hospital electrical systems preliminary site visit rpt rev2

Upload: shola-daley

Post on 06-Feb-2018

216 views

Category:

Documents


1 download

TRANSCRIPT

  • 7/21/2019 Hospital Electrical Systems Preliminary Site Visit Rpt Rev2

    1/23

    SITE VISIT REPORT & RECOMMENDATIONS DOCUMENT

    ELECTRICAL SYSTEMS UPGRADE

    Job # NG-23-1

    CLIENT: DEUX PROJECTS

    1 10thApril 13 First revision Complete with Pictures AI OAD

    0 7TH

    April 13 Preliminary draft document without pictures AI OAD

    REV DATE DESCRIPTION ORIG APPROVALS

    Document NumberProject No. Deliv. Code Doc. Type Seq. Num. Rev.

    IP-DP-01 1000 5040 001 1

  • 7/21/2019 Hospital Electrical Systems Preliminary Site Visit Rpt Rev2

    2/23

    SITE VISIT REPORT & RECOMMENDATIONS DOCUMENTELECTRICAL SYSTEMS UPGRADE

    Page 2 of 23 08/05/13

    Table of Contents

    0.0 BACKGROUND

    1.0 EXISTING INFRASTRUCTURE

    2.0 FUNCTIONAL/SAFETY COMPLIANCE ISSUES

    3.0 LOAD SUMMARY

    4.0 RECOMMENDATIONS

    5.0 IPGRUPPS EXECUTIVE COMPANY SUMMARY

  • 7/21/2019 Hospital Electrical Systems Preliminary Site Visit Rpt Rev2

    3/23

    SITE VISIT REPORT & RECOMMENDATIONS DOCUMENTELECTRICAL SYSTEMS UPGRADE

    Page 3 of 23 08/05/13

    0.0 BACKGROUND

    Ongoing upgrades/new infrastructure works at the specialist Hospital facility EKU over the last twoyears have added and upgraded several building facilities. To achieve the expected significantbenefits from this investment the overall electrical utility systems will require substantial upgradesand modifications.

    IPgrupp Engineering/NEGO Construction with the support of specialist Hospital EKU personnelhave conducted a site review of the existing electrical utilities ,this preliminary report has beendeveloped to highlight key functional and safety concerns arising from the inspection and provideearly recommendations for system upgrade with summary schedule of works to achieve same..

    The report begins with a technical overview of the existing electrical infrastructure and theoperational condition as a prelude to the identification of functional and safety compliance issueswe have identified, we conclude with recommendations to resolve these issues and bring overallsystem into compliance.

  • 7/21/2019 Hospital Electrical Systems Preliminary Site Visit Rpt Rev2

    4/23

    SITE VISIT REPORT & RECOMMENDATIONS DOCUMENTELECTRICAL SYSTEMS UPGRADE

    Page 4 of 23 08/05/13

    1.0 EXISTING INFRASTRUCTURE

    1.1 PHCN Power In-Take and Switching System

    Power from the PHCN utility company feeds into the EKU specialist hospital facility via11KV/415V 500KVA substation. The 11KV/415V substation is newly installed underthis project and is located close to the previously shared community sub-station withinthe hospital grounds.

    Fig 1 PHCN Intake HV/LV Substation

    The transformer unit is rated at 500KVA 11/0.4KV ONAN manufactured by ABB whilethe Feeder Pillar LV Distribution panel is rated for 600Amps

  • 7/21/2019 Hospital Electrical Systems Preliminary Site Visit Rpt Rev2

    5/23

    SITE VISIT REPORT & RECOMMENDATIONS DOCUMENTELECTRICAL SYSTEMS UPGRADE

    Page 5 of 23 08/05/13

    Fig 2 HV-LV 500KVA Transformer UnitThe Output from the 600Amp Feeder Pillar is routed thru a 4core x 95mmsq

    PVC/SWA/PVC copper cable to an over-head Aluminum 4 core x 100mmsq conductorline which feeds the Low Voltage power from this PHCN in-take substation to thefacility main power house/switching sub-station.

    Fig 3 LV O/Head Line from PHCN Intake S/Station Fig 4 PVC/SWA/PVC cable connection O/Head Lineto Main Power Plant Isolator

    A 4core x 120mmsq Flex Cable continues from where the overhead Aluminum lineends to feed power thru to a main isolator switch the ratings for which we were unableto determine during our survey.

    The isolator switch then feeds into a PHCN-to-Generator change-over switchassembly (SW1 fig 5 below)

    Transformer

    11/

    0.415KV Feeder Pillar

    600A

    Change-over

    SW1

    11KV Overhead Line Supply From PHCN 2.5MVA

    Substation 11KV Overhead Line Feeder to Power Station

    120mmsq Aluminum Conductor Cable

    3core x 35mmsq

    XLPE HV Cable 4core x 95mmsq

    PVC/SWA/PVCCable

    4core x 120mmsq

    PVC/SWA/PVCCable

    Main

    Isolator

    G

    Generator

    Change-over

    SW2

    G

    Generator

    Fig 5 Overall PHCN In-take one-line schematic

  • 7/21/2019 Hospital Electrical Systems Preliminary Site Visit Rpt Rev2

    6/23

    SITE VISIT REPORT & RECOMMENDATIONS DOCUMENTELECTRICAL SYSTEMS UPGRADE

    Page 6 of 23 08/05/13

    The PHCN-to-Generator change over switch #1 is cascaded to another change 0verswitch #2 which serves to enable selection between the outside functional 500KVAgenerator and the now derelict 230KVA CAT 230 V8 generator. Hence the changeover switch now functions as an isolator for the 500KVA outside generator only.

    Change-Over switch #2 enables

    selection between the functional

    500KVA generator and now

    derelict 230KVA CAT generator

    (shown beside the change-over

    switch)

    Fig 6 Change-over switch #2 and faulty 230KVA CAT Generator

    Main Change-Over switch #1

    enables selection between the

    PHCN Supply and selected

    generator from Change-Over

    switch #2 (now confined 500KVA

    generator only as the 230KVAgenerator is faulty

    Fig 7 Change-Over Switch #1 PHCN-Generator Supply

    Change-over

    SW1

    G

    230KVA

    Change-over

    SW2

    G

    500KVA

    Faulty

    PHCN

    Supply

    MainIsolator

    Fig 8 Change-Over Switch #1 and # 2 Schematic

  • 7/21/2019 Hospital Electrical Systems Preliminary Site Visit Rpt Rev2

    7/23

    SITE VISIT REPORT & RECOMMENDATIONS DOCUMENTELECTRICAL SYSTEMS UPGRADE

    Page 7 of 23 08/05/13

    Output from changeover switch # 1 is fed thru a 4core 120mmsq PVS/SWA/PVCcopper cable to a secondary internal overhead aluminum conductor system, utilizingconcrete poles slightly shorter than those used for transferring power from the PHCNs/station to the main facility substation.

    Secondary Overhead distribution

    concrete pole and PVC sheated

    100mmsq Aluminum Conducted

    Power from PHCN and the main

    500KVA Generator is distributed

    to the various hospital load

    centers thru this overhead

    system

    PHCN Over Head LV feeder from

    Transformer Sub-Station close

    to the main gate

    Fig 9 Primary and Secondary Power Distr. Overhead Systems

    1.2 Local Power Generation System and Ancillary Equipment

    Power Plant inspection determined that the facility designed Power generation systemhad previously consisted of two Diesel driven CATERPILLAR Generators CAT 150

    and CAT 230 with KVA ratings of 150KVA and 230KVA respectively. Over the yearsas these fell into disrepair a 350KVA PERKINS, 27KVA WOERMANN, 500KA LISTERand a 15KVA unbranded Generator have been added to the Power pool.

    As at time of inspection only the 500KVA and the 15KVA generators where in afunctional state the others all being at different stages of disrepair or completelyscrapped out.

  • 7/21/2019 Hospital Electrical Systems Preliminary Site Visit Rpt Rev2

    8/23

    SITE VISIT REPORT & RECOMMENDATIONS DOCUMENTELECTRICAL SYSTEMS UPGRADE

    Page 8 of 23 08/05/13

    The Power plant equipment interconnect feeder and control cabling has beenrepeatedly altered, decommissioned and re-routed so extensively in variance to allapplicable safety or functional compliance code/regulatory requirements

    500KVA Generator currently in

    service

    Fig 10

    150KVA CAT 150 Generator in

    state of disrepair (cracked engine

    block)

    Fig 11

    350KVA PERKINS

    Generator requiring

    general overhauling

    repairs works

    Far right is the

    27KVA WOERMANN

    Generator shown with

    a missing alternator

    Fig 12

  • 7/21/2019 Hospital Electrical Systems Preliminary Site Visit Rpt Rev2

    9/23

    SITE VISIT REPORT & RECOMMENDATIONS DOCUMENTELECTRICAL SYSTEMS UPGRADE

    Page 9 of 23 08/05/13

    1.3 Power Distribution to Hospital Load Centers

    The main power distribution system for this facility is a low voltage overhead linesystem routed to all the main load centers/buildings within the complex. Service 4corealuminum condor cables are generally used to tap power from the nearest overheadpole to each building

    Service cable used to tap power

    from overhead power distribution

    system to each building as

    required.

    Fig 12 Showing service cables used to Tap Power into Buildings

    The emergency power system consist of the 15KVA generator and a distribution panelwith outgoing feeders directly to identified critical loads/facilities. The inspectionrevealed that the outgoing feeders and the distribution panel had been re-workedrepeatedly to an extent that the safety and functionality had been significantlycompromised .

    Fig 13 Showing 15KVA Generator and Emergency Feeder Panel

  • 7/21/2019 Hospital Electrical Systems Preliminary Site Visit Rpt Rev2

    10/23

    SITE VISIT REPORT & RECOMMENDATIONS DOCUMENTELECTRICAL SYSTEMS UPGRADE

    Page 10 of 23 08/05/13

    500 KVA Transformer

    11/

    0.415KV Feeder Pillar

    600A

    11KV Overhead Line Supply FromPHCN 2.5MVA

    Substation

    11KV Overhead Line Feeder to Power Station120mmsq AluminumConductor Cable

    3core x 35mmsq

    XLPE HV Cable 4core x 95mmsq

    PVC/SWA/PVC

    Cable

    4core x 120mmsq

    PVC/SWA/PVC

    Cable

    Main

    Isolator

    G

    500KVA

    Change-over

    SW2

    G

    230KVA

    PHCNSupply

    PHCN Isolator

    SW

    Faulty-But still

    Connected

    Change-over

    SW1

    LowVo

    ltageOverheadLine

    InternalDistributionsystem

    G

    15KVA

    Change-over

    SW3

    Emergency supply to selected wards and theater

    Directcablingtoloads

    Viaservicecables

    4corex120mmsq

    PVC/SWA/PVCCable

    G

    150KVA

    Faulty-But still

    Connected

    Change-overSW4

    Safety/

    Compliance

    Issue 1

    Safety/

    Compliance

    Issue 2

    Fig 14 Showing Overall Power Generation and Distribution System

  • 7/21/2019 Hospital Electrical Systems Preliminary Site Visit Rpt Rev2

    11/23

    SITE VISIT REPORT & RECOMMENDATIONS DOCUMENTELECTRICAL SYSTEMS UPGRADE

    Page 11 of 23 08/05/13

    2.0 FUNCTIONAL/SAFETY COMPLIANCE ISSUES

    The technical audit on the electrical systems for the facility revealed several non-compliance and safety issues that should be addressed in any future upgrade program

    It was noted that the interconnecting power cabling between generators , change-overand isolator switches has been altered/added and was exposed in several instances .

    Control Panels for several of the generators are derelict and need to be decommissioned

    as live cabling is still routed thru as part of the generator switching system.

    Fig 15 Control Panel and Change-Over Switch Cabling in Plant Room

    All switch operations are performed manually with no safety inter-lock systems in placehence only experienced and plant specific trained personnel can perform switchingsafely. Accidental power feedback to generating systems remains a substantial risk withthe current operations.

  • 7/21/2019 Hospital Electrical Systems Preliminary Site Visit Rpt Rev2

    12/23

    SITE VISIT REPORT & RECOMMENDATIONS DOCUMENTELECTRICAL SYSTEMS UPGRADE

    Page 12 of 23 08/05/13

    3.0 PROJECTED LOAD SUMMARY

    S/No Gate House Load Description QTY Watts Voltage Current W VA

    1 13amps Ring Main 5 240 6 1440 1800

    2 External Lights 20 60 240 1200 1500

    3 Ceiling Fan 1 400 240 400 500

    240 0 0

    TOTAL 3040 3800

    S/No Waiting room Load Description QTY Watts Voltage Current W VA

    1 13amps Ring Main 15 240 18 4320 5400

    2 External Lights 20 60 240 1200 1500

    3 Ceiling Fan 5 400 240 2000 2500

    4 Airconditioners 4 1110 240 4440 5550

    5 Internal Lights 13 36 240 468 585

    6 Emergency Lights 1 40 240 40 50

    240 0 0

    TOTAL 12468 15585

    S/No Maternity Ward Load Description QTY Watts Voltage Current W VA

    1 13amps Ring Main 100 240 120 28800 36000

    2 External Lights 18 60 240 1080 1350

    3 Ceiling Fan 20 400 240 8000 10000

    4 Airconditioners 9 1110 240 9990 12487.

    5 Internal Lights 89 36 240 3204 4005

    6 Emergency Lights 3 40 240 120 150

    7 Water Heater 3 1000 240 3000 3750

    8 Expeller Fan 6 200 240 1200 1500

    9 Bed Lights 28 12 240 336 420

    240 0 0

    TOTAL 55730 69662.

  • 7/21/2019 Hospital Electrical Systems Preliminary Site Visit Rpt Rev2

    13/23

    SITE VISIT REPORT & RECOMMENDATIONS DOCUMENTELECTRICAL SYSTEMS UPGRADE

    Page 13 of 23 08/05/13

    S/No Family Medicine Load Description QTY Watts Voltage Current W VA

    1 13amps Ring Main 5 240 6 1440 1800

    2 External Lights 4 60 240 240 300

    3 Ceiling Fan 2 400 240 800 1000

    4 Airconditioners 2 1110 240 2220 2775

    5 Internal Lights 7 36 240 252 315

    6 Emergency Lights 0 40 240 0 0

    7 Water Heater 0 1000 240 0 0

    8 Expeller Fan 0 200 240 0 0

    TOTAL 4952 6190

    S/No Children's Ward Load Description QTY Watts Voltage Current W VA

    1 13amps Ring Main 114 240 136.8 32832 41040

    2 External Lights 21 60 240 1260 1575

    3 Ceiling Fan 18 400 240 7200 9000

    4 Airconditioners 6 1110 240 6660 8325

    5 Internal Lights 70 36 240 2520 3150

    6 Emergency Lights 6 40 240 240 300

    7 Water Heater 1 1000 240 1000 1250

    8 Expeller Fan 18 200 240 3600 4500

    9 Bed Lights 10 12 240 120 15010 Hand Dryer 1 600 240 600 750

    11 Cooker Unit 1 240 32 7680 9600

    TOTAL 63712 79640

    S/No Private Ward Load Description QTY Watts Voltage Current W VA

    1 13amps Ring Main 94 240 112.8 27072 33840

    2 External Lights 16 60 240 960 1200

    3 Ceiling Fan 19 400 240 7600 9500

    4 Airconditioners 18 1110 240 19980 24975

    5 Internal Lights 90 36 240 3240 4050

    6 Emergency Lights 9 40 240 360 450

    7 Water Heater 1 1000 240 1000 1250

    8 Expeller Fan 0 200 240 0 0

    9 Bed Lights 33 12 240 396 495

    10 Hand Dryer 0 600 240 0 0

    TOTAL 60608 75760

  • 7/21/2019 Hospital Electrical Systems Preliminary Site Visit Rpt Rev2

    14/23

    SITE VISIT REPORT & RECOMMENDATIONS DOCUMENTELECTRICAL SYSTEMS UPGRADE

    Page 14 of 23 08/05/13

    S/No Men's Ward Load Description QTY Watts Voltage Current W VA

    1 13amps Ring Main 86 240 103.2 24768 30960

    2 External Lights 21 60 240 1260 1575

    3 Ceiling Fan 20 400 240 8000 10000

    4 Airconditioners 4 1110 240 4440 5550

    5 Internal Lights 77 36 240 2772 3465

    6 Emergency Lights 5 40 240 200 250

    7 Water Heater 1 1000 240 1000 1250

    8 Expeller Fan 4 200 240 800 1000

    9 Bed Lights 33 12 240 396 495

    10 Hand Drye 1 600 240 600 750

    11 Cooker Unit 1 240 32 7680 9600

    TOTAL 51916 64895

    S/No Women's Ward Load Description QTY Watts Voltage Current W VA

    1 13amps Ring Main 97 240 116.4 27936 34920

    2 External Lights 21 60 240 1260 1575

    3 Ceiling Fan 24 400 240 9600 12000

    4 Airconditioners 5 1110 240 5550 6937.5

    5 Internal Lights 77 36 240 2772 3465

    6 Emergency Lights 6 40 240 240 300

    7 Water Heater 3 1000 240 3000 3750

    8 Expeller Fan 2 200 240 400 500

    9 Bed Lights 40 12 240 480 600

    10 Hand Dryer 1 600 240 600 750

    11 Cooker Unit 1 240 32 7680 9600

    TOTAL 59518 74397.5

    S/No Store Load Description QTY Watts Voltage Current W VA

    1 13amps Ring Main 6 240 7.2 1728 2160

    2 External Lights 6 60 240 360 450

    3 Ceiling Fan 3 400 240 1200 1500

    4 Airconditioners 3 1110 240 3330 4162.5

    5 Internal Lights 10 36 240 360 450

    TOTAL 6978 8722.5

  • 7/21/2019 Hospital Electrical Systems Preliminary Site Visit Rpt Rev2

    15/23

    SITE VISIT REPORT & RECOMMENDATIONS DOCUMENTELECTRICAL SYSTEMS UPGRADE

    Page 15 of 23 08/05/13

    S/No Canteen Load Description QTY Watts Voltage Current W VA

    1 13amps Ring Main 33 240 39.6 9504 11880

    2 External Lights 6 60 240 360 450

    3 Ceiling Fan 4 400 240 1600 2000

    4 Airconditioners 4 1110 240 4440 5550

    5 Internal Lights 56 36 240 2016 2520

    6 Emergency Lights 4 40 240 160 200

    7 Water Heater 1 1000 240 1000 1250

    8 Expeller Fan 2 200 240 400 500

    9 Bed Lights 0 12 240 0 0

    10 Hand Dryer 0 600 240 0 0

    11 Cooker Unit 0 240 0 0 0

    TOTAL 19480 24350

    S/No Isolation Ward Load Description QTY Watts Voltage Current W VA

    1 13amps Ring Main 43 240 51.6 12384 15480

    2 External Lights 12 60 240 720 900

    3 Ceiling Fan 10 400 240 4000 5000

    4 Airconditioners 13 1110 240 14430 18037.5

    5 Internal Lights 49 36 240 1764 2205

    6 Emergency Lights 1 40 240 40 50

    7 Water Heater 0 1000 240 0 0

    8 Expeller Fan 0 200 240 0 0

    9 Bed Lights 0 12 240 0 0

    10 Hand Dryer 0 600 240 0 0

    11 Cooker Unit 1 240 32 7680 9600

    TOTAL 41018 51272.5

    S/No Walkway Load Description QTY Watts Voltage Current W VA

    1 13amps Ring Main 0 240 0 0 0

    2 External Lights 59 60 240 3540 4425

    3 Ceiling Fan 0 400 240 0 0

    TOTAL 3540 4425

  • 7/21/2019 Hospital Electrical Systems Preliminary Site Visit Rpt Rev2

    16/23

    SITE VISIT REPORT & RECOMMENDATIONS DOCUMENTELECTRICAL SYSTEMS UPGRADE

    Page 16 of 23 08/05/13

    S/No

    A & E Ward Load

    Description QTY Watts Voltage Current W VA

    1 13amps Ring Main 186 240 223.2 53568 66960

    2 External Lights 16 60 240 960 1200

    3 Ceiling Fan 40 400 240 16000 20000

    4 Airconditioners 31 1110 240 34410 43012.5

    5 Internal Lights 158 36 240 5688 7110

    6 Emergency Lights 6 40 240 240 300

    7 Water Heater 5 1000 240 5000 6250

    8 Expeller Fan 17 200 240 3400 4250

    9 Bed Lights 20 12 240 240 300

    10 Hand Dryer 0 600 240 0 0

    11 Cooker Unit 1 240 32 7680 9600

    TOTAL 127186 158982.5

    S/No Luandry Load Description QTY Watts Voltage Current W VA

    1 13amps Ring Main 25 240 30 7200 9000

    2 External Lights 11 60 240 660 825

    3 Ceiling Fan 6 400 240 2400 3000

    4 Airconditioners 6 1110 240 6660 8325

    5 Internal Lights 26 36 240 936 1170

    6 Emergency Lights 0 40 240 0 0

    7 Water Heater 4 1000 240 4000 5000

    8 Expeller Fan 0 200 240 0 0

    9 Bed Lights 0 12 240 0 0

    10 Hand Dryer 0 600 240 0 0

    11 Cooker Unit 1 240 32 7680 9600

    TOTAL 29536 36920

    S/No Walkway Load Description QTY Watts Voltage Current W VA

    1 13amps Ring Main 4 240 4.8 1152 14402 External Lights 4 60 240 240 300

    3 Ceiling Fan 1 400 240 400 500

    4 Airconditioners 1 1110 240 1110 1387.5

    5 Internal Lights 6 36 240 216 270

    TOTAL 3118 3897.5

  • 7/21/2019 Hospital Electrical Systems Preliminary Site Visit Rpt Rev2

    17/23

    SITE VISIT REPORT & RECOMMENDATIONS DOCUMENTELECTRICAL SYSTEMS UPGRADE

    Page 17 of 23 08/05/13

    S/No

    Admin Building Load

    Description QTY Watts Voltage Current W VA

    1 13amps Ring Main 125 240 150 36000 45000

    2 External Lights 25 60 240 1500 1875

    3 Ceiling Fan 70 400 240 28000 35000

    4 Airconditioners 25 1110 240 27750 34687.5

    5 Internal Lights 100 36 240 3600 4500

    6 Emergency Lights 5 40 240 200 250

    7 Water Heater 10 1000 240 10000 12500

    8 Expeller Fan 10 200 240 2000 2500

    9 Bed Lights 0 12 240 0 0

    10 Hand Dryer 5 600 240 3000 3750

    11 Cooker Unit 0 240 0 0 0

    TOTAL 112050 140062.5

    S/No Building Description W VA

    1 Gate House Load Description 3040 3800

    2 Waiting Room 12468 15585

    3 Maternity Ward 55730 69662.5

    4 Family Medicine 4952 6190

    5 Children's Ward 63712 79640

    6 Private Ward 60608 75760

    7 Men's Ward 51916 64895

    8 Women's Ward 59518 74397.5

    9 Canteen 19480 24350

    10 Store 6978 8722.5

    11 Isolation Ward 41018 51272.5

    12 A& E Ward 127186 158982.5

    13 Luandry 29536 36920

    14 Walkway 3540 4425

    15 Prayer Room 3118 3897.5

    16 Admin Building 112050 140062.5

    TOTAL 654850 818562.5

    TOTAL KVA 818.5625 KVA

    TOTAL KVA AT 70%

    DIVERSITY 573 KVA

  • 7/21/2019 Hospital Electrical Systems Preliminary Site Visit Rpt Rev2

    18/23

    SITE VISIT REPORT & RECOMMENDATIONS DOCUMENTELECTRICAL SYSTEMS UPGRADE

    Page 18 of 23 08/05/13

    4.0 RECOMMENDATIONS

    The Schematic below depicts an overview of the proposed Power generating and distributionsystems.

    PHCN Isolator

    SW#1Automatic

    Change-OverPanel #1

    LowVoltageOve

    rheadLine

    InternalDistribut

    ionsystem

    Emergency supply to selected wards and theater

    4corex

    120mmsq

    PVC/SWA/PVCCable

    G

    500KVA

    (Existing)

    PERKINS

    Generator

    PHCN Isolator

    SW#2

    From 500KVA

    Xformer Sub-Station

    Automatic

    Change-Over

    Panel #3

    G

    350KVA

    Proposed New

    Generator

    Automatic

    Change-Over

    Panel #4

    Proposed Typical Change-Over

    Arrangement to be Located in Each

    Building Requiring Emergency Power

    Supply

    BattInverter System

    Providing continuous powerto Life Saving Equipment

    and all Lighting as

    Connected to DB#1Distribution

    Panel

    # 1

    Distribution

    Panel

    # 2

    Lighting & Critical

    Equipment

    Non Critical

    loads

    G

    750KVA

    (Future)

    Proposed New

    Generator Automatic

    Change-Over

    Panel #2

    Bus-Tie

    Interlocked Switch

    Fig 16 Proposed Overall Generation and Distribution Schematic

  • 7/21/2019 Hospital Electrical Systems Preliminary Site Visit Rpt Rev2

    19/23

    SITE VISIT REPORT & RECOMMENDATIONS DOCUMENTELECTRICAL SYSTEMS UPGRADE

    Page 19 of 23 08/05/13

    The above schematic refers:

    POWER PLANT

    Install one(1) 500KVA generator(existing) and make provision for a future 750KVAgenerator thru the use of a automatic change-over switch #2 system.

    Tie-In PHCN utility supply thru a main automatic change-over switch #1 cascaded tosecondary changeover switch #2

    Install adequately rated fused Isolator units for PHCN tie-in to change-over switch #1

    Install one(1) 350KVA generator unit for emergency load supply thru automatic changeover switch unit #3

    Tie-In PHCN thru a fused isolator connected to automatic change-over switch #3

    Install a split bus main Low Voltage(LV) panel rated for at least 2000Amps continuousduty

    DISTRIBUTION

    Connect Output of main change-over switch #1 to one side of the split bus-bar LV Panelthru to the existing over head conductor distribution system.

    Connect Output of change-over switch #2 to the other side of the LV Panel bus-bar thruto service circuit breakers feeding identified critical load centers.

    Install dedicated service cables from the Power plant LV Panel to each identified criticalload center utilizing cable trays to be mounted along the newly installed walkway roof

    trusses

    Install manual/automatic change over switches #4 at each critical load center as identifiedto enable selection between normal mains power as supplied from overhead lines andemergency power as supplied from dedicated service runs from the Power Plant.

    Install adequately sized inverter/UPS systems within each building identified as criticalload and connect output of change-over switch #4 as its input.

  • 7/21/2019 Hospital Electrical Systems Preliminary Site Visit Rpt Rev2

    20/23

    SITE VISIT REPORT & RECOMMENDATIONS DOCUMENTELECTRICAL SYSTEMS UPGRADE

    Page 20 of 23 08/05/13

    Connect Inverter/UPS output to distribution panel #1 which should be wired to power allcritical loads and Lighting within the building

    Connect distribution panel #2 directly to the change-over switch #4 output and wiredistribution panel to feed all high demand loads within the building including airconditioners, water heaters and cooker units.

  • 7/21/2019 Hospital Electrical Systems Preliminary Site Visit Rpt Rev2

    21/23

    SITE VISIT REPORT & RECOMMENDATIONS DOCUMENTELECTRICAL SYSTEMS UPGRADE

    Page 21 of 23 08/05/13

    PROPOSED PROJECT PLAN

    ID TASK DESCRIPTION IN SUMMARY

    WK 1 WK2 WK3 WK4 WK5 WK6 WK7 WK8 WK9 Wk10 WK11 WK12

    1 Project Start

    2

    Site Evaluation and Load Flow and Fault

    Studies For Approval of Construction

    Drawings/Specifications

    3 Procurement

    4 Mobilize to Site

    5

    Installation of Generator & Change Over

    Switches

    6 Installation of Main LV Panel

    7

    Installation of Support Cable Trays for

    Dedicated Emergency Service Cables

    8 Install Emergency Service Cables

    9

    Install Inverter/UPS Systems in identified

    Critical Load Centers

    10

    Install Change-Over Switchs in identified

    Critical Load centers

    11 Testing and Commissioning

    12 Project Close-Out

    IPGRUPPS EXECUTIVE COMPANY SUMMARY

    IPgrupp.Engineering has been serving the small and medium sized Electrical & Specialty ControlIndustrial community in Nigeria since 1996.

    Our strength lies in the ability to provide dedicated

    Construction, commissioning and specialistelectrical/Instrumentation engineering design support servicesfor industrial production facilities. Our services include powersystem design & planning, electrical/Instrumentationprocurement, Construction coordination and maintenancesupport for electrical power distribution systems. .

  • 7/21/2019 Hospital Electrical Systems Preliminary Site Visit Rpt Rev2

    22/23

    SITE VISIT REPORT & RECOMMENDATIONS DOCUMENTELECTRICAL SYSTEMS UPGRADE

    Page 22 of 23 08/05/13

    From conceptual power system studies to commissioning, IPGRUPP Engineering have averifiable track record of vast technical expertise, equipment and network of technical resourcepartners to complete projects safely, cost- effectively, within schedule and to requiredspecifications. Over the years we have developed and attracted field tested site team techniciansand engineers, extensively supported by experienced Project Managers and design Engineers.

    Our core service areas include:

    Design and Installation of Back-up PowerSystems including cable distribution.

    Design and Installation of SurveillanceSystem.

    Design and Installation of Fire & Gasdetection and Alarm System.

    Design & Installation of alternative energypower supply systems.

    Installation of Power Monitoring & ControlSCADA Systems.

    IPgrupp.Engineering is a limited liability company with corporate registration number RC 424165.We have our main office at Lekki-Ajah, Lagos with operations yard and satellite offices in Warri,

    Abuja and Port-Harcourt in Delta and Rivers State respectively.

    We have successfully completed several Electrical and Instrumentation Projects eitherindependently or as a value adding team member in multiple company efforts. Notable among thenumerous projects include the deployment of real-time gas monitoring SCADA system for fiscalmonitoring on behalf of the Department of Petroleum Resources, Obudu Cattle Ranch (Cross-Rivers)- electrical and network systems, University of Western Delta, Oghara- Electrical,Communication, Safety and Fire Alarm structured cabling and active device systems amongstmany

  • 7/21/2019 Hospital Electrical Systems Preliminary Site Visit Rpt Rev2

    23/23

    SITE VISIT REPORT & RECOMMENDATIONS DOCUMENTELECTRICAL SYSTEMS UPGRADE

    OUR VISION STATEMENT

    Achieve sustainable and significant service capacity for Enginering Design, Construction,Maintenance and Manufacturing in West Africa and beyond.

    OUR MISSION STATEMENT

    To Provide excellent and sustainable Engineering Services to the Oil & Gas and Power Sub-sectors of West-African energy industry through effective alliances, local capacity developmentand good business practices.