DR. SPANG INGENIEURGESELLSCHAFT FÜR BAUWESEN, GEOLOGIE UND UMWELTTECHNIK MBH DEVELOPER Deutsche Bahn AG, Dresden PROJECT Upgrade to Berlin-Dresden line, rebuilding with full closure Rebuilding with full closure of track section BD km 31.200 to 33.209 Rehabilitation of the Röderflutgraben and Röder railway crossing bridges, which have steel superstructures Poor track condition OUR SERVICES Investigation of structure condition and railway embankments Recording of the geotechnical conditions of the railway embankment and the embankment contact area Geotechnical inspection Investigation programme pursuant to DIN 4020 Expert report on contamination to establish procedures for dealing with existing ballast Subsoil expert report for seven overbridges along section 6248 DE

Upload: others

Post on 30-Jul-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: DR. SPANG · 2018-06-13 · DR. SPANG INGENIEURGESELLSCHAFT FÜR BAUWESEN, GEOLOGIE UND UMWELTTECHNIK MBH DEVELOPER Deutsche Bahn AG, Dresden PROJECT Upgrade to Berlin-Dresden line,

DR. SPANG

INGENIEURGESELLSCHAFT FÜR BAUWESEN, GEOLOGIE UND UMWELTTECHNIK MBH

DEVELOPER Deutsche Bahn AG, Dresden

PROJECT Upgrade to Berlin-Dresden line, rebuilding with full closure

Rebuilding with full closure of track section BD km 31.200

to 33.209

Rehabilitation of the Röderflutgraben and Röder railway

crossing bridges, which have steel superstructures

Poor track condition

OUR SERVICES

Investigation of structure condition and railway embankments

Recording of the geotechnical conditions of the railway

embankment and the embankment contact area

Geotechnical inspection

Investigation programme pursuant to DIN 4020

Expert report on contamination to establish procedures for

dealing with existing ballast

Subsoil expert report for seven overbridges along section