gross catholic high school weight room renovation bellevue, nebraska · 2016-09-16 · daniel j....
TRANSCRIPT
Daniel J. Gross Catholic High School Engineering Team 2011-2012
Gross Catholic High School Weight Room Renovation Bellevue, Nebraska
Gross Catholic High School takes tremendous pride in their successful athletic program. A
major contribution to the athlete’s performance on the field, court, or diamond is the weight
training program. The athletic program has grown to the point where the current weight room is
insufficient, too small, and needs to be relocated and updated. The Gross Catholic engineering
team has taken on the task of redesigning a new weight room. This new weight room would
improve safety measures, provide more space, and have the proper ventilation that would overall
be very beneficial for the school and the performance of their athletes.
Team Members Grade
Team Members Grade
Conner Burke 12 Amy Lohaus 12
Elizabeth Edmundson 10 Jordan Melton 11
Michael Friend 12 Abigail Peters 12
Ian Ginnaty 12 Anton Rice 12
Anne Grzywa 12 Connor Sauley 10
Nicole Ketchmark 10
Teacher Steve Hamersky
Mentors Andrew Shelby, Carlson West Povondra Architects
Patrick Rainbolt, Kiewit Building Group
Society of American Military Engineers Student Initiative Mentoring Program
Presentation Date March 29, 2012
Table of Contents
Project Problem Statement ............................................................ 1 Problem Introduction ........................................................... 1 Scope of Project .................................................................. 1 Summary ............................................................................. 2 Recommendations ......................................................................... 3 Architectural Program .......................................................... 3 Site Visits ............................................................................. 4 Location Options ................................................................. 5 Design Details ..................................................................... 6 Floor Plan ............................................................................ 6 Accessibility ......................................................................... 7 Interior Materials and Equipment ......................................... 8 Exterior Materials ................................................................ 9 Structural ............................................................................. 9 Mechanical ........................................................................ 10 Electrical ............................................................................ 11 Cost Estimate .................................................................... 11 Action Plan .................................................................................... 11 Presentations .................................................................... 11 Project Schedule ............................................................... 12 Funding ............................................................................. 12 Project Summary ............................................................... 12 Journey ......................................................................................... 13 Lessons Learned ............................................................... 13 Team Work ......................................................................... 14 Supporting Research ......................................................... 15 Location Analysis .............................................................. 15 Sunshades and LEED Ratings .......................................... 17 Site Visit to the TD AmeriTrade Building .......................... 17 Acknowledgements ....................................................................... 19 References .................................................................................... 20
Daniel J. Gross Catholic High School, Page 1
1 – Project Problem Justification
1.1 – Problem Statement – Introduction
Daniel J. Gross Catholic High School is located in Bellevue, NE on 43rd Street just south of
Harrison Street. Gross Catholic was founded by the Archdiocese of Omaha with the Society of
Mary (the Marianists) and the Franciscan Sisters of Our Lady of Perpetual Help. The Society of
Mary is an international religious order of brothers and priests. More than six hundred Marianists
serve in the Province of the United States and sponsor three universities, eighteen high schools,
twelve parishes, and five retreat centers. Today, Gross Catholic continues to be a Marianist-
sponsored school. The mission of
Marianist education is continued by a very
dedicated group of Christian lay women
and men and Diocesan clergy.
There are a total of seventeen athletic
programs at Gross Catholic. Cougar teams
finish consistently in the Nebraska state
top ten team rankings with multiple district
and conference titles, and state
championships. The weight room is open
from 6:45 AM to 4:30 PM and it is open to
students, faculty/staff, and alumni. Approximately one hundred and fifty people use the weight
room each day. Our professional strength and conditioning coach, Mrs. Cheryl Sacco, has a big
impact on the success of our athletes. For school location, see figures 1 and 2 in the appendix.
1.2 – Problem Statement – Scope
With the success of our athletes, one would think that our athletes train in an above-average
weight room. In reality, their training is hindered. Our engineering team felt it would be
beneficial to understand student opinions as to what should be updated and what they do not like
about the weight room. We decided to survey of students and teachers that use the weight room.
We surveyed Mrs. Sacco’s 5th period class. We asked them three questions that we felt would
best help determine the current issues with the weight room.
Question 1: What do you like about the current weight room?
We discovered for question number one that the most liked attribute of the weight room is the
equipment. The problem with the equipment, however, is that there is not enough equipment to
support an entire class being in the weight room. A student who took our survey stated that they
do not like to wait in line to use the squat racks because they have a hard time finishing their
workout by the time the class period is over. We found this information to help ensure us that we
design the weight room to have more space for more equipment than the current one.
Daniel J. Gross Catholic High School, Page 2
Question 2: What don’t you like about the current weight room?
These results were not too surprising. Through personal experience and talking with fellow
classmates we were already aware that the
current weight room is too small with a
inadequate ventilation system. The architects
who originally designed the school had
designed the space that the weight room is
located in now to be a storage room (see
figure 3); which explains the lack of natural
light and a poor ventilation system. Other
problems included not enough equipment and
low ceilings. The inadequate space and low
ceilings also create problems with safety.
Taller athletes can hit the lights or air ducts
with weights as they lift.
Question 3: What would you like to add to the current weight room?
Most of the items that the students listed as
additions are pretty standard for a weight
room such as mirrors or a sound system. The
main additions that the students want to see
put into the new weight room is a sound
system and new and more equipment.
Currently, the only source of music is through
a boom box with two speakers on either side.
It is loud enough because of the room’s size
and the echo, but with our new design we are
going to need a better source than just a little
boom box. Other items listed included more ventilation and more equipment.
1.3 – Problem Statement – Summary
The weight room is a weak point at our school. Constructing a new weight room with the latest
technology in equipment, a larger area to work with, proper ventilation and natural light would
give students more motivation to better ourselves and show pride in our school. This project can
start new programs in the summer not just for Gross Catholic students but for alumni or even
parents who want to work out as well. During the school year if parents are waiting for their son
or daughter to get done with play practice, culinary club, etc., they can work out and finish at the
same time as their child. A new weight room would bring more opportunities to Gross Catholic.
Daniel J. Gross Catholic High School, Page 3
We as students are taught the Five Characteristics of a Marianist Education. In order to grow as a
school and a family we must always adapt and open our eyes to new ideas. The last teaching says
to educate for adaptation and change. The best way to incorporate this teaching is to make a big
change in our school. A change that will benefit everyone affiliated with our school. This project
is that big change we need.
2 - Recommendations
2.1 - Recommendations - Architectural Program
We interviewed Mrs. Cheryl Sacco, our current strength and conditioning coach, and received
many answers regarding the proposed weight room. We believe she was very intrigued with the
idea and we could sense her excitement. She had many ideas for us, for example she wants more
space, an area for cardiovascular workouts, and even an indoor three-lane track. Here are the
needs and issues:
1 Vertical space for TRX suspension training (www.trxtraining.com)
2 Floor space for agility work, stepper ladder space
3 Track that is inside, 20 yards long with 3 lanes, for spring training
4 Need space for speed work with the track and ladder
5 Ventilation to provide fresh air and remove moisture for health and safety
6 Windows for natural light and possibly natural ventilation
7 Office space for personal conversations and to store personal items
8 Access to outside and athletic fields for outdoor work, weather permitting
9 Rubber flooring since heavy weights are dropped during some exercises
10 Need more space for equipment such as squat racks, free weights, TRX tower, and
cardiovascular equipment such as bikes and rowing machines
11 There are renovation plans which used all available input, that included a virtual tour, and
satisfied all requirements, and used the central courtyard location
12 Consideration of other locations:
Bernadette Gym - not available
Wrestling/Art area - not available
West Garages area - not available
Central Courtyard (Senior deck) - available, windows from East commons (good, bad)
13 Could use as separate building with outside public access, which could allow community
gym memberships to be sold, but that requires more supervision
14 Training room could be included - could be a mini station in a little office
15 Storage areas are needed for equipment
16 10 treads, 10 bikes, 10 rowers
17 Need water fountains
Daniel J. Gross Catholic High School, Page 4
Mrs. Sacco seemed very set on the proposed location, in the center courtyard area where the
senior deck currently is, because she said all other location ideas had flaws. It was not clear to us
that very many other locations were considered. We decided that we would look at different
options for the location.
To help us start the design we decided to visit some other schools and look at their weight rooms.
We talked with our athletic director, Mr. Michael Dempsey and he talked with other athletic
directors at their monthly meeting. He gave us a list of schools that were willing to give us a tour
of their weight room. From the list we selected two schools: Elkhorn South High School and
Conestoga High School. We liked Elkhorn South because it is a new state of the art school and
we would be able to see all the bells and whistles that might be considered for a high school level
facility. We chose Conestoga High School because it about the same size school as ours. The
number of students using the weight room at Conestoga would match our requirements and the
budgeting and funding would be a close match as well.
Elkhorn South High School (11/1/11, Morning) Tom Ramsbottom - Athletic Director Elkhorn South can be classified as the perfect high school. The school has everything, being just
a mere two years in existence. The athletic area is complete with two gyms, six locker rooms
along with referees locker room, a 195 yard
long track, a wrestling room, a training room,
rehab room, an enormous storage area, offices,
and of course a weight room. The weight
room at Elkhorn South is very simple in
design, which is what most weight rooms are:
simple. The room is a very spacious rectangle
with plenty of room to walk around even as
athletes are using the equipment. There are
many windows on one side of the room that
let in natural light and look out towards a
parking lot and landscaping; on the other side
windows look out to the track and gym.
Lining the walls are large inspirational posters that seem to also light up the room. Of course the
room wouldn’t be complete without a sound system, which is what all athletes’ love to have
while working out.
Daniel J. Gross Catholic High School, Page 5
Conestoga High School (11/1/11, Afternoon) Kyle Steckler - Athletic Director Conestoga High School is a small school found in the middle of Nebraska. They recently built a
completely separate building for their weight room and wrestling room combined. Similar to our
current wrestling/art building, this is just a
metal building that they put up on their
property. Half of this structure had turf floor so
that sports teams could use it to warm up,and
do other activities when the weather was not
ideal. This was also used by the wrestling team
by just rolling mats over the turf. The other
half had an office and a loft area where
equipment was stored and the majority of the
half was their weight area. This type of weight
room was more realistic to our budget and
resources so we were very interested.
From this research, the team developed an architectural program to serve as a guide in the design
of the weight room. From the analysis of our needs we determined that the weight room should
be about 3700 square feet with an additional 2600 square feet for an indoor sprinting track. The
full architectural program is given as figure 4 in the appendix.
2.2 - Recommendations - Location Options
Once the approximate amount of space for the weight room was determined, the possible
locations could be selected. There were a number of locations that were considered for the
weight room project. The weight room
should be located close to the locker rooms
and the athletic fields. It would be nice to
have a view of the athletic fields and a way
to provide natural light. After completing an
analysis of five locations, a location to the
south of the lower gym was selected. The
complete analysis of locations is contained in
section 4.1 of this report.
Some of the issues that will need to be
addressed with this location include the
sloping hill, utilities in the area, and the
access roadway. The sloping hill was
Daniel J. Gross Catholic High School, Page 6
originally fill dirt to level and extend the lower gym area. There would need to be extensive soil
testing and there may need to be soil enhancements to accommodate the building. There may
also be roof drains and storm drains in the area as well as a sanitary sewer and fire hydrants to be
moved. There is also an access roadway that wraps around the south side of the building. This
roadway is used by people walking to the lower gyms or athletic fields, and by people driving to
the wrestling room or making other deliveries to the lower gym area. Walking and driving access
will need to be provided by the new design.
2.3 - Recommendations - Design Details
We really liked the southern exposure of our selected location which provides opportunities for
natural light and wonderful views of our athletic fields. The location is close to existing athletic
spaces within the school
building such as the locker
rooms and training room. Some
of the design details that we
considered include the floor
plan, building codes, interior
materials and equipment, and
exterior materials. We will also
consider structural, mechanical,
and electrical issues.
Floor Plan
The design for the projected weight room includes two levels complete with access to the locker
rooms, bathrooms, storage area, an office, entrance area, and a 20 meter track straightaway.
There is roughly 5800 square feet of floor space in
the weight room itself, allowing plenty of room for
free weights, treadmills, cardio equipment, TRX, and
anything else that would be done in a weight room.
This large open space would make it easy to move
around weights and equipment with ease and also
allow plenty of room for the equipment to be used
and for those not using the equipment to walk around
safely.
We essentially chose this design from various
alternate locations because of its access to the
athletic fields, and because their was adequate open
space that would not limit the size of the weight
Daniel J. Gross Catholic High School, Page 7
room. The design is easily accessible from the athletic fields and the west parking lot. We made
sure there would also be access to the existing locker rooms from the proposed weight room;
there will be a hallway connecting the two buildings. The hallway would be located close to the
entrance of the existing lower gym and
a hallway away from the training room
which is located between the men and
women’s locker rooms.
One of the main reasons the idea for a
new weight room was brought up was
of the current stuffiness and less
spaciousness of the much smaller
weight room. The current weight room was in fact a storage area before its use as a weight
training facility. The problem with the stuffiness is from the lack of natural light in the current
weight room; there are no windows letting natural light in because of its location in the basement
of the school. The new proposal is complete with large open windows that would allow an
excessive amount of natural
light into the large open area.
These windows would also
have electronic shades that
could be moved up and down
depending on the time of day.
This natural lighting would
conserve energy considerably
because during the day lights
would not need to be turned on when the weight room is in use. The building would have both
upper and lower entrances/exits.
Building Codes - Accessibility
Building codes insure that buildings meet a minimum standard regarding safety. We chose to
focus on two important codes: fire safety and accessibility. Both of these codes are relatively
easy to achieve with this building. Fire safety will involve adding or extending the fire sprinkler
system that is used throughout the rest of the school, and planning for enough exits. There will
be two exits out of each level on both levels of the weight room. The upper level will exit to the
front for parking lot access and the rear for access to the upper athletic fields and outdoor
exercise areas. The lower level will have one door to the outside that will provide access to the
lower athletic fields and the track. The restrooms in the new building would need to be
accessible with a 5 foot turning radius within the restroom that has access to all restroom
facilities. Adjacent to an exterior door on the south side of the weight room will also provide
access to the lower level of the weight room.
Daniel J. Gross Catholic High School, Page 8
Interior Materials and Equipment
At Gross Catholic, we find sustainability to be one of our most important components to
compliment our projects. When designing the inside of the weight room, we wanted to find
sports flooring that would be the most beneficial to our athletes. The product Sport Impact
Flooring from Mondo is a perfect example of excellent flooring. With this product comes a
Greenguard Certification, which verifies the product is made for sustainable projects being 100%
recyclable. Sport Impact also offers a variety of colors, textures, and designs we can put on our
floor. We have discussed the possible designs with our athletes and weight trainer and they are
definitely in favor of our ideas. This product also gives us a health aspect in that it is non-porous
and antibacterial which helps eliminate germs left behind after a tough workout. The pictures
below show how designs can be created using the Sport Impact Flooring.
For the ceiling we decided that subtle was best. Armstrong manufacturing makes drop down
“clouds” that are designed to help absorb sound. Also, these special ceiling pieces allow a room
to have exposed beams and pipes. We decided to
choose a light grey for our ceiling with the structure
and HVAC systems above painted black. The
“clouds” will be arranged in a grid pattern across
the entire ceiling, giving it a uniform feel.
Our Strength and Conditioning Coach, Mrs. Sacco,
shared with us a plan of all of the most important
and vital exercise machines she would like to see in
the weight room. The ideal weight room would
focus on muscle strength while maintaining cardio
stamina. Living in Nebraska does not allow us
much time to run/condition outside during the winter period. Mrs. Sacco’s goal is to have the
room open to a “sprinting/ladder” section while still using the space to have multiple squat racks,
exercise bikes, and elliptical machines. The back of the weight room will have mirrors lining the
Daniel J. Gross Catholic High School, Page 9
wall so we can have a yoga/Pilate's strengthening area. Dumbbell racks will be located in an
open multipurpose area. The pictures below show how the interior can be decorated with bold
lines and inspirational phases and logos.
Exterior Materials
For the lower portions of the walls we plan to use brick that matches the existing school. The top
half will be metal siding and windows. We decided to go with so many windows because it adds
a sense of sustainability to our project, being that they provide us with the natural light from the
sun. With this amount of windows, we needed to make sure that we retained a healthy and safe
temperature inside the room throughout the day. Insolroll is a window manufacturing company
that offers different window shades. We have chosen the Oasis 2700 Exterior Solar window
shade that will provide about 5% of the natural sun rays and heat into the building while
bouncing the other 95% off of the shades. A plus to these solar shades is that they enhance the
view of the outside athletic fields by blocking the glare of the sun, allowing a glorious view of
the outside for the runners on the treadmills and elliptical machines that will face the windows.
The shades can be printed with images and/ or text giving our weight room a creative and
appealing look. These shades are also energy sufficient and can earn LEED points between 8 and
20 points. See section 4.3 of this report for details of the LEED points values.
Structural
In 2002, our school added a library media center as a new addition that was built right next to the
existing building. Mr. Hamersky, our teacher, told us how the structure of the addition would be
very similar to the structure of the new weight room. The new building for our weight room
addition would have to be free standing, just like our media center addition.
In our library media center we went through the structure of the building to see how buildings
and structures are built as additions onto an original building without disturbing the original
building. We walked around the halls as well and Mr. Hamersky explained the structure of our
building. He told us how the base and skeleton on the building was placed and why. We looked
Daniel J. Gross Catholic High School, Page 10
at where the metal beams went, and how big they would have to be. We realized that there would
need to be special planning and calculations made for the actual building structure, but the
building would likely be supported on individual spread footings that support columns. The
columns would be spanned by beams that would support the roof joists. Roof decking and
exterior walls would complete the building structure.
For our weight room we would use spread footings to support columns. The support columns
would be placed away from the existing building so that they do not disturb the existing footings.
The columns would support a roof system of horizontal or sloping beams to follow the roof
pitch. Some of the roof support beams would need to create an overhang to span the gap from the
column structure to existing building. The roofing material would be supported by steel trusses
and steel decking. The exterior walls would be supported by foundation wall footings and the
lower portion would be built using concrete masonry units (CMU) with a brick exterior to match
the school. This would help protect the lower portions of the new building. The upper portion of
the exterior walls could be built using steel studs covered with steel siding or stucco.
Mechanical
We researched some of the requirements of the building mechanical systems such as the Heating
Ventalation and Air Conditioning (HVAC) and plumbing systems. We talked with our mentors
about issues we should consider and found a very helpful section of Whole Building Design
Guide (WBDG, www.wbdg.org). Here are some of the suggestions they offered for
consideration:
● Exercise areas require a 20% increase in cooling capacity
● Provide air handling unit (AHU) for exercise areas
● Create negative air pressure relative to other areas of the building
● Have separate zones and return air for each exercise area and locker rooms
● Use ducted ceiling supply with ducted ceiling return air system with no transfer ducts
● Use sound baffles at all acoustically rated partitions
● Toilets and showers provide direct 100% exhaust operated
● Setback thermostat
● Building automation system (BAS) control of exhaust fans and thermostats
Many of these suggestions seemed to match things we had talked about with our strength coach
and among the team members. We see a need to increase the cooling capacity, particularly since
fall athletes work out in the summer months. We want to provide more than adequate air
handling, a problem in our current weight room. Since our weight room design is a separate
building, negative air pressure may not be needed. Exhaust fans would help with efficient
cooling when used in the early morning. Sound baffles would not be needed since the air
handling system will be self contained and will not conduct noise into other parts of the building.
Daniel J. Gross Catholic High School, Page 11
Electrical
The weight room addition would have a moderate impact on the school electrical system. The
lighting system and supporting the exercise machines would require the most planning. The
lighting system should include a lighting control or building control system to adjust the lighting
levels to balance the natural and artificial lighting. With the large amount of window area and
much of the building use being during daylight hours, a lighting control system would produce a
significant energy savings.
The electrical system would provide standard services such as electrical wall outlets at a standard
spacing along exterior walls for floor maintenance equipment. It is recommended that the
exercise equipment be carefully selected and placed in predetermined locations. An electrical
outlet should be located on the floor just under each piece of exercise equipment. This would
keep the cords from crossing the floor which otherwise would be a safety issue.
Special services should also be included such as the fire alarm, building intercom, and data,
video, and phone networks. The athletes also made it clear they expect a sound system.
Cost Estimate
The cost estimate was determined by considering the component parts of the building and
looking up the unit cost in the RS Means estimating guides. The team consulted with our
mentors who were very experienced with current costs for certain materials such as skylights and
for the overall cost expected per square foot for the entire building. The RS Means guides that
we used were older, and to correct that we assumed an increase in cost of about 3% per year
based on the year the estimating guide was published.
We estimate that the new weight room will cost about 1.15 million dollars which includes all
material, construction, equipment, and contingency costs. This does not include the design costs.
The building has at total of 6012 square feet which gives a building cost of about $192 per
square foot. The cost estimate details are given in the report appendix, figure 11.
3 - Action Plan 3.1 - Action Plan - Presentations
Once we have finalized our project we plan to present the idea to the decision making team in
hopes that it will be something that Gross Catholic will be able to develop and pursue. The group
we would bring to together and present to would include Ms. Cleveland (President), Mrs. Sacco
(Strength Coach), Mr. Dempsey (Athletic Director), Mrs. Poly (Director of Development), along
with the advisory board and sport coaches.
Daniel J. Gross Catholic High School, Page 12
3.2 - Action Plan - Project Schedule
Provide a 3 year plan for project completion
Year 1 - Schematic Design, Start Capital Campaign,
Year 2 - Quiet Campaign and Fund Raising
Year 3 - Develop Design Documents, Select Contractor
Year 4 - Complete Construction
3.3 - Action Plan - Funding
In order to launch a new project the president, Ms. Becky Cleveland, will present the idea to the
Advisory Board. If it is something they agree is worth pursuing the next step would be to
conduct a feasibility study in order to find out if the community will help support the project.
Sometimes the community will want their money spent elsewhere, but if they seem to be in favor
of the idea Gross will need to get permission from the Archdiocese of Omaha with a project this
large. If we are given permission then a three to five year campaign will be launch. It will take
from six months to a year in order to put the campaign together. Budgets, visual aids, and action
plans will need to be ready and set.
A “quiet phase” of the campaign will begin by approaching those who we feel will be larger
donors. After those contacts have been made then the campaign will be launched to the
community as a whole. Personal contact will be out primary form of fundraising, a phonathon
will be held, and mailings will be sent out. We will hold events with in order to show a visual to
prospective donors. This means that virtual aids will need to be made. Being a Catholic school it
will be difficult to get a federal grant, but we will apply for those we can and for those that
support health and physical wellness in young people. We can approach foundations that
advocate for the importance of health.
If these means of fundraising are not sufficient to support our project we can explore the options
of outside community use. Memberships could be purchased by parents and members of the
local community to use the facilities after school hours. This would provide another source of
funding, but would create liability issues that would complicate the process.
Project Summary
Daniel J. Gross Catholic High School needs a new weight room. Most students use the weight room and
many students spend long hours of intense training in the weight room. Our athletes need a healthy and
safe environment in which to prepare their bodies for the rigors of competition. This weight room project
will maximize the effectiveness of our athletic, strength, and training staff and is extremely important to
the continued success of our athletic programs.
Daniel J. Gross Catholic High School, Page 13
4 - Journey
4.1 - Journey - Lessons Learned
There have been many challenges we have encountered while working on this project. At first,
we didn’t know how complicated and how much work was needed to complete the entire
process. One of the most difficult parts of the process was deciding the location for the weight
room. We had many possibilities and there were pros and cons to each site. We had to analyze
each site and choose which location would be best. This analysis may prove to be the most
important result of our project for our school as it seemed only one location, the central
courtyard area, was considered in the current plan proposed by the school. We proved this site
was not the most practical for what we wanted to accomplish in a new weight room.
The team learned many things about architectural design and construction through this project. A
strong appreciation for the level of detail required to design and construct a building was
developed in the team as we went on the site visits, talked with our mentors, or did our own
design work. The more the team worked on the weight room project, the more work there
seemed to be. The team also developed an appreciation for the buildings that they see around
them every day, but never noticed before.
Projects also can involve many social aspects within an organization, like a school, as the team
discovered. There are many different ways that a new weight room could be designed, and
sometimes the simplest solutions are not considered due to the social history of the organization.
One interesting part of the project for the team was to discuss how ideas can be packaged to
overcome the social barriers and get the best solution. The team did not realize how much
building designers need to sell their ideas.
The team also came to realize how important communication can be in a technical project where
changes and adjustments are being made to a design, and all the groups need to be aware of the
changes. Professional designers and construction engineers must maintain strong communication
as the building concepts develop. On our tour of the TD AmeriTrade building the team learned
about the design and build process. With design and build the amount of communication
increases. Both mentors talked with the team about the importance of communication.
Scheduling the work on the project can also be a challenge. The team developed a Gantt chart
with the project schedule and checked our progress throughout the year. The team could only
imagine what would be involved in scheduling the design and construction of an actual project.
The Gantt chart is included in the appendix, figure 12.
Daniel J. Gross Catholic High School, Page 14
4.2 - Journey - Team Work
Team work is very important to the successful completion of this project. The team started in September meeting on Tuesday evenings. The group of students that met in the evening was the core group that chose the project, set the schedule, organized the site visits, and completed the report and presentation. We also have an engineering physics class that would meet during the school day. The engineering physics class did a number of other projects throughout the first semester, but they did help some on this project. Communication between the two groups, the day time group and the evening group, was accomplished using online services like Google Documents and Google Sites. The research was assigned and posted to the Google Sites engineering physics class web site. It allowed interactive creation of pages and sharing of files. The report was written using Google Documents so that each team member could contribute to their part of the report, even at the same time. The team organization chart is shown below:
Teacher
Mr. Steve Hamersky
Mentors
Andrew Shelby, CWP Architects Patrick Rainbolt, Kiewit Building Group
Team Leaders
Anne Grzywa Amy Lohaus
Abigail Peters
Problem Definition Surveys and Interviews
Location Analysis Conner Burke
Elizabeth Edmundson Nicole Ketchmark
Abigail Peters Connor Sauley
Architectural Program Architectural Design
Interior Design Michael Friend Jordan Melton Abigail Peters
Anton Rice
CAD Drafting Computer Modeling
Anton Rice Ian Ginnaty
Marketing Action Plan Cost Analysis Anne Grzywa Ian Ginnaty
Journey
Amy Lohaus
Daniel J. Gross Catholic High School, Page 15
4.3 Journey - Supporting Research Location Analysis
Taking into consideration all the desired attributes of the new weight room, the possible
locations are:
Central Location (Senior Deck): This option offers a central location easily accessible from the
locker rooms. The St. Bernadette Gym being just to the south would block the view of athletic
fields and much of the direct natural light. The athletic fields would be accessible by going
between the St. Bernadette Gym and the wrestling/art building Unless the weight room in this
location were lowered, it would block the windows located in the east commons. This would
reduce the amount of natural light in the existing school, which is pretty limited already. The
space available for building a weight here is limited since it is surrounded by other buildings on
all sides.
East Location (Wrestling/Art): This location allows access to the fields and ample space for
activities; however, the art room would need to be relocated. This location is not close to the
locker rooms. The big advantage of this location is cost. The building already exists and would
just need to be renovated. The building was just recently renovated for dual use by wrestling and
also as an art studio, so the school may be reluctant to renovate a new space for art.
South Location (St. Bernadette Gym): The location and space offered with this option is highly
preferred; however, St. Bernadette would need to find a new gym, making this option unlikely.
The space is located near the lower gym and locker rooms and would provide a large amount of
space for all weight room activities. It is also located with direct access to the track and athletic
fields.
West Location 1 (Garages): This location provides ample space and would allow for very
visually appealing aspects since the location is adjacent to the main school parking lot. Everyone
that parks in the parking lot would see the new weight room. It would be two stories tall,
doubling the space of the current location of the weight room. With the garages are already there,
less construction would be required. This is the closest location to the existing weight room and
it would be easily accessible from the locker rooms. The garages would be turned into the
training room which leaves a problem of where to keep the grounds equipment. We could build a
stand alone garage on the east side of the parking lot where there is plenty of space. Some other
issues include the water chiller tower that is located near this area and the existing garages would
need to be relocated. The design does not meet some of needs expressed by our strength coach
such as a track or offices, or drinking fountains. An important issue that must be addressed is the
fire safety exits as this design covers some existing exits from the building.
Daniel J. Gross Catholic High School, Page 16
West Location 2 (On End of Lower Gym): At this location the weight room would be visible to
the public and would provide natural light. It would have an excellent view of and access to the
athletic fields. The major negative issues with this location would be access from the locker
rooms and cost. This option would require an entirely new building with a way to connect to the
existing building. Also an access road that runs along the south side of the existing lower gym
would need to be relocated. People that attend athletic events park in the main parking lot and
need access to the St. Bernadette Gym and athletic fields.
Each of these locations was developed by different design groups using the architectural program
requirements. The resulting rough floor plans were evaluated using the criteria shown in the
table. A location evaluation table was created to decide on the recommended location.
Location Evaluation Table (Higher score = more desirable)
Central (Sr Deck)
East (Wrestling)
South (Bern. Gym)
West 1 (Garages)
West 2 (Lower Gym)
Sufficient area 3 5 5 3 5
Access to athletic fields 2 5 5 2 5
View of athletic fields 1 3 3 1 5
Natural light 2 3 3 5 5
Available 5 1 1 3 5
Low cost 2 5 5 2 1
Total 15 22 22 16 26
From the evaluation ratings, the location called West 2 was determined to be the most desirable.
It satisfied all design goals and is available for use.
Daniel J. Gross Catholic High School, Page 17
Verosol Sunshades and LEED ratings for New Construction v2.2
From: Verosol and LEED brochure available on the Verosol website
LEED Credit LEED Points
Sustainable Sites:
Credit 8: Light Pollution Reduction
1 point
Energy and Atmosphere:
Credit 1: Optimize energy performance
1 - 10 points
Indoor Environmental Quality:
Credit 6.1: Controllability of Systems - Lighting
Credit 6.2: Controllability of Systems - Thermal Comfort
Credit 7.1: Thermal Comfort - Design
Credit 8.1: Daylight & Views - Daylight 75% of Spaces
Credit 8.1: Daylight & Views - Daylight 90% of Spaces
1 point
1 point
1 point
1 point
1 point
Innovation & Design Process:
Credit 1.1 - 1.4: Innovation in Design
1 - 4 points
Total 8 - 20 points
Site Visit to TD AmeriTrade building
Our mentor, Mr. Patrick Rainbolt, suggested that we visit the site of the new TD AmeriTrade
building, which is his current project. Mr. Rainbolt is a construction engineer for the Kiewit
Building Group. He said that different parts of the building are at various stages of construction
and that we would be able to see the steel framework in some places and some of the exterior
materials and window treatments. We had a general idea what the steel framework looked like in
our library media center, but we felt it would be a good idea to see a steel framework before any
finishing was done. As it turned out, we were right, it really helped the us understand how a
standard steel column, steel beam, steel truss building system goes together. After seeing the TD
AmeriTrade building we felt we could better imagine how the steel framework for our new
weight room would be designed and built.
On November 5, 2011 our team met at the new TD Ameritrade construction site to take a tour of
the building. We arrived to the site at around 10:00 A.M Saturday morning. We met with our
mentor, Patrick Rainbolt, to receive some information about the project. He presented a
PowerPoint containing a lot of information. This information varied between when they started
the project to what materials they are using to construct the building. After the PowerPoint, the
Daniel J. Gross Catholic High School, Page 18
group headed to the site outside. Patrick led us on an hour and a half long tour of the entire
construction site.
The tour began at the cafeteria section. Our team liked the framework and structure behind their
cafeteria and we could see that our new weight room would have a similar column and beam
construction. It was interesting to see the raw structure before any roofing or other coverings
were added. Another part of the
building that stood out was the solar
panels and natural lighting. Our team
could really get a feel for how
efficient energy saving ideas could
be added to our design. Patrick then
led us to the top floor of the building
where they will be putting all the
mechanical equipment. We learned
that instead of sending the air up the
high rise, the mechanical engineers
decided to put the machines on the
top floor and have the air flow down
the high rise. This was interesting
information, however not helpful with ideas for our weight room. We will not soon forget the
experience however since we were at the top of the building, there were no walls, just wire safety
railing, and we were there on a day when Omaha had 50 mph winds. We were really getting
blown around as we looked down the 350 foot elevator shaft! It was really fun and scary.
We then proceeded down to the fifth floor. On that floor, we got a closer look at the main
building from above. We noticed that the main building’s roof is going to be made into a green
roof. One member of our team brought this idea into his center location design with the weight
room underground and doing a green roof area above. We finished the tour with many ideas and
excited to start designing.
Daniel J. Gross Catholic High School, Page 19
Acknowledgements
The Gross Catholic engineering team would like to thank the following groups and individuals
for helping the team with this project.
Society of American Military Engineers (SAME) - Program Sponsor
All volunteers and judges
Thank you for helping with this valuable program
Mentors
Andrew Shelby, Carlson West Povondra Architects
Patrick Rainbolt, Kiewit Building Group
Gross Catholic High School
Steve Hamersky - Teacher and team sponsor
Michael Dempsey - Athletic Director
Cheryl Sacco - Strength and Conditioning Coach
Lynn Poly - Development Director
Tom Ramsbottom - Elkhorn South High School, Athletic Director
Kyle Steckler - Conestoga High School, Athletic Director
Daniel J. Gross Catholic High School, Page 20
References - Websites
TRX Training
http://www.trxtraining.com/
Insolroll Window Shading Systems
http://insolroll.com
Whole Building Design Guide
http://www.wbdg.org
WBDG - Sun Shades http://www.wbdg.org/resources/suncontrol.php WBDG - Fitness Center Design http://www.wbdg.org/design/physical_fit.php http://www.wbdg.org/design/fitness_centers.php WBDG - Fitness Center Construction Criteria http://www.wbdg.org/pdfs/gsa_constr_criteria_physical.pdf References - Books
The American Institute of Architects
Architectual Graphic Standards, 1988
International Code Council
International Building Code, 2000
Francis D. K. Ching
Building Construction Illustrated, 1991
Deborah S. Kearney, PhD
The New ADA: Compliance and Costs, 1992
RS MEANS
Building Construction Cost Data, 2001
Square Foot Costs, 2003
Appendix - Table of Contents
Appendix - Table of Contents
Figure Description
1 Map of the Location
2 Aerial Photograph of the Location
3 Existing Weight Room
4 Architectural Program
5 Location Analysis
6 Southwest View of Addition
7 Proposed Weight Room Floor Plan
8 Building Cross Section
9 West Elevation
10 South Elevation
11 Cost Analysis
12 Gantt Chart
Existing Weight Room
Reference: Original School Design
Boyer & Biskup
January 16, 1967
Appendix
Figure 3
Existing Weight Room
Existing Weight Room
Approximately 64' 2" x 36' 6"
2,342 square feet
Appendix - Figure 3
N
Appendix - Figure 4
Figure 4
Architectural Program
Length Width Buffer Area Quantity
Total
Area
Equipment (ft) (ft) (ft) (sq ft)
(sq ft)
Treadmill 6.67 2.04 1.50 49 10 487
Bike 3.46 1.67 1.50 30 10 302
Double Squat Rack 14.33 6.00 1.50 156 10 1560
Leg Press 8.00 6.08 1.50 100 1 100
Lat Pulldown 3.00 4.50 1.50 45 1 45
Rowing 6.30 2.50 1.50 51 10 512
Circulation 70.00 6.00 0.00 420 1 420
Office 10.00 12.00 0.00 120 2 240
Restroom 8.00 8.00 1.00 100 3 300
Subtotal
3665
Track 4.00 120.00 1.50 861 3 2583
Total
6248
Reference:
Gross Catholic Engineering Team, 2012
Appendix - Figure 5
Figure 5
Location Analysis
Reference: http://maps.google.com
Location Analysis Legend
A Central - Senior Deck
B East - Wrestling and Art Building
C South - St. Bernadette Gym
D West - Maintenance Garages
E South - Lower Gym
A
B C
D
E
Main Gym and Locker Rooms
Academic Wing
Athletic Fields
Lower Gym
Southwest View of
Reference:
Gross Catholic Engineering Team, 2012
Appendix
Figure 6
Southwest View of Weight Room Addition
Gross Catholic Engineering Team, 2012
Appendix - Figure 6
Addition
North
Proposed Weight Room Floor Plan
Reference:
Gross Catholic Engineering Team, 2012
Appendix
Figure 7
Proposed Weight Room Floor Plan
Gross Catholic Engineering Team, 2012 N
Appendix - Figure 7
Appendix - Figure 8
Figure 8
Building Cross Section
Reference:
Gross Catholic Engineering Team, 2012
Appendix - Figure 11
Figure 11
Cost Analysis Substructure Unit Unit Cost # of Units Total
Standard Foundation Poured concrete L.F. $4.45 431 $1,917.86
Slab on Grade 6” reinforced concrete S.F. $9.54 4159 $39,698.54
Basement Excavation Site preparation C.Y. $5.12 420 $2,149.91
Basement Walls 8” foundation wall L.F. $246.58 199 $48,987.95
Shell
Roof Construction Steel deck on steel trusses S.F. $21.32 4807 $102,502.29
Exterior Walls Metal studs with sheathing S.F. $19.39 7148 $138,614.99
Exterior Windows Glass curtain wall S.F. $42.01 781 $32,798.55
Skylights Each $300.00 196 $58,800.00
Exterior Doors Aluminum and glass Each $3,554.93 4 $14,219.72
Interiors Partitions Gypsum board on metal S.F. $12.80 $0.00
Interior Doors Single leaf hollow metal Each $1,208.81 6 $7,252.86
Fittings Toilet partitions, hardware S.F. $3.46 716 $2,478.60
Stair Construction 20 risers with landing Each $13,127.10 1 $13,127.10
Wall Finishes Paint S.F. $10.19 5814 $59,233.05
Floor Finishes Rubber flooring S.F. $9.97 3918 $39,051.67
Tile flooring S.F. $3.65 2039 $7,451.17
Ceiling Finishes Mineral fiber tile S.F. $8.36 5900 $49,340.62
Services Plumbing Fixtures Toilet and service fixtures Each $4,021.92 6 $24,131.52
Water Distribution Includes water heater S.F. $7.58 6012 $45,576.24
HVAC Extend existing system S.F. $24.24 6012 $145,750.36
Fire Sprinklers Wet pipe sprinkler system S.F. $4.15 6012 $24,947.40
Electrical Distribution 900 Ampere service S.F. $7.82 6012 $47,016.24
Lighting and Wiring Fixtures, receptacles S.F. $7.87 6012 $47,304.10
Communications Alarm systems S.F. $1.69 6012 $10,170.86
Furnishings Gym Equipment Ellipticals, bikes, rowing Each $1,276.80 30 $38,304.00
Weight Equipment Dual squat racks Each $7,980.00 6 $47,880.00
Contingency (10%) $104,870.56
Total Cost $1,153,576.16
Cost per S.F. $191.88
Reference:
Gross Catholic Engineering Team, 2012