hydrogen delivery system schedule

19
Hydrogen Delivery System Schedule MICE Schedule Review 23 rd -25 th May 2011 M Hills STFC

Upload: maeve

Post on 06-Jan-2016

34 views

Category:

Documents


1 download

DESCRIPTION

Hydrogen Delivery System Schedule. MICE Schedule Review 23 rd -25 th May 2011 M Hills STFC. Outline. Work package overview Task breakdown Staff resources Schedule summary Schedule by task Milestones Risks STEPS V & VI. Work package overview. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Hydrogen Delivery System Schedule

Hydrogen Delivery SystemSchedule

MICE Schedule Review 23rd-25th May 2011

M HillsSTFC

Page 2: Hydrogen Delivery System Schedule

MICE Schedule Review24th May 2011

Outline

i. Work package overviewii. Task breakdowniii. Staff resourcesiv. Schedule summaryv. Schedule by taskvi. Milestonesvii.Risksviii.STEPS V & VI

2

Page 3: Hydrogen Delivery System Schedule

MICE Schedule Review24th May 2011

Work package overview– The Hydrogen Delivery Systems will provide liquid hydrogen to the

Absorbers in MICE

– Each Absorber will have a dedicated delivery system (A, B & C)

– The systems use metal-hydride storage and an R&D phase is planned to de-bug this novel part of the system

– The R&D phase uses a dedicated test cryostat in place of the final MICE Absorber

– Upon completion of the R&D, the system will be integrated with the AFC containing a KEK absorber for final commissioning

3

Page 4: Hydrogen Delivery System Schedule

MICE Schedule Review24th May 2011

What we have to do...to test the system

4

Heater/Chiller units for the hydride bed

Test Cryostat

Ventilation System(continues on the roof)

Hydrogen Charging Station

Vacuum Pumps(more on the roof)

View of MICE Hall South Side (mezzanine not shown)

Gas Panel Enclosure

AND Pass a pre-operation safety review

Vacuum lines

Page 5: Hydrogen Delivery System Schedule

MICE Schedule Review24th May 2011

...to be ready for STEP IV5

AFC module in STEPIV position

Gas Panel Enclosure moved up the mezzanine

New vacuum line

Ventilation extract duct moved

Page 6: Hydrogen Delivery System Schedule

MICE Schedule Review24th May 2011

What we have done so far6

Test Cryostat Ventilation System

Gas Panel Enclosure

Vacuum Pump Enclosure

Vent stacks

Control System

Page 7: Hydrogen Delivery System Schedule

MICE Schedule Review24th May 2011

Tasks– Controls

– Mechanical Design

– Safety

– Hall Infrastructure and Installation

– R&D Testing

– STEP IV Preparation (AFC Commissioning)

7

Page 8: Hydrogen Delivery System Schedule

MICE Schedule Review24th May 2011

People M Hills - project management, cryogenic and mechanical design

M Courthold - cryogenic design, controls and testing

T Bradshaw – advice and consultation on cryogenic issues

I Mullacrane, P Warburton - control system design and implementation

A Muir, S Postlethwaite (with supervision from A Grant) – mechanical design

Hall technicians – installation and assembly

8

Page 9: Hydrogen Delivery System Schedule

MICE Schedule Review24th May 2011

2011/12 Schedule Overview9

Page 10: Hydrogen Delivery System Schedule

MICE Schedule Review24th May 2011

Controls10

– Controls for helium testing already in place– This work covers the additional tasks for hydrogen testing

Page 11: Hydrogen Delivery System Schedule

MICE Schedule Review24th May 2011

Mechanical Design11

Mostly laying the foundations for integration with the AFC

Page 12: Hydrogen Delivery System Schedule

MICE Schedule Review24th May 2011

Safety12

– Working closely with consultants to ensure DSEAR and IEC61508 compliance– Plenty of documentation to prepare

Page 13: Hydrogen Delivery System Schedule

MICE Schedule Review24th May 2011

Infrastructure and Installation13

EMR run will push back several tasks, but work can continue on external infrastructure during this period

Page 14: Hydrogen Delivery System Schedule

MICE Schedule Review24th May 2011

Testing14

– Helium testing to start once power and water in the Hall are restored– Second EMR run may delay some hydrogen testing

Page 15: Hydrogen Delivery System Schedule

MICE Schedule Review24th May 2011

STEP IV Preparation15

– Repositioning of Gas Panel Enclosure and related services is driven by completion of R&D testing

– AFC commissioning extends into May 2012

Page 16: Hydrogen Delivery System Schedule

MICE Schedule Review24th May 2011

Milestones16

Milestone Date

Helium R&D testing complete July 2011

Safety Review passed August 2011

Hall infrastructure and installation complete September 2011

Hydrogen R&D complete December 2011

Manufacture of items for AFC adaption complete

November 2011

AFC Commissioning complete April/May 2012

Page 17: Hydrogen Delivery System Schedule

MICE Schedule Review24th May 2011

Risk Summary

– Funding availability

– Manpower restrictions/key staff availability– Would impact all aspects of the project

– Hydride bed has been affected by long term storage– A concern given that a direct replacement is no longer available

– Safety review recommends major design changes before R&D testing can commence

– Significant knock-on effect for STEP IV

– R&D system manufacturers are unwilling or unable to take on contract for systems B & C

– Would result in delays to transfer knowledge and require closer oversight of the new contract from STFC

17

Page 18: Hydrogen Delivery System Schedule

MICE Schedule Review24th May 2011

STEPS V & VI– This means Systems B & C in the context of the Hydrogen Delivery System

– Most of the hall infrastructure (e.g. vacuum enclosure, ventilation system, gas supplies) will serve all three systems, so it is ‘only’ the hydride bed, gas panel, transfer lines and control system that are required

– If R&D system is successful design can be carried over with very few changes

– Type of hydride bed is currently the major unknown as the current manufacturer, Treibacher, no longer supply an equivalent model

– Each system will take approximately 1 year to design, manufacture and test with an AFC module (full Gantt chart available)

– Current assumption is that work in System B will start in April 2012 with System C following in April 2013, but this is highly dependent on the overall project schedule

18

Page 19: Hydrogen Delivery System Schedule

MICE Schedule Review24th May 2011

Summary– Detailed schedule is known for System A installation and the

R&D testing

– This is due to be completed by the end of 2011

– MICE running to commission the EMR will impact the current plan and may delay this date

– Significant work following R&D testing to prepare for AFC commissioning and STEP IV

– Delivery of Systems B & C should be in line with their need-by dates, but hydride bed supply issues need resolving

19