important aspects in road construction
TRANSCRIPT
-
8/3/2019 Important Aspects in Road Construction
1/89
-
8/3/2019 Important Aspects in Road Construction
2/89
-
8/3/2019 Important Aspects in Road Construction
3/89
305. Soils unsuitable for embankment,sub grade and shoulders
(i) Material from swamps, marshes and bogs.(ii) Peat, log, stump and perishable material; soil
classified as OL, OI, OH or Pt as per IS:1498.(iii)Materials susceptible to spontaneous combustion.(iv)Clay having liquid limit exceeding 70% and
plasticity index exceeding 45%. (tests conductedon material passing 0.425 mm IS Sieve as perIS:2720 part 5)
(v) Material with salts resulting in leaching action e.g.Soils of pH > 8.5).(vi) Expansive clay with free swelling index (test
conducted on material passing 0.425 mm IS Sieve
as per IS:2720 part 40) exceeding 50%
-
8/3/2019 Important Aspects in Road Construction
4/89
305. Soils unsuitable for embankment,
sub grade and shoulders continued
(vii) Materials in a frozen condition.
(viii) Fill materials with a soluble sulphate contentexceeding 1.9 gm of sulphate, (expressed as SO3) per litrewhen tested in accordance with BS:1377 test 10, but using
-
or other distance described in the Contract, of concrete,cement bound materials or other cementitious materialsforming part of permanent works.
(ix) Material with a total sulphate content (expressedas SO3) exceeding 0.5 per cent by mass when tested inaccordance BS: 1377 test 9, shall not be deposited within500 mm or other distance described in the Contract, of
metallic items forming part of permanent works
-
8/3/2019 Important Aspects in Road Construction
5/89
305.4.4: Embankment and Sub Grade
Requirements around structures
The filling around culverts, bridges and other
structures upto a distance of twice the height ofthe road from the back of the abutment shall becarried out inde endent of the work on the main
embankment.Material with LL more than 40% and PI more than20% shall not be allowed as backfill for all earth
retaining structures. Backfill material shallconform to the general requirements given in
appendix 6 of IRC: 78 (Standard Specifications
and Code of practice for road bridges-section VII)
-
8/3/2019 Important Aspects in Road Construction
6/89
-
8/3/2019 Important Aspects in Road Construction
7/89
Soil group to
IS: 1498-1970 Visual
description
MDD
Kg/ m3OMC %
range
Anticipated
performance
Most
probablepossible
GW,GP,G
Granular 1850 to Good to
Filling behind abutments, retaining walls and retun wallsGeneral guide to the selection of soils on basis of anticipated
embankment performance appendix - 6, IRC: 78-2000
, ,HP
-
materials
2280-
Excellent
SB, SM,GM, GC,SM, SC
-
Granularmaterials
With soils
1760 to2160
9 - 18Fair to
excellent
SP - sand1760 to
185019 - 25
Fair togood
MI, MH,
DL
CL,
SM,SB,SC
Sandy soils &
silts
1760 to
2080 10 - 20
Fair to
good
-
8/3/2019 Important Aspects in Road Construction
8/89
Some Test Results on Soils done at Soil Testing Cell (R&B) Vijayawada
District classification
LL
%
PI
%
OMC
%
MDD
g/cc
FSI
%
CBR
%
Guntur CH 66 33 21.3 1.6 65 3
Krishna CI 48 24 19.2 1.63 46 3
Prakasam SM - NP 13.7 1.90 - 10
W G CI 39 21 26 1.45 65 4
Kurnool SC 24 12 8.29 1.75 - 9
W G CL 31 13 15.7 1.84 33 6
E G CI 48 24 14.3 1.82 33 7
Prakasam CH 61 32 24.5 1.4 95 3
W G CI 49 29 16.7 1.68 200 5
-
8/3/2019 Important Aspects in Road Construction
9/89
401.Granular Sub Base as Drainage Layer:
Permeability requirement for drainage layer is 20 m/dayas per Pavement Design Guide (1986) by AmericanAssociation of State Highway and Transportation Officials
(AASHTO) and 4/6 laning manual
Table: 300-4 of Orange Book: Grading Requirements for
A re ate Drains
IS Sieve size Percent passing by weight
37.5mm 100
9.5mm 45 - 100
3.35mm 25 - 80
600 micron 8 - 45
150 micron 5 - 10
75 micron < 5
-
8/3/2019 Important Aspects in Road Construction
10/89
401 Granular Sub Base
1) Material passing 75 micron sieve shall be less than10%2) Material in mix shall have 10% fines value (for sample insoaked condition as per with BS: 812 (part III) > 50 KN3) Water Absorption(IS: 2386-part 3) of coarse aggregate 2%.If
it is more, soundness test requirements be satisfied.4) Material in mix passing 425 micron sieve shall have
Liquid limit < 25% and Plasticity index < 6%.5) Material in the mix shall satisfy specified grading
6) CBR test (IS: 2720 part 16). In-situ CBR tests are not reliable.
30% CBR (4 day soaked) for design traffic more than 2 msaas per IRC:37-200120% CBR (4 day soaked) for design traffic less than 2 msaas per IRC:37-2001
7) Layer thickness:100 mm compacted with smooth wheeled roller
225 mm compacted with vibratory roller
-
8/3/2019 Important Aspects in Road Construction
11/89
TABLE 400-1, Grading for Close Graded Granular Sub-Base
(for gravel roads as per Rural Roads Manual IRC:SP 20-2002)
IS SieveDesignation
Grading I Grading II Grading III
75.0 mm 100 -- --
53.0 mm 80-100 100
26.5 mm 55-90 70-100 1009.50 mm 35-65 50-80 65-95
4.75 mm 25-55 40-65 50-80
2.36 mm 20-40 30-50 40-65
0.425 mm 10-25 15-25 20-35
0.075 mm 3-10 3-10 3-10
-
8/3/2019 Important Aspects in Road Construction
12/89
TABLE 400-2. GRADING FOR COARSE GRADEDGRANGULAR SUB-BASE MATERIALS
IS SieveDesignation
Percent by weight passing throughthe IS sieve
Grading I Grading II Grading III
75.0 mm 100 -- --
53.0 mm 100
26.5 mm 55-75 50-80 100
9.50 mm
4.75 mm 10-30 15-35 25-45
0.075 mm < 10 < 10 < 10
CBR Value(Minimum)
30 25 20
-
8/3/2019 Important Aspects in Road Construction
13/89
Coarse Aggregates: Gr-I to Gr-III , 40mm & 65 mm
Screenings: Type-A :6mm and 10mm,Type-B: Stone Dust
Binder: Stone Dust
Process of WBMSpreading Metal > Sectioning and Dry Rolling >
Light Sprinkling of Water > rolling > Application ofScreenings > Brooming > Rolling > Watering &
Sweeping > Rolling > Application of Binder >Sprinkling of Water & Sweeping > Rolling > Settingand Drying
-
8/3/2019 Important Aspects in Road Construction
14/89
Table 400-7, WBM gradation Requirements
IS Sieve
size
Cumulative percent passing
Grade I Grade II Grade III
125mm 100 - -90mm 90-100 100 -
63mm 25-60 90-100 100
53mm - 25-75 95-100
45mm 0-15 0-15 65-90
22.4mm 0-5 0-5 0-1011.2mm - - 0-5
Aggregate Impact Value (IS:2386: part-4) :30% (max)
Combined flakiness and elongation index (IS:2386: part-1) : 30% (max),
-
8/3/2019 Important Aspects in Road Construction
15/89
Table 400 - 8
404.2.6. Screenings: Screenings to fill voids in thecoarse aggregate shall generally consist of the same material
as the coarse aggregate. However, where permitted,predominantly non-plastic material such as moorum or gravel(other than rounded river borne material) may be used for thispurpose provided liquid limit and plasticity index of suchmaterial are below 20 and 6 respectively and fraction passing75 micron sieve does not exceed 10 per cent.
Type of screenings IS Sieve % passing
Type A 13.2mm
(6mm & 10mm chips)
13.2mm 100
11.2mm 95-100
5.6mm 15-35180 micron 0-5
Type B 11.2mm
(stone dust)
11.2mm 100
5.6mm 90-100
180 micron 15-35
-
8/3/2019 Important Aspects in Road Construction
16/89
DOs Donts
1. Check aggregates for
Soundness test when waterabsorption is more than 2%
2. Soft aggregate should be
tested for wet aggregate impactvalue.3. Construct shoulders
simultaneously along with
1. Do not use any material derived from
rocks e.g. phyllites, shales or slates.2. Do not use local soil and clayey
material as screenings or binding
material unless it meats the
requirements of PI mentioned
3. Do not use binding material if
screenings are of crushable type.
4. Do not spread coarse aggregate more
than 3 days in advance of any
WBM layers.4. Use inverted choke over fine
grained soil sub-grade.5. Remove BT surface before
WBM is laid on an existingblack top road.
6. Remove defective macadam tofull depth and replace by freshmaterial and re-compact.
subsequent operations.
5. Do not roll if sub-grade is soft or
yielding or causes a wave like motion
while rolling.
6. Do not lay WBM layer on lime treated
sub-base until it has attained its strength.7. Do not use screenings to make up
depressions.
8. Do not allow traffic till WBM is fully
set.
-
8/3/2019 Important Aspects in Road Construction
17/89
DOs Donts
1. Check aggregates for
Soundness test when waterabsorption is more than 2%
2. Soft aggregate should be
tested for wet aggregate impactvalue.3. Construct shoulders
simultaneously along with
1. Do not use any material derived
from rocks e.g. phyllites, shales orslates.2. Do not use local soil and clayey
material as screenings or bindingmaterial unless it meats the
requirements of PI mentioned3. Do not use binding material ifscreenings are of crushable type.
4. Do not spread coarse aggregate
WBM layers.4. Use inverted choke over fine
grained soil sub-grade.5. Remove BT surface before
WBM is laid on an existingblack top road.
6. Remove defective macadam tofull depth and replace by freshmaterial and re-compact.
subsequent operations.5. Do not roll if sub-grade is soft oryielding or causes a wave likemotion while rolling.
6. Do not lay WBM layer on lime
treated sub-base until it has attainedits strength.7. Do not use screenings to make updepressions.8. Do not allow traffic till WBM is
fully set.
-
8/3/2019 Important Aspects in Road Construction
18/89
WET MIX MACADAM
IS Sieve DesignationPer cent by weight
passing the IS Sieve
53.00 mm 100
45.00 mm 95-100
22.4 mm 60-80
11.20 mm 40-60
Table 400-11. Grading Requirements of Aggregates for WMM
Materials : 40mm, 20mm , 12mm, 6mm &Stone Dust Mixing at Pug Mill with Water,Conveyed to Site, Spreading by Paver and Rolling. Relative Compaction = 98 %
Aggregate Impact Value (IS:2386: part-4) :30% (max)
Combined flakiness and elongation index (IS:2386: part-1) : 30% (max),Plasticity Index (IS:2720: part5) shall not exceed 6%.
4.75 mm 25-402.36 mm 15-30
600.00 micron 8-22
75.00 micron 0-8
-
8/3/2019 Important Aspects in Road Construction
19/89
DOs Donts
1. Ensure compliance of allmaterial and plantrequirements.
2. Check aggregate forsoundness test whenwater absorption is more
1. Do not use materialother than crushedstone.
2. Do not allowsegregation or pockets of
an .3. Build shoulderssimultaneously along withWMM layers.
4. Remove BT surfacebefore WMM is laid on anexisting road.
coarse ne ma er a onthe layer.
3. Do not allow any trafficon the WMM surfacewithout covering it with awearing course.
-
8/3/2019 Important Aspects in Road Construction
20/89
Bitumen
grade
Penetration at
25C
Viscosity at 60C in
Poises
Kinematic
viscosity at 135C,
cSt, Min
VG - 40 40 to 6040 to 60 4000200 400
Important Requirements Viscosity
Grades of Bitumen as per IS: 73 - 2006
VG - 30 50 to 7050 to 70 3000600 350
VG - 20 60 to 8060 to 80 2000400 300
VG - 10 80 to 10080 to 100 1000200 250
-
8/3/2019 Important Aspects in Road Construction
21/89
Stipulations of IS: 73 2006 in selection of VG grade bitumensin place of Penetration Grade (prevailing) bitumens
Viscosity Grade General Applications
VG-40
(40 to 60 penetration)
Use in highly stressed areas suchas those in intersections, near tollbooths and truck parking lots in
lieu of old 30/40 penetration grade
Use for paving for most parts of
(50 to 70 penetration)
India in lieu of old 60/70penetration grade.
VG-20
(60 to 80 penetration)
Use in cold climatic, high altituderegions of North India
VG-10 (80 to 100penetration)
Use in spraying applications suchas surface dressing and paving invery cold climatic region in lieu of
old 80/100 penetration grade
-
8/3/2019 Important Aspects in Road Construction
22/89
BitumenBitumenTemp.C
AggregateTemp.C
MixTemp.C
LayingTemp. C
RollingTemp.C
VG - 40 160 - 170 160 - 170 160 170 150 min. 100 min.
Mixing, laying and rolling temperatures for VG grade
paving bitumen and modified binder
- - . .
VG - 20 145 165 145 165 145 165 135 min. 85 min.
VG - 10 140 160 140 160 140 160 130 min. 80 min.
Modified 165 - 185 155 175160
maximum130
Minimum115
minimum
-
8/3/2019 Important Aspects in Road Construction
23/89
Manufacturing and Rolling Temperatures
for penetration grade bitumen
Bitumen
Penetration
Bitumen
Mixing -C
Aggregate
Mixing-C
Mixed
Material -
C
MinimumRolling
temp.
C
Laying-C
35- -
(30-40)
65
(60-70)
150 - 165 150-170 165 Max 90 Min 125 Min
90
(80-100)
140 - 160 140-165 155 Max 80 Min 115 Min
-
8/3/2019 Important Aspects in Road Construction
24/89
Factors Influencing Compaction of Asphalt mixes
1) Type of Aggregates2) Shape of Aggregates
3) Grading of mix4) Residual moisture content in aggregates5) Binder conent
6) Viscosity of binder7) Temperature of mix during compaction
Note: The first six requirements are taken care inthe mix design, leaving temperature ofcompaction as the single most important affectingthe final result.
-
8/3/2019 Important Aspects in Road Construction
25/89
Recommended use of Cationic Emulsions
as per IS 8887: 2004
Type Recommended uses
Rapid Setting RS 1 Tack Coat
Rapid Setting RS 2 Surface Dressing
Medium Setting MS Pre mixes and plant mixes
Slow Setting SS 1Fog seal, Crack Seal, Prime
Coat
Slow Setting SS 2 Slurry Seal and mixes withhigher fine aggregate %
Slow Setting SS 1 is being used as tack coat in USA
and other countries
-
8/3/2019 Important Aspects in Road Construction
26/89
Designation
Grade and RequirementsMethod of
testCRMB60
CRMB55
CRMB50
Table 500-46, Specifications for modified bitumen
Penetration at 25C 50 - 70 50 - 60 40- 60
-
1978
Softening point C-min
50 55 60IS: 1205-
1978
Elastic recovery at15C-minimum
40 35 30ASTM D5976
1996
-
8/3/2019 Important Aspects in Road Construction
27/89
Minimumpavement
temperature
in C
Maximum Atmospheric Temperatures in C
< 35o
c 35o
c to 45o
c > 45o
c
< - 10 ocPMB/NRMB - 120
CRMB - 50
PMB/NRMB - 70
CRMB - 55
PMB/NRMB - 70
CRMB - 55
Selection Criteria for type of modified bitumen basedon Atmospheric temperature
+10 oc to-10 oc
PMB/NRMB - 70CRMB - 50
PMB/NRMB - 70CRMB - 55
PMB/NRMB - 40CRMB - 60
> 10 ocPMB/NRMB - 70
CRMB - 55
PMB/NRMB - 70
CRMB - 55
PMB/NRMB - 40
CRMB - 60
PMB - Polymer Modified BitumenNRMB- Natural Rubber Modified Bitumen
CRMB- Crumb Rubber Modified Bitumen
-
8/3/2019 Important Aspects in Road Construction
28/89
Prime Coat over granular base
Application of single coat of low viscosity liquid bituminousmaterial to an absorbent granular surface for anysuperimposed bituminous treatment
Table 500-1,Viscosity requirements and quantity of bituminous primer
Prime Coat over granular base
Application of single coat of low viscosity liquid bituminousmaterial to an absorbent granular surface for anysuperimposed bituminous treatment
Table 500-1,Viscosity requirements and quantity of bituminous primer
KinematicViscosity of Quantity / 10r mer at o (Centistokes)
q.m gs
low porosity 30 60 6 to 9
Mediumporosity
70 140 9 to 12
High porosity 250-500 12 to 15
-
8/3/2019 Important Aspects in Road Construction
29/89
Methodology for Prime Coat
1. Bituminous primer should be slow setting bitumenemulsion, use of cutback being restricted to areas having subzero temperature or for emergency operations.
2. The prime coat should be applied only on the top
most granular base layer, over which bituminous treatment isto be applied. The granular base surface should be sweptclean of dust and loose particles and where required, lightly
and uniformly sprinkled with water to moist the surface.3. The primer should be sprayed uniformly over the drysurface of absorbent granular base, using suitable bitumenpressure distributor or sprayer capable of spraying primer at
specified rates and temperature so as to provide a uniformlyunbroken spread of primer. Normal temperature range ofspraying emulsion should be 20C to 60 C. The rate of application depends upon the porosity characteristics of the
surface to be primed and is given in above table.
-
8/3/2019 Important Aspects in Road Construction
30/89
DOs Donts
1. Use slow setting emulsionand restrict the use ofcutback to subzero
temperature conditions oremergency operations.2. Use only pressure
1. Do not apply primerwhen the atmospherictemperature in shade is
less than 10C or whenthe weather is foggy, rainy
or windy.sprayers.
3. Preferably lay a trialsection.
4. The Contractor to
demonstrate at a sprayingtrial to ensure that theequipment is capable of
producing a uniform spray.
. o no a ow pour ng oprimer using perforatedcans.3. Do not allow traffic on
primed surface.4. Do not applybituminous material to a
wet surface.
-
8/3/2019 Important Aspects in Road Construction
31/89
Table 500-2, rate of application of tack coat
Bituminous material
503 Tack Coat ( MORT & H )503.4.3: The application of tack coat shall be at the rate
specified in the contract and shall be applied uniformly. Ifrate of application of tack coat is not specified in the
contract then it shall be at the rate specified in table 500-2
Kg/10 Sq.MNormal bituminous surfaces 2.0 to 2.5
Dry and hungry bituminous surfaces 2.5 to 3.0
Granular surfaces treated with primer 2.5 to 3.0Non- bituminous surfaces:
Granular base (not primed)
Cement concrete pavement
3.5 to 4.0
3.0 to 3.5
-
8/3/2019 Important Aspects in Road Construction
32/89
S.No Type ofsurface
Rate of
spray(emulsion)
K /M2
Rate of spray
(Bitumen -VG-10)K /M2
Rate of application of tack coat
as per table 4 of IRC:SP: 78-2008
iBituminous
surface0.20
to 0.300.30 to 0.40
ii
Granularsurface
treated withprimer
0.25to 0.30
0.35 to 0.40
-
8/3/2019 Important Aspects in Road Construction
33/89
Methodology for Tack Coat
1. Use a rapid setting bitumen emulsion for applying a tack coat,the use of cutback being restricted to areas having sub-zerotemperature or for emergency applications.2. The surface on which tack coat is to be applied should be
clean, free from dust, dirt and any extraneous materials and dry.3. The surface should be prepared as per sub-section 501.4. The binder should be sprayed uniformly over the surfaceusin suitable bitumen ressure s ra er ca able of s ra in
bitumen and emulsion at specified rates and temperature so asto provide a uniformly unbroken spread of bitumen emulsion.For smaller jobs, a pressure hand sprayer may be used. Normalrange of spraying temperature should be 20C-60C in case of
emulsion and 50 C-80C in case of cutback. The rate of application depends upon the type of surface and is given inabove Table.5. The surface should be allowed to cure until all the volatiles
have evaporated.
DO D t
-
8/3/2019 Important Aspects in Road Construction
34/89
DOs Donts
1.Plan the work so that nomore than the necessarytack coat for the daysoperation is placed on
surface.
1. Do not apply tackcoat whenatmospherictemperature is less
than 10C or whenweather is foggy, rainy
cutback carefully to avoidfire mishap.
2. Do not apply tackcoat on a wet surface.
3. Do not allow anyequipment or vehicles
on Tack Coat.
-
8/3/2019 Important Aspects in Road Construction
35/89
Physical Requirements of Coarse Aggregates forBM/DBM/SDBC/BC
Table 500-3 for BM, table 500-8 for DBM, table 500-14 forSDBC & 500-17 for BC of 4th Revision
Property Test Specification
Code
Reference
CleanlinessGrain sizeanalysis
Max. 5% passing0.075mm sieve
IS: 2386 part1
Particleshape
Flakiness andElongation
IndexMax. 30% IS: 2386 part
1
Strength
Los Angeles
Abrasion Valueor
Max. 40% for BM ,
35% for DBM & SDBC&30% for BC
IS: 2386 part4
Aggregate
Impact Value
Max 30%for BM,27%for DBM & SDBC,
24%for BC
IS: 2386 part
4
h i l i i d
-
8/3/2019 Important Aspects in Road Construction
36/89
DurabilitySoundness:
Sodium Sulphate
Magnesium Sulphate
12%
18%
IS: 2386 part 5
Absorption Water Absorption 2% IS: 2386 part 3
Coating and Stripping
Physical requirements continued
o ggregate tumen :
WaterSensitivity
Retained TensileStrength Min. 80%
to be done ifstripping fails
Polishing Polished Stone Valuefor SDBC and BC
Min. 55 Bs: 812 part114
-
8/3/2019 Important Aspects in Road Construction
37/89
513 Seal Coat
Requirement of materials fo seal coat
Type
Aggregate Bitumen Emulsion
SpecificationSize mm
Quantitycum
specification QuantityKg/10 sqm
specification QuantityKg/10sqm
-
A
. .
6mm 0.09 S-65 9.8 RS 15.0
B
2.36- 0.18
Sand ordust
0.06 S-90 6.8 SS 10.0
Type A seal coat is for high rainfall areas ( over 1500mm )
Table 500 4 COMPOSITION OF BITUMINOUS MACADAM (4th Revision)
-
8/3/2019 Important Aspects in Road Construction
38/89
Table 500-4, COMPOSITION OF BITUMINOUS MACADAM (4th Revision)
Mix Designation Grading I Grading II
Nominal AggregateSize
40 mm 19 mm
Layer Thickness 80 100 mm 50 75 mm
IS Sieve (mm) Cumulative % by weight of total aggregate passing
45 100 -----
37.5 90 100 ------
26.5 75 100 100
19 --- 90 10013.2 35 61 56 88
4.75 13 22 16 36
2.36 4 19 4 19
0.30 2 -10 2 -10
0.075 0 -8 0 -8
Bitumen content, % 3.10 3.40 3.30 3.50
Bitumen Grade 35 to 90 35 to 90
Cl 4 2 3 1 of IRC: 37 2001
-
8/3/2019 Important Aspects in Road Construction
39/89
Cl. 4.2.3.1 of IRC: 37-2001BM has low binder content and high
voids and is thus not impervious to water.Effect of high voids is reduced stiffness and
increased stress concentrations. From fatigueconsiderations, the detrimental effects ofvoids is more a arent at low tem eratures.
During prolonged hot spells, BM mix willoperate over a very low stiffness range.
Hence, use of BM may desirably be
restricted only to roads designed to carrytraffic less than 5 msa. DBM is recommendedfor roads designed to carry higher traffic than
5 msa
Methodology for Bituminous Macadam
-
8/3/2019 Important Aspects in Road Construction
40/89
Methodology for Bituminous Macadam1. Prepare the base on which bituminous macadam
course is to be laid and shape to the specified lines, grade andcross-section.
2. Apply tack coat over the base preparatory to laying ofthe bituminous macadam.
3. Bituminous Macadam should be prepared in a Hot MixPlant of adequate capacity Ensure manufacturing and rollingtemperatures for Bituminous Macadam as specified.
.
lay by means of an approved self-propelled mechanical paver.5. Commence initial rolling with 80-100 kN rollers (three-
wheel or tandem type), beginning from the edge and progressing towards the centre longitudinally. On super
elevated portions, rolling should progress from lower to upperedge parallel to centre line of pavement. Thereafter, do intermediate rolling with vibratory or pneumatic tyred roadrollers. This should be followed by final rolling while the
material is still workable.
Methodology for Bituminous Macadam continued
-
8/3/2019 Important Aspects in Road Construction
41/89
Methodology for Bituminous Macadam continued6. Any high spots or depressions noticed after the roller has
passed over the whole area once should be corrected byremoving or adding premixed material. Rolling shouldrecommence thereafter. Each pass should have an overlap of atleast one-third of the track made in the preceding pass.
Rolling should be continued till all roller marks have beeneliminated.7. For single lane roads no longitudinal joint is required, while
-
depending on the paver width.8. For making longitudinal or transverse joint, cut the edges ofthe bituminous layer laid earlier to their full depth so as toexpose fresh surface and apply a thin coat of binder. Lay
adjacent new layer and compact flush with the existing layer. 9.Cover the bituminous macadam with the wearing course withina period of 48 hours. If there is any delay in providing wearingcourse the bituminous macadam surface should be covered
with a seal coat before opening to traffic.
DOs Donts
-
8/3/2019 Important Aspects in Road Construction
42/89
1.Ensure that stone aggregate
conforms to the physicalrequirements and gradingrequirements and are dry and clean.2. In case the aggregate has pooraffinity to bitumen use anti strippingagent with the approval of Engineer.3. While transporting the mixture itshould be suitably covered by
1. Do not undertake the work infoggy, rainy or windy weather orwhen the atmospheric temperaturein the shade is less than 10C.2. Do not allow the difference intemperature of binder and
aggregate to increase beyond 14OCat any time.3. Do not allow the premix materialto adhere to the roller wheels. (Do
arpau n.
4. Rolling operations should becompleted before the mix becomesunworkable5. Maintain strict control on
temperature while mixing androlling.6. Regulate the rate of delivery ofmaterial to paver to enable it to
operate continuously.
no use excess wa er or e
purpose. Light sprinkling shoulddo.)4. Do not use lubricating oil on thewheels of the roller to prevent mixfrom adhering.
5. Do not allow traffic until the mixhas been covered with a wearingcourse.6. Do not move roller at a speed
more than 5 km/h.
-
8/3/2019 Important Aspects in Road Construction
43/89
Mix Design of DBM, SDBC or BC
1 Proportioning of Coarse aggregate and Fine
aggregate to satisfy the specified gradation.
specified values of:a) Marshal Stability Valueb) Flow Value
c) Voids in Mineral Aggregate (VMA)d) Voids Filled by Bitumen (VFB)e) Air Voids in Mix
Table 500-10 Composition of Dense Graded Bituminous Macadam Pavement Layers.
-
8/3/2019 Important Aspects in Road Construction
44/89
p y
Grading 1 2
Nominal aggregate size 40 mm 25 mm
Layer Thickness 80-100mm 50-75 mm
IS Sieve (mm) Cumulative % by weight of total aggregate passing
45 100
37.5 95-100 100
26.5 63-93 90-100
- -
13.2 55-75 56-804.75 38-54 38-54
2.36 28-42 28-42
0.3 7-21 7-21
0.075 2-8 2-8
Bitumen content % bymass of total mix
Min 4.0 in 4.5
Bitumen grade (pen) 65 or 90 65 or 90
-
8/3/2019 Important Aspects in Road Construction
45/89
Description Requirements
Minimum stability (KN at600C)
9.0
Minimum flow (mm) 2
Maximum flow (mm) 4
Table 500-11, Requirements of DBM layer
Compaction level (Number ofblows)
75 blows on each face ofthe specimen
Percent air voids 3-6
Percent voids in mineral
aggregate (VMA) See table 500-12
Percent voids filled withbitumen (VFB)
65-75
-
8/3/2019 Important Aspects in Road Construction
46/89
IS Sieve(mm)
Cumulative per cent passingby weight of total aggregate
0.6 100
0.3 95 - 100
-
Table 500-9, Grading Requirements of mineral filler
.
The filler shall be free from organic impurities and have a Plasticity
Index not greater than 4. The Plasticity Index requirement shall not apply iffiller is cement or lime. When the coarse aggregate is gravel, 2 per centbyweight of total aggregate, shall be Portland cement or hydrated lime and the
percentage of fine aggregate reduced accordingly. Cement or hydrated limeis not required when the limestone aggregate is used. Where the aggregates
fail to meet the requirements of the water sensitivity test in Table 500-8, then2 per cent by total weight of aggregate, of hydrated lime shall be addedwithout additional cost.
Table 500-12, Minimum per cent voids in mineral aggregate (VMA)
-
8/3/2019 Important Aspects in Road Construction
47/89
NominalMaximum
particle size
Minimum VMA, per cent related to design airvoids, per cent
3.0 4.0 5.0
9.5 14.0 15.0 16.0
12.5 13.0 14.0 15.0
, p gg g ( )
19.0 12.0 13.0 14.0
25.0 11.0 12.0 13.0
37.5 10.0 11.0 12.0
Notes: 1. The nominal maximum particle size isone size larger thanthe first sieve to retain more than 10%.
2. Interpolate minimum voids in the mineral (VMA) for design air voids
values between those listed
Table 500-15 Composition Of Semi Dense Bituminous Concrete Pavement Layers.
-
8/3/2019 Important Aspects in Road Construction
48/89
Grading 1 2
Nominal aggregate size 13 mm 10 mm
Layer Thickness 35-40mm 25-30 mm
IS Sieve (mm) Cumulative %by weight of total aggregate passing
19 100
13.2 90-100 100
9.5 70-90 90-100
. - -
2.36 24-39 24-39
1.18 15-30 15-30
0.3 9-19 9-19
0.075 3-8 3-8Bitumen content % by
mass of total mixMin 4.5 Min 5.0
Bitumen grade (pen) 65* 65*
* Only in exceptional circumstances, 80/100 penetration grade bitumen may be used
-
8/3/2019 Important Aspects in Road Construction
49/89
Description Requirements
Minimum stability (KN at600C)
8.2
Minimum flow (mm) 2
Maximum flow (mm) 4
Table 500-16, Requirements of SDBC layer
Compaction level (Number ofblows)
75 blows on each face ofthe specimen
Percent air voids 3-5
Percent voids in mineral
aggregate (VMA) See table 500-12
Percent voids filled withbitumen (VFB)
65-78
Table 500-18 Composition of Bituminous Concrete Pavement Layers.
-
8/3/2019 Important Aspects in Road Construction
50/89
Grading 1 2
Nominal aggregate size 19 mm 13 mm
Layer Thickness 50-65mm 30-45 mm
IS Sieve (mm) Cumulative % by weight of total aggregate passing
26.5 100
19 79-100 100
13.2 59-79 79-100
9.5 52-72 70-88
4.75 35-55 53-712.36 28-44 42-58
1.18 20-34 34-48
0.6 15-27 26-38
0.3 10-20 18-28
0.15 5-13 12-20
0.075 2-8 4-10
Bitumen content % bymass of total mix
5.0 - 6.0 5.0 - 7.0
Bitumen grade (pen) 65 65
Table 500-19, Requirements of BC layers
-
8/3/2019 Important Aspects in Road Construction
51/89
Minimum stability (kN at60 C)
9.0
Minimum flow (mm) 2
Maximum flow (mm) 4Compaction level(Number of blows)
75 blows on each of the twofaces of the specimen
q y
Percent air voids 3-6
Percent voids in mineralaggregate (VMA)
See table 500-12
Percent voids filled with
bitumen (VFB) 65-75
Loss of stability onimmersion in water at
60C (ASTM D 1075
Minimum 75 % retainedstrength
Table 5500-13, Permissible variations from job mix formula for DBM, SDBC, and BC
-
8/3/2019 Important Aspects in Road Construction
52/89
Description Permissible variation
Base/binder course Wearing course
Aggregate passing 19mm sieve or
larger
8% 7%
Aggregate passing 13.2mm, 9.5mm 7% 6%
Aggregate passing 4.75mm 6% 5%
Aggregate passing 2.36mm, 1.18mm,0.6mm
5% 4%
Aggregate passing 0.3mm, 0.15mm 4% 3%
Aggregate passing 0.075mm 2% 1.5mm
Binder content 0.3% 0.3%
Mixing temperature 10C 10C
Reasons for Poor performance of Asphalt mixes
-
8/3/2019 Important Aspects in Road Construction
53/89
Reasons for Poor performance of Asphalt mixes
1 Inadequate initial compaction making themix vulnerable to high secondary compaction
under traffic.2 Relatively high asphalt contents thatpermit the reduction of air voids to less than 3per cent under secondary compaction, leadingto rutting under heavy axle loads whenpavement temperatures rise in summer.
3 Low asphalt contents and high air voids
in the mix leading to top- down cracking,raveling and stripping making the mix lesdurable.
-
8/3/2019 Important Aspects in Road Construction
54/89
Modified Penetration Macadam (MPM) 506 Rural Roads Manual
-
8/3/2019 Important Aspects in Road Construction
55/89
Description
Rate of application for 10sqm area
75mm 50mm
Bituminoussurface,
cum
On WBMsurface,
cum
Bituminoussurface,
cum
On WBMsurface,
cum
40mm size handbroken metal
0.9 0.6
12mm size chi s 0.18 0.18
Description
Bitumen rate of application for 10sqm area (kg)
75mm 50mm
Bituminoussurface On WBMsurface Bituminoussurface On WBMsurface
Bitumen for grouting
Tack coat for existing
bituminous surface
20
5
20
-
17.5
5
17.5
-
1. Spread coarse aggregate of 40 mm size metal uniformly at the rate of 0.9cum for 75 mm thickness (0.6 cum for 50 mm thickness) per 10 sqm area to
-
8/3/2019 Important Aspects in Road Construction
56/89
( ) p qproper camber/ super-elevation. Remedy all high spots and depressions by
removing or adding aggregates.2. Commence rolling with 80-100 kN rollers (three-wheel or tandem type),beginning from the edge and progressing towards the centre longitudinally. Onsuper elevated portions, rolling should progress from lower to upper edge
parallel to centre line of pavement.3. Correct any irregularities noticed after the roller has passed over the wholearea once by loosening the surface and removing or adding the coarseaggregates followed by rolling. Continue rolling till the entire surface has beenrolled to desired compaction such that there is no crushing of aggregates and al
roller marks have been eliminated. Each pass of roller should overlap not lessthan one-third of the track made in the preceding pass.4. Heat bitumen (paving grade S-35 to S-90) to a temperature of 160C to180C and spray uniformly on aggregate layer at the rate of 20 kg per 10 m2 for
75 mm thick layer and 17.5 kg per 10 m2
for 50 mm thick layer.5. Immediately after application of bitumen, spread 12 mm size key aggregatesat a uniform rate of 0.18 cum for 75 mm thickness (0.12 cum for 50 mmthickness) per 10 m2 so as to cover the surface completely and roll. Rollingshould continue until the key aggregates are firmly embedded in position and
stop moving under roller
DOs Donts
-
8/3/2019 Important Aspects in Road Construction
57/89
1. Ensure that aggregatesconform to gradingspecified and are dryand clean at the time of
laying.
1. Do not undertake thework in foggy. rainy orwindy weather or whenthe atmospheric
temperature in theshade is less than l0C.
.
temperature of bitumenappropriate tothe grade of bitumen.
3. Remove excessivedeposits of binder
during spray operation.
2. Do not allow anytraffic over Built upspray grout
without laying wearingcourse or seal coat.
512 Open Graded Pre Mix Carpet (OGPC)20 mm thick pre mix carpet
-
8/3/2019 Important Aspects in Road Construction
58/89
20 mm thick pre mix carpet
Aggregate013.2mmchips = 0.18cum11.2mm chips = 0.09cum
(13.2mm = passing 22.4 & retained on 11.2mm sieves11.2mm chips passing 13.2mm
AIV < 40%, FIV < 25% and WA < 1% for coarse aggregates.
reta ne on 5.6mm s eves
BinderBitumen @ 14.6 kg/ 10sqmEmulsion @ 21.5 kg/ 10sqm
Appropriate technology and machinery for
-
8/3/2019 Important Aspects in Road Construction
59/89
pp p gy y
Premix Carpet
1.Applying Prime Coat : Hand-held lance providedwith sprayer, operated by compressor
2.Applying Tack Coat : Hand-held lance provided,
3.Mixing of aggregates and bitumen in : Mini HotMix Plant, capacity of with specified quantities
around 6 tonnes/hour
4.Transporting from the mixer to site : Tarpaulin-
covered tractor-trailer or hand barrows
Methodology for OGPC1 Mixing should be thorough to ensure that a homogenous mixture is
-
8/3/2019 Important Aspects in Road Construction
60/89
1.Mixing should be thorough to ensure that a homogenous mixture is
obtained. The temperature of bitumen at the time of mixing should be in therange of 150 C to 163 C and that of aggregates 155C to 163C, providedthat the difference between the temperature of aggregate and the binder shouldnot exceed 14C. If modified bitumen is used, temperature should be asrecommended in Subsection 512. The temperature at the time of discharge of
the mixture should be between l30C and 160C.2. The premixed material shall be spread on the road surface with rakes.3. Commence rolling with 80-100 kN rollers (three-wheel or tandem type),
.
super elevated portions, rolling should progress from lower to upper edgeparallel to centre line of pavement). Continue rolling operations till a smoothuniform surface is achieved and all roller marks are eliminated. Each passshould have an overlap of at least one-third of the track made in the precedingpass.
4. Correct any high spots or depressions noticed after the roller haspassed over the whole area once by removing or adding premixed material andre-compacting.
5. Provide a seal coat to the surface immediately after laying the carpet
as per details in Sub-section
DOs Donts
1 Ensure that the 1 Do not allow manual
-
8/3/2019 Important Aspects in Road Construction
61/89
1. Ensure that the
aggregates and bindersatisfy the specifiedrequirements.
2. Before opening thebitumen emulsion drum,
1. Do not allow manual
mixing.
2. Do not undertake work
in foggy, rainy or windyweather or when theminimum air temperature
ro e rum a s ow
speed, to and fro at leastfive times for a distance ofabout 10 m to ensure
proper distribution ofstorage sedimentation.
3. As far as possible use
suitable cold mixin lant
s ess an .
3. Do not allow any trafficunless the emulsion is
properly set and thesurface has acquiredadequate stability
-
8/3/2019 Important Aspects in Road Construction
62/89
512 Mix Seal surfacing
-
8/3/2019 Important Aspects in Road Construction
63/89
Table 500-26, aggregate gradationIS sieve
designation
(mm)
Cumulative per cent by weight oftotal aggregate passing
Type A Type B
13.2 mm - 100
11.2 mm 100 88 - 100
5.6 mm 52 - 88 31 - 52
2.8 mm 14 - 38 5 - 25
0.090 mm 0 - 5 0 - 5
Bitumen 22 kg / 10 sqm 19 kg / 10 sqm
As per Manual for construction and supervision ofbituminous works Type A grading may be used for 25mm
thick MSS also, by proportionately increasing bitumen
content
Stone Matrix AsphaltA IRC SP 79 2008
-
8/3/2019 Important Aspects in Road Construction
64/89
As per IRC: SP: 79 -2008
SMA is a gap graded hot mix which contains:a) Coarse aggregate: 70-80%
b) binder content: 6-7%c) filler: 8-12%
. .
e) layer thickness: 40 to 75mm
Bitumen for SMA shalll be VG-30 grade
bitumen or PMB-40 grade BitumenFiller shall be stone dust and /or hydrated lime
passing in 0.3mm sieve by 95 100% and in
0.075mm sieve by 85 100%
-
8/3/2019 Important Aspects in Road Construction
65/89
Causes of superior performance of SMA
1) Higher amount of coarse aggregateprovides better stone-to-stone contact,which rovides hi hl rut resistant
bituminous course.2) Higher binder content adds durability3) Stabilising additive reduces drain
down of binder
Physical Requirements of Coarse Aggregates for SMAPhysical Requirements of Coarse Aggregates for SMA
CodeCode
-
8/3/2019 Important Aspects in Road Construction
66/89
PropertyProperty TestTest SpecificationSpecificationCodeCode
ReferenceReference
CleanlinessCleanliness Grain size analysisGrain size analysis% passing 0.075mm sieve% passing 0.075mm sieve
< 2%< 2%IS: 2386 part 1IS: 2386 part 1
ParticleParticle
shapeshape
Combined FlakinessCombined Flakiness
and Elongation Indexand Elongation Index
< 30%< 30% IS: 2386 part 1IS: 2386 part 1
StrengthStrength
Los Angeles AbrasionLos Angeles Abrasion
ValueValue< 25%< 25%
IS: 2386 part 4IS: 2386 part 4
ggrega e mpac a ueggrega e mpac a ue 55%> 55%
durabilitydurability
Soundness (either Sodium or Magnesium)Soundness (either Sodium or Magnesium) 5 cycles5 cycles
Sodium SulphateSodium SulphateIS: 2386 part 5IS: 2386 part 5
< 12%< 12%
Magnesium SulphateMagnesium Sulphate < 18%< 18%WaterWater
AbsorptionAbsorptionWater AbsorptionWater Absorption IS: 2386 part 3IS: 2386 part 3 < 2%< 2%
*Polishing Value does not apply when the coarse aggregate is used in the 19mm
SMA, which is used as an intermediate (binder) course
SMA Designation 13mm SMA 19mm SMA
Composition of Stone Matrix Asphalt
-
8/3/2019 Important Aspects in Road Construction
67/89
SMA Designation 13mm SMA 19mm SMA
Nominal Aggregate size 13mm 19mm
Nominal layer thickness 40 50mm 45 75mm
IS sieveCumulative % passing
by weight of total
aggregates
Cumulative %passing by weightof
total aggregates
26.5 - 100
-
13.2 mm 90 - 100 45 - 709.5 mm 50 - 75 25 - 60
4.75 mm 20 - 28 20 - 28
2.36 mm 16 - 24 16 - 24
1.18 mm 13 21 13 - 21
0.6 mm 12 18 12 - 18
0.3 mm 10 - 20 10 - 20
0.075 mm 8 - 12 8 - 12
515.Mastic Asphalt
-
8/3/2019 Important Aspects in Road Construction
68/89
Mastic Asphalt is used as a wearing course for bridgedecks and heavily stressed intersections in urban areas. Thisis a homogeneous mixture of well graded aggregates,limestone powder filler and a hard grade bitumen (10 to 20
pen) to yield a plastic and void less mass, which whenapplied hot can be trowelled and floated to form a very denseim ermeable surfacin .
Binder content is 14 to 17%.Normal thickness is 25 to 50mm.
Hardness number (IS: 1195-1978): Mastic Asphalt shall have ahardness number of 60 to 80 at the time of manufacture at
25C prior to the addition of coarse aggregate and 10 to 20 at25C at the time of laying after the addition of coarse
aggregate.
Table 500 29, Requirements for physicalproperties of binder
-
8/3/2019 Important Aspects in Road Construction
69/89
PropertyTest
methodRequirements
Penetration at 25C IS:1203 15 5
Softening Pont, C IS:1205 65 10
properties of binder
C Max
IS:1212 2.0
Solubility in trichloroethylene,% by mass Min
IS:1216 95
Ash, (mineral matter) by massMax IS:1217 1.0
Table 500 30, Grade and thickness of Mastic AsphaltPaving and Grading of Coarse aggregate
-
8/3/2019 Important Aspects in Road Construction
70/89
ApplicationThickness range
(mm)
Nominal size ofcoarse
aggregate (mm)
Coarseaggregate, % by
mass of totalmass
Roads andCarriageway
25 - 50 13 40 10
Heavily stressed
g g gg g
areas .e.
junctions andtoll plazas
40 - 50 13
Nominal size of coarseaggregate
13mm
IS Sieve (mm) Cumulative % passing by weight
19 100
13.2 88 - 100
2.36 0 - 5
Table 500 31, Grading of fine aggregate(inclusive of Filler)
-
8/3/2019 Important Aspects in Road Construction
71/89
IS SievePercentage by
weight of aggregate
Passing 2.36mm but retainedon 0.600mm 0 - 25
Passin 0.600mm but
( )
retained on 0.212mm
Passing 0.212mm butretained on 0.075mm
10 - 30
Passing 0.075mm 30 - 55
Filler shall be limestone powder passing 0.075mm sieveand shall have a calcium carbonate content of not less than80%by weight when determined in accordance with IS: 1514
-
8/3/2019 Important Aspects in Road Construction
72/89
-
8/3/2019 Important Aspects in Road Construction
73/89
501.6 COMPACTION
Commence From Edges And Progress
Towards Centre
Initial Breakdown Rolling 8 To 10 T Smoothee o er
Intermediate Rolling 8-10 T Dead Wt. OrVibratory Roller, Pneumatic Tyred Roller :12-15 TWt. 5.6 Kg/Sq.Cm Pressure.
Finished Rolling 6-8 T Smooth WheelTandem Roller
-
8/3/2019 Important Aspects in Road Construction
74/89
Recommended Frequency and Amplitude
For Vibratory Compaction
Lift frequency amplitude
Thin maximum low
thick minimum high
The frequency of vibration is the number of complete cycles thatthe eccentrics rotate per minute. The faster the rotation of the eccentrics,the greater the frequency of vibration.
-
8/3/2019 Important Aspects in Road Construction
75/89
Some vibratory rollers can operate at only one frequency or havea very limited selection of frequencies.
Other vibratory rollers can alter the frequency of the applied loadbetween 1600 and 4000 vibrations per minute.
Frequencies below 2000 vibrations per minute are not normallyacceptable to compact asphalt mixtures.
If the width of the roller drum is 2.1 m (7 ft), only two passes ofthe roller are needed to cover the 3.7 meter (12 ft) wide lane, including a150 mm (6 in) overhang at each edge of pavement.
A roller that is 1.8 m (5.9 ft) wide cannot cover the complete 3.7meter (12 ft) wide lane in only two passes.
Three passes of the 1.8 m (6 ft) wide roller would be necessary toproperly compact the lane.
If the roller had drums that were 1.5 m (5 ft) wide, three passes ofthe roller would be required, similar to the roller with the 1.8 m (6 ft) widedrums.
A 1.4 m (4.5 ft) drum needs four passes for one coverage.For thick lifts, first pass should be about 0.30 m (1 ft) in from edge to
prevent shoving.
-
8/3/2019 Important Aspects in Road Construction
76/89
AmplitudeAmplitude
Normal values of nominal amplitude range from 0.25 to 1 mm (1/100 to1/32 in).
Some rollers can operate at only one fixed amplitude, while others have
high and low amplitude positions.
Typically as the layer thickness increases, it is often advantageous toincrease the nominal amplitude applied to the asphalt mix.
Unless high amplitude is needed to achieve a particular density level,the vibratory roller should be operated in low amplitude.
Ask: Does changing frequency change the compaction effort? (Yes. 10-12
vibrations/ft. Never less than 10.)
-
8/3/2019 Important Aspects in Road Construction
77/89
Impact SpacingImpact Spacing
High FrequencyHigh FrequencyLow FrequencyLow Frequency
DIRECTION OF TRAVELDIRECTION OF TRAVEL
FrequencyFrequency
ONE ROLLER PASS
-
8/3/2019 Important Aspects in Road Construction
78/89
1122
CROWNCROWN22--lanes @lanes @
O O SS
44
33
55
66
(12 ft)(12 ft)
Drum WidthDrum Width= 1.8 meters= 1.8 meters
6 ft6 ft
The capabilities of each type of roller vary,
-
8/3/2019 Important Aspects in Road Construction
79/89
however, with mat thickness, mix temperature, mixdesign and environmental conditions.In addition, the number of passes required
depends on the position of the rollers in the roller
train. A test strip aids us in this decision process.
,
which can tell us whether the designed mix isresistant to rutting. It should be able to proof test themixes and tell us whether a mix satisfies a definitecriteria and passes or fails the torture test. This test
should be a laboratory test method so that it can beused on designed mixes, and it should be a simpletest method so that it can be used routinely by the
folks who actually build our pavements.
Rolling
-
8/3/2019 Important Aspects in Road Construction
80/89
Rolling is a highly technical and skillful operationduring which poor judgment is likely to result in failure toachieve the required compaction. Although various
guidelines describing sound engineering practices forcompaction procedures are available each case will have itsunique features and there can be no substitute forexper ence n ac ev ng success u compact on.
Initial or breakdown RollingIntermediate Rolling
Finish Rolling
Rolling sequence: Transverse joint, Longitudinal joint,Lower edge rolling, Break-down rolling, Intermediate
rolling(vibratory) Finished rollin
-
8/3/2019 Important Aspects in Road Construction
81/89
2.25
2.3
2.35
2.4
Relationship of density with passes
sity
PASSINGDENSITY
Use 3 to 4 passes
2
2.05
2.1
2.15
.
0 2 4 6 8
Too
many
passes
Den
No of Passes
-
8/3/2019 Important Aspects in Road Construction
82/89
Table 900 2,Maximum permitted number of irregularities
-
8/3/2019 Important Aspects in Road Construction
83/89
Surfaces ofcarriageways and
paved shoulders
Surfaces of laybys,service roads and all
bituminous courses
Irregularity 4mm 7mm 4mm 7mm
Length(m) 300 75 300 75 300 75300
75
National highways/
Expressways 20 9 2 1 40 18 4 2
Roads of lowercategory
40 18 4 2 60 27 6 3
The maximum allowable difference between the roadsurface and underside of a 3m straight edge when
-
8/3/2019 Important Aspects in Road Construction
84/89
For pavement surface (bituminousand cement concrete)
3mm
placed parallel with, or at right angles to the center lineof the road at points decided by the Engineer
For bituminous courses 6mm
For granular sub-base or basecouses
8mm
For sub-base under concrete
pavements 10mm
903.2 Tests on Earthwork for embankment, sub-gradeconstruction and cut formation
-
8/3/2019 Important Aspects in Road Construction
85/89
Test type As per codeFrequency of
testing
Sand Content IS:2720 part 42 per 3000 cubic
meters
Plasticity IS:2720 part 52 per 3000 cubic
meters
Density IS:2720 part 8
2 per 3000 cubic
meters
DeleteriousContent
IS:2720 part 27As and whenrequired by
engineer
Moisture Content IS:2720 part 21 test per 50 cubic
meter
Soaked/ un-soaked
CBR
IS:2720 part 161 per 3000 cubic
meters
Important quality Control Tests for sub base andbase
-
8/3/2019 Important Aspects in Road Construction
86/89
Test Type of construction Frequency (min)
Gradation
(IS:2386 part1)
Granular Sub Base
WBM/ WMM
1 per 200cum
1 per 100cum
Atterbergs limits
(IS:2720 part 5)
Granular Sub BaseWMM on aggregates
WBM(for binding material)
1 per 200cum1 per 100cum
1 per 25cum
Moisture content
(IS:2720 part 2)
Granular Sub Base
(prior to compaction) 1 per 250sqm
Density (IS: 2720 part28) for compacted layer
Granular Sub Base 1 per 500sqm
CBR (IS:2720 part 16) Granular Sub Base As required
AIV (IS:2386 part 4) WBM/ WMM 1 per 100cum
FIV and EIV
(IS:2386 part 1)WBM/ WMM 1 per 200cum
Important quality Control Tests for Prime Coatand tack coat
-
8/3/2019 Important Aspects in Road Construction
87/89
Test Reference Frequency (min)
Quality of binder IS:73, IS:217 andIS: 8887
As applicable in thecodes
Temperature forapplication - At regular intervals
Rate of spread of
binder
-One test per 500m2
and not less than 2
per day
Tests for Bituminous Macadam
Test type As per code Frequency of testing
-
8/3/2019 Important Aspects in Road Construction
88/89
Quality of binderIS:73, IS:217 and
IS: 8887As applicable in the codes
Aggregate Impact Value LosAngeles Abrasion Value
IS:2386 part 4 1 test per 50 cubic meter
Flakiness and ElongationIndex
IS:2389 part 1 1 test per 50 cubic meter
Initially 1 set of 3 specimens for each
tr pp ng a ue :9241 source an su sequent y y c ange nquality of aggregates
Water Absorption IS:2386 part 3 - DO -
Water Sensitivity of mix AASHTO T83 In case of failure in stripping test.
Soundness IS:2386 part 5 1 test by each method for each source
Binder content and grading - 2 tests per day per plant
Density - 1 test per 250 M2
Tests for DBM, SDBC and BCIn addition to the tests on BM
-
8/3/2019 Important Aspects in Road Construction
89/89
Test type As per code Frequency of testing
Sand Equivalent Test Is:2720 part 37 As required
Plasticity Index IS:2720 part 5 As required
Polished Stone value BS:812 part114 As required for SDBC and BC
Mix grading -
1 set of tests on individual constituents and
mixed aggregate from the dryer for each 400T of mix subject to a minimum of 2 per plant
per day
Stability of MixMS 2 of Asphaltic
Institute3 Marshall specimens for 400M3 subject to a
minimum of 2 per day per plant
Control of bindercontent and grading
- 1 test for 400M3 subject to a minimum of 2
per day per plant
Rate of spread of mixedmaterial
-Regular control through checks on the
weight of mied material and layer thickness.