facilities and enrollment task force modular removal planning monday, february 4, 2013
DESCRIPTION
Outcomes from Last Meeting Reviewed updated NESDEC enrollment projections for next 10 years Compared number of classrooms to be needed in each building with the number of classrooms available with modulars removed Reviewed estimated costs of modular removal along with estimated utility and maintenance savings Request development of a plan for phased removal showing impact on program deliveryTRANSCRIPT
Facilities and Enrollment Task Force
Modular Removal PlanningMonday, February 4, 2013
Overview
• Outcomes from last meeting• Why is modular removal a viable option?• Proposed timeline of the 3-year modular
removal• Modular location examination:
o Required program movement and new locationso Removal costo Utilities / Maintenance savings
Outcomes from Last Meeting
• Reviewed updated NESDEC enrollment projections for next 10 years
• Compared number of classrooms to be needed in each building with the number of classrooms available with modulars removed
• Reviewed estimated costs of modular removal along with estimated utility and maintenance savings
• Request development of a plan for phased removal showing impact on program delivery
Why Modular Removal?
• Modular space meant to be temporary• Utility cost and maintenance savings• Avoid capital expenditures for modulars• Maintenance of K-6 programs and community-based
schools• Capacity of schools more aligned with enrollment
projections
Proposed TimelineModular Location Recommended Removal Date
Tootin’ Hills Summer 2013
Latimer Lane – White modular Summer 2013
Central School Summer 2014*
Latimer Lane Summer 2015*
* Reviewed on an annual basis based upon enrollments
Tootin’ Hills Relocation
Tootin’ Hills School 2013-14
Squadron Line School 2013-14
Tootin’ Hills SchoolAssociated Costs and Savings
Latimer Lane White Modular: Summer 2013
Latimer Lane School White ModularAssociated Costs/Savings
Central School Relocation:Summer 2014
Central SchoolAssociated Costs and Savings
Latimer Lane: Summer 2015
Latimer Lane SchoolAssociated Costs/Savings
Additional Considerations
• Long term planning to centralize Pre-School• Room readiness costs for program relocation• More appropriate program space• Purchase/reuse of modulars• Developing communications plan based upon
Task Force feedback
Next Steps