grosvenor coal mine underground operations
TRANSCRIPT
GROSVENOR COAL MINE Underground Operations
PLN – Grosvenor Mine Overview Plan
GRO-1435-PLN-Grosvenor Mine
Overview Plan
Original Issue Date:
13/12/2013
Version: 2 Printed: 16/06/2020
Page 1 of 48 Date of Issue: 11/11/2015
PRINTED COPIES OF THIS DOCUMENT ARE UNCONTROLLED AND DEEMED VALID ONLY ON THE DAY OF PRINTING
Underground operations
grosvenor mine overview plan
AGM.002.001.0818
GROSVENOR COAL MINE Underground Operations
PLN – Grosvenor Mine Overview Plan
GRO-1435-PLN-Grosvenor Mine
Overview Plan
Original Issue Date:
13/12/2013
Version: 1 Printed: 16/06/2020
Page 2 of 48 Date of Issue: 13/12/2013
PRINTED COPIES OF THIS DOCUMENT ARE UNCONTROLLED AND DEEMED VALID ONLY ON THE DAY OF PRINTING
Table of Contents
1. Introduction ............................................................................................................................................. 4
2. Mine Characteristics ............................................................................................................................... 6
2.1 Location ........................................................................................................................................ 6
2.2 Seam Characteristics .................................................................................................................... 7
2.3 Coal Quality .................................................................................................................................. 7
2.4 Mine Reserves .............................................................................................................................. 7
2.5 Subsidence Constraints ................................................................................................................ 8 2.5.1 Blair Athol Rail Line / Eungella Eastern Water Pipe Line ................................................... 8 2.5.2 Goonyella Railway .............................................................................................................. 8 2.5.3 Lease Boundary .................................................................................................................. 8 2.5.4 Moranbah Township............................................................................................................ 8 2.5.5 Isaac River .......................................................................................................................... 8
2.6 Geology and Geotechnical ........................................................................................................... 9 2.6.1 Permian Coal Measures ..................................................................................................... 9 2.6.2 Moranbah Coal Measures Stratigraphy .............................................................................. 9 2.6.3 Seam Splitting ................................................................................................................... 10 2.6.4 Depth of Cover .................................................................................................................. 10 2.6.5 Stress Orientation ............................................................................................................. 10 2.6.6 Geotechnical considerations ............................................................................................. 11 2.6.7 Gas Content ...................................................................................................................... 12 2.6.8 Gas Reservoir at the Time of Mining ................................................................................ 13 2.6.9 Outburst Risk .................................................................................................................... 14
2.7 Spontaneous Combustion .......................................................................................................... 15
3. Mine Operations ................................................................................................................................... 15
3.1 Mine Design and Layout ............................................................................................................. 15
3.2 Pillar design ................................................................................................................................ 16 3.2.1 Main headings ................................................................................................................... 16 3.2.2 Chain pillars ...................................................................................................................... 16
3.3 Surface Infrastructure ................................................................................................................. 17 3.3.1 Administration buildings .................................................................................................... 17 3.3.2 Change house ................................................................................................................... 17 3.3.3 Diesel Storage ................................................................................................................... 17 3.3.4 Workshop/warehouse building .......................................................................................... 17 3.3.5 Coal transportation ............................................................................................................ 18
3.4 Production Capacity .................................................................................................................... 18 3.4.1 Longwall Productivity ........................................................................................................ 18 3.4.2 Development Productivity ................................................................................................. 18
3.5 Mining Methodology and Equipment .......................................................................................... 19 3.5.1 Mine Development ............................................................................................................ 19 3.5.2 Longwall Mining ................................................................................................................ 19 3.5.3 Conveyors ......................................................................................................................... 21 3.5.4 Transport Arrangements ................................................................................................... 21
3.6 Ventilation System ...................................................................................................................... 22 3.6.1 Ventilation requirements ................................................................................................... 22 3.6.2 Airways .............................................................................................................................. 22 3.6.3 Surface Fans ..................................................................................................................... 22 3.6.4 Ventilation and gas monitoring .......................................................................................... 22 3.6.5 Heat management............................................................................................................. 23
AGM.002.001.0819
GROSVENOR COAL MINE Underground Operations
PLN – Grosvenor Mine Overview Plan
GRO-1435-PLN-Grosvenor Mine
Overview Plan
Original Issue Date:
13/12/2013
Version: 1 Printed: 16/06/2020
Page 3 of 48 Date of Issue: 13/12/2013
PRINTED COPIES OF THIS DOCUMENT ARE UNCONTROLLED AND DEEMED VALID ONLY ON THE DAY OF PRINTING
4. Integrated Operational Risk Management ............................................................................................ 23
4.1 Group Technical Standard 02 Integrated Risk Management Standard...................................... 23
4.2 Operational Risk Assessment Methodology ............................................................................... 24
4.3 Four Layered Approach .............................................................................................................. 26
4.4 Baseline Operational Risk Analysis of Grosvenor Operations ................................................... 28 4.4.1 Operational Risk Analysis Process ................................................................................... 28 4.4.2 Site Operational Processes Baseline................................................................................ 29 4.4.3 Hazard Inventory: Baseline Hazard Map ......................................................................... 30 4.4.4 Principle Hazards .............................................................................................................. 31
4.5 System Integrity .......................................................................................................................... 33
5. Operational Structures .......................................................................................................................... 39
5.1 Management Structure ............................................................................................................... 39
6.2 SHMS Document Structure ............................................................................................................ 39
6. Roles and Responsibilities ................................................................................................................... 41
7. Resources Required ............................................................................................................................. 42
8. Trigger Action Response Plans ............................................................................................................ 42
9. Communication ..................................................................................................................................... 42
10. Training ................................................................................................................................................. 42
11. Corrective Action .................................................................................................................................. 43
12. Audit and Management Review ............................................................................................................ 43
13. Records ................................................................................................................................................ 44
14. Legislation ............................................................................................................................................. 44
15. Appendix I Control Effectiveness Matrix ............................................................................................. 45
16. Appendix II Business Unit Risk Matrix ................................................................................................ 46
AGM.002.001.0820
GROSVENOR COAL MINE Underground Operations
PLN – Grosvenor Mine Overview Plan
GRO-1435-PLN-Grosvenor Mine
Overview Plan
Original Issue Date:
13/12/2013
Version: 1 Printed: 16/06/2020
Page 4 of 48 Date of Issue: 13/12/2013
PRINTED COPIES OF THIS DOCUMENT ARE UNCONTROLLED AND DEEMED VALID ONLY ON THE DAY OF PRINTING
1. Introduction
A safe and productive underground mine begins with a detailed understanding of the processes involved
in the operation of the mine and the effective control of the hazards and risks present within those
processes.
Grosvenor Mine has developed a Safety and Health Management System [SHMS] based on an integrated
risk management process aimed at documenting the processes, hazards, risks and controls across the
activities at the mine.
1.1 Purpose
The Grosvenor Mine Overview Plan [GMOP] provides context and background data of the mine
characteristics and proposed mining operations together with the risk management processes used to
identify and control the hazards at the mine.
1.2 Scope
The GMOP applies to the Grosvenor Mine [Underground Operations] including the drivage of the two
access drifts, ventilation shafts and the first workings development of the pit bottom area, mains and first
longwall panel gate roads. The plan applies to all persons working at the underground mine.
1.3 Definitions
Term Definition
Control any measure used to modify risk or manage work processes
Control
Effectiveness
a matrix based assessment of Control Hierarchy and Control Quality that
provides an analysis of the effectiveness of a control. Effectiveness is
defined as being –
Green: indicating that the control should be very effective. This is the
desired effectiveness of every control but the matrix indicates that even a
90% quality Administrative or PPE control is not considered to be an
effective control. The intent of the matrix is to promote the development
and application of “harder” controls such as Engineering or Substitution
Yellow: indicates a satisfactory control could be improved to a green
control either through improving its Quality or by changing its Type. Yellow
controls should be improved first if total control effectiveness for an
unwanted event is inadequate.
Red: indicates that the control does not contribute effectively to reducing
the risk of an unwanted event
There should be two Green preventative controls for every cause of a
priority unwanted event. Refer GRO-201-PRO-Risk Management.
AGM.002.001.0821
GROSVENOR COAL MINE Underground Operations
PLN – Grosvenor Mine Overview Plan
GRO-1435-PLN-Grosvenor Mine
Overview Plan
Original Issue Date:
13/12/2013
Version: 1 Printed: 16/06/2020
Page 5 of 48 Date of Issue: 13/12/2013
PRINTED COPIES OF THIS DOCUMENT ARE UNCONTROLLED AND DEEMED VALID ONLY ON THE DAY OF PRINTING
Term Definition
Control
Hierarchy
the classification of types of control according to their potential to reduce
risk. In descending order are -
Elimination: the complete elimination of the hazard by design
Substitution / Minimise: replacing the hazard, material or process with a
less hazardous one, or significantly reduce the magnitude of the hazard or
material so consequences are greatly reduced
Engineering: incorporate controls into the design or redesign the
equipment or work process
Separation: placing a physical barrier on the hazard by guarding or
enclosing it
Administrative / Procedural: providing control such as training and
procedures
Personal Protective Equipment: use of appropriate and properly fitted
PPE where other controls are not practical
Control
Quality
the quality of a control based on its–
Reliability: will the control operate on demand as intended
Survivability: will the control remain unimpaired during the unwanted
event
Availability: will the control be available to perform its function
and categorised into ranges between < 30%; 30%-60%; 60%-90% and >
90%
Critical
Control
a “Green” level control that is- Specific, Measureable, Attainable, Realistic,
Timely, Evaluated and Reviewed. Refer GRO-201-PRO-Risk
Management.
Critical
Control
Register
a register that documents the Critical Controls at the operation. It is a
“live” document intended to record and communicate the current status of
the effectiveness of the operation’s critical controls
Hazard any energy that has the potential to do harm
Principal
Hazard
a hazard at the coal mine with the potential to cause multiple fatalities
[CMSHA Section 20]
Principal
Hazard
Management
Plan (PHMP)
a documented plan to identify, analyse and assess risks associated with
principal hazards, including the identification, analysis and assessment of
the controls implemented to reduce the risks to acceptable levels
Risk a calculation of the Likelihood of a unwanted event occurring and the
Consequence should that event occur
AGM.002.001.0822
GROSVENOR COAL MINE Underground Operations
PLN – Grosvenor Mine Overview Plan
GRO-1435-PLN-Grosvenor Mine
Overview Plan
Original Issue Date:
13/12/2013
Version: 1 Printed: 16/06/2020
Page 6 of 48 Date of Issue: 13/12/2013
PRINTED COPIES OF THIS DOCUMENT ARE UNCONTROLLED AND DEEMED VALID ONLY ON THE DAY OF PRINTING
Term Definition
Risk and
Control
Register
a register that documents the identification and analysis of the hazards,
risks, and preventative and mitigation controls at an operation. It is a “live”
document intended to record and communicate the current status of
effectiveness of the operation’s hazard’s, risks and controls.
Standard
Operating
Procedures
(SOP)
a documented way of working, or an arrangement of facilities, at the coal
mine to achieve an acceptable level of risk, developed after consultation
with coal mine workers [CMSHA Section 14] The term SOP only applies to
those procedures prescribed in the CMSHR 2001
Trigger
Action
Response
Plan (TARP)
a documented set of escalating actions that are to be taken in the event
that certain criteria are met
First Action
Response
Plans
(FARP)
simple documents that set out the immediate steps required to be taken by
those persons first on the scene at an incident
Unwanted
Event Any unwanted release of energy
2. Mine Characteristics
2.1 Location
The Grosvenor Construction Mine Project is located in the Bowen Basin of Central Queensland in Australia,
approximately 180 kilometres south-west of the coastal port city of Mackay and 5 kilometres north-west of
the town of Moranbah. The resource adjoins Anglo American Metallurgical Coal’s Moranbah North Mine to
the north.
AGM.002.001.0823
GROSVENOR COAL MINE Underground Operations
PLN – Grosvenor Mine Overview Plan
GRO-1435-PLN-Grosvenor Mine
Overview Plan
Original Issue Date:
13/12/2013
Version: 1 Printed: 16/06/2020
Page 7 of 48 Date of Issue: 13/12/2013
PRINTED COPIES OF THIS DOCUMENT ARE UNCONTROLLED AND DEEMED VALID ONLY ON THE DAY OF PRINTING
Figure 1 Moranbah Township and Grosvenor Mine
2.2 Seam Characteristics
The Goonyella Middle (GM) is the target for mining operations at Grosvenor. It is recognisable throughout
the region, correlating with the GM seam at Moranbah North and the Harrow Creek seam at Peak Downs.
This seam is also the lateral equivalent of the Aquila and Tieri seams at German Creek. The depth to the
GM seam is from 160 at pit bottom to 500 metres at the north east corner of the Grosvenor mine plan area.
2.3 Coal Quality
The Grosvenor resource has a slightly higher ash product [9.5%] than the neighbouring Moranbah North
Mine [8.5%] when washed to optimal yield. However, a reducing supply of the GM seam coal from
competitors and demand from the market should provide for the Grosvenor GM seam coal to be washed
at this higher yield.
2.4 Mine Reserves
The minable reserves of the Grosvenor mine are detailed in Table 1 below.
AGM.002.001.0824
GROSVENOR COAL MINE Underground Operations
PLN – Grosvenor Mine Overview Plan
GRO-1435-PLN-Grosvenor Mine
Overview Plan
Original Issue Date:
13/12/2013
Version: 1 Printed: 16/06/2020
Page 8 of 48 Date of Issue: 13/12/2013
PRINTED COPIES OF THIS DOCUMENT ARE UNCONTROLLED AND DEEMED VALID ONLY ON THE DAY OF PRINTING
Mine Block Thickness
mined (m)
ROM tonnes Yield Saleable
tonnes
Development 3.6 12,924,748
Longwall 3.6-4.2 134,041,990
Totals 146,966,738 69.4% 102,030,136
Table 1 Mine Reserves
2.5 Subsidence Constraints
The following summarises the mining constraints adopted in the feasibility study.
2.5.1 Blair Athol Rail Line / Eungella Eastern Water Pipe Line
The Feasibility Study plan includes the relocation of the Blair Athol rail line immediately after crossing the
Isaac River to a location directly over the main headings. The adjacent raw water pipe line will be relocated
with the rail line. For the entire route of the combined relocated rail line/water pipe line, a longwall extraction
exclusion zone based on an angle of draw of 26 degrees to minimum measurable subsidence has been
applied as a constraint for the purposes of feasibility study mine planning.
2.5.2 Goonyella Railway
The Goonyella railway line constrains the Grosvenor panels to the north. The panels have been stopped
short of the railway line to avoid subsidence of the railway line and the adjacent pipeline.
2.5.3 Lease Boundary
The lease boundary forms a partial constraint to the north. The longwall panels are stopped short of the
lease boundary to avoid subsiding beyond the lease boundary.
2.5.4 Moranbah Township
Protecting the Moranbah Township and adjoining mining/exploration leases from any measurable impacts
associated with subsidence will be crucial to avoiding compensation and minimising community concerns.
This is not considered an issue for Phase 1 of the project as the extraction area is removed far enough
away from the township to avoid any impact.
2.5.5 Isaac River
The Isaac River flows from north to south across the Grosvenor tenements on a NNW-SSE trend that is, in
general, perpendicular to the major interpreted faults. Maximum surface strains, and hence potential
surface damage, will exist where the river crosses the boundaries of the subsidence basin between chain
pillars.
Numerous studies and comprehensive risk analysis have been completed at MNM to assess the potential
for water inflow and associated consequences through longwall extraction beneath the Isaac River. MNM
has successfully undermined the river at a depth of cover of 160-170m in LW105, and again in LW107 at a
depth of cover of 200-220m. Extensive piling of the banks to retain stability in combination with sealing the
natural channel was completed prior to undermining.
AGM.002.001.0825
GROSVENOR COAL MINE Underground Operations
PLN – Grosvenor Mine Overview Plan
GRO-1435-PLN-Grosvenor Mine
Overview Plan
Original Issue Date:
13/12/2013
Version: 1 Printed: 16/06/2020
Page 9 of 48 Date of Issue: 13/12/2013
PRINTED COPIES OF THIS DOCUMENT ARE UNCONTROLLED AND DEEMED VALID ONLY ON THE DAY OF PRINTING
The minimum depth of cover under the river in the project area is 220m and the maximum 380m. Based
on experience to date at MNM, it is considered highly unlikely at these cover depths that water from the
river will seep into workings from subsidence cracking developing from longwall extraction. Extraction
beneath the Isaac River therefore, although requiring remedial and environmental rehabilitation measures,
is not considered to represent a constraint to mine planning.
2.6 Geology and Geotechnical
2.6.1 Permian Coal Measures
The Grosvenor project area straddles the subcrop boundary between Moranbah and Fort Cooper Coal
measures. The Moranbah Coal Measures range in thickness from 190m to 350m, and contains splits from
nine coal seam groups, with and average coal thickness of 20m. Sandstone, siltstone, mudstone and coal
are the predominant lithology, with one distinctive tuffaceous marker bed, the P tuff, recognised throughout
the area.
The overlying Fort Cooper Coal measures subcrop over the eastern half of the area, with the base of the
unit characterised by a thick inter-bedded sequence of tuff, mudstone and coal (Fair Hill seam).
2.6.2 Moranbah Coal Measures Stratigraphy
The coal measures within the Grosvenor Project area lie along the strike from those currently mined at the
Moranbah North Mine and BMA’s Peak Downs Mine to the south. A similar seam nomenclature to
Moranbah North has been adopted for seams of the Grosvenor deposit to facilitate a combined geological
model. The lowermost seam is the Goonyella Lower (GL) some 60m below the Goonyella Middle (GM)
seam at Moranbah North. Progressing to the south, the inter-burden between these two seams increases
to over 140m at the south eastern lease boundary.
2.6.2.1 Goonyella Middle Seam
The widespread Goonyella Middle (GM) seam is the most prospective seam within the stratigraphy and is
recognised throughout the region, correlating directly with the GM seam at Moranbah North and the Harrow
Creek seam at Peak Downs. This is also the lateral equivalent of the Aquila and Tieri seams at German
creek. The nature of the seam changes from the familiar seam recognised at Moranbah North as seam
splitting occurs in the general location of the Moranbah township. In the north of the Grosvenor project
area, the GM seam has a thickness of 4.5-5.5m. Closer to town, the seam thins due to seam splitting to
be 2.5-3.5m thick.
2.6.2.2 Goonyella Middle Seam Rider
A thin rider seam called the Goonyella Middle seam rider (GMR), is present in the immediate roof at
Moranbah North splitting away towards the southern end of the 100’s longwall panels. This split is
maintained across the Grosvenor project area with the seam some 25-35m above the GM seam and more
closely associated with the P Tuff.
2.6.2.3 P Tuff
The P Tuff is a regionally exclusive tuffaceous marker bed that can be recognised throughout much of the
Grosvenor project area varying in thickness from 0.4- to 2m. Commonly associated with the P Tuff are thin
coaly bands above and below the tuff band. The P Tuff usually lies about 10-15m below the P seam, but
the interval thickens to 43m in DDG010 to the south of the town
AGM.002.001.0826
GROSVENOR COAL MINE Underground Operations
PLN – Grosvenor Mine Overview Plan
GRO-1435-PLN-Grosvenor Mine
Overview Plan
Original Issue Date:
13/12/2013
Version: 1 Printed: 16/06/2020
Page 10 of 48 Date of Issue: 13/12/2013
PRINTED COPIES OF THIS DOCUMENT ARE UNCONTROLLED AND DEEMED VALID ONLY ON THE DAY OF PRINTING
2.6.2.4 P Seam
The P Seam occurs as three discrete seams at Moranbah North (GR, PL1 and PL2). These coalesce and
are present as one seam across the majority of the Grosvenor area splitting towards the far east. Despite
the coalescence, the seams are easily distinguished using geophysics, and a number of consistent partings
are present. The lowermost PL2 seam averages 0.6-1.2m in thickness and is separated from the overlying
PL1 by a 0.1-0.15m tuffaceous claystone parting. Despite being an excellent coking coal, the PL1 seam
coal contains high inherent ash levels that make washing to a suitable ash coking coal difficult at an
economic yield.
2.6.3 Seam Splitting
Unlike the GM seam at Moranbah North, the seam at Grosvenor does not maintain a uniform thickness
across the deposit. The seam undergoes 3 ply splitting events to significantly reduce the workable seam
thickness across the lease.
Just south of the railway line north of the Moranbah township, the parting between the 4A and the 4B plies
thickens from its normal 0.15-0.2m. This rapidly thickens to the south with the lower 4B, 5T and 5B plies
separating from the main seam by approximately 12m. Where the parting is 0.3m or greater, the plies are
regarded as being split and no longer included in the GM seam thickness. The 0.3m interburden contour is
taken as the split line. This effectively thins the seam from 4.5-6.5m north of the split line to 3.5m south of
the split line.
2.6.4 Depth of Cover
The depth to the GM seam from the surface varies from 60m to 120m at the subcrop to 500m at the north
east corner of the Grosvenor mine plan area. The variation in cover thickness at the subcrop is due to
thickening of Tertiary sediments towards the north. Cover depth at Moranbah North is seen as contributing
to mining hazard with difficult conditions often experienced with the longwall at depths greater than 220m.
This is interpreted as the point where the in-situ horizontal stress is equivalent to the strength of the coal
(5-6MPa) leading to rib and coal beam instability. The 1750t supports have successfully mined LW108 at
depths of 300m with the design better able to cope with damaged roof beam coal. Similar conditions are
expected in the proposed Grosvenor mining area and the knowledge gained at Moranbah North are to be
built into the design of the Grosvenor supports.
2.6.5 Stress Orientation
The major horizontal stress direction rotates to the east over the eastern part of the Grosvenor 1 lease
area. The gate roads are incrementally rotated in the eastern area as a means of minimising stress
concentration impacts during longwall retreat and optimising chain pillar size.
AGM.002.001.0827
GROSVENOR COAL MINE Underground Operations
PLN – Grosvenor Mine Overview Plan
GRO-1435-PLN-Grosvenor Mine
Overview Plan
Original Issue Date:
13/12/2013
Version: 1 Printed: 16/06/2020
Page 11 of 48 Date of Issue: 13/12/2013
PRINTED COPIES OF THIS DOCUMENT ARE UNCONTROLLED AND DEEMED VALID ONLY ON THE DAY OF PRINTING
Figure 2 Grosvenor Mine Horizontal Stress Orientation
2.6.6 Geotechnical considerations
The behaviour of roadways within the Goonyella Middle Seam is categorised for a range of geotechnical
domains at various depths and for both development and retreating longwall operations. Table describes
the domains identified for analysis.
The input data for the models was based on available stress and coring/rock testing in combination with
borehole geophysics.
Domain Type
Section
Working
Seam
Section
Description
A Seam
Split
Lithology
~4.5m Lithology dominated by GM1 Split from GMS. GM1 to
GM2 interburden thickness is variable to 2.4m (1.6
modelled). Interburden comprised of weak, low density
material. Introduction of moderate strength strata above
~7m (above seam floor) and below seam.
Virgin gas content 9 to 11 m3/t.
B Normal
Lithology-
(West of
Split
Line)
~5m Weakly bedded, laminated strata immediately overlying
GMS. Moderate strength strata from ~6m (above seam
floor) and below seam. Potential for weaker floor in
some areas.
Virgin gas content less than 4 m3/t
C Weak
Sub-Crop
Lithology
~5m Weak, bedded sequence immediately above and below
GMS.
Potential for weakly bedded silt/sandstone immediately
above seam.
AGM.002.001.0828
GROSVENOR COAL MINE Underground Operations
PLN – Grosvenor Mine Overview Plan
GRO-1435-PLN-Grosvenor Mine
Overview Plan
Original Issue Date:
13/12/2013
Version: 1 Printed: 16/06/2020
Page 12 of 48 Date of Issue: 13/12/2013
PRINTED COPIES OF THIS DOCUMENT ARE UNCONTROLLED AND DEEMED VALID ONLY ON THE DAY OF PRINTING
Virgin gas content <5m3/t.
Currently no Grosvenor 1 mining will occur in Domain C.
D Normal
Lithology
(East of
Split
Line)
~5m Weakly bedded, laminated strata immediately overlying
GMS. Moderate strength strata from ~6m (above seam
floor) and below seam. Potential for weaker floor in
some areas.
Virgin gas content 4 to +11 m3/t.
Table 2: Description of the Grosvenor Geotechnical Domains
Figure shows the extent of the geotechnical domains for ground support recommendations.
Figure 3: Geotechnical Domains
2.6.7 Gas Content
With the exception of the inbye half of the mine plan (Teviot Brook area), the gas reservoir database for
Grosvenor is extensive for the P and GM seams. From testing undertaken to date, the composition of all
seams is predominately CH4 with compositions ranging from 97% to 100%.
AGM.002.001.0829
GROSVENOR COAL MINE Underground Operations
PLN – Grosvenor Mine Overview Plan
GRO-1435-PLN-Grosvenor Mine
Overview Plan
Original Issue Date:
13/12/2013
Version: 1 Printed: 16/06/2020
Page 13 of 48 Date of Issue: 13/12/2013
PRINTED COPIES OF THIS DOCUMENT ARE UNCONTROLLED AND DEEMED VALID ONLY ON THE DAY OF PRINTING
The gas parameters for the P seam are:
▪ Measured virgin gas content varies from 6.5m3/t to 11.5m3/t at seam ash content.
▪ Measured permeability ranges from 264mD at a depth of 157m to 0.7mD at 389m.
▪ Calculated gas reservoir size ranges from 40m3/m2 to about 80m3/m2.
The gas parameters for the GM seam are:
▪ Measured virgin gas content varies from 5.2m3/t to 11m3/t at seam ash content.
▪ Measured permeability ranges from 225mD at a depth of 219m to 0.1mD at 471m.
▪ Calculated gas reservoir size ranges from 41m3/m2 at MG1 entry to about 115m3/m2 in the
deeper north-eastern areas of the mine plan.
2.6.8 Gas Reservoir at the Time of Mining
The mining schedule will progressively impact the gas production wells of Arrow Energy. The timing of
these impacts have been assessed on the flow rates and remaining gas for each well at the time of
intersection. Gas content at the time of mining has been calculated to be between 3 and 7 m3/t in the P
seam as shown in Figure and from 2 to 10 m3/t in the GM seam as shown in Figure , indicating the need
to implement a pre-drainage program for outburst mitigation ahead of mining in the GM seam, in addition
to the current Arrow pre-drainage program.
Reservoir modeling simulating gas emission rates during mining incorporating the remaining gas content
estimations, indicate the intake CH4 concentrations will exceed design limits at planned ventilation
quantities and panel advance rates during the development of Tailgate 1, Maingate 1 and Maingate 2.
Where panel advance rates are increased by 50%, design intake CH4 limits are exceeded in those gates
as well as in Maingate 6. This means additional pre-drainage will be required to ensure gas is at acceptable
mining levels prior to mining operations in these areas.
Figure 4: Expected Gas Content at the Time of Mining – P Seam (Qm, m3/t @ seam ash)
2.8
3.2
3.3
2.9
2.4
2.7
2.6
2.2
2.7
5.1
4.1
3.3
5.6
6.6
3.6
4.5
6.8
6.7
6.5
6.3
6.6
6.8
6.8
5.8
5.8
5.8
5.4
5.9
3.1
5.7
7.1
3.7
4.7
6.0
AGM.002.001.0830
GROSVENOR COAL MINE Underground Operations
PLN – Grosvenor Mine Overview Plan
GRO-1435-PLN-Grosvenor Mine
Overview Plan
Original Issue Date:
13/12/2013
Version: 1 Printed: 16/06/2020
Page 14 of 48 Date of Issue: 13/12/2013
PRINTED COPIES OF THIS DOCUMENT ARE UNCONTROLLED AND DEEMED VALID ONLY ON THE DAY OF PRINTING
Figure 5: Expected Gas Content at the Time of Mining – GM Seam (Qm, m3/t @ seam ash)
2.6.9 Outburst Risk
Although the Arrow Energy coal seam methane drainage program will have removed a considerable
quantity of gas from the GM seam up to the time of intersection of the SIS holes, the GeoGAS study
indicates that the remaining gas content will still be above the outburst threshold over a considerable portion
of the proposed workings. An outburst management plan will be developed and implemented and will also
address the following:
• Intersection of gas drainage boreholes
• Compliance coring and the permit to mine process
• Pre-drainage required for areas of known outburst levels
• Treatment of structure from an outburst perspective.
• Remote mining if required
Outburst and gas drainage thresholds at 99% CH4 and sample ash for the GM seam have been determined
using GeoGAS’s 900DRI method as:
▪ Outburst threshold 7 m3/t.
▪ Gas drainage threshold 6 m3/t (Mean less 2 Standard Deviations).
Plotting the estimated gas content at seam ash at the time of mining for the GM seam suggests that the
gas content will exceed the outburst and gas drainage threshold across the inbye areas as shown in Figure
.
1.5
3.0
1.4
1.5
1.3
2.0
2.4
2.4
3.8
2.0
2.3
2.5
1.9
3.3
1.4
3.2
2.6
2.5
4.6
4.0
3.6
6.1
3.6
5.2
3.4
3.4
7.4
4.7
4.8
4.6 5.6
6.7
8.2
8.8
7.4
10.0
8.9
7.0
5.4
5.5
2.4
7.0
6.7
7.4
6.6
7.1
5.8
5.2
2.6
4.3
4.4
4.6
4.9
AGM.002.001.0831
GROSVENOR COAL MINE Underground Operations
PLN – Grosvenor Mine Overview Plan
GRO-1435-PLN-Grosvenor Mine
Overview Plan
Original Issue Date:
13/12/2013
Version: 1 Printed: 16/06/2020
Page 15 of 48 Date of Issue: 13/12/2013
PRINTED COPIES OF THIS DOCUMENT ARE UNCONTROLLED AND DEEMED VALID ONLY ON THE DAY OF PRINTING
Figure 6: GM Seam Gas Content at the Time of Mining and Outburst Thresholds (@ Seam Ash)
2.7 Spontaneous Combustion
The test work on the Grosvenor drill cores from the GM seam indicates that the propensity of the coal to
spontaneous combustion is low and is consistent with the results of tests previously undertaken for the GM
seam at MNM. It is noted however that Moranbah North Mine has experienced events where high levels of
carbon monoxide generated from oxidation of the coal in the goaf has resulted in the withdrawal of the
workforce from the mine and the cessation on work underground for extended periods.
In order to minimise the risk of spontaneous combustion the following controls will considered for
Grosvenor:
• Use of U ventilation on the longwall to minimize differential pressure across the goaf
• Operation of the goaf drainage plant to minimise air being drawn into the goaf
• Installation of 140kPa seals in the cut throughs behind the longwall
• Operation and maintenance of extensive tube bundle and real time gas monitoring system to
provide early indication of spontaneous combustion.
• Operation of a floxal nitrogen generator for active goaf inertisation at all times.
3. Mine Operations
3.1 Mine Design and Layout
The mine access is located near the subcrop of the Goonyella Middle seam approximately 5 kilometres
north-east of the Moranbah township. The positioning of the pit bottom area is such that the seam is
accessed at a depth of 160 metres with almost immediate access for the development of the tailgate and
maingate of the first longwall panel.
Mine access will be via two drifts –
Men & Materials approximately 7.0m in diameter, 1.2km long and at a grade of 1:8 the M&M
Drift will be used for rubber tyred personnel, materials and equipment access.
1.5
3.0
1.4
1.5
1.3
2.0
2.4
2.4
3.8
2.0
2.3
2.5
1.9
3.3
1.4
3.2
2.6
2.5
4.6
4.0
3.6
6.1
3.6
5.2
3.4
3.4
7.4
4.7
4.8
4.6 5.6
6.7
8.2
8.8
7.4
10.0
8.9
7.0
5.4
5.5
2.4
7.0
6.7
7.4
6.6
7.1
5.8
5.2
2.6
4.3
4.4
4.6
4.9
AGM.002.001.0832
GROSVENOR COAL MINE Underground Operations
PLN – Grosvenor Mine Overview Plan
GRO-1435-PLN-Grosvenor Mine
Overview Plan
Original Issue Date:
13/12/2013
Version: 1 Printed: 16/06/2020
Page 16 of 48 Date of Issue: 13/12/2013
PRINTED COPIES OF THIS DOCUMENT ARE UNCONTROLLED AND DEEMED VALID ONLY ON THE DAY OF PRINTING
Conveyor Drift approximately 7m in diameter, 0.9km long at a grade of 1:6 the conveyor drift
will also serve as the secondary escapeway from the mine.
Both the drifts are to be driven with an Earth Pressure Balance Tunnel Boring Machine (EPBTBM) and will
be fully lined with pre-cast concrete segments.
Two vertical shafts are to be developed
Upcast (return) shaft blind bored approximately 5.8m diameter fully concrete lined fitted with
exhausting ventilation fans
Downcast (intake) shaft blind bored approximately 2 x 2.5m diameter fully concrete lined equipped
with emergency evacuation facilities to act as (temporarily) secondary escapeway during pit-bottom
development.
The mine will be developed in an easterly direction sub-parallel to the strike of the seam. The longwall
blocks are orientated to the north-east with the seam dipping down in the same direction at approximately
1:15.
The longwall panels will be up to 300m wide, 6200m long and contain up to 11Mt of ROM coal. At the
extremity of the mine the seam depth will approach 500m.
The panels are to be extracted in sequence from west to east with the longwall panels to progressively
rotate in a clockwise direction to allow change of stress direction and increase of the width of gate road
pillars with depth.
3.2 Pillar design
3.2.1 Main headings
The criteria for the design of the main headings is a factor of safety of approximately 2.5 and a width to
height ratio of 8. The pillar widths are based on a pillar length of 95 metres. The table below shows the
design parameters for main pillar widths for a range of depths based upon the above criteria.
Depth of cover (m) Pillar Width Rib to Rib (m)
<300 30
300-350 35
350-400 40
400-450 42
Table 3 Main Headings Pillar Design Parameters
3.2.2 Chain pillars
The chain pillar widths are designed with a conservative factor of safety of 1.25.
The table below shows the design parameters for main pillar widths for a range of depths based upon the
above criteria. All pillar sizes are based upon 90 metre pillar lengths (final pillar length in design is 100m).
Two heading chain pillar lengths Three heading chain pillar lengths
AGM.002.001.0833
GROSVENOR COAL MINE Underground Operations
PLN – Grosvenor Mine Overview Plan
GRO-1435-PLN-Grosvenor Mine
Overview Plan
Original Issue Date:
13/12/2013
Version: 1 Printed: 16/06/2020
Page 17 of 48 Date of Issue: 13/12/2013
PRINTED COPIES OF THIS DOCUMENT ARE UNCONTROLLED AND DEEMED VALID ONLY ON THE DAY OF PRINTING
Depth of cover (m) Pillar Width Rib to Rib
(m)
Depth of cover (m) Pillar Width Rib to Rib
(m)
150 30 150 2*30
200 35 200 2*30
250 42 250 2*30
300 50 300 2*37
350 60 350 2*45
400 67 400 2*52
450 70 450 2*60
500 2*65
Table 4 Chain Pillar Design Parameters
3.3 Surface Infrastructure
3.3.1 Administration buildings
The administration buildings comprise offices, workstations and adjacent training room sized to
accommodate up to 60 persons. The cap lamp and self-rescuer storage facility is sized to accommodate
600 lamps and self-rescuers
A muster area adjacent to the administration buildings provides a covered area for crews to gather prior to
starting work.
3.3.2 Change house
The change house will provide separate wash and ablution facilities for male and female personnel. Each
facility will contain clean and dirty change areas which will include adequate locker numbers for personnel.
3.3.3 Diesel Storage
Two 80,000 litre diesel tanks will be installed. The re-order point will be set at approximately 110,000 litres
to provide a reserve of almost 11 days usage at typical demand plus 20%.
3.3.4 Workshop/warehouse building
The work shop building comprises -
• Six MV workshop bays with for onsite servicing of mining vehicles
• Service area for limited on site servicing of light vehicles
• A dedicated welding bay with fume extraction
• General purpose maintenance shop for fixed plant
• Workshop offices area incorporating crib and toilet facilities
AGM.002.001.0834
GROSVENOR COAL MINE Underground Operations
PLN – Grosvenor Mine Overview Plan
GRO-1435-PLN-Grosvenor Mine
Overview Plan
Original Issue Date:
13/12/2013
Version: 1 Printed: 16/06/2020
Page 18 of 48 Date of Issue: 13/12/2013
PRINTED COPIES OF THIS DOCUMENT ARE UNCONTROLLED AND DEEMED VALID ONLY ON THE DAY OF PRINTING
The warehouse building comprises -
• A stores area with storage racking and separate sorting area
• Office with stores counter to workshop area
• A covered loading bay for handling incoming and outgoing materials.
3.3.5 Coal transportation
Raw coal will be transported to the Moranbah North Mine via a new overland conveyor for processing at
the Moranbah North Coal preparation plant. The product coal will be loaded out through the existing MNM
train load out to unit trains of 10,000 tonnes capacity and railed along the existing railway network.
Tailings and reject will be combined at the Moranbah North CPP into a slurry and pumped to the existing
co-disposal area located to the west of the CPP.
3.4 Production Capacity
3.4.1 Longwall Productivity
The longwall has been scheduled as a bi-directional cut with an 850mm web cutting at a height of between
3 and 4.2 metres. Utilisation rates have been set at 75 cutting hours per week. Longwall ROM is planned
to be between 5Mt and 7.5Mt per annum with the variation driven by panel length and forecast mining
conditions.
3.4.2 Development Productivity
Development operations will be standard Continuous Miner development units utilising on-board bolting
rigs for primary support and shuttle cars for coal clearance. The Joy 12ED25 has been selected as the
continuous miner for development.
There will be three development units, two gateroad development units and one mains development unit.
A fourth unit may be mobilised from periodically to maintain appropriate development float in line with the
mine schedule.
Table 5 below shows the scheduled base development rate [metres per week] based upon depth of cover
and geological domain.
Domain A Domain B Domain C
Depth of
cover (m)
Two
heading
gateroads
Three
heading
gateroads
Two
heading
gateroads
Three
heading
gateroads
Two
heading
gateroads
Three
heading
gateroads
< 225 176 167 197 197 197 197
225-275 158 149 183 176 183 176
275-350 133 126 154 145 154 145
>350 125 117 142 134 142 134
Table 5 Development Rates metres/week
AGM.002.001.0835
GROSVENOR COAL MINE Underground Operations
PLN – Grosvenor Mine Overview Plan
GRO-1435-PLN-Grosvenor Mine
Overview Plan
Original Issue Date:
13/12/2013
Version: 1 Printed: 16/06/2020
Page 19 of 48 Date of Issue: 13/12/2013
PRINTED COPIES OF THIS DOCUMENT ARE UNCONTROLLED AND DEEMED VALID ONLY ON THE DAY OF PRINTING
3.5 Mining Methodology and Equipment
3.5.1 Mine Development
Development operations will be standard Continuous Miner development units utilising on-board bolting
rigs for primary support and shuttle cars for coal clearance. The Joy 12ED25 has been selected as the
continuous miner for development coupled with 10SC42 shuttle cars.
3.5.2 Longwall Mining
The longwall has been scheduled as a uni-directional cut with an 850mm web cutting at a height of between
3 and 4.2 metres. A single 4500tph shearer has been proposed for operation at Grosvenor.
Table 6 below summarises the parameters and expected requirements of the longwall system.
Parameter Requirement
Longwall panel width 300 metres (rib to rib)
Longwall panel length 6200 metres
Mining extraction range Typical 4.0 metres(nominal cutting height, minimum 3.5 and maximum
4.5 metres
Retreat distance Approx. 70000 metres over life of mine
Total tones Approx. 132Mt over life of mine
Cutting processes Uni-di, Bi-di and half web capability
Nominal wed depth 850mm
Nameplate capacity 4500tph
process cycle capacity >3500tph
Average cycle capacity >2850tph
Resourced time 168 hours per week
Planned maintenance
work
40 hours per week
Estimated operating
time
95 - 100 hours per week
Equipment Requirement
Roof supports Two leg, 2 metre nominal spacing (width), 2.3-4.8 m hydraulic range
Support density yield>145t/m2 before cut
Immediate Face Support (IFS) canopy and single side shield
Full electro hydraulic system
suitable for longwall automation
Integrated dust suppression sprays
Shearer Double ended raging arm with multi motor shearer
AGM.002.001.0836
GROSVENOR COAL MINE Underground Operations
PLN – Grosvenor Mine Overview Plan
GRO-1435-PLN-Grosvenor Mine
Overview Plan
Original Issue Date:
13/12/2013
Version: 1 Printed: 16/06/2020
Page 20 of 48 Date of Issue: 13/12/2013
PRINTED COPIES OF THIS DOCUMENT ARE UNCONTROLLED AND DEEMED VALID ONLY ON THE DAY OF PRINTING
Suit 4500 tph nameplate capacity longwall
Radio remote control
Bi-directional data communication system
suitable for longwall automation
Armoured Face
Conveyor (AFC)
Continuous rating 4500tph, peak volume capacity 5000tph
capable of a reserve chain pull of 170 tonnes
Automatic chain tensioning system
Beam Stage Loader Continuous rating 5000tph
Automatic Chain tensioning system
Full dust cover and system including dust extraction
Crusher Continuous rating 5000tph
Output regulation <4700tph
Output material sizing to ,300mm
Boot End Skid type with steering, side shift and levelling
Overlap to suit two face advances
Belt conveyor tail pulley to transfer load to the stage loader
Belt lifting unit to assist with conveyor structure salvage
Suit 1600mm belt width maingate conveyor
Longwall Pump Station Track mounted pump and tanks capable of being relocated underground
by tramming or towing with mine LHDs
Located in cut through outbye of the longwall face, one station
connected to the longwall system by monorail, second station on
maintenance, ready for reconnection to monorail upon services
relocation
Hydraulic supply for roof supports with 20% reserve capacity
water supply for shearer cooling and dust suppression sprays
water supply for roof support dust suppression sprays
Monorail System Suit 200m of longwall retreat between retractions
Included 110 metres movement materials management system
Includes monorail installation and salvage platforms and relocation
sleds
Electrical System Incoming supply 11kV
Face Voltage 3.3kV (AFC drives 11kV optional)
Designed to limit voltage drop during AFC overloaded starts to 20% of
nominal motor voltage
Automation System Includes LASC standards
Table 6 Longwall Equipment Schedule
AGM.002.001.0837
GROSVENOR COAL MINE Underground Operations
PLN – Grosvenor Mine Overview Plan
GRO-1435-PLN-Grosvenor Mine
Overview Plan
Original Issue Date:
13/12/2013
Version: 1 Printed: 16/06/2020
Page 21 of 48 Date of Issue: 13/12/2013
PRINTED COPIES OF THIS DOCUMENT ARE UNCONTROLLED AND DEEMED VALID ONLY ON THE DAY OF PRINTING
3.5.3 Conveyors
Table 7 below outlines conveyor configurations. Note that the same conveyors will be used for both
development and longwall.
Design Parameters
Parameter Units
Gate Road Duty
(CVU 101-109)
Trunk Conveyor T1 Duty
(CVU002)
Drift Conveyor
UC101 (CVU001)
Develop L/wall At Start-up LW1 Final At Start-
up Final
Required
volumetric
capacity
tph up to
1000
4725 7800 7800 3000 6800
Required
continuous
capacity
tph up to
510
4500 4500 from LW
200 from MG2
200 from MG3
400 from mains
5800 700 6000
Belt length m varies up to
6625m
1600 2760 1082
Belt lift m varies up to 280m 63.5 85.5 177
Belt Width mm 1600 2000 2000
Belt speed m/s 1.5-2.0 5.2 1.5-2.0 5.1 1.5-2.0 5.1
Equipment Parameters
Head drive
power
kW 1x750 3x750 2x750 2x750 1500kW
Tripper
drive power
kW No
tripper
up to
3x750
No tripper 2x750 N/A
No. of
trippers
Nil up to 3 Nil 1 N/A
Belting type PN2500 4x4mm PN2000 6x4mm ST2800 8x7mm
Carry
trough
idlers
3*400
3m spacing
3*350
3m spacing
3*350
3m spacing
Return
trough
idlers
2*100
6m spacing
2*100
6m spacing
2*100
3m spacing
Table 7 Conveyor Configurations
3.5.4 Transport Arrangements
Men and Materials transport will be conducted by rubber tyred diesel vehicles operating principally within
the Men & Material drift. The Conveyor drift does have the capacity to accommodate rubber tyred diesel
vehicles.
Coal clearance will be exclusively by conveyor belts installed in the separated conveyor roadways and the
Conveyor drift.
AGM.002.001.0838
GROSVENOR COAL MINE Underground Operations
PLN – Grosvenor Mine Overview Plan
GRO-1435-PLN-Grosvenor Mine
Overview Plan
Original Issue Date:
13/12/2013
Version: 1 Printed: 16/06/2020
Page 22 of 48 Date of Issue: 13/12/2013
PRINTED COPIES OF THIS DOCUMENT ARE UNCONTROLLED AND DEEMED VALID ONLY ON THE DAY OF PRINTING
3.6 Ventilation System
3.6.1 Ventilation requirements
Total mine ventilation requirements will change with the number of panels and their extent, including
standing gate roads. A nominal assessment of ventilation requirements is shown in the table below. These
quantities are indicative and will depend on seam gas management requirements, standards of mains
stoppings and configuration of the rear block shaft (intake or exhaust)
Item Quantity (m3/sec)
Longwall 2 heading 75
Development Panels (last c/t) 55
Mains panel (cumulative of flanks) 70
Standing gateroad 40
Total Panels 350
Conveyor Drift and belt road air dump 80
Fuel bay 15
Transformer and pumps 15
Misc 10
Total Ancillary 120
Total Ventilation requirement 540
Table 8 Ventilation Quantities
3.6.2 Airways
The initial development of the mine will be ventilated by the men and materials drift on intake, the conveyor
drift on intake, an upcast (return) shaft of 5.5 metres diameter and a free venting intake shaft.
3.6.3 Surface Fans
The upcast shaft will be fitted with three identical centrifugal fans with VVVF speed control. The specification
calling for 2 fans to deliver 400m3/sec with the third spare on the initial shaft. The fan static pressure at this
operating point will be approximately 4 kPa. Three fans operating in parallel may be required for LoM
ventilation requirements.
3.6.4 Ventilation and gas monitoring
The ventilation system will be monitored as follows
1. 30 point infrared tube bundle system reticulated throughout the mine to monitor the active location
of the explosive fringe in the active goaf, status of the goaf stream, status of sealed goafs and
chosen roadway analysis in conjunction with real time monitors.
AGM.002.001.0839
GROSVENOR COAL MINE Underground Operations
PLN – Grosvenor Mine Overview Plan
GRO-1435-PLN-Grosvenor Mine
Overview Plan
Original Issue Date:
13/12/2013
Version: 1 Printed: 16/06/2020
Page 23 of 48 Date of Issue: 13/12/2013
PRINTED COPIES OF THIS DOCUMENT ARE UNCONTROLLED AND DEEMED VALID ONLY ON THE DAY OF PRINTING
2. Real time monitoring as required by regulations, monitoring for oxygen, carbon monoxide, carbon
dioxide and methane.
3. Safegas / Seagas system or similar to collect data, provide trends and alarms and predetermined
TARPS.
4. Gas chromatograph to analyse discrete samples from active and sealed areas
5. Surface barometric pressure transducers
6. Air velocity transducers
7. Surface fan pressure transducers
8. Pressure differential transducers at select locations between intake and return
9. Green House Gas monitoring system
3.6.5 Heat management
The general approach for heat management is as follows
1. Maintain relatively high velocities on longwall and development faces to minimize effective
temperatures. In development areas 760mm duct will be used instead of 600mm duct.
2. As far as practicable, ventilate large equipment to return airways e.g. bleed over gate road drive
heads through coffin seals and main pumps through stoppings to return airways
3. Segregation of drift, mains trunk and gateroad belts and use of belt road air dumps
4. Provide for bulk cooling of intake air
4. Integrated Operational Risk Management
4.1 Group Technical Standard 02 Integrated Risk Management Standard
As defined in GTS02 the Integrated Risk Management Process flow diagram, depicted below shall be the basis for risk management throughout Anglo American.
Figure 2 Anglo Risk Management Process [based on ISO 31 000 Risk Management
AGM.002.001.0840
GROSVENOR COAL MINE Underground Operations
PLN – Grosvenor Mine Overview Plan
GRO-1435-PLN-Grosvenor Mine
Overview Plan
Original Issue Date:
13/12/2013
Version: 1 Printed: 16/06/2020
Page 24 of 48 Date of Issue: 13/12/2013
PRINTED COPIES OF THIS DOCUMENT ARE UNCONTROLLED AND DEEMED VALID ONLY ON THE DAY OF PRINTING
A key output from integrated risk management shall be a single, integrated Risk and Critical Control
Register for each Business Unit, operation and project. These registers shall be structured such that the
Business Units can analyse and consolidate the data from across its operations/projects allowing the
material risks to the Business Unit to be reflected and managed from a single integrated Business Unit
Risk and Critical Control Register.
These registers shall be structured such that the data required for reporting purposes can be readily
filtered from the respective registers.
4.2 Operational Risk Assessment Methodology
It is crucial that all Coal Mine Workers at Grosvenor Mine operations knows what is expected in terms of
managing safety in their workplace. Anglo has invested heavily in the development a simple, uniform
approach to Safety Risk Management so that all personnel have the training, tools and resources
required to help them make the right decisions in their workplaces.
In using this approach, Anglo has adopted a cohesive Four-Layer Approach recognising that safety risk is
affected by decisions made for different reasons, at different layers within the organisation and should be
controlled at each of these decision points. Decisions made at the top can have a huge impact on
underlying layers. Within each layer, application of risk assessment methods and tools will vary
depending on the nature of the assessment, the detail required and a number of other factors. It is likely
that several tools would be used in each layer.
Figure 5 illustrates this Four Layered Approach with a more detailed Step by Step Guide on applying this
approach included in Table 3.
AGM.002.001.0841
GROSVENOR COAL MINE Underground Operations
PLN – Grosvenor Mine Overview Plan
GRO-1435-PLN-Grosvenor Mine
Overview Plan
Original Issue Date:
13/12/2013
Version: 1 Printed: 16/06/2020
Page 25 of 48 Date of Issue: 13/12/2013
PRINTED COPIES OF THIS DOCUMENT ARE UNCONTROLLED AND DEEMED VALID ONLY ON THE DAY OF PRINTING
OVERALL FUNCTION, SITE MAJOR HAZARD, BASELINE OR FULL SITE RISK ASSESSMENT.
Objective: to look across an entire site, find potential major incidents and analyse, establish controls, document, and apply approaches so related risks are as low as reasonably practicable (ALARP). This layer also applies to executive decisions made in head offices and in specialist functions.
PROJECT, CHANGE OR ISSUE-BASEDRISK ASSESSMENT.
Objective: to review equipment, changes, and major incidents for risks so related risks are tolerable.
ROUTINE AND NON-ROUTINE TASK BASEDRISK ASSESSMENT.
Objective: to develop effective safe work expectations - guidelines, standard operating practices (SOPs), job plans, etc. - and review tasks where adequate SOPs are not available so related risks are ALARP.
‘EVERYDAY’, CONTINUOUS, FACE LEVEL RISK ASSESSMENT.
Objective: to have the person ‘stop and think’ and proceed with a task only if safe.
Figure 5 The Four Layered Approach to Risk Management
The growing global reach of Anglo’s operations, combined with widely varying underlying safety cultures
and maturity, has resulted in a range of risk management processes that vary in quality and application.
Anglo’s Peer Review process and fatality investigations have highlighted the importance of creating a
standard Anglo approach to managing risk assessments and methods of risk control. In this same way, it
has been recognised that these same leading edge practices and resources are equally as applicable to
the effective control of all hazards and risks across an operation, not just safety risks. Operational
Performance, Regulatory Impacts, Occupational Health, Environmental Management and Community
Expectations [to name a few] are all potential sources of harm to our businesses and must all be subject
to the same rigour of risk management analysis and effective control.
As such, Anglo has developed a Group Technical Standard GTS 02 Operational Risk Management
[and a range of supporting guidelines and templates] to provide a standardised risk management
approach across its operations.
This standard forms the basis of the Integrated Operation Risk Management Processes in place at
Grosvenor Mine.
AGM.002.001.0842
GROSVENOR COAL MINE Underground Operations
PLN – Grosvenor Mine Overview Plan
GRO-1435-PLN-Grosvenor Mine
Overview Plan
Original Issue Date:
13/12/2013
Version: 1 Printed: 16/06/2020
Page 26 of 48 Date of Issue: 13/12/2013
PRINTED COPIES OF THIS DOCUMENT ARE UNCONTROLLED AND DEEMED VALID ONLY ON THE DAY OF PRINTING
4.3 Four Layered Approach
Layer 1 Baseline Full Site Risk Assessment Layer 2 Project / Change or Issue Based Risk Assessment
AGM.002.001.0843
GROSVENOR COAL MINE Underground Operations
PLN – Grosvenor Mine Overview Plan
GRO-1435-PLN-Grosvenor Mine
Overview Plan
Original Issue Date:
13/12/2013
Version: 1 Printed: 16/06/2020
Page 27 of 48 Date of Issue: 13/12/2013
PRINTED COPIES OF THIS DOCUMENT ARE UNCONTROLLED AND DEEMED VALID ONLY ON THE DAY OF PRINTING
Layer 3 Routine Task Risk Assessment Layer 4 Individual Risk Assessment
Table 3 The Four Layered Approach to Risk Management
AGM.002.001.0844
GROSVENOR COAL MINE Underground Operations
PLN – Grosvenor Mine Overview Plan
GRO-1435-PLN-Grosvenor Mine
Overview Plan
Original Issue Date:
13/12/2013
Version: 1 Printed: 16/06/2020
Page 28 of 48 Date of Issue: 13/12/2013
PRINTED COPIES OF THIS DOCUMENT ARE UNCONTROLLED AND DEEMED VALID ONLY ON THE DAY OF PRINTING
4.4 Baseline Operational Risk Analysis of Grosvenor Operations
4.4.1 Operational Risk Analysis Process
The Baseline Operational Risk Analysis undertaken at Grosvenor Mine was conducted by -
i. Defining the site boundaries and limits of review
ii. Consider life cycle aspects in new projects from concept and design, through to operations and
maintenance and, if relevant, disposal and closure
iii. Systematically breaking down the entire site by Functional Activity, Process or Location to
appropriate detail to identify the hazards and associated risks within those Functions, Processes
or Locations
iv. Establish a relevant hazard inventory for the Operational functions at the site that includes clear
understanding of the existence, magnitude, release mechanisms and potential impacts of the
hazards [the Hazard Profile]
v. Rank the identified hazards and unwanted events to define the major potential unwanted incidents
for further analysis
vi. Analyse the major potential unwanted incidents to an adequate depth with appropriate risk
assessment methods (WRAC, FMEA, HAZOP, FTA, BTA, etc.)
vii. Define the existing Preventative and Mitigation/Recovery controls in place
viii. Conduct a Control Effectiveness analysis of the existing controls [the Control Profile]
ix. Review the Hazard Profile against the Control Profile and determine if the risks are at Acceptable
Levels and As Low As Reasonably Practical [ALARP]
x. If risks are not ALARP, define new controls and conduct new effectiveness analysis until risks are
tolerable
xi. Determine an Action Plan for establishing new required controls
xii. Define the Critical Controls and assign ownership, accountabilities and the monitoring and auditing
requirements for each
xiii. Transfer the critical controls into the Critical Control Monitoring system to ensure they remain
available, reliable and survivable throughout the life-cycle of the hazard
xiv. Document the information from the analyses in a Risk & Critical Control Register
xv. Ensuring the Risk & Critical Control Register it is kept up to date including integration of results
from the Critical Control Monitoring system as well as any risk assessment analysis done at any of
the Four Layer risk assessments
The outcomes of this Step-by-Step process are summarised in the following sections with full details
incorporated into the site Safety and Health Management System.
AGM.002.001.0845
GROSVENOR COAL MINE Underground Operations
PLN – Grosvenor Mine Overview Plan
GRO-1435-PLN-Grosvenor Mine
Overview Plan
Original Issue Date:
13/12/2013
Version: 1 Printed: 16/06/2020
Page 29 of 48 Date of Issue: 13/12/2013
PRINTED COPIES OF THIS DOCUMENT ARE UNCONTROLLED AND DEEMED VALID ONLY ON THE DAY OF PRINTING
4.4.2 Site Operational Processes Baseline
AGM.002.001.0846
GROSVENOR COAL MINE Underground Operations
PLN – Grosvenor Mine Overview Plan
GRO-1435-PLN-Grosvenor Mine
Overview Plan
Original Issue Date:
13/12/2013
Version: 1 Printed: 16/06/2020
Page 30 of 48 Date of Issue: 13/12/2013
PRINTED COPIES OF THIS DOCUMENT ARE UNCONTROLLED AND DEEMED VALID ONLY ON THE DAY OF PRINTING
4.4.3 Hazard Inventory: Baseline Hazard Map
AGM.002.001.0847
GROSVENOR COAL MINE Underground Operations
PLN – Grosvenor Mine Overview Plan
GRO-1435-PLN-Grosvenor Mine
Overview Plan
Original Issue Date:
13/12/2013
Version: 1 Printed: 16/06/2020
Page 31 of 48 Date of Issue: 13/12/2013
PRINTED COPIES OF THIS DOCUMENT ARE UNCONTROLLED AND DEEMED VALID ONLY ON THE DAY OF PRINTING
4.4.4 Principle Hazards
As developed during the Operational Baseline Risk Analysis Process and defined in the Hazard Inventory,
those hazards with the potential to cause Multiple Fatalities are -
1. Fire (Surface and UG)
2. Explosion
3. Strata Failure
4. Spontaneous Combustion
5. Outburst
6. Inrush / Inundation
7. Vehicle Interactions
8. Ventilation
9. Gas Drainage
10. Gas Monitoring [Management]
11. Emergency Preparedness & Response
12. Toxic/Irrespirable atmosphere
Each of these Principle Hazards have been subject to either a detailed Bow-Tie Analysis and/or HAZOP
analysis. The functional process of the Bow-Tie Analysis is to develop-
i. Fault Tree Analysis of Causation and identification of Preventative Controls
ii. Event Tree Analysis of Consequences and identification of Mitigation / Recovery Controls
iii. Control Analysis of each group of controls to determine Control Profile [Effectiveness]
iv. Risk Analysis of each Causation and Consequence element to determine Risk Profile
[Ranking]
v. Comparison of Risk Profile vs. Control Profile to determine Acceptability of Risk
vi. Identification of New and/or Improved Controls where risk levels as regarded as unacceptable
vii. Identification of Critical Controls, assigning Owners to each critical control and defining
Monitoring Requirements and Risk Indicators for each
viii. Identification of any Specific Actions required to execute any of the control strategies, together
with action owner and completion date, finally
ix. Defining the Assurance, Status Tracking and/or Governance systems to ensure all controls
are in place and remain effective
The outcomes of these Bow-Tie analyses are contained in detail in the site portfolio of Bow-Tie Analysis
[as drawn using Bow-Tie XP] and the GTS02 compliant Baseline WRAC and Risk and Critical Control
Registers.
The functional process of the detailed HAZOPS analysis is to -
AGM.002.001.0848
GROSVENOR COAL MINE Underground Operations
PLN – Grosvenor Mine Overview Plan
GRO-1435-PLN-Grosvenor Mine
Overview Plan
Original Issue Date:
13/12/2013
Version: 1 Printed: 16/06/2020
Page 32 of 48 Date of Issue: 13/12/2013
PRINTED COPIES OF THIS DOCUMENT ARE UNCONTROLLED AND DEEMED VALID ONLY ON THE DAY OF PRINTING
i. Break the designed control system into Nodes for detailed analysis
ii. Define the required Performance Criteria for each node
iii. Identify potential Deviations from these normal operations
iv. Identify how each deviation may occur, its potential consequence and whether it presents
an Operational or Hazardous risk
v. Identification of Preventative and Mitigation/Recovery Controls for each plausible
deviation
vi. Control Analysis of each group of controls to determine Control Profile [Effectiveness]
vii. Comparison of Risk Profile vs. Control Profile to determine Acceptability of Risk
viii. Identification of New and/or Improved Controls where risk levels as regarded as
unacceptable
ix. Identification of Critical Controls, assigning Owners to each critical control and defining
Monitoring Requirements and Risk Indicators for each
x. Identification of any Specific Actions required to execute any of the control strategies,
together with action owner and completion date, finally
xi. Defining the Assurance, Status Tracking and/or Governance systems to ensure all
controls are in place and remain effective
Essentially, the HAZOP examination procedure systematically questions every part of a process Or
operation to discover qualitatively how deviations from normal operation can occur and whether further
protective measures, altered operating procedures or design changes are required. The examination
procedure uses a full description of the process which will, almost invariably, include a Process &
Instrumentation Diagram [P&ID] or equivalent, and systematically questions every part of it to discover
how deviations from the intention of the design can occur and determine whether these deviations can
give rise to hazards. The questioning is sequentially focused around a number of guide words which are
derived from method study techniques. The guide words ensure that the questions posed to test the
integrity of each part of the design will explore every conceivable way in which operation could deviate
from the design intention. Some of the causes may be so unlikely that the derived consequences will be
rejected as not being meaningful. Some of the consequences may be trivial and need be considered no
further. However, there may be some deviations with causes that are conceivable and consequences that
are potentially serious. The potential problems are then noted for remedial action.
The main advantage of this technique is its systematic thoroughness in failure case identification. The
method may be used at the design stage, when plant alterations or extensions are to be made, or applied
to an existing facility.
AGM.002.001.0849
GROSVENOR COAL MINE Underground Operations
PLN – Grosvenor Mine Overview Plan
GRO-1435-PLN-Grosvenor Mine
Overview Plan
Original Issue Date:
13/12/2013
Version: 1 Printed: 16/06/2020
Page 33 of 48 Date of Issue: 13/12/2013
PRINTED COPIES OF THIS DOCUMENT ARE UNCONTROLLED AND DEEMED VALID ONLY ON THE DAY OF PRINTING
4.5 System Integrity
To provide a level of governance and assurance over the critical controls identified by the Integrated
Operational Risk Management process, three elements together comprising the Critical Controls
Management System have been developed. These being-
1. All Critical Controls are developed in compliance with the GTS 02 Integrated Risk
Management Standard, detailed in the site Risk and Critical Control Register and
recorded in the site Enablon risk management module and/or the Ellipse System
2. All Critical Control Assurance Actions required to validate that the critical controls have
been implemented and remain effective are defined, issued, recorded and reported
against using the site Enablon risk management module and/or the Ellipse System
3. A set of System Integrity Controls developed to ensure that the Critical Control
Management System itself remains effective are also defined, issued, recorded and
reported against using the site Enablon risk management module and/or the Ellipse
System
Compliance with the requirements of the Critical Control Monitoring System is key to ensuring the
ongoing effective control of the hazards and risks across Grosvenor Mine. These system integrity controls
are captured in the underpinning HAZOP for the Management Overview Plan.
Further to this, a suite of “Quality Control Assurance” Critical Controls were also identified for an
additional level of onsite governance. These Critical Controls were identified by the General Managers
and Underground Mine Managers from across the UG operations in response to the Grasstree Mine loss
of life incidents. These Critical Controls were based on recent incident history and were determined as
fundamental risks that required an additional level of assurance built into their auditing process. The
Quality Control Assurance Critical Controls scrutinise the audits completed in areas where high probability
Critical Control failures have been identified. The addition of these assurance processes validates that
quality Critical Control audits are taking place and that the effectiveness scores given to the Critical
Controls are truly representative.
A summary of the System Integrity Controls are listed below:
AGM.002.001.0850
GROSVENOR COAL MINE Underground Operations
PLN – Grosvenor Mine Overview Plan
GRO-1435-PLN-Grosvenor Mine
Overview Plan
Original Issue Date:
13/12/2013
Version: 1 Printed: 16/06/2020
Page 34 of 48 Date of Issue: 13/12/2013
PRINTED COPIES OF THIS DOCUMENT ARE UNCONTROLLED AND DEEMED VALID ONLY ON THE DAY OF PRINTING
Node Deviation / Unwanted Event
Critical Control
Critical Control Responsibility
Critical Control Owner
Critical Control Monitoring Req'ts /
Risk Indicators
Critical Control Management System
Risk Management activities are not conducted to a standard
Formal, documented and auditable Integrated Operational Risk Management processes
HSE Supt HSE Manager Ensure that Risk Management at a functional, process or project level occurs to standard
Critical Control Management System
Change management activities are not conducted to a standard
Formal, documented Change Management processes
HSE Supt HSE Manager Ensure that PHMP Change Management occurs to standard
Critical Control Management System
Change management activities are not conducted to a standard
Formal, documented Change Management processes
HSE Supt HSE Manager Ensure that Change Management at a functional, process or project level occurs to standard
Critical Control Management System
Senior Management review of the CCMS is not conducted
Site Senior Executive Statutory and Corporate Obligations
HSE Supt HSE Manager Ensure the following is undertaken: • Systemised monitoring of Processes, Hazard Inventories and Control Effectiveness have been identified, are in place, effective, comprehensive and working. • Critical Control Assurance Actions (quality) are occurring to standard
AGM.002.001.0851
GROSVENOR COAL MINE Underground Operations
PLN – Grosvenor Mine Overview Plan
GRO-1435-PLN-Grosvenor Mine
Overview Plan
Original Issue Date:
13/12/2013
Version: 1 Printed: 16/06/2020
Page 35 of 48 Date of Issue: 13/12/2013
PRINTED COPIES OF THIS DOCUMENT ARE UNCONTROLLED AND DEEMED VALID ONLY ON THE DAY OF PRINTING
Node Deviation / Unwanted Event
Critical Control
Critical Control Responsibility
Critical Control Owner
Critical Control Monitoring Req'ts /
Risk Indicators
Critical Control Management System
Critical Control strategies are not maintained
Formal, documented and auditable Integrated Operational Risk Management processes - Identified Critical Controls that are • Specific • Measureable • Attainable • Realistic • Timely • Evaluated and • Reviewed - Formal Critical Control Monitoring System - Formal System Integrity Controls
HSE Supt HSE Manager Ensure the following is undertaken: • Systemised monitoring of Principal Hazard Risks and Controls have been identified, are in place, effective, comprehensive and working. • Critical Control Assurance Actions (quality) are occurring to standard
Critical Control Management System
Existing control strategies are NOT updated based on the findings from Incidents [at site and other places]
Formal, documented and auditable Learning from Incidents processes - Formal Critical Control Monitoring System - Formal System Integrity Controls
HSE Supt
HSE Manager Ensure Actions from incidents related to PHMP’s are being, tracked to completion, and completed to standard (quality)
AGM.002.001.0852
GROSVENOR COAL MINE Underground Operations
PLN – Grosvenor Mine Overview Plan
GRO-1435-PLN-Grosvenor Mine
Overview Plan
Original Issue Date:
13/12/2013
Version: 1 Printed: 16/06/2020
Page 36 of 48 Date of Issue: 13/12/2013
PRINTED COPIES OF THIS DOCUMENT ARE UNCONTROLLED AND DEEMED VALID ONLY ON THE DAY OF PRINTING
Node Deviation / Unwanted Event
Critical Control
Critical Control Responsibility
Critical Control Owner
Critical Control Monitoring Req'ts /
Risk Indicators
Critical Control Management System
Hard barrier controls are not installed in accordance with standards
Formal, documented and auditable Construction Standards, Installation Standards, Panel Standards - Statutory Inspections - Formal Critical Control Monitoring System - Formal System Integrity Controls
HSE Supt HSE Manager Ensure Principal hazard control installation standard checks or inspections are in place; effective, comprehensive, and working (e.g. seal construction standards, etc.)
Critical Control Management System
Early indications of increased levels of risks are not defined, identified or acted upon
Formal, documented and auditable Integrated Operational Risk Management processes - Formal Principal Hazard Management Plans, Principal Control Management Plans - Site Risk & Critical Control Register - Critical Control Monitoring System - Formal System Integrity Controls
UMM HSE Manager Ensure TARPs are relevant and utilised within scope
Critical Control Management System
Inspections are not completed to required standards
Formal, documented and Mine Inspections risk assessment and inspection SOPs
UMM HSE Manager
Ensure that Mine Inspections are completed to standard (including inspection quality, timeliness, & reporting quality).
AGM.002.001.0853
GROSVENOR COAL MINE Underground Operations
PLN – Grosvenor Mine Overview Plan
GRO-1435-PLN-Grosvenor Mine
Overview Plan
Original Issue Date:
13/12/2013
Version: 1 Printed: 16/06/2020
Page 37 of 48 Date of Issue: 13/12/2013
PRINTED COPIES OF THIS DOCUMENT ARE UNCONTROLLED AND DEEMED VALID ONLY ON THE DAY OF PRINTING
Node Deviation / Unwanted Event
Critical Control
Critical Control Responsibility
Critical Control Owner
Critical Control Monitoring Req'ts /
Risk Indicators
Critical Control Management System
Control Room does not recognise early signs of increasing risks and does not initiate timely defined response
Formal Principal Hazard Management Plans that incorporate Trigger Action Response Plans - Critical Control Monitoring System
UMM HSE Manager Ensure that TARPs are applied in-line with requirements to manage the hazard and response to alarms in Control Room are as per TARP’s
Critical Control Management System
Coal Mine Workers are unfamiliar with the requirements of the PHMP and CCMS processes
Comprehensive Training Needs Analysis - Authorised Mine Training Scheme - SceanarioTES training recording and monitoring system
UMM HSE Manager Ensure: • Personnel have received effective training on PHMP’s (Multiple Fatality Hazard Awareness) • TARP familiarisation and response training is effective and ongoing
Critical Control Management System
Assurance on the maintenance of CCMS is not maintained
Formal Critical Control Monitoring System that assigns specific accountabilities, frequencies and Technical Requirements for implementing and assuring that Critical Controls are in place and remain effectives - System Integrity controls to assure that the CCMS itself remains effective
SHE Supt
HSE Manager Ensure that Critical Control Assurance Actions are being scheduled as per PHMP’s and all changes are authorised through Change Management and/or document control.
AGM.002.001.0854
GROSVENOR COAL MINE Underground Operations
PLN – Grosvenor Mine Overview Plan
GRO-1435-PLN-Grosvenor Mine
Overview Plan
Original Issue Date:
13/12/2013
Version: 1 Printed: 16/06/2020
Page 38 of 48 Date of Issue: 13/12/2013
PRINTED COPIES OF THIS DOCUMENT ARE UNCONTROLLED AND DEEMED VALID ONLY ON THE DAY OF PRINTING
Node Deviation / Unwanted Event
Critical Control
Critical Control Responsibility
Critical Control Owner
Critical Control Monitoring Req'ts /
Risk Indicators
Critical Control Management System
Effective critical control strategies are not maintained
Formal Critical Control Monitoring System that assigns specific accountabilities, frequencies and Technical Requirements for implementing and assuring that Critical Controls are in place and remain effectives - System Integrity controls to assure that the CCMS itself remains effective
She Supt HSE Manager Ensure that Systemised monitoring of Principal Hazards controls is effective and Critical Control Actions are being completed as scheduled.
AGM.002.001.0855
GROSVENOR COAL MINE Underground Operations
PLN – Grosvenor Mine Overview Plan
GRO-1435-PLN-Grosvenor Mine
Overview Plan
Original Issue Date:
13/12/2013
Version: 1 Printed: 16/06/2020
Page 39 of 48 Date of Issue: 13/12/2013
PRINTED COPIES OF THIS DOCUMENT ARE UNCONTROLLED AND DEEMED VALID ONLY ON THE DAY OF PRINTING
5. Operational Structures
5.1 Management Structure
AGM.002.001.0856
GROSVENOR COAL MINE Underground Operations
PLN – Grosvenor Mine Overview Plan
GRO-1435-PLN-Grosvenor Mine
Overview Plan
Original Issue Date:
13/12/2013
Version: 1 Printed: 16/06/2020
Page 40 of 48 Date of Issue: 13/12/2013
PRINTED COPIES OF THIS DOCUMENT ARE UNCONTROLLED AND DEEMED VALID ONLY ON THE DAY OF PRINTING
6.2 SHMS Document Structure
AGM.002.001.0857
GROSVENOR COAL MINE Underground Operations
PLN – Grosvenor Mine Overview Plan
GRO-1435-PLN-Grosvenor Mine
Overview Plan
Original Issue Date:
13/12/2013
Version: 1 Printed: 16/06/2020
Page 41 of 48 Date of Issue: 13/12/2013
PRINTED COPIES OF THIS DOCUMENT ARE UNCONTROLLED AND DEEMED VALID ONLY ON THE DAY OF PRINTING
6. Roles and Responsibilities
Core responsibilities to ensure the ongoing effectiveness of the control strategies identified by the
Integrated Operational Risk Management and integrated into the site Safety and Health Management
System are:
Role Responsibility
All Employees & Contractors
o Comply with, and apply, standards as defined in Grosvenor systems, plans, and
procedures
o Regularly check for, and where possible control and /or report, possible hazards in
the work area
o Do not enter any area that has not been inspected
o Take action in line with alarm protocols and the Trigger Action Response Plan
o Complete Critical Control Activities to standard
o To the extent of the worker’s or person’s capability, participate in and conform to
the risk management practices of the mine
o Rectify defects to standard in timely manner where possible.
o Report defects which cannot be rectified.
o Always ensure that you know TARP levels
o Always follow your training in an Emergency
ERZ Controller o Notify the Shift Supervisor of any abnormal conditions
o Suspend mining operations if there are conditions present that contain an
unacceptable level of risk
o Ensure that gas monitoring installations are maintained at the necessary standard,
o Ensure that gas monitors are advanced in line with panel advancement/retreat,
o Report any unusual gas emissions to the Ventilation Officer.
o Act immediately to control and /or report, possible hazards in the work area
o Take action in line with alarm protocols and the Trigger Action Response Plans
o Complete Critical Control Activities to standard
o Complete Self Audits under this plan to standard
o Communicate to standard as specified in this plan
Undermanager o Complete ERZ Controller activities to standard
o Suspend mining activities if warning signs present an unacceptable level of risk
o Audit this plan per Critical Control Assurance action, and Self-audit actions
o Take action on notification of any abnormal conditions
o Audit and review monitoring controls
o Act to control and /or report, possible hazards in the work area
o Complete Critical Control Activities & Critical Control Assurance Actions under this
plan to standard
o Audit this plan as per Critical Control Assurance Activities, and Audit and
Management sections of this document
o Communicate as per Communication Section this document
UMM o Complete Critical Control Activities & Critical Control Assurance Actions under this
plan to standard
AGM.002.001.0858
GROSVENOR COAL MINE Underground Operations
PLN – Grosvenor Mine Overview Plan
GRO-1435-PLN-Grosvenor Mine
Overview Plan
Original Issue Date:
13/12/2013
Version: 1 Printed: 16/06/2020
Page 42 of 48 Date of Issue: 13/12/2013
PRINTED COPIES OF THIS DOCUMENT ARE UNCONTROLLED AND DEEMED VALID ONLY ON THE DAY OF PRINTING
o Communicate as per Communication Section this document
o Authorise changes to PHMP Critical Control Actions, Critical Control Assurance
Actions, and Critical Control Assurance Action Checklists after due regard to:
• the effectiveness of the change in controlling the Principal Hazard, and
the risk of Human Error
HS&E Manager o Communicate as per Communication Section of this document
o Complete activities as per Critical Control Assurance Actions section of this
document
Training Superintendent
o Ensure a system of training is present that trains new starters in the required areas
of Critical Control
o Refresher training conducted for permanent employee’s as per Training
o Section of this document
Site Senior Executive
o Ensure consistent ongoing management and review of this plan and to trigger,
review and authorise any changes to this document
o Ensure that this plan is implemented across the operation
o Authorise changes to PHMP Critical Control Actions, Critical Control Assurance
Actions, and Critical Control Assurance Action Checklists after due regard to the
effectiveness of the change in controlling the Principal Hazard
ROLE RESPONSIBILITIES
7. Resources Required
In addition to the general provision of sufficient resources to enable the site Safety and Health
Management System to be effective, Grosvenor Mine commits to provide the following specific resources:
RESOURCE
• Resources (time, competency and/or experience) necessary to complete Critical Control
Assurance Actions to the nominated standard (quality)
• SSE visual felt leadership in the completion of Critical Control Audits to the nominated standard
(quality)
8. Trigger Action Response Plans
No specific TARP’s have been identified for this plan.
9. Communication
Information pertaining to this plan shall be communicated to all coal mine workers at Grosvenor mine in
accordance with the HSE Communication System. PERSON RESPONSIBLE DE
10. Training
Generic training requirements are specified in the Mine Training Scheme with basic understanding of the
SHMS incorporated in this scheme and delivered through Induction Programs/Refreshers.
AGM.002.001.0859
GROSVENOR COAL MINE Underground Operations
PLN – Grosvenor Mine Overview Plan
GRO-1435-PLN-Grosvenor Mine
Overview Plan
Original Issue Date:
13/12/2013
Version: 1 Printed: 16/06/2020
Page 43 of 48 Date of Issue: 13/12/2013
PRINTED COPIES OF THIS DOCUMENT ARE UNCONTROLLED AND DEEMED VALID ONLY ON THE DAY OF PRINTING
Training modules specific to this plan are -NNEL GROU
Module Description
Fre
qu
en
cy
Personnel Group
Op
era
tors
&
Tra
de
sm
en
Cre
w
Su
pe
rvis
ors
an
d
Co
ord
ina
tors
P
rod
uc
tio
n
Sta
ff
Te
ch
nic
al
Sta
ff
Oth
er
Sta
ff
Pe
rso
nn
el a
nd
Co
ntr
ac
tors
Basic Principal Hazard Management System
Introduction and basic explanation of Integrated Operational Risk Management process, the Safety and Health Management System, the SHMS Mine Overview Plan, all Principal Hazard Management Plans and the Critical Controls Management System
Induction & Refresher
11. Corrective Action
Corrective Actions/Defects will be reported using the Hazard, Defect and Incident Management System
and will be recorded and managed in Enablon.
12. Audit and Management Review
The SSE shall ensure that the Critical Control audits detailed in the Critical Control Management system
integrated with Enablon, including the System Integrity controls, are completed at the designated times.
The Plan shall be subject to a program of auditing to determine whether the mine activities conform to the
Plan, and whether the arrangements in the Plan are adequate, implemented and effective. This program
shall include:
• Internal critical control auditing on a yearly basis, and
• External auditing every 3 years (e.g. OMS, OCA and GTS auditing).
• The audit findings shall be acted upon through the corrective action process and review
mechanisms.
• Internal and external audits of the Plan will be identified in the mine Audit Schedule.
In undertaking any review the Document Owner must be cognitive that the PHMS is an integrated
system. Subsequent revisions to this document or system should only be done with a defined
understanding of the basis and structure of the entire “as developed” system.
AGM.002.001.0860
GROSVENOR COAL MINE Underground Operations
PLN – Grosvenor Mine Overview Plan
GRO-1435-PLN-Grosvenor Mine
Overview Plan
Original Issue Date:
13/12/2013
Version: 1 Printed: 16/06/2020
Page 44 of 48 Date of Issue: 13/12/2013
PRINTED COPIES OF THIS DOCUMENT ARE UNCONTROLLED AND DEEMED VALID ONLY ON THE DAY OF PRINTING
13. Records
Legislation requires that the following records related to the Integrated Operational Risk Management
process, the Safety and Health Management System, the SHMS Mine Overview Plan, all Principal
Hazard Management Plans and the Critical Controls Management System be maintained and kept at the
mine site:
o Any risk assessment while ever the hazard is present at the mine
Additionally the following records are to be kept:
o Hazard, Defect and Incident Reports
o Critical Control audit findings
14. Legislation
The Integrated Operational Risk Management process, the Safety and Health Management System, the
SHMS Mine Overview Plan, all Principal Hazard Management Plans and the Critical Controls
Management System have been developed in accordance with the requirements of the Coal Mining
Safety and Health Act (CMSHA) 1999, and the Coal Mining Safety and Health Regulation 2001.
AGM.002.001.0861
GROSVENOR COAL MINE Underground Operations
PLN – Grosvenor Mine Overview Plan
GRO-1435-PLN-Grosvenor Mine
Overview Plan
Original Issue Date:
13/12/2013
Version: 1 Printed: 16/06/2020
Page 45 of 48 Date of Issue: 13/12/2013
PRINTED COPIES OF THIS DOCUMENT ARE UNCONTROLLED AND DEEMED VALID ONLY ON THE DAY OF PRINTING
15. Appendix I Control Effectiveness Matrix
Control Type 6 Elimination: the complete elimination of the hazard by design
5 Substitution / Minimise: replacing the hazard, material or
process with a less hazardous one, or significantly the magnitude
of the hazard or material so consequences are greatly reduced
4 Engineering: incorporate controls into the design or redesign
the equipment or work process
3 Separation: placing a physical barrier on the hazard by
guarding or enclosing it
2 Administrative / Procedural: providing control such as
training and procedures
1 Personal Protective Equipment: use of appropriate and
properly fitted PPE where other controls are not practical
Control Quality
Co
ntr
ol T
yp
e
A >90%
B 60-
90%
C 30-
60%
D <30%
6 Elimination
5 Substitution
4 Engineering
3 Separation
2 Administrative
1 PPE
Control Quality
• Reliability: will the control operate on demand as intended
• Survivability: will the control remain unimpaired during the unwanted event
• Availability: will the control be available to perform its function
The Control Effectiveness method provides four percentage categories that express an overall opinion of reliability, survivability and availability. A- 90% or more of the time the control will operate, survive and
function as required B- 60 to 90% of the time the control will operate, survive and
function as required C- 30 to 60% the control will operate, survive and function as
required D- Less than 30% of the time the control will operate, survive
and function as required
Control Effectiveness A GREEN control rating indicates that the control should be effective. This is the desired effectiveness of every control but the matrix indicates that even a 90% quality Administrative or PPE control is not considered to be an effective control. The intent of this design is to promote the development and application of harder controls such as Engineering or Substitution A YELLOW control rating indicates a satisfactory control that could be improved to a green either through improving its Quality or by changing its Type. Yellow controls should be improved first if total control effectiveness for an unwanted event is inadequate RED control rating indicates that the control does not contribute effectively to reducing the risk of an unwanted event. The CER method provides a rating for each control. Overall Event Control Effectiveness is a summary of the total effectiveness of all controls. To establish this overall status the set of controls and their CER ratings should be examined. The decision that the set is adequate can be tested by the rule :- There should be two GREEN preventative controls for every cause of a priority unwanted event
AGM.002.001.0862
GROSVENOR COAL MINE Underground Operations
PLN – Grosvenor Mine Overview Plan
GRO-1435-PLN-Grosvenor Mine
Overview Plan
Original Issue Date:
13/12/2013
Version: 1 Printed: 16/06/2020
Page 46 of 48 Date of Issue: 13/12/2013
PRINTED COPIES OF THIS DOCUMENT ARE UNCONTROLLED AND DEEMED VALID ONLY ON THE DAY OF PRINTING
16. Appendix II Business Unit Risk Matrix
AGM.002.001.0863
GROSVENOR COAL MINE Underground Operations
PLN – Grosvenor Mine Overview Plan
GRO-1435-PLN-Grosvenor Mine
Overview Plan
Original Issue Date:
13/12/2013
Version: 1 Printed: 16/06/2020
Page 47 of 48 Date of Issue: 13/12/2013
PRINTED COPIES OF THIS DOCUMENT ARE UNCONTROLLED AND DEEMED VALID ONLY ON THE DAY OF PRINTING
BUSINESS UNIT RISK MATRIX
CONSEQUENCE (Where an event has more than one ‘Consequence Type’, choose the ‘Consequence Type’ with the highest rating)
Consequence Type 1 - Insignificant 2 - Minor 3 - Moderate 4 - High 5 - Major
Projects
Schedule Less than 1% impact on overall project timeline
May result in overall project timeline overrun equal to or more than 1% and less than 3%
May result in overall project timeline overrun of equal to or more than 3% and less than 10%
May result in overall project timeline overrun of equal to or more than 10% and less than 30%
May result in overall project timeline overrun of 30% or more
Cost Less than 1% impact on the overall budget of the project
May result in overall project budget overrun equal to or more than 1% and less than 3%
May result in overall project budget overrun of equal to or more than 3% and less than 10%
May result in overall project budget overrun of equal to or more than 10% and less than 30%
May result in overall project budget overrun of 30% or more
Quality and Technical Integrity
No significant impact on quality of deliverables or effect on production
Quality issues that can be addressed prior to handover or could affect production by more than 1% and less than 3%
Quality issues that can be addressed during ramp-up or could affect production by more than 3% and less than 10%
Quality issues that require significant intervention to maintain performance or could affect production by more than 10% and less than 30%
Quality issues that require significant intervention to achieve performance or could affect production by 30% or more
Financial (Use PDBI Values as guidance)
No disruption to operation / Less than 1% loss of budgeted operating profit and listed assets
Brief disruption to operation / 1 % to less than 3% loss of budgeted operating profit and listed assets
Partial shutdown of operation / 3 % to less than 10% loss of budgeted operating profit and listed assets
Partial loss of operation / 10% to less than 30% loss of budgeted operating profit and listed assets
Substantial or total loss of operation / 30% or higer loss of budgeted operating profit and listed assets
Safety First aid case Medical treatment case Lost time injury Permanent disability or single fatality
Numerous permanent disabilities or multiple fatalities
Occupational Health Exposure to health hazard resulting in temporary discomfort
Exposure to health hazard resulting in symptoms requiring medical intervention and full recovery (no lost time)
Exposure to health hazards/ agents (over the OEL) resulting in reversible impact on health (with lost time) or permanent change with no disability or loss of quality of life
Exposure to health hazards/ agents (significantly over the OEL) resulting in irreversible impact on health with loss of quality of life or single fatality
Exposure to health hazards/ agents (significantly over the OEL) resulting in irreversible impact on health with loss of quality of life of a numerous group/population or multiple fatalities
Environment Lasting days or less; limited to small area (metres); receptor of low significance/ sensitivity (industrial area)
Lasting weeks; reduced area (hundreds of metres); no environmentally sensitive species/ habitat)
Lasting months; impact on an extended area (kilometres); area with some environmental sensitivity (scarce/ valuable environment).
Lasting years; impact on sub-basin; environmentally sensitive environment/ receptor (endangerous species/ habitats)
Permanent impact; affects a whole basin or region; highly sensitive environment (endangerous species, wetlands, protected habitats)
Legal & Regulatory Technical non-compliance. No warning received; no regulatory reporting required
Breach of regulatory requirements; report/involvement of authority. Attracts administrative fine
Minor breach of law; report/investigation by authority. Attracts compensation/ penalties/ enforcement action
Breach of the law; may attract criminal prosecution, penalties/ enforcement action. Individual licence temporarily revoked
Significant breach of the law. Individual or company law suits; permit to operate substantially modified or withdrawn
Social / Communities Minor disturbance of culture/ social structures
Some impacts on local population, mostly repairable. Single stakeholder complaint in reporting period
On going social issues. Isolated complaints from community members/ stakeholders
Significant social impacts. Organized community protests threatening continuity of operations
Major widespread social impacts. Community reaction affecting business continuity. “License to operate” under jeopardy
Reputation Minor impact; awareness/ concern from specific individuals
Limited impact; concern/ complaints from certain groups/ organizations (e.g. NGOs)period
Local impact; public concern/ adverse publicity localised within neighbouring communities
Suspected reputational damage; local/ regional public concern and reactions
Noticeable reputational damage; national/ international public attention and repercussions
AGM.002.001.0864
GROSVENOR COAL MINE Underground Operations
PLN – Grosvenor Mine Overview Plan
GRO-1435-PLN-Grosvenor Mine
Overview Plan
Original Issue Date:
13/12/2013
Version: 1 Printed: 16/06/2020
Page 48 of 48 Date of Issue: 13/12/2013
PRINTED COPIES OF THIS DOCUMENT ARE UNCONTROLLED AND DEEMED VALID ONLY ON THE DAY OF PRINTING
CONSEQUENCE
1 - Insignificant 2 - Minor 3 - Moderate 4 - High 5 - Major
LIKELIHOOD RISK RATING
5 Almost Certain 1 year
The unwanted event has occurred frequently; occurs in order of one or more times per year & is likely to reoccur within 1 year
11 (Medium)
16 (Significant)
20 (Significant)
23 (High)
25 (High)
4 - Likely 3 years
The unwanted event has occurred infrequently; occurs in order of less than once per year & is likely to reoccur within 3 years
7 (Medium)
12 (Medium)
17 (Significant)
21 (High)
24 (High)
3 - Possible 10 years
The unwanted event has happened in the business at some time; or could happen within 10 years
4 (Low)
8 (Medium)
13 (Significant)
18 (Significant)
22 (High)
2 – Unlikely 30 years
The unwanted event has happened in the business at some time; or could happen within 30 years
2 (Low)
5 (Low)
9 (Medium)
14 (Significant)
19 (Significant)
1 - Rare >30 years
The unwanted event has never been known to occur in the business; or it is highly unlikely that it will occur within 30 years
1 (Low)
3 (Low)
6 (Medium)
10 (Medium)
15 (Significant)
AGM.002.001.0865