geotechnical report 03-1
TRANSCRIPT
![Page 1: Geotechnical Report 03-1](https://reader031.vdocuments.net/reader031/viewer/2022020812/577cc3711a28aba711960a62/html5/thumbnails/1.jpg)
7/26/2019 Geotechnical Report 03-1
http://slidepdf.com/reader/full/geotechnical-report-03-1 1/21
GROUP:
Geotechnical Exploration and Evaluation Report
Health Clinic Building
Florida
Date:-_____________
CLIENT
The General Services Administration (GSA) of
Atlantic City, Florida
![Page 2: Geotechnical Report 03-1](https://reader031.vdocuments.net/reader031/viewer/2022020812/577cc3711a28aba711960a62/html5/thumbnails/2.jpg)
7/26/2019 Geotechnical Report 03-1
http://slidepdf.com/reader/full/geotechnical-report-03-1 2/21
Page | 1
The General Services Administration (GSA), Our Ref:
Atlantic City, Date:
Florida
Attention: The Manager
Subject: Geotechnical Exploration and Evaluation Report of
Health Clinic Building, Florida
Dear Sir,
I am submitting the final geotechnical exploration and
evaluation report of your proposed project of health clinic
building, Florida. The report includes the recommended
foundation type and design based upon the field and laboratory
testing.
I hope that the investigation results presented in this report
will provide all the necessary information for the construction
of the subject building.
It is pleasure to provide services to you upon your request. If
you have any problem please don’t hesitate to call for any kind
of assistance.
Yours Truly,
(Student Name)
![Page 3: Geotechnical Report 03-1](https://reader031.vdocuments.net/reader031/viewer/2022020812/577cc3711a28aba711960a62/html5/thumbnails/3.jpg)
7/26/2019 Geotechnical Report 03-1
http://slidepdf.com/reader/full/geotechnical-report-03-1 3/21
Page | 2
Table of Contents
1. INTRODUCTION 3
2. INVESTIGATION PURPOSE 3
3. GEOTECHNICAL EXPLORATION SCOPE 3
4. SUBSOIL STRATIFICATION 4
5. FIELD TEST 5
6. FOUNDATION DESIGN CONSIDERATION 5
7. ENGINEERING RECOMMENDATIONS 7
8. INSPECTION AND MONITORING 8
9. SUMMARY OF RECOMMENDATIONS 8
10. REFERNCE 8
11. APPENDIX 9
![Page 4: Geotechnical Report 03-1](https://reader031.vdocuments.net/reader031/viewer/2022020812/577cc3711a28aba711960a62/html5/thumbnails/4.jpg)
7/26/2019 Geotechnical Report 03-1
http://slidepdf.com/reader/full/geotechnical-report-03-1 4/21
Page | 3
1. INTRODUCTION
The site for Health Clinic Building, Florida was explored
through 6-boreholes maximum drilled up to 7.62 m depth. The site
is located near the Government Centre Florida and is almost at
road level. This detailed report presents the field testing for
geotechnical investigation and recommendation for foundation
design of the proposed project with the following information.
Project : Health Clinic Building
Client : The General Services Administration (GSA) of
Atlantic City
Location : Florida
Site Area : 8,825 m2
Height of building : 9.14 m
No of Floor : 02
Type of Construction : Reinforced Cement Concrete
2. INVESTIGATION PURPOSE
The main purpose of the report presents description of the site,
a general geotechnical assessment of the project area, details
of the investigation performed and an appreciation of the
subsurface conditions as well as recommendations and conclusions
with respect to the foundation design for the proposed structure
based on the investigation results. The report also includes
recommendations on earthwork including grading, excavation, fill
and compaction.
3.
GEOTECHNICAL EXPLORATION SCOPE
The program of investigation comprised of following field and
laboratory testing;
Drilling of 06 Nos. bore holes of 50 mm diameter to a depth
of 7.62 m from, the respective borehole levels, using 63.5
kg weight using Cable tool Percussion method
Performance of related field test of SPT
Collection of representative disturbed & undisturbed
subsoil samples during soil exploration
Conducting various Laboratory tests
Evaluation of Field & Laboratory test results
Technical Report with recommendations of suitable
type/depth of foundation & safe bearing capacity
![Page 5: Geotechnical Report 03-1](https://reader031.vdocuments.net/reader031/viewer/2022020812/577cc3711a28aba711960a62/html5/thumbnails/5.jpg)
7/26/2019 Geotechnical Report 03-1
http://slidepdf.com/reader/full/geotechnical-report-03-1 5/21
Page | 4
Fieldwork was initiated on 25/03/2008 and was accomplished
on 31/03/2008.
4. SUBSOIL STRATIFICATION
The site was explored through 6-boreholes maximum drilled up to
7.62 m depth from the respective existing levels. The subsoilstrata are explained as below:
BH-1
00.00 - 01.80 m = Grey Silty Sand With Some Shells
01.80 - 04.60 m = Black Decomposed Organic Material
04.60 - 07.62 m = Tan Fragmented Limestone
BH-2
00.00 - 01.80 m = Sand With Fragmented Limestone
01.80 - 02.43 m = Gray Silty Sand With Organics And Shell
02.43 - 04.60 m = Black Decomposed Organic Material
04.60 - 06.10 m = Gray Silty Sand And Organics
06.10 - 07.62 m = Tan Fragmented Limestone
BH-3
00.00 - 00.61 m = Tan Silty Sand With Trace Fragmented
Limestone
00.61 - 01.22 m = Gray Silty Sand With Trace Shells
01.22 - 03.05 m = Black Decomposed Organic Material
03.05 - 06.10 m = Black Decomposed Organic Material And Sand
06.10 – 07.62 m = Tan Fragmented Limestone
BH-4
00.00 - 00.61 m = Brown Sand With Trace Fragmented Limestone
00.61 - 01.82 m = Fragmented Limestone And Limestone
01.82 - 02.43 m = Black Decomposed Organic Material
02.43 - 03.05 m = Gray Silty Sand And Shells
03.05 - 04.58 m = Black Decomposed Organic Material
04.58 – 06.10 m = Gray Silty Sand With Some Shells
06.10 – 07.62 m = Tan Fragmented Limestone
![Page 6: Geotechnical Report 03-1](https://reader031.vdocuments.net/reader031/viewer/2022020812/577cc3711a28aba711960a62/html5/thumbnails/6.jpg)
7/26/2019 Geotechnical Report 03-1
http://slidepdf.com/reader/full/geotechnical-report-03-1 6/21
Page | 5
BH-5
00.00 - 00.61 m = Sand With Trace Fragmented Limestone
00.61 - 01.22 m = Gray Sand With Fragmented Limestone
01.22 - 01.83 m = Tan Fragmented Limestone And Limestone
01.83 - 04.60 m = Black Decomposed Organic Material
04.60 - 06.10 m = Gray Silty Sand And Shells
06.10 – 07.62 m = Tan Fragmented Limestone
BH-6
00.00 - 02.43 m = Gray Silty Sand With Shell
02.43 - 04.60 m = Black Decomposed Organic Material
04.60 - 06.10 m = Gray Silty Sand With Traces Shells
04.60 - 07.62 m = Tan Fragmented Limestone
Groundwater-LEVEL
Ground water was come upon at depths ranging from 0.61-1.52 m
from the explored ground level.
5. FIELD TEST
STANDARD FENETRATION TESTS
Standard penetration test (SPT's) is performed on a regular
basis at 15 cm intervals up to the investigated depth in
accordance with the drilling manual specified in ASTM D-1586.
The test was carried out using a manual drop hammer assembly,
which utilizes a manual trip mechanism to release the weight all
in accordance with ASTM D-1586. Results are presented on
borehole logs appendix B figure 03 to figure 09.
6. FOUNDATION DESIGN CONSIDERATION
PILE FOUNDATIONS
Alternatively, pile foundation can be used instead of the
shallow foundations. Bored cast in situ or continuous flight
auger piles are recommended to be used. Table-1 gives the
working loads for piles installed at a pile toe level of H into
Limestone layers. Thus, the net (effective) length of the pile
is (Y) m given in Table-1.
![Page 7: Geotechnical Report 03-1](https://reader031.vdocuments.net/reader031/viewer/2022020812/577cc3711a28aba711960a62/html5/thumbnails/7.jpg)
7/26/2019 Geotechnical Report 03-1
http://slidepdf.com/reader/full/geotechnical-report-03-1 7/21
Page | 6
Table-01 (Working Loads for Piles)
These working loads are functions of both point (bearing)
resistance and skin friction and are estimated based on the “N”
values as well as the unconfined compressive strength of the
rock cores extracted from various depths of the boreholes
drilled. Moreover, the resulting pile capacities are compared
with structural capacities of each pile and taking into
consideration the compressive strength of the specified
concrete.
Even though the minimum value of the concrete compressive
strength of 30N/mm2 is allowed for the design of piles, the
concrete to be specified hereby is recommended to be of high
strength. For tall structures, a stiff raft foundation (Rite
Cap) has to be considered for the design of the pile system so
as to resist the differential and total settlement due to the
huge vertical and lateral forces (such as wind & earthquake).
The above working loads allow for a safety factor of at least
2.5.
The loads were calculated based on the method outlined in the
reference “Foundation design and construction” by Tomlinson.
It may be noted that the above recommended pile working load
capacities are tentative and hence these values should be
confirmed by carrying out pile load tests. Piling contractors
shall be contacted to confirm the working loads for their
respective system.
Every pile must be tested for its integrity (quality and
homogeneity) by carrying out non- destructive tests like sonic
test method. This is necessary to check out the defects or
damages (if any) which may occur after installation of piles dueto the lateral impacts, movements, soil instability and others.
Care should be taken into account during installation of piles
in such case good interactions between the concrete (or grout)
and the soil/rock are ensured in order to mobilize optimum
friction. Moreover, no disturbance shall be caused to the end
bearing strata so as to cause no excessive settlement under
initial loading.
![Page 8: Geotechnical Report 03-1](https://reader031.vdocuments.net/reader031/viewer/2022020812/577cc3711a28aba711960a62/html5/thumbnails/8.jpg)
7/26/2019 Geotechnical Report 03-1
http://slidepdf.com/reader/full/geotechnical-report-03-1 8/21
Page | 7
The recommended optimal spacing (S) between clustered piles is
in the order of (2.5 to 3.5 Diameter of the pile-C/C) for
vertical loads, such that: S > 76 cm tor Friction Piles
and S > 60 cm for Point Load Piles. Larger pile spacing is
usually more efficient for groups carrying lateral and/or
dynamic loads.
7. ENGINEERING RECOMMENDATIONS
During the construction measures should be taken as piling is a
critical activity and for the long stability of structure, it is
recommended to follow such measures.
The ground water table reported is expected to vary subject
to seasonal variations or any dewatering process in thevicinity. Hence it is advisable to install a standpipe
Piezometer and monitor the ground water table at regular
intervals until it was established that the water level in
borehole had reached equilibrium. At the time of construction
it shall be made sure that the excavation levels for
foundations are at least 0.3m above the ground water table so
that compaction process at the excavated level can be
properly carried out to the required degree.
For excavations deeper than 2.0m, suitable side protections
have to be ensured so that the excavation shall not pause athreat to the personnel working on the site or cause any
damage to nearby existing buildings or roads.
While carrying out dewatering, it shall be ensured that no
excessive settlement is caused to the nearby structures and
the process shall be carried out in stages. Moreover,
suitable precautions have to be taken especially in areas
with weak strata.
In case there is an existing structure, which is waiting for
demolition, and the soil investigation has to be carried out
outside the existing structure it is advisable to sink one or
two more boreholes after demolition to confirm the bearing
pressure.
It is advisable to keep the foundations at least 1.0m below
the finished ground level so that any future excavations for
service lines may not undermine the foundations.
![Page 9: Geotechnical Report 03-1](https://reader031.vdocuments.net/reader031/viewer/2022020812/577cc3711a28aba711960a62/html5/thumbnails/9.jpg)
7/26/2019 Geotechnical Report 03-1
http://slidepdf.com/reader/full/geotechnical-report-03-1 9/21
Page | 8
8. INSPECTION AND MONITORING
At the time of pile foundation construction, this office shall
be contacted to carry out compaction, plate load or other tests
if recommended in our report at random locations selected by us
in which case only a letter of confirmation can be issued for
the Safe Bearing Pressure and foundation levels. In case ofpiles, this office shall be contacted for pile integrity tests
without which a confirmation letter cannot be issued.
9. SUMMARY OF RECOMMENDATIONS
Type of Foundation : Pile Foundation
Depth of Pile : 6.5 m
Size of Pile : 0.8 m diameter
Shape of Pile : Circular
Material : RCC 30MPA
Bearing Pressure : 2050 kN
10. REFERNCE
Braja M. Das, "Principles of Foundation Engineering ",Third
Edition, PWS Publishing company
Joseph E Bowles, "Foundation Analysis and Design ", Fourth
Edition, MeGraw Hill International Edition
Joseph E Bowles, "Physical and Geotechnical Properties of
soils " Second Edition, MeGraw Hill International Edition
MJ Tomlinson, Foundation Design and Construction ", Fifth
Edition, Longman Scientific & Technical
Hsai - Yang Fang, "Foundation Engineering Handbook ", Second
Edition, Van Nostrand Reinhold
BS 5930:1999, “Code of Practice for Site Investigation "
![Page 10: Geotechnical Report 03-1](https://reader031.vdocuments.net/reader031/viewer/2022020812/577cc3711a28aba711960a62/html5/thumbnails/10.jpg)
7/26/2019 Geotechnical Report 03-1
http://slidepdf.com/reader/full/geotechnical-report-03-1 10/21
Page | 9
11. APPENDIX
Tables (Appendix A)
Bore Hole Logs figures (Appendix B)
![Page 11: Geotechnical Report 03-1](https://reader031.vdocuments.net/reader031/viewer/2022020812/577cc3711a28aba711960a62/html5/thumbnails/11.jpg)
7/26/2019 Geotechnical Report 03-1
http://slidepdf.com/reader/full/geotechnical-report-03-1 11/21
Page | 10
APPENDIX - A
Table-2
Calculation of Pile Length
The ultimate bearing capacity of pile is calculated by following formula
2
4
2
145tan
2
2
Dπ
A
AqQ
πDL A
qαβ f
A f Q
QQQ
tip
tiptip
s
uc
s friction
tip frictionult
N
q N q uctip
![Page 12: Geotechnical Report 03-1](https://reader031.vdocuments.net/reader031/viewer/2022020812/577cc3711a28aba711960a62/html5/thumbnails/12.jpg)
7/26/2019 Geotechnical Report 03-1
http://slidepdf.com/reader/full/geotechnical-report-03-1 12/21
Page | 11
APPENDIX - B
Figure -01: Site Plan
![Page 13: Geotechnical Report 03-1](https://reader031.vdocuments.net/reader031/viewer/2022020812/577cc3711a28aba711960a62/html5/thumbnails/13.jpg)
7/26/2019 Geotechnical Report 03-1
http://slidepdf.com/reader/full/geotechnical-report-03-1 13/21
Page | 12
Figure -02 (a) : Legends
![Page 14: Geotechnical Report 03-1](https://reader031.vdocuments.net/reader031/viewer/2022020812/577cc3711a28aba711960a62/html5/thumbnails/14.jpg)
7/26/2019 Geotechnical Report 03-1
http://slidepdf.com/reader/full/geotechnical-report-03-1 14/21
Page | 13
Figure -02 (b) : Legends
![Page 15: Geotechnical Report 03-1](https://reader031.vdocuments.net/reader031/viewer/2022020812/577cc3711a28aba711960a62/html5/thumbnails/15.jpg)
7/26/2019 Geotechnical Report 03-1
http://slidepdf.com/reader/full/geotechnical-report-03-1 15/21
Page | 14
Figure -03: Test bore log B-1
![Page 16: Geotechnical Report 03-1](https://reader031.vdocuments.net/reader031/viewer/2022020812/577cc3711a28aba711960a62/html5/thumbnails/16.jpg)
7/26/2019 Geotechnical Report 03-1
http://slidepdf.com/reader/full/geotechnical-report-03-1 16/21
Page | 15
Figure -04: Test bore log B-2
![Page 17: Geotechnical Report 03-1](https://reader031.vdocuments.net/reader031/viewer/2022020812/577cc3711a28aba711960a62/html5/thumbnails/17.jpg)
7/26/2019 Geotechnical Report 03-1
http://slidepdf.com/reader/full/geotechnical-report-03-1 17/21
Page | 16
Figure -05: Test bore log B-3
![Page 18: Geotechnical Report 03-1](https://reader031.vdocuments.net/reader031/viewer/2022020812/577cc3711a28aba711960a62/html5/thumbnails/18.jpg)
7/26/2019 Geotechnical Report 03-1
http://slidepdf.com/reader/full/geotechnical-report-03-1 18/21
Page | 17
Figure -06: Test bore log B-4
![Page 19: Geotechnical Report 03-1](https://reader031.vdocuments.net/reader031/viewer/2022020812/577cc3711a28aba711960a62/html5/thumbnails/19.jpg)
7/26/2019 Geotechnical Report 03-1
http://slidepdf.com/reader/full/geotechnical-report-03-1 19/21
Page | 18
Figure -07: Test bore log B-5
![Page 20: Geotechnical Report 03-1](https://reader031.vdocuments.net/reader031/viewer/2022020812/577cc3711a28aba711960a62/html5/thumbnails/20.jpg)
7/26/2019 Geotechnical Report 03-1
http://slidepdf.com/reader/full/geotechnical-report-03-1 20/21
Page | 19
Figure -08: Test bore log B-6
![Page 21: Geotechnical Report 03-1](https://reader031.vdocuments.net/reader031/viewer/2022020812/577cc3711a28aba711960a62/html5/thumbnails/21.jpg)
7/26/2019 Geotechnical Report 03-1
http://slidepdf.com/reader/full/geotechnical-report-03-1 21/21
Page | 20
Figure -09: Multiple Boring Profiles