i 290 presentation

Upload: wednesdayjournal

Post on 01-Jun-2018

219 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/9/2019 I 290 Presentation

    1/28

    1

    I-290

    OAK PARKVILLAGE BOARD

    BRIEFING

    January 26, 2015

  • 8/9/2019 I 290 Presentation

    2/28

    2

    I

    -

    290 Planning Process & Schedule

  • 8/9/2019 I 290 Presentation

    3/28

    3

    I

    -

    290 Study Area

    ReconstructionSection

    (9 m iles)

    Re-stripingSection

    (4 m iles)

    Circle Interchange

    Study Area

    13-mile study area

    West of Mannheim Road to Racine Avenue

    Connects between:

    I-88 on the west

    Circle Interchange on the east

  • 8/9/2019 I 290 Presentation

    4/28

    4

    Stakeholder Involvement

    Context Sensitive Solutions

    Considers safety, mobility,

    community and environmental

    factors

    Stakeholders have helped to:

    Define transportation needs

    Identify constraints

    Develop alternatives Evaluate alternatives

  • 8/9/2019 I 290 Presentation

    5/28

    5

    I

    -

    290 Transportation Needs, Alternatives Summary

    Transportation Needs Mobility, safety, condition and design

    Alternatives Additional lane within trench

    Transit, bicycle, and pedestrian improvements

    Level of detail increases as evaluation advances

    Environmental Considerations The communities make up the environment

    Detailed engineering/traffic data required for noise, air, social, economic and

    cultural analysis

    Overall goal:Create an asset for adjoining communities

  • 8/9/2019 I 290 Presentation

    6/28

    6

    Alternatives Carried Forward

  • 8/9/2019 I 290 Presentation

    7/28

    7

    Alternatives Carried Forward

  • 8/9/2019 I 290 Presentation

    8/28

    8

    Blue Line Extension

    Blue Line Extension Station

    Feeder/Intersecting Bus Route

    P Station Park-and-Ride Facility

    Included in all alternatives:

    Extension to Mannheim most

    effective termini

    Initial service option bus on inside

    I-290 shoulder

    I-290 corridor improvements willenable/leverage transit

    improvements

  • 8/9/2019 I 290 Presentation

    9/28

  • 8/9/2019 I 290 Presentation

    10/28

    1010

    Alternatives Evaluation Round 3 Initial Findings

    25,000 to over 30,000 additional personsthrough the corridoreach day on highway and

    transit

    Up to 397,000 additional jobs accessible by

    highway and transit (within 60 minutes)

    56% to 59% peak period travel time savings on

    managed lanes

    24% to 52% travel time savings on general

    purpose lanes

    Improves expressway safety up to 8%

  • 8/9/2019 I 290 Presentation

    11/28

    11

    Alternatives Evaluation Round 3

    Round 3 Timeframe: January 2015 August 2015

    OBJECTIVE: Ad vance from 4 concepts to a Preferred

    Alternat ive

    Summer 2014 Fall 2015, multiple stakeholder meetings

    Geometry (starting point for Round 3) Drainage

    Detailed environmental studies

    Blue Line Vision Study results

    Travel performance

    Cost

    Aesthetics Intelligent Transportation Systems (ITS)

    Project funding/financing

    Construction staging scenarios

    Sustainability

    .. .an excellent (and crit ic al)

    opp or tuni ty to shape the

    outcome of th is p lann ing

    process

  • 8/9/2019 I 290 Presentation

    12/28

    12

    Round 3 Village of Oak Park

    Village comments

    Technical studies

    Meetings and workshops

    Working group

    Village participants

    IDOT/CTA project team

  • 8/9/2019 I 290 Presentation

    13/28

    13

    CTA Blue Line Forest Park Branch

    Feasibility/Vision Study

    Recommendations

  • 8/9/2019 I 290 Presentation

    14/28

    14 14

    Purpose & Study Process

  • 8/9/2019 I 290 Presentation

    15/28

    15 15

    Study Area

  • 8/9/2019 I 290 Presentation

    16/28

    16 16

    Summary of Existing Conditions Assessment

    Minimal upgrades have been completed as needed Special Trackwork: crossovers & switches recently upgraded (except Lathrop)

    Signals: recently upgraded

    Remaining elements beyond useful life and severely worn

    Track: contaminated ballast, deteriorated ties, poor drainage, worn rail

    Stations: over 50 years old, only 4 of 12 are accessible, narrow platforms

    Structures: approaching end of useful life

    Traction Power: substation, cabling, third rail, etc require upgrading

    Communications System: warrants technical improvements

    Maintenance Shop: approaching end of useful life; inadequate track

    configuration and capacity

  • 8/9/2019 I 290 Presentation

    17/28

    17 17

    Overall Recommendations

    Complete reconstruction/modernization for the Forest Park branch

    Maintain existing entrance locations

    Improve customer experience

    Improve infrastructure

    Improve terminal site

    Maintain existing service

    Work with IDOT on corridor improvements

  • 8/9/2019 I 290 Presentation

    18/28

    18 18

    Maintain Existing Entrance Locations

  • 8/9/2019 I 290 Presentation

    19/28

    19 19

    Improve Customer Experience: Conceptual Rendering

  • 8/9/2019 I 290 Presentation

    20/28

    20 20

    Improve Customer Experience: Conceptual Rendering

  • 8/9/2019 I 290 Presentation

    21/28

    21 21

    Improve Terminal Site

  • 8/9/2019 I 290 Presentation

    22/28

    22 22

    Forest Park Terminal Station Conceptual Rendering

  • 8/9/2019 I 290 Presentation

    23/28

  • 8/9/2019 I 290 Presentation

    24/28

    24 24

    Intermodal Coordination

  • 8/9/2019 I 290 Presentation

    25/28

    25 25

    Summary of Overall Recommendations

  • 8/9/2019 I 290 Presentation

    26/28

    26 26

    Next Steps Blue Line

    Present results to public in coordination with IDOT I-290 Public Hearing

    Continue to evaluate funding options and project phasing

  • 8/9/2019 I 290 Presentation

    27/28

    27

    Next Steps I-290

    Round 3 Coordination Village of Oak Park Establish working group participants, agendas and schedule

    Round 3 Overall Technical Analysis

    One-on-one meetings

    CAG meetings

    Draft Environmental Impact Statement Circulation & Public Hearing Fall 2015

    Letter of Intent Project scope and commitments

    Maintenance and cost responsibilities

    Documents local approval

  • 8/9/2019 I 290 Presentation

    28/28