good neighbourly relations committee meeting - brossard - january 25, 2017
TRANSCRIPT
Good Neighbourly Relations Committee Meeting City of Brossard : 25 january 2017 New Champlain Bridge Corridor Project Centre communautaire Nathalie Croteau
Please note that the English version is used only for refernce purposes. In case of disrepancy between the English and French versions, the French version shall prevail.
Projet de corridor du nouveau pont Champlain
2
Committee Members
Residents Luis Oscar Corrales Ginette Dufresne Marc Gagné Nabil Halouani Jacques Picard Jaime Reis Marc Turcotte – Representative from a community organization Éric Jutras – Member of the business community Partners Dan Genest – The Signature on the Saint-Laurent team Benoît Fillion – City of Brossard Vincent Jarry – Infrastructure Canada
Projet de corridor du nouveau pont Champlain
1. Follow up on the various files under the responsibility of Infrastructure Canada : anti-noise wall and DEL lightning
2. Provide information about the work that has been completed, is underway and planned between now and July 2017
3. Answer questions, find potential solutions and discuss the issues
Objectives of the Meeting
3
Projet de corridor du nouveau pont Champlain
Agenda
4
Série Item Durée Heure
1. Opening 10 min. 19h00 à 19h10
2. Anti-noise wall : update 20 min. 19h10 à 19h30
3. Question period 10 min. 19h30 à 19h40
4. Work completed, underway and to come • Eastern approach area • Hwy-10 area • Cable-stayed bridge area
40 min. 19h40 à 20h20
5. Question period 20 min. 20h20 à 20h40
6. Varia 15 min. 20h40 à 20h55
7. Adjournment: next meeting and topic 5 min. 20h55 à 21h00
Projet de corridor du nouveau pont Champlain
Work Completed over the Past Few Months
Projet de corridor du nouveau pont Champlain
Survol des travaux complétés
6
• Fall season: solid work progress in general on the East Approach Construction of footings and pier bases completed Beginning of installation of prefabricated segments
of piers and pier caps Continue the construction of the east abutment
• Installation of the new construction site exit • Very few complaints, mainly about the new
construction site exit (5 on 8)
Projet de corridor du nouveau pont Champlain
Impacts: new construction site exit
7
Impact sonore
Visual impact Mobility impact
Noise impact Opening of the new construction site exit Duration : 3 years
Period : 2017 à 2019
• No incidents recorded or reported • Flow rate : 75 to 150 car / day 10 à 30 car/ night
• Installation of a visual screen • Visible beacon
• Below the 75 dBA criteria • Exceedance caused by traffic on
the upper road network
Projet de corridor du nouveau pont Champlain
Noise Impact
8
Noise tracking at 7070 Place Turenne in Brossard
Sou
nd le
vel
(dB
a)
Noise limit
Projet de corridor du nouveau pont Champlain
Community relations
9
• Presentation at the Club Optimiste Clamplain-Brossard: 1st November 2016
• Presentation in a primary school in Saint-Lambert : 2 December 2016
• Presentation at Association des gens d’affaires de Brossard : 7 December 2016
Projet de corridor du nouveau pont Champlain
A great achievement of our workers
›Dons
Projet de corridor du nouveau pont Champlain
Complaints Handling (April 29 to September 20, 2016)
Thématique Brossard
Fermées Ouvertes Total
Noise 2 1 3
Air Quality 2 - 2
Traffic 3 - 3
Vibrations - - -
Brightness 2 - 2
Other - - -
Total 9 1 10
11
Eight complaints in the previous period from April 30 to September 20, 2016
Projet de corridor du nouveau pont Champlain
Main Priorities for the Upcoming Months- South Shore
Projet de corridor du nouveau pont Champlain
Location of Work Areas City of Brossard
Cable-stayed bridge
Projet de corridor du nouveau pont Champlain
Highway 10
• Soil management
• Preparatory works for the configuration of the highway 10
East Approch
• Installation of prefabricated segments of piers and pier caps
• Continue the construction of the east abutment, including the building housing the electric systems
• Preparations for the construction of the span above Route 132
Cable-stayed bridge
• Construction of main pylon and rear span
South Shore Priorities : January to June 2017
14
Projet de corridor du nouveau pont Champlain
Description of Activity Approximate Duration of Works
Planned Work Period
Legend: Work and Impacts
• Traffic and Public Transportation: • Proximity of Residential Areas: • Boating: • Bike Paths:
Minor impact Medium impact
Major impact
Indication by level colour code
15
Projet de corridor du nouveau pont Champlain
Key Activities Underway and to Come - East Approach
Design and planning underway so modifications are possible
Projet de corridor du nouveau pont Champlain
Objective: Construction of East Approach of the new Champlain Bridge
Travaux en cours et à venir :
• Placement of prefabricated segments of piers and pier caps
• Continue the construction of the abutment, including the building housing the electric systems
• Preparatory works for the construction of the span above Highway 132
Approach:
• Daytime work, to the extent possible, when the impacts (especially noise levels) are significant
• Nighttime work, to the extent possible, when the impacts on daytime traffic are too significant
East Approach Area
17
Projet de corridor du nouveau pont Champlain
Nov 2015
May Nov 2016
May Nov. 2017
Nov 2018
May
East Approach: Timetable
18
Feb 2016
Aug Feb 2017
Aug. Feb. 2018
Aug.
Construction of footings and pier
bases
Installation of piers and pier caps
Assembly of superstructure and deck
Finishing work
Projet de corridor du nouveau pont Champlain
Works and Impacts: East Approach
19
Placement of prefabricated segments of piers and pier caps
Duration: eight months Projected period: October 2016 to Summer 2017
Projet de corridor du nouveau pont Champlain
Works and Impacts: East Approach
20
Construction of East Abutment’s building Duration: four months
Projected period: April to July 2017
Projet de corridor du nouveau pont Champlain
Works and Impacts: East Approach
Preparatory works for the construction of the span above Highway 132
Duration : four months Projected period: april to july 2017
21
Projet de corridor du nouveau pont Champlain
Key Activities Underway and to Come Highway 10
Conception et planification en développement donc des modifications sont possibles
Projet de corridor du nouveau pont Champlain
Highway 10 Area
23
Objective: Area reserved for soil management for the work site and preparatory work for the reconfiguration of highway links
Work underway:
• Soil storage
• Earthworks at the eastern abutment
• Creation of a retaining basin for permanent drainage
Upcoming Works
• Installation of permanent anti-noise walls
Approach:
• Daytime work, to the extent possible, when the impacts (especially noise levels) are significant
• Night-time trucking from the West Approach to the East Approach
Projet de corridor du nouveau pont Champlain
Works and Impacts: Highway 10
Soil management and creation of a retaining basin Duration: throughout the project Projected period: 2016 to 2019
24
Projet de corridor du nouveau pont Champlain
Works and Impacts: Highway 10
Earthworks at the eastern abutment Duration: one year
Projected period: April 2016 to Spring 2017
25
Projet de corridor du nouveau pont Champlain
Works and Impacts: Highway 10
Installation of permanent anti-noise walls Duration : three months
Projected period: summer / fall 2017
26
Projet de corridor du nouveau pont Champlain
Key Activities Underway and to Come Cable-stayed Bridge
Design and planning underway so modifications are possible
Projet de corridor du nouveau pont Champlain
Cable-stayed Bridge: Timetable
28
2. Pylon foundations October 2015 to April 2016 1. Jetty
August to October 2015
7. Main span March 2017 to
September 2018
3. Rear span November 2015 to July 2017
6. Upper pylon February to December
2017
4. Lower pylon May to October 2016
5. Lower crossbeam October to February 2017
Projet de corridor du nouveau pont Champlain
Key activities since fall 2016
29
Construction of the lower pylon and the rear span
Projet de corridor du nouveau pont Champlain
Key activities since fall 2016
Installation of the lower crossbeam
Projet de corridor du nouveau pont Champlain
Works and impacts : Bike path of the seaway dike
31
Ponctual closing of variable duration for the seasons 2017 and 2018 et, if necessary, long term closing
Communication strategy : bike path signs, newspaper, e-mail alerts and signalers
Projet de corridor du nouveau pont Champlain
Anticipated Impacts
Projet de corridor du nouveau pont Champlain
Anticipated impacts
• Road traffic
• Noise
• Air quality
33
Projet de corridor du nouveau pont Champlain
Traffic
• Disruptions to come
• Upcoming major disruptions for the Spring / Summer 2017 : installation of superstructure and deck above Highway 132 traffic lanes
34
Configuration – Disruptions Schedule Duration
Installation of foundations and temporary scaffolding
March / April 2017 1 week
Passage of pier caps pieces May 2017 8 nights
Route Deviation from route 132 & boul. Marie-Victorin May 2017 2 years
Projet de corridor du nouveau pont Champlain
Passage of Pier Caps Pieces
35
Projet de corridor du nouveau pont Champlain
Steel Pier Caps
36
Projet de corridor du nouveau pont Champlain 37
B1: Turenne area B2: Voltaire area B3: Tisserand area
Noise Management Ar
ea Activity
Period D/E/N
Exposed sensitive
area
Ambient noise dBA
Criterion dBA
Estimatednoise dBA
Required measures
D B1/B2 60/62 75 62/63 Not required
Construction of building (east abutment) D B2 62 75 66 Not required
Placement of prefabricated segments of piers and
pier caps
D/E-N B2 62 75/67 To come
A10
Earthworks at the Eastern Abutment
D B2 62 75
Cabl
e-st
ayed
Miscellaneous work D B1/B2 60/62 75 61/64 Not required
East
App
roac
h
D B2 62 75
Preparatory works Highway 132
To come
Installation of permanent anti-noise walls
Monitoring required
73
Monitoring required
75
Projet de corridor du nouveau pont Champlain
Air Quality Management
• Migitation measures : increased environmental monitoring + Frequent
water spaying and cleaning
• Regulatory framework : Contractual environmental obligations and Clean Air Regulation (CAR)
Applicable MDDELCC standards
MDDELCC CAR
PMt PM2.5
120 ug/m3 30 ug/m3
38
Projet de corridor du nouveau pont Champlain
Follow-up on Interventions
39
SSL • Follow-up on the impacts of the new site exit • Date for the installations of anti-noise walls • Landscaping and building of the east abutment
Ville de Brossard • Communications regarding the detour for cyclists during the
reconstruction of Panama
INFC (discuss previously) • Follow-up on the anti-noise walls • LED lighting tracking
Projet de corridor du nouveau pont Champlain
Next meetings
Projet de corridor du nouveau pont Champlain
Good Neighbourly Relations Committee : 10 or 17 may (to be confirmed) Topics:
Mobility Landscaping
A site visit is planned for Friday 5 May in the afternoon
Next meetings
41
Projet de corridor du nouveau pont Champlain
• Newsletter: sign up online
• Information sheets delivered to residents’ homes, if required, and notices in local newspapers
• Sign up / contact us: Website: www.newchamplain.ca Email: [email protected]
Phone us at: (514) 876-1020 Twitter: @NOUV_CHAMPLAIN
Communication
42