elecrical equipment maintenance in pipelines

Upload: diwakarngm

Post on 02-Jun-2018

224 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/10/2019 Elecrical Equipment Maintenance in Pipelines

    1/59

    ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

    1submitted by Anirban Das

    ELECRICAL EQUIPMENT MAINTENANCE IN PIPELINES

    1. INTRODUCTION:

    The most economical way of transporting petroleum products from one place to

    another is through the pipelines. The pipeline offers low operating cost and high reliability of

    transportation of fluids.

    Generally pipeline consists of the following major systems:

    Tank farms

    Pumping stations

    Metering stations

    Valve manifolds

    Pigging stations

    SCADA systems

    Corrosion control systems

    Figure-1: Product pipe line system

  • 8/10/2019 Elecrical Equipment Maintenance in Pipelines

    2/59

    ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

    2submitted by Anirban Das

    The major electrical equipments that are used in pipelines are:

    POWER SUPPLY AND DISTRIBUTION

    SUB STATIONS

    TRANSFORMERS

    SWITCH GEAR

    ELECTRIC MOTORS

    MOV ACTUATORS

    CATHODIC PROTECTION SYSTEMS

    EMERGENCY GENERATORS

    2. POWER SUPPLY AND DISTRIBUTION

    The power supply and distribution depend on the electrical power requirements (or

    maximum demand load) for the installation.

    2.1 LOAD ESTIMATION:

    Load estimation requires analysis of load characteristics and will take into account

    the demand factor relationship between connected loads and the actual demand imposed on the

    system. For load estimation the following factors are used.

    2.1.1 Preliminary loads:

    The minimum loads which are connected to power system.

    2.1.2 Demand Factor:

    It is defined as ratio of maximum demand (largest demand during a specified time) to

    the total connected load.

  • 8/10/2019 Elecrical Equipment Maintenance in Pipelines

    3/59

    ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

    3submitted by Anirban Das

    By this demand factor we can know the capacity of transformer and the conductor

    size, and all equipment associated with distribution of electrical power to utilization equipment.

    2.1.3 Diversity Factor:

    Diversity factor is defined as the ratio of the sum of the individual maximum

    demands of various subsystems within a system to the maximum demand of the system.

    2.1.4 Load Factor:

    Load factor is defined as the ratio of the average load over a designated period of

    time to the peak load occurring in that period.

    A low load factor indicates short-time demand peaks which can result in heavy

    charges to the Using Agency. Low load factor will be corrected by shedding loads or by peak-

    shaving generation during periods of peak demand.

    2.2 Voltage Requirement:

    The voltage requirement is based on the type of distribution. That means

    primary distribution and secondary distribution.

    Primary distribution means distribution from main substations to local substations.

    Secondary distribution means local substations to domestic users.

    The voltage requirement is also based the type of equipment we are using.

    3. SUBSTATIONS

    Substations mainly consist of:

    Power transformers

    Underground cables

    Air circuit breakers or Oil circuit breakers

    Buses

  • 8/10/2019 Elecrical Equipment Maintenance in Pipelines

    4/59

    ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

    4submitted by Anirban Das

    Protective relays

    Current transformers and Voltage transformers

    LT/HT control panels

    Lightening or Surge arrestor

    Grounding

    Figure-2: An 11 KV substation (single line diagram)

    4. TRANSFORMERS

    4.1 BASIC PRINCIPLE:

    The transformer is based on two principles:

    An electric current can produce a magnetic field (electromagnetism)

    A changing magnetic field within a coil of wire induces a voltage across the ends of the

    coil (electromagnetic induction).

  • 8/10/2019 Elecrical Equipment Maintenance in Pipelines

    5/59

    ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

    5submitted by Anirban Das

    Figure -3: An ideal step-down Transformer

    4.2 SWITCHING ON AND OPERATION:

    4.2.1 HV Energisation:

    When the installation has been fully checked, the HV side can first be switched-on and

    following this, the LV side. It is recommended that the transformer is left energized for a few

    hours before switching-on the LV side and applying load. During this time the transformer should

    be closely supervised paying attention to both coolant oil level and temperature. Verify the voltage

    between the low voltage phases and phase to neutral if used.

    4.2.2 Re-adjusting the tap switch:

    The tap switch enables sections of the HV winding to be in or out of the turns ratio

    thus affecting the secondary low voltage side. When the voltage measured at the low voltage side

    deviates from the required value this usually indicates that the incoming HV voltage is too high or

    too low. Normally the supply voltage is held within limits of plus or minus 6%. The tapping switch

    can compensate for variations of plus or minus 5% in 2.5% steps. If adjustment is desired then the

    following procedure should be followed.

  • 8/10/2019 Elecrical Equipment Maintenance in Pipelines

    6/59

    ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

    6submitted by Anirban Das

    Disconnect the transformer from both the HV systems and the LV systems.

    Unlock and remove the padlock, if fitted. Release the tapping switch mechanism by lifting

    the operating handle.

    Turn the handle to the desired position to increase LV volts - turn to a higher tap position

    number, which will decrease the HV, turns in circuit and proportionally increase the output

    voltage.

    4.3 MAINTENANCE:

    4.3.1 ONLINE MAINTENANCE:

    Frequency of routine maintenance is quarterly for distribution transformers and daily

    for grid transformers.

    Check load current: If more than rated, reduce non priority loads

    Check voltage: control the appropriate voltage H.V voltage and L.V voltage variations. If

    online tap changer (O.L.T.C) is provided change the tap positions as required.

    Check OTI&WTI readings:

    Check the temperature does not increase beyond rated temperature.

    Check oil level in Transformer and O.L.T.C: check the oil level in respective conservators.

    Ensure that they are not beyond rated temperature. If not top up with dry transformer oil.

    Check transformer for oil leaks.

    Check breather on transformer and O.L.T.C: check color of silica gel. It should be blue. If

    it is pink replace it by spare charge.

    Check sound level: Certified sound levels determined in accordance with NEMA, shall not

    exceed the following:

  • 8/10/2019 Elecrical Equipment Maintenance in Pipelines

    7/59

    ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

    7submitted by Anirban Das

    Transformer Rating

    Sound Level Rating

    0 - 9 KVA 40 dB

    10 - 50 KVA 45 dB

    51 - 150 KVA 50 dB

    151 - 300 KVA 55 dB

    301 - 500 KVA 60 dB

    TABLE-01

    4.3.2 ANNUAL SHUTDOWN MAINTENANCE:

    Visual inspection of transformers for oil leakage, oil level, and silica gel conditions should

    be done.

    Clean the transformer body and paint it if necessary.

    Check the oil level and top-up in necessary.

    Remove the silica gel and reactivate if necessary.

    Open H.T terminal box and check for loose connections, heating and oil leakage from

    bushings.

    Open L.T terminal box and check for the same.

    Check the body and neutral earthing joints.

    Check the tap changer for pitting and overheating etc;

    Examine Bucholzs relay, OTI (oil temperature indicator) and WTI (winding temperature

    indicator) relays operation and check for accuracy.

  • 8/10/2019 Elecrical Equipment Maintenance in Pipelines

    8/59

    ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

    8submitted by Anirban Das

    4.3.3 CAPITAL OVERHAUL:

    Capital over haul shall include overhaul inspection, lifting of core and coils, cleaning

    of transformer tank. Frequency of overhaul will be normally in between 7 to 8 years.

    TRANSFORMER OIL: Properties

    S.N Description New oil Old oil

    1

    2

    3

    4

    Electrical strength

    Moisture, Mechanicalimpurities

    Flash Point

    Viscosity at 270C

    40kv

    None

    140

    0

    C

    27 cst

    25kv/40kv

    25/35 ppm

    Max. 5

    0

    C lower

    27 cst

    TABLE-02

    After one year any changes in the oil properties above said, the oil should be changed. The old

    mineral oil should be reconditioned.

  • 8/10/2019 Elecrical Equipment Maintenance in Pipelines

    9/59

    ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

    9submitted by Anirban Das

    The following table depicts the transformer trouble shooting

    SYMPTOM CAUSE CORRECTIVE

    MAINTENANCE

    High Temperature.

    Fractured metal or

    porcelain parts of thebushings.

    Badly discolored oil.

    DRY_TYPE

    TRASNFORMERS:

    High temperatures

    Moisture

    Over voltage.

    Over current.

    High ambient temperatures.

    Insufficient cooling.

    Unusual strains place on

    terminal connections.

    Contaminated by varnishes.

    Carbonized oil due to

    switching.

    Winding or core failure.

    Insufficient air flow

    Transformer in moisture

    atmosphere or accidental

    wetting

    Change the circuit voltage or

    transformer connections to avoid

    over excitation.

    If possible reduce the load.

    Heating can often be reduced by

    improving power factor of load.

    Check parallel circuits for

    circulating currents which may be

    caused by improper ratios of their

    impedances.

    Either improve ventilation or

    relocate transformer in lower

    ambient temperature.

    Make sure cooling is adequate.

    Cables and bus bars attached to

    the transformers should beadequately supported. In the case

    of heavy leads, flexible

    connections should be provided to

    remove strain on the terminal and

    bushing porcelain.

    Retain oil if di-electric strength is

    satisfactory.

    Filter/ reclaim/ replace oil.

    Repair transformer.

    Check that in take is not

    obstructed. If unit is fan cooled

    check fan speed.

    Transformers dry out to be done.

    TABLE-03

  • 8/10/2019 Elecrical Equipment Maintenance in Pipelines

    10/59

    ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

    10submitted by Anirban Das

    5. ELECTRICAL POWER CABLES

    5.1 INTRODUCTION:

    A power cable is an assembly of two or more electrical conductors, usually held

    together with an overall sheath. The assembly is used for transmission of electrical power.

    Power cables may be installed as permanent wiring buried in the ground, run overhead, or

    exposed. Flexible power cables are used for portable devices, mobile tools and machinery.

    For constructional details of power cables see ANNEXURE- A

    For cable selection criterion see ANNEXURE-B

    For cable laying details see ANNEXURE-C

    For testing of cables see ANNEXURE-D

    For NETA insulation standards see ANNEXURE-E

    5.2 CABLE FAULTS:

    The problems occurs in the cables due to

    Environmental changes.

    Changes in the thermal resistivity of the soil.

    Defects in the earthing and bonding.

    Excavation by other utilities.

    The most frequent faults are short circuit faults and earth leakage faults and

    insulation breakdown. Due to these, some part of the cable (specifically, underground) get

    heated up and burst.

    5.3 LOCATING CABLE FAULT:

    There are two basic methods of locating an underground cable fault.

  • 8/10/2019 Elecrical Equipment Maintenance in Pipelines

    11/59

    ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

    11submitted by Anirban Das

    5.3.1 Sectionalizing:

    In this procedure, we divide the cable into smaller sections and examine the insulation

    resistance or continuity.

    5.3.2 Thumping:

    When we supply a high voltage to a faulted cable, the resulting high-current arc

    makes a noise loud enough for us to hear above ground. While this method eliminates the

    sectionalizing method's cutting and splicing, it has its own drawback. Thumping requires a

    current on the order of tens of thousands of amps at voltages as high as 25kV to make an

    underground noise loud enough for you to hear above ground.

    The heating from this high current often causes some degradation of the cable insulation.

    There are some relatively new methods of locating cable faults that use rather

    sophisticated technology.

    5.3.3 Time Domain Reflectometry (TDR):

    The TDR sends a low-energy signal through the cable, causing no insulation

    degradation. A theoretically perfect cable returns the signal in a known time and in a known

    profile. Impedance variations in a "real-world" cable alter both the time and profile, which

    the TDR screen or printout graphically represents. This graph (called a "trace") gives the user

    approximate distances to "landmarks" such as opens, splices, Y-taps, transformers, and water

    ingression.

    One weakness of TDR is that it does not pinpoint faults. TDR is accurate to

    within about 1% of testing range.

  • 8/10/2019 Elecrical Equipment Maintenance in Pipelines

    12/59

    ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

    12submitted by Anirban Das

    Another weakness of TDR is that reflectometers cannot see faults-to-ground with

    resistances much greater than 200 ohms. So, in the case of a "bleeding fault" rather than a

    short or near-short, TDR is blind.

    5.3.4 High-voltage radar method:

    There are three basic methods for high-voltage radar, they are

    Arc reflection

    Surge pulse reflection

    Voltage pulse reflection

    The arc reflection method uses a TDR with a filter and thumper. The filter limits both

    the surge current and voltage that can reach the cable under test, thus allowing

    minimal stress to the cable. Arc reflection provides an approximate distance to the

    fault (when there is an ionizing, clean arc produced at the fault and the TDR in use is

    powerful enough to sense and display a reflected pulse).

    The surge pulse reflection method uses a current coupler and a storage oscilloscope

    with a thumper. The advantage of this method is its superior ability to ionize difficult

    and distant faults. Its disadvantages are that its high output surge can damage the

    cable, and interpreting the trace requires more skill than with the other methods.

    The voltage pulse reflection method uses a voltage coupler and an analyzer with a

    dielectric test set or proof tester. This method provides a way to find faults that occur

    at voltages above the maximum thumper voltage of 25kV.

    One test to detect an open neutral requires shorting a known good conductor to a

    suspect neutral, then measuring the resistance with an ohmmeter. If the reading is 10

    ohms or higher, we can suspect an open neutral. Remember, other objects can

    complete the circuit.

  • 8/10/2019 Elecrical Equipment Maintenance in Pipelines

    13/59

    ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

    13submitted by Anirban Das

    5.4 REPAIRING OF CABLES:

    The repairing is nothing but locating the cable fault and cut the cable and re-joint

    the cables. There are two methods presently used in jointing of the cable, they are

    Polyurethane Cable Jointing.

    Heat shrinkable Cable Jointing.

    5.4.1 POLYURETHANE CABLE JOINT:

    Underground cable joints in electricity distribution networks must remain

    moisture free to prevent arc failure of any joint. Because the joints are created on-site, the

    quality of the jointing technique is critical.

    The quality of the joint is such that it does not add any resistant to the circuit. The

    materials and technique so designed to give adequate mechanical and electrical protection to

    the joints under all service conditions.

    Polyurethane kit consists of

    Adequate number of mechanical conductors.

    PTFE (Polytetrafluoroethylene) tube set to provide primary electrical insulation and

    correct cable positioning.

    Cast metal conducting tubes to make the electrical cable connection with snap -off

    bolt heads to ensure that perfect compression torque is applied.

    Armour bonding system in case of armoured cables (Earth continuity).

    A pair of white Glassfibre-Reinforced-Polyester (GRP) mating shell moulds which

    completely enclose and seal the joint, forming the inner shell.

    A container of liquid silicone, which is poured into the polyester mould, completely

    encasing the cable joint.

  • 8/10/2019 Elecrical Equipment Maintenance in Pipelines

    14/59

    ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

    14submitted by Anirban Das

    Figure-4: Cutaway view of straight water resistance medium voltage underground joint

    Figure-5: Cable jointing Kit

    Figure-6: Conductor joints in the cable

  • 8/10/2019 Elecrical Equipment Maintenance in Pipelines

    15/59

    ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

    15submitted by Anirban Das

    Figure-7: POLYURETHANE JOINTING PROCESS

    The above figure shows us how the polyurethane jointing process is going. The

    third from right connector is having its white, inner shell mould filled with liquid silicone.

    Note the temporarily placed funnel, mounted in the white inner shell, towards the foreground,

    which ensures the correct level of the silicone fill and zero air entrapment, and the support

    frame holding the container, as the filling is carried out. The liquid silicone container has two

    outlets, and the flow rate into the white, inner shell, is controlled by the gentle release of the

    seal on the second, (red) cap. As soon as the silicon pour is completed, the entry holes into

    this white mould are sealed. The whole process is cold, ideal for hazardous zoned areas.

    5.4.2 HEAT SHRINKABLE CABLE JOINT:

    Heat shrinksplices are available as a series of heat shrinkable tubes. Some may

    be preassembled by the manufacturer to reduce the number that must be handled in the field.

    The tubes must be slipped over the cable prior to connecting the conductors. After

    positioning each tubeover the connected cables, heat is applied to shrinkthe tube snugly over

    the underlying surface and soften anymastic material used in the assembly. Stress relief is

  • 8/10/2019 Elecrical Equipment Maintenance in Pipelines

    16/59

    ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

    16submitted by Anirban Das

    generally provided by stresscontrol tubesthat arealso shrunkinto place sothat endsof the

    stress control tubeoverlap both cable insulation shields. The joint is finished in thenormal

    manner.

    Figure-8: Heat shrinkable cable jointing Kit

    During the heat shrink installation process, the stored recovery force of the tube

    is released in addition to the recovery force of the heat shrinkable outer layer. A pre-designed

    screen and thick layer of insulation is installed in one simple process. This allows extremely

    tight electrical interfaces due to the shrink force generated. The elastomeric (tube) insulation

    characteristic combined with the rigid outer heat shrinkable screen layer enables the joint to

    follow the thermally induced dimensional changes of the cable insulation.

  • 8/10/2019 Elecrical Equipment Maintenance in Pipelines

    17/59

    ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

    17submitted by Anirban Das

    5.5 MAINTENANCE:

    SCHEDULE EQUIPMENT TASK

    Annually Cable Terminations Check connections for security

    (Except switchgear connections)

    Cable above ground Check for outer sheath damageCheck attachment to poleWhere fitted, ensure protectivepipe is secure.

    Cable loading Where fitted, check and recordDemand indicator readings(MV cable loadings are normallyestablished by load flow studies).

    Earthing Check all earth connections forsecurity.

    5 yearly Earthing Test all earth connections at MVand LV substations and compareto standards.

    TABLE-04

    6. SWITCH GEARS AND PROTECTIVE RELAYS

    6.1 INTRODUCTION:

    Switch gears are available in many forms, from single simple isolator to

    sophisticated vacuum breakers.

    The term switchgear, used in association with the electric power system, or grid,

    refers to the combination of electrical disconnects, fuses and/or circuit breakers used to isolate

    electrical equipment. Switchgear is used both to de-energize equipment to allow work to be done

    and to clear faults downstream.

  • 8/10/2019 Elecrical Equipment Maintenance in Pipelines

    18/59

    ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

    18submitted by Anirban Das

    6.2 TYPES OF CIRCUIT BREAKERS:

    The circuit breakers are classified on the basis of insulating medium present in it.

    They are

    Air circuit breaker

    Vacuum circuit breaker

    SF6 circuit breaker

    Oil circuit breaker

  • 8/10/2019 Elecrical Equipment Maintenance in Pipelines

    19/59

    ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

    19submitted by Anirban Das

    Figure-9: A 25 kv Single phase Air Circuit Breaker

    For the circuit breaker it is necessary to beak the circuit immediately when the fault

    occurs and isolates the fault position from healthy position.

    To ensure the equipment remains safe and reliable, regular examination is essential.

    6.3 MAINTENANCE:

    Essential areas requirements for inspection and testing:

    6.3.1 INSULATION:

    Insulation systems must be closely inspected for sings of over heating, cracking and

    other defects.

    6.3.2 CONTACTS:

    Inspect the contacts for signs of excessive wear and over heating. Free movement of

    the contactors also examined.

    6.3.3 TERMINALS:

    All terminals must be checked for firmness and signs of over heat.

    6.3.4 CABLES:

    Power and control cables must be examined with the connecting equipment.

    6.3.5 BUS BARS:

    Bus bars shall subject to periodic inspection.

    6.4 MAINTENANCE OF POWER AIR CIRCUIRT BREAKER:

    Power air circuit breaker should be maintained annually.

    To perform maintenance, withdraw the circuit breaker from its enclosure and do the following:

  • 8/10/2019 Elecrical Equipment Maintenance in Pipelines

    20/59

    ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

    20submitted by Anirban Das

    Inspect alignment of movable and stationary contacts. Make adjustments as

    recommended in manufacturers manual.

    Wipe bushings, barriers, and insulating parts. Remove the dust, smoke, and any foreign

    deposits. Replace the damaged parts.

    Check control devices and replace if needed.

    Check breaker control wiring and ensure that the connections will be tight.

    Operating breaker in fully opened and closed position after service. Check for any

    binding before going to put in the circuit.

    6.5 MAINTENANCE OF CONTACTOR:

    The duty of the contactor is very often in a day. Such duty reflected in mechanical wear and tear

    and also electrical contact wear. The maintenance process:

    Cleaning

    Dressing or renewal of main and auxiliary contacts.

    Checking contact alignment.

    Trip mechanism inspection.

    Check tightness and conditions of all connections.

    Arc chute inspection.

    Lubrication.

  • 8/10/2019 Elecrical Equipment Maintenance in Pipelines

    21/59

    ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

    21submitted by Anirban Das

    6.6 MAINTENANCE OF ISOLATOR:

    The maintenance of isolator mainly consists of:

    Cleaning, checking contact conditions and tightness of connections and confirming the

    tightness and continuity of the fuses, if fitted.

    6.7 PROTECTIVE RELAY MAINTENANCE:

    The maintenance of protective relays should include general inspection of physical condition of

    all parts at regular intervals. Maintenance as follows:

    Relays are provided with dust proof covers and before a cover is removed, the cases

    should be carefully dusted.

    Relay interior should be free from dust, iron particles etc.

    Dust and dirt should be carefully wiped off by a soft squirrel hair brush. Mechanical

    blowers or blowing by mouth is not recommended.

    The internal wiring, ICs, printed circuits should be examined for corrosion. Excessive

    heat may damage the insulation.

    Relay flags/targets should operate freely without friction and also reset freely.

    Perform complete tripping and operational tests to verify all control and protective

    functions and alarms and tripping mechanism.

  • 8/10/2019 Elecrical Equipment Maintenance in Pipelines

    22/59

    ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

    22submitted by Anirban Das

    TROUBLE SHOOTING:

    SYMPTOM CAUSE CORRECTIVE

    MAINTENANCE

    Over heating

    Breaker is not closing.

    Improper alignment and

    adjustment of contactor.

    Burnt and pitted due to

    lack of attention after

    many heavy operations,

    or too frequent

    operations.

    Breaker kept closed (oropen) for a too long

    period.

    Transmission of heat to

    the breaker from

    overheated or inadequate

    cables or connection bars.

    Failure of latching device.

    Damaged trip coil

    Damaged or dirty

    contacts of tripping

    circuit

    Faulty connections in trip

    circuit (loose or broken)

    Insufficient voltage

    caused by too much drop

    in leads.

    Poor voltage regulation

    Loose connections

    Contacts should be aligned and

    adjusted properly. Contacts to be

    repaired or replaced properly.

    Burnt and pitted contacts should

    be dressed up if possible or

    replace with new parts. Dressing

    up to be done carefully.

    Contacts to be wiped out forcleaning and if possible silver-to-

    silver contacts to be arranged.

    If heat is due to excess current,

    fault should be corrected. If

    cable size is in adequate, cable

    should be replaced.

    Examine surface of the latch, if

    worn or corroded, check latch,wipe, and adjust according to

    instruction book.

    Replace it.

    Dress or replace damaged

    contacts. Clean the dirty

    contacts.

    Replace faulty wires. All

    connections are to be tightened.

    Replace with oversize wires.

    Improve contact at connections.

    Check up voltage, if less correct

    it.

    Tighten the connections.

  • 8/10/2019 Elecrical Equipment Maintenance in Pipelines

    23/59

    ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

    23submitted by Anirban Das

    Frequent damage of

    moving and fixing

    contacts

    Bushing problems

    Inadequate current

    carrying capacity

    Improper replacement of

    switch gear during

    maintenance.

    Misalignment of controls

    or inadequate pressure

    between moving and

    fixed contacts

    Accumulation of dirt or

    other deposits

    Flash over due to foreign

    deposits like salt, cement

    dust etc.

    Capacity of contactors as well as

    breakers should be examined.

    Capacity of original switch gear

    should be matched with new one.

    Contacts to be dressed up. Spring

    etc. to be checked for proper

    pressure.

    Clean external surface.

    Frequency of cleaning to be

    increased. Carbon tetra chloride

    or liquid ammonia or any other

    suitable agent may be used to

    clean porcelain.

    TABLE-05

    7. ELECTRIC MOTOR

    7.1 INTRODUCTION:

    Motors covert electrical energy into mechanical energy. Mainly motors are classified

    into two types:

    D.C motors

    A.C motors

    D.C. motors are mainly used in traction works and cranes where constant speed

    characteristics are necessary. These are not used in domestic and industrial purposes because the

    cost of the D.C motor is high and also the supply of D.C power also costly one.

  • 8/10/2019 Elecrical Equipment Maintenance in Pipelines

    24/59

    ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

    24submitted by Anirban Das

    So the best alternative is using A.C motors. In general most of industries are using 3-

    phase motors. Hence we here consider 3-phase motors only.

    The motors are classified into two types:

    Induction motors

    Synchronous motors

    Let us briefly discuss about induction motors because many industries using

    induction motors only.

    7.2 CONSTRUCTION:

    Motor mainly consists of two basic parts know as

    Stator

    Rotor

    Figure-10: cut way view of squirrel cage induction motor

  • 8/10/2019 Elecrical Equipment Maintenance in Pipelines

    25/59

    ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

    25submitted by Anirban Das

    Figure-11: Rotor of the squirrel cage induction motor

    The stator winding and rotor windings are insulated. The primary purpose of

    insulation is to withstand turn-to-turn, phase to-phase and phase-to-ground voltage such that to

    direct the stator phase currents through the desired paths of stator windings.

    The insulations are classified as:

    Class A: 105C

    Class B: 130C

    Class F: 155C

    Class G: 180C

    For motors having high temperature rise class F insulation is uses.

    7.3 MAINTENANCE OF MOTOR:

    Motors are designed to give many years of reliable service with less attention. A

    definite schedule of preventive/inspection/predictive maintenance should be established to avoid

    breakdown. The schedule depends on the operating conditions and experience with the similar

    equipment.

  • 8/10/2019 Elecrical Equipment Maintenance in Pipelines

    26/59

    ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

    26submitted by Anirban Das

    7.3.1 PREDECTIVE MAINTENACE:

    The main goal of the predictive maintenance is to predict and fix the faults by using

    following techniques before they occur.

    The techniques are:

    Vibration analysis:

    This technique involves measuring machinery vibration to identify ongoing

    conditions through vibrometer. This tells us the bearing damages.

    Motor circuit analysis:

    This technology monitors the conditions of complete motor circuit parameters like phase

    resistance, inductance and capacitance.

    7.3.2 PREVENTIVE MAINTENANCE:

    7.3.2.1 A schedule for LT&HT motors (Half yearly):

    Counter check that equipment is isolated positively.

    Check the terminal box for loose connection in the cable termination.

    Perform regreasing.

    Remove front and rear grease cups if regreasing system is not healthy.

    Check the condition of the grease. Top up grease if condition is not o.k.

    Put back grease cups.

    Connect the terminal box.

    Check the earthing and return the clearance.

    Perform the visual inspection of the stator module, cable terminals.

    7.3.2.2 B schedule for LT&HT motors(Predictive):

  • 8/10/2019 Elecrical Equipment Maintenance in Pipelines

    27/59

    ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

    27submitted by Anirban Das

    Counter check that equipment is isolated positively by means of LT/HT tester.

    Get the motor decoupled.

    Open the terminal cover and remove the cable connections.

    Open the foundation bolts and take out the motor from foundation and send to electrical

    workshop for schedule.

    Inspect the motor for visible damages and rotor freeness.

    Open the fan cover and remove the fan from the shaft.

    Remove the grease cups on both sides. Inspect the condition of grease.

    Take out both rear and front end shields.

    Check the bearing housing for correct measurement of the bearing with sufficient

    tolerances.

    Remove both front and rear bearing from the shaft.

    Clean all the grease using suitable solvent. Then wash the bearing with diesel and dry air.

    Remove the rotor from stator.

    Inspect rotor thoroughly for the loose bars and cage/shorting rings.

    Inspect the bearing seat. If it is worn out and loose metalize the bearing.

    Check the rotor trueness. If the shaft is bent send it for reshafting.

    Replace the studs and nuts of the grease cups if worn out.

    Inspect the stator winding for loose coils, loose connections, heating effect, deterioration

    of insulation etc.

    Clean the stator winding with clean dry cloth and blower.

    Heat the winding in heating chamber up to 100C for 8 hours.

    Again clean the winding.

    Heat the stator for 6 hours.

  • 8/10/2019 Elecrical Equipment Maintenance in Pipelines

    28/59

    ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

    28submitted by Anirban Das

    Apply protective coat of varnish.

    Heat the windings (80C) till the varnish is dried.

    Clean the stator and make ready for the assembly.

    Clean the rotor also and insert the rotor in position.

    Put the bearings on the shaft.

    Assemble the motor with end shields in position.

    Put back the fan on shaft.

    Put back coupling on the shaft.

    Run the motor and monitor the performance for four hours.

    TROUBLE SHOOTING:

    SYMPTOM CAUSE CORRECTIVE

    MAINTENANCE

    Motor will not start Overload control trip

    Power not connected to motor

    Faulty (open) fuses

    Low voltage

    Wrong control connections

    Loose terminal lead connections

    Open circuit in stator or rotor

    winding

    Short circuit in stator winding

    Wait for overload to cool. Try

    starting again. If motor still

    doesnt start, check all thecauses shown below.

    Connect power to motor.

    Test fuses and circuit breakers.

    Check motor name plate values

    with power supply. Check

    voltage at motor terminals with

    motor under load to be sure wire

    size is adequate.

    Check connection with control

    wiring diagram.

    Tight connections.

    Check for open circuits.

    Check for shorted coil.

  • 8/10/2019 Elecrical Equipment Maintenance in Pipelines

    29/59

    ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

    29submitted by Anirban Das

    Motor noisy

    Motor vibrates

    At higher than normal

    temperature or

    smoking

    Bearings stiff

    Over load

    Motor running in single phase

    Electrical load unbalance

    Vibration due to unbalance or

    misalignment

    Mechanical system resonance

    Air gap is non uniform

    Noisy ball bearings

    Loose punching or loose rotor

    on shaft

    Objects caught between fan and

    end shields

    Motor loose on foundation

    Coupling loose

    Overload

    Electrical load unbalance

    Restricted ventilation

    Incorrect voltage and frequency.

    Stator winding shorted

    Rotor winding with loose

    Free bearings or replace.

    Reduce the load.

    Stop motor and then try to start

    motor, it will not start in singlephase.

    Check current balance.

    Balance or align the machine.

    Remove motor from load. If

    motor is still noisy, rebalance

    the rotor.

    Centre the rotor and if necessary

    replace the bearings.

    Check the lubrication. Replace

    bearings if noise is excessive.

    Tighten all holding bolts.

    Disassemble motor and clean it.

    Tighten holding-down bolts.

    Check coupling joint, check

    alignment. Tighten coupling.

    Measure the motor load with

    ammeter and reduce the load.

    Check for voltage un balance orsingle phasing.

    Clean air passages and

    windings.

    Check motor name plate values

    with power supply.

    Use insulation testing

    procedures.

    Tighten if possible or replace

  • 8/10/2019 Elecrical Equipment Maintenance in Pipelines

    30/59

    ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

    30submitted by Anirban Das

    Bearings hot

    Sleeve bearings

    connections

    Motor used for rapid reversing

    service

    Bent shaft

    Insufficient oil

    Foreign materials in oil or poor

    grade of oil

    Oil rings rotating slowly or not

    rotating at all

    Defective bearings or roughshaft

    with another rotor.

    Replace with motor designed for

    reversing service.

    Straighten the bent shaft atservice shop.

    Add oil if oil is very low.

    Drain, oil flush, and re lubricate

    using industrial lubricant.

    Oil too heavy, drain and replace.

    Replace bearings. Resurface

    shaft.

    TABLE-06

    8. MOV ACTUATORS

    8.1 DESCRIPTION:

    Electrically operated motor operated valves are widely used in power plant/process

    units and play a critical role. A typical actuator consists of

    3-phase induction motor

    Control gear

    Travel limit switches and torque switches

    Local controls

  • 8/10/2019 Elecrical Equipment Maintenance in Pipelines

    31/59

    ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

    31submitted by Anirban Das

    Electronics circuit consists of power supply unit, remote operating unit, and logic cords.

    Figure-12: Sectional View of Motor operated valve

  • 8/10/2019 Elecrical Equipment Maintenance in Pipelines

    32/59

    ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

    32submitted by Anirban Das

    Figure-13: Motor Operated Valve

    8.2 MAINTENANCE:

    Schedule:

    Based on the plant run length and application, a routine maintenance program is to

    be developed. The maintenance period will be 1 year.

    Check for evidence of oil leakage and rectify

    Check the condition of gear case oil and replace if necessary.

    Check the security of actuator mounting bolts.

    Check cable connections to the actuator.

    Check motor winding insulation resistance and check winding resistance is balance.

    Check engagement of the clutch.

    Energize the actuator and check direction of rotation.

    Check electrical operation to limits.

    In intelligent units check the healthiness from the diagnostic codes as per the vendors

    manual.

  • 8/10/2019 Elecrical Equipment Maintenance in Pipelines

    33/59

    ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

    33submitted by Anirban Das

    TROUBLE SHOOTING:

    TABLE-07

    9. CATHODIC PROTECTION

    9.1 INTRODUCTION:

    Cathodic protection is an electrochemical method used to prevent or control

    corrosion of buried or submerged metallic structures.

    After a CP system is installed and adjusted to provide adequate protection, currents

    and potentials should remain relatively stable; changes in currents or potentials indicate a

    problem.

    SYMPTOM CORRECTIVE MAINTENANCE

    MOV not operating

    MOV not operating

    although 3 phase

    supply is healthy

    MOV not operatingfor intelligent type

    MOV

    Check healthiness of 3 phase supply.

    Check mechanism for freeness.

    Check control gear/contactor.

    Check PCBs.

    Check control circuit.

    Check limit switch.

    Check internal battery.

    Check PCBs.

  • 8/10/2019 Elecrical Equipment Maintenance in Pipelines

    34/59

    ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

    34submitted by Anirban Das

    9.2 CATHODIC PROTECTION METHODS:

    Sacrificial (Galvanic) Cathodic protection.

    Impressed current Cathodic protection.

    Out of these two methods impressed current protection is the most economical one

    for the long pipelines. The disadvantages of the Galvanic protection is small driving voltage is

    available, and small current available in higher resistivity electrolytes. Here we discuss briefly

    about impressed current CP protection.

    In an impressed current system, the protective current is supplied by a rectifier (or

    other DC power source) to the structure.

    Figure-14: Impressed Current Cathodic Protection System

    Impressed current Cathodic protection systems use alternating current or solar

    powered rectifiers as a power source.

    Rectifiers used for Cathodic protection commonly use an

    Adjustable step down transformer,

    Rectifier stacks,

  • 8/10/2019 Elecrical Equipment Maintenance in Pipelines

    35/59

    ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

    35submitted by Anirban Das

    A shunt to measure output current,

    Meters to indicate output current and voltage.

    The function of the rectifier is to convert alternating current into controlled direct current.

    Figure-15: Impressed current Cathodic protection system Rectifier

    9.3 RECTIFIERS USED IN CATHODIC PROTECTION:

    Silicon diodes

    Thyristors

    Switch mode

    9.4 ANODE MATERIAL:

    The anodes of an impressed current system provide the means for the protective

    current to enter the electrolyte. Since the anodes form the corroding part of the system, the best

    material is one that has a low rate of weight loss per ampere-year. The most commonly used

    materials for impressed current anodes are graphite and high-silicon cast iron.

    9.5 MAINTENANCE:

    9.5.1 RECTIFIER OPERATIONAL INSPECTION:

  • 8/10/2019 Elecrical Equipment Maintenance in Pipelines

    36/59

    ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

    36submitted by Anirban Das

    The purpose of the rectifier operational inspection is to determine the serviceability

    of all components required to impress current to the anodes of the impressed current system.

    Maintenance Schedule:

    Thirty days after cathodic protection system is installed and properly adjusted.

    One to two years after that.

    Procedure:

    Visually check all rectifier components, shunt box components, safety switches.

    Tighten all accessible connections and check temperature of all the components.

    For rectifiers with more than one circuit, measure the output voltage and current for each

    circuit using a dependable hand-held meter, and calibrate the rectifier meters, if present.

    Calculate the cathodic protection system circuit resistance of each circuit by dividing the

    rectifier DC voltage output of each circuit by the rectifier DC ampere output for that

    circuit.

    9.5.2 IMPRESSED CURRENT CHECK:

    Maintenance schedule:

    Sixty days after rectifier inspection, more frequent checks may be required by local

    conditions.

    Procedure:

    Measure output D.C voltage and current from the rectifier.

    Ensure the DC ampere output of the rectifier meets the current (ampere) requirement of

    the system.

  • 8/10/2019 Elecrical Equipment Maintenance in Pipelines

    37/59

    ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

    37submitted by Anirban Das

    Calculate the cathodic protection system circuit resistance of each circuit by dividing the

    rectifier DC voltage output of each circuit by the rectifier DC ampere output for that

    circuit.

    Calculate the D.C out put voltage of the rectifier and check that it is rated or not.

    TROUBLE SHOOTING:

    Figure-16: Wiring diagram of a Rectifier

  • 8/10/2019 Elecrical Equipment Maintenance in Pipelines

    38/59

    ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

    38submitted by Anirban Das

    .

    TABLE-08

    10. EMERGENCY GENERATOR

    10.1 INTRODUCTION:

    Generator is the alternate energy source for emergency power needs in the pumping

    station. There are many names for generator such as A.C generator and alternator. Alternator is

    the commonly used name.

    A typical pump station consists of diesel engine driven alternator to cater to

    emergency power requirements like,

  • 8/10/2019 Elecrical Equipment Maintenance in Pipelines

    39/59

    ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

    39submitted by Anirban Das

    Radiator motors of mainline engines

    Air compressors

    Centrifuges

    UPS system

    Lighting in the pump shed and control room etc.

    10.2 GENERATOR CONSTRUCTION:

    The stationary field

    The rotating dc magnetic field.

    The armature, normally containing a three-phase winding, is mounted on the shaft.

    The armature winding is fed through three slip rings (collectors) and a set of brushes

    sliding on them.

    The rectifier-bridge is fed from a shaft-mounted alternator, which is itself excited by

    the pilot exciter.

    The core is slotted (normally open slots), and the coils making the winding are placed

    in the slots.

    .

  • 8/10/2019 Elecrical Equipment Maintenance in Pipelines

    40/59

    ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

    40submitted by Anirban Das

    Figure-17: The figure shows Silent type Generator

    10.3 MACHINE RATINGS:

    A generator is usually described by giving it a rating. This rating is given at the generators

    capability point of maximum continuous power output. The terms generally used to provide

    the rating are as follows:

    Apparent power MVA Mega volt amperes

    Real power MW Mega watts

    Reactive power MVARs Mega volt amps reactance

    Power factor pf A dimensionless quantity

    Stator terminal- Voltage Vt Alternating voltage

    Stator current Ia Alternating current amperes

    Field voltage Vf Direct voltage

    Field current If Direct current amperes

    Frequency Hz Hertz

    Speed rpm Revolutions per minute

  • 8/10/2019 Elecrical Equipment Maintenance in Pipelines

    41/59

    ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

    41submitted by Anirban Das

    Figure-21: Name plate details of A Generator

    10.4 GENERATOR MAINTENANCE:

    10.4.1 Weekly Maintenance: Before starting engine

    Check oil level (add oil as needed).

    Check coolant level.

    Walk around inspection.

    Check air cleaner indication (change filter as needed).

    Fuel system- check for leaks.

    Inspect belts, adjust or repair as needed.

    Check generator for moisture, dust, &debris and clean it.

    10.4.2 Weekly Maintenance: With engine running

    Check for proper oil pressure.

    Check for proper jacket water temperature.

  • 8/10/2019 Elecrical Equipment Maintenance in Pipelines

    42/59

    ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

    42submitted by Anirban Das

    Check for proper fuel pressure.

    Check frequency and voltage.

    Record engine run hours.

    10.4.3 Weekly Maintenance: After stopping engine

    Automatic switches- check switches in proper position for automatic start.

    Check fuel level; refill the tank if below 3/4 full.

    10.4.4 Yearly Maintenance: Before starting the engine

    Perform all weekly before starting engine maintenance first.

    Add coolant conditioner as needed.

    Drain water and sediment from fuel tank.

    Change fuel filter.

    Inspect and clean or replace air filter element if needed.

    Check and adjust all linkages.

    Test all engine protective devices.

    Check generator winding with mega ohm meter.

    Check generator bearing. Lubricate as required.

    10.4.5 Yearly Maintenance: With engine running

    Perform all weeklywith running engine maintenance first.

    Inspect engine mounts. Check for proper torque.

    Load test to minimum 30% its rated load for minimum 2 hours. Record all the gauge

    readings.

    Jacket water temperature will be higher compared to weekly no-load tests.

  • 8/10/2019 Elecrical Equipment Maintenance in Pipelines

    43/59

    ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

    43submitted by Anirban Das

    10.4.6 Yearly Maintenance: After stopping engine

    Perform all weekly after stopping engine maintenance first.

    Obtain oil sample for analysis of chemical and physical test.

    Change engine oil.

    Replace oil filter. Cut filter and inspect for foreign material.

    10.4.7 Three years maintenance: Before starting engine

    Perform all weekly & yearly before starting engine first.

    Cooling system

    Drain, clean and flush.

    Replace thermostats.

    Refill with coolant solution and conditioner.

    Inspect radiator cap and replace if needed.

    Replace all hoses and belts.

    Inspect turbo charger for proper operation.

    Perform engine adjustment & tune up.

    10.4.8 Three years maintenance: With engine running

    Perform all weekly & yearly before starting engine first.

    Check engine mounts. Check for proper torque.

    Check exhaust system for leaks. Repair as needed.

    10.4.9 Three years maintenance: After stopping engine

    Perform all weekly & yearly after stopping engine first.

    Obtain oil samples for analysis.

  • 8/10/2019 Elecrical Equipment Maintenance in Pipelines

    44/59

    ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

    44submitted by Anirban Das

    10.4.10 Grounding Cables:

    Schedule: Monthly:

    All generator frames and casings are grounded to the power plant grounding system.

    This is usually done at one location only to allow control over the ground current flow, and to

    ensure that there are no circulating currents in the generator frame structure that will cause arcing

    between components inside the machine.

    Figure-19: Grounding of a Generator

    The ground cables should be inspected to ensure they are tight and in generally good condition.

    Signs of damage would be corrosion, overheating, fraying, or cracking.

    11. SAFETY WHILE DOING ELECTRICAL MAINTENANCE

    While doing maintenance works every one should follow the safety procedures.

    A routine task can easily become a hazard if the required procedure is not followed or if

    attention to detail is not applied.

    Do not assume that the hazards in your work area are always at your eye/foot level. Be

    aware of ALL your surroundings.

  • 8/10/2019 Elecrical Equipment Maintenance in Pipelines

    45/59

    ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

    45submitted by Anirban Das

    A complete review of all systems should be conducted prior to any maintenance work.

    All electrical equipment connected to line voltage must be bonded to ground

    Necessary electrical repairs should be made by a qualified electrician.

    ALWAYS de-energize electrical power source before making any adjustments

    Discharge capacitors (if present) to prevent electrical shock.

    Beware of moving parts.

    Remove and replace any safety guards.

    Figure-20: Protective Equipment

    Wear Common Protective or Safety Equipment such as Safety Shoes, Glasses, Gloves,

    Hearing Protection, Hard Hats, or Life Jackets.

    When working on cables that are close to energized cables, particularly if they are

    running in parallel, precautions shall be taken to minimize the risk of injury to personnel.

    Similar precautions are required when working within 100 meters of a Zone.

    Jointing of high voltage cables shall only be carried out by personnel trained and

    accredited for a particular joint type.

  • 8/10/2019 Elecrical Equipment Maintenance in Pipelines

    46/59

    ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

    46submitted by Anirban Das

    Jointing of high voltage cables is not permitted if it is raining.

    Make sure that system is properly earthed.

    Tag out the devices.

    ANNEXURE-A:

  • 8/10/2019 Elecrical Equipment Maintenance in Pipelines

    47/59

    ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

    47submitted by Anirban Das

    CONSTRUCTION:

    Cables consist of three major components: conductors, insulation, and protective jacket. The

    makeup of individual cables varies according to application. The construction and material

    are determined by three main factors:

    Working voltage, determining the thickness of the insulation

    Current-carrying capacity, determining the cross-sectional size

    Environmental conditions such as temperature, water, chemical or sunlight exposure,

    and mechanical impact, determining the form and composition of the outer cable

    jacket.

    Fig:Cut way view of the cable

    TYPES OF CABLES USED FOR DISTRIBUTION NETWORK

    MAJOR TYPES MAJOR SIZES

    (Sq mm)

    33kv underground

    22kv underground

    11kv underground

    LT cables underground

    XLPE

    PILC

    PILC

    XLPE

    400,300

    300

    240,120,70

    240,120,50

  • 8/10/2019 Elecrical Equipment Maintenance in Pipelines

    48/59

    ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

    48submitted by Anirban Das

    XLPE- CROSS LINKED POLY ETHYLENE CONDUCTOR

    PILC- PAPRE INSULATED LEAD SHEATHED CONDUCTOR

    HT CABLES:

    FIG: CROSS SECTIONAL DRAWING FOR 33KV 3CX400 sq.mm-A2XWY CABLE

    HT cable components:

    Conductors:

    H4 grade Aluminum conductor of electrolytic grade stranded of circular cross section

    complying with IS-8130/1984.

  • 8/10/2019 Elecrical Equipment Maintenance in Pipelines

    49/59

    ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

    49submitted by Anirban Das

    Size

    mm2

    Min. Number of

    strands/wires per conductor

    Min. Diameter of each strand/

    Wire (mm)

    1000

    400

    300

    150

    89

    59

    36

    36

    3.93

    3.04

    3.4

    2.4

    Conductor Screening:

    Either non-metallic semi-conducting tape or a layer of extruded semi-conducting compound

    or a combination of two.

    Insulation:

    XLPE extruded insulation

    Insulation Screening:

    Extruded Semi-conducting screening with water swellable tapes and metallic screening.

    Inner Sheath:

    Pressure extruded inner sheathing of Black PVC.

    Armour:

    The Armour shall be of galvanized steel round wires with fault level of 1500 MVA at 33kV

    & 500 MVA at 11 kV. Duration of fault level is one (1) second.

    Outer Sheath:

  • 8/10/2019 Elecrical Equipment Maintenance in Pipelines

    50/59

    ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

    50submitted by Anirban Das

    An extruded outer sheathing of Blue PVC.

    LT CABLES:

    LT cables Standardized Ratings are:

    2 core 25 sq. mm

    4 core 25 sq. mm

    4 core 50 sq. mm

    3.5 core 120 /240 sq. mm

    3.5 core 150 / 300 sq. mm

    SECTOR SHAPED

    CROSS SECTIONAL DRAWING FOR3.5 C X 240 sqmm (A2 X FY) L.T. CABLE

    ALLUMINUM CONDUCTOR

    XLPE INSULATION EXTRUDED PVCOUTER SHEATH

    INNER SHEATHEXTRUDED PVC

    FLAT G.S.STRIP

    D:\\ OLDHDD\MISC\cross sectional view of 3.5 c x 240 sqmm cable

  • 8/10/2019 Elecrical Equipment Maintenance in Pipelines

    51/59

    ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

    51submitted by Anirban Das

    Insulation:

    XLPE extruded insulation

    Inner Sheath:

    An extruded inner sheathing of Black PVC conforming to the requirement of type

    ST-2.

    Armour:

    The dimension of galvanized steel Strips shall be as specified and shall conform to IS:

    7098/Pt-1

    Outer Sheath:

    An extruded outer sheathing of Yellow PVC.

  • 8/10/2019 Elecrical Equipment Maintenance in Pipelines

    52/59

    ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

    52submitted by Anirban Das

    ANNEXURE-B:

    Cable Selection Criterion:

    Cable Types- XLPE, PILC & PVC.

    XLPE cables are most popular because of its better electrical and thermal properties like

    higher continuous operating temperature, Short Circuit temperature, Break Down strength

    etc.

    Main Consideration:

    For 11 kV,22 kV and 33 kV cables, the cable size is determined by continuous current

    rating and short circuit rating.

    For 1.1 kV cable, the selection of size is determined by continuous current rating, the

    maximum permissible voltage drop and short circuit rating.

    In addition to above, following are some factors for deciding the type and size of

    cable.

    1. Earth fault current carrying capacity.

    2. Voltage drop (For low voltage system)

    3. Power loss

    ANNEXURE- C:

    METHODS OF CABLE LAYING:

    Laying direct in ground

    Drawing in Ducts

    Horizontal drilling

  • 8/10/2019 Elecrical Equipment Maintenance in Pipelines

    53/59

    ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

    53submitted by Anirban Das

    The cables are laid directly in the ground with a depth of 1 meter. Cables are also pulled in

    ducts. The pulling tension is important and depends on the method of pulling.

    Maximum allowable pulling tension:

    The maximum allowable tension on cable conductors that should be used during

    pulls must be based on experience as well as good engineering. Factors that have an impact

    on the value include type of metal, temper, and factors of safety.

    METAL TEMPER POUNDS PER

    CIRCULAR MILL

    Copper

    Aluminum

    Aluminum

    Aluminum

    Aluminum

    Soft

    Hard

    Hard

    Hard

    Soft

    0.008

    0.008

    0.006-0.008

    0.003-0.004

    0.002-0.004

    Ref: AEIC CG5-(2nd Edition)-2005

    Pulling tension calculation:

    The basic equation to calculate the pulling tension is

    T= W*L*f

    Where T= tension in pounds

    W= weight of one foot of cable in pounds

  • 8/10/2019 Elecrical Equipment Maintenance in Pipelines

    54/59

    ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

    54submitted by Anirban Das

    L= length of pull in feet

    f = co-efficient of friction for the duct material and outer layer of the cable.

    Horizontal drilling is employed where excavation of roads for cable laying is not possible. In

    this method the road is drilled horizontally and cables are laid through Hume pipes which are

    inserted into the drilled holes.

    CABLE INSTALLATION PLAN:

    On completion of laying, termination and jointing of cables, a computerized

    drawing is prepared, which contains the following details of the installation.

    Type of cables, cross-section area, rated voltage, details of construction, cable number and

    drum number;

    a. Year and month of laying;

    b. Actual length between joint-to-joint or ends;

    c. Location of cables and joints in relation to certain fixed reference points, for e.g.-

    Buildings, hydrant etc;

    d. Name of the jointer who carried the jointing work;

    e. Date of making joint and Result of original electrical measurements and testing on

    cable installation;

    All subsequent changes in the cable drawings are entered after the job. All drawings are

    maintained in digital format.

    CABLE MARKING AND LOCATION:

  • 8/10/2019 Elecrical Equipment Maintenance in Pipelines

    55/59

    ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

    55submitted by Anirban Das

    Cables shall be marked with one tag indicating direction or exit from underground

    facilities

    This tag shall indicate the general direction of the cable(s) to the next facility where

    the cable is located.

    All tags will be labeled with the next point of connection (i.e. transformer 1 to

    transformer

    A redplastic warning tape shall be spread above the underground electrical cable

    within the right-of-way at a depth of 0.6 m from the ground surface.

    ANNEXURE-D:

    TESTING OF CABLES:

    The testing methods are

    Direct voltage testing

    Low voltage D.C testing

    High voltage D.C testing

    Power frequency testing

    Low voltage testing:

    This test is used to determine the insulation resistance of the cable. In this test Cable phases

    not under test should have their conductors grounded. Ends, both at test location and remote,

    should be protected from accidental contact by personnel, energized equipment and grounds.

    Apply the prescribed test voltage for specified period of time. It may be advantageous to

    conduct the test with morethan one voltage level and record readings of more than one time

    period.

  • 8/10/2019 Elecrical Equipment Maintenance in Pipelines

    56/59

    ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

    56submitted by Anirban Das

    High voltage testing:

    This test is used to determine the leakage current in the cable. Apply the prescribed test

    voltage for the specifiedperiod of time.Totalapparent leakage output current is recorded asa

    functionof time at a prescribed voltage level.

    Power frequency testing:

    As the name implies, these test methods are based on using alternating current at the

    operating frequency of the system as the test source. This test is used to determine the Partial

    Discharge.Partial discharge measurement is an important method of assessing the quality of

    the insulation of power cable systems, particularly for extruded insulation materials.

    PD testing is an evolving technology for periodic diagnostic testing of XLPE-

    insulated cables. Partial discharges occur at voids in insulation and at the interface layers

    between cable and accessory insulation. These discharges emit broadband radiation in the

    range of 50 kHz to 500 MHzs PD testing is a nondestructive testing method, generally

    accepted as one of the most effective techniques for locating defects in XLPE cables.

    ANNEXURE-E:

    Insulation Resistance Test Values Electrical Apparatus and Systems

    Nominal Rating

    of Equipment in Volts Minimum Test Voltage, DC

    Recommended Minimum

    Insulation Resistance in

    Megohms

    250 500 25

  • 8/10/2019 Elecrical Equipment Maintenance in Pipelines

    57/59

    ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

    57submitted by Anirban Das

    600 1,000 100

    1,000 1,000 100

    2,500 1,000 500

    5,000 2,500 1,000

    8,000 2,500 2,00015,000 2,500 5,000

    25,000 5,000 20,000

    34,500 and above 15,000 100,000

    REF: INTERNATIONAL ELECTRICAL TESTING ASSOCIATION (NETA)

    ANNEXURE-F: ELECTRICAL TOOL KIT FOR MAINTENANCE WORKS

    S.No Tool name

  • 8/10/2019 Elecrical Equipment Maintenance in Pipelines

    58/59

    ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

    58submitted by Anirban Das

    1

    2

    3

    4

    5

    67

    8

    9

    10

    11

    12

    13

    14

    15

    16

    1718

    19

    20

    21

    22

    23

    24

    25

    26

    27

    28

    D-24 Reversible Screwdriver, 3/set

    D-74-L Screwdriver w/Checker

    D-81 Reversible Stubby Screwdriver

    D-331-150 Screwdriver

    D-332-150 Phillips Screwdriver

    N-9-150 Diagonal Cutting PliersN-838 Snips

    P-15-150 Long Nose Pliers w/Cutter

    P-56-175 Pliers w/Side Cutter

    P-86-125 Tweezers

    P-211Z-150 Slip Joint Pliers

    P-245 Slip Joint Pliers

    P-704 Crimping Tool, w/Stripper

    P-95 Wire Stripper

    W-210-200 Adjustable Wrench

    W-210-300 Adjustable Wrench

    W-521 Open End Wrench SetZ-341 Measure Tape

    Hammer

    Quick-point Knife (Large)

    Sealing Tape

    Vinyl Tape

    Plastic mallet

    Penlight (with Batteries)

    Brush

    Hex Wrench Set

    Multi meter

    B-56-B Tool Box

  • 8/10/2019 Elecrical Equipment Maintenance in Pipelines

    59/59

    ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

    List of Standards:

    IEEE Standard 43-2000 is the .Recommended Practice for Testing Insulation

    Resistance of Rotating Machinery.

    IEEE Standard 389-1996 is the IEEE Recommended Practice for Testing Electronics

    Transformers and Inductors.

    IEEE Standard 1415-2006 IEEE Guide for Induction Machinery Maintenance Testing

    and Failure Analysis.

    NACE SP0169:2007 - Control of External Corrosion on Underground or

    Submerged Metallic Piping Systems.

    NACE TM 0497 - Measurement Techniques Related to Criteria for Cathodic

    Protection on Underground or Submerged Metallic Piping Systems.

    NEMA (National Electrical Manufacturing Association) TR1-1993(R2000)

    Transformers.

    IS: 2705 for current transformer compilation.

    IS: 3156 for voltage transformer compilation.

    AEIC (Association of Edison illuminating Companies) G7-90 testing practices of

    underground cables.

    IEEE P-400 Guide for Field Testing and Evaluation of Shielded Power Cables