geotechnical report 03-1

21
 GROUP: Geotechnical Exploration and Evaluation Report Health Clinic Building Florida Date:-_____________ CLIENT The General Services Administration (GSA) of  Atlantic City, Florida

Upload: mahrbhojia

Post on 13-Apr-2018

213 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Geotechnical Report 03-1

7/26/2019 Geotechnical Report 03-1

http://slidepdf.com/reader/full/geotechnical-report-03-1 1/21

 

GROUP:

Geotechnical Exploration and Evaluation Report

Health Clinic Building

Florida

Date:-_____________

CLIENT

The General Services Administration (GSA) of

 Atlantic City, Florida

Page 2: Geotechnical Report 03-1

7/26/2019 Geotechnical Report 03-1

http://slidepdf.com/reader/full/geotechnical-report-03-1 2/21

Page | 1

The General Services Administration (GSA), Our Ref:

 Atlantic City, Date:

Florida

 Attention: The Manager

Subject: Geotechnical Exploration and Evaluation Report of

Health Clinic Building, Florida

Dear Sir,

I am submitting the final geotechnical exploration and

evaluation report of your proposed project of health clinic

building, Florida. The report includes the recommended

foundation type and design based upon the field and laboratory

testing.

I hope that the investigation results presented in this report

will provide all the necessary information for the construction

of the subject building.

It is pleasure to provide services to you upon your request. If

you have any problem please don’t hesitate to call for any kind

of assistance.

Yours Truly,

(Student Name)

Page 3: Geotechnical Report 03-1

7/26/2019 Geotechnical Report 03-1

http://slidepdf.com/reader/full/geotechnical-report-03-1 3/21

Page | 2

Table of Contents 

1.  INTRODUCTION  3 

2.  INVESTIGATION PURPOSE  3 

3.  GEOTECHNICAL EXPLORATION SCOPE  3 

4.  SUBSOIL STRATIFICATION  4 

5.  FIELD TEST  5 

6.  FOUNDATION DESIGN CONSIDERATION  5 

7.  ENGINEERING RECOMMENDATIONS  7 

8.  INSPECTION AND MONITORING  8 

9.  SUMMARY OF RECOMMENDATIONS  8 

10. REFERNCE  8 

11.  APPENDIX  9 

Page 4: Geotechnical Report 03-1

7/26/2019 Geotechnical Report 03-1

http://slidepdf.com/reader/full/geotechnical-report-03-1 4/21

Page | 3

1. INTRODUCTION

The site for Health Clinic Building, Florida was explored

through 6-boreholes maximum drilled up to 7.62 m depth. The site

is located near the Government Centre Florida and is almost at

road level. This detailed report presents the field testing for

geotechnical investigation and recommendation for foundation

design of the proposed project with the following information.

  Project : Health Clinic Building

  Client : The General Services Administration (GSA) of

Atlantic City 

 

Location : Florida

 

Site Area : 8,825 m2 

  Height of building : 9.14 m

  No of Floor : 02

 

Type of Construction : Reinforced Cement Concrete

2. INVESTIGATION PURPOSE

The main purpose of the report presents description of the site,

a general geotechnical assessment of the project area, details

of the investigation performed and an appreciation of the

subsurface conditions as well as recommendations and conclusions

with respect to the foundation design for the proposed structure

based on the investigation results. The report also includes

recommendations on earthwork including grading, excavation, fill

and compaction.

3. 

GEOTECHNICAL EXPLORATION SCOPE

The program of investigation comprised of following field and

laboratory testing;

 

Drilling of 06 Nos. bore holes of 50 mm diameter to a depth

of 7.62 m from, the respective borehole levels, using 63.5

kg weight using Cable tool Percussion method

  Performance of related field test of SPT

 

Collection of representative disturbed & undisturbed

subsoil samples during soil exploration

  Conducting various Laboratory tests

  Evaluation of Field & Laboratory test results

 

Technical Report with recommendations of suitable

type/depth of foundation & safe bearing capacity

Page 5: Geotechnical Report 03-1

7/26/2019 Geotechnical Report 03-1

http://slidepdf.com/reader/full/geotechnical-report-03-1 5/21

Page | 4

 

Fieldwork was initiated on 25/03/2008 and was accomplished

on 31/03/2008.

4. SUBSOIL STRATIFICATION

The site was explored through 6-boreholes maximum drilled up to

7.62 m depth from the respective existing levels. The subsoilstrata are explained as below:

BH-1

  00.00 - 01.80 m = Grey Silty Sand With Some Shells

  01.80 - 04.60 m = Black Decomposed Organic Material

  04.60 - 07.62 m = Tan Fragmented Limestone

BH-2

  00.00 - 01.80 m = Sand With Fragmented Limestone

  01.80 - 02.43 m = Gray Silty Sand With Organics And Shell

 

02.43 - 04.60 m = Black Decomposed Organic Material

 

04.60 - 06.10 m = Gray Silty Sand And Organics

 

06.10 - 07.62 m = Tan Fragmented Limestone

BH-3

 

00.00 - 00.61 m = Tan Silty Sand With Trace Fragmented

Limestone

  00.61 - 01.22 m = Gray Silty Sand With Trace Shells

  01.22 - 03.05 m = Black Decomposed Organic Material

 

03.05 - 06.10 m = Black Decomposed Organic Material And Sand

 

06.10 – 07.62 m = Tan Fragmented Limestone

BH-4

  00.00 - 00.61 m = Brown Sand With Trace Fragmented Limestone

 

00.61 - 01.82 m = Fragmented Limestone And Limestone

 

01.82 - 02.43 m = Black Decomposed Organic Material

  02.43 - 03.05 m = Gray Silty Sand And Shells

  03.05 - 04.58 m = Black Decomposed Organic Material

 04.58 – 06.10 m = Gray Silty Sand With Some Shells

  06.10 – 07.62 m = Tan Fragmented Limestone

Page 6: Geotechnical Report 03-1

7/26/2019 Geotechnical Report 03-1

http://slidepdf.com/reader/full/geotechnical-report-03-1 6/21

Page | 5

BH-5

  00.00 - 00.61 m = Sand With Trace Fragmented Limestone

  00.61 - 01.22 m = Gray Sand With Fragmented Limestone

  01.22 - 01.83 m = Tan Fragmented Limestone And Limestone

 

01.83 - 04.60 m = Black Decomposed Organic Material 

04.60 - 06.10 m = Gray Silty Sand And Shells

  06.10 – 07.62 m = Tan Fragmented Limestone

BH-6

  00.00 - 02.43 m = Gray Silty Sand With Shell

  02.43 - 04.60 m = Black Decomposed Organic Material

  04.60 - 06.10 m = Gray Silty Sand With Traces Shells

 

04.60 - 07.62 m = Tan Fragmented Limestone

Groundwater-LEVEL

Ground water was come upon at depths ranging from 0.61-1.52 m

from the explored ground level.

5. FIELD TEST

STANDARD FENETRATION TESTS

Standard penetration test (SPT's) is performed on a regular

basis at 15 cm intervals up to the investigated depth in

accordance with the drilling manual specified in ASTM D-1586.

The test was carried out using a manual drop hammer assembly,

which utilizes a manual trip mechanism to release the weight all

in accordance with ASTM D-1586. Results are presented on

borehole logs appendix B figure 03 to figure 09.

6. FOUNDATION DESIGN CONSIDERATION

PILE FOUNDATIONS

Alternatively, pile foundation can be used instead of the

shallow foundations. Bored cast in situ or continuous flight

auger piles are recommended to be used. Table-1 gives the

working loads for piles installed at a pile toe level of H into

Limestone layers. Thus, the net (effective) length of the pile

is (Y) m given in Table-1.

Page 7: Geotechnical Report 03-1

7/26/2019 Geotechnical Report 03-1

http://slidepdf.com/reader/full/geotechnical-report-03-1 7/21

Page | 6

Table-01 (Working Loads for Piles)

These working loads are functions of both point (bearing)

resistance and skin friction and are estimated based on the “N”

values as well as the unconfined compressive strength of the

rock cores extracted from various depths of the boreholes

drilled. Moreover, the resulting pile capacities are compared

with structural capacities of each pile and taking into

consideration the compressive strength of the specified

concrete.

Even though the minimum value of the concrete compressive

strength of 30N/mm2  is allowed for the design of piles, the

concrete to be specified hereby is recommended to be of high

strength. For tall structures, a stiff raft foundation (Rite

Cap) has to be considered for the design of the pile system so

as to resist the differential and total settlement due to the

huge vertical and lateral forces (such as wind & earthquake).

The above working loads allow for a safety factor of at least

2.5.

The loads were calculated based on the method outlined in the

reference “Foundation design and construction” by Tomlinson. 

It may be noted that the above recommended pile working load

capacities are tentative and hence these values should be

confirmed by carrying out pile load tests. Piling contractors

shall be contacted to confirm the working loads for their

respective system.

Every pile must be tested for its integrity (quality and

homogeneity) by carrying out non- destructive tests like sonic

test method. This is necessary to check out the defects or

damages (if any) which may occur after installation of piles dueto the lateral impacts, movements, soil instability and others.

Care should be taken into account during installation of piles

in such case good interactions between the concrete (or grout)

and the soil/rock are ensured in order to mobilize optimum

friction. Moreover, no disturbance shall be caused to the end

bearing strata so as to cause no excessive settlement under

initial loading.

Page 8: Geotechnical Report 03-1

7/26/2019 Geotechnical Report 03-1

http://slidepdf.com/reader/full/geotechnical-report-03-1 8/21

Page | 7

The recommended optimal spacing (S) between clustered piles is

in the order of (2.5 to 3.5 Diameter of the pile-C/C) for

vertical loads, such that: S > 76 cm tor Friction Piles

and S > 60 cm for Point Load Piles. Larger pile spacing is

usually more efficient for groups carrying lateral and/or

dynamic loads.

7. ENGINEERING RECOMMENDATIONS

During the construction measures should be taken as piling is a

critical activity and for the long stability of structure, it is

recommended to follow such measures.

 

The ground water table reported is expected to vary subject

to seasonal variations or any dewatering process in thevicinity. Hence it is advisable to install a standpipe

Piezometer and monitor the ground water table at regular

intervals until it was established that the water level in

borehole had reached equilibrium. At the time of construction

it shall be made sure that the excavation levels for

foundations are at least 0.3m above the ground water table so

that compaction process at the excavated level can be

properly carried out to the required degree.

  For excavations deeper than 2.0m, suitable side protections

have to be ensured so that the excavation shall not pause athreat to the personnel working on the site or cause any

damage to nearby existing buildings or roads.

 

While carrying out dewatering, it shall be ensured that no

excessive settlement is caused to the nearby structures and

the process shall be carried out in stages. Moreover,

suitable precautions have to be taken especially in areas

with weak strata.

 

In case there is an existing structure, which is waiting for

demolition, and the soil investigation has to be carried out

outside the existing structure it is advisable to sink one or

two more boreholes after demolition to confirm the bearing

pressure.

  It is advisable to keep the foundations at least 1.0m below

the finished ground level so that any future excavations for

service lines may not undermine the foundations.

Page 9: Geotechnical Report 03-1

7/26/2019 Geotechnical Report 03-1

http://slidepdf.com/reader/full/geotechnical-report-03-1 9/21

Page | 8

8. INSPECTION AND MONITORING

At the time of pile foundation construction, this office shall

be contacted to carry out compaction, plate load or other tests

if recommended in our report at random locations selected by us

in which case only a letter of confirmation can be issued for

the Safe Bearing Pressure and foundation levels. In case ofpiles, this office shall be contacted for pile integrity tests

without which a confirmation letter cannot be issued.

9. SUMMARY OF RECOMMENDATIONS

  Type of Foundation : Pile Foundation

 

Depth of Pile : 6.5 m 

  Size of Pile : 0.8 m diameter

 

Shape of Pile : Circular

  Material : RCC 30MPA

  Bearing Pressure : 2050 kN

10.  REFERNCE

 

Braja M. Das, "Principles of Foundation Engineering ",Third

Edition, PWS Publishing company

 

Joseph E Bowles, "Foundation Analysis and Design ", Fourth

Edition, MeGraw Hill International Edition

 

Joseph E Bowles, "Physical and Geotechnical Properties of

soils " Second Edition, MeGraw Hill International Edition

 

MJ Tomlinson, Foundation Design and Construction ", Fifth

Edition, Longman Scientific & Technical

 

Hsai - Yang Fang, "Foundation Engineering Handbook ", Second

Edition, Van Nostrand Reinhold

 

BS 5930:1999, “Code of Practice for Site Investigation "

Page 10: Geotechnical Report 03-1

7/26/2019 Geotechnical Report 03-1

http://slidepdf.com/reader/full/geotechnical-report-03-1 10/21

Page | 9

11.  APPENDIX

  Tables (Appendix A)

 

Bore Hole Logs figures (Appendix B)

Page 11: Geotechnical Report 03-1

7/26/2019 Geotechnical Report 03-1

http://slidepdf.com/reader/full/geotechnical-report-03-1 11/21

Page | 10

APPENDIX - A

Table-2

  Calculation of Pile Length

The ultimate bearing capacity of pile is calculated by following formula

2

4

2

145tan

 2

2

 Dπ 

 A

 AqQ

πDL A

qαβ  f  

 A f  Q

QQQ

tip

tiptip

 s

uc

 s friction

tip frictionult 

 N 

q N q uctip

 

  

 

  

 

Page 12: Geotechnical Report 03-1

7/26/2019 Geotechnical Report 03-1

http://slidepdf.com/reader/full/geotechnical-report-03-1 12/21

Page | 11

APPENDIX - B

Figure -01: Site Plan 

Page 13: Geotechnical Report 03-1

7/26/2019 Geotechnical Report 03-1

http://slidepdf.com/reader/full/geotechnical-report-03-1 13/21

Page | 12

Figure -02 (a) : Legends 

Page 14: Geotechnical Report 03-1

7/26/2019 Geotechnical Report 03-1

http://slidepdf.com/reader/full/geotechnical-report-03-1 14/21

Page | 13

Figure -02 (b) : Legends 

Page 15: Geotechnical Report 03-1

7/26/2019 Geotechnical Report 03-1

http://slidepdf.com/reader/full/geotechnical-report-03-1 15/21

Page | 14

Figure -03: Test bore log B-1 

Page 16: Geotechnical Report 03-1

7/26/2019 Geotechnical Report 03-1

http://slidepdf.com/reader/full/geotechnical-report-03-1 16/21

Page | 15

Figure -04: Test bore log B-2 

Page 17: Geotechnical Report 03-1

7/26/2019 Geotechnical Report 03-1

http://slidepdf.com/reader/full/geotechnical-report-03-1 17/21

Page | 16

Figure -05: Test bore log B-3 

Page 18: Geotechnical Report 03-1

7/26/2019 Geotechnical Report 03-1

http://slidepdf.com/reader/full/geotechnical-report-03-1 18/21

Page | 17

Figure -06: Test bore log B-4 

Page 19: Geotechnical Report 03-1

7/26/2019 Geotechnical Report 03-1

http://slidepdf.com/reader/full/geotechnical-report-03-1 19/21

Page | 18

Figure -07: Test bore log B-5 

Page 20: Geotechnical Report 03-1

7/26/2019 Geotechnical Report 03-1

http://slidepdf.com/reader/full/geotechnical-report-03-1 20/21

Page | 19

Figure -08: Test bore log B-6 

Page 21: Geotechnical Report 03-1

7/26/2019 Geotechnical Report 03-1

http://slidepdf.com/reader/full/geotechnical-report-03-1 21/21

Page | 20

Figure -09: Multiple Boring Profiles