good neighbourly relations committee meeting - brossard - january 25, 2017

42
Good Neighbourly Relations Committee Meeting City of Brossard : 25 january 2017 New Champlain Bridge Corridor Project Centre communautaire Nathalie Croteau Please note that the English version is used only for refernce purposes. In case of disrepancy between the English and French versions, the French version shall prevail.

Upload: nouveau-champlain

Post on 21-Feb-2017

12 views

Category:

Engineering


3 download

TRANSCRIPT

Page 1: Good neighbourly relations committee meeting - Brossard - January 25, 2017

Good Neighbourly Relations Committee Meeting City of Brossard : 25 january 2017 New Champlain Bridge Corridor Project Centre communautaire Nathalie Croteau

Please note that the English version is used only for refernce purposes. In case of disrepancy between the English and French versions, the French version shall prevail.

Page 2: Good neighbourly relations committee meeting - Brossard - January 25, 2017

Projet de corridor du nouveau pont Champlain

2

Committee Members

Residents Luis Oscar Corrales Ginette Dufresne Marc Gagné Nabil Halouani Jacques Picard Jaime Reis Marc Turcotte – Representative from a community organization Éric Jutras – Member of the business community Partners Dan Genest – The Signature on the Saint-Laurent team Benoît Fillion – City of Brossard Vincent Jarry – Infrastructure Canada

Page 3: Good neighbourly relations committee meeting - Brossard - January 25, 2017

Projet de corridor du nouveau pont Champlain

1. Follow up on the various files under the responsibility of Infrastructure Canada : anti-noise wall and DEL lightning

2. Provide information about the work that has been completed, is underway and planned between now and July 2017

3. Answer questions, find potential solutions and discuss the issues

Objectives of the Meeting

3

Page 4: Good neighbourly relations committee meeting - Brossard - January 25, 2017

Projet de corridor du nouveau pont Champlain

Agenda

4

Série Item Durée Heure

1. Opening 10 min. 19h00 à 19h10

2. Anti-noise wall : update 20 min. 19h10 à 19h30

3. Question period 10 min. 19h30 à 19h40

4. Work completed, underway and to come • Eastern approach area • Hwy-10 area • Cable-stayed bridge area

40 min. 19h40 à 20h20

5. Question period 20 min. 20h20 à 20h40

6. Varia 15 min. 20h40 à 20h55

7. Adjournment: next meeting and topic 5 min. 20h55 à 21h00

Page 5: Good neighbourly relations committee meeting - Brossard - January 25, 2017

Projet de corridor du nouveau pont Champlain

Work Completed over the Past Few Months

Page 6: Good neighbourly relations committee meeting - Brossard - January 25, 2017

Projet de corridor du nouveau pont Champlain

Survol des travaux complétés

6

• Fall season: solid work progress in general on the East Approach Construction of footings and pier bases completed Beginning of installation of prefabricated segments

of piers and pier caps Continue the construction of the east abutment

• Installation of the new construction site exit • Very few complaints, mainly about the new

construction site exit (5 on 8)

Page 7: Good neighbourly relations committee meeting - Brossard - January 25, 2017

Projet de corridor du nouveau pont Champlain

Impacts: new construction site exit

7

Impact sonore

Visual impact Mobility impact

Noise impact Opening of the new construction site exit Duration : 3 years

Period : 2017 à 2019

• No incidents recorded or reported • Flow rate : 75 to 150 car / day 10 à 30 car/ night

• Installation of a visual screen • Visible beacon

• Below the 75 dBA criteria • Exceedance caused by traffic on

the upper road network

Page 8: Good neighbourly relations committee meeting - Brossard - January 25, 2017

Projet de corridor du nouveau pont Champlain

Noise Impact

8

Noise tracking at 7070 Place Turenne in Brossard

Sou

nd le

vel

(dB

a)

Noise limit

Page 9: Good neighbourly relations committee meeting - Brossard - January 25, 2017

Projet de corridor du nouveau pont Champlain

Community relations

9

• Presentation at the Club Optimiste Clamplain-Brossard: 1st November 2016

• Presentation in a primary school in Saint-Lambert : 2 December 2016

• Presentation at Association des gens d’affaires de Brossard : 7 December 2016

Page 10: Good neighbourly relations committee meeting - Brossard - January 25, 2017

Projet de corridor du nouveau pont Champlain

A great achievement of our workers

›Dons

Page 11: Good neighbourly relations committee meeting - Brossard - January 25, 2017

Projet de corridor du nouveau pont Champlain

Complaints Handling (April 29 to September 20, 2016)

Thématique Brossard

Fermées Ouvertes Total

Noise 2 1 3

Air Quality 2 - 2

Traffic 3 - 3

Vibrations - - -

Brightness 2 - 2

Other - - -

Total 9 1 10

11

Eight complaints in the previous period from April 30 to September 20, 2016

Page 12: Good neighbourly relations committee meeting - Brossard - January 25, 2017

Projet de corridor du nouveau pont Champlain

Main Priorities for the Upcoming Months- South Shore

Page 13: Good neighbourly relations committee meeting - Brossard - January 25, 2017

Projet de corridor du nouveau pont Champlain

Location of Work Areas City of Brossard

Cable-stayed bridge

Page 14: Good neighbourly relations committee meeting - Brossard - January 25, 2017

Projet de corridor du nouveau pont Champlain

Highway 10

• Soil management

• Preparatory works for the configuration of the highway 10

East Approch

• Installation of prefabricated segments of piers and pier caps

• Continue the construction of the east abutment, including the building housing the electric systems

• Preparations for the construction of the span above Route 132

Cable-stayed bridge

• Construction of main pylon and rear span

South Shore Priorities : January to June 2017

14

Page 15: Good neighbourly relations committee meeting - Brossard - January 25, 2017

Projet de corridor du nouveau pont Champlain

Description of Activity Approximate Duration of Works

Planned Work Period

Legend: Work and Impacts

• Traffic and Public Transportation: • Proximity of Residential Areas: • Boating: • Bike Paths:

Minor impact Medium impact

Major impact

Indication by level colour code

15

Page 16: Good neighbourly relations committee meeting - Brossard - January 25, 2017

Projet de corridor du nouveau pont Champlain

Key Activities Underway and to Come - East Approach

Design and planning underway so modifications are possible

Page 17: Good neighbourly relations committee meeting - Brossard - January 25, 2017

Projet de corridor du nouveau pont Champlain

Objective: Construction of East Approach of the new Champlain Bridge

Travaux en cours et à venir :

• Placement of prefabricated segments of piers and pier caps

• Continue the construction of the abutment, including the building housing the electric systems

• Preparatory works for the construction of the span above Highway 132

Approach:

• Daytime work, to the extent possible, when the impacts (especially noise levels) are significant

• Nighttime work, to the extent possible, when the impacts on daytime traffic are too significant

East Approach Area

17

Page 18: Good neighbourly relations committee meeting - Brossard - January 25, 2017

Projet de corridor du nouveau pont Champlain

Nov 2015

May Nov 2016

May Nov. 2017

Nov 2018

May

East Approach: Timetable

18

Feb 2016

Aug Feb 2017

Aug. Feb. 2018

Aug.

Construction of footings and pier

bases

Installation of piers and pier caps

Assembly of superstructure and deck

Finishing work

Page 19: Good neighbourly relations committee meeting - Brossard - January 25, 2017

Projet de corridor du nouveau pont Champlain

Works and Impacts: East Approach

19

Placement of prefabricated segments of piers and pier caps

Duration: eight months Projected period: October 2016 to Summer 2017

Page 20: Good neighbourly relations committee meeting - Brossard - January 25, 2017

Projet de corridor du nouveau pont Champlain

Works and Impacts: East Approach

20

Construction of East Abutment’s building Duration: four months

Projected period: April to July 2017

Page 21: Good neighbourly relations committee meeting - Brossard - January 25, 2017

Projet de corridor du nouveau pont Champlain

Works and Impacts: East Approach

Preparatory works for the construction of the span above Highway 132

Duration : four months Projected period: april to july 2017

21

Page 22: Good neighbourly relations committee meeting - Brossard - January 25, 2017

Projet de corridor du nouveau pont Champlain

Key Activities Underway and to Come Highway 10

Conception et planification en développement donc des modifications sont possibles

Page 23: Good neighbourly relations committee meeting - Brossard - January 25, 2017

Projet de corridor du nouveau pont Champlain

Highway 10 Area

23

Objective: Area reserved for soil management for the work site and preparatory work for the reconfiguration of highway links

Work underway:

• Soil storage

• Earthworks at the eastern abutment

• Creation of a retaining basin for permanent drainage

Upcoming Works

• Installation of permanent anti-noise walls

Approach:

• Daytime work, to the extent possible, when the impacts (especially noise levels) are significant

• Night-time trucking from the West Approach to the East Approach

Page 24: Good neighbourly relations committee meeting - Brossard - January 25, 2017

Projet de corridor du nouveau pont Champlain

Works and Impacts: Highway 10

Soil management and creation of a retaining basin Duration: throughout the project Projected period: 2016 to 2019

24

Page 25: Good neighbourly relations committee meeting - Brossard - January 25, 2017

Projet de corridor du nouveau pont Champlain

Works and Impacts: Highway 10

Earthworks at the eastern abutment Duration: one year

Projected period: April 2016 to Spring 2017

25

Page 26: Good neighbourly relations committee meeting - Brossard - January 25, 2017

Projet de corridor du nouveau pont Champlain

Works and Impacts: Highway 10

Installation of permanent anti-noise walls Duration : three months

Projected period: summer / fall 2017

26

Page 27: Good neighbourly relations committee meeting - Brossard - January 25, 2017

Projet de corridor du nouveau pont Champlain

Key Activities Underway and to Come Cable-stayed Bridge

Design and planning underway so modifications are possible

Page 28: Good neighbourly relations committee meeting - Brossard - January 25, 2017

Projet de corridor du nouveau pont Champlain

Cable-stayed Bridge: Timetable

28

2. Pylon foundations October 2015 to April 2016 1. Jetty

August to October 2015

7. Main span March 2017 to

September 2018

3. Rear span November 2015 to July 2017

6. Upper pylon February to December

2017

4. Lower pylon May to October 2016

5. Lower crossbeam October to February 2017

Page 29: Good neighbourly relations committee meeting - Brossard - January 25, 2017

Projet de corridor du nouveau pont Champlain

Key activities since fall 2016

29

Construction of the lower pylon and the rear span

Page 30: Good neighbourly relations committee meeting - Brossard - January 25, 2017

Projet de corridor du nouveau pont Champlain

Key activities since fall 2016

Installation of the lower crossbeam

Page 31: Good neighbourly relations committee meeting - Brossard - January 25, 2017

Projet de corridor du nouveau pont Champlain

Works and impacts : Bike path of the seaway dike

31

Ponctual closing of variable duration for the seasons 2017 and 2018 et, if necessary, long term closing

Communication strategy : bike path signs, newspaper, e-mail alerts and signalers

Page 32: Good neighbourly relations committee meeting - Brossard - January 25, 2017

Projet de corridor du nouveau pont Champlain

Anticipated Impacts

Page 33: Good neighbourly relations committee meeting - Brossard - January 25, 2017

Projet de corridor du nouveau pont Champlain

Anticipated impacts

• Road traffic

• Noise

• Air quality

33

Page 34: Good neighbourly relations committee meeting - Brossard - January 25, 2017

Projet de corridor du nouveau pont Champlain

Traffic

• Disruptions to come

• Upcoming major disruptions for the Spring / Summer 2017 : installation of superstructure and deck above Highway 132 traffic lanes

34

Configuration – Disruptions Schedule Duration

Installation of foundations and temporary scaffolding

March / April 2017 1 week

Passage of pier caps pieces May 2017 8 nights

Route Deviation from route 132 & boul. Marie-Victorin May 2017 2 years

Page 35: Good neighbourly relations committee meeting - Brossard - January 25, 2017

Projet de corridor du nouveau pont Champlain

Passage of Pier Caps Pieces

35

Page 36: Good neighbourly relations committee meeting - Brossard - January 25, 2017

Projet de corridor du nouveau pont Champlain

Steel Pier Caps

36

Page 37: Good neighbourly relations committee meeting - Brossard - January 25, 2017

Projet de corridor du nouveau pont Champlain 37

B1: Turenne area B2: Voltaire area B3: Tisserand area

Noise Management Ar

ea Activity

Period D/E/N

Exposed sensitive

area

Ambient noise dBA

Criterion dBA

Estimatednoise dBA

Required measures

D B1/B2 60/62 75 62/63 Not required

Construction of building (east abutment) D B2 62 75 66 Not required

Placement of prefabricated segments of piers and

pier caps

D/E-N B2 62 75/67 To come

A10

Earthworks at the Eastern Abutment

D B2 62 75

Cabl

e-st

ayed

Miscellaneous work D B1/B2 60/62 75 61/64 Not required

East

App

roac

h

D B2 62 75

Preparatory works Highway 132

To come

Installation of permanent anti-noise walls

Monitoring required

73

Monitoring required

75

Page 38: Good neighbourly relations committee meeting - Brossard - January 25, 2017

Projet de corridor du nouveau pont Champlain

Air Quality Management

• Migitation measures : increased environmental monitoring + Frequent

water spaying and cleaning

• Regulatory framework : Contractual environmental obligations and Clean Air Regulation (CAR)

Applicable MDDELCC standards

MDDELCC CAR

PMt PM2.5

120 ug/m3 30 ug/m3

38

Page 39: Good neighbourly relations committee meeting - Brossard - January 25, 2017

Projet de corridor du nouveau pont Champlain

Follow-up on Interventions

39

SSL • Follow-up on the impacts of the new site exit • Date for the installations of anti-noise walls • Landscaping and building of the east abutment

Ville de Brossard • Communications regarding the detour for cyclists during the

reconstruction of Panama

INFC (discuss previously) • Follow-up on the anti-noise walls • LED lighting tracking

Page 40: Good neighbourly relations committee meeting - Brossard - January 25, 2017

Projet de corridor du nouveau pont Champlain

Next meetings

Page 41: Good neighbourly relations committee meeting - Brossard - January 25, 2017

Projet de corridor du nouveau pont Champlain

Good Neighbourly Relations Committee : 10 or 17 may (to be confirmed) Topics:

Mobility Landscaping

A site visit is planned for Friday 5 May in the afternoon

Next meetings

41

Page 42: Good neighbourly relations committee meeting - Brossard - January 25, 2017

Projet de corridor du nouveau pont Champlain

• Newsletter: sign up online

• Information sheets delivered to residents’ homes, if required, and notices in local newspapers

• Sign up / contact us: Website: www.newchamplain.ca Email: [email protected]

Phone us at: (514) 876-1020 Twitter: @NOUV_CHAMPLAIN

Communication