francis howell school district · 2019. 5. 29. · francis howell school district . 4545 central...

2
FRANCIS HOWELL SCHOOL DISTRICT 4545 Central School Road St. Charles, MO 63304-7113 Phone: 636-851-4000 Fax: 636-851-4093 www.fhsdschools.org MEMORANDUM TO: FHSD Board of Education FROM: Kevin Supple DATE: October 1, 2014 RE: Approval of Additional Capital Projects BACKGROUND Voters approved a $78.5 million bond issue in November 2008. Favorable construction pricing allowed the District to complete all of the initially identified projects. Remaining funds were used to address other major capital needs in the District. The Board previously approved the concept of utilizing the Facilities Committee prioritized list of major capital projects as its primary guide in determining uses of remaining bond issue funds. The Board previously approved the use of $2 million of bond issue funds for design and construction of additional electric service at Becky-David, Castlio and Fairmount Elementary Schools, and Barnwell and Hollenbeck Middle Schools and the renovation of the HVAC system at Hollenbeck Middle School. The Administration recommended that the remaining $500,000 in bond issue funds be used for renovations to the band practice field and baseball fields at Francis Howell North High School. The Board asked that a master plan for FHN be completed prior to approval of the renovations. ANALYSIS The District engaged Hoener Associates to develop a master plan for FHN, including the location of a new auditorium. Once it was determined that placement of the new auditorium would not impact the planned renovations to the fields at FHN, the Director of Operations and Facilities met with the principal, activities director, coaches and parents of FHN to develop a phased plan for the field renovations. The Administration is now seeking approval to proceed with the field renovations at FHN to be funded with remaining bond issue funds. RECOMMENDATION The Administration recommends approval of Phase I renovations to the fields at Francis Howell North High School, as shown in the accompanying drawing, with an estimated cost of $500,000. Kevin F. Supple, MBA, RSBA Chief Financial Officer Voice: (636) 851-4023 Fax: (636) 851-4091 [email protected]

Upload: others

Post on 29-Aug-2021

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: FRANCIS HOWELL SCHOOL DISTRICT · 2019. 5. 29. · FRANCIS HOWELL SCHOOL DISTRICT . 4545 Central School Road ... ACKGROUND. Voters approved a $78.5 million bond issue in November

FRANCIS HOWELL SCHOOL DISTRICT 4545 Central School Road ▪ St. Charles, MO 63304-7113

Phone: 636-851-4000 ▪ Fax: 636-851-4093 ▪ www.fhsdschools.org

MEMORANDUM TO: FHSD Board of Education

FROM: Kevin Supple

DATE: October 1, 2014

RE: Approval of Additional Capital Projects

BACKGROUND

Voters approved a $78.5 million bond issue in November 2008. Favorable construction pricing allowed the District to complete all of the initially identified projects. Remaining funds were used to address other major capital needs in the District. The Board previously approved the concept of utilizing the Facilities Committee prioritized list of major capital projects as its primary guide in determining uses of remaining bond issue funds.

The Board previously approved the use of $2 million of bond issue funds for design and construction of additional electric service at Becky-David, Castlio and Fairmount Elementary Schools, and Barnwell and Hollenbeck Middle Schools and the renovation of the HVAC system at Hollenbeck Middle School. The Administration recommended that the remaining $500,000 in bond issue funds be used for renovations to the band practice field and baseball fields at Francis Howell North High School. The Board asked that a master plan for FHN be completed prior to approval of the renovations.

ANALYSIS

The District engaged Hoener Associates to develop a master plan for FHN, including the location of a new auditorium. Once it was determined that placement of the new auditorium would not impact the planned renovations to the fields at FHN, the Director of Operations and Facilities met with the principal, activities director, coaches and parents of FHN to develop a phased plan for the field renovations.

The Administration is now seeking approval to proceed with the field renovations at FHN to be funded with remaining bond issue funds.

RECOMMENDATION

The Administration recommends approval of Phase I renovations to the fields at Francis Howell North High School, as shown in the accompanying drawing, with an estimated cost of $500,000.