environmental and social management plan of majuwa khok...
TRANSCRIPT
Government of Nepal
National Reconstruction Authority
Central Level Project Implementation Unit
District Level Project Implementation Unit
(Grant Management and Local Infrastructure)
Dolakha
Environmental and Social Management Plan of
Majuwa Khok Drinking Water Maintenance Sub-Project
Melung Rural Municipality-4
December, 2018
ii
Silent Features (Additional Information) of the Sub Project
SN Particulars Description
1 Name of Project Majuwa Khok Drinking Water
Maintenance Sub-Project
2 Type of Project Rehabilitation / Maintenance/
Reconstruction
3 Location Melung Rural Municipality-4, Lahare
Lobate Tole
4 District Dolakha
5 No. of Beneficiary HHs with in
sub-project area
65
6 No. of Earthquake Beneficiary 65
7 Major Works Earthwork, stone masonry wall, Stone
soling, PCC, RCC and Rehabilitation of
RVT and Intake Tank, pipeline fitting,
construction of public taps
8 Existing Structures with Capacity Cracked intake, 60% HDPE pipe damaged
9 Total Estimated Cost (NRs.)
Project Contribution
User Contribution
Other Contribution
1,754,400.04
1,578,960.04
175,440.00
0
10 Rationality
(a) Source Damage
(b) Increased Demand
(c) New Scheme
(d) Extension
(e) Others (………………)
Intake, reserve tank and distribution
pipeline damaged which had increased the
shortage of water and and no earthquake
beneficiaries house could start the
construction.
11 How does the Proposed Project
Fulfill the Provision of EHRP-
ESMF?
Before Gorkha earthquake, the drinking
water system was working properly. After
the earthquake, intake, reserve tank and
distribution pipelines have damaged and
thus local people of Lahare Lobate Tole
got affected. It has halted reconstruction
process for 31 households as they have
difficulties to manage the water needed for
drinking and reconstruction purpose
12 Is ESSR Approved? (if applicable) Yes
13 Is Separate ESMP Prepared? Yes
14 Earthquake and Safeguard Perspective of the Proposal:
Previously working drinking water system was damaged in Post-Gorkha
earthquake
Local people of Lahare Lobate Tole have deficit of water supply for
drinking & reconstruction
iii
Due to deficit of water supply people are facing problem in regular supply
of water especially in dry season.
15 Technical Data
1. Number of HHs to be
reconstructed during
project selection
31
2. Vulnerable HHs (with
Categories)
2 (Senior citizen and Single women above
70)
3. Source Name Bhedpu Khola
4. Source discharge (Dry
Season)
0.93 Liter/s
5. Water Demand (m3/day) 3.25 (50 Liter per HH)
6. Reservoir capacity 14m3
7. Break Pressure Tank
number
0
8. Length of pipe line
(transmission mains and
distribution
3035m
9. Type of transmission mains
and distribution pipe
HDPE
10. Numbers of tap stand 10
(A) Endorsement: DL-PIU (GMaLI) Prepared By:
Designation:
…………………..
Approved By:
Designation:
…………………..
(B) Endorsement: CL-PIU (GMaLI) Reviewed By:
Designation:
…………………..
Approved By:
…………………..
iv
Table of Contents Silent Features (Additional Information) of the Sub Project ......................................... ii
1. Introduction ............................................................................................................ 1
2. Objectives of ESMP ............................................................................................... 3
3. Methodology ........................................................................................................... 3
4. Site Description ...................................................................................................... 3
5. Environmental and Social Issues ............................................................................ 3
6. Environmental and Social Mitigation Plan ............................................................. 4
7. ESMP Cost ............................................................................................................. 4
ANNEXES ..................................................................................................................... I
Annex-I: Detail Cost-Estimate .................................................................................. II
Annex-II: Design and drawing ................................................................................. III
Annex-III: Google Map ........................................................................................... IV
Annex-IV: Photographs ............................................................................................ V
Annex-V: Beneficiaries List .................................................................................... VI
Annex-VI: Meeting Minutes ................................................................................. VIII
Annex-VII: Letter from DL-PIU .......................................................................... XIII
Annex-VII: Letter from Ward office .................................................................... XIV
1
1. Introduction
A magnitude 7.6 earthquake of shallow depth struck central Nepal with an epicenter
approximately 77km north-west of Kathmandu on April 25th 2015 causing widespread
destruction. On May 12, 2015 a large after shock of a magnitude 6.8 hit Nepal and caused
further causalities and damage. As of 3 June 2015, the reported casualties include: 8,702
deaths and 22,493 people injured. As the earthquake sequence destroyed 490,000 houses
mostly traditional mud brick and mud stone built and occupied by the rural poor and
rendered another 265,000 houses at least temporarily uninhabitable, the largest single
need identified in the Post Disaster Needs Assessment (PDNA) was housing and human
settlements, accounting for US$ 3.27 billion of needs.
The Government of Nepal (GON) has requested support from a number of development
partners, including the WB, to address the immediate and long-term damage inflicted by
the earthquake in Nepal. In response to this, World Bank approved a US$200 million
loan to finance the Earthquake Reconstruction Project (EHRP) approved on 18 June 2015
to support 55 thousand households of three severely affected districts namely: Dolakha,
Dhading and Nuwakot. The project will support in restoring affected houses with multi
hazard resistant core housing units in target areas and to enhance government’s ability to
improve long-term disaster resilience. Initially, the EHRP is to be completed by July
2020.
Considering the further need to support GoN, International Development Association (the
World Bank) has agreed to support additional US$300 million loan to finance the
Earthquake Housing Reconstruction Project (EHRP). The recent additional loan support
will cover another eleven severely affected districts including Gorkha covering 96000
households from Additional Financing and 3200 households from Multi Donor Fund.
Environment and Social Management Framework serves as a practical tool to ensure that
environment and social aspects are duly considered in the planning and implementation
process of earthquake housing reconstruction project. Accordingly, Revised ESMF, have
guided to address the environmental and social issues of the projects by site-specific
environmental and social management plan after selection of the sub-projects prioritized
by orientation and consultation in the respective local government.
Dolakha district is located in province- 3 situated in the height from 762 m to 7132 m
from mean sea level. The district lies in the latitude of 85 50' to 86 32' East and longitude
of 27 28' to 28 00' North. The climatic condition of districts varies from tropical to alpine
and tundra type. The average annual maximum temperature is 19° C and minimum
temperature is 8° C. The average rainfall is 2043.5 ml (District Profile Dolakha, 2015).
Dolakha is one the earthquake affected district. According to National Reconstruction
Authority (NRA), the total number of houses damaged in district is 58,388 of which
56553 are fully damaged and 1835 partially damaged. Dolakha district is administratively
divided into 7 Rural Municipality and 2 municipalities (former: 48 VDCs & 2
Municipalities). The total population residing in the district is about 186,557 in 45,688
households (HH) with an average HH size of 4.11 The female population (99554) in the
2
districts is higher than that of male population (87003). The sex ratio of the district is
85.47 (CBS, 2012)
Beneficiaries’ data of Dolakha District:
SN Beneficiaries
(Nos)
Beneficiaries
with
Agreement
(Nos)
Ist tranche
(Nos)
2nd tranche
(Nos)
3rd tranche
(Nos)
1 72819 67337 63532 54130 46856 Source: MIS dated 2076/01/02
Melung Rural Municipality ranges from the altitude of 845 to 2615 meter covers the
former VDCs Pawati, Ghyang Sukathokar, Vedpu, Dandakharka, Melung.
Administratively it is divided into 7 wards. The Charange river is major river passes
through Melung Rural Municipality.
3
2. Objectives of ESMP
This Environmental and Social Management Plan (ESMP) is addresses the problem
arise by shortage of water on hygiene, sanitation and other daily activities due to increase
demand of water for reconstruction and decreased capacity of storage tank. Therefore the
Main Objective of this ESMP is to maintain and rehabilitate the RVT, Intake, distribution
pipeline and construction of public taps of Water Supply System to support in
reconstruction of remaining houses of EHRP beneficiaries.
3. Methodology
Consultation and discussion: Consultation and discussion program was held
with Local Government (Chair of RM, deputy Chair, chief administrative
officer, ward chair persons and secretary) and engineers from DLPIU and
collected the environmental and social Issues.
Field visit: After the consultation walkover survey for verification of
environmental and social Issues which were collected from local level
consultation were carried out at project level. Environmental and Social
screening checklist was used for relevancy with ESMF guideline.
Desk study: Documents such as district profile, Municipality profile, CBS
publication and publication of line agencies at district level and other project
related reports were reviewed. Google earth map was taken to get the
overview of the project area.
4. Site Description
The sub-project is located at Lahare Lobate, Ward No. 4 of Melung Rural Municipality,
Dolakha district. The geographical location of the site is 27o32’37”N and 86o04’22”E.
with altitude of 812 MSL. According to Census 2011 the total household on Ward No. 4
of the Melung Rural Municipality is 918 and total population is 3705 of which 1596 are
male and 2109 are female. The area is dominated by Brahmin and Chhetri and is mostly
Hindu by religion. In Ward No. 4 of Melung Rural Municipality (Previously Bhedapu
VDC), the total housing reconstruction beneficiaries are 1797 in which out of total 65
Sub-project beneficiaries household, 31 houses were remained to be reconstructed due to
lack of water supply. Previously for the construction of other than these remaining
houses, people collected the water from almost half an hour walking distance downhill
which created trouble in water supply for reconstruction. Discharge of the source at
Bhedpu Khola is 0.93 liter/s in dry season. Rehabilitation and maintenance of the 14m3
capacity one RVT, Intake tank, 3000m distribution pipeline and construction of ten
different public tap on Lahare Lobate Tole will supply the ample amount of water for the
reconstruction.
5. Environmental and Social Issues
Site verification carried out on 2075/07/27 by Environmental Specialist, Social
Development specialist along with district engineer. Before Gorkha earthquake, the
4
drinking water system was working properly. After the earthquake, intake, reserve tank
and distribution pipelines have damaged and thus local people, especially Brahmin
community of Lahare Lobate Tole were affected. It has halted reconstruction process as
they have difficulties to manage the water needed for drinking and reconstruction
purpose.
After the completion of this sub-project water supply system will be smoothly run.
Further, the program will help for the sustainable safe drinking water supply in the area
which enhances the sanitation and hygiene along with reconstruction in the area. After
the completion of reconstruction of those remaining 31 houses, water supply system will
be managed by the user committee. For the maintenance of water supply system they will
generate the maintenance fund from the amount collected within the beneficiaries.
6. Environmental and Social Mitigation Plan
Rehabilitation and Reconstruction of water storage tank and distribution pipeline have
been proposed to address the issues of water scarcity raised by Ward Chairperson during
orientation and consultation program held on 2075/01/21 at Melung Rural Municipality.
The existing water supply has directly benefited more than 65 Households through public
taps.
Location Issues/
Significan
ce
Likely Potential
Impact
Time
of action
Responsibility
Melung Rural
Municipality-
4, Lahare
Lobate Tole
Cracked
intake,
60%
HDPE pipe
damaged
Increase in water
demand for
reconstruction
Adverse impact on
hygiene and sanitation
due to lack of
availability of water
Falgun,
2075 to 30
Baisakh,
2076
UG's/RM
ward/DLPIU-
GMaLI
7. ESMP Cost
Major works under ESMP includes dismantling old tank, earthwork, stone
masonry wall, Stone soling, PCC, RCC and water tank fitting, Distribution pipeline
fitting, tap construction. The total cost of sub-project is NRs. 999,150.00 of which
contribution from GMaLI will be NRs 890,000.00 and user committee will contribute
NRs 109,150.88. The contribution from user committee accounts for 10.92% of the total
cost. Per household capita cost of sub-project is NRs. 15,372.
VI
Annex-V: Beneficiaries List
S.N Name Address
ward
No. Settlement Remarks
1 Dal Bahadur Adhikari Melung Rural Municipality 4 Majuwa Khok Bhramin
2 Prakash Adhikari Melung Rural Municipality 4 Majuwa Khok Bhramin
3 Ramji Adhikari Melung Rural Municipality 4 Majuwa Khok Bhramin
4 Purna Bahadur Adhikari Melung Rural Municipality 4 Majuwa Khok Bhramin
5 Sushila Adhikari Melung Rural Municipality 4 Majuwa Khok Bhramin
6 Ramhari Adhikari Melung Rural Municipality 4 Majuwa Khok Bhramin
7 Munhari Adhikari Melung Rural Municipality 4 Majuwa Khok Bhramin
8 Kopila Adhikari Melung Rural Municipality 4 Majuwa Khok Bhramin
9 Ram Bahadur Adhikari Melung Rural Municipality 4 Majuwa Khok Bhramin
10 Ram Bahadur Adhikari Melung Rural Municipality 4 Majuwa Khok Bhramin
11 Om Bahadur Adhikari Melung Rural Municipality 4 Majuwa Khok Bhramin
12 Purna Bahadur Adhikari Melung Rural Municipality 4 Majuwa Khok Bhramin
13 Lal bahadur Adhikari Melung Rural Municipality 4 Majuwa Khok Bhramin
14 Puskar Adhikari Melung Rural Municipality 4 Majuwa Khok Bhramin
15 Devi Adhikari Melung Rural Municipality 4 Majuwa Khok Bhramin
16 Pamfa Adhikari Melung Rural Municipality 4 Majuwa Khok Bhramin
17 Ujjwal Adhikari Melung Rural Municipality 4 Majuwa Khok Bhramin
18 Bhola Adhikari Melung Rural Municipality 4 Majuwa Khok Bhramin
19 Susan Adhikari Melung Rural Municipality 4 Majuwa Khok Bhramin
20 Nilhari Adhikari Melung Rural Municipality 4 Majuwa Khok Bhramin
21 Nil Hari Adhikari Melung Rural Municipality 4 Majuwa Khok Bhramin
22 Bani Bahadur Adhikari Melung Rural Municipality 4 Majuwa Khok Bhramin
23 Sita Adhikari Melung Rural Municipality 4 Majuwa Khok Bhramin
24 Batuli Adhikari Melung Rural Municipality 4 Majuwa Khok Bhramin
25 Laxmi Adhikari Melung Rural Municipality 4 Majuwa Khok Bhramin
26 Kumar Adhikari Melung Rural Municipality 4 Majuwa Khok Bhramin
27 Dewa Adhikari Melung Rural Municipality 4 Majuwa Khok Bhramin
28 Sankala Adhikari Melung Rural Municipality 4 Majuwa Khok Bhramin
29 Santa Adhikari Melung Rural Municipality 4 Majuwa Khok Bhramin
30 Gea Adhikari Melung Rural Municipality 4 Majuwa Khok Bhramin
31 Biahnu Maya Adhikari Melung Rural Municipality 4 Majuwa Khok Bhramin
32 Krishna Adhikari Melung Rural Municipality 4 Majuwa Khok Bhramin
33 Kopila Adhikari Melung Rural Municipality 4 Majuwa Khok Bhramin
34 Prashant Adhikari Melung Rural Municipality 4 Majuwa Khok Bhramin
35 Shila Adhikari Melung Rural Municipality 4 Majuwa Khok Bhramin
36 Padam Kumari Adhikari Melung Rural Municipality 4 Majuwa Khok Bhramin
37 Bhawani Adhikari Melung Rural Municipality 4 Majuwa Khok Bhramin
38 Dipesh Adhikari Melung Rural Municipality 4 Majuwa Khok Bhramin
VII
39 Ramesh Adhikari Melung Rural Municipality 4 Majuwa Khok Bhramin
40 Lalit Bahadur Adhikari Melung Rural Municipality 4 Majuwa Khok Bhramin
41 Hari Adhikari Melung Rural Municipality 4 Majuwa Khok Bhramin
42 Laxmi Adhikari Melung Rural Municipality 4 Majuwa Khok Bhramin
43 Shusma Adhikari Melung Rural Municipality 4 Majuwa Khok Bhramin
44 Bishnu Bahadur Adhikari Melung Rural Municipality 4 Majuwa Khok Bhramin
45 Bipan Adhikari Melung Rural Municipality 4 Majuwa Khok Bhramin
46 Sushmita Adhikari Melung Rural Municipality 4 Majuwa Khok Bhramin
47 Tika Bahadur Adhikari Melung Rural Municipality 4 Majuwa Khok Bhramin
48 Manoj Adhikari Melung Rural Municipality 4 Majuwa Khok Bhramin
49 Suresh Adhikari Melung Rural Municipality 4 Majuwa Khok Bhramin
50 Ramita Adhikari Melung Rural Municipality 4 Majuwa Khok Bhramin
51 Tej Adhikari Melung Rural Municipality 4 Majuwa Khok Bhramin
52 Ranjit Adhikari Melung Rural Municipality 4 Majuwa Khok Bhramin
53 Ranjita Adhikari Melung Rural Municipality 4 Majuwa Khok Bhramin
54 Sushan Adhikari Melung Rural Municipality 4 Majuwa Khok Bhramin
55 Rabin Adhikari Melung Rural Municipality 4 Majuwa Khok Bhramin
56 Gyanu Adhikari Melung Rural Municipality 4 Majuwa Khok Bhramin
57 Bikram Adhikari Melung Rural Municipality 4 Majuwa Khok Bhramin
58 Januka Adhikari Melung Rural Municipality 4 Majuwa Khok Bhramin
59 Ramhari Adhikari Melung Rural Municipality 4 Majuwa Khok Bhramin
60 Samjata Adhikari Melung Rural Municipality 4 Majuwa Khok Bhramin