flexible riser installation challenges
TRANSCRIPT
-
8/11/2019 Flexible Riser Installation Challenges
1/7
The 15th
Marine Industries Conference (MIC2013)
29-31 October 2013 Kish Island
Flexible Riser Installation Challenges
Ramin Valizadeh1,
Morteza Hoseinpour2, Alireza Ghaemi3, Farshid Ebrahimi4
1Offshore structural engineer, Petro Barasun International Co.;[email protected] structural engineer, Petro Barasun International Co.;[email protected]
Hydraulics structural engineer, Petro Barasun International Co.;[email protected] structural engineer, Petro Barasun International Co.;[email protected]
Abstract
The Soroosh / Nowrooz integrated field development is located in the Persian Gulf with the Nowrooz satellite field
located 50km to the north of Soroosh. The processed fluids are exported to an FSU in 45m of water (LAT) for storageand off-take by shuttle tankers. The present development phase comprises the export of crude from each of the fields to
a single FSU (KHALIJ-e-FARS).
Petro Barasun International Company (PBI) was selected to execute the installation of flexible riser between subsea
pipeline PLEM and FSU TURRET. The client in this project is Iranian Offshore Oil Company and the project consist of
installation of 49" oil FFRP export Pipeline to new FSU with about 200 meters length with a related PLEM (Pipeline
End Manifold.
The purpose of the paper is to define the primary considerations affecting flexible riser installation and to determinefurther and highlight which areas of product specification may be addressed with a view to improving the economics of
installation operations. The paper first defines flexible riser characteristics and identifies the necessary installation
hardware prior to providing commentary on the methods of installation. A basic cost model is introduced to illustrate
the major cost elements of the installation process. Areas of potential hazard and risk are briefly highlighted and asummary of conclusions is provided.
Keywords:flexible riser installation, installation methods, bending stiffness, installation economics.
Introduction
The installation of flexible risers presents a series of practical problems, some of which are of sufficient note to be ofimportance to the designer and to the end user. Their flexibility may easily be brought into question as soon as the
installation contractor begins to handle the end product. Without the benefits of the manufacturing plant, machinery and
conditions it soon becomes obvious that the material is often far from flexible and that what flexibility it possesses onlycreates problems for the contractor.
Whilst the contractor is in the business of overcoming these problems, it is of obvious benefit to all parties that the
relevant direct experience be fed back into the design cycle. This then allows the designer, manufacturer and end user toassess and interpret any benefits that may be achievable by alteration in the specification or design parameters. To date,
the manufacturers have often been left largely to their own devices and conscience with regard to specification, design
and construction. They have expended finance, resources and time in large quantities on the research and development
of their products.
The end products they have created are considered fit for their purpose by the relevant authorities and end users. The
products fill a market requirement and have assisted in pushing forward the technical innovations of subsea
developments. The majority of their R&D work is of a confidential and commercially sensitive nature.
The installation of the end product is an area in which independent installation contractors have been, and will continue
to be, involved, often in association with the manufacturer. It is, however, not immediately apparent that full use is
made of the accumulated experiences gained during installation operations. This is not to say that the current endproduct is in any way deficient or that large scale improvements are possible, only that as part of the expansion of the
subject knowledge it is important to consider the products inherent installation problems.
The authors are invited to use the following guidelines in preparing papers, exactly. We are sure that the authors will
respect the following guidelines in order to raise the conference quality.
The length of the full paper must be between 6 to 10 pages. Please use the following guidelines in preparing your full
papers.
CHARACTERISTICS
The detailed specifics of materials and the methods of construction of a flexible riser are not in themselves relevant to
the installation operation. They do, however, determine the riser characteristics which govern the methods of
installation. Some of these are so basic that the main reason to mention them here is to ensure they are not ignored.
LengthThe continuous length of the riser product is a characteristic of obvious importance. The length required is an outcome
of the riser system design for its specific application and will depend intrinsically on the water depth, the motion
mailto:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected] -
8/11/2019 Flexible Riser Installation Challenges
2/7
2
characteristics of the permanent topside vessel and the designs weather criteria for the site. The length required istherefore normally a physical necessity which is independent of any installation considerations.
The riser length affects the overall riser weight and the dimensions of the reels and winches necessary. There is nodefinable maximum limit on the length of riser that can be installed. However, it is self-evident that the shorter the
length then the more easily it may be installed. Generally, there would be no anticipated difficulties with a riser length
up to 1000 m. Over this length the weight may become a limiting factor, particularly if a riser system such as a Lazy- orSteep-S is being installed as these will require ancillary mid-water and gravity bases to be carried. The installation time
does not increase in direct proportion to the riser length, but it does increase. If multiple riser systems are being installed
then the overall installation time will increase dramatically if additional vessel trips are required because of deck
loading constraints.
Diameter
The internal diameter of a riser is effectively a feature of the flow requirements. The external diameter is a design and
manufacturing feature necessary for the specified internal diameter and flow requirement.
The external diameter is a characteristic which impacts installation in several ways. The riser diameter affects the
overall riser weight and the dimensions of reels and winches: this has a bearing on vessel selection. The diameter also
affects the weight/unit length, the minimum bending radius and the bending stiffness, all of which are of primary
concern to the installation contractor as they dictate the handling characteristics of the riser. Generally, experience
indicates that whilst a 6 in (1 in = 25.4 mm) diameter riser is relatively easy to handle, an 8 in may be difficult.
Weight
The weight/unit length of a flexible riser is determined by the design, materials and construction and is dependent on
the diameter required and the service application. The greater the weight/unit length, the more difficult the handlingproblems associated with over boarding, laydown and pull-in.
The overall weight of the complete riser affects deck loading, sea fastening and craneage requirements. Generally, any
weight-saving possible, either overall or per unit length, will have a consequent benefit towards ease of handling and
vessel requirements during installation.
Table 1 presents typical weight/unit length values for various diameter risers. The values are dependent on design
factors such as service conditions and operating pressures.
Table 1: Typical Values for Flexible Risers Used in Production Systems
External Diameter 4 6 8 10
Weight/Unit length (kg/m) 15 22 75 150
Weight/Unit MBR (m) 0.7 1.0 1.75 2.10
Minimum bending radius
The minimum bending radius (MBR) is a primary characteristic of a flexible riser and it is governed by the design,materials and construction of the product. The MBR is a definitive radius to which the riser may be bent without
damage. It has been suggested that safety factors should be incorporated and further that a factor of 1 -5 should be used
for installation purposes except when the riser is to be bent and supported permanently. Table 1 presents typical MBR
values for various diameter risers.
The MBR of a riser defines the storage drum and winch dimensions necessary. It also controls the dimensions of any
gutter used to feed the riser over the deck edge. It is used as a governing criterion for analysis of the catenary and itsseabed touchdown point. Effectively, it is the main characteristic that must be monitored during installation operations.
A large MBR in excess of 2 m must be accommodated by design, analysis and careful preparation of the installation
procedures. The handling and monitoring requirements increase and the installation time increases. Note that using the
suggested safety factor of 1-5 entails the installation contractor attempting to maintain the actual bend radius in excessof 3 m. During laying operations, this is simply a matter of adjusting the parameters of length paid out and/or vessel
position. However, during seabed handling operations for pull-in and tie-in, it is difficult if not impossible to ensure thatthis is maintained.
Maximum allowable tension
The maximum allowable tension that can be applied to a flexible riser itself is normally so high as to be irrelevant to the
installation. However, there may be a lower maximum allowable tension that should not be exceeded for the riser to end
fitting connection. Effectively, if the catenary self-weight for the water depth can be applied on the end fitting then this
is most unlikely to be exceeded by pull-in loads. Typical values for the actual tensile strength of various riser diameters
are given in Table 2 together with their maximum allowable tensions using a safety factor of 2.
-
8/11/2019 Flexible Riser Installation Challenges
3/7
3
Table 2: Typical Values for Riser Tensile Strength
Riser diameter Tensile strength Max. allowable
(in) (ton) (ton)
4 55 27-5
6 79 39-58 90 450
Tensions during installation operations need to be fully analyzed; however, typically for a 6 in riser, being installed in
120 m water depth, these would need to be maintained below 15 tones.
Bending stiffnessThe bending stiffness of a flexible riser is a characteristic, which has a major impact during installation, particularly onhandling operations subsea. It is often not included as standard datum and the information is not always made available
to the installation contractor. The bending stiffness affects the lifting and manoeuvring of the riser on the seabed during
laydown and during pull-in operations. Typically bending stiffnesses in excess of 90 kN m2 will result in handling
difficulties during laydown, pull-in and tie-in operations.
INSTALLATION EQUIPMENT
The equipment requirements for the installation of a flexible riser are dictated by the riser characteristics.
Winches
A suitable main winch is required to safely deploy a flexible riser. This may take the form of a base and motor, which
engages into a separate and removable drum, thus allowing the change out of a whole drum complete with the
individual riser stored on that drum. If this is not possible then it is necessary to transfer the riser from a delivery orstorage drum on to the main installation winch.
A complete riser length will be a considerable weight that will be dependent on its characteristics and the weight of its
ancillary end fittings. For a Lazy-S system in a 120 m water depth, this will be in the region of 40 tones for a 4 in riser
and up to 80 tones for an 8 in riser.
With the MBR of a riser being of the order of 1-75 m, and this governing the drum diameter, it can be appreciated that
this necessitates a dimensionally large and powerful winch.
Generally, hydraulic winches are utilized offshore and they will be capable of providing upwards of 15 tones line pull at
variable speeds up to 25 m/min. Actual-laying speeds will be in the region 10-15 m/min.
As the flexible riser and pipe market is relatively small, there is a very limited element of choice in the selection ofwinches. Whilst there may be a requirement to optimize winch design, it is not viewed as economically justified.
For safe deployment, it is necessary that the winch be provided with a positive braking mechanism.
Gutters
In order to deploy safely a flexible riser over the side of a vessel deck it is necessary to utilize a gutter or chute
arrangement to lead the riser safely and ensure that a safe bending radius is maintained both over the deck edge and at
either side on entry and exit. Depending on the vessel shape, an angle in excess of 90 may be required to be radiused to
ensure that the riser does not contact any sharp or sudden edge in the event of the vessel backing up on the catenary.
INSTALLATION VESSELS
The minimum vessel requirements are dictated by the necessary installation equipment and the riser characteristics.
Deck space
Flexible riser installation requires a large deck space particularly as it will usually be necessary to carry the variousancillary items that make up the complete riser system, such as a mid-water arch and gravity base structures. The
installation winch itself will take up a large area of deck and there must be sufficient area of deck between the winch
and the gutter to allow handling and rigging of end fittings and positioning of the riser system ancillary items.
Riser systems may easily consist of three or more risers in a single group and these may be required to be installed
simultaneously. The deck space requirements can easily stretch the limits of even large construction vessels.
Effectively, the minimum deck space, which would be considered feasible for the majority of operations, would be
1000 m2.
With deck space and loading as primary requirements, the semi- submersible construction vessels offer the most viable
solution.
Deck loading
As noted above, the installation vessel may be required to accommodate several complete riser systems on deck and all
up deck loadings may be of the order of 700 tones. This may also be concentrated over relatively small areas
-
8/11/2019 Flexible Riser Installation Challenges
4/7
4
necessitating a deck loading capacity in the region of 5 tones/m2. Attention must be paid to the positioning of the
equipment and the sea fastening requirements.
Craneage
An anticipated rating would be 100 tones or more, capable of a single fall operation to the seabed depth and maintaining
in excess of 50 tones at a radius of 10-15 m from the vessels side. An adequate hoisting speed would be in the order of10 m/min. Slewing and topping speeds are not critical. Vessel cranes will be used for handling and over boarding
operations. It may be necessary to use the crane for lifting and handling drums complete with their spooled riser and this
could easily require larger capacity craneage, dependent on available deck space and crane positions.
Diving capability
The diving capability required for a typical North Sea operation as outlined in Section 3.1 above would be anticipated
as a 300 m rated diving system, capable of supporting 16 divers or more and with twin three-man bells. An air diving
station would be advantageous to allow for potential shallow water intervention during over boarding operations.
Additionally, a remotely operated vehicle (ROV) capability is necessary. An eyeball ROV is adequate but because deck
space is at a premium it would be advantageous for the vessel to have a built-in system
Vessel motions
Flexible riser deployment operations will only be carried out in favorable weather conditions with a similar forecast.
However, good vessel motion characteristics can increase the weather operating window which can have obvious
advantages in the case of rapid and unexpected changes in weather and sea-state.
Additionally, seabed pull-in and tie-in operations may be carried out in relatively adverse conditions and the motion
characteristics can determine whether the vessel will be operating or on weather downtime. The advantages of a semi-submersible vessel are obvious.
Positioning
As the installation vessel should be capable of diving operations, this should in itself ensure that an adequate dynamic
positioning (DP) system is available. It is extremely advantageous to have a long baseline acoustic array with real time
video output in both the vessel DP control room and the dive control station. The output should have all major featureson screen including the position of seabed structures.
INSTALLATION ANALYSIS
A sequential analysis of the riser during critical periods of the installation is necessary to confirm that basic criteria
determined from the riser characteristics are being met.
Criteria
The primary criteria to be monitored during riser installation are:
location of the touchdown point;
location of the vessel; and
length of catenary.
These points, together with the riser basic data, will allow full analysis of the riser using standard catenary theory and
hence ensure that adequate safety margins can be maintained for both bending radii and tensions.
Statics or dynamics
The use of standard centenary static analysis is the current practice for determination of geometry and forces during
installation.
Riser installation operations by their nature are limited to extremely good weather conditions in the region of sea-states1 to 2. Unless a static analysis suggests that the load limits are being approached then the introduction of dynamic
analysis does not seem to provide any specific benefits to the operational aspects. However, the time scheduled for the
installation should also be taken into account and it may be considered beneficial to incorporate dynamics, particularly
when multiple riser systems are being installed.
OPERATIONAL METHODS AND CONDITIONS
Operational methods are initially defined by experience and analysis against the previously determined background of
the riser characteristics and selected installation equipment and vessels. Only a general commentary on operational
methods can be presented here and it is to be remembered that operational conditions may necessitate deviation from
proposed methods.
Overboarding
Overboarding of end terminations and ancillary systems such as mid-water arches and gravity bases can presentrelatively complex rigging operations. Most overboarding operations utilize the vessel craneage but ancillary winches
and stopper wires are often required. Chinese fingers are used when it is necessary to stop the riser or to attach holdback
-
8/11/2019 Flexible Riser Installation Challenges
5/7
5
winches. It is to be noted that Lazy- and Steep-Wave configurations minimize overboarding and rigging requirements
and significantly reduce both deployment times and risks associated with overboarding.
Deployment
Deployment of the riser itself is relatively simple, requiring gradual payout of the installation winch in conjunction with
vessel positioning.Deployment of the final end termination or other items to the seabed may require diver intervention to monitor final
positioning and to de-rig lifting slings and attachments.
Pull-ins
Subsea pull-in operations may necessitate divers working in adverse conditions of poor visibility and high tidal currents.
They are in effect rigging problems which are aggravated by the fact that the lifting and moving of the end termination
and riser lifted length cause mud movement which may reduce visibility to nil. For Lazy-Wave and Lazy-S riser
systems, use of the vessel crane attached to the end fitting is the most commonly used method. Further pull-in wires will
be attached to the seabed structure close to the fixed tie-in location, incorporating tirfors, or if necessary run to a surface
constant tension winch. Lifting bags may be attached at intervals along the riser length to assist in reducing pull-in
tensions and frictional resistance.
For the Steep-Wave and Steep-S riser configurations, the riser end connection is required to be pulled down into its
seabed riser base connector (RBC). The methods for carrying out this operation have yet to be optimised and have a
tendency to exceed the pull-in times for Lazy riser configurations.
Alignments and tie-in
Final alignment and tie-in of a seabed flange can present one of the biggest and potentially most time-consumingaspects of installation of the Lazy riser configurations.
A flexible riser must be laid correctly to the seabed with sufficient but not excess overlength to facilitate pull-in. If this
is not the case then the result after pull-in may be significant misalignment of the flanges. It can then require a certain
amount of persuasion to enable the flanges to mate successfully, particularly with large diameter flexibles that in
practice demonstrate considerable rigidity and resistance to bending. Judicial use of dead man anchors, tirfor lines and
lifting bags can be used, but pulling the riser length transversely across the seabed is far from easy as mud build-up willalways occur in the area of the touchdown point. In the resulting poor visibility, the divers spatial reference pointsdisappear and it is impossible to achieve a clear and definite understanding of the riser position.
Once alignment has been achieved, the tie-in becomes similar to that of a rigid pipe flange and provided that the access
around the flange is easy then the operation can be achieved in a timely manner.
For the Steep riser configurations the controlled pull-down to the RBC will positively guide and locate the riser end
connection into place eliminating alignment times.
INSTALLATION ECONOMICS
This section does not aim to provide an indication of the economic merits of subsea production nor to address the
relative proportion ofoverall development costs which are attributed to installation. It is rather the intention to definethe major cost elements inherent in the installation operation.
Operational costs
Operational costs constitute the major proportion of the total installation cost. Operational costs may be split into
various degrees of refinement but essentially consist of the following:
a) vessel costsinclusive of vessel day rate, fuel and lube and marine crew;
b) personnel costsinclusive of project personnel day rates, individual equipment and victualling; and
c)
equipment costsinclusive of project specific equipment day rates.Inclusive costs for North Sea operations may be running in excess of 50 000 per day. With operational costs forming
75% of the overall budget there is a substantial incentive to reduce operational times to a minimum.
Engineering and preparation costs
Because of the high costs associated with the operational aspects, it becomes the aim that all engineering andpreparation works be targeted at reducing the operational time. Well considered, prepared and presented procedures will
do much to reduce overall costs. Preparing the groundwork for logistics, and ensuring that all needs are foreseen prior to
the operational requirement, are primary concerns. An increase in engineering resources is easily justifiable even if it
results in minor savings in operational time. A smooth operation is a cost-effective operation.
Comparative costs for riser systems installation
It is not possible to provide definitive costs for riser installation operations unless a specific project is fully assessed and
this would not greatly assist during the initial design considerations of a project with different design criteria. However,a comparison of the relative costs is given in Table 3 and it is believed that this may prove useful as a guideline for
initial cost assessment for the differing types of riser systems.
-
8/11/2019 Flexible Riser Installation Challenges
6/7
6
The model is simplistic in approach but could be further refined to incorporate weighting for relative risk and factors to
uplift for multiple or group installation.
Table 3:Relative Costs for Riser System InstallationFree hanging Lazy-S Lazy-Wave Steep-S Steep-Wave
Relative vessel days 0-40 0-80 0-60 100 0-80Relative vessel cost/day 0-75 100 1 00 100 100
Relative cost of installation a 30 0-80 0-60 1 00 0-80
To allow the designer and operator to put this into perspective against design and manufacturing costs:
1)
Assume overall engineering costs as equivalent to 50% of the vessel cost per installation day.
2) Assume additional equipment costs as equivalent to one-third of the vessel cost per installation day.3)
Assume that installation of a free hanging catenary riser takes two days which is a realistic starting base.
4)
Assume that an installation vessel capable of installing a free hanging riser system costs 35 000 per day
(approximately 1990 cost).
Relative installation costs would then be as detailed in Table 4. It is important to note that these are orders of magnitude
only.
Table 4:Relative Installation Costs for Riser SystemsRiser system Installation cost (order of magnitude) ()
Free Hanging 127 500Lazy-S 340 000
Lazy-Wave 255 000
Steep-S 425 000
Steep-Wave 340 000
The illustrated costs are for a single riser but costs would not be pro rata for multiple or group installation.Certain costs are not included, notably mob and demob costs. It is obviously of importance to review the uplifts for
engineering and additional equipment as these are subject to prevailing market conditions. The model should only be
used for indicative purposes. The model should be reviewed, adjusted and revised as necessary for any specificapplication. The use of any cost model is not recommended as a replacement for cost analysis based on detailed
schedules and defined resources. The potential for time and hence cost savings that have been previously discussed
cannot easily be illustrated without a detailed cost analysis.
HAZARDS AND RISKS
Heavy rigging operations in a marine environment hold inherent hazards for both personnel and equipment.
Methods and procedures for the installation work should be specifically reviewed with regard to safety aspects and
operational personnel must be aware of any potential risks.With regard to the flexible riser itself, there are two major mechanisms of potential damage:
1)
Mechanical damage by over-tension or by bending. Correct implementation of procedures and monitoring during
installation effectively negates the possibility of damage occurring, unless caused by vessel DP drive-off or during
local rigging operations. It is impossible to guarantee safeguards against DP drive or other hazards throughout riser
installation operations. The risks should, however, be assessed and contingency procedures prepared accordingly.
Local rigging operations on the vessel deck or on the seabed must be carefully planned and controlled.2)
Coating damage by abrasion or impact. Whilst every effort will be made to reduce the possibility of coating
damage it must be recognized that this is a problem inherent with the handling of a riser. There is a relatively highrisk of minor coating damage occurring. Materials and repair procedures should therefore be available.
Methods and materials for permanent subsea repairs are understood not to be available and this aspect could be
actively progressed. Meanwhile, it is essential that the criteria for acceptable/ unacceptable damage be predefined.
CONCLUDING REMARKS
The basic parameters which determine the handling characteristics of a flexible riser are determined prior to the
consideration of the installation aspects. This may be detrimental to the overall economics of the riser system.
Specific areas which will result in the reduction of installation costs are shorter overall length, smaller overall diameter,
lower MBR and lower weight/unit length. The areas which potentially require to be addressed further are the MBR andbending stiffness. Any reduction in the bending stiffness of the riser will have positive benefits throughout the
installation and later maintenance operations.
References[1] American Petroleum Institute (API), Recommended Practice for Flexible Pipes API-RP 17B, API, Washington DC,
USA, 1988.
-
8/11/2019 Flexible Riser Installation Challenges
7/7
7
[2] Cocks, P. J., Testing and Structural Integrity of Flexible Pipes. Engineering Structures, Oct 1989, Butterworth and
Co.
[3] Veritec, Guidelines for Flexible Pipes, Rev. 2, Veritec A/S, Oslo, Norway, 1987.
[4] Johnston, D. R. A., Installation aspects of flexible riser systems, Eng. Struct., Vol. 11, 1989.
[5] Frank Lim, INSTALLATION OF RISERS IN DEEP WATERS, 4th PetroMin Deepwater & Subsea Technol ogy
Conference & Exhibition, Hotel Istana, Kuala Lumpur, Malaysia, 20th - 21st June 2006.[6] Patel, M. H., Seyed, F. B., Review of flexible riser modeling and analysis techniques, Engineering Structures,Vol. 17, No. 4, pp. 293-304, 1995.
[7] Headworth, C., Aylwin, E., Smith, M., Enhanced Flexible Riser Installation Extending Towed Production System
Technologies, Marine Structures, Vol. 5, pp 455-464, 1992.
[8]http://www.globalccsinstitute.com/
[9]http://www.onepetro.org
http://www.globalccsinstitute.com/http://www.onepetro.org/http://www.onepetro.org/http://www.globalccsinstitute.com/