dpwh strategic infrastructure policies and programs
DESCRIPTION
DPWH Strategic Infrastructure Policies and Programs, Arangkada Forum 2014: More Reforms=More Jobs!TRANSCRIPT
The Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
DPWH STRATEGIC INFRASTRUCTURE DPWH STRATEGIC INFRASTRUCTURE POLICIES AND PROGRAMSPOLICIES AND PROGRAMS
1
3rd Anniversary Forum of Arangkada Philippines “More Reforms=More Jobs”Rizal Ballroom, Makati Shangri-La Hotel
26 February 2014
Secretary ROGELIO L. SINGSON
Condition of Philippine Road Network:Condition of Philippine Road Network:
Based on 2013 Road Condition DataBased on 2013 Road Condition Data
Legend
Road Classification
National Arterial
National Secondary
300,000 sq. km Total Land Area
215,717 kms Total Overall Road Network
32,227 kms Total National Road Length
0.72 km/sq. km Road Density
0.20 km/sq. km Paved Road Density
0.27 Overall Paved Road Ratio
0.83 Paved Road Ratio for Nat’l. Roads
2
DPWH Strategic Policies and Programs:DPWH Strategic Policies and Programs:
3
Good Governance and Anti-Corruption Program
Better Quality and Safer National Roads and Bridges Program
Effective Flood Control Program
Strategic Convergence Program
Public-Private Partnership Program
Resiliency Program
The Global Competitiveness Report: by World Economic Forum
4
QUALITY OF ROADS
2010-2014
Ranking of the Philippines significantly improved from no. 114 (2010-2011) to no. 87 (2013-2014)
Legend: 1 = extremely underdeveloped; 7 = extensive and efficient by international standards (Based on 148 Countries)
5.7
5.7 5.
45.4 5.
1 5 5 4.9
3.5
3.5
3.4
3.7
2.7 2.
6
2.7
3.1 2.
8
3.1
3.4
3.6
5
FY 2011 vs. FY 2012 vs. FY 2013 Fund Utilization (FULL YEAR)
In Billion Pesos
DPWH Performance Report (2011 vs. 2012 vs. 2013):Continue to fine tune disbursement mechanisms to improve service delivery
Note: NCA-Notice of Cash Allocation; TRA-Tax Remittance Advice; FC-Forex Cash; FNC-Forex Non-Cash
In B
illio
n P
eso
s
As of February 13, 2014
6
2011-2014 DPWH Infrastructure Program:2011-2014 DPWH Infrastructure Program:Economic growth will receive a big push through increased infrastructure spending
Am
ou
nt
(In
Bill
ion
Pe
sos)
10%
45%
33%
7
Highways – 70%, P100.93 B *
DPWH FY 2014 Budget (based on GAA): DPWH FY 2014 Budget (based on GAA):
FY 2014 Budget (Capital Outlays-Projects)
(In Billion Pesos)
(P 33.62 B)
(P 128.22 B) *
(P 3.01 B)
(P 17.10 B)
(P 4.98 B)
(P 2.82 B)
(P 129.41 B)
TOTAL : P190.93 B
Distribution of FY 2014 Budget by Region:Distribution of FY 2014 Budget by Region:(Based on GAA-Capital Outlays, Projects)(Based on GAA-Capital Outlays, Projects)
8
CAR – P 6.87 B
Region I – P 6.36 B
Region II – P 6.67 B
Region III – P 11.94 B
NORTHERN LUZON-P31.84 B (21.1%)
Region XIII – P 5.77 B
Region X – P 11.02 B
Region IX – P 7.34 B
Region XI – P 7.89 B
Region XII – P 5.55 B
MINDANAO – P37.58 B (24.9%)
NCR – P 23.78 B (15.7%)
Region IV-A – P 12.60 B
Region IV-B – P 8.03 B
Region V – P 9.92 B
SOUTHERN LUZON-P30.56 B (20.2%)
Region VI – P 12.60 B
Region VII – P 7.91 B
VISAYAS – P27.42 B (18.1%)
Region VIII – P 6.91 B
TOTAL : P151.17 B* Excluding Inter-Regional/Nationwide-P39.76 B
FY 2011-FY 2014 Annual Infrastructure Program for Mindanao
In Php billion
Infrastructure Support Program for ARMM
In Php billionPhp37.58
Php27.59
Php19.96
Php13.99*
ARMM
Main
* Excludes the Php2.85 billion under the Transition Investment Support Program (TISP)-ARMM
Php0.62
Php1.21
Php2.10
Php2.34
Php2.51
TOTAL : Php8.78 **
** Total cost includes TISP-ARMM, SFD-MRIP and other projects funded from FY 2011 to FY 2013
Name of Project Cost Length Completion Date
Status
Basilan Circumferential Road Php1.567 50.60 km December 2014 On-going, 61%
Lake Lanao Circumferential Road Php0.767 29.88 km February 2015 On-going, 9%
Cotabato East Diversion Road, Phase I Php0.709 13.27 km May 2014 On-going, 45%
Infrastructure Support Program for MindanaoInfrastructure Support Program for MindanaoHelping unleash Mindanao’s growth potential by accelerating provision of better infrastructure facilities
9
TOTAL : Php99.12
Flood Control Program:Flood Control Program:
10
FY 2011 - FY 2014 Investment for Flood Control and Drainage Projects (based on GAA)
(In Billion Pesos)
Continuing investments in infrastructure for more Continuing investments in infrastructure for more jobs and sustained growth:jobs and sustained growth:
11
Institutionalizing Good Governance and Anti-Corruption Reforms
National Roads and Bridges Upgrading Program for Better Quality and Safer Roads
Convergence Program for better access to tourist destinations, regional and international airports, seaports and Roro ports; better Farm-to-Market Roads
Climate Change Adaptation Measures-Flood Control Program and Structural Resiliency Program
The Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
THANK YOU !!!
12