executive summary of environmental impacts assessment (eia ... · executive summary of...

80
PEOPLE' COMMITIEE OF CANTHO CITY PPMU OF CANTHO CITY URBAN UPGRADING PROJECT ----* MEKONG DELTA REGION URBAN UPGRADING PROJECT (MDR-UUP) EXECUTIVE SUMMARY OF ENVIRONMENTAL IMPACTS ASSESSMENT (EIA) AND ENVIRONMENTAL MANAGEMENT PLAN (EMP) FOR CAN THO CITY Can Tho, December 2011 Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized

Upload: vuonglien

Post on 27-Apr-2018

217 views

Category:

Documents


1 download

TRANSCRIPT

PEOPLE' COMMITIEE OF CANTHO CITY

PPMU OF CANTHO CITY URBAN UPGRADING PROJECT

----*

MEKONG DELTA REGION URBAN UPGRADING PROJECT (MDR-UUP)

EXECUTIVE SUMMARY OF ENVIRONMENTAL IMPACTS ASSESSMENT (EIA) AND

ENVIRONMENTAL MANAGEMENT PLAN (EMP) FOR CAN THO CITY

Can Tho, December 2011

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

wb406484
Typewritten Text
E2934 v2

SOCIALIST REPUBLIC OF VIETNAM

CAN THO CITY PEOPLE COMMITTEE

CAN THO CONSTRUCTION DEPARTMENT

WORLD BANK (WB)

ENVIRONMENT IMPACT SSESSMENT REPORT

NATIONAL URBAN UPGRADING PROJECT - MEKONG RIVER DELTA REGION

(MDR-UUP)

CAN THO SUB-PROJECT

Project's owner

CAN THO CONSTRUCTION DEPARTMENT -:i!

Consulting unit

DONG DUONG CONSTRUCTION

~M---'-----

GtAMDOC

~//t ~b ./l6i1vf

Table of Contents

TABLE OF CONTENTS ............................................................................................................ 1

LIST OF TABLE ...................................................................................................................... 111

LIST OF FIGURE .................................................................................................................... III

ABBREVIATIONS .................................................................................................................. IV

INTRODUCTION ...................................................................................................................... 1

Background ................................................................................................................................ 1

Compliance with legal framework and World Bank policies .................................................... 1

PROJECT DESCRIPTION ........................................................................................................ 5

1.1. Project objective and principles .......................................................................................... 5

1.2. Project description ............................................................................................................... 5

CHAPTER 2: BASELINE CONDITIONS IN THE PROJECT AREA .................................. 10

2.1. Geography and climate ...................................................................................................... 10

2.2. Socio-economic conditions ............................................................................................... 10

2.3. Urban infrastructure and services ...................................................................................... 10

2.4. Environmental baseline ..................................................................................................... 11

CHAPTER 3: SUMMARY OF ASSESSMENT OF NEGATIVE IMPACTS ........................ 12

3.1. General impacts ................................................................................................................. 12

3.2. Site specific impacts assessment ....................................................................................... 19

3.3. Socio-economic impacts .................................................................................................... 21

3.4. Potential impacts to sensitive facilities ............................................................................. 22

3.5. Cumulative impact assessment for relative projects ......................................................... 22

CHAPTER 4: MITIGATION MEASURE ............................................................................... 2 7

CHAPTER 5: MANAGEMENT AND MONITORING PROGRAM ..................................... 29

5.1. Environmental management program ............................................................................... 30

5.2. Environment monitoring program ..................................................................................... 37

5.3. Role and Responsibilities for EMP Implementation ......................................................... 50

5.4. Capacity Building Program ............................................................................................... 57

5.5. Estimated EMP Cost ......................................................................................................... 59

REFERENCES ......................................................................................................................... 60

ANNEX .................................................................................................................................... 61

ANNEX 1: Environmental Codes of Practice (ECOPs) for Urban Construction Projects ...... 61

ANNEX 2: Guidelines for the Preparation of a Dredged Materials Management Plan (DMMP) for Contaminated Sludge .......................................................................................... 74

ii

List of Table

Table 1: World Bank Safeguard Policies Triggered ................................................................. .4

Table 2: The main investment items ofthe project.. .................................................................. 6

Table 3: Levels of Potential Negative Impacts of the Can Tho subproject .............................. 13

Table 4: Loads and concentrations of pollutants in 0 Mon, Binh Thuy and Can Tho rivers

after receiving wastewater ................................................................................................ 20

Table 5: Impacts of land acquisition ........................................................................................ 21

Table 6: Site Specific Impacts and Mitigation Measures ......................................................... 30

Table 7: Scope of environmental monitoring during construction ........................................... 39

Table 8: Estimated number of soil, water and air samples and analysis for environmental

't . d . t t' 46 monl orlng urlng cons ruc Ion ....................................................................................... .

Table 9: Estimated cost for samples collection and analysis .................................................. .47

Table 10: Basic cost for chemical analyses (Exchange rate: I USD = 21,000 VND) ............ .48

Table 11: Roles and responsibilities of key parties (Description referred to Figure 3) ........... 51

Table 12: Training programs for capacity building on environmental supervision and

management. ..................................................................................................................... 58

Table 13: Estimated Cost for EMP implementation (million USD) during the project

implementation ................................................................................................................. 60

List of Figure

Figure 1: Project location map ................................................................................................... 9

Figure 2: Chance-finds procedure to follow in case of archeological artifacts found during the project construction .................................................................................................................. 37

Figure 3: Organization Diagram for the EMP Implementation ............................................... 51

iii

CSC CUPs DONRE ECOP EIA EMDP EMP EMS GoV IEMC LIA MoC

NUUP

MDR-UUP

PCR

PMU-MoC

PPMU

RAP RP RPF RPs SEMP TA URENCO VUUP

WB

WWTP

ABBREVIATIONS

Construction Supervision Consultant Community Upgrading Plans Department of Natural resource and Environment Environmental Code of Practice Environmental Impact Assessment Ethnic Minority Development Plan Environmental Management Plan Environmental Monitoring System Government of Vietnam Independent Environmental Monitoring Consultant Low-Income Area Ministry of Construction National Urban Upgrading Program Mekong Delta Region Urban Upgrading Project

Physical Cultural Resources

MoC Project Management Unit

Provincial Project Management Unit

Resettlement Action Plan Resettlement Plan Resettlement Policy Framework Resettlement plans Site Environmental Management Plan Technical Assistance Urban Environment Company Vietnam Urban Upgrading Program

World Bank Waste water treatment plan

iv

INTRODUCTION

Background

Can Tho city is the center of the Mekong River delta. The city has experienced over 120 years of development and has achieved many accomplishments in economics, culture, science and engineering. However, the city's infrastructure is still insufficient and seriously degraded adversely affecting peoples' quality of life and urban landscapes. Due to such conditions, Can Tho city needs to develop upgraded infrastructure to secure its socio-economic future. Therefore, implementing the National Urban Upgrading Project, Mekong Delta region (MDR­UUP), Can Tho city sub-project will benefit many areas including improvement of infrastructure, sanitation, living conditions, roads, ponds, and lakes. The sub-project will also provide technical assistance to government authorities and stakeholders. The Can Tho MDR­UUP sub-project includes five components:

Component 1: Tertiary Infrastructure Upgrading In Low-income Areas

Component 2: Supporting Primary and Secondary Infrastructure

Component 3: Resettlement Site

Component 4: Implementation and Project Management

Component 5: Technical Assistance to the Ministry of Construction to Implement NUUP and for Project Coordination

A full Environmental Impact Assessment report, a detailed resettlement and compensation plan report, and a development plan report for ethnic minority have been prepared to ensure the project will be implemented to safeguard environmental and social issues in compliance with Vietnamese laws and regulations and the World Bank's Safeguard Policies, including the World Bank's Environmental, Health and Safety Guidelines.

Compliance with legal framework and World Bank policies

The project is required to comply with the current applicable environmental laws in Vietnam, which include the Law on Environmental Protection No. 52/2005/QHll dated 2911112005, and all Laws, Decrees, Circulars, Decisions, standards and regulations of Vietnam on Environment; Circular No. 26120111TT-BTNMT dated 18/04/2011 of the Minister of Natural Resources and Environment on guidelines for preparation of strategic EIA reports, as listed in detail below:

- Law on water resources No. 1998/QH adopted by Vietnam social republic parliament, session X, third time dated 20/5/1998.

- Law on construction No. 16/2003/QHli adopted by Vietnam social republic parliament, session XI, fourth time dated 26/1112003 and announced following Command No. 26/2003/L/CTN dated 10112/2003 of President.

- Law on Vietnam technical regulations No. 68/2006/QH11 dated 29/6/2006. - Law on Chemicals No. 06/2007/QHli adopted by Parliament on 2111112007 and came

into effect on 01/7/2008;

- Law of revision, supplementation of some articles relating to basic construction investment No. 38/2009/QH12 dated 19/6/2009 of Vietnam social republic parliament, session XII, fifth time.

- Decree No. 179/19991ND-CP dated 3011211999 of Prime Minister on water resource law implementation.

- Decree No. 13120031ND-CP dated 191212003 of Prime Minister on articles regUlating hazardous waste types and their transportation on road;

- Decree No. 149/20041ND-CP dated 2717/2004 of Prime Minister on Regulations of permission for surveying, exploitation, using water resource, discharge into water source;

- Decree No. 80120061ND-BTNMT dated 8/9/2006 of Prime Minister on Regulation and guideline for environmental protection law implementation;

- Decree No. 140120061ND-CP dated 22112/2006 of Prime Minister on regulations of environmental protection in preparation, appraisal, approval and organization of strategy, plan, program and development project; Decree No. 04/20071ND-CP dated 08/0112007 of Prime Minister on revision, supplementation some articles of decree No. 67/20031ND-CP dated 1316/2003 of government for waste water;

- Decree No. 59/20071ND-CP dated 09/4/2007 of Prime Minister on Solid waste management;

- Decree No. 88/20071ND-CP dated 28/5/2007 of Prime Minister on Industrial park and urban drainage (include drainage fee);

- Decree No. 174/20071ND-CP dated 2911112007 of Prime Minister on Fee of environmental protection for solid waste;

- Decree No. 21120081ND-CP dated 28/0212008 of Prime Minister on revision, supplementation some articles of Decree No. 80120061ND-CP dated 09/8/2006 of Prime Minister on detailed regulations and guidelines for implementation of some articles of environmental protection law.

- Decree No. 108/20081ND-CP dated 0711012008 of Prime Minister on detailed regulations and guidelines for implementation of some articles of chemical law;

- Decree No. 12/20091ND-CP dated 10102/2009 of Prime Minister on construction investment management;

- Decree No. 117/2009IND-CP dated 31112/2009 of Prime Minister on law breaking handle in environmental protection aspect;

- Decision No. 64/2003/QD-TTg dated 221412003 of Prime Minister on approval of "Absolutely handle of enterprises causing serious environmental pollution";

- Decision No. 256/QD-TTg dated 02112/2003 of Prime Minister on approval of national environmental protection strategy towards 2020;

- Decision No. 48/2008/QD-TTg dated 03/412008 of Prime Minister on promulgating general guidelines for feasibility study report- project use capital of official development supporting from 5 banks (Asia development bank, France development enterprise, Japan international cooperation bank, German bank for Reconstruction, World Bank);

- Instruction No. 17/2008/CT-TTg dated 05/6/2008 of Prime Minister on urgent solutions for strengthening absolutely handle of environmental pollution enterprises following decision No. 64/2003/QD-TTg.

2

- Decision No. 23/2006/QD-BTNMT dated 26/12/2006 of Ministry of Natural resources and environment on hazardous waste catalogue;

- Decision No. 04/2008/QD-BXD dated 03/4/2008 of Minister of Construction ministry on promulgation of "National regulation on construction plan";

- Decision No. 04/2008/QD-BTNMT dated 1817/2008 of Ministry of Natural resources and environment on national regulations on environment;

- Decision No. 16/2008/QD-BTNMT dated 31112/2008 of Ministry of Natural resources and environment on national technical regulations on environment;

- Joint Circular No. 12S/2003fTTLT-BTC-BTNMT dated 1811212003 of Cooperation between Financial ministry and natural resources and environmental ministry on guidelines of implementing decree No. 67/2003IND-CP;

- Circular No. 12/2006fTT-BTNMT dated 26/12/2006 of natural resources and environmental ministry on guidelines of practice condition, document procedures, registration, practice permit, code for hazardous waste management;

- Circular No. 0612007/TT-BTNMT dated 27/8/2007 of Minister of planning and investment ministry on guidelines for implementing decree No. 140/20061ND-CP dated 221111 2006 of government on environmental protection in preparation, appraisal, approval and implementation of strategy, plan, program and development project;

- Circular No. OS/2008fTT-BTNMT dated 08112/2008 of Minister of natural resources and environmental on guidelines for preparation of strategical EIA report, EIA report and environmental protection commitment;

- Circular No. 02/2009/TT -BTNMT dated 10/03/2009 of Ministry of Natural resources and environment on regulations of waste water receiving capacity of water resource

- Circular No. 04/2009/TT-BYT dated 17/6/2009 of Medical ministry on promulgation of national technical regulations of drinking water quality;

- Circular No. OS/2009fTT-BYT dated 17/6/2009 of medical ministry on national technical regulations on drinking water quality;

- Circular No.16/2009/BTNMT dated 07/10/2009 of ministry of natural resources and environment on environmental national technical regulations;

Vietnam National Technical Regulations/Standards, include: QCVN 01 :2009IBYT-National technical regulations on drinking water quality; QCVN 02:20091BYT -National technical regulations on household water quality; QCVN 03:2008IBTNMT-National technical regulation on the allowable limit of heavy metals in the soils; QCVN OS :20091BTNMT -National technical regulations on ambient air quality; QCVN 06:2009/BTNMT -National technical regulation on hazardous substances in ambient air; QCVN 07:2010IBXD·National technical regulations-Technical infrastructure work; QCVN 08:20081BTNMT -National technical regulation on surface water quality; QCVN 09:20081BTNMT -National technical regulation on undergroundwater quality; QCVN 14:2008IBTNMT-National technical regulation on domestic wastewater; QCVN 24:2009IBTNMT-National technical regulation on industrial wastewater QCVN 19:2009IBTNMT-National technical regulation on industrial emission of dust and inorganic substances.

3

QCVN 20:2009IBTNMT-National technical regulations on industrial emission of some organic substances. Noise standards: TCVN 5948:1999: Acoustic - Noise generated from means of transportation when raising speed. Maximum allowable noise; QCVN 26:2010IBTNMT: Acoustic - Noise from public area and residence. Maximum allowable noise; TCVN 3985:1999: Acoustic - Allowable noise level at working areas. QCVN 27:2010IBTNMT: National technical regulation on vibration Water quality standards: TCVN 7222:2002: General environmental requirements of centralized wastewater treatment plants; TCVN 6773:2000: Water quality - Water quality for irrigation; TCVN 6774:2000: Water quality - freshwater quality for water organism protection. Solid waste standards: TCVN 6705-2000: Non-harzadous waste. Classification; TCVN 6706-2000: Harzadous waste. Classification.

Table 1: World Bank Safeguard Policies Triggered

Safeguard Policy Compliance Actions

Environmental • A detailed EIA including an Environment Management Plan (EMP) has been Assessment (OPIBP prepared for each project city. Summary EIA and EMP reports for each city, and 4.01) a Consolidated EIA Report have also been prepared for and submitted to the

WB.

Physical and Cultural • Environmental screening conducted in the six cities included screening for Resources (OPIBP Physical Cultural Resources (PCR); no PCR are expected to be found in project 4.11) areas.

• Chance finds procedures for archaeological artifacts found during construction have been prepared and will be included in bidding documents and construction contracts.

Involuntary • City-specific Resettlement Plans (RPs) have been prepared for each city. Resettlement (OPIBP 4.12)

Indigenous Peoples • Ethnic Khmer minority communities live in some project LIAs. Four Ethnic (OPIBP 4.10) Minorities Development Plan (EMDPs) have been prepared where these Khmer

communities live.

Public consultation and • Intensive, culturally-sensitive consultations were carried out in all communities disclosure in the project areas of the six cities, including with ethnic minority groups in

relevant cities. The key comments and project responses are reported in the six EIAs and in the four EMDPs. Government agencies and NGOs were also consulted in public meetings or have sent their written opinion as required by the Government's environmental regulations. The final draft ofthe EIAs and RPs for the six cities and the EMDP for the four cities were disclosed prior to project appraisal.

4

PROJECT DESCRIPTION

1.1. Project objective and principles

The project development objective is to improve the living conditions and infrastructure services in low income areas. The following principles have been adhered to during project preparation and will continue to be applied during the design and project implementation:

• Active participation by communities in the planning, design and decision-making; communities will also be expected to contribute to the funding of the improvements -between 3% and 10%.

• Adoption of appropriate technical standards in the planning and design of infrastructure improvements, thereby ensuring costs are minimized and infrastructure provision is affordable by the cities and the communities.

• Minimizing relocation and/or resettlement in order to maintain the social cohesiveness of the communities.

• Improved service provision to all households in upgraded communities.

1.2. Project description

1.2.1. Investment location of project.

Project will focus on 13 wards in four inner districts such as Ninh Kieu, Cai Rang, 0 Mon and Binh Thuy in Can Tho city.

Of which:

• Ninh Kieu district includes Hung Loi, An Binh, Thoi Binh, Xuan Khanh, An Khanh and An Hoa wards

• 0 Mon district includes Thoi Hoa and Chau Van Liem wards

• Binh Thuy district includes Bui Huu Nghia, Binh Thuy, Long Tuyen and An Thoi wards

• Cai Rang district includes Le Binh ward

1.2.2. Investor information

• Name of investor: Department of Construction of Can Tho City

• Representative: Mr. Le Hong Phat - Director

• Address: 25 Ngo Huu Hanh street, An Hoi ward, Ninh Kieu district, Can Tho City

• Tel.: 0710 3820335, Fax: 07103827839

• Web: soxaydungcantho.vn, Email: [email protected]

1.2.3. Project cost and financing

Total investment capital for the project is: 1,910,969,333,000 VND, equivalent to $ 93,218,016 (IUSD = 20,500VND, currency exchange on April 2011). In particular, preferential loan of World Bank accounts for 75.38% and corresponding capital of Can Tho city accounts for 24.62%.

5

1.2.4. Main investment items of the Can Tho city sub-project

Table 2: The main investment items ofthe project

No. Item Phase Description

1 Component 1 Tertiary Infrastructure upgrading and service improvement in 31 LIAs, including a total area of 413 ha, 7,234 households and 32,521 residents. (USS 22.167 milliolt)

1.1 Upgrading and Phase 1 Widen existing alleys (mostly 2-3m width, and few to 6m) with concrete widening of and 2 or asphalt structure. A total of 100 alleys to be renovated, upgraded with alleys in LIAs a total length of28.5 kIn.

1.2 Installation of Phase 2 Installation of HDPE water pipe 032, 060 and connections to supply water supply water in 1389 households in LIA 1, 2, 4, 5, 6, 31. Total pipe length: system 29300 m. Water supply pipelines are connected to the main city water

supply system.

1.3 Installation of Phase I Construction of a separate drainage system along roads and upgraded drainage system and 2 alleys in LIAs. Drainage discharge points are coordinated with the KfW

financed wastewater treatment. Pipe size ranging from 0400 - 0600. Typically, LIA 10 use 0800 - DI 00 to discharge to Ba Bo canal and B2000xI500 in LIA 11 to Binh Thuy river. Dredging to clear drains will be conducted in number of LIAs such as LIA 12, 13 with dredging of Rach Mieu canal for the total length of 2.9 kIn. The total estimated volume of dredged materials is about 3,242 m3. For LIA 31 the dredging of Rach Ranh covers about 600 m length. The total estimated volume of dredged materials is 4,735 m3

1.4 Installation of Phase 1 Installation of public lighting system at the interval of25 - 30 m/pole public lighting and 2 and 70W light bulb for auto lighting. Power source is supplied from the system existing substation at a nearby location.

1.5 Provision of Phase 1 Purchase of 515 garbage bins, volume 120 I at the entry of the alleys and solid waste and 2 83 garbage carts, volume 660 1. management equipment

2 Component 2 Upgrading tertiary and secondary infrastructure. (USS 31. 768 million)

2.1 Installation of Phase 1 Construction of pipeline to connect supply source via pipe network of domestic water Chau Van Liem ward, and connected to water supply network in LIA I supply system in (invested in component I) to supply water to households. LIAI Total pipeline length is 2564 m, diameter DIOO - DI50, constructed

with PVC and steel materials. Depth of pipe: 0.5 - 0.8 m.

2.2 Improvement of Phase I The improvement will increase drainage capacity, reduce environmental BunXang pollution ofLIA 25, 26, 28, and plant greenery. Scale works: reservoir Dredging lake with an area of 18 ha. Dredged depth from 1-3 m; total

volume of dredged materials is 195,735 m3 material.

- Providing reservoir embankment with total length of 2.9 kIn. Embankment structure is quarry stone slope and bed reinforcement. - Road along the reservoir is of 15 m width linking with Rach Ngong, canal at the south.

- Collection of surface water drainage and wastewater from households. Waste water to be transferred to the drainage system under KtW project; - A culture and greenery area of 200 to 250 m2

, and public lighting system around the reservoir.

- Spillway and penstock systems: spillway, penstock and waste screeninK will be built at two points: the intersection of Bun Xang lake

6

No. Item

2.3 Improvement of Ngong canal, Sao canal, and the canal south ofBunXang reservoir

2.4

2.5

3

3.1

Upgrading of reads in Le B inh ward, Cai Rang district

Provision of solid waste management equipment

Component 3

Resettlement area at Long Tuyen ward

Phase Description

and the canal at south of Bun Xang lake and the intersection of Ngong canal and Bun Xang lake. Length of spillway: 30-35m, spillway peak elevation: +2.40m, outlet elevation: +1.65m ..

Phase 2 Improvement of flow from Bun Xang reservoir to connected LIA 26, 28 and 25.

Ngong canal:

- Dredged material: 9800 m3

- Canal embankment upgrading: reinforced concrete wall with sheet pile for foundation reinforcement. Total embankment length: 1.8 km

- Construction of embankment road of2 m width and 900 m length with drainage system, sewage systems and landscaping.

Sao canal:

- Dredged material: 17,500 m3

- Embankment upgrading on both sides using quarry stone. Total embankment length: 950 m;

- Construction of box culvert BxH = 4x2 m of 50 m length; - Building 2 m wide road of 1.9 km length and at +2.4 m level. Lighting system and separated drainage system to be provided along the embankment with connection to individual households. Drainage discharge connections to the Kfw drainage system along Cai Khe canaL

Canal south of Bun Xang reservoir:

- Dredged material: 10,000 m3

- Both embankment sides to upgraded with reinforced concrete wall. Total embankment length: 850 m;

- Construction of box culvert BxH = 4x2 m of945 m length.

- Construction of 10-11 m wide road and, 1,500m length at a level of +2.4 m. Lighting system and separated drainage system shall be provided along the embankment with connection to individual households. Drainage discharge connection to the Kfw drainage system.

Phase 2 Road upgrading includes:

- Nguyen Tanh: of5.5m width and 1,650m length

- Nguyen Viet Dung: of6.5m - 7m width and 700m length.

- Extended Ba Cai road: of 5.5m width and 1,500m length

- Road of Economic high school: 5m width, 145m length.

- Tran Hung Oao: of5.5 m width and 262m length

Upgraded roads are in LIA 29, 30, 31, and other improvements include public lighting system along roads, drainage systems, manholes and connections to households. Surface water and waste water from roads collected and discharged to Vo Tanh street and to Can Tho river.

Phase 2 Purchase of one sludge pumping cart, one sludge truck, and 3 trucks for collection, compressing, and transporting and garbage collected from river.

Construction of Resettlement Area (USS 7.660 million)

Phase 1 Resettlement areas for households relocated from Ninh Kieu and Binh Thuy districts will located in Long Tuyen ward (adjoining and Ninh Kieu and Binh Thuy) with total area of 22 ha. Resettlement area includes schools, health clinic, cultural center, market and wastewater systems. Ground elevation to be +2.5 m; excavation volume is 198,806

7

No. Item Phase Description

m3•

The project area resettlement is 5.5521 ha with 160 lots serving for on-site resettlement (22 households) and I II households to be relocated within the project area.

8

.... I.-"

,-""--. - '\ ._..J --.. / I -----, I 8

/,- i •

I I I I I I

, · · · · \ \ .

I \ ~ i

CHAPTER 2: BASELINE CONDITIONS IN THE PROJECT AREA

2.1. Geography and climate

Can Tho city is a Class I city under the management of the Central Government. The city is the center of economy, finance, trade and advanced science and technology in the Mekong River Delta with a well developed and diversified waterway and highway transport network.

Can Tho city is surrounded by the following provinces: An Giang in the North, Hau Giang in the South, Vinh Long and Dong Thap in the East, and Kien Giang in the West. Total area of the city is 1,401.61 km2

, which includes five urban districts: Ninh Kieu, Binh Thuy, Cai Rang, 0 Mon and Thot Not, occupying about 295 km2

, and four suburban districts and outlying communes, wards and townships occupying approximately 1,106 km2

Can Tho's terrain is flat with an average elevation ranging from 0.8 - 1.0m above the sea level. Can Tho city is characterized by many rivers and canals; the major waterways flowing through the city are the Hau River and Can Tho River and several major canal systems.

The monsoon season lasts from May to November. The total annual rainfall in 2009 was 1,247.7 mm. The highest temperatures occur in April while the lowest are in January. Storms and typhoons may occur in May and October; the average number of potential storm events is 63 days/year. The flood season usually extends from July to December due to heavy rains upstream; flooding peaks mostly happen in September and October. Local flooding is caused by high tides and rains. With maximum rainfall amounts of up to 100 mm/day, inundation levels may reach about 0.2 - 0.5 m.

Can Tho city is influenced by tidal regimes of the Hau River, and the semi-diurnal tidal regime of the East Sea. The highest water levels can reach 1.93 - 2.0 m above sea level.

2.2. Socio-economic conditions

The total population of Can Tho city was 1,189,555 in 2009, of which the urban population was 783,104 or 65.8%, and the rural population was 406,451 (34.2% of the total population. The average population density of the city is 1,189 people per km2 and annual popUlation growth rate is 7.9% (2010). Average per capita income is 463,500 VND/month (about US$22 equivalent). In general, the poverty rate in the LIAs is about 24%, and the employment rate is estimated at about 71 %.

The Kinh ethnic community predominates in the project area, but in three LIAs (1, 3, 6) ethnic Khmer people account for a significant percentage of the population. There are 15 temples and pagodas and 16 schools located near the project works.

2.3. Urban infrastructure and services

Can Tho city has five water treatment plants: Can Tho No.1 (50.000 m3/day), Can Tho No.2 (40,000 m3/day), Tra Noc (10,000 m3/day), Hung Phu (10,000 m3/day) and 0 Mon (2,400 m3/day). Raw water is withdrawn from the Hau, Can Tho and 0 Mon Rivers. Among the 31 LIAs, there are 5 LIAs where households are still without water meters.

10

Both Binh Thuy and Ninh Kieu districts have no separate wastewater systems, and only a small percentage of alleys have adequate drainage systems. The drainage capacity of existing lakes and canals is poor, resulting in water logging and local flooding after heavy rains. Flood levels can reach about 0.3 - 0.4 m in some places, lasting for several hours. In the 31 LIAs, wastewater and domestic wastes are not collected but are discharged/disposed of directly into lakes and canals, thereby causing serious pollution.

Municipal solid waste is mainly collected from 4 districts: Ninh Kieu, Binh Thuy, Cai Rang, and 0 Mon). The collection and transport capacity is about 416 tons/day. The waste collection rate is 55% of the city's total waste generation. Two landfills service the city: (i) Tan Long landfill in Phung Hiep district in Hau Giang province with total area of 20.8 ha, and (ii) Phu Thu landfill in Phu Thu ward in Cai Rang district with a total area of 3.5 ha; it can be expanded to 6 ha.

2.4. Environmental baseline

Analysis of air samples shows that air quality has deteriorated due to dust and vehicular exhaust fumes. Air pollution concentrations and noise levels are high, and not in compliance with current national standards.

Surface water in the subproject areas is contaminated with organic matter and microorganisms from waste and wastewater discharges. The concentrations of BOD5, COD, N are 1.2 - 4.3 times higher than the regulatory threshold. The coliform count is 10 - 100 times higher than the current threshold.

Local groundwater is contaminated by ammonia and coliform in the 4 districts of the project area, exceeding the standard threshold by 1.8 - 24 times. Groundwater pollution is likely caused by wastewater leaking from abandoned or improperly sealed wells; the excessive use of fertilizers may also contribute to groundwater pollution.

The concentration of heavy metals in the sludge in canals that are proposed to be dredged, is lower than the current Vietnamese standards. Therefore, dredged sludge can be used for leveling land or as fill material.

11

CHAPTER 3: SUMMARY OF ASSESSMENT OF NEGATIVE IMPACTS

When the project is completed, the overall impact will be positive. The total number of direct beneficiaries from the project is 46,205 people, including: 26,075 people (from component I), 19,598 people (from component 2), 532 people (from component 3) and the indirect beneficiaries are 479,466 people. Nevertheless, the project will cause some negative impacts on the local environment and the local population. Therefore, effective implementation of mitigation measures will be necessary.

The potential negative impacts of the project's subcomponent on the physical, biological, and socio-economic environments are identified using the checklist method, including assessment of the levels of impacts during the preconstruction, construction, and operation phases. Potential negative cumulative and social and impacts on physical cultural resources (peR) have been identified separately.

3.1. General impacts

Based on the analysis of baseline data, field visits, and discussion with key officials and stakeholders, the potential negative impacts on the physical, biological, and socio-economic environment caused by the project have been identified. Table 3 summarizes the potential impacts by the project subcomponents. The level of impacts are assigned as follows: None (N) -no impact; Low (L) - Small works, minor impacts, localized, reversible, temporary; Medium (M) - Small works in urban/sensitive areas, medium scale works with moderate impacts of which most are reversible, reducible and manageable, localized, temporary; High (H) - Medium scale works in small urban Isensitive area, large scale works with significant impacts (socially and/or environmentally) of which some are irreversible and require compensation. The residual impacts of the project, after implementation of mitigation measures discussed in the EMP, are expected to be mostly negligible.

12

Table 3: Levels of Potential Negative Impacts of the Can Tho subproject

Pre-c.onst.

Construction

Operation

L

M

M

M L

M M

M L

L

L

N

N

N

N

H N

N N

N N

Component 2: Primary and Secondary Infrastructure Upgrading (US$ 29.828 million)

L M

L M

L M

L

M

L

L

M

L

Small-scale impacts are best addressed through ECOPs (see Note 2 below)

- Issues may include the need for offsite material borrow; local flooding; disturbance to residents (small roads, densely populated, locations of borrow areas).

Ensure adequate O&M for wastewater management

Wastewater of:

12/31 LIAs are discharged directly into receiving water sources

313 I LIAs are treated before discharged into receiving sources (meet QCVN 14:20081BTNMT Class A)

16/31 LIAs are connected to existing sewer and flow to KFW collection and treatment systems

Subcomponent 2.1: Installation of water supply network for Lia 1 - Installation of uPVC-PN8, D 11 0 water supply pipeline, L = 2,564 m

13

Pre-const. I L

Construction I M

Operation I M

!~t\b~;~~ne:t7.2 ·It.lf!1sppHroatl:,fl .22:;

Pre-const. I M

Construction I H

M

M

M

M

H

IL IL IN IH IN IL 1M ·1 L IL I Small-scale impacts are best addressed

I~ I~ IN I: I: I~n I: I~ I~ through ECOPs (see Note 2 below

I Ensure adequate O&M for water IN supply pipeline management

0,£ !~~,xa~g\~~!~;U~graJi;;gl;!~~~~I/~;~!~!tl~ ~:~!(tf 5~~~~00rf!~1J~~~if.~litgte~~ils v~{~me Ig (3,5/ffh). pub{i~t~or;lg;JO IBltlturlfllz0U:ffl.J/;O J ~fill.~!J info~"1pli~rz'~Ruse,o,lw$eho.Pf/!!)~~ark '(~4, 47.

" "i dd, , I" '<, I "" i ' , "'I" "" I'~·!-~T-

1M IN IL 1M IN IL 1M 1M 1M I - Issues are populated areas with

lH IN IL 1M IN IN 1M 1M 1M limited road access; dredging and

I disposal of large volume of dredged materials; local flooding; off site impacts; disturbance to residents; increased traffic.

Operation I LIM I MIN I N I N I N I N I N I M I M I - Ensure effective O&M; disposal of solid waste and local flooding.

~~b~g~ponenf~~: i~~!~~II~ti:~io!dr~i~age ~y~t~mpr~!~1! X~?g l~~~ba~iniwi~~ J iO~f!!~ PiP,e,.I)3~§!k;\.D6~9\J(~le~~1r(17. 7~9kniJi':~~eles\<61~!~~~;~()~h61£i~!,. co~ecti0f!.~anhbl~.s{12,40~~ts);iOtltlet (8~!~!s);se"aratedwell (~Units); p1lIIlping~tatio~{ 1·· un~!l; nwnbe~~coll11~cted.!~puseh~ld~ (1:2,406~~g~~h9,J~)(\\! .... < ! (.i i •. !;

c, i' , ,,> ", II'! i, 'i I '" I, ) ) , '," ) " ) )

Pre-const. IL 1M IL IL IN IH IN IL 1M IL IL I Small-scale impacts are best addressed

Construction

I: I: I~ I~ I: I: I: I~ I: 1M 1M

I through ECOPs (see Note 2 below

Operation IL IL I Ensure adequate O&M for wastewater management

Wastewater is connected to existing sewer and flows to KFW collection and treatment systems

14

Pre-const. 1M 1M 1M IN IL 1M IN IL 1M 1M 1M I - Issues are populated areas with

Construction IH IH IH IN IL 1M IN IN 1M 1M 1M limited road access; minor dredging

I and disposal of dredged materials; local flooding; off site impacts; disturbance to residents.

Operation IL 1M 1M IN IN IN IN IN IN 1M 1M 1- Ensure effective O&M; disposal of solid waste and local flooding.

Pre-const. 1M 1M 1M IN IL 1M IN IL 1M 1M 1M I -Issues are populated areas with

Construction IH IH IH IN IL 1M IN IN 1M 1M 1M limited road access; minor dredging

I and disposal of dredged materials; local flooding; off site impacts; disturbance to residents.

Operation IL 1M 1M IN IN IN IN IN IN 1M 1M I -Ensure effective O&M; disposal of solid waste and local flooding.

Pre-const. 1M 1M 1M IN IL 1M IN IL 1M 1M 1M I -Issues are populated areas with

Construction IH IH IH IN IL 1M IN IN 1M 1M 1M limited road access; minor dredging

I and disposal of dredged materials; local flooding; off site impacts; disturbance to residents.

15

Small-scale impacts are best addressed through ECOPs (see Note 2 below)

Construction I M I M 1M· I LIN I N I NIL I M I M I M I th d C - Issues may include e nee lor offsite material borrow; local flooding; disturbance to residents (small roads, densely populated, locations of borrow areas).

Operation I M I M I L I N I N I N I N I L I M I L I L I Ensure adequate O&M for wastewater management

Wastewater is discharged directly into receiving water sources

~ __ ~ __ ~ __ ~ __ ~~ __ ~~ ______ ~ ____ ~L-____ -L ____ ~~~~~~~~~ __ __

Subcomponent 2.8: Installation of Sewer connecti()D for Xang Thoi lake~ L = 500 m, reinforced concrete sewer D400 ;"ith length L=500m, and 20 manholes

Pre-const. I L I M I L I L I N I H .. I N I L 1M· I L I L I Small-scale impacts are best addressed through ECOPs (see Note 2 below)

Construction I M I M I MIL I N I N I NIL I M I M I MI. I d th d C - Issues may IDC u e e nee lor offsite material borrow; local flooding; disturbance to residents (small roads, densely populated, locations of borrow areas).

-------------

Operation I M I MIL I N I N I N I NIL I MIL I L I Ensure adequate O&M for wastewater management

16

"S,~b~oDlw~e9l9~8l~fy~ch~~e"pl.~arii~'!~~'i¢q9i~Dl.~~ '. Ul'lits); waste compactor truck (1 unlt),' w~te collection~qu

Pre-const. L L L IL IL I - Small-scale impacts best addressed

Construction L L jN IN IN IN lN L N N N N N L L

I~ I~ through ECOPs (see Note 2 below)

1- O&M problems. Loss of containers or L Operation L L IN IN IN IN IN L carts

CoDlPonent3; ~ese~il~;~;;;is~t~ .~r~ii atLing'fu>:en (US$9il¥9:mil!i~nf~ t!;nl~~ti~)n,~ol to~g tuYe;n;~eltle"'e~;$~~~rvilhl~Ql~;iol~O.-120 rn!iea~h,iiI1Cl1fdfn~s;te leveling, road networks, water~upply: and drainage systems,power supp/y,.sireetliiliting,i:m4packageservagetreatttJ.e~i pla.nt,qna.f!~e~ spac~ . . ... '.

Pre-const. L I I I I I Small-scale impacts best addressed Construction M M M L ! L I N t N I L I M I M t M [ through ECOPs (see Note 2 below)

- Need to watch for PCR; need for imported fill from offsite; local flooding; disturbance to residents (small road, densely populated).

L M L L L H N L M L

Operation L L L N N N N L L L L - Need to address risks due to inadequate OIM (wastewater will be treated by onsite package treatment plant; livelihood restoration; and local flooding.

Notes: (l) The following criteria are used for the assessment oflevel of impacts: None (N) - no impact; Low (L) - Small works, minor impacts, localized, reversible, temporary; Medium (M) -Small works in urban/sensitive areas, medium scale works with moderate impacts of which most are reversible, reducible and manageable, localized, temporary; High (H) - Medium scale works in small urban Isensitive areas, large scale works with significant impacts (socially and/or environmentally) of which

17

(2) For small and medium scale works, most impacts are localized, temporary, and can be mitigated through the application of good engineering and construction management practices and with close supervision and monitoring, and close consultation with local communities.

18

3.2. Site specific impacts assessment

3.2.1 Component 1

(1) Construction phase

Impacts on ethnic minority

There are no Khmer households displaced in the project area. Only one household of Mr. Pham Van Tuan at alley 3 and LIA 2 will lose 3m2 of agricultural land (accounting for 8.3% of his total land area) due to alley expansion.

Impact from sludge transportation

Volumes of dredged materials from Mieu canal (2,900m long, LIA 12, 13) and Ranh canal (600m long, LIA 31) are 1,493.5m3 and 3,242m3

, respectively. The dredging activities are conducted mainly by hand and the dredged materials will be transported by special trucks to Cai Sau landfill. Sludge transport routes are proposed for Mieu and Ranh canals as following:

+ Mieu canal (12km): Mieu canal -+ Binh Thuy street -+ CMT8 street -+ 30/4 street -+ Quang Trung street -+ Cai Sau landfill

+ Ranh canal (12km): Ranh canal -+ Nguyen Viet Dung street -+ National Highway No.1 -+ Quang Trung street-+ Cai Sau landfill

The dredged material transportation process also generates a large amount of dust and other air pollutants due to fuel consumption.

(2) Operation phase

Impacts of temporary discharge of wastewater into rivers

Installed drainage systems will collect wastewater from 3,535 households (15,909 people) of 12/31 LIAs and discharge directly into receiving water sources. The predicted sewage volumes range from 2,912m3 (in 2015) to 4,705 m3 per day (in 2025). These impacts will be assessed in more detail with Component 2.

Risk assessment of temporary flooding caused by raising road level

There will be 100 alleys upgraded. However, most of them are only few hundred meters in length and will be increased about 20-40 cm in elevation. There are only 12 alleys longer than 400 m which could have some risk of flooding. This impact is not great because after completion of drainage systems, the drainage capacity is also significantly increased. The flooding risk only occurs in short periods; a few hours on certain days when heavy rainfall and high tide occur simultaneously. Some alleys run along the river and canals (LIA 1, LIA 19) where house levels are much higher than the existing road level. The flooding effect only occurs in a short-time and can be minimized.

3.2.2 Component 2

(1) Construction phase

Dredged material

Total sludge volume of dredged materials from Bun Xang lake, Ngong canal, Sao canal and canal at the south of Bun Xang lake will be 233,035 m3

• Sediments will be dredged by shell

19

scrapers, and then loaded on barges for transporting to Cai Sau landfill. According to the sediment quality sampling results in the dredged canals and lake, pollutant and heavy metal concentrations are below the permitted standard, QCVN 03:2008. The sediment/dredged materials can be also used as leveling material or farmland soil conditioner after pretreatment.

Dredged material transportation

Dredged material will be transported by barge starting from Bun Xang lake, Ngong canal, Sao canal and the Southern canal -+ Cai Khe canal -+ Hau River -+ Can Tho River -+ Cai Sau sludge dumping landfill. The one-way transportation distance is estimated to be 10km and barge capacity is 100 ton. Dust and pollutants generated from dredging equipments TSP, S02, N02, CO, and THC. Generated pollutants from the transport of dredged materials include HC, CO and NOx.

Impact assessment of construction of water supply line for LIAI - section through 0 MonBridge

According to the project design, the steel water-supply pipeline for LIAI has a total length of 114m and a diameter of 150mm aligned over the bridge installed on a V -shaped steel frame . Pipeline construction and installation are simple and not obstructive and will not affect traffic on the bridge during the construction and operation.

(2) Operation phase

Impacts on water quality of receiving sources

In operation phase, drainage renovation installed along routes in Le Binh Ward (component 2) and 12/31 Lias (Lia 2, 4, 6, 10, 11, 14, 17, 18, 20, 21, 22, 24) (component 1) will be

temporarily discharged untreated domestic wastewater into 0 Mon, Binh Thuy, Can Tho

Rivers. They will increase environmental pollution risk in these rivers. The calculation results

in comparison with class A2, QCVN 08-2008 and wastewater quality of the World Bank

Environmental, Health and Safety Guidelines (Table 4) show that 0 Mon, Binh Thuy, Can Tho

Rivers are still able to receive pollution loads except NRi. The temporary discharge of

untreated wastewater will increase ammonia concentrations in Can Tho River slightly above

allowed standards, class A2, QCVN 08-2008 (0.5 mg/l) (WB HSE only has standard on total nitrogen (10 mg/L) not for amonia). Therefore, for long term, it is necessary to collect and

treat wastewater to meet permitted standards before discharging into surrounding environment, as well as control ammonia discharges from non-point sources entering these nvers.

Table 4: Loads and concentrations of pollutants in 0 Mon, Binh Thuy and Can Tho rivers after receiving wastewater

Parameter BOD COD NH4

River Can Binh 0 Can Binh 0 Can Binh 0 Tho Thuy Mon Tho Thuy Mon Tho Thuy Mon

Ltn- Load can receive

(kg/day) 47,957 3,240 4,904 84,596 21,945 32,976 -1,416 21 35 --_ .. M"' _____

__~·_~'M'~ .... _·_ ~.~---

Concentration after

receiving (mg/l) 2.15

% increase compared

with origin 2.16

Comparison with

QCVN 08, Column A2

Wastewater quality of

WB'sEHS

4.83

0.59

6

30

4.82 8.20 7.06

0.36 1.25 0.90

IS

125

Impacts of solid waste and dredged material from canals/lake

7.05 0.61 0.19 0.19

0.70 0.61 1.25 0.77

0.2

NA

Estimated solid waste amount is 125, ton/day arising from canals: Sao canal, Ngong canal, Southern canal of Bun Xang lake and Bun Xang lake. The calculation results for Component 2 for canal sedimentation shows that Component 2 contributes to open flow and requires significantly periodic sludge dredging of Sao canal, Ngong canal, and Southern canal of Bun Xang lake. Sediment deposition will depend on the suspended solid concentrations of Hau River. So wastewater discharge to the lake basin does not significantly impact dredging frequency. The sludge dredging frequency to clear sediment build up in lake and canals is 80 years for Sao canal, 86 years for Ngong canal, 117 years for canal at the south of Bun Xang lake and 38 years for Bun Xang lake.

3.3. Socio~economic impacts

Land Acquisition and Resettlement

Detailed information regarding the nature and scale of the impacts and proposed mitigation measures are provided in the "Resettlement Plan" (RP) report which was prepared separately. There are no indigenous people affect~d by the Can Tho city subproject.

Based on the RP, the impacts due to land acquisition and resettlement include the following:

Table 5: Impacts of land acquisition

. Subject . Component I I Component 2

Land (m2) Agriculture ',: 16,181

Non- agriculture

Residence 15,407

I 62

I Fourth house (m2) 14:35'6'

! Impacted Whole part 21 97 : household

part of house 449 :

part of land 1682

Tree (m2) 1,914

No Khmer households will be relocated due to the project.

Other social impacts

Component 3

95,336

2010

1,229

.. 1..

! I

21

!

I I

Other potential social impacts on local communities are transportation obstructions, road safety or public safety, labor accidents, or disruptions to communities during site clearance, construction, and operation.

3.4. Potential impacts to sensitive facilities

The project will not directly impact historical and cultural monuments, religious sites, schools or health facilities during the land acquisition process. However, during the construction phase, construction material transportation and construction activities can affect sensitive points. There are 15 temples, pagodas, churches and 16 schools which could be affected by dust and noise during construction phase. Most sensitive areas more than 10m from construction sites. A few of them are as close as 5 m including: Van Phuoc pagoda, national historic and cultural monument - Hau Giang An Nam Communist Party, Ngoc Hoa monastery, Thien Hau temple, Bach Chu Su temple, Linh Thanh pagoda, Long An pagoda, the Duc Me Hang Cuu Giup Cathedral, Kim Ngoc temple, Thanh Quy seminary, Nguyen Du Primary School, Thai Hoa kindergarten, Trung Vuong primary school, and Le Binh kindergarten.

3.5. Cumulative impact assessment for relative projects

1. KFW project. This is considered an associated subproject to MDR-UUP subproject in Can Tho City since it will treat wastewater collected from MDR-UUP prior to discharge. As such, due diligence work has been conducted by the PMU/consultant and below are the detailed information and findings of the due diligence work.

KFW project

~ Scope of work

Can Tho drainage and domestic wastewater treatment project (KFW) with capacity of 30,000 m3/day.night in the frrst stage and extended to 30,000 m3/day.night in the second stage, in the area of2lha. The project owner is Can Tho Water Drainage and Supply Company. The objectives of the project are to build a new collection system and upgrade the old sewer system to collect and treat wastewater of 10 wards, including An Phu, An Lac, An Hoa, Xuan Khanh, Thoi Binh, Cai Khe, Tan An, An Cu, An Hoi and An Nghiep of Ninh Kieu District.

~ Relationship with MDR-UUP project:

The collected wastewater from MDR-UUP (16/31 Lias including Bun Xang lake) will be pumped to the KFW treatment plant. The drainage system of some Lias in Ninh Kieu district, and the drainage system of Bun Xang lake of MDR-UUP project witt be connected and associated with the drainage network of the KFW project.

Wastewater flow from the project area will account for 38% of the total design capacity of the KFW plant (60,000 m3/day). However, it will not overburden the capacity of the treatment plant because this flow had been included in the design of the KFW project.

~ Sources of Finance

The capital source is from the German Development Bank (KFW) with the total investment of 18.723 million Euro.

The collection system and wastewater treatment plant of the KFW project have been

22

started since 2007 and will be completed at the end of2012. ~~--~--~--~~~--------

The EIA of the project have been approved by Can Tho DONRE and evaluated by environmental specialist from the German government. Below are summary of the impact evaluation for each project component:

);> Newly building separate drainage systems for wastewater and rainwater

Digging ditch, canal to install water pipe to cause dust, noise and to affect on living activity of people on surrounding areas.

Flooding: The execution process can cause local flood at improper and prompt arrangement of drains.

);> Waste water treatment plant

The treatment position selection is very important action to ensure effective treatment, support of people and maximum restriction of impacts on environment and people living. Design works for the components are suitable with the general planning of Can Tho City to ensure safe distance to residences, discharge gates at the downstream of Can Tho River and the treated wastewater must be met the Viet Nam environmental standard of type A, TCVN 5945:2005 (now it is replaced by the QCVN 14:2008/BTNMT) before discharging to receiving source.

Most of the negative environmental impacts are insignificant, short-term and reducible. Mitigation measures have been properly proposed in EMP including mitigation measures, roles and responsibilities of stakeholders concerning to the environmental management, monitoring and the capacity building program.

Community consultation has been conducted during project preparation. Almost participants agreed with the contents of the project. However, some comments asked the PMU must comply with the mitigation measures proposed, particularly with odor emissions from the wastewater treatment plant.

Proposed mitigation measures in the approved EIA report of the WWTP project foUowas:

);> Mitigation measures to treat generated sludge of the WWTP

Generated sludge from WWTP processing will be treated by the technical diagram following as: Activated sludge ~ Sludge pump ~ Sludge conveyor, press ~ to transport to landfills or recycle into fertilizer.

);> To control tbe quality oftbe treated wastewater of the WWTP

According to the approved decision of the EIA report by Can Tho province People's Committee - Department of Natural Resources and Environment (DONRE), the effluent of the WWTP must meet standard of type A, TCVN 5945:2005 (now it is replaced by the QCVN 14:2008/BTNMT).

);> Mitigation measures to treat odor and pathogens microorganisms

To prevent odors, to spray EM (effective microorganism) regularly during the WWTP operation period.

To plant trees to create buffer areas separated from residential areas should be performed adequately and construct walls (fences) around.

To spray insecticides to kill flies, mosquitoes and insects which have the potential to cause disease at the sludge treatment area.

23

Environmental management program has been proposed in the EIA report, has mentioned the roles and responsibilities of stakeholders in the implementation of the environmental management plans for the KFW project.

Environmental monitoring program proposed in the EIA report, including monitoring indicators, locations, frequency and applicable standards. Monitoring frequency of environmental quality is 4 months per time during the construction period and 6 months per time in the first operation year.

Due to the schedule, the project will be completed at the end of 2012 and will not coincide or overlap will with the implementation of the MDR-UUP subproject. The negative cumulative impacts of MDR-UUP and the KFW project will only occur at the drainage systems of some Lias in Ninh Kieu district and Bun Xang lake. Cumulative impacts are expected to be insignificant.

Cooperation between two PMUs need to be established in order to:

2. Cai Sau sludge landflll

Exchanging information on the environmental mitigation compliance of two project's contractors

Properly arranging schedule (especially related to heavy load work) to avoid construction activities occurring at the same time and same place.

Cai Sau sludge landfill

)0> Scope of work

Cai Sau sludge landfill has been designed to contain sludge of WWTP and dredged material of MDR-UUP. Sediment from dredging activities of the MDR-UUP project in Can Tho city will be also transported and treated at this site.

)0> Relationship with MDR-UUP project

All dredged material from MDR-UUP project in Can Tho city will be disposed at this landfill.

)0> Sources of finance

Local budget

The curent area is 3,500m2 which are being built and will be operated in the end of 2011. This landfill had been approved to expand to about 5-6 ha in 2012 by Can Tho City People's Committee, which should be completed and ready when the MDR­UUP subproject commences implementation.

Environmental protection commitment of this project was certified by the People's

Committee of Cai Rang district No. 25/GXN-UBND dated on July 13ni, 2011. Below

are summary ofthe impacts for each project item:

)0> Assessment of options to select the location

The location to construct Cai Sau landfill has enough land for treatment and landfill of sludge ofWWTP and dredging material ofMDR-UUP.

The distance from the landfill to residential areas is reasonable to limit the direct impacts to residents (noise, dust, and odor) by the waste transportation

24

and treatment; it is around 2 km radius.

The landfill location is at the end of the main wind direction.

~ Assessment of negative impacts on the implementation of Cai Sau sludge landfill: construction phase, operation phase and closure of landfill.

Construction phase: (1) change air quality, noise, vibration and dust emissions by digging activities, transportation vehicles of materials and waste and construction machineries; (2) change water quality by wastewater from camps of workers and truck washing before going out of the site; (3) change soil quality by solid waste generation from workers, (4) other impacts: occupational safety, transportation, landscape change.

Operation phase: (l) wastewater from leachate of landfill, and from worker and operator activities, (2) gas emission from landfills by decomposition of organic matter and gases (N2, H2S, C~), noise from trucks, (3) other impacts: fire risk, occupational safety and impacts on public health by creating growth medium flies and disease-causing microorganisms.

Landfill closing period: (1) wastewater: similar with landfill operation phase if fmal cover and surface water drainage systems are not designed, installed and operated reasonable, (2) gas emission: gases (N2, H2S, C~) from landfill; (3) other inlpacts: subsidence landfill, ignition risk and gas dispersion from landfill sheets, re-landscape.

The environmental impacts are significant: Leachate and gas emissions from landfill,

development of flies, sticks and microorganisms in operation period. The EMP has

been proposed including mitigation measures, roles and responsibilities of

stakeholders for environmental monitoring, management and capacity building

programs.

~ Mitigation measures to treat leachate from landfill

Landfill leachate will be collected by the pile HPHO 0200 perforated tube, the end of each pipe leachate collection arrangement of pumping station rubbish to leachate treatment system.

The quality of wastewater output has met standard of type A, QCVN 25:2009 IBTNMT.

~ Mitigation ~easure to treat gas emission from the landfill

Gas emission is collected by vertical wells spaced. Pipe HOPE 0200 collects gas from wells ..

~ Mitigation measures to treat odor and pathogens microorganisms

During the operation phase, daily use soil to cover layer to prevent odors, spray EM (effective microorganism) regularly, especially after rain.

To plant trees adequately to create buffer areas separated from residential areas and construct walls (fences) around.

To spray insecticides to kill flies, mosquitoes and insects with high potential to cause disease.

Environmental monitoring program proposed including: monitoring indicators, monitoring location, frequency and applicable standards. Monitoring frequency of environmental quality is 6 months per time in the construction period and 6 months per time in the operation period.

25

Assessment of The upgraded landfill has been designed and constructed following the national standards with sufficient technical facilities for solid waste treatment. The capacity of landfill is enough for the MDR-UUP project. Thus, the impacts generated from dumping of solid waste will be minimized within scale of landfill. As calculated, about 237,770.5 m3 of dredged sediment of MDR-UUP will be transferred and dumped into the Cai Sau landfill. The landfill totally has capacity to treat this sludge. Environmental impacts and other impacts of Cai Sau landfill were assessed and its mitigation measures were proposed to ensure that it could receive and treat all slud e enerated in the ci . The environmental monitoring program needs to be developed. It is included (but not limited) by:

Air quality monitoring Groundwater monitoring

26

CHAPTER 4: MITIGATION MEASURE

This chapter identifies measures to mitigate the key negative project impacts during construction (which include site clearance, ground leveling, and construction) and operation. Given that most key impacts will occur due to civil works and transportation of construction/waste materials, many of the potential negative impacts on physical, biological, and social environment can usually be mitigated through a set of general measures that are typically applied to construction projects to minimize impacts such as noise, dust, traffic disruption, wastewater generation, etc. As part of the Environmental Management Plan (EMP) for the project these general measures have been transformed into a set of standard environmental specification that will be incorporated into all bidding and contract documents of the project. These measures are referred to as Environmental Codes of Practice (ECOPs), and they will be applied to mitigate typical and general impacts the project's civil works. The scope and content of the ECOPs are presented below.

ECOPs are a set of actions and measures to mitigate the general negative impacts during construction. They describe typical actions to be taken by contractors, supervised by the construction supervision consultants (CSC) during construction, and monitored by the communities and the Independent Environmental Monitoring Consultant (IEMC). These ECOPs also cover the applicable provisions under Section 4.0 on Construction and Decommissioning of the IFC-W orId Bank Group Guidelines for Environmental, Health, and Safety (EHS). The detailed ECOPs will be incorporated into the bidding and contract documents (BD/CD) during the detailed design stage. The scope and content ofthe ECOPs is limited to construction activities for small and medium-size contract works. The impacts of such works are of limited extent, are temporary and reversible, and can be managed readily with good construction practices.

The ECOP measures identify typical mitigation actions for the following types of impacts:

- Dust generation - Air pollution - Impacts from noise and vibrations - Water pollution - Drainage and sedimentation control - Management of stockpiles, quarries, and borrow pits - Solid waste management - Management of dredged materials - Disruption of vegetative covers and ecological resources - Traffic management - Interruption of utility services - Restoration of affected areas - Workers' and public safety - Communication with local communities - Chance finds of cultural or archeological artifacts

The detailed ECOPs (Annex 1) are cross-referenced to the respective equivalent Vietnamese regulations, standards, and codes of practice.

If impacts require site-specific mitigation measures that are not adequately covered in these generic EeOps, they must be addressed separately in the EMP. For example, the above Eeops do not cover impacts from worker camps - assuming they would not generally be needed for small urban works projects - and impacts from large works, such as dams, bridges, tunnels, and major roads. The EeOps cover small dredging operations; however, operations generating very large amounts, or seriously contaminated, sludge would need to be handled through a separate set of measures outside of the scope of these EeOps, such as in a dredging and materials management plan (DMMP - Annex 2). Social impacts caused by involuntary resettlement or involving ethnic minorities are addressed in other safeguard instruments.

28

CHAPTER 5: MANAGEMENT AND MONITORING PROGRAM

Prepared as a part of the EIA, an Environmental Management Plan (EMP) is a safeguards instrument that is typically used in many projects. It consists of information on, and guidance for, the process of mitigating and managing adverse environmental impacts throughout project implementation. Typically in Vietnam, an EMP comprises a list of typical mitigation measures to be carried out by contractors and others, an environmental monitoring program, capacity building, organizational arrarigements and responsibilities, and the estimated cost of EMP implementation and monitoring.

There is a comprehensive regulatory framework in Vietnam related to EIA preparation, environmental standards, protection and management of forests and cultural property, and other aspects related to construction and operation of facilities and infrastructures in Vietnam. This EMP in consistent with these regulations.

To facilitate effective implementation of the EMP, the PPMU will: (a) Establish an Environment and Social Unit (ESU) responsible for ensuring timely implementation of the EMP, including monitoring, reporting, and capacity building related to safeguards; (b) Assign the Construction Supervision Consultant (CSC) to also be responsible for supervision of the contractor's safeguard performance as part of the construction contract and this requirement will be included in the CSC's terms of reference; and (c) One Independent Environmental Monitoring Consultant (IEMC) is hired by PMU-MOC to assist the ESUs in performing its task.

Can Tho City Water Supply Company, URENCO, and the Department of Transport will be responsible for implementation of the mitigation measures during the operation stage of the project and they will ensure that the mitigation measures are implemented and adequate budget is provided. The Provincial Steering Committee (PSC) chaired by the Chairman or Vice Chairman of the Provincial People's Committee (PCP) will provide the overall policy guidance and oversight of the project implementation. Roles and responsibilities of the specialized agencies and the Departments of Planning and Investment and Natural Resources and Environment (DONRE) will also be critical.

There are two main parts to this EMP. Firstly, the City will use Urban Construction Environmental Codes of Practice (ECOPs) for urban construction works. Environmental codes of practice (ECOPs) are mitigation measures for generic impacts from project activities during the construction phase; they must be included in the bidding documents as requirements directed to the construction contractor. ECOPs are not a formally recognized World Bank safeguards instrument but their use, as part of an EMP, is a convenient and effective way to ensure that the main generic, common and typical construction impacts are adequately mitigated during project implementation.

If impacts require site-specific mitigation measures that are not adequately covered in these generic ECOPs, they will be addressed separately in the EMP. These ECOPs also do not cover impacts (i) from worker camps (camps will not be needed for small and medium urban infrastructure projects), (ii) from large works, such as dams, tunnels, large road and bridge projects (which are not part of this project). Social impacts caused by involuntary resettlement or involving ethnic minorities are addressed in other, social safeguard instruments. The ECOPs

cover dredging operations producing relatively small amounts of sludge, whilst very large amounts or seriously contaminated sludge would need to be handled through a separate set of procedures outside of the scope of these ECOPs.

Activities carried out to mitigate impacts due to land acquisition and resettlement are presented separate safeguard documents (in the RPF and RP); they will be carried out and monitored separately.

Also included in the EMP are related measures, above and beyond actual mitigation measures. This includes the PPMUs' EMP program, including capacity building and safeguard training; and environmental monitoring.

5.1. Environmental management program

5.1.1. Management of impact on project sites

Table 6 presents site-specific impacts and mitigation measures that are not fully addressed through the application of ECOPs. This may be because the impact is not a typical one and is not included in the ECOPs, because the severity of the impact goes beyond the scope of the mitigation measures in the ECOPs, or because simply of the very specific nature of the mitigation measure that is needed.

Impacts

Mitigation:

Implementation mechanisms:

Responsibility:

Fund source:

Impacts

Mitigation:

Table 6: Site Specific Impacts and Mitigation Measures

• Surface water quantity

• Ensure install work is safely, in accordance with contract conditions • Periodically dredged to prevent clogged drainage systems • Installation of sewage pump or drain to divert runoff • Periodically check the status of the drainage system

• Do not throw garbage into drains

• Contract conditions, supplementing those of the ECOPs

Contractor

IDA Credit

Supervision ConsultantlPPMU

• Inadequate attention to drainage and waste management

• Surface water quantity

• Ensure that surface water quantity do not polluted in the city's operations and maintenance

• Surface water monitoring periodically in the outlet sites

• Place signs in the outlet sites

• Provide a monitoring information for authorities and local people

• Leaks on drainage system must be detected and corrected promptly

30

Implementation mechanisms:

Responsibility:

Fund source:

Monitoring:

Impacts

Mitigation:

Implementation mechanisms:

Responsibility:

Fund source:

Impacts

Mitigation:

Implementation mechanisms:

Responsibility:

Fund source:

Monitoring:

City Operations and Maintenance Plan

City

City

City

• Odor, generation of dredged materials

• As set out in the ECOPs

• Before carrying out the dredging plan, must specify the time of construction, construction methods and measures to ensure public, traffic safety and environmental hygiene

• Using specialized trucks to transport dredged materials, covered enclose vehicles to transport in order to prevent waste not to scatter the traffic

• Contract with URENCO for transportation and disposal and sludge treatment in an appropriate manner

• No sludge stored temporarily in residential areas, do not leave waste on the street overnight

• Dredged waste must be put in closed container out and carried to the dump site within the day

• No dredging in the period from II am to 13 pm, from 17 to 19 pm. In urgent cases, the dredging from I I am to 13 pm, from 17 to 19 pm must be approved by Director of Department of Transport and Public Works.

• Restore the original situation of the area after detecting the risk of waste, and spreading sludge of the areas or after completion of works identified at the temporary landfill

Contract conditions, supplementing those of the ECOPs

Contractor

IDA Credit

• Inadequate attention to drainage and waste management

• Odor, sedimentation

• Ensure that the site is included in the city's operations and maintenance plan and budget

• Planning Operation and maintenance (0 & M)

• Periodic inspection and maintenance of damage incurred during the operation

City Operations and Maintenance Plan

City

City

City

31

Impact:

Mitigation:

Implementation mechanisms:

Fund source:

Monitoring:

Impacts

Mitigation:

Land acquisition and resettlement

Implementation of approved RP in accordance with its provisions

ApprovedRP

PPMU

City

Independent Monitoring Consultant

• Dredged materials and odor generation, health and safety, erosion and landslides, landscape and ecosystem, water way traffic safety, turbidity increase, water quality, prevention of pollutant disperse

• Dredging method + Ngong canal and Bun Xang lake: Sedimemt is dredged by shell scraper. This method is suitable for the project because of limitations of mooring and tidal regime on canals and Bun Xang lake.

+ Canal at south of Bun Xang lake and Sao canal: Sediment is dredged by excavator because of small width and excavators can move easily in narrow areas.

• Before carrying out the dredging plan, must specify the time of construction, construction methods and measures to ensure public, traffic safety and environmental hygiene

• Contract with URENCO for transportation and disposal of dredged materials in an appropriate manner at Cai Sau landfill.

• No dredging in the period from I I am to 13 pm, from 17 to 19 pm. In urgent cases, the dredging from II am to 13 pm, from 17 to 19 pm must be approved by Director of Department of Transport and Public Works.

• Restore the original situation of the area after detecting the risk of waste, and spreading sludge of the areas or after completion of works identified at the temporary landfill

• Determined route ofthe appropriate disposal

• Install construction barriers/ fences and dangerous warning signs

• Installation of lighting at night • Training workers on safety regulations • In case of problems, stop the construction and implement of necessary measures • Contractors should apply the appropriate measures to avoid the reinforcement of soil

erosion, damage and accidents in the process of digging the soil and exploit the holes they have materials and so on.

• Workers should be trained on how to handle when there are landslides • Contractors shall ensure absolute safety for workers perform excavation and other

common tasks

• The all equipment used for the dredging, embankment must do registration

• Determined route of transported barges

• All workers on the barge must be training, testing and certification

• Streamline traffic for water navigation

• Putting up signal for passing boats in the area

• Practicing workers about working safety and respond to situation when the accident waterway

32

Implementation mechanisms:

Responsibility:

Fund source:

Impacts

Mitigation:

Implementation mechanisms:

Responsibility:

Fund source:

Monitoring:

Impacts

Implementation mechanisms:

Responsibility:

Fund source:

Monitoring:

Operation

Impacts

Mitigation:

Implementation mechanisms:

• Isolate a part of the lake for construction

• Good management of waste

Contract conditions, specifications, and the ECOPs and the DMMP

Contractor/detailed design consultant

IDA Credit

• Odor, sedimentation, and solid waste

• Ensure that household and other wastewater does not enter the canal and lake, but is diverted into the interceptor drains that will be installed along both sides of the channel during rehabilitation

• Ensure that the canal and lake are kept free of silt deposits and other blockages, to minimize flooding risk

City Operations and Maintenance Plan

City Drainage Company

City

City

None significant

Contract conditions, specifications, supplementing those of the ECOPs

Contractor/detailed design consultant

IDA Credit

Supervision ConsultantlPPMU

• Noise, odor, solid waste and flooding

• Periodically maintain machinery and transport means (6 months/time foe new equipment or every 3 months for older devices)

• Equipped workers with labor protection facilities such as helmet or ear cover when using these devices cause noise such as foundation drilling

• Environmental education for workers

• Noise monitoring during construction

• Determining the location of construction waste dumps with the consent of the receiving local governments

• Sludge will be taken to dumps sludge disposal in the city

• Maintain buffer zones and green belts around the WWTP

• Planning Operation and Maintenance (O&M)

• Operating procedures shall be implemented under the current regulations about infrastructure (water supply and drainage, electricity, roads and other public works)

City Operations and Maintenance Plan

Responsibility:

Fund source:

Monitoring:

Impacts

Mitigation:

Implementation mechanisms:

Responsibility:

Fund source:

Monitoring:

City Drainage Company

City

City

• Surface water and groundwater quality, sludge generation, solid waste management

• Leaks on drainage system must be detected and corrected promptly

• Surface water monitoring periodically in the outlet sites

• Place signs in the outlet sites

• Provide a monitoring information for authorities and local people

• Maintain buffer zones and green belts around the WWTP

• Regularly dredge sewers and manhole and drainage to prevent sludge deposit and cause unpleasant smells toxic gases

• Open the lid of a manhole or ventilation time before dredging • Provide safety equipments and proper tools and protective clothing as well as ensuring

the application of safety measures for construction

• Specialized vehicles used to suck mud and transported to disposal sites to handle

• Using EM preparations with the do safe of 10 ml EMf OIL water for IOOkg waste (sludge)

• A void prolonged dredging sludge

• Periodically dredged to prevent clogged drainage systems

• Periodically check the status of the drainage system

• Do not throw garbage into drains

• Determining the location of construction waste dumps with the consent of the receiving local governments

• Sludge will be taken to dumps sludge disposal in the city

• Periodically dredged to prevent clogged drainage systems • Periodically check the status of the drainage system • Do not throw garbage into drains • Classification of solid waste before processing disposal

• Propaganda and raising awareness to environment for local people

City Operations and Maintenance Plan

City Drainage Company

City

City

34

Mitigation:

I Implementation i mechanisms:

Responsibility:

Fund source:

Monitoring:

• Before starting construction, construction management plan and traffic management plans in the construction sites will be informed to local authorities and communities in order to request their cooperation and discuss with them to fmd out the feasible traffic management plans, especially on main transportation routes, high traffic density or more activities of production and business or religious activities, e.g. roads in Le Binh ward.

• Establish temporary paths for residential and business households; avoid traffic on main roads at rush hour if possible; the temporary paths must be determined before construction and upgrading when needed.

• All roads must be restored like the old status as soon as possible. During and after construction, contractors must clean and wash surface roads and alleys, sidewalks, roadsides to ensure traffic safety and sanitation of roads.

• All constructing vehicles used for the project must be clearly stated (e.g. paste the project logo and the project relative information) or registered. If any vehicle does not comply, the project staffs or communities can detect and report to managers.

• Install protective fences or warning signals, lighting to ensure safety for traffic vehicles in the construction site. The separation and physical signs must have reflective strips or maintain a signal light system that help pedestrians and vehicles can easily recognize and avoid the working sites.

• Must maintain barriers/ protective fence at least at 1.5 m high, which defme the boundary of working sites and not allow anyone to encroach and ensure traffic order in residential areas.

• Respect lanes reserved for traffic, plan routes for construction vehicles to avoid traffic congestion, prohibit contractors parking motor vehicles encroaching roads, especially in small and high traffic areas.

• Traffic-separating subjects should be used appropriately during peak hours; separate clearly lanes for cars and motorcycle, bicycle, walkers; promote separation of one­way when necessary.

• Request the assistance of traffic polices, the direct local authorities to solve problems and risks (e.g. accident, congestion)

• Consult and disseminate information to all business and enterprises to early alarm and help them to have active plans to reduce impacts (e.g. adjust goods transport time, working time, travel route, transportation means), typically for large businesses on Cach Mang Thang 8 street, extended Nguyen Van Cu street and National Highway No.91B.

• Disseminate the construction plans to local authorities, management officers of sensitive areas (e.g. kindergartens, schools, hospitals, pagodas, churches, clinics) to allocate and separate traffic reasonably.

• Arrange the constructing time reasonably to avoid the rush hours and quickly complete in one working area.

• Contract conditions, specifications, and the ECOPs

• Contractor/detailed design consultant

• IDA Credit

• Supervision ConsultantIPPMU

35

Mitigation:

Implementation mechanisms:

Responsibility:

Fund source:

Monitoring:

• As set out in the ECOPs

• Invite managers of cultural, entertainment, religious facilities to attend the presentation on construction plans and mitigation measures of contractors to offer specific information and unify on the plans.

• Disseminate information of plans, time schedule and scopes of contractors to local residents such as construction site boundaries and operation time of equipments.

• A void constructing at time when cultural and religious activities happen.

• Local authorities after be informed on activities of contractors will actively coordinate with the PPMU, the contract management and construction supervision consultants, local organizations to co-manage, supervise and control mitigation measures as well as to support security for the construction area, to avoid disorder and affect on sensitive areas.

• Establish hot lines, online to the PPMU.

• Apply mitigation measures ECOPs:

+ Avoid construction activities at sensitive times (e.g. festival days, lunar days, ... )

+ Avoid construction activities from 18 p.m to 20 p.m at the pagoda (every month on 1st and 15th in lunar)

+ A void construction activities from 15.30 p.m to 18 p.m at the church

+ Collecting sand stone, digging material scattered in sensitive sites

+ Notice the construction plan for the Catholic Priest/Superior monk, and Principal at school

+ Areas of stored material shall be far at the sensitive sites about 200m

+ Avoid construction activities during rush hour at the school, kindergarten: In the morning: 6 a.m 7.30 am; In the afternoon: 16 p.m - 18p.m

+ Frequently watering at the school, kindergartner

+ Successive construction method

• Contract conditions, specifications, and the ECOPs

• Contractor/detailed design consultant

• IDA Credit

• Supervision ConsultantIPPMU

5.1.2 Management of Impacts on Physical Cultural Resources

Based on the EIA study and the preparation of the RP, non sensitive works, temples, historical sites, graves and natural conservation areas are affected by land acquisition.

These specific procedures are to be followed in case of archeological, cultural or similar finds of artifacts or relics. The diagram below identifies the detailed steps to be taken. The PPMU

36

will be responsible for the overall coordination and reporting. The chance find procedures will be included in all construction contracts and key staff and contractors will be trained on how to implement them.

during project construction install the protection fence, [

Archeological ~ifacts found H' Te~-por-ar-ily-st-op-~-o-ns-tru-~tion, and

(Contractor and CSC) , I immediately contact the PPMU _________ ~ _ ___JI .--- _...1

All parties record the scene (in the form proposed by CSC)

PPMU report in writing to

[

Implement next steps under guidance of DCIT i+----i Department of Culture,

---------------------~ Tourism (DCIT)

Figure 2: Chance-fmds procedure to follow in case of archeological artifacts found during the project construction

5.2. Environment monitoring program

The Environmental Monitoring Program is a key element of the EMP. Its main objective is to check and ensure that (a) the potential negative impacts of the project are minimized; (b) the EMP is effectively implemented; and (c) the EMP is adequate to mitigate the potential negative impacts. Given that monitoring the implementation of the RP will be conducted separately, the environmental monitoring program will comprise (a) monitoring the safeguards performance of the contractors during site clearance and construction, (b) environmental quality monitoring, (c) monitoring the effectiveness of the EMP.

It is essential to design the monitoring program - in conjunction with the selected monitoring locations, parameters and frequencies - in such a manner to be able to record both, the overall performance of the project works as well as the short-term impacts due to construction activities. The environmental monitoring program will be implemented during construction at three levels:

• Monitoring the level of compliance with mitigation measures, • Monitoring the environmental,parameters set out in the EIAs for each of the works,

and • Community-based monitoring.

Monitoring of Contractor's Safeguard Performance

Three levels of environmental safeguards monitoring will be implemented as follows:

- Routine monitoring: This will be done by the Construction Supervision Consultant (CSC) as assigned by the PPMUs. The CSC will include the environmental monitoring results in the monthly project progress reports.

- Periodic monitoring: This will be done every six months as part of the overall monitoring of the EMP implementation. The environmental and social unit (ESU) of the PPMUs, assisted by the Independent Environmental Monitoring Consultant

37

(IEMC) will also monitor the contractor performance every xis months and the results will be reported to the PPMUs and the WB.

- Community monitoring: Monitoring by local communities will be conducted following Government practices, with technical and management support from the PPMU.

To ensure an acceptable level of environmental quality, monitoring of dust, noise, vibration, air quality, and water quality will be .made at project-specific locations that are likely to be most affected by the construction activities. Specific monitoring locations may also be requested by local authorities and/or communities for specific purposes. ESU/IEMC will have overall responsibility for the monitoring program.

The following are the key issues, citeria and scope of monitoring that will be taken into account in the implementation of the monitoring program:

- General Construction Impacts: local flooding; traffic congestion and/or disruption, especially in residential areas; air quality, and noise and dust levels in residential areas; surface water quality upstream and downstream of construction sites, with specific attention paid to impacts on local residents;

- Implementation of site-specific EMPs that require specific monitoring activities that are not covered by the ECOPs nor by the Vietnamese lregulations, standards and codes. Such monitoring activities will be as agreed with local agencies and communities during the preparation of the EMP and monitoring program.

- Implementation of Dredged M.aterials Management Plan (DMMP): for all sludge and similar material excavated from the project work sites that exceeds the national thresholds for toxic substances, a site-specific DMMP will be used. Amounts, levels of heavy metals, if any, locations and activities at disposal sites, and impacts on local residents will be monitored, based on a water quality monitoring plan with specific stations and parameters for monitoring impacts on other water users.

- Monitoring the Effectiveness of the EMP: The ESU assisted by IEMC will monitor the overall performance of the EMP implementation during the detailed designlbidding stage as well as during construction and the first year operation of the facilities to ensure that (a) appropriate dredging and disposal of drainage sludge is properly carried out, in accordance with the DMMP, (b) other impacts identified in the EMP are effectively managed and mitigated; (c) traffic management is adequate and the levels of impacts are acceptable, i.e. there are no new complaints nor any outstanding cases, and (d) all typical general impacts are mitigated in accordance with the ECOPs. Results are to be kept in the project file for possible review by PPMU and the WB. Cost for the monitoring will be part of the PPMU cost.

The following tables outline the parameters for the part of the monitoring program that is performed by sampling and testing air, soil I sediment, and water quality, and also measures noise levels and any other pertinent ambient parameters, if needed. Its estimated cost considering that some activities will be carried out (i) before construction (project baseline environmental conditions), (ii) during construction (assumed to take five years), and (iii) during the first year of operation. Detailed monitoring programs will be prepared during the detailed design stage. The estimated cost for monitoring forms part of the EMP costs; the costs for sampling and laboratory testing will be included in the CSCs' contracts. Many of the parameters listed below are required by Vietnamese regulations and would need to be done even if they are not directly related to expected project impacts.

No.

Table 7: Scope of environmental monitoring during construction

Item Pre-construction

1. Parameter

---'''''-"-'''---,, """""""""""''''''''''-'''--

2. Frequency

3. Monitoring position

----""""'",, .. ,-, .. ,'''''

------"""""""-,-"""----

4. Applied standard

------''''''''----Construction phase

All mitigation measures at construction site

Every month ----

At all construction sites

According to EMP document

Operation phase

1. Parameter TSP, CO, NOz• SOz, HC, Noise and Vibration

2. Frequency

Component I o I time before construction

---, .. -"--'" ,-----Component 2

Component 3

3. Monitoring position

3.1 Component 1

01 time before construction

15 samples:

1 point: Hoa Thanh, Thoi Hoa Ward

I point: area 13, Chau Van Liem Ward

I point: 0 Mon Market

1 point: Opposite with 0 Mon district's Martyrs cemetery

1 point: Chau Van Liem Park

I point: Area 5, Chau Van Liem Ward, adjacent NhumCanal

point: Binh Thuy Communal House

1 point: Opposite Rach Suc rivulet mouth

1 point: Behind the 9 Military Zone Stadium

I point: Pha Le Coffee shop, adjacent National Road No.1

1 point: Ba Le Bridge, Tam Vu Str.

03 months/time

06 months/time during the fIrst year of operation

06 months/time during the fIrst year of operation

---"'-,-""'--", .. ,,'--""----""---

NONE 5 samples:

I point: area 13, Chau Van Liem Ward

I point: Chau Van Liem Park

I point: 1 alley, 918 street, Binh Thuy ward

I point in 287 alley, Tran Quang Dieu street, An Thoi ward

I point: Intersection of Vo Truong Toan Str. and Nguyen Van Cu Str.

,-----,,-,-,,-'''------ --------"----

39

No. Item

._-_ ......... _ .. _ .... _--,-,_ ... __ .. _ .. _,

Pre-construction

point: Dau Sau Hang Bang Str., adjacent National Road No.1

I point: An Binh Ward (Adjacent Area I & 2)

1 point: T-junction of Cong Ba Cai Str. and Truong Chinh Tri Str.

1 point: End of Nguyen Viet Dung Str, adjacent Can Tho River

Construction phase Operation phase

----,-,_ ...... _ .... -_ .. _ .... __ ...... _ .. _ .. -.. _ .. _,----_._,--- -,-_ .. _ .. "' .... _-_ .... , .... _----,-,-,--_.

3.2 Component 2 6 samples:

1 point: Intersection ofVo Truong Toan Str. and Nguyen Van Cu Str.

1 point: Xuan Khanh Market

1 point: In Alley 51, opposite with Aquacultural Faculty, Can Tho Unv.

point: Alley 51, with

Faculty, opposite Environmental Can Tho Unv.

1 point: Intersection of Tran Hung Dao Str. and Nguyen Trai Str.

1 point: Hau Thanh My Road

6 samples: Bun xang Lake, Tran Hung Dao street

3 samples:

1 point: In Alley 51, opposite with Aquacultural Faculty, Can Tho Unv.

point: Pumping station in Bun Xang Lake

1 point: Intersection of Tran Hung Dao Str. and Nguyen Trai Str.

----,----,-----------,_ .. _-------,---------3.3 Component 3 1 sample: 3 sample:

1 point: Binh Pho B, 3 points in Long Tuyen adjacent Ba Bo Canal resettlement area

1 sample:

1 point: Long Tuyen resettlement area

,_ .. ,--_ ... ,_ ........ __ .. _,---_. 4. Applied standard

1. Parameter

QCVN 05:2009IBTNMT, QCVN 26:2010IBTNMT;

QCVN 27:20l0IBTNMT; World Bank Environmental, Health and Safety Guidelines.

pH, temperature, TSS, N-NI-l4, N- NO)- T-P, BODs, COD, DO, oil & grease, Coliform,

--- ----, .. _-----"'--------.... __ ._---------------' .. _---,-2. Frequency ---_ ... _ .. _-_ .. , ......... _----,--,_ .. '-----_ .. __ .. _ .. _--_._--Component 1 o I time before construction - 06 months/time during

the fIrst year of operation

----------, -,---_ .. __ .. _---------------,------, Component 2 01 time before construction 03 months/time

Component 3

06 months/time during the fIrst year of operation

----, .. ------,-----_ .. , .... _---,--------3. Monitoring position --_ ..... _,-,-, .. _, .. _--------------

40

----.---~-.-.... --"""" .. --." .. ----...... -.... -.--... -... _--_._----_ ... "._._.,,-_ ... _ .... - ... _----_._---_ .. _-_ .. -No. Item Pre-construction Construction phase Operation phase

3.1 Component 1 17 samples: NONE 5 samples:

3.2 Component 2

2 points: 0 Mon river

1 point: Nhum canal

1 point: Ba Rich canal

5 points: Binh Thuy river

2 points: Sao canal

1 point: Muong Dat canal

1 point: Dau Sau canal

5points: Can Tho river.

13 samples:

2 points: 0 Mon river

1 point: Can Tho river

2 points: Bun Xang Lake

2 points: Ngong canal

2 points: Sao canal,

2 points: South canal Bun Xang Lake

1 point: Ba Lang river

1 point: Cai Rang river

7 samples:

2 point: Can Tho river

2 point: Bun Xang Lake

1 point: Ngong Lake

1 point: Sao Lake

of I point: South canal of XangLake

2 points: 0 Mon river

2 points: Binh Thuy river

1 point: Dau Sau canal

3 samples:

1 point: Bun Xang Lake

2 points: Can Tho river

3.3 Component 3 I samples: NONE NONE

4. Applied standard

1. Parameter

1 point: Muong Khai canal

QCVN 08;2008-BTNMT; World Bank Environmental, Health and Safety Guidelines.

pH, Hardness, TSS, COD, cr, As, Fe, Mn, E-coli -_ .. "._-_ .... _ ......... _ .. __ ... _._--_._--_ .. _---_ ... _._ ...... _"._"._-_._._-_."----"".""-,,_._--,,,,_._,,.-

2. Frequency

Component 1

Component 2

Component 3

01 time before construction 03 months/time

01 time before construction

01 time before construction 03 months/time

06 months/time

06 months/time during the fIrst year of operation

06 months/time during the fIrst year of operation ------"._"._---_._"._. ------"._----"._-----"-"""_._"""-,,-,, .. __ ._-----

3. Monitoring position --------------,,--_ .. -._,,_._-----3.1 Component 1 20 samples:

1 point: Lia 3, Chau Van Liem Ward

1 point: Lia 4, Chau Van Liem Ward

1 point: Lia 1, Thoi Hoa Ward

I point: Lia 5, Chau Van Liem Ward

NONE NONE

____ . __ " .... _l_E.<>.int: Lia 2, Chau yan ___ . ---""."--" .. _--_.,,,,"-,,----,,---

41

No. Item Pre-construction

Liem Ward

1 point: Lia 1, Thoi Hoa Ward

1 point: Alley 287, An Thoi Ward

1 point: Alley 412, Bui Huy Nghia Ward

1 point: Xom Moi, Binh ThuyWard

1 point: Alley 7, Binh Thuy Ward

1 point: Lia 22, An Binh Ward

1 point: Lia 22, An Binh Ward

1 point: Alley 216, Hung Loi Ward

1 point: Alley 132, Hung Loi Ward

1 point: Alley 51, Xuan Khanh Ward

1 point: Alley 314, An Hoa Ward

1 point: Alley 35, Thoi Hoa Ward

1 point: Alley 30, Le Binh Ward

1 point: Lia 31, Le Binh Ward

1 point: Lia 30, Le Binh Ward

Construction phase Operation phase

--_._-_._-_._-------_._ .. __ ... _----_._ .. _-_._--_._----_ .. _. __ .. __ .. _----_ ... _ .. _._----3.2 Component 2 5 samples: NONE NONE

3.3 Component 3

1 point: Lia 1, Thoi Hoa Ward

1 point: Mau Than Str., Xuan Khanh Ward

1 point: Bun Xang Lake, An Khanh Ward

1 point: Nguyen Trai Str., Le Binh Ward

1 point: Hau Thanh My Road, Le Binh Ward

........... __ ._-_._ .. _-------1 sample: Long Tuyen Resettlement Area

---_._ ... _._-_ .. _-----1 sample: Long Tuyen Resettlement Area

1 sample: Long Tuyen Resettlement Area

----_._-....... _---_._-_ ...... _ ...... _----... _ ... _._----~--.. --.------.---... . .......... _-_ ...... . 4. Applied standard

1. Parameter

QCVN 09;2008-BTNMT; World Bank Environmental, Health and Safety Guidelines.

pH, TSS, BODs, TDS, N-N}4, N-N03' P04, Coliforms

----...... _ ..... _------ . __ ._--_ ...... __ ... ----_ .. __ .... _---------------_._---

42

No. Item Pre-construction Construction phase

2. Frequency

Component 1 01 time before construction

._--_ ............. __ .. _ ......... _--Component 2

Component 3

01 time before construction 03 months/time

.---.... ---~ .... --................ ---.. --..................... _ .. _-........... .

3. Monitoring position

Operation phase

06 months/time during the frrst year of operation

06 months/time during the first year of operation

-_ ...................... _-- ................. __ .......... _---_._ ....................... --_ ......................... _ .... --_ ... -_._ .. _ .......................... _._--_ .................. -3.1 Component 1 25 samples:

I point: Lia I, Thoi Hoa Ward

1 point: Lia 3, Chau Van Liem Ward

1 point: Lia 4, Chau Van Liem Ward

I point: Lia I, Thoi Hoa Ward

1 point: Lia 5, Chau Van Liem Ward

1 point: Lia 5, Chau Van Liem Ward

1 point: Alley 7, Binh Thuy Ward

1 point: Alley 6, Binh Thuy Ward

1 point: Xom Moi, Binh Thuy Ward

1 point: Alley 10, Binh Thuy Ward

I point: Alley i87, An Thoi Ward

1 point: Alley 517, An Thoi Ward

1 point: Alley 506/6, Bui Huu NghiaWard

1 point: Alley 412, Bui Huy NghiaWard

1 point: Lia 2, An Binh Ward

1 point: Lia 22, An Binh Ward

1 point: Alley 216, Hung Loi Ward

1 point: Alley 132, Hung Loi Ward

1 point: Alley 51, Xuan Khanh Ward

1 point: Alley 134, An Hoa Ward

1 point: Alley 35, Thoi Hoa Ward

1 point: Lia 29, Le Binh Ward

I point: Alley 30, Le Binh Ward

I point: Lia31,Le Binh Ward .---.. --.......

NONE NONE

43

No. Item Pre-construction

] point: Lia 30, Le Binh Ward

3.2 Component 2 4 samples:

3.3 Component 3

1 point: Lia 1, Thoi Hoa Ward

1 point: Alley 51, Xuan Khanh Ward

1 point: Mau Than Stro, Xuan KhanhWard

1 point: Nguyen Trai Stro, Le Binh Ward

1 sample: Long Tuyen Resettlement Area

Construction phase

NONE

I sample: Long Tuyen Resettlement Area

Operation phase

NONE

I sample: Long Tuyen Resettlement Area

4. Applied standard

QCVN14:2OO81BTNMT;World Bank Environmental, Health and Safety Guidelines.

1. Parameter pH,As,Cd,Cu, Pb, Zn

2. Frequency

Component I o I time before construction

Component 2

Component 3

o I time before construction 03 months/time

3. Monitoring position

3.1 Component I 11 samples: °

3.2 Component 2

I point: 0 Mon River

2 points: Binh Thuy

3 points: Mieu canal

I point: Can Tho river

I point: Dau Sau canal

3 points: Ranb canal

22 samples:

I point: 0 Mon River

1 point: Can Tho river

8 points: Bun Xang Lake

4 points: Ngong canal

4 points: Sao canal

3 points: South canal of Bun Xang Lake

1 points: Ba Lang river ----__ 0 ___ 0_-0 __ -

3.3 Component 3 1 sample:

1 point: Muong Khai canal

NONE

4 samples:

2 points: Bun Xang Lake

I point: Ngong canal

I point: Sao canal

NONE

06 months/time during the flrst year of operation

06 months/time during the flrst year of operation

___ 0_'" ____ _

5 samples:

I point Bun Xang Lake

I point: Ngong canal

I point: Sao canal

I point: South canal of Bun Xang Lake

1 point: Can Tho river

NONE

4. Applied standard

QCVN 03:2008IBTNMT; QCVN 07:2009IBTNMT; World Bank Environmental, Health and Safety Guidelines.

44

No. Item

1. Parameter

2. Frequency

Component I

Pre-construction Construction phase

Species composition and Species composition number of plant plankton and number of plant cell plankton cell

o I time before construction

Operation phase

Species composition and number of plant plankton cell

06 months/time during the first year of operation

.. -.... -----....... -.-.... ~.-----.............. ---------.. _ .. __ ..... _------._ .. _._._._----Component 2

Component 3

o I time before construction 03 months/time

._._ ... _._ ........ _-_ ..... _-_ .... _._------_._._._--_.-. __ ._ ... ---- ._--3. Monitoring position

3.1 Component 1 4 samples:

1 point: 0 Mon river

1 point: Binh Thuy river

2 points: Can Tho river

NONE

06 months/time during the first year of operation ---_ ... _ ......... __ ._._-

3 samples:

1 point: 0 Mon river

1 point: Binh Thuy river

1 point: Can Tho river .. _._-------------_ ......... __ .. _ .... _---.. - .......... ----_ ... _._ ... __ ._--_._._ ... _-... ---

3.2 Component 2 5 samples:

1 point: 0 Mon river

1 point: Bun Xang Lake

3 points: Hau river

NONE I samples:

I point: Bun Xang Lake

Table 8: Estimated number of soil, water and air samples and analysis for environmental monitoring during construction

Location of

Total monitoring times

Total AirlNoise samples

Bun 31 Lias Xang

15 2 o

S South canal Roads of Long Tuyen aO

I of Bun Xang Le Binh resettlement Other Total

cana

2 22 _ ...... ____ .. ____ ._ ... _ .. _. __ ••••• _ ""····no •• _""~·_m"" .. ____ .~m __ ""' ____ , ... ,_ ... _·" ... ""'~, ___ ~,,_ .. _. __ .. __ , .. ,_~._ ...... _._.~_ ... __ ....... __ " ........ ,., __ " ..

Total surface water samples

Total wastewater quality samples

Total sludge samples

Total phytoplankton sample

Total time of construction

Air sample (1 time)

17

20

25

11

4

24

0

0

2 2 2

o o

o o o

8 4 4

o o

12 6 6

3 ...... _--_ ... _--, ....... ",-

2

2 o 5 31

o 3 26

2 30

3 o 3 34

o o o 4 9

6 6 12

8 ---,,,"-''''''-, .......... _-

0 0 2 7 Surface water sample (1 time) -~-----,---'""""'""-- ""'"'-"---"-""---,-------,,,-,,'---"",,',,--,,,"---""----"-",,-Ground water sample (1 time) o o o o o o

-"-,,--------,,,," "'"""--"""""",,"'-----"-"',,,,"""--""',,"""-"--"""""-"",,---""----,,',,",,"""

Waste water sample (1 time) o o o o o o

1

1

---"---"'--"""""",,"'"---,,,"'" "'"-,-----,_ .. _--",,',,--- ""--"'"""""'"'--'

Sludge sample (1 time)

Checklist sample (1 time)

o

8

2

2

-------"'''----,,,-"--,,-------, Total monitoring times

Total air samples

Total surface water samples

o

o

o

4 2 2

12 2 2

8 2 2

o o o 4

15

2 2 4

2 2 4 24

2 o o 6 20

Location of Bun Ngong Sao South canal Roads of Long Tuyen

Construction 31 Lias Xang

Canal canal of Bun Xang Le Binh resettlement Other Total

Lake lake Ward area

Total ground 0 0 0 0 0 0 4 4

water samples ---.. "" .... _".""""""." ... """"------_._--,,._-- ""------"." .... _-------------Total wastewater samples

o o o o o o 4 4

.""-"."."" ... _-"""""."""""""--,,.,,.,,"--""",,._--_ .... _,,-""""" •... _ ... _""""-",, """"""" ... _."""""""._---"-"._"."".""---"",,,,

Total sludge samples

Checklist! Auditing (01 time/month)

Total monitoring times

o

192

2

8 2 .

24 6

2 2

2 o o o 12

6 6 6 12 252

2 2 2 2 --"-""--"" ..... """". __ ._-_.""._-"-_."""""---"".,,,,._.,,,,.--".,,"-- ---"-". __ .""--,,,, ..... ,,--

Total air samples 10 2 o o o 2 2 2 18 --_ .... _""._""-----."---"",,._-"""""""""""--"""""""-""""""--"."""._--""""-_ ... _---""."."""""._.""",,,,

Total surface water samples 10 2 o o o o o 4 16

._-_._---"""--"""".-------"""".""-"-""--"._""",,,,.,,,,.,,-""""""''''''-'''''---'---

Total ground water samples o o o o o o 2 2

-----"'"-"""""._."""'"".-.... """._--"--._._--"""""",,,,,, ... _--"""_ ... _-"'---"._--,,,,-._----Total wastewater samples

Total sludge samples

o

o

o

2

o o

2 2

o o 2 2 --------_._--"""

2 o 0 2 10 -"._--_. __ ._"._"."--""'''".,,-'''',,-,,-_._-'''',,._.,,''--'''''''''''''''""",,.,,"""-----

Total phytopplankton samples

6 2 o o o o 0 o 8

Table 9: Estimated cost for samples collection and analysis

No Content Unit

AirlNoise Sample

2 Surface water Sample

(Exchange rate: 1 USD = 20.500 VND)

Quantity Price (VND) Total (VND) Total USD)

22

31

1,900,000

1,130,000

41,800,000 2,039.02

35,030,000 1,708.78 --'''--'''''-'''''''''''''''-'''''''''''''-''''''--''''''''-'''''''''''''''-'''''''''''''''' .... _"". __ ... _""""""."._-"""""""""""""_.""",,",,.""-""-,,.,,-,,.--"--""._,,._-_.

3

4

Ground water

Waste water

Sample

Sample

26

30

880,000

640,000

22,880,000

19,200,000

1,116.10

936.59 ---_.-"""""""""._._".,,""--"",,.,,_.,,. --_.""."-_."-----_. __ ."""",,--,,._-.,,-,,,,----"'-

5 Sludge "''''''-'''''''''-'''' ----

6 Phytoplankton

AirlNoise

Sample

Sample

Sample

34

9

24

670,000

600,000

1,900,000

22,780,000 1,111.22 ------

5,400,000 263.41

45,600,000 926.83 "._-"--".""._--""."'''----_."._"--"._--"._.",,.,,. ---''''''''''''''--''''''''''''''''

47

No Content Unit Quantity Price (VND) Total (VND) Total USD)

2 Surface water Sample 20 1,130,000 22,600,000 1,102.44 -- ... " ... _ .... _ ..... _ ....... __ ._ .. _ ...... _ .. _ ......... _ ... --~ ......... - .... - ....... -..... ---.-.---. 3 Ground water Sample 4 880,000 3,520,000 171.71

.. -_ .. -. __ ._--_._. __ ...... _--_ ..... _ ....... __ .......... _ .. __ ._ .. __ .... _ ........ _---_ ................ - ...... -_.-.. _._-_ ..... - .. _ ....... _ ... _ ............ _ ..... -_ ........... -. __ ...... __ ....... -4 Waste water Sample 4 640,000 2,560,000 124.88

5 Sludge Sample 12 670,000 8,040,000 392.20 -_ .. _ ..... -_._._-_ .. __ ... __ . 6 Checklist! Auditing Sample 252 120,000 30,240,000 1,475.12

AirlNoise Sample 18 1,900,000 34,200,000 1,668.29 --_ .... _-_. __ .. _. __ ...... __ ... _ ........ _-_ .. _ ... __ ... -_._._ .. _---_. 2

3

4

5

6

Surface water

Ground water

Waste water

Sludge

Phytoplankton

Sample

Sample

Sample

Sample

16

2

2

10

1,130,000

880,000

640,000

670,000 ---_. ""---'-'-

Sample 8 600,000

18,080,000

1,760,000

1,280,000

6,700,000

4,800,000

881.95

85.85

62.44

326.83

234.15 ---_._-._ .. _--- ..... __ . __ ... __ ._ .. _"._._ ... _ .. _-.. _" .. _-_ .. __ ._-Total 299,870,000 14,627,8

Total cost (after being rounded·up) 15,000

Table 10: Basic cost for chemical analyses· (Exchange rate: 1 usn = 21,000 VND)

2

3

4

5

No. Sample

TSP

Price

(VND)

300,000

Quantity

(Sample)

Total Total

(VND) (USD)

50 15,000,000 731.71 --_._._._".,,--_ .. _. __ ... ,,-_. __ ._---_._--_._--_ .. _- ._--,,--CO 300,000 50 15,000,000 731.71

.. -,---... ,,-~---'" "-".~----,,--,, -,,-----N02 300,000 50 15,000,000 731.71

".-.. -~"'-... ---. ""-,----- '.',_ .. _ .......... ---S02 300,000 50 15,000,000 731.71

HC 600,000 50 30,000,000 1,463.41 --_ .. _--_._----_ .. -._-_ .. _ .. _--_ ........... _--"."._ ...... "" ... ----_."."-"""""_._--,,,, .. _._-_. 6

2

3

4

5

Noise and Vibration 100,000 50 5,000,000 243.90

Temperature 20,000 67 1,340,000 65.37 ----"---_._---_._"-_._--_ ... _,,,,_. __ . __ ._._,,._-_ .. _-,,-----_.-pH

DO

TSS

40,000 67 2,680,000 "---"-,,,,_._-,,--,,-,,._,,-_._-_.-._._._--._._---_.

130.73

228.78 '''-''-'--'--''---'

70,000

70,000

80,000

67 4,690,000 ----"._--,,,,,--._._--_.-._._-

67 4,690,000 228.78

67 5,360,000 261.46 ---"._---"-------_._",,._------ ---''''''''-''---''''---'''''--'''''-''''''-'''''---''-

6 70,000 67 4,690,000 228.78 -----_._._,,---,,-_._---_._---

1 for the environmental monitoring program during the construction phase and the fIrst-year of the operation phase

48

No. Sample

7 Total Photphogen

8 BODs

9 COD

10 OiVGrease

11 Coliform

1 pH

2 Hardness

3 TSS - .. _-..... ---_ .... " ...... "_.,,._--

4

5

COD

CI

Price

(VND)

70,000

120,000

120,000

350,000

120,000

40,000

80,000

70,000

120,000

90,000

Quantity

(Sample)

67

67

67

67

67

32

32

32

32

32

Total

(VND)

4,690,000

8,040,000

8,040,000

23,450,000

8,040,000

1,280,000

2,560,000

2,240,000

3,840,000

2,880,000

Total

(USD)

228.78

392.20

392.20

1,143.90

392.20

62.44

124.88

109.27

187.32

140.49 -_ .. __ ._._._-_ ... __ ... "" ...... _ .... __ ._ ... __ ............... ----_ .... ------_._-"._ .... " ..... _",,-,,-6 As 120,000 32 3,840,000 187.32

7 Fe 120,000 32 3,840,000 187.32 -". __ ._"--_._"._"--" .. " .. " .... _"_ ...... _---,,,,,, ....... _--_ ... __ .-" .... _-""--"-,, ............. ..

Mn 120,000 32 3,840,000 187.32 8

9 "" ... """"._-"." ... ". ""---" .. """"---_._-----"_ ... -_."--"" ... ,, .. ,,,, ....... _-_.

E-Coli 120,000 32 3,840,000 187.32

40,000 36 1,440,000 70.24 pH

TSS

___ .M· .. __ ·M···"" ____ .. __ ... _.~. __ . __

2 36 ---_ .... _ .. _ ........... _--_._--- 70,000

120,000 3 BODs 36 ..... -.--.---. -.-.-~-

4 TDS 70,000 36 "._ ... " ... _ .. " .... -..... _-- ---.. ~-.---.-.. -,

5 N-~ 80,000 36

2,520,000 122.93

4,320,000 210.73

2,520,000 122.93

2,880,000 140.49 -_..... .. ......... _" .. ""._-- .----..... - .. " ..... ----~ ....... - ..... - ....... "" .... ""-...... - .. --

6 70,000 36

7 70,000 36

8 E-Coli 120,000 36

pH 40,000 56 '''--..--'--- ._._"-"""'-,, ..

2 Cu 120,000 56 ",,"'._-_.

3 Pb 120,000 56

4 Cd 120,000 56

5 Hg 150,000 56 ..... __ ._,,---_.,,----,,---""-_._---"_. __ ._'''-.......

6 Zn

Species composition and number of plant plankton cell

120,000 56

600,000 17

2,520,000

2,520,000

4,320,000

2,240,000

6,720,000

6,720,000

6,720,000

8,400,000

6,720,000

10,200,000

----.--" .... " ........ -.--...... "" ...... --~.-,,-.. ---.. --.. -------

122.93

122.93

210.73

109.27 M'n~_'M'M ___

327.80

327.80

327.80

409.76 " ... -"'"---.~--

327.80

497.56

49

No. Sample

All mitigation measures at construction site

Price

(VND)

120,000

Quantity

(Sample)

252

5.3. Role and Responsibilities for EMP Implementation

5.3.1 Organization Arrangement

Total Total

(VND) (USD)

30,240,000 1,475.12

The Project Management Unit (PMU-MOC) in the Ministry of Construction (MoC) will be responsible for the overall consolidated monitoring and quality assurance of the Project. While Cities are responsible for EMP implementation, the PMU-MOC will have a quality assurance and monitoring role including all safeguards aspects. The Cities will submit all safeguards progress and monitoring reports to the PMU-MOC. The MoC will also be responsible for contracting and managing the Independent Environmental Monitoring Consultant (IEMC) who will monitor the environmental performance in all six project cities. The IEMC's costs are therefore part of the MoC budget, and not do not form part of the cities' EMP implementation costs. The figure and subsequent table below summarize the roles and responsibilities of the key parties and their relationships with regard to the implementation of the EMP. The roles and responsibilities of the ESU, PPMUs, CSC, and IEMC are outlined below:

• Contractors have the main responsibility for implementing mitigation measures. Those measures will be included in the bidding documents and the costs are to be included in their bids and the construction contracts.

• CSC is responsible for supervising and monitoring the day-to-day implementation of mitigation measures. The associated costs are included in CSC service contracts.

• IEMC will be responsible for environmental monitoring which includes (i) support to the ESUIPPMU for implementing supervision and monitoring, and (ii) reporting on the implementation through periodic monitoring reports.

50

Figure 3: Organization Diagram for the EMP Implementation

Table 11: Roles and responsibilities of key parties (Description referred to Figure 3)

Links Description of Roles and Responsibilities

la Based on quarterly reports of IEMC, PMU-MOC is responsible for preparing periodic reports to i submit to the WB.

Ib PMU-MOC send a notice to PPMU on working plan of IEMC, receive reports of lEMC and monitoring the implementation of agreed proposals and monitor the sending of the monthly report from the Safety policy officer to the PPMU

Ic PMU-MOC with the assistance of contracted lEMC, provide the guideline to and monitor the implementation ofPPMU's EMP,

(2a) PPMU assigns the safeguard staff (ESU) to review and check the environment-related sections in of the bidding and contract documents for appropriate items, such as the ECOPs, to ensure compliance with EMP

PPMU assigns the safeguards staff (ESU) to supervise, manage and carry out EMP activities and also assigns CSC to closely supervise and monitor safeguard performance of the contractor, including implementing the environmental monitoring program.

PPMUIESU establishes a hotline communication with the local community to be responsive to the complaints, comments, and/or recommendations from local people and the public throughout the site clearance and construction period.

(2b) Based on quarterly reports oflEMC, PPMU is responsible for preparing periodic reports to submit to the Provincial DONRE.

(2c) lEMC contracted by PMU-MOC supports PPMUIESU to implement the EMP in line with Government's environmental regulations as well as the WB safeguard policies. In consultation with DONREs, lEMC will establish a specific environmental monitoring program for the project to be implemented by CSC at key locations as shown in the detailed design documents.

51

(3 a) Contractor: Before construction, with general guideline from IEMC, prepares a site-specific environment management plan (SEMP) during site clearance and construction process as part of their construction method statement, then submit it to CSC and/or PPMU for review and approval; During construction, the contractor has to submit a monthly report on safeguard issues, mitigation, and results throughout the construction period. In case of unexpected problem, the contractor will consult CSCIPPMU.

PPMU/CSC: Reviews the SEMP and can propose change as deemed necessary to be in line with the contractual obligations as well as appropriate to each specific site. Daily supervision and monitoring of contractor's safeguard performance will be responsibility of the CSC.

(3b) CSC submits periodic monitoring reports of environmental mitigation measures to PPMU; recommends to the PPMU to suspend, in part or completely, construction work if it does not meet labor safety or environmental protection requirements of the contract.

PPMU reviews CSC's periodic reports to monitor compliance with mitigation measures.

(3c) Community: According to Vietnamese practice, the community has the right and responsibility to routinely monitor environmental performance during construction to ensure that their rights and safety are adequately protected and that the mitigation measures are effectively implemented by contractors and/or PPMU. In case of unexpected problems, they will report to CSCIPPMU and/or call the hotline.

PPMU: Encourage, support and create good conditions for local community to participate in the environmental supervision and monitoring activities. PPMU/CSC will review and response to the requests and/or recommendations made by community to ensure that the potential negative impacts are adequately mitigated.

(4a) Contractor: Carries out the EMP as required during site clearance and construction, including conduct self-monitoring and submission of report.

IEMC: periodically supervises and monitors the overall project EMP implementation including provision of safeguard training to PPMUIESU staff, community, CSC, and contractors as needed. The training will be designed· to enhance the effectiveness of the EMP implementation and reporting.

(4b) Community: Support and collaborate with IEMC during periodic monitoring and provide inputs to the overall safeguard issues that require attention and/or mitigation.

IEMC: Strengthen local community's capacity and relevant agencies through preparation of relevant documents necessary for monitoring, supervision, and reporting including preparation of a database for the activities.

IEMC: assist PPMU and communities for the implementation of Information-Education­Communication (1EC) activities within Component 4 with regard to environmental hygiene, sanitation, road safety, etc.

(4c) CSC: Supports and colIaborates with IEMC to establish, collect and highlight information about essential environmental parameters in the field, and information for construction implementation.

IEMC: Monitors the implementation of the EMP every 3 months including submission of the field report. Creates database of results from environmental supervision and monitoring and training PPMU in use of such a database:

IEMC: Coordinates with CSC for carrying out the monitoring activities and the preparing the safeguard reports on EMP performance; enhances the capacity of CSC staff through training programs in environmental supervision.

52

I Links Description of Roles and Responsibilities i

Ia Based on quarterly reports of IEMC, PMU-MOC is responsible for preparing periodic reports to submit to the WB.

PMU-MOC send a notice to PPMU on working plan of IEMC, receive reports of IEMC and Ib monitoring the implementation of agreed proposals and monitor the sending of the monthly report

from the Safety policy officer to the PPMU

Ic PMU-MOC with the assistance of contracted IEMC, provide the guideline to and monitor the implementation ofPPMU's EMP,

PPMU assigns the safeguard staff (ESU) to review and check the environment-related sections in of the bidding and contract documents for appropriate items, such as the ECOPs, to ensure compliance with EMP

PPMU assigns the safeguards staff (ESU) to supervise, manage and carry out EMP activities and (2a) also assigns CSC to closely supervise and monitor safeguard performance of the contractor,

including implementing the environmental monitoring program.

PPMUIESU establishes a hotline communication with the local community to be responsive to the complaints, comments, and/or recommendations from local people and the public throughout the site clearance and construction period.

(2b) Based on quarterly reports of IEMC, PPMU is responsible for preparing periodic reports to submit to the Provincial DONRE.

(2c) IEMC contracted by PMU-MOC supports PPMUIESU to implement the EMP in line with Govemment's environmental regulations as well as the WB safeguard policies. In consultation with DONREs, IEMC will establish a specific environmental monitoring program for the project to be implemented by CSC at key locations as shown in the detailed design documents.

(3a) Contractor: Before construction, with general guideline from IEMC, prepares a site-specific environment management plan (SEMP) during site clearance and construction process as part of their construction method statement, then submit it to CSC and/or PPMU for review and approval; During construction, the contractor has to submit a monthly report on safeguard issues, mitigation, and results throughout the construction period. In case of unexpected problem, the contractor will consult CSCIPPMU.

PPMU/CSC; Reviews the SEMP and can propose change as deemed necessary to be in line with the contractual obligations as well as appropriate to each specific site. Daily supervision and monitoring of contractor's safeguard performance will be responsibility of the CSC.

CSC submits periodic monitoring reports of environmental mitigation measures to PPMU;

(3b) recommends to the PPMU to suspend, in part or completely, construction work if it does not meet labor safety or environmental protection requirements of the contract.

PPMU reviews CSC's periodic reports to monitor compliance with mitigation measures.

(3c) Community: According to Vietnamese practice, the community has the right and responsibility to routinely monitor environmental performance during construction to ensure that their rights and safety are adequately protected and that the mitigation measures are effectively implemented by contractors and/or PPMU. In case of unexpected problems, they will report to CSCIPPMU and/or call the hotline.

PPMU: Encourage, support and create good conditions for local community to participate in the environmental supervision and monitoring activities. PPMU/CSC will review and response to the requests and/or recommendations made by community to ensure that the potential negative impacts are adequately mitigated.

(4a) Contractor: Carries out the EMP as required during site clearance and construction, including conduct self-monitoring and submission of report.

IEMC: periodically supervises and monitors the overall project EMP implementation including provision of safeguard training to PPMUIESU staff, community, CSC, and contractors as needed. The training will be designed to enhance the effectiveness of the EMP implementation and reporting.

(4b) Community: Support and collaborate with IEMC during periodic monitoring and provide inputs to the overall safeguard issues that require attention and/or mitigation.

(4c)

IEMC: Strengthen local community's capacity and relevant agencies through preparation of relevant documents necessary for monitoring, supervision, and reporting including preparation of a database for the activities.

IEMC: assist PPMU and communities for the implementation of Information-Education­Communication (lEC) activities within Component 4 with regard to environmental hygiene, sanitation, road safety, etc.

CSC: Supports and collaborates with IEMC to establish, collect and highlight information about essential environmental parameters in the field, and information for construction implementation.

IEMC: Monitors the implementation of the EMP every 3 months including submission of the field report. Creates database of results from environmental supervision and monitoring and training PPMU in use of such a database.

IEMC: Coordinates with CSC for carrying out the monitoring activities and the preparing the safeguard reports on EMP performance; enhances the capacity of CSC staff through training programs in environmental supervision.

5.3.2. Specific Responsibilities ofPMU, CSC, and IEMC

City-level Project Management Units (PPMUs)

1. PPMUs are responsible for implementing the EMP during the detailed design and construction stages. EMP implementation during operation stage is the responsibility of the facilities' operators at the city level. PPMU will set up an Environmental and Social Unit (ESU) to ensure timely and effective implementation of the EMP, including preparation of reports on safeguard compliance as required by Government and WB.

PPMUIESUs are responsible for ensuring that the relevant sections in the bidding and contract documents for all construction works are in compliance with the EMP; this means they contain the requirements of the ECOPs and site-specific EMPs.

PPMUIESUs are responsible for communicating with relevant local, provincial and national departments; and with the agencies responsible for implementing and supervising EMP, especially with the provincial Department of Natural Resources and Environment (DONRE), and with the concerned wards/communes during planning, monitoring, management and operation.

PPMUIESUs will coordinate with community organizations to encourage them to actively participate in the planning, management, and implementation of the project, including monitoring of the contractor's performance.

To ensure effective monitoring and timely implementation of the EMP, PPMUIESUs will hire national environmental consultants to assist them with carrying out and monitoring the EMP implementation. Responsibilities of the Independent Environmental Monitoring Consultant (IEMC) are described further below.

- In the course of supervising and monitoring the contractors' perfonnance, PPMUs will be responsible for: (a) checking project implementation indicators relating to the environment; (b) conducting unscheduled, surprise inspections to ensure that mitigation measures are being implemented as required in construction contract by contractor; (c) reviewing the periodic reports of the construction supervision consultant (CSC) to ensure compliance with mitigation measures and EMPs; and (d) based on the periodic reports by CSC and IEMC, preparation of reports on environmental compliance of subprojects, to be submitted to WB and DONRE (this will be part of the submission of progress report to WB every six months).

PPMUs will coordinate closely with relevant city enterprises for water supply, environmental sanitation, and solid waste collection, to monitor their operation and maintenance activities during project implementation.

Construction Supervision Consultant (CSC)

The CSC is responsible for monitoring the safeguard perfonnance of the contractors during site clearance and construction, including oversight of the self-monitoring to be conducted by contractor. With regard to environmental safeguards, the CSC's main responsibility will include, but not be limited to, the following:

- Assist IEMC to establish, collect and provide infonnation essential environmental indicators, on-site and for the construction works.

- Ensure that all work comply with the approved EMPs, relevant enevironmental standards and codes of practice (ECOPs), as set out in docwnents for environmental impact mitigation and monitoring.

- Monitor the implementation of mitigation measures by the contractors, propose and deploy any necessary supplementary measures in time to improve mitigation measures to fully meet the environmental management and safety requirements of project.

- Prepare action plans and/or propose urgent solutions to cope with environmental problems, emergency situations and damage that occurred during construction

- Recommend to PPMUs to suspend partially or completely construction work if labor safety and environmental protection requirements of the contract are not being complied with.

- Organize regular discussions with relevant parties, agencies and other stakeholders to provide infonnation about implementation plans to increase people's awareness of the need for environmental protection and management during construction process.

Construction Contractor

The construction contractor's responsibilities with respect to all aspects of the works, including the environmental aspects, are set out in the contract docwnents, signed with the PPMU.

Construction contractors are responsible for carrying out environmental impact mitigation measures and for complying with the approved EMP when implementing construction contracts. When preparing the "technical method statement", the contractor will study the project's approved EIA report and propose a construction method that includes environmental mitigation and monitoring measures that are in line with the approved EMP.

55

- Contractor's method statement will be submitted to PPMUs and CSC for review, as well as to IEMC, as deemed necessary. Changes, if any, will be evaluated for their feasibility and for legal issues (laws, decrees, circulars and other regulations) before suitable adjustments are approved for specific cases on-site.

During the construction work, the construction contractors will be closely supervised by PPMUs, CSC, IEMC, environmental authorities and the local community for their compliance with the EMP.

Independent Environmental Monitoring Consultant (IEMC)

The IEMC will be responsible for assisting the PPMU with the EMP implementation. This also includes advising the CSC, contractors and communities on environmental compliance, and on carrying out the monitoring program in accordance with regulations, procedures and policies of the Government and the WB, respectively. After the detailed implementation of the environmental monitoring programs was discussed by the city-level PPMU and World Bank supervision staff, the IEMC will be responsible for quarterly checking, and for supporting the PPMU staff to supervise overall project activities to ensure that uniform environmental policies of the Government and World Bank are applied and supervised during project implementation. The IEMC will be responsible for: (1) providing training and capacity building for construction management PPMUIESU staff, including field engineers and/or consultants (CSC), in supervising the EMP implementation by the contractors; (2) ensuring active participation of the local communities and schools in the project areas, (3) monitoring of environmental parameters to assess the overall impacts of the project, and (4) establish the environmental training program that is part of Component 4.

Specifically, the IEMC's responsibilities include:

- Ensuring that the approved EMP and all other relevant project legal agreements related to environmental safeguards are fully applied and complied with during project implementation.

- Assessing the effectiveness of mitigation measures which are applied by contractors and CSC during project implementation; providing proposals and recommendations to the PPMUs on improvements needed to meet the safeguard requirements.

- Reporting periodically (every 3 months) to the PPMUs on actual EMP performance during project implementation.

- Establishing standard procedures, methods and forms to assist the PPMUs and CSC to assess contractors' progress in implementing the required impact mitigation and monitoring measures.

- Assisting the PPMUs' environmental staff to review and check that relevant environmental sections (based on the ECOPs) have been included in the bid packages and concstruction contract documents to ensure compliance with environmental policies and impact mitigation and monitoring requirements.

- Measuring, taking samples and monitoring periodically the key environmental parameters, i.e. once every 3 months.

- Assistance with the preparation of documents and implementation of training programs in environmental monitoring and supervision for contractors, CSC and relevant staff of the PPMU s (environmental staff and coordinators of contract packages).

Via PPMUs, discussing with relevant enterprises, as necessary, to find suitable solutions for unexpected risks relating to environmental sanitation.

56

7.3.3. Reporting Arrangements

The PPMU will prepare reports twice per year for submission to the World Bank including the compliance with the EMP. The report will contain the monitoring results and assessments of the IEMC that show project progress and the status of implementation of the EMP. The reports will cover, among other matters as appropriate, the following:

- Contractor's compliance with mitigation measures

- Wastewater and environmental sanitation issues

- Existing flooding situation, where relevant

- Traffic congestion or disruption

- Performance of the water supply systems

- Quality of wastewater-receiving water bodies

- Potential project-related risks and risk management issues

- Quality of water in rivers (fien, Hau, 0 Mon and Binh Thuy), canals (Ngong, Sao and canal at the south of Bun Xang lake) and Bun Xang lake

- Status of measures to assist project-affected people at the new resettlement sites on environmental aspects

- Consultation with local communities in key project areas

5.4. Capacity Building Program

5.4.1. Technical Assistance support for the implementation of safeguards

An assessment of safeguards implementation capacity of existing PPMU staff indicates that PPMU staffs have limited knowledge on WB safeguard requirements as well as limited knowledge of environment and social issues. Such lack of capacity represents a risk to project implementation of safeguards requirements contained in the EMP and, as required by the WB policy, is to be addressed through capacity building. Therefore it is proposed to provide capacity building through technical assistance that will support the PMU during the implementation of the safeguards requirements. The technical assistance will provide the necessary technical support the PPMU in its work with contractors as well as other entities involved in the implementation of the EMP.

The scope of the technical assistance would cover support from experts and training that would cover both the knowledge on safeguards requirements and procedures for the project as well as training that covers both specific knowledge on safeguard procedures and requirement for the project staff, consultants, and national contractor would be important. This would include, for example, assistance in the preparation of documents and implementation of training program on environmental management and environmental monitoring for contractors, CSC and relevant staffs of PPMU (environmental staffs and coordinators of packages) to do their tasks. It would also include assisting the PPMU's environmental staffs with the review of contract documents on the bidding packages for construction items of the project to ensure compliance with environmental protection policies and impact mitigation and monitoring requirements as well as provide general environmental guidance as requested by the PPMU to enhance overall project implementation and performance.

Given the nature, locations, and scale of construction, it is anticipated that the safeguard technical assistance support and training will be provided at least during the first 3 years of the project implementation. The WB safeguard specialists will participate in the capacity building in particular in the training activities as appropriate.

5.4.2. Training programs proposed

Table 11 below provides examples of the basic trainings for safeguards during project implementation. The training programs will be developed and delivered by the Technical Assistance team for the implementation of safeguards for the PPMU training. The PPMUIIEMe with the support of the Technical Assistance team for the implementation of safeguards will provide the training to contractors, esc and other groups.

Other more specific and tailored training will be developed and agreed upon between PMU, IEMe and the Technical Assistance team for the implementation of safeguards during project implementation based upon a reassessment of needs and the status of safeguards implementation.

- Target groups for the training: include PPMU staff, ESU staff, field engineers, esc, construction contractors, local authorities and community representatives in the project area. Training of workers and drivers is the responsibility of the contractor.

- Training schedule: At least 1 month before the construction of the first contract. The training can be adjusted in line with the implementation schedule of the subproject/contracts.

- Training frequency: The basic training programs proposed in table 12 will take place every six months on a yearly basis and its content updated and adapted to implementation issues. Training frequency and content will be reassessed during implementation depending on needs. It is foreseen that the training program for PPMU staff will continue until year three of implementation. Three days of training for esc and contractors are also planned to take place twice a year on an annual basis for at least two years.

Table 12: Training programs for capacity building on environmental supervision and management

Target Group PPMUs (preferably to be organized jointly for all six PPMUs)

Course Title Environmental supervision, monitoring and reporting

Participants Environmental staff and technical staff

Training Soon after project effectiveness but at least I month before start of construction of Frequency the first contract. Follow-up training will be scheduled as needed.

Time Four days of training, to be held twice a year, and then to be repeated on a yearly basis until year three of implementation.

Content General environmental management relating to the project, and covering the requirements ofWB, DONRE

General aspects of environmental supervision;

Implementation and supervision of mitigation measures;

Community participation in environmental supervision monitoring.

Guidance and supervision of contractors, CSCs and community representatives in the implementation of environmental supervision.

Use of forms for environmental supervision;

58

Risk response and control;

Receipt and ubmission of reporting forms

Other areas of training needs, as determined

Responsibilities PPMU, IEMC with support of the Technical Assistance team for the implementation of safeguards.

Target Groups CSC, CONTRACTORS, COMMUNESIW ARDS AUTHORITIES, COMMUNITY REPRESENTATIVES

Course Title Implementation of mitigation measures

Participators CSC; on-site construction management staff; environmental staff of contractors; commune/ward/group authorities.

Training After bidding, and determine based on needs frequency

Time 3 days of training for CSC and contractors and 2 days of training for others, to be repeated twice a year on an annual basis depending on needs

Content Overview of environmental monitoring;

Requirements of environmental monitoring;

Role and responsibilities of contractors and CSC

Scope and methods of environmental monitoring;

Response and risk control;

Propagate monitoring forms and guide how to fill in the forms and risk report;

Preparation and submission of reports

Other areas to be determined.

Responsibilities PPMU, IEMC with support of the Technical Assistance team for the implementation of safeguards

Target Groups COMMUNITIES AND WORKERS

Course Title Environmental sanitation and safety

Participators Representatives of community and/or worker leaders (as appropriate)

Training As appropriate frequency

Time One-day presentation and one-day on-the job training twice a year, to be repeated on as needed basis

Content Preliminary presentation on environmental protection and environmental overview

Key issues that require communities' and workers' attention to minimize safety risks (roads, waterways, equipment, machines, open excavations, etc.) as well as reduce pollution (dust, fumes, gases, oiVgrease spills, waste management, etc.)

Management of environmental safety and sanitation on work sites;

Mitigation measures at construction sites;

Safety measures on electricity, mechanical, transportation, air pollution;

Procedures to deal with emergency situations;

Other areas to be determined.

Responsibilities Contractor, PPMU, with support from IEMC

5.5. Estimated EMP Cost

The costs of EMP implementation will comprise (i) cost of implementation of the mitigation measures by the contractors, (ii) costs of supervision by the CSC, (iii) cost for environmental monitoring consultant (IEMC), (iv) costs of monitoring of environmental quality, (v) PPMU

59

safeguard management costs, including technical assistance support for the implementation of safeguards and training. They exclude all resettlement cost and all costs for independent monitoring of the RP and EMDP implementation.

Costs for the implementation of the mitigation measures during construction will be part of the contract costs while the costs for the supervision and monitoring of all construction contractors by the CSC is provided for in the construction supervision contracts. Costs for PPMU operations related to EMP are provided for in the project management budget of the PPMU, including basic safeguards training and allowances for all staff who participate in the monitoring program. After project completion, the cost for environmental monitoring of the constructed facilities will be funded by the cities' operations and maintenance budgets.

The participation of community representatives in EMP implementation is voluntary, and without salary. Hence, to encourage the participation of community members, the cost for materials, equipment used for monitoring and rewards for people who are voted to implement monitoring are taken into account.

The table below shows the sources of funding for the EMP implementation, including the environmental quality monitoring program.

Table 13: Estimated Cost for EMP implementation (million USD) during the project implementa tion

(a) Mitigation during construction

(b) Supervision of safeguards during construction

Source of funds

Part of construction contracts under Components I, 2 and 3 --_._-"._"._"._---Part of CSC contracts costs

under Component 4 "-"."._._-" ... _---_."--,--,---,,,,._-,,'-,,",

(c) Environmental Safeguards Part ofPPMU operational costs unit (ESU) ofPMU under Component 4

",,-------- , , ---_. (d) Environmental quality Included in CSC contracts costs

(e) Independent Environmental Part ofMoC costs Monitoring Consultant (IEMC)

Cost ($US)

14,627.8

"""-_._"--""."-"-""".,,'-"',,._--"",,._,,-'''-,--,-,_._---,,""--_._-"-_._-"---". -----(f) Safeguards capacity building Included in CSC and IEMC program consultants' contracts 20,000

References

1. Assessment of Sources of Air, Water, and Land Pollution - A Guide to Rapid Source Inventory Techniques and their Use in Formulating Environmental Control Strategies - WHO, 1993.

2. Can Tho city's Statistic yearbook, Can Tho Statistic Office 2010

3. Feasibility Study of Can Tho sub-project, 2011

The environmental status report, Department of Natural Resources and Environment, 2009

4. Waste amount discharged daily into canal systems in Can Tho city is 400 ton/day (Source: http://tuoitre.vn/Chinh-tri-xa-hoiIMoi-truong/372692/Can-Tho-Moi-ngay-kenh-rach-hung-tren-400%C2%AOtan­rac.html)

60

ANNEX

ANNEX 1: Environmental Codes of Practice (ECOPs) for Urban Construction Projects

ENVIRONMENTAL - MITIGATION MEASURE VIETNAM SOCIAL ISSUES CODEIREGULA TION;

WB Environmental,

Health and Safety

Guidelines

1. Dust generation • The Contractor is responsible for compliance with all relevant Vietnamese laws, regulations and • QCVN05: standards with respect to ambient air quality. 20091BTNMT: National

• The Contractor shall ensure that the generation of dust is minimized and does not become a nuisance technical regulation on

to local residents. He shall implement a dust control plan to maintain a safe working environment and ambient air quality

minimize disturbances to surrounding residential areas/dwellings. • WB Environmental,

• The Contractor shall implement dust suppression measures (e.g. use water spraying vehicles to water Health and Safety roads, covering of material stockpiles, etc.) as required. Guidelines: Air

• Material loads shall be suitably covered and secured during transport to prevent the scattering of soil, Emissions and sand, materials, or dust. Ambient Air Quality;

• Exposed soil and material stockpiles shall be protected against wind erosion and the location of Construction and stockpiles shall take into consideration the prevailing wind directions and locations of sensitive

Decommissioning receptors.

• Dust masks should be used where dust levels are excessive. •

2. Air pollution • All vehicles must comply with Vietnamese regulations controlling the allowable emission limits of • TCVN 6438-2005: Road exhaust gases. vehicles Maximum

• Vehicles in Vietnam must undergo a regular emissions check and get certified named: "Certificate of permitted emission limits

conformity from inspection of quality, technical safety and environmental protection" following of exhaust gas.

Decision No. 35/2005/QD-BGTVT; • No. 3512005/QD-

• There should be no burning of waste or construction materials, such as bitumen, etc., on site. BGTVT on inspection of quality, technical safety and environmental

61

ENVIRONMENTAL - MITIGATION MEASURE VIETNAM SOCIAL ISSUES CODEfREGULATION;

WB Environmental, Health and Safety

Guidelines

protection;

• QCVN 05:2009IBTNMT: National technical regulation on ambient air quality

• WB Environmental,

Health and Safety

Guidelines: Air

Emissions and Ambient Air Quality;

Construction and

Decommissioning

3. Impacts from noise • The contractor is responsible for compliance with the relevant Vietnamese legislation with respect to • QCVN and vibration noise and vibration. 26:20 1 OIBTNMT:

• All vehicles must have appropriate "Certificate of conformity from inspection of quality, technical National technical

safety and environmental protection" following Decision No. 35/2005IQD-BGTVT; to avoid regulation on noise

exceeding noise emission from poorly maintained machines. • QCVN

• When needed, implement measures to reduce noise to acceptable levels; this should include silencers, 27:2010IBTNMT:

mufflers, acoustically dampened panels or placement of noisy machines in acoustically protected National technical

areas. regulation on vibration

• Avoid, or at least minimize, heavy vehicle traffic (carrying construction materials) or noisy material • WB Environmental,

processing facilities through or near residential areas. Health and Safety

• Plan activities in consultation with local communities so that activities that generate high noise levels Guidelines: Noise

are done during periods of the day that will result in the least disturbance to the public. Management;

Construction and Decommissioning

---.--.-.. -.---.-.. - _ ... __ ._.- - - - _ .. _ .. _ .... _ .. ,- -

62

ENVIRONMENTAL - MITIGA TION MEASURE VIETNAM SOCIAL ISSUES CODEIREGULA TION;

WB Environmental,

Health and Safety

Guidelines

4. Water pollution • The Contractor is responsible for compliance with the relevant Vietnamese legislation relevant to • QCVN wastewater discharges into watercourses. 09:2008IBTNMT:

• Portable or constructed toilets must be provided on site for construction workers. National Technical

• Wastewater from toilets, kitchens, showers, sinks, etc. shall be discharged into a sealed holding tank Standard on underground

for removal from the site or for discharge into the municipal sewerage systems, if any; there should be water Quality

no direct discharges to any waterbody. • QCVN

Wastewater that does not meet the standards set by relevant Vietnam technical standards/regulations 14:2008IBTNMT: •

must be collected in a sealed holding tank and removed from site by licensed waste collectors. National technical regulation on domestic

• Using techniques such as berms ·or flow diversion during construction to limit the ·exposure of wastewater; disturbed sediments to moving water

• QCVN24: • Make appropriate arrangements for collecting, diverting or intercepting wastewater from households 20091BTNMT: National

to ensure minimal discharge or local clogging and flooding. technical regulation on

• Before the start of construction, obtain all necessary wastewater disposal permits/licenses and/or industrial wastewater; finalize all necessary wastewater disposal contracts. • TCVN 7222: 2002:

• At completion of construction works, wastewater collection tanks and septic tanks shall be safely General requirements on disposed or effectively sealed off. centralized wastewater

treatment plant;

• WB Environmental,

Health and Safety

Guidelines:

Wastewater and

Ambient Water

Quality; Construction

and Decommissioning

5. Drainage and • The Contractor shall follow the detailed drainage designs included in the construction plans, intended • TCVN 4447:1987: Earth sedimentation control to prevent storm water from causing local flooding or scouring slopes and areas of unprotected works-Codes for

63

ENVIRONMENTAL - MITIGATION MEASURE VIETNAM SOCIAL ISSUES CODEIREGULATION;

WB Environmental, Health and Safety

Guidelines

soil,resulting in heavy sediment loads affecting local watercourses. construction

• Ensure drainage system is always well maintained and cleared of mud and other obstructions. • Decree No. 2212010nT-

• Areas of the site not disturbed by construction activities shall be maintained in their existing BXD on regulation of

conditions. construction safety

• Earthworks, cuts, and fill slopes shall be properly maintained, in accordance with the construction • QCVN 08:20081BTNMT

specifications, including measures such as installation of drains, and use of plant cover. - National technical

• To avoid sediment-laden runoff that could adversely impact watercourses, install sediment control regulation on quality of

structures where needed to slow or redirect runoff and trap sediment until vegetation is established. surface water

Sediment control structures could include windrows of logging slash, berms, sediment catchment • World Bank

basins, straw bales, storm drain inlet protection systems, or brush fences. Environmental, Health

• Site de-watering and water diversions: Where construction activities require that work be carried out and Safety Guidelines:

within the watercourse (e.g. culvert or bridge crossing construction, retaining wall construction, Construction and

erosion protection works), the work area must be dewatered to facilitate work in dry conditions. The Decommissioning; sediment-laden water pumped from the work area must be discharged to an appropriate sediment Wastewater and control structure for treatment before release to the stream. Ambient Water

• Stream diversions or construction of cofferdams would require site-specific mitigation measures in the Quality EMP.

6. Management of • All locations to be used must have been previously identified in the approved construction work plan. World Bank stockpiles, quarries, Sensitive sites such as scenic spots, areas of natural habitat, areas near sensitive receptors, or areas Environmental, Health and and borrow pits near water should be avoided. Safety Guidelines: Waste

• Build an open ditch around the stockpile site to intercept the runoff. Management; Hazardous

• Stockpile topsoil when first opening a borrow pit and use it later to restore the area to near natural Materials Management;

conditions. Occupational Health and

• If the need for new stockpile or disposal sites arises during construction, they must be pre-approved Safety; Construction and

by the Construction Supervision Engineer. Decommissioning

• If any landowners are affected by use of their land for stockpiles or borrow pits, they must be included -.~ .. --.-.. - .. _ .. - - -

64

ENVIRONMENTAL - MITIGATION MEASURE VIETNAM SOCIAL ISSUES CODEIREGULATION;

WB Environmental, Health and Safety

Guidelines

in the project resettlement plan.

• If access roads are needed, they must have been considered in the environmental assessment.

• Quarries and large material borrow pits or material stockpiles may need site~specific measures.

7. Solid waste • Before the start of construction, prepare a solid waste management plan for storage, provision of bins, • Decree No. 5912007IND-site clean-up schedule, bin clean-out schedule, etc.; it must be carefully followed monitored during CP on solid waste construction. management

• Before the start of construction, obtain all necessary waste disposal permits or licenses. • World Bank

• Take all necessary measures to reduce the potential for litter and negligent behavior with regard to the Environmental, Health disposal of refuse. At all places of work, the Contractor shall provide litter bins, containers and refuse and Safety Guidelines: collection facilities. Waste Management;

• Solid waste may be temporarily stored on site in a designated area approved by the Construction Hazardous Materials Supervision Consultant and relevant local authorities prior to collection and disposal through a Management; licensed waste collector. Construction and

• Cover all waste storage containers, to be tipping~proof, weatherproof and scavenger~ proof. Decommissioning

• No burning, on-site burying or dumping of solid waste shall occur.

• Recyclable materials such as wooden plates for trench works, steel, scaffolding material, site holding, packaging material, etc. shall be collected and separated on-site from other waste sources for reuse, for use as fill, or for sale.

• If not removed off site, solid waste or construction debris shall be disposed of only at sites identified and approved by the Construction Supervision Consultant and included in the solid waste plan. Under no circumstances shall the contractor dispose of any waste materials in environmentally sensitive areas, such as in areas of natural habitat or in watercourses.

8. Chemical or • Chemical waste of any kind shall be disposed of at an approved appropriate sanitary landfill site and • Decision No. hazardous wastes in accordance with local legislative requirements. The Contractor shall obtain needed disposal 2312006/QD-BTNMT

certificates. with list of hazardous

• The removal of asbestos-containing materials or other toxic substances shall be performed and substance

65

ENVIRONMENTAL -SOCIAL ISSUES

9. Management of dredged materials

MITIGATION MEASURE VIETNAM CODEIREGULATION;

WB Environmental, Health and Safety

Guidelines

disposed of by specially trained and certified workers.

• Used oil and grease shall be removed from site and sold to an approved used oil recycling company.

• Circular No. 12/20111TT­BTNMT on management of hazardous substance

• Used oil, lubricants, cleaning materials, etc. from the maintenance of vehicles and machinery shall be collected in holding tanks and removed from site by a specialized oil recycling company for disposal I •

at an approved hazardous waste site.

• Used oil or oil-contaminated materials that could potentially contain PCBs shall be securely stored to avoid any leakage or affecting workers. The local DONRE must be contacted for further guidance.

• Unused or rejected tar or bituminous products shall be returned to the supplier's production plant.

• Relevant agencies shall be promptly informed of any accidental spill or incident.

• Store hazardous chemicals appropriately and with appropriate labeling, and in locked containers.

• Appropriate communication and training programs should be put in place to prepare workers to recognize and respond to workplace chemical hazards

• Prepare and initiate a remedial action following any spill or incident. In this case, the contractor shall provide a report explaining the reasons for the spill or incident, remedial action taken, consequences/damage from the spill, and proposed corrective actions.

• Dredging plan should be established including time schedule, method statement to meet the I. requirements of traffic safety, public health, and environmental sanitation. In order to ensure dredging that is consistent with environmental regulations, key decision makers (local authority, DONRE, utility company, CSC, etc.) must be involved and concur in each key decision point in the process

leading to preparation and implementation of a plan.

Characteristics of sludge/sediment should be determined by sampling and analysis if not already fully evaluated during the EIA. Sludge that is heavily contaminated would require measures that go beyond the scope of these ECOPs.

Ensure that dredged material management plans incorporate environmental considerations in the identification of short-term and long-term disposal alternatives, consider methods to reduce dredging, and maximize the beneficial use of dredged materials.

World Bank Environmental, Health and Safety Guidelines: Waste Management; Hazardous Materials Management; Construction and Decommissioning

Decision No. 23/2006/QD-BTNMT with list of hazardous substance

Decree No. 59120071ND­CP on solid waste management

Circular No. I 2120 11 ITT­BTNMT on management of hazardous substance

World Bank

66

ENVIRONMENTAL -SOCIAL ISSUES

10. Disruption of vegetative cover and ecological resources

MITIGATION MEASURE

• Leachate from dredged materials should not be allowed to enter watercourses without appropriate filtering or treatment.

• Collected dredged materials have to be processed, as per Vietnamese regulations on waste collection, to ensure safe and environmentally secure transportation, storage, treatment and management

• Those involved in handling of sludge should be specialized and have certification of sludge handling. Guidelines for certification of sludge handling is in the Circular No. 12/2011ITT-BTNMT on management of hazardous substance

• Sanitary landfill sites should meet technical requirements, based on level of potential contamination. In the case of disposal at a dumpsite, a hazardous cell may need to be constructed if sludge is contaminated by heavy metals,

• The Contractor shall prepare a Clearance, Re-vegetation and Restoration Management Plan for prior I. approval by the Construction Supervision Engineer, following relevant regulations. This plan shall be approved by the Construction Supervision Consultant and followed strictly by contractor. Areas to be cleared should be minimized as much as possible.

• The Contractor shall remove topsoil from all areas where topsoil will be impacted by construction activities, including temporary activities such as storage and stockpiling, etc; the stripped topsoil shall be stockpiled in areas agreed with the Construction Supervision Consultant for later use in re­vegetation; it shall be adequately protected while it is stored.

• The application of chemicals for vegetation clearing is not permitted.

• Prohibit cutting of any tree unless explicitly authorized in above-referred plan.

• When needed, erect temporary protective fencing to effectively protect all trees before commencement of any works within the site.

• No area of potential importance as an ecological resource should be disturbed unless there is prior authorization from CSC, who should consult with PPMUs, IEMC and the relevant local authorities. This could include breeding or feeding areas of birds or animals, fish spawning areas, or any other

VIETNAM CODEIREGULA TlON;

WB Environmental, Health and Safety

Guidelines

Environmental, Health and Safety Guidelines:

Waste Management;

Hazardous Materials

Management;

Contaminated Land;

Community Health and Safety; Construction

and Decommissioning

Law on Environment protection No. 52/2005/QHII

World Bank Environmental, Health

and Safety Guidelines:

Construction and

Decommissioning

67

ENVIRONMENTAL - MITIGATION MEASURE VIETNAM SOCIAL ISSUES CODEIREGULA TION;

WB Environmental, Health and Safety

Guidelines

area that is protected as a green space.

• The Contractor shall ensure that no hunting, trapping shooting, poisoning of animals takes place on the construction site or by the workers.

11. Traffic management • Before construction, carry out consultations with the affected local government and communities and • Law on traffic and with the traffic police. transportation No.

• Cover any significant increases in number of vehicle trips must in a construction plan. For routing of 23/2008/QH12

construction traffic, especially of heavy vehicles, take into account sensitive sites such as schools, • Law on construction No. hospitals, temples, churches and markets. 1 612003/QH I 1

• Install lighting at night, if necessary, to ensure safe traffic circulation. • Decree No. 22/20 101TT-

• Place signs around the construction areas to facilitate traffic movement, provide directions to various BXD on regulation of

components of the works, and provide safety warning signs. construction safety

• Use safe traffic control measures, including road/rivers/canal signs and flag persons to warn of • World Bank

dangerous conditions. Environmental, Health

• Avoid the transport of construction materials during rush hours. and Safety Guidelines:

• Provide separate passageways for pedestrians and vehicles within and outside construction areas to Community Health and

allow easy, safe, and appropriate access. Signs shall be installed appropriately in both water-ways and Safety

roads where necessary.

12. Interruption of utility • With regard to planned and unplanned interruptions to water, gas, electric power, and internet • Decree No. 7312010/ND-services services, the Contractor must undertake prior consultation and contingency planning with local CP on administrative

authorities about the consequences of a particular service failure or disconnection. penalization security and

• Coordinate with relevant utility providers to establish appropriate construction schedules. society issues

• Provide information to affected households on work schedules as well as planned disruptions at least 5 days in advance.

• A void interruptions of irrigation water supply to agricultural areas.

• Ensure alternative water supply to affected residents in the event of disruptions lasting more than one day.

--_ .. _ .. - - - -----_._ .. _._.- ---.----.-

68

ENVIRONMENTAL - MITIGA TION MEASURE VIETNAM SOCIAL ISSUES CODEIREGULA TION;

WB Environmental,

Health and Safety Guidelines

I I

I

• Report any damages to existing utility systems of cable to authorities concerned, make sure they are repaired as soon as possible.

13. Restoration of • Restore cleared areas such as borrow pits which are no longer in use, disposal areas, site facilities, • Law on Environment affected areas workers' camps, stockpiles areas, working platforms and any areas temporarily occupied during protection No.

construction of the project works; use landscaping, adequate drainage and re-vegetation. 52f2005fQHII

• Start re-vegetation at the earliest opportunity, and select appropriate local native plant species for the • World Bank re-planting and restoration of the natural landscape. Environmental, Health

• Spoil heaps and excavated slopes shall be re-profiled to stable batters, and grassed to prevent erosion. and Safety Guidelines:

• landscaPe all areas affected by construction and undertake any necessary remedial works without Construction and

delay. Decommissioning

• Plant trees on exposed land and on slopes to prevent or reduce land slippage or collapse and keep slopes stable.

• Remove any soil contaminated with chemicals or hazardous substances and transport it to waste disposal areas for burial.

• Restore all damages to road and bridges caused by project activities.

14. Workers' and Public • Comply with all Vietnamese regulations regarding workers' and public safety. • Decree No. 22f201OfIT-Safety • Prepare and implement action plan to cope with risks and emergencies BXD on regulation of

• Have emergency ftrst aid equipment available at construction sites. construction safety

• Instruction No. 02 • Train workers in occupational health and safety regulations.

f2008/CT-BXD on safety • Ensure that workers wear I use appropriate personal protective equipment (PPE), such as safety and sanitation issues in

glasses, face shields, hard hats, safety shoes, etc. construction agencies

• Ensure that ear pieces (noise protection ear muffs) are provided to and used by workers who use noisy • TCVN 5308-91: machines such as piling hammers, for workers' protection. Technical regulation on

• During demolition of existing infrastructure, workers and the general public must be protected from safety in construction falling debris by measures such as warning signs, chutes, traffic control, barriers and restricting • Decision No. --_._-_ .. _ .. -

69

ENVIRONMENTAL - MITIGATION MEASURE VIETNAM SOCIAL ISSUES CODEIREGULATION;

WB Environmental, Health and Safety

Guidelines

access. 96/2008/QD-TIg on

• Install fences, barriers, warning/prohibition signs around construction sites with potential dangers to clearance ofUXO. I the public. • World Bank I

• Provide safety measures through installation of fences, barriers warning signs, lighting system against Environmental, Health

traffic accidents as well as other risks to the public. and Safety Guidelines:

• Remove hazardous conditions on construction sites that cannot be controlled effectively with access Occupational Health

restrictions, such as covering small openings and ensuring means of escape from larger openings, such and Safety; as trenches or open excavations. Community Health and

• Ensure visibility of workers through their use of high visibility vests when working in heavy Safety; Construction

equipment operating areas. and Decommissioning

• Ensure that moving equipment is fitted with audible back-up alarms.

• When work is done in confined spaces, such as deep excavation (trenches) use dewatering, adequate side-wall supports (shoring) and slope gradients that minimize the risks of collapse, entrapment or drowning.

• Provide safe means of access and exit from excavations through graded access, or stairs and ladders.

• Train and use temporary fall prevention devices, such as rails or other barriers when working at heights greater then 2 meters.

• Conduct sawing, cutting, grinding, sanding, chipping or chiseling with proper anchoring and guards, i.e. safety glasses

• Implement good housekeeping practices on site, such as sorting and placing loose construction materials and debris in established areas away from footpaths.

• Locate electrical cords and ropes in common areas and marked corridors.

• Clean up excessive waste, debris and liquid spills regularly.

• If explosives and blasting will be used, evacuate work areas during blasting, use blast mats or other means to minimize flying rock if work is conducted in proximity to people and structures. Use

- .. -. _ .. - - -_. _ ... _ .. _ .. _ ... -L __ ~.~.~. w~rni!1IL~~fl~ ~l1d ~standard procedures to secure site. Addition~l mitigation measures and safe!)'

. -

70

ENVIRONMENTAL - MITIGATION MEASURE VIETNAM SOCIAL ISSUES CODEIREGULATION;

WB Environmental, Health and Safety

Guidelines

precautions may be required.

• Ifprevious assessments indicate there could be unexploded ordinance (UXO), clearance must be done by qualified personnel and as per detailed plans approved by the Construction Engineer.

15. Communication with • Maintain open communications with the local government and concerned communities; the contractor • Decree No. 7312010/ND-local communities shall coordinate with local authorities (leaders of local wards or communes, leaders of villages) the CP on administrative

agreed schedules of construction activities at areas nearby sensitive places or at sensitive times (e.g., penalization security and religious festival days). society issues

• Copies in Vietnamese of these ECOPs and of other relevant environmental safeguard documents shall • World Bank be made available to local communities and to workers at the site. Environmental, Health

• Reduced playground space, loss of playing fields and car parking: The loss of amenities during the and Safety Guidelines: construction process is often an unavoidable source of inconvenience to users in sensitive areas. Community Health and However, early consultation with those affected, provides an opportunity to investigate and implement Safety; Construction alternatives. and Decommissioning

• Disseminate project information to affected parties (for example local authority, enterprises and affected households, etc.) through community meetings before construction starts;

• Provide a community relations contact from whom interested parties can receive information on site activities, project status and project implementation results;

• Provide all information, especially technical fmdings, in a language that is understandable to the general public and in a form that is useful to interested citizens and elected officials through the preparation of fact sheets and news releases, when major fmdings become available during project phase;

• Monitor community concerns and information requirements as the project progresses;

• Respond to telephone inquiries and written correspondence in a timely and accurate manner;

• Inform local residents about construction and work schedules, interruption of services, traffic detour routes and provisional bus routes, blasting and demolition, as appropriate;

• Provide technical documents and drawings to affected communities, especially a sketch of the

71

ENVIRONMENTAL - MITIGATION MEASURE VIETNAM SOCIAL ISSUES CODEIREGULA TION;

WB Environmental,

Health and Safety Guidelines

construction area and a copy of the EMP for the construction site;

• Notification boards shall be erected at all construction sites providing information about the project, as well as the contact information of the site managers, environmental staff, health and safety staff. Telephone numbers and other contact information must be provided so that any affected people have the channel to voice their concerns and suggestions.

16. Chance find If the Contractor discovers archeological sites, historical sites, remains and objects, including graveyards • Law on Cultural Heritage procedures and/or individual graves during excavation or construction, the Contractor shall: (2002)

• Stop the construction activities in the area of the chance find; • Law on Cultural Heritage

• Delineate the discovered site or area; (2009) for supplementary

• Secure the site to prevent any damage or loss of removable objects. In cases of removable antiquities and reformation

or sensitive remains, a night guard shall be arranged until the responsible local authorities or the • Decree No. 98/20101ND·

Department of Culture and Information takes over; CP for supplementary

• NotifY the Construction Supervision Consultant who in turn will notifY the responsible local or and reformation

national authorities in charge of the cultural property in Viet Nam (within 24 hours or less);

• Relevant local or national authorities, once they have been notified, will be responsible for protecting and preserving the site before deciding on subsequent appropriate procedures. This would require a preliminary evaluation of the fmdings to be performed. The significance and importance of the findings should be assessed according to the various criteria relevant to cultural heritage, such as aesthetic, historic, scientific or research, social and economic values;

• Decisions on how to handle the finding shall be taken by the responsible authorities. This could include changes in the layout of the work (such as when finding an irremovable remain of cultural or archeological importance) conservation, preservation, restoration and salvage;

• If the cultural sites and/or relics are of high value and site preservation is recommended by the professionals and required by the cultural relics authority, the Project's Owner will need to make necessary design changes to accommodate the request and preserve the site;

• Decisions concerning the management of the finding shall be communicated in writing by relevant authorities;

72

ENVIRONMENTAL - MITIGATION MEASURE VIETNAM SOCIAL ISSUES CODEIREGULA TION;

WB Environmental, Health and Safety

Guidelines

• Construction works could resume only after permission is granted from the responsible local authorities concerning safeguard of the heritage.

- _. _ .. _ ... _ .. _ .. __ . __ .. -

73

ANNEX 2: Guidelines for the Preparation of a Dredged Materials Management Plan (DMMP) for Contaminated Sludge

To ensure that dredging, transportation, and disposal of contaminated sludge will not create adverse impacts on local residents and the environment, a guideline for the preparation of a DMMP is provided below. If during the environmental assessment stage, contaminated material is identified in the water body to be excavated, the detailed design will include a comprehensive testing program and the development of a DMMP, reflecting the guidelines below. The detailed DMMP shall be prepared by the contractor in consultation with the PMU and the World Bank: prior to commencement of civil works.

The main environmental and social issues related to contaminated dredged materials are: (a) pollution during the transport of the dredged materials from the dredging site to the disposal area; (b) potential increase in turbidity and pollution of the ambient water in the lakes/canals during dredging; (c) odors and other nuisance to local residents; and (d) potential improper use of contaminated sludge for public infrastructure works or in residential areas. To facilitate the preparation of a DMMP given that the activities will be carried out in an urban area and/or in an existing water body that may be used by other water users, the following important aspects must be considered:

• Assess the quality of the sediments. This assessment mustbe carried out to confirm that the sediments do not include large amounts of environmentally harmful materials, such as heavy metals and/or other toxic substances. If the materials are found to be above the thresholds for heavy metals or toxic substances stipulated by the national standards, a special disposal plan should be prepared, together with a monitoring plan. The special disposal plan should also include a program to protect the residents in nearby communities from using the dredged materials for house construction or gardening. The bottom sediment/sludge samples will be analysed for key pollutants according to the Vietnamese national standards. The sampling and analytical methods should be in line with the Go V regulations while the number of sampling locations will depend on the risk levels for each specific site. The number of samples to be analysed will be determined by the proposed volume of dredging as follows:

Volume of Dredged Material in m3 No. of Sediment Samples

IUp to 25,000 3

~5,000 to 100,000 4-6

100,000 to 500,000 6-10

500,000 to 2,000,000 10-20

For each 1,000,000 above 2,000,000 Additional 10

• Identify the land available for the disposal of the dredged materials. The DMMP should identify the landfill sites andlor land that would be suitable for the disposal of dredged materials in line with the level of risks associated with it. Public land, land for construction of rural roads or other public works, or private land, may be used, if the affected landowners agree. If the risks due to contamination of the sludge are high, the sludge must be disposed of at sanitary landfills.

• Prepare a dredging and transport plan. The dredging procedures and transport plan will outline the following: (a) dredging methods (pipeline, water pumping before digging, etc.), mode of transport to the disposal areas andlor temporary storage sites. If trucks are used, indicate proposed transport routes from the dredging site to the disposal area, (b) time and hours of operation, (c) types of barges or vehicles/trucks and proposed measures to reduce the leakage of the dredged materials from the transport trucks, (d) contractors' responsibilities for cleaning the roads and carry out remedial works if necessary, and (e) a communication plan for the nearby communities, including contact numbers for lodging complaints.

• Temporary storage/disposal for uncontaminated sediment/mud The dredged materials are in a mud-like state before settling for 24 - 48 hours. All drainage water from the temporary storage on land shall be discharged back to the canaInakes. For highly contaminated sludge, or sludge containing organic materials that generate strong odors, the dredged materials should be hauled by closed tanker trucks away from the construction site as soon as possible. For bottom sediments with a low content organic materials, the dredged sediments will be transported to a containment area which is appropriately located and properly designed and of an adequate size. A monitoring plan for tracking the disposal of highly contaminated materials, if any are present, will also be prepared.

• Identify key areas and/or facilities (businesses, schools, public services, etc.) that are sensitive to dredging and transport of dredged materials. The DMMP shall include an inventory / analysis of the potentially affected local businesses, access to water, and transport due to the dredging operations, and provide a plan to mitigate andlor compensate for the disturbances. The plan should include all measures necessary to avoid impacts on local transportation and water supply, and access to local residents as much as possible.

• Identify other water users. In areas where dredging may cause negative impacts to these water users, the respective subproject owner is required to inform/consult them and develop a series of actions to address their concerns, including water quality monitoring intheDMMP.

75