executive summary · web viewcalifornia distribution resources plan integrated capacity analysis...

62
California Distribution Resources Plan Integration Capacity Analysis Working Group DRAFT Final Report – Due March 1, 2017 NOTE: This is a second draft of the ICA WG report. Comments in tracked changes can be sent to [email protected] and are due Monday EOB, March 6. Contents 1 Executive Summary.................................................2 2 Introduction and Background.......................................2 3 Discussion Topics, Points of Consensus, Proposed Alternatives if Any, Recommendations, Next Steps.....................................6 3.1 Use Cases of ICA...............................................9 3.2 Development of Common IOU methodology.........................12 3.2.1 Overview.................................................. 12 3.2.2 Streamlined method........................................13 3.2.3 Iterative method.......................................... 13 3.2.4 Recommendations........................................... 14 3.3 Schedule and Timelines........................................15 3.4 Frequency of Updates..........................................17 3.5 Presentation of ICA values....................................17 3.6 ACR Requirements..............................................18 3.6.1 Modeling and extracting power system data.................18 3.6.2 Power system criteria methodology.........................19 3.6.3 Power quality/voltage criteria............................19 3.6.4 Safety/reliability, or “operational flexibility”..........20 3.6.5 Circuit models............................................ 23 3.6.6 Pre-existing conditions...................................24 3.7 Short-term activities.........................................24 3.7.1 ACR Section 3.1.b: Recommend methods for evaluation of hosting capacity for the following resource types: i) DER bundles or portfolios, responding to CAISO dispatch; ii) facilities using smart inverters..................................................25 3.7.2 ACR Section 3.1.c: Recommend a format for the ICA maps and downloadable data to be consistent and readable by all California stakeholders across the utilities service territories with similar data and visual aspects (Color coding, mapping tools, etc.)......27 1

Upload: others

Post on 01-Apr-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Executive Summary · Web viewCalifornia Distribution Resources Plan Integrated Capacity Analysis Working Group DRAFT Final Report – Due March 1, 2017 NOTE: This is a first draft

California Distribution Resources Plan Integration Capacity Analysis Working Group

DRAFT Final Report – Due March 1, 2017

NOTE: This is a second draft of the ICA WG report. Comments in tracked changes can be sent to [email protected] and are due Monday EOB, March 6.

Contents1 Executive Summary.............................................................................................................................2

2 Introduction and Background..............................................................................................................2

3 Discussion Topics, Points of Consensus, Proposed Alternatives if Any, Recommendations, Next Steps............................................................................................................................................................6

3.1 Use Cases of ICA..........................................................................................................................9

3.2 Development of Common IOU methodology............................................................................12

3.2.1 Overview............................................................................................................................12

3.2.2 Streamlined method..........................................................................................................13

3.2.3 Iterative method................................................................................................................13

3.2.4 Recommendations.............................................................................................................14

3.3 Schedule and Timelines.............................................................................................................15

3.4 Frequency of Updates................................................................................................................17

3.5 Presentation of ICA values.........................................................................................................17

3.6 ACR Requirements.....................................................................................................................18

3.6.1 Modeling and extracting power system data.....................................................................18

3.6.2 Power system criteria methodology..................................................................................19

3.6.3 Power quality/voltage criteria...........................................................................................19

3.6.4 Safety/reliability, or “operational flexibility”.....................................................................20

3.6.5 Circuit models....................................................................................................................23

3.6.6 Pre-existing conditions.......................................................................................................24

3.7 Short-term activities..................................................................................................................24

3.7.1 ACR Section 3.1.b: Recommend methods for evaluation of hosting capacity for the following resource types: i) DER bundles or portfolios, responding to CAISO dispatch; ii) facilities using smart inverters.........................................................................................................................25

3.7.2 ACR Section 3.1.c: Recommend a format for the ICA maps and downloadable data to be consistent and readable by all California stakeholders across the utilities service territories with similar data and visual aspects (Color coding, mapping tools, etc.)...................................................27

3.7.3 ACR Section 3.1.d: Evaluate and recommend new methods that may improve the calculation of ICA values using computational efficiency method in order to calculate and update ICA values across all circuits in each utility’s service territory...........................................................29

3.7.4 ACR Section 3.1.e: Evaluate ORA’s recommendation to require establishment of reference circuits and reference use cases for comparative analyses of Demo Project A results......................30

1

Page 2: Executive Summary · Web viewCalifornia Distribution Resources Plan Integrated Capacity Analysis Working Group DRAFT Final Report – Due March 1, 2017 NOTE: This is a first draft

California Distribution Resources Plan Integration Capacity Analysis Working Group

DRAFT Final Report – Due March 1, 2017

NOTE: This is a second draft of the ICA WG report. Comments in tracked changes can be sent to [email protected] and are due Monday EOB, March 6.

3.7.5 ACR Section 3.1.f: Establish a method for use of Smart Meter and other customer load data to develop more localized load shapes to the extent that is not currently being done.............32

3.7.6 ACR Section3.1.g: Establish definite timelines for future achievement of ICA milestones, including frequency and process of ICA updates...............................................................................33

3.8 Long-term refinement activities................................................................................................35

3.9 Additional Cost Recovery...........................................................................................................36

3.10 Recommendation Summary Table.............................................................................................36

4 Next Steps for the ICA WG.................................................................................................................38

5 Appendix............................................................................................................................................40

5.1 Acronyms...................................................................................................................................40

5.2 Working Group Meetings and Topics.........................................................................................40

5.3 Working Group Participants.......................................................................................................41

1 Executive SummaryThis is the Final Demo A Report of the Integration Capacity Analysis Working Group (WG) to the California Public Utilities Commission. The report is a status report that summarizes the development of the Integration Capacity Analysis to date, the recommendation ICA methodology which is to be implemented across IOU’s service territories on their first system wide roll out as well as an implementation timeline, and recommendations on how to improve the methodology through the long-term enhancement via the ICA WG. This final report also provides recommendations on how the ICA results may be used to inform decision-making on the part of the Commission, utilities, providers of distributed energy resources, and customers.

2 Introduction and BackgroundOverviewAdopted in 2014, Section 769 of the California Public Utilities Code requires the Investor Owned Utilities (IOUs) to prepare a distribution resources plan which identifies optimal locations for the deployment of distributed energy resources. In August 2014, the California Public Utilities Commission (CPUC, or Commission) began implementation of this requirement through Rulemaking (R.) 14-08-013, the Distribution Resources Plan (DRP) proceeding. A Ruling from the Assigned Commissioner in November 2014 introduced the Integration Capacity Analysis (ICA) as a tool which would support the determination of optimal locations by specifying how much capacity of integrated distributed energy resources may be

2

David, 02/24/17,
This section should be built out and expanded once everything else is finalized.
Page 3: Executive Summary · Web viewCalifornia Distribution Resources Plan Integrated Capacity Analysis Working Group DRAFT Final Report – Due March 1, 2017 NOTE: This is a first draft

California Distribution Resources Plan Integration Capacity Analysis Working Group

DRAFT Final Report – Due March 1, 2017

NOTE: This is a second draft of the ICA WG report. Comments in tracked changes can be sent to [email protected] and are due Monday EOB, March 6.

available on the distribution network at the circuit level.1 Pursuant Commission direction, California’s Investor Owned Utilities (IOUs) filed Applications2 developing their Distribution Resource Plans, including a proposal to complete a Demonstration of their proposed ICA (“Demo A”). Stakeholder holder input on the IOU proposals was gathered, leading to further guidance issued in May 2016. That guidance authorized a demonstration project of the ICA, requiring the Investor Owned Utilities (IOUs) to meet the following nine functional requirements:

1. Quantify the Capability of the Distribution System to Host DER 2. Common Methodology Across All IOUs 3. Analyze Different Types of DERs 4. Line Section or Nodal Level on the Primary Distribution System 5. Thermal Ratings, Protection Limits, Power Quality (including Voltage), and Safety Standards6. Publish the Results via Online Maps7. Use Time Series Models 8. Avoid Heuristic approaches, where possible9. Perform the complete ICA analysis for all feeders down to the line section or node on two Distribution Planning Areas (DPA).3

In addition to the ACR, the May 2016 ruling established the ICA Working Group (WG). The purpose of the WG is to monitor and provide consultation to the IOUs on the execution of Demonstration Project A and further refinements to ICA methodology. CPUC Energy Division staff has oversight responsibility of the working group, but it is currently managed by the utilities and interested stakeholders on an interim basis. The utilities jointly engaged More Than Smart (MTS), a 501(c)3 non-profit organization, to facilitate the WG. The Energy Division may at its discretion assume direct management of the working group or appoint a working group manager.

Between May 2016 and this Final WG Report, the WG met 16 times. Discussions focused on developing the ICA have been facilitated by MTS. The WG has benefitted from contributions by a large range of stakeholders. A complete list of contributing stakeholders is provided in Appendix A. The WG expects to continue its efforts through August 2017 as it begins to address long-term ICA refinement.

In December 2016, Pacific Gas & Electric (PG&E), Southern California Edison (SCE), and San Diego Gas and Electric (SDG&E) submitted their final Demo A reports, representing a substantial milestone for the WG. 4These reports summarize demo results, lessons learned, and the IOUs’ recommendations on methodology calculation and feasibility of implementation of the ICA across the entire distribution system.

1 Assigned Commissioners Ruling, November 2014. (http://docs.cpuc.ca.gov/PublishedDocs/Efile/G000/M141/K905/141905168.PDF)2 http://www.cpuc.ca.gov/General.aspx?id=5071 3 Assigned Commissioner’s Ruling, May 2016. (http://docs.cpuc.ca.gov/PublishedDocs/Efile/G000/M161/K474/161474143.PDF)4 IOU demo results can be found at: http://drpwg.org/sample-page/drp/

3

Page 4: Executive Summary · Web viewCalifornia Distribution Resources Plan Integrated Capacity Analysis Working Group DRAFT Final Report – Due March 1, 2017 NOTE: This is a first draft

California Distribution Resources Plan Integration Capacity Analysis Working Group

DRAFT Final Report – Due March 1, 2017

NOTE: This is a second draft of the ICA WG report. Comments in tracked changes can be sent to [email protected] and are due Monday EOB, March 6.

Summary of RecommendationsThis Final Report contains the full Working Group’s recommendations for the ICA methodology and related action items coming out of the IOU’s December filings. The WG offers recommendations on the methodology and timing considerations for the first system wide implementation, recommendations on how to improve the methodology through the long-term enhancements to ICA and how the results may be used to inform decision-making on the part of the Commission, utilities, providers of distributed energy resources, and customers. At a high level, these include recommendations on the following four categories:

[1.] Uses of ICA: the WG identifies two primary use cases for the ICA. The first and most developed use of ICA is to facilitate a significantly streamlined expedited Fast Track interconnection process. The second, less developed use of ICA is within various system planning processes to identify when and where interconnection of DERs may be constrained by hosting capacity limits. The WG report outlines immediate, near and long term methodological refinements to enable the use of ICA within the interconnection process, and lays out considerations for the planning use case, with a goal of developing methodology recommendations for use within the planning context in the near-term (and in coordination with ongoing planning proceedings at the CPUC)

1.[2.] Development of Common IOU methodology: The ACR stated that the CPUC envisions approval of a final ICA methodology common across all utilities would result in a Proposed Decision in early 2017. The IOUs tested the ICA using two separate methodologies in Demo A, known as “iterative” and “streamlined”. A majority of WG members recommend that the IOUs use the iterative methodology for interconnection purposes, assuming added refinements detailed further in this report can be achieved at a reasonable cost. PG&E recommends a “blended” approach using both methods for interconnection5. The WG believes the streamlined methodology may provide value in the planning process, and will continue to consider it while defining the uses of ICA in system planning.

2.[3.] Timeline: the IOUs intend to implement ICA across their entire distribution service territories, using a common Commission-approved methodology. IOUs provided recommendations on when implementation should be completed, while some stakeholders offered a second perspective. The WG agrees that this first system-wide rollout should include the identified recommendations from this report.

3.[4.] Modifications to scope and schedule. Further, the WG recommends that the Commission establish two processes to incorporate modifications to the ICA:

1. A Working Group internal approval process. As the WG continues to refine and enhance the ICA based on new studies and developed methods, it is requested that the Commission establish a process to allow the IOUs to make enhancements to the methodology as they are developed in consultation with the WG during the long-term refinement process. This process should provide flexibility to phase in refinements within boundaries established by the CPUC. The Commission should decide whether this

5 See PG&E’s final Demo A report: http://drpwg.org/wp-content/uploads/2016/07/R1408013-PGE-Demo-Projects-A-B-Final-Reports.pdf

4

Laura Wang, 02/27/17,
Brad Heavner:“Streamlined” doesn’t capture the benefit of giving customers data to design systems with the best fit to local capacity. This may be even more important than other process changes, and I worry that by using “streamlined” as the shorthand term this other benefit doesn’t get sufficient emphasis.
Page 5: Executive Summary · Web viewCalifornia Distribution Resources Plan Integrated Capacity Analysis Working Group DRAFT Final Report – Due March 1, 2017 NOTE: This is a first draft

California Distribution Resources Plan Integration Capacity Analysis Working Group

DRAFT Final Report – Due March 1, 2017

NOTE: This is a second draft of the ICA WG report. Comments in tracked changes can be sent to [email protected] and are due Monday EOB, March 6.

process takes the form of a revised rulemaking, consultation with ICA WG or Energy Division staff, advice letter, etc.

2. Consultation with CPUC Energy Division on implementation. The WG has developed recommendations on methodology refinements based on best available knowledge and in-depth discussions among a broad stakeholder group, though there are recommendations contingent upon costs and modeling software capabilities. It is requested that the Commission establish a process for the IOUs to consult with the Energy Division if one or more IOUs determines that a methodology component (specific to the added refinements) cannot be included in the first system-wide rollout of ICA due to issues not possible to predict at this time and consequently discovered during the rollout process (i.e. inability of vendor software). For those changes, the WG expects that IOUs will prioritize their resolution in the next iteration of ICA.

Scope and Process

The “Working Group” references all active parties participating in ICA WG meetings, which include the IOUs, government representatives, DER developers, nonprofits, and independent advocates and consultants. All meeting dates and topics covered are, as well as all stakeholder groups attending at least one meeting or webinar of the ICA WG, are described in Appendix A. This report is the product of significant edits and contributions from the following organizations:

- CPUC Energy Division (ED)

- CPUC Office of Ratepayer Advocates (ORA)

- California Solar Energy Industries Association (CALSEIA)

- Clean Coalition (CC)- Independent

Advocates

- Interstate Renewable Energy Council (IREC)

- Pacific Gas & Electric (PG&E)

- San Diego Gas and Electric (SDG&E)

- Santa Barbara Community Environmental Council

- SolarCity

- Solar Energy Industries Association (CALSEIA)

- Southern California Edison (SCE)

- The Utility Reform Network (TURN)

- Vote Solar

The ICA WG met regularly to discuss the proposed methodology for Demonstration A and review final Demo A reports. A full summary of WG documents including meeting agendas, presentation slides, and participant list is included in Appendix B.

All three IOUs submitted their Demo A reports at the end of December 2016 in compliance with the ACR, and made the maps and downloadable data available in January and February 2017. These reports lay out in detail the assumptions and calculations used within the ICA methodology. Additionally, the

5

Laura Wang, 03/01/17,
Please let me know if this list is appropriately indicative. I summarized based on submitted comments to both the report and the list of stakeholder questions developed in January/February.
Laura Wang, 02/28/17,
There are a few options here for WG consideration. There is general agreement that process should be flexible and not unnecessarily burdensome. The WG can either 1.agree w/ consensus on a process, or 2. Let Commission decide on best process. Alternatively, IOUs propose: WG recommends that the CPUC establish a process by which IOUs could modify the planned scope and schedule of the ICA implementation by filing a Tier 1 Advice Letter. This process would allow changes to be formalized and visible to all parties, and the AL process provides an opportunity for stakeholders to formally respond to the modifications.
Page 6: Executive Summary · Web viewCalifornia Distribution Resources Plan Integrated Capacity Analysis Working Group DRAFT Final Report – Due March 1, 2017 NOTE: This is a first draft

California Distribution Resources Plan Integration Capacity Analysis Working Group

DRAFT Final Report – Due March 1, 2017

NOTE: This is a second draft of the ICA WG report. Comments in tracked changes can be sent to [email protected] and are due Monday EOB, March 6.

IOUs each separately made recommendations on which methodology (i.e., using a streamlined, iterative, or blended approach) to use going forward in a system-wide rollout of ICA. WG stakeholder review and further discussion of these recommendations led to different conclusions in some areas.

The ACR additionally specifies multiple items the WG should focus on to continue refining the ICA methodology. The WG filed an interim long-term refinement report in December 2016 detailing work to-date on those items, and sorting topics into a tiered system to develop a rough schedule for WG work in 2017. Since the filing of that report, the WG has identified additional long-term refinement items after reviewing the IOUs’ final Demo A reports. Those items are included in an amended Table6, and the WG will endeavor to prioritize this list at the beginning of its long-term refinement work. For the WG, “long-term refinement” details WG activity 6 months after the filing of this final report, beginning March 15, 2017 and ending September 15, 2017.

To this end, the WG agrees to identify consensus items where parties have built consensus, and identify specific parties where there is non-consensus and alternative proposals have been made.

3 Discussion Topics, Points of Consensus, Proposed Alternatives if Any, Recommendations, Next Steps

The sections below detail the further refinements to ICA methodology the WG recommends for incorporation. Where possible, recommendations are mapped to the specific section in the ACR.

The WG recommendations can be defined in these categories:1. Use cases of ICA2. Development of common IOU methodology3. Schedule and timelines4. Frequency of updates5. Presentation of values 6. Standardization of methodology7. ACR requirements8. Short-term activities9. Long-term refinement activities10. Modifications to scope and Schedule11. Additional cost recovery12. Recommendation summary table

These recommendations are based on WG meetings and discussion of IOU Demo A reports from May 2016 to March 2017, and focuses only on areas of refinement rather than providing a full summary of

6 See “Next Steps” section

6

Page 7: Executive Summary · Web viewCalifornia Distribution Resources Plan Integrated Capacity Analysis Working Group DRAFT Final Report – Due March 1, 2017 NOTE: This is a first draft

California Distribution Resources Plan Integration Capacity Analysis Working Group

DRAFT Final Report – Due March 1, 2017

NOTE: This is a second draft of the ICA WG report. Comments in tracked changes can be sent to [email protected] and are due Monday EOB, March 6.

Demo A projects. Areas where this WG report does not comment on methodology outlined in final IOU reports is considered as support for, or non-opposition to, methodological choices made for Demo A.

The WG recognizes that this report provides a key resource for the Commission to make a Proposed Decision on the final common methodology to be deployed on system-wide basis across all three IOUs. This full system implementation requires significant effort and resources from the IOUs. Further, it is understood that many methodological choices have practical cost considerations that should be taken into account. These considerations include potential upgrades needed for modeling software, staff resources, and additional tests to further refine methodology. The WG has engaged in discussion around how methodological recommendations may impact estimated costs for implementation and should consider needed granularity to achieve stated ICA use, and on February 27 reviewed IOU estimated costs for implementing ICA system-wide based on different levels of granularity, frequency of updates, and methodology choices.

Iterative Cost ($000) (Year 1) Cost ($000) (Beyond Year 1)

Scenario 1: 96 loading conditions, monthly updatesICA WG Iterative Methodology base case

PG&E $2,040-$3,800 PG&E $1,740-$3,050

SCE $3,300-$6,300 SCE $1,400-$2,600

SDG&E $2,200-$3,300 SDG&E $1,100-$1,700

Scenario 2: 576 loading conditions, monthly updates

PG&E $2,990 - $5,300 PG&E $2,690 - $4,550

SCE $3,800-$7,000 SCE $2,200-$3,900

SDG&E $2,400-$3,500 SDG&E $1,500-$2,200

Scenario 3: 96 loading conditions, weekly updates

PG&E $4,130-$7,100 PG&E $3,830-$6,350

SCE $4,300-$8,100 SCE $2,900-$5,200

SDG&E $3,100-$4,700 SDG&E $2,200-$3,300

Streamlined Cost ($000) (Year 1) Cost ($000) (Beyond Year 1)

Scenario 1: 8760 loading conditions, annual updatesICA WG Streamlined Methodology base case

PG&E $1,480-$3,060 PG&E $680-$1,560

SCE $2,000-$3,600 SCE $600-$1,400

SDG&E $1,700-$2,500 SDG&E $600-$900

Scenario 2: 8760 loading conditions, monthly updates

PG&E $1,630-$3,360 PG&E $830-$1,860

SCE $2,00-$3,600 SCE $1,100-$2,100

SDG&E $1,700-$2,500 SDG&E $900-$1,400

7

Laura Wang, 02/28/17,
Proposed language based on discussion from webinar, looking forward to comments
Page 8: Executive Summary · Web viewCalifornia Distribution Resources Plan Integrated Capacity Analysis Working Group DRAFT Final Report – Due March 1, 2017 NOTE: This is a first draft

California Distribution Resources Plan Integration Capacity Analysis Working Group

DRAFT Final Report – Due March 1, 2017

NOTE: This is a second draft of the ICA WG report. Comments in tracked changes can be sent to [email protected] and are due Monday EOB, March 6.

Scenario 3: 8760 loading conditions, weekly updates

PG&E $1,810-$3,720 PG&E $1,160-$2,470

SCE $3,300-$5,900 SCE $1,700-$3,200

SDG&E $2,300-$3,500 SDG&E $1,500-$2,200

These cost estimates consider resources required to complete the following tasks:1. Model creation and validation: includes 1) the creation of distribution system models by

integrating data from multiple sources, including SCADA Historian, GIS, and Distribution Management System data; and 2) the validation of the distribution circuit models ensuring accurate modeling of the distribution system (i.e., validate that models reflect actual planned conditions).

2. Implement ICA methodology: includes 1) implementation of final ICA methodology on an enterprise-friendly system capable of handling large datasets; 2) development of databases, data structures, and processes; 3) implementation of algorithms and assumptions (e.g., pre-existing conditions); and 4) additional work with vendor community.

3. Run ICA: includes 1) performing ICA on distribution system models and 2) working with vendor community and software licensing. Based on methodology requirements (e.g., number of hours, frequency of updates), computing resources need to be procured and configured. In addition, based on volume of data, computing resource management systems may need to be developed. “Stop and run” of ICA to troubleshoot problems is expected, proportional to the number of scenarios/loading conditions analyzed.

4. Quality assurance and control: Once ICA is complete, the results need to be evaluated for abnormal data due to divergence or modeling issues. These data can include ICA results that fail to converge, which will require manual troubleshooting by engineers.

5. Publication of results: based on the final data attributes, volume of data, and frequency of updates, development work is required to update the mapping systems and integrate these to ICA results databases.

6. Periodic updates: software development to support Tasks 1-5 to meet periodic update requirements as mandated by final ICA methodology, including automatic identification circuitry changes requiring ICA update, and end-to-end integration of processes and data.

WG refinements consider these estimates in context when making recommendations, given the considerable variability contained within the numbers, and difficulty in attributing certain methodological refinements to a proportionate level of additional costs. Level of confidence within estimates among these six categories vary, and some are more significant than others (e.g., frequency of updates is more impactful than number of hours from a cost perspective…?). All parties recognize that these numbers are estimates only. So, while the WG endeavored to weigh these cost estimates within the context of necessary granularity to meet the identified use case, it also realizes the limitations of doing so based on the existing information available for review. These considerations are particularly important with regards to

8

Laura Wang, 02/28/17,
Proposed language based on discussion from webinar, looking forward to comments
Laura Wang, 02/28/17,
This is what I heard from webinar, but if there isn’t confident confirmation, we can just take out.
Page 9: Executive Summary · Web viewCalifornia Distribution Resources Plan Integrated Capacity Analysis Working Group DRAFT Final Report – Due March 1, 2017 NOTE: This is a first draft

California Distribution Resources Plan Integration Capacity Analysis Working Group

DRAFT Final Report – Due March 1, 2017

NOTE: This is a second draft of the ICA WG report. Comments in tracked changes can be sent to [email protected] and are due Monday EOB, March 6.

Development of Common Methodology (Section 3.2), Frequency of Updates (Section 3.4) and Computational Efficiency (Section 3.7.3). 3.1 Use Cases of ICAAt the beginning of the WG process, the WG agreed to identify the specific uses of ICA and make recommendations on ICA based on these concrete use cases, to the full extent possible. The WG expects that methodological considerations regarding frequency of updates, hourly load profiles, the basic methodology (streamlined vs. iterative), and other modeling options, may change based on the use of ICA.

At a high level, the WG has so far identified two uses of ICA:

1. Inform and expedite the Rule 21 interconnection process. In the interconnection use case, ICA information may potentially be used to update Rule 21 interconnection procedures as to expedite the interconnection processes for interconnection requests within the identified ICA level at a given point of interconnection. The WG recognizes that the Rule 21 changes must be made via an appropriate Rule 21 proceeding.

2. Inform and identify DER growth constraints in the planning process. In the planning use case, the ICA information may be used as an input into system planning processes which can potentially be used to identify when and where capacity upgrades are needed on the distribution system as a result of various DER growth scenarios among other possible uses.

The WG report outlines methodological refinements to enable the use of ICA within the interconnection process as determined by a future Rule 21 proceeding, and lays out considerations for the planning use case with a goal of developing methodology recommendations for use within the planning context.

These two use cases of ICA are described in further detail below:

1. Informing interconnection siting decisions and facilitating an expedited interconnection process

The CPUC final DRP guidance document calls for the “dramatic” streamlining of interconnection as one of the key purposes of the DRP7 ICA results can be used in expediting the interconnection study process, and help customers design DER systems that do not exceed hosting capacity by providing accurate information to customers and third parties about the amount of DER capacity that can be interconnected at a specific location (point of interconnection) without significant distribution system upgrades. It is expected that future Rule 21 proceedings will closely coordinate with the development of ICA to implement the recommendation in this report as

7 “Final Guidance Assigned Commissioner Ruling on Distribution Resource Plans. http://www.cpuc.ca.gov/WorkArea/DownloadAsset.aspx?id=5108

9

Laura Wang, 02/27/17,
Note: frequency of updates comments moved to separate section.
Laura Wang, 02/28/17,
Comments reflect discussion on how to describe this use case, using the words “dramatic streamlining,” to “expedited”, etc.Multiple comments suggest using “streamlined” may be confusing to non-WG members (easily confused with “streamlined methodology”).Another comment requests we use “dramatic streamlining” based on Final DRP Guidance doc.
Page 10: Executive Summary · Web viewCalifornia Distribution Resources Plan Integrated Capacity Analysis Working Group DRAFT Final Report – Due March 1, 2017 NOTE: This is a first draft

California Distribution Resources Plan Integration Capacity Analysis Working Group

DRAFT Final Report – Due March 1, 2017

NOTE: This is a second draft of the ICA WG report. Comments in tracked changes can be sent to [email protected] and are due Monday EOB, March 6.

deemed applicable. Thus, the WG proposes that an interconnection use case to be adopted by the Commission include the following considerations pending discussion under a still-to-be opened Rule 21 proceeding or equivalent. Utilities also specifically point out a need to coordinate the application of ICA with regards to timing, configuration, and equipment used for interconnection. The future Rule 21 proceeding should consider for modification to Rule 21 the following:

1. Developers should be able to submit a Rule 21 Fast Track application for DER interconnection up to the identified ICA value at the proposed point of interconnection, based on the ICA map, and be able to pass those screens the ICA has evaluated.

2. The ICA values identified at a point of interconnection are expected to replace the need for some size limits and technical screens in the Rule 21 Fast Track process that currently rely on broad assumptions that can be better addressed through the site-specific analysis contained in the ICA. These include screens F (Short circuit current contribution), M (aggregate generation less or equal to 15% of the line section peak load), G (short circuit interrupting capability), O (power quality and voltage fluctuation) and N (penetration test). These screens should provide developers reasonably strong assurance that if the ICA map shows a certain available capacity at a given location, then a project at that size should be able to pass Fast Track in most circumstances as configured, as long as other Fast Track eligibility criteria are met.

3. Rule 21 proceeding should incorporate a process to include future enhancements to ICA which would address other screens such as screen L (transmission dependency/stability test) and screen P (safety and reliability). This additionally includes functions such as single-phase and other advanced functions which are pending additional information and study through ICA long-term refinements.

4. Rule 21 proceeding should incorporate a process for inclusion of future ICA methodologies which may identify additional criteria or screens that can pass other screens within the Rule 21 fast track process

5. The ICA value used for the interconnection review should be the same ICA value shown on the online maps

6. The ICA shall be frequent enough to allow for a dramatically faster interconnection process for projects that are proposed below the ICA value at their point of interconnection.

7. The ICA should provide monthly and hourly data about hosting capacity limitations that enables a developer to design a system that takes full advantage of the available hosting capacity at their proposed point of development, contingent upon verification and increased communication and visibility to ensure operational profile of these projects abide by ICA hourly limitations. At a minimum, the ICA should be current system-wide on at least a monthly basis and the maps should thereby reflect the updated values at least monthly. This would best be portrayed as the

10

Laura Wang, 02/28/17,
Question from stakeholders: What does this mean??
Page 11: Executive Summary · Web viewCalifornia Distribution Resources Plan Integrated Capacity Analysis Working Group DRAFT Final Report – Due March 1, 2017 NOTE: This is a first draft

California Distribution Resources Plan Integration Capacity Analysis Working Group

DRAFT Final Report – Due March 1, 2017

NOTE: This is a second draft of the ICA WG report. Comments in tracked changes can be sent to [email protected] and are due Monday EOB, March 6.

minimum and maximum load representative of each hour of the day in each month, resulting in 576 data points for each circuit segment.

8. Rule 21 proceeding should identify processes and procedures which are required to insure safety and reliability while maximizing the ICA values to expedite the interconnection process.

9. The iterative method is based on added a fixed incremental level of DER in each grid location until an ICA violation is triggered. In Demo A, this incremental level was _500?__ kW. If this increment is used going forward, the published ICA value for any location will only be available in 500 kW steps, and ICA will provide minimal guidance regarding interconnection of small scale DER such as residential roof top solar. A smaller increment could add value to the ICA, but would increase processing time. The incremental DER value is an additional methodological detail to be considered once the IOUs have provide cost data on processing

2. Distribution system annual planning

The WG determined that there is a role for a planning use case for the ICA, as it is expected that the ICA can help determine and guide where and when future integration capacity may be needed. The WG envisions that ICA results may also guide sourcing and procurement of DER solutions with additional locational granularity in the future. The three IOUs all propose to use the streamlined methodology in the planning context, as the iterative methodology creates a large amount of data, and requires considerable resources to conduct multiple scenario analyses. However, many components of this use case remain undefined, due to multiple ongoing efforts in other CPUC proceedings that will inform how ICA will be used in system planning, as well as the need for further clarity into the utility annual planning process itself. Further, the multiple ways ICA may be incorporated into planning (from guiding grid modernization investments, to how DERs may be evaluated as solutions in the IRP) are quite variable in the level of detail (e.g., granular hourly profiles, frequency of updates, etc.) they require from the ICA methodology. Because many open questions remain about the precise definition of the planning use case, the WG was not able to make specific recommendations regarding the appropriate methodology that would ultimately serve this use case best. Finally, the WG determined that the need to incorporate ICA in planning, while highly important, is less immediate when compared to the use of ICA in expediting the interconnection of DERs through Rule 21 modifications.

Thus, the WG proposes to further define the planning use case as a key high-priority long-term refinement issue beginning March 15, and outlines several considerations for the planning use case going forward:

1. Further refinement of the planning use case will allow the WG to form a specific list of uses of ICA in planning, evaluate the methodological needs for each use case, and determine whether the iterative or streamlined method may better serve that use case.

11

Laura Wang, 03/01/17,
From ORA – I kept here but open to suggestions on where it fits best (alternatively Section 3.2.3?)
Laura Wang, 02/27/17,
Tam Hunt:This is NOT a step forward. We had non-binding and non-actionable interconnection information in online maps 5 years ago. The ONLY way that the ICA information in the maps will be a significant step forward – let alone a “dramatic” step forward – is if the ICA process replaces IN TOTO the Fast Track screens. So for that to happen we need to have the ICA include all relevant screens.
Laura Wang, 03/01/17,
Consensus? Discussion after considering cost estimates?
Page 12: Executive Summary · Web viewCalifornia Distribution Resources Plan Integrated Capacity Analysis Working Group DRAFT Final Report – Due March 1, 2017 NOTE: This is a first draft

California Distribution Resources Plan Integration Capacity Analysis Working Group

DRAFT Final Report – Due March 1, 2017

NOTE: This is a second draft of the ICA WG report. Comments in tracked changes can be sent to [email protected] and are due Monday EOB, March 6.

2. There are steps the IOUs will take to implement the first system-wide rollout of ICA for the facilitation of interconnection which will additionally benefit the deployment of ICA for the planning use case.

3. Achieving these identified uses may require a blended approach (using aspects of both iterative and streamlined methodology) based on future discussion on planning use cases. Refinement conversations may continue to consider the streamlined methodology. The WG appreciates and understands the benefits that employing a streamlined method offers regarding computational resources, and looks forward to better evaluating its application to the planning use case in further WG meetings.

The WG requests further guidance from the CPUC on uses of ICA within the planning context, and the role the WG is expected to play in developing uses that may be included in other proceedings or DRP tracks. To date, some members of the WG have suggested the following discussion items, though these are not met with consensus by the entire WG:

a. The scale, pace and prioritization of ratepayer funded grid modernization investments may be guided by projected ICA values. ICA may be one tool to guide and prioritize ratepayer-funded investments for grid modernization as determined by other proceedings.

b. IOUs may use the ICA to evaluate DER as potential solutions to address needs identified in the Integrated Resources Planning process

c. The current system capacity revealed through the ICA may be combined with location-specific projections of DER growth (i.e., DER growth scenarios) project system needs.

d. IOUs and stakeholders may consider the ICA and LNBA may in tandem to identify opportunities where additions to hosting capacity can enable DER growth and avoid more costly distribution system upgrades.

3.2 Development of Common IOU methodology

3.2.1 Overview

In their Demo A studies, the IOUs tested ICA under two separate methodologies, referred to as the “iterative” and the “streamlined” methodologies. The iterative ICA method is based on iterations of successive power flow simulations, whereas streamlined relies on one baseline power flow. The iterative method parallels detailed study procedures used within the interconnection process relying on direct simulation of resources. The streamlined method relies on one baseline power flow simulation to extract elements of the network models which are then inserted into streamlined algorithms to determine ICA values. During implementation of Demo A projects, the IOUs tested variance between the iterative and streamlined analyses, as well as among the three IOUs, using a reference circuit.

12

Page 13: Executive Summary · Web viewCalifornia Distribution Resources Plan Integrated Capacity Analysis Working Group DRAFT Final Report – Due March 1, 2017 NOTE: This is a first draft

California Distribution Resources Plan Integration Capacity Analysis Working Group

DRAFT Final Report – Due March 1, 2017

NOTE: This is a second draft of the ICA WG report. Comments in tracked changes can be sent to [email protected] and are due Monday EOB, March 6.

The IOUs presented a comparison summary of Demo A results using both methodologies, and outlined recommendations within their Demo reports on which methodology, or portions of methodology, should be employed in a full system-wide rollout. The rationale behind these recommendations is based on lessons learned from the Demo projects and full system-wide implementation considerations, computational efficiency, capability of CYME/Synergi software, and costs. 8

3.2.2 Streamlined method

The streamlined method uses an abstraction approach, applying a set of equations and algorithms to evaluate power system criteria at each node on the distribution system. The streamlined method first performs a baseline power flow and a short-circuit simulation to acquire the initial conditions of the circuit that will be used in the streamlined calculations. These conditions can be, but are not limited to, electrical characteristics such as thermal ratings, resistance, voltages, current, fault duties, etc. The streamlined method then evaluates the full set of criteria, including thermal, voltage, protection, and safety limits independently to determine the maximum hosting capacity at a given node or component of the system. Simpler methods utilized in the streamlined methodology may not capture some of the more dynamic effects on the more complex circuits. However, the ability to utilize simpler equations and algorithms can enable faster computations on more scenarios and hours.

3.2.3 Iterative method

The iterative method performs an iterative power flow simulation at each node on the distribution system. The iterative method solves for thermal and voltage conditions simultaneously using voltage simulations. Fault flow simulations are used for protection criteria not dependent on power flows. Due to the large number of iterations required, iterative analysis can result in long processing times, especially when expanded to large numbers of distribution circuits. However, the use of an iterative simulation parallels what IOUs would perform as part of a detailed interconnection study. This technique is expected to provide more confidence in representation of integration capacity on more complex circuit conditions.

3.2.4 Recommendations

The WG recommends a consistent approach be used across all three IOUs in order to facilitate future advancements and maintain consistency across the state, and in accordance with the Commission guidance ruling.

After multiple meetings, two different recommendations were developed:

1. A majority of the WG (SCE, SDG&E, and all WG stakeholders involved in the active development of this report) recommended that the iterative methodology be used for the interconnection use case

8 Reference to IOU ICA reports

13

Laura Wang [2], 02/16/17,
Please let me know if your party would like to include an alternative recommendation here
Laura Wang, 02/28/17,
From ORA: ORA is not sure whether the WG should support the “blended” method, since the use case for such a method has still not been adequately defined, nor has the cost information for the need of a blended approach been identified. Essentially, having three separate methodologies (iterative, blended, and streamlined) would further complicate the process of defining one standard methodology between the utilities.
Page 14: Executive Summary · Web viewCalifornia Distribution Resources Plan Integrated Capacity Analysis Working Group DRAFT Final Report – Due March 1, 2017 NOTE: This is a first draft

California Distribution Resources Plan Integration Capacity Analysis Working Group

DRAFT Final Report – Due March 1, 2017

NOTE: This is a second draft of the ICA WG report. Comments in tracked changes can be sent to [email protected] and are due Monday EOB, March 6.

(with the following refinements detailed in this report) to update the interconnection maps, expedite the interconnection process and be deployed in the first system wide deployment of ICA.. Within their Demo A reports, SCE and SDG&E supported the use of iterative method as appropriate means of supporting the interconnection processes, as the iterative method parallels the study procedures followed in the Rule 21 process, and considered that future changes to Rule 21 may be potentially be significantly simplified with the use of the iterative method

2. Separately, PG&E recommends a “blended” approach, using both the iterative and streamlined methods within the interconnection use case. The streamlined method would be applied to an overall analysis for the whole system, and iterative would be utilized to analyze specific conditions within the interconnection process.

This divided recommendation is driven by several factors. First, the results of the Demo A in the final IOU reports raised many stakeholder concerns regarding whether the streamlined methodology produced results with sufficient accuracy to be relied upon within the interconnection process, without forcing additional caveats and manual review. Thus, many WG members deemed the streamlined methodology as insufficient for meeting the interconnection use case.

The WG additionally discussed using a “blended” streamlined/iterative approach, as detailed in the PG&E Final Demo A report. Within this approach, the streamlined method would be applied to an overall analysis for the whole system, and iterative would be utilized to analyze specific conditions within the interconnection process. Within PG&E’s Demo A report, it was included that this adopting the application based iterative and system wide streamlined recommendation would allow PG&E to more efficiently use existing resources and tool capabilities. Additionally, PG&E states that the blended approach better parallels an efficient tiered Rule 21 process that has proven to be a major success in California that promotes an efficient and accurate interconnection process.

PG&E notes that adoption of this blended approach would require fewer engineering resources. PG&E projects that if iterative is required for use then a new team would be needed to manage the ICA process. It is projected that if streamlined is adopted and the iterative approach is adopted more efficiently on application basis then the new work load can be more efficiently managed with current engineering resources.

PG&E is also undergoing existing planned work on modifications to its gateway to (1) utilize the new GIS system implemented in 2016, (2) expand the gateway to include substation models, and (3) expand its ability to include service transformers in the models. If recommendations require the incorporation of planned modifications and automated iterative across the whole system then significant additional work would be required on the gateway and could postpone work to include substation and service transformers. Also, if PG&E’s recommendation of application based used of iterative is not adopted, then more engineering resources would have to be hired and trained in order to perform the regular iterative ICA analysis. Adopting the application based iterative and system wide streamlined recommendation would allow PG&E to more efficiently use existing resources and tool capabilities

14

Laura Wang, 03/01/17,
From IREC:I would find it helpful if the preceding and following comments could be clarified to make it clear whether PG&E’s desire to use a blended approach is largely driven by their own unique circumstances, or whether they would be making that recommendation either way. I also think it would be helpful for the Commission if PG&E explained why the tradeoff of not having an ICA map that matches the interconnection outcome is worth making]
Laura Wang, 02/27/17,
Stakeholder comment for PG&E response:I don’t know what this means. The interconnection process is not ICA. It sounds like they are proposing streamlined for ICA and iterative for interconnection review
Page 15: Executive Summary · Web viewCalifornia Distribution Resources Plan Integrated Capacity Analysis Working Group DRAFT Final Report – Due March 1, 2017 NOTE: This is a first draft

California Distribution Resources Plan Integration Capacity Analysis Working Group

DRAFT Final Report – Due March 1, 2017

NOTE: This is a second draft of the ICA WG report. Comments in tracked changes can be sent to [email protected] and are due Monday EOB, March 6.

WG discussions of the “blended” approach as suggested by PG&E concluded that the approach was unsatisfactory in meeting the goal of the interconnection use case, which seeks to move towards an automated process that requires less manual review by engineers and would enable the ICA information displayed on the map to be the same as what is applied in the interconnection process. Additionally, the WG discussed that there may be reasonable ways to reduce the data intensity while utilizing more efficient computing resources to address concerns regarding computational intensity of the iterative method. In the long run, it seemed likely to the majority of the WG that the costs of the computing issues could be reasonably managed as technology and understanding of the ICA methodology advance. Finally, the WG emphasizes a desire to maintain a consistent approach across all three IOUs in order to facilitate future advancements and limit confusion across the state.

The WG also recommends that the WG and IOUs continue to evaluate the streamline method for potential use in the planning use cases. Given that planning use cases are still being evaluated, the WG recommends that further discussion is needed to determine the appropriate ICA methodology for the planning use case and that continued discussion of the streamline method as support to the planning use case be part of long-term refinements to ICA.

3.3 Schedule and TimelinesStakeholders and the IOUs have separate recommendations with regards to when IOUs implement ICA across their service territory. In both recommendations, the ICA methodology should include the identified short-term recommendations from the final report. Further discussion is below in section 3.10, Modifications to Scope and Schedule.

All three IOUs (plus X stakeholders) recommend that the ICA is implemented within 12 months of a CPUC decision on final ICA methodology.

Other stakeholders recommend that the IOUs begin the implementation process following the publishing of the ICA Final WG report, and finish implementation within 12 months of final report submission.

Further, the WG recommends that the Commission establish two processes to incorporate modifications to the ICA both as part of the implementation of ICA system wide on its first rollout and as future enhancements are added to the methodology. These processes should balance the need for flexibility in implementation and appropriate CPUC practices for review:

1. As the utilities continue to refine and enhance the ICA methodology through long term enhancements to ICA and based on future advanced studies, such as inclusion of smart inverters, single phase line sections and transmission impacts, it is requested that the Commission establish a process to allow the ICA WG to collaborate and determine how enhancements to the methodology are to be deployed system wide (what about approval process?). The WG views the ICA methodology as one which will continue to evolve in an expedited and effective manner. This process should provide flexibility to phase in refinements within boundaries established by the CPUC. The Commission

15

Laura Wang, 02/27/17,
As written, includes discussion on potential things included in first system roll out?
Laura Wang, 02/28/17,
The WG recommends the CPUC establish a process that allows the IOUS expeditiously inform stakeholders and implement the change in plans. Specifically, WG recommends that the CPUC establish a process by which IOUs could modify the planned scope and schedule of the ICA implementation by filing a Tier 1 Advice Letter. This process would allow changes to be formalized and visible to all parties, and the AL process provides an opportunity for stakeholders to formally respond to the modifications.
Laura Wang, 02/27/17,
Brandon Smithwood:This is another good question related to my question above. Should the ICA be revised by rulemaking (that would be WAY too cumbersome), WG/or staff (seems too informal), revisions to the interconnection handbook (too much utility control), advice letter (maybe this fits the goldilocks standard and is “just right”)?
Laura Wang, 02/27/17,
WG comments/feedback on report needed on “Commission guidance on what is appropriate, gives appropriate levels of flexibility and maintain consistency with CPUC guidance”
Laura Wang, 02/27/17,
Brad Heavner:I’m wary of creating a formal WG approval process and having the CPUC rely on it. We need next steps for CPUC action in addition to flexibility to implement changes that are consistent with CPUC guidance.
Laura Wang, 02/28/17,
Please ID if any?
Page 16: Executive Summary · Web viewCalifornia Distribution Resources Plan Integrated Capacity Analysis Working Group DRAFT Final Report – Due March 1, 2017 NOTE: This is a first draft

California Distribution Resources Plan Integration Capacity Analysis Working Group

DRAFT Final Report – Due March 1, 2017

NOTE: This is a second draft of the ICA WG report. Comments in tracked changes can be sent to [email protected] and are due Monday EOB, March 6.

should decide whether this process takes the form of a revised rulemaking, consultation with ICA WG or Energy Division staff, advice letter, etc.

2. The methodology and refinements recommended in this report are based on the best available knowledge of software and tool capabilities, costs of implementation, and complexity of the project. Further, there are several meaningful recommendations made in this report that were not required to be tested as a part of Demo A, but were discussed among the WG as part of its direction from the ACR to “improve and refine the ICA methodology.” For these recommendations, the WG engaged in discussion regarding the need for changes, and the practical feasibility of incorporation within either the initial system-wide rollout, versus establishing as longer-term goals. Given the scope and complexities of system wide implementation of ICA, the WG acknowledges that new challenges and limitation will surface that are not possible to predict at this time, but may arise during full system rollout, and recommends that the Commission establishes a process for the IOUs to modify scope and schedule of the roll out due to these unforeseen circumstances. It is recommended that these requests are brought to the CPUC Energy Division for resolution. For those changes, the WG expects that IOUs will prioritize their resolution in the next iteration of ICA, and work with stakeholders on refinements that may be necessary as a result of new learning.

3.4 Frequency of UpdatesThe WG recommends that ICA should be updated frequently enough to allow for a meaningful impact to interconnection process for projects that are proposed below the ICA value at their point of interconnection. To meet this goal, WG stakeholder have diverse opinions on the appropriate frequency of updates to system wide ICA values.

Some WG stakeholders believe that, at a minimum, system-wide ICA values should be updated annually and that specific ICA values be at minimum updated at least monthly to reflect new projects or other system changes above a defined threshold, to allow the ICA figure shown on the maps to provide the most accurate ICA to be used for interconnection requests. The ICA should be run system-wide as needed to reconcile local changes. Interconnection approval will be contingent upon sufficient capacity in the secondary distribution system until such time as the secondary can be included in the ICA.

SCE supports system-wide monthly updates for the initial rollout with consideration of additional functionality and higher levels of frequency of updates in subsequent iterations, such as case-by-case updates, weekly or on demand updates contingent upon cost and funding and system capabilities.

PG&E notes that these envisioned condition-based updates requested by some WG stakeholders will require significant front-end coding and development to implement properly, and may create additional costs and/or delay implementation.

16

Laura Wang, 02/28/17,
See above – need discussion or guidance on best practice
Page 17: Executive Summary · Web viewCalifornia Distribution Resources Plan Integrated Capacity Analysis Working Group DRAFT Final Report – Due March 1, 2017 NOTE: This is a first draft

California Distribution Resources Plan Integration Capacity Analysis Working Group

DRAFT Final Report – Due March 1, 2017

NOTE: This is a second draft of the ICA WG report. Comments in tracked changes can be sent to [email protected] and are due Monday EOB, March 6.

As a long-term vision in future years, and not part of the ACR’s long-term refinement scope (final ICA long-term refinement report 6 months from now), some members of the WG envision that the ICA should be updated on a real-time or daily basis to the extent possible to allow the reflecting values to be used in an automated interconnection process. Future enhancement should work towards this goal, while considering issues such as the following in coordination with the Rule 21 proceeding:

1. Development of automated interconnection studies which considers specific application information that cannot be known ahead of time to be reflected in ICA. Generation queuing, commercial operation dates, and planned work/transfers can all have a unique impact on certain locations in the system, which must be considered application-by-application with manual engineering review, since specific elements can’t be predicted or known ahead of time.

2. Consider stricter enforcement of applicant timelines and milestone provisions to prevent the risk of individuals claiming queue positions via speculative process.

3. Cost considerations to develop necessary tools and procedures.

3.5 Presentation of ICA valuesICA information will be presented in both online maps and downloadable data formats. The ICA information to be used in the maps and to be downloadable is based on the (1) the unconstrained operation ICA value for generation (Technology-Agnostic ICA value) , (2) the unconstrained operation ICA value for load (Technology-Agnostic ICA value) and (3) ICA value using a typical fixed PV production shape. The WG will provide a review of existing assumptions IOUs have used and, as part of the ICA WG’s long term refinements, develop a standard PV generation profile to be used within the online map that is sufficiently conservative to be relied upon for interconnection approval. In addition, the IOUs developed an offline ICA Calculator that can be used to determine ICA values at specific locations for user-defined DER profiles. Users may “toggle” maps to make maps specific to certain technologies.

The ICA value used for the interconnection review should be the same ICA value shown on the online maps – as noted above, at a minimum, the ICA should be current system-wide on at least a monthly basis and the maps should thereby reflect the updated values at least monthly. [

3.6 ACR Requirements

3.6.1 Modeling and extracting power system data

The IOUs used either LoadSEER or an equivalent load forecasting analysis tool to develop load profiles at the feeder, substation, and system levels. In Demo A, IOUs aligned load allocation methodology with current interconnection practices, and further detailed how weather assumptions were incorporated through separate written responses9.

9 http://drpwg.org/wp-content/uploads/2016/07/WG-Recs-and-Questions-SCE-PGE-SDGE.docx

17

Brandon Smithwood, 02/20/17,
I still don’t think we should settle for monthly since as far as I can tell that is an arbitrary frequency.
Laura Wang, 02/28/17,
Comment from Tom Roberts ORAPG&E’s map allows for users to toggle between different types of DERs (uniform generation, uniform load, and solar PV ), SCE does not include this function, [SDG&E?]. There should be consistency across the utilities’ maps, allowing for users to choose among these three profiles in order to easily see integration capacity at various line segments.
Page 18: Executive Summary · Web viewCalifornia Distribution Resources Plan Integrated Capacity Analysis Working Group DRAFT Final Report – Due March 1, 2017 NOTE: This is a first draft

California Distribution Resources Plan Integration Capacity Analysis Working Group

DRAFT Final Report – Due March 1, 2017

NOTE: This is a second draft of the ICA WG report. Comments in tracked changes can be sent to [email protected] and are due Monday EOB, March 6.

Stakeholders of the WG posed questions on assumptions used in load forecasting, including questions on inclusion of weather conditions (e.g., temperature, irradiance, wind speed, concurrent with each hour of the load forecast). Because load forecasts are significant factors in forecasting grid conditions and which can influence ICA values, the WG recommends that the findings and recommendations from the CPUC workshop from Track 3, sub-track 1 on Load and DER forecasting, as well as all findings from this DRP sub-track, be incorporated as appropriate into the ICA to coordinate the load forecasting methods used in determining ICA value. Within the ICA long-term refinement period, some members of the WG would like to further examine underlying weather assumptions.

The WG additionally provides the following considerations, to help inform the Track 3 process:- Stakeholders of the WG believe additional transparency can be provide regarding underlying

weather assumptions from which IOU high and low load hours are derived. Understanding the conditions underlying load forecasts is important if developers are meant to model DER performance to ensure hosting capacity limits are not violated.

- Currently, there is divergence among the methodology employed by the three IOUs. Stakeholders of the WG would like to further understand reasons for methodological divergence.

- Within PG&E and SDG&E’s methodology, some stakeholders would like to further understand whether the synthetic days created are sufficiently reflective of real conditions that would be experienced on the distribution system.

3.6.2 Power system criteria methodology

ICA results are dependent on the most limiting power system criteria. The four criteria used for Demo A are:

1. Thermal criteria: amount of additional load and generation that can be placed on the distribution feeder without exceeding equipment thermal ratings

2. Power quality/voltage criteria: steady state voltage violations and voltage fluctuation calculated based on system voltage, impedances and DER power factor. Violations outside of Electric Rule 2 and voltage fluctuation of up to 3% is part of system design criteria for all three utilities.

3. Protection criteria: amount of fault at various detective devices factoring in contributions from DER.

4. Safety/reliability criteria: operational flexibility that accounts for reverse power flow issues when DER/DG is generating into abnormal circuit operating scenarios. Other limitations supporting the safe and reliable operation of the distribution system apply.

5. Additional on steady-state voltage?

18

Laura Wang, 02/27/17,
Ask IOUs for clarity
Page 19: Executive Summary · Web viewCalifornia Distribution Resources Plan Integrated Capacity Analysis Working Group DRAFT Final Report – Due March 1, 2017 NOTE: This is a first draft

California Distribution Resources Plan Integration Capacity Analysis Working Group

DRAFT Final Report – Due March 1, 2017

NOTE: This is a second draft of the ICA WG report. Comments in tracked changes can be sent to [email protected] and are due Monday EOB, March 6.

The WG developed recommendations regarding the input assumptions for the power system criterion. To the extent possible, the WG identified where methodological changes may apply to specific use cases.

3.6.3 Power quality/voltage criteria

The IOUs take various approaches to how they treat voltage regulating devices within the iterative methodology. Devices may be “locked”, meaning that these voltage regulating devices do not adjust from one simulation to the next simulation in the ICA automation modules, or the devices can be “unlocked”, meaning that these voltage devices adjust to maximize voltage profile from one simulation to the next in the ICA automation modules. Currently, CYME software does not have the capability for “unlocked” operations allowing voltage control devices to adjust during ICA iterations (refers to as “float”), while Synergi does have that capability. Through WG meetings, it was explained that the CYME module used for Demo A locked voltage devices to better allow for modeling convergence. Although allowing devices to float more closely models real-world conditions and results in a higher ICA, it adds to modeling complexity.

The WG is in consensus recommendation that voltage regulating devices should be “unlocked” within the iterative methodology, but are not in consensus with regards to timing of implementation.

- PG&E, SCE, and SDG&E recommend that for the first system-wide rollout, voltage regulating devices may be operated as applied in Demo A for each IOU, but the IOUs should work with software vendors to encourage the inclusion of an optional function to “unlock” the voltage regulating devices into the power flow modeling tools automation modules. As this requires action and commitment from vendors, this function should not be required for the first system-wide rollout but rather on subsequent rollouts when the function has been added to the power flow tools. The WG should continue to evaluate the value of not locking down the voltage regulator.

- Other WG stakeholders recommend that IOUs work with software vendors to encourage its inclusion into the first system-wide rollout, given that software vendors have already shown the capability to do so.

The WG is open to continued discussion on the number of iterations of adjustment as determine the most accurate ICA value efficiently.

3.6.4 Safety/reliability, or “operational flexibility”

Feeders contain a web of cross-ties that allow utilities to reconfigure circuits in response to faults or during system maintenance. Utilities like to maintain maximum operational flexibility to reconfigure circuits quickly. This creates a challenge for evaluating hosting capacity because the reach of a DER system’s impact is not only along the circuit to which it is normally connected but also to all other circuits to which is could potentially be actively connected. A DER system that could impact the

19

Page 20: Executive Summary · Web viewCalifornia Distribution Resources Plan Integrated Capacity Analysis Working Group DRAFT Final Report – Due March 1, 2017 NOTE: This is a first draft

California Distribution Resources Plan Integration Capacity Analysis Working Group

DRAFT Final Report – Due March 1, 2017

NOTE: This is a second draft of the ICA WG report. Comments in tracked changes can be sent to [email protected] and are due Monday EOB, March 6.

functionality of a protective device on an adjacent feeder is considered even if the two items are not electrically connected during normal operating conditions.

Demo A required two power flow methodologies for compliance with the ACR ruling which states that:

The demonstration is to employ two different methodologies of calculating the ICA values using:a) A scenario which limits power flow analysis to ensure power does not flow towards the

transmission system beyond the distribution substation bus;

b) A scenario which determines the technical maximum amount of interconnected DERs that the system is capable of accommodating irrespective of power flow direction;

To comply with the requirements of (a), the IOUs employed a method which prevented reverse flow of power across any SCADA-operated device in the distribution feeders. This method ensured that no power would be send toward the transmission system as required by (a).

To comply with (b) the IOUs removed the limitation at the SCADA devices. This method provided an ICA value irrespective of power flow direction as required by (b).

The method of calculating the requirements for (a), where the utilities applied a “no power flow across SCADA devices”, also served as limitation to provide an “operational flexibility limit” as required to maintain safety and reliability. This operational limit is required to maintain the operation of the distribution system without affecting distribution system reliability. That is, this methodology is designed to allow the highest levels of DER to be connected to the distribution feeder, without a reduction on operation of the distribution system in order to ensure that any switching operation does not create safety or reliability concerns.

The intent of the safety/reliability constraint is to ensure that all operational flexibility is preserved when DERs are added to the grid. The SCADA-operated devices represent points at which the grid can be reconfigured, either permanently or temporarily. Because the ability of the grid to tolerate reverse flow depends on the configuration, by prohibiting reverse flow at these points, the ICA determines the DER adoption that produces no reverse flow in any configuration.

The WG recognizes that the operational flexibility criterion as implemented and described above is based on engineering practices that allow for calculation of the operational flexibility criteria across all circuits. Consequently, the results of Demonstration A show that operational flexibility, as currently modeled by the IOUs, is a significant limit to ICA that produces conservative results which ensure power quality to all customers and DER.

A goal of the development of the ICA methodology was to avoid heuristics to the degree possible and to favor engineering analysis. Some WG members agree that the operational flexibility criterion could

20

Page 21: Executive Summary · Web viewCalifornia Distribution Resources Plan Integrated Capacity Analysis Working Group DRAFT Final Report – Due March 1, 2017 NOTE: This is a first draft

California Distribution Resources Plan Integration Capacity Analysis Working Group

DRAFT Final Report – Due March 1, 2017

NOTE: This is a second draft of the ICA WG report. Comments in tracked changes can be sent to [email protected] and are due Monday EOB, March 6.

accurately be described as a heuristic, while other members believe that this limit is based on a proven engineering practice used to prevent power quality issues and not necessary heuristic in nature.

The operational flexibility criterion based on no reverse power flow across SCADA-operated devices was implemented in Demo A because no other options for ensuring operational flexibility were identified and determined to be feasible given the current understanding of the capabilities of either the iterative or streamlined methods. The WG agrees that this was a reasonable short-term path, but believes that developing an improved approach to evaluating DER adoption limits related to operational flexibility should be an ICA development priority.

Additionally, The IOUs included in their Demo A projects a no reverse flow limits across voltage regulators as to prevent power quality and voltage limits. This is because as existing voltage regulators (both field and substation) may not currently be adequate to allow for backflow, and existing control settings may not be adequate to properly manage increased levels of DER (some controls are programed to existing system conditions). Voltage regulators and LTCs require finite setting based on the load and DER connected to the voltage regulators. Thus, allowing reverse power flow on voltage regulator without varication on regulator capability to accept reverse power flow or without evaluating that the voltage regulator settings may cause power quality issues for load and DER customer.

First System Rollout Recommendations

Therefore, the WG agrees and recommends that the operational flexibility criterion based on no reverse power flow across SCADA-operated devices is a reasonable short-term solution to the preservation of operational flexibility. Therefore, the IOUS should calculate the ICA values both, with and without this constraint in the first system-wise rollout of the ICA in order to start that process without waiting for further refinement of the criterion. The WG recommends that in the first system-wide rollout of ICA results, two values are published:

1. Uniform Generation ICA values as applied in Demo A with Operational flexibility limitations on SCADA devices

2. Uniform Generation ICA values allowing reverse power flow across the SCADA devices up to the substation low-side busbar and without allowing reverse power flow to the high-side busbar across the substation transformer towards the transmission system

Publishing both values will better indicate the hosting capacity where this factor is mitigated or determined to be non-constraining through Supplemental Review. It is important to note that this second value is different than the value tested in Demo A.

Considerations for Long-Term Refinement

Many WG members place high priority on development of an improved operational flexibility value as a key long-term refinement item. For these WG members, it is envisioned that the WG develop an improved, less conservative approach based on engineering analysis that evaluates whether a limit on

21

Page 22: Executive Summary · Web viewCalifornia Distribution Resources Plan Integrated Capacity Analysis Working Group DRAFT Final Report – Due March 1, 2017 NOTE: This is a first draft

California Distribution Resources Plan Integration Capacity Analysis Working Group

DRAFT Final Report – Due March 1, 2017

NOTE: This is a second draft of the ICA WG report. Comments in tracked changes can be sent to [email protected] and are due Monday EOB, March 6.

operational flexibility actually results in any safety or reliability impacts. This new approach may be enabled by an improved understanding of the ICA’s ability to evaluate a large number of scenarios and configurations or by a discussion of how the utilities study the operational flexibility impact of an interconnection application that requires such a study. This improved value is expected to replace Screen P (the Safety and Reliability Screen) within the Rule 21 process.

These WG members additionally recognize that utility or third-party commands to DER systems with advanced inverters may be one solution to this limitation. However, that capability will only be available after the CPUC develops rules for contractual relationships between utilities and DER system owners. These WG members encourage the CPUC to begin that work in the IDER proceeding as soon as possible, and additionally intend to pursue alternative methodologies within the ICA. This view is not shared across IOUs, which would like to examine whether the problem may be solved in future years independent of new WG methodology, through the implementation of other potential solutions such as the implementation of future DERMS solutions which would provide high levels of visibility and control which would mitigate the system flexibility limitation. The WG will determine a more detailed priority list of items in the beginning stages of the long-term refinement process.

Some WG recommend that the PUC consider the following questions of the interplay between ICA and operational flexibility:

1. If increased DER adoption has the potential to become a consideration in operational flexibility, how can we quantify the impact of the change in operational flexibility?

2. What kind of change in operational flexibility is appropriate to reach policy goals related to DER adoption?

3. Are there technical and/or policy solutions to expand ICA while still preserving operational flexibility?

4. Given that DERs will provide some positive impacts on reliability and resiliency, what are appropriate trade-offs with regards to operational flexibility?

Understanding these questions may require a separate research initiative or pilot project and which may negatively impact the ability to serve DERs and customers. Some WG members view that reduction of operation flexibility which impacts customer service reliability in favor of increasing ICA is contrary to the goals of DER implementation.

3.6.5 Circuit models

Unlike the transmission system, the IOUs have not historically created computer models of their substations and distribution circuits such that engineering analyses such as power flow and short-circuit analyses can be performed. PG&E modeled its distribution system in ___ to ____. SDG&E modeled its distribution system as part of Demo A. SCE modeled 83 of its circuits are part of Demo A, it is currently modeling the balance of its system, and expects to complete this process in ____, barring further direction from the CPUC. While the IOUs build these models using the best available data, the models and underlying data may require adjustment if power flow models do not converge on a solution during

22

Page 23: Executive Summary · Web viewCalifornia Distribution Resources Plan Integrated Capacity Analysis Working Group DRAFT Final Report – Due March 1, 2017 NOTE: This is a first draft

California Distribution Resources Plan Integration Capacity Analysis Working Group

DRAFT Final Report – Due March 1, 2017

NOTE: This is a second draft of the ICA WG report. Comments in tracked changes can be sent to [email protected] and are due Monday EOB, March 6.

ICA analysis. In the streamlined analysis, only one power flow analysis is performed and model adjustment is only required once (except when circuits change as discussion below). With the iterative method, additional model adjustments may be required during any of the hundreds or thousands of power flow analyses performed for each circuit, as adding DER in each location has a different impact. PG&E found that significant model adjustment was required when running the iterative method in Demo A, even though it had vetted its models to perform its streamlined analysis.10

Separately, IOU distribution circuits are constantly changing due to circuit reconfigurations, new utility equipment, new or modified loads, and DER additions. IOU circuit models must be routinely updated and vetted for ICA values to be current and accurate. PG&E has a methodology for incorporating circuit updates into its circuit models on a weekly basis, but these updates cannot yet be included in an iterative ICA. SDG&E? SCE? ICA cannot be deployed on a system wide basis until each IOU develops a means accurately incorporate changes in the distribution circuits and loads. may Therefore, the WG recommends the IOUs’ present to the WG the ability to incorporate changes to their circuit models before a full circuit modeling takes place.

3.6.6 Pre-existing conditions

The WG identified a challenge whereby circuit models sometimes display violations of one or more power system criteria before the DER adoption is modeled, resulting in a hosting capacity of zero (i.e., a pre-existing condition on the circuit is responsible for the violation). A targeted DER solution may not impact the existing violation criteria, and in some cases, could even improve the existing violation criteria. However, it may be difficult to automatically determine whether adding a DER solution worsens a violation criteria or creates an entirely new violation.

To address this condition, the IOUs understand that (1) ICA should be limited by pre-existing conditions when adding DER degrades the pre-existing condition and (2) that ICA not be limited by a pre-existing condition when adding DER improves the pre-existing condition. For example, in a situation when low voltage exists in an area, adding generation may improve the low voltage condition but adding load may degrade the pre-existing conditions. In this particular example, generation ICA would not be limited by the pre-existing condition but load ICA would be limited by the pre-existing condition. It must be noted that in some cases, such as substations with LTC control, adding generation to a low voltage pre-existing condition may actually further degrade the low voltage condition rather than improve the low voltage condition.

The IOUs would need to create automated processes as part of the ICA implementation plan to efficiently evaluate the feeders and substations for pre-existing conditions. These processes would need to determine if any pre-existing conditions exist and to determine if adding DER would improve or degrade the detected pre-existing condition and take the necessary action to determine when ICA can be allowed or when ICA must be limited by the pre-existing condition. The IOUs expect that this process

10 PG&E final Demo A report. http://drpwg.org/wp-content/uploads/2016/07/R1408013-PGE-Demo-Projects-A-B-Final-Reports.pdf

23

Brad Heavner, 02/20/17,
No more demonstrations. We have to do full system rollout now to the best of our abilities.
TOM roberts, 02/20/17,
We need to be clear here: did PG&E actually test and determine this in Demo A, or is this extrapolated from the testing it actually performed.
Page 24: Executive Summary · Web viewCalifornia Distribution Resources Plan Integrated Capacity Analysis Working Group DRAFT Final Report – Due March 1, 2017 NOTE: This is a first draft

California Distribution Resources Plan Integration Capacity Analysis Working Group

DRAFT Final Report – Due March 1, 2017

NOTE: This is a second draft of the ICA WG report. Comments in tracked changes can be sent to [email protected] and are due Monday EOB, March 6.

would require significant IT resources to automate and/or significant engineering resources to properly consider evaluate pre-existing conditions on a regular basis.

3.7 Short-term activities The ACR outlines seven discrete activities for WG consultation related to Demo A (ACR Section 3.1). The IOUs consulted with the WG on each of these topics in 2016. A summary of those topics, discussions, and recommendations are included below.

3.7.1 ACR Section 3.1.b: Recommend methods for evaluation of hosting capacity for the following resource types: i) DER bundles or portfolios, responding to CAISO dispatch; ii) facilities using smart inverters

3.7.1.1 With regards to DER bundles or portfolios responding to CAISO dispatch

For Demo A, the IOUs explored how hourly limits can differ depending on the DER technology or portfolio, without calculating separate ICA for each DER type. Through Demo results, the IOUs concluded that location (distance from substation), rather than temporal variance, may be a more significant driver of ICA variation. This supports locational mapping of single values to be the more effective publication, while raw temporal profile publication will be supplemental.

The IOUs recommend continuing the use of a technology-agnostic approach in a full system-wide rollout of ICA, rather than making assumptions about CAISO dispatch, or other specific resource types. The WG is in agreement and recommends that utilities continue with use of a technology-agnostic approach on determine ICA values and not be required to determine ICA values based on technology specific, DER bundles or portfolios.

3.7.1.2 With regards to smart inverters

The WG envisions that smart inverters can influence the ICA in two ways: smart inverters may in certain conditions support greater hosting capacity on the system, and DER with smart inverters may be able to address integration capacity limitations.

Within Demo A, the IOUs began analysis to start understanding the impact of smart inverters on ICA. IOUs limited their Demos A study to the Smart Volt/Var function which when used properly may have ability to reduce voltage impacts caused by DER. These capabilities were tested on a limited basis by each utility using either the streamlined method or the iterative method.

The utilities performed ICA calculations applying a limited set of smart inverter capabilities on one distribution feeder to determine how smart inverters may be able increase the integration capacity. The capabilities tested were a static volt/VAR curve (SCE) and fixed power factor (PG&E and SDG&E). The

24

Page 25: Executive Summary · Web viewCalifornia Distribution Resources Plan Integrated Capacity Analysis Working Group DRAFT Final Report – Due March 1, 2017 NOTE: This is a first draft

California Distribution Resources Plan Integration Capacity Analysis Working Group

DRAFT Final Report – Due March 1, 2017

NOTE: This is a second draft of the ICA WG report. Comments in tracked changes can be sent to [email protected] and are due Monday EOB, March 6.

studies indicated that smart inverter may in certain system condition be able to support higher levels of ICA. However, the studies performed in the Demos A with smart inverters was very limited and additional studies are required to determine how smart inverters can be used to support higher levels of ICA without causing distribution system problems.

Additional studies, methodology development, and software enhancements are required to incorporate smart inverters in the near term. The ICA WG agrees that smart inverter functionality be included into ICA calculations when the adequate studies have been completed, the functional methodology has been agreed and developed, and tools are capable of implementing smart inverter technology in automated and efficient manner. The scope of studies will be determined with WG as part of long term enhancement to ICA and if studies, methodologies, and tool enhancements are developed in time for inclusion to the first system wide roll out, then those functions of smart inverters would be added to the first system wide roll out; otherwise, the IOUs will include the agreed upon-smart inverter functions in subsequent iterations of ICA as studies are completed, methodologies are developed, and tools are enhanced.

The WG identified several recommended studies to undertake, including static volt/VAR and fixed power factor functions, as inverter standards are finalized through the IEEE process and as smart inverters begin to enter the market. These studies should consider two overarching questions: 1) at what point can smart inverters be expected to have an impact on increasing hosting capacity? 2) once smart inverters are implemented as common practice, how much will they impact hosting capacity?

Though CYME and Synergi currently have the capability to model advanced inverter functions, certain functionalities (e.g., fixed power factor, dynamic volt/VAR) are currently not included in ICA modules. Inclusion of additional functionalities may depend on development of assumptions and additional studies, and will require work with CYME and Synergi for incorporation into the ICA modules. SCE identified the following areas of additional evaluation:

i. How the various smart inverter functions and applicable function ranges affect ICA values

1. Volt/Var2. Fix Power Factor3. Volt/Watt4. Function prioritization5. Phase II communication implications6. Phase III advanced functions implications7. Future IEEE 1547 oversizing implications if approved

ii. Identify the settings and curves will be used can provide maximum ICA without negatively affecting the distribution system

iii. Determine effects of application of smart inverter function to the distribution system reactive capacity and system efficiency

iv. Others studies as determined by the ICA WG

25

Laura Wang, 03/01/17,
Any WG agreement here on these areas of additional evaluation for us to say “WG”?
Laura Wang, 02/27/17,
Brad Heavner:There is already a near-final draft of the IEEE standards. They will be adopted in 2017. Final adoption should not slow us down from developing methodology and including it in ICA as soon as it is ready on our end.
Page 26: Executive Summary · Web viewCalifornia Distribution Resources Plan Integrated Capacity Analysis Working Group DRAFT Final Report – Due March 1, 2017 NOTE: This is a first draft

California Distribution Resources Plan Integration Capacity Analysis Working Group

DRAFT Final Report – Due March 1, 2017

NOTE: This is a second draft of the ICA WG report. Comments in tracked changes can be sent to [email protected] and are due Monday EOB, March 6.

Additional studies have been recommended by some WG members to much longer-term goals (2-4 years) for smart inverter inclusion, which will require additional policy discussion. . These are listed here, and may be revisited as a long-term refinement topic:

v. Static volt/VAR and fixed power factor functions assuming reactive power priority. New inverter standards under pending changes in IEEE 1547 would require inverters to be sufficiently oversized to create the headroom that enables advanced functionality even when solar panels are at full production levels. A small increase in inverter size can result in a large increase in capacity to produce reactive power. It is therefore likely that active power priority is an excessively conservative assumption, and the smart inverter studies in Demo A are not as informative as they should be on the impact of advanced inverter functionality on hosting capacity. The WG recognizes that universal reactive power priority cannot be incorporated into ICA until standards are approved and compliant inverters are widespread, but a study to measure the impact of this will be greatly informative.

vi. How changes in grid operations may enable greater DER penetration while remaining within steady state voltage standards.

vii. How ICA may potentially evaluate optimal reactive power to systematically address voltage limits. This may allow developers to locate DERs with advanced inverters at optimal locations.

viii. How ICA may consider dynamic inverter functions, which may include settings to be changed by season, TOU period, and weekday vs. weekend, and in response to price signals and temperature forecasts. The WG should take steps towards evaluating this capability in coordination with a need for Rule 21 to include verification of operating profiles before systems can be approved based on dynamic functions.

3.7.2 ACR Section 3.1.c: Recommend a format for the ICA maps and downloadable data to be consistent and readable by all California stakeholders across the utilities service territories with similar data and visual aspects (Color coding, mapping tools, etc.).

The WG discussed ICA map formats in the July WG meeting. The ACR specifies requirements for how ICA results shall be available via utility maps. To reach common fundamental principles guiding the ICA map formats, the joint IOUs presented a proposal for displaying ICA results, including structure of mapping layers (substations, circuits, line segments all visible) and which information will be viewable in map format and which will be included in the downloadable data set.

The WG agrees and recommends that the IOUs should continue to standardize to a common mapping structure and mapping functionality while using what was developed for Demo A for first system rollout, with proposed modifications.

3.7.2.1 ICA Maps

26

Page 27: Executive Summary · Web viewCalifornia Distribution Resources Plan Integrated Capacity Analysis Working Group DRAFT Final Report – Due March 1, 2017 NOTE: This is a first draft

California Distribution Resources Plan Integration Capacity Analysis Working Group

DRAFT Final Report – Due March 1, 2017

NOTE: This is a second draft of the ICA WG report. Comments in tracked changes can be sent to [email protected] and are due Monday EOB, March 6.

The following attributes are currently visible across all three IOU maps for their Demo A DPAs: 1) circuit; 2) section ID; 3) voltage (kV); 4) substation; 5) system; 6) customer breakdown percentage (agriculture, commercial, industrial, residential, other); 7) existing generation (MW); 8) queued generation (MW); 9) total generation (MW); 10) ICA with uniform generation (MW); 11) ICA with uniform load (MW); 12) integration capacity of a typical/generic PV system (MW).

Currently, utilities assume that a solar system produces its maximum rated power every hour of the year and is consequently treated as uniform generation within the ICA. As hosting capacity will be measured on an hourly and seasonal basis, the hourly and seasonal profiles of DERs should be considered. The WG will develop assumptions for a standard PV generating profile that is sufficiently conservative to be relied upon for interconnection approval, as a long-term refinement item.

The WG identifies incorporation of single phase circuits as a high priority item for long-term refinements beginning Q1 2017, and discussed the inclusion of identifying single phase line sections within the first system-wide rollout of ICA to support the interconnection use case. The WG recommends that the IOU online maps display all single phase line sections with a unique color in the first system-wide rollout. Until the ICA WG develops methodology for inclusion of single phase line sections, the reflected ICA value will not be of the single phase line section, but rather indicate their location and connection to a three phase feeder. The IOUs agree on the potential use but additionally outline that determining accurate single phase ICA would require significant investment in the development of comprehensive single phase network models. This is because the IOUs do not currently have a complete source of single phase information for their network models. The IOUs agree that the WG should continue to explore the applicability of single phase ICA values taking into account the cost to develop the single phase ICA values against the efficiencies gained from ICA values in the interconnection use case.

As a long-term refinement, some WG stakeholders would like to consider how the map may provide verification that available capacity has not been absorbed by another interconnection application submitted since publication of the ICA value. This factor will be reduced as utilities get closer to real-time ICA updates. Much of the coordination work will need to be done within the context of the Rule 21 proceeding.

3.7.2.2[3.7.2.1] Downloadable data sets

All IOUs make the following information available via downloadable data set from their Demo A projects: 1) Demo A final report; 2) ICA Translator; 3) load profiles; 4) customer type breakdown; 5) detailed ICA results by circuit.

The WG envisions that there may be some differences between the interconnection use case and planning use case with regards to map and dataset needs. These following recommendations should be incorporated in the first system-wide rollout for the interconnection use case only. Given the amount of data produced in calculating ICA results, the IOUs recommend limiting future downloadable data to only actionable data based on use cases determined to be deployed. Additional downloadable data should be

27

Goldman, Brian, 03/03/17,
These criteria are not met across all three IOUs – SDG&E has still not distributed its map to the WG. PG&E is still missing a number of attributes that should be visible: substation, system, customer breakdown percentage, existing generation, queued generation, total generation.
Page 28: Executive Summary · Web viewCalifornia Distribution Resources Plan Integrated Capacity Analysis Working Group DRAFT Final Report – Due March 1, 2017 NOTE: This is a first draft

California Distribution Resources Plan Integration Capacity Analysis Working Group

DRAFT Final Report – Due March 1, 2017

NOTE: This is a second draft of the ICA WG report. Comments in tracked changes can be sent to [email protected] and are due Monday EOB, March 6.

discussed with WG to determine which data should be downloadable for system wide implementation and the associated requirements and costs.

The WG has already identified issues related to data access as an important long-term refinement item, and would like to highlight the topic of providing data in machine readable formats as a future discussion topic. This discussion of practical implementation will also highlight cybersecurity concerns.

3.7.3 ACR Section 3.1.d: Evaluate and recommend new methods that may improve the calculation of ICA values using computational efficiency method in order to calculate and update ICA values across all circuits in each utility’s service territory

The IOUs presented three proposed methods to improve ICA computational efficiency at the September and October WG meetings, with the purpose of reducing the number of data points needed to calculate in ICA without reducing the quality of results. These methods focus on 1) hourly reduction and mapping, 2) node filtering, and 3) criteria bounding. Each IOU employed different levels of computational efficiency methods in their demo projects. The WG is in general consensus with regards to the methodology underlying these computational efficiency refinements.

i. Hourly load profile reduction methods analyze fewer loading conditions. For example, an ICA using a 576 hourly profile (which uses minimum and maximum load days for every month, for 12 months – 24 x 2 x 12) may be efficiently reconstructed by reducing the number of hours analyzed with similar loading conditions.

ii. Node filtering methods improve efficiency by limiting the number of nodes analyzed – when nodes are within close proximity to each other with no customer loads in between, or nodes exists only for simulation purposes, those nodes have the same level of ICA due to similar levels of impedance and loading conditions.

iii. Reduction of limitation categories for feeders with a high short circuit duty. For those specific feeders, the voltage fluctuation screens and protection limitation screens do not need to be evaluated, as they will not affect the final ICA value.

SCE recommends that the computations efficiencies methods accepted by the ICA WG for utilization in Demo A be granted for implementation in the IOUs first system wide rollout. SCE also recommends and supports that discussion of computation efficiencies and new methodologies be a continue discussion via the long-term enhancements to ICA and that modification, adjustments or additions be allowed for future ICA system wide roll-outs as deemed appropriate by the ICA WG.

WG recommendation on load profile – from stakeholder document, 576 hourly profile, at least monthly updates? From IOUs?

28

Laura Wang, 02/27/17,
Don’t necessarily need this paragraph as written in full here, but does WG need to improve all methods for use, or say for ii and iii that IOUs SHALL use them in full system roll out?
Laura Wang, 02/27/17,
Brandon Smithwood:Without more information on cost of different levels of computational intensity, it seems premature to use these computational efficiency measures long term. I am mostly unsure about the hourly reduction.
Page 29: Executive Summary · Web viewCalifornia Distribution Resources Plan Integrated Capacity Analysis Working Group DRAFT Final Report – Due March 1, 2017 NOTE: This is a first draft

California Distribution Resources Plan Integration Capacity Analysis Working Group

DRAFT Final Report – Due March 1, 2017

NOTE: This is a second draft of the ICA WG report. Comments in tracked changes can be sent to [email protected] and are due Monday EOB, March 6.

3.7.4 ACR Section 3.1.e: Evaluate ORA’s recommendation to require establishment of reference circuits and reference use cases for comparative analyses of Demo Project A results.

The CPUC directed the IOUs to work towards additional consistency between IOUs’ calculation methodology and assumptions, for both the iterative and streamlined approach. To ensure a common approach between IOUs, the Commission asked the IOUs to compare methodologies against reference circuits, for discussion and approval by the WG.

The IOUs used the IEEE 123 test feeder as the reference circuit for comparative analysis as it employs a public data set of power flow results. The IOUs first compared power flow results between the power system analysis tools (PG&E and SCE employ CYME, and SDG&E employs Synergi), and then within each IOU for the Demo A test feeder.

The IOU Demo A reports include a joint report component concluding that overall, the ICA results do not have significant variation across the IOUs for both the iterative and streamlined methodologies, with the slight variations attributed to how power flow models are treated between CYME and Synergi.

Another comparative assessment in IOUs Demo A projects evaluated the difference between iterative and streamline methods. This assessment was used to determine which of the two methods would be most appropriate for the use cases and for implementation of first system wide roll out. Full exploration of these differences are detailed in the separate IOU Final Demo A Reports.

The WG recommends exploration to utilization of more representative circuits from California feeders, and will prioritize this future testing alignment against other competing resources and cost considerations through full WG discussions, within ICA long-term refinement. This recommendation should be part of the long-term future enhancements to ICA. While SCE and SDG&E support this future exploration, SCE and SDG&E caution that there are many long-term activities and that engineering resources and costs should be factored in determining the need for these additional studies.

The CPUC Office of Ratepayer Advocates (ORA) include 12 metrics for success for evaluating ICA. ORA provided the WG with a table of these criteria on January 10, 2017, with a brief description of whether the IOUs have met the criteria. The most recent version of the table is provided below:

ORA Criteria SCE SDG&E PG&E Comments1. Accurate and meaningful results

29

Laura Wang, 02/27/17,
If phrased here, is there consensus?
Laura Wang, 02/27/17,
Tom Roberts comment: I don’t think there is consensus on this – the results were different and the IOUs did not explain how the difference would be resolved going forward.
Page 30: Executive Summary · Web viewCalifornia Distribution Resources Plan Integrated Capacity Analysis Working Group DRAFT Final Report – Due March 1, 2017 NOTE: This is a first draft

California Distribution Resources Plan Integration Capacity Analysis Working Group

DRAFT Final Report – Due March 1, 2017

NOTE: This is a second draft of the ICA WG report. Comments in tracked changes can be sent to [email protected] and are due Monday EOB, March 6.

A. Meaningful scenarios ORA:Need to verify if reverse flow at substation busbar is correctly modeled?ACR scenarios best for use cases?

B. Reasonable technology assumptions

ORA: Need plan to incorporate smart inverter data.

C. Accurate inputs (i.e. load and DER profiles)

Track 3 Track 3 Track 3 ORA: Track 3.

D. Reasonable tests (i.e. voltage flicker)

ORA: No concerns/alternatives from working group.

E. Reasonable test criteria (i.e. 3% flicker allowed)

ORA: No concerns/alternatives from working group.

F. Tests and analysis performed consistently using proven tools, or vetted methodology

ORA: Tools being developed as part of Demo A and LT refinements.

[G.] Meaningful result metrics provided in useful formats

See #5 See #5 See #5 Duplicative

2. Transparent methodology ORA: IOUs have been open to information requests.

3. Uniform process that is consistently applied

LT Item LT Item LT Item ORA: QA/QC of custom Python scripts TBD.

4. Complete coverage of service territory

ORA: Not required at this point.

5. Useful formats for results ORA: SDG&E has not provided access to results. PG&E is still missing required data.

6. Consistent with industry, state, and federal standards

ORA: No concerns/alternatives from working group.

7. Accommodates portfolios of DER on one feeder

ORA: Uniform Gen map, plus DER translator. Need to ensure DER translator will work independent of the map showing uniform generation or PV profile.

8. Reasonable resolution –Spatial ORA: Optimal (lower) resolution

TBD; nodal reduction proposal. –Temporal ORA: Optimal (lower) resolution

TBD; 576 vs. 24 hours.

30

Goldman, Brian, 03/03/17,
Changed from Green to Yellow.
Tom Russell, 02/24/17,
Same as point 1.g
Tom Russell, 02/24/17,
Please confirm with ORA if these are still red given that we submitted results
Page 31: Executive Summary · Web viewCalifornia Distribution Resources Plan Integrated Capacity Analysis Working Group DRAFT Final Report – Due March 1, 2017 NOTE: This is a first draft

California Distribution Resources Plan Integration Capacity Analysis Working Group

DRAFT Final Report – Due March 1, 2017

NOTE: This is a second draft of the ICA WG report. Comments in tracked changes can be sent to [email protected] and are due Monday EOB, March 6.

9. Easy to update based on improved and approved changes in methodology

ORA: QA/QC of custom Python scripts TBD.

10. Easy to update based on changes in inputs (loads, DER portfolio, DER penetration, circuit changes, assumptions, etc.)

ORA: Tweaks to circuit models in CYME/Synergi required for convergence are currently lost when new data from GIS and other data sources is incorporated into power flow circuit model.

11. Consistent methodologies across large IOUs

See #3 See #3 See #3 Duplicative

12. Methodology accommodates variations in local distribution system

LegendCriteria met, OK to proceedMust be resolved before full scale deployment, but ORA believes they will be resolved by ongoing WG activity.Additional work pending as long term refinementImportant issues have not been resolved to ORA's satisfaction, and it is not certain whether they will be before full scale deployment.Delay full scale circuit modeling until resolved

Is this the right go/nogo objective? If not, what?

The legend describes how close to the IOUs are to meeting the Criteria. Green means that the IOUs have met the criteria, so it is ok to proceed with full scale circuit modeling. Yellow means that these are areas that have been identified as criteria that must be resolved before full scale deployment, but current WG activity will resolve them. longer term refinement goals Red means that these are issues that have not been adequately resolved, and it is not certain whether they will be resolved before full scale deployment. The IOUs cannot begin full scale modeling until these criteria are met. . . The WG understands that not all of the requirements can or need to be met in order to begin performing the full scale circuit modeling.

31

Goldman, Brian, 03/03/17,
Text is red inside due to track changes. Text reads – “Important issues have not been resolved to ORA's satisfaction, and it is not certain whether they will be before full scale deployment.”
Goldman, Brian, 03/03/17,
Both Utilities need to explain more. Basic Issue is that they go through the effort to model circuit. If they update circuit, then the model needs to change. PG&E currently has a process. However, they do not have a way to get changes into model, so either the model is run without current info, or they need to input changes manually. Fundamental thing that reflects on SCE, since they have not developed this yet. Response is OK, but needs to be red, since they have not demonstrated it yet. Until they can demonstrate, is a problem. Expecting result that is based on accurate data.
Roger Salas, 02/24/17,
For SCE, this should not be red. SCE will put systems and processes in place to prevent this from happening. SCE is in the process of mapping processes with engineering to prevent this from occurring. Should be green.PG&E – agreed, but implementing such a requirement will cost money to retool and enhance the gateway.
Page 32: Executive Summary · Web viewCalifornia Distribution Resources Plan Integrated Capacity Analysis Working Group DRAFT Final Report – Due March 1, 2017 NOTE: This is a first draft

California Distribution Resources Plan Integration Capacity Analysis Working Group

DRAFT Final Report – Due March 1, 2017

NOTE: This is a second draft of the ICA WG report. Comments in tracked changes can be sent to [email protected] and are due Monday EOB, March 6.

However, the WG expects the IOUs to meet these criteria as the ICA is refined over time. Red means that the IOUs have not met the criteria, and the IOUs cannot begin full scale circuit modeling until these criteria are met.

3.7.5 ACR Section 3.1.f: Establish a method for use of Smart Meter and other customer load data to develop more localized load shapes to the extent that is not currently being done

In reviewing Demo A reports, WG stakeholders requested further clarification on the use of advanced metering infrastructure within ICA methodology. This application is detailed further:

SCE aggregated smart meter measurements to their corresponding distribution transformers. That is, the loading of a distribution transformer for a certain hour is characterized by

Transformer_loading=∑_(i=0)^n▒〖Customer_i 〗where Customer_i represents a customer served by the transformer and n is the number of customers served by the transformer. By performing this analysis for each hour, load shapes and patterns are generated for each transformer. These localized shapes in combination with the circuit level loading profile were utilized to allocate the feeder level forecasted loading down to the service transformer level or individual customer level. This allowed SCE to more accurately geographically allocate feeder level forecasted loading values down to specific regions on the circuit.

PG&E: Need clarification on what is desired past what we already discussed.

SDG&E brings AMI data at the time of the peak for each customer to establish the demand. Then SDG&E leverage its AMI data to develop different customer classes load profiles. Each customer class has its profile and is created per substation bus. The profile curve adding all the customers consumption on each customer class by hour for that specific class and bus.LoadSeer creates monthly profiles curves per circuit for peak and minimum day (48 points per month) using SCADA data at the breakers. These curves get imported into Synergi and the load gets allocated on the feeder using the combination of Customer class’s curves at the transformer level and Feeder profile curves at the breaker level.

It is recommended that the IOUs continue to utilize customer level load data as used in Demos A for first system wide roll out, and the WG would like to further explore reasons for divergence, as well as trade-offs between methods, as part of long-term refinement.

32

Brandon Smithwood, 02/23/17,
I imagine they’ll want to fill this out
Laura Wang, 03/01/17,
MTS to IOUs: I took this directly from the “written responses” sheet, please modify or clean up as you see fit!
Laura Wang, 02/27/17,
From Tom Roberts:The IOUs need to add more here based on what they explained verbally at recent meetings, as from what they explain they are developing unique profiles for circuits segments based on SM data, not just allocating circuit level profiles.
Page 33: Executive Summary · Web viewCalifornia Distribution Resources Plan Integrated Capacity Analysis Working Group DRAFT Final Report – Due March 1, 2017 NOTE: This is a first draft

California Distribution Resources Plan Integration Capacity Analysis Working Group

DRAFT Final Report – Due March 1, 2017

NOTE: This is a second draft of the ICA WG report. Comments in tracked changes can be sent to [email protected] and are due Monday EOB, March 6.

3.7.6 ACR Section3.1.g: Establish definite timelines for future achievement of ICA milestones, including frequency and process of ICA updates

Following the completion of Demo A, the IOUs plan to perform final system-wide implementation of ICA. The WG engaged in multiple discussions surrounding expediency around this implementation, given the size and complexity of this project.

The IOUs understand the urgency of implementing an approved ICA methodology system wide and the IOUs are committed on implementing the ICA Methodology in the most expeditious manner. The IOUs also ask the stakeholder to understand that what is being asked is a very large and complex project which has not been attempted by any utility. For reference, in Demo A, SCE performed an ICA on 82 distribution feeders and the time allowed for that was 4 months. In the system wide implementation, SCE has to implement ICA on more than 4,500 distribution feeder which exponentially higher in magnitude with significant reduction in time as compared to what was done in Demo A (Demo A: 21 circuit/month, System implementation: 375 circuit/month).

While a final decision is pending, the IOUs will continue to work on preparation activities such as preparing network models, data sources, work force plans and implementation procedures. Once the PUC issues a final decision, IOUs anticipate 12 months will be necessary for implementation.

More specific details on what IOUs work activities prior to and after the decision are outlined below (applicable to all three IOUs):

Work to commence while a decision is pending: Model creation and validation: SCE engineers to create distribution system models. Activity can

start prior to PUC Final Decision, but it is estimated to last 10-months. Preparation of data sources: Preparation of data sources such as, SCADA Historian, GIS, and

Distribution Management System is required.

Work to commence after decision (12 months): Implement ICA Methodology – SCE estimates 4 months of development once final ICA

Methodology is established. Work cannot start prior to PUC final decision as development requires all assumptions and functionality be outlined prior to start of solution design. In addition, based on Demo A work, various iterations of testing are required to stabilize code (e.g., troubleshoot bugs) to render solution production ready. Code will not be stabilized until after various distribution circuit models have been analyzed. Vendor engagement is required.

Run ICA – Perform the ICA on the distribution system models. Based on the ICA Methodology requirements (e.g., number of hours, periodicity of updates) computing resources need to be configured and computing resource management systems may need to be developed. Work with vendor community is required.

33

Laura Wang, 02/27/17,
Brandon Smithwood:I want to make clear that I for one totally recognize and appreciate that this is a HUGE effort and that tons of great work has been done by the IOUs. The issue is making sure that we have something that is ready for a dramatically streamlined interconnection process. I am mostly concerned about anything that will create path dependence—is there a decision we make which will have long term consequences when we go to revise Rule 21? My view is if we have cost estimates on different levels of computational intensity we can make decisions based on the ICA’s functioning over the long term (i.e., not just the initial system wide roll out).
Laura Wang [2], 02/16/17,
WG members, please review the IOU explanations of timelines to justify 12 month rollout. Still need to determine whether consensus rec on timeline
Page 34: Executive Summary · Web viewCalifornia Distribution Resources Plan Integrated Capacity Analysis Working Group DRAFT Final Report – Due March 1, 2017 NOTE: This is a first draft

California Distribution Resources Plan Integration Capacity Analysis Working Group

DRAFT Final Report – Due March 1, 2017

NOTE: This is a second draft of the ICA WG report. Comments in tracked changes can be sent to [email protected] and are due Monday EOB, March 6.

Quality Assurance and Control– In support of ICA Methodology implementation activities, and to support SCE in the publication of most accurate results, quality control and quality assurance systems and processes need to be designed, developed, and implemented.

Publication of Results – Develop interfaces between ICA Results databases, mapping databases, and other data sources required by the PUC final decision. Edit map symbology to meet ICA requirements.

Separately, PG&E recommends that the ICA by implemented by June 2018, to coordinate with PG&E’s planning process (currently distribution planning analysis and engineering review occur in the January to May timeframe). PG&E notes that if adopting recommendations of PG&E to use the “streamlined” method for system wide analysis and the “iterative” method on an as requested or pre-application basis, then it is expected that less engineering resources are needed to implement this efficient approach. PG&E projects that if the iterative method is required for use then a new team would be needed to manage the ICA process. It is projected that if streamlined is adopted and the iterative approach is adopted more efficiently on application basis then the new work load can be more efficiently managed with current engineering resources.

IOUs strongly recommend that the appropriate time to complete full system wide implementation of ICA be 12 months following PUC final ruling. This will insure that IOUs can implement the appropriate methodology without the risk of losing valuable engineering work if decision is different the anticipated. Additionally, IOUs will continue to prepare those elements such as preparing network models, data sources, work force plans and implementation procedures that are needed for full implementation while a decision is provided.

After review/discussion of this section, still split recommendation of 12 months from report vs. 12 months from Commission decision vs. PG&E separate recommendation?

3.8 Long-term refinement activities In December 2016, the WG filed an interim status report on long-term refinement items. This status report includes both the suggested list of topics for further refinement, as outlined in the ACR, as well as additional topics proposed by WG members. It was noted that, as the report was due before IOUs published final Demo A reports, some recommendations for long-term methodology refinement will be adjusted after full review of final demo results and incorporated into the final WG report.

3.2.a: Single phase feeders: The ACR identifies expansion of ICA methodology to single phase feeders as a long-term refinement item to begin after the submission of the final ICA WG report. In discussions to date, the IOUs have proposed to evaluate the impact of performing single-phase ICA on at least one circuit. This test evaluation would examine the capability of single phase radials to accept additional loads of DER. This test evaluation should then inform a recommended methodological approach for approaching single phase ICA over an entire distribution system.

34

Page 35: Executive Summary · Web viewCalifornia Distribution Resources Plan Integrated Capacity Analysis Working Group DRAFT Final Report – Due March 1, 2017 NOTE: This is a first draft

California Distribution Resources Plan Integration Capacity Analysis Working Group

DRAFT Final Report – Due March 1, 2017

NOTE: This is a second draft of the ICA WG report. Comments in tracked changes can be sent to [email protected] and are due Monday EOB, March 6.

The WG identifies incorporation of single phase circuits as a high priority item for long-term refinements beginning Q1 2017, due to its usage within the interconnection use case. To facilitate the analysis of single phase circuits once methodology is developed, the WG recommends the following refinements to ICA for incorporation into the first system-wide rollout:

- IOUs should further develop their gateway and circuit modeling with the understanding that single phase line sections will eventually be incorporated

- All three IOUs’ maps should visible include all single phase line sections to enable developers to identify which three-phase circuits they are connected to without ICA or data information. Even though ICA values are not yet available for single phase lines, their locations should be shown, and it should be possible to clearly identify what three phase circuit they are connecting to.

Coordination with LNBA process The interim ICA long-term refinement report identified “actively engage to determine how ICA and LNBA may influence each other or be used concurrently.”

- The WG noted that understanding where planned grid upgrades are expected, and having those upgrades indicated in the LNBA online map will also be useful to ICA stakeholders.

3.9 Additional Cost RecoveryThe WG acknowledges that continued deliberation with regards to cost impacts and cost recovery will likely occur in a separate forum. It is also acknowledged that the IOUs can continue to engage in some work related to the full system roll-out, such as data clean-up efforts, independent of a CPUC proposed decision.

Depending upon the implementation requirements adopted by the Commission, additional cost recovery may be necessary. The Working Group therefore recommends that CPUC adopt a process to facilitate IOU requests for additional funding to support ICA implementation. Specifically, the working group recommends that CPUC implement a new ratesetting sub-track (“Track 1A”) with a scope narrowly focused on IOU funding requests necessary to comply with CPUC guidance for ICA implementation. Track 1A should commence immediately following the issuance of the CPUC Decision determining guidance for the ICA implementation. The Working Group Recommends the Commission adopt following schedule for Track 1A (timing refers to days following issuance of the Decision):

30 days: IOUs file funding proposals 45 days: Parties file comments 60 days: IOUs file reply comments 90 days: PD

3.10 Recommendation Summary TableThrough rigorous discussion on use cases, frequency of updates, and related discussion topics, the WG recommends that consideration for final decision be based on majority of consensus considering future refinements to ICA to account for non-consensus and other alternatives as outlined in the table 1 below.

35

Laura Wang, 02/28/17,
IOU recommendation – new section, needs comment
Page 36: Executive Summary · Web viewCalifornia Distribution Resources Plan Integrated Capacity Analysis Working Group DRAFT Final Report – Due March 1, 2017 NOTE: This is a first draft

California Distribution Resources Plan Integration Capacity Analysis Working Group

DRAFT Final Report – Due March 1, 2017

NOTE: This is a second draft of the ICA WG report. Comments in tracked changes can be sent to [email protected] and are due Monday EOB, March 6.

Table 1: Summary of Recommendations for Interconnection Use Case For full detail, please reference specific report sections.

Majority Consensus Recommendation: first system rollout

Non-Consensus and Alternatives

WG activity on Long-Term Refinement (6 months)

Refer to Report Section

1. Methodology Iterative PG&E: “blended” approach (see final Demo report)

2. Update frequency

Monthly Non-IOU stakeholders: At least monthly, on case-by-case basisSCE: no more than monthlyPG&E: dictate updates by conditions, not time frame

Use cases

3. Hourly profile 96 24, 576, 8760 <missing report section here? Or would include in a cost considerations section>

4. Voltage regulating devices

Based on Demo A implementation:SCE & PGE - LockedSDG&E – Float.

This is necessary due to limitation of existing tools (CYME) used by SCE and PG&E

SCE: The tools (CYME) which SCE is using do not currently support this option. SCE will work with CYME and tool vendors to incorporate this feature. SCE urges that if this is a requirement, SCE will likely not be able to meet the 12 months as the tools do not currently support this option

Power system criteria

5. Operational flexibility

Publish two ICA values: 1) no reverse flow across SCADA operated devices, 2) reverse flow up to substation low voltage busbar with no export to the high side busbar towards the transmission system

Develop new methodology

Power system criteria

36

Page 37: Executive Summary · Web viewCalifornia Distribution Resources Plan Integrated Capacity Analysis Working Group DRAFT Final Report – Due March 1, 2017 NOTE: This is a first draft

California Distribution Resources Plan Integration Capacity Analysis Working Group

DRAFT Final Report – Due March 1, 2017

NOTE: This is a second draft of the ICA WG report. Comments in tracked changes can be sent to [email protected] and are due Monday EOB, March 6.

6. Circuit models Incorporate changes to circuit models based on utility practice

Circuit models

7. Smart inverters

No include in first system roll out until further studies, methodologies and modification to tools is developed and implemented

Begin work with software vendors to determine best means of incorporating smart inverter data when methodology is developed

Begin studies on reactive power, static volt/VAR, fixed power factor – other studies TBD

3.1.b

8. Maps Publish uniform generation ICA and ICA value based on common PV shape

3.1.c

9. Computational efficiency

As approved for use in Demo A

3.1.d

10. ORA success criteria and reference circuits

Not applicable 3.1.e

11. Smart meter As used for Demo A 3.1.f12. Timelines System wide

implementation of ICA 12 months from final PUC decision.

Non-IOU stakeholders: 12 months from filing of WG final reportSCE and SDG&E: 12 months from PUC decisionPG&E: June 2018, potentially longer based on methodology. IOUs point that without an approved methodology, automated system cannot be developed and the at minimum 12 months are needed to develop such systems after final decision.

3.1.g

13. Scope System Wide

4 Next Steps for the ICA WGThe WG looks forward to continuous improvement and development of additional methodological components for the ICA. The WG identified a tiered list of discussion topics in 2017 in the interim ICA long-term refinement report submitted December 2016. This list of topics has been updated since, and the WG aims to create a proposed working schedule as a priority item once work on long-term refinement items begin.

37

Page 38: Executive Summary · Web viewCalifornia Distribution Resources Plan Integrated Capacity Analysis Working Group DRAFT Final Report – Due March 1, 2017 NOTE: This is a first draft

California Distribution Resources Plan Integration Capacity Analysis Working Group

DRAFT Final Report – Due March 1, 2017

NOTE: This is a second draft of the ICA WG report. Comments in tracked changes can be sent to [email protected] and are due Monday EOB, March 6.

Topic Rationale ACRTier 1: Higher PriorityOperational flexibility criteria

Development of a non-heuristic approach to operational flexibility based on engineering analysis

Operational flexibility criteria

Smart Inverters Studies to facilitate inclusion of smart inverters into ICA at soonest possible rollout

3.1.b

Expansion to single phase feeders

Initial discussions should align with streamlined interconnection discussions, IOUs may start analysis on single circuit on a Tier 2 timeline

3.2.a

Data access Data discussion focused on understanding IT requirements to address market sensitive information, data sharing, and automated data analysis.

3.2.b, 3.2.d

Interactive maps Discussion focused on understanding IT requirements and benefits of increasing data directly visualized onto ICA maps.

3.2.c

Load forecast assumptions

Leverage work of CPUC DER and load forecast workshop Q1 2017

Tier 2: Lower PriorityIntegration of ICA into growth scenarios for decision making purposes

Refine how growth scenarios are implemented, understand how use cases for growth scenarios may impact ICA results, and make recommendations on incorporation of ICA into growth scenarios. Conversations will occur after February 2017 CPUC workshop on growth scenarios as part of Track 3 efforts.

Comparative analysis

Expansion of comparative analysis to more than one circuit and test more complicated circuits, as IOUs consider expansion of ICA to all circuits within service territories.

3.1.e

Independent validation of ICA

Proceeding in coordination with Track 3 efforts, and following comparative analysis discussion with an agreed-upon dataset and results for parties to compare and validate.

3.2.f

Method for reflecting the effect of potential load modifying resources on integration capacity

Begin development of methodology to include resource reliability and uncertainty factors into ICA, model resource impacts on ICA indicators, assess impacts of load-modifying resources, and include non-grid engineering analysis within ICA methodology

3.2.e

Definition of quality assurance and quality control measures

The WG will determine whether this long-term refinement issue identified in the ACR requires further discussion after reviewing the final Demo A reports

3.2.g

38

Page 39: Executive Summary · Web viewCalifornia Distribution Resources Plan Integrated Capacity Analysis Working Group DRAFT Final Report – Due March 1, 2017 NOTE: This is a first draft

California Distribution Resources Plan Integration Capacity Analysis Working Group

DRAFT Final Report – Due March 1, 2017

NOTE: This is a second draft of the ICA WG report. Comments in tracked changes can be sent to [email protected] and are due Monday EOB, March 6.

ICA in peak load conditions

Continue discussion of ICA that allows DERs to serve peak load conditions, while maintaining grid stability during low-load conditions

39

Page 40: Executive Summary · Web viewCalifornia Distribution Resources Plan Integrated Capacity Analysis Working Group DRAFT Final Report – Due March 1, 2017 NOTE: This is a first draft

California Distribution Resources Plan Integration Capacity Analysis Working Group

DRAFT Final Report – Due March 1, 2017

NOTE: This is a second draft of the ICA WG report. Comments in tracked changes can be sent to [email protected] and are due Monday EOB, March 6.

5 Appendix5.1 AcronymsTBD5.2 Working Group Meetings and Topics

Meeting Date Topic(s)May 12 – 1:00pm-3:00pmWebinar

Opening meeting

May 18 – 10:30am-12:00pmWebinar

Seeking input regarding 1) use of power flow analysis and 2) level of granularity

June 1- 9:00am-3:00pmIn person

First discussion of demonstration implementation plan before June 16th submission

June 9 – 9:00am-3:30pmIn person

Second discussion of demonstration implementation plan before June 16th submission

July 5 – 2:00pm-4:00pmConference call

Call to discuss submission of demonstration implementation plan

July 25 – 9:00am-3:30 pmIn person

Discussion of submitted stakeholder comments on demonstration implementation plansUse cases3.1.c/3.2.c – data and maps3.1.b – portfolio analysis

August 31 – 9:00am – 4:15pmIn person

Use cases3.1.b – smart inverters3.1.f – smart meter/customer load dataData access

September 30 – 9:00am-4:00pmIn person

3.1.e – comparative analysis3.1.b.i – portfolio analysis3.1.d – computational efficiencyData access

October 17 – 9:00 am-4:00pmIn person

Demo A update3.1.d – computational efficiency3.1.f – smart inverters3.1.e – comparative analysis3.1.b.i – DER portfolios3.2.a-g – long-term scoping discussion

November 18 – 9:00am-4:00pmIn person

Review of Working Group short term final report outlineLong-term scoping discussion of 3.2.a-g plus other topicsData

40

Page 41: Executive Summary · Web viewCalifornia Distribution Resources Plan Integrated Capacity Analysis Working Group DRAFT Final Report – Due March 1, 2017 NOTE: This is a first draft

California Distribution Resources Plan Integration Capacity Analysis Working Group

DRAFT Final Report – Due March 1, 2017

NOTE: This is a second draft of the ICA WG report. Comments in tracked changes can be sent to [email protected] and are due Monday EOB, March 6.

December 13 –webinar

Review of Working Group interim long-term report topics

January 6 – 9:00am – 4:00pmIn person

Review of Final IOU Demo A Reports

January 17 – 9:00am – 4:00pmIn person

Review of Final IOU Demo A Reports

January 20 – 9:00am – 4:00pmIn person

ICA Recommendations

February 2 – 2:00pm-4:00pmWebinar

ICA Recommendations and development of report

February 14- 9:00am – 1:00pmWebinar

ICA Recommendations and development of report

March 1 - Final report due

5.3 Working Group ParticipantsThe following stakeholder groups attended at least one meeting or webinar of the ICA WG:

-        ABB Group -        Comverge-        Lawrence Berkeley National Laboratory

-        Advanced Microgrid Solutions -        DNV GL

-        Lawrence Livermore National Labs

-        Alcantar & Kahl-        ECCO International Inc.

-        Natural Resources Defense Council

-        AMS-        Energy and Environmental Economics

-        Northern California Power Agency

-        Artwel Electric-        Electric Power Research Institute -        NextEra Energy

-        Bloom Energy -        Energy Foundation -        New Energy Advisors

-        CAISO-        Environmental Defense Fund -        Nexant

-        California Energy Storage Alliance -        Gratisys Consulting

-        Open Access Technology International

-        California Energy Commission -        Greenlining Institute

-        Pacific Gas and Electric Company

-        California Public Utilities Commission -        Helman Analytics -        PSE Healthy Energy-        CPUC Office of Ratepayer Advocates -        ICF International -        Quanta Technology-        California Solar Energy Industries Association

-        Independent Energy Producers Association

-        Sacramento Municipal Utilities District

41

Page 42: Executive Summary · Web viewCalifornia Distribution Resources Plan Integrated Capacity Analysis Working Group DRAFT Final Report – Due March 1, 2017 NOTE: This is a first draft

California Distribution Resources Plan Integration Capacity Analysis Working Group

DRAFT Final Report – Due March 1, 2017

NOTE: This is a second draft of the ICA WG report. Comments in tracked changes can be sent to [email protected] and are due Monday EOB, March 6.

-        City of Burbank-        Independent advocates -        San Diego Gas & Electric

-        Clean Coalition-        Independent consultants -        SEIA

-        Community Choice Partners -        Integral Analytics

-        Shute, Mihaly & Weinberger LLP

-        Community Environmental Council (Community Renewable Solutions LLC representing)

-        Interstate Renewable Energy Council -        Siemens

-        Smart Electric Power Alliance -        Kevala Analytics -        SunPower

-        SoCal REN-        Southern California Edison -        The Utility Reform Network

-        SolarCity -        Stem Inc. -        UC Berkeley

-        Solar Retina -        Strategy Integration -        Vote Solar

-        Sunrun

42