calls
Fridays
10/26/2018 – 12/21/2018
27. Conducted SyRS Public Webinar for USDOT 11/5/2018
28.
OBU Installation Observation and Workforce Development Planning Session with DriveOhio -Observed HDV installations and discussed challenges -Reviewed training requirements for installers -Coordinated upcoming efforts to avoid duplication of work
11/16/2018
29.
Smart Columbus and DriveOhio Meeting
-Discussed the DriveOhio SCMS and timeframe to implementation
-Reviewed possible alignment of work with DriveOhio for in-kind contribution
-OBU and RSU implementations and approaches of Smart Columbus and statewide deployments
11/29/2018
30. Submit Final SyRS to USDOT 11/30/2018
Smart City Challenge Demonstration Quarterly Report: 2018 4th Quarter (October 2018 – December 2018) 23
Q4 Project Accomplishment Date
31.
Multimodal Trip Planning Application
MMTPA vendor selection 10/29/2018
32. Webinar - Strategies for Accelerating Multimodal Project Delivery
10/31/2018
33. Mtech (Vendor) NTP 12/7/2018
34. Kickoff meeting 12/10/2018
35. Mobility provider introduction/coordination meeting
12/13/2018
36.
Sprint 1
-Designed route planning web app and ability to record trips to Blockchain
12/20/2018
37.
Common Payment System
Submitted Draft SyRS to USDOT 10/22/2018
38. Conduct SyRS Public Webinar for USDOT 11/28/2018
39. Submit RFP for Courtesy USDOT Review 12/2/2018
40. Publically Advertised RFP 12/10/2018
41. Submitted Final SyRS to USDOT 12/19/2018
42.
Smart Mobility Hubs
Submitted Draft SyRS to USDOT 10/3/2018
43. Webinar on Lighting Strategies for Improving Pedestrian Safety and Walkability 10/17/2018
44. Conducted Bi-Weekly Meetings Thursdays 10/18/2018 – 12/27/2018
45. Conducted SyRS Public Webinar for USDOT 10/24/2018
46. Conducted discussion with Denver on Mobility Hubs
11/13/2018
47. Submitted Final SyRS to USDOT 11/16/2018
48. Submitted Draft ICD to USDOT 12/29/2018
49.
Mobility Assistance
Conducted Bi-Weekly Coordination Meeting Mondays 10/1/2018 – 12/10/2018
50. PIECE Program Suggestions and Data 10/29/2018
51. Submitted Draft IRB Human Use Approval Request
10/23/2018
52. Submitted Draft Test Plan to USDOT 11/27/2018
53. Submitted revised IRB Part 1 – Participant Identification
12/15/2018
Smart City Challenge Demonstration Quarterly Report: 2018 4th Quarter (October 2018 – December 2018) 24
Q4 Project Accomplishment Date
54.
Prenatal Trip Assistance
ODM Discussion 10/1/2018
55. Rides4Baby Mobility Option meeting 10/2/2018
56. Conducted Weekly Meetings
Thursdays
10/4/2018 – 12/20/2018
57. Conducted Bi-Weekly Coordination Calls with Health Insurance Companies and OSU
Fridays
10/5/2018 – 12/28/2018
58. Publically Advertised RFP 10/10/2018
59. Conducted CelebrateOne Lead Entities Meetings
10/12/2018, 11/9/2018, 12/14/2018
60. Meeting with Primary One Health 11/5/2018
61. Meeting with Lower Lights Christian Health Center
11/6/2018
62. Meeting with Medicaid 11/9/2018
63. Conducted ConOps Public Webinar for USDOT
11/14/2018
64. CINO Approval of Vendor 11/27/2018
65.
Event Parking Management
Conducted Weekly Meetings -Discussed System Requirements, existing parking providers, Parking Services projects and coordination
Thursdays
10/4/2018 – 12/20/2018
66.
Conducted System Requirements Walkthrough with Parking Providers -Reviewed gap analysis obtaining input from multiple parking providers in the downtown region -Learned of applications impact to parking providers fiscally and interaction with local business and how major events are handled on reservations
10/24/2018
67. Conducted SyRS Public Webinar for USDOT 11/15/2018
Smart City Challenge Demonstration Quarterly Report: 2018 4th Quarter (October 2018 – December 2018) 25
Q4 Project Accomplishment Date
68. Event Parking Management
Conducted Meeting with Park Mobile -Discussed the Smart Columbus System Functional Requirements with Park Mobile and Division of Parking Services -Assessed the feasibility of Park Mobile reviewing the other system requirements for the EPM project in determining if there may be a possibility of leveraging the Park Columbus app for the EPM thereby having one parking application in Columbus.
11/29/2018
69. Submitted Final SyRS to USDOT 12/11/2018
70.
Connected Electric Autonomous Vehicles
Conducted Weekly Meetings Wednesdays
10/3/2018 – 12/26/2018
71.
Participated in Weekly AV Shuttle Deployment SOP & Emergency Management Protocol Working Group Meetings
Wednesdays
10/3/2018 – 12/19/2018
72. Publicly Advertised RFI 10/11/2018
73. Participated in AV Research and Data Working Group
10/22/2018, 11/5/2018, 12/31/2018
74. AV Shuttle - Emergency Operations coordination meeting
10/25/2018
75. Witness Factory Acceptance Testing (Scioto Mile)
11/9/2018
76. Conduct emergency responder tabletop exercise (Scioto Mile)
11/14/2018
77. Witness Preliminary Acceptance Testing (Scioto Mile)
11/16/2018
78. Accept final API schema for Operating System (Scioto Mile)
11/21/2018
79. Witness Final Acceptance Testing (Scioto Mile)
11/28/2018
80. Go-Live for Passenger Service (Scioto Mile) 12/10/2018
81. Submit RFP for Courtesy USDOT Review 12/19/2018
82. Truck Platooning
Conducted Next Steps meeting with Navistar 10/9/2018
83. Conducted Next Steps meeting with Bosch 10/9/2018
84. Submit Revised Final Trade Study to USDOT 10/11/2018
85. Multiple Projects Conducted Weekly MMTPA/CPS Meetings
Thursdays 10/11/18 – 12/27/18
Smart City Challenge Demonstration Quarterly Report: 2018 4th Quarter (October 2018 – December 2018) 26
Project-Level Plans for Next Quarter
Q1 Project Accomplishment Date
1.
Smart Columbus Operating System
Daily Standing Scrum Meetings for Sprint 41 for Platform Framework and discuss status, blockers, and stories.
1/2/2019 – 1/8/2019
2. Conduct Weekly Architecture and Demo Presentations.
1/8/2019 – 3/26/2019
3. Conduct Sprint 41 Retrospective meeting. 1/8/2019
4. Daily Standing Scrum Meetings for Sprint 42 for Platform Framework and discuss status, blockers, and stories.
1/9/2019 – 1/22/2019
5. Conduct Bi-Weekly Update Meetings with USDOT.
Fridays 1/11/2019 – 3/22/2019
6. Conduct Sprint 42 Retrospective meeting. 1/22/2019
7. Daily Standing Scrum Meetings for Sprint 43 for Platform Framework and discuss status, blockers, and stories.
1/23/2019 – 2/5/2019
8. Conduct Monthly Data Technical Working Group Meeting
1/24/2019,
2/12/2019,
3/21/2019
9. Conduct Monthly Demo Presentations 1/29/2019, 2/26/2019, 3/26/2019
10. Conduct Sprint 43 Retrospective meeting. 2/5/2019
11. Daily Standing Scrum Meetings for Sprint 44 for Platform Framework and discuss status, blockers, and stories
2/6/2019 – 2/19/2019
12. Conduct Sprint 44 Retrospective meeting. 2/19/2019
13. Daily Standing Scrum Meetings for Sprint 45 for Platform Framework and discuss status, blockers, and stories
2/20/2019 – 3/5/2019
14. Conduct Sprint 45 Retrospective meeting. 3/5/2019
15. Daily Standing Scrum Meetings for Sprint 46 for Platform Framework and discuss status, blockers, and stories
3/6/2019 – 3/19/2019
Smart City Challenge Demonstration Quarterly Report: 2018 4th Quarter (October 2018 – December 2018) 27
Q1 Project Accomplishment Date
16. Smart Columbus Operating System
Conduct Sprint 46 Retrospective meeting. 3/19/2019
17. Daily Standing Scrum Meetings for Sprint 47 for Platform Framework and discuss status, blockers, and stories
3/20/2019 – 3/29/2019
18.
Connected Vehicle Environment
Work on System Design Document Q1 2019
19. Engage with IRB and develop participant recruitment plan
Q1 2019
20. Conduct Weekly Meetings Thursdays 1/3/2019 – 1/10/2019
21. Participate in Bi-Weekly CV Pilot Technical Roundtable Calls
1/4/2018
22. Submit Request for Review of Subcontractor Approval of RSU Consultant to USDOT
1/7/2019
23. Submit Request for Review of Subcontractor Approval of OBU Consultant to USDOT
1/7/2019
24. Meeting with Stantec to discuss future RFP 1/7/2019
25. Meeting with Siemens to discuss future RFP 1/7/2019
26. OBU Vendor Days with DriveOhio 1/8/2019 –
1/9/2019
27. Publically Advertise RFP for RSU and OBU 1/29/2018
28. Submit Draft Interface Control Document to USDOT
2/22/2019
29. Submit Installation Plans for USDOT Review 2/27/2019
30. Conduct ICD Public Webinar for USDOT 3/18/2019
31. Conduct Vendor Interviews for RSU and OBU System Integrators
3/20/2019 – 3/21/2019
32.
Multimodal Trip Planning Application
Sprints 2-7 Q1 2019
33. Bi-weekly demonstrations
Q1 2019
1/3/2019 – 3/28/2019
34. MVP (Release 1) 2/28/2019
35.
Common Payment System
CINO approval of vendor 2/8/2019
Smart City Challenge Demonstration Quarterly Report: 2018 4th Quarter (October 2018 – December 2018) 28
Q1 Project Accomplishment Date
36.
Common Payment System
Vendor NTP 3/22/2019
37.
Smart Mobility Hubs
Work on Draft System Design Document Q1 2019
38. Conduct Bi-Weekly Meetings Thursdays 1/24/2019 – 3/21/2019
39. Conduct ICD Public Webinar for USDOT 1/18/2019
40. Submit Final ICD to USDOT 2/15/2019
41. Submit Installation Plans for USDOT Review 3/12/2019
42.
Mobility Assistance
Acceptance Testing Q1 2019
43. Conduct Bi-Weekly Meetings Mondays 1/7/2019 – 3/22/2019
44. Submit Final Test Plan to USDOT 1/18/2019
45. Submit IRB Application part 2 2/15/2019
46. Submit Draft O&M Plan to USDOT 3/5/2019
47. Submit Final O&M Plan to USDOT 3/28/2019
48.
Prenatal Trip Assistance
Develop Participant Recruitment Plan Q1 2019
49. OSU/MCO/CelebrateOne monthly communications
1/7/2019,
2/4/2019,
3/4/2019
50. NTP 1/8/2019
51. Conduct Bi-Weekly Coordination Calls with Health Insurance Companies and OSU
Fridays 1/11/2019 – 3/22/2019
52. Conduct CelebrateOne Lead Entities Meetings
1/11/2019,
2/8/2019,
3/8/2019
53. Submit Human Use Approval Request to IRB 2/15/2019
54. Submit IRB Application 3/11/2019
55. MVP Release 3/31/2019
56. Event Parking Management Conduct Weekly Meetings
Thursdays 1/3/2019 – 3/28/2019
Smart City Challenge Demonstration Quarterly Report: 2018 4th Quarter (October 2018 – December 2018) 29
Q1 Project Accomplishment Date
57.
Event Parking Management
Submit Draft ICD to USDOT 2/11/2019
58. Conduct ICD Public Webinar for USDOT 3/6/2018
59. Submit Final ICD to USDOT 3/27/2019
60. CINO Approval of Contractor 3/27/2019
61.
Connected Electric Autonomous Vehicles
Prepare Testing Report, Integrate OS, Performance and System Monitoring
Q1 2019
62. Conduct Weekly Meetings Wednesdays 1/2/2019 – 3/27/2019
63. AV Research and Data Working Group Mondays 1/14/2019 – 3/25/2019
64. Publically Advertised RFP (Use Case #2) 1/17/2019
65. Conduct Overview of Emerging Technologies Webinar
1/30/2019
66.
Multiple Projects
Develop Participant Recruitment Plan for MMTPA/CPS
Q1 2019
67. Conducted Bi-Weekly MMTPA/CPS Meetings Thursdays 1/10/2019 – 3/21/2019
68. Submit Human Use Approval Request to IRB for MMTPA/CPS
3/14/2019
Smart City Challenge Demonstration Quarterly Report: 2018 4th Quarter (October 2018 – December 2018) 30
Subcontractor Status Summary Key Tasks / A summary of Subcontractor Coordination and Management Activities
Status of Key Procurements and sub-contract awards in October
1.) Proteon: Finalize Mod #2
2.) HNTB: Finalize Mod #4
3.) HNTB: Finalize Mod #3
Status of Key Procurements and sub-contract awards in November
1.) MTECH: Finalized contract for $854,683
2.) Prenatal Trip Assistance: Release RFP
3.) Pillar: Finalized contract Mod #2
Status of Key Procurements and sub-contract awards in December
1.) Common Payment System: Release RFP
Future Key Procurements and sub-contract awards in the Next Quarter –
January - March 2019
1.) Prenatal Trip Assistance: Finalize MCO contract with Kaizen
2.) Engage: Finalize contract Mod #4
3.) Pillar: Finalize contract Mod #1
4.) CEAV: Release RFP
5.) CVE OBU: Release RFP
6.) CVE RSU: Release RFP
7.) HNTB: Finalize Contract Mod #6
Smart City Challenge Demonstration Quarterly Report: 2018 4th Quarter (October 2018 – December 2018) 31
Leveraged Partner Resources Status Summary
Summary of activities related to Leveraged Partner Resources
Status of Key Procurements and sub-contract awards
1) The next pages contain the Partnership/Stakeholder Status Summary from January 2018.
Smart City Schedule Cooperative Agreement No. DTFH6116H00013
Partnership/Stakeholder Status Summary
1/28/2019 Page 1 of 4
National Partners
AT&T Total Value $1,000,000 Primary Grant USDOT Agreement Executed 8/22/2017
Introductory Discussion X Agreement Sent to USDOT 8/22/2017 Sent Draft Agreement X Hand Off
Negotiating Agreement X NDA Executed Covered in cooperative agreement Offering: $100,000 IoT Security consulting, $900,000 in equipment and data services. AT&T has committed to provide in-kind partnering to the City to assist with the deployment of the Columbus Connected Transportation Network (CCTN). The proposed partnering includes professional services and technical support resources; communications and data management technologies; USB cellular modems and SIM cards and connectivity; hardware to support communications and data management services. Current Status: Cooperative agreement executed 8/22/17. City currently determining if contribution is needed.
Autodesk Total Value $219,060
Primary Grant USDOT Agreement Executed 3/20/2017 Introductory Discussion X Agreement Sent to USDOT 3/22/2017
Sent Draft Agreement X Hand Off 3/22/17 to K. Zehnder and R. Bollo Negotiating Agreement X NDA Executed Covered in cooperative agreement
Offering: 4-yr subscription to Infraworks, an information modeling platform that uses 3-D visualizations and real-world data to plan major engineering projects, on-site training, continued technical support. Current Status: Cooperative agreement executed 3/22/17.
AWS Total Value $1,000,000
Primary Grant USDOT Agreement Executed 5/26/2017 Introductory Discussion X Agreement Sent to USDOT 5/30/2017
Sent Draft Agreement X Hand Off 5/30/17 to S. Elhami Negotiating Agreement X NDA Executed Executed 2/17/2017
Offering: $750,000 Service credits, $250,000 Professional Services. Credits to AWS Cloud services and AWS Professional Services. AWS will also provide solution architecture and best practices guidance to Columbus. Currently hosting OS on AWS but using open source tool stacks. Current Status: Grant agreement executed 6/29/17.
Continental Total Value $1,000,000
Primary Grant USDOT Agreement Executed February 2018 Introductory Discussion X Agreement Sent to USDOT April 2018
Sent Draft Agreement X Hand Off TBD Negotiating Agreement X NDA Executed Executed 4/12/2017
Offering: Continental will deploy a roadside infrastructure sensing system in a phased approach, with one intersection to be deployed and beta tested before additional intersections are fitted. Intersections will demonstrate DSRC communication systems to enable communication between roadside and onboard systems; API interfaces on cloud backend comprised of APIs for accessing data from both onboard and roadside V2X systems; basic safety messages to demonstrate the effectiveness of the CCTN on alleviating transportation-related issues such as intersection safety warnings, traffic management, automated system to regulate the flow of traffic according to real time traffic information, in-car productivity and safety, V2X warnings based on driver profile, route optimization or navigation, and reduced traffic congestion through load balancing via rerouting services enhanced with real time navigation data. Current Status: Received signed agreement on 1/26/2018. Advancing coordination with Continental.
Sidewalk Labs Total Value $230,000
Primary Grant USDOT Agreement Executed 5/23/2017 Introductory Discussion X Agreement Sent to USDOT 5/25/2017
Sent Draft Agreement X Hand Off 5/25/17 to A. Wolpert Negotiating Agreement X NDA Executed Covered in cooperative agreement
Offering: $200,000 staff, $30,000 travel. Flow technology, an analytics platform that Columbus can use to identify traffic-prone areas and parts of a city that are underserved by public transportation, all by using traffic patterns culled from aggregated, anonymized data. From that information the software can suggest solutions like ride-sharing, new transportation access or a rerouting of traffic to better serve the community. Current Status: Cooperative agreement executed 5/25/17. Work complete
Smart City Schedule Cooperative Agreement No. DTFH6116H00013
Partnership/Stakeholder Status Summary
1/28/2019 Page 2 of 4
Local Partners
Battelle Total Value $1,000,000 Primary Grant USDOT Agreement Executed 8/7/2017
Introductory Discussion X Agreement Sent to USDOT Sent Draft Agreement X Hand Off
Negotiating Agreement X NDA Executed Executed 04/24/2017 Offering: In-kind program staff support Current Status: USDOT approved sole source request 8/1/17. Executed cooperative agreement 8/7/2017. DPM, Fiscal team, Battelle working to satisfy to follow up info requests from USDOT to sole source approval. - met with Battelle 8/8/17. Fiscal team provided contract draft to Battelle 8/8/17. Negotiated new agreement. Signed contract on 1/26/2018. Continues to provide resource/data curator.
Columbus Partnership Total Value $17,500,000
Primary Grant USDOT Agreement Executed 3/31/2017 Introductory Discussion X Agreement Sent to USDOT 3/31/2017
Sent Draft Agreement X Hand Off Negotiating Agreement X NDA Executed Covered in cooperative agreement
Offering: $500K for program staff support; $7.5M in private sector in-kind programs and private sector commitments for electrification; and $5M in facilitating in-kind CV/AV transportation research Current Status: Cooperative agreement executed 3/31/17
COTA Total Value $9,000,000
Primary Grant USDOT Agreement Executed 7/28/2017 Introductory Discussion X Agreement Sent to USDOT 7/28/2017
Sent Draft Agreement X Hand Off Negotiating Agreement X NDA Executed Covered in cooperative agreement
Offering: In-kind staff Current Status: Cooperative agreement executed 7/28/17.
Econolite Total Value $900,000
Primary Grant USDOT Agreement Executed 7/18/2017 Introductory Discussion X Agreement Sent to USDOT 7/25/2017
Sent Draft Agreement X Hand Off 7/25/2017 to R. Bollo Negotiating Agreement X NDA Executed Covered in cooperative agreement
Offering: $700,000 firmware licenses; $200,000 analytics software licenses Current Status: Cooperative agreement executed 7/18/17.
Franklin County Total Value $4,000,000
Primary Grant USDOT Agreement Executed Still negotiating. Introductory Discussion X Agreement Sent to USDOT
Sent Draft Agreement 12/29/2016 Hand Off Negotiating Agreement X NDA Executed
Offering: $3M program, $1M cash Current Status: Meeting with Franklin County 10/24/18 to discuss incorporating NEMT project concept into Franklin County partnership. Met w/ Franklin Co. Asst. Administrator in December 2018. Met w/FCEO to discuss engineers contribution. Still negotiating.
GCAC (Arts) Total Value $1,000,000
Primary Grant USDOT Agreement Executed 2/23/2017 Introductory Discussion X Agreement Sent to USDOT 2/24/2017
Sent Draft Agreement X Hand Off Negotiating Agreement X NDA Executed Covered in cooperative agreement
Offering: $1M investment to support communication, education and awareness of smart city programs Current Status: Cooperative agreement executed 2/23/17.
Smart City Schedule Cooperative Agreement No. DTFH6116H00013
Partnership/Stakeholder Status Summary
1/28/2019 Page 3 of 4
HERE Total Value $1,000,000 Primary Grant USDOT Agreement Executed TBD
Introductory Discussion X Agreement Sent to USDOT Sent Draft Agreement Hand Off
Negotiating Agreement NDA Executed Offering: Mapping, application development Current Status: Met with HERE 5/30/17 to review status of program and potential partnership with HERE. HERE staff has been participating in advising on OVR project. Reached out to HERE to discuss data availabilty. Currently coordinating.
Honda Total Value $2,600,000
Primary Grant USDOT Agreement Executed 6/6/2017 Introductory Discussion X Agreement Sent to USDOT 6/6/2017
Sent Draft Agreement X Hand Off 6/6/17 to R. Bollo and B. Braughton Negotiating Agreement X NDA Executed Executed 11/29/2016
Offering: $1.6M Labor, $1.54M hardware, $0.6M software Current Status: Cooperative agreement executed 6/6/17.
INRIX Total Value $1,424,000
Primary Grant USDOT Agreement Executed 6/20/2017 Introductory Discussion X Agreement Sent to USDOT 6/22/2017
Sent Draft Agreement X Hand Off Negotiating Agreement X NDA Executed Executed 04/24/2017
Offering: Data and application development Current Status: Cooperative agreement executed 6/20/17. Calls with INRIX to understand product in November 2017.
MORPC Total Value $600,000
Primary Grant USDOT Agreement Executed 1/5/2017 Introductory Discussion X Agreement Sent to USDOT 1/5/2017
Sent Draft Agreement X Hand Off Negotiating Agreement X NDA Executed Covered in cooperative agreement
Offering: $600K cash for EV charging station design and installation Current Status: Cooperative agreement executed 1/5/17.
ODOT Total Value $7,000,000
Primary Grant USDOT Agreement Executed 3/22/2017 Introductory Discussion X Agreement Sent to USDOT 3/22/2017
Sent Draft Agreement X Hand Off Negotiating Agreement X NDA Executed Covered in cooperative agreement
Offering: In-kind staff support and data services Current Status: Cooperative agreement executed 3/22/17. Received INRIX data use agreement through ODOT partnership 9/7/17; sent to legal for review 9/7/17. USDOT has approved $2,991,690 as cost share.
OSU Total Value $64,000,000
Primary Grant USDOT Agreement Executed 12/21/2016 Introductory Discussion X Agreement Sent to USDOT 1/19/2017
Sent Draft Agreement X Hand Off Negotiating Agreement X NDA Executed Covered in cooperative agreement
Offering: $2M cash for USDOT projects; $5M in-kind EV program support; and $8M in-kind program support for mobility, smart grid and related areas Current Status: Cooperative agreement executed 12/21/2016. OSU working to invest $2M in work by faculty, staff & students. New relationship manager began 1/22/18. Working with OSU to get $2M approved by their fiscal department for submission as cost share to USDOT.
Smart City Schedule Cooperative Agreement No. DTFH6116H00013
Partnership/Stakeholder Status Summary
1/28/2019 Page 4 of 4
Electrification Partners
DC Solar Total Value $1,500,000 Primary Grant Vulcan Agreement Executed 2/2/2017
Introductory Discussion X Agreement Sent to USDOT 2/24/2017 Sent Draft Agreement X Hand Off 4/10/17 to B. Braughton
Negotiating Agreement X NDA Executed Executed 11/14/2016 Offering: DC Solar will partner with the City to deploy eight to ten mobile solar generators or EV charging stations in 11 month increments at locations in the City to be determined. Mobile solar generators and EV charging stations will demonstrate the use of renewable energy sources in support of fleet electrification and power generation. Current Status: Cooperative agreement executed 2/2/17.
Vulcan Total Value $10,000,000
Primary Grant Vulcan Agreement Executed 4/25/2017 Introductory Discussion X Agreement Sent to USDOT
Sent Draft Agreement X Hand Off 4/25/17 to B. Braughton Negotiating Agreement X NDA Executed N/A
Offering: Electrification initiatives Current Status: 2017 grant agreement executed 4/27/17. Finalized Year 2 budget in March 2018. Year 3 contract to be executed in or before Jan 2019.
Smart City Challenge Demonstration Quarterly Report: 2018 4th Quarter (October 2018 – December 2018) 32
Schedule Update
Current schedule for the project
Status of schedule
1) The next pages contain a schedule.
ID Outline Number
Task Name Duration %Complete
Start Finish Predecessors
1 1 Project Milestones 1169 days 96% Thu 8/18/16 Wed 3/31/21
2 1.1 CoC Task 1 Notice to Proceed (NTP) 0 days 100% Thu 8/18/16 Thu 8/18/16
3 1.2 USDOT Cooperative Agreement NTP 0 days 100% Tue 8/30/16 Tue 8/30/16
4 1.3 CoC Task 2 NTP 0 days 100% Mon 10/3/16 Mon 10/3/16
5 1.4 Independent Evaluator NTP 0 days 100% Wed 9/14/16 Wed 9/14/16
6 1.5 USDOT/City Reset Meeting 1 day 100% Thu 9/7/17 Thu 9/7/17
7 1.6 USDOT Authorization to Resume Phase I ‐ Systems Engineering Activities 22 days 100% Wed 12/20/17 Thu 1/18/18
8 1.7 Project End 1 day 0% Wed 3/31/21 Wed 3/31/21 227,309,556
9 2 Program Management 1205 days 82% Thu 8/18/16 Thu 5/20/21
10 2.1 USDOT Kick Off Meeting 19 days 100% Thu 8/18/16 Tue 9/13/16
11 2.1.1 Prepare for Kick Off Meeting 10 days 100% Thu 8/18/16 Wed 8/31/16 3
12 2.1.2 USDOT Kick Off Meeting (Task A) 2 days 100% Mon 9/12/16 Tue 9/13/16 11
13 2.2 Project Management Plan (PMP) 1004 days 89% Thu 8/18/16 Thu 7/30/20
14 2.2.1 PMP Original 118 days 100% Thu 8/18/16 Mon 1/30/17
37 2.2.2 PMP Version 2.0 63 days 100% Mon 9/11/17 Wed 12/6/17
72 2.2.3 Quarterly PMP Update (as necessary) 895 days 50% Wed 1/18/17 Thu 7/30/20
73 2.2.3.1 Quarterly PMP Update (as necessary) 1 9 days 100% Wed 1/18/17 Mon 1/30/17
74 2.2.3.2 Quarterly PMP Update 2 (DEPRECATED) 10 days 100% Tue 10/17/17 Mon 10/30/17
75 2.2.3.3 Quarterly PMP Update 3 (as necessary) 20 days 100% Tue 1/16/18 Mon 2/12/18
76 2.2.3.4 Quarterly PMP Update (as necessary) 6 10 days 100% Tue 4/17/18 Mon 4/30/18
77 2.2.3.5 Quarterly PMP Update (as necessary) 7 10 days 100% Tue 7/17/18 Mon 7/30/18
78 2.2.3.6 Quarterly PMP Update (as necessary) 8 10 days 100% Wed 10/17/18 Tue 10/30/18
79 2.2.3.7 Quarterly PMP Update (as necessary) 9 10 days 0% Wed 1/16/19 Wed 1/30/19
80 2.2.3.8 Quarterly PMP Update (as necessary) 10 10 days 0% Wed 4/17/19 Tue 4/30/19
81 2.2.3.9 Quarterly PMP Update (as necessary) 11 10 days 0% Wed 7/17/19 Tue 7/30/19
82 2.2.3.10 Quarterly PMP Update (as necessary) 12 10 days 0% Thu 10/17/19 Wed 10/30/19
83 2.2.3.11 Quarterly PMP Update (as necessary) 13 10 days 0% Thu 1/16/20 Thu 1/30/20
84 2.2.3.12 Quarterly PMP Update (as necessary) 14 10 days 0% Fri 4/17/20 Thu 4/30/20
8/18
8/30
10/3
9/14
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q2016 2017 2018 2019 2020 2021
Smart City ScheduleCooperative Agreement No. DTFH6116H00013
Smart Columbus Project - All Activities
file: SCC‐A‐SmartColumbus Program Schedule_revised_v8.mpp Page: 1/58 Printed on: Mon 1/28/19 @ 1:59 PM
ID Outline Number
Task Name Duration %Complete
Start Finish Predecessors
85 2.2.3.13 Quarterly PMP Update (as necessary) 15 10 days 0% Fri 7/17/20 Thu 7/30/20
86 2.3 Schedule 1108 days 67% Thu 8/18/16 Thu 12/31/20
87 2.3.1 Detailed SmartColumbus Schedule (SCS) 412 days 100% Thu 8/18/16 Wed 3/21/18
98 2.3.2 SCS Monthly Updates 1058 days 69% Thu 10/27/16 Thu 12/31/20
99 2.3.2.1 SCS Monthly Updates 1 3 days 100% Thu 10/27/16 Mon 10/31/16 93
100 2.3.2.2 SCS Monthly Updates 2 3 days 100% Mon 11/28/16 Wed 11/30/16
101 2.3.2.3 SCS Monthly Updates 3 3 days 100% Tue 1/3/17 Thu 1/5/17
102 2.3.2.4 SCS Monthly Updates 4 3 days 100% Fri 1/27/17 Tue 1/31/17
103 2.3.2.5 SCS Monthly Updates 5 7 days 100% Fri 2/17/17 Tue 2/28/17
104 2.3.2.6 SCS Monthly Updates 6 7 days 100% Thu 3/23/17 Fri 3/31/17
105 2.3.2.7 SCS Monthly Updates 7 7 days 100% Thu 4/20/17 Fri 4/28/17
106 2.3.2.8 SCS Monthly Updates 8 7 days 100% Mon 5/22/17 Wed 5/31/17
107 2.3.2.9 SCS Monthly Updates 9 7 days 100% Thu 6/22/17 Fri 6/30/17
108 2.3.2.10 SCS Monthly Updates 10 7 days 100% Fri 7/21/17 Mon 7/31/17
109 2.3.2.11 SCS Monthly Updates 11 7 days 100% Wed 8/23/17 Thu 8/31/17
110 2.3.2.12 SCS Monthly Updates 12 (DEPRECATED) 7 days 100% Thu 9/21/17 Fri 9/29/17
111 2.3.2.13 SCS Monthly Updates 13 7 days 100% Mon 10/23/17 Tue 10/31/17
112 2.3.2.14 SCS Monthly Updates 14 7 days 100% Mon 11/20/17 Thu 11/30/17
113 2.3.2.15 SCS Monthly Updates 15 7 days 100% Thu 12/7/17 Fri 12/15/17
114 2.3.2.16 SCS Monthly Updates 16 7 days 100% Tue 1/23/18 Wed 1/31/18
115 2.3.2.17 SCS Monthly Updates 17 (Lockdown Schedule Submission) 7 days 100% Wed 2/14/18 Fri 2/23/18
116 2.3.2.18 SCS Quarterly Updates 18 7 days 100% Thu 6/21/18 Fri 6/29/18
117 2.3.2.19 SCS Quarterly Updates 19 7 days 100% Thu 9/20/18 Fri 9/28/18
118 2.3.2.20 SCS Quarterly Updates 20 7 days 100% Thu 12/20/18 Mon 12/31/18
119 2.3.2.21 SCS Quarterly Updates 21 7 days 0% Thu 3/21/19 Fri 3/29/19
120 2.3.2.22 SCS Quarterly Updates 22 7 days 0% Thu 6/20/19 Fri 6/28/19
121 2.3.2.23 SCS Quarterly Updates 23 7 days 0% Fri 9/20/19 Mon 9/30/19
122 2.3.2.24 SCS Quarterly Updates 24 7 days 0% Fri 12/20/19 Tue 12/31/19
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q2016 2017 2018 2019 2020 2021
Smart City ScheduleCooperative Agreement No. DTFH6116H00013
Smart Columbus Project - All Activities
file: SCC‐A‐SmartColumbus Program Schedule_revised_v8.mpp Page: 2/58 Printed on: Mon 1/28/19 @ 1:59 PM
ID Outline Number
Task Name Duration %Complete
Start Finish Predecessors
123 2.3.2.25 SCS Quarterly Updates 25 7 days 0% Mon 3/23/20 Tue 3/31/20
124 2.3.2.26 SCS Quarterly Updates 26 7 days 0% Mon 6/22/20 Tue 6/30/20
125 2.3.2.27 SCS Quarterly Updates 27 7 days 0% Tue 9/22/20 Wed 9/30/20
126 2.3.2.28 SCS Quarterly Updates 28 7 days 0% Tue 12/22/20 Thu 12/31/20
127 2.3.3 SCS Monthly Submittal (Task A) 1056 days 27% Mon 10/31/16 Thu 12/31/20
128 2.3.3.1 SCS Monthly Submittal (Task A) 1 0 days 100% Mon 10/31/16 Mon 10/31/16
129 2.3.3.2 SCS Monthly Submittal (Task A) 2 0 days 100% Wed 11/30/16 Wed 11/30/16
130 2.3.3.3 SCS Monthly Submittal (Task A) 3 0 days 100% Thu 1/5/17 Thu 1/5/17
131 2.3.3.4 SCS Monthly Submittal (Task A) 4 0 days 100% Mon 1/30/17 Mon 1/30/17
132 2.3.3.5 SCS Monthly Submittal (Task A) 5 0 days 100% Tue 2/28/17 Tue 2/28/17
133 2.3.3.6 SCS Monthly Submittal (Task A) 6 0 days 100% Fri 3/31/17 Fri 3/31/17
134 2.3.3.7 SCS Monthly Submittal (Task A) 7 0 days 100% Fri 4/28/17 Fri 4/28/17
135 2.3.3.8 SCS Monthly Submittal (Task A) 8 0 days 100% Wed 5/31/17 Wed 5/31/17
136 2.3.3.9 SCS Monthly Submittal (Task A) 9 0 days 100% Fri 6/30/17 Fri 6/30/17
137 2.3.3.10 SCS Monthly Submittal (Task A) 10 0 days 100% Mon 7/31/17 Mon 7/31/17
138 2.3.3.11 SCS Monthly Submittal (Task A) 11 (DEPRECATED) 0 days 100% Wed 8/30/17 Wed 8/30/17
139 2.3.3.12 SCS Monthly Submittal (Task A) 12 0 days 100% Fri 10/6/17 Fri 10/6/17 64FF
140 2.3.3.13 SCS Monthly Submittal (Task A) 13 0 days 100% Tue 10/31/17 Tue 10/31/17
141 2.3.3.14 SCS Monthly Submittal (Task A) 14 0 days 100% Thu 11/30/17 Thu 11/30/17
142 2.3.3.15 SCS Monthly Submittal (Task A) 15 0 days 100% Fri 12/29/17 Fri 12/29/17
143 2.3.3.16 SCS Monthly Submittal (Task A) 16 0 days 100% Wed 1/31/18 Wed 1/31/18
144 2.3.3.17 SCS Monthly Submittal (Task A) 17 (Lockdown Schedule Submission) 0 days 100% Fri 2/23/18 Fri 2/23/18
145 2.3.3.18 SCS Quarterly Submittal to USDOT 18 7 days 100% Thu 6/21/18 Fri 6/29/18
146 2.3.3.19 SCS Quarterly Submittal to USDOT 19 7 days 100% Thu 9/20/18 Fri 9/28/18
147 2.3.3.20 SCS Quarterly Submittal to USDOT 20 7 days 100% Thu 12/20/18 Mon 12/31/18
148 2.3.3.21 SCS Quarterly Submittal to USDOT 21 7 days 0% Thu 3/21/19 Fri 3/29/19
149 2.3.3.22 SCS Quarterly Submittal to USDOT 22 7 days 0% Thu 6/20/19 Fri 6/28/19
150 2.3.3.23 SCS Quarterly Submittal to USDOT 23 7 days 0% Fri 9/20/19 Mon 9/30/19
10/31
11/30
1/5
1/30
2/28
3/31
4/28
5/31
6/30
7/31
8/30
10/6
10/31
11/30
12/29
1/31
2/23
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q2016 2017 2018 2019 2020 2021
Smart City ScheduleCooperative Agreement No. DTFH6116H00013
Smart Columbus Project - All Activities
file: SCC‐A‐SmartColumbus Program Schedule_revised_v8.mpp Page: 3/58 Printed on: Mon 1/28/19 @ 1:59 PM
ID Outline Number
Task Name Duration %Complete
Start Finish Predecessors
151 2.3.3.24 SCS Quarterly Submittal to USDOT 24 7 days 0% Fri 12/20/19 Tue 12/31/19
152 2.3.3.25 SCS Quarterly Submittal to USDOT 25 7 days 0% Mon 3/23/20 Tue 3/31/20
153 2.3.3.26 SCS Quarterly Submittal to USDOT 26 7 days 0% Mon 6/22/20 Tue 6/30/20
154 2.3.3.27 SCS Quarterly Submittal to USDOT 27 7 days 0% Tue 9/22/20 Wed 9/30/20
155 2.3.3.28 SCS Quarterly Submittal to USDOT 28 7 days 0% Tue 12/22/20 Thu 12/31/20
156 2.4 Partnership/Stakeholder Status 136 days 100% Thu 8/18/16 Thu 2/23/17
179 2.5 Quarterly Reports 915 days 55% Tue 1/3/17 Wed 8/12/20
180 2.5.1 Prepare Quarterly Progress Report (Task A) 907 days 55% Tue 1/3/17 Fri 7/31/20
181 2.5.1.1 Prepare Quarterly Progress Report 1 20 days 100% Tue 1/3/17 Mon 1/30/17
182 2.5.1.2 Prepare Quarterly Progress Report 2 21 days 100% Fri 3/31/17 Fri 4/28/17
183 2.5.1.3 Prepare Quarterly Progress Report 3 21 days 100% Fri 6/30/17 Fri 7/28/17
184 2.5.1.4 Prepare Quarterly Progress Report 4 21 days 100% Mon 10/2/17 Mon 10/30/17
185 2.5.1.5 Prepare Quarterly Progress Report 5 20 days 100% Wed 1/3/18 Tue 1/30/18
186 2.5.1.6 Prepare Quarterly Progress Report 6 21 days 100% Mon 4/2/18 Mon 4/30/18
187 2.5.1.7 Prepare Quarterly Progress Report 7 21 days 100% Mon 7/2/18 Tue 7/31/18
188 2.5.1.8 Prepare Quarterly Progress Report 8 21 days 100% Tue 10/2/18 Wed 10/31/18
189 2.5.1.9 Prepare Quarterly Progress Report 9 21 days 30% Wed 1/2/19 Thu 1/31/19
190 2.5.1.10 Prepare Quarterly Progress Report 10 21 days 0% Tue 4/2/19 Tue 4/30/19
191 2.5.1.11 Prepare Quarterly Progress Report 11 21 days 0% Tue 7/2/19 Wed 7/31/19
192 2.5.1.12 Prepare Quarterly Progress Report 12 21 days 0% Wed 10/2/19 Thu 10/31/19
193 2.5.1.13 Prepare Quarterly Progress Report 13 21 days 0% Thu 1/2/20 Fri 1/31/20
194 2.5.1.14 Prepare Quarterly Progress Report 14 21 days 0% Thu 4/2/20 Thu 4/30/20
195 2.5.1.15 Prepare Quarterly Progress Report 15 21 days 0% Thu 7/2/20 Fri 7/31/20
196 2.5.2 Submit Quarterly Progress Report (Task A) 886 days 0% Mon 1/30/17 Thu 7/30/20
197 2.5.2.1 Submit Quarterly Progress Report (Task A) 1 0 days 100% Mon 1/30/17 Mon 1/30/17
198 2.5.2.2 Submit Quarterly Progress Report (Task A) 2 0 days 100% Fri 4/28/17 Fri 4/28/17
199 2.5.2.3 Submit Quarterly Progress Report (Task A) 3 0 days 100% Sun 7/30/17 Sun 7/30/17
200 2.5.2.4 Submit Quarterly Progress Report (Task A) 4 0 days 100% Mon 10/30/17 Mon 10/30/17
1/30
4/28
7/30
10/30
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q2016 2017 2018 2019 2020 2021
Smart City ScheduleCooperative Agreement No. DTFH6116H00013
Smart Columbus Project - All Activities
file: SCC‐A‐SmartColumbus Program Schedule_revised_v8.mpp Page: 4/58 Printed on: Mon 1/28/19 @ 1:59 PM
ID Outline Number
Task Name Duration %Complete
Start Finish Predecessors
201 2.5.2.5 Submit Quarterly Progress Report (Task A) 5 0 days 100% Tue 1/30/18 Tue 1/30/18
202 2.5.2.6 Submit Quarterly Progress Report (Task A) 6 0 days 100% Mon 4/30/18 Mon 4/30/18
203 2.5.2.7 Submit Quarterly Progress Report (Task A) 7 0 days 100% Mon 7/30/18 Mon 7/30/18
204 2.5.2.8 Submit Quarterly Progress Report (Task A) 8 0 days 100% Tue 10/30/18 Tue 10/30/18
205 2.5.2.9 Submit Quarterly Progress Report (Task A) 9 0 days 0% Wed 1/30/19 Wed 1/30/19
206 2.5.2.10 Submit Quarterly Progress Report (Task A) 10 0 days 0% Tue 4/30/19 Tue 4/30/19
207 2.5.2.11 Submit Quarterly Progress Report (Task A) 11 0 days 0% Tue 7/30/19 Tue 7/30/19
208 2.5.2.12 Submit Quarterly Progress Report (Task A) 12 0 days 0% Wed 10/30/19 Wed 10/30/19
209 2.5.2.13 Submit Quarterly Progress Report (Task A) 13 0 days 0% Thu 1/30/20 Thu 1/30/20
210 2.5.2.14 Submit Quarterly Progress Report (Task A) 14 0 days 0% Thu 4/30/20 Thu 4/30/20
211 2.5.2.15 Submit Quarterly Progress Report (Task A) 15 0 days 0% Thu 7/30/20 Thu 7/30/20
212 2.5.3 Quarterly Project Briefing (Task A) 889 days 53% Wed 2/8/17 Wed 8/12/20
213 2.5.3.1 Quarterly Project Briefing (Task A) 1 1 day 100% Wed 2/8/17 Wed 2/8/17
214 2.5.3.2 Quarterly Project Briefing (Task A) 2 1 day 100% Wed 5/10/17 Wed 5/10/17
215 2.5.3.3 Quarterly Project Briefing (Task A) 3 1 day 100% Thu 9/7/17 Thu 9/7/17
216 2.5.3.4 Quarterly Project Briefing (Task A) 4 1 day 100% Wed 11/8/17 Wed 11/8/17
217 2.5.3.5 Quarterly Project Briefing (Task A) 5 1 day 100% Wed 3/7/18 Wed 3/7/18
218 2.5.3.6 Quarterly Project Briefing (Task A) 6 1 day 100% Wed 5/9/18 Wed 5/9/18
219 2.5.3.7 Quarterly Project Briefing (Task A) 7 1 day 100% Wed 8/8/18 Wed 8/8/18
220 2.5.3.8 Quarterly Project Briefing (Task A) 8 1 day 100% Wed 11/14/18 Wed 11/14/18
221 2.5.3.9 Quarterly Project Briefing (Task A) 9 1 day 0% Wed 2/13/19 Wed 2/13/19
222 2.5.3.10 Quarterly Project Briefing (Task A) 10 1 day 0% Wed 5/8/19 Wed 5/8/19
223 2.5.3.11 Quarterly Project Briefing (Task A) 11 1 day 0% Wed 8/14/19 Wed 8/14/19
224 2.5.3.12 Quarterly Project Briefing (Task A) 12 1 day 0% Wed 11/13/19 Wed 11/13/19
225 2.5.3.13 Quarterly Project Briefing (Task A) 13 1 day 0% Wed 2/12/20 Wed 2/12/20
226 2.5.3.14 Quarterly Project Briefing (Task A) 14 1 day 0% Wed 5/13/20 Wed 5/13/20
227 2.5.3.15 Quarterly Project Briefing (Task A) 15 1 day 0% Wed 8/12/20 Wed 8/12/20
228 2.6 Interim and Final Reporting 944 days 43% Fri 8/18/17 Thu 5/20/21
1/30
4/30
7/30
10/30
1/30
4/30
7/30
10/30
1/30
4/30
7/30
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q2016 2017 2018 2019 2020 2021
Smart City ScheduleCooperative Agreement No. DTFH6116H00013
Smart Columbus Project - All Activities
file: SCC‐A‐SmartColumbus Program Schedule_revised_v8.mpp Page: 5/58 Printed on: Mon 1/28/19 @ 1:59 PM
ID Outline Number
Task Name Duration %Complete
Start Finish Predecessors
229 2.6.1 Year 1 Report 31 days 100% Fri 8/18/17 Fri 9/29/17
236 2.6.2 Final Report Submittal (Task J) ‐ TBD 28 days 0% Thu 4/1/21 Mon 5/10/21
237 2.6.2.1 Develop Draft 15 days 0% Thu 4/1/21 Wed 4/21/21 1255,1383,1568,166
238 2.6.2.2 Prepare Draft Final Report 10 days 0% Thu 4/22/21 Wed 5/5/21 237
239 2.6.2.3 QAQC Final Report 3 days 0% Thu 5/6/21 Mon 5/10/21 238
240 2.6.2.4 Submit Final Report 0 days 0% Mon 5/10/21 Mon 5/10/21 239
241 2.6.3 Close Out Meeting 11 days 0% Thu 5/6/21 Thu 5/20/21
242 2.6.3.1 Close Out Meeting Preparation 10 days 0% Thu 5/6/21 Wed 5/19/21 238
243 2.6.3.2 Project Close Out Meeting 1 day 0% Thu 5/20/21 Thu 5/20/21 242
244 2.7 Program Execution 1082 days 95% Sat 9/10/16 Thu 12/17/20
245 2.7.1 Human Resources Management 205 days 100% Mon 9/11/17 Thu 6/28/18
246 2.7.1.1 Urgent Needs 53 days 100% Mon 9/11/17 Wed 11/22/17
252 2.7.1.2 Long Range Planning 150 days 100% Mon 11/27/17 Thu 6/28/18
255 2.7.2 Cost Management 993 days 99% Sat 9/10/16 Mon 8/10/20
310 2.7.3 Technical Working Groups (TWGs) 1080 days 86% Wed 9/14/16 Thu 12/17/20
311 2.7.3.1 Working Group Coordination Original 51 days 100% Wed 9/14/16 Wed 11/23/16
324 2.7.3.2 Technical Working Group Review 49 days 100% Wed 11/1/17 Wed 1/10/18
331 2.7.3.3 Data TWG 1035 days 72% Wed 11/16/16 Thu 12/17/20
332 2.7.3.3.1 Meeting #1 62 days 100% Wed 11/16/16 Thu 2/9/17
340 2.7.3.3.2 Meeting #2 19 days 100% Mon 6/26/17 Thu 7/20/17
348 2.7.3.3.3 Meeting #3 46 days 100% Fri 11/17/17 Tue 1/23/18
356 2.7.3.3.4 Monthly Data TWG Coordination Meeting 741 days 31% Thu 2/15/18 Thu 12/17/20
357 2.7.3.3.4.1 Monthly Data TWG Coordination Meeting 1 1 day 100% Thu 2/15/18 Thu 2/15/18
358 2.7.3.3.4.2 Monthly Data TWG Coordination Meeting 2 1 day 100% Thu 3/15/18 Thu 3/15/18
359 2.7.3.3.4.3 Monthly Data TWG Coordination Meeting 3 1 day 100% Thu 4/19/18 Thu 4/19/18
360 2.7.3.3.4.4 Monthly Data TWG Coordination Meeting 4 1 day 100% Thu 5/17/18 Thu 5/17/18
361 2.7.3.3.4.5 Monthly Data TWG Coordination Meeting 5 1 day 100% Wed 6/6/18 Wed 6/6/18
362 2.7.3.3.4.6 Monthly Data TWG Coordination Meeting 6 1 day 100% Thu 7/19/18 Thu 7/19/18
5/10
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q2016 2017 2018 2019 2020 2021
Smart City ScheduleCooperative Agreement No. DTFH6116H00013
Smart Columbus Project - All Activities
file: SCC‐A‐SmartColumbus Program Schedule_revised_v8.mpp Page: 6/58 Printed on: Mon 1/28/19 @ 1:59 PM
ID Outline Number
Task Name Duration %Complete
Start Finish Predecessors
363 2.7.3.3.4.7 Monthly Data TWG Coordination Meeting 7 1 day 100% Thu 8/16/18 Thu 8/16/18
364 2.7.3.3.4.8 Monthly Data TWG Coordination Meeting 8 1 day 100% Thu 9/20/18 Thu 9/20/18
365 2.7.3.3.4.9 Monthly Data TWG Coordination Meeting 9 1 day 100% Thu 10/18/18 Thu 10/18/18
366 2.7.3.3.4.10 Monthly Data TWG Coordination Meeting 10 1 day 100% Thu 11/15/18 Thu 11/15/18
367 2.7.3.3.4.11 Monthly Data TWG Coordination Meeting 11 1 day 100% Thu 12/20/18 Thu 12/20/18
368 2.7.3.3.4.12 Monthly Data TWG Coordination Meeting 12 1 day 0% Thu 1/17/19 Thu 1/17/19
369 2.7.3.3.4.13 Monthly Data TWG Coordination Meeting 13 1 day 0% Thu 2/21/19 Thu 2/21/19
370 2.7.3.3.4.14 Monthly Data TWG Coordination Meeting 14 1 day 0% Thu 3/21/19 Thu 3/21/19
371 2.7.3.3.4.15 Monthly Data TWG Coordination Meeting 15 1 day 0% Thu 4/18/19 Thu 4/18/19
372 2.7.3.3.4.16 Monthly Data TWG Coordination Meeting 16 1 day 0% Thu 5/16/19 Thu 5/16/19
373 2.7.3.3.4.17 Monthly Data TWG Coordination Meeting 17 1 day 0% Thu 6/20/19 Thu 6/20/19
374 2.7.3.3.4.18 Monthly Data TWG Coordination Meeting 18 1 day 0% Thu 7/18/19 Thu 7/18/19
375 2.7.3.3.4.19 Monthly Data TWG Coordination Meeting 19 1 day 0% Thu 8/15/19 Thu 8/15/19
376 2.7.3.3.4.20 Monthly Data TWG Coordination Meeting 20 1 day 0% Thu 9/19/19 Thu 9/19/19
377 2.7.3.3.4.21 Monthly Data TWG Coordination Meeting 21 1 day 0% Thu 10/17/19 Thu 10/17/19
378 2.7.3.3.4.22 Monthly Data TWG Coordination Meeting 22 1 day 0% Thu 11/21/19 Thu 11/21/19
379 2.7.3.3.4.23 Monthly Data TWG Coordination Meeting 23 1 day 0% Thu 12/19/19 Thu 12/19/19
380 2.7.3.3.4.24 Monthly Data TWG Coordination Meeting 24 1 day 0% Thu 1/16/20 Thu 1/16/20
381 2.7.3.3.4.25 Monthly Data TWG Coordination Meeting 25 1 day 0% Thu 2/20/20 Thu 2/20/20
382 2.7.3.3.4.26 Monthly Data TWG Coordination Meeting 26 1 day 0% Thu 3/19/20 Thu 3/19/20
383 2.7.3.3.4.27 Monthly Data TWG Coordination Meeting 27 1 day 0% Thu 4/16/20 Thu 4/16/20
384 2.7.3.3.4.28 Monthly Data TWG Coordination Meeting 28 1 day 0% Thu 5/21/20 Thu 5/21/20
385 2.7.3.3.4.29 Monthly Data TWG Coordination Meeting 29 1 day 0% Thu 6/18/20 Thu 6/18/20
386 2.7.3.3.4.30 Monthly Data TWG Coordination Meeting 30 1 day 0% Thu 7/16/20 Thu 7/16/20
387 2.7.3.3.4.31 Monthly Data TWG Coordination Meeting 31 1 day 0% Thu 8/20/20 Thu 8/20/20
388 2.7.3.3.4.32 Monthly Data TWG Coordination Meeting 32 1 day 0% Thu 9/17/20 Thu 9/17/20
389 2.7.3.3.4.33 Monthly Data TWG Coordination Meeting 33 1 day 0% Thu 10/15/20 Thu 10/15/20
390 2.7.3.3.4.34 Monthly Data TWG Coordination Meeting 34 1 day 0% Thu 11/19/20 Thu 11/19/20
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q2016 2017 2018 2019 2020 2021
Smart City ScheduleCooperative Agreement No. DTFH6116H00013
Smart Columbus Project - All Activities
file: SCC‐A‐SmartColumbus Program Schedule_revised_v8.mpp Page: 7/58 Printed on: Mon 1/28/19 @ 1:59 PM
ID Outline Number
Task Name Duration %Complete
Start Finish Predecessors
391 2.7.3.3.4.35 Monthly Data TWG Coordination Meeting 35 1 day 0% Thu 12/17/20 Thu 12/17/20
392 3 Design Guidance Planning Documents 954 days 40% Thu 6/15/17 Wed 3/31/21
393 3.1 Performance Measurement Plan (PfMP) 465 days 43% Thu 6/15/17 Tue 4/16/19
394 3.1.1 Draft PfMP 56 days 100% Thu 6/15/17 Thu 8/31/17
395 3.1.1.1 Prepare Draft PfMP 45 days 100% Thu 6/15/17 Wed 8/16/17 396SF
396 3.1.1.2 CoC Review 5 days 100% Fri 8/18/17 Thu 8/24/17 397SF
397 3.1.1.3 Update PfMP 5 days 100% Fri 8/25/17 Thu 8/31/17
398 3.1.2 Revised Draft PfMP 29 days 28% Mon 1/7/19 Fri 2/15/19
399 3.1.2.1 Update PfMP Based on SyRS Finalization 10 days 85% Mon 1/7/19 Fri 1/18/19 977,1292FS+10 days
400 3.1.2.2 CoC Review 5 days 0% Mon 1/21/19 Fri 1/25/19 399
401 3.1.2.3 Update Revised PfMP 5 days 0% Mon 1/28/19 Fri 2/1/19 400
402 3.1.2.4 Submit Revised PfMP to USDOT 0 days 0% Fri 2/1/19 Fri 2/1/19 401
403 3.1.2.5 USDOT Review Revised PfMP 10 days 0% Mon 2/4/19 Fri 2/15/19 402
404 3.1.3 Final PfMP 41 days 0% Fri 2/15/19 Tue 4/16/19
405 3.1.3.1 Receive USDOT Comments on Draft PfMP 0 days 0% Fri 2/15/19 Fri 2/15/19 403
406 3.1.3.2 Prepare Final PfMP 10 days 0% Mon 2/18/19 Fri 3/1/19 405
407 3.1.3.3 Prepare PfMP Comment Resolution Report (CRR) 10 days 0% Mon 2/18/19 Fri 3/1/19 405
408 3.1.3.4 Public Comment Period on PfMP 10 days 0% Mon 3/4/19 Fri 3/15/19 406
409 3.1.3.5 Webinar for PfMP 1 day 0% Mon 3/11/19 Mon 3/11/19 406FS+5 days
410 3.1.3.6 CoC Review 7 days 0% Mon 3/4/19 Tue 3/12/19 406,407
411 3.1.3.7 Update PfMP 15 days 0% Wed 3/13/19 Tue 4/2/19 410
412 3.1.3.8 Submit Final PfMP 0 days 0% Tue 4/2/19 Tue 4/2/19 411,408,409
413 3.1.3.9 Submit PfMP Comment Resolution Report 0 days 0% Fri 3/1/19 Fri 3/1/19 407
414 3.1.3.10 USDOT Review Final PfMP 10 days 0% Wed 4/3/19 Tue 4/16/19 412
415 3.1.3.11 Notice of USDOT Approval 0 days 0% Tue 4/16/19 Tue 4/16/19 414
416 3.2 Deployment Tracking Survey 187 days 0% Mon 12/3/18 Wed 8/28/19
417 3.2.1 USDOT ITS Deployment Tracking Survey Response 187 days 0% Mon 12/3/18 Wed 8/28/19
418 3.2.1.1 Prepare and submit response (est. 2018 as needed) 10 days 0% Mon 12/3/18 Fri 12/14/18
2/1
2/15
4/2
3/1
4/16
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q2016 2017 2018 2019 2020 2021
Smart City ScheduleCooperative Agreement No. DTFH6116H00013
Smart Columbus Project - All Activities
file: SCC‐A‐SmartColumbus Program Schedule_revised_v8.mpp Page: 8/58 Printed on: Mon 1/28/19 @ 1:59 PM
ID Outline Number
Task Name Duration %Complete
Start Finish Predecessors
419 3.2.1.2 Prepare and submit response (est. 2019) 20 days 0% Thu 8/1/19 Wed 8/28/19
420 3.3 Data Privacy Plan (DPP) 308 days 67% Tue 1/16/18 Mon 4/8/19
421 3.3.1 Draft DPP 241 days 100% Tue 1/16/18 Mon 12/31/18
422 3.3.1.1 Prepare Draft DPP 75 days 100% Tue 1/16/18 Mon 4/30/18 353
423 3.3.1.2 CoC Review 10 days 100% Tue 5/1/18 Mon 5/14/18 422
424 3.3.1.3 Update DPP 10 days 100% Tue 5/15/18 Mon 5/28/18 423
425 3.3.1.4 QA/QC 3 days 100% Tue 5/29/18 Thu 5/31/18 424
426 3.3.1.5 CoC Final Review 5 days 100% Fri 6/1/18 Thu 6/7/18 425
427 3.3.1.6 Submit Draft Data Privacy Plan (Task D) 0 days 100% Thu 6/7/18 Thu 6/7/18 426
428 3.3.1.7 USDOT Review Draft DPP 10 days 100% Fri 6/8/18 Thu 6/21/18 427
429 3.3.1.8 Receive USDOT Comments on Draft DPP 0 days 100% Thu 6/21/18 Thu 6/21/18 428
430 3.3.1.9 Prepare Quarterly Update of DPP 1 10 days 100% Mon 9/17/18 Fri 9/28/18 429
431 3.3.1.10 Prepare Quarterly Update of DPP 2 10 days 100% Mon 12/17/18 Mon 12/31/18 430
432 3.3.2 Final DPP 126 days 13% Wed 10/3/18 Mon 4/8/19
433 3.3.2.1 Public Comment Period on DPP 10 days 100% Wed 10/3/18 Wed 10/17/18
434 3.3.2.2 Webinar for DPP 1 day 100% Wed 10/10/18 Wed 10/10/18
435 3.3.2.3 Prepare Final DPP (All SyRS' finalized) 10 days 0% Mon 1/7/19 Fri 1/18/19 399SS,977,1292FS+1
436 3.3.2.4 CoC Review 5 days 0% Mon 1/21/19 Fri 1/25/19 435
437 3.3.2.5 Update DPP 4 days 0% Mon 1/28/19 Thu 1/31/19 436
438 3.3.2.6 QA/QC 3 days 0% Fri 2/1/19 Tue 2/5/19 437
439 3.3.2.7 CoC Final Review 3 days 0% Wed 2/6/19 Fri 2/8/19 438
440 3.3.2.8 Submit Final DPP to USDOT 0 days 0% Fri 2/8/19 Fri 2/8/19 439
441 3.3.2.9 USDOT Review Final DPP 10 days 0% Mon 2/11/19 Mon 2/25/19 440
442 3.3.2.10 Receive USDOT Comments on DPP 0 days 0% Mon 2/25/19 Mon 2/25/19 441
443 3.3.2.11 Prepare Revised Final DPP 10 days 0% Tue 2/26/19 Mon 3/11/19 442
444 3.3.2.12 CoC Review 5 days 0% Tue 3/12/19 Mon 3/18/19 443
445 3.3.2.13 Update DPP 5 days 0% Tue 3/19/19 Mon 3/25/19 444
446 3.3.2.14 QA/QC 3 days 0% Tue 3/26/19 Thu 3/28/19 445
6/7
6/21
2/8
2/25
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q2016 2017 2018 2019 2020 2021
Smart City ScheduleCooperative Agreement No. DTFH6116H00013
Smart Columbus Project - All Activities
file: SCC‐A‐SmartColumbus Program Schedule_revised_v8.mpp Page: 9/58 Printed on: Mon 1/28/19 @ 1:59 PM
ID Outline Number
Task Name Duration %Complete
Start Finish Predecessors
447 3.3.2.15 CoC Final Review 3 days 0% Fri 3/29/19 Tue 4/2/19 446
448 3.3.2.16 Submit Revised Final DPP 0 days 0% Mon 3/25/19 Mon 3/25/19 445
449 3.3.2.17 USDOT Review Final DPP 10 days 0% Tue 3/26/19 Mon 4/8/19 448
450 3.3.2.18 Receive USDOT Approval of Revised Final DPP 0 days 0% Mon 4/8/19 Mon 4/8/19 449
451 3.4 Independent Evaluation Support Plan (IESP) 494 days 1% Thu 6/29/17 Tue 6/11/19
452 3.4.1 Draft IESP 464 days 1% Thu 6/29/17 Mon 4/29/19
453 3.4.1.1 Independent Evaluation Kickoff Meeting 1 day 100% Thu 6/29/17 Thu 6/29/17
454 3.4.1.2 Receive IE Draft Data Needs 0 days 100% Thu 8/10/17 Thu 8/10/17 453SF+44 days
455 3.4.1.3 TTI Receive Final ConOps/Trade Study 0 days 100% Fri 11/16/18 Fri 11/16/18 950,1599,1688,1410
456 3.4.1.4 TTI Finalize IE Plan 60 days 0% Mon 11/19/18 Fri 2/15/19 455
457 3.4.1.5 Receive Final IE Plan from TTI 0 days 0% Fri 2/15/19 Fri 2/15/19 456
458 3.4.1.6 Assemble Draft IESP 40 days 0% Tue 2/19/19 Mon 4/15/19 457
459 3.4.1.7 CoC Review 5 days 0% Tue 4/16/19 Mon 4/22/19 458
460 3.4.1.8 Update IESP 5 days 0% Tue 4/23/19 Mon 4/29/19 459
461 3.4.1.9 Submit Draft IESP 0 days 0% Mon 4/29/19 Mon 4/29/19 460
462 3.4.2 Final IESP 30 days 0% Tue 4/30/19 Tue 6/11/19
463 3.4.2.1 USDOT Review Draft IESP 10 days 0% Tue 4/30/19 Mon 5/13/19 461
464 3.4.2.2 Receive USDOT Comments on Draft IESP 0 days 0% Mon 5/13/19 Mon 5/13/19 463
465 3.4.2.3 Public Comment Period for IESP 10 days 0% Tue 5/14/19 Tue 5/28/19 464
466 3.4.2.4 Webinar for IESP 1 day 0% Tue 5/21/19 Tue 5/21/19 464SS+5 days
467 3.4.2.5 Assemble Final IESP 10 days 0% Tue 5/14/19 Tue 5/28/19 464
468 3.4.2.6 Prepare IESP Comment Resolution Report (CRR) 10 days 0% Tue 5/14/19 Tue 5/28/19 464
469 3.4.2.7 CoC Review 5 days 0% Wed 5/29/19 Tue 6/4/19 467,465
470 3.4.2.8 Updated IESP 5 days 0% Wed 6/5/19 Tue 6/11/19 469
471 3.4.2.9 Submit Final IESP 0 days 0% Tue 6/11/19 Tue 6/11/19 470
472 3.4.2.10 Submit IESP Comment Resolution Report 0 days 0% Tue 6/11/19 Tue 6/11/19 470
473 3.4.3 Data Available to IE Team 0 days 0% Tue 6/11/19 Tue 6/11/19
474 3.4.3.1 Data Available to IE Team 0 days 0% Tue 6/11/19 Tue 6/11/19 471,472
3/25
4/8
8/10
11/16
2/15
4/29
5/13
6/11
6/11
6/11
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q2016 2017 2018 2019 2020 2021
Smart City ScheduleCooperative Agreement No. DTFH6116H00013
Smart Columbus Project - All Activities
file: SCC‐A‐SmartColumbus Program Schedule_revised_v8.mpp Page: 10/58 Printed on: Mon 1/28/19 @ 1:59 PM
ID Outline Number
Task Name Duration %Complete
Start Finish Predecessors
475 3.5 Data Management Plan (DMP) 279 days 77% Tue 1/16/18 Tue 2/26/19
476 3.5.1 Draft DMP 241 days 100% Tue 1/16/18 Mon 12/31/18
477 3.5.1.1 Prepare Draft DMP 75 days 100% Tue 1/16/18 Mon 4/30/18 353
478 3.5.1.2 CoC Review 10 days 100% Tue 5/1/18 Mon 5/14/18 477
479 3.5.1.3 Update DMP 10 days 100% Tue 5/15/18 Mon 5/28/18 478
480 3.5.1.4 QA/QC 3 days 100% Tue 5/29/18 Thu 5/31/18 479
481 3.5.1.5 CoC Final Review 5 days 100% Fri 6/1/18 Thu 6/7/18 480
482 3.5.1.6 Submit Draft Data Management Plan (Task E) 0 days 100% Thu 6/7/18 Thu 6/7/18 481
483 3.5.1.7 USDOT Review Draft DMP 10 days 100% Fri 6/8/18 Thu 6/21/18 482
484 3.5.1.8 Receive USDOT Comments on Draft DMP 0 days 100% Thu 6/21/18 Thu 6/21/18 483
485 3.5.1.9 Prepare Quarterly Update of DMP 1 10 days 100% Mon 9/17/18 Fri 9/28/18 484
486 3.5.1.10 Prepare Quarterly Update of DMP 2 10 days 100% Mon 12/17/18 Mon 12/31/18 485
487 3.5.2 Final DMP 97 days 21% Wed 10/3/18 Tue 2/26/19
488 3.5.2.1 Public Comment Period on DPP 10 days 100% Wed 10/3/18 Wed 10/17/18
489 3.5.2.2 Webinar for DPP 1 day 100% Wed 10/10/18 Wed 10/10/18
490 3.5.2.3 Prepare Final DMP (All SyRS' Finalized) 10 days 0% Mon 1/7/19 Fri 1/18/19 977,1292FS+10 days
491 3.5.2.4 CoC Review 5 days 0% Mon 1/21/19 Fri 1/25/19 490
492 3.5.2.5 Update DMP 2 days 0% Mon 1/28/19 Tue 1/29/19 491
493 3.5.2.6 Submit Draft Final Data Management Plan (Task E) 0 days 0% Tue 1/29/19 Tue 1/29/19 492
494 3.5.2.7 USDOT Review Draft DMP 10 days 0% Wed 1/30/19 Tue 2/12/19 493
495 3.5.2.8 Prepare Updated DMP 5 days 0% Wed 2/13/19 Tue 2/19/19 494
496 3.5.2.9 Update Comment Resolution Report based on USDOT Comments on DMP
5 days 0% Wed 2/13/19 Tue 2/19/19 494
497 3.5.2.10 CoC Review 3 days 0% Wed 2/20/19 Fri 2/22/19 495,496
498 3.5.2.11 Update DMP 2 days 0% Mon 2/25/19 Tue 2/26/19 497
499 3.5.2.12 Submit DMP Comment Resolution Report 0 days 0% Tue 2/26/19 Tue 2/26/19 498
500 3.5.2.13 Submit Final DMP 0 days 0% Tue 2/26/19 Tue 2/26/19 498
501 3.6 Human Use Approval 193 days 0% Mon 6/3/19 Wed 3/11/20
502 3.6.1 Human Use Approval Summary 193 days 0% Mon 6/3/19 Wed 3/11/20
6/7
6/21
1/29
2/26
2/26
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q2016 2017 2018 2019 2020 2021
Smart City ScheduleCooperative Agreement No. DTFH6116H00013
Smart Columbus Project - All Activities
file: SCC‐A‐SmartColumbus Program Schedule_revised_v8.mpp Page: 11/58 Printed on: Mon 1/28/19 @ 1:59 PM
ID Outline Number
Task Name Duration %Complete
Start Finish Predecessors
503 3.6.1.1 Prepare Initial Human Use Approval Summary 52 days 0% Mon 6/3/19 Tue 8/13/19
504 3.6.1.2 CoC Review 5 days 0% Wed 8/14/19 Tue 8/20/19 503
505 3.6.1.3 Update Summary 3 days 0% Wed 8/21/19 Fri 8/23/19 504
506 3.6.1.4 Submit Draft Human Use Approval Request to USDOT 0 days 0% Fri 8/23/19 Fri 8/23/19 505
507 3.6.1.5 USDOT Review Draft Human Use Approval Request 10 days 0% Mon 8/26/19 Mon 9/9/19 506
508 3.6.1.6 Receive USDOT Comments on Draft Human Use Approval Summary 0 days 0% Mon 9/9/19 Mon 9/9/19 507
509 3.6.1.7 Public Comment Period for Human Use Approval Summary 10 days 0% Tue 9/10/19 Mon 9/23/19 508
510 3.6.1.8 Webinar for Human Use Approval Summary 1 day 0% Tue 9/17/19 Tue 9/17/19 509SS+5 days
511 3.6.1.9 Prepare Final Human Use Approval Summary 3 days 0% Tue 9/10/19 Thu 9/12/19 508
512 3.6.1.10 Submit Final Human Use Approval to USDOT 0 days 0% Mon 9/23/19 Mon 9/23/19 511,509
513 3.6.1.11 Prepare Quarterly Human Use Approval Summary Update 59 days 0% Mon 12/16/19 Wed 3/11/20
514 3.6.1.11.1 Prepare Quarterly Human Use Approval Summary Update 3 3 days 0% Mon 12/16/19 Wed 12/18/19
515 3.6.1.11.2 Prepare Quarterly Human Use Approval Summary Update 4 3 days 0% Mon 3/9/20 Wed 3/11/20 514,517
516 3.6.1.12 Submit Quarterly Human Use Approval Summary (Task F) 56 days 0% Wed 12/18/19 Wed 3/11/20
517 3.6.1.12.1 Submit Quarterly Human Use Approval Summary (Task F) 3 0 days 0% Wed 12/18/19 Wed 12/18/19 514
518 3.6.1.12.2 Submit Quarterly Human Use Approval Summary (Task F) 4 0 days 0% Wed 3/11/20 Wed 3/11/20 515
519 3.7 Safety Management Plan (SMP) 602 days 23% Wed 10/31/18 Wed 3/31/21
520 3.7.1 Draft SMP 30 days 100% Wed 10/31/18 Fri 12/14/18
521 3.7.1.1 Prepare Draft SMP 10 days 100% Wed 10/31/18 Wed 11/14/18 645,928,1267,1803,1
522 3.7.1.2 CoC Review 5 days 100% Thu 11/15/18 Wed 11/21/18 521
523 3.7.1.3 Updated SMP 5 days 100% Mon 11/26/18 Fri 11/30/18 522
524 3.7.1.4 Submit Draft Safety Management Plan (Task F) 0 days 100% Fri 11/30/18 Fri 11/30/18 523
525 3.7.1.5 USDOT Review Draft Safety Management Plan 10 days 100% Mon 12/3/18 Fri 12/14/18 524
526 3.7.2 Final SMP 218 days 0% Fri 12/14/18 Mon 10/28/19
527 3.7.2.1 Receive USDOT Comments on Draft SMP 0 days 100% Fri 12/14/18 Fri 12/14/18 525
528 3.7.2.2 Public Comment Period for SMP 10 days 0% Thu 1/3/19 Wed 1/16/19 527FS+11 days
529 3.7.2.3 Webinar for SMP 1 day 0% Thu 1/10/19 Thu 1/10/19 527SS+16 days
530 3.7.2.4 Prepare Final SMP 10 days 0% Mon 9/30/19 Fri 10/11/19 527,1734
8/23
9/9
9/23
12/18
3/11
11/30
12/14
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q2016 2017 2018 2019 2020 2021
Smart City ScheduleCooperative Agreement No. DTFH6116H00013
Smart Columbus Project - All Activities
file: SCC‐A‐SmartColumbus Program Schedule_revised_v8.mpp Page: 12/58 Printed on: Mon 1/28/19 @ 1:59 PM
ID Outline Number
Task Name Duration %Complete
Start Finish Predecessors
531 3.7.2.5 Prepare SMP Comment Resolution Report (CRR) 10 days 0% Mon 12/17/18 Mon 12/31/18 527
532 3.7.2.6 CoC Review 5 days 0% Tue 10/15/19 Mon 10/21/19 530,531
533 3.7.2.7 Update SMP 5 days 0% Tue 10/22/19 Mon 10/28/19 532
534 3.7.2.8 Submit Final SMP 0 days 0% Mon 10/28/19 Mon 10/28/19 533
535 3.7.2.9 Submit SMP Comment Resolution Report 0 days 0% Mon 10/28/19 Mon 10/28/19 533,588
536 3.7.3 Safety Assessments 480 days 0% Tue 4/30/19 Wed 3/31/21
537 3.7.3.1 Annual Safety Assessment (2019) 20 days 0% Tue 4/30/19 Tue 5/28/19 1668
538 3.7.3.2 Annual Safety Assessment (2020) 20 days 0% Fri 5/15/20 Fri 6/12/20 537SS+262 days
539 3.7.3.3 Final Safety Assessment (2021) 20 days 0% Thu 3/4/21 Wed 3/31/21
540 4 Management 807 days 52% Mon 10/3/16 Wed 12/4/19
541 4.1 Systems Engineering Management Plan (SEMP) 366 days 100% Mon 10/3/16 Thu 3/1/18
542 4.1.1 Draft SEMP 36 days 100% Mon 10/3/16 Mon 11/21/16
549 4.1.2 Final SEMP 76 days 100% Wed 12/7/16 Thu 3/23/17
564 4.1.3 508 Compliant Documentation 36 days 100% Fri 3/24/17 Fri 5/12/17
567 4.1.4 SEMP Version 2.0 80 days 100% Tue 10/10/17 Wed 1/31/18
591 4.1.5 508 Compliant Documentation Version 2.0 20 days 100% Thu 2/1/18 Thu 3/1/18
594 4.2 Demonstration Site Map and Installation Schedule 180 days 1% Tue 3/19/19 Wed 12/4/19
595 4.2.1 Draft Demonstration Site Map and Installation Schedule 50 days 3% Tue 3/19/19 Tue 5/28/19
596 4.2.1.1 Prepare Initial Demonstration Demonstration Site Map and Installation Schedule
15 days 10% Tue 3/19/19 Mon 4/8/19 950,1599,1688,1410days,1829,2005FS+1days
597 4.2.1.2 CoC Review 5 days 0% Tue 4/2/19 Mon 4/8/19 596FF
598 4.2.1.3 Update Demonstration Site Map and Installation Schedule 5 days 0% Tue 4/9/19 Mon 4/15/19 597
599 4.2.1.4 Submit Initial Site Map 0 days 0% Mon 4/15/19 Mon 4/15/19 598
600 4.2.1.5 USDOT Review Initial Site Map 10 days 0% Tue 4/16/19 Mon 4/29/19 599
601 4.2.1.6 Receive USDOT Comments on Draft Site Map and Schedule 0 days 0% Mon 4/29/19 Mon 4/29/19 600
602 4.2.1.7 Prepare Demonstration Site Map and Installation Schedule Comment Resolution Report
10 days 0% Tue 4/30/19 Mon 5/13/19 601
603 4.2.1.8 Review Comment Resolution Report with USDOT 1 day 0% Tue 5/14/19 Tue 5/14/19 602
604 4.2.1.9 Update Demonstration Site Map and Installation Schedule 5 days 0% Wed 5/15/19 Tue 5/21/19 603
10/28
10/28
4/15
4/29
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q2016 2017 2018 2019 2020 2021
Smart City ScheduleCooperative Agreement No. DTFH6116H00013
Smart Columbus Project - All Activities
file: SCC‐A‐SmartColumbus Program Schedule_revised_v8.mpp Page: 13/58 Printed on: Mon 1/28/19 @ 1:59 PM
ID Outline Number
Task Name Duration %Complete
Start Finish Predecessors
605 4.2.1.10 CoC Review 5 days 0% Wed 5/22/19 Tue 5/28/19 604
606 4.2.1.11 Submit Updated Site Map 0 days 0% Tue 5/28/19 Tue 5/28/19 605
607 4.2.2 Final Demonstration Site Map and Installation Schedule 45 days 0% Fri 9/27/19 Wed 12/4/19
608 4.2.2.1 Prepare Final Demonstration Site Map and Installation Schedule 10 days 0% Fri 9/27/19 Thu 10/10/19 1018FS+10 days,145
609 4.2.2.2 CoC Review 5 days 0% Fri 10/11/19 Thu 10/17/19 608
610 4.2.2.3 Update Demonstration Site Map and Installation Schedule 5 days 0% Fri 10/18/19 Thu 10/24/19 609
611 4.2.2.4 Submit Final Demonstration Site Map and Installation Schedule 0 days 0% Thu 10/24/19 Thu 10/24/19 610
612 4.2.2.5 USDOT Review Final Demonstration Map and Installation Schedule 10 days 0% Fri 10/25/19 Thu 11/7/19 611
613 4.2.2.6 Receive USDOT Comments on Demonstration Site Map and Installation Schedule
0 days 0% Thu 11/7/19 Thu 11/7/19 612
614 4.2.2.7 Public Comment Period for Site Map and Installation Schedule 10 days 0% Fri 11/8/19 Thu 11/21/19 613
615 4.2.2.8 Webinar for Site Map and Installation Schedule 1 day 0% Fri 11/15/19 Fri 11/15/19 613SS+5 days
616 4.2.2.9 Prepare Demonstration Site Map and Installation Schedule Comment Resolution Report
10 days 0% Fri 11/8/19 Thu 11/21/19 613
617 4.2.2.10 Update Demonstration Site Map and Installation Schedule 10 days 0% Fri 11/8/19 Thu 11/21/19 616SS
618 4.2.2.11 CoC Review 5 days 0% Fri 11/22/19 Thu 11/28/19 616,617,614
619 4.2.2.12 Update Demonstration Site Map and Installation Schedule 4 days 0% Fri 11/29/19 Wed 12/4/19 618
620 4.2.2.13 Submit Final Site Map 0 days 0% Wed 12/4/19 Wed 12/4/19 619
621 4.3 System Architecture and Standards Plan (SASP) 51 days 10% Thu 12/20/18 Wed 3/6/19
622 4.3.1 Draft SASP 32 days 21% Thu 12/20/18 Wed 2/6/19
623 4.3.1.1 Develop Draft SASP 15 days 50% Thu 12/20/18 Wed 1/9/19 977,1292,1426,1614
624 4.3.1.2 CoC Review 5 days 0% Thu 1/10/19 Wed 1/16/19 623
625 4.3.1.3 Update SASP 5 days 0% Thu 1/17/19 Wed 1/23/19 624
626 4.3.1.4 Submit Draft SASP 0 days 0% Wed 1/23/19 Wed 1/23/19 625
627 4.3.1.5 USDOT Review Draft SASP 10 days 0% Thu 1/24/19 Wed 2/6/19 626
628 4.3.2 Final SASP 19 days 0% Wed 2/6/19 Wed 3/6/19
629 4.3.2.1 Receive USDOT Comments on Draft SASP 0 days 0% Wed 2/6/19 Wed 2/6/19 627
630 4.3.2.2 Public Comment Period for SASP 10 days 0% Thu 2/7/19 Wed 2/20/19 629
631 4.3.2.3 Webinar for SASP 1 day 0% Thu 2/14/19 Thu 2/14/19 629SS+5 days
5/28
10/24
11/7
12/4
1/23
2/6
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q2016 2017 2018 2019 2020 2021
Smart City ScheduleCooperative Agreement No. DTFH6116H00013
Smart Columbus Project - All Activities
file: SCC‐A‐SmartColumbus Program Schedule_revised_v8.mpp Page: 14/58 Printed on: Mon 1/28/19 @ 1:59 PM
ID Outline Number
Task Name Duration %Complete
Start Finish Predecessors
632 4.3.2.4 Prepare Final SASP 10 days 0% Thu 2/7/19 Wed 2/20/19 629
633 4.3.2.5 Prepare SASP Comment Resolution Report 10 days 0% Thu 2/7/19 Wed 2/20/19 629
634 4.3.2.6 CoC Review 5 days 0% Thu 2/21/19 Wed 2/27/19 632,633,630
635 4.3.2.7 Update SASP 5 days 0% Thu 2/28/19 Wed 3/6/19 634
636 4.3.2.8 Submit Final SASP 0 days 0% Wed 3/6/19 Wed 3/6/19 635
637 4.3.2.9 Submit Comment Resolution Report for SASP 0 days 0% Wed 3/6/19 Wed 3/6/19 635
638 4.4 System of System Framework 29 days 100% Mon 12/4/17 Fri 1/12/18
639 4.4.1 Draft SoS Framework 29 days 100% Mon 12/4/17 Fri 1/12/18
646 4.5 RFP for Testing Contractor 109 days 0% Mon 1/14/19 Tue 6/18/19
647 4.5.1 Consultant Selection Process (QBS) (Professional Services) 73 days 0% Mon 1/14/19 Fri 4/26/19
648 4.5.1.1 Prepare project LOI / RFQ / RFP 10 days 0% Mon 1/14/19 Fri 1/25/19
649 4.5.1.2 USDOT Review of Request for Subcontractor Approval 5 days 0% Mon 1/28/19 Fri 2/1/19 648
650 4.5.1.3 Advertise LOI / RFQ / RFP in Performance Series 15 days 0% Mon 2/4/19 Fri 2/22/19 649
651 4.5.1.4 Receive Technical Proposals 1 day 0% Mon 2/25/19 Mon 2/25/19 650
652 4.5.1.5 Request highest ranking firm to define project scope of services 10 days 0% Tue 2/26/19 Mon 3/11/19 651
653 4.5.1.6 CINO Approval 2 days 0% Tue 3/12/19 Wed 3/13/19 652
654 4.5.1.7 Negotiate project final scope of services 10 days 0% Thu 3/14/19 Wed 3/27/19 653
655 4.5.1.8 Request Fee Proposal 10 days 0% Thu 3/28/19 Wed 4/10/19 654
656 4.5.1.9 Negotiate fees 10 days 0% Thu 4/11/19 Wed 4/24/19 655
657 4.5.1.10 Notify CINO 1 day 0% Thu 4/25/19 Thu 4/25/19 656
658 4.5.1.11 USDOT Review 1 day 0% Fri 4/26/19 Fri 4/26/19 657
659 4.5.2 Legislation Process 24 days 0% Thu 4/25/19 Wed 5/29/19
660 4.5.2.1 Prepare legislation and submit to Fiscal (min 2 working days days) 3 days 0% Thu 4/25/19 Mon 4/29/19 656
661 4.5.2.2 Fiscal modifies and processes legislation (min 6 working days) 3 days 0% Fri 4/26/19 Tue 4/30/19 657
662 4.5.2.3 To CIFO 2 days 0% Wed 5/1/19 Thu 5/2/19 661
663 4.5.2.4 To Finance 3 days 0% Fri 5/3/19 Tue 5/7/19 662
664 4.5.2.5 To Equal Business Opportunity (min 4 working days) 2 days 0% Wed 5/8/19 Thu 5/9/19 663
665 4.5.2.6 To Auditor (min 2 working days) 3 days 0% Fri 5/10/19 Tue 5/14/19 664
3/6
3/6
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q2016 2017 2018 2019 2020 2021
Smart City ScheduleCooperative Agreement No. DTFH6116H00013
Smart Columbus Project - All Activities
file: SCC‐A‐SmartColumbus Program Schedule_revised_v8.mpp Page: 15/58 Printed on: Mon 1/28/19 @ 1:59 PM
ID Outline Number
Task Name Duration %Complete
Start Finish Predecessors
666 4.5.2.7 To City Attorney (min 2 working days) 3 days 0% Wed 5/15/19 Fri 5/17/19 665
667 4.5.2.8 To City Clerk (min 6 working days) 5 days 0% Mon 5/20/19 Fri 5/24/19 666
668 4.5.2.9 Council passes legislation (Mon) 1 day 0% Tue 5/28/19 Tue 5/28/19 667
669 4.5.2.10 Mayor Signs (Thurs) 1 day 0% Wed 5/29/19 Wed 5/29/19 668
670 4.5.3 Contract Process 36 days 0% Mon 4/29/19 Tue 6/18/19
671 4.5.3.1 Prepare contract documents 4 days 0% Mon 4/29/19 Thu 5/2/19 658
672 4.5.3.2 Fiscal enters Performance information 2 days 0% Thu 5/30/19 Fri 5/31/19 669
673 4.5.3.3 Sent to Consultant and returned to City 7 days 0% Mon 5/20/19 Tue 5/28/19 666
674 4.5.3.4 To City Attorney 5 days 0% Mon 6/3/19 Fri 6/7/19 672
675 4.5.3.5 To Auditor 5 days 0% Mon 6/10/19 Fri 6/14/19 674
676 4.5.3.6 Notice to proceed issued 2 days 0% Mon 6/17/19 Tue 6/18/19 675
677 5 Projects 1169 days 33% Thu 8/18/16 Wed 3/31/21
678 5.1 SmartColumbus Operating System (SCOS) 1120 days 45% Mon 9/26/16 Mon 3/1/21
679 5.1.1 SCOS Strategy Plan 54 days 100% Mon 9/26/16 Thu 12/8/16
686 5.1.2 SCOS Architecture and Governance Story Workshop 168 days 100% Tue 1/10/17 Thu 8/31/17
696 5.1.3 SCOS Architecture and Governance Development 61 days 100% Thu 1/19/17 Thu 4/13/17
717 5.1.4 SCOS Platform Framework Story Workshop 3 days 100% Fri 3/24/17 Tue 3/28/17
720 5.1.5 SCOS Development 989 days 39% Tue 3/28/17 Mon 3/1/21
721 5.1.5.1 SCOS Phase I Sprints (Open Data Portal, DevOps, Real‐Time Data Streaming)
322 days 100% Tue 3/28/17 Tue 6/26/18
883 5.1.5.2 SCOS Phase II Sprints (Core Big Data Architecture) 254 days 99% Wed 6/27/18 Tue 6/18/19
884 5.1.5.2.1 SCOS Phase II Sprints (Core Big Data Architecture) 129 days 100% Wed 6/27/18 Mon 12/24/18 882
885 5.1.5.2.2 MVP ‐ Release 3 0 days 100% Tue 7/3/18 Tue 7/3/18 884SS
886 5.1.5.2.3 MVP ‐ Release 4 0 days 100% Tue 8/7/18 Tue 8/7/18 885
887 5.1.5.2.4 MVP ‐ Release 5 0 days 100% Tue 9/4/18 Tue 9/4/18 886
888 5.1.5.2.5 Data Platform 2.0 0 days 100% Tue 12/4/18 Tue 12/4/18 887
889 5.1.5.2.6 MMTPA Data Integration 0 days 100% Tue 12/18/18 Tue 12/18/18 888
890 5.1.5.2.7 Machine Learning Support/IDAM/Service Security Model 0 days 30% Mon 4/22/19 Mon 4/22/19 889
891 5.1.5.2.8 Application Hosting 0 days 0% Tue 6/18/19 Tue 6/18/19 890
7/3
8/7
9/4
12/4
12/18
4/22
6/18
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q2016 2017 2018 2019 2020 2021
Smart City ScheduleCooperative Agreement No. DTFH6116H00013
Smart Columbus Project - All Activities
file: SCC‐A‐SmartColumbus Program Schedule_revised_v8.mpp Page: 16/58 Printed on: Mon 1/28/19 @ 1:59 PM
ID Outline Number
Task Name Duration %Complete
Start Finish Predecessors
892 5.1.5.3 SCOS Phase III Sprints (Projects Data Exchange) 388 days 2% Wed 12/19/18 Tue 7/7/20
893 5.1.5.3.1 CEAV Data Integration (Vendor #1) 20 days 50% Wed 12/19/18 Thu 1/17/19 1773FF
894 5.1.5.3.2 MAPCD Data Integration 20 days 0% Tue 4/2/19 Mon 4/29/19 1668FF
895 5.1.5.3.3 PTA Data Integration 20 days 0% Fri 5/3/19 Fri 5/31/19 2049FF
896 5.1.5.3.4 MMTPA (Final) Data Integration 20 days 0% Fri 8/2/19 Thu 8/29/19 1381FF
897 5.1.5.3.5 CEAV Data Integration (Vendor #2‐3) 20 days 0% Tue 10/22/19 Tue 11/19/19 1774FF
898 5.1.5.3.6 MMTPA with CPS Data Integration 20 days 0% Mon 12/9/19 Tue 1/7/20 1382FF
899 5.1.5.3.7 SMH Data Integration 20 days 0% Fri 1/24/20 Fri 2/21/20 1567FF
900 5.1.5.3.8 SCOS Phase III Sprints (Projects Data Exchange) 304 days 0% Wed 12/26/18 Fri 3/13/20 884
901 5.1.5.3.9 EPM Data Integration 20 days 0% Fri 2/28/20 Thu 3/26/20 1981FF
902 5.1.5.3.10 CVE Data Integration 20 days 0% Tue 6/9/20 Tue 7/7/20 1254FF
903 5.1.5.4 SCOS Phase IV: Operations and Maintenance 240 days 0% Mon 3/16/20 Mon 3/1/21
904 5.1.5.4.1 Establish Operational Plan 240 days 0% Mon 3/16/20 Mon 3/1/21 900
905 5.1.5.4.2 Productization 240 days 0% Mon 3/16/20 Mon 3/1/21 900
906 5.1.5.4.3 Transition 182 days 0% Mon 3/16/20 Thu 12/3/20
907 5.1.5.4.3.1 Identify Transition Stakeholders 5 days 0% Mon 3/16/20 Fri 3/20/20 900
908 5.1.5.4.3.2 Transition Period 132 days 0% Mon 3/23/20 Fri 9/25/20 907
909 5.1.5.4.3.3 Deliver Technical Docs for Transition Activities 45 days 0% Mon 9/28/20 Thu 12/3/20 908
910 5.2 Connected Vehicle Environment (CVE) 1137 days 26% Mon 10/3/16 Wed 3/31/21
911 5.2.1 Phase I ‐ Systems Engineering 790 days 62% Mon 10/3/16 Wed 11/6/19
912 5.2.1.1 CVE Strategy Plan 120 days 100% Mon 10/3/16 Fri 3/17/17
919 5.2.1.2 CVE Concept of Operations (ConOps) 688 days 86% Tue 2/7/17 Tue 10/22/19
920 5.2.1.2.1 Draft CVE ConOps 119 days 100% Tue 2/7/17 Fri 7/21/17
929 5.2.1.2.2 CVE ConOps Walkthrough 2 days 100% Wed 8/9/17 Fri 8/11/17
934 5.2.1.2.3 Revised Draft CVE ConOps 82 days 100% Mon 1/22/18 Wed 5/16/18
943 5.2.1.2.4 Final CVE ConOps 26 days 100% Thu 5/17/18 Fri 6/22/18
951 5.2.1.2.5 508 Compliant Documentation 20 days 100% Mon 6/25/18 Mon 7/23/18
954 5.2.1.2.6 ConOps Refresh 41 days 0% Fri 8/23/19 Tue 10/22/19
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q2016 2017 2018 2019 2020 2021
Smart City ScheduleCooperative Agreement No. DTFH6116H00013
Smart Columbus Project - All Activities
file: SCC‐A‐SmartColumbus Program Schedule_revised_v8.mpp Page: 17/58 Printed on: Mon 1/28/19 @ 1:59 PM
ID Outline Number
Task Name Duration %Complete
Start Finish Predecessors
955 5.2.1.2.6.1 Update CVE ConOps per SDD Changes 20 days 0% Fri 8/23/19 Fri 9/20/19 1018FS+10 days,145
956 5.2.1.2.6.2 CoC Review 5 days 0% Mon 9/23/19 Fri 9/27/19 955
957 5.2.1.2.6.3 Address CoC Comments CVE ConOps 5 days 0% Mon 9/30/19 Fri 10/4/19 956
958 5.2.1.2.6.4 CoC Final Review 1 day 0% Mon 10/7/19 Mon 10/7/19 957
959 5.2.1.2.6.5 Submit Final Revised CVE ConOps to USDOT 0 days 0% Mon 10/7/19 Mon 10/7/19 958
960 5.2.1.2.6.6 USDOT Review Final Revised CVE ConOps 10 days 0% Tue 10/8/19 Tue 10/22/19 959
961 5.2.1.2.6.7 Receive USDOT Approval on Final Revised CVE ConOps 0 days 0% Tue 10/22/19 Tue 10/22/19 960
962 5.2.1.3 CVE System Requirements Specification (SyRS) 344 days 79% Mon 6/25/18 Wed 11/6/19
963 5.2.1.3.1 Draft CVE SyRS 61 days 100% Mon 6/25/18 Wed 9/19/18
970 5.2.1.3.2 Final CVE SyRS 46 days 100% Mon 9/24/18 Fri 11/30/18
971 5.2.1.3.2.1 Update Final CVE SyRS 35 days 100% Mon 9/24/18 Tue 11/13/18 969
972 5.2.1.3.2.2 Public Comment Period for CVE SyRS 10 days 100% Tue 10/30/18 Tue 11/13/18 971SS+25 days
973 5.2.1.3.2.3 Webinar for CVE SyRS 1 day 100% Mon 11/5/18 Mon 11/5/18 972SS+4 days
974 5.2.1.3.2.4 CoC Review 5 days 100% Wed 11/14/18 Tue 11/20/18 971,972
975 5.2.1.3.2.5 Address CoC Comments CVE SyRS 5 days 100% Wed 11/21/18 Thu 11/29/18 974
976 5.2.1.3.2.6 CoC Final Review 1 day 100% Fri 11/30/18 Fri 11/30/18 975
977 5.2.1.3.2.7 Submit Final CVE SyRS to USDOT 0 days 100% Fri 11/30/18 Fri 11/30/18 976
978 5.2.1.3.3 SyRS Refresh 32 days 0% Mon 9/23/19 Wed 11/6/19
979 5.2.1.3.3.1 Update CVE SyRS per SDD Changes 20 days 0% Mon 9/23/19 Mon 10/21/19 1018FS+30 days,145
980 5.2.1.3.3.2 CoC Review 5 days 0% Tue 10/22/19 Mon 10/28/19 979
981 5.2.1.3.3.3 Update CVE SyRS 5 days 0% Tue 10/29/19 Mon 11/4/19 980
982 5.2.1.3.3.4 QA/QC 1 day 0% Tue 11/5/19 Tue 11/5/19 981
983 5.2.1.3.3.5 CoC Final Review 1 day 0% Wed 11/6/19 Wed 11/6/19 982
984 5.2.1.3.3.6 Submit Final Revised CVE SyRS to USDOT 0 days 0% Wed 11/6/19 Wed 11/6/19 983
985 5.2.1.4 CVE Interface Control Document (ICD) 87 days 14% Mon 12/3/18 Mon 4/8/19
986 5.2.1.4.1 Draft CVE ICD 66 days 20% Mon 12/3/18 Fri 3/8/19
987 5.2.1.4.1.1 Prepare Draft CVE ICD 45 days 30% Mon 12/3/18 Wed 2/6/19 977
988 5.2.1.4.1.2 COC Review of Draft CVE 5 days 0% Thu 2/7/19 Wed 2/13/19 987
10/7
10/22
11/30
11/6
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q2016 2017 2018 2019 2020 2021
Smart City ScheduleCooperative Agreement No. DTFH6116H00013
Smart Columbus Project - All Activities
file: SCC‐A‐SmartColumbus Program Schedule_revised_v8.mpp Page: 18/58 Printed on: Mon 1/28/19 @ 1:59 PM
ID Outline Number
Task Name Duration %Complete
Start Finish Predecessors
989 5.2.1.4.1.3 Address CoC Comments ICD 5 days 0% Thu 2/14/19 Thu 2/21/19 988
990 5.2.1.4.1.4 CoC Final Review 1 day 0% Fri 2/22/19 Fri 2/22/19 989
991 5.2.1.4.1.5 Submit Draft CVE ICD to USDOT 0 days 0% Fri 2/22/19 Fri 2/22/19 990
992 5.2.1.4.1.6 USDOT Review CVE ICD 10 days 0% Mon 2/25/19 Fri 3/8/19 991
993 5.2.1.4.2 Final CVE ICD 21 days 0% Fri 3/8/19 Mon 4/8/19
994 5.2.1.4.2.1 Receive USDOT Comments on Draft CVE ICD 0 days 0% Fri 3/8/19 Fri 3/8/19 992
995 5.2.1.4.2.2 Public Comment Period for CVE ICD 10 days 0% Mon 3/11/19 Fri 3/22/19 994
996 5.2.1.4.2.3 Webinar for CVE ICD 1 day 0% Mon 3/18/19 Mon 3/18/19 994SS+5 days
997 5.2.1.4.2.4 Update CVE ICD 10 days 0% Mon 3/11/19 Fri 3/22/19 994
998 5.2.1.4.2.5 CoC Review 5 days 0% Mon 3/25/19 Fri 3/29/19 997,995
999 5.2.1.4.2.6 Address CoC Comments CVE ICD 5 days 0% Mon 4/1/19 Fri 4/5/19 998
1000 5.2.1.4.2.7 CoC Final Review 1 day 0% Mon 4/8/19 Mon 4/8/19 999
1001 5.2.1.4.2.8 Submit Final CVE ICD to USDOT 0 days 0% Mon 4/8/19 Mon 4/8/19 1000
1002 5.2.1.5 CVE System Design Document (SDD) 117 days 0% Mon 2/25/19 Thu 8/8/19
1003 5.2.1.5.1 Draft CVE SDD 76 days 0% Mon 2/25/19 Tue 6/11/19
1004 5.2.1.5.1.1 Prepare Draft CVE SDD 50 days 0% Mon 2/25/19 Fri 5/3/19 968,991
1005 5.2.1.5.1.2 COC Review of Draft SDD CVE 5 days 0% Mon 5/6/19 Fri 5/10/19 1004
1006 5.2.1.5.1.3 Address CoC Comments SDD 10 days 0% Mon 5/13/19 Fri 5/24/19 1005
1007 5.2.1.5.1.4 CoC Final Review 1 day 0% Tue 5/28/19 Tue 5/28/19 1006
1008 5.2.1.5.1.5 Submit Draft CVE SDD to USDOT 0 days 0% Tue 5/28/19 Tue 5/28/19 1007
1009 5.2.1.5.1.6 USDOT Review Draft CVE SDD 10 days 0% Wed 5/29/19 Tue 6/11/19 1008
1010 5.2.1.5.2 Final CVE SDD 41 days 0% Tue 6/11/19 Thu 8/8/19
1011 5.2.1.5.2.1 Receive USDOT Comments on Draft CVE SDD 0 days 0% Tue 6/11/19 Tue 6/11/19 1009
1012 5.2.1.5.2.2 Update Final CVE SDD 30 days 0% Wed 6/12/19 Wed 7/24/19 1011
1013 5.2.1.5.2.3 Public Comment Period for CVE SDD 10 days 0% Thu 7/11/19 Wed 7/24/19 1012SS+20 days
1014 5.2.1.5.2.4 Webinar for CVE SDD 1 day 0% Thu 7/18/19 Thu 7/18/19 1013SS+5 days
1015 5.2.1.5.2.5 CoC Review 5 days 0% Thu 7/25/19 Wed 7/31/19 1012,1013
1016 5.2.1.5.2.6 Address CoC Comments SDD 5 days 0% Thu 8/1/19 Wed 8/7/19 1015
2/22
3/8
4/8
5/28
6/11
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q2016 2017 2018 2019 2020 2021
Smart City ScheduleCooperative Agreement No. DTFH6116H00013
Smart Columbus Project - All Activities
file: SCC‐A‐SmartColumbus Program Schedule_revised_v8.mpp Page: 19/58 Printed on: Mon 1/28/19 @ 1:59 PM
ID Outline Number
Task Name Duration %Complete
Start Finish Predecessors
1017 5.2.1.5.2.7 CoC Final Review 1 day 0% Thu 8/8/19 Thu 8/8/19 1016
1018 5.2.1.5.2.8 Submit Final CVE SDD to USDOT 0 days 0% Thu 8/8/19 Thu 8/8/19 1017
1019 5.2.1.6 CVE Test Plan (TP) 72 days 0% Wed 6/12/19 Mon 9/23/19
1020 5.2.1.6.1 Draft CVE Test Plan 51 days 0% Wed 6/12/19 Thu 8/22/19
1021 5.2.1.6.1.1 Prepare Draft CVE Test Plan 30 days 0% Wed 6/12/19 Wed 7/24/19 1011
1022 5.2.1.6.1.2 COC Review of CVE Test Plan 5 days 0% Thu 7/25/19 Wed 7/31/19 1021
1023 5.2.1.6.1.3 Address CoC Comments CVE Test Plan 5 days 0% Thu 8/1/19 Wed 8/7/19 1022
1024 5.2.1.6.1.4 CoC Final Review 1 day 0% Thu 8/8/19 Thu 8/8/19 1023
1025 5.2.1.6.1.5 Submit Draft CVE Test Plan to USDOT 0 days 0% Thu 8/8/19 Thu 8/8/19 1024
1026 5.2.1.6.1.6 USDOT Review Draft CVE Test Plan 10 days 0% Fri 8/9/19 Thu 8/22/19 1025
1027 5.2.1.6.2 Final CVE Test Plan 21 days 0% Thu 8/22/19 Mon 9/23/19
1028 5.2.1.6.2.1 Receive USDOT Comments on Draft CVE Test Plan 0 days 0% Thu 8/22/19 Thu 8/22/19 1026
1029 5.2.1.6.2.2 Update CVE Test Plan 10 days 0% Fri 8/23/19 Fri 9/6/19 1028
1030 5.2.1.6.2.3 Public Comment Period for CVE Test Plan 10 days 0% Fri 8/23/19 Fri 9/6/19 1028
1031 5.2.1.6.2.4 Webinar for CVE Test Plan 1 day 0% Fri 8/30/19 Fri 8/30/19 1030SS+5 days
1032 5.2.1.6.2.5 CoC Review 5 days 0% Mon 9/9/19 Fri 9/13/19 1029,1030
1033 5.2.1.6.2.6 Address CoC Comments Test Plan 5 days 0% Mon 9/16/19 Fri 9/20/19 1032
1034 5.2.1.6.2.7 CoC Final Review 1 day 0% Mon 9/23/19 Mon 9/23/19 1033
1035 5.2.1.6.2.8 Submit Final CVE Test Plan to USDOT 0 days 0% Mon 9/23/19 Mon 9/23/19 1034,1018FS+10 day
1036 5.2.2 Phase II ‐ Develop, Procure, Deploy 691 days 15% Mon 6/25/18 Wed 3/31/21
1037 5.2.2.1 Installation Development 182 days 86% Mon 6/25/18 Tue 3/19/19
1038 5.2.2.1.1 Stage 1/2 104 days 100% Mon 6/25/18 Wed 11/21/18
1039 5.2.2.1.1.1 Review Base Plans 15 days 100% Mon 6/25/18 Mon 7/16/18 950
1040 5.2.2.1.1.2 Prepare Preliminary Layout 20 days 100% Mon 6/25/18 Mon 7/23/18 1039SS
1041 5.2.2.1.1.3 Utility Identification and Research & Identification 25 days 100% Tue 7/17/18 Mon 8/20/18 1039
1042 5.2.2.1.1.4 Corridor Reviews 20 days 100% Tue 7/17/18 Mon 8/13/18 1039
1043 5.2.2.1.1.5 Investigate Technology Options 30 days 100% Mon 6/25/18 Mon 8/6/18 1039SS
1044 5.2.2.1.1.6 Installation Details 75 days 100% Mon 6/25/18 Wed 10/10/18
8/8
8/8
8/22
9/23
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q2016 2017 2018 2019 2020 2021
Smart City ScheduleCooperative Agreement No. DTFH6116H00013
Smart Columbus Project - All Activities
file: SCC‐A‐SmartColumbus Program Schedule_revised_v8.mpp Page: 20/58 Printed on: Mon 1/28/19 @ 1:59 PM
ID Outline Number
Task Name Duration %Complete
Start Finish Predecessors
1045 5.2.2.1.1.6.1 High Level Communication System Block Diagram 20 days 100% Mon 6/25/18 Mon 7/23/18 1039SS
1046 5.2.2.1.1.6.2 Plan Sheets 75 days 100% Mon 6/25/18 Wed 10/10/18 1039SS
1047 5.2.2.1.1.6.3 Sizing 10 days 100% Mon 6/25/18 Mon 7/9/18 1039SS
1048 5.2.2.1.1.6.4 Field Devices, Equipment, & Electrical Details 45 days 100% Mon 6/25/18 Mon 8/27/18 1039SS
1049 5.2.2.1.1.6.5 Site Plan and Field Interconnection Block Diagrams 60 days 100% Mon 6/25/18 Tue 9/18/18 1039SS
1050 5.2.2.1.1.7 Preliminary Design Workshop 1 day 100% Tue 8/21/18 Tue 8/21/18 1040,1041,1042,104
1051 5.2.2.1.1.8 Submit Preliminary Plans 1 day 100% Thu 10/11/18 Thu 10/11/18 1046,1050
1052 5.2.2.1.1.9 City Review *Expedited Review 28 days 100% Fri 10/12/18 Wed 11/21/18 1051
1053 5.2.2.1.2 Stage 3 ‐ Installation Plans 78 days 52% Mon 11/26/18 Tue 3/19/19
1054 5.2.2.1.2.1 Address Stage 1/2 Comments 10 days 100% Mon 11/26/18 Fri 12/7/18 1052
1055 5.2.2.1.2.2 Stage 3 Installation Details 20 days 89% Mon 12/10/18 Tue 1/8/19 1054
1056 5.2.2.1.2.2.1 Quantities 15 days 100% Mon 12/10/18 Mon 12/31/18 1054
1057 5.2.2.1.2.2.2 Special Provisions 15 days 100% Mon 12/10/18 Mon 12/31/18 1054
1058 5.2.2.1.2.2.3 Finalize Detailed Site Plan Sheets 17 days 85% Mon 12/10/18 Thu 1/3/19 1054
1059 5.2.2.1.2.2.4 Fiber Optic Splicing Details 20 days 75% Mon 12/10/18 Tue 1/8/19 1054
1060 5.2.2.1.2.3 Engineer's Estimate 5 days 100% Wed 12/19/18 Wed 12/26/18 1058FS‐10 days
1061 5.2.2.1.2.4 Submit Stage 3 Plans 15 days 0% Fri 1/4/19 Fri 1/25/19 1058
1062 5.2.2.1.2.5 City Review *Expedited Review 15 days 0% Mon 1/28/19 Fri 2/15/19 1061
1063 5.2.2.1.2.6 Address Stage 3 Comments 5 days 0% Tue 2/19/19 Mon 2/25/19 1062
1064 5.2.2.1.2.7 Final Submittal 1 day 0% Tue 2/26/19 Tue 2/26/19 1063
1065 5.2.2.1.2.8 Signatures 15 days 0% Wed 2/27/19 Tue 3/19/19 1064
1066 5.2.2.1.2.9 USDOT Review 10 days 0% Wed 2/27/19 Tue 3/12/19 1064
1067 5.2.2.2 RSU Installation Procurement 177 days 6% Mon 12/3/18 Wed 8/14/19
1068 5.2.2.2.1 Procure RSU Contractor 104 days 0% Wed 3/20/19 Wed 8/14/19
1069 5.2.2.2.1.1 Prepare advertisement documents 9 days 0% Wed 3/20/19 Mon 4/1/19 1065
1070 5.2.2.2.1.2 USDOT Review 5 days 0% Tue 4/2/19 Mon 4/8/19 1069
1071 5.2.2.2.1.3 Ad to performance series 1 day 0% Tue 4/9/19 Tue 4/9/19 1070
1072 5.2.2.2.1.4 Pre‐bid meeting 1 day 0% Thu 4/18/19 Thu 4/18/19 1071SS+7 days
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q2016 2017 2018 2019 2020 2021
Smart City ScheduleCooperative Agreement No. DTFH6116H00013
Smart Columbus Project - All Activities
file: SCC‐A‐SmartColumbus Program Schedule_revised_v8.mpp Page: 21/58 Printed on: Mon 1/28/19 @ 1:59 PM
ID Outline Number
Task Name Duration %Complete
Start Finish Predecessors
1073 5.2.2.2.1.5 Advertisement 15 days 0% Wed 4/10/19 Tue 4/30/19 1071
1074 5.2.2.2.1.6 Addendum(s) issued if required, minimum 72 hours prior to bid opening
5 days 0% Wed 5/1/19 Tue 5/7/19 1073
1075 5.2.2.2.1.7 Bid opening (recorded by Auditor per Columbus City Code 329. 1 day 0% Wed 5/8/19 Wed 5/8/19 1074
1076 5.2.2.2.1.8 Select responsive and responsible contractor 2 days 0% Thu 5/9/19 Fri 5/10/19 1075
1077 5.2.2.2.1.9 Prepare recommendation memo and other forms for signature 2 days 0% Mon 5/13/19 Tue 5/14/19 1076
1078 5.2.2.2.1.10 Recommend contractor to CINO 2 days 0% Wed 5/15/19 Thu 5/16/19 1077
1079 5.2.2.2.1.11 Receive letter of contractor approval from CINO 1 day 0% Fri 5/17/19 Fri 5/17/19 1078
1080 5.2.2.2.1.12 USDOT Review 5 days 0% Wed 5/29/19 Tue 6/4/19 1079
1081 5.2.2.2.1.13 Legislation Process 29 days 0% Mon 5/20/19 Fri 6/28/19
1082 5.2.2.2.1.13.1 Prepare legislation and submit to Fiscal (2 working days day 2 days 0% Mon 5/20/19 Tue 5/21/19 1079
1083 5.2.2.2.1.13.2 Fiscal modifies and processes legislation (6 working days) 6 days 0% Wed 5/22/19 Thu 5/30/19 1082
1084 5.2.2.2.1.13.3 To Administrator (2 working days) 2 days 0% Fri 5/31/19 Mon 6/3/19 1083
1085 5.2.2.2.1.13.4 To CINO (4 working days) 3 days 0% Tue 6/4/19 Thu 6/6/19 1084
1086 5.2.2.2.1.13.5 To Finance (7 working days) 3 days 0% Fri 6/7/19 Tue 6/11/19 1085
1087 5.2.2.2.1.13.6 To Equal Business Opportunity (4 working days) 2 days 0% Wed 6/12/19 Thu 6/13/19 1086
1088 5.2.2.2.1.13.7 To Auditor (2 working days) 2 days 0% Fri 6/14/19 Mon 6/17/19 1087
1089 5.2.2.2.1.13.8 To City Attorney (2 working days) 2 days 0% Tue 6/18/19 Wed 6/19/19 1088
1090 5.2.2.2.1.13.9 To City Clerk (6 working days min.) 5 days 0% Thu 6/20/19 Wed 6/26/19 1089
1091 5.2.2.2.1.13.10 Council passes legislation* 1 day 0% Thu 6/27/19 Thu 6/27/19 1090
1092 5.2.2.2.1.13.11 Mayor Signs (2 working days) 1 day 0% Fri 6/28/19 Fri 6/28/19 1091
1093 5.2.2.2.1.14 Contract Process 32 days 0% Mon 7/1/19 Wed 8/14/19
1094 5.2.2.2.1.14.1 Prepare contract documents 4 days 0% Mon 7/1/19 Fri 7/5/19 1092
1095 5.2.2.2.1.14.2 Fiscal enters Performance information 8 days 0% Mon 7/8/19 Wed 7/17/19 1094
1096 5.2.2.2.1.14.3 Sent to Consultant and returned to City 7 days 0% Thu 7/18/19 Fri 7/26/19 1095
1097 5.2.2.2.1.14.4 To CINO 5 days 0% Mon 7/29/19 Fri 8/2/19 1096
1098 5.2.2.2.1.14.5 To City Attorney 5 days 0% Mon 8/5/19 Fri 8/9/19 1097
1099 5.2.2.2.1.14.6 To Auditor 2 days 0% Mon 8/12/19 Tue 8/13/19 1098
1100 5.2.2.2.1.14.7 Notice to proceed issued 1 day 0% Wed 8/14/19 Wed 8/14/19 1099
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q2016 2017 2018 2019 2020 2021
Smart City ScheduleCooperative Agreement No. DTFH6116H00013
Smart Columbus Project - All Activities
file: SCC‐A‐SmartColumbus Program Schedule_revised_v8.mpp Page: 22/58 Printed on: Mon 1/28/19 @ 1:59 PM
ID Outline Number
Task Name Duration %Complete
Start Finish Predecessors
1101 5.2.2.2.2 Procure RSU Equipment 165 days 11% Mon 12/3/18 Mon 7/29/19
1102 5.2.2.2.2.1 Consultant Selection Process (QBS) (Professional Services) 112 days 17% Mon 12/3/18 Mon 5/13/19
1103 5.2.2.2.2.1.1 Prepare project LOI / RFQ / RFP 23 days 75% Mon 12/3/18 Fri 1/4/19 977
1104 5.2.2.2.2.1.2 USDOT Review of Request for Subcontractor Approval 5 days 0% Mon 1/7/19 Fri 1/11/19 1103
1105 5.2.2.2.2.1.3 Advertise LOI / RFQ / RFP in Performance Series 15 days 0% Tue 1/29/19 Tue 2/19/19 1104FS+10 days
1106 5.2.2.2.2.1.4 Receive Technical Proposals 0 days 0% Tue 2/19/19 Tue 2/19/19 1105
1107 5.2.2.2.2.1.5 Request highest ranking firm to define project scope of serv 10 days 0% Wed 2/20/19 Tue 3/5/19 1106
1108 5.2.2.2.2.1.6 CINO Approval 5 days 0% Wed 3/6/19 Tue 3/12/19 1107
1109 5.2.2.2.2.1.7 Negotiate project final scope of services 5 days 0% Wed 3/13/19 Tue 3/19/19 1108
1110 5.2.2.2.2.1.8 Vendor Interviews 2 days 0% Wed 3/20/19 Thu 3/21/19 1107FS+10 days
1111 5.2.2.2.2.1.9 Establish contract terms 10 days 0% Wed 3/20/19 Tue 4/2/19 1109
1112 5.2.2.2.2.1.10 City Attorney reviews (if required) 0 days 0% Tue 4/2/19 Tue 4/2/19 1111
1113 5.2.2.2.2.1.11 Request fee proposal 13 days 0% Wed 4/3/19 Fri 4/19/19 1112
1114 5.2.2.2.2.1.12 Negotiate fees 10 days 0% Mon 4/22/19 Fri 5/3/19 1113
1115 5.2.2.2.2.1.13 Notify CINO 1 day 0% Mon 5/6/19 Mon 5/6/19 1114
1116 5.2.2.2.2.1.14 USDOT Review 5 days 0% Tue 5/7/19 Mon 5/13/19 1115
1117 5.2.2.2.2.2 Legislation Process 27 days 0% Mon 5/6/19 Wed 6/12/19
1118 5.2.2.2.2.2.1 Prepare legislation and submit to Fiscal (2 working days day 2 days 0% Mon 5/6/19 Tue 5/7/19 1114
1119 5.2.2.2.2.2.2 Fiscal modifies and processes legislation (6 working days) 5 days 0% Wed 5/8/19 Tue 5/14/19 1118
1120 5.2.2.2.2.2.3 To Administrator (2 working days) 3 days 0% Wed 5/15/19 Fri 5/17/19 1119
1121 5.2.2.2.2.2.4 To CINO (4 working days) 3 days 0% Mon 5/20/19 Wed 5/22/19 1120
1122 5.2.2.2.2.2.5 To Finance (7 working days) 3 days 0% Thu 5/23/19 Tue 5/28/19 1121
1123 5.2.2.2.2.2.6 To Equal Business Opportunity (4 working days) 2 days 0% Wed 5/29/19 Thu 5/30/19 1122
1124 5.2.2.2.2.2.7 To Auditor (2 working days) 1 day 0% Fri 5/31/19 Fri 5/31/19 1123
1125 5.2.2.2.2.2.8 To City Attorney (2 working days) 1 day 0% Mon 6/3/19 Mon 6/3/19 1124
1126 5.2.2.2.2.2.9 To City Clerk (6 working days min.) 5 days 0% Tue 6/4/19 Mon 6/10/19 1125
1127 5.2.2.2.2.2.10 Council passes legislation* 1 day 0% Tue 6/11/19 Tue 6/11/19 1126
1128 5.2.2.2.2.2.11 Mayor Signs (2 working days) 1 day 0% Wed 6/12/19 Wed 6/12/19 1127
2/19
4/2
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q2016 2017 2018 2019 2020 2021
Smart City ScheduleCooperative Agreement No. DTFH6116H00013
Smart Columbus Project - All Activities
file: SCC‐A‐SmartColumbus Program Schedule_revised_v8.mpp Page: 23/58 Printed on: Mon 1/28/19 @ 1:59 PM
ID Outline Number
Task Name Duration %Complete
Start Finish Predecessors
1129 5.2.2.2.2.3 Contract Process 32 days 0% Thu 6/13/19 Mon 7/29/19
1130 5.2.2.2.2.3.1 Prepare contract documents 4 days 0% Thu 6/13/19 Tue 6/18/19 1128
1131 5.2.2.2.2.3.2 Fiscal enters Performance information 8 days 0% Wed 6/19/19 Fri 6/28/19 1130
1132 5.2.2.2.2.3.3 Sent to Consultant and returned to City 7 days 0% Mon 7/1/19 Wed 7/10/19 1131
1133 5.2.2.2.2.3.4 To CINO 5 days 0% Thu 7/11/19 Wed 7/17/19 1132
1134 5.2.2.2.2.3.5 To City Attorney 5 days 0% Thu 7/18/19 Wed 7/24/19 1133
1135 5.2.2.2.2.3.6 To Auditor 2 days 0% Thu 7/25/19 Fri 7/26/19 1134
1136 5.2.2.2.2.3.7 Notice to proceed issued 1 day 0% Mon 7/29/19 Mon 7/29/19 1135
1137 5.2.2.3 OBU Installation Procurement 241 days 7% Mon 12/3/18 Fri 11/15/19
1138 5.2.2.3.1 Procure OBU Contractor 104 days 0% Wed 6/19/19 Fri 11/15/19
1139 5.2.2.3.1.1 Prepare advertisement documents 9 days 0% Wed 6/19/19 Mon 7/1/19 1065FS+64 days
1140 5.2.2.3.1.2 USDOT Review 5 days 0% Tue 7/2/19 Tue 7/9/19 1139
1141 5.2.2.3.1.3 Ad to performance series 1 day 0% Wed 7/10/19 Wed 7/10/19 1140
1142 5.2.2.3.1.4 Pre‐bid meeting 1 day 0% Fri 7/19/19 Fri 7/19/19 1141SS+7 days
1143 5.2.2.3.1.5 Advertisement 15 days 0% Thu 7/11/19 Wed 7/31/19 1141
1144 5.2.2.3.1.6 Addendum(s) issued if required, minimum 72 hours prior to bid opening
5 days 0% Thu 8/1/19 Wed 8/7/19 1143
1145 5.2.2.3.1.7 Bid opening (recorded by Auditor per Columbus City Code 329. 1 day 0% Thu 8/8/19 Thu 8/8/19 1144
1146 5.2.2.3.1.8 Select responsive and responsible contractor 2 days 0% Fri 8/9/19 Mon 8/12/19 1145
1147 5.2.2.3.1.9 Prepare recommendation memo and other forms for signature 2 days 0% Tue 8/13/19 Wed 8/14/19 1146
1148 5.2.2.3.1.10 Recommend contractor to CINO 2 days 0% Thu 8/15/19 Fri 8/16/19 1147
1149 5.2.2.3.1.11 Receive letter of contractor approval from CINO 1 day 0% Mon 8/19/19 Mon 8/19/19 1148
1150 5.2.2.3.1.12 USDOT Review 5 days 0% Tue 8/20/19 Mon 8/26/19 1149
1151 5.2.2.3.1.13 Legislation Process 29 days 0% Tue 8/20/19 Mon 9/30/19
1152 5.2.2.3.1.13.1 Prepare legislation and submit to Fiscal (2 working days day 2 days 0% Tue 8/20/19 Wed 8/21/19 1149
1153 5.2.2.3.1.13.2 Fiscal modifies and processes legislation (6 working days) 6 days 0% Thu 8/22/19 Thu 8/29/19 1152
1154 5.2.2.3.1.13.3 To Administrator (2 working days) 2 days 0% Fri 8/30/19 Tue 9/3/19 1153
1155 5.2.2.3.1.13.4 To CINO (4 working days) 3 days 0% Wed 9/4/19 Fri 9/6/19 1154
1156 5.2.2.3.1.13.5 To Finance (7 working days) 3 days 0% Mon 9/9/19 Wed 9/11/19 1155
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q2016 2017 2018 2019 2020 2021
Smart City ScheduleCooperative Agreement No. DTFH6116H00013
Smart Columbus Project - All Activities
file: SCC‐A‐SmartColumbus Program Schedule_revised_v8.mpp Page: 24/58 Printed on: Mon 1/28/19 @ 1:59 PM
ID Outline Number
Task Name Duration %Complete
Start Finish Predecessors
1157 5.2.2.3.1.13.6 To Equal Business Opportunity (4 working days) 2 days 0% Thu 9/12/19 Fri 9/13/19 1156
1158 5.2.2.3.1.13.7 To Auditor (2 working days) 2 days 0% Mon 9/16/19 Tue 9/17/19 1157
1159 5.2.2.3.1.13.8 To City Attorney (2 working days) 2 days 0% Wed 9/18/19 Thu 9/19/19 1158
1160 5.2.2.3.1.13.9 To City Clerk (6 working days min.) 5 days 0% Fri 9/20/19 Thu 9/26/19 1159
1161 5.2.2.3.1.13.10 Council passes legislation* 1 day 0% Fri 9/27/19 Fri 9/27/19 1160
1162 5.2.2.3.1.13.11 Mayor Signs (2 working days) 1 day 0% Mon 9/30/19 Mon 9/30/19 1161
1163 5.2.2.3.1.14 Contract Process 32 days 0% Tue 10/1/19 Fri 11/15/19
1164 5.2.2.3.1.14.1 Prepare contract documents 4 days 0% Tue 10/1/19 Fri 10/4/19 1162
1165 5.2.2.3.1.14.2 Fiscal enters Performance information 8 days 0% Mon 10/7/19 Thu 10/17/19 1164
1166 5.2.2.3.1.14.3 Sent to Consultant and returned to City 7 days 0% Fri 10/18/19 Mon 10/28/19 1165
1167 5.2.2.3.1.14.4 To CINO 5 days 0% Tue 10/29/19 Mon 11/4/19 1166
1168 5.2.2.3.1.14.5 To City Attorney 5 days 0% Tue 11/5/19 Tue 11/12/19 1167
1169 5.2.2.3.1.14.6 To Auditor 2 days 0% Wed 11/13/19 Thu 11/14/19 1168
1170 5.2.2.3.1.14.7 Notice to proceed issued 1 day 0% Fri 11/15/19 Fri 11/15/19 1169
1171 5.2.2.3.2 Procure OBU Equipment 166 days 11% Mon 12/3/18 Tue 7/30/19
1172 5.2.2.3.2.1 Consultant Selection Process (QBS) (Professional Services) 113 days 19% Mon 12/3/18 Tue 5/14/19
1173 5.2.2.3.2.1.1 Prepare project LOI / RFQ / RFP 23 days 75% Mon 12/3/18 Fri 1/4/19 977
1174 5.2.2.3.2.1.2 USDOT Review of Request for Subcontractor Approval 5 days 0% Mon 1/7/19 Fri 1/11/19 1173
1175 5.2.2.3.2.1.3 Advertise LOI / RFQ / RFP in Performance Series 15 days 0% Tue 1/29/19 Tue 2/19/19 1174FS+10 days
1176 5.2.2.3.2.1.4 Receive Technical Proposals 0 days 0% Tue 2/19/19 Tue 2/19/19 1175
1177 5.2.2.3.2.1.5 Request highest ranking firm to define project scope of serv 10 days 0% Wed 2/20/19 Tue 3/5/19 1176
1178 5.2.2.3.2.1.6 Vendor Interviews 2 days 0% Wed 3/20/19 Thu 3/21/19 1177FS+10 days
1179 5.2.2.3.2.1.7 CINO Approval 2 days 0% Fri 3/22/19 Mon 3/25/19 1178
1180 5.2.2.3.2.1.8 Negotiate project final scope of services 5 days 0% Tue 3/26/19 Mon 4/1/19 1179
1181 5.2.2.3.2.1.9 Establish contract terms 5 days 0% Tue 4/2/19 Mon 4/8/19 1180
1182 5.2.2.3.2.1.10 City Attorney reviews (if required) 0 days 0% Mon 4/8/19 Mon 4/8/19 1181
1183 5.2.2.3.2.1.11 Request fee proposal 10 days 0% Tue 4/9/19 Mon 4/22/19 1182
1184 5.2.2.3.2.1.12 Negotiate fees 10 days 0% Tue 4/23/19 Mon 5/6/19 1183
2/19
4/8
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q2016 2017 2018 2019 2020 2021
Smart City ScheduleCooperative Agreement No. DTFH6116H00013
Smart Columbus Project - All Activities
file: SCC‐A‐SmartColumbus Program Schedule_revised_v8.mpp Page: 25/58 Printed on: Mon 1/28/19 @ 1:59 PM
ID Outline Number
Task Name Duration %Complete
Start Finish Predecessors
1185 5.2.2.3.2.1.13 Notify CINO 1 day 0% Tue 5/7/19 Tue 5/7/19 1184
1186 5.2.2.3.2.1.14 USDOT Review 5 days 0% Wed 5/8/19 Tue 5/14/19 1185
1187 5.2.2.3.2.2 Legislation Process 27 days 0% Tue 5/7/19 Thu 6/13/19
1188 5.2.2.3.2.2.1 Prepare legislation and submit to Fiscal (2 working days day 2 days 0% Tue 5/7/19 Wed 5/8/19 1184
1189 5.2.2.3.2.2.2 Fiscal modifies and processes legislation (6 working days) 5 days 0% Thu 5/9/19 Wed 5/15/19 1188
1190 5.2.2.3.2.2.3 To Administrator (2 working days) 3 days 0% Thu 5/16/19 Mon 5/20/19 1189
1191 5.2.2.3.2.2.4 To CINO (4 working days) 3 days 0% Tue 5/21/19 Thu 5/23/19 1190
1192 5.2.2.3.2.2.5 To Finance (7 working days) 3 days 0% Fri 5/24/19 Wed 5/29/19 1191
1193 5.2.2.3.2.2.6 To Equal Business Opportunity (4 working days) 2 days 0% Thu 5/30/19 Fri 5/31/19 1192
1194 5.2.2.3.2.2.7 To Auditor (2 working days) 1 day 0% Mon 6/3/19 Mon 6/3/19 1193
1195 5.2.2.3.2.2.8 To City Attorney (2 working days) 1 day 0% Tue 6/4/19 Tue 6/4/19 1194
1196 5.2.2.3.2.2.9 To City Clerk (6 working days min.) 5 days 0% Wed 6/5/19 Tue 6/11/19 1195
1197 5.2.2.3.2.2.10 Council passes legislation* 1 day 0% Wed 6/12/19 Wed 6/12/19 1196
1198 5.2.2.3.2.2.11 Mayor Signs (2 working days) 1 day 0% Thu 6/13/19 Thu 6/13/19 1197
1199 5.2.2.3.2.3 Contract Process 32 days 0% Fri 6/14/19 Tue 7/30/19
1200 5.2.2.3.2.3.1 Prepare contract documents 4 days 0% Fri 6/14/19 Wed 6/19/19 1198
1201 5.2.2.3.2.3.2 Fiscal enters Performance information 8 days 0% Thu 6/20/19 Mon 7/1/19 1200
1202 5.2.2.3.2.3.3 Sent to Consultant and returned to City 7 days 0% Tue 7/2/19 Thu 7/11/19 1201
1203 5.2.2.3.2.3.4 To CINO 5 days 0% Fri 7/12/19 Thu 7/18/19 1202
1204 5.2.2.3.2.3.5 To City Attorney 5 days 0% Fri 7/19/19 Thu 7/25/19 1203
1205 5.2.2.3.2.3.6 To Auditor 2 days 0% Fri 7/26/19 Mon 7/29/19 1204
1206 5.2.2.3.2.3.7 Notice to proceed issued 1 day 0% Tue 7/30/19 Tue 7/30/19 1205
1207 5.2.2.4 RSU Installation 120 days 0% Thu 8/15/19 Mon 2/10/20
1208 5.2.2.4.1 Install Field Equipment (Cable, mounting equipment, switches and RSUs)
120 days 0% Thu 8/15/19 Mon 2/10/20 1100
1209 5.2.2.4.2 Install Fiber and Splicing 120 days 0% Thu 8/15/19 Mon 2/10/20 1100
1210 5.2.2.5 OBU Installation 290 days 0% Wed 7/31/19 Thu 9/24/20
1211 5.2.2.5.1 Application Development for OBUs (Light Vehicles) 150 days 0% Wed 7/31/19 Mon 3/9/20 1136,1206
1212 5.2.2.5.2 Application Development for OBUs (Transit Vehicles) 150 days 0% Wed 7/31/19 Mon 3/9/20 1211SS
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q2016 2017 2018 2019 2020 2021
Smart City ScheduleCooperative Agreement No. DTFH6116H00013
Smart Columbus Project - All Activities
file: SCC‐A‐SmartColumbus Program Schedule_revised_v8.mpp Page: 26/58 Printed on: Mon 1/28/19 @ 1:59 PM
ID Outline Number
Task Name Duration %Complete
Start Finish Predecessors
1213 5.2.2.5.3 IRB Management 1 day 0% Fri 8/16/19 Fri 8/16/19 1136,1235,1206
1214 5.2.2.5.4 Recruit Participants 290 days 0% Wed 7/31/19 Thu 9/24/20
1215 5.2.2.5.4.1 Participant Outreach 24 days 0% Wed 7/31/19 Tue 9/3/19 1211SS
1216 5.2.2.5.4.2 Participant Recruiting 61 days 0% Wed 9/4/19 Tue 12/3/19 1215
1217 5.2.2.5.4.3 Participant Informed Consent 205 days 0% Wed 12/4/19 Thu 9/24/20 1216
1218 5.2.2.5.5 Installations 205 days 0% Wed 12/4/19 Thu 9/24/20 1170,1217FF
1219 5.2.2.6 Draft O&M Manual 54 days 0% Fri 3/20/20 Thu 6/4/20
1220 5.2.2.6.1 Develop Draft O&M Manual 20 days 0% Fri 3/20/20 Fri 4/17/20 1221SF
1221 5.2.2.6.2 QA/QC Draft O&M Manual 5 days 0% Fri 4/17/20 Fri 4/24/20 1222SF
1222 5.2.2.6.3 CoC Review Draft O&M Manual 5 days 0% Fri 4/24/20 Fri 5/1/20 1223SF
1223 5.2.2.6.4 Address Comments From CoC Review 5 days 0% Fri 5/1/20 Fri 5/8/20 1224SF
1224 5.2.2.6.5 CoC Final Review 1 day 0% Fri 5/8/20 Mon 5/11/20 1225SF
1225 5.2.2.6.6 Submit Draft O&M Manual 0 days 0% Mon 5/11/20 Mon 5/11/20 1226SF
1226 5.2.2.6.7 USDOT Review Draft O&M Manual 10 days 0% Mon 5/11/20 Tue 5/26/20 1227SF
1227 5.2.2.6.8 Receive DOT Comments Draft O&M Manual 0 days 0% Tue 5/26/20 Tue 5/26/20 1228SF
1228 5.2.2.6.9 Update Final Draft O&M Manual 8 days 0% Tue 5/26/20 Thu 6/4/20 1254FF‐22 days
1229 5.2.2.7 IRB Process 155 days 0% Mon 1/7/19 Thu 8/15/19
1230 5.2.2.7.1 Engage IRB 20 days 0% Mon 1/7/19 Mon 2/4/19
1231 5.2.2.7.2 Develop Participant Recruitment Plan 20 days 0% Tue 2/5/19 Tue 3/5/19 1230
1232 5.2.2.7.3 Develop and Submit Human Use Approval Request for IRB 20 days 0% Wed 3/6/19 Tue 4/2/19 1231
1233 5.2.2.7.4 IRB Review and Provide Findings (Initial) 45 days 0% Wed 4/3/19 Wed 6/5/19 1232
1234 5.2.2.7.5 Update and Submit IRB Application 30 days 0% Thu 6/6/19 Thu 7/18/19 1233
1235 5.2.2.7.6 IRB Review and Provide Findings (Revised) 20 days 0% Fri 7/19/19 Thu 8/15/19 1234
1236 5.2.2.8 Post‐Installation 220 days 0% Tue 2/11/20 Thu 12/24/20
1237 5.2.2.8.1 Verification 40 days 0% Tue 2/11/20 Tue 4/7/20
1238 5.2.2.8.1.1 Component Verfication 20 days 0% Tue 2/11/20 Tue 3/10/20 1208,1209
1239 5.2.2.8.1.2 System Verification 20 days 0% Wed 3/11/20 Tue 4/7/20 1218SS+5 days,1238
1240 5.2.2.8.2 City completes as‐built drawing mark‐ups 30 days 0% Tue 2/11/20 Tue 3/24/20 1238SS
5/11
5/26
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q2016 2017 2018 2019 2020 2021
Smart City ScheduleCooperative Agreement No. DTFH6116H00013
Smart Columbus Project - All Activities
file: SCC‐A‐SmartColumbus Program Schedule_revised_v8.mpp Page: 27/58 Printed on: Mon 1/28/19 @ 1:59 PM
ID Outline Number
Task Name Duration %Complete
Start Finish Predecessors
1241 5.2.2.8.3 Consultant makes as‐built revisions 20 days 0% Wed 3/25/20 Tue 4/21/20 1240
1242 5.2.2.8.4 City reviews revisions 30 days 0% Wed 4/22/20 Wed 6/3/20 1241
1243 5.2.2.8.5 Consultant makes final revisions 23 days 0% Thu 6/4/20 Tue 7/7/20 1242
1244 5.2.2.8.6 Evaluation of Consultant 10 days 0% Wed 7/8/20 Tue 7/21/20 1243
1245 5.2.2.8.7 Warranty work check‐out (within one year of completion) 220 days 0% Tue 2/11/20 Thu 12/24/20 1238SS
1246 5.2.2.9 Testing 40 days 0% Wed 4/8/20 Wed 6/3/20
1247 5.2.2.9.1 Prepare for Acceptance Testing (Schedule, Eqpt, Artifacts) 10 days 0% Wed 4/8/20 Tue 4/21/20 1239
1248 5.2.2.9.2 Conduct Acceptance Testing 6 days 0% Wed 4/22/20 Wed 4/29/20 1247,1035FS+10 day
1249 5.2.2.9.3 Review Results with Contractor 1 day 0% Thu 4/30/20 Thu 4/30/20 1248
1250 5.2.2.9.4 Contractor Revisions based on Test Results 7 days 0% Fri 5/1/20 Mon 5/11/20 1249
1251 5.2.2.9.5 Perform Regression Testing Until Acceptance 6 days 0% Tue 5/12/20 Tue 5/19/20 1250
1252 5.2.2.9.6 Prepare and Submit Test Report 10 days 0% Wed 5/20/20 Wed 6/3/20 1251
1253 5.2.2.10 Demonstration Period 182 days 0% Tue 7/7/20 Wed 3/31/21
1254 5.2.2.10.1 Go Live 0 days 0% Tue 7/7/20 Tue 7/7/20 1243,1252FF
1255 5.2.2.10.2 Performance and System Monitoring 182 days 0% Wed 7/8/20 Wed 3/31/21 1254
1256 5.2.2.10.3 Data Collection 182 days 0% Wed 7/8/20 Wed 3/31/21 1254
1257 5.2.2.10.4 O&M Plan Final Update 20 days 0% Thu 3/4/21 Wed 3/31/21 1255FF,1256FF
1258 5.3 Multi Modal Trip Planning Application/Common Payment System (MMTPA/CPS)
753 days 28% Mon 1/22/18 Mon 1/25/21
1259 5.3.1 Phase I ‐ Systems Engineering 230 days 100% Mon 1/22/18 Wed 12/19/18
1260 5.3.1.1 MMTPA/CPS Concept of Operations (ConOps) 159 days 100% Mon 1/22/18 Wed 9/5/18
1261 5.3.1.1.1 Draft MMTPA/CPS ConOps 94 days 100% Mon 1/22/18 Mon 6/4/18
1269 5.3.1.1.2 Final MMTPA/CPS ConOps 65 days 100% Tue 6/5/18 Wed 9/5/18
1277 5.3.1.2 CPS ONLY System Requirements Specification (SyRS) 90 days 100% Thu 8/9/18 Wed 12/19/18
1278 5.3.1.2.1 Draft CPS ONLY SyRS 61 days 100% Thu 8/9/18 Mon 11/5/18
1285 5.3.1.2.2 Final CPS ONLY SyRS 29 days 100% Tue 11/6/18 Wed 12/19/18
1286 5.3.1.2.2.1 Update Final CPS ONLY SyRS 22 days 100% Tue 11/6/18 Mon 12/10/18 1284
1287 5.3.1.2.2.2 Public Comment Period for CPS SyRS 10 days 100% Tue 11/20/18 Wed 12/5/18 1286SS+9 days
1288 5.3.1.2.2.3 Webinar for CPS SyRS 1 day 100% Wed 11/28/18 Wed 11/28/18 1287SS+4 days
7/7
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q2016 2017 2018 2019 2020 2021
Smart City ScheduleCooperative Agreement No. DTFH6116H00013
Smart Columbus Project - All Activities
file: SCC‐A‐SmartColumbus Program Schedule_revised_v8.mpp Page: 28/58 Printed on: Mon 1/28/19 @ 1:59 PM
ID Outline Number
Task Name Duration %Complete
Start Finish Predecessors
1289 5.3.1.2.2.4 CoC Review 4 days 100% Tue 12/11/18 Fri 12/14/18 1286
1290 5.3.1.2.2.5 Address CoC Comments 2 days 100% Mon 12/17/18 Tue 12/18/18 1289
1291 5.3.1.2.2.6 CoC Final Review 1 day 100% Wed 12/19/18 Wed 12/19/18 1290
1292 5.3.1.2.2.7 Submit Final CPS ONLY SyRS 0 days 100% Wed 12/19/18 Wed 12/19/18 1291
1293 5.3.2 Phase II ‐ Develop, Procure, Deploy 678 days 18% Tue 5/8/18 Mon 1/25/21
1294 5.3.2.1 MMTPA Procurement 152 days 100% Tue 5/8/18 Fri 12/14/18
1295 5.3.2.1.1 Preparation for RFP/Agile Artifacts 50 days 100% Tue 5/8/18 Wed 7/18/18
1296 5.3.2.1.1.1 Product Roadmap 10 days 100% Tue 5/8/18 Mon 5/21/18 1263
1297 5.3.2.1.1.2 Requirements (essential, desirable, optional) 30 days 100% Tue 5/22/18 Tue 7/3/18 1296
1298 5.3.2.1.1.3 MVP definition 5 days 100% Thu 7/5/18 Wed 7/11/18 1297
1299 5.3.2.1.1.4 Business Value 5 days 100% Thu 7/12/18 Wed 7/18/18 1298
1300 5.3.2.1.2 RFP and Vendor Selection 152 days 100% Tue 5/8/18 Fri 12/14/18
1301 5.3.2.1.2.1 Develop RFP 69 days 100% Tue 5/8/18 Tue 8/14/18
1302 5.3.2.1.2.1.1 Draft RFP 15 days 100% Tue 5/8/18 Tue 5/29/18 1263
1303 5.3.2.1.2.1.2 Revised RFP 25 days 100% Tue 5/29/18 Mon 7/2/18 1302
1304 5.3.2.1.2.1.3 COTA Review 10 days 100% Tue 7/3/18 Tue 7/17/18 1303
1305 5.3.2.1.2.1.4 USDOT Review 10 days 100% Wed 7/18/18 Tue 7/31/18 1304
1306 5.3.2.1.2.1.5 Final RFP 5 days 100% Wed 8/1/18 Tue 8/7/18 1305
1307 5.3.2.1.2.1.6 RFP Posting 5 days 100% Wed 8/8/18 Tue 8/14/18 1306
1308 5.3.2.1.2.2 RFP and Vendor Selection 60 days 100% Wed 8/8/18 Thu 11/1/18 1306
1309 5.3.2.1.2.3 Legislation Process 12 days 100% Fri 11/2/18 Tue 11/20/18
1310 5.3.2.1.2.3.1 Prepare and Submit to Fiscal 5 days 100% Fri 11/2/18 Thu 11/8/18 1308
1311 5.3.2.1.2.3.2 Council Passes Legislation 5 days 100% Fri 11/9/18 Fri 11/16/18 1310
1312 5.3.2.1.2.3.3 Mayor Approves 2 days 100% Mon 11/19/18 Tue 11/20/18 1311
1313 5.3.2.1.2.4 Contract Process 7 days 100% Wed 11/21/18 Mon 12/3/18
1314 5.3.2.1.2.4.1 Prepare Contract Documents 5 days 100% Wed 11/21/18 Thu 11/29/18 1312
1315 5.3.2.1.2.4.2 Review and Sign Off 2 days 100% Fri 11/30/18 Mon 12/3/18 1314
1316 5.3.2.1.2.5 Notice to proceed 9 days 100% Tue 12/4/18 Fri 12/14/18 1315
12/19
5/21
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q2016 2017 2018 2019 2020 2021
Smart City ScheduleCooperative Agreement No. DTFH6116H00013
Smart Columbus Project - All Activities
file: SCC‐A‐SmartColumbus Program Schedule_revised_v8.mpp Page: 29/58 Printed on: Mon 1/28/19 @ 1:59 PM
ID Outline Number
Task Name Duration %Complete
Start Finish Predecessors
1317 5.3.2.2 CPS Procurement 113 days 49% Fri 10/5/18 Fri 3/22/19
1318 5.3.2.2.1 Preparation for RFP/Agile Artifacts 30 days 100% Fri 10/5/18 Mon 11/19/18
1319 5.3.2.2.1.1 Product Roadmap 10 days 100% Fri 10/5/18 Fri 10/19/18 1279
1320 5.3.2.2.1.2 Requirements (essential, desirable, optional) 10 days 100% Mon 10/22/18 Fri 11/2/18 1319
1321 5.3.2.2.1.3 MVP definition 5 days 100% Mon 11/5/18 Fri 11/9/18 1320
1322 5.3.2.2.1.4 Business Value 5 days 100% Tue 11/13/18 Mon 11/19/18 1321
1323 5.3.2.2.2 RFP and Vendor Selection 113 days 33% Fri 10/5/18 Fri 3/22/19
1324 5.3.2.2.2.1 Develop RFP 42 days 100% Fri 10/5/18 Fri 12/7/18
1325 5.3.2.2.2.1.1 Draft RFP 10 days 100% Fri 10/5/18 Fri 10/19/18 1279
1326 5.3.2.2.2.1.2 Revised RFP 11 days 100% Tue 11/6/18 Wed 11/21/18 1325,1284
1327 5.3.2.2.2.1.3 Final RFP 10 days 100% Mon 11/26/18 Fri 12/7/18 1326
1328 5.3.2.2.2.2 RFP and Vendor Selection 42 days 0% Mon 12/10/18 Fri 2/8/19
1329 5.3.2.2.2.2.1 RFP Release 0 days 100% Mon 12/10/18 Mon 12/10/18 1327
1330 5.3.2.2.2.2.2 Proposals Due 20 days 0% Wed 12/12/18 Thu 1/10/19 1329
1331 5.3.2.2.2.2.3 Vendor Selection 8 days 0% Fri 1/11/19 Wed 1/23/19 1330
1332 5.3.2.2.2.2.4 Vendor Interviews 2 days 0% Thu 1/31/19 Fri 2/1/19 1331FS+5 days
1333 5.3.2.2.2.2.5 Vendor Recommendation 3 days 0% Mon 2/4/19 Wed 2/6/19 1332
1334 5.3.2.2.2.2.6 CINO Approval of Vendor Recommendation 2 days 0% Thu 2/7/19 Fri 2/8/19 1333
1335 5.3.2.2.2.3 Legislation Process 12 days 0% Mon 2/11/19 Wed 2/27/19
1336 5.3.2.2.2.3.1 Prepare and Submit to Fiscal 5 days 0% Mon 2/11/19 Fri 2/15/19 1334
1337 5.3.2.2.2.3.2 Council Passes Legislation 5 days 0% Tue 2/19/19 Mon 2/25/19 1336
1338 5.3.2.2.2.3.3 Mayor Approves 2 days 0% Tue 2/26/19 Wed 2/27/19 1337
1339 5.3.2.2.2.4 Contract Process 7 days 0% Thu 2/28/19 Fri 3/8/19
1340 5.3.2.2.2.4.1 Prepare Contract Documents 5 days 0% Thu 2/28/19 Wed 3/6/19 1338
1341 5.3.2.2.2.4.2 Review and Sign Off 2 days 0% Thu 3/7/19 Fri 3/8/19 1340
1342 5.3.2.2.2.5 Notice to proceed 10 days 0% Mon 3/11/19 Fri 3/22/19 1341
1343 5.3.2.3 Agreement with TSPs 262 days 25% Mon 12/17/18 Fri 1/3/20
1344 5.3.2.3.1 Finalize Agreement with Transportation Service Providers 262 days 25% Mon 12/17/18 Fri 1/3/20 1316
10/19
12/10
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q2016 2017 2018 2019 2020 2021
Smart City ScheduleCooperative Agreement No. DTFH6116H00013
Smart Columbus Project - All Activities
file: SCC‐A‐SmartColumbus Program Schedule_revised_v8.mpp Page: 30/58 Printed on: Mon 1/28/19 @ 1:59 PM
ID Outline Number
Task Name Duration %Complete
Start Finish Predecessors
1345 5.3.2.4 IRB Process 246 days 2% Mon 12/17/18 Tue 12/10/19
1346 5.3.2.4.1 Engage IRB 20 days 20% Mon 12/17/18 Tue 1/15/19 1357SS
1347 5.3.2.4.2 Develop Participant Recruitment Plan 20 days 0% Wed 1/16/19 Wed 2/13/19 1346
1348 5.3.2.4.3 Develop and Submit Human Use Approval Request for IRB 20 days 0% Thu 2/14/19 Thu 3/14/19 1347
1349 5.3.2.4.4 IRB Review and Provide Findings (Initial) 45 days 0% Fri 3/15/19 Thu 5/16/19 1348
1350 5.3.2.4.5 Update and Submit IRB Application 30 days 0% Mon 3/25/19 Fri 5/3/19 1362SS
1351 5.3.2.4.6 IRB Review and Provide Findings (Revised) 20 days 0% Mon 5/6/19 Mon 6/3/19 1350
1352 5.3.2.4.7 Training Program ‐ MMTPA 20 days 0% Tue 7/9/19 Mon 8/5/19 1351,1359
1353 5.3.2.4.8 Training Program ‐ MMTPA/CPS 20 days 0% Fri 11/8/19 Tue 12/10/19 1352,1364
1354 5.3.2.5 Product Delivery 226 days 8% Fri 12/14/18 Thu 11/7/19
1355 5.3.2.5.1 MMTPA Agile Development 140 days 18% Fri 12/14/18 Mon 7/8/19
1356 5.3.2.5.1.1 Kickoff 0 days 100% Fri 12/14/18 Fri 12/14/18 1316
1357 5.3.2.5.1.2 Release 1 50 days 50% Mon 12/17/18 Thu 2/28/19 1356
1358 5.3.2.5.1.3 Release 2 50 days 0% Fri 3/1/19 Thu 5/9/19 1357
1359 5.3.2.5.1.4 Release 3 40 days 0% Fri 5/10/19 Mon 7/8/19 1358
1360 5.3.2.5.2 CPS Agile Development 160 days 0% Fri 3/22/19 Thu 11/7/19
1361 5.3.2.5.2.1 Kickoff 0 days 0% Fri 3/22/19 Fri 3/22/19 1342
1362 5.3.2.5.2.2 Release 1 60 days 0% Mon 3/25/19 Mon 6/17/19 1361
1363 5.3.2.5.2.3 Release 2 60 days 0% Tue 6/18/19 Wed 9/11/19 1362
1364 5.3.2.5.2.4 Release 3 40 days 0% Thu 9/12/19 Thu 11/7/19 1363
1365 5.3.2.6 Testing 164 days 0% Fri 5/10/19 Tue 1/7/20
1366 5.3.2.6.1 MMTPA Testing 78 days 0% Fri 5/10/19 Thu 8/29/19
1367 5.3.2.6.1.1 Prepare for Acceptance Testing (Schedule, Eqpt, Artifacts) 20 days 0% Fri 5/10/19 Fri 6/7/19 1358
1368 5.3.2.6.1.2 Conduct Acceptance Testing 20 days 0% Mon 6/10/19 Mon 7/8/19 1367
1369 5.3.2.6.1.3 Review Results with Contractor 1 day 0% Tue 7/9/19 Tue 7/9/19 1368
1370 5.3.2.6.1.4 Contractor Revisions based on Test Results 17 days 0% Wed 7/10/19 Thu 8/1/19 1369
1371 5.3.2.6.1.5 Perform Regression Testing Until Acceptance 10 days 0% Fri 8/2/19 Thu 8/15/19 1370
1372 5.3.2.6.1.6 Prepare and Submit Test Report 10 days 0% Fri 8/16/19 Thu 8/29/19 1359FF,1371
12/14
3/22
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q2016 2017 2018 2019 2020 2021
Smart City ScheduleCooperative Agreement No. DTFH6116H00013
Smart Columbus Project - All Activities
file: SCC‐A‐SmartColumbus Program Schedule_revised_v8.mpp Page: 31/58 Printed on: Mon 1/28/19 @ 1:59 PM
ID Outline Number
Task Name Duration %Complete
Start Finish Predecessors
1373 5.3.2.6.2 CPS Testing 78 days 0% Thu 9/12/19 Tue 1/7/20
1374 5.3.2.6.2.1 Prepare for Acceptance Testing (Schedule, Eqpt, Artifacts) 20 days 0% Thu 9/12/19 Wed 10/9/19 1363
1375 5.3.2.6.2.2 Conduct Acceptance Testing 20 days 0% Thu 10/10/19 Thu 11/7/19 1374
1376 5.3.2.6.2.3 Review Results with Contractor 1 day 0% Fri 11/8/19 Fri 11/8/19 1375
1377 5.3.2.6.2.4 Contractor Revisions based on Test Results 17 days 0% Tue 11/12/19 Fri 12/6/19 1376
1378 5.3.2.6.2.5 Perform Regression Testing Until Acceptance 10 days 0% Mon 12/9/19 Fri 12/20/19 1377
1379 5.3.2.6.2.6 Prepare and Submit Test Report 10 days 0% Mon 12/23/19 Tue 1/7/20 1364FF,1378
1380 5.3.2.7 Demonstration Period 348 days 0% Thu 8/29/19 Mon 1/25/21
1381 5.3.2.7.1 Go Live (MMTPA Only) 0 days 0% Thu 8/29/19 Thu 8/29/19 1352,1372
1382 5.3.2.7.2 Go Live (MMTPA and CPS) 0 days 0% Tue 1/7/20 Tue 1/7/20 1344,1353,1372FF,1
1383 5.3.2.7.3 Performance and System Monitoring 262 days 0% Wed 1/8/20 Mon 1/25/21 1382
1384 5.3.2.7.4 Data Collection 262 days 0% Wed 1/8/20 Mon 1/25/21 1382
1385 5.3.2.7.5 Quarterly Update 1 (Application) 66 days 0% Wed 1/8/20 Fri 4/10/20 1382
1386 5.3.2.7.6 Quarterly Update 2 (Application) 66 days 0% Mon 4/13/20 Wed 7/15/20 1385
1387 5.3.2.7.7 Quarterly Update 3 (Application) 66 days 0% Thu 7/16/20 Mon 10/19/20 1386
1388 5.4 Smart Mobility Hubs (SMH) 1134 days 25% Thu 8/18/16 Tue 2/9/21
1389 5.4.1 Phase I ‐ Systems Engineering 786 days 70% Thu 8/18/16 Mon 9/16/19
1390 5.4.1.1 SMH Strategy Plan 167 days 100% Thu 8/18/16 Fri 4/7/17
1395 5.4.1.2 SMH Concept of Operations (ConOps) 134 days 100% Fri 1/19/18 Mon 7/30/18
1396 5.4.1.2.1 Draft SMH ConOps 122 days 100% Fri 1/19/18 Thu 7/12/18
1404 5.4.1.2.2 Final SMH ConOps 12 days 100% Thu 7/12/18 Mon 7/30/18
1411 5.4.1.3 SMH System Requirements Specification (SyRS) 65 days 100% Tue 8/14/18 Thu 11/15/18
1412 5.4.1.3.1 Draft SMH SyRS 48 days 100% Tue 8/14/18 Thu 10/18/18
1413 5.4.1.3.1.1 Prepare Draft SMH SyRS 30 days 100% Tue 8/14/18 Tue 9/25/18 1410FS+10 days
1414 5.4.1.3.1.2 CoC Review Draft SMH SyRS 3 days 100% Wed 9/26/18 Fri 9/28/18 1413
1415 5.4.1.3.1.3 Address Comments Draft SMH SyRS 2 days 100% Mon 10/1/18 Tue 10/2/18 1414
1416 5.4.1.3.1.4 CoC Final Review 1 day 100% Wed 10/3/18 Wed 10/3/18 1415
1417 5.4.1.3.1.5 Submit Draft SMH SyRS to USDOT 0 days 100% Wed 10/3/18 Wed 10/3/18 1416
8/29
1/7
10/3
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q2016 2017 2018 2019 2020 2021
Smart City ScheduleCooperative Agreement No. DTFH6116H00013
Smart Columbus Project - All Activities
file: SCC‐A‐SmartColumbus Program Schedule_revised_v8.mpp Page: 32/58 Printed on: Mon 1/28/19 @ 1:59 PM
ID Outline Number
Task Name Duration %Complete
Start Finish Predecessors
1418 5.4.1.3.1.6 USDOT Review Draft SMH SyRS 10 days 100% Thu 10/4/18 Thu 10/18/18 1417
1419 5.4.1.3.2 Final SMH SyRS 20 days 100% Thu 10/18/18 Thu 11/15/18
1420 5.4.1.3.2.1 Address Comments on Final SMH SyRS 12 days 100% Fri 10/19/18 Mon 11/5/18 1418
1421 5.4.1.3.2.2 Public Comment Period on SMH ConOps & SyRS 10 days 100% Thu 10/18/18 Wed 10/31/18 1420SS‐1 day
1422 5.4.1.3.2.3 Webinar on SMH ConOps & SyRS 1 day 100% Wed 10/24/18 Wed 10/24/18 1421SS+4 days
1423 5.4.1.3.2.4 CoC Review Final SMH SyRS 3 days 100% Tue 11/6/18 Thu 11/8/18 1420,1421
1424 5.4.1.3.2.5 Address Comments Final SMH SyRS 3 days 100% Fri 11/9/18 Wed 11/14/18 1423
1425 5.4.1.3.2.6 CoC Final Review 1 day 100% Thu 11/15/18 Thu 11/15/18 1424
1426 5.4.1.3.2.7 Submit Final SMH SyRS to USDOT 0 days 100% Thu 11/15/18 Thu 11/15/18 1425
1427 5.4.1.4 SMH Interface Control Document (ICD) 51 days 36% Tue 12/4/18 Fri 2/15/19
1428 5.4.1.4.1 Draft SMH ICD 28 days 64% Tue 12/4/18 Mon 1/14/19
1429 5.4.1.4.1.1 Prepare Draft SMH ICD 10 days 100% Tue 12/4/18 Mon 12/17/18 1426FS+10 days
1430 5.4.1.4.1.2 COC Review of Draft SMH 3 days 100% Tue 12/18/18 Thu 12/20/18 1429
1431 5.4.1.4.1.3 Address CoC Comments ICD 2 days 100% Fri 12/21/18 Mon 12/24/18 1430
1432 5.4.1.4.1.4 CoC Final Review 1 day 100% Wed 12/26/18 Wed 12/26/18 1431
1433 5.4.1.4.1.5 Submit Draft SMH ICD (Task B) 2 days 100% Wed 12/26/18 Fri 12/28/18 1432
1434 5.4.1.4.1.6 USDOT Review Draft SMH ICD 10 days 0% Mon 12/31/18 Mon 1/14/19 1433
1435 5.4.1.4.2 Final SMH ICD 24 days 0% Mon 1/14/19 Fri 2/15/19
1436 5.4.1.4.2.1 Receive USDOT Comments on Draft SMH ICD 0 days 0% Mon 1/14/19 Mon 1/14/19 1434
1437 5.4.1.4.2.2 Public Review Period for SMH ICD 10 days 0% Tue 1/15/19 Tue 1/29/19 1436
1438 5.4.1.4.2.3 Webinar for SMH ICD 1 day 0% Wed 1/23/19 Wed 1/23/19 1437SS+5 days
1439 5.4.1.4.2.4 Update SMH ICD 5 days 0% Tue 1/15/19 Tue 1/22/19 1436
1440 5.4.1.4.2.5 CoC Review 3 days 0% Wed 1/23/19 Fri 1/25/19 1439
1441 5.4.1.4.2.6 Address CoC Comments SMH ICD 2 days 0% Mon 1/28/19 Tue 1/29/19 1440
1442 5.4.1.4.2.7 CoC Final Review 1 day 0% Wed 1/30/19 Wed 1/30/19 1441,1437
1443 5.4.1.4.2.8 Submit Final SMH ICD to USDOT 0 days 0% Fri 2/15/19 Fri 2/15/19 1442,1498FF
1444 5.4.1.5 SMH System Design Document (SDD) 104 days 0% Mon 12/31/18 Wed 5/29/19
1445 5.4.1.5.1 Draft SMH SDD 73 days 0% Mon 12/31/18 Mon 4/15/19
11/15
1/14
2/15
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q2016 2017 2018 2019 2020 2021
Smart City ScheduleCooperative Agreement No. DTFH6116H00013
Smart Columbus Project - All Activities
file: SCC‐A‐SmartColumbus Program Schedule_revised_v8.mpp Page: 33/58 Printed on: Mon 1/28/19 @ 1:59 PM
ID Outline Number
Task Name Duration %Complete
Start Finish Predecessors
1446 5.4.1.5.1.1 Prepare Draft SMH SDD 48 days 0% Mon 12/31/18 Mon 3/11/19 1433
1447 5.4.1.5.1.2 COC Review of Draft SDD SMH 5 days 0% Tue 3/12/19 Mon 3/18/19 1446
1448 5.4.1.5.1.3 Update SDD 10 days 0% Tue 3/19/19 Mon 4/1/19 1447
1449 5.4.1.5.1.4 Submit Draft SMH SDD (Task B) 0 days 0% Mon 4/1/19 Mon 4/1/19 1448
1450 5.4.1.5.1.5 USDOT Review Draft SMH SDD 10 days 0% Tue 4/2/19 Mon 4/15/19 1449
1451 5.4.1.5.2 Final SMH SDD 31 days 0% Mon 4/15/19 Wed 5/29/19
1452 5.4.1.5.2.1 Receive USDOT Comments on Draft SMH SDD 0 days 0% Mon 4/15/19 Mon 4/15/19 1450
1453 5.4.1.5.2.2 Update Final SMH SDD 20 days 0% Tue 4/16/19 Mon 5/13/19 1452
1454 5.4.1.5.2.3 Public Comment Period for SMH SDD 10 days 0% Tue 4/30/19 Mon 5/13/19 1453SS+10 days
1455 5.4.1.5.2.4 Webinar for SMH SDD 1 day 0% Tue 5/7/19 Tue 5/7/19 1454SS+5 days
1456 5.4.1.5.2.5 CoC Review 5 days 0% Tue 5/14/19 Mon 5/20/19 1453
1457 5.4.1.5.2.6 Address CoC Comments SDD 5 days 0% Tue 5/21/19 Tue 5/28/19 1456
1458 5.4.1.5.2.7 CoC Final Review 1 day 0% Wed 5/29/19 Wed 5/29/19 1457,1454
1459 5.4.1.5.2.8 Submit Final SMH SDD 0 days 0% Wed 5/29/19 Wed 5/29/19 1458
1460 5.4.1.6 SMH Test Plan (TP) 107 days 0% Tue 4/16/19 Mon 9/16/19
1461 5.4.1.6.1 Draft SMH Test Plan 51 days 0% Tue 4/16/19 Wed 6/26/19
1462 5.4.1.6.1.1 Prepare Draft SMH Test Plan 30 days 0% Tue 4/16/19 Tue 5/28/19 1452
1463 5.4.1.6.1.2 COC Review of SMH Test Plan 5 days 0% Wed 5/29/19 Tue 6/4/19 1462
1464 5.4.1.6.1.3 Address CoC Comments SMH Test Plan 5 days 0% Wed 6/5/19 Tue 6/11/19 1463
1465 5.4.1.6.1.4 CoC Final Review 1 day 0% Wed 6/12/19 Wed 6/12/19 1464
1466 5.4.1.6.1.5 Submit Draft SMH Test Plan (Task B) 0 days 0% Wed 6/12/19 Wed 6/12/19 1465
1467 5.4.1.6.1.6 USDOT Review Draft SMH Test Plan 10 days 0% Thu 6/13/19 Wed 6/26/19 1466
1468 5.4.1.6.2 Final SMH Test Plan 56 days 0% Wed 6/26/19 Mon 9/16/19
1469 5.4.1.6.2.1 Receive USDOT Comments on Draft SMH Test Plan 0 days 0% Wed 6/26/19 Wed 6/26/19 1467
1470 5.4.1.6.2.2 Update SMH Test Plan 10 days 0% Fri 8/16/19 Thu 8/29/19 1469,1528
1471 5.4.1.6.2.3 Public Comment Period for SMH Test Plan 10 days 0% Fri 8/16/19 Thu 8/29/19 1470SS
1472 5.4.1.6.2.4 Webinar for SMH Test Plan 1 day 0% Fri 8/23/19 Fri 8/23/19 1471SS+5 days
1473 5.4.1.6.2.5 CoC Review 5 days 0% Fri 8/30/19 Fri 9/6/19 1470
4/1
4/15
5/29
6/12
6/26
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q2016 2017 2018 2019 2020 2021
Smart City ScheduleCooperative Agreement No. DTFH6116H00013
Smart Columbus Project - All Activities
file: SCC‐A‐SmartColumbus Program Schedule_revised_v8.mpp Page: 34/58 Printed on: Mon 1/28/19 @ 1:59 PM
ID Outline Number
Task Name Duration %Complete
Start Finish Predecessors
1474 5.4.1.6.2.6 Update Test Plan 5 days 0% Mon 9/9/19 Fri 9/13/19 1473
1475 5.4.1.6.2.7 CoC Final Review 1 day 0% Mon 9/16/19 Mon 9/16/19 1474
1476 5.4.1.6.2.8 Submit Final SMH Test Plan 0 days 0% Mon 9/16/19 Mon 9/16/19 1475,1459FS+10 day
1477 5.4.2 Phase II ‐ Develop, Procure, Deploy 621 days 7% Tue 8/14/18 Tue 2/9/21
1478 5.4.2.1 Design 256 days 31% Tue 8/14/18 Wed 8/21/19
1479 5.4.2.1.1 Stage 1 96 days 80% Tue 8/14/18 Thu 1/3/19
1480 5.4.2.1.1.1 Finalize HUB locations 10 days 100% Tue 8/14/18 Mon 8/27/18 1410FS+10 days
1481 5.4.2.1.1.2 Survey 30 days 75% Wed 9/26/18 Wed 11/7/18 1480FS+20 days
1482 5.4.2.1.1.3 Utility coordination 50 days 75% Wed 9/12/18 Mon 11/26/18 1480FS+10 days
1483 5.4.2.1.1.4 Site plans 37 days 95% Tue 8/28/18 Fri 10/19/18 1480
1484 5.4.2.1.1.5 Network communication plans 10 days 100% Thu 10/11/18 Thu 11/1/18 1483
1485 5.4.2.1.1.6 Power service plans 10 days 100% Tue 11/27/18 Mon 12/10/18 1482
1486 5.4.2.1.1.7 Stage 1 submittal 1 day 100% Tue 12/11/18 Tue 12/11/18 1484,1485
1487 5.4.2.1.1.8 Stage 1 review 15 days 30% Wed 12/12/18 Thu 1/3/19 1486
1488 5.4.2.1.2 RoW (if needed) 160 days 0% Fri 1/4/19 Wed 8/21/19
1489 5.4.2.1.2.1 RoW plans 10 days 0% Fri 1/4/19 Thu 1/17/19 1487
1490 5.4.2.1.2.2 RoW certification 30 days 0% Fri 1/18/19 Mon 3/4/19 1489
1491 5.4.2.1.2.3 RoW aquistion 120 days 0% Tue 3/5/19 Wed 8/21/19 1490
1492 5.4.2.1.3 Stage 3 35 days 0% Fri 1/4/19 Mon 2/25/19
1493 5.4.2.1.3.1 Address stage 1 review comments 10 days 0% Fri 1/4/19 Thu 1/17/19 1487
1494 5.4.2.1.3.2 Finalize HUB services 10 days 0% Fri 1/18/19 Fri 2/1/19 1493
1495 5.4.2.1.3.3 Network communication plans 15 days 0% Mon 2/4/19 Mon 2/25/19 1494
1496 5.4.2.1.4 Develop plan quantities 5 days 0% Fri 1/18/19 Fri 1/25/19 1493
1497 5.4.2.1.5 Engineer's Estimate 5 days 0% Mon 1/28/19 Fri 2/1/19 1496
1498 5.4.2.1.6 Submit Final Plans (P,S, & E) 10 days 0% Mon 2/4/19 Fri 2/15/19 1497
1499 5.4.2.1.7 City Review 15 days 0% Tue 2/19/19 Mon 3/11/19 1498
1500 5.4.2.1.8 USDOT Review 10 days 0% Tue 3/12/19 Mon 3/25/19 1499
1501 5.4.2.1.9 Signatures 20 days 0% Tue 2/19/19 Mon 3/18/19 1498
9/16
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q2016 2017 2018 2019 2020 2021
Smart City ScheduleCooperative Agreement No. DTFH6116H00013
Smart Columbus Project - All Activities
file: SCC‐A‐SmartColumbus Program Schedule_revised_v8.mpp Page: 35/58 Printed on: Mon 1/28/19 @ 1:59 PM
ID Outline Number
Task Name Duration %Complete
Start Finish Predecessors
1502 5.4.2.2 Installation Procurement 106 days 0% Tue 3/19/19 Thu 8/15/19
1503 5.4.2.2.1 Develop procurement criteria (Site, Kiosk, Software) 15 days 0% Tue 3/19/19 Mon 4/8/19 1487,1501
1504 5.4.2.2.2 Prepare contract documents 1 day 0% Tue 4/9/19 Tue 4/9/19 1503
1505 5.4.2.2.3 City review 10 days 0% Wed 4/10/19 Tue 4/23/19 1504
1506 5.4.2.2.4 Issue for bid (IFB) 0 days 0% Tue 4/23/19 Tue 4/23/19 1505
1507 5.4.2.2.5 Receive proposals 20 days 0% Wed 4/24/19 Tue 5/21/19 1506
1508 5.4.2.2.6 City evaluation of bids 10 days 0% Wed 5/22/19 Wed 6/5/19 1507
1509 5.4.2.2.7 OSS Vendor Recommendation to CINO 5 days 0% Thu 6/6/19 Wed 6/12/19 1508
1510 5.4.2.2.8 CINO approves vendor recommentation 0 days 0% Wed 6/12/19 Wed 6/12/19 1509
1511 5.4.2.2.9 Legislation Process 31 days 0% Thu 6/13/19 Fri 7/26/19
1512 5.4.2.2.9.1 Prepare legislation and submit to Fiscal (min 2 working days da 3 days 0% Thu 6/13/19 Mon 6/17/19 1510
1513 5.4.2.2.9.2 Fiscal modifies and processes legislation (min 6 working days) 3 days 0% Tue 6/18/19 Thu 6/20/19 1512
1514 5.4.2.2.9.3 To CIFO 2 days 0% Fri 6/21/19 Mon 6/24/19 1513
1515 5.4.2.2.9.4 To Finance 3 days 0% Tue 6/25/19 Thu 6/27/19 1514
1516 5.4.2.2.9.5 To Equal Business Opportunity (min 4 working days) 2 days 0% Fri 6/28/19 Mon 7/1/19 1515
1517 5.4.2.2.9.6 To Auditor (min 2 working days) 3 days 0% Tue 7/2/19 Fri 7/5/19 1516
1518 5.4.2.2.9.7 To City Attorney (min 2 working days) 3 days 0% Mon 7/8/19 Wed 7/10/19 1517
1519 5.4.2.2.9.8 To City Clerk (min 6 working days) 10 days 0% Thu 7/11/19 Wed 7/24/19 1518
1520 5.4.2.2.9.9 Council passes legislation (Mon) 1 day 0% Thu 7/25/19 Thu 7/25/19 1519
1521 5.4.2.2.9.10 Mayor Signs (Thurs) 1 day 0% Fri 7/26/19 Fri 7/26/19 1520
1522 5.4.2.2.10 Contract Process 26 days 0% Thu 7/11/19 Thu 8/15/19
1523 5.4.2.2.10.1 Prepare contract documents 4 days 0% Mon 7/29/19 Thu 8/1/19 1521
1524 5.4.2.2.10.2 Fiscal enters Performance information 2 days 0% Mon 7/29/19 Tue 7/30/19 1521
1525 5.4.2.2.10.3 Sent to Consultant and returned to City 7 days 0% Thu 7/11/19 Fri 7/19/19 1518
1526 5.4.2.2.10.4 To City Attorney 5 days 0% Wed 7/31/19 Tue 8/6/19 1524
1527 5.4.2.2.10.5 To Auditor 5 days 0% Wed 8/7/19 Tue 8/13/19 1526
1528 5.4.2.2.10.6 Notice to proceed issued 2 days 0% Wed 8/14/19 Thu 8/15/19 1527
1529 5.4.2.3 Installation 72 days 0% Fri 8/16/19 Mon 12/2/19
4/23
6/12
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q2016 2017 2018 2019 2020 2021
Smart City ScheduleCooperative Agreement No. DTFH6116H00013
Smart Columbus Project - All Activities
file: SCC‐A‐SmartColumbus Program Schedule_revised_v8.mpp Page: 36/58 Printed on: Mon 1/28/19 @ 1:59 PM
ID Outline Number
Task Name Duration %Complete
Start Finish Predecessors
1530 5.4.2.3.1 Infrastructure Improvements 72 days 0% Fri 8/16/19 Mon 12/2/19 1528
1531 5.4.2.3.2 Install Kiosks 40 days 0% Wed 10/2/19 Mon 12/2/19 1530FF
1532 5.4.2.4 Draft O&M Manual 54 days 0% Wed 10/30/19 Tue 1/21/20
1533 5.4.2.4.1 Develop Draft O&M Manual 20 days 0% Wed 10/30/19 Mon 12/2/19 1534SF
1534 5.4.2.4.2 QA/QC Draft O&M Manual 5 days 0% Mon 12/2/19 Mon 12/9/19 1535SF
1535 5.4.2.4.3 CoC Review Draft O&M Manual 5 days 0% Mon 12/9/19 Mon 12/16/19 1536SF
1536 5.4.2.4.4 Address Comments From CoC Review 5 days 0% Mon 12/16/19 Mon 12/23/19 1537SF
1537 5.4.2.4.5 CoC Final Review 1 day 0% Mon 12/23/19 Tue 12/24/19 1538SF
1538 5.4.2.4.6 Submit Draft O&M Manual 0 days 0% Tue 12/24/19 Tue 12/24/19 1539SF
1539 5.4.2.4.7 USDOT Review Draft O&M Manual 10 days 0% Tue 12/24/19 Thu 1/9/20 1540SF
1540 5.4.2.4.8 Receive DOT Comments Draft O&M Manual 0 days 0% Thu 1/9/20 Thu 1/9/20 1541SF
1541 5.4.2.4.9 Update Final Draft O&M Manual 8 days 0% Thu 1/9/20 Tue 1/21/20 1567FF‐22 days
1542 5.4.2.5 IRB Process 155 days 0% Tue 4/16/19 Mon 11/25/19
1543 5.4.2.5.1 Engage IRB 20 days 0% Tue 4/16/19 Mon 5/13/19 1452
1544 5.4.2.5.2 Survey Development for IRB 20 days 0% Tue 5/14/19 Tue 6/11/19 1543
1545 5.4.2.5.3 Develop and Submit Human Use Approval Request for IRB 20 days 0% Wed 6/12/19 Wed 7/10/19 1544
1546 5.4.2.5.4 IRB Review and Provide Findings (Initial) 45 days 0% Thu 7/11/19 Thu 9/12/19 1545
1547 5.4.2.5.5 Update and Submit IRB Application (If needed) 30 days 0% Fri 9/13/19 Fri 10/25/19 1546
1548 5.4.2.5.6 IRB Review and Provide Findings (Revised) 20 days 0% Mon 10/28/19 Mon 11/25/19 1547
1549 5.4.2.6 Post‐Installation 250 days 0% Tue 12/3/19 Tue 12/1/20
1550 5.4.2.6.1 Verification 15 days 0% Tue 12/3/19 Mon 12/23/19
1551 5.4.2.6.1.1 Component Verfication 10 days 0% Tue 12/3/19 Mon 12/16/19 1530,1531
1552 5.4.2.6.1.2 System Verification 5 days 0% Tue 12/17/19 Mon 12/23/19 1551
1553 5.4.2.6.2 City completes as‐built drawing mark‐ups 30 days 0% Tue 12/3/19 Wed 1/15/20 1551SS
1554 5.4.2.6.3 Consultant makes as‐built revisions 37 days 0% Thu 1/16/20 Tue 3/10/20 1553
1555 5.4.2.6.4 City reviews revisions 30 days 0% Wed 3/11/20 Tue 4/21/20 1554
1556 5.4.2.6.5 Consultant makes final revisions 12 days 0% Wed 4/22/20 Thu 5/7/20 1555
1557 5.4.2.6.6 Evaluation of Consultant 10 days 0% Fri 5/8/20 Thu 5/21/20 1556
12/24
1/9
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q2016 2017 2018 2019 2020 2021
Smart City ScheduleCooperative Agreement No. DTFH6116H00013
Smart Columbus Project - All Activities
file: SCC‐A‐SmartColumbus Program Schedule_revised_v8.mpp Page: 37/58 Printed on: Mon 1/28/19 @ 1:59 PM
ID Outline Number
Task Name Duration %Complete
Start Finish Predecessors
1558 5.4.2.6.7 Warranty work check‐out (within one year of completion) 250 days 0% Tue 12/3/19 Tue 12/1/20 1551SS
1559 5.4.2.7 Testing 40 days 0% Tue 12/24/19 Fri 2/21/20
1560 5.4.2.7.1 Prepare for Acceptance Testing (Schedule, Eqpt, Artifacts) 10 days 0% Tue 12/24/19 Wed 1/8/20 1552,1548
1561 5.4.2.7.2 Conduct Acceptance Testing 6 days 0% Thu 1/9/20 Thu 1/16/20 1560,1476FS+10 day
1562 5.4.2.7.3 Review Results with Contractor 1 day 0% Fri 1/17/20 Fri 1/17/20 1561
1563 5.4.2.7.4 Contractor Revisions based on Test Results 7 days 0% Tue 1/21/20 Wed 1/29/20 1562
1564 5.4.2.7.5 Perform Regression Testing Until Acceptance 6 days 0% Thu 1/30/20 Thu 2/6/20 1563
1565 5.4.2.7.6 Prepare and Submit Test Report 10 days 0% Fri 2/7/20 Fri 2/21/20 1564
1566 5.4.2.8 Demonstration Period 242 days 0% Fri 2/21/20 Tue 2/9/21
1567 5.4.2.8.1 Go Live 0 days 0% Fri 2/21/20 Fri 2/21/20 1565FF
1568 5.4.2.8.2 Performance and System Monitoring 242 days 0% Mon 2/24/20 Tue 2/9/21 1567
1569 5.4.2.8.3 Data Collection 242 days 0% Mon 2/24/20 Tue 2/9/21 1567
1570 5.4.2.8.4 O&M Plan Final Update 20 days 0% Tue 1/12/21 Tue 2/9/21 1568FF,1569FF
1571 5.4.2.8.5 Quarterly Update 1 (Application) 66 days 0% Mon 2/24/20 Tue 5/26/20 1567
1572 5.4.2.8.6 Quarterly Update 2 (Application) 66 days 0% Wed 5/27/20 Thu 8/27/20 1571
1573 5.5 Mobility Assistance (MAPCD) 951 days 58% Thu 8/18/16 Thu 5/14/20
1574 5.5.1 Phase I ‐ Systems Engineering 677 days 96% Thu 8/18/16 Thu 4/11/19
1575 5.5.1.1 MA Strategy Plan 224 days 100% Thu 8/18/16 Wed 6/28/17
1580 5.5.1.2 MA Trade Study 238 days 100% Mon 5/1/17 Mon 4/2/18
1600 5.5.1.3 MA Interface Control Document (ICD) 91 days 100% Tue 4/3/18 Thu 8/9/18
1601 5.5.1.3.1 Draft Mobility Assistance Interfaces 60 days 100% Tue 4/3/18 Tue 6/26/18
1608 5.5.1.3.2 Final Mobility Assistance Interfaces 31 days 100% Tue 6/26/18 Thu 8/9/18
1616 5.5.1.4 MA Test Plan (TP) 144 days 74% Wed 9/12/18 Thu 4/11/19
1617 5.5.1.4.1 Draft Mobility Assistance Test Plan 61 days 100% Wed 9/12/18 Tue 12/11/18
1618 5.5.1.4.1.1 Prepare Draft Mobility Assistance Test Plan 40 days 100% Wed 9/12/18 Wed 11/7/18 1615
1619 5.5.1.4.1.2 COC Review of Mobility Assistance Test Plan 5 days 100% Thu 11/8/18 Thu 11/15/18 1618
1620 5.5.1.4.1.3 Address CoC Comments 5 days 100% Fri 11/16/18 Mon 11/26/18 1619
1621 5.5.1.4.1.4 CoC Final Review 1 day 100% Tue 11/27/18 Tue 11/27/18 1620
2/21
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q2016 2017 2018 2019 2020 2021
Smart City ScheduleCooperative Agreement No. DTFH6116H00013
Smart Columbus Project - All Activities
file: SCC‐A‐SmartColumbus Program Schedule_revised_v8.mpp Page: 38/58 Printed on: Mon 1/28/19 @ 1:59 PM
ID Outline Number
Task Name Duration %Complete
Start Finish Predecessors
1622 5.5.1.4.1.5 Submit Draft Mobility Assistance Test Plan (Task B) 0 days 100% Tue 11/27/18 Tue 11/27/18 1621
1623 5.5.1.4.1.6 USDOT Review Draft Mobility Assistance Test Plan 10 days 100% Wed 11/28/18 Tue 12/11/18 1622
1624 5.5.1.4.2 Final Mobility Assistance Test Plan 83 days 30% Tue 12/11/18 Thu 4/11/19
1625 5.5.1.4.2.1 Receive USDOT Comments on Draft Mobility Assistance Test Pl 0 days 100% Tue 12/11/18 Tue 12/11/18 1623
1626 5.5.1.4.2.2 Update Mobility Assistance Test Plan 15 days 75% Wed 12/12/18 Thu 1/3/19 1625
1627 5.5.1.4.2.3 Public Comment Period for MAPCD Test Plan 10 days 0% Fri 1/4/19 Thu 1/17/19 1626
1628 5.5.1.4.2.4 Webinar for MAPCD Test Plan and results 1 day 0% Thu 4/11/19 Thu 4/11/19 1627SS+5 days,1666
1629 5.5.1.4.2.5 CoC Review 5 days 0% Fri 1/4/19 Thu 1/10/19 1626
1630 5.5.1.4.2.6 Update Test Plan 5 days 0% Fri 1/11/19 Thu 1/17/19 1629
1631 5.5.1.4.2.7 CoC Final Review 1 day 0% Fri 1/18/19 Fri 1/18/19 1630,1627
1632 5.5.1.4.2.8 Submit Final Mobility Assistance Test Plan 0 days 0% Fri 1/18/19 Fri 1/18/19 1631
1633 5.5.2 Phase II ‐ Develop, Procure, Deploy 541 days 34% Tue 3/20/18 Thu 5/14/20
1634 5.5.2.1 Contract 70 days 100% Tue 3/20/18 Tue 6/26/18
1635 5.5.2.1.1 Finalize Contract with Mobility Assistance Partner 70 days 100% Tue 3/20/18 Tue 6/26/18 1609FF
1636 5.5.2.2 Draft O&M Manual 54 days 0% Thu 1/10/19 Thu 3/28/19
1637 5.5.2.2.1 Develop Draft O&M Manual 20 days 0% Thu 1/10/19 Fri 2/8/19 1638SF
1638 5.5.2.2.2 QA/QC Draft O&M Manual 5 days 0% Fri 2/8/19 Fri 2/15/19 1639SF
1639 5.5.2.2.3 CoC Review Draft O&M Manual 5 days 0% Fri 2/15/19 Mon 2/25/19 1640SF
1640 5.5.2.2.4 Address Comments From CoC Review 5 days 0% Mon 2/25/19 Mon 3/4/19 1641SF
1641 5.5.2.2.5 CoC Final Review 1 day 0% Mon 3/4/19 Tue 3/5/19 1642SF
1642 5.5.2.2.6 Submit Draft O&M Manual 0 days 0% Tue 3/5/19 Tue 3/5/19 1643SF
1643 5.5.2.2.7 USDOT Review Draft O&M Manual 10 days 0% Tue 3/5/19 Tue 3/19/19 1644SF
1644 5.5.2.2.8 Receive DOT Comments Draft O&M Manual 0 days 0% Tue 3/19/19 Tue 3/19/19 1645SF
1645 5.5.2.2.9 Update Final Draft O&M Manual 8 days 0% Tue 3/19/19 Thu 3/28/19 1668FF‐22 days
1646 5.5.2.3 IRB Process 143 days 69% Fri 7/27/18 Mon 2/25/19
1647 5.5.2.3.1 Engage IRB ‐ OSU 5 days 100% Fri 7/27/18 Thu 8/2/18 1614
1648 5.5.2.3.2 Develop Participant Recruitment Plan 59 days 100% Fri 8/3/18 Fri 10/26/18 1647
1649 5.5.2.3.3 Develop and Submit Human Use Approval Request for IRB 10 days 100% Fri 8/31/18 Fri 11/2/18 1648
11/27
12/11
1/18
3/5
3/19
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q2016 2017 2018 2019 2020 2021
Smart City ScheduleCooperative Agreement No. DTFH6116H00013
Smart Columbus Project - All Activities
file: SCC‐A‐SmartColumbus Program Schedule_revised_v8.mpp Page: 39/58 Printed on: Mon 1/28/19 @ 1:59 PM
ID Outline Number
Task Name Duration %Complete
Start Finish Predecessors
1650 5.5.2.3.4 IRB Review and Provide Findings (Initial) 10 days 100% Mon 11/5/18 Mon 11/19/18 1649
1651 5.5.2.3.5 Update and Submit IRB Application (If needed) 28 days 0% Mon 12/31/18 Fri 2/8/19 1650FS+26 days
1652 5.5.2.3.6 IRB Review and Provide Findings (Revised) 10 days 0% Mon 2/11/19 Mon 2/25/19 1651
1653 5.5.2.4 Product Delivery 269 days 58% Tue 4/3/18 Mon 4/29/19
1654 5.5.2.4.1 Refinements and Updates to Mobility App based on Smart Columbus Needs
60 days 100% Tue 4/3/18 Tue 6/26/18 1599,1609FF
1655 5.5.2.4.2 Recruitment of Test Participants 40 days 75% Tue 10/23/18 Thu 12/20/18
1656 5.5.2.4.3 COTA, OSU, Franklin County Board of Developmental Disabilities preparation for deployment
40 days 10% Fri 12/21/18 Wed 2/20/19 1655,1661
1657 5.5.2.4.4 Training Program 23 days 0% Thu 3/28/19 Mon 4/29/19 1656,1666
1658 5.5.2.5 Testing 206 days 78% Wed 5/30/18 Wed 3/27/19
1659 5.5.2.5.1 Prepare for Acceptance Testing (Schedule, Eqpt, Artifacts) 20 days 100% Wed 5/30/18 Tue 6/26/18 1654FF
1660 5.5.2.5.2 OSU Conduct Testing 40 days 100% Wed 6/27/18 Wed 8/22/18 1659
1661 5.5.2.5.3 AbleLink Incorporate Findings from OSU Testing 66 days 100% Thu 8/23/18 Thu 11/29/18 1660
1662 5.5.2.5.4 Conduct Acceptance Testing 10 days 0% Tue 2/5/19 Tue 2/19/19 1659,1632FS+10 day
1663 5.5.2.5.5 Review Results with Contractor 1 day 0% Wed 2/20/19 Wed 2/20/19 1662
1664 5.5.2.5.6 Contractor Revisions based on Test Results 10 days 0% Thu 2/21/19 Wed 3/6/19 1663
1665 5.5.2.5.7 Perform Regression Testing Until Acceptance 5 days 0% Thu 3/7/19 Wed 3/13/19 1664
1666 5.5.2.5.8 Prepare and Submit Test Report 10 days 0% Thu 3/14/19 Wed 3/27/19 1665
1667 5.5.2.6 Demonstration Period 262 days 0% Mon 4/29/19 Thu 5/14/20
1668 5.5.2.6.1 Go Live 0 days 0% Mon 4/29/19 Mon 4/29/19 1657
1669 5.5.2.6.2 Performance and System Monitoring 262 days 0% Tue 4/30/19 Thu 5/14/20 1668
1670 5.5.2.6.3 Data Collection 262 days 0% Tue 4/30/19 Thu 5/14/20 1668
1671 5.5.2.6.4 O&M Plan Final Update 20 days 0% Fri 4/17/20 Thu 5/14/20 1669FF,1670FF
1672 5.6 Connected Electric Autonomous Vehicle (CEAV) ‐ Revised 689 days 21% Wed 3/7/18 Fri 12/4/20
1673 5.6.1 Project evaluation 39 days 100% Wed 3/7/18 Mon 4/30/18
1678 5.6.2 Concept Development for RFP #2 96 days 89% Mon 7/2/18 Fri 11/16/18
1689 5.6.3 Procurement 274 days 61% Tue 5/1/18 Tue 6/4/19
1690 5.6.3.1 Procurement #1 (Columbus Partnership + ODOT) 86 days 100% Tue 5/1/18 Thu 8/30/18
4/29
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q2016 2017 2018 2019 2020 2021
Smart City ScheduleCooperative Agreement No. DTFH6116H00013
Smart Columbus Project - All Activities
file: SCC‐A‐SmartColumbus Program Schedule_revised_v8.mpp Page: 40/58 Printed on: Mon 1/28/19 @ 1:59 PM
ID Outline Number
Task Name Duration %Complete
Start Finish Predecessors
1691 5.6.3.1.1 Develop RFP 55 days 100% Tue 5/1/18 Wed 7/18/18
1698 5.6.3.1.2 Responses Due 0 days 100% Thu 8/9/18 Thu 8/9/18 1696FS+18 days
1699 5.6.3.1.3 Evaluation and Vendor Selection 10 days 100% Fri 8/10/18 Thu 8/23/18 1698
1700 5.6.3.1.4 Notice to proceed 5 days 100% Fri 8/24/18 Thu 8/30/18 1699
1701 5.6.3.2 Procurement #2 (CoC + ODOT + OSU) 231 days 44% Mon 7/2/18 Tue 6/4/19
1702 5.6.3.2.1 RFI 86 days 100% Mon 7/2/18 Thu 11/1/18
1703 5.6.3.2.1.1 RFI background (routes, evaluation criteria, data, etc.) 20 days 100% Mon 7/2/18 Mon 7/30/18 1695
1704 5.6.3.2.1.2 Draft RFI (Aligns with Draft Operational Concept) 5 days 100% Thu 9/13/18 Wed 9/19/18 1681FF,1703
1705 5.6.3.2.1.3 USDOT Review 10 days 100% Thu 9/20/18 Wed 10/3/18 1704
1706 5.6.3.2.1.4 Final RFI 5 days 100% Thu 10/4/18 Thu 10/11/18 1705
1707 5.6.3.2.1.5 RFI Release (OSU) 0 days 100% Thu 10/11/18 Thu 10/11/18 1706
1708 5.6.3.2.1.6 Vendor Response 0 days 100% Thu 11/1/18 Thu 11/1/18 1707FS+15 days
1709 5.6.3.2.2 RFP #2 135 days 25% Mon 11/19/18 Tue 6/4/19
1710 5.6.3.2.2.1 RFP development (use cases, data and integration requirement 20 days 100% Mon 11/19/18 Tue 12/18/18 1688,1708
1711 5.6.3.2.2.2 USDOT Review 10 days 100% Wed 12/19/18 Thu 1/3/19 1710
1712 5.6.3.2.2.3 Final RFP 10 days 0% Fri 1/4/19 Thu 1/17/19 1711
1713 5.6.3.2.2.4 RFP Release 0 days 0% Thu 1/17/19 Thu 1/17/19 1712
1714 5.6.3.2.2.5 Vendor Response 0 days 0% Fri 2/8/19 Fri 2/8/19 1712FS+15 days
1715 5.6.3.2.2.6 Downselect 10 days 0% Mon 2/11/19 Mon 2/25/19 1714
1716 5.6.3.2.2.7 Vendor Interviews 20 days 0% Tue 2/26/19 Mon 3/25/19 1715
1717 5.6.3.2.2.8 Vendor Recommendation 5 days 0% Tue 3/26/19 Mon 4/1/19 1716
1718 5.6.3.2.2.9 CINO Approves Recommendation 1 day 0% Tue 4/2/19 Tue 4/2/19 1717
1719 5.6.3.2.2.10 Legislation Process 12 days 0% Wed 4/3/19 Thu 4/18/19
1720 5.6.3.2.2.10.1 Prepare and Submit to Fiscal 5 days 0% Wed 4/3/19 Tue 4/9/19 1718
1721 5.6.3.2.2.10.2 Council Passes Legislation 5 days 0% Wed 4/10/19 Tue 4/16/19 1720
1722 5.6.3.2.2.10.3 Mayor Approves 2 days 0% Wed 4/17/19 Thu 4/18/19 1721
1723 5.6.3.2.2.11 Contract Process 7 days 0% Fri 4/19/19 Mon 4/29/19
1724 5.6.3.2.2.11.1 Prepare Contract Documents 5 days 0% Fri 4/19/19 Thu 4/25/19 1722
8/9
10/11
11/1
1/17
2/8
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q2016 2017 2018 2019 2020 2021
Smart City ScheduleCooperative Agreement No. DTFH6116H00013
Smart Columbus Project - All Activities
file: SCC‐A‐SmartColumbus Program Schedule_revised_v8.mpp Page: 41/58 Printed on: Mon 1/28/19 @ 1:59 PM
ID Outline Number
Task Name Duration %Complete
Start Finish Predecessors
1725 5.6.3.2.2.11.2 Review and Sign Off 2 days 0% Fri 4/26/19 Mon 4/29/19 1724
1726 5.6.3.2.2.12 NTP 25 days 0% Tue 4/30/19 Tue 6/4/19 1725
1727 5.6.4 Phase II ‐ Develop, Deploy/Test, Demonstrate 564 days 9% Fri 8/31/18 Fri 12/4/20
1728 5.6.4.1 Product Development 308 days 40% Fri 8/31/18 Mon 11/25/19
1729 5.6.4.1.1 Solution Delivery (Turn Key) 272 days 34% Fri 8/31/18 Wed 10/2/19
1730 5.6.4.1.1.1 Vendor/RFP #1 40 days 100% Fri 8/31/18 Mon 10/29/18 1700
1731 5.6.4.1.1.2 Safety Management Plan Inputs 1 day 100% Tue 10/30/18 Tue 10/30/18 1730
1732 5.6.4.1.1.3 Operational Demonstration 2 days 100% Tue 10/30/18 Wed 10/31/18 1730
1733 5.6.4.1.1.4 Vendor/RFP #2 80 days 0% Wed 6/5/19 Thu 9/26/19 1726
1734 5.6.4.1.1.5 Safety Management Plan Inputs 1 day 0% Fri 9/27/19 Fri 9/27/19 1733
1735 5.6.4.1.1.6 Operational Demonstrations 4 days 0% Fri 9/27/19 Wed 10/2/19 1733
1736 5.6.4.1.2 Infrastructure ‐ RFP #1 40 days 100% Tue 10/30/18 Fri 12/28/18
1737 5.6.4.1.2.1 Infrastructure enhancements 20 days 100% Tue 10/30/18 Thu 11/29/18 1730
1738 5.6.4.1.2.2 RSU installation 20 days 100% Fri 11/30/18 Fri 12/28/18 1730FF,1737
1739 5.6.4.1.3 Infrastructure ‐ RFP #2 40 days 0% Fri 9/27/19 Mon 11/25/19
1740 5.6.4.1.3.1 Infrastructure enhancements 20 days 0% Fri 9/27/19 Fri 10/25/19 1733
1741 5.6.4.1.3.2 RSU installation 20 days 0% Mon 10/28/19 Mon 11/25/19 1740
1742 5.6.4.2 Deployment 333 days 29% Tue 10/9/18 Mon 2/10/20
1743 5.6.4.2.1 IRB Process (Vendor #2) 90 days 0% Fri 9/27/19 Mon 2/10/20
1744 5.6.4.2.1.1 Engage IRB 10 days 0% Fri 9/27/19 Thu 10/10/19 1733
1745 5.6.4.2.1.2 Develop Participant Recruitment Plan 20 days 0% Fri 10/11/19 Fri 11/8/19 1744
1746 5.6.4.2.1.3 Develop and Submit Human Use Approval Request for IRB 20 days 0% Tue 11/12/19 Wed 12/11/19 1745
1747 5.6.4.2.1.4 IRB Review and Provide Findings (Initial) 10 days 0% Thu 12/12/19 Thu 12/26/19 1746
1748 5.6.4.2.1.5 Update and Submit IRB Application 20 days 0% Fri 12/27/19 Mon 1/27/20 1747
1749 5.6.4.2.1.6 IRB Review and Provide Findings (Revised) 10 days 0% Tue 1/28/20 Mon 2/10/20 1748
1750 5.6.4.2.2 Verification 243 days 50% Tue 10/9/18 Thu 9/26/19
1751 5.6.4.2.2.1 Vendor #1 15 days 100% Tue 10/9/18 Mon 10/29/18
1752 5.6.4.2.2.1.1 Component Verfication 10 days 100% Tue 10/9/18 Mon 10/22/18 1730FF‐5 days
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q2016 2017 2018 2019 2020 2021
Smart City ScheduleCooperative Agreement No. DTFH6116H00013
Smart Columbus Project - All Activities
file: SCC‐A‐SmartColumbus Program Schedule_revised_v8.mpp Page: 42/58 Printed on: Mon 1/28/19 @ 1:59 PM
ID Outline Number
Task Name Duration %Complete
Start Finish Predecessors
1753 5.6.4.2.2.1.2 System Verification 5 days 100% Tue 10/23/18 Mon 10/29/18 1730FF
1754 5.6.4.2.2.2 Vendor #2 15 days 0% Fri 9/6/19 Thu 9/26/19
1755 5.6.4.2.2.2.1 Component Verfication 10 days 0% Fri 9/6/19 Thu 9/19/19 1733FF‐5 days
1756 5.6.4.2.2.2.2 System Verification 5 days 0% Fri 9/20/19 Thu 9/26/19 1733FF
1757 5.6.4.2.3 Testing 264 days 49% Tue 10/30/18 Tue 11/19/19
1758 5.6.4.2.3.1 Vendor #1 53 days 87% Tue 10/30/18 Thu 1/17/19
1759 5.6.4.2.3.1.1 Test Plan (Schedule, Eqpt, Artifacts) 17 days 100% Tue 10/30/18 Mon 11/26/18 1753
1760 5.6.4.2.3.1.2 Conduct Acceptance Testing 10 days 100% Tue 11/27/18 Mon 12/10/18 1759
1761 5.6.4.2.3.1.3 Review Results with Contractor 1 day 100% Tue 12/11/18 Tue 12/11/18 1760
1762 5.6.4.2.3.1.4 Contractor Revisions based on Test Results 10 days 100% Wed 12/12/18 Wed 12/26/18 1761
1763 5.6.4.2.3.1.5 Perform Regression Testing Until Acceptance 5 days 100% Thu 12/27/18 Thu 1/3/19 1762
1764 5.6.4.2.3.1.6 Prepare and Submit Test Report (Test Logs) 10 days 30% Fri 1/4/19 Thu 1/17/19 1763
1765 5.6.4.2.3.2 Vendor #2 41 days 0% Fri 9/20/19 Tue 11/19/19
1766 5.6.4.2.3.2.1 Test Plan (Schedule, Eqpt, Artifacts) 5 days 0% Fri 9/20/19 Thu 9/26/19 1756FF
1767 5.6.4.2.3.2.2 Conduct Acceptance Testing 10 days 0% Fri 9/27/19 Thu 10/10/19 1766
1768 5.6.4.2.3.2.3 Review Results with Contractor 1 day 0% Fri 10/11/19 Fri 10/11/19 1767
1769 5.6.4.2.3.2.4 Contractor Revisions based on Test Results 10 days 0% Tue 10/15/19 Mon 10/28/19 1768
1770 5.6.4.2.3.2.5 Perform Regression Testing Until Acceptance 5 days 0% Tue 10/29/19 Mon 11/4/19 1769
1771 5.6.4.2.3.2.6 Prepare and Submit Test Report (Test Logs) 10 days 0% Tue 11/5/19 Tue 11/19/19 1770
1772 5.6.4.3 Demonstration Period 451 days 0% Thu 1/17/19 Tue 11/3/20
1773 5.6.4.3.1 Go Live (Vendor #1) 0 days 100% Thu 1/17/19 Thu 1/17/19 1764FF
1774 5.6.4.3.2 Go Live (Vendor #2) 0 days 0% Tue 11/19/19 Tue 11/19/19 1771FF
1775 5.6.4.3.3 Integration to Operating System (Vendor #1) 20 days 0% Fri 1/18/19 Fri 2/15/19 1773
1776 5.6.4.3.4 Integration to Operating System (Vendor #2) 20 days 0% Wed 11/20/19 Thu 12/19/19 1774
1777 5.6.4.3.5 Performance and System Monitoring (Vendor #1) 240 days 0% Fri 1/18/19 Fri 1/3/20 1773
1778 5.6.4.3.6 Performance and System Monitoring (Vendor #2) 240 days 0% Wed 11/20/19 Tue 11/3/20 1774
1779 5.6.4.3.7 Data Collection (Vendor #1) 240 days 0% Fri 1/18/19 Fri 1/3/20 1773
1780 5.6.4.3.8 Data Collection (Vendor #2) 240 days 0% Wed 11/20/19 Tue 11/3/20 1774
1/17
11/19
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q2016 2017 2018 2019 2020 2021
Smart City ScheduleCooperative Agreement No. DTFH6116H00013
Smart Columbus Project - All Activities
file: SCC‐A‐SmartColumbus Program Schedule_revised_v8.mpp Page: 43/58 Printed on: Mon 1/28/19 @ 1:59 PM
ID Outline Number
Task Name Duration %Complete
Start Finish Predecessors
1781 5.6.4.4 Documentation 50 days 0% Tue 9/22/20 Fri 12/4/20
1782 5.6.4.4.1 Draft Demonstration Summary 50 days 0% Tue 9/22/20 Fri 12/4/20
1783 5.6.4.4.1.1 Lessons Learned 30 days 0% Tue 9/22/20 Tue 11/3/20 1779FF,1780FF
1784 5.6.4.4.1.2 Deployment Playbook 40 days 0% Tue 10/6/20 Fri 12/4/20
1785 5.6.4.4.1.2.1 User acceptance 20 days 0% Tue 10/6/20 Tue 11/3/20 1779FF,1780FF
1786 5.6.4.4.1.2.2 Interoperability 20 days 0% Wed 11/4/20 Fri 12/4/20 1785
1787 5.6.4.4.1.2.3 Safety 10 days 0% Wed 11/4/20 Wed 11/18/20 1785
1788 5.6.4.4.2 USDOT Review 10 days 0% Wed 11/4/20 Wed 11/18/20 1783
1789 5.6.4.4.3 Final Demonstration Summary 10 days 0% Thu 11/19/20 Fri 12/4/20 1788
1790 5.7 Event Parking Management (EPM) 1168 days 36% Thu 8/18/16 Tue 3/30/21
1791 5.7.1 Phase I ‐ Systems Engineering 821 days 69% Thu 8/18/16 Tue 11/5/19
1792 5.7.1.1 EPM Strategy Plan 167 days 100% Thu 8/18/16 Fri 4/7/17
1797 5.7.1.2 EPM Concept of Operations (ConOps) 730 days 90% Fri 12/2/16 Tue 10/15/19
1798 5.7.1.2.1 Draft Event Parking Management ConOps 166 days 100% Fri 12/2/16 Fri 7/21/17
1804 5.7.1.2.2 Event Parking Management ConOps Walkthrough 2 days 100% Wed 8/9/17 Fri 8/11/17
1809 5.7.1.2.3 Additional End User Engagement 69 days 100% Mon 1/22/18 Fri 4/27/18
1815 5.7.1.2.4 Final Event Parking Management ConOps 71 days 100% Tue 4/3/18 Thu 7/12/18
1830 5.7.1.2.5 ConOps Refresh 41 days 0% Fri 8/16/19 Tue 10/15/19
1831 5.7.1.2.5.1 Update ConOps per SDD Changes 20 days 0% Fri 8/16/19 Fri 9/13/19 1895FS+10 days
1832 5.7.1.2.5.2 CoC Review 5 days 0% Mon 9/16/19 Fri 9/20/19 1831
1833 5.7.1.2.5.3 Address CoC Comments ConOps 5 days 0% Mon 9/23/19 Fri 9/27/19 1832
1834 5.7.1.2.5.4 CoC Final Review 1 day 0% Mon 9/30/19 Mon 9/30/19 1833
1835 5.7.1.2.5.5 Submit Final Revised ConOps 0 days 0% Mon 9/30/19 Mon 9/30/19 1834
1836 5.7.1.2.5.6 USDOT Review Final Revised ConOps 10 days 0% Tue 10/1/19 Tue 10/15/19 1835
1837 5.7.1.2.5.7 Receive DOT Approval on Revised ConOps 0 days 0% Tue 10/15/19 Tue 10/15/19 1836
1838 5.7.1.3 EPM System Requirements Specification (SyRS) 330 days 76% Fri 7/13/18 Tue 11/5/19
1839 5.7.1.3.1 Draft Event Parking Management SyRS 61 days 100% Fri 7/13/18 Tue 10/9/18
1846 5.7.1.3.2 Final Event Parking Management SyRS 42 days 100% Wed 10/10/18 Tue 12/11/18
9/30
10/15
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q2016 2017 2018 2019 2020 2021
Smart City ScheduleCooperative Agreement No. DTFH6116H00013
Smart Columbus Project - All Activities
file: SCC‐A‐SmartColumbus Program Schedule_revised_v8.mpp Page: 44/58 Printed on: Mon 1/28/19 @ 1:59 PM
ID Outline Number
Task Name Duration %Complete
Start Finish Predecessors
1847 5.7.1.3.2.1 Update Final Event Parking Management SyRS 31 days 100% Wed 10/10/18 Mon 11/26/18 1845
1848 5.7.1.3.2.2 Public Comment Period for EPM SyRS 10 days 100% Thu 11/8/18 Mon 11/26/18 1847SS+21 days
1849 5.7.1.3.2.3 Webinar for EPM SyRS 1 day 100% Thu 11/15/18 Thu 11/15/18 1848SS+4 days
1850 5.7.1.3.2.4 CoC Review 5 days 100% Tue 11/27/18 Mon 12/3/18 1847
1851 5.7.1.3.2.5 Address coC Comments EPM SyRS 5 days 100% Tue 12/4/18 Mon 12/10/18 1850
1852 5.7.1.3.2.6 CoC Final Review 1 day 100% Tue 12/11/18 Tue 12/11/18 1851
1853 5.7.1.3.2.7 Submit Final Event Parking Management SyRS 0 days 100% Tue 12/11/18 Tue 12/11/18 1852
1854 5.7.1.3.3 SyRS Refresh 36 days 0% Mon 9/16/19 Tue 11/5/19
1855 5.7.1.3.3.1 Update SyRS per SDD Changes 15 days 0% Mon 9/16/19 Fri 10/4/19 1895FS+30 days
1856 5.7.1.3.3.2 CoC Review 5 days 0% Mon 10/7/19 Fri 10/11/19 1855
1857 5.7.1.3.3.3 Address CoC Comments SyRS 5 days 0% Tue 10/15/19 Mon 10/21/19 1856
1858 5.7.1.3.3.4 CoC Final Review 1 day 0% Tue 10/22/19 Tue 10/22/19 1857
1859 5.7.1.3.3.5 Submit Final Revised Event Parking Management SyRS 0 days 0% Tue 10/22/19 Tue 10/22/19 1858
1860 5.7.1.3.3.6 USDOT Review Final Revised SyRS 10 days 0% Wed 10/23/19 Tue 11/5/19 1859
1861 5.7.1.3.3.7 Receive DOT Approval on Revised SyRS 0 days 0% Tue 11/5/19 Tue 11/5/19 1860
1862 5.7.1.4 EPM Interface Control Document (ICD) 62 days 0% Thu 12/27/18 Wed 3/27/19
1863 5.7.1.4.1 Draft Event Parking Management Interfaces 41 days 0% Thu 12/27/18 Tue 2/26/19
1864 5.7.1.4.1.1 Prepare Draft Event Parking Management Interfaces 20 days 0% Thu 12/27/18 Fri 1/25/19 1853FS+10 days
1865 5.7.1.4.1.2 COC Review of Draft Event Parking Management Interfaces 5 days 0% Mon 1/28/19 Fri 2/1/19 1864
1866 5.7.1.4.1.3 Address CoC Comments Draft EPM Interfaces 5 days 0% Mon 2/4/19 Fri 2/8/19 1865
1867 5.7.1.4.1.4 CoC Final Review 1 day 0% Mon 2/11/19 Mon 2/11/19 1866
1868 5.7.1.4.1.5 Submit Draft Event Parking Management Interfaces (Task B) 0 days 0% Mon 2/11/19 Mon 2/11/19 1867
1869 5.7.1.4.1.6 USDOT Review Draft Event Parking Management Interfaces 10 days 0% Tue 2/12/19 Tue 2/26/19 1868
1870 5.7.1.4.2 Final Event Parking Management Interfaces 21 days 0% Tue 2/26/19 Wed 3/27/19
1871 5.7.1.4.2.1 Receive USDOT Comments on Draft Event Parking Management Interfaces
0 days 0% Tue 2/26/19 Tue 2/26/19 1869
1872 5.7.1.4.2.2 Public Comment Period for EPM ICD 10 days 0% Wed 2/27/19 Tue 3/12/19 1871
1873 5.7.1.4.2.3 Webinar for EPM ICD 1 day 0% Wed 3/6/19 Wed 3/6/19 1872SS+5 days
1874 5.7.1.4.2.4 Update Event Parking Management Interfaces 10 days 0% Wed 2/27/19 Tue 3/12/19 1871
12/11
10/22
11/5
2/11
2/26
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q2016 2017 2018 2019 2020 2021
Smart City ScheduleCooperative Agreement No. DTFH6116H00013
Smart Columbus Project - All Activities
file: SCC‐A‐SmartColumbus Program Schedule_revised_v8.mpp Page: 45/58 Printed on: Mon 1/28/19 @ 1:59 PM
ID Outline Number
Task Name Duration %Complete
Start Finish Predecessors
1875 5.7.1.4.2.5 CoC Review 5 days 0% Wed 3/13/19 Tue 3/19/19 1874
1876 5.7.1.4.2.6 Address CoC Comments EPM Interfaces 5 days 0% Wed 3/20/19 Tue 3/26/19 1875
1877 5.7.1.4.2.7 CoC Final Review 1 day 0% Wed 3/27/19 Wed 3/27/19 1876
1878 5.7.1.4.2.8 Submit Final Event Parking Management Interfaces 0 days 0% Wed 3/27/19 Wed 3/27/19 1877
1879 5.7.1.5 EPM System Design Document (SDD) 120 days 0% Tue 2/12/19 Thu 8/1/19
1880 5.7.1.5.1 Draft Event Parking Management System Design Document 81 days 0% Tue 2/12/19 Thu 6/6/19
1881 5.7.1.5.1.1 Prepare Draft Event Parking Management System Design Docu 60 days 0% Tue 2/12/19 Tue 5/7/19 1844,1868
1882 5.7.1.5.1.2 COC Review of Draft SDD Event Parking Management 5 days 0% Wed 5/8/19 Tue 5/14/19 1881
1883 5.7.1.5.1.3 Address CoC Comments Draft EPM SDD 5 days 0% Wed 5/15/19 Tue 5/21/19 1882
1884 5.7.1.5.1.4 CoC Final Review 1 day 0% Wed 5/22/19 Wed 5/22/19 1883
1885 5.7.1.5.1.5 Submit Draft Event Parking Management System Design Document (Task B)
0 days 0% Wed 5/22/19 Wed 5/22/19 1884
1886 5.7.1.5.1.6 USDOT Review Draft Event Parking Management System Design Document
10 days 0% Thu 5/23/19 Thu 6/6/19 1885
1887 5.7.1.5.2 Final Event Parking Management System Design Document 39 days 0% Thu 6/6/19 Thu 8/1/19
1888 5.7.1.5.2.1 Receive USDOT Comments on Draft Event Parking Management System Design Document
0 days 0% Thu 6/6/19 Thu 6/6/19 1886
1889 5.7.1.5.2.2 Update Final Event Parking Management System Design Docum 20 days 0% Wed 6/19/19 Wed 7/17/19 1888,1949
1890 5.7.1.5.2.3 Public Comment Period for EPM SDD 10 days 0% Wed 7/3/19 Wed 7/17/19 1889SS+10 days
1891 5.7.1.5.2.4 Webinar for EPM SDD 1 day 0% Thu 7/11/19 Thu 7/11/19 1890SS+5 days
1892 5.7.1.5.2.5 CoC Review 5 days 0% Thu 7/18/19 Wed 7/24/19 1889
1893 5.7.1.5.2.6 Address CoC Comments EPM System Design Document 5 days 0% Thu 7/25/19 Wed 7/31/19 1892
1894 5.7.1.5.2.7 CoC Final Review 1 day 0% Thu 8/1/19 Thu 8/1/19 1893
1895 5.7.1.5.2.8 Submit Final Event Parking Management System Design Docum 0 days 0% Thu 8/1/19 Thu 8/1/19 1894
1896 5.7.1.6 EPM Test Plan (TP) 72 days 0% Thu 5/23/19 Wed 9/4/19
1897 5.7.1.6.1 Draft Event Parking Management Test Plan 51 days 0% Thu 5/23/19 Mon 8/5/19
1898 5.7.1.6.1.1 Prepare Draft Event Parking Management Test Plan 30 days 0% Thu 5/23/19 Fri 7/5/19 1885
1899 5.7.1.6.1.2 COC Review of Event Parking Management Test Plan 5 days 0% Mon 7/8/19 Fri 7/12/19 1898
1900 5.7.1.6.1.3 Address CoC Comments Draft EPM Test Plan 5 days 0% Mon 7/15/19 Fri 7/19/19 1899
3/27
5/22
6/6
8/1
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q2016 2017 2018 2019 2020 2021
Smart City ScheduleCooperative Agreement No. DTFH6116H00013
Smart Columbus Project - All Activities
file: SCC‐A‐SmartColumbus Program Schedule_revised_v8.mpp Page: 46/58 Printed on: Mon 1/28/19 @ 1:59 PM
ID Outline Number
Task Name Duration %Complete
Start Finish Predecessors
1901 5.7.1.6.1.4 CoC Final Review 1 day 0% Mon 7/22/19 Mon 7/22/19 1900
1902 5.7.1.6.1.5 Submit Draft Event Parking Management Test Plan (Task B) 0 days 0% Mon 7/22/19 Mon 7/22/19 1901
1903 5.7.1.6.1.6 USDOT Review Draft Event Parking Management Test Plan 10 days 0% Tue 7/23/19 Mon 8/5/19 1902
1904 5.7.1.6.2 Final Event Parking Management Test Plan 21 days 0% Mon 8/5/19 Wed 9/4/19
1905 5.7.1.6.2.1 Receive USDOT Comments on Draft Event Parking Management Test Plan
0 days 0% Mon 8/5/19 Mon 8/5/19 1903
1906 5.7.1.6.2.2 Public Comment Period for EPM Test Plan 10 days 0% Tue 8/6/19 Mon 8/19/19 1905
1907 5.7.1.6.2.3 Webinar for EPM Test Plan 1 day 0% Tue 8/13/19 Tue 8/13/19 1906SS+5 days
1908 5.7.1.6.2.4 Update Event Parking Management Test Plan 10 days 0% Tue 8/6/19 Mon 8/19/19 1905,1949
1909 5.7.1.6.2.5 CoC Review 5 days 0% Tue 8/20/19 Mon 8/26/19 1908
1910 5.7.1.6.2.6 Address CoC Comments EPM Test Plan 5 days 0% Tue 8/27/19 Tue 9/3/19 1909
1911 5.7.1.6.2.7 CoC Final Review 1 day 0% Wed 9/4/19 Wed 9/4/19 1910
1912 5.7.1.6.2.8 Submit Final Event Parking Management Test Plan 0 days 0% Wed 9/4/19 Wed 9/4/19 1911
1913 5.7.2 Phase II ‐ Develop, Procure, Deploy 702 days 6% Thu 6/7/18 Tue 3/30/21
1914 5.7.2.1 Procurement 161 days 26% Thu 10/25/18 Tue 6/18/19
1915 5.7.2.1.1 Develop Procurement Criteria 22 days 100% Thu 10/25/18 Wed 11/28/18 1845FS+11 days
1916 5.7.2.1.2 CoC Review/Approval 22 days 100% Thu 11/29/18 Mon 12/31/18 1915
1917 5.7.2.1.3 Prepare contract documents 9 days 0% Wed 1/2/19 Mon 1/14/19 1916
1918 5.7.2.1.4 RFP Release 1 day 0% Tue 1/15/19 Tue 1/15/19 1917
1919 5.7.2.1.5 RFP Posting 20 days 0% Wed 1/16/19 Wed 2/13/19 1918
1920 5.7.2.1.6 Pre‐bid meeting 1 day 0% Thu 1/24/19 Thu 1/24/19 1918FS+5 days
1921 5.7.2.1.7 Addendum(s) issued if required, minimum 72 hours prior to bid o 7 days 0% Fri 1/25/19 Mon 2/4/19 1920
1922 5.7.2.1.8 Receive vendor proposals 1 day 0% Thu 2/14/19 Thu 2/14/19 1919
1923 5.7.2.1.9 City review vendor proposals 10 days 0% Fri 2/15/19 Fri 3/1/19 1922
1924 5.7.2.1.10 CoC Evaluation 5 days 0% Mon 3/4/19 Fri 3/8/19 1923
1925 5.7.2.1.11 Select responsive and responsible contractor 5 days 0% Mon 3/11/19 Fri 3/15/19 1924
1926 5.7.2.1.12 Prepare recommendation memo for signature 2 days 0% Mon 3/18/19 Tue 3/19/19 1925
1927 5.7.2.1.13 Recommend vendor to CINO 5 days 0% Wed 3/20/19 Tue 3/26/19 1926
1928 5.7.2.1.14 Receive letter of contractor approval from CINO 1 day 0% Wed 3/27/19 Wed 3/27/19 1927
7/22
8/5
9/4
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q2016 2017 2018 2019 2020 2021
Smart City ScheduleCooperative Agreement No. DTFH6116H00013
Smart Columbus Project - All Activities
file: SCC‐A‐SmartColumbus Program Schedule_revised_v8.mpp Page: 47/58 Printed on: Mon 1/28/19 @ 1:59 PM
ID Outline Number
Task Name Duration %Complete
Start Finish Predecessors
1929 5.7.2.1.15 Legislation Process 35 days 0% Thu 3/28/19 Wed 5/15/19
1930 5.7.2.1.15.1 Prepare legislation and submit to Fiscal (2 working days days) 3 days 0% Thu 3/28/19 Mon 4/1/19 1928
1931 5.7.2.1.15.2 Fiscal modifies and processes legislation (6 working days) 6 days 0% Tue 4/2/19 Tue 4/9/19 1930
1932 5.7.2.1.15.3 To Administrator (2 working days) 2 days 0% Wed 4/10/19 Thu 4/11/19 1931
1933 5.7.2.1.15.4 To CIFO (4 working days) 3 days 0% Fri 4/12/19 Tue 4/16/19 1932
1934 5.7.2.1.15.5 To Finance (7 working days) 3 days 0% Wed 4/17/19 Fri 4/19/19 1933
1935 5.7.2.1.15.6 To Equal Business Opportunity (4 working days) 2 days 0% Mon 4/22/19 Tue 4/23/19 1934
1936 5.7.2.1.15.7 To Auditor (2 working days) 2 days 0% Wed 4/24/19 Thu 4/25/19 1935
1937 5.7.2.1.15.8 To City Attorney (2 working days) 2 days 0% Fri 4/26/19 Mon 4/29/19 1936
1938 5.7.2.1.15.9 To City Clerk (6 working days min.) 10 days 0% Tue 4/30/19 Mon 5/13/19 1937
1939 5.7.2.1.15.10 Council passes legislation* 1 day 0% Tue 5/14/19 Tue 5/14/19 1938
1940 5.7.2.1.15.11 Mayor Signs (2 working days) 1 day 0% Wed 5/15/19 Wed 5/15/19 1939
1941 5.7.2.1.16 Contract Process 23 days 0% Thu 5/16/19 Tue 6/18/19
1942 5.7.2.1.16.1 Prepare contract documents 1 day 0% Thu 5/16/19 Thu 5/16/19 1940
1943 5.7.2.1.16.2 Fiscal enters Performance information 1 day 0% Fri 5/17/19 Fri 5/17/19 1942
1944 5.7.2.1.16.3 Sent to Consultant and returned to City 0 days 0% Fri 5/17/19 Fri 5/17/19 1943
1945 5.7.2.1.16.4 To CIFO 5 days 0% Mon 5/20/19 Fri 5/24/19 1944
1946 5.7.2.1.16.5 To City Attorney 5 days 0% Tue 5/28/19 Mon 6/3/19 1945
1947 5.7.2.1.16.6 To Auditor 5 days 0% Tue 6/4/19 Mon 6/10/19 1946
1948 5.7.2.1.16.7 To Equal Business Opportunity 5 days 0% Tue 6/11/19 Mon 6/17/19 1947
1949 5.7.2.1.16.8 Notice to proceed issued 1 day 0% Tue 6/18/19 Tue 6/18/19 1948
1950 5.7.2.2 Agreement 90 days 25% Wed 10/10/18 Thu 2/21/19
1951 5.7.2.2.1 Finalize Agreement with Parking Providers 90 days 25% Wed 10/10/18 Thu 2/21/19 1845
1952 5.7.2.3 Draft O&M Manual 54 days 0% Fri 12/6/19 Tue 2/25/20
1953 5.7.2.3.1 Develop Draft O&M Manual 20 days 0% Fri 12/6/19 Tue 1/7/20 1949,1954SF
1954 5.7.2.3.2 QA/QC Draft O&M Manual 5 days 0% Tue 1/7/20 Tue 1/14/20 1955SF
1955 5.7.2.3.3 CoC Review Draft O&M Manual 5 days 0% Tue 1/14/20 Wed 1/22/20 1956SF
1956 5.7.2.3.4 Address Comments From CoC Review 5 days 0% Wed 1/22/20 Wed 1/29/20 1957SF
5/17
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q2016 2017 2018 2019 2020 2021
Smart City ScheduleCooperative Agreement No. DTFH6116H00013
Smart Columbus Project - All Activities
file: SCC‐A‐SmartColumbus Program Schedule_revised_v8.mpp Page: 48/58 Printed on: Mon 1/28/19 @ 1:59 PM
ID Outline Number
Task Name Duration %Complete
Start Finish Predecessors
1957 5.7.2.3.5 CoC Final Review 1 day 0% Wed 1/29/20 Thu 1/30/20 1958SF
1958 5.7.2.3.6 Submit Draft O&M Manual 0 days 0% Thu 1/30/20 Thu 1/30/20 1959SF
1959 5.7.2.3.7 USDOT Review Draft O&M Manual 10 days 0% Thu 1/30/20 Thu 2/13/20 1960SF
1960 5.7.2.3.8 Receive DOT Comments Draft O&M Manual 0 days 0% Thu 2/13/20 Thu 2/13/20 1961SF
1961 5.7.2.3.9 Update Final Draft O&M Manual 8 days 0% Thu 2/13/20 Tue 2/25/20 1981FF‐22 days
1962 5.7.2.4 IRB Process 411 days 1% Thu 6/7/18 Thu 1/30/20
1963 5.7.2.4.1 Engage IRB 20 days 10% Thu 6/7/18 Mon 7/15/19 1970SS
1964 5.7.2.4.2 Develop Participant Recruitment Plan 20 days 0% Tue 7/16/19 Mon 8/12/19 1963
1965 5.7.2.4.3 Develop and Submit Human Use Approval Request for IRB 20 days 0% Tue 8/13/19 Tue 9/10/19 1964
1966 5.7.2.4.4 IRB Review and Provide Findings (Initial) 45 days 0% Wed 9/11/19 Thu 11/14/19 1965
1967 5.7.2.4.5 Update and Submit IRB Application (if needed) 30 days 0% Fri 11/15/19 Tue 12/31/19 1966
1968 5.7.2.4.6 IRB Review and Provide Findings (Revised) 20 days 0% Thu 1/2/20 Thu 1/30/20 1967
1969 5.7.2.5 Product Development 186 days 0% Wed 6/19/19 Wed 3/18/20
1970 5.7.2.5.1 Product Delivery 6.6 mons 0% Wed 6/19/19 Mon 12/30/19 1949
1971 5.7.2.5.2 Refinements and Updates to App based on Smart Columbus Need 30 days 0% Tue 12/31/19 Wed 2/12/20 1951,1970
1972 5.7.2.5.3 Preparation for Deployment 10 days 0% Thu 3/5/20 Wed 3/18/20 1968,1977
1973 5.7.2.6 Testing 40 days 0% Thu 1/30/20 Thu 3/26/20
1974 5.7.2.6.1 Prepare for Acceptance Testing (Schedule, Eqpt, Artifacts) 10 days 0% Thu 1/30/20 Wed 2/12/20 1971FF
1975 5.7.2.6.2 Conduct Acceptance Testing 6 days 0% Thu 2/13/20 Fri 2/21/20 1974,1912FS+10 day
1976 5.7.2.6.3 Review Results with Contractor 1 day 0% Mon 2/24/20 Mon 2/24/20 1975
1977 5.7.2.6.4 Contractor Revisions based on Test Results 7 days 0% Tue 2/25/20 Wed 3/4/20 1976
1978 5.7.2.6.5 Perform Regression Testing Until Acceptance 6 days 0% Thu 3/5/20 Thu 3/12/20 1977
1979 5.7.2.6.6 Prepare and Submit Test Report 10 days 0% Fri 3/13/20 Thu 3/26/20 1978
1980 5.7.2.7 Demonstration Period 252 days 0% Thu 3/26/20 Tue 3/30/21
1981 5.7.2.7.1 Go Live 0 days 0% Thu 3/26/20 Thu 3/26/20 1972,1979FF
1982 5.7.2.7.2 Performance and System Monitoring 252 days 0% Fri 3/27/20 Tue 3/30/21 1981
1983 5.7.2.7.3 Data Collection 252 days 0% Fri 3/27/20 Tue 3/30/21 1981
1984 5.7.2.7.4 O&M Plan Final Update 20 days 0% Wed 3/3/21 Tue 3/30/21 1982FF,1983FF
1/30
2/13
3/26
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q2016 2017 2018 2019 2020 2021
Smart City ScheduleCooperative Agreement No. DTFH6116H00013
Smart Columbus Project - All Activities
file: SCC‐A‐SmartColumbus Program Schedule_revised_v8.mpp Page: 49/58 Printed on: Mon 1/28/19 @ 1:59 PM
ID Outline Number
Task Name Duration %Complete
Start Finish Predecessors
1985 5.8 Prenatal Trip Assistance (PTA) 824 days 30% Fri 9/8/17 Fri 12/18/20
1986 5.8.1 Phase I ‐ Systems Engineering 306 days 100% Fri 9/8/17 Wed 11/21/18
1987 5.8.1.1 PTA Strategy Plan 148 days 100% Fri 9/8/17 Fri 4/6/18
1992 5.8.1.2 PTA Concept of Operations (ConOps) 158 days 100% Mon 4/9/18 Wed 11/21/18
1993 5.8.1.2.1 Draft PTA ConOps 47 days 100% Mon 4/9/18 Wed 6/13/18
2000 5.8.1.2.2 Final PTA ConOps 90 days 100% Mon 7/16/18 Wed 11/21/18
2001 5.8.1.2.2.1 Update Final PTA ConOps 30 days 100% Mon 7/16/18 Fri 8/24/18 2016,1999
2002 5.8.1.2.2.2 CoC Review 5 days 100% Mon 8/27/18 Fri 8/31/18 2001
2003 5.8.1.2.2.3 Address CoC Comments Final PTA ConOps 5 days 100% Tue 9/4/18 Mon 9/10/18 2002
2004 5.8.1.2.2.4 CoC Final Review 1 day 100% Tue 9/11/18 Tue 9/11/18 2003
2005 5.8.1.2.2.5 Submit Final PTA ConOps 0 days 100% Tue 9/11/18 Tue 9/11/18 2004
2006 5.8.1.2.2.6 Public Comment Period for PTA ConOps 10 days 100% Wed 11/7/18 Wed 11/21/18
2007 5.8.1.2.2.7 Webinar for PTA ConOps 1 day 100% Wed 11/14/18 Wed 11/14/18 2006SS+4 days
2008 5.8.2 Phase II ‐ Develop, Procure, Deploy 647 days 14% Fri 5/18/18 Fri 12/18/20
2009 5.8.2.1 Preparation for RFP/Agile Artifacts 40 days 100% Fri 5/18/18 Mon 7/16/18
2010 5.8.2.1.1 Product Roadmap 20 days 100% Fri 5/18/18 Fri 6/15/18 1994
2011 5.8.2.1.2 Requirements (essential, desirable, optional) 10 days 100% Mon 6/18/18 Fri 6/29/18 2010
2012 5.8.2.1.3 MVP definition 5 days 100% Mon 7/2/18 Mon 7/9/18 2011
2013 5.8.2.1.4 Business Value 5 days 100% Tue 7/10/18 Mon 7/16/18 2012
2014 5.8.2.2 RFP and Vendor Selection 130 days 93% Fri 6/29/18 Tue 1/8/19
2015 5.8.2.2.1 Develop RFP 70 days 100% Fri 6/29/18 Tue 10/9/18
2016 5.8.2.2.1.1 Draft RFP 10 days 100% Fri 6/29/18 Fri 7/13/18 1999FS+11 days
2017 5.8.2.2.1.2 Revised RFP 20 days 100% Mon 7/16/18 Fri 8/10/18 2016
2018 5.8.2.2.1.3 Stakeholder Review (MCO) 10 days 100% Mon 8/13/18 Fri 8/24/18 2017
2019 5.8.2.2.1.4 USDOT Review 10 days 100% Tue 9/11/18 Mon 9/24/18 2018FS+10 days
2020 5.8.2.2.1.5 Final RFP 10 days 100% Tue 9/25/18 Tue 10/9/18 2019
2021 5.8.2.2.2 Vendor Selection 26 days 100% Wed 10/10/18 Thu 11/15/18 2020
2022 5.8.2.2.3 Vendor Recommendation 5 days 100% Fri 11/16/18 Mon 11/26/18 2021
9/11
6/15
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q2016 2017 2018 2019 2020 2021
Smart City ScheduleCooperative Agreement No. DTFH6116H00013
Smart Columbus Project - All Activities
file: SCC‐A‐SmartColumbus Program Schedule_revised_v8.mpp Page: 50/58 Printed on: Mon 1/28/19 @ 1:59 PM
ID Outline Number
Task Name Duration %Complete
Start Finish Predecessors
2023 5.8.2.2.4 CINO Approval of Vendor Recommendation 2 days 100% Tue 11/27/18 Wed 11/28/18 2022
2024 5.8.2.2.5 Legislation Process 12 days 100% Thu 11/29/18 Fri 12/14/18
2025 5.8.2.2.5.1 Prepare and Submit to Fiscal 5 days 100% Thu 11/29/18 Wed 12/5/18 2023
2026 5.8.2.2.5.2 Council Passes Legislation 5 days 100% Thu 12/6/18 Wed 12/12/18 2025
2027 5.8.2.2.5.3 Mayor Approves 2 days 100% Thu 12/13/18 Fri 12/14/18 2026
2028 5.8.2.2.6 Contract Process 7 days 100% Mon 12/17/18 Wed 12/26/18
2029 5.8.2.2.6.1 Prepare Contract Documents 5 days 100% Mon 12/17/18 Fri 12/21/18 2027
2030 5.8.2.2.6.2 Review and Sign Off 2 days 100% Mon 12/24/18 Wed 12/26/18 2029
2031 5.8.2.2.7 Notice to proceed 8 days 0% Thu 12/27/18 Tue 1/8/19 2030
2032 5.8.2.3 Agile Development 90 days 0% Tue 1/8/19 Thu 5/16/19
2033 5.8.2.3.1 Kickoff 0 days 0% Tue 1/8/19 Tue 1/8/19 2031
2034 5.8.2.3.2 Release 1 40 days 0% Wed 1/9/19 Thu 3/7/19 2033
2035 5.8.2.3.3 Release 2 30 days 0% Fri 3/8/19 Thu 4/18/19 2034
2036 5.8.2.3.4 Release 3 20 days 0% Fri 4/19/19 Thu 5/16/19 2035
2037 5.8.2.4 IRB Process 47 days 47% Wed 1/9/19 Mon 3/18/19
2038 5.8.2.4.1 Engage IRB 2 days 100% Wed 1/9/19 Thu 1/10/19 2031
2039 5.8.2.4.2 Develop Participant Recruitment Plan 15 days 100% Fri 1/11/19 Fri 2/1/19 2038
2040 5.8.2.4.3 Develop and Submit Human Use Approval Request for IRB 10 days 50% Mon 2/4/19 Fri 2/15/19 2039
2041 5.8.2.4.4 IRB Review and Provide Findings (Initial) 5 days 0% Tue 2/19/19 Mon 2/25/19 2040
2042 5.8.2.4.5 Update and Submit IRB Application 10 days 0% Tue 2/26/19 Mon 3/11/19 2041
2043 5.8.2.4.6 IRB Review and Provide Findings (Revised) 5 days 0% Tue 3/12/19 Mon 3/18/19 2042
2044 5.8.2.5 Testing 130 days 0% Fri 4/19/19 Wed 10/23/19
2045 5.8.2.5.1 Participant recruitment 100 days 0% Fri 5/17/19 Tue 10/8/19 2036
2046 5.8.2.5.2 Testing and app refinement 30 days 0% Fri 4/19/19 Fri 5/31/19 2035
2047 5.8.2.5.3 Training 60 days 0% Mon 7/29/19 Wed 10/23/19 2045FF+10 days
2048 5.8.2.6 Demonstration Period 388 days 0% Fri 5/31/19 Fri 12/18/20
2049 5.8.2.6.1 Go Live 0 days 0% Fri 5/31/19 Fri 5/31/19 2036,2046
2050 5.8.2.6.2 Performance and System Monitoring (18 months) 388 days 0% Mon 6/3/19 Fri 12/18/20 2049
1/8
5/31
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q2016 2017 2018 2019 2020 2021
Smart City ScheduleCooperative Agreement No. DTFH6116H00013
Smart Columbus Project - All Activities
file: SCC‐A‐SmartColumbus Program Schedule_revised_v8.mpp Page: 51/58 Printed on: Mon 1/28/19 @ 1:59 PM
ID Outline Number
Task Name Duration %Complete
Start Finish Predecessors
2051 5.8.2.6.3 Data Collection (18 months) 388 days 0% Mon 6/3/19 Fri 12/18/20 2049
2052 6 Communications and Outreach 1040 days 70% Thu 8/18/16 Wed 8/12/20
2053 6.1 Communications and Outreach Plan (Comm Plan) 872 days 93% Thu 8/18/16 Fri 12/20/19
2054 6.1.1 Draft Comm Plan 78 days 100% Thu 8/18/16 Mon 12/5/16
2055 6.1.1.1 Comm Plan Initial Draft Submitted by City of Columbus 0 days 100% Thu 8/18/16 Thu 8/18/16
2056 6.1.1.2 Review and Update Draft Comm Plan / Crisis Comm 51 days 100% Thu 8/18/16 Fri 10/28/16 2055
2057 6.1.1.3 City Review of Draft Comm / Crisis Plan 10 days 100% Mon 10/31/16 Mon 11/14/16 2056
2058 6.1.1.4 Process CoC Comments 13 days 100% Tue 11/15/16 Mon 12/5/16 2057
2059 6.1.1.5 Submit Draft Comm Plan to USDOT (Task G) 0 days 100% Mon 12/5/16 Mon 12/5/16 2058
2060 6.1.2 Final Comm Plan 794 days 89% Tue 12/6/16 Fri 12/20/19
2061 6.1.2.1 USDOT Review of Final Draft Comm Plan 10 days 100% Tue 12/6/16 Mon 12/19/16 2059
2062 6.1.2.2 Receive DOT Comments on Draft Comm Plan 26 days 100% Wed 1/4/17 Wed 2/8/17 2061
2063 6.1.2.3 Prepare Final Comm Plan 5 days 100% Fri 2/10/17 Thu 2/16/17 2062
2064 6.1.2.4 Prepare Comm Plan Comment Resolution Report (CRR) 5 days 100% Fri 2/10/17 Thu 2/16/17 2062
2065 6.1.2.5 Submit Final Comm Plan 0 days 100% Thu 2/16/17 Thu 2/16/17 2063
2066 6.1.2.6 Submit Comm Plan Comment Resolution Report 0 days 100% Thu 2/16/17 Thu 2/16/17 2064
2067 6.1.2.7 Receive Comments and Resubmit Plan (Delete V Ref) 36 days 100% Fri 2/17/17 Fri 4/7/17 2065
2068 6.1.2.8 Receive Comments from USDOT 11 days 100% Mon 3/20/17 Mon 4/3/17
2069 6.1.2.9 Send Comments to USDOT 19 days 100% Tue 4/4/17 Fri 4/28/17 2068
2070 6.1.2.10 Prep and Request USDOT Comments Clarifications 12 days 100% Mon 5/1/17 Tue 5/16/17 2069
2071 6.1.2.11 Receive USDOT Clarifications Response 30 days 100% Wed 5/17/17 Tue 6/27/17 2070
2072 6.1.2.12 Resubmit Final Comm Plan to USDOT (v3) 2 days 100% Thu 6/29/17 Fri 6/30/17 2071
2073 6.1.2.13 Receive USDOT Comments (v3) 12 days 100% Fri 6/30/17 Mon 7/17/17 2072
2074 6.1.2.14 Receive Comment Clarifications (v3) via call 5 days 100% Wed 7/19/17 Tue 7/25/17 2073
2075 6.1.2.15 Create Comm Plan (v4) 60 days 100% Wed 7/26/17 Tue 10/17/17 2074
2076 6.1.2.16 Update Communications Plan 40 days 100% Mon 8/20/18 Tue 10/16/18
2077 6.1.2.17 USDOT Review of Draft Communications Plan 10 days 100% Wed 10/17/18 Tue 10/30/18 2076
2078 6.1.2.18 Revise to Final Communications Plan 20 days 100% Wed 10/31/18 Fri 11/30/18 2077
8/18
12/5
2/16
2/16
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q2016 2017 2018 2019 2020 2021
Smart City ScheduleCooperative Agreement No. DTFH6116H00013
Smart Columbus Project - All Activities
file: SCC‐A‐SmartColumbus Program Schedule_revised_v8.mpp Page: 52/58 Printed on: Mon 1/28/19 @ 1:59 PM
ID Outline Number
Task Name Duration %Complete
Start Finish Predecessors
2079 6.1.2.19 USDOT Review of Final Communications Plan 10 days 100% Mon 12/3/18 Fri 12/14/18 2078
2080 6.1.2.20 Quarterly Update #1 of Communications Plan 10 days 0% Mon 3/18/19 Fri 3/29/19 2079
2081 6.1.2.21 Quarterly Update #2 of Communications Plan 10 days 0% Mon 6/17/19 Fri 6/28/19 2080
2082 6.1.2.22 Quarterly Update #3 of Communications Plan 10 days 0% Mon 9/16/19 Fri 9/27/19 2081
2083 6.1.2.23 Quarterly Update #4 of Communications Plan 10 days 0% Mon 12/9/19 Fri 12/20/19 2082
2084 6.1.3 508 Compliant Documentation 119 days 100% Thu 2/9/17 Tue 7/25/17
2094 6.2 Public Relations and Marketing Material Development 451 days 100% Tue 11/15/16 Tue 8/7/18
2095 6.2.1 Communication Toolkit 413 days 100% Fri 1/6/17 Tue 8/7/18
2096 6.2.1.1 Year 1 Toolkit 167 days 100% Fri 1/6/17 Mon 8/28/17
2104 6.2.1.2 Year 2 Toolkit 246 days 100% Tue 8/29/17 Tue 8/7/18
2112 6.2.2 Brand Development 124 days 100% Tue 11/15/16 Fri 5/5/17
2120 6.3 Outreach Products 991 days 54% Mon 9/19/16 Wed 8/12/20
2121 6.3.1 Smart Columbus Video 289 days 0% Mon 6/3/19 Mon 7/27/20
2122 6.3.1.1 Develop Smart Columbus Video 20 days 0% Mon 6/3/19 Fri 6/28/19
2123 6.3.1.2 Update #1 20 days 0% Thu 12/12/19 Fri 1/10/20 2122SS+132 days
2124 6.3.1.3 Update #2 20 days 0% Mon 6/22/20 Mon 7/20/20 2123SS+132 days
2125 6.3.1.4 508 Compliant Documentation 5 days 0% Tue 7/21/20 Mon 7/27/20 2124
2126 6.3.2 Smart Columbus Website 977 days 55% Tue 11/15/16 Wed 8/12/20
2127 6.3.2.1 Website Strategy 5 days 100% Tue 11/15/16 Mon 11/21/16 2113
2128 6.3.2.2 Website Design 15 days 100% Fri 12/2/16 Thu 12/22/16 2112SS+11 days
2129 6.3.2.3 Website Design Review by City of Columbus (Task G) 5 days 100% Mon 1/9/17 Fri 1/13/17 2128
2130 6.3.2.4 Revise Design per Comments 5 days 100% Tue 1/17/17 Mon 1/23/17 2129
2131 6.3.2.5 Submittal of Final Website Design to City 0 days 100% Mon 1/23/17 Mon 1/23/17 2130
2132 6.3.2.6 City Review of Final Design 3 days 100% Tue 1/24/17 Thu 1/26/17 2131
2133 6.3.2.7 Incorporate Website Design Edits 13 days 100% Fri 1/27/17 Tue 2/14/17 2132
2134 6.3.2.8 City Final Approval 0 days 100% Tue 2/14/17 Tue 2/14/17 2133
2135 6.3.2.9 Live Website launched by City 5 days 100% Fri 3/17/17 Thu 3/23/17 2134FS+21 days
2136 6.3.2.10 Website Hosting and Maintenance by City 837 days 52% Fri 3/24/17 Wed 7/15/20 2135
1/23
2/14
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q2016 2017 2018 2019 2020 2021
Smart City ScheduleCooperative Agreement No. DTFH6116H00013
Smart Columbus Project - All Activities
file: SCC‐A‐SmartColumbus Program Schedule_revised_v8.mpp Page: 53/58 Printed on: Mon 1/28/19 @ 1:59 PM
ID Outline Number
Task Name Duration %Complete
Start Finish Predecessors
2137 6.3.2.11 Website / Blog Updates 918 days 57% Mon 2/6/17 Wed 8/12/20
2138 6.3.2.11.1 Initial update (Typical cycle, 30 days after Live Website) 26 days 100% Mon 4/3/17 Mon 5/8/17
2143 6.3.2.11.2 Regular Monthly Website Update 918 days 53% Mon 2/6/17 Wed 8/12/20
2144 6.3.2.11.2.1 Regular Monthly Website Update 1 8 days 100% Mon 2/6/17 Wed 2/15/17
2145 6.3.2.11.2.2 Regular Monthly Website Update 2 8 days 100% Mon 3/6/17 Wed 3/15/17
2146 6.3.2.11.2.3 Regular Monthly Website Update 3 8 days 100% Mon 4/3/17 Wed 4/12/17
2147 6.3.2.11.2.4 Regular Monthly Website Update 4 8 days 100% Mon 5/1/17 Wed 5/10/17
2148 6.3.2.11.2.5 Regular Monthly Website Update 5 8 days 100% Mon 6/5/17 Wed 6/14/17
2149 6.3.2.11.2.6 Regular Monthly Website Update 6 8 days 100% Mon 7/3/17 Wed 7/12/17
2150 6.3.2.11.2.7 Regular Monthly Website Update 7 8 days 100% Mon 8/7/17 Wed 8/16/17
2151 6.3.2.11.2.8 Regular Monthly Website Update 8 8 days 100% Mon 9/4/17 Wed 9/13/17
2152 6.3.2.11.2.9 Regular Monthly Website Update 9 8 days 100% Mon 10/2/17 Wed 10/11/17
2153 6.3.2.11.2.10 Regular Monthly Website Update 10 8 days 100% Mon 11/6/17 Wed 11/15/17
2154 6.3.2.11.2.11 Regular Monthly Website Update 11 8 days 100% Mon 12/4/17 Wed 12/13/17
2155 6.3.2.11.2.12 Regular Monthly Website Update 12 8 days 100% Mon 1/1/18 Wed 1/10/18
2156 6.3.2.11.2.13 Regular Monthly Website Update 13 8 days 100% Mon 2/5/18 Wed 2/14/18
2157 6.3.2.11.2.14 Regular Monthly Website Update 14 8 days 100% Mon 3/5/18 Wed 3/14/18
2158 6.3.2.11.2.15 Regular Monthly Website Update 15 8 days 100% Mon 4/2/18 Wed 4/11/18
2159 6.3.2.11.2.16 Regular Monthly Website Update 16 8 days 100% Mon 5/7/18 Wed 5/16/18
2160 6.3.2.11.2.17 Regular Monthly Website Update 17 8 days 100% Mon 6/4/18 Wed 6/13/18
2161 6.3.2.11.2.18 Regular Monthly Website Update 18 8 days 100% Mon 7/2/18 Thu 7/12/18
2162 6.3.2.11.2.19 Regular Monthly Website Update 19 8 days 100% Mon 8/6/18 Wed 8/15/18
2163 6.3.2.11.2.20 Regular Monthly Website Update 20 8 days 100% Tue 9/4/18 Thu 9/13/18
2164 6.3.2.11.2.21 Regular Monthly Website Update 21 8 days 100% Mon 10/1/18 Thu 10/11/18
2165 6.3.2.11.2.22 Regular Monthly Website Update 22 8 days 100% Mon 11/5/18 Thu 11/15/18
2166 6.3.2.11.2.23 Regular Monthly Website Update 23 8 days 100% Mon 12/3/18 Wed 12/12/18
2167 6.3.2.11.2.24 Regular Monthly Website Update 24 8 days 0% Mon 1/7/19 Wed 1/16/19
2168 6.3.2.11.2.25 Regular Monthly Website Update 25 8 days 0% Mon 2/4/19 Wed 2/13/19
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q2016 2017 2018 2019 2020 2021
Smart City ScheduleCooperative Agreement No. DTFH6116H00013
Smart Columbus Project - All Activities
file: SCC‐A‐SmartColumbus Program Schedule_revised_v8.mpp Page: 54/58 Printed on: Mon 1/28/19 @ 1:59 PM
ID Outline Number
Task Name Duration %Complete
Start Finish Predecessors
2169 6.3.2.11.2.26 Regular Monthly Website Update 26 8 days 0% Mon 3/4/19 Wed 3/13/19
2170 6.3.2.11.2.27 Regular Monthly Website Update 27 8 days 0% Mon 4/1/19 Wed 4/10/19
2171 6.3.2.11.2.28 Regular Monthly Website Update 28 8 days 0% Mon 5/6/19 Wed 5/15/19
2172 6.3.2.11.2.29 Regular Monthly Website Update 29 8 days 0% Mon 6/3/19 Wed 6/12/19
2173 6.3.2.11.2.30 Regular Monthly Website Update 30 8 days 0% Mon 7/1/19 Thu 7/11/19
2174 6.3.2.11.2.31 Regular Monthly Website Update 31 8 days 0% Mon 8/5/19 Wed 8/14/19
2175 6.3.2.11.2.32 Regular Monthly Website Update 32 8 days 0% Tue 9/3/19 Thu 9/12/19
2176 6.3.2.11.2.33 Regular Monthly Website Update 33 8 days 0% Mon 10/7/19 Thu 10/17/19
2177 6.3.2.11.2.34 Regular Monthly Website Update 34 8 days 0% Mon 11/4/19 Thu 11/14/19
2178 6.3.2.11.2.35 Regular Monthly Website Update 35 8 days 0% Mon 12/2/19 Wed 12/11/19
2179 6.3.2.11.2.36 Regular Monthly Website Update 36 8 days 0% Mon 1/6/20 Wed 1/15/20
2180 6.3.2.11.2.37 Regular Monthly Website Update 37 8 days 0% Mon 2/3/20 Wed 2/12/20
2181 6.3.2.11.2.38 Regular Monthly Website Update 38 8 days 0% Mon 3/2/20 Wed 3/11/20
2182 6.3.2.11.2.39 Regular Monthly Website Update 39 8 days 0% Mon 4/6/20 Wed 4/15/20
2183 6.3.2.11.2.40 Regular Monthly Website Update 40 8 days 0% Mon 5/4/20 Wed 5/13/20
2184 6.3.2.11.2.41 Regular Monthly Website Update 41 8 days 0% Mon 6/1/20 Wed 6/10/20
2185 6.3.2.11.2.42 Regular Monthly Website Update 42 8 days 0% Mon 7/6/20 Wed 7/15/20
2186 6.3.2.11.2.43 Regular Monthly Website Update 43 8 days 0% Mon 8/3/20 Wed 8/12/20
2187 6.3.3 Workshops/Conferences/Trade Shows (6/yr.) 1010 days 54% Mon 9/19/16 Fri 7/31/20
2188 6.3.3.1 Workshop/Conference/Trade Show Preparation 983 days 54% Mon 9/19/16 Fri 7/31/20
2189 6.3.3.1.1 Workshop/Conference/Trade Show Preparation 1 10 days 100% Mon 9/19/16 Fri 9/30/16
2190 6.3.3.1.2 Workshop/Conference/Trade Show Preparation 2 10 days 100% Mon 11/21/16 Fri 12/2/16
2191 6.3.3.1.3 Workshop/Conference/Trade Show Preparation 3 10 days 100% Tue 1/17/17 Mon 1/30/17
2192 6.3.3.1.4 Workshop/Conference/Trade Show Preparation 4 10 days 100% Mon 3/20/17 Fri 3/31/17
2193 6.3.3.1.5 Workshop/Conference/Trade Show Preparation 5 10 days 100% Mon 5/22/17 Fri 6/2/17
2194 6.3.3.1.6 Workshop/Conference/Trade Show Preparation 6 10 days 100% Mon 7/17/17 Fri 7/28/17
2195 6.3.3.1.7 Workshop/Conference/Trade Show Preparation 7 10 days 100% Mon 9/18/17 Fri 9/29/17
2196 6.3.3.1.8 Workshop/Conference/Trade Show Preparation 8 10 days 100% Mon 11/20/17 Fri 12/1/17
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q2016 2017 2018 2019 2020 2021
Smart City ScheduleCooperative Agreement No. DTFH6116H00013
Smart Columbus Project - All Activities
file: SCC‐A‐SmartColumbus Program Schedule_revised_v8.mpp Page: 55/58 Printed on: Mon 1/28/19 @ 1:59 PM
ID Outline Number
Task Name Duration %Complete
Start Finish Predecessors
2197 6.3.3.1.9 Workshop/Conference/Trade Show Preparation 9 10 days 100% Mon 1/22/18 Fri 2/2/18
2198 6.3.3.1.10 Workshop/Conference/Trade Show Preparation 10 10 days 100% Mon 3/19/18 Fri 3/30/18
2199 6.3.3.1.11 Workshop/Conference/Trade Show Preparation 11 10 days 100% Mon 5/21/18 Mon 6/4/18
2200 6.3.3.1.12 Workshop/Conference/Trade Show Preparation 12 10 days 100% Mon 7/16/18 Fri 7/27/18
2201 6.3.3.1.13 Workshop/Conference/Trade Show Preparation 13 10 days 100% Mon 9/17/18 Fri 9/28/18
2202 6.3.3.1.14 Workshop/Conference/Trade Show Preparation 14 10 days 0% Mon 11/19/18 Tue 12/4/18
2203 6.3.3.1.15 Workshop/Conference/Trade Show Preparation 15 10 days 0% Tue 1/22/19 Mon 2/4/19
2204 6.3.3.1.16 Workshop/Conference/Trade Show Preparation 16 10 days 0% Mon 3/18/19 Fri 3/29/19
2205 6.3.3.1.17 Workshop/Conference/Trade Show Preparation 17 10 days 0% Mon 5/20/19 Mon 6/3/19
2206 6.3.3.1.18 Workshop/Conference/Trade Show Preparation 18 10 days 0% Mon 7/22/19 Fri 8/2/19
2207 6.3.3.1.19 Workshop/Conference/Trade Show Preparation 19 10 days 0% Mon 9/16/19 Fri 9/27/19
2208 6.3.3.1.20 Workshop/Conference/Trade Show Preparation 20 10 days 0% Mon 11/18/19 Tue 12/3/19
2209 6.3.3.1.21 Workshop/Conference/Trade Show Preparation 21 10 days 0% Tue 1/21/20 Mon 2/3/20
2210 6.3.3.1.22 Workshop/Conference/Trade Show Preparation 22 10 days 0% Mon 3/16/20 Fri 3/27/20
2211 6.3.3.1.23 Workshop/Conference/Trade Show Preparation 23 10 days 0% Mon 5/18/20 Mon 6/1/20
2212 6.3.3.1.24 Workshop/Conference/Trade Show Preparation 24 10 days 0% Mon 7/20/20 Fri 7/31/20
2213 6.3.3.2 Workshop/Conference/Trade Show Attendance 977 days 54% Mon 9/19/16 Thu 7/23/20
2214 6.3.3.2.1 Workshop/Conference/Trade Show Attendance 1 4 days 100% Mon 9/19/16 Thu 9/22/16
2215 6.3.3.2.2 Workshop/Conference/Trade Show Attendance 2 4 days 100% Mon 11/21/16 Thu 11/24/16
2216 6.3.3.2.3 Workshop/Conference/Trade Show Attendance 3 4 days 100% Tue 1/17/17 Fri 1/20/17
2217 6.3.3.2.4 Workshop/Conference/Trade Show Attendance 4 4 days 100% Mon 3/20/17 Thu 3/23/17
2218 6.3.3.2.5 Workshop/Conference/Trade Show Attendance 5 4 days 100% Mon 5/22/17 Thu 5/25/17
2219 6.3.3.2.6 Workshop/Conference/Trade Show Attendance 6 4 days 100% Mon 7/17/17 Thu 7/20/17
2220 6.3.3.2.7 Workshop/Conference/Trade Show Attendance 7 4 days 100% Mon 9/18/17 Thu 9/21/17
2221 6.3.3.2.8 Workshop/Conference/Trade Show Attendance 8 4 days 100% Mon 11/20/17 Thu 11/23/17
2222 6.3.3.2.9 Workshop/Conference/Trade Show Attendance 9 4 days 100% Mon 1/22/18 Thu 1/25/18
2223 6.3.3.2.10 Workshop/Conference/Trade Show Attendance 10 4 days 100% Mon 3/19/18 Thu 3/22/18
2224 6.3.3.2.11 Workshop/Conference/Trade Show Attendance 11 4 days 100% Tue 6/19/18 Fri 6/22/18
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q2016 2017 2018 2019 2020 2021
Smart City ScheduleCooperative Agreement No. DTFH6116H00013
Smart Columbus Project - All Activities
file: SCC‐A‐SmartColumbus Program Schedule_revised_v8.mpp Page: 56/58 Printed on: Mon 1/28/19 @ 1:59 PM
ID Outline Number
Task Name Duration %Complete
Start Finish Predecessors
2225 6.3.3.2.12 Workshop/Conference/Trade Show Attendance 12 4 days 100% Mon 7/16/18 Thu 7/19/18
2226 6.3.3.2.13 Workshop/Conference/Trade Show Attendance 13 4 days 100% Mon 9/17/18 Thu 9/20/18
2227 6.3.3.2.14 Workshop/Conference/Trade Show Attendance 14 4 days 0% Mon 11/19/18 Mon 11/26/18
2228 6.3.3.2.15 Workshop/Conference/Trade Show Attendance 15 4 days 0% Tue 1/22/19 Fri 1/25/19
2229 6.3.3.2.16 Workshop/Conference/Trade Show Attendance 16 4 days 0% Mon 3/18/19 Thu 3/21/19
2230 6.3.3.2.17 Workshop/Conference/Trade Show Attendance 17 4 days 0% Mon 5/20/19 Thu 5/23/19
2231 6.3.3.2.18 Workshop/Conference/Trade Show Attendance 18 4 days 0% Mon 7/22/19 Thu 7/25/19
2232 6.3.3.2.19 Workshop/Conference/Trade Show Attendance 19 4 days 0% Mon 9/16/19 Thu 9/19/19
2233 6.3.3.2.20 Workshop/Conference/Trade Show Attendance 20 4 days 0% Mon 11/18/19 Thu 11/21/19
2234 6.3.3.2.21 Workshop/Conference/Trade Show Attendance 21 4 days 0% Tue 1/21/20 Fri 1/24/20
2235 6.3.3.2.22 Workshop/Conference/Trade Show Attendance 22 4 days 0% Mon 3/16/20 Thu 3/19/20
2236 6.3.3.2.23 Workshop/Conference/Trade Show Attendance 23 4 days 0% Mon 5/18/20 Thu 5/21/20
2237 6.3.3.2.24 Workshop/Conference/Trade Show Attendance 24 4 days 0% Mon 7/20/20 Thu 7/23/20
2238 6.3.4 USDOT organized webinars (4/yr.) 396 days 100% Mon 10/3/16 Mon 4/9/18
2239 6.3.4.1 Webinar Preparation 392 days 100% Mon 10/3/16 Fri 4/6/18
2240 6.3.4.1.1 Webinar Preparation 1 5 days 100% Mon 10/3/16 Fri 10/7/16
2241 6.3.4.1.2 Webinar Preparation 2 5 days 100% Tue 1/3/17 Mon 1/9/17 2240,2248
2242 6.3.4.1.3 Webinar Preparation 3 5 days 100% Mon 4/3/17 Fri 4/7/17 2241,2249
2243 6.3.4.1.4 Webinar Preparation 4 5 days 100% Mon 7/3/17 Fri 7/7/17 2242,2250
2244 6.3.4.1.5 Webinar Preparation 5 5 days 100% Mon 10/2/17 Fri 10/6/17 2243,2251
2245 6.3.4.1.6 Webinar Preparation 6 5 days 100% Mon 1/1/18 Fri 1/5/18 2244,2252
2246 6.3.4.1.7 Webinar Preparation 7 5 days 100% Mon 4/2/18 Fri 4/6/18 2245,2253
2247 6.3.4.2 Webinar Participation 387 days 100% Tue 10/11/16 Mon 4/9/18
2248 6.3.4.2.1 Webinar Participation 1 1 day 100% Tue 10/11/16 Tue 10/11/16 2240
2249 6.3.4.2.2 Webinar Participation 2 1 day 100% Tue 1/10/17 Tue 1/10/17 2241
2250 6.3.4.2.3 Webinar Participation 3 1 day 100% Mon 4/10/17 Mon 4/10/17 2242
2251 6.3.4.2.4 Webinar Participation 4 1 day 100% Tue 7/11/17 Tue 7/11/17 2243
2252 6.3.4.2.5 Webinar Participation 5 1 day 100% Mon 10/9/17 Mon 10/9/17 2244
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q2016 2017 2018 2019 2020 2021
Smart City ScheduleCooperative Agreement No. DTFH6116H00013
Smart Columbus Project - All Activities
file: SCC‐A‐SmartColumbus Program Schedule_revised_v8.mpp Page: 57/58 Printed on: Mon 1/28/19 @ 1:59 PM
ID Outline Number
Task Name Duration %Complete
Start Finish Predecessors
2253 6.3.4.2.6 Webinar Participation 6 1 day 100% Mon 1/8/18 Mon 1/8/18 2245
2254 6.3.4.2.7 Webinar Participation 7 1 day 100% Mon 4/9/18 Mon 4/9/18 2246
2255 6.4 International Collaboration 287 days 100% Wed 2/1/17 Thu 3/8/18
2256 6.4.1 Prepare for International Meetings 265 days 100% Wed 2/1/17 Thu 2/8/18
2257 6.4.1.1 Prepare for International Meetings 1 6 days 100% Wed 2/1/17 Wed 2/8/17
2258 6.4.1.2 Prepare for International Meetings 2 6 days 100% Thu 2/1/18 Thu 2/8/18 2257,2263
2259 6.4.2 Attend International Meetings 263 days 100% Wed 2/15/17 Wed 2/21/18
2260 6.4.2.1 Attend International Meetings 1 5 days 100% Wed 2/15/17 Tue 2/21/17 2257
2261 6.4.2.2 Attend International Meetings 2 5 days 100% Thu 2/15/18 Wed 2/21/18 2258
2262 6.4.3 International Meeting Debrief 264 days 100% Wed 3/1/17 Thu 3/8/18
2263 6.4.3.1 International Meeting Debrief 1 6 days 100% Wed 3/1/17 Wed 3/8/17 2260
2264 6.4.3.2 International Meeting Debrief 2 6 days 100% Thu 3/1/18 Thu 3/8/18 2261
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q2016 2017 2018 2019 2020 2021
Smart City ScheduleCooperative Agreement No. DTFH6116H00013
Smart Columbus Project - All Activities
file: SCC‐A‐SmartColumbus Program Schedule_revised_v8.mpp Page: 58/58 Printed on: Mon 1/28/19 @ 1:59 PM
Smart City Challenge Demonstration Quarterly Report: 2018 4th Quarter (October 2018 – December 2018) 33
Risk Status
A summary of risks identified
The Risk log currently has 29 risks identified to varying threats to the project with three sections.
The Risk Identification section contains risk identification by categories, individual project, and
description. The Qualitative Baseline Assessment weights the risk with the probability of
occurrence, impacts to the schedule and costs, and a ranking calculated from it. Monitoring &
Control has the status and associated notes.
Risk Log
Project Risk Register
Retired Active TotalLow priority: 0-19 11 19 30
Medium priority: 20-29 7 8 15High priority: 30+ 4 2 6
Total 22 29 51
No. Name Risk Group Category Project Phase
Type Description (Cause, Effect) Risk Trigger Engage
USDOTProbability of Occurrence
Impact to Cost
Impact to Schedule
On or near CP?
Rank Status Status Notes as of 12/30/18
1 Multi-Modal Trip Planning is limited to a couple services Technical Enhanced Human
Services 3 - MMTPA/CPS Design
Thre
at If at the time of deployment, COTA is the only confirmed provider. Will limit user access to services.
Confirmation of MMTPA service providers. Yes Moderate Low Low No 12
Activ
e
ADW | We have 5 providers that are ready to be a part of the system. We will continue to have discussions with additional proviers to educate them.
2 Limited FMLM providers engaged Technical Enhanced Human Services
4 - Smart Mobility Hubs Design
Thre
at If at the time of deployment, we have not confirmed FMLM service providers we will not improve existing conditions.
Submittal of demonstration site map and installation schedule
Yes Moderate Low Low No 12
Activ
e ADW | Yellow Cab, Zipcar, CoGo, and Lyft are very interested to provide services at Mobility Hubs.
3 Cannot Recruit 3000 Aftermarket Safety Device (ASD) Participants Technical Enabling
Technologies 2 - CVE Requirements
Thre
at
At conclusion of installation, less than 3000 units have been installed. Reduces amount of data collected and extends schedule
Number of signed up interested participants by the time installation begins
Yes Very Low Low Moderate No 5
Ret
ired
RJB | 1500-1800 total participants are needed with simplified scope. No longer applicable. Additional outreach will need to be coordinated with Communications Team for Q3 of 2018.
4 Media driven scope creep Organizational Outreach All All Phases
Thre
at
Media mis-interprets or misrepresents the message/real scope of the project. Creates expectation to include more scope in the project.
Media event Yes High Low Low No 16
Activ
e ANC | Coordination of all media events will be through the Communications Team to the media and thru partners to the media.
5 Media driven negative perception of project Organizational Outreach All All Phases
Thre
at
Media mis-interprets or misrepresents the scope of the project. Creates negative response and lack of participation/support by the users/public.
Media event Yes Moderate Moderate Moderate No 18
Activ
e ANC | Coordination of all media events will be through the Communications Team to the media and thru partners to the media.
6 RFID Parking Permit "system" cannot be integrated into CoC System Technical Downtown 11-Enhanced
Permit Parking Design
Thre
at
During development of requirements workshop, we identify the system is incompatible . Parking improvements/benefits not realized.
During the system requirements development phase
Yes Moderate Moderate Moderate Yes 18
Ret
ired
RJB | Project removed from program.
7 Parking permit technology Technical Downtown 11-Enhanced Permit Parking Concept
Thre
at City preference identified in ConOps approach versus technology solution specified in the application (RFID).
Technology decision during SE process Yes High Moderate Moderate No 24
Ret
ired
RJB | Project removed from program.
8 Delivery zone availability application development Usability Downtown 10-Delivery Zone
Availability Deployment
Thre
at Development of end user application not in the scope, but identified as a user need Deployment phase Yes High High Moderate Yes 28
Ret
ired RJB | INRIX is providing the
application, risk is retired. Project removed from program.
9 City not able to use designated partner Technical All All Deployment
Thre
at
City is unable to accept partner offerings. Decision on partner agreement Yes High High Moderate Yes 28
Ret
ired
MKB | City not able to use NXP. Budget increased. Risk retired.
10Wi-Fi coverage not sufficient to
improve access to educational/employment resources
Technical Enabling Technologies
2-Smart Street Lighting Design
Thre
at
During field testing, system does not meet service expectations. Access to educational/employments services not realized
SDD Yes High Moderate Low No 20
Ret
ired RJB | Not a performance measure,
risk is retired. Project removed from program.
11 Development required for OBUs & RSUs to meet requirements. Technical Enabling
Technologies All Procurement
Thre
at Off-the-shelf OBUs & RSUs do not meet requirements. Delay deployment/change in scope.
During vendor pre-qual/assessment process Yes Moderate Moderate High Yes 21
Activ
e RJB | Coordination with the CV Pilots and outreach to OBU / RSU manufacturers need to stay active throughout the life of the project.
12 CV product does not meet technical specifications. Technical Enabling
Technologies All Deployment
Thre
at Off-the-shelf application does not meet specifications. Delay deployment/change in scope.
During lab testing Yes Moderate Low High Yes 18
Activ
e
RJB | Low risk due to simplified scope. Coordination with the CV Pilots and outreach to OBU / RSU manufacturers need to stay active throughout the life of the project.
13 Development required for off-the-shelf applications to meet requirements. Technical All All Procurement
Thre
at Off-the-shelf applications do not meet requirements. Delay deployment/change in scope.
During the RFQs / Procurement process Yes High High High Yes 32
Activ
e
JMB | 1) Understand the must have requirements for each solution and convey the same clearly in RFI/RFP 2) Understand what is not off the shelf by starting procurement with an RFI to determine effort for customziation work, 3) Manage software development using Agile approach to ensure 'fail fast', thin slice delivery to enable quick pivots if needed for optimized delivery.
Risk Identification Qualitative Baseline Assessment Monitoring & Control
Page 1 of 4 1/29/2019
Project Risk Register
Retired Active TotalLow priority: 0-19 11 19 30
Medium priority: 20-29 7 8 15High priority: 30+ 4 2 6
Total 22 29 51
No. Name Risk Group Category Project Phase
Type Description (Cause, Effect) Risk Trigger Engage
USDOTProbability of Occurrence
Impact to Cost
Impact to Schedule
On or near CP?
Rank Status Status Notes as of 12/30/18
Risk Identification Qualitative Baseline Assessment Monitoring & Control
14 USDOT funding priorities Schedule All All Concept
Thre
at After Administration change, funding is interrupted/ cancelled. If interrupted - delay in schedule/stop work order.
Policy change in USDOT. Yes Low Moderate Low No 10
Ret
ired
MKB | Funding is not interrupted.
15 Unforeseen procurement process duration with City Schedule All All Procurement
Thre
at Unable to shorten typical procurement process. Delayed schedule.
During the RFQs / Procurement process Yes Moderate Low High Yes 18
Activ
e
JMB | We know the city procurement cycle is 80 days. Plan for this in the project and be out in front of the process as much as possible - getting as much pre-work done as possible to reduce cycle time. Run parallel efforts wherever possible for efficiency.
16 Unforeseen procurement process duration with partners Schedule All All Procurement
Thre
at Unexpected change in partner delivery date. Delayed schedule.
When installation is scheduled to begin Yes High Low High Yes 24
Ret
ired
MKB | Procurement factored into schedule.
17 Timeframe to Install on AEP Assets Schedule Enabling Technologies 2 - CVE Deployment
Thre
at Do not have authorization to attach to AEP poles. Delayed Schedule
During deployment phase Yes High Low High Yes 24
Activ
e RJB | Early evaluation of corridors exist that do not have communication infrastructure.
18 Equipment attachment point on poles not high enough and limits coverage Technical Enabling
Technologies 2 - CVE Deployment
Thre
at Existing infrastructure cannot support additional equipment at the required height. Delayed schedule/increase cost
During deployment phase Yes Moderate Low High No 18
Activ
e RJB | Field meetings occurred for development of the Installation Plans to identify locations and height.
19 Lack of "Mobility Assistance" resources Technical Enhanced Human
Services5 - Mobility Assistance Deployment
Thre
at
Limited ability to fully test the Mobility Assistance application and application does not provide benefit to people with Cognitive Disabilities.
During field testing Yes High Low Low No 16
Ret
ired ADW | Two applications have been
tested with OSU faculty and COTA staff. Risk is mitigated.
20 Sensitive PII becomes compromised Technical OS 1 - OS Deployment
Thre
at Data privacy safeguard policies are circumvented and personally identifiable information (PII) is compromised
During deployment phase Yes Low Moderate High Yes 14
Activ
e
JMB | We will aggregage and anonymize PII information at the edge before accepting into OS. There will be algorithms written to serve as a check and balance filter to monitor for any ingestion of PII information. If PII is identified during ingestion, the data publisher will be notified and the data will not be published to the OS.
21 Legislation for the deployment of the planned autonomous shuttles Legislative Emerging
Technologies 8 - CEAV Deployment
Thre
at Legislation will likely be required for the deployment of AV on City streets
Appropriate legislation not in place prior to deployment commencing
Yes High High High Yes 32
Ret
ired
ADW | Governor's office issed an exutive order allowing AV testing.
22 Significantly more stakeholders to coordinate with than anticipated Schedule All All Concept
Thre
at
Due to the enthusiasm and interest in the Smart Columbus Program, there have been many more players to coordinate with to allow appropriate time to listen and respond to user needs.
Concept of Operation development Yes High Moderate Moderate Yes 24
Ret
ired
MKB | Risk not realized
23 Legislation for truck platooning on public streets Legislative Emerging
Technologies9 - Truck
Platooning Deployment
Thre
at Legislation may be desired for truck platooning on highways (see note). Deployment phase yes Moderate Low High Yes 18
Ret
ired
ADW | The truck platooning project is being removed from the portfolio.
24Partners: SPARC, local partner in the City’s grant application, delayed their
ground breaking developmentSchedule Emerging
Technologies 8 - CEAV Deployment
Thre
at
SPARC, a committed local partner in the City’s grant application, has not yet broken ground on their development, which is the City’s proposed primary site for vehicle testing prior to deployment.
During deployment phase Yes High Moderate Low No 20
Ret
ired
MKB | The SPARC facility will not be available in time for us to use it for testing. The city is in conversations with TRC to determine if testing can occur there.
25 COTA Mobility Assistance Call Center Support Liability Organizational Enhanced Human
Services5 - Mobility Assistance Concept
Thre
at
COTA is not able to provide call center support, as it creates a "special duty" that may result in COTA being held liable for negligence related to mobility app user care.
Upon COTA legal team making a decision. Yes High Low Low No 16
Ret
ired ADW | Support center is not
supported by COTA, caregiver approach is provided by both applications. Risk is retired.
26Projects not deployed in time to
collect 12 months of performance data.
Schedule All All Deployment
Thre
at Project delays result in projects not be operational for 12 months during the 4-year grant period.
Schedule indicates projects will not be completed by the end of the grant's 3rd year.
Yes Moderate Low High Yes 18
Ret
ired MKB | Grant period may be
extended, so risk retired.
27 Delayed agreement with TRC to test vehicles Schedule Emerging
Technologies 8 - CEAV Deployment
Thre
at With SPARC unavailable, we need to establish an agreement with TRC to test vehicles.
During deployment phase Yes Moderate Moderate High No 21
Activ
e MKB | Talks with TRC are ongoing. Risk downgraded.
28 Delayed definition of partner scope Schedule All All Procurement
Thre
at Unexpected/ late change in partner scope definition/ contribution. Increased costs and delayed schedule.
Notification of scope of change Yes Low Moderate Low Yes 10
Ret
ired MKB | Risk not realized
Page 2 of 4 1/29/2019
Project Risk Register
Retired Active TotalLow priority: 0-19 11 19 30
Medium priority: 20-29 7 8 15High priority: 30+ 4 2 6
Total 22 29 51
No. Name Risk Group Category Project Phase
Type Description (Cause, Effect) Risk Trigger Engage
USDOTProbability of Occurrence
Impact to Cost
Impact to Schedule
On or near CP?
Rank Status Status Notes as of 12/30/18
Risk Identification Qualitative Baseline Assessment Monitoring & Control
29 Common Payment System has limited partners Technical Enhanced Human
Services 3 - MMTPA/CPS Design
Thre
at May not be able to integrate with several back office pay distribution systems.
Confirmation of CPS service providers Yes High High Moderate No 28
Activ
e ADW |Conversations with TSPs continue. National TNCs like Uber and Lyft remain the biggest challenge.
30 CV Interoperability Technical Enabling Technologies 2 - CVE Procurement
Thre
at CV vendor provides proprietary solution that is not interoperable with other vendor's products based on the latest standards
Deployment phase Yes Moderate Moderate Moderate No 18
Activ
e RJB | Appropriate procurement must be established/draft to endure CV equipment will be interoperable.
31 DSRC Onboard Equipment (OBE) Cost Enabling Technologies 2 - CVE Requirements
Thre
at
DSRC OBE vendor not willing to develop all proposed CV applications as identified by the City as part of their standard OBE pricing.
Partner agreement Yes Low High High Yes 16
Activ
e
RJB | Mitigation Strategy: With scope simplification, removed low TRL applications from consideration. May contract with vendor/3rd party to develop these applications.
32 Adding DSRC RSUs to the planned management tool Technical Enabling
Technologies 2 - CVE Deployment
Thre
at DSRC Roadside Units (RSUs) may not easily be added to the planned RSU Management tool.
Deployment phase Yes Moderate Moderate Moderate No 18
Activ
e
RJB | Mitigation Strategy: work with RSU management toll vendor to identify early in requirements phase the necessary functions that need to be included in any RSU vendor product offering.
33 Need for multiple OBE vendors Technical Enabling Technologies 2 - CVE Requirements
Thre
at Multiple OBE Vendors may be necessary to support multiple vehicle types planned for SmartColumbus deployment.
Results of requirements work Yes Moderate Moderate Moderate No 18
Activ
e RJB | Contact OBE vendors prior to procurement period to determine feasibility of meeting these requirements.
34Technology can't support proposed
CEAV routes in mixed traffic environment.
Usability Emerging Technologies 8 - CEAV Procurement
Thre
at Technology is not advanced enough for vendors to commit to supporting the proposed CEAV routes in the Easton area.
No RFP responses Yes Low Moderate High Yes 14
Activ
e ADW | Issued an RFI to vendors to assist in selecting a proposed route. Vendor input helped the city identify a feasible route.
35 Vendor unable to integrate CV into navigation system Technical Emerging
Technologies 8 - CEAV Procurement
Thre
at Vendor is unable/unwilling to integrate CV technology into the vehicle's navigation services.
Deployment phase Yes Low Low Low No 8
Activ
e
RJB | Revise City concept to de-scope or eliminate the active CV elements of the EAV. EAVs are still expected to include an aftermarket safety device for generation of outbound BSMs by the EAV.
36 Additional snow removal required along CEAV routes Cost Emerging
Technologies 8 - CEAV O&M
Thre
at
More frequent/aggressive snow removal by local maintenance crews needed once CEAV is deployed for it to operate properly.
Deployment phase Yes Moderate Low Low No 12
Activ
e
ADW | Local maintenance personnel increase frequency and/or revise method for snow removal to avoid impacting operations of CEAV by creating previously unknown obstacle (snow pile) along the route.
37 Operation and Maintenance of CEAV Contractual Emerging Technologies 8 - CEAV O&M
Thre
at Need to develop plan for O&M during pilot project with ODOT, OSU, Partnership, and COTA.
Requirements and specifications phase Yes Moderate Very High Very High No 30
Activ
e
ADW | The vendor must identify storage and charging facilities per the RFP. From the RFI responses, vendors are willing to do this; however, this is a risk to the project.
38
Finalize outreach information for COTA, Columbus (Public Safety and
Public Service), and other key stakeholders
Organizational Enabling Technologies 2 - CVE Concept
Thre
at Public Safety is not in agreement with applications for deployment. Deployment phase Yes Moderate Moderate Low No 15
Activ
e
RJB | Information was distributed to Public Safety to review with the applications and proposed number of vehicles. Meetings with Fleet for other department vehicles is ongoing.
39Developing business/cost model to
sustain the project after the life of the grant
Cost Enhanced Human Services 3 - MMTPA/CPS Concept
Thre
at Develop business/cost model to sustain the project after the life of the grant Deployment phase Yes Moderate High High No 24
Activ
e ADW | MMTPA has low ongoing costs after the grant, which makes it sustainable. The CPS proposals do offer ways to generate revenue.
40Unknown time and resources needed
to reach agreements and integrate with TSP and existing systems
Cost Enhanced Human Services 3 - MMTPA/CPS Concept
Thre
at
Project costs - unknown time and resources needed to reach agreements and integrate with TSPs and existing systems.
RFP Yes Moderate High High No 24
Activ
e ADW | Developing agreements and beginning negotiations to allow for adequate time.
41Variable costs for software
development due to emerging technologies
Cost Enhanced Human Services 3 - MMTPA/CPS Requirements
Thre
at Variable costs for software development due to emerging technologies. RFP Yes Moderate Moderate Moderate No 18
Activ
e ADW | MMTPA cost is within the budget. CPS proposals are within or above the estimated budget.
Page 3 of 4 1/29/2019
Project Risk Register
Retired Active TotalLow priority: 0-19 11 19 30
Medium priority: 20-29 7 8 15High priority: 30+ 4 2 6
Total 22 29 51
No. Name Risk Group Category Project Phase
Type Description (Cause, Effect) Risk Trigger Engage
USDOTProbability of Occurrence
Impact to Cost
Impact to Schedule
On or near CP?
Rank Status Status Notes as of 12/30/18
Risk Identification Qualitative Baseline Assessment Monitoring & Control
42 Obtaining ROW/Easements/Agreements Technical Enhanced Human
Services4 - Smart Mobility
Hubs Design
Thre
at
Obtaining ROW/Easements/Agreements Design Yes Low Moderate High Yes 14
Activ
e ADW | Met with City Real Estate department. Initial process would only require agreements.
43 AbleLink agreement Contractual Enhanced Human Services
5 - Mobility Assistance Concept
Thre
at
AbleLink does not agree to contract terms Contract negotiation Yes Low Very High High Yes 18
Ret
ired
ADW | AbleLink is under contract.
44 Need IRB approval for participant recruitment plan Usability Enhanced Human
Services5 - Mobility Assistance Deployment
Thre
at Institutional Review Board must approve participate recruitment and training. Training Yes Low Low High Yes 12
Activ
e ADW | Part 1 of the IRB has been approved by the OSU IRB. Part 2 will be submitted in February.
45 Finalize agreement with OSU Contractual Enhanced Human Services
5 - Mobility Assistance Concept
Thre
at
Finalize agreement with OSU Design Yes Low Moderate Moderate No 12
Ret
ired
ADW | OSU agreement is signed.
46OSU faculty obtaining funding for
technical assistance during planning, testing, and deployment
Cost Enhanced Human Services
5 - Mobility Assistance Requirements
Thre
at OSU faculty obtaining funding for technical assistance during planning, testing, and deployment
Testing Yes Low Moderate High Yes 14
Ret
ired
ADW | OSU has a process of obtaining funding for faculty.
47Develop procurement process for
technology vendor that the Managed Care Plans can all agree to.
Usability Enhanced Human Services
6 - Prenatal Trip Assistance Procurement
Thre
at Develop procurement process for technology vendor that the Managed Care Plans can all agree to.
RFP Yes Moderate Moderate High Yes 21
Activ
e ADW | City has reached agreements with the MCOs. MCOs are negotiating with Kaizen Health.
48 Accelerate schedule Schedule Enhanced Human Services
6 - Prenatal Trip Assistance Concept
Thre
at
Inability to accelerate the schedule RFP Yes High Moderate Very High Yes 32
Ret
ired
ADW | City was able to accelerate the procurement process.
49 Peloton agreement Contractual Emerging Technologies
9 - Truck Platooning Concept
Thre
at Peloton does not want to participate in a 12 month deployment. Design Yes Very High High High No 40
Ret
ired ADW | Peloton does not want to
participate. Team will begin discussions with OEMs to determine interest in participating in a pilot.
50 Truck Platooning Project Technical Emerging Technologies
9 - Truck Platooning Concept
Thre
at
The technology is not advanced enough to deploy in a live environment. Vendors/OEMs are not will to share data from a deployment.
RFI Yes High High High Yes 32
Ret
ired
ADW | The project is being removed from the program
51 Participant Incentives for MMTPA, MAPCD, CVE, PTA Cost All All Deployment
Thre
at Projects will need to secure funds for monetary and non-monetary incentives to pilot participants.
Deployment phase No Moderate High High Yes 24
Activ
e ADW | Need to compile list of all incentive asks and provide to leadership.
Page 4 of 4 1/29/2019
Smart City Challenge Demonstration Quarterly Report: 2018 4th Quarter (October 2018 – December 2018) 34
Issues/Concerns/ Other See note in the risk section.