i 290 presentation
TRANSCRIPT
-
8/9/2019 I 290 Presentation
1/28
1
I-290
OAK PARKVILLAGE BOARD
BRIEFING
January 26, 2015
-
8/9/2019 I 290 Presentation
2/28
2
I
-
290 Planning Process & Schedule
-
8/9/2019 I 290 Presentation
3/28
3
I
-
290 Study Area
ReconstructionSection
(9 m iles)
Re-stripingSection
(4 m iles)
Circle Interchange
Study Area
13-mile study area
West of Mannheim Road to Racine Avenue
Connects between:
I-88 on the west
Circle Interchange on the east
-
8/9/2019 I 290 Presentation
4/28
4
Stakeholder Involvement
Context Sensitive Solutions
Considers safety, mobility,
community and environmental
factors
Stakeholders have helped to:
Define transportation needs
Identify constraints
Develop alternatives Evaluate alternatives
-
8/9/2019 I 290 Presentation
5/28
5
I
-
290 Transportation Needs, Alternatives Summary
Transportation Needs Mobility, safety, condition and design
Alternatives Additional lane within trench
Transit, bicycle, and pedestrian improvements
Level of detail increases as evaluation advances
Environmental Considerations The communities make up the environment
Detailed engineering/traffic data required for noise, air, social, economic and
cultural analysis
Overall goal:Create an asset for adjoining communities
-
8/9/2019 I 290 Presentation
6/28
6
Alternatives Carried Forward
-
8/9/2019 I 290 Presentation
7/28
7
Alternatives Carried Forward
-
8/9/2019 I 290 Presentation
8/28
8
Blue Line Extension
Blue Line Extension Station
Feeder/Intersecting Bus Route
P Station Park-and-Ride Facility
Included in all alternatives:
Extension to Mannheim most
effective termini
Initial service option bus on inside
I-290 shoulder
I-290 corridor improvements willenable/leverage transit
improvements
-
8/9/2019 I 290 Presentation
9/28
-
8/9/2019 I 290 Presentation
10/28
1010
Alternatives Evaluation Round 3 Initial Findings
25,000 to over 30,000 additional personsthrough the corridoreach day on highway and
transit
Up to 397,000 additional jobs accessible by
highway and transit (within 60 minutes)
56% to 59% peak period travel time savings on
managed lanes
24% to 52% travel time savings on general
purpose lanes
Improves expressway safety up to 8%
-
8/9/2019 I 290 Presentation
11/28
11
Alternatives Evaluation Round 3
Round 3 Timeframe: January 2015 August 2015
OBJECTIVE: Ad vance from 4 concepts to a Preferred
Alternat ive
Summer 2014 Fall 2015, multiple stakeholder meetings
Geometry (starting point for Round 3) Drainage
Detailed environmental studies
Blue Line Vision Study results
Travel performance
Cost
Aesthetics Intelligent Transportation Systems (ITS)
Project funding/financing
Construction staging scenarios
Sustainability
.. .an excellent (and crit ic al)
opp or tuni ty to shape the
outcome of th is p lann ing
process
-
8/9/2019 I 290 Presentation
12/28
12
Round 3 Village of Oak Park
Village comments
Technical studies
Meetings and workshops
Working group
Village participants
IDOT/CTA project team
-
8/9/2019 I 290 Presentation
13/28
13
CTA Blue Line Forest Park Branch
Feasibility/Vision Study
Recommendations
-
8/9/2019 I 290 Presentation
14/28
14 14
Purpose & Study Process
-
8/9/2019 I 290 Presentation
15/28
15 15
Study Area
-
8/9/2019 I 290 Presentation
16/28
16 16
Summary of Existing Conditions Assessment
Minimal upgrades have been completed as needed Special Trackwork: crossovers & switches recently upgraded (except Lathrop)
Signals: recently upgraded
Remaining elements beyond useful life and severely worn
Track: contaminated ballast, deteriorated ties, poor drainage, worn rail
Stations: over 50 years old, only 4 of 12 are accessible, narrow platforms
Structures: approaching end of useful life
Traction Power: substation, cabling, third rail, etc require upgrading
Communications System: warrants technical improvements
Maintenance Shop: approaching end of useful life; inadequate track
configuration and capacity
-
8/9/2019 I 290 Presentation
17/28
17 17
Overall Recommendations
Complete reconstruction/modernization for the Forest Park branch
Maintain existing entrance locations
Improve customer experience
Improve infrastructure
Improve terminal site
Maintain existing service
Work with IDOT on corridor improvements
-
8/9/2019 I 290 Presentation
18/28
18 18
Maintain Existing Entrance Locations
-
8/9/2019 I 290 Presentation
19/28
19 19
Improve Customer Experience: Conceptual Rendering
-
8/9/2019 I 290 Presentation
20/28
20 20
Improve Customer Experience: Conceptual Rendering
-
8/9/2019 I 290 Presentation
21/28
21 21
Improve Terminal Site
-
8/9/2019 I 290 Presentation
22/28
22 22
Forest Park Terminal Station Conceptual Rendering
-
8/9/2019 I 290 Presentation
23/28
-
8/9/2019 I 290 Presentation
24/28
24 24
Intermodal Coordination
-
8/9/2019 I 290 Presentation
25/28
25 25
Summary of Overall Recommendations
-
8/9/2019 I 290 Presentation
26/28
26 26
Next Steps Blue Line
Present results to public in coordination with IDOT I-290 Public Hearing
Continue to evaluate funding options and project phasing
-
8/9/2019 I 290 Presentation
27/28
27
Next Steps I-290
Round 3 Coordination Village of Oak Park Establish working group participants, agendas and schedule
Round 3 Overall Technical Analysis
One-on-one meetings
CAG meetings
Draft Environmental Impact Statement Circulation & Public Hearing Fall 2015
Letter of Intent Project scope and commitments
Maintenance and cost responsibilities
Documents local approval
-
8/9/2019 I 290 Presentation
28/28