e. doyle 7/20/06 rev 9/13/06 1 / 16rf coupler assembly facility slac ttf3 coupler assembly facility...
TRANSCRIPT
E. Doyle 7/20/06 rev 9/13/06 1 / 16RF Coupler Assembly Facility
SLAC TTF3 Coupler Assembly Facility Specifications
Based on TESLA facility built at LAL, Orsay.
E. Doyle 7/20/06 rev 9/13/06 2 / 16RF Coupler Assembly Facility
Finished Product – Pair of Couplers on Stand
SLAC will assemble and test couplers and ship them to Fermilab for use in ILC superconducting cavity tests. 12 couplers to be shipped by summer ’07.
~30 in
E. Doyle 7/20/06 rev 9/13/06 3 / 16RF Coupler Assembly Facility
Model Assembly Facility – LAL, Orsay
Assembly in B006
Testing Elsewhere- ESB(?)
Parts Storage – B006
SLAC will duplicate DESY assembly/test procedure as implemented at Orsay. Clean room to be modular, factory assembled, installed at SLAC by vendor.
E. Doyle 7/20/06 rev 9/13/06 4 / 16RF Coupler Assembly Facility
Gowning area
Air shower
Material Pass-through - more area recommended
Air Handling System – outdoor concrete pad
Class 10 – more area recommendedClass
1000
Clean Room ~50 m2
(500 ft2)
LAL Coupler Assembly Facility
Vacuum Oven
Washing Vat
E. Doyle 7/20/06 rev 9/13/06 5 / 16RF Coupler Assembly Facility
Air Shower
GowningMaterial Passthrough
Class 1000
Class 10
Clean Room Air Handling SystemUpdated flow values shown on next slide
38.315 16.5
E. Doyle 7/20/06 rev 9/13/06 6 / 16RF Coupler Assembly Facility
106B - SSRL office/storage – possible office space
50m2 clean room
CTL - possible expansion extent unknown
Laser HV power
Possible clean room storage & office areas – extent unknown
Air System 20m2
footprint - possible locations
B006 High Bay – possible home for ILC RF coupler assembly facility
Possible clean room storage area
High Bay
E. Doyle 7/20/06 rev 9/13/06 7 / 16RF Coupler Assembly Facility
B006 High Bay – Bunker Currently Installed in Proposed Site
9’ W x 25’ L x 9’ H
Experimental apparatus removed previously. Radiation survey completed inside and out.
Ultra-Pure Water System: high pressure rinsing and particle counter to be saved
E. Doyle 7/20/06 rev 9/13/06 8 / 16RF Coupler Assembly Facility
B006 High Bay – preliminary layout 9/12/06
GowningClean Room
Material Pass-Through
Class 10
Storage Lockers
Class 1000
Office Space
Vacuum Oven
Locate Air Handling System?
E. Doyle 7/20/06 rev 9/13/06 9 / 16RF Coupler Assembly Facility
Manpower assignments
function lead support
process planning Doyle, Swent McKee, Tice
facilities planning McKee teamaction Tice team
operations process TBD TBDfacilities TBD TBD
safety site prep Joe Kenny Doyle/Ticeconstruction Joe Kenny Doyle/Ticeoperation Joe Kenny Doyle/Tice
E. Doyle 7/20/06 rev 9/13/06 10 / 16RF Coupler Assembly Facility
Project Phases
• Safety Oversight Committee Review [8/31/06]– Eight Safety committees to approve before start work
• Project Plan [10/15/06]– Write plan– approval
• Site Preparation [12/15/06]– UPWS removal *– Bunker removal *
• Clean Room Installation (Modular, factory assembled & tested) – Design, write spec and order [11/15/06]– Installation by vendor * [1/15/07]
• Clean Room Operation– Optimize cleaning process (ultrasonic+detergent vs high pressure water)
[3/15/07]– Assemble couplers [3/15 – 8/15/07]– Ongoing production: ~12 in 08; ~30 in 09
* Possible use of outside contractors
E. Doyle 7/20/06 rev 9/13/06 11 / 16RF Coupler Assembly Facility
Numerical Specifications
E. Doyle 7/20/06 rev 9/13/06 12 / 16RF Coupler Assembly Facility
Clean Room & Air Handling SystemAir Shower
(Laminar Flow)
Gowning Material Pass-through
Class 1000 Class 10
Area (ft2) 18 76 22
44
256
164
140
210
Height (ft) 8 8 8 8 8
Air in (cfm) 59 395 106
212
1700
684
12200
18300
Recirculation (cfm)
620 - - - 11300
17400
Transfer (cfm) - - - +885 -885
Air Return (cfm) - 378 100
200
2450
1570
-
Overpressure(in H2O)
- .06 .06 .12 .16
Exchange (V/hr) 225 30 30 40 530
Orsay Modified
Note: Orsay contacts recommend increased area for Class 10 and material pass-through. This table reflects, in red, changes resulting from a 50% increase in Class 10 area and a 100% increase in mat’l pass-through area and a corresponding decrease in Class 1000 area.
E. Doyle 7/20/06 rev 9/13/06 13 / 16RF Coupler Assembly Facility
• Power load– Cooling: 38.3 kW– Heating: 16.5 kW– Heating for feed-throughs: 9 kW– Added heating for class 1000: 15 kW
• Air Conditioning specs– Occupancy: two people– Temp 18 – 22C +/- 1C– RH 50% +/- 10%– Ambient
• Summer 30C, 40% RH• Winter 7 C, 90% RH
Air Handling System
E. Doyle 7/20/06 rev 9/13/06 14 / 16RF Coupler Assembly Facility
• 20 L/h• Tank: 350 L (per Orsay) 200 L (per Millipore)• Footprint: ~ 4 m2• 18 MOhm-cm• Output to process: 10 lpm @3 bar• equivalent to Milli RX 20 (Millipore current model
is Elix 20)• Final polishing: ionex filter, organex filter (for
organics), durapore filter (0.22 um mesh).• Sufficient capacity for high pressure washing?
(NLC high-pressure system: 3.6gpm @ 2000 psi)
Ultrapure Water System
E. Doyle 7/20/06 rev 9/13/06 15 / 16RF Coupler Assembly Facility
• Detergent – Tickopur R33– Concentration: 5 parts per 160 parts H2O
• Washing tank– Inside L, W, D: 1000x500x400 mm– Outside L, W, D: 1180x600x800 mm– Volume: 180 L– Ultrasonic specs: 25 / 40 khz, 2 kW– Make: Bandelin RM180
• Rinsing station(s)– Inside L,W,D: 800x600x450 mm (216 L)
• Vacuum oven– External: 2 m L, 800 mm diam– Internal: 1.2 m L, 380 mm diam (.14 m3, 4.8 ft3)– Rough pump: 12 m3/h scroll– Turbo pump: varian 550 L/s– Vac: 10-6 mbar @ 150C (.75 x 10-6 Torr)– Vac: 10-7 mbar at r.t. after bake (.75 x 10-7 Torr)– Power requirement: <?>– Make: company no longer in business
Fixtures, etc
E. Doyle 7/20/06 rev 9/13/06 16 / 16RF Coupler Assembly Facility
• Ionized N2 system– Flow: 5.5 SCFM– Pressure: 3 bar– Ionization System: 3.5 – 8 kV– Make, model: Simco PG-8
• Assembly tables– 120 x 60 cm, SST– 5 tables located in class 10
• Hoist (?)• Storage cabinets (external to clean room)
– Qty: five total, two with N2 purge– Dimensions: ~ 2x1.2x0.7 m– N2 pressure: small overpressure– Make: home-built
Fixtures, etc, continued