dudbc.gov.npdudbc.gov.np/uploads/default/files/fb9104575f9bdbb... · i table of contents acronyms
TRANSCRIPT
Environmental and Social
Management Framework
Nepal Urban Governance and Infrastructure Project
August 2020
i
TABLE OF CONTENTS
ACRONYMS ..................................................................................................................... iv
EXECUTIVE SUMMARY .................................................................................................. vi
1. INTRODUCTION ........................................................................................................... 1
1.1. Project background ............................................................................................................................ 1
1.2. Rationale and Objective of ESMF .................................................................................................... 2
2. ENVIRONMENTAL AND SOCIALREGULATIONS AND POLICY FRAMEWORK ........... 3
2.1. National and International Laws/Conventions .............................................................................. 3
2.2. International Conventions ............................................................................................................... 4
2.3. World Bank Safeguard Policies ....................................................................................................... 4
2.4. Comparison of GoN and World Bank Policies ................................................................................5
3. KEY ENVIRONMENTAL AND SOCIAL CONDITIONS IN THE CLUSTER
MUNICIPALITIES ............................................................................................................ 9
4. ENVIRONMENTAL AND SOCIAL MANAGEMENT FRAMEWORK (ESMF) ................ 10
4.1. Environment and Social Risk Management Procedure ................................................................ 10
4.1.1. Environmental and Social Screening .................................................................................... 10
4.1.2. Scoping ................................................................................................................................... 11
4.1.3. Project categorization ............................................................................................................ 12
4.1.4. Establishment of Baseline Condition ................................................................................... 12
4.1.5. Analysis of Alternative ........................................................................................................... 14
4.1.6. Impact Assessment ................................................................................................................ 14
4.1.7. Mitigation Measures for Identified Impacts and Guide to ESMP ...................................... 18
4.1.8. Stakeholder Consultation ...................................................................................................... 19
4.1.9. Preparation of ESIA/ESMP Report ...................................................................................... 19
4.1.10. Environmental Mitigation and Enhancement Management Plan ................................... 20
4.1.11. Approval and Implementation of Site-specific ESMP ....................................................... 23
4.1.12. Environmental and Social Monitoring of Management Plans ......................................... 23
4.1.13. Applicability of ESMF on Associated Projects .................................................................. 23
4.1.14. List of Ineligible Sub-Projects ............................................................................................ 23
4.1.15. LIPW subprojects ................................................................................................................ 23
4.1.16. Legal Contract for E&S Compliance .................................................................................. 24
4.1.17. Subproject Monitoring ........................................................................................................ 24
4.2. Specific labor and OH&S-related considerations in the context of COVID-19 .......................... 24
4.3. Considerations where CERC is activated ...................................................................................... 26
5. RESETTLEMENT POLICY FRAMEWORK (RPF) ........................................................ 27
5.1. Principles of RPF .............................................................................................................................27
5.2. Land & Asset Acquisition ................................................................................................................27
5.2.1. Involuntary Land Acquisition .............................................................................................. 28
5.2.2. Acquisition of Land through Negotiations ......................................................................... 29
5.2.3. Voluntary Land Donation .................................................................................................... 30
5.2.4. Loss of other Assets ............................................................................................................... 31
ii
5.3. Preparation of RAP ........................................................................................................................ 32
5.4. Entitlement Policy Matrix ............................................................................................................. 32
5.5. Monitoring and Reporting of RAP ................................................................................................ 39
5.6. Stakeholder Consultation and Grievance Redress ....................................................................... 39
6. VULNERABLE COMMUNITY DEVELOPMENT FRAMEWORK (VCDF) ...................... 40
6.1. Classification of Vulnerable Groups in Nepal ............................................................................... 40
6.2. Baseline of Vulnerable Groups in Nepal ........................................................................................ 41
6.3. Preparation of VCDP for the sub-projects .................................................................................... 42
6.4. Potential Impacts and Identification of Mitigation measures ..................................................... 43
6.5. Consultation and Information Disclosure .................................................................................... 45
6.6. Institutional Responsibilities ........................................................................................................ 46
6.7. Stakeholder Consultation and Grievance Redress ....................................................................... 46
7. SEA/SH RISK MITIGATION ACTION PLAN ................................................................ 47
7.1. Need and Purpose ........................................................................................................................... 47
7.2. Legal and policy environment for women’s safety ....................................................................... 47
7.3. Recommended Actions to Adddress SEA/SH Risks .................................................................... 48
8. STAKEHOLDER ENGAGEMENT AND CONSULTATION FRAMEWORK ..................... 51
8.1. Existing Stakeholder Engagement Process .................................................................................... 51
8.2. Stakeholder Mapping..................................................................................................................... 52
8.3. Mechanism for Consultation ......................................................................................................... 53
8.3.1. Subproject Identification Stage ........................................................................................... 53
8.3.2. Planning/Design Stage ........................................................................................................ 54
8.3.3. Implementation Stage ..........................................................................................................55
8.3.4. Post-construction Stage ........................................................................................................55
8.4. Information Disclosure...................................................................................................................55
8.5. Adapting stakeholder consultions to COVID-19 .......................................................................... 56
9. GRIEVANCE REDRESS MECHANISM ........................................................................ 58
9.1. Existing Grievance Redress Process .............................................................................................. 58
9.2. Establishing Grievance Redress Mechanism................................................................................ 58
9.3. Channels and procedures for receiving and addressing grievances............................................ 58
9.4. Functions of GRCs ......................................................................................................................... 59
9.5. Other Mechanism for Grievance Redress ..................................................................................... 60
9.6. GRM considerations for the COVID-19 context ........................................................................... 60
10. INSTITUTIONAL ARRANGEMENT FOR ESMP IMPLEMENTATION ........................ 61
10.1. Institutional Assessment for E&S Sections/Departments .......................................................... 61
10.1.1. Existing Institutional Capacity ............................................................................................ 61
10.1.2. Capacity Development ......................................................................................................... 61
10.2. Proposed Institutional Arrangement .......................................................................................... 62
ESMP Implementation Structure and Stakeholers Responsibility ................................................... 119
iii
List of Appendix
Appendix A: Land use map of 17 Municipalities .................................................................................................... 64
Appendix B: Consultation with municipalities ........................................................................................................ 72
Appendix C: Templates for Environmental & Social Screening Checklist / ......................................................... 110
Appendix D: Initial scoping for subprojects........................................................................................................ 113
Appendix E: Environmental & Social Mitigation Measures ................................................................................. 117
Appendix F: Contents of the Resettlement Action Plan ........................................................................................ 129
Appendix G: Assessment of Institutional Capacity ............................................................................................... 131
Appendix H: Summary Environmental and Social Conditions in the Cluster Municipalities ............................... 142
Appendix I: Summary Information on the Type of Baseline Indicators ................................................................ 150
Appendix J: List of Ineligible Sub-Projects ........................................................................................................... 158
Appendix K: COVID-19 considerations in construction/civil works projects ........................................................... 0
List of Figures
Figure 4-1:Flowchart for conducting ESIA ........................................................................................................... 10
Figure 6-1: Composition of Madhesi Caste Groups .............................................................................................. 42
Figure 8-1: Project identification Process through Stakeholder Engagement ........................................................ 52
Figure 9-1: Grievance Redress Process ................................................................................................................. 59
Figure 10-1: Coordination of Proposed Project Implementation Mechanism ....................................................... 63
List of Tables
Table 2-1List of National Policies, Rules, Laws, Regulations, Relevant to the Project .......................................... 3 Table 2-2 Listof International Conventions, Relevant to the Project ..................................................................... 4 Table3-1: Key Environmental and Social Issues in the Eastern and Western Cluster Municipalities ...................... 9 Table 4-1: Description of Social Baseline Information required for the Project ................................................... 12 Table 4-2: Anticipated Environmental and Social Impacts due to Development of Sub-projects ......................... 15 Table 4-3: Anticipated Social issues pertaining to the project ............................................................................. 17 Table 4-4.Template Environnemental Mitigation & Enchancement Management Plan ....................................... 20 Table 5-1: Entitlement Matrix applicable for the Project .................................................................................... 35 Table 6-1: Classification of Indigenous People on development ......................................................................... 41 Table 6-2: Population of Indigenous People in project specific districts ............................................................. 41 Table 6-3: Potential Impacts and Mitigation measures ...................................................................................... 43 Table 7-1.Recommended actions to address SEA/SH Risks ...................................................................... 48 Table 8-1: Stakeholder Mapping and Consultation ............................................................................................. 52 Table 10-1. Capacity Development Training Requirement ................................................................................. 62
iv
ACRONYMS
ADB Asian Development Bank
ARAP Abbreviated Resettlement Action Plan
CERC Contingency Emergency Response Component
CDO Chief District Officer
DCC District Coordination Committee
DFO District Forest Officer
DHM Department of Hydrology and Meteorology
DoE Department of Environment
DoR Department of Roads
DSC Design and Supervision Consultant
DUDBC Department of Urban Development & Building Construction
EA Environmental Assessment
EIA Environmental Impact Assessment
EMP Environmental Management Plan
EPR Environmental Protection Rules
ESMF Environment & Social Management Framework
ESMP Environment and Social Management Plan
FGD Focus Group Discussion
FUG Forest User Groups
GDP Gross Domestic Product
GESI Gender equality and social inclusion
GIS Geographic Information System
GoN Government of Nepal
GRM Grievance Redress Mechanism
IDA International Development Association
IEE Initial Environmental Examination
IP Indigenous Peoples
IUCN International Union for Conservation of Nature
JICA Japan International Cooperation Agency
LACP Land Acquisition and Compensation Plan
LIPW Labor-Intensive Public Works
LRUC Local Road Users Committee
MoFE Ministry of Forests and Environment
MoUD Ministry of Urban Development
NEFIN Nepal Federation of Indigenous Nationalities
NGO Non-Governmental Organizations
NUGIP Nepal Urban Governance and Infrastructure Project
NTFP Non-timber forest products
OH&S Occupational Health and Safety
OP Operational Policy
PAF Project Affected Family
PAH Project Affected Household
PAP Project Affected People
PCO Project Coordination Office
PIA Project Influence Area
PIU Project Implementation Unit
PIM Project Implementation Manual
v
PPE Personal Protective Equipment
RAP Resettlement Action Plan
RoW Right of Way
RPF Resettlement Policy Framework
SA Social Assessment
SEA/SH Sexual Exploitation and Abuse/Sexual Harassment
SECF Stakeholder Engagement & Consultation Framework
SHG Self Help Group
SIA Social Impact Assessment
SMO Social Mobilization Officer
SMP Social Management Plan
TOR Terms of Reference
UDGs Urban Development Grants
UDST Urban Development Support Teams
USD United States Dollar
VCDP Vulnerable Community Development Plan
VCDF Vulnerable Community Development Framework
VDC Village Development Committee
VGs Vulnerable Groups
WB World Bank
vi
EXECUTIVE SUMMARY
Nepal has recently transitioned from a unitary to federal government system, comprised of three tiers of
government with seven provinces and 753 local governments for which new legislation, institutions, and
administrative procedures are being formalized as constitutionally prescribed. To enable the federal
implementation process and to support municipalities in the efficient provision of assigned service delivery
responsibilities in the context of rapid urbanization, the proposed Nepal Urban Governance and Infrastructure
Project (NUGIP) to be implemented by the Ministry of Urban Development (MoUD) with support from the World
Bank aims to address two main challenges under the new federal context: (i) limited institutional systems and
capacities of municipalities; and (ii) critical gaps in core municipal services and infrastructure.
The development objective of NUGIP is to strengthen the institutional and fiscal capacities of participating
municipalities for strategic municipal infrastructure and service delivery. The proposed project comprises five
components:
Component 1: Urban Development Grants (UDGs)for strategic municipal infrastructure and service
delivery(International Development Association (IDA) allocation of US$ 115 million). This component will
provide UDG to participating municipalities for financing strategic municipal infrastructure sub-projects focusing
on, amongst others, rehabilitation and improvements in municipal roads, drainage, drinking water supply and
onsite sanitation, as well as associated design and implementation support.
Component 2 Institutional strengthening of participating municipalities(IDA financing: US$7 million). This
component will focus on strengthening institutional systems and capacities of participating municipalities for
improved urban management and service delivery.
Component 3: Support to municipalities for COVID-19 Recovery (Total financing: US$20 million). This
component provides support and relief to vulnerable groups in the target municipalities to help mitigate the short
and medium negative impact of the COVID 19 crisis through rapid labor-intensive public works (LIPW).
Component 4: Contingency Emergency Response (Total financing: US$0 million). The proposed project includes
a Contingent Emergency Response (CER) component to respond rapidly at the Government’s request in the event
of an eligible disaster, including climate-related events and pandemics.
Component 5: Project management and coordination (IDA financing: US$8 million). This component will provide
support to the MoUD for managing, coordinating and monitoring the implementation of the proposed Project, and
also for enhancing its federal policy and regulatory role for urban development.
NUGIP will support municipalities located in two strategic urban clusters: Eastern-Terai region (Provinces 1 and
2) and Western region (Provinces 4 and 5). The eastern region includes 9 municipalities of Itahari-
Mechinagarcorridor and the central region includes 8 municipalities of Pokhara economic corridors.17
municipalities were selected as recipients of resources for municipal infrastructure and service delivery
investments. Four additional municipalities in the Central-Hill cluster were included for the capacity building
program under Component 2. 12municipalitiesparticularly identified for this activity by the Government will
supported for COVID-19 response and recovery activities under Component 3.
The present Environmental and Social Management Framework (ESMF) has beenprepared to assist in the
screening, identification, and assessment of environmental and social risks applicable to the environmental and
social requirements of the Government of Nepal (GoN) and the World Bank during the sub-project design,
implementation and operation phases. It includes a Resettlement Policy Framework (RPF), a Vulnerable
Community Development Framework (VCDF), Sexual Abuse and Exploitation/Sexual Harassment (SEA/SH)
Risk Mitigation Action Plan, and a Stakeholder Engagement and Consultation Framework (SECF).The framework
provides guidanceon the procedures to be followed for mitigation of impacts, along with roles and responsibilities
of the implementing agencies. The ESMF presents detailed guidelines and formats for carrying out these
activities.
UnderNUGIP, the municipalities are responsible for identification of sub-projects, with the engagement of
citizens, preparation of sub-project description, “screening” and “analysis of alternatives”. Based on these and
other relevant documents, the Project Coordination Office (PCO) along with the municipality will assess the need
vii
for further environmental and social assessment (e.g., IEE/ ESIA). The schedules as per the Environment
Protection Rules will be the guiding document for categorizing the project and assessing the requirements for IEE/
EIA. The ESMF, which integrates Nepal’s laws and regulations on social and environmental safeguards, and the
Bank’s policies as well, shall be used to determine location specific issues for screening as well as defining scope
for the sub-project.
The major activities to be carried out for IEE and ESIA include: (i) Identification and selection of proposed sub-
projects and the sites based on results of screening and scoping; (ii) Establishment of baseline environmental &
social conditions; (iii) Assessment, prediction and evaluation of environment and social impacts; (iv) Analysis of
alternatives; (v) Identification of mitigation measures and preparation of ESMP;(vi) Public consultations and
information dissemination;(vii) Monitoring and preparation of Environmental and Social Monitoring reports; and
(viii) Institutional arrangements and capacity building
The resettlement activities envisaged under the project aims to assist, resettle and rehabilitate the affected persons
on account of the variousproject interventions in a manner that would improve or at the minimum, retain their
previous standard of living, earning capacity and production levels. Specifically, the Resettlement Policy
Framework (RPF) has been developed to guide detailed resettlement planning to address land acquisition and
resettlement impacts. This framework establishes the procedures for land acquisition and resettlement, the
compensation principles, organizational arrangements to be applied to meet the needs of the people who may be
affected by the project activities in terms of loss of land, shelter, assets or livelihoods, and/or loss of access to
economic resources. The RPF has been prepared in accordance with the national regulations as well as the
operational policies of the World Bank, especially OP/BP 4.12: Involuntary Resettlement.
The objective of the Vulnerable Community Development Framework (VCDF) is to guide the preparation of the
Vulnerable Community Development Plan (VCDP) for the sub-projects where there are vulnerable communities,
particularly indigenous people, present in and have collective attachment to the project area. The impact on
vulnerable communities and the need of a VCDP will be identified through a social screening process. If a VCDP
is deemed to be necessary, the plan will be prepared based on the findings of the Social Assessment and will also
involvefree, prior and informed consultation. Additionally, a Sexual Exploitation and Abuse/Sexual Harassment
(SEA/SH) Risk Mitigation Action Plan which provides guidance for addressing SEA/SH risks in sub-projects is
also provided in the ESMF.
A good communication strategy among the institution and community needs to be established to ensure that the
project is implemented in a sustainable manner. There are two key objectives of Stakeholder Engagement and
Consultation Framework (SECF). First, it is to keep all stakeholders informed of the project activities, the
potential beneficial and adverse impacts. Second, it is to ensure that stakeholders actively participate in all levels
of the project cycle, i.e., they are able to share and provide inputs in the preparation and implementation of project
activities, including safeguards management; engaged in implementation and monitoring activities, where
relevant; and are well-trained and equipped to take over the responsibilities of operation and management once the
project phases out. Consultations on social and environmental issues carried out during implementation of
subprojects will be done in an inclusive manner and with active participation from women representatives,
communities and vulnerable social groups. To help support the capacity building of local governments, existing
local mechanisms will be used for engaging with stakeholders. The SECF also outlines the disclosure
requirements for the project. The ESMF waspublicly disclosed on the websites of the GoN and the World Bank on
October 18 and 17, 2019 respectively. Likewise, all the other instruments prepared under the project will be
similarly disclosed.
The ESMF also outlines the Grievance Redress Mechanism (GRM) set up for the project. The GRM will be a
three-tiered but an integrated mechanism for addressing complaints and feedback. The structure as well as
procedures for the GRM will draw on the existing mechanisms and processes established at the local level to help
strengthen the capacity of these local systems.
MoUD has set up a project coordination office (PCO) under the Department of Urban Development and Building
Construction (DUDBC) for NUGIP in Kathmandu, and a Project Implementation Unit (PIU) will be established in
each municipality for project implementation in the field. To ensure that the investment sub-projects are
viii
efficiently implemented,and completed in accordance with environmental and social safeguards requirements,
technical assistance will be delivered through a Design and Supervision Consultancy (DSC). The role of the
PIU/DSC includes implementation of the ESMPs, RAPs and VCDPs.
This ESMF has been revised to additional environmental and social risks and impacts arising as a result of the
COVID-19 pandemic, and as well as to addres potential risks and impacts arising under theadded component for
LIPW, added to provide support and relief to vulnerable groups in target municipalities to help mitigate the short
and medium term impacts of COVID-19. Guidance has been provided to address occupational health and safety
risks and impacts to workers,and considerations for adapting citizen engagement and stakeholder engagement
requirements to the COVID-19 context have also been included. This ESMF does not address risks and impacts in
relation to the CER component (CERC), given that the type of likely emergency and indicative list of activities
that will be required under CERC cannot yet be determined. Environmental and social screening of activities
under Component 4 (CERC) will follow the procedures outlined in the ESMF and in the CER Implementation
Manual. In case new activities are identified for the CERC when triggered that go beyond the scope of the ESMF,
then the ESMF will be updated as needed and redisclosed.
1
1. INTRODUCTION
1.1. Project background
The Project Development Objective of the Nepal Urban Governance and Infrastructure Project (NUGIP) isto
strengthen the institutional and fiscal capacities of participating municipalities for strategic municipal
infrastructure and service delivery.
The proposed NUGIP is comprisedof the following five components:
Component 1: Urban Development Grants (UDGs) for strategic municipal infrastructure and service
delivery (International Development Association (IDA) allocation of US$ 115 million). This component will
provide UDG to participating municipalities for financing strategic municipal infrastructure sub-projects
focusing on, amongst others, rehabilitation and improvements in municipal roads, drainage, drinking water
supply and onsite sanitation, as well as associated design and implementation support. The component will
support the operationalization of Nepal’s first urban sector conditional grant (UDG) system, that focuses
exclusively on strategic municipal infrastructure and service delivery improvement at the local level. The UDG
allocations have been determined based on an objective and transparent allocation formula1, and will allow
municipalities to develop their multi-year municipal investment program in year 1. Municipalities will identify,
design and implement identified subprojects in line with the guidelines and procedures outlined in the Project
Implementation Manual (PIM). The component, through the design and implementation support will help the
participating municipalities in developing robust contract structuring and implementation modalities to attract
private sector participation for construction as well as operations and maintenance of the municipal
infrastructure, to the extent feasible.
Component 2 Institutional strengthening of participating municipalities(IDA financing: US$7 million). This
component will focus on strengthening institutional systems and capacities of participating municipalities for
improved urban management and service delivery of, amongst others: (a) integrated urban development
planning; (b) OSR mobilization; (c) municipal FM, procurement, and contract management; (d) citizen
engagement and gender inclusion; (e) urban infrastructure asset management system and (f) institutional
performance monitoring and reporting system for municipalities. In addition to these six core urban management
areas, the technical assistance will also include dedicated support to the municipalities in the context of the
COVID 19 pandemic, including in: (i) Support to Business Continuity Plans to allow municipalities to maintain
and operate key municipal functions during the short and medium term as their staff and finances are affected by
the crisis, (ii) Mapping of particular vulnerable/high risk/highly impacted zones within the cities, (including
informal settlements) and provide targeted interventions, (iii) Communication and awareness raising campaigns
on actions to limit the risks for exposure and spread of virus, including handwashing, and (iv) Support to design
targeted interventions to help reduce the risk of spread of the virus. The specific TA can be tailored to meet the
needs of the municipality.
Component 3: Support to municipalities for COVID-19 Recovery (Total financing: US$20 million). This
component provides support and relief to vulnerable groups in the target municipalities to help mitigate the short
and medium negative impact of the COVID 19 crisis through rapid labor-intensive public works (LIPW).
Thiscomponent will finance (i) payment of wages for unskilled labor to undertake temporary employment in
participating municipalities, (ii) expenses for tools and materials for the implementation of such projects, and
(iii) expenses related to management of the LIPW (consultations, administration, and supervision).Target
beneficiaries for the LIPW will be individuals from poor and vulnerable households. Participants will be
provided with appropriate training on construction methods, where required, and specific occupational health and
safety measures, including the use of protective personal equipment. The selection process for beneficiaries will
specifically cater to supporting vulnerable groups including the elderly, physically challenged, minorities and
disadvantaged groups. The LIPW subprojects will require a minimum percentage representation of female
workers; The criteria and other guidance for targeting beneficiaries will be detailed in the PIM.
1 The agreed sectoral allocation formula is: 50 percent weightage for population; 30 percent weightage for equal share; 10 percent weightage for area of the municipality; and 10 percent weightage for infrastructure gap.
2
Component 4: Contingency Emergency Response (Total financing: US$0 million). The proposed project
includes a Contingent Emergency Response (CER) component to respond rapidly at the Government’s request in
the event of an eligible disaster, including climate-related events and pandemics. This Component will finance
the implementation of emergency infrastructure reconstruction, rehabilitation and associated studies (Emergency
Response Activities). Resources will be allocated to this component as needed by the project during
implementation. Disbursements will be made against a preestablished list of critical goods or the procurement of
goods, works, and consultant services required to support the immediate response and recovery needs of the
GoN. A separate Implementation Manual for this component will be prepared by the GoN and will provide
detailed guidelines and instructions on how to trigger the CER component and use funds.
Component 5: Project management and coordination (IDA financing: US$8 million). This component will
provide support to the MoUD for managing, coordinating and monitoring the implementation of the proposed
Project, and also for enhancing its federal policy and regulatory role for urban development.
In order to ensure the long-term sustainability of the projects supportedunder NUGIP, the Environmental and
Social Management Framework (ESMF) has been prepared. It is the guiding document to integrate the
environmental and social safeguards at subproject level through appropriate measures during the planning,
design, construction and operation phases of various activities of NUGIP. The framework will help identify the
adverse environment and social impacts and provide specific guidance on the policies and procedures to be
followed for Environmental and Social Impact Assessment (ESIA) and preparation of site-specific safeguards
management plan (e.g., ESMP, RAPs, etc), inclusive of the roles and responsibilities of the implementing
agencies.
At the time of revising the ESMF, detailed design of the LIPW had not be determined. Once detailed design has
been confirmed, this ESMF will be updated in order to provide guidance to municipalities in addressing
subproject environmental and social risks and impacts.
1.2. Rationale and Objective of ESMF
The Environmental and Social Management Framework (ESMF) is prepared to assist in screening, assessment,
management of environmental and social risks of the project at an early stage in project planning and integrate
mitigation measures during the subproject design, implementation and operation. The framework will help
provide specific guidance on the policies and procedures to be followed for environmental and social assessment
along with roles and responsibilities of the implementing agencies. A systematic methodology has been provided
in ESMF that can be followed along with engineering and institutional interventions required for the sub-project
activities to effective integration of the environmental and social safeguards.
The objective of ESMF is to frame guidelines and procedures to address environmental and social impacts
associated with the implementation of this project. The specific objectives are as follows:
• Ensure that the environment and social management plans are aligned with the requirements of the
country system as well as with the World Bank safeguard requirements
• Outline the process identify and assess the environmental and social risks/ impacts/ issues relevant to
the proposed project
• To establish clear procedures and methodologies for the environmental and social screening, review,
approval and implementation of sub-projects to be financed under the Project
• To ensure that mitigation measures are designed to effectively mitigate the potential adverse social and
environmental impacts
• To specify appropriate roles and responsibilities at the national and municipal levels, taking into
consideration the law on federalization, and outline the necessary procedures for managing and
monitoring environmental and social concerns related to sub-projects, and report on the same
• Strengthen the institutional capacity of the ULGs on safeguards management and compliance.
3
2. ENVIRONMENTAL AND SOCIALREGULATIONS AND POLICY FRAMEWORK
2.1. National and International Laws/Conventions
Table 2-1 and 2-2 list thenational lawsand international conventions pertinent to the project components and sectors
covered under NUGIP which are required during the process of carrying out ESIA and preparation of ESMP, RAP, VCDP,
and other relevant instruments under the project.
Table 2-1List of National Policies, Rules, Laws, Regulations, Relevant to the Project
1. Constitution of Nepal
2. Ancient Monument Protection Act 1956
3. Aquatic Animal Protection Act 1961
4. Environment Protection Act 1997 (2053 BS)
5. Explosive Act 1961 as Amended
6. Forest Act 1993
7. Labor Act 2017
8. Land Acquisition Act, 1977 (and amendments 2010) and Land Acquisition Regulations, 1969
9. Land Reform Act 1964
10. Local Government Operation Act 2017
11. Motor vehicle and Transport Management Act, 2049
12. National Foundation for the Development of Indigenous Nationalities Act 2002,
13. National Park and Wildlife Conservation Act, 1972 and amendments 1992
14. Plant Protection Act 2007
15. Public Road Act, 1974 and amendment 2010
16. Road Board Act 2059
17. Soil and Watershed Conservation Act, 1982 and Subsequent Amendment
18. Solid Waste Management Act 2011 and Solid Waste management Rules 2013
19. Water Resources Act 1992
20. Wildlife Conservation and Trade Act 2004
21. Drinking Water Service Charge (Recovery) Rules 1994
22. Buffer Zone Management Rules, 2052 (1996)2
23. Environment Protection Rule 1997 (2054 BS) as amended
24. Forest Rules 1995
25. Water Resources Regulations 1993
26. Wildlife Reserve Rules 1977
27. 20 Year Road Plan, 2059 –2079BS (2002-2022AD)
28. 2002, National Dalit Commission 2002
29. Forest Policy 2015
30. Hydropower Development Policy 2001
31. Land Acquisition, Resettlement and Rehabilitation0 Policy for Infrastructure Development Project 2014
32. National Biodiversity Strategy and Action Plan (NBSAP) 2014-2020
33. National Environmental Standards Information Booklet 2018
34. National Human Rights Action Plan 2005, National Women Commission
35. National Ramsar Strategy and Action Plan 2018-2024
36. Public Works Directive 2002
37. Work Procedure to Provide Forest Area for other Purposes, 2006
38. EIA guidelines for human settlement and Urban Development Sector 1996
39. EIA guidelines for Road Sector 1994
40. EIA guidelines for Sanitary Landfill Site 1996
41. EIA guidelines for Water Supply sector 1995
42. National EIA guidelines 1993
43. Operational Guideline for mainstreaming GESI in MoUD
44. Solid Waste Management Technical Guideline for Municipalities of Nepal
2These rules will be evaluated case by case for Sub Projects. In exercise of the powers conferred by the Section-33 of the National Parks and Wildlife
Conservation Act, 1973, Government of Nepal has framed the Rules. This Regulation aims at a proper management of the buffer zone. To this end it
provides: (a) for the division of the area into units, on the basis of its status, extent and users' settlement; and (b) for the preparation of a buffer zone management work plan for community development, environmental conservation and rational utilization of forest resources. The plan shall be submitted
to the Department of National Parks and Wildlife Conservation and shall include all the provisions listed in Part. Rule 17 - Gha of this regulation restricts
introduction of harmful chemicals, poison or explosive in to river or water sources located inside buffer zones. However, use of these materials for development of physical infrastructures with permission is not prohibited.
4
2.2. International Conventions
Table 2-2Listof International Conventions, Relevant to the Project
1. Convention on Biological Diversity, 1992)
2. Ramsar Convention 1971 (Convention on wetland of international importance)
3. Convention on the International Trade in Endangered Wild Fauna and Flora (CITES), 1975
4. United Nations Framework Convention on Climate Change, 1992
5. International Tropical Timber Agreement, 2006
2.3. World Bank Safeguard Policies
Table 2-3.World Bank Safeguard Policies relevant to Project
World Bank’s
OP/ BP
Objective & Brief Description
Environmental
Assessment (EA)
OP/BP 4.01
An Environmental Assessment is conducted to ensure that Bank-financed projects are environmentally
sound and sustainable, and that decision-making is improved through appropriate analysis of actions
and of their likely environmental impacts. Any World Bank project that is likely to have potential
adverse environmental risks and impacts in its area of influence requires an EA indicating the
potential risks, mitigation measures and environmental management framework or plan.
Natural Habitats
OP/BP 4.04
The policy is triggered by any project (including any subproject under a sector investment or financial
intermediary loan) with the potential to cause significant conversion (loss) or degradation of natural
habitats, whether directly (through construction) or indirectly (through human activities induced by
the project). The policy has separate requirements for critical (either legally or proposed to be
protected or high ecological value) and non-critical natural habitats. The Bank’s interpretation of
“significant conversion or degradation” is on a case-by-case basis for each project, based on the
information obtained through the EA.
Forestry OP/BP
4.36
This policy is triggered by forest sector activities and other Bank sponsored interventions, which have
the potential to impact significantly upon forested areas. The Bank does not finance commercial
logging operations but aims to reduce deforestation, enhance the environmental contribution of
forested areas, promote afforestation, reduce poverty and encourage economic development
Physical Cultural
Resources
OP/BP 4.11
The Bank seeks to assist countries to manage their physical cultural resources and to avoid or mitigate
adverse impact of development projects on these resources.
Involuntary
Resettlement
OP/BP 4.12
Key objectives of the policy is to avoid or minimize involuntary resettlement where feasible,
exploring all viable alternative project designs; assist displaced persons in improving their former
living standards, income earning capacity, and production level, or at least in restoring them;
encourage community participation in planning and implementing resettlement; and provide
assistance to affected people regardless of the legality of land tenure. The policy covers not only
physical relocation, but any loss of land or other assets resulting in relocation or loss of shelter; loss of
assets or access to assets; loss of income sources or means of livelihood whether or not the affected
people must move to another location. When the policy is triggered, a Resettlement Action Plan must
be prepared. An abbreviated plan may be developed when less than 200 people are affected by the
project. In situations, where the precise impacts cannot be assessed during project preparation,
provision is made for preparing a Resettlement Policy Framework. The Resettlement Action Plan /
Resettlement Policy Framework must ensure that all the Bank’s policy provisions detailed in OP 4.12
are addressed particularly the payment of compensation for affected assets at their replacement cost
Indigenous
Peoples OP/BP
4.10
Key objectives of the Indigenous Peoples policy are to:
1. ensure that indigenous people affected by World Bank funded projects have a voice in project
design and implementation;
2. ensure that adverse impacts on indigenous peoples are avoided, minimized or mitigated; and
3. ensure that benefits intended for indigenous peoples are culturally appropriate.
The policy is triggered when there are distinct, vulnerable, social and cultural groups in the project
area possessing the following characteristics in varying degrees:(a) self-identification as members of a
distinct indigenous cultural group and recognition of this identity byothers;(b) collective attachment to
geographically distinct habitats or ancestral territories in the project area and tothe natural resources in
5
World Bank’s
OP/ BP
Objective & Brief Description
these habitats and territories; (c) customary cultural, economic, social, or political institutions that are
separate from those of the dominantsociety and culture; and(d) an indigenous language, often different
from the official language of the country or region.When this policy is triggered, an Indigenous
Peoples Development Plan is to be prepared to mitigate the potential adverse impacts or maximize the
positive benefits of the
Gender and
Development OP
4.20
The prime objective of the Gender and Development policy is to assist member countries to reduce
poverty and enhance economic growth, human well-being, and development effectiveness by
addressing the gender disparities and inequalities that are barriers to development, and by assisting
member countries in formulating and implementing their gender and development goals. In sectors
and thematic areas where the Country AssistanceStrategy has identified the need for gender-
responsive interventions, the Bank's assistance to the country incorporates measures designed to
address this need. Projects in these sectors and thematic areas are designed to adequately take into
account the gender implications of the project. Preparation of a Gender Action Plan and its
implementation should be ensured by each project undertaken with Bank support.
Safety of Dams
OP/BP 4.37
The policy triggered when Bank finances new dam project or existing dam on which project is directly
dependent. In cases where the bank financed project depends on the existing dam or a DUC then the
Bank requires that the borrower arrange for one or more independent dam specialists to (a) inspect and
evaluate the safety status of the existing dam or DUC, its appurtenances, and its performance history;
(b) review and evaluate the owner's operation and maintenance procedures; and (c) provide a written
report of findings and recommendations for any remedial work or safety-related measures necessary to
upgrade the existing dam or DUC to an acceptable standard of safety. Necessary additional dam safety
measures or remedial work may be financed under the proposed project.
International
Waterways
OP/BP 7.50
The policy requires project state to notify other riparian of the proposed project and the intended
impact on water rights.
This policy applies to the following types of international waterways:
(a) any river, canal, lake, or similar body of water that forms a boundary between, or any river or
body of surface water that flows through, two or more states,
(b) any tributary or other body of surface water that is a component of any waterway described in (a)
above.
2.4. Comparison of GoN and World Bank Policies
Table 2-4: Gap Analysis of GoN and World Bank Policies
Category
Government of Nepal
(GoN) Policy
World Bank (WB) Policy
Gaps between
GoN& WB policy
Recommendations to
Bridge the Gaps
A.
Environment
(Natural
Habitat &
Forest
including
terrestrial and
aquatic)
(OP/BP-4.01,
4.04 & 4.36)
Development Project
falling under
Environment Protection
Rule (EPR) criteria
should be subjected to
IEE/EIA as per the
schedules which are
based on nature of work
work, scale of project,
location and jurisdiction.
However, EIA is
required if any project
development site is
located within -
1. Historical, cultural
and archeological sites.
Environment Assessment
shall be carried out for
identifying potential risks
and adverse impacts, along
with mitigation measures;
Detail Environmental
Management Plan (EMP)
shall be prepared to
address all the policies
triggered related with
natural habitat and
physical, cultural
resources. The EMP shall
adequately address the
relevant issues.
Activities listed in
EPR Schedule 1
requires an IEE, and
those listed in
Schedule 2 requires
EIA. The Schedule
1 and 2 are based on
activity type,
threshold/size, as
well as location. The
Potential risks
associated with the
project are omitted
in GoN policy.
Hence,
Environmental &
Detailed E&S
Screening shouldbe
carried out in the
feasibility study of the
sub-projects followed
by detailed IEE/EIA-
ESMP in parallel with
the Detail Engineering
Design to bridge the
gap between WB and
GoN
requirements/approach.
The ESMP should seek
to to address all the
adverse environmental
impacts arise during
6
Category
Government of Nepal
(GoN) Policy
World Bank (WB) Policy
Gaps between
GoN& WB policy
Recommendations to
Bridge the Gaps
2. Environmentally weak
and wet Areas.
3. National parks, wild
life sanctuaries and
conservation areas.
4. Semi-arid,
mountainous and
Himalayan regions.
5. Flood prone and other
dangerous areas.
6. Residential, school
and hospital areas.
7. Areas with main
sources of public water
supply
Social (E&S)
Screening exercise
shall be carried out
to assess the
potential risk
associated with the
project before
selection of the
project proposal.
execution and operation
of the project.
The ESIA/IEE and
ESMP so prepared
should be made integral
part of bidding
document so that the
Contractor shall adhere
to the provisions
prescribed in the ESMP
during execution of the
project
B. Physical-
Cultural
Resources
(OP/BP-
4.11)
The EPR Rule 28 & 30
states that physical and
cultural resources shall
not be disturbed or
damaged without the
prior approval of
concerned authority.
OP 4.11 and their
application as an integral
part of the Bank’s
environmental assessment
(EA) process
“Chance find’ is not
covered by the EPR
requirements
E&S study should
include (a) measures to
avoid or mitigate any
adverse impacts on
physical cultural
resources; (b)
provisions for
managing chance finds
C.
Involuntary
Resettlement
and Loss of
Land/Structur
e
Crop/Income
Source
(OP/BP-4.12)
Clause 3 of the Land
Acquisition Act states
that any asset that is
required for public
purposes shall be
acquired by providing
compensation.
Compensation Fixation
Committee will establish
the Compensation rates.
Full compensation at
replacement cost for lost
assets shall be provided
according to asset types
and location.
Resettlement and
Rehabilitation assistance to
affected people shall be
provided by the project to
enable them to improve
their living standard.
As per OP 4.12 community
assets needs to be replaced
in consultation with the
community.
As per OP 4.12, all those
who are affected needs to
be assisted including
tenants and sharecroppers.
Full compensation for loss
of land/crop/ asset/income
source shall be provided.
The Land
Acquisition Act of
Nepal only has a
provision for cash
compensation based
on degree of loss. It
does not take into
account
vulnerability of the
affected person
upon losing the
land/asset.
GoNlaws have no
provision for
compensation to
non-titleholders
(i.e., those who do
not possess land
ownership
certificates e.g.
informal
leaseholders,
encroachers)
Factors to be
considered for
calculating
compensation are
not clearly defined
ESMF, inclusive of the
RPF,should include an
indicative entitlement
matrix which indicates
valuation and
associated
compensation for
titleholders and non-
titleholders.
ESMP for sub-projects
affecting livelihood or
economic resources
should also include
livelihood restoration
plan
Community assets need
to be replaced in the
same or better
condition than before.
Livelihood assistance
should be provided as
per criteria set by
ESMF, inclusive of the
RPF.
Entitlement matrix
should be drafted for
each project clearly
stating the rights of the
7
Category
Government of Nepal
(GoN) Policy
World Bank (WB) Policy
Gaps between
GoN& WB policy
Recommendations to
Bridge the Gaps
in the local
regulations
project affected people.
D. Indigenous
People &
Community
(IP&C)
(OP/BP-4.10)
Nepal’s constitution
includesprovisionsrelatin
g to the social security,
participation and
representation of
indigenous community.
National Foundation for
the Development of
Indigenous Nationalities
Act 2002 declares 59
Janjati as indigenous
Nepal Federation of
Indigenous Nationalities
(NEFIN), an
autonomous body, has
further classified these
groups as Endangered,
Highly marginalized,
marginalized,
disadvantaged and
advantaged groups based
on historical economic
and political
background.
In GESI policy, GoN
defines other vulnerable
groups beyond
indigenous and gender-
based groups
WB policies ensures free,
prior, and informed
consultation with the
affected indigenous people
to obtain broad community
support to the project.
Social Impact Assessment
should be carried out to
identity potential impacts
and prepare plan to ensure
that indigenous peoples
receive social and
economic benefits that are
culturally appropriate.
Procedure of free
and prior
consultation with
indigenous group is
not defined in the
local regulations of
Nepal. However,
free, prior and
informed consent
(FPIC) is recognized
in the United
Nations Declaration
on the Rights of
Indigenous Peoples
(UNDRIP) and ILO
Convention 169 to
which Nepal is a
signatory.
GoN does not have
a standalone policy
on Indigenous
Peoples and other
vulnerable
communities which
could have put
substantial emphasis
on bringing basic
services to the
disadvantaged and
indigenous people,
Dalits, women,
disabled and other
vulnerable groups.
At each sub-project
level, free prior
informed consultations
should be carried out
with the indigenous
community and other
vulnerable
communities to obtain
broad consent for the
project.
Project should prepare
Vulnerable Community
Development
Framework (VCDF)
based on community
needs of indigenous as
well as other vulnerable
communities.
E. Gender
Development
Through constitution of
Nepal, guidelines
prepared by National
Women Commission and
GESI guidelines looks
after gender issues and
barriers. These policies
also cover indicators for
monitoring progress of
plans on inclusion of all
genders.
Equal access should be
ensured to female members
as of the male members of
the society to the
opportunities created and
the activities performed by
Bank supported
development interventions.
Appropriate Plans and
policies should be
formulated and
implemented adhering to
the principles of free, prior
and impartial consultation
and participation of the
women throughout the
Disaggregated data
is not available.
Mainstreaming of
M&E of GESI
guidelines hasn’t
happened.
MoUD and DUDBC
don’t have active
GESI unit.
Municipalities does
have women
committees, but all
the issues are not
represented
holistically under
one unit
All government
departments should
collect disaggregated
data.
Where appropriate,
sub-projectsshould
prepare Gender
Empowerment
Plansand implement the
plan to ensure equal
access to various
opportunities created
by the project
8
Category
Government of Nepal
(GoN) Policy
World Bank (WB) Policy
Gaps between
GoN& WB policy
Recommendations to
Bridge the Gaps
project cycle.
9
3. KEY ENVIRONMENTAL AND SOCIAL CONDITIONS IN THE CLUSTER MUNICIPALITIES
Summary of Key Environmental and Social Issues
Table3-1: Key Environmental and Social Issues in theEastern and Western Cluster Municipalities3
Eastern Cluster Municipalities
Key Environmental issues
Birtamod Damak Urlabari SundarHaraicha Mechinagar Itahari Rajbiraj Triyuga Dhankuta
• High iron content in ground water • Threat to Sal trees
• Threats to dhanesh bird species
• Jaljale wetlands need protection
• Blockage of drainage system
(particularly in ward no 1,5,8,13)
• High iron content in ground water
• Solid Waste disposal on
river banks
• Flooding in Mawa,
Bakraha,
SunpakuwaKhola- and
land cutting at places
• High iron content in
ground water
• River bank erosion
• Flooding in Mechi,
Ninda, Timai, Hadiya
• High iron content in
ground water
• Chure -
Environmental
Protected Area
• Lack of drainage
system &
contamination of
water through
effluent discharge
from industries
• Depletion of water
resources
• Disposal of solid
waste on the
riverbanks/open field.
• High iron content in
groundwater, and
existing water supply
system unable to cater
to the demand for
water to growing
population
• Flooding in Khado
River
• Depletion of ground
water
• Pollution due to sewerage
disposal
• Flooding
• Deforestation in southern
part
• Landslide prone areas in
ward no 4,5,6,14,15,16
• Chure - Environmental
Protected Area
• Threat to
water body
due to siltation
• Depletion of
water sources
Social Baseline Condition
• Immigration rate 8-10%
• Poverty 7-10%
• High rates of child marriage
amongTarai caste, Muslim and
Adibasi groups
• Very High Immigration (5-7%)
• Child marriage high in poor
communities
• Limited threat to Dhimal community
• Ward 3,4, 9 has Dhimal community
dependent on forest
• Poverty 20%
• Child marriage common
in indigenous group and
Terai caste group
• Very High Immigration
• Poverty 10-12 %
• Child marriage in poor
in Chaudahry, Dum,
Jhangar, Bantar and
Musar communities
• Limited threat to Dhimal
community
• Ward 3,4, 9 has Dhimal
community dependent
on forest
• Poverty about 10% • Very High
Immigration (7-9%).
• Child Marriagehigh
among Taraidalits,
Muslims and Adibasi
groups
• Khanar, Budhikhola,
Sunsari-Morang
Irrigation Canal.
• There is proposal to
construct 6 lane road,
therefore diverting
canal land at the
TyandraKhola is
required
• Very High
Immigration 1:5 in
rural areas
• Poverty 30-40%
• Caste discrimination
• About 10% women
haveland owner
certificate due to
government tax
incentive policy.
• Child marriage is also
high among
marginalized
communities
• Very High Immigration
• Limited illegal mining
issue
• Ethnic communities
dependent to some extent
on fishing and forest
resources
• Presence of marginalized
vulnerable group Musar
and dalits in ward number
1,2,3,4,5,6,7,8,9,10,11,12,
13
• Very High
Immigration
• Aathpariya is
one of the
deprived
community
concentrated
in Ward no. 8
Western Cluster Municipalities
KeyEnvironmentalIissues
PokharaLeknath Vyas Putalibazar Baglung Tansen Ramgram Tilottama Shuklagandaki
• Flooding in Seti and Mardi River
• Ramsar Site- Lake Cluster of
Pokhara Valley
• Municipality boundary overlaps
with southern part’s Annapurna
Conservation Area
• Flooding in Madi&Seti River
• Water pollution in some stretches
• Flooding in
Aandhikhola,
sumrekhola, bodikhola,
ringikhola
• Water Pollution and
siltation especially
during rainy season
• During rainy season
there is problem of
flooding, water
pollution, siltation,
landslide
• During rainy season,
there is problem of
flooding, water
pollution, siltation,
landslide in nearby
areas of
Aandhikhola,
sumrekhola,
bodikhola, ringikhola
• Flooding in Tinahu
river
• Water pollution in
dug wells
• Flooding in Tinahu
river
• Water pollution in
dug wells
• Flooding in the rivers and siltation in rainy
season
• River pollution from crusher plants located
near the river
Key social issues
- • Poverty rate 20% • Poverty rate 25% • Poverty rate 35% • Poverty rate 15% • Immigration from
hilly region and
rural wards
• Poverty rate 30%
• Poverty rate of 15% • Poverty rate 20%
Source: Stakeholder consultation at Municipalities, Municipality Profiles, and data is based on the available data, the data should be updated as per the requirement of Project Operations Manual. Relevant data inAppendix A and I.
3 See detailed matrix in Appendix I
10
4. ENVIRONMENTAL AND SOCIAL MANAGEMENT FRAMEWORK (ESMF)
4.1. Environment and Social Risk Management Procedure
Under NUGIP, the municipalities are responsible for identification of sub-projects, and execution of sub-project
while integrating the Environmental and Social (E&S) safeguards issues. The guideline for effective integration of
the E&S safeguards is outlined in the ESMF. The ESMF details the procedure for the E&S Risk Assessment and
mitigation through instruments like ESIA, ESMP and RAP. The extent of the assessment is governed through
screening procedure. The flowchart for conducting ESIA is also presented in this figure.
Figure 4-1:Flowchart for conducting ESIA
4.1.1. Environmental and Social Screening
4.1.1.1. Environmental Screening
The environmental screening is the early identification of each sub-project’s potential impacts and a review of the
available environmental information and its surrounding Project Influence Areas (PIAs4) and the project’s potential
impacts (Appendix C). The PIA varies from sub-project to sub-project depending on its location and geographical
condition. The PIA is established with proper justification at the time of scoping process and also determined with
4As per World Bank OP 4.01, Project area of influence can be defined as: The area likely to be affected by the project,
including all its ancillary aspects, such as power transmission corridors, pipelines, canals, tunnels, relocation and access roads,
borrow and disposal areas, and construction camps, as well as unplanned developments induced by the project (e.g., spontaneous
settlement, logging, or shifting agriculture along access roads). The area of influence may include, for example, (i) the watershed
within which the project is located; (ii) any affected estuary and coastal zone; (iii) off-site areas required for resettlement or
compensatory tracts; (iv) the airshed (e.g., where airborne pollution such as smoke or dust may enter or leave the area of
influence); (v) migratory routes of humans, wildlife, or fish, particularly where they relate to public health, economic activities,
or environmental conservation; and (vi) areas used for livelihood activities (Hunting, fishing, grazing, gathering, agriculture,
etc.) or religious or ceremonial purposes of a customary nature.
11
the advice of environmental specialists and set out in the ESIAterms of reference by gathering preliminary idea
regarding the nature, extent, and phasing of environmental issues that would need to be handled during the
subsequent stages.The Zone of Influence (ZOI) varies according to the nature of project. As per Environmental
Protection Regulations (1997), the affected wards/rural municipality are considered as ZOI. This will be assessed
rationally based on the nature of sub project. Filling up theEnvironmental Screeningchecklist, category B sub
project EA requirements is the first step in the conduct of an ESIA and is provided in AppendixC.The following
steps are key to the screening.
• Confirm presence of environmentally sensitive areas from secondary information
• Site observations. If the sub project falls under ineligible category, avoid such sub projects. Only Category
B projects are eligible for funding under NUGIP5.
• Verify applicability of the GoN and the World Bank policies in sub-project activities
• Identify potential negative and positive direct or indirect impacts and provide clarity on issue, which needs
to be investigated under Category B EA type (for higher impact category requires ESIA, for medium
impact category requires abbreviated EMP and for lower impact category require Best Environmental
Practices-BEP).
• Incorporate feedback of public consultation and answers to published notice
• Comply with GoN specific EIA/IEE requirements in the EPA/EPR 1997
• Determine applicability of regulatory and policy and requirement of clearances and permissions
• Identify of key environmental concerns
• Scope Impact Assessment and Mitigations
4.1.1.2. Social Screening
Social screening is to be undertaken by the municipality with support from the relevant experts at planning stage in
all subprojects, which will provide necessary information on the potential social impacts likely to be encountered
during implementation. The nature of upgrading and new project requirements are characteristically different
therefore range and requirement of the social data varies accordingly. This screening will be carried out in close
consultation with various primary stakeholders such as roadside farmers, shopkeepers, indigenous community,
women and Dalits. The Social screening report will provide all information as determined by screening
questionnaire presented in AppendixC for the new project. For the upgrading project, the relevant experts will
develop the criteria applicable to the specific project. The screeningshould gather first stage information about the
subproject to identify:(i) beneficiary population living within various impact zones of the project based on distance;
(ii) extent of land required and number of land owners affected; (iii) impacts on poor and vulnerable groups
including needs and priority for social and economic betterment; (iv) willingness of people for voluntary land
donation; and v) other impacts. The screening report also should include information about the potential damage
and loss of common community structures such as resting place (Chautaro), water tank including pipelines,
religious cultural monumentsand sites, foot trail, Trial Bridge and so on. The results of the screening should include
the following.
• Determination of theapplicability of regulatory and policy instruments and the requirementsfor
clearance,permission, and notifications;
• Identification of key social concerns and vulnerable groups
• Scoping for conducting Social Impact Assessment and the preparation of Resettlement Action Plan (RAP)
or Abbreviated Resettlement Action Plan (ARAP)
4.1.2. Scoping
The scoping for E&S study will be undertaken based on the screening to fulfill the following objectives:
• Familiarize with the project
• Define the study area comprising the project site and its PIA
• Outline the environmental and social interactions pertaining to the project focused on the ESIA study
• Define the scope of work and the approach and methodology to conduct the IEE/ESIA, RAP or ARAP
5 Refer to the Annex
12
Specifically, scoping willascertain the environmental and social issues associated with the nature of project, extent
and coverage of project influence area and project affected persons, to be reflected in the focus of the IEE/ESIA
study. For this purpose, the project documents and design reports willbe reviewed and site survey will be
undertaken to understand the environmental and social sensitivities prevailing in the project area.The information
on the project area and on similar project willalso be studied. Based on the study, likely environmental and social
issues associated with the Project activities during preconstruction, construction and operation will be determined.
4.1.3. Project categorization
According to the World Bank safeguard policy the NUGIP project is a ‘Category-B’ project.
4.1.4. Establishment of Baseline Condition
4.1.4.1. Establishment of Existing Environmental Condition
For environmental assessment (IEE and ESIA), it is very important to adequately define the existing environmental
condition (Environmental Baseline) against which environmental impacts of a sub-project would be subsequently
evaluated. The characteristics of “environmental baseline” would depend on:
• Nature of the sub-project location,
• Nature/ extent of a sub-project and its likely impact,
• Level of environmental assessment (e.g., IEE/ESIA)
For systematic definition and recording, the baseline environment is usually classified into Physical, biological, and
social environment. Important features/ parameters under each category are identified and measured during baseline
survey. The table (in Appendix J) summarizes information on the type of baseline indicators that would be adopted,
based on site-specific potential impacts as identified in the environmental screening and scoping process.
.
4.1.4.2. Establishment of Social Baseline
For Social Impact Assessment, it is very important to adequately define the “social baseline” against which
projected social impacts of a sub-project would be subsequently evaluated. The characteristics of “social baseline”
would depend on:
• Land requirement
• Social issues specifically faced by women or vulnerable groups
• Identify social needs, benefits and barriers
• Extent and type of losses even due to the changes of circumstances.
• Number of Project Affected Family
The table below summarizes the type of baseline indicators that will be required. In cases where projects, which are
categorized with very, limited social impacts, the baseline parameters will be captured through socio-economic
survey (10 % - 25% of base population depending on the type, scale and size of the sub-project). However, if the
project has significant impact, a full census survey will be conducted. It is important to project the number of
affected family andthe extent of losses incurred.
Table 4-1: Description of Social Baseline Information required for the Project
Component Possible Social Issue/ aspect Baseline Information
Demography Socio Economic Condition
• Population
• Age pyramid by gender
• Sex Ratio
• Literacy
• Labor force participation, by occupation
• Population Density
Forestry Forest user group affected due to acquisition of
forest land • Forest type
• Forest land getting acquired
• Uses of forest produce
• No. of users in forest user group (present in the
corridor of impact)
• No. of users under each category of social
category (caste, gender, vulnerable, disability,
economic status)
13
Component Possible Social Issue/ aspect Baseline Information
Conflict for the use of forestry resources between
locals and labors, depletion of NTFP resources and
invasive species
• Flow of migrants/ their sources of forestry
product
• Impact due to increased accessibility.
Agriculture Loss of agricultural land due to urbanization due
to the project • Demographic and socio- economic profile along
and at the project site (PIA)
• Land holding pattern (marginal, small, large)
along and at the project site (PIA)
• Land holding according to social categories
along and at the project site (PIA)
• Farm labors employed
• Livelihood pattern (farmer, business, industry,
service etc. within and outside the project site
(PIA?)
• Source of water for irrigation
• Low lying area
• Crop damages
• Enumeration of PAFs/PAPs
• Affected Plot No/ Survey No and details of its
ownership
• Estimation on loss of Properties (Land Area,
Structures, associated structure etc.)
• Estimation of other properties like cattle’s,
Vehicles, Crops, Trees etc.
• Demographic details of affected PAFs/ PAPs
• Quality of life (To access parameters such as
access to basic amenities such as water,
transport, education, health etc.)
• Health, Sanitation condition
• Prevalence of Social Development Programs
(Govt./NGO)
• Property prices
Loss of crop
Disturbance to agriculture production, influx of
invasive species and pests
Loss of livelihood of cultivators ( farm labors)
Disruption of access to water for irrigation
Flooding or drying of agricultural land
Personal assets
Loss of land • Land holding pattern by size (new construction
of road)
• Type of structures
• Types of minor structures
• Socio-economic profile of affected family
• Types of utility services that need to be shifted
and no. of users
• Types of public/ common assets that have to be
shifted and has public consented for relocation
• Livelihood pattern
• Income generated from the business/ shop/
farming
• Types of trees and count
• Types and value of fruit bearing and flowering
shrubs
Loss of major structure (house, shop etc.)
Loss of minor structure (hand pump, boundary,
cattle sheds etc.)
Loss of assets or access to assets
Disruption of access to common resources
including road, utility services etc.
Loss of livelihood or residence (non-title holders)
Loss of income or means of livelihood
Loss of trees/ vegetation (fruit bearing trees/
shrubs, flowers etc.)
Common
property
resources
Disturbance/ demolition of water supply
infrastructure, groundwater changes leading to
drinking water and irrigation problems
Damage to resting sheds, bus stops, water source
etc.
Land use by in-
migrants and
labor
Acquisition of land and property; social conflicts,
resettlement issues • Changing land use pattern
• Approximate labor requirement for the project
(about 30 % of the labor from outside)
Health Introduction and spreading of communicable
diseases or respiratory disease • Existing medical facilities
• List of sensitive receptors (e.g. hospitalsand
schools) and their capacity
• Prevailing diseases
Road safety • Type and number of accidents
Cultural Heritage Sites of Religious/ cultural importance being
disturbed • Age of the cultural site, its significance,
location, number and type of such properties
Sites of historical / archaeological/anthropological
Importance • It is to be ensured that safe distance (as per the
defined regulations of GoN has been maintained
from such sites
14
Component Possible Social Issue/ aspect Baseline Information
Vulnerable
community
Affects Vulnerable communities (Indigenous
people) by disrupting customary rights of use and
access to land and natural resources, cultural and
integrity
• Type of indigenous group present and their
cultural practices
• Community consultation practices
• Can the project adversely impact local
knowledge and alter lifestyle?
Gender issues Not including in the decision making process of
selection of beneficiaries of the project (/project
design)
• Type and number of public consultations held
for the project
• Record of these consultation and representation
of different social categories
• Women groups especially Dalit women were
involved in consultations?
• How they use the roads or tracks, will there be
any kind of disruption?
• Will women be employed for the project
activities?
• Prevailing wages for men & women
• Are they also part of land ownership
entitlements?
• Source of income
• Instances of gender violence
Limit access to common property or natural
resources
Excluded from opportunities ( construction and
maintenance work)
Disparity in wages
Loss of entitlement to land/ property and
compensation thereof (if women are not included
in the land ownership certificate)
Loss of income or means of livelihood
Increase in instances of gender violence due to
labor influx/ in-migration
Citizen
Engagement
Exclusion of community from decision making
process • Means and number of public consultations
• Public notice provided in accessible manner
(e.g., language and means used for information)
• Type and number of people with disabilities in
the project impact corridor
• Willingness to contribute to the
project,includingto donate land
• Expectation for compensation
• Legal case pending in the court for the land, if
relevant
• Use of the current grievance mechanism
established at the municipality (through ward
representative)
Exclusion of certain vulnerable section from
decision making process and selection of
beneficiaries
Project design limiting access to common
resources for people with disability
Coercion on donating land
4.1.5. Analysis of Alternative
The analysis of alternatives willbe carried out at project planning phase. Analysis of alternatives is necessary to
minimize negative impacts and maximize positive ones. Analysis of alternative may include site selection for sub-
project, provision for alternative design, materials and technologies.In general, for any sub-project, the analysis of
alternative willfocus on:
• Alternative location or alignment;
• Alternative design and technology;
• Assessment of ‘with sub-project’ and ‘no sub-project’ scenario
• Alternative source of resource (water/ material)
• Alternative location for labor camps, storage and disposal of waste
• Alternative route/time for transporting material
• Construction arrangements
4.1.6. Impact Assessment
Key potential benefits as well as adverse impacts on physical, biological and socio-economic environment
associated with the preconstruction, construction, post-construction and operation and maintenance phases of the
project in the Project Influence Area (PIA)will be identified. Difference in the status between the future-with-
Project and future-without-Project condition would be considered as the impact of project on the environmental
components and willbe analyzed in the context of area of influence spanning covering: (a) the primary project site
(b) associated facilities/raw materials source used exclusively in the project (c) possible cumulative impact and (d)
induced impact in the selected PIA for the ESIA study.
15
• Without-Project scenario would provide the status if the proposed interventions are not undertaken. This
will be done by analyzing the previous status using data collected during environmental-social baseline and
field investigations; and
• With-Project scenario, status with implementation of the proposed interventions, will be projected.
The envisaged impacts will be categorized as impacts during the preconstruction, construction and operation phase
of the project. There are common E&S risks which are associated with pre-construction, construction and operation
stage as listed below:
• Impact due to change in land use
• Impact on livelihoods and sources of livelihoods
• Impact due to change in drainage pattern
• Impact on ecology &biodiversity
• Impact on ambient air quality and noise levels
• Impact on water quality
• Impact on properties (by type/category) (including Community Property Resources)
• Impact on permanent ortemporary useof public spaces and facilities
• Health and safety issues during construction and operation phases
• Occupation and safety hazards during preconstruction, construction and operation phase
• Temporary accesscontrol,includingprovisionforbarricadingand safety signage markers if required
• Construction materials (quantity requirement and storage)
• Water requirement for the project with basis of calculations, and its sources during the construction phase
• Type of vehicle/equipment usage during construction
• Utility shifting
• Quantities of solid and hazardous wastes generated
• Disposal ofexcessexcavatedearth,wastedisposal/reuse
• Waste handling and management, including construction waste, hazardous and non-hazardous waste
Additional E&S risks in the COVID-19 context to be considered include management and disposal of health-care
and medical waste including personal protective equipment (PPE), virus transmission between workers and between
workers and community members.
Qualitative and quantitative impact assessment tools (e.g. GIS mapping, analytical matrices, and other relevant
analytical tools) will be used to understand the extent of impact due to the proposed sub-projects. Effort will be
given to quantify the impacts, to the extent possible. For example, quantitative assessment of impact is essential to
be carried out for loss of land-properties- other assets, loss of trees, acquisition of forest land – waterbodies, impact
on common property resources, impact on utilities, generation of debris/waste, requirement of natural resources in
the project etc. On the other hand, qualitative impact assessment may be carried out for impact due to labour influx,
safety and security of workers and communities etc. If necessary, projection of impact though modeling /statistical
analysis will be undertaken to understand the projected level of pollution load due to the proposed sub-project.
4.1.6.1. Potential Key Environmental and Social Impacts at Sub-project Level
Based on the stakeholder consultation with the municipalities, an indicative list of projects which could be taken up
under NUGIP are road construction/upgradation, drainage, water supply, wastewatertreatment, and solid waste
management. Accordingly, the anticipated environmental and social impacts for the NUGIP sub-projects are
furnished below:
Table 4-2: Anticipated Environmental and SocialImpacts due to Development of Sub-projects
Sector Environmental& Social Impacts
Roads and
drainage
• Land acquisition for widening or realigning roads, damage to crops, loss of livelihood
• Acquisition of forest land
• Loss of trees and vegetation cover, associated biodiversity and natural habitat
• Impact on structures, common property resources, religious/cultural properties, utilities
16
Sector Environmental& Social Impacts
• Generation of debris from dismantling of structures and its disposal
• Traffic congestion and disruption to local access during to preconstruction and construction
phase
• Air Pollution and noise pollution during construction and operation phase due to material
handling, vibration during construction work and movement of traffic
• Destabilization of slope which may lead to impacts such as soil erosion, sedimentation etc.
• Leaching of materials which may lead to contamination of water sources, affecting aquatic
habitats
• Air pollution during preparation of the bitumen
• Contamination of soil, water environment due to accidental spillage of oil, grease from the
construction vehicles, fuel storage area
• Possibility of contamination of surrounding soil, water environment from labor camp sites
and improper material handling/transportation
• Loss/partial acquisition of water body and siltation due to construction work
• Concerns related to excavation of quarries and borrow areas (if required)
• Increase in accidents or Deterioration of safety of road users/ pedestrians
• Urbanization and commercialization leading to drastic change in land use pattern
• Impact on migratory path of wildlife/habitat fragmentation
• Possibility of increased illegal hunting/ trapping/ fishing/poaching due to improved
accessibility
Water
Supply
• Contamination of surface or ground water quality during boring/ well construction
• Stress on water source. Impact on availability of water after abstraction of water for the sub-
project or drying up of water supply due to over-extraction
• Generation of muck/excavated material, other debris and its disposal
• Loss of trees and vegetation cover and associated biodiversity
• Air and water quality deterioration due to dust generation and vehicular emissions during
transportation, loading /unloading of construction materials and construction work
• Soil erosion, Contamination of water resource due to silt runoff during trenching
• Generation of noise due to excavation, other construction works, movement of vehicle and
construction equipment
• Traffic congestion and Disruption to local access due to construction, operation-maintenance
work and excavation
• Temporary disturbance to household water supply
• Impact on religious/cultural properties, utilities
• Temporary flooding of adjacent areas due to accidental leakages/bursts
• Acquisition of land requirement for water treatment plant
• Potential threat to safety of dam due to over-discharge or construction of new structure (if
water is sourced from dam)
Waste Water • Lack of proper hygiene and sanitation facilities in labor worker camps
• Land required for sewer pipe network, sewerage treatment plants and possibly for treatment
ponds
• Generation of muck/excavated material, other debris and its disposal
• Loss of trees and vegetation cover and associated biodiversity
• Air quality deterioration due to dust generation and vehicular emissions during transportation,
loading /unloading of construction materials and construction work
• Generation of noise due to excavation, other construction works, movement of vehicle and
construction equipment
• Impact on religious/cultural properties, utilities
• Soil erosion, Contamination of water resource due to silt runoff during trenching
• Temporary flooding of adjacent areas due to accidental leakages/bursts and also due to
blockages and backlogging of lines in operation phase
17
Sector Environmental& Social Impacts
• Risk of accidental contamination of Soil/surface / ground water resource and possibility of
mixing with water supply line due to leakages/ overflows from the sewer lines in operation
phase
• Traffic congestion and disruption to local access due to construction - excavation and
operation maintenance work
• Disposal of waste generated from waste treatment plant such as effluents, septage and sludge
Solid Waste
Management
• Lack of solid waste (including medical wastes) collection, segregation and its recycling
facilities
• Land acquisition and site clearance for waste disposal sites
• Closure of existing open dumpsites and displacement of dependent waste pickers
• Dust emissions and noise generation from site preparation, excavation, material handling and
other construction activities at site, vehicular movement
• Tree & vegetation removal at waste disposal site and loss of associated biodiversity
• Possibility of contamination of surrounding soil, water environment from labor camp sites
and improper material handling/transportation
• Generation of landfill gas i.e. methane (CH4) and carbon dioxide (CO2)
• Nuisance due to generation of foul odor from disposal site or poor transportation/handling of
waste
• Nuisance associated with irregular collection of waste at household level
• Accidental contamination of soil and water environment during transportation and handling
of waste, including medical wastes
• No segregation of waste may lead to uncontrolled disposal of hazardous and medical waste
which may contaminate soil/water resource
• Risk of flooding of landfills (particularly in low lying areas)
• Risk of contaminating surface and ground water by seepage and leachate from disposal sites
• Destabilization of heaps of waste at the landfill site
Anticipated social issues based on thematic areas are listed in the table below:
Table 4-3: Anticipated Social issuespertaining to the project
Theme Social Issues
Inclusion • Lack of inclusion and representation of women and other vulnerable groups in the LIPW
• Lack of representation of female gender and other vulnerable groups
• Lack of use of participatory approach
• Exclusion of women and other vulnerable groups in the decision-making process of selection
of beneficiaries of the project (project design)
• Limited access to common property or natural resources specially of vulnerable groups
• Exclusion from opportunities (construction and maintenance work),esp. of vulnerable groups
such as women and disadvantaged commuities
• Disparity in wages specially of females and other vulnerable groups
• Lack of subsidies on user charges for females and other vulnerable groups
• Social barriers faced by females and other vulnerable groups
• Lack of proper channelsfor communicating grievances
• Assessment not including differentiated priorities for design of human settlements, the location
of housing and the provision of urban services.
• Differentiation of PAPs on the basis of Gender/caste/ethnicity
• Access to public park, public toilets, public taps, public hall and temples could be restricted
• Not consulting other important stakeholders such as line departments, user groups etc.
• Project design limiting access to common resources for people with disability
Land &
Asset
Related
• Coercion on donating land
• Loss of fruit bearing or flowering trees/ shrubs
• Loss of cultivable land and crops
18
Theme Social Issues
• Loss of major or minor structure (residential)
• Loss of temporary shelters
• Loss of livelihood or residence of non-title holders (e.g., squatters, encroachers, tenants, etc)
• Loss of assets or access to assets
• Damage to Resting sheds, bus stops, water source etc. and other common community resources
• Loss of entitlement to land/ property and compensation thereof (if women/ vulnerable families
are not included in the land ownership certificate)
• Dismantling of existing structures
• Disturbance to agriculture production, influx of invasive species and pests
• Loss of visual aesthetic value of the land/area due to the sub-project
Labor influx • Increased pressure on the forest in the vicinity for fuel wood
• Impact on surface and ground water from unsanitary disposal of toilet waste
• Conflict for the use of forestry resources between locals and labors
• Introduction and spreading of communicable diseases or respiratory disease
• Acquisition of land and property; social conflicts, resettlement issues, over establishment of
labor camps
• In-migration affecting the local social and economic conditions
• Increase in instances of gender violence
Indigenous
people
• Disruption of customary rights over use and access to land and natural resources
• Impact on cultural and communal integrity of vulnerable groups, including indigenous people
• Altering or undermining of the recognition of indigenous knowledge
• Impact on foot trails connecting indigenous groups
Additional environmental and social risks and issues in relation to COVID-19
• Risks to workerssuch as in relation to occupation health and safety,hygiene and sanitation
• Requirements for social distancing amongst workers and with community members
• Risks arising from the disposal of health care and medical waste such as personal protective equipment (PPE)
• Exposure of workers and community members to COVID-19
4.1.7. Mitigation Measures for Identified Impacts and Guide to ESMP
An Environmental and Social Management Plan (ESMP) is the key document focused on implementation of
mitigation measures, once the potential impacts are identified. It starts operationalizing the avoidance /
minimization aspects from design/pre-construction phase and ensures that the project impacts are reduced to an
acceptable level during implementation of the sub-project. Thus, ESMP becomes the document to ensure that all the
effort has been made to ensure environmental quality within thePIA.
The ESMPsprepared under the project will be sub-project specific, and will clearly and concisely describing
adverse impacts, selected management measures to minimize and mitigate those impacts, and the timelines for
implementing these measures. It will also clarify roles and responsibilities of various entities such as Project
Proponent, Municipalities, Contractors and other stakeholders. The key components of an ESMP are the following:
• Mitigation measures to be adopted for every possible potential adverse impacts during the Design, Pre-
construction, Construction/Implementation and Operation phases as identified through IEE/ESIA
• Enhancement plans for positive impacts
• Monitoring Plan with indicators, mechanisms, frequency, locations,
• Budgetary allocations for all the above activities
• Institutional arrangements for each activity and mitigation measures
• Implementation schedules for each activity
• Reporting procedures, including for redressing grievances related to environmental issues
19
The ESMP will abide by the following core principles.
i) Local Community Participation and Demand Driven Decisions
ii) Ownership of ULGs
iii) Environmental Sustainability, Protection and Enhancement
iv) Community Cohesion and Security
v) Gender Equity and Social Inclusion
vi) Empowerment of Local Communities/ULGs
vii) Resilience to Disaster, Climate Change
viii) Institutionalization of Land Donation Processes
ix) Adaptability to changing circumstances and context
The cost for implementation of the management measures, the institutional arrangements for monitoring willbe
included in the estimated project cost. The AppendixE summarizes probable impact, its subsequent mitigation
measures institutional roles and responsibilities. However, the actual mitigation measures will be designed on the
basis of the project, location, IEE/ESIA findings, public recommendations and prevalent best practices.
Budget for ESMP
Each sub-project will have its own budget to cover the ESMP implementation costs relating to mitigation measures,
enhancements, and monitoring costs. In addition, training and capacity building costs willbe added for specific
issues that ESIA may bring out. For instance, there may be a need to have short courses on specific topics,
experience exchanges on any particular issue, and so on.
4.1.8. Stakeholder Consultation
Stakeholder consultation is one of the most important components of the ESIA exercise and is to be carried out with
institutional stakeholders as well as with community. Accordingly, consultations will be carried out during the
ESIA process to collect information on baseline scenario, obtain in-depth understanding of the sub-project and the
related environmental and social issues,understand the applicability of various law/legislation, opinions of the
public and to disseminate information about the Project. The consultationswill be preceded by a stakeholder
analysis to identify relevant stakeholders to the proposed intervention. The primary objective of stakeholder
analysis is to map the stakeholders, their organizational structure, operational network, representation requirements
and impact on type of activity in the project to strategically prioritize them and develop an understanding of
operational and organizational gaps. The stakeholder interactions will be managed in a way that would ensure they
are pluralistic, inclusive and conducted through the following mechanisms including the following: focused group
discussions (FGD); Key Informant Interviews (KII); individualinterviews
The outcome of the consultation and relevant documentswill be maintained and included in the ESIA report. The
concerns and the aspiration received from the consultation will be shared with the relevant authority for their
decisions. Subsequently, the decisions madewill be communicated back to the community members. The ESMF
envisages stakeholder consultationsas a continuous process and will be conducted at various phases of the project.
Initial public consultation will be carried out while conducting reconnaissance survey before categorizing the
project. After the preparation of ESIA report, the report will be made available for public review through public
notice. A copy of the report will be kept available at municipality, Tole and ward level for at least 30 days to seek
public’s recommendation and concerns.
The ability to undertake stakeholder consultations as envisaged when originally preparing this ESMF may be
impacted due to COVID-19. There is consequently a need to consider social distancing and other measures when
undertaking stakeholder engagements to mitigate against the further spread of COVID-19. Chapter 8 on Stakeholder
Engagement includes some considerations for adapting stakeholder consulations and other forms of citizen
engagement in the COVID-19 context.
4.1.9. Preparation of ESIA/ESMP Report
Environmental and Social Impact Assessment (ESIA), ESMP for category B project is the most commonly used
tool to ensure that environmental and social aspects are considered during decision-making by influencing the
design of the sub-projects to avoid/minimize, and where unavoidable,mitigate the adverse impacts and/or
enhancepositive impacts. These instruments also provide a platform for getting views from stakeholders including
the directly affected community and institutions to improve the design so that the asset quality is improved (refer to
Appendices E and F).
20
4.1.10. Environmental Mitigation and Enhancement Management Plan
Environmental management actions to be undertaken and to be adopted for the realization of environmental
environmental mitigation and enhancement for construction and operation phases are presented in Table 4-4. The
Environmental Enhancement and Mitigation Management Plan is part of the ESMP and a templatebriefly describes
impacts, description of enhancement/mitigation action required, individual or agency responsible, national
standards and guidelines, timing of actions, responsible authority, and tentative financial requirements. An example
of a comprehensive EMEMP is provided at Appendix E.
Table 4-4.Template Environnemental Mitigation & Enchancement Management Plan
Construction
Stage/
Environmental
aspects
Environmental
Impact
Mitigation/ Enhancement
Measures
Schedule
of
Actions
Responsible
party
Costs
(NRs)
PRE-CONSTRUCTION STAGE
Physical Environnent
Change in land
use
The project
intervention may
impact the
existing land use
pattern of the area
Appropriate route selection to
minimize impacts
Maximum use of existing road
and public land
Collection of spoils and its
management in scientific way
DPR, ESIA
Consultants,
PCO,
Municipalities
None
Biological / Chemical Environment
Ecologically
sensitive areas
Adjoining
environmentally
sensitive areas
(National Parks,
Wildlife
Reserves, Ramsar
Sites etc) can be
affected
Prior care willbe given during
project screening. Project will
not be developed in
ecologically fragile areas.
DPR, ESIA
Consultants,
PCO,
Municipalities
None
Social-Economic /Cultural Environment
Cultural
heritage
Sites of cultural
and historical
importance can
be affected
Prior care will be given during
project screening. Historically
significant
archaeological/anthropological
site will be avoided in design
stage
DPR, ESIA
Consultants,
PCO,
Municipalities
None
CONSTRUCTION STAGE
Physical, Health and Safety Environment
Sanitation and
health of the
community
Increase in
disease vector
and transmission
of disease from
outside
workforce.
Workers are not allowed to
stay overnight out from the
camp. Awareness program will
be launched to prevent from
the STDs.
Provision of information
around hygiene, particularly in
regards to COVID-19.
Implementation of measures to
address COVID-19 risks
Contractor,
PCO,
Municipalities,
DSC
Integrated
in total
project
cost
21
Occupational
Health Hazard
and Safety
Accidents
causing Deaths/
Injuries
Implementation of OSH
activities. Distribution and
mandatory use of safety hats,
shoes, follow-up of safety
regulation, well-
communication of construction
safety instructions at all levels
Contractor,
PCO,
Municipalities,
DSC
Integrated
in total
project
cost
Risk of virus
transmision
Implementation of social
distancing and hygiene
measures, and other relevant
measures. Provision of
information around hygiene.
Distribution of PPE as
required.
Contractor,
PCO,
Municipalities,
DSC
Integrated
in total
project
cost
Biological / Chemical Environment
Degradation of
water quality
Contamination of
water bodies near
the construction
sites
Silt fencing to be provided in
the construction areas
adjoining water bodies,
material will not be stored near
any waterbody
Provision of proper hygience
and sanitation facilities in
worker labor camp sites
Workerswill be restricted from
polluting the source or
misusing the source.
Contractor,
PCO,
Municipalities
and Wards
in co-
ordination with
DSC
Integrated
in total
project
cost
Degradation of
air quality
Detoriation of air
quality due to
dust and gaseous
emission from
construction
activities and
equipment
Water spraying at regular
intervals, all vehicles,
equipment and machinery used
for construction to be regularly
maintained, regular monitoring
of ambient air quality,
embankment slopes to be
covered with turfing / stone
pitching.
Contractor,
PCO,
Municipalities
and Wards
in co-
ordination with
DSC
Integrated
in total
project
cost
Increase in
noise levels /
vibrations
Disturbance due
to noise from
vehicles,
equipment and
blasting or pre-
splitting
operations
Noise standards will be
maintained at processing
sites. Machinery and vehicles
will be regularly maintained.
Workers working in loud noise
areas will wear earplugs.
Construction will be stopped in
Night-time in sensitive receptor
areas.
Contractor,
PCO,
Municipalities
and Wards in
co- ordination
with DSC
Integrated
in total
project
cost
Social-Economic /Cultural Environment
Community
health and
safety
Uncollected solid
wastes from
worker labor
camps
Traffic
congestion,
possible accidents
Adequate solid wastes
(including medical wastes) are
conducted a
Plan for traffic decongestion
Contractor,
PCO,
Municipalities
and Wards in
co- ordination
with DSC
Integrated
in total
project
cost
22
and death will be kept. Barricades will be
maintained including signs and
flagmen as required. The
construction works will not
interfere with or cause
inconvenience to public or
restrict the access to use of
properties.
POST-CONSTRUCTION STAGE
Physical Environment
Risk of virus
transmission
Provision of information
around hygiene, particularly
with regards to COVID-19.
Implementation of measures to
address COVID-19 risks
Contractor,
PCO,
Municipalities,
DSC
Integrated
in total
project
cost
Disposal of
solid waste,
waste materials
and
construction
spoils
Possible
contamination,
disturbanceto
community,
accidents
Careful segregation of wastes,
regular collection and
treatment of wastes and proper
disposal
Project site and working area
will be cleared of unutilized
construction materials, heavy
equipment and debris; and a
final clean-up of solid wastes
will be conducted.
Contractor,
PCO
Integrated
in total
project
cost
Biological / Chemical Environment
Restoration of
waterways
Clogging of
water bodies,
surface run off
Disturbance of waterways will
be cleared to avoidobstruction
from construction debris and
other waste materials.
Contractor,
PCO
Integrated
in total
project
cost
Social-Economic /Cultural Environment
Termination of
emplyoment
Loss of
temporary jobs
by the local work
force after project
completion,
The local workforce will be
briefed in advance about the
loss of job after project
completion. Compensation, if
applicable, will be provided
Contractor,
PCO,
Municipalities
Integrated
in total
project
cost
OPERATION STAGE
Physical Environment
Soil/Water
quality
degradation
due to surface
run-off
Pollution of water
bodies, erosion
Proper drainage network and
silt fencing will beprovided to
ensure that the water quality is
not impaired due to
contaminants from road run-
off.
PCO,
Municipalities
Integrated
in total
project
cost
Biological/Chemical Environment
Replacement
plantation
Survival of
planted seedling
and their growth
The replacement plantation
will be maintained and taken
care to ensure the survival of
the seedlings to mitigate
vegetation loss during
construction
PCO,
Municipalities
Integrated
in total
project
cost
23
Social-Economic /Cultural Environment
Removal of
fruit trees
Loss of
production
The fruit trees will be
compensated at market value
on the basis of loss of future
production, based on 5 years
annual net production.
PCO,
Municipalities
Integrated
in total
project
cost
4.1.11. Approval and Implementation of Site-specific ESMP
After preparation of the site-specific ESMP report, it has to be endorsed and approved. After its approval the
provisions of the ESMP need to be included in the NUGIP sub project interventions’ designs and estimates before
final approval.After approval, ESMP provisions along with the NUGIP sub projects ‘designs/estimates shall be
implemented along with construction works. The responsibility of overall ESMP implementation as well
monitoring implementation for the category 2 interventions shall lie with the PIU.
4.1.12. Environmental and Social Monitoring of Management Plans
Three types of monitoring envisaged in the plan include: Baseline Monitoring, Compliance Monitoring and Impact
Monitoring. The compliance monitoring comprises two parts; the first is the compliance to the enhancement actions
and second compliance to mitigation actions including the corrective actions issued. The impact monitoring in the
plan relates to only those measurable indicators in the socio-economic, cultural/physical, chemical and biological
environments. For each of the monitoring indicators, monitoring methods, frequency of monitoring, responsible
parties along with the required cost estimates have been estimated (Refer to Appendix E).
4.1.13. Applicability of ESMF on Associated Projects
Besides all the project components and activities, the ESMF is also applicable on all the necessary associated
facilities that are required to set up and operate with the proposed sub-projects or without which the sub-project
would not be viable (e.g. access roads, ancillary buildings etc.). Associated projects under NUGIP do not need to be
funded by the World Bank for the ESMF to be applicable. If the sub-project financed by the World Bank is used as
an associated facility for another investment, the concerned investment will also be assessed to ascertain whether it
meets the requirements of the World Bank and if subsequent improvements can be made. Similarly, the impacts and
risks because of the cumulative effects with other projects in the sub-project region, will also be included in the
ESIA and the DPR and DED are to be updated based on the ESIA/ESMP.
4.1.14. List of Ineligible Sub-Projects
Depending on the scope and scale, a select number of sub-projects are ineligible for financing under the project. To
avoid adverse E&S impacts and to ensure that the projects being funded under NUGIP are ‘Category B’ projects,
proposals that involve activities listed in sub-projects explicitly excluded from funding under NUGIP (Appendix
K), will be screened out.
4.1.15. LIPW subprojects
LIPW subprojects will be selected based on local priorities and with the involvement of communities, for example,
through User Committees at the ward level, and through representative groups of women and Dalits. When
selecting LIPWsubprojects, the project will ensure that the subprojects do not have significiant environmental or
social risks and impacts. Guidance and criteria for selecting LIPWsubprojects will be detailed in the project
implementation manual (PIM).
Target beneficiaries for the LIPW will be individuals from poor and vulnerable groups and households. The
selection process for beneficiaries will specifically cater to supporting vulnerable groups, such as women, the
elderly, minorities, and other discriminated groups. The LIPW subprojects will require a minimum percentage
representation of female workers. Measures for targeting beneficiaries will be further detailed in the PIM.
24
4.1.16. Legal Contract for E&S Compliance
The environmental and social safeguard and mitigation measures willbe integrated in the design of the project itself.
Such approach will enhance the mitigation measures in terms of specific mitigation design, cost estimation of the
mitigation measures and specific implementation criteria. Integration of mitigation measures in the design phase
will also help in strengthening the benefits and sustainability of the project. The legal contractswill include at least
the following commitments:
• Design, construct, operate, maintain and monitor the subprojects in compliance with the specified
applicable E&S requirements.
• Implement the environmental and social mitigation measures specified in the IEE/ESIA-ESMP prepared
based on ESMF, including all conditions stipulated in the ESMP and other relevant plans prepared based
on the process of identification of E&S risks and impacts pursuant provisions tothe World Bank’s
safeguard policies. The project sponsor will also ensure that adequate E&S contracts are included in their
bidding and legal documentation with contractors and suppliers, as needed.
• Use all reasonable efforts to ensure that theenvironmental and social performance of the subproject is in
compliance with the applicable E&S requirements during implementation, including E&S monitoring.
• Provide periodic E&S performance reporting to the PCO andthe World Bank according to an agreed
template within a specified timeframe.
The tender instruction to bidders willexplicitly mention the site-specific mitigation measures to be performed, the
materials to be used, the specified and excluded sites for material retrieval, labor camp specifications, arrangements,
labor influx management and waste management and disposal areas, as well other site-specific environmental and
social requirements. Such a definition would clearly exhibit the cost requirement to undertake mitigation measures,
which otherwise might be lost as the bidders in an attempt to be more competitive may not include the price
realistic enough to fund mitigation measures and other protection measures.
The project contractor willbe bound by the parameters of contractual clauses which will be identified through ESIA
studies pertaining to specific mitigation measures in the subproject. Measures will be taken to ensure that the
contractor is aware and understand the respective contractual clauses and obligations. The final acceptance of the
completed works will not occur until the environmental and social clauses have been satisfactorily implemented.
Role of contractors will be to ensure compliance with ESMP, if any sub-contractors will be hired. There willbe a
legal contract between contractors and subcontractors to adhere to ESMP. Zero tolerance for child/forced labor,
gender-based violence, community H&S, equal wages, labor camp standards for contractors/subcontractors, will be
well-articulated and communicated to the laborers and others.
The contractor’s environmental and social management plan (CESMP) will be prepared by contractor and
submitted to the respective PIU within 45 days of contract signing. This applies to subcontractors too. The
subcontractors report to the main contractor regarding their E and S compliances on regular basis.
4.1.17. Subproject Monitoring
Monitoring is a major part of the ESMF to ensure its goals and objectives are adequately met. The environmental
and social safeguards implementation will be monitored internally. The safeguards staff (E&S) within
Municipalities, DSCs and PCO will monitor the project site in the initial, construction, post construction and
operational phase of project to ensure that all environmental and social issues related to each subprojects are well
addressed and comply with the requirements mentioned in ESMF. Municipalities will prepare quarterly progress
reports and submit them to PCO. PCO will prepare semi-annual monitoring reports and submit to the World Bank.
The reports will cover ESMP implementation, focusing on compliance and any needed corrective actions. As
mentioned earlier, public consultation will be conducted as necessary during preconstruction, construction,
operation phases. The template of monitoring report along with timetablecost is included in Appendix I.
4.2. Specific labor and OH&S-related considerations in the context of COVID-19
In the context of COVID-19, special consideration needs to be given with regards to labor procedures including the
health and safety of workers, the community members with whom workers come into contact, as well as the
management of medical and health care waste. To ensure that workers are safe in the workplace, or that workers
who are at risk or could put others at risk are not at work, is an important first step.
25
Considerations for workers
The World Bank has developed a Safeguards Interim Guidance Note on COVID-19 Considerations in Construction
and Civil Works Projects, which is included in Annex L. Some practical mitigation measures for prevention and
response is provided below.6
• Provide information on COVID-19: Provide information on good practices for preventing COVID-19
transmission, particularly observing recommendations on social distancing, and training to workers to
recognize the symptions of COVID-19.
• Ask sick or potentially infected workers to stay at home: To prevent potentially affected staff from
entering a worksite and infecting co-workers, the project should request workers to stay away from the
worksite where they exhibit any COVID-19 symptons or have been in close contact with a confirmed
COVID-19 patient during the past 14 days
• Cough hygiene: Workers should be instructed to follow cough etiquette to reduce the risk of spreading the
virus when coughing or sneezing, which includes covering the mouth when coughing or sneezing with
tissue and disposing used tissue into wastebasket, or coughing into elbow or sleeve, cleaning hands after
coughing or sneezing preferably by using hand wash or hand sanitizing gel.
• Social distancing: To prevent person-to-person infection, direct contact between workers should be
minimized. Where required to work or meet, a safe distance of 2 metres between people should be
observed. Workers should be informed about the hazards of close contact, and to promote alternative
behaviours such as maintaining safe distances. The contractor may also consider establishing alternative
working days or adding shifts to reduce the total number of employees on a work site at a given time.
• Hand washing: the project should promote frequent and thorough water-soap hand washing and provide
enough places for workers to wash their hands. If soap and running water are not immediately
available, provide alcohol-based hand rubs containing atleast 60% alcohol.
• Cleansing and disinfecting: Touched surfaces should be frequently cleaned such as equipment, handrails,
toilets etc, and instruct workers to clean equipment/workplaces at the end of a shift.
• Food preparation: Staff in labour camps should help ensure that food served to workers is safe. Measures
include: not working if they have symptons; being trained in common food safety practices; required to
wash hands regularly; prevent cross contamination caused by people sharing the same serving spoons.
• Air quality measures: Consider air quality control measures particularly for labor camps
• Personal Protective Equipment: People who come into contact with possibly infected workers or with
infected materials should use gloves and breathing protection
• Workers accommodation: Additional measures to those provided above include preventing infected
persons from entering workers’ accommodation areas, promote, respect and enforce occupancy density
limits in worker accommodations, and where new workers arrive from areas with high risk of COVID-19,
ensure that these persons are adequately quarantined as per local regulations or recommendations from
international organizations.
Health care and medical waste management
The management of health care and medical waste is a critical consideration as part of project activities. The World
Health Organization (WHO) provides guidance on the health-case waste management. As the WHO advises:
“Best practices for safely managing health care waste should be followed, including assigning responsibility and
sufficient human and material resources to dispose of such waste safely. There is no evidence that direct,
unprotected human contact during the handling of health care waste has resulted in the transmission of the COVID-
19 virus. All health care waste produced during the care of COVID 19 patients should be collected safely in
designated containers and bags, treated, and then safely disposed of or treated, or both, preferably onsite. If waste is
moved off-site, it is critical to understand where and how it will be treated and destroyed. All who handle health
care waste should wear appropriate PPE (boots, apron, long-sleeved gown, thick gloves, mask, and goggles or a
face shield) and perform hand hygiene after removing it. For more information refer to the WHO guidance, Safe
management of wastes from health-care activities”
6For more details, see Interim Advice on Supporting Workers in the Context of COVID-19, Interim Advice for IFC Clients on
Preventing and Manaing Health Risks of COVID-19 in the Workplace, as well as Interim Advice for IFC Clients on developing
a COVID-19 Emergency Preparedness & Response Plan.
26
Further details are provided at: https://www.who.int/publications-detail/water-sanitation-hygiene-and-waste-
management-for-covid-19
4.3. Considerations where CERC is activated
This ESMF does not address potential environmental and social risks and impacts arising in relation to the CER
component (CERC), given that the type of likely emergency and indicative list of activities that will be required
under CERC cannot yet be determined. Environmental and social screening of activities under Component 4
(CERC) will follow the procedures outlined in the ESMF and in the CER Implementation Manual. In case new
activities are identified for the CERC when triggered that go beyond the scope of the ESMF, then the ESMF will be
updated as needed and redisclosed.
The costs for of any needed instruments should be included in the budget for the Emergency Action Plan (EAP).
The EAP, to the extent possible, will focus on activities that can be readily implemented on the ground and which
will not result in additional environmental and social risks. The EAP will include a summary of the safeguard
implications of the proposed activities and will list any new safeguard instruments which are required to be
prepared. The sequencing for completing additional safeguard instruments (including requirements for
implementation and monitoring) will be determined at that time.
In the interest of delivering a rapid response in such emergency situations, the updated ESMF where prepared, will
adopt a flexible, “adaptive management” approach. A rapid assessment of the environmental and social baseline of
the CERC activities will be undertaken, based on readily available information. A phased approach to
implementation may be used. Based on the EAP, the CERC activities will be grouped into: (i) those activities which
can proceed as soon as the CERC is activated and with no additional environmental and social assessment; (ii) those
activities which would require an environmental and social assessment, stakeholder consultation, and disclosure of
the relevant management plans (eg ESMP), prior to CERC activities commencing.
The updated ESMF will describe: the potential emergencies and the types of activities likely to be financed and an
evaluation of the potential risks and mitigation measures associated with those activities; identify likely vulnerable
groups and/or locations and includes, where needed, a social assessment to guide emergency responses, such as
potential of exacerbating existing social conflicts. The ESMF will include a screening process for the potential
CERC activities, the institutional arrangements for environmental and social due diligence, and any needed capacity
building measures to implement the CERC-ESMF, generic guidance on emergency small scale civil works, and any
additional safeguard instruments which may be required for the CERC.
It will be determined at the time of CERC activiation whether MOUD-DUDBC will be retained as the
implementing agency, of if a different agency will be responsible for implementing the CERC activities. If
procurement of goods and services is required, the revised ESMF will provide how this will be undertaken.
Additional details regarding CERC implementation will be outlined in the PIM forNUGIP.
27
5. RESETTLEMENT POLICY FRAMEWORK (RPF)
The resettlement policy/strategy adopted for the project aims to ensure that in cases where there is any form of land
acquisition or resettlement on account of sub-projects supported under the project, the affected persons will be
resettled and rehabilitated in a manner that they do not suffer from adverse impacts and that their standard of living,
earning capacities and production levels will either beimproved or at the minimum, will be retained to pre-project
levels. It is also an effort of the project to ensure that resettlement will minimize dependency and be sustainable
socially, economically and institutionally. Special attention will be given to the improvement of living standards of
marginalized and vulnerable groups.
The rationale for the Resettlement Policy Framework has originated from the fact that specific subproject sites and
activities are yet to be identified under the project to be able to understand the exact nature, scope and scale of their
impacts. Thus, this Resettlement Policy Framework (RPF) has been developed to guide detailed resettlement
planning to address land acquisition and resettlement impacts during project implementation. Specifically, this
framework establishes the involuntary resettlement and compensation principles, organizational arrangements to be
applied to meet the needs of the people who may be affected by the project activities due to land acquisition, loss of
shelter, assets or livelihoods, and/or loss of access to economic resources. The RPF is prepared while adhering to
the national regulations as well as the safeguard policy guidelines of the World Bank.
5.1. Principles of RPF
a) Involuntary resettlement willbe avoided where feasible, or minimized, exploring all viable alternative
project designs;
b) Where it is not feasible to avoid resettlement, resettlement activities willbe conceived and executed as
sustainable development programs, providing sufficient investment resources to enable the persons
displaced by the project to share in project benefits. Displaced persons willbe meaningfully consulted and
should have opportunities to participate in planning and implementing resettlement programs;
c) Displaced persons willbe assisted in their efforts to improve their livelihoods and standards of living or at
least to restore them, in real terms, to pre-displacement levels or to levels prevailing prior to the beginning
of project implementation, whichever is higher;
d) Relocation and resettlement of the affected persons/households will be arranged close to the current place
of residence until and otherwise he/she willingly prefers to relocate him/herself;
e) Inclusive programs for the enhancement of their socio- economic development of disadvantagedgroups
(Dalit, Indigenous or Janajati groups and single women etc.) will be planned and implemented as part of
resettlement planning;
f) Compensation support of the built properties including resettlement and rehabilitation benefits for
persons/households who do not have land or legal right for the currently operated land, will be arranged;
g) Access on project benefit (share allocations) will be provided to the affected persons/households for
projects where return on investment is a potential.
5.2. Land & Asset Acquisition7
The World Bank’s Policy, 4.12 Involuntary Resettlement, will guide the social safeguards (land acquisition and
involuntary resettlement) planning and compliance during implementation of sub-projects. In the event a sub-
project requires acquisition of land or asset, necessary measureswillbe taken to ensure that the affected persons are:
i) informed about their options and rights pertaining to resettlement;
ii) consulted on, offered choices and provided with technically and economically feasible resettlement
alternatives;
iii) Provided prompt and effective compensation at full replacement cost for losses of assets attributable directly to
the project.
If the impacts include physical relocation, the resettlement plan or resettlement policy frameworkwill
includemeasures to ensure that the displaced persons are
i) provided assistance (such as moving allowances) during relocation; and
7“Land and Asset Acquisition” here refers to all methods of obtaining land and other asset for project purposes,
which may include involuntary acquisition, acquisition through negotiation and voluntary donation
28
ii) provided with residential housing, or housing sites, or, as required, agricultural sites for which a combination of
productive potential, location advantages, and other factors is at least equivalent to the advantages of the old
site.
Where necessary to achieve the objectives of the policy, the resettlement plan or resettlement policy framework also
includes measures to ensure that displaced persons are
i) Offered support after displacement, for a transition period, based on a reasonable estimate of the time likely to
be needed to restore their livelihood and standards of living; and
ii) Provided with development assistance in addition to compensation measures such as land preparation, credit
facilities, training, or job opportunities.
As per the World Bank policy, the RPF requires that no land will be acquired (taken possession of) before
compensation is paid fully and completely to the affected people.Depending on extent of land requirement for sub-
project, the nature of land acquisition process could be through three processes viz. involuntary land acquisition,
acquisition through negotiation, voluntary land donation.
Prerequisites for sub-project finalization and initiation of the land acquisition process
Prior to sub-project finalization and initiation of land acquisition process under NUGIP, the concerned
municipalities have to ensure that:
• Land recordshavebeen correctly updated in revenue record as well as the cadastral maps by the concerned
authorities
• Land and asset acquisition has been done in accordance to the regulation of GoN and World Bank
safeguard standards
• Land and asset acquisition has been done in legal, documented and transparent manner. The documents
pertaining to transfer of land, consents from owners areproperly documented and published in public
domain.
• No land is acquired before compensation is paid completely to the affected people, as per World Bank’s
policy requirements.
• If the land is already transferred to the proponent (executing agency 'EA"), the land entitlement certificate
(LalPurja) is in the name of the EA prior initiation of construction activities. This could be verified with
district land revenue office
• All grievances especially related to the land acquisition is communicated to the World Bank along with the
redress process followed.
5.2.1. Involuntary Land Acquisition
The Project will ensure that where a sub-project involves land acquisition (more than 10% of individual asset)
against compensation or loss of livelihood or shelter, the acquisition process will not proceed until a satisfactory
RAP/ARAP is prepared and shared with the affected persons, local community, and the World Bank. As mentioned
above, civil and other works in the project sitewill not start until the compensation and assistance is made available
in accordance with the framework. The resettlement and rehabilitation (R&R) benefits willbe extended to all the
Project Affected Families (PAF). Compensation amounts willbe based on the principle of replacement value. The
exact value of compensation and replacement cost will be different for each sub-project activity at different project
locations and willbe based on theeconomic and social survey of the area andthat of the affected persons.
The Land Acquisition Act 1977 authorizes the Government of Nepal to acquire any land in any place for any public
purpose as long as compensation is provided for loss of land and assets. According to the Act, public purposes
include functions undertaken in the interest of or, for the benefit or use of, the general public as well as functions to
be undertaken by GoN.
In preparing theRAPsRPF, the following steps will be followed, in accordance with the Land Acquisition Act and
World Bank policy OP4.12:
• The acquisition and compensation of privately-owned assets are undertaken according to a formal
procedure, consisting of (a) initial procedures, (b) a preliminary investigation process, (c) acquisition
notification, (d) compensation notification, and (e) appeal procedures
29
• Compensation Determination Committees are established (at district level) to ascertain compensation rates
for land and other assets
• Compensation must be paid: (a) for damages caused as a result of investigations during the preliminary
investigation process, and (b) for land and assets permanently acquired by the project (including, standing
crops, trees, houses and other assets)
• Compensation must take depreciation for salvage materials into account
• Under World Bank policy, preference should be given to land-based resettlement strategies where
livelihoods are land-based
• Compensation will be made to the person who has the right to claim for the compensation; to be entitled to
compensation for land, a person must submit an official land registration certificate at the time of
compensation claim
• Titleholders are required to submit compensation claims or complaints within a specified period after the
land acquisition notice had been issued by the Local Authority (Chief District Officer). Compensation for
land is paid after determination of rates and verification of the list of entitled applicants by the
Compensation Determination Committee (CDC)
• Two separate rates of compensation can be paid i) to titleholders who lose all their land, and ii) to
titleholders who lose only some part of their land.
• In determining the compensation amount, the committee has to consider relevant periodic guidelines of
GoN and the loss suffered by persons due to acquisition of land, shift of residence or place of business to
another place.
• While determining the compensation amount, the CFC has to consider price of the land prevailing at the
time of notification of land acquisition, price of standing crops and structure, and damage incurred by
persons being compelled to shift their residence or place of business due to land acquisition.
• After the completion of land transfer process, the municipality in coordination with Land Survey Office will
initiate cadastral survey to update the land record and ensure tax relaxation for the acquired land
5.2.2. Acquisition of Land through Negotiations
Section 27 of Land Acquisition Act 1977, refers that ‘notwithstanding anything contained elsewhere in this Act,
Government of Nepal may acquire any land for any purpose through negotiations with the concerned landowner. It
shall not be necessary to comply with the procedure laid down in this Act while acquiring lands through
negotiations’. The above statement from the Land Acquisition Act 1977 means that land acquisition through
negotiation i.e. ‘willing to buy-willing to sell’ is a possibleprocess for land acquisition under the project.
However, the acquisition of land through negotiations willbe based on the following criteria
• Preparation of Land Acquisition Plan (LAP) for the Project: The project design layout will be superimposed
on cadastral map to identify the affected plots and its corresponding area by Municipality in consultation
with the Design and Supervision Consultant (DSC). The details of other assets will also be identified during
this process
• The LAP will be officially verified and ownership details of affected land parcels will be identified by land
survey - land revenue department and the details should be shared with municipality
• The land acquisition through negotiation will be carried out in a transparent manner and without any
pressure/threat on asset ownership. The documents pertaining to transfer of land, consents from owners
willbe properly documented and published in public domain
• The land owners will be consulted by DSC and municipality to explain the project proposal and acquisition
of land through direct negotiation process
• The value of land and other assets willbe decided through negotiation between the land owner and
municipality, with the negotiation process adequately documented.
• The value of land and assets will be at least as per the prevailing market price
• After the completion of land transfer process, the municipality in coordination with Land Survey Office will
initiate cadastral survey to update the land record and ensure tax relaxation for the acquired land.
30
In case the legal owner fails to be present to receive compensation within given time by the project,
compensation can be handed over to their spouse or legitimate heirs or to the nearest relatives if they have no
immediate heirs such as spouse or children. For this, the compensation receiving person must submit evidences
to prove that they are legitimate heirs along with certification from concerned municipality describing reason of
inability of legal owner to presence themselves for claiming compensation
5.2.3. Voluntary Land Donation
The third option that the project will pursue to fulfill its land requirements will be through voluntary donation. In
such cases, the project will ensure that the donation of land is in fact ‘voluntary’ and free of any coercion—it will
be a legally recorded market transactions in which the donor is given an opportunity to retain the land and refuse to
donate it, and is fully informed about available choices and their implications – i.e. not involving expropriation. The
project will maintain a transparent record of all consultations and agreements reached and subject to the World
Bank approval, voluntary land donation will be one mode of land acquisition provided the following criteria is also
met:
Voluntary Land Donation Criteria
• Voluntary land donation will be limited to "Corridor of Impact" area only
• Project affected people are fully aware of required procedures and entitlement as well as principle of land
donation
• Impacts on individual households will be marginal (limited up to 10% of the productive assets) and the
remaining assets are economically viable to ensure livelihood and/or shelter and will not have an impact on
third parties
• Land donation will not cause relocation of households
• The amount of land being donated will not reduce the donor’s remaining land area below that required to
maintain the donor’s livelihood at current levels
• Donor will benefit directly from the project
• Potential donor or donors have been appropriately informed and consulted about the project and the choices
available to them
• The land donation is done in transparent manner without coercion
• Potential donors are aware that refusal is an option, and have confirmed in writing their willingness to
proceed with the donation
• For community or collective land, donation will only occur with the consent of individuals using or
occupying the land.
Land Donation Process
The main steps that will be followed forland and other permanent assets donation process are the following.
• The ULGs will inform local people about the sub-project activities
• The DSC will identify individual land donors, amount of land to be donated and remaining holding, damage
• Loss of residential structure and its percentage and loss of livelihood and minor structural damage or loss, at
the time of social assessment and inform the affected people about their damage/loss. In case of major
losses, voluntary land donation will not be permissible.
• After availability of detailed records on project impacts (based on the SIAs), the ULGs will publish notice
about land and other permanent assets acquisition.
• The DSC will raise awareness amongst local people about the benefits of the sub-project and inform them
about the provision of the project relating to land donation and structural damage.
• The municipality with DSC and community organizations willassist donors and will fill the voluntary land
donation form of the land donors. In case of any complaints, the affected persons will be able to approach
the grievance redress committeesformed to hear complaints related to voluntary donation process.
31
• The municipality in coordination with Land Survey Office will initiate cadastral survey of affected land
parcels to update the land record,
• The municipality will bear cadastral survey and land transfer cost and will take lead role for land ownership
transfer and,
• The municipality through Social Development section or departments/DSC will prepare documents of each
event and finally forward it to PCO in monthly, quarterly and annual report.
The project will adopt different methods of social recognition such as writing names in the hoarding board, and/ or
offering letter of appreciation to the owners for voluntary land donation. Where voluntary land donation has taken
place following the Project Concept Note review and prior to appraisal, the RAP will provide guidance on
undertaking due diligence to demonstrate that World Bank Policy on Involuntary Resettlement has been followed.
Land Transfer Process for Voluntary Land Donation
After identification of land donors from social assessment study, such donors shall be assisted according to
entitlement matrix and as proposed in ESMP. Individual land donation forms will be filled and land transfer process
initiated. The land donors will be exempted from the tax of the government and other costs incurred during land
ownership transfer.
The record of voluntary contribution will be duly taken prior to signing of the contract. Land ownership transfer
will be initiated prior to thecontract signing process and continue until the transfer is completed for all affected
families/ parcels. The land transfer process involves different stages:
i) Obtaining individual consent in written form from the affected people;
ii) Mobilization of cadastral survey / surveyors from Land Survey Office;
iii) Assistance distribution as per the entitlement matrix, and
iv) Formal land transfer and update of revenue record and cadastral map.
5.2.4. Loss of other Assets
Damage / Loss of Residential Structures
Based on past experience, the nature of subprojects supported under NUGIP are likely to cause damages of various
extents to the residential structures (e.g., road widening sub-projects). In the case of structural damage or loss of
residential structures, such damages will be considered ‘major’ impacts and the concerned persons/households will
be supported as per the entitlement matrix presented below. Further, the project will provide compensation to
thetitleholders and non-title holders differently because the titleholders will lose land along with the structure,
whereas the non-title holders will lose structure only. Damage or loss of other private structures such as compound
wall, cowshed, water tap, tape pillar, tube wells, etc. are considered minor structures. In minor structural damage,
the project will provide fixed assistance as per the entitlement matrix. For the damage and loss of common
community structures such as resting place, water tank, temple, bus stops, culverts, foot trail, trial-bridge, and so on,
the project willundertake repairs and renovations of damaged structures.
Loss of Livelihood/Income Source
In case of loss of livelihood or income sources (e.g., petty shops like teashops, mobile/ temporary shop, etc) and/or
land holdings following land acquisition being reduced to less than the minimum economically viable land
holdings, the project will provide rehabilitation assistance to the affected people. Further, for such
persons/households, livelihood assistance will also be provided.A one-time financial assistance in case of loss, or
skills training and income generation support will be provided. Preferential access to employment opportunities in
project-related construction will be given to vulnerable groups, as defined in the VCDF.
Crop Damage
In case of possible damage of crops by the subprojects, the concerned people will be informed in advance giving
time to harvest the crops from the field. However, in cases where crop damage do occur due to subproject activities,
it will be considered as direct impacts for which the project will provide replacement value of the crops as per
current market price in the same vicinity.
Loss of commercial structures
32
Compensation for full or partial loss of structures will be provide at full replacement cost of materials and labor
according to the structure type, with no deduction for depreciation. A notice to vacate will be issued at least 90
days prior to acquisition.
Impacts on community and cultural assets/facilities
Local community and cultural assets and structures which are affected will be restored in a same or better condition
than they were before, or cash compensation provided at full replacement cost. This will be undertaken in
consultation with the local community user’s groups.
Construction-related losses
Care will be taken to avoid any kind of damage to private and public properties during construction. In case of any
damages to private or public property, the affected parties will be compensated by the contractor.
Full details regarding loss of assets and other losses, together with corresponding compensation and other support
are provided in the entitlement matrix at Table 5.1.
5.3. Preparation of RAP
A social impact assessment, as referred in previous sections, will be undertaken for all projects with high to
moderate social impacts to assess the potential social impacts of the proposed projects. Before commencement of
construction under sub-projects, resettlement impacts will be identified, and RAPs will be prepared in accordance
with this RPF, and will be submitted to the World Bank for review and clearance.
The outcome of the SIA will help determine the extent of the impacted PAPs which in turn will govern the
preparation of the resettlement plans – which can either be an Abbreviated Resettlement Action Plans (ARAPs) or a
full Resettlement Action Plan (RAPs). The PIU, with or without external support,will prepare the RAP. The
compensation (if triggered) will be determined by the Compensation Fixation Committee (CFC) of the district. The
project proponent is responsible for the implementation of RAP.
Abbreviated Resettlement Action Plans (ARAPs): An ARAP is prepared when the impacts of the entire displaced
population are minor (if the affected people are not physically displaced and less than 10 percent of their productive
assets are lost), or fewer than 200 people are affected.
Resettlement Action Plan is prepared for (a) projects involving acquisition of private land or permanent loss of
private assets and livelihood, (b) if the project involves physical displacement and causes adverse impacts on more
than 200 PAPs and (c) projects which requires resettlement sites.
The resettlement plans will be prepared based on the principles of World Bank Operational Policy (OP) 4.12 on
Involuntary Resettlement, the national laws on land acquisition and this RPF. All affected persons will be fully
consulted so that they have a chance to participate in the design and implementation of the A/RAPs. The Executive
summary of thereport will be translated in Nepali language, communicated in local language and specifically
announced though public consultation where the indigenous community is not integrated in mainstream community.
Only after the Bank has accepted the RAPs will compensation, resettlement and restoration activities be initiated.
Such activities will be completed before the commencement of civil engineering. The content of RAP & ARAP is
provided in Appendix G.
5.4. Entitlement Policy Matrix
The Entitlement Policy Matrix is prepared with a view to provide assistance and support to those who need some
support and assistance following the process of land acquisition, even in instances where land donations are
voluntary.
Key definitions
1. Affected area: means such area as may be notified by the appropriate Government for the purposes of land
acquisition
33
2. Agricultural land: Means land used for the purpose of: (i) agriculture or horticulture; (ii) dairy farming,
poultry farming, pisciculture, sericulture, seed farming breeding of livestock or nursery growing medicinal
herbs; (iii) raising of crops, trees, grass or garden produce; and (iv) land used for the grazing of cattle;
3. Building: Means a house or other roofed structure of any material whatsoever but does not include a tent
or other portable and temporary shelter;
4. Encroacher: A person who has extended their building, agricultural lands, business premises or
workplaces into public/government land without authority;
5. Income: Income of the PAP shall mean the amount prior to the cut-off date from all occupations taken
together calculated by an objective assessment;
6. Land: "land" includes benefits to arise out of land, and things attached to the earth or permanently
fastened to anything attached to the earth
7. Project Affected Family: The Project Affected Family (PAF) includes the following:
• family whose land or other immovable property has been acquired;
• family which does not own any land but a member or members of such family may be agricultural
laborers, tenants including any form of tenancy or holding of usufruct right, share-croppers or
artisans or who may be working in the affected area for three years prior to the acquisition of the
land, whose primary source of livelihood stand affected by the acquisition of land;
• indigenous people and other traditional forest dwellers who have lost any of their forest rights
recognized under the operational plan of community forest
• family whose primary source of livelihood for three years prior to the acquisition of the land is
dependent on forests or water bodies and includes gatherers of forest produce, hunters, fisher folk
and boatmen and such livelihood is affected due to acquisition of land;
• member of the family who has been assigned land by the State Government or the Central
Government under any of its schemes and such land is under acquisition;
• family residing on any land in the urban areas for preceding three years or more prior to the
acquisition of the land or whose primary source of livelihood for three years prior to the
acquisition of the land is affected by the acquisition of such land;
8. Project Affected Person (PAP) is any person affected either directly or indirectly by the project and/or
project related activity, irrespective of the legal status and would include the following.
• Title holders,
• Encroachers,
• Squatters,
• Tenants, Leaseholders, Sharecroppers,
• Employees, Landless laborers,
9. ProjectAffected Household (PAH): A social unit consisting of a family and/or non-family members
living together, and is affected by the project negatively and/or positively;
10. Replacement Cost: A replacement cost/value of any land or other asset is the cost/value equivalent to or
sufficient to replace/purchase the same land or other asset and other applicable taxes to be incurred by the
affected person.
11. Shop: Means any premises where any trade or business is carried on and where services are rendered to
customers;
12. Squatter: A person who has settled on public/government land, land belonging to institutions, trust, etc.,
and or someone else’s land illegally for residential, business and or other purposes and/or has been
occupying land and building/asset without authority;
13. Temporary Impact: Impact expected during implementation of the project in the form of earth spoil,
tremors and vibrations, etc. affecting land and structure
14. Tenant: A person who holds/occupies land-/structure of another person and (but for a special contract)
would be liable to pay rent for that land/structure. This arrangement includes the predecessor and
successor-in-interest of the tenant but does not include mortgage of the rights of a landowner or a person to
34
whom holding has been transferred; or an estate/holding has been let in farm for the recovery of an arrear
of land revenue; or of a sum recoverable as such an arrear or a person who takes from Government a lease
of unoccupied land for the purpose of subletting it.
15. Vulnerable Households/PAPs: Vulnerable households/PAPs are those defined in VCDF as being
vulnerable (see next section)
16. Cut-off date: In the cases of land acquisition affecting legal titleholders, the cut-off date willbe the date of
issuing the preliminary notice under the Land Acquisition Act 2034. In cases where people lack title, the
cutoff-date shall be thestart date when the census survey was undertaken by the project authority
Entitlements for Project Affected Persons (PAPs)
The entitlement for different categories of impacts is explained in the following entitlement matrix. Briefly, the
entitlement matrix presents the entitlements for different impact categories in the following order:
1. Impact to title holders which covers
a. Loss of land
b. Loss of residential structures
c. Loss of commercial structures
2. Impact to tenants and leaseholders
a. Residential
b. Commercial
3. Impacts to non-title holders
a. residential squatters
b. commercial squatters
c. encroachers
4. Impacts to trees, plants and standing crops
5. Loss of livelihoods (Permanent loss and Temporary disruption to income)
a. Owners
b. Employees in shops, agricultural laborers, sharecroppers etc.,
6. Impacts to Vulnerable Households
7. Impacts to Community Assets
8. Loss of Access to Residences/place of business
9. Unidentified impacts
The exact value of compensation and replacement cost will be different for each sub-project activity at different
project locations and willbe based on the economic and social survey of the area of the activity and of the affected
persons. An indicative entitlement matrix for NUGIP project is furnished in thetable below.
35
Table 5-1: Entitlement Matrix applicable for the Project
Type of Loss Entitlement Unit Description of Entitlement Implementation procedures
Agricultural, Residential, Commercial, Pasture and Forestry Land
Loss of Private
land under any
form of tenure
Titleholder • Provide compensation at full
replacement cost orprovide full
title to land of equal area and
productivity acceptable to owner
in the vicinity.
• If land is not available
elsewhere, provide cash
compensation at full replacement
cost based on current market rate.
• In the case of farmland,
compensation for cultivation
disruption allowance equal to
one-year production.
• In case of vulnerable
groups,give preference for land-
for-land compensation
• Ensure that resettlement
assistance in addition to
compensation for land occupied
(land, other assets, employment)
at least restore their livelihoods
and standards of living to pre-
displacement levels.
• If remaining land becomes
unusable as a result of land
acquisition, option provided to
landowner to relinquish unusable
remaining portion of land and
receive similar benefits to those
losing all their land parcel(s).
• A List of available public land in
each municipality is required.
• A list of affected and entitled
persons and the area of land loss is
required.
• Notice to vacate the land should be
served at least a month priorto
acquisition date.
• To ensure fair compensation,
determination of rates will be
established not more than one year
prior to property acquisition.
• Land registration in the name of
both landowner and spouse (in case
of land for land compensation)
• In case of cash compensation,
deposited into a joint account in the
name of both landowner and spouse.
Loss of
Tenancy Land
Landowners
Tenants
• Both the landlord & the tenant
will be entitled for 50 percent of
land compensation amount each
(As per 2058 B.S. amendment in
Land Reform Act).
• Non-registered
tenant/renter/lease holder does
not qualify for compensation for
land losses; however, they will be
entitled to compensation for
standing crops and any other
assets built by them. Any upfront
cost for the tenancy agreement
will be reimbursed.
• Where a renter/leaseholder has a
share cropping arrangement, the
compensation payable should be
apportioned according to the
arrangement.
• An advance prior notice will be
provided to landlord and tenant
Temporary
Loss of Private
Land
Titleholder Tenants
and landlord
(As both are the
owner of equal (i.e.
50 %) share, hence
treated as private
• Compensation for crop, land
productivity and other property
losses for the duration of
temporary occupation.
• Compensation for other
disturbances & damages caused
• Advance notice for crop harvesting
• The owner/entitled party will sign
a temporary occupation contract
specifying:
1. Period of occupancy,
2. The terms and conditions for
36
Type of Loss Entitlement Unit Description of Entitlement Implementation procedures
land holder. to property.
• Project and the municipalities to
ensure that persons other than the
owner affected as a result of
temporary acquisition are
compensated for the temporary
period.
• Land should be returned to the
owner at the end of temporary
acquisition period, restored to its
original condition or improved as
agreed with owner.
calculation of production
losses,
3. The frequency of
compensation payment, and
4. Annual inflation adjustment
5. Land protection and
rehabilitation measures.
• Advance notice to vacate the land
before civil works start
• Compensation for any losses
crops/structures,
Land donations Voluntary donation
is accepted only if :
• AP is direct
project beneficiary
and is fully
consulted and
informed about
rights and choices
available to them;
• AP doesn’t fall
below poverty line
after land donation;
• No household
relocation is
involved.
• Landowners have
agreed to donate;
• AP is freely
willing to donate, is
awarethat refusal is
an option (with an
agreement,
including a "no
coercion" verified
by a third party);
and
• Impact limited to
less than 10% of
landholding and
minor assets
• Land is free from
disputes regarding
ownership or tenure
• No compensation for the
donated land, but entitled for
compensation of other assets such
as minor structure, trees, crops,
allowances, etc.
• Transfer of land ownership
• Free of any transfer costs,
registration fees or charges
• Preferential employment in
project construction
• Verify the requirements of the
donation
• Carry out due diligence on the
owners and users of land donated:
identify rightful owner(s); any
competing claims of ownership or
use; structures and assets on the
land; any encumbrances on the land.
• Ensure appropriate consultation
and disclosure
• Establish informed consent of the
person donating land
• Sign written commitment; local
witness or third-party verification to
the commitment letter
• Maintain a transparent record of
all consultations and agreements
reached.
Trees and Crops
Loss of Trees &
Crops
(Perennial/
Non- perennial)
Owner of affected
trees, fruits and
crops
• Advance notice to harvest crops
• Net value of existing crops
where harvesting is not possible.
• The crops, which live, in short
time will be paid in accordance
with one-year output value. The
crops which have lived for
• Inventory of the tree and plant
species list
• List of owners, non-perennial
crops and the area (if applicable) of
cultivation
• The APs will get notice 2 months
in advance regarding crop
37
Type of Loss Entitlement Unit Description of Entitlement Implementation procedures
several years will be
compensated at market value on
the basis of loss of future
production, based on 5 years
annual net production for fruit &
fodder trees & 3 years annual net
production for timber/ fuel wood
trees & other perennial crops
harvesting. Crops grown after the
issue of the notice will not be
compensated.
• The work schedule for
construction works will be adjusted
considering the crop seasons for
avoiding crop damage.
• Crop/trees/bamboo market values
will be determined by the CDCs in
consultation with District
agriculture and forestry office.
• Where a tenant/renter/lessee &
landowner have a share cropping
arrangement, the compensation
payable will be apportioned
according to the lease arrangement.
• Materials may be salvaged with no
deduction from compensation
Structures and Other basic facilities
Loss of
privately-
owned
structures
(residential,
commercial and
other structure)
Titleholder /non-
titleholder
• Compensation for full or partial
loss of structures at full
replacement cost of materials and
labor according to structure type,
with no deduction for
depreciation.
• Resettlement assistance (rental,
dislocation and transportation
allowances) for residential and
commercial structures.
• Households which lose
residential structures and/or more
than 10% of their land. Are
entitled to receive additional
training or benefits
• Replacement cost at market value
of structures will be determined by
the municipalities in consultation
with the Malpot(land revenue
office), local experts and
compensation prices will be
finalized with participation of AP
representatives.
• Other structures that will be
considered for compensation if
affected under the project include:
toilet, sheds, walls, fences, water
mills, workshop etc.
• Materials may be salvaged with no
deduction from compensation.
• Notice to vacate at least 90 days
prior to acquisition.
• Renter/ lessee holder will not be
entitled for compensation of
structures. However, if the
structures are made by them, they
will be entitled to compensation or
the nature of compensation will be
in accordance to the lessee
agreement
Community and Cultural Assets/ Facilities
Loss of land
and structures
Local community
user’s group
• Restoration of affected
structures by the project leaving
such facilities in a better
condition than they were before;
or cash compensation at full
replacement cost.
• Restoration of access to
community resources.
• The land revenue office in the
district and concerned Municipality
will be requested to assist
communities for land replacement
identifying the area nearby.
38
Type of Loss Entitlement Unit Description of Entitlement Implementation procedures
• The land revenue office in the
district and concerned
Municipality will be requested to
assist communities for land
replacement identifying the area
nearby.
Loss of
community
forests and
other natural
resources due
to construction
Forest user’s group
(FUG)/Other
Concerned Groups
• Mitigation measures should be
initiated to control erosion caused
by tree cutting, and to stabilize
and rehabilitate the slopes with
suitable bioengineering works
and vegetation.
• Community forestland lost due
to construction activities should
be replaced and reforested.
• Advance notice to harvest
resources from affected
community forest areas.
• Compensation for trees to the
FUG.
• List of plant and tree species lost
and an assessment for maintaining
the samekind of vegetation.
• Compensation for trees calculated
on the basis of type, age, and
productive value of affected trees in
consultation with concerned forest
office and FUG.
• To minimize damage, the
concerned forest office will be
requested to take necessary action.
Rehabilitation Assistance
Displacement of
household
Titleholders
Tenants
• Housing displacement
allowance for loss of own
residential accommodation
• House rental allowance
• Transportation allowance
• Displaced households will receive
a house rent allowance for 6 months
• Allowances will be paid at the
time of serving the notice to vacate.
Loss of income AP from
Vulnerable groups
• One-time financial assistance in
case of loss of income; or
• Skills training and income
generation support
• Preferential access to
employment opportunities in
project-related construction
works
• Priority to vulnerable group and
affected households for
skilled/unskilled employment.
Vulnerable groups as defined in the
VCDF
Damages caused during Construction – temporary losses
Any kind of
private and
public
properties
All categories of
entitled persons
• Extreme care willbe taken by
municipalities and their
contractors to avoid damaging
public and private property.
• Where damages do occur to
public or private property as a
result of construction works, the
affected parties shall be
compensated immediately for
damages to crops and trees,
damaged land, structure and
infrastructure shall be restored
immediately to their former
conditions.
• Compensation at market price
39
Type of Loss Entitlement Unit Description of Entitlement Implementation procedures
for the loss of income, damaged
crops, trees etc.
5.5. Monitoring and Reporting of RAP
Monitoring is a major part of the RAP to ensure its goals and objectives are adequately met. The implementation of
RAP willbe monitored internally bythe municipality staff. The safeguards staff (E&S) within Municipalities, DSCs
and PCO will monitor the project site in the initial design and planning, construction, post construction and
operational phase of project to ensure that compensation and all rehabilitation and resettlement issues related to
each subprojects are well addressed and are complied with the requirements mentioned in ESMF. Municipalities
will prepare quarterly progress reports and submit them to PCO. PCO will prepare semi-annual monitoring reports
and submit to the World Bank. The reports will cover RAP implementation, focusing on compliance and any
corrective actions needed as per the ESMF. Public consultation will be conducted as necessary during
preconstruction, construction, operation phases.
The role of DSC in this process will include impact assessments, resettlement planning/management, supervision of
compensation disbursement, on-site safety, etc. It is proposed that E&S Department of municipality will review
RAP-ARAP Reports prepared by DSCs, disbursement of compensation to PAPs and to supervise contractors work
to ensure E&S Safeguard as per World Bank standard.
5.6. Stakeholder Consultation and Grievance Redress
Stakeholder consultations and public participation will run through the whole resettlement process. RAPs will
describe all measures taken or to be taken to provide compensation and other R&R assistance, involve the affected
persons in the proposed resettlement arrangements, and foster a sense of participation in livelihood or living
standard improvement and/or restoration activities. To ensure that the opinions and suggestions of the affected
persons are fully considered, public participation will be conducted prior to finalization of project design. Public
participation will run through the whole RAP planning, implementation and external monitoring processes. At the
RAP drafting and finalization stages, the individual RAPs will be disclosed to the affected persons and to the public
at certain places of the project site and in relevant languages. The final RAP will be disclosed again after review and
clearance by the World Bank.
The manner in which stakeholder consultations are carried out may need to be altered to minimize the risk of
COVID-19 transmission. Chapter 8 Stakeholder Engagement provides some guidance for adapting stakeholder
consultations in the COVID-19 context.
In order to ensure that the affected persons have a channel to lodge any grievance on any issue concerned to land
acquisition and resettlement, a grievance redress procedure will be available at the various levels, which includes
relevant escalation points. A separate grievance redress mechanism will not be created for the project if there is
already an existing grievance mechanism at the local level. Where there is none existing at the local level, one will
be created.Unsatisfied grievantwill also have recourse to judicial and administrative mechanism, and the World
Bank’s Grievance Redressal System (GRS).
40
6. VULNERABLE COMMUNITY DEVELOPMENT FRAMEWORK (VCDF)
The objective of the Vulnerable Community Development Framework (VCDF) is to guide the preparation of the
Vulnerable Community Development Plan (VCDP) for the sub projects that will have animpact on vulnerable
communities. The impact on vulnerable communities and the need of a VCDP will be identified through a social
screening process.
The VCDF serves as a practical tool that will help ensure that the project fully respects the dignity, human rights,
economies and cultures of vulnerable communities (VCs), including the Indigenous Peoples. The framework also
aims to ensure that the project benefits are accessible to all vulnerable communities living in subproject areas.
Additionally, it details agreed principles, policies, guidelines and procedures to be integrated into project
implementation and will be in compliance with the applicable GoN’s laws relating to indigenous peoples and other
marginalized groups, and the World Bank’s safeguard policies and objectives relating to Indigenous Peoples.
While NUGIP will supportinfrastructure that will benefit all groups, due to social conditions of vulnerable
communities (VCs), their representation, participation and access to services could be limited, hence there is a
requirement foradditional support from the project. Specifically, the project will provideextra consideration to
Adivasi-Janajati and other vulnerable communities that will minimize the magnitude of impacts and provide
support to ensure benefits; and will also ensure their participation in the project cycles. Thus, this Vulnerable
Community Development Planning Framework (VCDF) has been designed to ensure that vulnerable groups,
including Indigenous Peoples, are regarded as special interest groups, and that impacts on their livelihoods are
minimized and addressed in a sensitive manner.
6.1. Classification of Vulnerable Groups in Nepal
Nepal is a country of significant diversity in many dimensions. The 2011 census of Nepal recorded the presence of
125 caste and ethnic groups, 123 languages spoken as mother tongue, and ten different types of religious groups.
Indigenous Peoples of Nepal are officially described as Indigenous Nationalities (Adivasi-Janajati) and make up for
35.81 per cent of the country's total population (approximately 8.5 million out of the 26 million Nepalis).
Indigenous Peoples in Nepal have distinct cultures, languages and belief systems. They live across the country – the
mountains, the hills and the plains.
As per the Article 42 of GoN’s Constitutional Right to Social Justice(1-5),socially backward women, Dalits,
indigenous people, Madhesi, Tharu, Muslim, people with disability, farmers, laborers, people from backward region
could be termed as vulnerable and need special protection and provision for empowerment. Therefore, vulnerable
groups can be broadly be categorized as
1. Indigenous Peoples
2. Poorest of the poor, irrespective of class, caste, gender and ethnicity
3. Female headed poor households
4. Marginal land holders
5. Elderly-headed (Jestha Nagarik) or child-headed households
6. Household members with disability
7. All Dalit and ethnic minorities/ indigenous groups as categorized by GoN as being vulnerable
Given the multi-ethnic, multi-lingual, multi-religious and multi-cultural nature of the social system in the project
specific municipalities, it is difficult to clearly separate the Indigenous Peoples (IPs) from other vulnerable groups.
The IPs and disadvantaged groups, though belonging to different ethnicity and/or social group, share commonalities
in terms of their economic and livelihood activities. Further, gender, caste and ethnicity have been officially
acknowledged as primary factors that determine a group's vulnerability and marginal status owing to: (i) limited
access to livelihood, assets and services; (ii) low levels of social inclusion and empowerment; (iii) restricted legal
inclusion and representation in decision-making positions; and (iv) economic marginalization. Thus, this framework
has been prepared in a manner that would ensure that the principles of World Bank’s OP 4.10 on Indigenous People
are followed and that the different categories of vulnerable groups, including indigenous people, are able to benefit
equally from the project while the adverse impacts are minimized.
41
6.2. Baseline of Vulnerable Groups in Nepal
Women headed household
The high rate of female-headed households in Nepal, as well as the project specific districts, is largely due to high
migration rates (8-10%) among males of productive age. It is noted however that contrary to other countries,
female-headed households are, on average, less poor than the male-headed households. Studies conducted in 2004
showed that only 24% of the female-headed population lived below the poverty line compared to 32% of male-
headed households. Some have attributed this difference due to higher remittances flowing to female-headed
households – approximately 65%, in contrast to only 24% flowing to male-headed households. Further, during the
stakeholder consultations within the municipalities, it was pointed out that due to GoN’s tax incentive for
registering land on woman’s name and efforts from municipalities to establish single woman networks, the status of
woman headed household has improved.
Landless and economically poor
Data from the Nepal Living Standards Survey 2010/11 and Agriculture Census 2011/12 indicates that in all of
Nepal, 22.9% of households do not own any agricultural land; 10.4% do not live in their own house; and 3% do not
have any land holding. It is likely that the data for the 14 project specific districts would be comparable. Thus, the
project will take special measures to address the needs and concerns of these groups while preparing and
implementing the project.
Adivasi and Janjati’s
The Nepal Federation of Indigenous Nationalities (NEFIN) has categorized the 59 indigenous peoples into five
groups based on developmental indicators (e.g. literacy and education, income, wealth, land holding and other
assets) as follows:
Table 6-1: Classification of Indigenous People on development
1 Endangered Group Kusunda; Bankariya; Raute; Surel; Hayu; Raji; Kisan; Lepcha; Meche;
and Kusbadiya
2 Highly marginalized group Majhi; Siyar; Lohmi; Thudam; Dhanuk; Chepang; Satar (Santhal);
Jhagad; Thami; Bote; Danuwar; and Baramu
3 Marginalized group Sunuwar; Tharu; Tamang; Bhujel; Kumal; Rajbansi; Gangai; Dhimal;
Bhote; Darai; Tajpuriya; Pahari; Topkegola; Dolpo; Free; Mugal; Larke;
Lohpa; Dura; and Walung
4 Disadvantaged group Chhairotan; Tangbe; TinganuleThakali; Bargaule; MarphaliThakali;
Gurung; Magar; Rai; Limbu; Sherpa; Yakkha; Chhantyal; Jirel; Byansi;
and Yolmo
5 Advanced group Newar; and Thakali.
Source: Nepal Federation of Indigenous Nationalities (NEFIN) 2004
The advanced group is not taken into consideration while describing the vulnerable groups. In Nepal, census survey
was conducted in 2011 and the data so collected is disaggregated only on the basis of caste and gender. Therefore, it
is very difficult to estimate number of people under other vulnerable group.
Table 6-2: Population of Indigenous People in project specific districts
Name of the District Population of IP in the
district
Total Population of the
district
Percentage distribution
of IPs in the districts
Baglung 84656 268,613 31.51597
Dhankuta 84393 163,412 51.64431
Jhapa 309308 812,650 38.06165
Kaski 152104 492,098 30.90929
Morang 333528 965,370 34.54924
Palpa 145167 261,180 55.58121
Parsa 78230 601,017 13.01627
42
Name of the District Population of IP in the
district
Total Population of the
district
Percentage distribution
of IPs in the districts
Rupandehi 207444 880,196 23.56793
Saptari 128249 639,284 20.06135
Sunsari 237064 763,487 31.05017
Syangja 91550 289,148 31.66199
Tanahu 144310 323,288 44.63822
Terhathum 52186 101,577 51.3758
Udayapur 162731 317,532 51.24869
Grand Total 2210920 6,878,852 36.34872
The data above depicts that close to 37% of the population in the project specific districts is constituted by
indigenous peoples.
Madhesis
Madhesi by definition means people who inhabit the flat southern region of Nepal (the Terai plains). All the NUGIP
municipalities in the eastern cluster, except Dhankuta have presence of madhesi groups. In these municipalities,
theTeraidalits, terai caste groups, dumjhangar, bantar, muslims, are the most socially backward groups. The
composition of these caste groupsis shown in the graph below:
Source: South Asia Check
Figure 6-1: Composition of Madhesi Caste Groups
Data on other vulnerable groups is not available in census data as the survey did not capture these dimensions.
6.3. Preparation of VCDP for the sub-projects
The need for VCDP will be identified through a social screening process carried as part of the environmental and
social screening for the project investments during the sub-project identification stage. The screening will help
determine whether vulnerable communities will be affected, either positively or negatively, by the proposed sub-
project activities.
If social screening indicates presence of Indigenous Peoples in the subproject area, a social assessment will be
carried out. The assessment will comprise ofsocio-economic survey, focused group discussion and social mapping
etc., in the subproject area to identify the vulnerable groups and determine the magnitude of impact andascertain
losses such as temporary impacts, severity of impacts etc. Information will be collected from separate group
meetings withthe different groups of vulnerable communities. A free, prior and informed consultation will be
43
carried with indigenous peoples to ensure that there is broad community support for the project. The significance of
impacts of the subprojects on vulnerable community will be determined by assessing the magnitude of impact in
terms of:
• Socioeconomic status
• Cultural and communal integrity
• Health, education, livelihood, and social security status and on the level of vulnerability of the affected
person/group/community
• Inclusion/exclusion dynamics
• Customary rights of use and access to land and natural resources
VCDP will be prepared based on the findings from social assessment and consultations with the vulnerable groups,
including indigenous people. The VCDP willinclude mitigation measures of potential adverse impacts through
revision of subproject design and development assistance to maximize subproject benefits. The subproject
willensure that the rights of vulnerable groups, including indigenous people, will not be violated and that if land
acquisition or structural losses involve vulnerable communities then they will be compensated for the use of any
part of their land or property in a manner that is socially and culturally acceptable to them. The subprojects
willfollow the process and procedures as well as compensation measures prescribed in RPF.
6.4. Potential Impacts and Identification of Mitigation measures
Table 6-3: Potential Impacts and Mitigation measures
S. No. Potential Impact on VG Proposed
Mitigation
Measure
Implementation
Phase
Institutional
Responsibility
1 Lack of representation of
vulnerable groups
Covered in SECF
2 Consultative and participatory
approaches not adopted
3 Exclusion in the decision-making
process for selection of
beneficiaries and also during
project design
Prioritising
investments on the
needs of VCs
Ensure
representation of
VCs in public
consultations
Planning stage Municipality, ward
and Tole
committee
4 Baseline data not disaggregated
and thus assessment of needs,
benefits and impacts of the project
inadequate
Public consultation
during baseline
survey
Social Assessment/
Planning Stage
DPR and ESIA
consultants
5 Insufficient analysis of
differentiated priorities for design
of human settlements, location of
housing and provision of urban
services in the social assessment.
Gender/caste/ethnicity/location-
differentiated access to
employment and income-earning
opportunities, access to public
park, public toilets, public taps,
public hall and temples
Social mapping
Assessment of the
needs and social
barriers of different
vulnerable groups.
Conduct separate
and exclusive
FGDs with
vulnerable groups
Social Assessment/
Planning Stage
Municipality, ward
and Tole
committee
6 Limited access to common
property or natural resources
Prior information
about the impacts
shared with the
affected VCs
Preconstruction,
Construction stage
Contractor, Tole/
Municipality staff,
DSCs, PCO,
various concerned
44
Arrangement for
alternative route to
provide access to
the resource
Arrangement for
alternative access
to the same
resource
authorities
7 Persistent discrimination and ill-
practices against VCs
Lack of proper attention to
measures to empower vulnerable
groups
Engaging VCs in
various project
development
activities at various
stages of project
Engaging
representatives of
VCs in decision-
making forums
relating to project
design,
implementation
and monitoring
Preconstruction,
Construction &
Operation stage
8 Geographical isolation (due to the
remoteness, lack of
transportation)causing project to
place less priority to remote areas
Identify settlements
located in remote
areas, to the extent
possible, and
inform them about
the project so that
they can get the
chance to engage
themselves in
project
development works
Preconstruction,
Construction &
Operation stage
9 User charges for infrastructure
services unaffordable to vulnerable
groups
Subsidized user
charges for
vulnerable groups
Operation stage
10 Disruption ofcustomary rights of
use and access to land and natural
resources
Compensation &
livelihood
restoration
Preconstruction,
Construction
11 Impacts oncultural and communal
integrity
Shifting,
restoration of
cultural properties
in consultation
with the concerned
VCs
Preconstruction
12 Undermining ofindigenous
knowledge
Engage VCs,
including
indigenous people,
in decision making
throughout the
project cycle
Preconstruction,
Construction &
Operation stage
45
13 Project features inattentive to the
needs of people with disability
Adopt universal
access as a major
design principle
Ensure disability-
friendly design
consideration in the
project, to the
extent possible
Preconstruction,
Construction Phase
14 Inadequate representation of
women in opportunities provided
under LIPW
Include women
when targeting
beneficiaries under
the LIPW
Preconstruction
15 Inadequate representation of
vulnerable groups such as Dalits in
opportunities provided under
LIPW
Include vulnerable
groups when
targeting
beneficiaries under
the LIPW
Preconstruction
16 Inadequate representation of
vulnerable groups including
women and Dalits when
identifying LIPW subprojects
Ensure that groups
represented
vulnerable interests
are involved when
LIPW subprojects
are selected
Preconstruction
6.5. Consultation and Information Disclosure
Information disclosureand public consultations are important and necessary during sub-project preparation and
implementation as well. As such, during project implementation, meaningful consultation, including with
vulnerable groups, will be a continuous feature. It is envisaged that such an approach would enable project affected
people, vulnerable groups, and other stakeholders to participate in and contribute to the project planning and
implementation, and thereby help minimize adverse impacts and maximize benefits.
Once the project-targeted vulnerable groups have been identified, ‘free, prior, and informed consultations’ will be
held with vulnerable groups, including IPs. Concerns raised during the consultations will be documented and
incorporated in the overall project design, the project implementation plan and the individual vulnerable community
development plan.
During the preparation of VCDP, consultations will also be held with relevant departments and district level offices
of the government, project-affected groups, community-based organizations, women’s groups, indigenous peoples’
organizations, etc., and also at local levels about the project’s environmental and social aspects. To ensure
meaningful consultations, the concerned groups will be provided with the draft documents in a timely manner prior
to consultation and in a form and language that is understandable and accessible to the groups to be consulted (See
SECF of the Environment and Social Management Framework (ESMF) for summary discussions of the
consultations).
Once the VCDPs are prepared they will be disclosed through municipalities’ website. The VCDP will also be made
available at both central/sub-project level project co-ordination offices and municipalities and respective ward
offices. Further, summary of VCDPs in Nepali language will be made available to the concerned communities, local
level NGOs and the others concerned at the subproject sites.
A detailed engagement and consultation process is outlined in the SECF section of the ESMF which is also
applicable to vulnerable communities.
46
The manner in which stakeholder consultations are carried out may need to be altered to minimize the risk of
COVID-19 transmission. Chapter 8 Stakeholder Engagement provides some guidance to adapting stakeholder
consultations in the COVID-19 context.
6.6. Institutional Responsibilities
As mentioned above, the necessity for a VCDP will be determined based on social assessment and stakeholder
consultations which will be conducted by DSCs and municipal officers. If it is found that VCDP is necessary for
any sub-project, the DSC will develop VCDP and get it approved through municipality and PCO. The VCDP will
be implementedthroughout the initial design and planning, construction, post construction and operational phase of
project to ensure that concerns pertaining to vulnerable community for the subproject/s are well addressed and
complied with the requirements mentioned in ESMF. The safeguards staff (E&S) within Municipalities, DSCs and
PCO will monitor the project site in the municipalities, prepare quarterly progress reports and submit them to PCO.
The PCO will prepare semi-annual monitoring reports and submit to the World Bank. The reports will cover the
implementation of VCDP, among others, focusing on compliance and any corrective actions that may be needed.
Public consultations will be conducted as necessary during the preconstruction, construction, operation phases of
the subprojects. The role of DSC includes preparing VCDP for subproject/s, if applicable while the E&S
departments of the respective municipalities will review VCDP prepared by DSCs, disbursement of compensation
to PAPs, and to supervise contractors work to ensure effective implementation of VCDP as per the ESMF.
6.7. Stakeholder Consultation and Grievance Redress
Consultations as part of the implementation stage will involvedirect interactions between the municipality project
engineers, the Environment and Social Development Staff of the municipality, and the Project Affected Persons
especially from the vulnerable communities. These would comprise consultations relating to relocation of the PAPs,
relocation of cultural properties and addressing the impacts on common property resources (CPRs) such as places of
religious importance, community buildings, trees, etc. With the implementation of the R&R provisions in progress,
consultations and information dissemination will be undertaken to inform the affected persons about the progress of
the same. Implementation stage will also involve redress of grievances in case of R&R issues and environment and
social concerns as discussed in detail under Chapter 9 of the ESMF.
47
7. SEA/SH RISK MITIGATION ACTION PLAN
7.1. Need and Purpose
Nepal ranks 118 out of 160 countries on the Gender Inequality Index8. In relation to that, most women face various
kinds of violence since the time they are conceived to old age. Violence against women are gender-based where
there is unequal distribution of power dynamic between men and women.
The Nepal Demographic and Health Survey (NDHS) 2016 records 23 percent women experiencing physical
violence with significant differences across various social groups. The experience of such violence was highest
among Madhesi Dalit women at 44 percent, Muslims at 38 percent while only 9 percent of hill Brahminsreported
having experienced it. By province, women’s experience of physical violence varies from a low of 12 percent in
Province 4 to a high of 34 percent in Province 2. Besides physical violence, about 12 percent of women in Nepal
also reported having experienced emotional violence with 17 percent to 19 percent Madhesi Brahman Chhetri, hill
Dalit and Newar women, respectively experiencing it. Seven percent of women aged 15-49 reported having
experienced sexual violence. Divorced, separated, or widowed women are much more likely to have experienced
sexual violence (20%) than currently married women (8%) and never married women (2%). Likewise, women with
only primary or no education are more vulnerable to sexual violence than educated women.
The current status of gender inequality and gender-based violence in Nepal reveals the need to mainstream gender
sensitivity and GBV, and more specifically, sexual exploitation and abuse, and sexual harassment (SEA/SH) risk
mitigation measures at all organization levels and all phases of project cycle. In Nepal, SEA/SH is prevalent due to
unequal gender relations and discrimination towards women in both public and private sphere. It has direct
implications on the reproductive health status of women and physical, emotional, and mental health of their
children.
The purpose of this action plan is to identify the issues, stakeholders, possible service providers and assess their
capacity and document the legal and institutional mechanisms that aid in accessing grievance redressal related to
gender-based violence. The action plan focuses on sensitizing the communities and other stakeholders
andstrengthening the institutional capacities to respond to the risks of such violence. In preparing the plan, a
survivor-centric approach is followed - all through, victimssurvivors’ care and provision for access to different
referral mechanisms, are considered key aspects of this plan.
One of the key aims of the project is to address critical gaps in core municipal services and infrastructure. For Year
1, four sub-project areas have been identified namely, in Pokhara, Damak, Urlabari and Birtamod, all of which
except for Pokhara, fall in Terai belt. All four subprojects involve upgradingof the road within the ROW (Right of
Way). Out of the total human resources, approximately two thirds are unskilled labors and one third skilled labors.
To the extent possible, laborers will be from the host community, and if not, from other parts of Nepal or
neighboring countriesincluding India. There are cases of domestic violence in the sub-projects and at least 80% of
women do not report cases of domestic violence, and beating is considered a common practice. In Birtamod, the
practice of child marriage is prevalent within the Dhimal and Satar community while in Pokhara teenage marriage
has become a common practice. With Pokhara being a tourist spot, risk of child labour is also prevalent as well a
commercial sex work leading to high risks of sexually transmitted disease. Trafficking of girls is high in Jhapa as
they share border with India.
Based on the SEA/SH Risk Assessment checklist and assessment carried out for the project by the World Bank, the
Project’s SEA/SH risks are assessed to be “Low”. Accordingly, this action plan has addressed “Table – 1:
Recommended actions to address SEA/SH Risks in IPF Projects” as per the “Good Practice Note” published by the
World Bank in September 2018.
This action plan is intended for and is applicable to Project implementing agencies, including contractors, and cover
the Project’s footprint and adjoining communities.
7.2. Legal and policy environment for women’s safety
Nepal is party to 16 international human rights instruments including the International Covenant on Economic,
Social and Cultural Rights, 1966, the International Covenant on Civil and Political Rights, 1966, the Second
Optional Protocol to the International Covenant on Civil and Political Rights, 1989, the Convention Against Torture
and Other Cruel, Inhuman or Degrading Treatment or Punishment, 1984 and the Convention on the Elimination of
all forms of Discrimination Against Women (CEDAW), 1979. By ratifying these conventions, the Government of
Nepal has committed to guaranteeing equality to both men and women in all spheres of their lives, which entails
ensuring that they are not subject to sexual harassment. General Recommendation No.19 (eleventh session, 1992) of
8UNDP Human Development Report 2017
48
the CEDAW Committee clearly stipulated that gender-based violence is a form of discrimination that seriously
inhibits women's ability to enjoy rights and freedoms on the basis of equality with men.
Under the Constitution of Nepal 2015, GBV has been quoted under the fundamental rights of women (Article 38) as
"No woman shall be subjected to physical, mental, sexual, psychological or other form of violence or exploitation
on grounds of religion, social, cultural tradition, practice or on any other grounds.” Similarly, Part 4 of the
Constitution, under directive principles, policies and obligations of the state, directs the policies relating to social
justice and inclusion be directed toward making self-dependent the women who are vulnerable, subjected to social
and family exclusion and victims of violence self-reliant by making their rehabilitation, protection and
empowerment (Article 51-j-2). The constitution under Part 27 makes provisions for various constitution
commissions and under Article 253, filing cases against any persons or bodies on matters of violence against
women or being subjected to social ill-practices or infringement of or deprivation of enjoyment of women’s rights is
listed as a major function, duty and power of National Women Commission.
The Gender Equality Act in 2006, brought tangible legal changes to sexual violence against women. A major
achievement of this act is the provision that an offender convicted for rape must compensate the victim for mental
and physical damage. Also important is the 2009 Domestic Violence (Crime and Punishment) Act, which
recognized for the first time that domestic violence is a crime punishable by law. However, while the act recognizes
domestic violence as a crime, it contains provisions for negotiations through police offices, which seems
contradictory. Also the National Civil Code Act 2017 states not to commit any inhumane or degrading treatment or
domestic violence and the Criminal Code Act 2017 states that violence against women in form of accusing of
witchcraft or practicing of ‘chhaupadi’ tradition9 and sexual violence is treated as criminal offense. Although there
are some laws and provisions against domestic violence, many victims are left without support mainly because of
the poor mechanism to deliver support services as well as a lack of awareness among people regarding such
provisions.
The Human Trafficking Act (2007) extended the definition of trafficking to include the offense of transportation for
the purpose of trafficking. With this extended definition and other support measures, the new Act helps to control
human trafficking and affords needed support and care for victims.
Apart from these laws and policies, the Supreme Court has also issued orders at different times prohibiting different
malpractices that contribute to GBV. For example, the Supreme Court issued a directive order that required the
government to declare Chhaupadi as a malpractice based on superstitious beliefs. Similarly, the court issued a
directive order requiring the government to launch a massive awareness campaign to stop the exploitation of
women accused of practicing witchcraft.
Further, the government's National Safe Motherhood Plan (2002-2017) recognizes GBV as an important issue for
women's health. The Nepal Health Sector Implementation Plan 2010-2015 has outlined GBV as an integral
component of health care provision. Protocols on the management of GBV, including sexual abuse, have been
developed and are now operational. These protocols will study the feasibility of implementing a screening and
support program at Maternity Hospital, Kathmandu for GBV.
7.3. Recommended Actions to Adddress SEA/SH Risks
Table 7-1: Recommended actions to address SEA/SH Risks
Objective Indicator Activities Timeline Responsibility
Project Appraisal
Include the
assessment of
SEA/SH risks (as
low SEA/SH risk)
as part of the
social/gender
assessment in
project’s
Environmental and
Social Impact
Assessment (ESIA)
Low SEA/SH risks
highlighted and
preliminary
mitigation measures
identified
Mapping completed
of available, quality
services in the
project affected area
Conduct consultations and
identify key SEA/SH risks in
project areas and indicate the
measures to be adopted for the
Project.
Map out SEA/SH prevention and
response services in project area
of influence – Reference to be
made from the service mapping
that already exists at the national
level
As part of
ESIA
PCO/PIU
9Chhaupadi is a tradition associated with the menstrual taboo, in the western part of Nepal which prohibits Hindu women and girls from participating in normal family activities while menstruating, as they are considered "impure"
49
Reflect SEA/SH
risks, and measures
to address them, in
Project ESMP and
Contractor ESMP
including the costs.
SEA/SH Action
plan included in the
ESMP
Procurement for
SEA/SH related
activities and costs
outlined in the
contract.
Address how SEA/SH-related
costs will be reflectedin the
contract, including the
procurement documents, to
mitigate risks.
Clearly define the
SEA/SHrequirements and
expectations in a note to bidders.
During
preparatio
n of ESMP
PCO/PIU
Develop
stakeholder
engagement plan
Inform
communities in
project areas of
SEA/SH risks and
options for
response
# of awareness and
consultations held
TOR developed for community
awareness raising activities
(specialized service
providers/contractors/NGOs
identified and hired under
contract) and awareness and
consultations carried out.
During
preparatio
n of ESMP
Prior to
contractor
mobilizati
on
PCO/PIU10
Formulate and
adopt code of
conduct including
sections on safety
of women and girls
CoC developed,
included in all
contracts, and staff,
consultants,
contractors trained.
Develop CoC and include it in all
contracts and also in operations
manual and provide training to all
Prior to
contractor
mobilizati
on
PCO/PIU/Cont
ractor
Hiring a Gender
Specialist with
expertise on
SEA/SH to advise
and monitor action
plan during project
implementation
Appointment of
gender specialist
with SEA/SH
expertise
Measure
effectiveness of
SEA/SH Action
Plan over a certain
number of months
Ensure implementation of the
‘Action Plan’.
Provide technical support for
conducting the trainings.
Develop tools, monitor and
evaluate the action plan items and
report on a monthly, quarterly and
annual basis.
PCO/PIU
Project Implementation
Codes of Conduct
signed and
understood
# of people oriented
and trained on CoC.
# of people who
signed CoCs
Ensure requirements in CoCs are
clearly understood by those
signing it.
Have CoCs signed by all those
with a physical presence at the
project site.
Train project-related staff on the
behavior obligations under the
CoCs.
Disseminate CoCs (including
visual illustrations) and discuss
with employees and surrounding
communities.
Contractor,
Consultant,
PIU.
Awareness on
Sexual exploitation
and abuse (SEA)
and sexual
harassment (SH).
#no. of people made
aware of SEA and
SH issues
IEC material on
Conduct training on SEA and SH
for project workers and local
community.
Implement stakeholder
PIU and
Gender
specialist of the
project
10 PIU is understood as Destination Level Units11 As per Article 221 (Subsection 1) of the Constitution of Nepal 2015, the
municipalities are required to establish a separate act or regulation which will outline the roles and responsibilities of the judicial
committee.
50
GBV, Codes of
Conduct, etc. put up
in the work site,
labor camps,
surrounding
communities.
engagement plan and conduct
community awareness raising
programs about SEA/SH
mitigation measures – eg. Codes
of Conduct, GRM, how to report
and provide multiple entry-points
Establish and
strengthen
grievance redressal
Availability of an
effective GRM with
multiple channels to
initiate a complaint
relating to SEA/SH.
Number of SEA/SH
members trained.
Inclusive SEA/SH
system in place.
Number of SEA/SH
issuesthat have been
referred to GBV
Services Providers
Provide appropriate referral to
complainants.
At project level, select one
women member as first point of
contact for the survivors of
SEA/SH and provide appropriate
training to them.
Implement stakeholder
engagement plan and conduct
community awareness raising
about SEA/SH mitigation
measures – eg. Codes of Conduct,
GRM, how to report and provide
multiple entry-points
Maintain proper documentation
for complaint registration and
management
Gender
specialist of the
project
Implement
appropriate
project-level
activities to reduce
SEA/SH risks prior
to civil works
commencing
Documentation of
measures taken to
reduce SEA/SH
risks.
Have separate, safe and easily
accessible facilities for women
and men working on the site.
Establish locker rooms and/or
latrines for workers and project
staff in separate, well-lit areas and
include the ability to lock them
from the inside.
Visibly display signs around the
project site (if applicable) that
signal to workers and the
community that the project site is
an area where SEA/SH is
prohibited.
As appropriate, ensure that public
spaces around the project grounds
are well-lit.
PIU, Gender
Specialist of
the project.
Project Monitoring
Report in the
quarterly progress
report and review
during ISR
missions.
Successful
implementation of
agreed SEA/SH
Risk Mitigation
Action Plan (Y/N)
Reports SEA/SH related issues in
the quarterly progress report and
review during ISR missions.
PCO, PIU,
Gender
Specialist
51
8. STAKEHOLDER ENGAGEMENT AND CONSULTATION FRAMEWORK
A good communication strategy among the institution and community needs to be established to ensure that the
project is implemented in sustainable manner.There are two key objectives of stakeholder engagement and
consultation framework prepared for the project. First, it is to keep all stakeholders informed of the project
activities, the potential beneficial and adverse impacts. Second, it is to ensure that stakeholders actively participate
in all levels of the project cycles, are able to share local knowledge, mitigation plans are able to minimize the
potential negative impacts of the project, and the relevant stakeholders are well-trained and equipped to take over
the responsibilities of operation and management once the project phases out. These will ultimately contribute
towards narrowing down the gaps between the project officials and beneficiaries and help create a
conduciveenvironment to mitigate the adverse social and environmental issues through optimal cooperation from
the project beneficiaries themselves. Stakeholder engagement strategy outlines engagement through the project
development phases and recommends a set of stakeholders’ engagement activities to be carried out throughout the
project development cycle. The SECF reiterates elements of the strategy that is relevant to social and environmental
issues in general and the ESMF in particular. In addition, it also outlines the disclosure requirements of documents
already prepared and planned under the project. It should be noted that consultations on social and environmental
issues carried out during implementation of subprojects will be done in an inclusive manner, including the inclusion
of vulnerable social groups (such as poor household, caste, and persons with disabilities, among others) and women.
Each municipality will develop a citizen engagement strategy based on the principles laid out in the Stakeholder
Engagement and Consultation Framework.
This chapter should be read in the current COVID-19 context. Social restrictions and other measures to prevent the
further transmission of COVID-19 may impact on the ability to follow guidance on carrying stakeholder
engagements provided in this chapter. Section 8.5 provides suggestions for adapting stakeholder engagement to the
COVID-19 context.
8.1. Existing Stakeholder Engagement Process
The project will use existing institutions established at the local level to carry out stakeholder engagements.
Municipal forums will be the primary mechanism for engaging with stakeholders and community participation, to
ensure that projects identified reflect local needs and priorities. Other mechanisms for community engagement and
consultations include community-based user committees in construction supervision and operations and
maintenance, as a social accountability and safeguard mechanism.As mentioned earlier, the stakeholder
consultations will draw on mechanisms already established at the local level. If such mechanisms doesnot exist, a
mechanism elaborated below willbe followed which is developed in consultation with municipalities during the
preparation of ESMF.
A three-layered decision-making procedure will befollowed to identify the need for infrastructural sub-project at
municipality level. The first level is the Tole Coordination committee, which willbe formed with theparticipation of
representatives of households of the respective Toles. The next level is Ward Level followed by municipality. At
the Tole level, meetingswill beorganized on regular interval to discuss the needs of the tole, including the
infrastructure need of the area. The requirements of particular toles are then forwarded to next level i.e. ward level.
The ward office will review the demand from various toles, screen the proposed interventionsand then forward their
recommendation further to municipality level for assessment and budgetary allocation. After receiving the demands
from various wards covering various toles, the municipality will prioritize the projects considering the available
fund. In case a municipality is not able to cater to the need of any particular area (Ward/tole) due to unavailability
of funds, the said project will automatically become apriority for next year, and this decision will be shared with all
the concerned stakeholders. In all municipalities, the citizens will beengaged in the decision-making process
through Tole Meetings for identification of project (Refer to Appendix B).
52
Figure 8-1: Project identification Process through Stakeholder Engagement
8.2. Stakeholder Mapping
“Stakeholders” under the project refer to those who have plausible stake in the environmental/social impacts due the
project or activity and are ascertained with a view to taking into account all the material concerns in the project or
activity design, as appropriate. It is highly desirable for all key stakeholders to arrive at a consensus on sensitive
features, impacts and remedial actions. The primary objective of stakeholder analysis is to map the stakeholders,
their role, operational network, representation requirements and impact on type of activity in the project to
strategically prioritize consultation with them and develop an understanding of operational and organizational gaps.
The stakeholder interactions will be through the following activities.
• Focused group discussions
• Public consultations
• Key informant interactions
• Consultation with institutional stakeholders
Through the formal and informal consultation, stakeholder mapping willbe done, and their interests concerning the
various project activities willbe identified. The indicative types of stakeholders are furnished in Table 8-1.
Table 8-1: Stakeholder Mapping and Consultation
Government Level Stakeholder Primary/ Secondary Consultation
Federal Level Department of Roads
Ministry of Forest &
Environment
Department of National
Parks & Wildlife
Ministry of Women,
Children and Senior
Citizen
Secondary Regarding the revision in
GoN’s regulations,
policies or plan
DUDBC
MoUD
Primary Regarding NUGIP project
objective, plan, internal
policies
Local Level Department of
Electricity
Forest
Land Survey
Land Revenue
Irrigation
Water supply & sanitation
Traffic Police
Secondary Specialized inputs on local
conditions, limitations and
needs of the public,
compensation estimation
Municipality
Ward
Tole Level Committee Need/Demand
Project/Need review
Project/Need prioritization and
budgetary allocation
53
District Coordination
Committee
Municipality Offices
Ward offices
Tole Development
Committees
Primary Project selection, selection
of beneficiary and their
needs
Sub-project Level Ward Representative
Associations (Business) &
user groups ( road, water,
irrigation, forest)
Women/ Mothers groups
Shopkeepers & vendors
Farmers group
Households
Primary Impact of the project and
possible measures for
mitigating them
Extended users of the
project
Secondary Projection of the usage of
the project infrastructure
8.3. Mechanism for Consultation
The Consultation Framework envisages involvement of all the stakeholders at each stage of project planning and
implementation. Involvement of the community is not limited to interactions with the community but also
disclosing relevant information pertaining to the project tasks. Community participation willbe ensured at the
following stages:
8.3.1. Subproject Identification Stage
The Project Implementation Manual (PIM) for NUGIP provides in detail the steps for identifying and selecting sub-
projects for investment. The municipalities will establish mechanisms to ensure that stakeholders are enagaged at
each step of the process. Some examples of mechanisms to engage with stakeholders are outlined below:
At step 1: Identification and selection of investment sub-projects, two processes will be followed while identifying
investment sub-projects:
• Conducting a comprehensive needs assessment and gap analysis for core municipal
services/infrastructure; and
• Conducting consultations with elected representatives, ULG Thematic Sections, civil society
organizations and community groups, to validate the gap analysis and to identify the local municipal
service delivery needs and priorities.
At step 2: Technical prioritization of investment sub-projects, based on the pre-appraisal of all selected investment
sub-projects conducted under Step 1, the ULG Planning Section will bring together ward representatives, municipal
officials, elected representatives to share and discuss the prioritized sub-projects that will be submitted to the
Municipal Executive.
At step 3: Executive prioritization of investment sub-projects, the Municipal Executive decides on a prioritized and
sequenced list of potential investment sub-projects which will be presented to and discussed with the Municipal
Investment Forum, the outomces of which will be presented to stakeholders
At step 4,the Municipal Executive presents its sub-project recommendations to a consultative forum, the Municipal
Investment Forum and seeks feedback and comments from citizens and local stakeholders. It is the Step during
which citizens and local stakeholders are informed of the Municipal Executive’s recommendations with respect to
the investment sub-projects to be financed out of the ULG’s UDG allocations.
Municipal Investment Forum (MIF): composition and process
The MIF will bring together the following citizen and stakeholder representatives in a half-day meeting with the
Municipal Executive (assisted by ULG Thematic Sections as needed).
• 2-3 representatives from each ward. Ward representatives will be selected by each Ward Committee;
54
• Representatives of 3-4 community-based groups in the ULG jurisdiction. Such groups include women’s
associations, youth organizations, pensioner associations, etc.;
• Representatives of local economic actors (e.g. Chamber of Commerce, trades unions, transport associations,
cooperatives, etc.);
• Representatives of local NGOs;
• Representatives of the local media etc;
The list of MIF members willbe agreed upon and drawn up by the Municipal Executive; and posted on the ULG
notice board. MIF will include for example women and other vulnerable community representatives.Members
willbe formally invited to the MIF at least one week before the meeting. Invited MIF members willbe informed of
the meeting agenda in advance.
By the end of the MIF session, the Municipal Executive willbe able to make a final decision on the prioritization of
its sub-project proposals for UDG funding. Minutes of the MIF meeting willbe kept and made available to the
public.
At step 5 – Sequencing of investment sub-project implementation over three (or four) years, the Planning Section
willdraft a three-year UDG investment plan. The 3-year investment plan willthen be translated into annual budget
proposals, to be confirmed by the Municipal Executive, included in each year’s annual budget proposals and then
submitted to the Municipal Assembly for approval and then will be publicly disclosed.These subprojects will then
be supported under NUGIP. For the subprojects that are selected, social and environmental screening, assessments
and preparation of safeguards management plans will be developed.
8.3.2. Planning/Design Stage
Dissemination of project information to the community and relevant stakeholders will be carried out by
municipality at this stage of the project initiative. The community at large willbe made aware of the project
alternatives and necessary feedback will be obtained. Further, other stakeholders will also be involved in the
decision making to the extent possible. Consultationsfor the project with stakeholders will also be carried out in the
relevant ward offices under the supervision of the Ward Chairperson, and will be done in an inclusive manner,
including vulnerable social groups (such poor household, caste, persons with disabilities, among others) and
women.
The outcome of consultations will be incorporated as appropriate in the designs and mitigation plans. As part of
such consultations, the draft safeguard management plans will also be presented and explained to the people on the
content and process of the implementation of the plans. Consultations with Project Affected Persons and their
profiling are mandatory as per the requirements of ESIA and preparation of RAP, ESMP, VCDP, etc. Consultations
with respect to cultural aspects are to be carried out as part of the Social Impact Assessments for all alternatives and
the selected alternative subproject option.
During ESIA study, two rounds of consultation meetings will be conducted, including consultations for obtaining
the informed views of the affected people and local Non-governmental Organizations (NGOs).
1 Hold consultation meeting at the site.
2 Hold consultations after preparing draft IEE/ESIA report with local communities. At this time ESMP,
RAP/ARAP to be disclosed at relevant local authorities and made available in Nepali/local language to the
community and other stakeholders.
In all subprojects involving resettlement, and prior to the preparation of Resettlement Action Plans, the PAPs will
be informed of the project objectives, likely impacts and essential provisions of Resettlement Policy through the
following activities:
• Awareness campaigns using local Cable TV channel, print media such as posters or information leaflets;
• Holding public information meetings in various project site locations and affected areas;
• Arranging interactive sessions with the PAPs & their representative stakeholder groups;
55
• Formation of focus groups involving key stakeholders, like local leaders, women, vulnerable group
members etc.; these could also serve as local community monitoring groups
For disseminating information pertaining to the subproject, work schedule and the procedures involved; finalization
of project components with identification of impacts, entitled persons, mitigation measures; and Grievance Redress
Mechanisms to be adopted.
In order to discuss and seek opinions and suggestions, all the PAPs and/or their representativeswill be formally
invited to participate in various meetings regarding resettlement issue as convened by the municipality. During such
consultations, draft RAPs will be presented and its contents, processes, eligible entitlements, institutional roles and
responsibilities, etc., will be shared publicly. Once the individual safeguards management plans have been finalized,
they will be shared with the PCO and the World Bank for review and clearance.
8.3.3. Implementation Stage
Consultations as part of the implementation stage will comprisedirect interactions of the municipality project
engineers, environment and social development staffs, DSC representatives, municipal officers, and the Project
Affected Persons. These would usually be one to one meeting of PAP or community representatives with the
grievance redress committeesestablished for the project. All consultations on social and environmental issues
carried out during implementation of subprojects willbe done in an inclusive manner, including vulnerable social
groups (such poor household, caste, persons with disabilities, among others) and women.
8.3.4. Post-construction Stage
The supervision consultant, and contractor will be responsible for Operations and Maintenance (O&M) during the
defect liability period. Thereafter the municipality will be responsible for O&M together with users’ groups.
8.4. Information Disclosure
Most often a development project, including its socio-economic and environmental setting, fails due to lack of
information or misinformation. For the success of a given program, the management must share all the information
obtained about the proposed activities and their expected results with the affected and interested public. The project
will commit itself for proactive disclosure and sharing of information with the key stakeholders, including the
communities/beneficiaries. The project will have a communication strategy focusing on efficient and effective
usage of print and electronic media, billboards, posters, wall writing, and adoption of any other method suiting local
context, logistics, human and financial resources.
Accordingly, in collaboration with different local authority, NGOs and other groups, the project willdisclose all the
relevant information to PAPs and other relevant stakeholders during the different stages of project cycle. Agencies
working for environmental and social aspects willalso be informed at both local and national level about the
ongoing and planed activities, to identify jointly appropriate protective or corrective measures. Subprojects will
adopt the following approaches to make information accessible to all the concerned stakeholders throughout the
project cycle. Project documents will be disclosed in the Nepali language, and if relevant in the local languages.
• Mass Media: Local media like newspaper, radio and TV will be used to broadcast any information
regarding the project.
• Meeting/Workshops: Meetings and workshops will be held to disseminate the information.
•Distribution of project document: Project related information materials in Nepali version will be
distributed prior to each construction work to local officials, PAPs and other concerned offices like
Municipality, Ward, Tole Committee etc. Such information will among othersinclude project description,
project benefits and impacts, entitlements, implementation arrangements, entitlement frameworks as well
as various periodic information sheets on compensation entitlements, project time frames etc.
An information centre will be established during implementation stage at the municipality level to disseminate all
the documents related to the project activities. Based on the policy on public information disclosure, PCO and
Municipality will also disclosethe information through its website.
56
8.5. Adapting stakeholder consultions to COVID-19
The Government of Nepal has imposed various measures to mitigate the spread of COVID-19 including restrictions
on non-essential movement, requirements for social distancing, and prohibitions on social gathering. Other
measures have also been recommended by health organizations to limit the spread within countries. These measures
impact the ability to undertake stakeholder engagement activities in the manner originally envisaged under the
NUGIP project. Given these measures, some practical suggestions have been provided below to undertake citizen
engagement and stakeholder participation activities.It is key that these mechanisms involve the participation of the
local government to help build and maintain trust between citizens and the local government, and to continue to
build the capacity of local governments. Adaptive and sustained citizen engagement is crucial to ensuring that
projects continue to be planned and implemented during this period, whilst ensuring successful efforts in
combatting COVID-19.
Considerations for adapting engagement activities
• Review the current approach and methodology for engagement activities and assess the adjustments
required: The PCO should assess the feasibility of undertaking engagement activities, including assessing
the potential risks of virus transmission and in consideration of current advice and restrictions of Government
of Nepal. Questions that should be considered include:
o Which activities are critical and cannot be postponed?
o What is the level of proposed engagement, including location and size of gatherings, frequency of
gatherings, and groups of stakeholders?
o What is the risk of virus transmission for carrying out these engagements?
o What is the level of ICT usage amongst the stakeholders, and which communication channels can be
used most effectively?
• Identify and connect with potential local partners for supporting in CE activities, including NGOs and
CSOs supporting particular vulnerable groups such as womens and Dalit groups. This may require connecting
with different local partners to those envisaged under the project. These local groups may be able to: provide
insights into the local context on the ground and current conditions; support in information dissemination on
both project information and COVID-19 prevention and precautions; serve as communication link between
project teams and local communities
• Engage local mobilizers or social influencers to support engagement: Individuals or organizations
engaged on the ground in the community can serve as strategic partners that would function as social
mobilizers and intermediaries for the project team. These could include trusted local individuals or social
influencers, for example, youth social influencers, respected elderly persons, representatives of indigenous
groups or women’s groups. They can facilitate consultations and community engagement when public
gatherings are restricted, or consultants cannot work safely with community members. An effective
engagement approach may be for project teams to convey information to the social influencers through ICT
tools, who can then use traditional methods to communicate with local communities.
• Special attention should be paid to vulnerable groups: Vulnerable groups are likely to be
disproportionately impacted by COVID-19 and may have further limitations in accessing information and
being engaged. The project should assess how COVID-related impacts might further restrict the ability of
vulnerable groups to engage and participate in project consultations. Strategic local partners can be key to
ensuring full engagement of vulnerable communities. The local community mobilizers noted above can be
instrumental in identifying and engaging with these groups.
• Broaden the channels for information dissemination using ICT channels where appropriate: Identify
the project information that needs to be disseminated and assess the available channels for distribution. Note
that channels for dissemination of project information can also be leveraged for sharing COVID-19 related
information where appropriate. Identify the extent to which ICT communication channels are accessed by
local communities to draw on these mechanisms. These may include Viber, WhatsApp, and Facebook groups
and other social media and online channels. ICT channels can also provide a useful feedback mechanism for
COVID-related queries and concerns.
• Diversify traditional transmission media(including radio, TV) for information dissemination to
maximise the reach of communications, particularly where other forms of communication such as meetings
and consultations may not be possible, and where communities do not have access to ICT tools. If radio
stations are not already a channel for information dissemination, consider delivering project information via
local radio, given the high rates which local communities in Nepal listen to radio. Other possible channels
57
could include distribution of messages via television, and using loudspeakers to travel through wards to
disseminate project-related information (where feasible).
• Adapt COVID protocols in consultation meetings: For consultations that cannot be postponed, and which
cannot be held virtually, some considerations:
o If smaller meetings are permitted, conduct meetings in small-group sessions, ensuring that meeting sizes
adhere to local regulations, and for example, space members at least 1.5 metres
o Project team membersshould express their understandings on social behaviour and good hygiene
practices, and that any consultations are preceded with the procedure for articulating such hygiene
practices
• Undertake consultation meetings virtually where feasible:The project should consider the following for
those consultations which cannot be postponed, and where all participants have proper ICT access and can be
notified in advance regarding timing and format of meetings. Some considerations:
o Where all participants have proper ICT access, deploy online meeting facilities, where large meetings,
workshops and consultations are essential, such Webex, Skype and Zoom. In the case of low ICT access,
audio meeting means can also be effective used (including Viber and Whatsapp)
o Vulnerabilities of participants need to be considered to ensure that vulnerable participants are not
disadvantaged by being unable to connect.
o Where direct consultation and engagement with beneficiaries is required, such for completion of
resettlement activities or indigenous peoples plans, identify direct channels for communication with the
affected household via a combination of email messages, text messages, dedicated phone lines
• Review the range of digital platforms which can be drawn upon for completing CE requirements such as
data collection: In-person data collection methods can be substituted by remote data collection methods, which
take into account limitations related to ICT access and literacy of community members. SMS surveys are a
common way to collect community-level data required to complete safeguard document requirements.
Customized SMS-based surveys can gather data from remote villages and traditionally hard-to-reach places as
it requires only access to mobile numbers of local users, without dependency on data plans or internet access.
Local partners and social mobilizers, as discussed above, can assist in obtaining mobile numbers.
58
9. GRIEVANCE REDRESS MECHANISM
An accessible and responsive complaint management process is an important part of any stakeholder engagement
strategy. A Grievance Redress Mechanism will accessible wherein all project stakeholders willbe provided with a
forum to lodge complaints regarding any aspect of the land acquisition, compensation, resettlement requirements,
hygiene, pollution, safety and any other project-related issues. The affected persons will have access to all levels of
grievance redress procedures.
9.1. Existing Grievance Redress Process
At present, there are several mechanisms for raising grievances including with the ward-level mediation centres and
with themunicipality’s judicial committee. Currently, grievances including environmental and social issues are
generally submitted directly with the judicial committee (NyayikSamiti).NyayikSamiti is a three-member
committee comprisingthe Deputy Mayor and two persons from the executive committee or ward11. Sometimes, the
views of environmental and social development sectionis taken into consideration to inform the decision-making
process if the committee feels relevant. The grievance can also be submitted to Chief Administrative Officer (CAO)
at Municipality level or to Ward Chairperson at Ward Level. Beside judicial committee, the municipalitiesalso have
a separate kiosk to register gender-based violence related grievances.
The project should drawn upon mechanisms established by local municipalities for receiving and addressing
grievances, to help strengthen these local systems and to support and build the capacity of local governments in
receiving and addressing grievances. As part of developing sub-project ESIAs, existing mechanisms for receiving
and addressing grievances will be identified and assessed. Grievants will first raise their grievances with the ward-
level mediation centre before going to the judicial committee.A grievance officer assigned to the municipality level
will also have the proper knowledge on the issues. The GRM mechanism as well as its procedures will also be
detailed in the Project Implementation Manual (PIM). The decision as to whether the case is addressed by the
judicial committee, or by the ward level GRM, is decided by the municipality Grievance Officer. The Grievance
Officer will keep all detailed documentation regarding the grievance with proper verification to answer how and
when the grievance was reported and addressed.
9.2. Establishing Grievance Redress Mechanism
The sub-project will build on existing grievance redress procedures. In the absence of any mechanism to address
grievances at the municipality level, a grievance redress mechanism will be established.
- The firstlevel will be set up at the Ward level. The staffing of the grievance redress committee will include
Ward Chairman, Environmental and Social Officers from respective Municipality
- the second level will be at the municipality level and will comprise the Nyayik Samit. The Nyayik Samiti
will discuss the environmental and social concern with E&S section/department of municipality to redress
grievance pertaining to gender, vulnerable community, and other social and environmental issues in
transparent and effective manner.
- the third level will be at the PCO level comprising members from the PCO. The teams who will be
engaged as the monitoring unit for ESMP, RAP, VCDP implementation for various subprojects, can be the
part of the committee.
9.3. Channels and procedures for receiving and addressing grievances
Grievances if any, may be submitted through various mediums, including in person, in written form to a noted
address, through a toll-free phone line or through direct calls to concerned officials, and emails. PCO will appoint a
person (Operator) at PCO- Kathmandu to receive such calls and receive online messages. The person (Operator)
based on nature of complaint, will forward the same to the concerned GRC at Ward Level (to Ward Chairman). A
ticket or a unique number will be generated for all such calls, messages and letters.
The complainant will follow up based that unique number with Operator at PCO-Kathmandu. All complaints will
be responded to within two weeks at any level. In case a response is not received fromthe first level within two
weeks, the complaint will be escalated to next level and the complainant will be notified accordingly. If a complaint
11 As per Article 221 (Subsection 1) of the Constitution of Nepal 2015, the municipalities are required to establish a separate act
or regulation which will outline the roles and responsibilities of the judicial committee.
59
remainsunaddressed at 1st and 2nd GRC levels, within maximum 30 days after registering the compliant, it will be
elevated to 3rd level of GRC at PCO level. GRC-PCO within 7 days of time willinstruct the concerned GRC at
Municipality level to arrange for a hearing within maximum 5 days of time. Effort will be given by all level of
GRCs to conduct hearing and resolve the concern at their level up to the satisfaction of complainant within the
stipulated timeframe. After conducting hearing at any level of GRC, the decision should be communicated to the
complainant within maximum 30 daysof time in writing.
All local contact information and options for complaint submission willbe available on site, on Toles, Wards,
Municipalities, PCO on information boards and municipality websites. A half yearly report on grievance redress by
the subproject project willbe prepared and sent to Municipalities’GRCs by Wards’ GRCs and ultimately to GRC of
PCO. The PCO will forward the same to World Bank.
Figure 9-1: Grievance Redress Process
9.4. Functions of GRCs
The functions of grievance mechanism include but not limited to:
• To redress grievances of community / beneficiaries / project affected persons (PAPs) in all respects
• Address complaints relating to rehabilitation and resettlement assistance and related activities
• Hear grievances from workers involved in the project at any level or phase
• Receive complains and issues related to environment, R&R and other matters relevant to the project
GRC will give its decision/verdict within 30 days after hearing the issues/concerns of the aggrieved person. The
final verdict of the GRC will be given by the Head of GRC in consultation with other members of the GRCs and
will be binding to all other members.
GRM Register/Operator
(at PCO)
Online Grievance
• Toll Free No
Offline Grievance
from Tole or Subproject
Level
Wards 1st Level GRC
Municipality: NyayikSamiti 2nd Level GRC
PCO 3rd Level GRC
15 Days Max.
Hearing of Grievance
7 Days Max.
Verdict by GRC
30 Days Max.
15 Days Max.
5 Days Max.
60
An indicative list of grievance, which will be addressed under the project are furnished below-
i. Rehabilitation &resettlement and compensation issue
ii. Loss of livelihood
iii. Access to resource /utility/facility
iv. Ambient air and noise quality
v. Impact on water quality/resource
vi. Grievance from vulnerable community
vii. Gender related issues
viii. Labor-related matters
ix. Safety risksrelated to the project
9.5. Other Mechanism for Grievance Redress
All grievants will have the option to approach the court / judiciary, or the World Bank’s Grievance Redress
Service12 in case he or she is not satisfied with the verdict provided by the project-level GRCs.
9.6. GRM considerations for the COVID-19 context
Restrictions and guidance on social distancing and travelling may impact the ability of individuals and groups to
submit grievances.Some factors to consider when adapting grievance redress to the COVID-19 context:
• The grievance mechanisms used should be reviewed to check that they are currently functioning and capable
of receiving grievances, given potentially restrictions on being able to access ward offices or project sites to
raise grievances
• Channels for receiving grievances should be reviewed to maximise ways to submit and response to
grievances. For example, whilst the project may envisage communities going to ward offices to submit
grievances, the project should consider establishing a phone line for people to call in concerns. Where
feasible, ICT-related options such as SMS or via email should be implemented and communicated
• Members assigned to receive and respond to or escalate grievances should be taught on how to respond to
grievances related to COVID-19
12http://www.worldbank.org/en/projects-operations/products-and-services/grievance-redress-service#3
61
10. INSTITUTIONAL ARRANGEMENT FOR ESMP IMPLEMENTATION
10.1. Institutional Assessment for E&S Sections/Departments
10.1.1. Existing Institutional Capacity
In Nepal, the municipalities usually have a separate social development sectionand a separate environmental
section. The municipalities like Birtamod, Damak, Sundarharaicha, Mechinagar, Itahari, Rajbiraj, Triyuga,
Dhankuta, Pokhara, Putalibazar, Tansen, Tilottama have environmental &social development department. Whereas
Vyas has only Social Development Department.Urlabari, Baglung,Ramgram municipalities do not have
Environmental and Social Development Department. To ensure that the investment sub-projects are efficiently
implemented, delivered on time, and completed in accordance with environmental and social safeguards
requirements, technical assistance will be provided by design and supervision consultant (DSC) to the concerned
municipalities. DSC will deploy engineering, procurement, E&S safeguards and other technical specialists to work
closely with ULG municipal engineers and other technical staff to design and supervise the implementation of sub-
projects in a socially and environmentally sustainable manner.
Roles and Responsibilities of Environmental & Social Development Departments
The Environment Department of municipalities are mostly engaged in plantation, maintenance of public parks,
greenery promotion, landscaping, pond conservation, conservation of religious trees, gabion filling, landslide
protection, solid waste management etc. In addition, theItahari Municipality also looks after issuance of ‘Pollution
under Control’ Certificate for various operational industries as well.The activities of Social Development
Departments include registration of vital events (Birth, Death), targeted group development (Women, Child,
Indigenous People, Sr. Citizen, Differently abled), need-based skill development programs through 3rd parties
(vegetable farming, cattle-poultry farming, handicrafts, driving, plumbing, mobile repair, computer training,
mushroom farming etc.), co-ordination and facilitation with ToleVikas Committees, issuance of senior
citizen/differently abled cards, etc.
Involvement in preparation/review of IEE/ESIA/ESMP Reports
Some of the municipalities like Damak, Sundarharaicha, Triyuga, Dhankuta, Pokhara, Vyas, Putalibazar, Tilottama
have prior experience of preparing ESIA, ESMP, RAPs, through external agencies. However, the staff of
Environment and Social Development department havenot been involved in the preparation or review of ESIAs,
ESMPs, RAPs, etc., as such. Only in the case of Dhankuta municipality one staff of Social Development sectionwas
involved in review of ESIA/ESMP report for UGDP Project (ADB funded). Similarly, the Environmental Officer of
Itahari municipality has prior experience of conducting IEE/ESIA-ESMP studies. Thus, capacity of the preparation,
implementation and monitoring of environmental and social safeguards issues is limited in the participating
municipalities.
Involvement in process of decision making for project Execution
As indicated by the staff of the Environment and Social Development Department of various Municipalities, they
are not engaged by the municipality in project planning process. As per the practice, after project finalization, the
responsibility is handed over to concerned user committees and they take charge of execution, monitoring of the
project.
Experience in working Multilateral Funded Project
Most of the staff of Environment and Social Development Department do not have prior experinece multilateral
funded project. Only the Environmental Officer of Itahari and one Staff of Social Development Department in
Dhankuta, were engaged in preparation/review of ESIA reports (both for ADB funded Projects).
A detailed statement on assessment of Institutional capacity is furnished in Appendix- H
10.1.2. Capacity Development
Role of UDSTs in process of Capacity Development
In order to deliver technical assistance to ULGs for their institutional strengthening, NUGIP will deploy two
regional Urban Development Support Teams (UDSTs), each of which will be responsible for working with a cluster
62
(Eastern and Western) of ULGs. One UDST (Eastern Cluster) will be based in Biratnagar and the second UDST
(Western Cluster) will be based in Pokhara.
Each UDST will consist of a team of full-time professionals to provide TA inputs that are aimed at strengthening
the overall ULG management capabilities. These inputs will be in areas such as urban and investment planning,
citizen engagement and gender inclusion, procurement, financial management, budgeting and budget execution,
asset management (O&M, etc.), E&S safeguards and other issues.UDST members will provide regular mentoring,
facilitation and on-the-job support to the ULGs within their respective clusters. UDSTs, however, will be
responsible for coordinating, quality assuring and backstopping such formal ICD processes and for providing advice
on the substance of training sessions, workshops and the like.
Apart from the regular mentoring and on-the-job support functions, each UDST will be responsible for drawing up
an annual TA plan and budget for training and other formal activities in its respective cluster. Annual plans willbe
based on needs identified by each ULG; such plans would ensure that training and other TA activities are efficiently
organized. These annual plans and budgets will be submitted to and discussed with the PCO by each UDST. Once
agreed, the PCO will allocate funds and then procure trainers/consultants. Implementation of annual cluster plans
for TA activities would be coordinated and overseen by the PCO and the UDSTs (for their respective cluster).
Institutional Capacity Development at Municipality Level
Urlabari, Baglung, Ramgram Municipalities and Vyas Municipality are requiredto create a Social Development
Department and Environment Department respectively, prior to sub-project identification.
Capacity Development Training Requirement
The following trainings are recommended for effective implementation of ESMF.
Table 10-1. Capacity Development Training Requirement
S.
No.
Nature of Training Targeted Entity Responsibility
1 Objective, purpose of ESMF
Process of ESMF implementation
PCO, DSCs, Environment & Social
Departments of Municipalities
World Bank, PCO
2 Understanding of ESIA/ESMP as
decision making tool for sustainable
project development
PCO, Environment & Social
Departments of Municipalities
PCO through UDST’s
(training to be given by
external experts)
3 Awareness training on probable
E&S concern pertaining to NUGIP
sub-projects
PCO, Environment & Social
Departments of Municipalities
PCO through UDST’s
(training to be given by
external experts)
4 Awareness training on
Environmental & Social Safeguard
Laws of GoN and World Bank’s
operational policy
PCO, Environment & Social
Departments of Municipalities
PCO through UDST’s
(training to be given by
external experts)
5 Process of land transfer in case of
involuntary resettlement
PCO, Social Departments of
Municipalities
PCO through UDST’s
(training to be given by
external experts)
6 Awareness training on occupational
Health and Safety issues relevant to
various phases (preconstruction,
construction, operation) of NUGIP
sub-projects
PCO, Environment & Social
Departments of Municipalities
PCO through UDST’s
(training to be given by
external experts)
7 Awareness training on purpose of
stakeholder engagement at various
stages of sub-project
PCO, Environment & Social
Departments of Municipalities
PCO through UDST’s
(training to be given by
external experts)
10.2. Proposed Institutional Arrangement
The institutional setup plays a vital role in successful implementation of Environmental and Social Safeguards
measures. The MoUD, Nepal has setup a Project Coordination Office (PCO) under DUDBC for NUGIP in
Kathmandu. PIU in each municipality is established for the implementation in the field. To ensure that the
investment sub-projects are efficiently implemented, delivered on time, and completed in accordance with
environmental and social safeguards requirements, technical assistance will be delivered through a Design and
63
Supervision Consultancy (DSC). DSC will deploy engineering, procurement, E&S safeguards and other technical
specialists to work closely with municipal engineers and other technical staff to design and supervise the
implementation of the sub-projectsin two clusters. The role of PIU/DSC includes implementation of ESMP, RAP,
VCDP, etc. The PCO with support from Project Management Support Team (PMST) will review implementation
support of environmental and social safeguard studies/ management plan prepared by PIUs/DSCs.
At subproject level, the contractor will be responsible for ESMP implementation. Each municipality will need
Environmental and Social Development (ESD) expert to review IEE/ESIA-ESMP, RAP-ARAP, etc. The E&Ssocial
safeguard specialists of DSCs will regularly visit both cluster municipalities and work closely with its technical
staff to ensure project implementation in accordance to World Bank’s safeguard standards. The ESD will bepart of
PIU. The DSCs provide municipalities’ technical staff with on-the-job training and mentoring. The role of DSC will
also include ensuring compliance of pertaining laws, policies, regulation for all sub projects, coordination and
liaising with government stakeholders as well as the World Bank with respect to various E&S issues. The PCO will
have overall responsibility to ensure compliance withpertaining laws, policies, regulation for all sub projects, and
development of sub-projects in sustainable way and allocation of fund for institutional capacity development. The
reporting of the PMST on the monitoring and evaluation on the project’s safeguard performance to WB is done
internally by the PCO and externally by the WB experts. The capacity of Municipalities isattached in the
Annex.
.
Figure 10-1.Coordination of Proposed Project Implementation Mechanism
Project Coordinating Office (PCO-e.g.
DUDBC)
Project Mgmt Support Team (PMST)
Municipalities (in East & West Clusters)
Design & Supervision Consultancy (DSC)
Municipals Project Implementation Unit
(PIU-e.g ESD)
64
Appendix A: Land use map of 17 Municipalities
Land use map of 17 Municipalities showing various physiographic features and drainage patterns
A.1. Birtamod&Mechinagar
A.2. Damak&Urlabari
65
A.3. Itahari&Sundarharaicha
A.4. Rajbiraj
66
A.5. Triyuga
A.6. Dhankuta
67
A.7. Pokhara
A.8. Byas
68
A.9. Putalibazar
A.10. Baglung
69
A.11. Shuklagandaki
A.12. Tansen
70
A.13. Ramgram
A.14. Tilottama
71
72
Appendix B: Consultation with municipalities
1. Birtamod
Attendance Sheet from the stakeholder consultation
73
74
75
Pictures from stakeholder consultations
76
2. Damak
Attendance Sheet for the consultations
77
Pictures from the stakeholder consultations
78
3. Urlabari
Attendance sheet for the stakeholder consultations
79
80
Pictures from stakeholder consultations
81
4. SundarHaraicha
Attendance sheet for the stakeholder consultations
82
5. Mechinagar
Attendance sheet for the stakeholder consultations
83
6. Itahari
Attendance sheet for the stakeholder consultations
84
Pictures from the stakeholder consultations
85
7. Rajbiraj
Attendance sheet from the stakeholder consultations
86
Pictures from the stakeholder consultation
87
8. Triyuga
Attendance sheet for the stakeholder consultation
88
Pictures from stakeholder consultation
89
Attendance sheet for the stakeholder consultations
90
9. PokharaLeknath
Attendance sheet for the stakeholder consultation
91
92
Pictures from the stakeholder consultation
93
10. Vyas
Attendance sheet for the stakeholder consultation
94
Pictures from the consultation
95
Putalibazar
Attendance sheet for the stakeholder consultation
96
97
Pictures from the stakeholder consultation
98
11. Baglung
Attendance sheets for the stakeholder consultation
99
100
Pictures from the stakeholder consultations
101
102
12. Shuklagandaki
Attendance sheet for the stakeholder consultation
103
13. Tansen
Attendance sheet for the stakeholder consultation
104
Pictures from the stakeholder consultation
105
14. Ramgram
Attendance sheet for stakeholder consultation
106
Pictures from stakeholder consultation
15. Tilottama
107
Attendance sheet for the stakeholder consultation
108
109
Pictures from the stakeholder consultation
110
Appendix C: Templates for Environmental &Social Screening Checklist /
Environment and Social Impact Assessment (ESIA) / Environment and Social
Management Plan (ESMP)
A. CHECKLIST FOR ENVIRONMENTAL AND SOCIAL SCREENING
Project Details
Sub Project Title
Nature of Project (New/ Expansion/Redevelopment/Upgradation
Brief about Project Components
Project Municipality
Project Ward/s
Terrain- flat, ridge, undulating, Hilly, valley etc.
Current land use (agriculture, grazing, barren, forest, settlement, road etc.
Type Quantity of construction materials/Resource needed
Quantity of debris that needs to be disposed
Any hazardous materials mixed with debris
Environmental Aspects
Checklist for Environmental Screening
S.
No Particulars Yes No
Can’t
Say Remarks
1. Is the site vulnerable to major natural or induced hazards
such as: Landslides, Flooding, Storm surge, Severe wind
damage, Earthquakes, Fire, Explosion, Other (specify)
2. Is the project area adjacent to or within any of thefollowing
environmentally sensitive areas?
• Cultural heritage site (historical, religious,
traditional, or cultural significance)
• Protected Area (National Parks, Wildlife Reserve,
Hunting Reserve, Conservation Areas, and Buffer
Zones etc.)
• Wetland/Ramsar Site/Simsar
• Forest
• Special area for protecting biodiversity/interest
• Breeding/nesting ground of wildlife/occurrence of
migratory species
• Migration route/Wildlife corridor
• Any site of national or international importance
3. Likely impact on trees (including Timber & fruit
bearing)and vegetation cover
4. Possibility of degradation of land and ecosystems of
surrounding?
5. Is the project area densely populated?
6. Heavy with development activities/big industries nearby &
type?
7. Alteration of surface water hydrology of waterways due to
111
S.
No Particulars Yes No
Can’t
Say Remarks
the project resulting in increased sediment in streams
affected by increased soil erosion at construction site?
8. Chance of deterioration of surface water quality due to silt
runoff and sanitary wastes from worker-based camps and
chemicals used in construction
9. Does the sub project requires significant extraction
ofsurface or ground water?
10. Increased risk of water pollution from oil, grease, fuel spills
and other materials
11. Impact on water quality due to release of sewage/sludge?
12. Possibility of flooding due to sewage
13. Possibility of increased air pollution during
preconstruction/construction/operation phase?
14. Other pollution concerns relating to inconveniences in
living conditions that may trigger cases of upper respiratory
problems?
15. Risks and vulnerabilities related to occupational health and
safety due to physical, chemical, biological hazards during
project construction and operation
16. Noise and vibration due to blasting and/or other civil
works?
17. Possibility of poor sanitation and solid waste disposal
18. Creation of temporary breeding habitats for diseases such
as those transmitted by mosquitoes and rodents?
19. Accident risks associated with pre construction,
construction & operation phases of project
20. large population influx during project construction and
operation that causes increased burden on social
infrastructure and services (such as water supply and
sanitation systems)
21. Risks to community health and safety due to the transport,
storage, and use and/or disposal of materials such as
explosives, fuel and other chemicals during construction
and operation?
22. interference with other utilities and blocking of access to
resource/utility
23. Generation of solid waste and/or hazardous waste during
construction/operation of project?
24. Conduct of medical health screening and testing to identify
the presence of suspected covid-19 positive individuals
among the construction workers in the workers’ labor
camps or among the community members that might infect
the construction workers
112
Social Aspects
Checklist for Social Screening
S. No. Particulars Details
1 Proposed Site Location-
a. Land requirement for the project
b. Landownership of the project area: Govt. / Private lands
c.
Is the project requires acquisition of Govt. land/structures?
If yes please mention the area of land, number of affected structures,
Households
d. Present use of Govt. Land that will be used for the project activities
with Persons/Households using
e.
Is the project requires acquisition of private land/structures?
If yes please mention the area of land, number of affected structures,
Households
f.
Present use of Govt. Land that will be used for the project activities
with Persons/Households using
✓ Agricultural purposes
✓ Residential purposes
✓ Commercial purposes
✓ Other purposes (Indicate)
g. Is the project requires relocation of encroachers/squatters
If yes please elaborate number and nature
h.
Is the project requires relocation of community facilities/Govt.
establishment or any object that are of religious, cultural and
historical significance
i.
Proposed project located in an area where residents are-
• All Mainstream
• All Indigenous peoples
• Majority Mainstream or Non-indigenous peoples
• Majority Indigenous peoples
2 Potential Social Impacts- Will the Project cause
a. Involuntary resettlement of people? (physical displacement and/or
economic displacement)
b. Impacts on the poor, women and children, Indigenous Peoples or
other vulnerable groups?
c. Will community facilities require relocation?
d. Will the sub-project disturb any traditional activity on adjoining or
nearby?
e. poor sanitation and solid waste disposal in construction camps and
work sites
113
S. No. Particulars Details
f. Possible transmission of communicable diseases (such as STI's and
HIV/AIDS) from workers to local populations?
g.
Large population influx during project construction and operation that
causes increased burden on social infrastructure and services (such as
water supply and sanitation systems)?
h. Social conflicts relating to inconveniences in living conditions where
construction interferes with preexisting roads
i. Describe any other impacts that have not been covered in this
screening form
j. Describe alternatives, if any, to avoid or minimize displacement from
private and public lands
k. RAP/ARAP Requirement
B. Category B Project’s ESIA Requirement
The potential negative and positive direct or indirect impacts and provide clarity on issue, which needs to be
investigated under Category B EA type (for higher impact category requires ESIA, for medium impact category
requires abbreviated EMP and for lower impact category require Best Environmental Practices-BEP).
Medium to High Impact Category B project: NUGIP Intervention Requiring ESIA and ESMP
Sub projects under this category havepotentially major Impacts of (CAT B range type); complex issues; likely need
for significant mitigation and monitoring. The indicative sub projects under this category include:
• Construction of sanitary landfill
• Construction of new waste water treatment plant, water supply projects
ESIA Template
• Executive Summary
• Introduction about sub project (nature, type, project location, site characteristics : physical, biological,
socio-economic)
• ESIA methodology
• Environmental and Social Baseline
• Legal and Regulatory Framework
• Environmental and Social Screening, Impact Identification, Prediction, and Management
• Resettlement Action Plan (RAP), Gender Action Plan, VCDP (as applicable)
• Environmental and Social Management Plan
• Information Dissemination and Communication Plan
• Appendix
Low to Medicum Impact Category B project: NUGIP Intervention Requiring ESMP
NUGIP sub projects which don’t require ESIA,but may involve civil construction works with some minor to
moderate degree of environmental and social issues.The sub projects under this category will haveModerate
impacts; straightforward issues; likely need for some routine mitigation and monitoring
Such NUGIP sub projectsrequire ESMP. The format and table of content for preparing ESMP is included below.
The following process will be followed to prepare the ESMP:
114
C. Environment and Social Management Plan (ESMP)
Phase I: Preparation of ESMP. The ESMP is an overall plan, which addresses the minor to moderate safeguard
issues arising from implementation of the NUGIP sub projects and suggests a strategy and action plan to mitigate
the adverse environmental and social impacts and enhance the beneficial impacts of the interventions. The EMP for
such sub projects consists of the set of mitigation, monitoring, and institutional measures to be taken during
implementation and operation to eliminate adverse environmental and social impacts, offset them, or reduce them to
acceptable levels. The plan also includes the actions needed to implement these measures. An EMP is required for
the following indicative sub projects
• Existing road upgrading related sub projects
• Waste to energy sub project projects
• Renovation and upgrading of sewerage and water supply projects
The ESMP includes:
• Site Specific ESMP Activity Schedule, including cost for implementation of mitigation measures.
• Site Specific ESMP Monitoring Schedule, including monitoring responsibility delineation.
• Cost Estimate for EMP Monitoring. This can include cost required for capacity building and training
activities basis as required or stated in activity
The PCO with external support (as required)will prepare the ESMP in the prescribed ESMP format incorporating all
information and data.
115
ESIA TEMPLATE
TABLE OF CONTENTS
CHAPTER 1
PROJECT DESCRIPTION
1. Introduction
1.1 Background
1.2 Project Scope
Project Activities
The project activities may be categorized mainly into two phase which are activities in the Pre- Construction,
Construction and Operational Phases.
CHAPTER 2
2.1 Scope of Environment and Social Management Plan (ESMP)
2.1 Objectives of Environment and Social Management Plan
The basic objectives of the ESMP are to:
• to ensure that all mitigation measures and monitoring requirements will actually be carried out at different
stages of project implementation and operation - pre-construction, construction and operation and
maintenance;
• recommend a plan of action and a means of testing the plan to meet existing and projected environmental
problems;
• establish the roles and responsibilities of all parties involved in the project’s environmental management;
• describe mitigation measures that shall be implemented to avoid or mitigate adverse environmental
impacts and maximizing the positive ones;
• ensure implementation of recommended actions aimed at environmental management and its enhancement;
and
• ensure that the environment and its surrounding areas are protected and developed to meet the needs of the
local people, other stakeholders and safeguard the interests of the common people
• ensure requirements of RAP, GAP, VCDP (as applicable) in the sub project context of NUGIP.
2.2 Implementation of ESMP
2.3 Project Impacts
The anticipated impacts due to project in and mitigation measures are mentioned in table 1 attached with this
document.
2.3.1 Anticipated Environmental Impacts and Mitigation Measures
Environmental impacts on the physical, biological, and socio-economic and cultural environments during the pre-
construction, construction and operation and maintenance phases are discussed here in detail with the mitigating
measures.
The summary of the anticipated environmental impacts and the mitigation measures are given in matrix form
attached with this document
2.3.1.1 Pre-construction Phase
a. Environmental impacts due to project design
116
2.3.1.2 Construction Phase
a. Environmental impacts due to project construction
i. Physical Environment (Examples)
Water and land pollution
Pollution due to air, noise and vibrations
ii. Biological Environment
iii. Socio-Economic and Cultural Environment
Reinstatement of damaged community services and infrastructure
Influx of outside workforce, money and unwanted activities
Occupational Health and Safety (OHS)
Traffic management
2.3.1.3 Operational Phase
3.0 Mitigation Measures:
The mitigation measures shall be designed during the construction and operation phases of the project to minimize
the adverse environmental impacts. The mitigation measures along with the item wise mitigation cost are prepared
in ESMP. A sample ESMP is shown below.
The envisaged impacts due to implementation of NUGIP component could be grouped into positive and adverse
impacts. The goal of mitigation measures is to maximize the positive impacts and minimize or reduce the adverse
impacts.
The proposed mitigation measures for predicted adverse impacts could be grouped into three categories as Physical,
Biological, Socio-economic and cultural environment. Such impacts could be further classified as impacts during
the construction stage and operation stage.
3.1 Mitigation Cost: The environmental and social mitigation cost in ESMP are basically related to activities
associated with the physical constructions, environmental conservations, health and safety and awareness raising.
The construction related mitigation measures are linked to the project's DPR and such costs are included in
construction Bill of Quantity. For such mitigation measures, the ESMP shall clearly highlight "included in project
BoQ" and ensure that DPR has included such cost in BoQ. For other mitigation costs like environmental and social
enhancement, awareness raising etc, the ESMP report should include the cost based on the district rates, or norms of
the government. Such mitigation cost should of clearly included in mitigation cost. This type of mitigation cost will
apply for construction and operation phases of the project.
ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN (ESMP)
Environmental management actions to be undertaken and to be adopted for the realization of environmental
mitigation and enhancement for construction and operation phases are presented in the table below. The
Environmental Mitigation and Enhancement Management Plan (EMEMP) which is part of the ESMP describes
impacts, description of enhancement/mitigation action required, individual or agency responsible, national
standards and guidelines, timing of actions, responsible authority, and tentative financial requirements.
Site-Specific ESMP Matrix
Name of
Sub
Project
Location Env Issues/
Significance
Likely
Potential
Impacts
Mitigation
Measures
BoQ/
Cost
Time of
Action
Responsib
ility
Sample Environmental Mitigation Measures
117
CONSTRUCTION PHASE IMPACTS
Physical Environment
S.N Identified Impacts Environment Mitigation Measures
1 Impacts associated with management of
excavated materials
The excavated materials shall be used as construction material
(as applicable). The unused materials will be sold to needy, non-
sellable items shall be disposed properly in identified areas.
2 Impacts of air pollution (particularly
dust) and its impacts on surrounding
environment
Vehicle speed control and sprinkling of water in road and in
construction site in a regular basis. Use of old and worn out
vehicles shall be avoided to control air pollution.
The construction material shall be covered during the
transportation of materials.
3 Impacts related to noise created by the
vehicle used for the transportation of
construction material
Night time construction work shall not be allowed (in general
conditions, for urgent work local community should be informed
and consent should be obtained). Vehicle speed control and
maintained vehicle shall be used. Use of old and worn out
vehicles shall be avoided to control noise pollution.
4 Impacts related to stockpiling of
construction materials
Construction material shall be stored/stockpiled in designated
area (fenced and secured, covered).
5 Impacts related to traffic obstruction and
traffic management
Adequate traffic signs, warning signs, and scheduling of
transport operator in off office hours to avoid traffic congestion
and inconvenience to people.
6 Possibility of contamination of water
source due sub project construction
activities.
Regular water sprinkling in approach road, construction sites.
Discourage use of direct discharge of water in to water bodies
without proper treatment.
7 Impacts related to health and safety of
workers, and visitors /worshippers
Social distancing during construction and medical testing to
determine the presence of covid-19 positive individuals among
the constructions workers or in the communities where the sub-
projects are located
Use of safety signs in places, fencing of active work
places/construction sites provision of PPE to workers.
8 Impacts related to obstruction and
disturbances to visitors/worshippers of
temple/shrine
Adequate signs shall be used, construction materials shall be
stored in designated areas with proper fencing, and construction
work shall be planned in such a way that it won’t stop
worshippers.
9 Impacts related to liquid waste, solid
waste, and sewage management during
construction phases of the project
Implementation of solid and liquid waste management
segregation, collection and treatment technology. Prohibition of
littering and illegal dumping of waste in premises and its
surroundings.
Establishment of adequate hygiene and sanitation facilities
Biological Environment
118
S.N Identified Impacts Environment Mitigation Measures
1 Impacts related to disturbance to flora
and it’s cutting/removal during
construction period
Trees should be protected and its cutting/removal is strictly not
recommended.
Socio-economic, Cultural and Archaeological Environment
S.N Identified Impacts Environmental Mitigation Measures
1 Disturbance to local residents due to
obstruction to their access, pollution etc
Prior information dissemination to the public regarding the
nature, schedule of work in advance
Timely completion of work to minimize disturbance
Adherence to pollution control measures as elaborated above.
2 Pressure on local infrastructures due to
influx of workers
Record keeping of workers
Provide orientation and training to workers for maintaining
social harmony, prohibition of ill social behaviors (alcohol,
gambling etc)
Local people shall be engaged in construction as per their skills
and qualifications.
3 Obstruction to
worshippers/pilgrims/visitors for
entering temple premises during
renovation of temple
The access shall be provided to the priest of the temple/shrine for
certain hours of the day. Due to this arrangement, the priest and
visitors can visit the temple.
Operation Phase Mitigation Measures
• Physical Environment
• Biological Environment
• Socio-economic environment
ENVIRONMENTAL AND SOCIAL MONITORING MANAGEMENT PLAN
Three types of monitoring are envisaged in the plan, namely: Baseline Monitoring, Compliance Monitoring and
Impact Monitoring. The compliance monitoring comprises two parts; the first is the compliance to the enhancement
actions and second compliance to mitigation actions including the corrective actions issued.
The impact monitoring in the plan relates to only those measurable indicators in the socio-economic,
Cultural/Physical, Chemical and Biological environments. For each of the monitoring indicators, monitoring
methods, frequency of monitoring, responsible parties along with the required cost estimates have been estimated.
Environment and Social Monitoring Management Plan and Responsible Agency
Issue
no.
Impacts Environmental
Monitoring Measures and
Projected Cost
Responsible
Agencies
Timing of Action
Construction/
Operation
Impacts on Physical Environment
1. Disposal of solid waste,
waste materials and
construction debris.
Hazardous wastes are
properly segregated, treated
and disposed in approved
Contractor
119
landfill sites.
Construction debris can de
used for land recovery and
land filling
2. Degradation of water
quality, air quality & noise
level due to project
construction activities.
Treatment facility during
construction period
Use of personal protective
equipment for workers.
3 Occupational Health
Hazard and Safety
Implementation of OSH
activities. Distribution and
encouragement for the use
of safety hats, shoes, follow-
up of safety regulation,
well-communication of
construction safety
instructions at all levels.
Contaminated medical
wastes are properly
segregated, treated and
disposed in approved
landfill sites.
11 Impacts on sanitation and
health of the community
due to increase in disease
vector and transmission of
disease from outside
workforce.
Workers are not allowed to
stay overnight out from the
camp. Awareness program
will be launched to prevent
covid-19 infection/
contamination and from the
STDs.
26 Reducing the land use
Appropriate route
selection to minimize
impacts
Maximum use of existing
road and public land
Collection of spoils and its
management in scientific
way
ESMP Implementation Structure and Stakeholers Responsibility
The overall project environmental management is the responsibility of PIU. The ESMP shall be prepared to show
linkages with different parties to be involved directly or indirectly during the different phases of project
development and operation in compliance with the existing Act and Rules.
120
Category III: NUGIP interventions requiring Codes of Conduct
NUGIP sub projects which don’t fall into categories I and II shall follow Codes of best practices during the
implementation and operation phases. This category has clearly minimal or no impacts; very simple or no
mitigation required
Environmental codes of practices provide technically specified solutions illustrating the general principles of
environmentally sound and sustainable planning, design and construction. This will help to enhance positive
impacts and to avoid or lessen adverse or negative impacts. This environmental and social code of practices should
be applied in conjunction with the standard technical standards for preparation of designs of civil works and during
implementation. The NUGIP sub projects requiring application of best practice code of conducts are component 2
activities such as:
1) Environmental Enhancement Projects
2) Minor repair and maintenance works
3) Small scale rain water harvesting schemes
The generic environmental best practices to be followed for NUGIP Sub projects and interventions are elaborated
below:
▪ Solid Waste Management, including medical wastes, should be based on Reduce, Reuse, and Recycle (3R)
principles: Generation of solid, semi-solid and liquid waste requires proper on site management and scientific
disposal.
▪ As there may be settlements around the component 2 activities, no or few nuisances to the community should
be produced. Examples: use of less noisy equipment and no work during night hours as well as adoption of
Environmentally Sound Technologies (energy efficient system design, selection of less polluting technology) in
civil construction.
▪ Covid-19 regulations and Health and Safety Standards (e.g., use of personal protective equipment, use of safety
signs) should be adopted in construction areas and replacement activities,
▪ Environment, Health, and Safety (EHS) related orientation and job specific training should be provided to
employees; IFCs General Environmental Health and Safety Guidelines section 2.2 (Occupational Health and
Safety ; Communication and Training shall be followed
▪ Strict implementation of ESMP, adherence to GoN Rules, Regulations, Policies and World Bank policies, and
compliance with formats and checklists developed by ministries
▪ Correction of shortcomings, periodic review meetings, clear assignment of roles and responsibilities
▪ Environmentally friendly technologies and awareness rising in environmental (including cultural and
archeological) should be promoted.
▪ Information dissemination and public consultations prior, during and concomitant to the garner understanding
and consensus should be an integral part of all activities under NUGIP
113113113
Appendix D: Initial scoping for subprojects
Pokhara:UpgradationofTalchowk- BegnasRoad
Proposed length: 3.2 Km
RoW: 30m
Carriage way: 14m tillSisuwa Chowk
7m afterthat intersection
Designfeatures: Road, greenarea, flexible
pavement, trafficsigns, street furniture,
cyclelane
Benefitsofthe project:
• ProjectwillincreasetourismtoBegnasLake
• Thiswill provideeconomicopportunitiestolocals
• Currentlytherearelotofroadaccidentshappeningwhich
couldbereducedbyusingsignalandspeedcontrolandroad
crossingfeaturesintheproposedproject
• Roadconnectstoessentialserviceslikehospitalandschool
• Proposeddrainagesystemwillreducetheinundation
happeningeveryyear
• Reducetimeforcommuting
KeyEnvironmentalIssues
• The project is expected to end
approximately500mawayfromRamsarsite(Begnaslake).Sincethisisanurbanroadproject
and at the fringes of the lake, it is important to determine its impact on the lake’s
catchment area.
• AsTalchowkisneartothelakethereismorewatervaporintheairduetowhich
inwintertheyhavelotoffoginthesurrounding area.Whentherewillbe
increaseintrafficandvehicular pollution thefogwillbecomedenserwhich
mightleadtodeteriorationofairqualityaswellas visibility.
• Privatetreeswill becutduringRoWclearance,someofthetreesarefruit bearing
• Roadshavewaterstreamsandculvertsoverit,duringconstructionwater
pollutioncouldbeanissue
• Thereare un-utilizedcanals alongthe road (the land shouldbelongto
irrigationdepartmentand thereshouldbe user group)whichneedsto be shifted
• Electricpoles,telephonelinesanddrainsneedto beshifted
• During operations, theincreaseinm o v e m e n t ofvehiclesmightcause
significantairpollution
• Roadhavesensitivereceptors (bothhospitals andschools)ontheside
–air pollutionandnoisepollutionisimportantissue
KeySocialIssues
• RoWwasclearedfewyearsbackbutthereisencroachmentfromfarmers
whichwillhavetoberemovedwhichmightleadtocroploss
• Disruptiontobasicutilitiesandcommonpropertyresources
• Fewhomeshavebuiltrampsforaccessroadswhichwillhaveto bedestroyed
• A religiousplacebuiltby mothers’ groupwillberelocated
114114114
UrlabariMunicipality:UpgradationofKrishna Chowk to Communityforest officeroad
Proposed length: 5.275 Km
RoW: 12 m
Carriage way: 7m
Designfeatures: Road, utility duct on both
sides, pavement, street furniture, cyclelane,
Tactiletileto aidmovement ofvisuallyimpaired,
Junction improvement ofKrishna Chowk
Benefitsofthe project:
• Willimproveeconomicprospectsfordhamilcommunitywhichis
sociallydeprivedIP
• Duetolackof puccaaccessroad,rateofdevelopmenthasbeenvery
slowandveryfewpublic busesplyontheroad
• It willimproveconnectivityofpublictransportation
• Reducecommutingtimeto healthfacility,highergradeschool,
marketetc.Currently,communityhastotravelatleast7-8kmto
accessthesefacilities,whichtakesthemmanyhoursasthereisno
directconnectivity.
• Mightalsoreduceimmigrationrate
• Drainagesystemwillreducethefloodingoftheroad
KeyEnvironmentalIssues
• Theroadterminatesatcommunityforestoffice,hencetheproximityof
communityforestisanenvironmental concern.Howevertheroaddoesnot
passorrequireanyforestland,thereforetheimplicationsoftheprojecton
thecommunityforestareminimal.
• CuttingofprivatetreeswhichbelongtoKadamandBakainaaspecies
• Roadhavewater streamsandculverts overit,during constructionwater
pollutioncouldbeanissue
• Electricpolesneedto beshifted
• Road have sensitive receptors (school) – air pollution and noise
pollutionisimportantissue
• Duetoincreasedaccessibilitytocommunityforest,therecouldbeincreasein
Illegalwaterlogging
KeySocialIssues
• RoW is not cleared in Tribeni Sunjoda stretch but Municipality has ascertained
peoplehavelandownership documentandwouldbewilling to donateportionofland
• Thereisan agriculturalland,partoflandwillhaveto beacquired
• Therewillbedamagestostructureslikeboundaryofhouseandschool, privatehandpump
• Disruptiontobasicutilitiesandcommonpropertyresources
• Duetohighimmigrationratemosthouseholdsarewomenheaded.Dueto
projectsomeofthe temporaryshops(ownedbyfemales)haveto be
shifted.Ifthelandownershipisontheir name,transferringportionof land
tomunicipalitymightbringconflictinhousehold.Duringconstruction,there
willberiskofraiseinsafetyissueoffemales.
• Due tolabor influx,theremightbe riseinconflictdue tosharedresources
Likefuelwood
• ProjectalignmentrunsalongSunjhodaRiverbank,duringconstructionfew
settlement’sroadaccessibilitywillbeimpacted
115115115
DamakMunicipality:Upgradationofroadat wardno. 2and5- P21
Proposed length: 4.861Km
RoW: 12 m
Carriage way: 7m
Designfeatures: Road, utility duct on both
sides, pavement, street furniture, cyclelane,
Tactiletileto aidmovement ofvisuallyimpaired,
Junction improvement of TarabariDipu
Benefitsofthe project:
• Reducecongestionon East-WestHighway
• Duetolackof puccaaccessroad,thereislot of dustdispersionby
vehicularmovement
• Thereisfloodinginmonsoon,culvertsarenotproperlyconstructed,
andriverbedrisesduetosedimentation.Projectwillimprove
drainagesystemandculvertsaswell.
• Willbringmoreeconomicopportunitiestothearea.Currently,
communityisnotabletodevelopmarketplaceastheroadis kuccha
thereislimitedtraffic movement
KeyEnvironmentalIssues
• Roadshavewaterstreamsandculvertsoverit,duringconstruction
Waterpollutioncouldbeanissue
• CuttingtreesfromKadamspecies
• Electricpolesneedto beshifted
• Roadhavesensitivereceptors(school)–airpollutionandnoise
pollutionisimportantissue
• Duetoincreasedaccessibilitytoriverbed,therecouldbeincreasein
Illegalsandmining
• Clearingoftrees
KeySocialIssues
• Thereisagriculturalland, partoflandwillhaveto beacquired
• Therewillberelocationofonetemporaryshopownedbybackward group
• Disruptiontobasicutilitiesandcommonpropertyresources
• Lackofsufficientpublictoiletsandhenceopendefecation
• Withconstructionofprojecttherewill beincreaseinmovementof
heavyvehiclesaswellasothermotorized vehiclewhich willincrease
roadsafetyconcerns
• Duetolaborinflux,theremightberiseinconflictduetoshared
Resourceslikefuel wood,water,food
Birtamod Municipality:Upgradationof Buttabari-Pyakurel Road-P15
116116116
Proposedlength: 6.26Km
RoW:12m(9-10mat
SaraswatiSchoolArea) Carriageway:
7m
Designfeatures: Road,utilityduct on
both sides,pavement, street, Tactile tile to aidmovement
ofvisuallyimpaired, Junction improvement at E-W
Highway JunctionandBirtamodChandragadhi
Road,minorbridges
Benefitsofthe project:
• Duetolackof puccaaccessroad,thereislotdustdispersionby
vehicularmovement
• Thereisfloodinginmonsoon,culvertsarenotproperlyconstructed.
Projectwillimprovedrainagesystemandculvertsas well.
• Willbringmoreeconomicopportunitiestothearea
• Accessibilitytolocalreligiousplaces
KeyEnvironmentalIssues
• ThereisaNationalForestPatch(CharaliForest)maintainedbycommunity at the
easternsideofprojectroadatadistance of0.250to1.000Kmrange.
DeniaKhola,aperennialriverflowsadjacenttotheforestareaontheeasternside
ofprojectroad.Butastheroadisintermediate whichwillhavelimitedtraffic
therebylimitedenvironmentalimpact
• Roadshavewaterstreamsandculvertsoverit,duringconstructionwater
pollutioncouldbeanissue
• Electricpolesneedto beshifted
• Roadhavesensitivereceptor(school)–airpollutionandnoisepollution
Isanimportantissue
• NearKhoparionproposedroad,therewasalow-lyingsmallsectionof50mwhich was
affectedduetowaterloggingfor quitealongtime
• Herdof migratoryElephant(6-13ina herd)usetofollowCharaliforestpatch
tomigratetowards JalthalNationalForest. JalthalForest islocatedabout8km
awaytothesouthernsideofprojectroad.Elephantmigration occursabout3
timesintheyearduringharvestingseasonsintheassociatedarea
• Clearingofprivatetrees
KeySocialIssues
• Therewillberelocationofaschoolwhichisalreadyunderprocess
• AfewindigenouswomensellBhakka(indigenouscookedbread onvapor)on
theroadsidewhichwillberelocated.
• Disruptiontobasicutilitiesandcommonpropertyresources
• Withconstructionofprojecttherewillbeincreaseinmovementofheavyvehicles
aswellasothermotorizedvehiclewhichwillincreaseroadsafetyconcerns
• Duetolaborinflux,there might beriseinconflictdueto sharedresourceslike
Fuelwood,water,food,raisewomensafetyconcerns
117
Appendix E:Environmental & SocialMitigation Measures EnvironmentalImpactsandMitigationMeasures
EnvironmentalImpact /
Aspect
MitigationMeasures ResponsibleEntity
DESIGNSTAGE
Consideration ofDesign
Alternatives
The proposedalignment/design tobeselected/
adjusted
to minimize landacquisition
toavoidsocially,culturally&environmentally
sensitive areas–structures, Common Property
Resources, cultural properties,
waterbodies,vegetationcover,forestetc.
DPRconsultant,PCO,
Municipalities
Issuesfromstakeholder
consultations
Variousissuesraisedduringpublic consultationtobeexamined&suitably incorporatedbasedon merit&othersafety measures
DPRconsultant,PCO,
Municipalities
DesignforGeologically Unstable/Land Slide prone areas
Provisionof retainingwall/breastwall(as applicable)andothersuitablemeasuresfor landstabilizationshouldbe adopted
DPRconsultant,PCO,
Municipalities
ImpactonEcologically
Sensitive areaslikeProtected
Areas (National Parks,
WildlifeReserve, Hunting
Reserve,Conservation Areas,
BufferZones), Ramsar Site,
Breeding, NestingGroundof
migratoryspecies, Wildlife
Corridor/MigrationRouteetc.
Priorcareshouldbe giventofinalizethe project
location/s.Projectshouldn’tbedevelopedin
suchecologicallyfragileor inthevicinitywhich
mayhaveplausibleimpactontheseecosystems
DPRconsultant,PCO,
Municipalities
Impactonhistorically
significantsites
Toavoidimpactonhistoricallysignificant archaeological/anthropologicalsites,the projectdevelopmentshouldn’tbecommenced in the vicinityof historicallyimportantsites
DPRconsultant,PCO, Municipalities
Roadsafetyissueduetopoor geometrics
Designofgeometricimprovementsasper designstandards
DPRconsultant,PCO, Municipalities
PRE-CONSTRUCTION STAGE
LandAcquisitionand LossofProperties
AcquisitionofPrivateLand Compensationforloss
Livelihoodrestoration
Trainingandcapacitybuilding
EngagingPAPsinprocessofproject development
ESIA consultant, ULGs,
PCO,Municipalities Impacton structures/properties
Impactonvulnerable communities
ShiftingofUtilities
RelocationofUtilities
Allcommunityundergroundandoverhead utilitieswillbeshiftedasperproperUtility ShiftingPlanaftertakingpriorpermissionfrom concerneddepartments likeElectricity, Telecommunications, Waterworksetc.
DPRconsultant, concerneddepartment/s, PCO,Municipalities
118
EnvironmentalImpact/ Aspect
MitigationMeasures ResponsibleEntity
Lossofdrinkingwatersource
Drinkingwatersourcetobe replacedin consultationwiththelocals.Temporary arrangementsshouldbe provided,if theexistingwatersupplyis likelytobe disrupted/disturbed
DPRconsultant,
concernedstakeholders,
PCO,Municipalities
Mobilisation&Site
Clearance
Removalof Trees &Vegetation
Cover
TreesandVegetationcoverwillberemoved fromthe projectdevelopmentareabeforethe Commencementof Constructionafterobtaining necessarypermissionsfromtheforest Department.Provisionforcompensatoryplantationshould be keptasperthe guidelineof the Forest Department
ESIAConsultant, Contractor,PCO, Municipalities
LossofForestLand
ForestClearancefromForestDepartmenttobe
obtainedpriortoinitiationofanyactivityon forest
ESIAConsultant,
Contractor,PCO,
Municipalities
LossofAgriculturalLand&Crops
Compensationtolandownerforacquisitionof landanddamageofcrops(asapplicable)
ESIAConsultant,PCO, Municipalities
Dismantlingof Existing Structures
Existingstructures(ifany)fromproject
developmentareashouldbedismantledafter
takingformalconcurrencefromrespective
stakeholder/s
ESIAConsultant, Contractor,PCO, Municipalities
Mobilizationof Crushers,
Constructionplants,other
ConstructionVehicles,
EquipmentandMachinery
Specificationsofcrushers,constructionplants,
OtherConstructionVehicles,Equipmentand
Machineryshouldcomplytothenormsof
pollutioncontrollegislationsofNepal
Contractor,PCO, Municipalitiesinco- ordinationwithDSC
Settingupof construction camps
Ideally theconstruction camps should be located
atleast 500mawayfromhabitations
awayfromsensitivelocations.
TheContractor duringtheprogressofwork
willprovide,erectandmaintain necessary
(temporary) livingaccommodation and
ancillaryfacilitiesforlabourtostandardsand
scalesapprovedbytheWorldBank.
Contractor, PCO, Municipalitiesinco- ordinationwithDSC
Identificationofconstruction
debrisdisposalsite
Followingpointsaretobe consideredfor
SelectionofsiteforDebrisdisposal-
It shouldnot belocatedwithindesignated to restore
ecologicallysensitiveareas
The dumping should not impact natural
drainagecourses
Settlements should be located acceptably
awayfromthedisposalsite
Contractor,PCO, Municipalitiesinco- ordinationwithDSC
GenerationofDustand
Emissionfromsiteclearing
equipment
Vehicles carrying dismantled materials
shouldbecovered toreduce spillsanddust
blowingofftheload.
Water spraying should be carried out at
regularintervalstolimitthedusttobelow
Plants,machinery andequipment shallbeso
handled(including clearingand dismantling) asto
minimize generationofdust.
Allvehicles,equipment andmachinery used
forconstructionshallberegularlymaintained
Contractor, PCO,Municipalitiesin coordinationwithDSC
119
EnvironmentalImpact/
Aspect
MitigationMeasures ResponsibleEntity
Toensurethatpollutionemission levels
complywiththerelevantrequirements of MoFE
Regular monitoring of ambient air quality
shouldbeconductedfortheparameters like PM10,
PM2.5, SO2,NOx,CO,O3,at suitablelocations
ShiftingofCultural/Religious
Properties
CulturalandReligiousproperties shouldbe
shiftedtothenearbylocation inconsultation
withlocalcommunityandadministration.
Contractor, PCO,
Municipalitiesincoordination
withDSC
CONSTRUCTIONSTAGE
Clearancesandapprovals
Priortoinitiationofconstructionwork
necessarypermissionsaretobetakenfrom
respective stakeholders.
ESIAConsultant,
Contractor,PCO,
Municipalities
Land
SoilErosionand
Sedimentationcontrol
Main reason of soil erosion is downpour.
Contractor shouldplantheactivitiessothatno naked
/looseearthsurfaceisleftoutbeforethe
onsetofmonsoon. Forminimising
thesoilerosionfollowingpreventive measurestobe
takensuchas:
Topsoilfromborrowarea,debrisdisposal
sites,construction sitetobeprotected/
coveredforsoil erosion.
Debris due to excavation of foundation,
dismantling ofexistingstructurewillbe
removedfrom thewatercourse immediately
andshouldbe reusedfor backfilling.
Alonglocations abuttingwaterbodies,stone
pitchingcan be carriedout.
Embankmentslopestobecovered,soonafter
completion.
Diversions for bridges/culvertswillbe
removedfromthe water coursebeforethe
onsetofmonsoon
Contractor,PCO,
Municipalitiesincoordination
withDSC
Lossofagriculturaltopsoil
Allareastobepermanentlycoveredorborrow areas will
be strippedtoadepthof150mmand
Storedinstockpile.Thestockpilewillbedesignedsuchtha
tthe slopedoesnotexceed1:2(verticalto
horizontal),andthe heightofthepileis tobe
restrictedto2m.Thestockpilesshouldbe
coveredwithgunnybagsor tarpaulin.
Topsoilwill besafeguardedfromerosionand
willbereusedas follows:
Coveringallborrowareasafterexcavationis over.
Dressingofslopesofroadembankment
Agriculturalfield,acquiredtemporarily
Landscaping
Contractor,PCO,Municipaliti
esincoordinationwithDSC
CompactionofSoiland
DamagetoVegetation
Constructionvehiclesshouldoperatewithinthe
projectdevelopmentzoneto avoiddamaging
soilandvegetationofoutside.
Contractor, PCO,
Municipalitiesincoordination
withDSC
EnvironmentalImpact/
Aspect
MitigationMeasures ResponsibleEntity
120
Diversions,accessroadsusedwillberedeveloped
byContractor tothesatisfactionof theowner/
villagersoncetheconstructionworkisover. While
operating on temporarily acquired
agriculturallandforanyconstructionactivities,
topsoilwillbe preservedin stockpiles.
Contaminationofsoil
DuetohandlingofHazardouswaste
Vehicle/machinery and
equipmentoperation,maintenance and refueling
shall becarried outinsuchafashion thatspillage
offuelsandlubricants doesnotcontaminate
theground.
Fuelstorageshallbeinproperbundedareas.
Allspillsandcollectedpetroleum products
shallbedisposedofinaccordancewith Government
ofNepalguidelinesatdesignatedlocations.
Oilinterceptorshouldbeinstalledat construction
siteforwashdownand refueling areas.
Septic tankwill beconstructed forsafe
disposaloflabourcampwaste.
Contractor, PCO,
Municipalitiesincoordinatio
nwithDSC
1.Quarrying
2.Materialsources
Quarry material shall be sourced from
approvedand licensedaggregateand sand quarries.
Foroperatingnewquarries,theContractor
shallobtainmaterialsfromquarriesonlyafter
consentoftheconcernedauthoritiesandonly
afterdevelopmentofacomprehensivequarry
redevelopmentplan.
Adequatesafetyprecautionsshallbeensured
duringtransportationofquarrymaterialfrom
quarriestotheconstruction site.Vehicles
transporting thematerialshallbecoveredto
preventspillage.
Contractor,PCO,
Municipalitiesincoordinatio
nwithDSC
GenerationofDebris
Debrisgeneratedduetoexcavation,dismantlingofstruct
ures, cuttingofthehilletcshouldbe
suitablyreusedintheconstructionactivitytothe
extentpossible
Contractor, PCO,
Municipalities in
coordination with DSC
Disposalof Debris
Thedisposalofdebrisshallbecarriedoutonly
atsitesidentified for the purpose. All
arrangementfortransportation, dismantling
andclearing debris shouldbeplannedand
implementedbytheContractor inan
environmentallyacceptablemanner
Contractor, PCO,
Municipalitiesincoordination
withDSC
Air
Dustgenerationand gaseous
emissionfromconstruction
activitiesandequipment
Vehicles delivering materials should be
coveredtoreducespills anddustblowing off
theload.
Clearingand grubbingtobe done, justbefore
thestartofnextactivityon thatsite.
Watersprayingisneededtoaidcompactionof the
earth material. After the compaction,
Contractor, PCO,
Municipalitiesin
coordinationwithDSC
121
EnvironmentalImpact/
Aspect
MitigationMeasures ResponsibleEntity
water spraying should be carried out at
regularintervalstolimitthedusttobelow
Construction surfaces shouldbecleanedwith
aircompressor andvacuum cleanerspriorto
theconstruction works.Manuallabourusing
brooms should beavoided, ifusedlabour to be
providedwithmasks.
Forroads,embankment slopestobecovered
withturfing/stonepitching immediately
aftercompletion.
TheContractorshall take everyprecautionto
reducethelevelofdustemissionfromthehot mix
plantsand thebatchingplants
Plants,machinery andequipment shallbeso
handled(includingdismantling) asto
minimisegenerationofdust.
Allvehicles,equipment andmachinery used
forconstructionshallberegularlymaintained
toensure thatpollutionemission levels
complywiththerelevantrequirements of MoFE
Regular monitoring of ambient air quality
shouldbeconductedfortheparameters like PM10,
PM2.5, SO2,NOx,CO,O3,Pbat suitablelocations
PollutionfromCrusher
Onlythecrushers already havingvalidlicense
ofGoNshall beused.
Contractor,PCO,
Municipalitiesincoordinatio
nwithDSC
Water
Impacton waterresources
Proposedsite should be devoid of any waterbody
sothatnoacquisition ofwater bodytakesplace
In case of unavoidable situation(like widening
ofroad)ifthewaterbody ispartly affected;
thevolumetric lossofcapacity
shouldbecompensated byexcavation ofan
equalvolume ofsimilardepthatclosest possible
location shouldbedoneinan
environmentallyacceptablemanner
Debrisshouldn’t bedisposed ornomaterial should
bestorednearanywaterbody which
threatstocausevolumetric lossofwater
resourceduetosiltation
Siltfencingtobeprovidedintheconstruction
areas(nearwaterbodies)
Priorpermission fromauthoritiesforuseof
water(surface/ground) forconstruction
activityshouldbetaken.
Constructionlabours to be restricted from
pollutingthesourceor misusingthe source.
Shifting of drinking water source to be
Contractor, PCO,
Municipalitiesincoordinatio
nwithDSC
122
EnvironmentalImpact/
Aspect
MitigationMeasures ResponsibleEntity
completedpriortodisruptionoftheactual source
Alternate
measurestobetaken/ensuredduringdisruptedper
iod.
Source tobereplaced immediately, in case of
accidentalloss.
Alterationofdrainage
SurfaceRunoff&Water
Logging
Siltationinwaterbody
If any alteration of existingdrainage is
requiredthendiversions willbeconstructed
duringdryseason,with adequate drainage facility,
and willbecompletely removed
beforetheonsetofmonsoon
Debris generated dueto the excavation of
foundationorduetothedismantling of
existingstructure willberemovedfromthe
watercourse
Siltfencing tobeprovidedonthemouth of
dischargeintonaturalstream
Properdrainage network tobedeveloped to
avoidanyimpactondrainage conditionand
tocatersurfacerunoffflow.
Contractor,PCO,
Municipalitiesincoordinatio
nwithDSC
Waterrequirementfor
project/stressonwater
source
Contractorshouldidentifyalistofsources
(surface/ ground)forconstructionwater
Priorto use of water (surface/ground) permission
shouldbetakenfromrespective authority
Duringconstructiononlypermittedquantity
(permission taken)fromapprovedsources
willbeused.
Contractorwillensureoptimumuseofwater;
wastage ofwaterinconstruction/labourcamp
shouldbereligiouslyrestricted.
Contractor, PCO,
Municipalities in
coordinationwithDSC
Silting/sedimentation
Measuressuggestedunder“SoilErosionand
Sedimentationcontrol”shouldbefollowed.
Silt fencing should be provided in the
constructionareasnearwaterbodies.
Construction activities should be avoided
nearwaterbodiesduringmonsoon.
Contractor, PCO,
Municipalities
incoordinationwithDSC
Contaminationof water
Measuressuggestedunder“Contaminationof
soil”will beenforced.
Construction work close to water bodies
shouldbeavoidedduringmonsoon.
Silt fencing should be provided in the
constructionareasnearwaterbodies.
Labour campsshouldbelocatedawayfrom
waterbodiesandshouldbeequipped with
septictank.
Caretobetakensothatthedischarge from
labourcamp/construction campdoesn’t
contaminatesurfaceor groundwater
Carwashing/workshopsnearwaterbodies
Contractor, CO,
Municipalities in
coordinationwithDSC
123
EnvironmentalImpact/
Aspect
MitigationMeasures ResponsibleEntity
shouldbeavoided.
Oilinterceptorshouldbeinstalledatsuitable
locations
Waterquality(surfaceand ground)should
bemonitoredatsuitablelocations
Contaminationof Ground
waterduringboring/well
construction
Necessarycareshouldbegivenduringwell
construction topreventaccidental contaminationof
Groundwater
Contractor, PCO,
Municipalities in
coordinationwithDSC
Noise
NoisefromVehicles,Plants
andEquipment,Blastingor Pre-
splittingOperations
Noise standard at processing sites, e.g. aggregate
crushing plants, batching plant,
hotmixplantwillbestrictlymonitored to
preventexceedingofnoisestandards.
Workersinvicinityofloudnoise,andworkers
workingwithorincrushing, compaction,
concretemixingoperations shallwear earplugs
andtheirworking timeshouldbe
limitedasasafetymeasure.
Inconstructionsiteswithin150mofsensitive
receptorsconstruction willbestoppedin Night-
time(from22:00to06:00).
Machineryand vehicleswill bemaintainedto
keeptheirnoisetoaminimumlevel.
Noisebarriersmaybe constructedatsensitive
receptorlocations.
All vehicles and equipment used in construction
shallbefittedwithexhaust silencers.
During routine servicing operations, the
effectiveness ofexhaustsilencersshouldbe
checkedandiffoundtobedefective shallbe replaced.
Contractor, PCO,
Municipalities in
coordinationwithDSC
SitesofHistorical
/CulturalImportance
ChanceFinds
The contractor should keep provisions for
managing chancefindswhichwillbeapplied
intheeventifcultural heritageis subsequently
discoveredorencountered unexpectedly
duringprojectdevelopment. Thecontractor
shouldensurenodisturbance
toanychancefindfurtheruntilanassessment
bycompetentprofessionals ismadeand
actionistakenbyconcernedauthority.
Contractor, PCO,
Municipalities
incoordinationwithDSC
Flora&Fauna
Fellingof trees and
disturbanceof vegetation
cover
Clearingofvegetation/treesmustbelimited
onlywithinprojectdevelopmentzone.
Avoidabletreesmust besaved
Possibility for transplantation of trees shouldbe
explored
Plantation/afforestationactivityshouldbe
activityinitiatedinaccordancetoGovt.of
Contractor, PCO,
Municipalities in
coordinationwithDSC
124
EnvironmentalImpact/
Aspect
MitigationMeasures ResponsibleEntity
Nepalafforestationpolicy
Provision of LPG should be kept for
construction campasfuelsourcetoavoid
treecutting
ImpactonFauna
Construction camps shouldbelocatedaway
fromecologicallysensitiveareas
Constructionworkers must protect natural
resourcesandwildanimals.
Huntingmust be prohibited.
Nestinggrounds&migratorypaths/wildlife corridor
ofthevicinity(ifany)shouldbe protected.
Compensatory afforestationshouldbetaken
uptomitigatelossofbiodiversity associated
withlossoftreeandvegetationcover
Contractor, PCO,
Municipalities in
coordinationwithDSC
Disturbance ofaquatic ecosystem
duetounwanted
discharge,malhandling of
material
Itshouldbeensuredthattreatedwasteare
onlydischarged todrainage systems(which
eventuallymeetaquaticsystem).
Provision for silt fencing/Oil interceptor shouldbe
keptforsuitablelocations
Construction materials should be handled
properlytoavoidaccidentalcontaminationof
aquaticsystem
Contractor, PCO,
Municipalities in
coordinationwithDSC
Socio–Economic
Environment
PublicHealthandSafety
Debris generated should be disposed of properly
indesignateddisposalsite/s
Monitoringofair,water,noiseandsoilshould
beconductedtocrosscheck environmental
conditionand to take necessarymitigation
measuresifrequired.
Contractor, PCO,
Municipalities in
coordinationwithDSC
ThreatofAccidents
The Contractorwillprovide,erectand maintain
barricades,includingsignsmarkingflats,lights
andflagmenasrequiredin theprojectduring
constructionphase
Contractor,PCO,
Municipalitiesincoordi
nationwithDSC
TemporaryLossof
Access/TrafficCongestion
Theconstruction worksshouldnotinterfere
withorcauseinconvenience topublicor
restricttheaccesstouseofpropertieswhetherpublic
or private and plan for traffic
decongestionshouldbe kept.
Contractor,
PCO,Municipalities in
coordinationwithDSC
Road Safety And
ConstructionSafety
TrafficControlandSafety
Detailed Traffic Control Plans should be
prepared. Thetrafficcontrolplansshould
containdetailsofarrangements for construction
undertrafficanddetailsof
trafficarrangementaftercessationof work eachday.
The Contractor shall take all necessary measures
forthesafety oftrafficduring
constructionandprovide,erectandmaintain
Contractor, PCO,
Municipalities in
coordinationwithDSC
125
EnvironmentalImpact/
Aspect
MitigationMeasures ResponsibleEntity
Suchbarricades, includingsigns,markings, flags,
lightsandflagmen asmayberequired
fortheinformationandprotection oftraffic
approachingorpassingthroughthesectionof
theroadunderimprovement.
RiskfromConstructionWork
TheContractorisrequiredtocomplywithall
theprecautions asrequiredforthesafetyof
theworkersaspertheInternational Labour
Organisation(ILO).
The Contractor shall supply all necessary safety
appliances such as safety goggles,
helmets,masks,etc.,totheworkersandstaff.
The Contractorhas to comply with all
regulationregardingsafescaffolding,ladders,
workingplatforms, gangway,stairwells,
excavations,trenchesandsafemeansofentry
andegress.
Nochildlabourshallbeutilizedintheproject
Contractor, PCO,
Municipalities in
coordinationwithDSC
RiskfromElectricalEquipment
Adequateprecautionsshouldbebetakento
preventdangerfromelectricalequipment.
All necessary fencing and lights will be
providedtoprotectthe public.
Contractor, PCO,
Municipalities in
coordinationwithDSC
RiskatHazardousActivity
All workers employed on mixing asphaltic
material,cement,limemortars,concreteetc, will
beprovidedwithprotectivefootwearand
protectivegoggles.
Workers, whoareengagedinweldingworks,
wouldbeprovided withwelder’s protective eye-
shields. Stonebreakerswillbeprovided
withprotectivegogglesandclothing andwill
beseatedatsufficientlysafeintervals.
Theuse of anytoxic chemicalshallbestrictly
inaccordance with themanufacturer’s instructions.
Contractor, PCO,
Municipalities in
coordinationwithDSC
RiskcausedbyForceMajure
All reasonable precaution will be taken toprevent
danger oftheworkers andthepublic fromfire,flood,
drowning,etc. All necessary
stepswillbetakenforpromptfirstaidtreatment
ofallinjurieslikelytobesustained duringthe
courseofwork.
Contractor, PCO,
Municipalities in
coordinationwithDSC
FirstAid
Ateveryworkplace,areadilyavailablefirst
aidunitincluding anadequate supplyof sterilised
dressingmaterialandappliances willbeprovided.
Suitable transport should be provided to
bringinjuredorillperson(s) tothenearest
applicablehospital.
Contractor, PCO,
Municipalities in
coordinationwithDSC
HealthandHygiene
Latrinesinconstruction/labourcampshould be
providedwithseptictank.
The septic tank should be cleaned periodically.
Contractor, PCO,
Municipalities in
coordinationwithDSC
EnvironmentalImpact/
Aspect
MitigationMeasures ResponsibleEntity
Theeffluentscanbedivertedforhorticulture
insidethecamps.
Workersmusthaveaccesstopotablewater.
Garbagebinsmustbeprovided inthecamps
andregularly disposedoffinahygienic manner.
Adequate health care facility should be
providedfortheworkforce.Unlessotherwise
arranged forbythelocalsanitaryauthority,
thelocal medicalhealth ormunicipal authorities.
On completion of the works, all such temporary
structures shallbeclearedaway,
septictankandotherdisposal pitsshouldbe
filledinenvironmentallyacceptablemanner
ConstructionCamps’
Restoration
Contractor should prepare site restoration
plans.TheplanistobeimplementedbytheContract
orpriortodemobilisation.
On completion of the works, all such temporary
structures shallbeclearedaway,
septictankandotherdisposal pitsshouldbe
filledinenvironmentallyacceptablemanner.
Residualtopsoil(ifany)willbedistributedon
adjoining/landscapingareas.
Contractor,
PCO,Municipalities in
coordinationwithDSC
MonitoringofEnvironmentalQuality ThemonitoringofAir,land,waterandNoiseto
becarriedoutatsuitablecriticallocationsof
projectsite.
Contractor, PCO,
Municipalities in
coordinationwithDSC
POST-CONSTRUCTION STAGE STAGE
Stockpiles, solid wastes and
construction debris
• Clean up the project site and clear the working
area of unutilized construction materials and
heavy equipment
• Conduct a final clean-up of solid wastes
• Proper disposal of construction debris
Contractor
Signages, barriers, road obstructions • Removal barriers and other signages
Contractor
Waterways • Ensure that waterways are not clogged with
construction debris and other waste materials
Contractor
OPERATIONSTAGE
Soil/Water quality
degradationdue to surface run-off
Siltfencing, Oil&Greasetraps,etc.shallbe
provided toensure thatthewaterqualityis
notimpairedduetocontaminants fromroad run-
off.
Monitoringshallbecarriedout at suitable
locations
Provisionforproperdrainagenetworkshould be
kept
PCO,Municipalities
Contamination ofSoiland
WaterResources from
Spills/Accidents
Contingency planstobeinplaceforcleaning
upofspillsofoil,fuelandtoxicchemicals.
Spill of oil, fuel and automobile servicing
unitswithoutadequate disposalsystemsin
placetobe discouraged.
Accidental spills are potentially disastrous,
butitsprobability isquitelowasoneofthe
objectives ofthisprojectistoenhance road safety.
The Public will be informedabout the
regulationsonland pollution.
Landpollutionmonitoringprogramhasbeen
devisedforchecking pollution leveland
suggestingremedialmeasures.
PCO,Municipalities
Increaseof PollutionLevel Dustsuppression PCO,Municipalities
EnvironmentalImpact/
Aspect
MitigationMeasures ResponsibleEntity
InAmbientAir
Noise
HORN PROHIBITED sign post will be enforced
Maintenanceofnoisebarriers
The public will be informed about the
regulationson noisepollution.
PCO,Municipalities
Ecology Compensatoryafforestation
Protectionofplantedtrees
PCO,Municipalities
TrafficandAccidentSafety
Depending on the level of congestion and
traffichazards,trafficmanagementplanswill be
prepared.
Traffic control measures including speed
limitstobeenforcedstrictly.
Road control width to be enforced. Local
government bodiesanddevelopment authorities
willbeencouraged tocontrol
buildingdevelopmentalongthe highway.
PCO,Municipalities
Generationofdustandnoise
duetomaintenancework
Asrecommendedunderconstructionsection Contractor, PCO,
Municipalities in
coordinationwithDSC
Temporarylossofaccess/trafficcon
gestion
Theconstruction worksshouldnotinterfere
withorcauseinconvenience topublicor
restricttheaccesstouseofpropertieswhetherpublic
or private and plan for traffic
decongestionshouldbe kept.
Contractor, PCO,
Municipalities
incoordinationwithDSC
Riskofaccidental
contaminationofsoil/surface,
groundwaterresourceand
possibilityof mixingwith
watersupplylineduetoleakages/
overflowsfromthe
sewerlinesinoperation phase
Immediate action to restrict the
contaminationandoverflowofsewage
Contractor, PCO,
Municipalities in
coordinationwithDSC
Chanceofcontaminationdue
tohandling,transportation
anddisposalofsolidwaste
andsewagetreatmentplants
Segregationofwasteatsource.
Collectionofwasteatregularinterval.
Propercollection,handling and disposalof
wasteisnecessarytoavoidcontamination of
surroundingsoil,waterenvironment and
nuisanceduetogenerationoffoulsmell.
Maintenanceofdisposalsite
Contractor,
PCO,Municipalities in
coordinationwithDSC
Riskofcontaminatingsurface
andgroundwaterbyseepage
andleachatefromdisposal sites&
destabilization of heapsof
wasteatthelandfillsite
Proper monitoring of landfill site and its
maintenance
Slopestabilization
PCO,Municipalities
EnvironmentalMonitoringat
criticallocations
ThemonitoringofAir,land,waterandNoisetobecarriedo
utidentifiedcriticallocationsas identified
PCO,Municipalities
Appendix F: Contents of the Resettlement Action Plan
ContentsoftheResettlementActionPlan(RAP)shallincludethefollowingasabasic minimum:
ExecutiveSummary
Projectdescription
ObjectivesandStudyMethodology
Socio-EconomicProfileofthe projectarea
RegulatoryPolicieswithrespecttoSocialSafeguards
ProposedImprovementsunderthe project
Optionsconsideredforminimizingadverseimpacts
AssessmentofProjectimpacts
BaselinesSocioEconomicSurvey
PublicConsultation&DisclosureandPlan
Natureandmagnitudeofimpacts
Typeofimpacts
CompensationandR&Rassistance
LivelihoodRestorationand IncomeGenerationPlan
GenderDimensionsandActionPlan
GrievanceRedressMechanism
ImplementationScheduleandBudget
InstitutionalArrangements
ImplementationArrangements
Monitoringand Evaluation
ARAPwouldbe preparedcoveringthefollowingminimumelements:
A censussurveyofdisplacedpersonsandvaluationof assets;
Descriptionofcompensationandotherresettlementassistancetobe provided;
Consultationswithdisplacedpeopleaboutacceptablealternatives;
Institutionalresponsibilityforimplementationand proceduresforgrievanceredress;
Arrangementsformonitoringandimplementation;and
A timetableandbudget.
131131131
Appendix G: Assessment of Institutional Capacity
AglimpseofInstitutionalStrength(E&SDepartment)ofEasternClusterMunicipalities
Particulars Birtamod Damak Urlabari Sundar Haraicha
Mechinagar Itahari Rajbiraj Triyuga Dhankuta
SeparateEnvironment&Social cell
Yes Yes No Yes Yes Yes Yes Yes Yes
Efficacy of E&S departments
•5Environment and 3 Socialstaff (including permanent and
temporary) involved in preliminary survey work pertaining to social and environmental assessment (like assessment of impact on trees, structures)
•Environment staff are hired ontemporary basis. Social staff is permanent
•Staff are not involved in projectplanning or appraisal process
•Municipalityhas experienceof preparingESIA/ ESMP through external agencies
•Staff are permanent
•Staff arenot involved in projectplanningor appraisal process
•Municipalityhas experience in preparing ESIA/ESMP through external agencies
•Hasn’t prepared ESIA/ESMP for multilateral funding agencies
•10 permanent
staff involved in survey work pertaining tosocial and environmental assessment
•Staff are permanent and temporary
•The Environment officer had pastexperience of conducting IEE/ESIA studies. He is alsoresponsiblefor monitoring of efficacy of EMP being adopted in various industriespriortoissuing pollution under control certificate
•Headoftheunit ispermanentand others staff are temporary.
•Department is responsible for coordinationand facilitationofthe environmental and social committeeunder themunicipality
•The department’s roles include management of education, health, social security, sanitation etc. related issues
•Staff are not involved in project planning or appraisal process
•Staff carryout preliminary social and environmental
•Bothexperts are permanent
•Staffarenot involved in project planning or appraisal process
•Municipality hasexperienceof preparing ESIA/ESMP through externalagencies
•Haven’t prepared ESIA/ESMP for multilateral funding agencies
•1Environmental Staff&3Social Staff
•Staff are not involved in project planning or appraisal process
•Municipality hasexperience of preparing EIA/ ESMF but all were outsourced
•Oneofthestaff wasengagedin review of ESIA-ESMP prepared by external consultant for UGDP (ADB funded)-2 weekly market development project
132132132
Particulars Birtamod Damak Urlabari Sundar Haraicha
Mechinagar Itahari Rajbiraj Triyuga Dhankuta
survey (like assessment of impact on trees, structures) after project identification
AglimpseofInstitutionalStrength(E&SDepartment)of WesternClusterMunicipalities
Particulars Pokhara
Leknath
Vyas Putalibazar Baglung Tansen Ramgram Tilottama Shuklagandaki
Separate
Environment
&Social cell
Yes OnlySocialUnit Yes No Yes No Yes Yes
Efficacy of
departments Roles:
Social
safeguard,
Panjikaran,
women child-
Dalit –Janajati
targeted
programs,elder
citizen
program, social
inclusion and
monitoring of
Social
Organization
Solid waste
management,
plantation,
Greenery
promotion
&Landscaping,
Pond
Conservation
Roles:social
safeguard,
social
inclusionand
monitoringof
Social
Organization
Municipality
has
experience of
preparing
ESIA/ ESMP
through
external
agencies
Have
experience of
working with
ADB
Roles: social
safeguard,
Panjikaran,
women –child-
Dalit-Janajati
targeted program,
elder citizen
program, social
inclusion and
monitoring of
SocialOrganization
Solid waste
management,
pollution,
plantation,
supervision of
environment
activities
Municipality has
experience of
preparing ESIA/
Roles: social
safeguard,
Panjikaran,
women – child-
Dalit - Janajati
targeted
program, elder
citizen program,
social inclusion
and monitoring
of Social
Organization
Solid waste
management,
pollution,
plantation,
supervision of
environment
activities
Roles: social
safeguard,
Panjikaran,
women–child-
Dalit - Janajati
targeted
program, elder
citizenprogram,
social inclusion
and monitoring
of Social
Organization
Solid waste
management,
pollution,
plantation,
supervision of
environment
activities
1 Env. Officer, 3
staffinsocialcell
Roles:Solidwaste
management,
Women
Empowerment
programs, Social
security and
registrationofvital
events, Co-
ordination and
facilitation of tole
vikassanstha.Skill
development
Staff have never
prepared/reviewed
any ESIA-ESMP
133133133
Particulars Pokhara Leknath
Vyas Putalibazar Baglung Tansen Ramgram Tilottama Shuklagandaki
•Municipality has experience of preparing ESIA/ESMP through external agencies
•Haveexperience ofworking with ADB and JICA
•Technicalteam examines and conducts survey;prepare feasibilityreport and the DPR.
ESMP through externalagencies
•Haveexperienceof workingwithADB
•Municipalityhas experience of preparing
ESIA/ ESMPthrough external agencies
InstitutionalAssessmentofEnvironmentDepartmentofVariousMunicipalities
Parameters Pokhara Putalibazar Shuklagandaki Itahari Dhankuta S.Haraincha
Strength of
Environment Cell
Env.Cell -1Staff(BSc-
Environmental Science,
Ukraine)DisasterManage
ment–1Staff
Env.Cell-1Staff (MA-
Economics, MA-Pol.
Science, LLB-
Environmental Law). The
staff is holding additional
charge of
AdminOfficer,Headof
Legal Section, Disaster
Management Officer
Env.Cell -1Staff (B.Com);
Innearfuture one more
Environmental Person will
be appointedin the
municipality
Env. Cell -1 Staff (M.Sc-
Environmental Science,
Khulna University).The
staff isholding additional
charge of Disaster
Management Officer
andSolid Waste
Management Officer
Env. Cell -1 Staff
(B.Com);
Disaster Management
Officer iscurrentlyin
additional charge of Env.
Officer(B.ED). However,
Disaster
Managementofficeris a
part ofSocialCell
Roles andresponsibilities Plantation,
Maintenance of Public
Park, Greenery
promotion &Landscaping,
Pond
Plantation, Gavian
Filling, Landslide
Protection
Solid waste
management only
Issuance of Pollution
Under Control
Certificate for various
operational industries,
Supervision of Solid
SolidWasteManagement,
Supervisionoflandfillsite
redevelopment, awareness
program on
Awareness on threat
from Elephant, fire
prevention; monitoring
of plantation,
134134134
Parameters Pokhara Putalibazar Shuklagandaki Itahari Dhankuta S.Haraincha
Conservation,
Conservation of
religioustrees,
Waste Management,
RiverBankProtection&
Flood Control, Monitoring
of plantationactivity
environmentalCleanliness,
plantation&greenery
development
supervision of solid
wastemanagement
KeyExpertise/Specializatio
n
- Thestaff completed
LLB in Environmental
lawin2017
- The staff had been
Involvedin preparation of
ESIA/IEE Reports.
Had verygood
understanding about
Environmental laws and
regulationsofGoN.
Solid wastemanagement
&landfill sitemanagement
-
Involvementin Project
execution (Planning,
Construction & Operation)
Notinvolved/consulted
during planning of
infrastructure development
project
Notinvolved/consulted
during planning of
infrastructure development
project
Notinvolved/consulted
during planning of
infrastructure development
project
Notinvolved/consulted
during planning of
infrastructure development
project.
Sometimes, theviewof
Env. cell is considered by
the municipality. For eg.
in case ofextraction
ofborrowmaterial from
riverbanks, thestaff’s
recommendation was
adopted by the
municipality.On other
hand, the
suggestionofexpert is not
considered in case of
dumping of solid waste
inforestarea(as thereisno
immediate alternative is
available). Pertinentto
state that,
currentlythesolidwaste is
disposed in Hasposa
Community Forest.
Notinvolved/consulted
during planning of
infrastructure development
project
Notinvolved/consulted
during planning of
infrastructure development
project
Ratio of budgetallocated
toEnvironmentcelltothetota
l budget of the municipality
20 Cr (4% of total Budget) 5% ofTotalBudget approx. 1% of total
Budget
Notanyspecificbudgetkept.
But project specific budget
is keptlikefortestingofwater
quality (during
approx. 1% of total
Budget
approx. 0.3% of total
Budget
135135135
Parameters Pokhara Putalibazar Shuklagandaki Itahari Dhankuta S.Haraincha construction/operation
phase),Plantation etc.
Understanding of
Environmental laws and
regulations of Nepal
pertaining to
infrastructure
development project
Thestaffneitherhadtheu
nderstanding of
Environmental laws
and regulations of
Nepal norawareabout
EIA/IEE requirements
Thestaffhadquiteafaira
wareness about
Environmental laws
and regulationsofGoN
Thestaffneitherhadtheu
nderstanding of
Environmental laws
and regulations of
Nepal norawareabout
EIA/IEE requirements
The staff had quite a
good understanding
about Environmental
laws andregulationsof
GoN.The
operationalprocedure
forItahari Municipality
for Pollution
Prevention&
Control,2018 is
prepared by the staff
Thestaffneitherhadtheu
nderstanding of
Environmental laws and
regulations of Nepal
norawareabout EIA/IEE
requirements
Thestaffneitherhadtheu
nderstanding of
Environmental laws and
regulations of Nepal
norawareabout EIA/IEE
requirements
Understanding ofWorld
Bank/ADB
Policies/Experience of
Workingwithanyofthe
above
Thestaffdoesnothaveun
derstanding
aboutWorldBank’sOPs/
BPsand othersafeguard
policies. Thepresent
staffhave neverworked
in anymultilateral
agency funded project
The staff does not have
understanding about
World Bank’s OPs/BPs
and other safeguard
policies. The present
staff have never worked
in any multilateral
agency funded project
The staff does not have
understanding about
World Bank’s OPs/BPs
and other safeguard
policies. The present
staff have never worked
in any multilateral
agency funded project
The staff was
notinvolved in any
WorldBank-
fundedprojectbutworke
d in LGCDP project
which was funded
byADBin past (notin
Itahari Municipality)
The staff does not have
understanding about
World Bank’s OPs/BPs
and other safeguard
policies. The present
staff have never worked
in any multilateral
agency funded project
The staff does not have
understanding about
World Bank’s OPs/BPs
and other safeguard
policies. The present
staff have never worked
in any multilateral
agency funded project General
understandingof
Environmental Issues
pertainingto
development
ofinfrastructureproject
Thestaffhadverybasicid
eaof common
environmental impacts
duetoaninfrastructurepr
ojectsuchas impact on
trees, dust generation
etc. however,
theylacked
projectspecific and
location specific
environmentalimpacts.
Thestaffhadverybasicid
eaof common
environmental impacts
duetoan
infrastructureproject.
Thestaff added that
hiring of an
Environmental Expert
forsupervising ESMP
implementation work
wouldbeofhelp.
Thestaffhadverybasicid
eaof common
environmental impacts
duetoaninfrastructurepr
oject. Thestaff added
that hiring of an
Environmental Expert
forsupervising ESMP
implementation work
wouldbeofhelp.
Thestaffhadverygoodund
erstanding of
environmental
concerns/issues as hewas
engagedin preparation of
IEE/ESIA reports.His
current responsibility
also includes monitoring
of
environmentalpollution
Thestaffhad a
verygoodunderstanding
of solid waste
management including
its disposal.
However, had very
generic understanding
of common
environmental impacts
(lacking understanding
of projectspecific
environmentalimpacts)
The staff had
verygeneric
understanding of
common environmental
impacts(lacking
understanding of
project specific
environmentalimpacts)
Understanding of
Environmental
Standards (like
Ambient Air,Noise etc.)
Thestaffhadnoideaof
Environmental
Standards such as on
air, noise and water
quality.
The staff had no in
depth idea of
Environmental
Standards such as on
air, noise and
waterquality
The staff had no in
depth idea of
Environmental
Standards such as on
air, noise and water
quality
The staffhas a very
thorough idea of
Environmental
Standards and current
responsibility includes
issueofPollutionUnderC
ontrol Certificates for
Thestaffhadnoideaof
Environmental
Standards such as on
air, noise and water
quality.
Thestaffhadnoideaof
Environmental
Standards such as on
air, noise and water
quality.
136136136
137137137
Parameters Pokhara Putalibazar Shuklagandaki Itahari Dhankuta S.Haraincha
the operational industries
Understanding ofESIA-
ESMP process
Thestaff had an
understanding about the
purpose of ESIA- ESMP.
However, had never
prepared/reviewed any
ESIA-ESMP
The staff had an
understanding about the
purpose of ESIA- ESMP.
Atmunicipality, the
stafftook helpfrom
external consultant for
preparation of IEE.
However, had never
prepared/reviewed any
ESIA-ESMP
The staff had an
understanding about the
purpose of ESIA- ESMP.
However, had never
prepared/reviewed any
ESIA-ESMP
Thestaffwasengagedin the
preparation of IEE/ESIA
reports for morethan 300
projects.
The staff hadunderstanding
about the purpose of ESIA-
ESMP. However, had
never prepared/reviewed
any ESIA-ESMP
The staff had an
understanding about the
purpose of ESIA- ESMP.
However, had never
prepared/reviewed any
ESIA-ESMP
Role in
StakeholderEngagement
Process
The staff is notinvolved in
stakeholder
engagementprocessesfor
development of
anyinfrastructureprojects.
The staff is notinvolved in
stakeholder
engagementprocesses for
development ofany
infrastructureproject
The staff is notinvolved in
stakeholder
engagementprocessesfor
development of
anyinfrastructureproject
The staff is notinvolved in
stakeholder
engagementprocessesfor
developmentof
anyinfrastructure projects
in the municipality.
However, he had very
fairideaof purpose and
process of stakeholder
engagements in project
development.
The staff is notinvolved in
stakeholder engagement
processfor development of
anyinfrastructureproject.
The staff is notinvolved in
stakeholder engagement
processes for development
of any
infrastructureproject
Experience of
ESMPImplementation
(atleast in supervisory
role)
The
presentEnvironmentalcell
wasnotinvolvedin ESMP
implementation work
forany project in the past
in any capacity and hence
doesnotpossess any
suchexperience.
The
presentEnvironmentalcell
wasnotinvolvedin ESMP
implementation work
forany project in the past
in any capacity and hence
doesnotpossess any such
experience. The
staffaddedthat hiring of an
Environmental Expert
forsupervising EMP
implementation work
wouldbeofhelp.
The present
Environmentalcellwasnoti
nvolvedin ESMP
implementation work
forany project in the past
in any capacity and hence
doesnotpossess any
suchexperience.
The staff’s currentprofile
at municipality
includes monitoring of
efficacyof EMPbeing
adopted in various
industries.
The
presentEnvironmentalcell
was notinvolvedin ESMP
implementation work
foranyprojectin the past in
any capacity and hence
does notpossess any
suchexperience.
ThepresentEnvironmental
cellwasnotinvolvedin
ESMP implementation
work foranyprojectin the
past in any capacity and
hence does notpossess any
suchexperience.
Participation/Role in
resolving Environment
related grievances
Allgrievancesincludingenv
ironmental issues
aredirectlyregisteredin
municipality and are
All grievances including
environmental issues are
directly registered in
municipality and are
All grievances including
environmental issues are
directly registered in
municipality and are
All grievances including
environmental issues are
directly registered in
municipality and are
All grievances including
environmental issues are
directly registered in
municipality and are
All grievances including
environmental issues are
directly registered in
municipality and are
138138138
Parameters Pokhara Putalibazar Shuklagandaki Itahari Dhankuta S.Haraincha handled by
municipality’s judicial committee (Nyayik Samiti). The environmental cell is not involvedinthis process.Grievance can also besubmittedto CAOat Municipality levelor toWard ChairmanatWardLevel
handled by municipality’s judicial committee (Nyayik Samiti). The environmental cell is not involvedinthis process.Grievance can also besubmittedto CAOat Municipality levelor toWard ChairmanatWardLevel
handled by municipality’s judicial committee (Nyayik Samiti). The environmental cell is not involvedinthis process.Grievance can also besubmittedto CAOat Municipality levelor toWard ChairmanatWardLevel
handled by municipality’s judicial committee (Nyayik Samiti).Based on the natureof grievance,the view of Env. Cell is taken as andwhen required. Grievance can also besubmittedto CAOat Municipality levelor toWard ChairmanatWardLevel
handled by municipality’s judicial committee (Nyayik Samiti).Basedon the natureof grievance,the view of Env. Cell is taken as andwhen required. Grievance can also besubmittedto CAOat Municipality levelor toWard ChairmanatWardLevel
handled by municipality’s judicial committee (Nyayik Samiti). TheDisaster Management Officer is partof Nyayik Samity body. Basedon the natureof grievance,the view of Env. Cell is taken as andwhen required. Grievance can also besubmittedto CAOat Municipality levelor toWard ChairmanatWardLevel
InstitutionalAssessmentofSocialDevelopmentDepartmentofVariousMunicipalities
Parameters Pokhara Putalibazar Shuklagandaki Itahari Dhankuta S.Haraincha StrengthofSocialCell Social Cell-6 Staff
(MA-Sociology, MA-
Public Administration,
BA-Sociology, MA-
Anthropology)
Social Cell- 2 Staff
(B.Sc.,)
Social Cell- 3 Staff
(B.A. in Public
Administration,
MastersinEnglishand
LLB)
Social Cell-3 Staff
(MA-Rural
Development, MA-
Sociology, 12th ); 3-4
new staff will be
appointed soon
Social Cell-3 Staff;
(MA-Geography,
PGD-Disaster
Management);
Disaster Management
CellalsopartofSocial
Cell
Social Cell-4 Staff
(MA-Rural
development, B.ED,
BA)
Rolesandresponsibilities Registration of Vital
Events(Birth,Death),
Targeted Group
Development
(Women, Child,
Indigenous People,Sr.
Citizen, Differently
abled), Need based
skill development
programs (vegetable
farming,cattle/poultry,
farming,handicrafts)
Skill
Development,Awarene
ss
Program,Socialsecurity
and registration of vital
events and Co-
ordination and
facilitation of tolevikas
sanstha
WomenEmpowerment
programs, Social
security and
registration of vital
events, Co-ordination
andfacilitation of tole
vikas sanstha.Skill
developmentprograms
onsewing, agriculture,
computer
training,beautyparlora
ndonhandicraftsetc.
Monitoring
&RegistrationofNGOs
,Maintenance of
Record forBirth&
Death, issuanceof
SeniorCitizen /
Differently abled card,
awareness program
forchildren and
women, awarenesson
Gender Based
Violence and ensuring
safety of victim
Social Mobilization-
arrangement for tole
meetings, senior
citizen day care/health
checkup, Janjati
/women/child
development
through3rd party
trainer
(capacitydevelopment
/ skilltraining-sewing,
Driving, plumbing,
mobile
repair,computer
training,
Issuance cards for
Senior
Citizen/Differently
abledperson,Targeted
program for Janjati,
Women, Children
(SkillDevelopment for
Shoemaking,
plumbing, bag
making, sewing etc.
through3rdparties.
139139139
138
Parameters Pokhara Putalibazar Shuklagandaki Itahari Dhankuta S.Haraincha
mushroom farming etc.) Clean cityawareness
programs anddustbin
distribution
Key Expertise/Specialization - - - - - -
Involvement in Project
execution (Planning,
Construction&Operation)
Notinvolved/consulted
during planning of
infrastructure
development project
Notinvolved/consulted
during planning
ofinfrastructure
development project
Notinvolved/consulted
during planning
ofinfrastructure
development project
Notinvolved/consulted
during planning
ofinfrastructure
development project
Notinvolved/consulted
during planning
ofinfrastructure
development project
Notinvolved/consulted
during planning
ofinfrastructure
development project
Ratio of budget allocated to
Socialcelltothetotalbudgetof
themunicipality
Approx.3Cr(lessthan
1% oftotalbudget)
Approx. 5 % of total
budget
Approx. 3 % of total
budget
Approx. 2 % of total
budget
Approx. 13-14% of
totalbudget
Approx. 1% of total
budget
Understanding of social laws
and regulations of Nepal pertaining
to infrastructure
development project suchas land
acquisition,R&R,Gender related,
Vulnerable Communities etc.
Thestaffdoesn’thaveunde
rstanding of social
safeguardlegislationsof
GoN
Thestaffdoesn’thaveunders
tandingof social safeguard
legislationsofGoN
Thestaffdoesn’thaveunder
standing of social
safeguardlegislationsof
GoN
The staff don’t
haveunderstanding of
social
safeguardlegislationsof
GoN
The staff don’t
haveunderstandingof
social
safeguardlegislationsof
GoN
The staff don’t
haveunderstanding of
social
safeguardlegislationsof
GoN
Understanding of World
Bank/ADB Policies/Experience
ofworkingwithanyoftheabove
Thestaffdoesnothave
understanding about
WorldBanks OPs/BPs
and other safeguard
Policiesof Multilateral
Agencies. However, few
of thestaff from social
cell were involved in
consultationandsocial
survey for Talchowk-
Begnas Lake roadin
theUGDP
The staffdonot have
understanding about
WorldBank’s OPs/BPs
and other
safeguardpolicies.
Thepresent
staffhaveneverworked in
anymultilateral agency
funded project
Thestaffdo nothave
understanding about
World Bank’s OPs/BPs
and
otherSafeguardpolicies.T
he presentstaff have
neverworked in any
multilateral agency
funded project
Thestaffdo nothave
understanding about
World Bank’s OPs/BPs
and
otherSafeguardpolicies.T
he presentstaff have
neverworked in any
multilateral agency
funded project
Thestaffdo nothave
understanding about
World Bank’s OPs/BPs
and othersafeguard
policies. However,
oneofthe staff was
engagedin review of
ESIA-ESMP prepared by
external consultantfor
UGDP (ADBfunded)-2
weekly market
development project
The staff do not have
understanding about
World Bank’s OPs/BPs
and
otherSafeguardpolicies.T
he presentstaff have
neverworked in any
multilateral agency
funded project
GeneralunderstandingofSocial
Issues pertainingto developmentof
infrastructure project
The staff hadbasic
understandingof key
social issues and impacts
pertaining todevelopment
of infrastructureproject
The staff had basic
understandingof key
social issues and impacts
pertaining todevelopment
of infrastructureproject
The staff hadbasic
understandingof key
social issues and impacts
pertaining
todevelopment of
infrastructureproject
The staff hadbasic
understandingof key
social issues and impacts
pertaining
todevelopment of
infrastructureproject
The staff hadbasic
understandingof key
social issues and impacts
pertaining
todevelopment of
infrastructureproject
The staff hadbasic
understandingof key
social issues and impacts
pertaining
todevelopment of
infrastructureproject Understanding of
LandAcquisition,R&R Process
Thepresent
staffhadbasicunderstandin
g ofLand Acquisition and
The present staff
hadbasicunderstandingofL
and Acquisition and
Thepresentstaffhadbasic
understanding ofLand
Acquisition and
Thepresentstaffhadbasicu
nderstandingofLand
Acquisition and
Thepresentstaffhad
basicunderstandingofLand
Acquisition and
Thepresentstaffhad
basicunderstandingofLand
Acquisition and
140
Parameters Pokhara Putalibazar Shuklagandaki Itahari Dhankuta S.Haraincha
R&R requirement.
However, theydid not
have detailed
understandingof the
process, entitlements and
other related activities.
R&R requirement.
However, theydidnot
have detailed
understandingof the
process, entitlements and
other related activities.
R&R requirement.
However, they did not
have detailed
understandingof the
process, entitlements and
other related activities
R&R requirement.
However, they did not
have detailed
understandingof the
process, entitlements and
other related activities.
R&R requirement.
However, they did not
have detailed
understandingof the
process, entitlements and
other related activities.
R&R requirement.
However, they did not
have detailed
understandingof the
process, entitlements and
other related activities.
Understanding of ESIA-
ESMPprocess
They hadunderstanding
about the purpose of
ESIA-
ESMP.However,they
have never
prepared/reviewed ESIA-
ESMP
They hadunderstanding
about the purpose of
ESIA- ESMP. However,
they have never
prepared/reviewed ESIA-
ESMP
Thestaffdidnothave
anyunderstanding on
ESIA-ESMP processes
and had neverworked
onpreparingthem.
They hadunderstanding
about the purpose of
ESIA-
ESMP.However,they
have never
prepared/reviewed ESIA-
ESMP
One of the staff
wasengaged in review of
ESIA-ESMP prepared
byexternal consultant
forUGDP(ADB funded)-
2weekly market
development project
They hadunderstanding
about the purpose of
ESIA-
ESMP.However,they
have never
prepared/reviewed ESIA-
ESMP
Role in StakeholderEngagement
Process
The social cell is
notinvolvedin stakeholder
engagement
processesfordevelopmento
fany infrastructureproject
The social cell is not
involved in stakeholder
engagement processes for
development of any
infrastructure project
The social cell is not
involved in stakeholder
engagement processes
for development of any
infrastructure project
The social cell is not
involved in stakeholder
engagement processes
for development of any
infrastructure project
The social cell is not
involved in stakeholder
engagement processes
for development of any
infrastructure project
The social cell is not
involved in stakeholder
engagement processes
for development of any
infrastructure project
Experience ofESMPImplementation
(at least in supervisory role)
Thepresentstaffofthesoci
al cell havenot been
involved in
ESMPimplementation
work of any project inthe
pastand hence donot
possessanysuch
experience.
The present staff of the
social cell have not been
involved in ESMP
implementation work of
any project in the past
and hence donot possess
any such experience.
The present staff of the
social cell have not been
involved in ESMP
implementation work of
any project in the past
and hence donot possess
any such experience.
The present staff of the
social cell have not been
involved in ESMP
implementation work of
any project in the past
and hence donot possess
any such experience.
The present staff of the
social cell have not been
involved in ESMP
implementation work of
any project in the past
and hence donot possess
any such experience.
The present staff of the
social cell have not been
involved in ESMP
implementation work of
any project in the past
and hence donot possess
any such experience.
Participation/Roleinresolving
socialgrievances
All grievances
aredirectly registered in
municipality and
arehandled by the
municipality’s judicial
committee (Nyayik
Samiti). Thesocial cell is
notinvolvedin this
process. Grievances can
also be submittedto the
CAO at Municipality
All grievancesincluding
environmental andsocial
issues are directly
registered in municipality
andare handled by
municipality’s judicial
committee (Nyayik
Samiti).The social cell
isnotinvolvedinthis
All grievancesincluding
environmental andsocial
issues are directly
registered in
municipality andare
handled by
municipality’s judicial
committee (Nyayik
Samiti). The social cell
isnotinvolvedinthis
All grievances
aredirectly registered in
municipality and
arehandled by
municipality’s judicial
committee (Nyayik
Samiti).Grievance can
also besubmittedto CAO
at Municipality level or
to Ward
All grievancesincluding
environmental andsocial
issues are directly
registered in
municipality andare
handled by
municipality’s judicial
committee (Nyayik
Samiti).
All grievancesincluding
environmental issues
are directly registered in
municipality and are
handled by
municipality’s judicial
committee (Nyayik
Samiti). The Disaster
Management Officer
(part of SocialCell)is
141
Parameters Pokhara Putalibazar Shuklagandaki Itahari Dhankuta S.Haraincha
level orto Ward
Chairman atWard Level
process.Grievances can
also be submittedto CAO
at Municipality levelor
toWard Chairman atWard
Level
process.Grievances can
also besubmittedto CAO
at Municipality level
ortoWard Chairman
atWard Level
Chairman at Ward
Level
Based on the nature of
grievance, the view of
Social.Cell is taken as
andwhen required.
Grievances can alsobe
submitted to the CAOat
the Municipality level or
to WardChairman at
Ward Level
part of Nyayik Samity
body. Basedon the nature
of grievance, the view of
Social Cell is taken as
andwhen required.
Grievances can also
besubmitted
toCAOatMunicipality
level orto Ward
Chairman atWard Level
142
Appendix H: Summary Environmental and Social Conditions in the Cluster Municipalities Basic Environmental and Social Conditions inthe Eastern and Western Cluster municipalities
Baseline Environment and Social information in the Eastern Cluster municipalities
Particulars Birtamod Damak Urlabari Sundar
Haraicha
Mechinagar Itahari Rajbiraj Triyuga Dhankuta
ULB Status Municipality Municipality Municipality Municipality Municipality Sub-
metropolitan
Municipality Municipality Municipality
District Jhapa Jhapa Morang Morang Jhapa Sunsari Saptari Udayapur Dhankuta
Population 92,575 87,637 122,803 80,562 176,153 173,312 72,106 87,557 36,619
Sex ratio (F:M) 1.07 1.13 1.14 1.10 1.10 1.11 0.95 1.12
1.13
Municipal area 7824 ha 7086 ha 7462 ha 9890 ha Total: 19261 ha Total: 9378 ha 5527 ha
54744 ha 11084 ha
Physiography Terai Terai Terai Terai Terai Terai Terai Terai Hill
Climatic Zone Tropical Tropical Tropical Tropical Tropical Tropical Tropical Tropical Sub-tropical
Land Use Agriculture
land: 87.05%
Barren:1.46%
Forest: 1.5%
Residential:
5.04%
Sand/
gravel/Boulders:
1%
Shrubland/
grassland: 0.6%
Agriculture
land: 70.32%
Barren: 4.2%
Forest: 7.2%
Residential: 9.35
%
Sand/
gravel/Boulders:
4.7%
Shrubland/
grassland:
4.33%
Agriculture
land: 77.8%
Barren: 7.2%
Forest: 0.9%
Residential:
5.02%
Sand/
gravel/Boulders:
7.8%
Shrubland/
grassland:
1.35%
Agriculture
land: 45.4%
Barren: 0.2%
Forest: 50%
Residential:
1.4%
Sand/
gravel/Boulders:
1.7
Shrubland/
grassland:
1.32%
Agriculture
land: 68.5%
Barren: 9%
Forest: 12.9%
Residential:
2.4%
Sand/
gravel/Boulders:
6.71%
Shrubland/
grassland:
0.52%
Agriculture
land: 72%
Barren:0%
Forest: 13.2%
Residential:
10.5%
Sand/
gravel/Boulders:
2.02%
Shrubland/
grassland: 2.3%
Agriculture
land: 83%
Barren:0%
Forest: 0%
Residential:
7.4%
Sand/
gravel/Boulders:
7.5%
Shrubland/
grassland: 2.3%
Agriculture
land: 13.17%
Barren: 0.6%
Forest: 80%
Residential:
0.2%
Sand/
gravel/Boulders:
5.3%
Shrubland/
grassland: 1.2%
Agriculture
land: 40%
Barren: 0.6%
Forest: 57%
Residential:
0.02%
Sand/
gravel/Boulders:
2.2%
Shrubland/
grassland:
0.27%
Key
municipality
services demand
Road
upgradation;
Drainage;
Solid waste
segregation and
disposal facility;
Increased access
to Water supply
(presently 57%
of the
population has
access to water
Road
upgradation;
Drainage
Upgradation of
urban roads with
drainage;
Solid waste
management;
Landfill site;
Water supply
(currently water
supply network
covers 40% area
of municipality);
Cold storage for
Urban Roads;
Demand of solid
waste
management
facility;
Water supply;
Drainage along
the roads
Urban Roads
and drainage
system;
Solid waste
management
system;
Water Supply
pipeline;
Treatment and
proper
management of
sewage;
Upgradation of
Urban Roads;
Solid Waste
management
and Water
supply pipelines
in rural wards;
Waste Water
treatment;
Parking space;
Public
Transport;
Urban Roads
and drainage
especially from
wards 1 and 9-
16;
Solid Waste
Management
facility for urban
area;
Water Supply
Urban Roads;
Water supply;
Public
transportation;
River protection
works
Drinking Water
Supply;
Drainage; solid
waste
management
and disposal
143
Particulars Birtamod Damak Urlabari Sundar
Haraicha
Mechinagar Itahari Rajbiraj Triyuga Dhankuta
supply
network);
Lack of
treatment and
proper
management of
sanitation;
Parking facility;
traffic
management
agriculture
products
Parking areas;
Better Traffic
management
River
embankment
Key
Environmental
issues
High iron
content in
ground water
Threat to Sal
trees; Dhanesh
Bird
Jaljale wetlands
need protection
blockage of
drainage system
(particularly in
ward no
1,5,8,13)
High iron
content in
ground water
Solid Waste
disposal on river
banks
Flooding in
Mawa, Bakraha,
Sunpakuwa
Khola- and land
cutting at places
High iron
content in
ground water
River bank
erosion
Flooding in
Mechi, Ninda,
Timai, Hadiya
High iron
content in
ground water
Lack of drainage
system &
contamination
of water through
effluent
discharge from
industries
Depletion of
water resources
Disposal of solid
waste on the
bank of rivers or
open field
High iron
content in
ground water
existing water
supply system
unable to cater
the demand of
water to
growing
population
Flooding in
Khado River
Depletion of
ground water
• Pollution due
to sewerage
disposal
Flooding
Deforestation in
southern part
Landslide prone
area in ward no
4,5,6,14,15,16
Threat to water
body due to
siltation
Depletion of
water sources
Social Baseline
Condition
Immigration rate
8-10%
Poverty 7-10%
Child marriage
in Tarai caste,
Muslim and
Adibasi group
Very High
Immigration (5-
7%)
Child marriage
in poor
communities
Limited threat to
Dhimal
community
Ward 3,4, 9 has
Poverty 20%
Child marriage
in Indigenous
group and Terai
caste group
Very High
Immigration
Poverty 10-12 %
Child marriage
in poor in
Chaudahry,
Dum, Jhangar,
Bantar and
Musar
communities
Poverty about
10%
Very High
Immigration (7-
9%)
Child Marrige in
Backward caste
like Tarai dalits,
Muslim and
Adibasi group
Khanar,
Budhikhola,
Very High
Immigration 1:5
in rural areas
Poverty 30-40%
Caste
discrimination
About 10%
woman has land
owner certificate
due to
Very High
Immigration
Limited illegal
mining issue
Some extent to
ethnic
communities
dependent on
fishing and
forest resources
Very High
Immigration
Aathpariya is
one of the
deprived
community
concentrated in
Ward no. 8
144
Particulars Birtamod Damak Urlabari Sundar
Haraicha
Mechinagar Itahari Rajbiraj Triyuga Dhankuta
Dhimal
community
dependent on
forest
Limited threat to
Dhimal
community
Ward 3,4, 9 has
Dhimal
community
dependent on
forest
Sunsari-Morang
Irrigation Canal.
There is
proposal to
construct 6 lane
road. Therefore,
there will be
requirement of
diverting canal
land at the
Tyandra Khola
government tax
incentive policy.
Child marriage
is also among
backward
communities;
Presence of
marginalized
vulnerable
group Musar
and dalits in
ward number
1,2,3,4,5,6,7,8,9,
10,11,12,13
Local
Governance
Tole committee
meetings happen
as per the need,
generally once a
month. On the
local issues;
especially
sanitation,
awareness and
so on. In
Municipality, 50
households have
1 tole
development
committee
They demand
development
plan and budget
to tole
development
committee
Project
identification as
a process.
Sometime, the
municipality
informed the
Effective
governance
system.
Municipality has
420 tole
committees.
Discussion as
per program and
other services
such as road
development,
women right,
child right, drug
issues
Meeting records
are recorded in a
written minute
format
Tole meetings
happen once a
month. On the
local issues;
especially
infrastructure
development
and upgrade;
livelihood
upliftment,
saving and
credit and so on
Project
identification as
a process.
Sometime, the
municipality
informed the
villagers about
the project.
Then they
discuss in tole
and then to
ward, and
municipality and
finally the
municipality
Effective
governance
system.
Municipality
Discussion as
per program and
other services
such as road
development,
Meeting records
are recorded in a
written minute
format
As per the need.
In the
municipality 40-
80 households
have one tole
development
committee.
Generally once a
month. On the
local issues;
especially
saniation,
awareness and
so on.
Project
identification as
a process.
Sometime, the
municipality
informed the
villagers about
the project.
Then they
discuss in tole
and then to
ward, and
municipality and
Effective
governance
system in older
municipal areas
whereas newly
added
municipalities
do not have tole
committees
Project
identification as
a process.
Sometime, the
municipality
informed the
villagers about
the project.
Then they
discuss in tole
and then to
ward, and
municipality and
finally the
municipality
assembly
approve the
project. Without
As per the need,
generally once a
month there is
tole committee
meetings.
Discuss on the
local issues;
especially
infrastructure
development
like drainage
and widening of
existing road
There are 113
tole committee
in the
municipality but
only few are
active and the
large numbers
are inactive
Project
identification as
a process.
Sometime, the
municipality
informed the
Effective
governance
system.
Municipality
Discussion on
project demands
and progress of
ongoing projects
Meeting records
are recorded in a
written minute
format
No major
dispute has
come up, If any,
it will be
resolved through
negotiation; and
provision of
Justice
committee in
Municipality
Effective Tole
system
Discussion as
per program and
other services
such as road
development
Meeting records
are recorded in a
written minute
format
There are 7
steps in planning
process where
public
participation is
ensured
Small disputes
get resolved at
tole committee
level,
municipality
also has Justice
Committee
145
Particulars Birtamod Damak Urlabari Sundar
Haraicha
Mechinagar Itahari Rajbiraj Triyuga Dhankuta
villagers about
the project.
Then they
discuss in tole
and then to
ward, and
municipality and
finally the
municipality
assembly
approve the
project. Without
women and
dalits
participation
project will not
be approved.
assembly
approve the
project. Without
women and
dalits
participation
project will not
be approved.
We follow the
government
policy regarding
the participation
of women and
dalits.
finally the
municipality
assembly
approve the
project. Without
women and
dalits
participation
project will not
be approved.
We follow the
government rule
regarding the
participation of
women and
dalits.
women and
dalits
participation
project will not
be approved.
We follow the
government
policy regarding
the participation
of women and
dalits.
villagers about
the project
through FM.
Then they
discuss in tole
and then to
ward, and
municipality and
finally the
municipality
assembly
approve the
project. Without
women and
dalits
participation
project will not
be approved.
We follow the
government rule
regarding the
participation of
women and
dalits. In each
committee 33%
is women. And
Dalits are also in
committee as
per the GoN
rule.
Availability of
updated
cadastral maps
Updation of
cadastral map is
under process
Cadastral maps
updated almost
entire
municipality (2
wards
remaining)
Cadastral Maps
are not updated.
Cadastral Maps
are updated.
Survey is under
process towards
updating
cadastral maps
Cadastral Maps
are updated.
There is some
confusion about
the extent of
jurisdiction. GIS
Map shows the
land belongs to
Dharan
Cadastral Maps
are not updated.
Updation of
cadastral map is
under process
Cadastral Maps
are not updated.
146
Particulars Birtamod Damak Urlabari Sundar
Haraicha
Mechinagar Itahari Rajbiraj Triyuga Dhankuta
Municipality,
however the
land has been
traditionally
used by Itahari
Sub-
metropolitan
city
Forest Areas One Community
Forest namely
sundarnicha
Jhoda managed
by user group
Community
Forest and
National Forest
present in the
municipality
300-400 ha
Forest Land in
municipality.
Presence of 8
community
forest and 1
collaborative
forest
17 % areas in
municipality is
forest.
7 Community
Forest and 2
collaborative
forest
13 Community
Forests managed
by user groups
Three
Community
Forests in the
municipality
namely
Saraswati,
Hanspokhari
and Santinagar
managed by
User groups
- Community
Forest and
National Forest
in the
municipality
Community
Forest and
National Forest
in the
municipality
Protected
Area/Ramsar
Site
No No No No Chure -
Environmental
Protected Area
No No Chure -
Environmental
Protected Area
No
Source: Stakeholder consultation at Municipalities, Municipality Profiles. This data is based on the available data.
Baseline Information of Western Cluster municipalities (partial)
Baseline Information of Western Cluster municipalities
Particulars Pokhara Leknath Vyas Putalibazar Baglung Tansen Ramgram Tilottama Shuklagandaki
ULB Status Metropolitan Municipality Municipality Municipality Municipality Municipality Municipality Municipality
District Kaski Tanahun Syangia Baglung Palpa Parasi Rupandehi Tanahun
Population 444,936
81,277 70,277
59,919 51,419
62,698
100,149
39,462
Sex ratio 1.10
1.25 1.29
1.24
1.21
1.04
1.12
1.18
Municipal area 46423 ha 24733 ha 14721 ha 9890 ha
10980 ha 9386 ha 12619 ha
147
Particulars Pokhara Leknath Vyas Putalibazar Baglung Tansen Ramgram Tilottama Shuklagandaki
Physiography Hill Hill Hill Hill Hill Terai Terai Hill
Climatic Zone Predominantly
subtropical and
tropical
Tropical Tropical and Sub-
tropical
Tropical Predominantly
subtropical
Tropical Tropical Tropical
Land Use Agriculture land:
40.29%
Barren: 0.63%
Forest: 46%
Residential: 8%
Sand/
gravel/Boulders:
4.5%
Shrubland/
grassland: 0.5%
Agriculture land:
36.4%
Barren: 0.11%
Forest: 57.5%
Residential:
0.32%
Sand/
gravel/Boulders:
3%
Shrubland/
grassland: 2.8%
Agriculture land: 48%
Barren: 0.02%
Forest: 50%
Residential: 1.4%
Sand/ gravel/Boulders:
1.8%
Shrubland/ grassland:
1.32%
Agriculture land:
45.4%
Barren: 0.2%
Forest: 50%
Residential:
1.4%
Sand/
gravel/Boulders:
1.7
Shrubland/
grassland: 1.32%
Agriculture land:
58.4%
Barren: 0.7%
Forest: 36%
Residential: 2.8%
Sand/
gravel/Boulders:
1.8%
Shrubland/
grassland: 0.4%
Agriculture land:
90.5%
Barren: 0.72%
Forest: 0.1%
Residential:
3.4%
Sand/
gravel/Boulders:
2.71%
Shrubland/
grassland: 2.45%
Agriculture land:
69.48%
Barren: 0.4%
Forest: 10%
Residential: 15%
Sand/
gravel/Boulders:
2.1%
Shrubland/
grassland: 3.5%
Key municipality
services demanded • Road
Upgradation
• Solid waste
management in
rural wards
• Water supply in
rural wards
• Drainage along
the roads
• Public
Transportation
• Solid waste
management
facility (
especially for
6 to 14
wards)
• Solid waste
management
• Water supply
(lacking in
wards 1,4,5)
• Road
upgradation
and drainage
Road upgradation;
Drainage
Management;
Safe and pure drinking
water
• Urban roads
and drainage
• Safe and pure
drinking water,
• Sewage
management
• Urban roads
and drainage
• Solid waste
collection.
Segregation and
disposal
• Sewage
management
• Drinking water
suuply
• Bus Terminal
• Road
upgrade;
• Drainage
Management
• Solid waste
management
• Water supply
• Transportatio
n in rural
wards
• Road upgrade;
• Drainage
Management
• solid waste
management,
• water supply
• Road
upgradation
• Drainage
Management,
• safe drinking
water,
• solid waste
management
Key
Environmental
issues
Flooding in Seti
and Mardi River • Flooding in
Madi & Seti
River
• Water
pollution in
some
stretches
• Flooding in Aandhi
khola, sumrekhola,
bodikhola, ringi
khola
• Water Pollution
and siltation
especially during
rainy season
During rainy
season there is
problem of
flooding, water
pollution,
siltation,
landslide
During rainy
season there is
problem of
flooding, water
pollution,
siltation,
landslide in
nearby areas of
• Flooding in
Tinahu river
• Water
pollution in
dug wells
• Flooding in
Tinahu river
• Water pollution
in dug wells
• Flooding in the
rivers and
siltation in rainy
season
• River pollution
from crusher
plants located
near the river
148
Particulars Pokhara Leknath Vyas Putalibazar Baglung Tansen Ramgram Tilottama Shuklagandaki
Aandhi khola,
sumrekhola,
bodikhola, ringi
khola
Key social issues - Poverty rate
20%
Poverty rate 25% Poverty rate
35%
Poverty rate 15% Immigration
from hilly region
and rural wards
Poverty rate
30%
Poverty rate of
15%
Poverty rate 20%
Local Governance
Level • As per law,
project
identification
starts from tole
committee
andthe demand
is forwarded to
wards and
Municipality
Council
approves the
program
• One Judicial
Committee is
at municipality
to take action
on public
complaints.
• A Cell is there
to register
gender based
grievances and
take necessary
action on that
• Tole
meetings are
conducted
once in a
month
• there are 235
tole
committee in
the
municipality
• Tole
committees
are the
lowest level
unit =for
project
identificatio
and also
works for
implementati
on
• One Judicial
Committee
is there at
municipality
to take
action on
public
complaints
• 120 Tole
committee are
there in the
municipality
• Issues like need for
road development,
women right, child
right etc. are
discussed
• Tole committees
are the lowest
level unit for
project
identification and
also works for
implementation
• Municipality plays
roles to address
these issues
• 80 Tole
committee are
there in the
municipality
• Issues like
road
development,
women right,
child right,
sanitation etc.
are discussed
• Tole
committees are
the lowest
level unit for
project
identification
and also works
for
implementatio
n
•
• 100 Tole
committee are
there in the
municipality
• Issues like road
development,
women right,
child right,
sanitation etc.
are discussed
• Tole
committees are
the lowest level
unit for project
identification
and also works
for
implementation
• One Judicial
Committee is
there at
municipality to
take action on
public
complaints
• Tole
meetings
once in a
month
• 235 Tole
committee
are there in
the
municipality
• Issues like
road
development,
women right,
child right,
sanitation etc.
are discussed
As per law, project
identification starts
from tole
committee and the
demand is
forwarded to wards
and Municipality.
Municipality
Council approves
the program
As per law, project
identification starts
from tole
committee and the
demand is
forwarded to wards
and Municipality.
Municipality
Council approves
the program
149
Particulars Pokhara Leknath Vyas Putalibazar Baglung Tansen Ramgram Tilottama Shuklagandaki
Forest Areas • Community
Forest and
National Forest
present in the
municipality
• Community
Forest and
National
Forest
present in the
municipality
• Community Forest
and National
Forest present in
the municipality
• Community
Forest and
National
Forest
present in the
municipality
• Community
Forest and
National
Forest present
in the
municipality
• Community
Forest and
National Forest
present in the
municipality
• Community
Forest and
National Forest
present in the
municipality
Protected
Area/Ramsar Site • Ramsar Site-
Lake Cluster of
Pokhara Valley
• Municipality
boundary
overlaps with
southern part’s
Annapurna
Conservation
Area
No No No No No No No
Source: Stakeholder consultation at Municipalities, Municipality Profiles, This data is based on the available data.
150
Appendix I: Summary Information on the Type of Baseline Indicators
Description of Environmental Baseline Information Required for Road Project
Environmental
Components/Concerns Baseline Information Source (Primary / Secondary)
Physical Environment
Geography Geographical information of Project Area
Location, physiography, geology, slope and elevation, drainage pattern, seismology, topography, landslide prone zones, flood
plain and contour map.
Secondary
Weather and
Climatology
Long term climatological profile of the project area
Temperature (max/min), precipitation
Secondary
Land Use Land Use pattern of immediate zone of Impact and Project Influence Area (PIA)
Cadastral map/land ownership document/record [only for new road] for immediate Zone of Impact and topographic and GIS
map for of PIA
Secondary
Ambient Air Ambient Air Quality (at highest traffic volume area and closest recipient at the interval of 10km)
• Level of PM10, PM2.5, CO, SO2, NOx
• Inventory of sensitive receptors like school, college, and hospital in the vicinity of the project area
•
Primary in case of site specific
secondary data of present time is
not available
Ambient Noise Ambient Noise Level (at highest traffic volume area and closest recipient at the interval of 10km), if primary data to be
generated.
• Day and night time Noise Levels
• Inventory of sensitive receptors like school, college, and hospital in the vicinity of the project area
• Inventory of major noise generating sources/industries in PIA
Primary in case of site specific
secondary data of present time is
not available
Water Information on ground and surface water resources (only in new road construction)
• Information of surface water resources in the PIA including tentative quantity, use and its distance from project site
• Information on hydrogeology and availability of groundwater table(upto 10 m. below the road surface)
Secondary-Hydrogeology and
ground water availability
Primary- quality monitoring and
inventory of surface water
resources
Soil Nature of soil in the RoW
• Soil profile
Nature of soil and fertility in the
RoW Secondary
Soil Quality- Secondary (DPR)
Natural Hazard Natural Hazard Threat
• Records on natural calamity like earthquake, flood, , drought, famine, etc. in the project area supported with local
consultation
Secondary
Debris Disposal Site Identification of Debris Disposal Site, mainly for new alignment.
Tentative site for disposal of dismantled/construction debris may be identified, if scarifying is expected.
Secondary
Quarry Sites and
Borrow Areas
Identification of Licensed Quarry Sites and Borrow Areas
Probable Borrow Areas and Quarry sites to be used in the sub project should be listed out with lead distance and mode of
Secondary
151
Description of Environmental Baseline Information Required for the Water Supply Project
transportation
Biological Environment
Felling of Trees and
Clearance of Vegetation
Cover
Trees falling within direct impact zone
• Listing with coordinate of species, girth size of trees and poles within RoW
• Information of endemic, endangered, medicinal, protected species in 50 meter from road edge
• Information on offset areas for compensation plantation
• List ofProtected Tree Species in RoW
Primary
Forest Area Forest within the proposed RoW
• Legal status of forest land
• Block/Compartment Number of the forest area concerned
• Extent of Forest area to be acquired
• Delineation of affected forest area on map (cadastral map preferably)
• Threat to associated biodiversity (flora and fauna)
• Information of endemic, endangered, medicinal, protected species (flora and fauna)
Primary and Secondary
Protected
Area/Ecologically
Sensitive Areas/
Ramsar Sites/Important
Bird Areas
Protected Area/Ecologically Sensitive Areas/ Ramsar Sites/Important Bird Areas in PIA
• Information on presence of Protected Area (National Parks, Wildlife Reserve, Hunting Reserve, Conservation Areas,
Buffer Zones) / site of ecological importance like nesting, breeding ground, important bird areas, Ramsar sites,
wildlife corridor/migration route, forest areas, any site of national/international importance etc. within PIA.
Information should include GIS map showing distance of protected area site from the road alignment, its ecological
condition and biodiversity
Primary and Secondary
Biodiversity Floral and faunal community of PIA
• Floral and faunal community of PIA
• Biodiversity of aquatic system
• Endangered/Vulnerable/rare/critically endangered species as per IUCN red list
• record of local extinction of any species or declining species (population decreasing day by day
Secondary information through
stakeholder consultation, literature study
followed by primary survey
Environmental
Components/Concerns
Baseline Information Source (Primary / Secondary)
Physical Environment
Geography Geographical information of project area
Location, physiography, geology, slope and elevation, drainage pattern, seismology, topography, landslide prone zones,
flood plain.
Contour map, flood passages and information on high levels flood periodicity as available data
Secondary
Weather and
Climatology
Long term climatological profileof the project area
Temperature (max/min), precipitation, , record of natural calamity
Secondary
152
Land Use Land Use pattern of Impact area including service areas and Project Influence Area (PIA)
Cadastral map/land ownership document/record of RoW and topographic and GIS maps of PIA
Secondary
Ambient Air Baseline condition of Ambient Air Quality
Primary in case of site specific secondary
data of present time is not available
Ambient Noise Baseline condition of Ambient Noise Level through primary 24hr Monitoring
• Day and night time noise level
• Inventory of sensitive receptors like school, college, hospital etc. in the immediate impact area
Primary in case of site specific secondary
data of present time is not available
Water Information on ground water and surface water resources
• Surface water resources in the PIA including tentative capacity, use and its distance from project site
• Information on Ground water table
• Ground and surface water quality of the PIA, ( if t is to be used as source)
Secondary-Hydrogeology and ground
water availability
Primary- Quality monitoring and
inventory of Surface water resources
Soil Nature of soil
• Nature and type of soil
Nature of soil and fertility in the PIA-
Secondary
Soil Quality-Secondary
Natural Hazard Threat from Natural Hazard
• Records on natural calamity like earthquake, flood, , drought, famine, epidemic, wildfire etc. in the project area
supported with local consultation
• Land slide prone /geologically unstable slope areas with respect to GPS Coordinate
Secondary
Debris Disposal Site Identification of debris disposal site, if the pipe to be laid is more than 500 mm diameter
Tentative site for disposal of dismantled/construction debris may be identified
Secondary
Biological Environment
Felling of Trees and
clearance of Vegetation
Cover
Trees falling within Raw of road
• Listing of species, girth size of affected trees and poles with location
• Information of endemic, endangered, medicinal, protected species
• List of affected protected tree species
Primary
Forest Area Acquisition of forest land for the project
• Legal status of forest land proposed for acquisition
• Block/compartment number of the area concerned
• Extent of Forest area to be acquired
• Delineation of affected forest area on map (Cadastral Map preferably)
• Threat to associated biodiversity (flora and fauna)
• Information of endemic, endangered, medicinal, protected species (flora and fauna)
Primary and Secondary
Protected
Area/Ecologically
Sensitive Areas/
Ramsar Sites/Important
Ecological condition of PIA
• Information on presence of Protected Area (National Parks, Wildlife Reserve, Hunting Reserve, Conservation Areas,
Buffer Zones) / site of ecological importance like nesting, breeding ground, Important Bird Areas, Ramsar Sites,
Wildlife Corridor/Migration Route, Forest Areas, any site of national/international importance etc. within PIA.
Secondary
153
Description of Environmental Baseline Information required for Wastewater ManegementProject
Bird Areas Information should include GIS Map showing distance of Protected Area site from project site, its ecological
condition and biodiversity
• Record of local extinction of any species or declining species (population decreasing day by day)
Biodiversity Floral & Faunal Community of PIA
• Floral and faunal community of PIA
• Biodiversity of aquatic system in case its within PIA
• Endangered/vulnerable/rare/critically endangered species as per IUCN red list
Secondary information through
stakeholder consultation, literature study
followed by primary survey
Environmental
Components/Concerns
Baseline Information Source (Primary / Secondary)
Physical Environment
Geography Geographical information of Project Area
Location, physiography, geology, slope and elevation, drainage pattern, , topography, landslide prone zones, flood plain
and river morphology.
Contour map, drainage, flood passages and information on high levels flood periodicity of available data
Secondary
Weather and
Climatology
Long term climatological profile of the project area
Temperature (max/min), precipitation, wind direction at the treatment site, wind speed, cloud cover, humidity, record of
natural calamity
Secondary
Land Use Land Use pattern of immediate zone of Impact and Project Influence Area (PIA) around the treatment site.
Cadastral Map/Land Ownership document/Record for immediate Zone of Impact by treatment site&Topographic and
GIS maps for Project Influence Area (PIA)
Secondary
Ambient Air Baseline condition of Ambient Air Quality at treatment site
• Level of CO2, SO2, NOxInventory of sensitive receptors like school, college, hospital etc. in the vicinity of the
treatment site
Primary in case of site specific secondary
data of present time is not available
Ambient Noise Baseline condition of Ambient Noise Level in receipants close to project foot prints through primary Monitoring
Day and night time noise level
• Inventory of sensitive receptors like school, college, and hospital in the vicinity of the project area
Primary in case of site specific secondary
data of present time is not available
Water Information on ground water and surface water resources
• Inventory surface water resources in the PIA including tentative capacity, use and its distance from project site
• Information on hydrogeology at the treatment site
•
Secondary-Hydrogeology
Primary- Quality monitoring and
inventory of Surface water resources
Soil Nature of soil Nature and type of soil
• Soil profile
Nature of soil and fertility in the PIA-
Secondary
154
Description of Environmental Baseline Information required for Solid Waste Management Project
Soil Quality- Secondary (DPR)
Natural Hazard Threat from Natural Hazard
• Records on natural calamity like flood, , epidemic, etc. in the project area supported with local consultation
• Land slide prone /geologically unstable slope areas with respect to GPS Coordinate
Secondary
Debris Disposal Site Identification of Debris Disposal Site, if the conveyance size is more than 0.25 sq.m.
Tentative site for disposal of dismantled/construction debris may be identified
Secondary (to be validated through
stakeholder consultation)
Biological Environment
Felling of Trees and
clearance of Vegetation
Cover
Trees falling within direct impact zone [construction site]
• Listing of Species, Girth size of affected Trees & Poles with respect to GPS Coordinates
• Information of Endemic, Endangered, Medicinal, Protected species
• Details of affected protected tree species
Primary
Forest Area Acquisition of forest land for the project
• Legal status of forest land proposed for acquisition
• Block/Survey/Compartment No. of the area concerned
• Extent of Forest area to be acquired
• Delineation of affected forest area on map (Cadastral Map preferably)
• Threat to associated biodiversity (Flora & Fauna)
• Information of Endemic, Endangered, Medicinal, Protected species (Flora & Fauna)
Primary and Secondary
Protected
Area/Ecologically
Sensitive Areas/
Ramsar Sites/Important
Bird Areas
Ecological condition of treatment site
• Information on presence of Protected Area (National Parks, Wildlife Reserve, Hunting Reserve, Conservation Areas,
Buffer Zones) / site of ecological importance like nesting, breeding ground, Important Bird Areas, Ramsar Sites,
Forest Areas, any site of national/international importance etc. within PIA. Information should include GIS Map
showing distance of Protected area site from project site, its ecological condition and biodiversity
Secondary
Biodiversity Floral and faunal community of PIA
• Floral and faunal (community of PIA
• Biodiversity of aquatic system in case its within PIA
• Endangered/vulnerable/rare/critically endangered species as per IUCN red list
Secondary information through
stakeholder consultation, literature
study followed by primary survey
Record of communicable
diseases
Collect data on communicable diseases in an around proposed treatment plant Secondary information
Environmental
Components/Concerns
Baseline Information Source (Primary / Secondary)
Physical Environment
Geography Geographical information of Project Area
Location, physiography, geology, slope and elevation, drainage pattern, seismology, topography, landslide prone
Secondary
155
zones, flood plain and river morphology.
Contour map, , flood passages and information on high levels flood periodicity of maximum available data
Weather and Climatology Long term climatological profile of the project area
Temperature (max/min), precipitation, wind direction, wind speed, cloud cover, humidity, record of natural calamity
Secondary
Land Use Land Use pattern of immediate zone of Impact and Project Influence Area (PIA) around the Sanitary
Management Site and route from transshipment site
Cadastral map/land ownership document/record of around the Sanitary management site and 50 m on both sides from
the transshipment routeand topographic and GIS maps for Project Influence Area (PIA)
Secondary
Ambient Air
Baseline condition of Ambient Air Qualityat proposed Sanitary management site
• Level of PM10, PM2.5, CO2, SOx, NOx, HC
• Indicators for odour, communicable dieses and vectors like moscutoes and fliees be added
• Inventory of sensitive receptors like school, college, hospital etc. in the vicinity of the project area
Primary in case of site specific
secondary data of present time is
not available
Ambient Noise
• Noise measurement at nearest receptor Primary in case of site specific
secondary data of present time is
not available
Water Information on ground water and surface water resources at and downstream of the sanitary management site.
• Inventory Surface Water resources including tentative quantity, use and its distance from project site
Quality of Ground and Surface Water at the sanitary management site through primary monitoring
Secondary-Hydrogeology
Primary- Quality monitoring and
inventorization of Surface water
resources
Soil • Nature and type of soil
• Soil profile
Nature of soil and fertility in the
PIA- Secondary
Soil Quality-Primary
Natural Hazard Threat from Natural Hazard
• Records on natural calamity like flood, epidemic, wildfire etc. in the Sanitary management area supported with
local consultation
• Land slide prone /geologically unstable slope areas near the Sanitary Management Sitewith respect to GPS
Coordinate
Secondary
Biological Environment
Felling of Trees and clearance
of Vegetation Cover
Trees falling within direct impact zone Sanitary management site and transshipment route
• Listing of Species, Girth size of affected Trees & Poles with respect to GPS Coordinates
• Information of Endemic, Endangered, Medicinal, Protected species
• Information on offset areas for tree plantation
• List of affected Protected Tree Species
Primary
Forest Area Acquisition of forest land for the project
• Legal status of forest land proposed for acquisition
• Block/Survey/Compartment No. of the area concerned
• Extent of Forest area to be acquired
• Delineation of affected forest area on map (Cadastral Map preferably)
• Threat to associated biodiversity (Flora & Fauna)
Primary and Secondary
156
Description of Environmental Baseline Information required for Stormwater Drainage Project
• Information of Endemic, Endangered, Medicinal, Protected species (Flora & Fauna)
Protected Area/Ecologically
Sensitive Areas/ Ramsar
Sites/Important Bird Areas
Ecological condition of PIA
• Information on presence of Protected Area (National Parks, Wildlife Reserve, Hunting Reserve, Conservation
Areas, Buffer Zones) / site of ecological importance like nesting, breeding ground, Important Bird Areas, Ramsar
Sites, Wildlife Corridor/Migration Route, Forest Areas, any site of national/international importance etc. within
PIA. Information should include GIS Map showing distance of Protected area site from project site, its ecological
condition and biodiversity
• record of local extinction of any species or declining species (population decreasing day by day)
In case proposed land fill site is located within PIA, a detailed ecological assessment may be undertaken. The study
should cover biological diversity, species richness of the area; seasonal, Diurnal and nocturnal movement of wildlife
towards project site; probable threat from proposed project and suggested mitigation in consultation with concerned
stakeholders
Primary and Secondary
Biodiversity Floral & Faunal community of PIA
• Floral and faunal community of PIA
• Biodiversity of aquatic system in case its within PIA and 200 m downstream where treated latchet and accidental
seepage will merge.
• Endangered/Vulnerable/rare/critically endangered species as per IUCN red list
• occurrence of Protected Species in PIA
Secondary information through
stakeholder consultation, literature
study followed by primary survey
Environmental
Components/Concerns
Baseline Information Source (Primary / Secondary)
Physical Environment
Geography Geographical information of Project Area
Location, Physiography, Geology, Slope & Elevation, Drainage Pattern, seismology, topography, landslide prone
zones, Flood plain & River Morphology.
Contour map, details of micro drainage, flood passages and information on high levels flood periodicity at least of last
50 years in the area
Secondary
Weather and Climatology Long term climatological profileof the project area
Temperature (Max/Min), Precipitation, record of natural calamity
Secondary
Land Use Land Use pattern of Project Influence Area (PIA) [Cadastral Map/Land Ownership document/Record for
immediate Zone of Impact & Topo Sheet and GIS Map for Project Influence Area (PIA)
Details of wetland and water log area, even if they are seasonal.
Secondary
Ambient Air Baseline condition of Ambient Air Quality [Level of PM10, PM2.5
• Inventory of sensitive receptors like school, college, hospital etc. in the vicinity of the project area
Primary in case of site specific
secondary data of present time is
not available
Ambient Noise Baseline condition of Ambient Noise Level through primary Monitoring [How does it relate? Primary in case of site specific
secondary data of present time is
not available
Water Information on ground water and surface water resources Secondary-Hydrogeology
157
• Inventory Surface Water resources in the PIA including tentative capacity, use and its distance from project site
Quality of Ground and Surface Water of the PIA through primary monitoring
Primary- Quality monitoring and
inventorization of Surface water
resources
Soil Nature of soil and fertility in the PIA
Nature and type of soil
• Soil profile
Nature of soil and fertility in the
PIA- Secondary
Soil Quality-Primary
Natural Hazard Threat from Natural Hazard
• Records on natural calamity like flood, drought, famine, epidemic, etc. in the project area supported with local
consultation
• Land slide prone /geologically unstable slope areas with respect to GPS Coordinate
• Prevalence of water born dieses especially mosquito vectored.
Secondary
Debris Disposal Site Identification of Debris Disposal Site
Tentative site for disposal of dismantled/construction debris may be identified
Secondary (to be validated through
stakeholder consultation)
Biological Environment
Felling of Trees and clearance
of Vegetation Cover
Trees falling within construction area.
• Listing of Species, Girth size of affected Trees & Poles with respect to GPS Coordinates
• Information of Endemic, Endangered, Medicinal, Protected species
• List of affected Protected Species of trees
Primary and secondary
Forest Area Acquisition of forest land for the project
• Extent of Forest area to be acquired (including Legal status of forest land,Block/Survey/Compartment No. of the
area concerned)
• Delineation of affected forest area on map (Cadastral Map preferably)
• Threat to associated biodiversity (Flora & Fauna)
• Information of Endemic, Endangered, Medicinal, Protected species (Flora & Fauna)
Primary and Secondary
Protected Area/Ecologically
Sensitive Areas/ Ramsar
Sites/Important Bird Areas
Ecological condition along the drain site
• Information on presence of Protected Area (National Parks, Wildlife Reserve, Hunting Reserve, Conservation
Areas, Buffer Zones) / site of ecological importance like nesting, breeding ground, Ramsar Sites and other wetland
and seasonal water logged area, Wildlife Corridor/Migration Route, Forest Areas, any site of national/international
importance etc. around the intervention (especially construction and diversion) site. Information should include GIS
Map showing distance of Protected area site from project site, its ecological condition and biodiversity
Secondary
information through stakeholder
consultation,
Biodiversity Floral & Faunal
Secondary information through
stakeholder consultation,
158
Appendix J: List of Ineligible Sub-Projects
Road sector
• New roads, road rehabilitation, road-surfacing or track upgrading of any kind inside critical natural habitats, forests, environmentally sensitive areas, protected areas (National Parks,
Wildlife Reserve, Hunting Reserve, Conservation Areas etc.), significant biodiversity and/or protected conservation zones
• Projects that may cause, or have the potential to result in permanent and/or significant damage to non-replicable cultural property, irreplaceable cultural relics, historical buildings and/or
archaeological sites
• Projects that may significantly convert or provide access into critical natural habitats or negatively affect rare or endangered species and their natural habitats
• New road construction that may cause habitat fragmentation and impact the wildlife corridors
• The projects that may result in large-scale involuntary land acquisition or significant physical displacement of affected communities or relocation of Indigenous Peoples that would restrict
or cease their access to traditional lands or resources
• Projects that does not meet minimum design standards with poor design or construction quality, particularly if located in vulnerable areas
Water supply
• Greenfield water supply projects: Projects involving withdrawal of surface water which may have a significantly reduce and create negative impacts13 on the quality, quantity and velocity of
the environmental flows that would affect the physical and ecological conditions, biodiversity (terrestrial and aquatic life) and ecosystem services of the surface water course at any point in
the water channel and its tributaries (from upstream, midstream and downstream).
• Brownfield water supply projects: Projects which result in the increased demand from the existing water source and if the watershed or aquifer feeding this source is not sufficient to meet
the increased demand14.
• Projects that will adversely affect the water supply and livelihoods of the communities in the project’s area of influence
• Projects which may result in abstraction of ground water in ground water stressed areas
• Projects that pass through critical natural habitats, forests, environmentally sensitive areas, significant biodiversity and/or protected conservation zones, protected areas (National Parks,
Wildlife Reserve, Hunting Reserve, Conservation Areas etc.)
• Projects that may cause, or have the potential to result in, permanent and/or significantly damage to non-replicable cultural property, irreplaceable cultural relics, historical buildings and/or
archaeological sites
• The projects that will result in large-scale involuntary land acquisition or significant physical displacement of affected communities, or relocation of Indigenous Peoples that would restrict
or cease their access to traditional lands or resources
• If the project would rely on the performance of an existing dam. The large dam (with a height of more than 15 m) triggers dam safety due diligence process and OP 4.37
Wastewater
13 To be assessed through detailed study of water availability, ecological assessment, assessment of permissible volume of water 14 To be assessed by determination of a water balance of the location of the water source and the demand from the existing water supply network and any informal extraction from deep wells,
shallow wells etc. to ensure that the replenishment rate in the water source is greater than the extraction rate of the water
159
• Treatment plant and effluent discharge is located/proposed to be located in critical natural habitats, forests, environmentally sensitive areas, significant biodiversity and/or protected
conservation zones, protected areas (National Parks, Wildlife Reserve, Hunting Reserve, Conservation Areas etc.) and environmentally fragile areas
• Projects that will cause, or have the potential to result in, permanent and/or significantly damage to non-replicable cultural property, irreplaceable cultural relics, historical buildings and/or
archaeological sites
• Projects that will adversely affect the water supply and livelihoods of the communities in the project’s area of influence
• The projects that will result in large-scale involuntary land acquisition or significant physical displacement of affected communities or relocation of Indigenous Peoples that would restrict or
cease their access to traditional lands or resources;
• Construction of wastewater treatment plant which receives industrial or hazardous influent without any pre-treatment to ensure that any incoming wastewater will not upset the designed
treatment process
Solid waste management
• Construction of a new landfill near a surface water body or aquifer, with the possibility of untreated leachate draining or contaminating any source of water supply, surface water or
groundwater resource or communities in the project’s area of influence
• Landfill site is proposed to be located in critical natural habitats, forests, environmentally sensitive areas, significant biodiversity and/or protected conservation zones, protected areas
(National Parks, Wildlife Reserve, Hunting Reserve, Conservation Areas etc.) and environmentally fragile area
• Construction of new landfill disposal site which may result in large-scale involuntary land acquisition or significant physical displacement of affected communities or relocation of
Indigenous Peoples that would restrict or cease their access to traditional lands or resources
• Waste to Energy projects with the installed capacity of greater than 25 MW or lower capacities with no air pollution control device or residual waste treatment process
• Projects involving management of significant quantities of toxic waste – toxic waste is defined as waste containing chemicals or materials that are capable of causing injury/death to life
having poisonous, radioactive, explosive, carcinogenic, mutagenic or teratogenic properties.
Storm water drainage system
• Storm water drainage network development or upgradation along new roads or existing roads inside critical natural habitats, forests, environmentally sensitive areas, protected areas
(National Parks, Wildlife Reserve, Hunting Reserve, Conservation Areas etc.), significant biodiversity and/or protected conservation zones
• Projects that would curtail, divert or reduce the environmental flows of surface water courses away from sources of water supply, agricultural lands or important water resources
• Storm water drainage projects resulting in the siltation or contamination of any surface water or groundwater resource or communities in the project’s area of influence
• Storm water drainage projects along New road construction that may cause habitat fragmentation and impact the wildlife corridors
0
Appendix K: COVID-19 considerations in construction/civil works projects
ESF/SAFEGUARDS INTERIM NOTE: COVID-19 CONSIDERATIONS IN
CONSTRUCTION/CIVIL WORKS PROJECTS
This note was issued on April 7, 2020 and includes links to the latest guidance as of this date (e.g. from WHO).
Given the COVID-19 situation is rapidly evolving, when using this note it is important to check whether any updates
to these external resources have been issued.
1. INTRODUCTION
The COVID-19 pandemic presents Governments with unprecedented challenges. Addressing COVID-19 related issues
in both existing and new operations starts with recognizing that this is not business as usual and that circumstances
require a highly adaptive responsive management design to avoid, minimize and manage what may be a rapidly
evolving situation. In many cases, we will ask Borrowers to use reasonable efforts in the circumstances, recognizing
that what may be possible today may be different next week (both positively, because more supplies and guidance may
be available, and negatively, because the spread of the virus may have accelerated).
This interim note is intended to provide guidance to teams on how to support Borrowers in addressing key issues
associated with COVID-19 and consolidates the advice that has already been provided over the past month. As such, it
should be used in place of other guidance that has been provided to date. This note will be developed as the global
situation and the Bank’s learning (and that of others) develops. This is not a time when ‘one size fits all’. More than
ever, teams will need to work with Borrowers and projects to understand the activities being carried out and the risks
that these activities may entail. Support will be needed in designing mitigation measures that are implementable in the
context of the project. These measures will need to take into account the capacity of the Government agencies,
availability of supplies and the practical challenges of operations on-the-ground, including stakeholder engagement,
supervision and monitoring. In many circumstances, communication itself may be challenging, where face-to-face
meetings are restricted or prohibited, and where IT solutions are limited or unreliable.
This note emphasizes the importance of careful scenario planning, clear procedures and protocols, management
systems, effective communication and coordination, and the need for high levels of responsiveness in a changing
environment. It recommends assessing the current situation of the project, putting in place mitigation measures to avoid
or minimize the chance of infection, and planning what to do if either project workers become infected or the work
force includes workers from proximate communities affected by COVID-19. In many projects, measures to avoid or
minimize will need to be implemented at the same time as dealing with sick workers and relations with the community,
some of whom may also be ill or concerned about infection. Borrowers should understand the obligations that
contractors have under their existing contracts (see Section 3), require contractors to put in place appropriate
organizational structures (see Section 4) and develop procedures to address different aspects of COVID-19 (see Section
5).
2. CHALLENGES WITH CONSTRUCTION/CIVIL WORKS
Projects involving construction/civil works frequently involve a large work force, together with suppliers and
supporting functions and services. The work force may comprise workers from international, national, regional, and
local labor markets. They may need to live in on-site accommodation, lodge within communities close to work sites or
return to their homes after work. There may be different contractors
permanently present on site, carrying out different activities, each with their own dedicated workers. Supply chains may
involve international, regional and national suppliers facilitating the regular flow of goods and services to the project
(including supplies essential to the project such as fuel, food, and water). As such there will also be regular flow of
parties entering and exiting the site; support services, such as catering, cleaning services, equipment, material and
supply deliveries, and specialist sub-contractors, brought in to deliver specific elements of the works.
Given the complexity and the concentrated number of workers, the potential for the spread of infectious disease in
projects involving construction is extremely serious, as are the implications of such a spread. Projects may experience
large numbers of the work force becoming ill, which will strain the project’s health facilities, have implications for local
emergency and health services and may jeopardize the progress of the construction work and the schedule of the
project. Such impacts will be exacerbated where a work force is large and/or the project is in remote or under-serviced
areas. In such circumstances, relationships with the community can be strained or difficult and conflict can arise,
particularly if people feel they are being exposed to disease by the project or are having to compete for scarce resources.
The project must also exercise appropriate precautions against introducing the infection to local communities.
3. DOES THE CONSTRUCTION CONTRACT COVER THIS SITUATION?
Given the unprecedented nature of the COVID-19 pandemic, it is unlikely that the existing construction/civil works
contracts will cover all the things that a prudent contractor will need to do. Nevertheless, the first place for a Borrower
to start is with the contract, determining what a contractor’s existing obligations are, and how these relate to the current
situation.
1
The obligations on health and safety will depend on what kind of contract exists (between the Borrower and the main
contractor; between the main contractors and the sub-contractors). It will differ if the Borrower used the World Bank’s
standard procurement documents (SPDs) or used national bidding documents. If a FIDIC document has been used, there
will be general provisions relating to health and safety. For example, the standard FIDIC, Conditions of Contract for
Construction (Second Edition 2017), which contains no ‘ESF enhancements’, states (in the General Conditions, clause
6.7) that the Contractor will be required:
• to take all necessary precautions to maintain the health and safety of the Contractor’s Personnel
• to appoint a health and safety officer at site, who will have the authority to issue directives for the purpose of
maintaining the health and safety of all personnel authorized to enter and or work on the site and to take protective
measures to prevent accidents
• to ensure, in collaboration with local health authorities, that medical staff, first aid facilities, sick bay, ambulance
services and any other medical services specified are available at all times at the site and at any accommodation
• to ensure suitable arrangements are made for all necessary welfare and hygiene requirements and for the prevention of
epidemics
These requirements have been enhanced through the introduction of the ESF into the SPDs (edition dated July 2019).
The general FIDIC clause referred to above has been strengthened to reflect the requirements of the ESF. Beyond
FIDIC’s general requirements discussed above, the Bank’s Particular Conditions include a number of relevant
requirements on the Contractor, including:
• to provide health and safety training for Contractor’s Personnel (which include project workers and all personnel that
the Contractor uses on site, including staff and other employees of the Contractor and Subcontractors and any other
personnel assisting the Contractor in carrying out project activities)
• to put in place workplace processes for Contractor’s Personnel to report work situations that are not safe or healthy
• gives Contractor’s Personnel the right to report work situations which they believe are not safe or healthy, and to
remove themselves from a work situation which they have a reasonable justification to believe presents an imminent
and serious danger to their life or health (with no reprisal for reporting or removing themselves)
• requires measures to be in place to avoid or minimize the spread of diseases including measures to avoid or minimize
the transmission of communicable diseases that may be associated with the influx of temporary or permanent contract-
related labor
• to provide an easily accessible grievance mechanism to raise workplace concerns
Where the contract form used is FIDIC, the Borrower (as the Employer) will be represented by the Engineer (also
referred to in this note as the Supervising Engineer). The Engineer will be authorized to exercise authority specified in
or necessarily implied from the construction contract. In such cases, the Engineer (through its staff on site) will be the
interface between the PIU and the Contractor. It is important therefore to understand the scope of the Engineer’s
responsibilities. It is also important to recognize that in the case of infectious diseases such as COVID-19, project
management – through the Contractor/subcontractor hierarchy – is only as effective as the weakest link. A thorough
review of management procedures/plans as they will be implemented through the entire contractor hierarchy is
important. Existing contracts provide the outline of this structure; they form the basis for the Borrower to understand
how proposed mitigation measures will be designed and how adaptive management will be implemented, and to start a
conversation with the Contractor on measures to address COVID-19 in the project.
4. WHAT PLANNING SHOULD THE BORROWER BE DOING?
Task teams should work with Borrowers (PIUs) to confirm that projects (i) are taking adequate precautions to prevent
or minimize an outbreak of COVID-19, and (ii) have identified what to do in the event of an outbreak. Suggestions on
how to do this are set out below:
• The PIU, either directly or through the Supervising Engineer, should request details in writing from the main
Contractor of the measures being taken to address the risks. As stated in Section 3, the construction contract should
include health and safety requirements, and these can be used as the basis for identification of, and requirements to
implement, COVID-19 specific measures. The measures may be presented as a contingency plan, as an extension of the
existing project emergency and preparedness plan or as standalone procedures. The measures may be reflected in
revisions to the project’s health and safety manual. This request should be made in writing (following any relevant
procedure set out in the contract between the Borrower and the contractor).
• In making the request, it may be helpful for the PIU to specify the areas that should be covered. This should include
the items set out in Section 5 below and take into account current and relevant
guidance provided by national authorities, WHO and other organizations. See the list of references in the Annex to this
note.
• The PIU should require the Contractor to convene regular meetings with the project health and safety specialists and
medical staff (and where appropriate the local health authorities), and to take their advice in designing and
implementing the agreed measures.
• Where possible, a senior person should be identified as a focal point to deal with COVID-19 issues. This can be a
work supervisor or a health and safety specialist. This person can be responsible for coordinating preparation of the site
and making sure that the measures taken are communicated to the workers, those entering the site and the local
2
community. It is also advisable to designate at least one back-up person, in case the focal point becomes ill; that person
should be aware of the arrangements that are in place.
• On sites where there are a number of contractors and therefore (in effect) different work forces, the request should
emphasize the importance of coordination and communication between the different parties. Where necessary, the PIU
should request the main contractor to put in place a protocol for regular meetings of the different contractors, requiring
each to appoint a designated staff member (with back up) to attend such meetings. If meetings cannot be held in person,
they should be conducted using whatever IT is available. The effectiveness of mitigation measures will depend on the
weakest implementation, and therefore it is important that all contractors and sub-contractors understand the risks and
the procedure to be followed.
• The PIU, either directly or through the Supervising Engineer, may provide support to projects in identifying
appropriate mitigation measures, particularly where these will involve interface with local services, in particular health
and emergency services. In many cases, the PIU can play a valuable role in connecting project representatives with
local Government agencies, and helping coordinate a strategic response, which takes into account the availability of
resources. To be most effective, projects should consult and coordinate with relevant Government agencies and other
projects in the vicinity.
• Workers should be encouraged to use the existing project grievance mechanism to report concerns relating to COVID-
19, preparations being made by the project to address COVID-19 related issues, how procedures are being
implemented, and concerns about the health of their co-workers and other staff.
5. WHAT SHOULD THE CONTRACTOR COVER?
The Contractor should identify measures to address the COVID-19 situation. What will be possible will depend on the
context of the project: the location, existing project resources, availability of supplies, capacity of local
emergency/health services, the extent to which the virus already exist in the area. A systematic approach to planning,
recognizing the challenges associated with rapidly changing circumstances, will help the project put in place the best
measures possible to address the situation. As discussed above, measures to address COVID-19 may be presented in
different ways (as a contingency plan, as an extension of the existing project emergency and preparedness plan or as
standalone procedures). PIUs and contractors should refer to guidance issued by relevant authorities, both national
and international (e.g. WHO), which is regularly updated (see sample References and links provided in the Annex).
Addressing COVID-19 at a project site goes beyond occupational health and safety, and is a broader project issue which
will require the involvement of different members of a project management team. In many cases, the most effective
approach will be to establish procedures to address the issues, and then to ensure that these procedures are implemented
systematically. Where appropriate given the project context, a designated team should be established to address
COVID-19 issues, including PIU representatives, the Supervising Engineer, management (e.g. the project manager) of
the contractor and sub-contractors, security, and medical and OHS professionals. Procedures should be clear and
straightforward, improved as necessary, and supervised and monitored by the COVID-19 focal point(s). Procedures
should be documented, distributed to all contractors, and discussed at regular meetings to facilitate adaptive
management. The issues set out below include a number that represent expected good workplace management but are
especially pertinent in preparing the project response to COVID-19.
(a) ASSESSING WORKFORCE CHARACTERISTICS
Many construction sites will have a mix of workers e.g. workers from the local communities; workers from a different
part of the country; workers from another country. Workers will be employed under different terms and conditions and
be accommodated in different ways. Assessing these different aspects of the workforce will help in identifying
appropriate mitigation measures:
• The Contractor should prepare a detailed profile of the project work force, key work activities, schedule for carrying
out such activities, different durations of contract and rotations (e.g. 4 weeks on, 4 weeks off).
• This should include a breakdown of workers who reside at home (i.e. workers from the community), workers who
lodge within the local community and workers in on-site accommodation. Where possible, it should also identify
workers that may be more at risk from COVID-19, those with underlying health issues or who may be otherwise at risk.
• Consideration should be given to ways in which to minimize movement in and out of site. This could include
lengthening the term of existing contracts, to avoid workers returning home to affected areas, or returning to site from
affected areas.
• Workers accommodated on site should be required to minimize contact with people near the site, and in certain cases
be prohibited from leaving the site for the duration of their contract, so that contact with local communities is avoided.
• Consideration should be given to requiring workers lodging in the local community to move to site accommodation
(subject to availability) where they would be subject to the same restrictions.
• Workers from local communities, who return home daily, weekly or monthly, will be more difficult to manage. They
should be subject to health checks at entry to the site (as set out above) and at some point, circumstances may make it
necessary to require them to either use accommodation on site or not to come to work.
(b) ENTRY/EXIT TO THE WORK SITE AND CHECKS ON COMMENCEMENT OF WORK
Entry/exit to the work site should be controlled and documented for both workers and other parties, including support
staff and suppliers. Possible measures may include:
3
• Establishing a system for controlling entry/exit to the site, securing the boundaries of the site, and establishing
designating entry/exit points (if they do not already exist). Entry/exit to the site should be documented.
• Training security staff on the (enhanced) system that has been put in place for securing the site and controlling entry
and exit, the behaviors required of them in enforcing such system and any COVID -19 specific considerations.
• Training staff who will be monitoring entry to the site, providing them with the resources they need to document entry
of workers, conducting temperature checks and recording details of any worker that is denied entry.
• Confirming that workers are fit for work before they enter the site or start work. While procedures should already be
in place for this, special attention should be paid to workers with underlying health issues or who may be otherwise at
risk. Consideration should be given to demobilization of staff with underlying health issues.
• Checking and recording temperatures of workers and other people entering the site or requiring self-reporting prior to
or on entering the site.
• Providing daily briefings to workers prior to commencing work, focusing on COVID-19 specific considerations
including cough etiquette, hand hygiene and distancing measures, using demonstrations and participatory methods.
• During the daily briefings, reminding workers to self-monitor for possible symptoms (fever, cough) and to report to
their supervisor or the COVID-19 focal point if they have symptoms or are feeling unwell.
• Preventing a worker from an affected area or who has been in contact with an infected person from returning to the
site for 14 days or (if that is not possible) isolating such worker for 14 days.
• Preventing a sick worker from entering the site, referring them to local health facilities if necessary or requiring them
to isolate at home for 14 days.
(c) GENERAL HYGIENE
Requirements on general hygiene should be communicated and monitored, to include:
• Training workers and staff on site on the signs and symptoms of COVID-19, how it is spread, how to protect
themselves (including regular handwashing and social distancing) and what to do if they or other people have symptoms
(for further information see WHO COVID-19 advice for the public). • Placing posters and signs around the site, with
images and text in local languages. • Ensuring handwashing facilities supplied with soap, disposable paper towels and
closed waste bins exist at key places throughout site, including at entrances/exits to work areas; where there is a toilet,
canteen or food distribution, or provision of drinking water; in worker accommodation; at waste stations; at stores; and
in common spaces. Where handwashing facilities do not exist or are not adequate, arrangements should be made to set
them up. Alcohol based sanitizer (if available, 60-95% alcohol) can also be used. • Review worker accommodations and
assess them in light of the requirements set out in IFC/EBRD guidance on Workers’ Accommodation: processes and
standards, which provides valuable guidance as to good practice for accommodation. • Setting aside part of worker
accommodation for precautionary self-quarantine as well as more formal isolation of staff who may infected (see
paragraph (f)).
(d) CLEANING AND WASTE DISPOSAL Conduct regular and thorough cleaning of all site facilities, including
offices, accommodation, canteens, common spaces. Review cleaning protocols for key construction equipment
(particularly if it is being operated by different workers). This should include: • Providing cleaning staff with adequate
cleaning equipment, materials and disinfectant. • Review general cleaning systems, training cleaning staff on
appropriate cleaning procedures and appropriate frequency in high use or high-risk areas. • Where it is anticipated that
cleaners will be required to clean areas that have been or are suspected to have been contaminated with COVID-19,
providing them with appropriate PPE: gowns or aprons, gloves, eye protection (masks, goggles or face screens) and
boots or closed work shoes. If appropriate PPE is not available, cleaners should be provided with best available
alternatives. • Training cleaners in proper hygiene (including handwashing) prior to, during and after conducting
cleaning activities; how to safely use PPE (where required); in waste control (including for used PPE and materials). •
Any medical waste produced during the care of ill workers should be collected safely in designated containers or bags
and treated and disposed of following relevant requirements (e.g., national, WHO). If open burning and incineration of
medical wastes is necessary, this should be for as limited a duration as possible. Waste should be reduced and
segregated, so that only the smallest amount of waste is incinerated (for further information see WHO interim guidance
on water, and sanitiation and waste management for COVID-19)
(e) ADJUSTING WORK PRACTICES Consider changes to work processes and timings to reduce or minimize
contact between workers, recognizing that this is likely to impact the project schedule. Such measures could include: •
Decreasing the size of work teams. • Limiting the number of workers on site at any one time.• Changing to a 24-hour
work rotation. • Adapting or redesigning work processes for specific work activities and tasks to enable social
distancing, and training workers on these processes. • Continuing with the usual safety trainings, adding COVID-19
specific considerations. Training should include proper use of normal PPE. While as of the date of this note, general
advice is that construction workers do not require COVID-19 specific PPE, this should be kept under review (for further
information see WHO interim guidance on rational use of personal protective equipment (PPE) for COVID-19). •
Reviewing work methods to reduce use of construction PPE, in case supplies become scarce or the PPE is needed for
medical workers or cleaners. This could include, e.g. trying to reduce the need for dust masks by checking that water
sprinkling systems are in good working order and are maintained or reducing the speed limit for haul trucks. •
Arranging (where possible) for work breaks to be taken in outdoor areas within the site. • Consider changing canteen
4
layouts and phasing meal times to allow for social distancing and phasing access to and/or temporarily restricting access
to leisure facilities that may exist on site, including gyms. • At some point, it may be necessary to review the overall
project schedule, to assess the extent to which it needs to be adjusted (or work stopped completely) to reflect prudent
work practices, potential exposure of both workers and the community and availability of supplies, taking into account
Government advice and instructions.
(f) PROJECT MEDICAL SERVICES
Consider whether existing project medical services are adequate, taking into account existing infrastructure (size of
clinic/medical post, number of beds, isolation facilities), medical staff, equipment and supplies, procedures and training.
Where these are not adequate, consider upgrading services where possible, including:
• Expanding medical infrastructure and preparing areas where patients can be isolated. Guidance on setting up isolation
facilities is set out in WHO interim guidance on considerations for quarantine of individuals in the context of
containment for COVID-19). Isolation facilities should be located away from worker accommodation and ongoing work
activities. Where possible, workers should be provided with a single well-ventilated room (open windows and door).
Where this is not possible, isolation facilities should allow at least 1 meter between workers in the same room,
separating workers with curtains, if possible. Sick workers should limit their movements, avoiding common areas and
facilities and not be allowed visitors until they have been clear of symptoms for 14 days. If they need to use common
areas and facilities (e.g. kitchens or canteens), they should only do so when unaffected workers are not present and the
area/facilities should be cleaned prior to and after such use.
• Training medical staff, which should include current WHO advice on COVID-19 and recommendations on the
specifics of COVID-19. Where COVID-19 infection is suspected, medical providers on site should follow WHO
interim guidance on infection prevention and control during health care when novel coronavirus (nCoV) infection is
suspected.
• Training medical staff in testing, if testing is available.
• Assessing the current stock of equipment, supplies and medicines on site, and obtaining additional stock, where
required and possible. This could include medical PPE, such as gowns, aprons, medical masks, gloves, and eye
protection. Refer to WHO guidance as to what is advised (for further information see WHO interim guidance on
rational use of personal protective equipment (PPE) for COVID-19).
• If PPE items are unavailable due to world-wide shortages, medical staff on the project should agree on alternatives and
try to procure them. Alternatives that may commonly be found on constructions sites include dust masks, construction
gloves and eye goggles. While these items are not recommended, they should be used as a last resort if no medical PPE
is available.
• Ventilators will not normally be available on work sites, and in any event, intubation should only be conducted by
experienced medical staff. If a worker is extremely ill and unable to breathe properly on his or her own, they should be
referred immediately to the local hospital (see (g) below).
• Review existing methods for dealing with medical waste, including systems for storage and disposal (for further
information see WHO interim guidance on water, sanitation and waste management for COVID-19, and WHO guidance
on safe management of wastes from health-care activities).
(g) LOCAL MEDICAL AND OTHER SERVICES
Given the limited scope of project medical services, the project may need to refer sick workers to local medical
services. Preparation for this includes:
• Obtaining information as to the resources and capacity of local medical services (e.g. number of beds, availability of
trained staff and essential supplies).
• Conducting preliminary discussions with specific medical facilities, to agree what should be done in the event of ill
workers needing to be referred.
• Considering ways in which the project may be able to support local medical services in preparing for members of the
community becoming ill, recognizing that the elderly or those with pre-existing medical conditions require additional
support to access appropriate treatment if they become ill.
• Clarifying the way in which an ill worker will be transported to the medical facility, and checking availability of such
transportation.
• Establishing an agreed protocol for communications with local emergency/medical services.
• Agreeing with the local medical services/specific medical facilities the scope of services to be provided, the procedure
for in-take of patients and (where relevant) any costs or payments that may be involved.
• A procedure should also be prepared so that project management knows what to do in the unfortunate event that a
worker ill with COVID-19 dies. While normal project procedures will continue to apply, COVID-19 may raise other
issues because of the infectious nature of the disease. The project should liaise with the relevant local authorities to
coordinate what should be done, including any reporting or other requirements under national law.
(h) INSTANCES OR SPREAD OF THE VIRUS
WHO provides detailed advice on what should be done to treat a person who becomes sick or displays symptoms that
could be associated with the COVID-19 virus (for further information see WHO interim guidance on infection
prevention and control during health care when novel coronavirus (nCoV) infection is suspected). The project should
5
set out risk-based procedures to be followed, with differentiated approaches based on case severity (mild, moderate,
severe, critical) and risk factors (such as age, hypertension, diabetes) (for further information see WHO interim
guidance on operational considerations for case management of COVID-19 in health facility and community). These
may include the following:
• If a worker has symptoms of COVID-19 (e.g. fever, dry cough, fatigue) the worker should be removed immediately
from work activities and isolated on site.
• If testing is available on site, the worker should be tested on site. If a test is not available at site, the worker should be
transported to the local health facilities to be tested (if testing is available).
• If the test is positive for COVID-19 or no testing is available, the worker should continue to be isolated. This will
either be at the work site or at home. If at home, the worker should be transported to their home in transportation
provided by the project.
• Extensive cleaning procedures with high-alcohol content disinfectant should be undertaken in the area where the
worker was present, prior to any further work being undertaken in that area. Tools used by the worker should be cleaned
using disinfectant and PPE disposed of.
• Co-workers (i.e. workers with whom the sick worker was in close contact) should be required to stop work, and be
required to quarantine themselves for 14 days, even if they have no symptoms.
• Family and other close contacts of the worker should be required to quarantine themselves for 14 days, even if they
have no symptoms.
• If a case of COVID-19 is confirmed in a worker on the site, visitors should be restricted from entering the site and
worker groups should be isolated from each other as much as possible.
• If workers live at home and has a family member who has a confirmed or suspected case of COVID-19, the worker
should quarantine themselves and not be allowed on the project site for 14 days, even if they have no symptoms.
• Workers should continue to be paid throughout periods of illness, isolation or quarantine, or if they are required to
stop work, in accordance with national law.
• Medical care (whether on site or in a local hospital or clinic) required by a worker should be paid for by the employer.
(i) CONTINUITY OF SUPPLIES AND PROJECT ACTIVITIES
Where COVID-19 occurs, either in the project site or the community, access to the project site may be restricted, and
movement of supplies may be affected.
• Identify back-up individuals, in case key people within the project management team (PIU, Supervising Engineer,
Contractor, sub-contractors) become ill, and communicate who these are so that people are aware of the arrangements
that have been put in place.
• Document procedures, so that people know what they are, and are not reliant on one person’s knowledge.
• Understand the supply chain for necessary supplies of energy, water, food, medical supplies and cleaning equipment,
consider how it could be impacted, and what alternatives are available. Early pro-active review of international, regional
and national supply chains, especially for those supplies that are critical for the project, is important (e.g. fuel, food,
medical, cleaning and other essential supplies). Planning for a 1-2-month interruption of critical goods may be
appropriate for projects in more remote areas.
• Place orders for/procure critical supplies. If not available, consider alternatives (where feasible).
• Consider existing security arrangements, and whether these will be adequate in the event of interruption to normal
project operations.
• Consider at what point it may become necessary for the project to significantly reduce activities or to stop work
completely, and what should be done to prepare for this, and to re-start work when it becomes possible or feasible.
(j) TRAINING AND COMMUNICATION WITH WORKERS Workers need to be provided with regular
opportunities to understand their situation, and how they can best protect themselves, their families and the community.
They should be made aware of the procedures that have been put in place by the project, and their own responsibilities
in implementing them. • It is important to be aware that in communities close to the site and amongst workers without
access to project management, social media is likely to be a major source of information. This raises the importance of
regular information and engagement with workers (e.g. through training, town halls, toolboxes) that emphasizes what
management is doing to deal with the risks of COVID-19. Allaying fear is an important aspect of work force peace of
mind and business continuity. Workers should be given an opportunity to ask questions, express their concerns, and
make suggestions.
• Training of workers should be conducted regularly, as discussed in the sections above, providing workers with a clear
understanding of how they are expected to behave and carry out their work duties.
• Training should address issues of discrimination or prejudice if a worker becomes ill and provide an understanding of
the trajectory of the virus, where workers return to work.
• Training should cover all issues that would normally be required on the work site, including use of safety procedures,
use of construction PPE, occupational health and safety issues, and code of conduct, taking into account that work
practices may have been adjusted.
• Communications should be clear, based on fact and designed to be easily understood by workers, for example by
displaying posters on handwashing and social distancing, and what to do if a worker displays symptoms.
6
(k) COMMUNICATION AND CONTACT WITH THE COMMUNITY
Relations with the community should be carefully managed, with a focus on measures that are being implemented to
safeguard both workers and the community. The community may be concerned about the presence of non-local
workers, or the risks posed to the community by local workers presence on the project site. The project should set out
risk-based procedures to be followed, which may reflect WHO guidance (for further information see WHO Risk
Communication and Community Engagement (RCCE) Action Plan Guidance COVID-19 Preparedness and Response).
The following good practice should be considered:
• Communications should be clear, regular, based on fact and designed to be easily understood by community members.
• Communications should utilize available means. In most cases, face-to-face meetings with the community or
community representatives will not be possible. Other forms of communication should be used; posters, pamphlets,
radio, text message, electronic meetings. The means used should take into account the ability of different members of
the community to access them, to make sure that communication reaches these groups.
• The community should be made aware of procedures put in place at site to address issues related to COVID-19. This
should include all measures being implemented to limit or prohibit contact between workers and the community. These
need to be communicated clearly, as some measures will have financial implications for the community (e.g. if workers
are paying for lodging or using local facilities). The community should be made aware of the procedure for entry/exit to
the site, the training being given to workers and the procedure that will be followed by the project if a worker becomes
sick.
• If project representatives, contractors or workers are interacting with the community, they should practice social
distancing and follow other COVID-19 guidance issued by relevant authorities, both national and international (e.g.
WHO).
6. EMERGENCY POWERS AND LEGISLATION
Many Borrowers are enacting emergency legislation. The scope of such legislation, and the way it interacts with other
legal requirements, will vary from country to country. Such legislation can cover a range of issues, for example:
• Declaring a public health emergency
• Authorizing the use of police or military in certain activities (e.g. enforcing curfews or restrictions on movement)
• Ordering certain categories of employees to work longer hours, not to take holiday or not to leave their job (e.g. health
workers)
• Ordering non-essential workers to stay at home, for reduced pay or compulsory holiday
Except in exceptional circumstances (after referral to the World Bank’s Operations Environmental and Social Review
Committee (OESRC)), projects will need to follow emergency legislation to the extent that these are mandatory or
advisable. It is important that the Borrower understands how mandatory requirements of the legislation will impact the
project. Teams should require Borrowers (and in turn, Borrowers should request Contractors) to consider how the
emergency legislation will impact the obligations of the Borrower set out in the legal agreement and the obligations set
out in the construction contracts. Where the legislation requires a material departure from existing contractual
obligations, this should be documented, setting out the relevant provisions.
ANNEX
WHO Guidance
Advice for the public
WHO advice for the public, including on social distancing, respiratory hygiene, self-quarantine, and seeking medical
advice, can be consulted on this WHO website: https://www.who.int/emergencies/diseases/novel-coronavirus-
2019/advice-for-public
Technical guidance
Infection prevention and control during health care when novel coronavirus (nCoV) infection is suspected, issued on 19
March 2020
Coronavirus disease (COVID-19) outbreak: rights, roles and responsibilities of health workers, including key
considerations for occupational safety and health, issued on 18 March 2020
Risk Communication and Community Engagement (RCCE) Action Plan Guidance COVID-19 Preparedness and
Response, issued on 16 March 2020
Considerations for quarantine of individuals in the context of containment for coronavirus disease (COVID-19), issued
on 19 March 2020
Operational considerations for case management of COVID-19 in health facility and community, issued on 19 March
2020
Rational use of personal protective equipment for coronavirus disease 2019 (COVID-19), issued on 27 February 2020
Getting your workplace ready for COVID-19, issued on 19 March 2020
Water, sanitation, hygiene and waste management for COVID-19, issued on 19 March 2020
Safe management of wastes from health-care activities issued in 2014
Advice on the use of masks in the community, during home care and in healthcare settings in the context of the novel
coronavirus (COVID-19) outbreak, issued on March 19, 2020
ILO GUIDANCE
7
ILO Standards and COVID-19 FAQ, issued on March 23, 2020 (provides a compilation of answers to most frequently
asked questions related to international labor standards and COVID-19)
MFI GUIDANCE
IDB Invest Guidance for Infrastructure Projects on COVID-19: A Rapid Risk Profile and Decision Framework
KfW DEG COVID-19 Guidance for employers, issued on 31 March 2020
CDC Group COVID-19 Guidance for Employers, issued on 23 March 2020