elpc polymet comments

3
1 March 13, 2014 Ms. Lisa Fay Minnesota Department of Natural Resources Division of Ecological and Water Resources Environmental Review Unit 500 Lafayette Road, Box 25 St. Paul, MN 55155-4025 [email protected] Re: Minnesota Department of Natural Resources, U.S. Army Corps of Engineers and U.S. Forest Service Supplemental Draft Environmental Impact Statement for the NorthMet Mining Project and Land Exchange Dear Ms. Fay, The Environmental Law & Policy Center (ELPC) appreciates the opportunity to comment on this proposed mine that would have a number of significant environmental and societal impacts. Because of the many significant impacts from the proposed project and flaws in the SDEIS, the Minnesota Department of Natural Resources, U.S. Army Corps of Engineers and U.S. Forest Service should deny PolyMet’s state mining and Clean Water Act Section 404 wetlands permit requests and the proposed land exchange. The following are serious flaws in the project proposal and SDEIS analysis relating to water quality, cumulative impacts analysis, project alternatives analysis and threatened and endangered species impacts. ELPC also supports the comments of the Friends of the Boundary Waters Wilderness, Conservation Minnesota, and the Minnesota Center for Environmental Advocacy that highlight these and other important issues in detail. The Minnesota Department of Natural Resources, U.S. Army Corps of Engineers and U.S. Forest Service should choose the No Action Alternative and deny the requested permits and land exchange. At the very least, the agencies must update the SDEIS with required analysis that was not included and correct other significant flaws identified in the comment process before the agencies make a decision on the proposed mine. Water Quality. The SDEIS and mining plan do not reasonably assure that the mine will not result in significant, irreversible water pollution. The SDEIS and mining plan model mechanical or potentially other types of water treatment as being required for at least 200 years at the mine site and at least 500 years at the plant site to prevent sulfate and other water pollution to watersheds connected to Lake Superior. At ES-35. The SDEIS, in fact, concludes that “[i]t is uncertain how long the project would require water treatment.At ES-11. No plan is presented

Upload: friends-of-the-boundary-waters-wilderness

Post on 27-Dec-2015

7 views

Category:

Documents


0 download

DESCRIPTION

Comments of the Environmental Law and Policy Center on the PolyMet SDEIS, March 2014.

TRANSCRIPT

Page 1: ELPC PolyMet Comments

1

March 13, 2014

Ms. Lisa Fay

Minnesota Department of Natural Resources

Division of Ecological and Water Resources

Environmental Review Unit

500 Lafayette Road, Box 25

St. Paul, MN 55155-4025

[email protected]

Re: Minnesota Department of Natural Resources, U.S. Army Corps of Engineers and

U.S. Forest Service Supplemental Draft Environmental Impact Statement for the

NorthMet Mining Project and Land Exchange

Dear Ms. Fay,

The Environmental Law & Policy Center (ELPC) appreciates the opportunity to comment on this

proposed mine that would have a number of significant environmental and societal impacts.

Because of the many significant impacts from the proposed project and flaws in the SDEIS, the

Minnesota Department of Natural Resources, U.S. Army Corps of Engineers and U.S. Forest

Service should deny PolyMet’s state mining and Clean Water Act Section 404 wetlands permit

requests and the proposed land exchange.

The following are serious flaws in the project proposal and SDEIS analysis relating to water

quality, cumulative impacts analysis, project alternatives analysis and threatened and endangered

species impacts. ELPC also supports the comments of the Friends of the Boundary Waters

Wilderness, Conservation Minnesota, and the Minnesota Center for Environmental Advocacy

that highlight these and other important issues in detail.

The Minnesota Department of Natural Resources, U.S. Army Corps of Engineers and U.S. Forest

Service should choose the No Action Alternative and deny the requested permits and land

exchange. At the very least, the agencies must update the SDEIS with required analysis that was

not included and correct other significant flaws identified in the comment process before the

agencies make a decision on the proposed mine.

Water Quality. The SDEIS and mining plan do not reasonably assure that the mine will

not result in significant, irreversible water pollution. The SDEIS and mining plan model

mechanical or potentially other types of water treatment as being required for at least 200 years

at the mine site and at least 500 years at the plant site to prevent sulfate and other water pollution

to watersheds connected to Lake Superior. At ES-35. The SDEIS, in fact, concludes that “[i]t is

uncertain how long the project would require water treatment.” At ES-11. No plan is presented

Page 2: ELPC PolyMet Comments

2

that reasonably assures that water treatment will be possible and effective for the stated hundreds

of years at a minimum.

Because of long timeframes that remain unknown, there is similarly no meaningful

demonstration that mine closure and reclamation will actually be possible. It is simply not

reasonable to determine – as the SDEIS does – that there are no significant sulfate and mercury

water quality impacts from the proposed mine when the proposed treatment is not demonstrated

as effective, when the water treatment relies on models that are projecting up to 500 years into

the future and when significant impacts are almost certain if the proposed treatment is not

effective for hundreds of years.

The agencies should deny the project on these water quality impacts alone. It is unreasonable to

approve a project that requires fully functioning water quality treatment for hundreds of years

into the future to avoid serious harm to Lake Superior and the watersheds adjacent to the mine.

Approval on these terms would constitute arbitrary and capricious agency action.

Cumulative Effects Assessment. The SDEIS’ Cumulative Effects assessment is

incomplete because it fails to include an analysis of the cumulative impacts of regional mining

affecting Lake Superior. The National Environmental Protection Act (NEPA) and the Minnesota

Environmental Protection Act (MEPA) require that cumulative effects analyses include other

past, present and reasonably foreseeable projects that, analyzed together, may have significant

impacts. The SDEIS’s Cumulative Effects assessment includes only mining and similar projects

in Northern Minnesota. At 6-15; Table 6-1. However, there are a number other current and

reasonably foreseeable mines near Lake Superior in Wisconsin and Michigan’s Upper Peninsula.

For example, large-scale existing and proposed mines include the Penokee Mine in Wisconsin,

the Empire and Tilden Mines near Marquette, Michigan and the Eagle Mine in Michigan. These

mines’ cumulative impacts on Lake Superior and the watersheds on which it depends must be

analyzed before the agencies can determine that there are no significant cumulative effects to

Lake Superior.

Alternatives. The SDEIS’ Alternatives analysis is too narrow. Both NEPA and MEPA

require that the agencies consider reasonable alternatives to the proposed action alternative and

that this analysis is included in the SDEIS. However, the SDEIS considers only one alternative

other than the No Action Alternative, and that alternative is just the same proposed mine, but

with a smaller land exchange acreage. At ES-42 – ES-43. Considering just one marginally

different alternative is too narrow of an alternatives range to satisfy NEPA and MEPA. The

SDEIS should consider additional reasonable proposed alternatives, such as an alternative

analyzing an underground mining proposal and an alternative requiring back-filling the mining

pits with waste-rock after closure.

Endangered and At-Risk Species Impacts. The PolyMet mine would cause serious

harm to the Endangered Canada lynx and the SDEIS fails to analyze impacts to Minnesota’s

moose population. The PolyMet mine plan would degrade 1,450 acres of habitat designated as

Critical Habitat for the Canada lynx under the Endangered Species Act. SDEIS at 5-365. The

mine and its related activities would also further increase the fragmentation of remaining Canada

Page 3: ELPC PolyMet Comments

3

lynx habitat. However, the SDEIS fails to include alternatives that would mitigate impacts, such

as alternatives minimizing new roads and traffic increases in Canada lynx habitat.

Moreover, the SDEIS does not address impacts to Minnesota’s moose population. Moose were

added to Minnesota’s list of Species of Special Concern in 2013 because of the population’s

recent, swift decline – a 50% decrease in population since 2005. Yet, the SDEIS’ moose

analysis does not meaningfully address how PolyMet’s proposal will impact moose or moose

habitat. The MDNR should insist on a thorough, specific analysis for this iconic Minnesota

species before it issues any mining permits.

For the foregoing reasons, the Minnesota Department of Natural Resources, the U.S. Army

Corps of Engineers and the U.S. Forest Service should find that the impacts and risks to the

environment and society from PolyMet’s proposed mine are too great to approve the project.

The agencies should choose the No Action Alternative and deny the requested permits and land

exchange. At a bare minimum, the agencies must require that the SDEIS is updated to include

legally-required analysis that was not included in this SDEIS and correct the other significant

flaws identified through the comment process before the agencies make a decision on the

proposed mine.

Thank you for your consideration.

Sincerely,

/s/ Allen Gleckner

Allen Gleckner

Staff Attorney

Environmental Law & Policy Center

2356 University Avenue West

Suite 403

St. Paul, MN 55114