hutch neilson, ncsx project manager for the project team princeton plasma physics laboratory

13
NCSX VVSA & MCWF Final Design Review May 19-20, 2004 NCSX Hutch Neilson, NCSX Project Manager for the Project Team Princeton Plasma Physics Laboratory Oak Ridge National Laboratory NCSX VVSA & MCWF Final Design Review Introduction

Upload: nassor

Post on 17-Jan-2016

37 views

Category:

Documents


0 download

DESCRIPTION

Hutch Neilson, NCSX Project Manager for the Project Team Princeton Plasma Physics Laboratory Oak Ridge National Laboratory. NCSX VVSA & MCWF Final Design Review Introduction. Welcome Back, Reviewers. Signed, the NCSX Project Team. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Hutch Neilson, NCSX Project Manager for the Project Team Princeton Plasma Physics Laboratory

NCSX VVSA & MCWF Final Design Review May 19-20, 2004

NCSX

Hutch Neilson, NCSX Project Manager

for the Project Team

Princeton Plasma Physics Laboratory

Oak Ridge National Laboratory

NCSX VVSA & MCWFFinal Design Review

Introduction

Page 2: Hutch Neilson, NCSX Project Manager for the Project Team Princeton Plasma Physics Laboratory

2

NCSX

NCSX VVSA & MCWF Final Design Review May 19-20, 2004

Welcome Back, Reviewers

Signed, the NCSX Project Team.

We request your critical technical review and feedback on our

readiness to procure long-lead components.

Page 3: Hutch Neilson, NCSX Project Manager for the Project Team Princeton Plasma Physics Laboratory

3

NCSX

NCSX VVSA & MCWF Final Design Review May 19-20, 2004

Outline

• Near-term plans for procurement of major components:

– The 3 Vacuum Vessel Sub-Assemblies (VVSA)

– The 18 Modular Coil Winding Forms (MCWF)

• Project responses to Fall, 2003 reviews.

• VVSA & MCWF cost and schedule risks.

• Summary: readiness to proceed.

Page 4: Hutch Neilson, NCSX Project Manager for the Project Team Princeton Plasma Physics Laboratory

4

NCSX

NCSX VVSA & MCWF Final Design Review May 19-20, 2004

FDR focus: establish a sound technical basis to proceed with VVSA and MCWF procurements.

• Charge for this review: assess project’s technical

readiness to proceed with these two procurements.

• Feedback on other aspects of the design are welcome.

(Please clearly distinguish).

Page 5: Hutch Neilson, NCSX Project Manager for the Project Team Princeton Plasma Physics Laboratory

5

NCSX

NCSX VVSA & MCWF Final Design Review May 19-20, 2004

Plan: Award VVSA & MCWF Contracts by Aug. 30

May June July August

5/19-20 FDR

5/15 Issue Specs & SOWs

for Production Proposals

6/7

Receive Proposals

7/2

Evaluate Proposals Award

Production Contracts

8/30

Select

Page 6: Hutch Neilson, NCSX Project Manager for the Project Team Princeton Plasma Physics Laboratory

6

NCSX

NCSX VVSA & MCWF Final Design Review May 19-20, 2004

R=1.42m, <a>=0.33m, B0 = 2 T

Fall 2003 Project Reviews Established a Sound Project Baseline.

Preliminary Design Review (PDR)

Performance Baseline Review (PBR,

a.k.a. Lehman Review)

External Independent Review

All found…

• Technically sound design.

• Cost and schedule estimates OK.

• Management and plans OK.

• Project ready to be baselined.

Project baseline was approved by

DOE in Feb., 2004 (CD-2)

Page 7: Hutch Neilson, NCSX Project Manager for the Project Team Princeton Plasma Physics Laboratory

7

NCSX

NCSX VVSA & MCWF Final Design Review May 19-20, 2004

Review Recommendations to Reduce Risk Were Included in the Baseline

Those affecting the VVSA and MCWF cost and

schedule:

• Vacuum vessel bakeable to 350C.– reduce future PFC costs and risks.

• Additional analysis and R&D.– reduce risks of downstream delays or performance shortfalls.

CD-2 baseline: $86.3M TEC, May ’08 1st Plasma

Page 8: Hutch Neilson, NCSX Project Manager for the Project Team Princeton Plasma Physics Laboratory

8

NCSX

NCSX VVSA & MCWF Final Design Review May 19-20, 2004

Technical Recommendations Affecting MCWF Procurement Readiness Have Been Resolved.

PDR 1 & 3– Coil current and LN2 feeds design and layout.

Location on coil selected; access penetration through MCWF provided; interfaces checked.

PDR 2– Short time between prototype delivery and procurement of production units.

Have worked closely with suppliers to keep production proposals on schedule; they are already reviewing drafts of final specs and SOWs.

PDR 4– Update winding tolerance budget.

Will do so as we develop winding process, but MCWF tolerance still appropriate.

PDR 8– MCWF “tee” deflections during machining.

Experience to date indicates no issue.

PDR 26– Inaccessible bolts at structural shell joints.

Analysis shows they are not needed.

Page 9: Hutch Neilson, NCSX Project Manager for the Project Team Princeton Plasma Physics Laboratory

9

NCSX

NCSX VVSA & MCWF Final Design Review May 19-20, 2004

Technical Recommendations Affecting VVSA Procurement Readiness Have Been Resolved. - 1

PDR 12– Increase VV bakeout temperature to 350 C.

Final design satisfies this requirement.

PDR 30– Follow through on in-progress diagnostic integration efforts.

Extensive final design effort led to significant modification of port configuration. Additional ports will increase VVSA costs.

PDR 10– Fix inconel-to-stainless transition point in port extensions.

Location chosen just outside modular coil shell.

PDR 11 / PBR 4– Investigate alternatives for final assembly welds.

R&D program budgeted and in progress.

Page 10: Hutch Neilson, NCSX Project Manager for the Project Team Princeton Plasma Physics Laboratory

10

NCSX

NCSX VVSA & MCWF Final Design Review May 19-20, 2004

Technical Recommendations Affecting VVSA Procurement Readiness Have Been Resolved. - 2

PDR 15– Thermally cycle VV sectors above bakeout temperature.

Specified for production units, but not for 20-deg prototype due to limited relevance.

PDR 15– Treat first sector as a prototype; allow staged sector delivery.

Manufacturing & QA plan provides in-process oversight and inspection needed to ensure conformance w/ spec for all three sectors.

Requirements were revised to allow (not require) staged sector delivery.

Page 11: Hutch Neilson, NCSX Project Manager for the Project Team Princeton Plasma Physics Laboratory

11

NCSX

NCSX VVSA & MCWF Final Design Review May 19-20, 2004

VVSA and MCWF Risk Management: Cost

Budget for VVSA ($2.9M) and MCWF ($4.8M) = $7.7M

• Based on suppliers’ budgetary estimates for the PDR (Oct., 2003)

Risks

• Project decision to add 33 ports in final design.– We estimate the impact at $0.3M.

• Cost growth in some of the manufacturing steps.– Some growth expected based on R&D to date (Viola, Heitzenroeder)

Risk Mitigation

• Competition (two suppliers each) keeping downward pressure on cost.

• Budget contingency: $3M (40%) associated with these components.– Cost growth expected to be within this amount.

Page 12: Hutch Neilson, NCSX Project Manager for the Project Team Princeton Plasma Physics Laboratory

12

NCSX

NCSX VVSA & MCWF Final Design Review May 19-20, 2004

VVSA and MCWF Risk Management: Schedule

Delivery Requirements

• Need VVSA: Nov., 2005 (3.4 months of free float)

• Need MCWF #1: Dec., 2004, MCWF #18: April, 2006 (critical path)

Risks

• Cost growth exceeding $1.4M might stretch out the schedule due to cash flow limitations.

• Production schedules might not meet requirements.

• Near-term procurement or design delays might delay award.

Risk Mitigation

• MCWF: split the order between the two suppliers.

• VVSA: use schedule float.

• Procurement: suppliers already working on proposals as contract deliverables, and already reviewing drafts of the final design specs and SOWs.

• Design: drawings and models are complete and in final checking. Hope to incorporate FDR conclusions and release by June 1 (VVSA) and June 7 (MCWF).

Page 13: Hutch Neilson, NCSX Project Manager for the Project Team Princeton Plasma Physics Laboratory

13

NCSX

NCSX VVSA & MCWF Final Design Review May 19-20, 2004

We Are Ready to Proceed with VVSA and MCWF Procurement

VVSA and MCWF designs meet their requirements

• At the system level (B. Nelson, W. Reiersen)

• At the subsystem and component level (VVSA and MCWF breakouts)

Adequacy of product specifications has been demonstrated.

• Final design models, drawings, specs, and SOWs are ready.

• Suppliers are using similar specs to build prototypes.

• Have successfully handled product data flow: designmanufactureinspect

Suppliers have been qualified via manufacturing R&D.

• They have developed solutions to fabrication and inspection challenges.

• Prototype fabrication, still in progress, is demonstrating capabilities.

The procurement plan we have been following since 2002 is working well.

• Two qualified suppliers for each component.

• They have the experience and information to prepare sound and timely proposals.