Powering our way of life.
Operate Responsibly by Attaining Environmental, Cultural Resource and Regulatory Compliance
Fish and Wildlife Quarterly Business Report
Grant PUD Commission MeetingJune 9, 2020
Purpose & Goal The Fish and Wildlife Business Unit uses technology, innovation, strategic thinking, good stakeholder relations and skilled negotiations to ensure we are achieving compliance with our Natural Resources regulatory requirements in a safe, cost efficient and biologically sound manner while helping to maintain the long-term financial health of the District.
2020 Safety Cultural No Recordable Incidents;
Job Site Reviews (N=15; Currently at 65.2%) Goal = 15%; Stretch Goal = 25%
Overall Safety Meeting Attendance = 100%;
Updated Job Hazard Assessments
Priest Rapids Hatchery Safety Fixes (Q2-Q3) Priest Rapids Hatchery
Covid-19 Site Specific Work Plans Priest Rapids Hatchery Off Ladder Adult Fish Trap Video Fish Counting Vegetation Mgmt. Fish Predator Control/USDA Angling Water Quality Juvenile White Sturgeon Release
2020 Compliance Review• File 22 annual reports and plans with various agencies;
• Progress & Implementation Report (8 Combined)• Aquatic Invasive Species Control & Prevention• Bull trout report and 10 year review• White Sturgeon annual report• Pacific Lamprey annual report• Northern Wormwood Conservation Plan• Gas Abatement Plan• Transmission Line Collision Protection• Bald Eagle Perching/Roosting Protection Plan• Wildlife Habitat Monitoring, Info & education• Native Resident Fish • Fish Spill and total dissolved gas report• USFWS Annual Recovery report• USFWS Annual – Special Use Permit
• File 12 reports related to mitigation sites;
• Boundary Adjustment for Nason Creek Acclimation Facility with FERC;
2020 Fish and Wildlife Budget Fish & Wildlife Business Unit - Allocated Resources
Fish & Wildlife Staff 17 Full-Time Regulars (FTRs)11.0 Full-Time Equivalents (FTEs)
Fish and Wildlife Manager (2 FTR) 1.0 FTEs
Hatchery & Habitat (7 FTRs) 3.0 FTEs
Anadromous & Resident Fish (5 FTRs) 7.0 FTEs
Wildlife/Botanical (3 FTRs)
Budget Operation & Maintenance = $12,693,611 Capital (Directs) = $ 1,519,769 Labor (non-benefit adjusted) = $ 3,377,095*
2020 Budget $17,590,475
* Includes Salaries & Wages, other labor and benefits/overheads
Operations and Maintenance = 72.2%
Labor = 19.2%
Cap = 8.6%
2020 Budget Review – Allocated Budget
Category Budget Actuals ($)For Month Ending
(4/30/2020)
Year-End Projection
($)
Year-End Projection
(%)
O&M $12,693,611 $818,467 $12,580,000 99.1%
Capital $1,519,769 $38,546 $1,426,837 93.9%
Labor $3,377,095 $864,151 $3,014,477 89.3%
Total $17,590,475 $1,721,164 $17,021,314 96.7%
Budget and Actuals came from the Finance report:https://reports.gcpud.org/Reports/powerbi/Finance%20Reports/Budget%20vs%20Actual%20Reports
Covid-19 - Essential Business Hatchery Production
Priest Rapids Hatchery (GPUD) Carlton & Nason Acclimation Facilities (GPUD) Eastbank Hatchery (CPUD) Wells & Methow Hatchery (DPUD) Penticton (ONA) Chief Joseph (CCT) St Mary’s Acclimation (CCT) Marian Drain (YN)
Anadromous & Resident Fish Passage
Video Fish Counting
Hanford Reach Operations
Juvenile Salmonid Passage
Vegetation Mgmt.
Compliance Reporting & Consultation
White Sturgeon Broodstock
2020 Tier 1 - Business ActivitiesCarlton Acclimation Intake Structure
Issue: Methow River migrating away from water intake.
Alternatives Analysis Completed 5 different Options ($1.2 – $5.3 Million) Estimates DID NOT include Mitigation Costs or Internal Labor Install additional Production/Domestic well
Lower cost alternative (Current Approved Capital =$670,000)
In Progress Development of technical specifications; Permitting; Contract development; Target date for contract award – Mid-July, 2020; Target completion date – Project Close out October, 2020.
2020 Tier 1 – Hanford ReachOperational Plan for Implementation of the Hanford
Reach Fall Chinook Protection Agreement
Issue: Formal operating protocols need to be developed to replace procedures that had been implemented through Mid-C Hourly Coordination with the Utility Parties.
In Progress
Working to development a joint operating plan.
2020 Tier 1 – Priest Rapids HatcheryDevelop financial and strength, weakness, opportunities and
threat analysis (SWOT) for the operation of the Priest Rapids Hatchery.
Completed
Financial analysis completed and reviewed by internal stakeholders; SWOT analysis; Information presented to CXO’s and CEO/General Manager (January 2020);
In Progress
FW staff responding to additional information request; Exploring contracting mechanisms with USCOE; January 2020 meeting with CXO’s & CEO/GM; June 16, 2020 meeting scheduled with CXO’s & CEO/GM.
2020 Tier 1 - Business Activities Rehabilitation of Wells at Priest Rapids Hatchery.
Issue: Three of the eight wells were inoperable during a majority of the timeframe when the Priest Rapids Reservoir was operated at lower elevations for Priest Rapids Spillway work/evaluation.
White River Spring Chinook Program
Vegetation Management
Survival Evaluations scheduled for 2025, 2026 & 2027
Avian Predation in the Columbia River Plateau
Northern Wormwood Conservation Plan
Predator Removal Program
2020 Tier 2 - Business Activities
2020 Business ActivitiesTumwater Dam
Tumwater Dam Fish Weir (Owned by Chelan PUD)
Interlocal Cooperative Agreement (ICA) in place that allows GPUD to utilize the Tumwater weir to collect adult broodstock for GPUD hatchery programs in the Wenatchee River Basin (summer Chinook and Nason Creek spring Chinook).
The ICA specifically defines the specific cost allocations to each PUD depending on the type of activity and/or reactive repair (GPUD’s share is = 36%).
Chelan PUD staff identified erosion and undercutting on the lowermost section of the fishway adjacent to Tumwater dam.
CPUD has indicated that the preliminary estimated is ~$550,000. Of which GPUD would be responsible for $198,000 (36%).
Powering our way of life.
Quarter 2 Commission Update 6/9/20
Powering our way of life.
Power Production:Cultural Resources
2020 Q1 Business Review
Major Projects & Work Activities
• We completed the Memorandum of Agreement with our stakeholder group for the Priest Rapids Right Embankment project and initiated a Social Impact Assessment of the potential effects of the Priest Rapids Right Bank Project on the WanapumIndian Village.
• We submitted our first annual report to the Cultural Resources Working Group; There are no anticipated issues.
Cultural Resources Safety Status
Quarter 1 was completed without any safety incidents or close calls.
Three safety monitors were added in order to respond to the right bank construction project.
Safety meeting attendance was 100% in Q1.
2020 Q2 Budget Data
Category Budget
Actuals ($) for Month
Ended 04/30/2020
Year-End Projection
($)
Year-End Projection
(%)CAP $9,999 $247 $250 3%
O&M $1,287,126 $242,943 $1,253,256 97%Labor $2,698,677 $714,887 $2,321,690 86%Total $3,995,802 $958,077 $3,575,196 89%
2020 Q2/3 Forecast
• Continuation of effects mitigation plan in consultation with our Tribal, Federal and State stakeholders.
-Mitigation discussions will begin in Q3
• Continuation of Priest Rapids Right Embankment work-Focus is on meeting the MOA details-Completion of a Social Impact Assessment is resulting in our working directly with the Wanapum to address issues that may arise. Anticipated issues are related to dust abatement, sound etc.
2020 Q2/3 Forecast
Use of Allocated Resources
• Staffing – No staffing changes anticipated
2020 Forecast
Potential Management Challenges
• Continued discussions with Tribal groups, state and federal agencies regarding mitigation of project-related adverse effects to project-wide cultural resources.
- We are in the information gathering stage for our mitigation activities and will have a better understanding of potential mitigation later in Q3.
8
Questions ??
Powering our way of life.
June 9, 2020
Strategic Plan Metrics2020 Q1
Objective 1 – Safety PerformanceZero Recordable Incident Rate
2020 Target 2020 Q10 3.0
• 4 Recordables Total 2020 to date • 1 Lost Time • 2 Restricted Duty• 1 Recordable Injury
Changing the Culture• 95% Safety Meeting attendance Jan
and Feb• 87% attendance in March• Moved safety meetings to online
format
3.83.5
2.6
2.93.4
3.12.9 3.0 3.0
0.00
0.50
1.00
1.50
2.00
2.50
3.00
3.50
4.00
Q12018
Q22018
Q32018
Q42018
Q12019
Q22019
Q32019
Q42019
Q12020
Recordable Injury Rate12-Month Rolling
Objective 2 – Design and Sustain an Engaging and Fulfilling Grant PUD Culture
Organizational Health Index2020 Target Current Status
≥ 75 42
Employee Engagement Assessment
2020 Target Current StatusTo Be Determined Launch this Fall
• Scored in 2019• Scored every two years, next cycle in 2021• Target is top quartile based on McKinsey’s Organizational Health Index
• Slated for launch in fall timeframe• Will use the Gallup Q12 Employee Engagement Instrument
Objective 2 – Design and Sustain an Engaging and Fulfilling Grant PUD CultureEducational Reimbursement
Target2020 Target Current Status
To Be Determined To Be Determined
Training Effectiveness Assessment
2020 Target Current StatusTo Be Determined To Be Determined
• In development phase, undergoing Executive Team review• Requires Commission action on revised educational reimbursement program
• Anticipated target of 4/5 on an internally developed rating scale• Rating will identify the employees’ perception of a training’s overall effectiveness
Objective 3 – Maintain a Strong Financial PositionElectric System Liquidity
2020 Target 2020 Year End Projection≥ $105 MM $163 MM
• Liquidity reduced after financial optimization
• Year-end projection represents value of 456 days cash on hand
159
215 226258
193 189 209 205
163
0
50
100
150
200
250
300
Q12018
Q22018
Q32018
Q42018
Q12019
Q22019
Q32019
Q42019
Q12020
Electric System Liquidity
Objective 3 – Maintain a Strong Financial PositionConsolidated Return
on Net Assets2020 Target 2020 Year End Projection
≥ 4.0% 3.0%
• This year, target increases to ≥ 4.0% from ≥ 3.8%
• Net plant anticipated to grow by > $51M this year
• Interest and Other Income down• Anticipate some Labor expense
moving from Capital to O&M2.42.9 2.9
4.3
3.3 3.5 3.7 4.0
3.0
0.00.51.01.52.02.53.03.54.04.55.0
Q12018
Q22018
Q32018
Q42018
Q12019
Q22019
Q32019
Q42019
Q12020
Consolidated Return on Net Assets (%)
Objective 3 – Maintain a Strong Financial PositionConsolidated
Debt to Plant Ratio2020 Target 2020 Year End Projection
≤ 60% 52%
• Target declined from ≤ 62%to ≤ 60%• Ratio declined after financial
optimization in January and additional debt refunding in March
• Based on book value; Ratio based on estimated fair market value is 39%
6161 62 62
60 59 5958
52
45
50
55
60
65
70
Q12018
Q22018
Q32018
Q42018
Q12019
Q22019
Q32019
Q42019
Q12020
Consolidated Debt to Plant Ratio (%)
Objective 3 – Maintain a Strong Financial PositionAdjusted ConsolidatedDebt Service Coverage
2020 Target 2020 Year End Projection≥ 1.8 x 2.2 x
• Annual adjusted debt service requirement has fallen ~ $8M from 2019
• Anticipate slightly lower net income and interest/other income
1.8 1.82.0
2.12.0 1.9 2.1 2.2 2.2
0.0
0.5
1.0
1.5
2.0
2.5
Q12018
Q22018
Q32018
Q42018
Q12019
Q22019
Q32019
Q42019
Q12020
Consolidated Debt Service Coverage
Objective 4 – Provide Long Term Low RatesRetail Operating Ratio -
Adjusted2020 Target 2020 Year End Projection
≤ 112% 108%
• Target fell to ≤ 112% from ≤ 113%• Calculated as total retail expenditures
divided by total retail revenue• Retail revenues and expenditures both
down, ratio stable109
111 111 109106 107 109 109 108
90
95
100
105
110
115
120
Q12018
Q22018
Q32018
Q42018
Q12019
Q22019
Q32019
Q42019
Q12020
Retail Operating Ratio %
Objective 4 – Provide Long Term Low Rates
Peer Group of Excellence Retail Rate Index
2020 Target Current StatusTo Be Determined To Be Determined
• In development phase
Objective 4 – Provide Long Term Low RatesDistrict Credit Rating
2020 Target 2020 Year End Projection≥ Aa3 Aa3
System Moody’s S&P FitchElectric Aa3 AA+ AA
Outlook Stable Stable Stable
Effective Date 11/21/17 06/27/19 11/06/17
PRP Aa3 AA AAOutlook Stable Stable Stable
Effective Date 09/16/15 06/28/19 11/06/17
Items to our Favor: Ownership of competitive hydro generation, low rates, water and power price risks reduced by exchange contract, and favorable debt service coverage
Objective 5 – Outstanding Service to CustomersAverage System
Availability Index (ASAI)2020 Target 2020 through Q1≥ 99.985% 99.980%
• Delta from target is -0.005%• Month by month values
• Jan 99.957%• Feb 99.999%• Mar 99.983%
• 2018 Target was 99.97%
-0.025-0.020-0.015-0.010-0.0050.0000.0050.0100.0150.0200.0250.030
Q12018
Q22018
Q32018
Q42018
Q12019
Q22019
Q32019
Q42019
Q12020
ASAI Compared to Target (%)
Objective 5 – Outstanding Service to CustomersCustomer Average
Interruption Index (CAIDI)2020 Target 2020 through Q1< 110 min 131 min
• Delta from target is 21 minutes• Month by month values
• Jan 149 min• Feb 150 min• Mar 101 min
• 2018 Target was 150 minutes• Top 3 known outage causes by
duration • Equipment damage 822k min• Equipment worn out 165k min• Vehicle accidents 55k min
-60-40-20
020406080
100120
Q12018
Q22018
Q32018
Q42018
Q12019
Q22019
Q32019
Q42019
Q12020
CAIDI Compared to Target (min)
Objective 5 – Outstanding Service to CustomersPRP Availability
2020 Target 2020 through Q1Meet 12 of 12 Monthly Targets 3 of 3
-1
0
1
2
3
4
5
Jan Feb Mar
Project Availability Compared to Target (%)
-1012345
Jan Feb Mar
Wanapum vs. Target (%)
-1012345
Jan Feb Mar
Priest Rapids vs. Target (%)
Objective 6 – Operate Responsibly2020 Target 2020 through Q1
Financial Statement Audit Performance Unmodified Audit Opinion 2019 Audit Unmodified Opinion
2020 Audit TBD April 2021
WA State Audit Office Compliance Audit No Audit Findings TBD Sep – Nov Timeframe
FERC / NERC / WECCCompliance Performance No Findings No Findings
FERC and Regulatory Filings No Late Filings No Late Filings
Environmental and Cultural No Issues No Issues
Objective 7 – Develop a Sustainable Broadband Network
Achieve Planned Capital Build2020 Target 2020 through Q1
100% 91%
Average System Take Rate2019 Target 2020 through Q1
≥ 60.0% 58.9%
• Expansion capital year to date spend is 23% of budget• Routine capital year to date spend is 21% of budget
Participation by CommunityCoulee City 36.8% Grand Coulee 61.2% Quincy 55.0%
Desert Aire 76.8% Mardon 51.5% Royal City 64.5%
Electric City 58.8% Mattawa 71.6% Soap Lake 55.6%
Ephrata 72.8% Moses Lake 57.5% George-Burke 44.2%
• Up from take rate of 57.5% at end of 2019
2020 Strategic Plan Metrics – Q1 StatusObjective Strategic Plan Metrics 2020 Target 2020 through Q1
Objective 1 - Safety Performance Zero Recordables Incident Rate 0 3.0
Objective 2 – Design and Sustain an Engaging and Fulfilling Grant PUD Culture
Organizational Health Index ≥ 75 42
Employee Engagement Assessment TBD TBD
Educational Reimbursement Target TBD TBD
Training Effectiveness Assessment TBD TBD
Objective 3 – Maintain a Strong Financial Position
Electric System Liquidity ≥ $105 MM $163 MM
Consolidated Return on Net Assets ≥ 4.0% 3.0%
Consolidated Debt to Plant Ratio ≤ 60% 52%
Adjusted Debt Service Coverage ≥ 1.8 x 2.2 x
Objective 4 – Provide Long Term Low Rates
Retail Operating Ratio ≤ 112% 108%
Peer Group Retail Rate Index Coming Q2 2020 Coming Q2 2020
District Credit Rating ≥ Aa3 Aa3
Objective 5 – Outstanding Service to Customers
Average System Availability Index ≥ 99.985% 99.980%
Customer Average Interruption Index < 110 min 131 min
PRP Availability 12 of 12 Monthly Targets 3 of 3 Monthly Targets
Objective 6 – Operate Responsibly Operate Responsibly No Findings / No Late Filings
No Findings / No Late Filings
Objective 7 – Develop a Sustainable Broadband Network
Achieve Planned Capital Build 100% 22%
Average System Take Rate ≥ 60.0% 58.9%
Questions
Commission Presentation June 09, 2020
Andrew Munro, Sr. Mgr., Ext. Affairs & Communications
Chuck Allen, Supervisor, Public Affairs
Community Engagement Activity Report
Agenda• External Affairs & Communications – Structure & Personnel
• Introduction - Annette Lovitt, Public Affairs Officer - Community Relations
• WiFi Hotspots in Grant County
• Employee Association
• Artificial Intelligence (AI) for Earth Grant
• Pay it Forward
• Online Elementary Education & Library Programs
• Social Media Awareness Videos
• Facebook Metrics
• Fiber Marketing & Ag Outreach
• COVID-19 Info
Team
External Affairs and Communications
Andrew Munro Senior Manager
Cindy McClure Administrative
Assistant
Cliff Sears Senior Policy
Analyst
Government/ Regulatory Affairs
Jessie Allemand Policy
Administrator
Policy Management
Records Management
Beverly Peterson Records
Officer
Michelle Clark Records
Officer
Public Affairs
Chuck Allen Supervisor
Ryan Holterhoff Public Affairs
Officer
Christine Pratt Public Affairs
Officer
Lindsay Thompson Communications
Specialist
Structure & Personnel
Annette LovittPublic Affairs
Officer
Community OutreachIn times of COVID-19
WiFi Hotspots in Grant County
• ACH School District Brick House• Wilson Creek City Park• East Beach Park• Ephrata Recycling Center• Quincy Middle School• George Community Hall• Warden Community Center• Quincy Columbia Basin Irrigation District• Port of Mattawa Office
Employee AssociationHelping to coordinate Food Bank Dollar Drive through Grant PUD Employee Association to support local food banks.
Food Bank Dollar DriveDue to social distancing we are asking for money,
which will be distributed throughout our county.Each dollar we give can buy up to $3 in food
with the buying power of the food banks!
Three ways to give:
Call GRANCO and transfer money tothe PUD Employee Association account
______
Venmo @Grant-Empassoc______
Send a check toGrant PUD EAPO Box 1251
Ephrata, WA 98823
Artificial Intelligence (AI) for Earth GrantReceived a $15,000 credit from Microsoft Azure to develop an educational project based on Artificial Intelligence to help fish counters.
Pay it Forward money to food banks
Through Columbia Basin Foundation, $9,000 of Pay it Forward funds were allocated to county food banks.• Donations were earmarked for
funds to help families with school-aged children.
Educational outreachModifications to continue mission
Online Elementary Education & Library ProgramsModifying our online programs to teach electrical safety benefits of hydropower with our education partners.
Awareness videos
https://www.youtube.com/watch?v=yAgI2RdWPYA https://www.youtube.com/watch?v=c6nkNm-WAA8
Facebook Metrics
Facebook ComparisonGrant PUD is consistently at the top when it comes to “engagement” on Facebook
out of larger, regional utilities.
Marketing MessagesEmphasizing our mission
Fiber MarketingIn April 2020, we set a record of 486 new fiber subscribers and a take rate of 60 percent.
Ag Outreach
COVID-19 Info