eTOD integration
into Flight procedure Design Environment
Vadim Tumarkin, LGS, Latvia
PBN Implementation and PANS-OPS provisions Workshop
Minsk, Republic of Belarus 7-10 April 2015
PBN/PANS-OPS Workshop, Minsk 2015 1
Riga FIR PBN based Airspace concept development and implementation
PBN/PANS-OPS Workshop, Minsk 2015 2
PBN/PANS-OPS Workshop, Minsk 2015 3
Presentation purposes
• Outline eTOD scope and benefits with focus on PBN;
• Remind eTOD needs for conventional and PBN Flight Procedure
Design;
• Review eTOD ICAO provisions;
• Share Latvian eTOD production and management experience;
• Consider current eTOD implementation difficulties dealing with FPD;
• Discuss CRM implementation issues using eTOD;
• Present eTOD implemented practices commonly elaborated by
eTOD provider, FPD SW developer and ANS provider.
PBN/PANS-OPS Workshop, Minsk 2015 4
PBN/PANS-OPS Workshop, Minsk 2015 5
Application of CRM for
conventional navigation
PBN/PANS-OPS Workshop, Minsk 2015 6
What we need to implement CRM
PBN/PANS-OPS Workshop, Minsk 2015 7
Application of CRM for PBN
PBN/PANS-OPS Workshop, Minsk 2015 8
PBN/PANS-OPS Workshop, Minsk 2015 9
This leads us to the following conclusion
• CRM is staying in the game for PBN procedures design;
• CRM has to be improved to have possibility to use eTOD as an input;
• CRM Obstacle data has to be added by CRM Terrain data taking into
account the ICAO eTOD provisions;
• The new solution is required to effectively upload eTOD into CRM
environment.
PBN/PANS-OPS Workshop, Minsk 2015 10
eTOD provision for CRM calculations
Common approach of:
R.I.S.K. Company as FPD Developer;
Latvijas Gaisa Satiksme as AIS/PANS-OPS provider ;
METRUM Company as eTOD provider.
PBN/PANS-OPS Workshop, Minsk 2015 11
PANS-OPS provider/FPD SW
developer consolidated solution
PBN/PANS-OPS Workshop, Minsk 2015 12
Polyline obstacle conversion into walls
PBN/PANS-OPS Workshop, Minsk 2015 13
Polygon obstacle
conversion into walls
eObstacle data set provision for FPD
DEMO movie
PBN/PANS-OPS Workshop, Minsk 2015 14
eObstacle data set conversion into CRM walls
DEMO movie
PBN/PANS-OPS Workshop, Minsk 2015 15
Wall format obstacle import into CRM
PBN/PANS-OPS Workshop, Minsk 2015 16
DEMO movie
eTOD provision’ implemented practice
Common approach of:
R.I.S.K. Company as FPD Developer;
Latvijas Gaisa Satiksme as AIS/PANS-OPS provider and;
METRUM Company as eTOD provider.
PBN/PANS-OPS Workshop, Minsk 2015 17
Electronic Obstacles
PBN/PANS-OPS Workshop, Minsk 2015 18
Production and Management
ICAO eTOD provisions
19 PBN/PANS-OPS Workshop, Minsk 2015
eTOD industry request example
PBN/PANS-OPS Workshop, Minsk 2015 20
Dear colleagues, We are interested in obtaining the electronic obstacle data and are kindly asking if you could provide us with sample files of both xml and ASCII format. That way we can determine whether we can read the data with our applications. Could you provide us with information on fees and frequency of updates of the obstacle data files? We read on your website that the access to eTOD data could be given to registered users. Our user name is AIMZRH. We would very much appreciate your response. Kind regards, Anna Gernss Aeronautical Information Management Lufthansa Systems FlightNav Inc. P.O. Box 202 8058 Zurich Airport Switzerland
PBN/PANS-OPS Workshop, Minsk 2015 21
Approach used for obstacle provision
22 PBN/PANS-OPS Workshop, Minsk 2015
Direct electronic connection Distribution
PBN/PANS-OPS Workshop, Minsk 2015 23
Electronic Terrain
Production and Management
PBN/PANS-OPS Workshop, Minsk 2015 24
ICAO Terrain feature
25 PBN/PANS-OPS Workshop, Minsk 2015
Proposed approach for terrain provision
Contour lines associated with vertical accuracy
26 PBN/PANS-OPS Workshop, Minsk 2015
DSM
DTM
DEM supported by AIXM 5.1
• In recent years, the point densities for DTM (DEM) have increased
dramatically due to the use of new sensors and digital processing
capabilities, and often reach 1 point per square metre.
• For this reason, DEM direct implementation for Flight procedure design
purpose becoming more and more problematic and the innovative
solution is needed to make the design process more effective.
• AIXM 5.1 has a possibility to form terrain data set for predefined areas as
specified in Annex 15, Chapter 10.
• AIXM 5.1 VerticalStructure feature may be used to store Terrain data set.
PBN/PANS-OPS Workshop, Minsk 2015 27
AIXM 5.1 VerticalStructure
PBN/PANS-OPS Workshop, Minsk 2015 28
• <feature> Vertical Structure consist of several <object> Vertical Structure part
• Obstacle Vertical Structure may be realized by the following Terrain geometry elements:
• Point
• Line
• Polyline
• This structure is applicable both for the complex obstacles and for Terrain also with an appropriate vertical Extent value associated with specific terrain parts.
Grid Terrain vs DEM contour lines
PBN/PANS-OPS Workshop, Minsk 2015 29
Latvian State area 1 terrain
representation through Grid
requests approximatelly 13 millions
points using AIXM 5.1 <feature>
Vertical Structure.
To reduce the storage volume
needed for Terrain presentation by
means of AIXM 5.1 it was decided to
implement the following mechanism:
Terrain data set represented as
DEM was divided for slices with a
vertical step that is an equivalent of
the half of the vertical accuracy for
area of the interest.
At the this step DEM is transformed
into contour lines associated with
vertical accuracy.
DEM presentation using AIXM 5.1 contour lines
30 PBN/PANS-OPS Workshop, Minsk 2015
Latvian METRUM Company has
prepared terrain digital model in form
of the AIXM 5.1 contour lines using
“VerticalStructure” feature.
Then, that AIXM 5.1 terrain snapshot
was successfully imported in LGS
integrated AIM DB by the Data
Manager tool provided by the R.I.S.K.
Company.
AIXM 5.1 terrain data stored in LGS
AIM DB were successfully retrieved
and processes during Flight
procedure design by the PANDA
system.
eTOD processing in FPD environment by PANDA system
PBN/PANS-OPS Workshop, Minsk 2015 31
AIXM 5.1 DEM contour lines benefits
• DEM presentation using AIXM 5.1 contour lines provides the following benefits for automation of the Flight procedure design process keeping calculation accuracy:
– Generalize terrain data and significant reduce data volume and storage resources needed;
– Directly implement AIXM 5.1 DEM contour lines for Instrument approach procedures altitude and Minimum altitudes calculations within the obstacle assessment areas associated with the procedure constructed;
– Reduce terrain data processing to expedite Flight Procedure design process.
PBN/PANS-OPS Workshop, Minsk 2015 32
Electronic Terrain and Obstacles data portrayal
PBN/PANS-OPS Workshop, Minsk 2015 33
34 PBN/PANS-OPS Workshop, Minsk 2015
AD Liepaja Terrain and Obstacle
– LUCIAD AIXM 5 Viewer
35 PBN/PANS-OPS Workshop, Minsk 2015
AD Liepaja Terrain and Obstacle
– Snowflake ATM Viewer
PBN/PANS-OPS Workshop, Minsk 2015 36
AD Liepaja eTOD Portrayal – ArcScene 10.2
PBN/PANS-OPS Workshop, Minsk 2015 37
AD Liepaja Terrain and Obstacle
– ArcGIS online
PBN/PANS-OPS Workshop, Minsk 2015 38
AD Riga eTOD Portrayal – 3D PDF
PBN/PANS-OPS Workshop, Minsk 2015 39
AD Obstacle Chart production automation – Type A example
PBN/PANS-OPS Workshop, Minsk 2015 40
Terrain and Obstacle (Combined) eChart example
Quality assured eTOD to support procedure validation process
PBN/PANS-OPS Workshop, Minsk 2015 41
PBN/PANS-OPS Workshop, Minsk 2015 42
Thank you for your attention
Vadim Tumarkin, LGS, Latvia
Questions, please