evaluating the economic efficiency of transportation ...srg/book/files/pdf/8....
TRANSCRIPT
1K u m a r e s C. S I n h a a n d S a m U E L L a b I
Evaluating the Economic Efficiency of Transportation Interventions
Costs $
Benefits $
Transportation Decision-making – Principles of Project Evaluation and Programming
Contents of this Presentation
Cash Flow Illustrations
The 5 Variables in any Cash Flow Diagram
Equivalence Equations (Interest Formula)
Criteria for Economic Efficiency Evaluation
Special Cases of Equivalence Equation
Steps for Economic Efficiency Analysis
What is Life-cycle Cost Analysis (LCCA)?2
Economic Efficiency
Why Carry out Economic Efficiency Analysis?
Economic efficiency is a key criterion for evaluation of most engineering systems
Useful for evaluating systems on basis of 1 or more PM that are monetizeable
Is a type of multiple-objective decision analysis
Reflects that fact that the value of money changes over time (Example: $1,000 in today is not the same as $1,000 in 1993, and is not the same as $1,000 in 2013)
Concept of cash flow over time
3
Economic Efficiency
The Concept of Cash Flows
Is a representation of money inflows and outflows assoc. with an engineering system
Table or Diagram can be used
Table: +ve money coming in (revenues, savings)-ve money going out (costs)
Diagram: downward arrows money coming in (revenues, savings)upward arrows money going out (costs)
Time intervals of money flows: daily, weekly, monthly, yearly, etc.
4
Economic Efficiency
Cash Flow Diagrams for Transportation Projects
For CE systems, intervals are mostly Yearly
Amounts received or incurred during year are assumed to have happened …
… at end of year, or … at beginning of year(choose only 1 of above conventions, and stick to it)
5
Economic Efficiency
Example 1:
Construction of a Freeway BypassConsider the following annual cash flows for a proposed freeway bypass.
Construction will be completed by December 2009 and the estimated annual benefits of travel time, safety, and VOC are provided below.
Year Construction Cost ($)
(Chapter 3)
Demand
(Chapter 4)
Travel Benefits ($)
(Demand and
Chapter 5)
Safety Time Benefits ($)
(Demand and
Chapter 6)
VOC Benefits ($)
(Demand and
Chapter 7) 2009 $35 M 2010 320,000 $5.76 M $1.33 M $0.60 M 2011 345,000 $6.12 M $1.43 M $0.65 M 2012 365,000 $6.57 M $1.51 M $0.69 M 2013 380,000 $6.84 M $1.58 M $0.72 M 2014 405,000 $7.29 M $1.68 M $0.76 M 2015 418,000 $7.52 M $1.73 M $0.79 M 2016 438,000 $7.88 M $1.82 M $0.83 M 2017 460,000 $8.28 M $1.91 M $0.87 M 2018 490,000 $8.82 M $2.03 M $0.92 M 2019 525,000 $9.45 M $2.18 M $0.99 M
Travel Time Benefits ($)
Safety Benefits ($)
6
Economic Efficiency
Cash Flow Diagram for Freeway Bypass Construction
35M
2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019
Construction Cost
7
Economic Efficiency
Cash Flow Diagram for Freeway Bypass Construction
6.57M6.12M35M 5.76M 6.84M 7.29M 7.52M 7.88M 8.28M 8.82M 9.45M
2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019
Travel Time Benefits
8
Economic Efficiency
Cash Flow Diagram for Freeway Bypass Construction
2.03M
6.57M6.12M35M 5.76M 6.84M 7.29M 7.52M 7.88M 8.28M 8.82M 9.45M
1.33M 1.43M 1.51M 1.58M 1.68M 1.73M 2.18M1.91M1.82M
2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019
Safety Benefits
9
Economic Efficiency
Cash Flow Diagram for Freeway Bypass Construction
2.03M
6.57M6.12M35M 5.76M 6.84M 7.29M 7.52M 7.88M 8.28M 8.82M 9.45M
1.33M 1.43M 1.51M 1.58M 1.68M 1.73M 2.18M1.91M1.82M
0.60M 0.65M 0.99M0.92M0.69M 0.72M 0.76M 0.79M 0.83M 0.87M
2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019
VOC Benefits
10
Economic Efficiency
Example 2:
Post-implementation EvaluationReconstructed I-975 Bridge and Tollway
Initial Contract Cost (Year 1997)- $8 milToll receipts (1998-2005)- $2 mil per year Major Maintenance (Year 2000) - $3 milMinor Maintenance (Year 2004) - $1 mil
Benefits of Travel Time, Safety, VOCs: $4 mil/year (1997-2005) Operating costs (1997-2005)- $1.5 mil per year
Draw the Cash Flow Diagram for this example.11
Economic Efficiency
2M 2M2M 2M 2M 2M 2M 2M8M
3M 1M
4M
2003
Initial Contract Cost (Year 1997)- $8 milToll receipts (1998-2005)- $2 mil per year Major Maintenance (Year 2000) - $3 milMinor Maintenance (Year 2004) - $1 milBenefits of Travel Time, Safety, VOCs: $4 mil/year (1997-2005) Operating costs (1997-2005)- $1.5 mil per year
4M 4M 4M 4M 4M 4M 4M
1.5M 1.5M 1.5M 1.5M 1.5M 1.5M 1.5M 1.5M
1997 1998 1999 2000 2001 2002 2004 2005
12
Economic Efficiency
The 5 Variables in any Cash Flow Diagram
P - Present AmountF - Future AmountA - Annual Amounti - Interest RateN - Analysis Period
Typically, we’re given 4 of the above variables and we will need to calculate the 5th, using equivalence equations.
13
Economic Efficiency
Discussion of the 5 Variables
1. Present Amount, PAmount received or incurred in Year 0. Typically a large
amount, e.g., initial construction cost, initial money collected for car loan, etc.
2. Future Amount, FA future amount that is equivalent to a given present
amount (received or incurred).Also called “discounted amount”. May be incurred (or paid) at end of analysis period or
anytime within the analysis period.
14
Economic Efficiency
3. Annual Amounts, A
Amount received or incurred every period
Examples are operating costs and maintenance costs
Typically are “uniform amounts” but not always uniform. For example, O&M costs typically increases with system age or as demand increases
15
Economic Efficiency
4. Analysis Period, N
Is the total time over which we are carrying out economic evaluation for a system.
Synonyms: Payment Period, Planning Horizon, Planning Period.
Typically, expressed in years for CE systems.
Length depends on system type and expected life of the system.
May be the overall life of a system or only a part thereof
Examples: 35 years for highway pavements, 50 years for RC bridges, 70 years for steel bridges, 100 years for some dams. 16
Economic Efficiency
17
5. Interest Rate, i
Represents the extent to which the value of money changes over time.
Opportunity cost: Money used by a transportation agency for the project could’ve been used elsewhere to generate profit or used elsewhere to generate interest
Thus, by implementing the project, the agency is foregoing some benefit elsewhere (i is a measure of that benefit)
National interest rate is determined by the Central Bank (or Federal Reserve Board). Individual lenders also have their own rates, but are generally pegged to the federal rate.
Simple interest vs. compound interest
Economic Efficiency
Simple Interest vs. Compound Interest
1. Simple InterestLet’s say in Dec 2007 you borrow $1000 with 5% simple interest
Year Principal Interest Total Amount Owed at the End of The Year (=Principal + Interest)
Dec 2007 $1000 $1000
Dec 2008 $50 $1050
Dec 2009 $50 $1100
Dec 2010 $50 $1150
Dec 2011 $50 $120018
Economic Efficiency
2. Compound InterestLet’s say in Dec 2007 you borrow $1000 with 5% compound interest
Year Principal Interest Total Amount Owed at the End of The Year (=Principal + Interest)
Dec 2007 $1000 - $1000
Dec 2008 $1000 $50 $1050
Dec 2009 $1050 $52.5 $1102.5
Dec 2010 $1102.5 $55.13 $1157.63
Dec 2011 $1157.63 $57.88 $1215.5119
Economic Efficiency
Simple Interest vs. Compound Interest
Year Simple Interest
Compound Interest
Dec 2007 $1000 $1000
Dec 2008 $1050 $1050
Dec 2009 $1100 $1102.5
Dec 2010 $1150 $1157.63
Dec 2011 $1200 $1215.51
Total Amount Owed at the End of The Year (=Principal + Interest)
20
Economic Efficiency
Compound interest (not simple interest) is often used.
Compound interest may be fixed or variable
Fixed (constant) interest: same interest rate during the year
same interest rate in each of several years
Variable interest rate: interest rate changes during the year.
Change may be as follows:
- compounding a finite number of times during each year
- compounding an infinite number of times each year21
Economic Efficiency
The 5 Variables …
P - Present AmountF - Future AmountA - Annual Amounti - Interest RateN - Analysis Period
Given any 4 Find value of 5th variable
Use “Equivalence equations”(also called “Interest formula”)
22
Economic Efficiency
Equivalence Equations …Used for calculating any 1 of the 5 Cash Flow Variables, given the other 4.
Two main categories of Equivalence Equations, mostly depending on the nature of the interest rate (how it changes).
Equivalence Equations
23
Type 1Interest rate is:
- Constant, OR
- Variable but compounded a finite number of times within the year
Type 2Interest rate is:
- Variable but compounded an infinite number of times within the year
Economic Efficiency
Equivalence Equations Type I
24
Economic Efficiency
Description: Finding the future amount (F) to be yielded by an initial amount (P) at the end of a given period.
Example: Current car price is $20,000. Jim takes the car now (Dec 2007) and agrees with the dealer to pay nothing until Dec 2012 when he pays everything at a go.
What price will he pay in 2012? Assume 5% interest rate.
Case 1
25
Economic Efficiency
26
Case 1 (cont’d)Problem Definition:
This is a Single Payment Compound Amount Factor (SPCAF) problem
Cash Flow Diagram:
Computational Formula:2007 2012
P F = ?
])1[( niPF +×=SPCAF
Economic Efficiency
Solution to Case 1 Example:
Question: Current car price is $20,000. Jim takes the car now (Dec 2007) and agrees with the dealer to pay nothing until Dec 2012 when he pays everything at a go.
What price will he pay in 2012? Assume 5% interest rate.
Solution:
526,25$])05.01[(000,20])1[( 5 =+=+×= niPF
27
Economic Efficiency
Case 2:
Description: Finding the initial amount (P) that would yield a future amount (F) at the end of a given period
Example: Jim has seen the 2012 model in a car magazine. Wishes to buy that model when it is released in 2012, at a price of $50,000 at that year.
How much should Jim put away now in order to be able to pay for the car in 2008?
XXZ, 2012 Edition
28
Economic Efficiency
29
Problem Definition: This is a Single Payment Present Worth Factor (SPPWF) problem
Cash Flow Diagram:
Computational Formula:
niFP
)1( +=
2007 2012
P F
Case 2 (continued):
SPCAF
Economic Efficiency
Solution to Case 2 Example:
Question: Jim has seen the 2012 model in a car magazine. Wishes to buy that model when it is released in 2012, at a price of $50,000 at that year.
Solution:
176,39$)05.01(
000,50)1( 5 =+
=+
= niFP
30
Economic Efficiency
Case 3:
Description: Finding the amount of uniform annual payments (A) that would yield a certain future amount (F) at the end of a given period.
Example: Jim has seen the 2012 model in a car magazine. Wishes to buy that model when it is released in 2012, at a price of $50,000 at that year. Jim agrees to pay 5 yearly amounts until 2012, starting December 2008. How much should he pay every year?
31
Economic Efficiency
Case 3 (continued):
32
Problem Definition: This is a Uniform Series Sinking Fund DepositFactor (USSFDF) problem
Cash Flow Diagram:
Computational Formula:
2007 2012
A=?
F
1)1( −+×= ni
iFA
A=?A=?A=?A=?
SPCAF
Economic Efficiency
Solution to Case 3 Example:
Question :Jim agrees to pay 5 yearly amounts, starting December 2007 until 2012. How much should he pay every year so he can end up paying full price ($50,000) in 2012?
Solution:
74.048,9$1)05.01(
05.0000,501)1( 5 =
−+×=
−+×= ni
iFA
33
Economic Efficiency
Case 4:
Description: Finding the final compounded amount (F) at the end of a given period due to uniform annual payments (A).
Example: Same as for Case 2 (Jim has seen the 2012 model in a car magazine, and wishes to purchase it when it is released in 2012).
Price of the car is not fixed. Rather, the Dealer and Jim agree that Jim will pay $9,000 every year starting December 2007 until 2012. How much will he end up paying for the car in 2012?
34
Economic Efficiency
Problem Definition: This is a Uniform Series Compounded AmountFactor (USCAF) problem
Cash Flow Diagram:
Computational Formula:
2007 2012
F = ?
iiAF
n 1)1( −+×=
A A A A A
Case 4 (continued):
SPCAF
Economic Efficiency
Solution to Case 4 Example:
Question:Dealer and Jim agree that Jim will pay $9,000 every year starting December 2007 until 2012. How much will he end up paying for the car in 2012?
Solution:
68.730,49$05.0
1)05.01(000,91)1( 5
=−+
×=−+
×=iiAF
n
Economic Efficiency
Case 5:
Description: Finding the initial amount (P) that would yield specified uniform future amounts (A) over a given period.
Example: Jim takes the 2007 model now (in 2007). He has enough money to
pay for it, but rather decides to pay in annual installments of $5,000 over a 5-year period (starting in Dec 2007 till Dec 2012). How much should he set aside now so that he can make such annual payments?
37
Economic Efficiency
Case 5 (continued):
Problem Definition: This is a Uniform Series Present Worth Factor (USPWF) problem
Cash Flow Diagram:
Computational Formula:
2007 2012
P=?A A A AA
n
n
iiiAP
)1(1)1(
+−+
×=USPWF
Economic Efficiency
Solution to Case 5 Example:
Question:Jim rather decides to pay in annual installments of $5,000 over a 5-
year period (starting in Dec 2007 till Dec 2012).
How much should he set aside now so that he can make such annualpayments?
Solution:
38.647,21$)05.01(05.01)05.01(000,5
)1(1)1(
5
5
=+
−+×=
+−+
×= n
n
iiiAP
39
Economic Efficiency
Case 6:
Description: Finding the amount uniform annual payments (A) over a given period, that would completely recover an initial amount (P) such as a loan
Example:
Jim receives a loan of $25,000 to pay for the 2007 model and take it right now. How much will he have to pay back to the bank every year (starting Dec 2008) until Dec 2012?
40
Economic Efficiency
Case 6 (continued):
Problem Definition: This is a Capital Recovery Factor (CRF) problem. (that is, the bank seeks to “recover its capital” from Jim).
Cash Flow Diagram:
Computational Formula:
2007 2012
PA=?
1)1()1(−+
+×= n
n
iiiPA
A=? A=? A=? A=?
CRF
41
Economic Efficiency
Solution to Case 6 Example:
Question:Jim receives a loan of $25,000 to pay for the 2007 model and
take it right now. How much will he have to pay back to the bank every year (starting Dec 2008) until Dec 2012?
Solution:
37.774,5$1)05.01()05.01(05.0000,25
1)1()1(
5 =−+
+×=
−++
×=n
n
n
iiiPA
42
SummaryCash Flow Diagram
Computational Formula Factor Computation
P F=? 0 1 … … N
F = P × SPCAF The Single Payment Compound Amount Factor, SPCAF (i%, N).
NiSPCAF )1( +=
P=? F 0 1 … … N
P = F× SPPWF The Single Payment Present Worth Factor, SPPWF (i%, N).
NiSPPWF
)1(1+
=
A=? A=? A=? A=? 0 1 2 … N F
A = F × SFDF The Sinking Fund Deposit Factor, SFDF (i%, N).
1)1( −+= Ni
iSFDF
A A A A 0 1 2 … N F=?
F = A × USCAF The Uniform Series Compound Amount Factor, USCAF (i%, N).
iiUSCAF
N 1)1( −+=
P=? A A A A 0 1 2 … N
P = A× USPWF The Uniform Series Present Worth Factor, USPWF (i%, N).
N
N
iiiUSPWF
)1(1)1(
+×−+
=
P A=? A=? A=? A=? 0 1 2 … N
A = P × CRF The Capital Recovery Factor, CRF (i%, N).
1)1()1(−+
+×= N
N
iiiCRF
43
What if the Interest Rate, i is not fixed but is(i) Variable(ii) Compounded a fixed number of
times, m, during each year?
44
In that case, in place of i in the Interest Formula, we should use ie, the nominal interest rate
But how do we determine the value of ie?
11 −⎟⎠⎞
⎜⎝⎛ +=
mn
e mii
If:
in is the nominal annual interest rate, and
m is the number of compounding periods in a year
Then:
45
SUMMARY FOR FORMULA FOR:When the Interest Rate, i is not fixed but is (i) variable and (ii) compounded a fixed number of times, m, during each year?
Cash Flow Diagram
Computational Formula FaComp
P F=? 0 1 … … N
F = P × SPCAF The Single Payment Compound Amount Factor, SPCAF (i%, N).
NiSPCAF )1( +=
P=? F 0 1 … … N
P = F× SPPWF The Single Payment Present Worth Factor, SPPWF (i%, N).
NiSPPWF
)1(1+
=
A=? A=? A=? A=? 0 1 2 … N F
A = F × SFDF The Sinking Fund Deposit Factor, SFDF (i%, N).
1)1( −+= Ni
iSFDF
A A A A 0 1 2 … N F=?
F = A × USCAF The Uniform Series Compound Amount Factor, USCAF (i%, N).
iiUSCAF
N)1( −+=
P=? A A A A 0 1 2 … N
P = A× USPWF The Uniform Series Present Worth Factor, USPWF (i%, N).
N
iiiUSPWF
)1()1(+×
−+=
P A=? A=? A=? A=? 0 1 2 … N
A = P × CRF The Capital Recovery Factor, CRF (i%, N).
1)1()1(−+
+×= N
N
iiiCRF
Factor Computation
NeiSPCAF )1( +=
Nei
SPPWF)1(
1+
=
1)1( −+= N
eiiSFDF
ii
USCAFN
e 1)1( −+=
N
ee
Ne
iii
USPWF)1(1)1(
+×−+
=
1)1()1(−+
+×= N
e
Nee
iii
CRF
11 −⎟⎠⎞
⎜⎝⎛ +=
mn
e mii
Where:
Example:
(Case 1) Current car price is $20,000. Jim takes the car now (Dec 2007) and agrees with dealer to pay nothing until Dec 2012 when he pays everything at a go.
What price will he pay in 2012? Assume a nominal 5% interest rate compounded every quarter.
Solution:in is the nominal annual interest rate, andm is the number of compounding periods in a year
The final amount F can then be calculated as follows:21.635,25$])0509.01[(000,20])1[( 5 =+=+×= n
eiPF
Economic Efficiency
%09.50509.01405.0111
4
==−⎟⎠⎞
⎜⎝⎛ +=−⎟
⎠⎞
⎜⎝⎛ +=
mn
e mii
47
What if the Interest Rate, i is not fixed but is(i) Variable(ii) Compounded an infinite number of
times during each year?
48
Effective Interest Rate when: interest rate is variable and is being compounded an infinite number of time in a year
In that case, in place of i in the Interest Formula, we should use ie, the nominal interest rate
But how do we determine the value of ie?
1−= ie ei
If:
in is the nominal annual interest rate, and
m is the number of compounding periods in a year
Then:
Substituting ie for i in the original equations yield a new set of Interest Equations (next slide) 49
Interest Equations for Variable and Infinite CompoundingCash Flow Diagram
Computational Formula Factor Computation
P F=? 0 1 … … N
F = P × SPCAF The Single Payment Compound Amount Factor, SPCAF (i%, N).
iNeSPCAF ×=
P=? F 0 1 … … N
P = F× SPPWF The Single Payment Present Worth Factor, SPPWF (i%, N).
iNeSPPWF ×=
1
A=? A=? A=? A=? 0 1 2 … N F
A = F × SFDF The Sinking Fund Deposit Factor, SFDF (i%, N).
11−−
= × iN
i
eeSFDF
A A A A 0 1 2 … N F=?
F = A × USCAF The Uniform Series Compound Amount Factor, USCAF (i%, N).
11
−−
=×
i
iN
eeUSCAF
P=? A A A A 0 1 2 … N
P = A× USPWF The Uniform Series Present Worth Factor, USPWF (i%, N).
11
−−
=×−
i
iN
eeUSPWF
P A=? A=? A=? A=? 0 1 2 … N
A = P × CRF The Capital Recovery Factor, CRF (i%, N).
iN
i
eeCRF ×−−
−=
11
50
Some In-class questions …Five years from now, an airport authority intends to rehabilitate its runways at a cost of $1.5 million. Ten years from now, the runways will be replaced at a cost of $5.8 million.
Assuming an interest rate of 8%, find the total present worth ofthese costs.
51
SolutionFive years from now, an airport authority intends to rehabilitate its runways at a cost of $1.5 million. Ten years from now, the runways will be replaced at a cost of $5.8 million.
Assuming an interest rate of 8%, find the total present worth of these costs.
PW = 1.5M*SPPWF (8%, 5 years) + 5.8M*SPPWF (8%, 10 years) = 3.71M
PW = ? 1.5 M 5.8 M
5 5
52
Some In –class questions …A major corridor investment is expected to yield $50,000 per year in reduced crash costs, $200,000 per year in reduced vehicle operating costs, and $405,000 per year in travel time costs.
What is the combined present worth of these costs? Assume the interest rate is 5% and the analysis period is 20 years.
53
SolutionA major corridor investment is expected to yield $50,000 per year in reduced crash costs, $200,000 per year in reduced vehicle operating costs, and $405,000 per year in travel time costs.
What is the combined present worth of these costs? Assume the interest rate is 5% and the analysis period is 20 years.
PW = (50,000 + 20,000 + 405,000)* USPWF (5%, 20) = 5.92M
54
Criteria for Economic Efficiency Impact Evaluation
Present Worth of Costs (PWC)
Equivalent Uniform Annual Cost (EUAC)
Equivalent Uniform Annual Return (EUAR)
Net Present Value (NPV)
Internal Rate of Return (IRR)
Benefit-cost Ratio (BCR)
55
1. Present Worth of CostsIs used when benefits of all alternatives are equal, so cost is the only criterion to consider in choosing the best alternative
Alternatives have the same service life or analysis period
Converts all costs into an equivalent single cost assumed to occur at the beginning of the analysis period (time = zero).
56
Present Worth of Costs - Example
An airplane purchase is proposed.
For airplane type Ainitial cost = $50 million, average annual maintenance cost = $0.25 million, salvage value = $8 million.
For airplane type Binitial cost = $30 million, average annual maintenance cost = $0.75 million, salvage value = $2 million.
Both types have a useful life of 15 years. Which alternative should be selected? Assume 7% interest rate.
57
Solution
PWCA (in millions)
= 50 + 0.25*USPWF(7%, 15) – 8*SPPWF(7%, 15) = $49.38M
PWCB (in millions)
= 30 + 0.75*USPWF(7%, 15) – 2*SPPWF(7%, 15) = $36.11M
Alternative B has a lower PWC
Thus Alt B. is more desirable.58
2. Equivalent Uniform Annual Costs (EUAC)
Is used when benefits of all alternatives are equal, so cost is the only criterion to consider in choosing the best alternative
Alternatives have the different service lives or analysis periods
Converts all costs into an equivalent cost assumed to occur at each year of the analysis period.
59
ExampleBus transit services in MetroCity can be performed satisfactorily using any one of two alternative bus types, A or B.
Bus type A: initial cost = $100,000estimated life = 6 yrsannual maintenance & operating costs = $8,000salvage value = $20,000.
Bus type B: initial cost = $75,000estimated life = 5 yrsannual maintenance & operating costs = $8,000 for
the first 2yrs and $12,000 for the remaining 4 yrssalvage value = $10,000.
Find the equivalent annual cost of each alternative, and decide which option is more desirable. Assume a 6% interest rate.
60
SolutionEUACA (in thousands) = 100CRF(6%, 6) + 8USPWF(6%, 6) CRF(6%, 6) – 20SFDF(6%, 6) = $25.47
EUACB (in thousands) = 75CRF(6%, 5) + 8USPWF(6%, 2) CRF(6%, 6) + (12USPWF(6%, 4) SPPWF(6%, 2)CRF(6%, 6) – 40SFDF(6%, 6) = $22.57
Alternative B is more desirable.
61
Equivalent Uniform Annual Return
Used when costs are different and benefits are also different across alternatives
Combines all costs and benefits or returns associated into a single annual value of return (benefits less costs) over the analysis period.
This method can be used when the alternatives have different service lives.
62
ExampleTwo alternative designs proposed for renovating Water Port. Annual benefits Aare in terms of monetized savings in inventory delay, safety and security, and vessel operations.Alternative A: initial project cost = $200 million, life = 25 yrs,
salvage value = $22 million, annual maintenance/operating costs = $80 million, annual benefits = $75 million.
Alternative B: initial project cost = $175 million, life = 20 yrs, salvage value = $15 million, annual maintenance/operating costs =
$90 million, annual benefits = $55 million.
Find the equivalent uniform annual return of each alternative and identify the better alternative. Assume a 4% interest rate.
63
EUARA (in millions)
= 75 – 200CRF(4%,25) – 80 + 22SFDF(4%,25) = –$17.27M
EUARB (in millions)
= 55 – 175CRF(4%,25) – 90 + 15SFDF(4%,25) = –$45.84M
Alternative A is more desirable.
64
The NPV of an investment is the difference between the present worth of benefits and the present worth of costs.
NPV reflects the value of the project at the time of the base year of the analysis which may be considered the year of decision making.
NPV is often considered as the best economic efficiency indicator as it provides a magnitude of net benefits in monetary terms.
Among competing transportation projects or policies, the alternative with the highest NPV is considered the most “economically efficient.”
65
ExampleTwo alternative designs proposed for renovating Water Port. Annual benefits Aare in terms of monetized savings in inventory delay, safety and security, and vessel operations.Alternative A: initial project cost = $200 million, life = 25 yrs,
salvage value = $22 million, annual maintenance/operating costs = $80 million, annual benefits = $75 million.
Alternative B: initial project cost = $175 million, life = 20 yrs, salvage value = $15 annual maintenance/operating costs = $90
million, annual benefits = $55 million.
Find the NPV each alternative and identify the better alternative. Assume a 4% interest rate.
66
NPVA (in millions)
= 75 *USPWF(4%, 25) – 200 – 80*USPWF(4%, 25) + 22*SPPWF(4%,25) = – $269.86M
NPVB (in millions)
= 55* USPWF(4%, 20) – 175 – 90*USPWF(4%, 20) + 15*SPPWF(4%,20) = – $716.15M
Alternative A is more desirable.
67
The Internal Rate of Return (IRR)IRR found by equating PWbenefits to PWcosts, or by equating EUACbenefits to EUACcosts.
Minimum attractive rate of return (MARR)
is the lowest rate of return that investors will accept before they invest considering the likely investment risks or the opportunity to invest elsewhere for possibly greater returns.
Then the IRR is compared to the Minimum Attractive Rate of Return (MARR).
If the IRR > MARR, then the investment is considered worthwhile.If the IRR < MARR, then investment is considered NOT worthwhile.
68
ExampleAn urban rail transit agency is considering the purchase of a
new $30,000 ticketing system that will reduce travel time.
The estimated life of the system is 10 years at which time the value of the system will be $15,000.
The expected travel time savings per year is $5,000 per year, and the average annual maintenance and operating cost is $2,000.
Is the project economically more desirable than the do-nothing alternative? The minimum attractive rate of return is 5%.
SolutionEquating the net cash flow on both sides yields:
5,000USPWF(i%,10) + 15,000SPPWF(i%,10) = 30,000 + 2000USPWF(i%,10)
Solving this equation by trial and error or using Microsoft Excel yields: i = 6.25% This value exceeds the MARR value of 5%.
So it is economically more efficient to undertake the project than to do nothing.
SolutionEquating the net cash flow on both sides yields:
5,000USPWF(i%,10) + 15,000SPPWF(i%,10) = 30,000 + 2000USPWF(i%,10)
Solving this equation by trial and error or using Microsoft Excel yields: i = 6.25% This value exceeds the MARR value of 5%.
So it is economically more efficient to undertake the project than to do nothing.
Benefit Cost Ratio
The benefit-cost ratio (BCR) is a ratio of benefits to costs.
That is:
NPVBenefits/NPBCosts, OR
EUABenefits/EUACosts
An investment with a BCR exceeding 1 is considered to be economically feasible
The alternative (investment) with the highest BCR value is considered the best.
72
Example
73
Two alternative designs proposed for renovating Water Port.
Annual benefits Aare in terms of monetized savings in inventory delay, safety and security, and vessel operations.
Alternative A: initial project cost = $200 million, life = 25 yrs, salvage value = $22 million, annual maintenance/operating costs = $80 million, annual benefits = $75 million.
Alternative B: initial project cost = $175 million, life = 20 yrs,
salvage value = $15 annual maintenance/operating costs = $90 million, annual benefits = $55 million.
Find the equivalent uniform annual return of each alternative and identify the better alternative. Assume a 4% interest rate.
SolutionTaking the ratio of all benefits to all costs yields:
For Alternative A:
For Alternative B:
BCRA > BCRB, hence, A is a better alternative.
75 (4%,25) 22 (4%,25) 0.8139200 80 (4%,25)
AA
A
PWB USPWF SPPWFBCRPWC USPWF
× + ×= = =
+ ×
55 (4%,25) 15 (4%,25) 0.5470175 90 (4%,25)
BB
B
PWB USPWF SPPWFBCRPWC USPWF
× + ×= = =
+ ×
74
What’s your opinion …?
NPV vs. BCR
Which is better?
Special Interest-Equations
- Comparing Alternatives with Different Service Lives
- Present Worth of Continuously Compounded Payments with Continuously Compounded Interest
Special Interest Equations:Comparing Alternatives with Different Service Lives
Approaches
1. For each alternative, convert all costs and benefits into EUAR, OR
2. For alternative, find NPW over a service life that is a LCD (lowest common denominator), OR
3. Present Worth of Periodic Payments to Perpetuity
Approach 2 for Evaluating Alternatives with Different Service Lives
For service lives n1 and n2, determine the lowest common denominator, n* and repeat the entire cost stream over n*, for both alternatives.
n1 = 3 years n2 = 4 yearsAlternative 1 Alternative 2
Assume total replacement (reconstruction) of the facility after the end of its service life
n* = 12 yearsAlternative 1
n* = 12 yearsAlternative 2
With the same analysis period of 12 years, we can now proceed to use NPV to evaluate the two alternatives
Approach 3 for Evaluating Alternatives with Different Service Lives
Present Worth of Periodic Payments in Perpetuity
For each alternative i: For one service life only, convert all costs and benefits over service life N, to a single compounded amount, R at end of service life find the present worth of R payments every N years over an analysis period of infinity
Assume total replacement (reconstruction) of the facility after the end of its service life, forever
N yrs N yrs N yrs N yrs
P’ R R R RR
RP’ P’
Approach 3 for Evaluating Alternatives with Different Service Lives
Present Worth of Periodic Payments in Perpetuity
For each alternative i: For one service life only, convert all costs and benefits over service life N, to a single present worth, R and find the present worth of R payments every ni years over an analysis period of infinity
...)1()1()1(
' 32, ++
++
++
+=∞ NNNR iR
iR
iRPPW
⎥⎦
⎤⎢⎣
⎡+
++
++
++= ...
)1(1
)1(1
)1(1' 32 NNN iii
RP
⎥⎥⎥⎥
⎦
⎤
⎢⎢⎢⎢
⎣
⎡
−
+−
+= 1
)1(11
1'Ni
RP 1)1('
−++= Ni
RP
Assume total replacement (reconstruction) of the facility after the end of its service life, forever
Example:A railway bridge is slated for reconstruction.
Estimated service life of the structure is 60 years.
Reconstruction cost is $600,000.
During its replacement cycle, the bridge will require two rehabilitations, each with a cost of $200,000, at the 20th and 40th year
Average annual cost of maintenance is $5,000.
At the end of the replacement cycle, the bridge will again be reconstructed and the entire cycle is assumed to repeat in perpetuity.
Find the present worth of all costs to perpetuity? Assume 5% interest rate. Assume P’ (non-recurring cost = 0)
Solution:
C = $600,000 $200,000 $200,000
0 20 yr 40 yr 60 yr
$5000/yr
R
R = compounded life-cycle cost= 600,000SPCAF(5%, 60) + 200,000SPCAF(5%, 40) + 200,000SPCAF(5%, 20) + 5,000USCAF(5%, 60) = $14,914,087
R R
0 60 yrs 120 yrs∞
1)1( −+ NiR
( )596,843$
105.01087,914,1460 =−+
=PWR∞ =
60 years
What’s your opinion …?
Why is the perpetuity issue particularly relevant to transportation
systems evaluation?
Why is perpetuity particularly relevant to transportation systems evaluation?
Because:
Transportation facilities are needed by society forever
Transportation facilities do not last foreverHence need replacement after some decades
Special Interest Equations: Present Worth of Continuously Compounded Payments with Continuously Compounded Interest
Consider a general case where an initial amount, R0, grows exponentially at a rate of r expressed as a percentage per year.
Bringing all future streams to the present gives:
R0: Present worth of R0 = R0 = R
R1: Present worth of R1 = (R × er)/ei
R2: Present worth of R2 = (R × e2r)/e2i
Rn-1: Present worth of R-1n = (R × e(n-1)r)/e(n-1)i
R0 R1 R2
R3
1st year 2nd year 3rd year
Rn-1
nth year 1 3 n–1 n 2 0
⎥⎦
⎤⎢⎣
⎡−−
×=⎥⎦
⎤⎢⎣
⎡++++×=
−
−
−
)(1...1
)(
)(
)(
2
2
, ireR
ee
ee
eeRPW
irn
iin
rin
i
r
i
r
CCICCP r < i
Example
160,719$)10.003.0(1000,100
)(1 )10.003.0(10)(
, =⎥⎦
⎤⎢⎣
⎡−
−×=⎥
⎦
⎤⎢⎣
⎡−−
×=−− e
ireRPW
irn
CCICCP
The average annual cost of operating the physical infrastructure of a small airport facility is currently $100,000.
Due to growth in air traffic, the annual costs are compounded continuously at 3% per annum.
What is the present worth of the operating costs over a period of 10 years? Assume a 10% interest rate that is compounded continuously
Solution
What’s your opinion …?
Present Worth of
Continuously Compounded Payments with
Continuously Compounded Interest
Is this really an issue?
Special Interest Equations: Present Worth of Continuously Compounded Payments with Continuously Compounded Interest
Is this really an issue?Annual costs not really uniform but typically grow with time
(i) Systems get olderCurrent year’s condition depend on previous years conditionCosts more to preserveCosts are compounded as the years go by
(ii) Traffic grows with timeAll costs link to traffic use (annual operating costs are not constant but increase (compounded over time)
Steps for Economic Efficiency Analysis
89
Steps for Economic Efficiency Analysis
90
1. Identify the Characteristics of the Transportation Project
2. Identify the Purpose of the Economic Analysis
3. Select and Describe the Base CaseandtheOther Alternatives4. Define and Describe
the Study Area 5. Select the Appropriate
Analysis Period for the Study
6. Identify the Appropriate Impact Types for Economic
8. Determine Characteristics of the Transportation System under theVariousAlternativeScenarios
7. Select the Appropriate Economic Analysis Criterion
9. Apply Data to Estimate the Economic Efficiency Impacts
Software Packages for Economic Efficiency Analysis
Surface Transportation Efficiency Analysis Model (STEAM)
MicroBenCost
Highway Development and Management (HDM) Standards Model — World Bank
Highway Economic Requirements (HERS)
Indiana DOT’s Major Corridor Investment-Benefit Analysis System (MCIBAS)
California DOT’S Cal B/C System
Software Packages for Economic Efficiency Analysis
MicroBenCost Demonstration
What is Life-cycle Cost Analysis (LCCA)?Assessing the impacts of a transportation system over its service life. LCCA is relevant for new facilities.
Service life:Construction to Demolition/SalvageOften in years
Involves both costs and benefits ($)
Includes cost of operations, routine maintenance, periodic maintenance, etc.
Helps us decide over the service life:what activities to do When to do those activities
What is Remaining Service Life (RSL) Analysis?
Sometimes, facility already exists, has some more years left to serve. RSL is relevant for existing facilities.
And we need to decide over its remaining service life:what activities to do when to do those activities
Thus, we assess the cost and benefits of transportation system over its remaining service life
Most infrastructure are existing. So RSL analysis very relevant.
94
Reading Assignment
Is it really “fair” to evaluate projects on basis of only Economic Efficiency? Some thoughts (Pages 212-213 of the Text)
95