expansion of group housing “kw srishti village noor...

21
Expansion of Group Housing “KW Srishtiat Khasra No. 1125/1, 1125/2 &1125/3, Village Noor Nagar, Pragana Loni, Raj Nagar Extension, Ghaziabad, Uttar Pradesh _________________________________________________________________FORM-1 Page 1 www.dasindia.org FORM 1 i. Basic Information Sl. Item Details 1 Name of the project/s Expansion of Group Housing “KW Srishtiat Khasra No.1125/1, 1125/2 &1125/3, Village Noor Nagar, Pargana Loni, Raj Nagar Extension, Ghaziabad, Uttar Pradesh. 2 S.No. In the schedule Category B, Activity 8 (b) of Schedule Gazette Notification dated Sep 14 th , 2006 and its subsequent amendments. 3 Proposed capacity/area/length/tonnage to be handled/command area/lease area/number of wells to be drilled Total Plot Area: 40,686 m 2 Total Built-up Area: 1,57,383.999 m 2 4 New/Expansion/Modernization Expansion 5 Existing Capacity/Area etc. Total Plot Area: 40,686 m 2 Built-up Area: 97,779.347 m 2 (as per EC granted in 2011) 6 Category of Project i.e. ‘A’ or ‘B’ Item- 8, Category -B (Township and Area Development) 7 Does it attract the general condition? If yes, please specify. No 8 Does it attract the specific condition? If yes, please specify. No. 9 Location Plot/Survey/Khasra No. Khasra No.1125/1, 1125/2 &1125/3, Village Noor Nagar Tehsil Village Noor Nagar, Pargana Loni, Raj Nagar Extension District Ghaziabad State Uttar Pradesh 10 Nearest railway station/airport along with distance in kms. New Ghaziabad railway station -3 km. (SE) Indira Gandhi International Airport, at approx- 36 km. (SW) 11 Nearest town, city, district headquarters along with distance in kms. New Delhi- 23 km, while Noida is 17 km & Greater Noida is 25 km 12 Village Panchayats, Zilla Parishad, Muncipal corporation, Local body (complete postal addresses with telephone nos. to be given) Ghaziabad Nagar Nigam, Ghaziabad, UP 13 Name of the applicant Dingle Buildcons Pvt. Ltd.

Upload: lykhanh

Post on 07-May-2018

217 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: Expansion of Group Housing “KW Srishti Village Noor …environmentclearance.nic.in/writereaddata/FormB/TOR/...Expansion of Group Housing “KW Srishti” at Khasra No. 1125/1, 1125/2

Expansion of Group Housing “KW Srishti”at Khasra No. 1125/1, 1125/2 &1125/3,Village Noor Nagar, Pragana Loni,Raj Nagar Extension, Ghaziabad, Uttar Pradesh_________________________________________________________________FORM-1

Page 1www.dasindia.org

FORM 1

i. Basic Information

Sl. Item Details

1 Name of the project/s Expansion of Group Housing “KW Srishti”at KhasraNo.1125/1, 1125/2 &1125/3, Village Noor Nagar,Pargana Loni, Raj Nagar Extension, Ghaziabad, UttarPradesh.

2 S.No. In the schedule Category B, Activity 8 (b) of Schedule – GazetteNotification dated Sep 14th, 2006 and its subsequentamendments.

3 Proposedcapacity/area/length/tonnage to behandled/command area/leasearea/number of wells to be drilled

Total Plot Area: 40,686 m2

Total Built-up Area: 1,57,383.999 m2

4 New/Expansion/Modernization Expansion

5 Existing Capacity/Area etc. Total Plot Area: 40,686 m2

Built-up Area: 97,779.347 m2 (as per EC granted in 2011)6 Category of Project i.e. ‘A’ or ‘B’ Item- 8, Category -B

(Township and Area Development)7 Does it attract the general

condition? If yes, please specify.No

8 Does it attract the specificcondition? If yes, please specify.

No.

9 Location

Plot/Survey/Khasra No. Khasra No.1125/1, 1125/2 &1125/3,

Village Noor Nagar

Tehsil Village Noor Nagar, Pargana Loni, Raj NagarExtension

District Ghaziabad

State Uttar Pradesh

10 Nearest railway station/airportalong with distance in kms.

New Ghaziabad railway station -3 km. (SE)Indira Gandhi International Airport, at approx- 36 km. (SW)

11 Nearest town, city, districtheadquarters along with distancein kms.

New Delhi- 23 km, while Noida is 17 km & Greater Noidais 25 km

12 Village Panchayats, Zilla Parishad,Muncipal corporation, Local body(complete postal addresses withtelephone nos. to be given)

Ghaziabad Nagar Nigam, Ghaziabad, UP

13 Name of the applicant Dingle Buildcons Pvt. Ltd.

Page 2: Expansion of Group Housing “KW Srishti Village Noor …environmentclearance.nic.in/writereaddata/FormB/TOR/...Expansion of Group Housing “KW Srishti” at Khasra No. 1125/1, 1125/2

Expansion of Group Housing “KW Srishti”at Khasra No. 1125/1, 1125/2 &1125/3,Village Noor Nagar, Pragana Loni,Raj Nagar Extension, Ghaziabad, Uttar Pradesh_________________________________________________________________FORM-1

Page 2www.dasindia.org

Sl. Item Details

14 Registered address Plot no B-2/5 Ashok Nagar, DB Gupta Road Near FaizChowk, Karol Bagh New Delhi-110005.

15 Address for correspondence B-97,Sector-63,Noida Uttar Pradesh -201301

Name Mr. Sonu Goel

Designation (Owner/Partner/CEO) General Manager

Address B-97,Sector-63,Noida Uttar Pradesh

Pin Code 201301

E-mail [email protected], [email protected]

Telephone No. 0120-4804747/19, 9650095984, 9911443255

Fax no.

16 Details of Alternative sitesexamined, if any. Location of thesesites should be shown on a toposheet.

No site alternatives are under consideration.

17 Interlinked projects Nil

18 Whether separate application ofinterlinked project has beensubmitted?

N.A.

19 If yes, date of submission N.A.

20 If no, reason N.A.

21 Whether the proposal involvesapproval/clearance under: If yes,details of the same and their statusto be given.(a) The forest (conservation) Act,

1980?

(b) The wildlife (protection) Act,1972?

(c) The C.R.Z. Notification, 1991?

No

No

No

22 Whether there is any Governmentorder/Policy relevant/relating tothe site?

The project lies in the Residential landuse of GhaziabadMaster Plan 2021. Master plan is a Govt. notified document,which is a land use certificate in itself. Ghaziabad MasterPlan attached as Annexure- I

23 Forest land involved (hectares) No24 Whether there is any litigation

pending against the project and/orland in which the project ispropose to be set up? Nil

Page 3: Expansion of Group Housing “KW Srishti Village Noor …environmentclearance.nic.in/writereaddata/FormB/TOR/...Expansion of Group Housing “KW Srishti” at Khasra No. 1125/1, 1125/2

Expansion of Group Housing “KW Srishti”at Khasra No. 1125/1, 1125/2 &1125/3,Village Noor Nagar, Pragana Loni,Raj Nagar Extension, Ghaziabad, Uttar Pradesh_________________________________________________________________FORM-1

Page 3www.dasindia.org

Sl. Item Details

(a) Name of the court(b) Case No.(c) Orders/directions of the court,

if any and its relevance withthe proposed project.

25 Expected cost of the project Rs.347.97 Crore

ii. Activity

1. Construction, operation or decommissioning of the Project involving actions, which willcause physical changes in the locality (topography, land use, changes in water bodies,etc.)

S.No. Information/Checklistconfirmation

Yes/No Details thereof (with approximate quantities /rates,wherever possible) with source of information data

1.1 Permanent ortemporary change inland use, land cover ortopography includingincrease in intensity ofland use (with respectto local land use plan)

No It is expansion of Residential project within same plot areadue to change in project conceptual and layout plan.Environment Clearance had already been granted bySEIAA vide letter no. 1900/612/Parya/SEAC/AD(H)/2010 -11, Dated 30-August-2011.The projectenvisages the development of Residential use buildingcomplex as per Master Plan of GDA, 2021. The site planshave already been approved by Ghaziabad DevelopmentAuthority.Hence the project do not anticipate any permanent ortemporary change in land use, land cover or topography ofthe area.EC is attached as Annexure-(II)

1.2 Clearance of existingland, vegetation andbuildings.

No This is an expansion project and has already beenapproved from MoEF (SEIAA) for Building andConstruction of Residential use Development in 2011.Siteclearing (which included sparse shrubs and grasses) wasdone following grant of EC in 2011.

1.3 Creation of new landuses?

No The project site is already earmarked for Residential usepurposes as per the local development plan and will bedeveloped as per the local building by-laws. Hence no newland use will be created.

1.4 Pre-constructioninvestigations e.g.bore holes, soil testing?

Yes Soil Investigation has been carried out for building design.

Page 4: Expansion of Group Housing “KW Srishti Village Noor …environmentclearance.nic.in/writereaddata/FormB/TOR/...Expansion of Group Housing “KW Srishti” at Khasra No. 1125/1, 1125/2

Expansion of Group Housing “KW Srishti”at Khasra No. 1125/1, 1125/2 &1125/3,Village Noor Nagar, Pragana Loni,Raj Nagar Extension, Ghaziabad, Uttar Pradesh_________________________________________________________________FORM-1

Page 4www.dasindia.org

S.No. Information/Checklistconfirmation

Yes/No Details thereof (with approximate quantities /rates,wherever possible) with source of information data

1.5 Construction works? Yes

.

This is a Residential Use complex. All constructionactivities will be confined within project area..

Items New ProposalTotal Plot Area 40,686 m2

Area under 24 m Circulation Road 2953 m2

Area under Chak Road 283.23 m2

Deductible area(Road widening) 3236.23 m2

Net Plot area 37,449.77 m2

Less 15% Green area 5617.47 m2

School plot area 500 m2

Net plot Area for GroupHousing (NPAGH)

31,332.30 m2

Permissible Ground coverage 12,532.92 m2

(40% ofNPAGH)

Proposed Ground coverage 8458.33 m2

(27.00% ofNPAGH)

Total open (NPAGH - Groundcoverage) area

22873.97 m2

Area for roads and internalcirculation

2, 0314.248 m2

(65%)Area for Services 2559.722 m2

Permissible FAR (@2.50 ofNPAGH)(A)

78,330.76 m2

Allowed purchasable FAR 38237.75 m2

Permissible including purchasableF.A.R @ 3.75 (On Net Area)

1,17496.12 m2

Achieved FAR Area (On NetArea)

1,16,568.51 m2

Community Facility/Club-1StoresConvenient shops (Commercial)(1)FAR Achieved (Club, Stores,Convenient shops)(2)Residential FAR Achieved

399.768 m2

2602.291 m2

374.237 m2

3376.296 m2

1,13,192.217m2

FAR(1)+(2) 1,16,568.513m2 (@3.720)

School FAR 400 m2(@0.80)Total FAR Achieved 1,16,968.513m2

Total Non- FAR 40415.486m2

Built up Area (FAR+ Non FAR) 1,57,383.999m2

Maximum Height 48 m

Page 5: Expansion of Group Housing “KW Srishti Village Noor …environmentclearance.nic.in/writereaddata/FormB/TOR/...Expansion of Group Housing “KW Srishti” at Khasra No. 1125/1, 1125/2

Expansion of Group Housing “KW Srishti”at Khasra No. 1125/1, 1125/2 &1125/3,Village Noor Nagar, Pragana Loni,Raj Nagar Extension, Ghaziabad, Uttar Pradesh_________________________________________________________________FORM-1

Page 5www.dasindia.org

S.No. Information/Checklistconfirmation

Yes/No Details thereof (with approximate quantities /rates,wherever possible) with source of information data

The building bye-laws of Ghaziabad DevelopmentAuthority (GDA) permits for construction of additional10% compoundable FAR areas over permissible basicFAR area. Therefore, additional provision of 10%FARover sanctioned FAR has been made in the drawings forfuture development.The developer has obtained height NOC of 69 m fromHindon Airforce station and has done the provision instructure of Tower A for B+S+17 floor and in Tower H & Ifor 2B+G+21 Floor (vetted by IIT Delhi) to accommodatethe extra 10% compoundable FAR. The design ofunderground water tank & STP has been done as permaximum permissible FAR & population.

1.6 Demolition works? No Not required

1.7

Temporary sites usedfor construction worksor housing ofconstruction workers?

Yes All the constructions activities including storing of rawmaterials are confined within the project site only. Labourhutment has been made on a hired land nearby.

1.8 Above groundbuildings, structures orearthworks includinglinear structures, cutand fill or excavations

Yes The construction of Residential use complex includeserection of structures like water storage tank, piping,electric substations, temporary site offices, maintenanceworkshop facilities & other infrastructures to support allthese activities.Details of earthwork:

a. Total Amount of Excavated Earth :-90,000cu.mt

Substantial amount of excavated quantity was used at sitefor development of landscape, road construction,backfilling and filling of low-lying area. The earthworkwas done after grant of EC in 2011. The balance earthexcavated as part of expansion will be used for landscapeand filling of low-lying area.

1.9 Undergroundtunneling? worksincluding mining or

No No underground works are required

1.10 Reclamation works? No No reclamation work required.

1.11 Dredging? No No dredging required.

1.12 Offshore structures? No No off shore structures required.

1.13 Production and No No production / manufacturing process is involved.

Page 6: Expansion of Group Housing “KW Srishti Village Noor …environmentclearance.nic.in/writereaddata/FormB/TOR/...Expansion of Group Housing “KW Srishti” at Khasra No. 1125/1, 1125/2

Expansion of Group Housing “KW Srishti”at Khasra No. 1125/1, 1125/2 &1125/3,Village Noor Nagar, Pragana Loni,Raj Nagar Extension, Ghaziabad, Uttar Pradesh_________________________________________________________________FORM-1

Page 6www.dasindia.org

S.No. Information/Checklistconfirmation

Yes/No Details thereof (with approximate quantities /rates,wherever possible) with source of information data

manufacturingprocesses?

1.14 Facilities for storage ofgoods or materials?

Yes Construction Phase:Minimum bulk material for construction is beingpurchased as per requirement and temporarily stored at sitewith appropriate arrangement which will be removed later.Thus, the impact on physical environment will betemporary.Separate storage arrangements will be made for storage ofbulk raw material. Cement is being stored under cover inbales and Sand is stacked neatly under tarpaulin cover.Bricks and steel is being laid in open.

Operation Phase:Not required except for common cleaning and maintenanceequipment and material. There will be well designatedconfined storage areas within the building, which will nothave impact on the physical environment.

1.15 Facilities for treatmentof disposal of solidwaste or liquideffluents?

Solid WasteConstruction Phase:Construction activities causes generation of debris, brickbats, plaster falls, battered stone mixture, aggregateleftovers, sand leftovers, empty cement bags, cartons, etc.Most of the construction waste generated is being reused inroad construction and filling.

Operation Phase:Domestic waste:3525 kg/dayHorticultural waste : 21kg/dayE- waste : 3 kg/daySTP Sludge: 26 kg/daySolid wastes generated from project site will be ofdomestic in nature. A door to door collection system willbe provided for collection of kitchen & other wastes at acommon collection point and disposed by hired/municipalagency for further treatment and disposal.Segregation of wastes will be encouraged among residentsthrough twin bin system colored bins (green and Blue –separate for Bio-degradable and Non Bio-degradable).A 48 hour storage facility will be developed with cover.Biodegradable segregated waste and garden litter will betransported to the compost site for bio-composting by the

Page 7: Expansion of Group Housing “KW Srishti Village Noor …environmentclearance.nic.in/writereaddata/FormB/TOR/...Expansion of Group Housing “KW Srishti” at Khasra No. 1125/1, 1125/2

Expansion of Group Housing “KW Srishti”at Khasra No. 1125/1, 1125/2 &1125/3,Village Noor Nagar, Pragana Loni,Raj Nagar Extension, Ghaziabad, Uttar Pradesh_________________________________________________________________FORM-1

Page 7www.dasindia.org

S.No. Information/Checklistconfirmation

Yes/No Details thereof (with approximate quantities /rates,wherever possible) with source of information data

hired vendors.The percentage of recyclable wastes will be high and theserecyclable wastes will be handed over to authorizedrecyclers/ vendors.Litter bins will also be provided in open areas like parksetc.Waste will be collected on daily basis by contracted/licensed agency.

Liquid Effluent

Construction Phase:Sewage generation during construction phase is beingtreated and disposed through septic tank with soak pits/sewer line.

Operation Phase:During operation, 563 KLD will be the total waste watergenerated, which will be treated in the STP of 900KLD(225+225+450KLD). After considering evaporation andother losses, 188KLD treated tertiary water will berecycled for various uses including Flushing &Horticulture and the spare 319 KLD will be treated up tosecondary treatment before its disposal into MunicipalSewer line.At present, there is occupancy of approx. 200 families.One module of 225 KLD STP is functional. Treated wateris being utilized within site for different purposes(Flushing, horticulture and construction). Residual treatedwater (upto Secondary Treatment) is being disposedthrough tankers.Wastewater treatment details are mentioned in Form 1A.

1.16 Facilities for long termhousing of operationalWorkers?

No No long term housing for operational workers is proposed

1.17 New road, rail or seatraffic duringconstruction oroperation?

Yes There is movement of vehicles during constructioncarrying construction material, labor and supervising staff.After construction, minor traffic increase will be observedon the road to some extent.There is no new road, rail or sea traffic.

1.18 New road, rail, airwaterborne or othertransport infrastructure

No No alteration of routes.Internal roads will be constructed for smooth movement oftraffic.

Page 8: Expansion of Group Housing “KW Srishti Village Noor …environmentclearance.nic.in/writereaddata/FormB/TOR/...Expansion of Group Housing “KW Srishti” at Khasra No. 1125/1, 1125/2

Expansion of Group Housing “KW Srishti”at Khasra No. 1125/1, 1125/2 &1125/3,Village Noor Nagar, Pragana Loni,Raj Nagar Extension, Ghaziabad, Uttar Pradesh_________________________________________________________________FORM-1

Page 8www.dasindia.org

S.No. Information/Checklistconfirmation

Yes/No Details thereof (with approximate quantities /rates,wherever possible) with source of information data

including new oraltered routes andstations, ports, airportsetc?

1.19 Closure or diversion ofexisting transportroutes or infrastructureleading to changes intraffic movements?

No No diversion of transport routes will be required

1.20 New or divertedtransmission lines orpipelines?

No There will be no shifting of transmission lines.

1.21 Impoundment,damming, culverting,realignment or otherchanges to thehydrology of watercourses or aquifers?

No No impounding, damming, culverting, realignment orother changes to the hydrology of surface watercourses isproposed.

1.22 Stream crossings? No Not required.

1.23 Abstraction or transfersof water from groundor surface waters?

Yes Ground water abstraction is being done.

1.24 Changes in waterbodies or the landsurface affectingdrainage or run-off?

Yes Due to increase in paved area, the runoff during rains willincrease from the project during the monsoon. Provisionsas per EMP shall be kept to capture this runoff and harvestthe rain water from the project area. Well planned stormwater drainage has been designed for internal storm waterdrainage.

1.25 Transport of personnelor materials forconstruction, operationor decommissioning?

Yes Construction workers and material is being procured fromthe nearest available market. During the operation phase,parking provision as per norms shall be provided.

1.26 Long-term dismantlingor decommissioning orrestoration works?

No Not applicable

1.27 Ongoing activityduringdecommissioningwhich could have animpact on theenvironment?

No There will be no decommissioning activity related to theproject

Page 9: Expansion of Group Housing “KW Srishti Village Noor …environmentclearance.nic.in/writereaddata/FormB/TOR/...Expansion of Group Housing “KW Srishti” at Khasra No. 1125/1, 1125/2

Expansion of Group Housing “KW Srishti”at Khasra No. 1125/1, 1125/2 &1125/3,Village Noor Nagar, Pragana Loni,Raj Nagar Extension, Ghaziabad, Uttar Pradesh_________________________________________________________________FORM-1

Page 9www.dasindia.org

S.No. Information/Checklistconfirmation

Yes/No Details thereof (with approximate quantities /rates,wherever possible) with source of information data

1.28 Influx of people to anarea in eithertemporarily orpermanently?

Yes During the construction phase, majority labourers arelocally and temporarily hired hence there will not be majorinflux of people anticipated during construction phase ofproject. Whereas during operation phase permanentresidential and commercial population will be there forwhich all amenities and supporting infrastructure isproposed to accommodate this influx of personnel.

1.29 Introduction of alienspecies?

No All plantations will be of indigenous species.

1.30 Loss of native speciesor genetic diversity?

No No loss of native species or genetic diversity is envisaged.

1.31 Any other actions? No No

2. Use of Natural resources for construction or operation of the Project (such as land,water, materials or energy, especially any resources which are non-renewable or in shortsupply):

S.No. Information/checklistconfirmation

Yes/No Details thereof (with approximate quantities /rates,wherever possible) with source of information data

2.1 Land especiallyundeveloped oragricultural land (ha)

No Land has been developed as Residential Use project as perGDA. Earlier this land was agricultural land.

2.2 Water (expectedsource & competingusers) unit:

Water/ Waste water Details:Fresh water 465KLDFlushing 160 KLDHorticulture 28KLD

Total waterrequirement

653KLD

Waste water 563KLDWater Source: Ground Water & Recycled

water2.3 Minerals (MT) No Sand and Murram are required for the construction and

development works. These are being purchased fromvarious vendors.

2.4 Construction material– stone aggregates,,and / soil (expectedsource – MT)

Yes Stone, aggregate, sand, and cement is required for theconstruction of roads. Thereafter, different types ofconstruction material will be required according to thedesign and size. These will be purchased from variousvendors. Hence no permission is required separately.Cement, Steel, Sand, Aggregate and ACC blocks are beingused in construction.

Page 10: Expansion of Group Housing “KW Srishti Village Noor …environmentclearance.nic.in/writereaddata/FormB/TOR/...Expansion of Group Housing “KW Srishti” at Khasra No. 1125/1, 1125/2

Expansion of Group Housing “KW Srishti”at Khasra No. 1125/1, 1125/2 &1125/3,Village Noor Nagar, Pragana Loni,Raj Nagar Extension, Ghaziabad, Uttar Pradesh_________________________________________________________________FORM-1

Page 10www.dasindia.org

2.5 Forests and timber(source MT)

No Timber required for scaffoldings, doors and windowswould be procured from authorized dealers.

2.6 Energy includingelectricity and fuels(source, competingusers) Unit: fuel (MT),energy (MW)

Yes Power requirement:5200KWSource of Power: UP PVVNLBack up DG sets (as per requirement): 4 DG Sets havingcapacity 500 KVA.4 x 500 =2000 KVA

2.7 Any other naturalresources (useappropriate standardunits)

No Not required.

3. Use, storage, transport, handling or production of substances or materials, which could beharmful to human health or the environment or raise concerns about actual or perceivedrisks to human health.

S.No. Information/Checklistconfirmation

Yes/No Details thereof (with approximatequantities/rates, wherever possible) withsource of information data

3.1 Use of substances or materials,which are hazardous (as perMSIHC rules) to human healthor the environment (flora, fauna,and water supplies)

No The Project is a Township and AreaDevelopment Project in which no storage ofhazardous chemicals (as per MSIHC rules)will be done, except HSD (low sulphurvariety) required to run standby DG sets.Also, the quantity to be stored will be belowthe threshold limit specified in the MSIHCrules. Suitable management practice will beadopted for the same.

3.2 Changes in occurrence ofdisease or affect disease vectors(e.g. insect or water bornediseases)

No Suitable drainage and waste managementmeasures will be adopted in bothconstruction and operational phase, whichwill restrict stagnation of water oraccumulation of waste. This will effectivelyrestrict the reproduction and growth ofdisease vectors.

3.3 Affect the welfare of people e.g.by changing living conditions?

Use, storage, transport, handling orproduction of any harmful product is notenvisaged from the project. Thus, no majoradverse impacts on the humanhealth/environment are envisaged.Local vendors, retailers, workers will beemployed during construction & operationof the project. The project and employmentgenerated from it would help in improvingthe socioeconomics of the area and will

Page 11: Expansion of Group Housing “KW Srishti Village Noor …environmentclearance.nic.in/writereaddata/FormB/TOR/...Expansion of Group Housing “KW Srishti” at Khasra No. 1125/1, 1125/2

Expansion of Group Housing “KW Srishti”at Khasra No. 1125/1, 1125/2 &1125/3,Village Noor Nagar, Pragana Loni,Raj Nagar Extension, Ghaziabad, Uttar Pradesh_________________________________________________________________FORM-1

Page 11www.dasindia.org

create a more interactive environment forliving, leisure and recreation.

3.4 Vulnerable groups of peoplewho could be affected by theproject e.g. hospital patients,children, the elderly etc.,

No This is development of ResidentialComplex. The changes in the air & noiseenvironment during both construction andoperation phase would be low and shall becontrolled through EMP, so no adverseimpact is anticipated by this project.

3.5 Any other causes No

4. Production of solid wastes during construction or operation or decommissioning(MT/month)

S.No. Information/Checklistconfirmation

Yes/No Details thereof (with approximatequantities/rates, wherever possible) with

source of information data4.1 Spoil, overburden or mine

wastesNo Details of earthwork:

Amount of Excavated Earth :- 90,000 m3

Approximately 90,000 m3 is the total earthexcavated during construction phase forfoundations & basement. Substantialamount of excavated quantity was used atsite for development of landscape, roadconstruction, backfilling and filling of low-lying area. The earthwork was done aftergrant of EC in 2011. The balance earthexcavated as part of expansion will be usedfor landscape and filling of low-lying area.

Page 12: Expansion of Group Housing “KW Srishti Village Noor …environmentclearance.nic.in/writereaddata/FormB/TOR/...Expansion of Group Housing “KW Srishti” at Khasra No. 1125/1, 1125/2

Expansion of Group Housing “KW Srishti”at Khasra No. 1125/1, 1125/2 &1125/3,Village Noor Nagar, Pragana Loni,Raj Nagar Extension, Ghaziabad, Uttar Pradesh_________________________________________________________________FORM-1

Page 12www.dasindia.org

S.No. Information/Checklistconfirmation

Yes/No Details thereof (with approximatequantities/rates, wherever possible) with

source of information data4.2 Municipal Waste (domestic and

or commercial wastes)Yes Domestic waste:3525kg/day

Horticultural waste : 21 kg/dayE- waste : 3 kg/daySTP Sludge: 26 kg/daySolid wastes likely to be generated in theproject are of domestic in nature. It will becollected from door to door and floor tofloor and segregated into inorganic andorganic wastes as far as possible.

Biodegradable segregated waste (organicwaste such as waste vegetables, foods etc)and garden litter will be handed over towaste collecting agency for bio-compostingand energy recovery.

Recyclable wastes will be handed over toauthorized recyclers and inert waste will beused for construction of road & pavement.

4.3 Hazardous wastes(as per Hazardous WasteManagement Rules)

Yes Construction Phase:The domestic hazardous waste likecontainers of paints, acrylics, PVC,chemicals, admixtures, bitumen etc. Lampsand tubelights, electrical scrap etc are likelyto be generated.Provisions are being made to segregate thewaste and the waste is being sold to thevendors for recycling.

Post Construction/ Operational Phase:The only hazardous waste in the project willbe used/spent oil from standby DG set,which is classified as hazardous wastecategory 5.1 as per Hazardous & OtherWastes (Management & Handling)Amendments Rules, 2016. The spent oil willbe carefully stored in HDPE drums underisolated storages, and periodically sold toauthorize recyclers. All precautions will betaken to avoid spillage from the storage. Theimpact will be negligible as DG setsoperated will be environmental friendly(operated on LSD).

Page 13: Expansion of Group Housing “KW Srishti Village Noor …environmentclearance.nic.in/writereaddata/FormB/TOR/...Expansion of Group Housing “KW Srishti” at Khasra No. 1125/1, 1125/2

Expansion of Group Housing “KW Srishti”at Khasra No. 1125/1, 1125/2 &1125/3,Village Noor Nagar, Pragana Loni,Raj Nagar Extension, Ghaziabad, Uttar Pradesh_________________________________________________________________FORM-1

Page 13www.dasindia.org

S.No. Information/Checklistconfirmation

Yes/No Details thereof (with approximatequantities/rates, wherever possible) with

source of information data4.4 Other industrial process wastes No Not applicable

4.5 Surplus product No Not applicable

4.6Sewage sludge or other sludgefrom effluent treatment

Yes Will be used as manure for horticulture.

4.7 Construction or demolitionwastes

Yes

Constructionwaste

material

Totalconstruction

waste generated@ 40 Kg/sq.m of

builtup area(MT)

6284(MT)

soil, sand &Gravel

0.35 2198

bricks &Masonry

0.3 1884

concrete 0.25 1570metal 0.05 314bitumen 0.0204 128wood 0.0204 128other 0.01 62

Source: TIFAC

Approx. 93,000 m3 of earth material wasexcavated during initial construction phasefor foundations, basement. Excavatedmaterial was re-used for back filling, roadconstruction, leveling of site andlandscaping.

4.8 Redundant machinery orequipment

No There is no generation of redundantmachinery or equipment for disposal.

4.9 Contaminated soils or othermaterials

No Not applicable

4.10 Agricultural wastes No No agriculture waste will be generatedduring operation phase. Only dry leaves,grasses, weeds etc will be cleared.

4.11 Other solid wastes No Not applicable

5. Release of pollutants or any hazardous, toxic or noxious substances to air (Kg/hr)

S.No. Information/Checklistconfirmation

Yes/No

Details thereof (with approximate quantities/rates,wherever possible) with source of information data

Page 14: Expansion of Group Housing “KW Srishti Village Noor …environmentclearance.nic.in/writereaddata/FormB/TOR/...Expansion of Group Housing “KW Srishti” at Khasra No. 1125/1, 1125/2

Expansion of Group Housing “KW Srishti”at Khasra No. 1125/1, 1125/2 &1125/3,Village Noor Nagar, Pragana Loni,Raj Nagar Extension, Ghaziabad, Uttar Pradesh_________________________________________________________________FORM-1

Page 14www.dasindia.org

S.No. Information/Checklistconfirmation

Yes/No

Details thereof (with approximate quantities/rates,wherever possible) with source of information data

5.1 Emissions fromcombustion of fossil fuelsfrom stationary or mobilesources

Yes During construction emission are being generated fromvehicles and machineries and D.G. sets to be installed forPower supply. During operation, the main source ofemission would be D.G. Sets and emissions due tovehicular movement.

5.2 Emissions fromproduction processes

No

5.3 Emissions from materialshandling includingstorage or transport

Yes Water sprinkling is being carried out regularly atconstruction and camp sites. Vehicles deliveringconstruction materials are being covered to avoid spillageof construction materials. Paints, adhesives and sealantsare stored as per the product instructions.

5.4 Emissions fromconstruction activitiesincluding plant andequipment

Yes The dust emission sources during construction phase willbe: Excavation Haul-road movements Construction Material Handling FinishingEmissions factors for construction equipment are givenin table below:Equipment

Emissions Factors(g/hr)CO VOC NOX SOX PM10

Excavator 214.09 43.99 516.18 3.31 27.21Backhoe/FrontEnd loader

190.05 56.69 370.13 1.58 37.64

Rubbertiredcrane

161.02 39.00 464.02 2.67 23.58

HydraulicCrane 161.02 39.00 464.02 2.67 23.58ConcreteVibrator 72.57 13.60 122.46 0 4.53PavingEquipment 186.42 48.53 412.31 1.95 29.93Roller/Compactor 165.10 34.92 316.15 1.90 23.13*Source: SCAQMD CEQAHandbook

Impacts:Increase levels of PM10, PM2.5, NOx, HC, VOC etc. fromthe above activities.Mitigation measures like: minimizing drop heights ofdebris, enclosures, covered transport, use of barriers,wetting surface, plantation, avoiding idling of vehiclesetc. will be adopted.

Page 15: Expansion of Group Housing “KW Srishti Village Noor …environmentclearance.nic.in/writereaddata/FormB/TOR/...Expansion of Group Housing “KW Srishti” at Khasra No. 1125/1, 1125/2

Expansion of Group Housing “KW Srishti”at Khasra No. 1125/1, 1125/2 &1125/3,Village Noor Nagar, Pragana Loni,Raj Nagar Extension, Ghaziabad, Uttar Pradesh_________________________________________________________________FORM-1

Page 15www.dasindia.org

S.No. Information/Checklistconfirmation

Yes/No

Details thereof (with approximate quantities/rates,wherever possible) with source of information data

5.5 Dust or odours fromhandling of materials,including constructionmaterials sewage andwaste

Yes Dust is being generated during construction, this is watersprinkled, and provided with tarpaulin cover over storedraw material to reduce dust emission. Duringconstruction and operation phase, odour emanating fromwaste and sewage would be managed through properhousekeeping and implementation of EMP.

5.6Emissions fromincineration of waste

No There is/ will be no incineration of waste

5.7 Emissions from burningof waste in open air (e.g.slash materials,construction debris)

No No open burning of waste will be allowed.

5.8 Emissions from any othersources

No Not applicable

6. Generation of Noise and Vibration, and Emissions of Light and Heat:

S.No. Information/Checklistconfirmation

Yes/No

Details thereof (with approximate quantities/rates,wherever possible) with source of information data

with source of information data

6.1 From operation ofequipment ventilationplant, crushers e.g.engines,

Yes Noise will be generated from the construction equipment’sand operation of DG sets.During construction work following will be the tentativesources of noise:

Name ofsource

Noise Level at 16m (50 ft) fromSource in db (A)

Noise level at 1 mfrom source in dB(A)

Back hoe/Loader

81 105

Cranes-mobile 81 105Dump truck 83 107Generator Not considered 75 (as prescribed

by CPCB)The following measures will be taken: CPCB certified DG sets conforming to the standards

for noise are being used. All construction equipment and machineries are being

maintained in good conditions. Personal protective equipment like ear muffs, ear plugs

are being provided to the workers.Silent type DG Sets with anti-vibration pads are beingprovided.

6.2 From industrial orsimilar processes

No Not applicable

Page 16: Expansion of Group Housing “KW Srishti Village Noor …environmentclearance.nic.in/writereaddata/FormB/TOR/...Expansion of Group Housing “KW Srishti” at Khasra No. 1125/1, 1125/2

Expansion of Group Housing “KW Srishti”at Khasra No. 1125/1, 1125/2 &1125/3,Village Noor Nagar, Pragana Loni,Raj Nagar Extension, Ghaziabad, Uttar Pradesh_________________________________________________________________FORM-1

Page 16www.dasindia.org

6.3 From construction ordemolition

Yes During construction work, there is short term noise impactsin the immediate vicinity of the project site due to variousconstruction activities such as excavation activities,Concreting and mixing, vehicular movement and variousconstruction machinery;Following precautions shall be taken to control noisepollution : High noise generating construction activities is

being carried out only during day time Installation, use and maintenance of mufflers on

equipmentWorkers working near high noise construction machineryare being supplied with ear muffs/ear plugs

6.4 From blasting or piling No No blasting or piling is being done.

6.5 From construction oroperational traffic

Yes It shall be restricted within a limited area. Some amount ofnoise will be generated in the construction and operationalphase however, adequate precautions will be taken toreduce noise generation i.e. development of green areawhich will act as barrier to control noise/air pollution(detailed in EMP).

6.6 From lighting orcooling systems

No Cooling towers are not proposed so there will be no noisegeneration from them. During power failure, operation ofDG sets will generate noise. However, these shall behoused in acoustically enclosed chambers. Hence, nosignificant impact anticipated.

6.7 From any other sources No

7. Risks of contamination of land or water from releases of pollutants into the ground orinto sewers, surface waters, groundwater, coastal waters or the sea:

S.No. Information/Checklistconfirmation

Yes/No Details thereof (with approximate quantities/rates,wherever possible) with source of information data

7.1 From handling, storage,hazardous materials useor Spillage of hazardousmaterials

Yes The hazardous waste includes spilled paints, adhesive,sealants and spent oil from standby DG sets. The spilledhazardous waste would be carefully collected anddisposed off as per applicable norms. The spent oil willbe carefully stored in HDPE drums under isolatedstorage, and periodically sold to authorize recyclers. Allprecautions will be taken to avoid spillage from storage.

7.2 From discharge ofsewage or othereffluents water or theland (expected modeand place of discharge)to

No There will be no discharge of untreated sewage on wateror land, as the wastewater after tertiary treatment will bereused for flushing, horticultural and the remainingamount of treated water (upto Secondary treatment) willbe discharged into the municipal sewers. So, no adverseeffect is envisaged

Page 17: Expansion of Group Housing “KW Srishti Village Noor …environmentclearance.nic.in/writereaddata/FormB/TOR/...Expansion of Group Housing “KW Srishti” at Khasra No. 1125/1, 1125/2

Expansion of Group Housing “KW Srishti”at Khasra No. 1125/1, 1125/2 &1125/3,Village Noor Nagar, Pragana Loni,Raj Nagar Extension, Ghaziabad, Uttar Pradesh_________________________________________________________________FORM-1

Page 17www.dasindia.org

7.3 By deposition ofpollutants emitted to airinto the land or intowater

No Deposition of dust on land & plants from air due totransportation will be there, both during operational &construction phase but will be minimal. Watersprinkling and good house keeping shall be regularlycarried out

7.4 From any other sources No Not applicable

7.5 Is there a risk of longterm build up ofpollutants in theenvironment from thesesources?

No There is no risk of long term build up of pollutants inthe environment from handling, storage, use or spillageof hazardous materials, discharge of sewage or othereffluents to water or the land and by deposition ofpollutants emitted to air into the land or into watersources.

8. Risk of accidents during construction or operation of the Project, which could affecthuman health or the environment

S.No.Information/Checklist

confirmation Yes/No

Details thereof (with approximatequantities/rates, wherever possible) with

source of information data

8.1 From explosions, spillages, firesetc from storage, handling, useor production of hazardoussubstances

This is basically a construction project and doesnot involve major hazardous constructionactivity. Hence, chances of explosions,spillages, fires are minimal.

All construction workers are being providedwith suitable personal protective equipment(PPE) as per the health & safety norms. Trainingand awareness about the safety norms is beingprovided to all supervisors and workers involvedin construction activities.

An agreement is signed with the contractor,which clearly deals safety aspects duringconstruction. No major hazardous waste is beingstored with in the project site. No industrial orprocess activity is involved in this project hencechances of chemical hazards and accidents areminimal. However, suitable fire-fightingmeasures will be provided.

8.2 From any other causes No For accidental fires, Fire fighting Pumps shall beinstalled

8.3 Could the project be affected bynatural disasters causingenvironmental damage (e.g.

No As per the secondary data available no suchprecedents has been reported. However thepossibility of such incidents cannot be ruled out.

Page 18: Expansion of Group Housing “KW Srishti Village Noor …environmentclearance.nic.in/writereaddata/FormB/TOR/...Expansion of Group Housing “KW Srishti” at Khasra No. 1125/1, 1125/2

Expansion of Group Housing “KW Srishti”at Khasra No. 1125/1, 1125/2 &1125/3,Village Noor Nagar, Pragana Loni,Raj Nagar Extension, Ghaziabad, Uttar Pradesh_________________________________________________________________FORM-1

Page 18www.dasindia.org

floods, earthquakes, landslides,cloudburst etc)?

Earthquakes:The project falls under seismic Zone IV. Designand architecture of RCC Frame work isearthquake resistant and complies with therequired IS Specifications.Suitable seismic coefficients in horizontal andvertical directions respectively, are beingadopted while designing the structures tominimize the impact of any disaster.Landslide: Area is not land slide proneCloudburst: Not reportedFloods:The area is not flood prone. The project hasplanned storm water layout in regards to thepeak intensity of the rainfall so far received asrecorded by IMD.

9. Factors which should be considered (such as consequential development) which couldlead to environmental effects or the potential for cumulative impacts with other existingor planned activities in the locality.

S.No. Information/Checklist confirmation Yes/No Details thereof (with approximatequantities/rates, wherever possible)

with source of information data9.1 Lead to development of supporting

facilities, ancillary development ordevelopment stimulated by the projectwhich could have impact on theenvironment e.g.:• Supporting infrastructure (roads,power supply, waste or waste watertreatment, etc.)

Yes

This is a development of Residentialcomplex. The existing infrastructure isadequate to meet the requirement ofproject.In order to support, power lines will bedrawn, roads will be constructed withinthe project as well as for access. Watersupply and sewage systems will be laiddown extensively.

• housing development• extractive industries• supply industries• other

YesNoYesNo

Construction of Residential complexproject.In order to meet the requirement of theproject, the supply industry will grow tomeet the demand for vegetable,processed food, gas, cloth, groceries,stationary and several other items.

9.2Lead to after-use of the site, whichcould have an impact on theenvironment

No

Page 19: Expansion of Group Housing “KW Srishti Village Noor …environmentclearance.nic.in/writereaddata/FormB/TOR/...Expansion of Group Housing “KW Srishti” at Khasra No. 1125/1, 1125/2

Expansion of Group Housing “KW Srishti”at Khasra No. 1125/1, 1125/2 &1125/3,Village Noor Nagar, Pragana Loni,Raj Nagar Extension, Ghaziabad, Uttar Pradesh_________________________________________________________________FORM-1

Page 19www.dasindia.org

9.3 Set a precedent for later developments No The area falls under Residential zone ofMaster Plan, therefore, no illegalactivity is predicted and development ofthe entire region is anticipated as perGhaziabad Master Plan, 2021.

9.4 Have cumulative effects due toproximity to other existing or plannedprojects with similar effects

It will improve the environment bycreating a more attractive and interactive environment for living, leisure &recreation, create an urban landmark.

iii. Environmental Sensitivity

S.No. Areas Name/Identity

Aerial distance (within 15km.) Proposed project

location boundary1. Areas protected under international conventions,

national or local legislation for their ecological,landscape, cultural or other related value

No Nil

2. Areas which are important or sensitive forecological reasons -Wetlands, watercourses orother water bodies, coastal zone, biospheres,mountains, forests

Yes River Hindon: 3.5 km (W)River Yamuna: 20 km (SW)

3. Areas used by protected, important or sensitivespecies of flora or fauna for breeding, nesting,foraging, resting, over wintering, migration

No Nil

4. Inland, coastal, marine or underground waters No Nil

5. State, National boundaries No Project lies in U.P.State.Delhi boundary lies approx20 km from project site.

6. Routes or facilities used by the public for accessto recreation or other tourist, pilgrim areas

No

7. Defense installations Yes Hindon Air Base- 7 km(W)

8. Densely populated or built-up area(aerial distances)

New Delhi: 23 km (SW)Noida: 17 km (SE)Greater Noida: 25km (SE)

9. Areas occupied by sensitive man-made land uses(hospitals, schools, places of worship,community facilities)

Yes There are several hospitals,schools, places of worship,and community facilitieswithin 15 Km radius of theproject site.

10.

Areas containing important, high quality orscarce resources (ground water resources,surface resources, forestry, agriculture,fisheries, tourism, minerals)

Yes River Hindon: 3.5 km (W)River Yamuna: 20 km (SW)

Page 20: Expansion of Group Housing “KW Srishti Village Noor …environmentclearance.nic.in/writereaddata/FormB/TOR/...Expansion of Group Housing “KW Srishti” at Khasra No. 1125/1, 1125/2

Expansion of Group Housing “KW Srishti”at Khasra No. 1125/1, 1125/2 &1125/3,Village Noor Nagar, Pragana Loni,Raj Nagar Extension, Ghaziabad, Uttar Pradesh_________________________________________________________________FORM-1

Page 20www.dasindia.org

S.No. Areas Name/Identity

Aerial distance (within 15km.) Proposed project

location boundary11. Areas already subjected to pollution or

environmental damage.(Those where existing legal environmentalstandards are exceeded).

Nil

12 Areas susceptible to natural hazard which couldcause the project to present environmentalproblems (earthquakes, subsidence, landslides,erosion, flooding or extreme or adverse climaticconditions)

No According to the IndianStandard Seismic ZoningMap, the area under studyfalls in Zone-IV. Suitableseismic coefficients inhorizontal and verticaldirections will be adoptedwhile designing thestructures.

“I hereby given undertaking that the data and information given in the application and enclosuresare true to the best of my knowledge and belief and I am aware that if any part of the data and

information submitted is found to be false or misleading at any stage, the project will be rejected

and clearance give, if any to the project will be revoked at our risk and cost.

Date:Place: Ghaziabad

Signature of the applicantWith Name and Full Address

(Project Proponent/ Authorized Signatory)

NOTE:1. The Projects involving clearance under Coastal Regulation Zone Notification, 1991 shall

submit with the application a C.R.Z map duly demarcated by one of the authorizedagencies, showing the project activities, w.r.t. C.R.Z. and the recommendations of the state

Page 21: Expansion of Group Housing “KW Srishti Village Noor …environmentclearance.nic.in/writereaddata/FormB/TOR/...Expansion of Group Housing “KW Srishti” at Khasra No. 1125/1, 1125/2

Expansion of Group Housing “KW Srishti”at Khasra No. 1125/1, 1125/2 &1125/3,Village Noor Nagar, Pragana Loni,Raj Nagar Extension, Ghaziabad, Uttar Pradesh_________________________________________________________________FORM-1

Page 21www.dasindia.org

Coastal Zone management Authority. Simultaneous action shall also be taken to obtain therequisite clearance under the provisions of the C.R.Z. Notification, 1991 for the activitiesto be located in the CRZ.

2. The projects to be located within 10 km of the National Parks, Sanctuaries, BiosphereReserves, Migratory Corridors of Wild Animals, the project proponent shall submit themap duly authenticated by Chief Wildlife Warden showing these features vis-à-vis theproject location and the recommendations or comments of the Chief Wildlife Wardenthereon.”

3. All correspondence with the Ministry of Environment & Forests including submission ofapplication for TOR/ Environmental Clearance, subsequent clarifications, as may berequired from time to time, participation in the EAC Meeting on behalf of the projectproponent shall be made by the authorized signatory only. The authorized signatory shouldalso submit a document in support of his claim of being an authorized signatory for thespecific project”.