important aspects in road construction

Upload: kaviprakash6992

Post on 06-Apr-2018

216 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/3/2019 Important Aspects in Road Construction

    1/89

  • 8/3/2019 Important Aspects in Road Construction

    2/89

  • 8/3/2019 Important Aspects in Road Construction

    3/89

    305. Soils unsuitable for embankment,sub grade and shoulders

    (i) Material from swamps, marshes and bogs.(ii) Peat, log, stump and perishable material; soil

    classified as OL, OI, OH or Pt as per IS:1498.(iii)Materials susceptible to spontaneous combustion.(iv)Clay having liquid limit exceeding 70% and

    plasticity index exceeding 45%. (tests conductedon material passing 0.425 mm IS Sieve as perIS:2720 part 5)

    (v) Material with salts resulting in leaching action e.g.Soils of pH > 8.5).(vi) Expansive clay with free swelling index (test

    conducted on material passing 0.425 mm IS Sieve

    as per IS:2720 part 40) exceeding 50%

  • 8/3/2019 Important Aspects in Road Construction

    4/89

    305. Soils unsuitable for embankment,

    sub grade and shoulders continued

    (vii) Materials in a frozen condition.

    (viii) Fill materials with a soluble sulphate contentexceeding 1.9 gm of sulphate, (expressed as SO3) per litrewhen tested in accordance with BS:1377 test 10, but using

    -

    or other distance described in the Contract, of concrete,cement bound materials or other cementitious materialsforming part of permanent works.

    (ix) Material with a total sulphate content (expressedas SO3) exceeding 0.5 per cent by mass when tested inaccordance BS: 1377 test 9, shall not be deposited within500 mm or other distance described in the Contract, of

    metallic items forming part of permanent works

  • 8/3/2019 Important Aspects in Road Construction

    5/89

    305.4.4: Embankment and Sub Grade

    Requirements around structures

    The filling around culverts, bridges and other

    structures upto a distance of twice the height ofthe road from the back of the abutment shall becarried out inde endent of the work on the main

    embankment.Material with LL more than 40% and PI more than20% shall not be allowed as backfill for all earth

    retaining structures. Backfill material shallconform to the general requirements given in

    appendix 6 of IRC: 78 (Standard Specifications

    and Code of practice for road bridges-section VII)

  • 8/3/2019 Important Aspects in Road Construction

    6/89

  • 8/3/2019 Important Aspects in Road Construction

    7/89

    Soil group to

    IS: 1498-1970 Visual

    description

    MDD

    Kg/ m3OMC %

    range

    Anticipated

    performance

    Most

    probablepossible

    GW,GP,G

    Granular 1850 to Good to

    Filling behind abutments, retaining walls and retun wallsGeneral guide to the selection of soils on basis of anticipated

    embankment performance appendix - 6, IRC: 78-2000

    , ,HP

    -

    materials

    2280-

    Excellent

    SB, SM,GM, GC,SM, SC

    -

    Granularmaterials

    With soils

    1760 to2160

    9 - 18Fair to

    excellent

    SP - sand1760 to

    185019 - 25

    Fair togood

    MI, MH,

    DL

    CL,

    SM,SB,SC

    Sandy soils &

    silts

    1760 to

    2080 10 - 20

    Fair to

    good

  • 8/3/2019 Important Aspects in Road Construction

    8/89

    Some Test Results on Soils done at Soil Testing Cell (R&B) Vijayawada

    District classification

    LL

    %

    PI

    %

    OMC

    %

    MDD

    g/cc

    FSI

    %

    CBR

    %

    Guntur CH 66 33 21.3 1.6 65 3

    Krishna CI 48 24 19.2 1.63 46 3

    Prakasam SM - NP 13.7 1.90 - 10

    W G CI 39 21 26 1.45 65 4

    Kurnool SC 24 12 8.29 1.75 - 9

    W G CL 31 13 15.7 1.84 33 6

    E G CI 48 24 14.3 1.82 33 7

    Prakasam CH 61 32 24.5 1.4 95 3

    W G CI 49 29 16.7 1.68 200 5

  • 8/3/2019 Important Aspects in Road Construction

    9/89

    401.Granular Sub Base as Drainage Layer:

    Permeability requirement for drainage layer is 20 m/dayas per Pavement Design Guide (1986) by AmericanAssociation of State Highway and Transportation Officials

    (AASHTO) and 4/6 laning manual

    Table: 300-4 of Orange Book: Grading Requirements for

    A re ate Drains

    IS Sieve size Percent passing by weight

    37.5mm 100

    9.5mm 45 - 100

    3.35mm 25 - 80

    600 micron 8 - 45

    150 micron 5 - 10

    75 micron < 5

  • 8/3/2019 Important Aspects in Road Construction

    10/89

    401 Granular Sub Base

    1) Material passing 75 micron sieve shall be less than10%2) Material in mix shall have 10% fines value (for sample insoaked condition as per with BS: 812 (part III) > 50 KN3) Water Absorption(IS: 2386-part 3) of coarse aggregate 2%.If

    it is more, soundness test requirements be satisfied.4) Material in mix passing 425 micron sieve shall have

    Liquid limit < 25% and Plasticity index < 6%.5) Material in the mix shall satisfy specified grading

    6) CBR test (IS: 2720 part 16). In-situ CBR tests are not reliable.

    30% CBR (4 day soaked) for design traffic more than 2 msaas per IRC:37-200120% CBR (4 day soaked) for design traffic less than 2 msaas per IRC:37-2001

    7) Layer thickness:100 mm compacted with smooth wheeled roller

    225 mm compacted with vibratory roller

  • 8/3/2019 Important Aspects in Road Construction

    11/89

    TABLE 400-1, Grading for Close Graded Granular Sub-Base

    (for gravel roads as per Rural Roads Manual IRC:SP 20-2002)

    IS SieveDesignation

    Grading I Grading II Grading III

    75.0 mm 100 -- --

    53.0 mm 80-100 100

    26.5 mm 55-90 70-100 1009.50 mm 35-65 50-80 65-95

    4.75 mm 25-55 40-65 50-80

    2.36 mm 20-40 30-50 40-65

    0.425 mm 10-25 15-25 20-35

    0.075 mm 3-10 3-10 3-10

  • 8/3/2019 Important Aspects in Road Construction

    12/89

    TABLE 400-2. GRADING FOR COARSE GRADEDGRANGULAR SUB-BASE MATERIALS

    IS SieveDesignation

    Percent by weight passing throughthe IS sieve

    Grading I Grading II Grading III

    75.0 mm 100 -- --

    53.0 mm 100

    26.5 mm 55-75 50-80 100

    9.50 mm

    4.75 mm 10-30 15-35 25-45

    0.075 mm < 10 < 10 < 10

    CBR Value(Minimum)

    30 25 20

  • 8/3/2019 Important Aspects in Road Construction

    13/89

    Coarse Aggregates: Gr-I to Gr-III , 40mm & 65 mm

    Screenings: Type-A :6mm and 10mm,Type-B: Stone Dust

    Binder: Stone Dust

    Process of WBMSpreading Metal > Sectioning and Dry Rolling >

    Light Sprinkling of Water > rolling > Application ofScreenings > Brooming > Rolling > Watering &

    Sweeping > Rolling > Application of Binder >Sprinkling of Water & Sweeping > Rolling > Settingand Drying

  • 8/3/2019 Important Aspects in Road Construction

    14/89

    Table 400-7, WBM gradation Requirements

    IS Sieve

    size

    Cumulative percent passing

    Grade I Grade II Grade III

    125mm 100 - -90mm 90-100 100 -

    63mm 25-60 90-100 100

    53mm - 25-75 95-100

    45mm 0-15 0-15 65-90

    22.4mm 0-5 0-5 0-1011.2mm - - 0-5

    Aggregate Impact Value (IS:2386: part-4) :30% (max)

    Combined flakiness and elongation index (IS:2386: part-1) : 30% (max),

  • 8/3/2019 Important Aspects in Road Construction

    15/89

    Table 400 - 8

    404.2.6. Screenings: Screenings to fill voids in thecoarse aggregate shall generally consist of the same material

    as the coarse aggregate. However, where permitted,predominantly non-plastic material such as moorum or gravel(other than rounded river borne material) may be used for thispurpose provided liquid limit and plasticity index of suchmaterial are below 20 and 6 respectively and fraction passing75 micron sieve does not exceed 10 per cent.

    Type of screenings IS Sieve % passing

    Type A 13.2mm

    (6mm & 10mm chips)

    13.2mm 100

    11.2mm 95-100

    5.6mm 15-35180 micron 0-5

    Type B 11.2mm

    (stone dust)

    11.2mm 100

    5.6mm 90-100

    180 micron 15-35

  • 8/3/2019 Important Aspects in Road Construction

    16/89

    DOs Donts

    1. Check aggregates for

    Soundness test when waterabsorption is more than 2%

    2. Soft aggregate should be

    tested for wet aggregate impactvalue.3. Construct shoulders

    simultaneously along with

    1. Do not use any material derived from

    rocks e.g. phyllites, shales or slates.2. Do not use local soil and clayey

    material as screenings or binding

    material unless it meats the

    requirements of PI mentioned

    3. Do not use binding material if

    screenings are of crushable type.

    4. Do not spread coarse aggregate more

    than 3 days in advance of any

    WBM layers.4. Use inverted choke over fine

    grained soil sub-grade.5. Remove BT surface before

    WBM is laid on an existingblack top road.

    6. Remove defective macadam tofull depth and replace by freshmaterial and re-compact.

    subsequent operations.

    5. Do not roll if sub-grade is soft or

    yielding or causes a wave like motion

    while rolling.

    6. Do not lay WBM layer on lime treated

    sub-base until it has attained its strength.7. Do not use screenings to make up

    depressions.

    8. Do not allow traffic till WBM is fully

    set.

  • 8/3/2019 Important Aspects in Road Construction

    17/89

    DOs Donts

    1. Check aggregates for

    Soundness test when waterabsorption is more than 2%

    2. Soft aggregate should be

    tested for wet aggregate impactvalue.3. Construct shoulders

    simultaneously along with

    1. Do not use any material derived

    from rocks e.g. phyllites, shales orslates.2. Do not use local soil and clayey

    material as screenings or bindingmaterial unless it meats the

    requirements of PI mentioned3. Do not use binding material ifscreenings are of crushable type.

    4. Do not spread coarse aggregate

    WBM layers.4. Use inverted choke over fine

    grained soil sub-grade.5. Remove BT surface before

    WBM is laid on an existingblack top road.

    6. Remove defective macadam tofull depth and replace by freshmaterial and re-compact.

    subsequent operations.5. Do not roll if sub-grade is soft oryielding or causes a wave likemotion while rolling.

    6. Do not lay WBM layer on lime

    treated sub-base until it has attainedits strength.7. Do not use screenings to make updepressions.8. Do not allow traffic till WBM is

    fully set.

  • 8/3/2019 Important Aspects in Road Construction

    18/89

    WET MIX MACADAM

    IS Sieve DesignationPer cent by weight

    passing the IS Sieve

    53.00 mm 100

    45.00 mm 95-100

    22.4 mm 60-80

    11.20 mm 40-60

    Table 400-11. Grading Requirements of Aggregates for WMM

    Materials : 40mm, 20mm , 12mm, 6mm &Stone Dust Mixing at Pug Mill with Water,Conveyed to Site, Spreading by Paver and Rolling. Relative Compaction = 98 %

    Aggregate Impact Value (IS:2386: part-4) :30% (max)

    Combined flakiness and elongation index (IS:2386: part-1) : 30% (max),Plasticity Index (IS:2720: part5) shall not exceed 6%.

    4.75 mm 25-402.36 mm 15-30

    600.00 micron 8-22

    75.00 micron 0-8

  • 8/3/2019 Important Aspects in Road Construction

    19/89

    DOs Donts

    1. Ensure compliance of allmaterial and plantrequirements.

    2. Check aggregate forsoundness test whenwater absorption is more

    1. Do not use materialother than crushedstone.

    2. Do not allowsegregation or pockets of

    an .3. Build shoulderssimultaneously along withWMM layers.

    4. Remove BT surfacebefore WMM is laid on anexisting road.

    coarse ne ma er a onthe layer.

    3. Do not allow any trafficon the WMM surfacewithout covering it with awearing course.

  • 8/3/2019 Important Aspects in Road Construction

    20/89

    Bitumen

    grade

    Penetration at

    25C

    Viscosity at 60C in

    Poises

    Kinematic

    viscosity at 135C,

    cSt, Min

    VG - 40 40 to 6040 to 60 4000200 400

    Important Requirements Viscosity

    Grades of Bitumen as per IS: 73 - 2006

    VG - 30 50 to 7050 to 70 3000600 350

    VG - 20 60 to 8060 to 80 2000400 300

    VG - 10 80 to 10080 to 100 1000200 250

  • 8/3/2019 Important Aspects in Road Construction

    21/89

    Stipulations of IS: 73 2006 in selection of VG grade bitumensin place of Penetration Grade (prevailing) bitumens

    Viscosity Grade General Applications

    VG-40

    (40 to 60 penetration)

    Use in highly stressed areas suchas those in intersections, near tollbooths and truck parking lots in

    lieu of old 30/40 penetration grade

    Use for paving for most parts of

    (50 to 70 penetration)

    India in lieu of old 60/70penetration grade.

    VG-20

    (60 to 80 penetration)

    Use in cold climatic, high altituderegions of North India

    VG-10 (80 to 100penetration)

    Use in spraying applications suchas surface dressing and paving invery cold climatic region in lieu of

    old 80/100 penetration grade

  • 8/3/2019 Important Aspects in Road Construction

    22/89

    BitumenBitumenTemp.C

    AggregateTemp.C

    MixTemp.C

    LayingTemp. C

    RollingTemp.C

    VG - 40 160 - 170 160 - 170 160 170 150 min. 100 min.

    Mixing, laying and rolling temperatures for VG grade

    paving bitumen and modified binder

    - - . .

    VG - 20 145 165 145 165 145 165 135 min. 85 min.

    VG - 10 140 160 140 160 140 160 130 min. 80 min.

    Modified 165 - 185 155 175160

    maximum130

    Minimum115

    minimum

  • 8/3/2019 Important Aspects in Road Construction

    23/89

    Manufacturing and Rolling Temperatures

    for penetration grade bitumen

    Bitumen

    Penetration

    Bitumen

    Mixing -C

    Aggregate

    Mixing-C

    Mixed

    Material -

    C

    MinimumRolling

    temp.

    C

    Laying-C

    35- -

    (30-40)

    65

    (60-70)

    150 - 165 150-170 165 Max 90 Min 125 Min

    90

    (80-100)

    140 - 160 140-165 155 Max 80 Min 115 Min

  • 8/3/2019 Important Aspects in Road Construction

    24/89

    Factors Influencing Compaction of Asphalt mixes

    1) Type of Aggregates2) Shape of Aggregates

    3) Grading of mix4) Residual moisture content in aggregates5) Binder conent

    6) Viscosity of binder7) Temperature of mix during compaction

    Note: The first six requirements are taken care inthe mix design, leaving temperature ofcompaction as the single most important affectingthe final result.

  • 8/3/2019 Important Aspects in Road Construction

    25/89

    Recommended use of Cationic Emulsions

    as per IS 8887: 2004

    Type Recommended uses

    Rapid Setting RS 1 Tack Coat

    Rapid Setting RS 2 Surface Dressing

    Medium Setting MS Pre mixes and plant mixes

    Slow Setting SS 1Fog seal, Crack Seal, Prime

    Coat

    Slow Setting SS 2 Slurry Seal and mixes withhigher fine aggregate %

    Slow Setting SS 1 is being used as tack coat in USA

    and other countries

  • 8/3/2019 Important Aspects in Road Construction

    26/89

    Designation

    Grade and RequirementsMethod of

    testCRMB60

    CRMB55

    CRMB50

    Table 500-46, Specifications for modified bitumen

    Penetration at 25C 50 - 70 50 - 60 40- 60

    -

    1978

    Softening point C-min

    50 55 60IS: 1205-

    1978

    Elastic recovery at15C-minimum

    40 35 30ASTM D5976

    1996

  • 8/3/2019 Important Aspects in Road Construction

    27/89

    Minimumpavement

    temperature

    in C

    Maximum Atmospheric Temperatures in C

    < 35o

    c 35o

    c to 45o

    c > 45o

    c

    < - 10 ocPMB/NRMB - 120

    CRMB - 50

    PMB/NRMB - 70

    CRMB - 55

    PMB/NRMB - 70

    CRMB - 55

    Selection Criteria for type of modified bitumen basedon Atmospheric temperature

    +10 oc to-10 oc

    PMB/NRMB - 70CRMB - 50

    PMB/NRMB - 70CRMB - 55

    PMB/NRMB - 40CRMB - 60

    > 10 ocPMB/NRMB - 70

    CRMB - 55

    PMB/NRMB - 70

    CRMB - 55

    PMB/NRMB - 40

    CRMB - 60

    PMB - Polymer Modified BitumenNRMB- Natural Rubber Modified Bitumen

    CRMB- Crumb Rubber Modified Bitumen

  • 8/3/2019 Important Aspects in Road Construction

    28/89

    Prime Coat over granular base

    Application of single coat of low viscosity liquid bituminousmaterial to an absorbent granular surface for anysuperimposed bituminous treatment

    Table 500-1,Viscosity requirements and quantity of bituminous primer

    Prime Coat over granular base

    Application of single coat of low viscosity liquid bituminousmaterial to an absorbent granular surface for anysuperimposed bituminous treatment

    Table 500-1,Viscosity requirements and quantity of bituminous primer

    KinematicViscosity of Quantity / 10r mer at o (Centistokes)

    q.m gs

    low porosity 30 60 6 to 9

    Mediumporosity

    70 140 9 to 12

    High porosity 250-500 12 to 15

  • 8/3/2019 Important Aspects in Road Construction

    29/89

    Methodology for Prime Coat

    1. Bituminous primer should be slow setting bitumenemulsion, use of cutback being restricted to areas having subzero temperature or for emergency operations.

    2. The prime coat should be applied only on the top

    most granular base layer, over which bituminous treatment isto be applied. The granular base surface should be sweptclean of dust and loose particles and where required, lightly

    and uniformly sprinkled with water to moist the surface.3. The primer should be sprayed uniformly over the drysurface of absorbent granular base, using suitable bitumenpressure distributor or sprayer capable of spraying primer at

    specified rates and temperature so as to provide a uniformlyunbroken spread of primer. Normal temperature range ofspraying emulsion should be 20C to 60 C. The rate of application depends upon the porosity characteristics of the

    surface to be primed and is given in above table.

  • 8/3/2019 Important Aspects in Road Construction

    30/89

    DOs Donts

    1. Use slow setting emulsionand restrict the use ofcutback to subzero

    temperature conditions oremergency operations.2. Use only pressure

    1. Do not apply primerwhen the atmospherictemperature in shade is

    less than 10C or whenthe weather is foggy, rainy

    or windy.sprayers.

    3. Preferably lay a trialsection.

    4. The Contractor to

    demonstrate at a sprayingtrial to ensure that theequipment is capable of

    producing a uniform spray.

    . o no a ow pour ng oprimer using perforatedcans.3. Do not allow traffic on

    primed surface.4. Do not applybituminous material to a

    wet surface.

  • 8/3/2019 Important Aspects in Road Construction

    31/89

    Table 500-2, rate of application of tack coat

    Bituminous material

    503 Tack Coat ( MORT & H )503.4.3: The application of tack coat shall be at the rate

    specified in the contract and shall be applied uniformly. Ifrate of application of tack coat is not specified in the

    contract then it shall be at the rate specified in table 500-2

    Kg/10 Sq.MNormal bituminous surfaces 2.0 to 2.5

    Dry and hungry bituminous surfaces 2.5 to 3.0

    Granular surfaces treated with primer 2.5 to 3.0Non- bituminous surfaces:

    Granular base (not primed)

    Cement concrete pavement

    3.5 to 4.0

    3.0 to 3.5

  • 8/3/2019 Important Aspects in Road Construction

    32/89

    S.No Type ofsurface

    Rate of

    spray(emulsion)

    K /M2

    Rate of spray

    (Bitumen -VG-10)K /M2

    Rate of application of tack coat

    as per table 4 of IRC:SP: 78-2008

    iBituminous

    surface0.20

    to 0.300.30 to 0.40

    ii

    Granularsurface

    treated withprimer

    0.25to 0.30

    0.35 to 0.40

  • 8/3/2019 Important Aspects in Road Construction

    33/89

    Methodology for Tack Coat

    1. Use a rapid setting bitumen emulsion for applying a tack coat,the use of cutback being restricted to areas having sub-zerotemperature or for emergency applications.2. The surface on which tack coat is to be applied should be

    clean, free from dust, dirt and any extraneous materials and dry.3. The surface should be prepared as per sub-section 501.4. The binder should be sprayed uniformly over the surfaceusin suitable bitumen ressure s ra er ca able of s ra in

    bitumen and emulsion at specified rates and temperature so asto provide a uniformly unbroken spread of bitumen emulsion.For smaller jobs, a pressure hand sprayer may be used. Normalrange of spraying temperature should be 20C-60C in case of

    emulsion and 50 C-80C in case of cutback. The rate of application depends upon the type of surface and is given inabove Table.5. The surface should be allowed to cure until all the volatiles

    have evaporated.

    DO D t

  • 8/3/2019 Important Aspects in Road Construction

    34/89

    DOs Donts

    1.Plan the work so that nomore than the necessarytack coat for the daysoperation is placed on

    surface.

    1. Do not apply tackcoat whenatmospherictemperature is less

    than 10C or whenweather is foggy, rainy

    cutback carefully to avoidfire mishap.

    2. Do not apply tackcoat on a wet surface.

    3. Do not allow anyequipment or vehicles

    on Tack Coat.

  • 8/3/2019 Important Aspects in Road Construction

    35/89

    Physical Requirements of Coarse Aggregates forBM/DBM/SDBC/BC

    Table 500-3 for BM, table 500-8 for DBM, table 500-14 forSDBC & 500-17 for BC of 4th Revision

    Property Test Specification

    Code

    Reference

    CleanlinessGrain sizeanalysis

    Max. 5% passing0.075mm sieve

    IS: 2386 part1

    Particleshape

    Flakiness andElongation

    IndexMax. 30% IS: 2386 part

    1

    Strength

    Los Angeles

    Abrasion Valueor

    Max. 40% for BM ,

    35% for DBM & SDBC&30% for BC

    IS: 2386 part4

    Aggregate

    Impact Value

    Max 30%for BM,27%for DBM & SDBC,

    24%for BC

    IS: 2386 part

    4

    h i l i i d

  • 8/3/2019 Important Aspects in Road Construction

    36/89

    DurabilitySoundness:

    Sodium Sulphate

    Magnesium Sulphate

    12%

    18%

    IS: 2386 part 5

    Absorption Water Absorption 2% IS: 2386 part 3

    Coating and Stripping

    Physical requirements continued

    o ggregate tumen :

    WaterSensitivity

    Retained TensileStrength Min. 80%

    to be done ifstripping fails

    Polishing Polished Stone Valuefor SDBC and BC

    Min. 55 Bs: 812 part114

  • 8/3/2019 Important Aspects in Road Construction

    37/89

    513 Seal Coat

    Requirement of materials fo seal coat

    Type

    Aggregate Bitumen Emulsion

    SpecificationSize mm

    Quantitycum

    specification QuantityKg/10 sqm

    specification QuantityKg/10sqm

    -

    A

    . .

    6mm 0.09 S-65 9.8 RS 15.0

    B

    2.36- 0.18

    Sand ordust

    0.06 S-90 6.8 SS 10.0

    Type A seal coat is for high rainfall areas ( over 1500mm )

    Table 500 4 COMPOSITION OF BITUMINOUS MACADAM (4th Revision)

  • 8/3/2019 Important Aspects in Road Construction

    38/89

    Table 500-4, COMPOSITION OF BITUMINOUS MACADAM (4th Revision)

    Mix Designation Grading I Grading II

    Nominal AggregateSize

    40 mm 19 mm

    Layer Thickness 80 100 mm 50 75 mm

    IS Sieve (mm) Cumulative % by weight of total aggregate passing

    45 100 -----

    37.5 90 100 ------

    26.5 75 100 100

    19 --- 90 10013.2 35 61 56 88

    4.75 13 22 16 36

    2.36 4 19 4 19

    0.30 2 -10 2 -10

    0.075 0 -8 0 -8

    Bitumen content, % 3.10 3.40 3.30 3.50

    Bitumen Grade 35 to 90 35 to 90

    Cl 4 2 3 1 of IRC: 37 2001

  • 8/3/2019 Important Aspects in Road Construction

    39/89

    Cl. 4.2.3.1 of IRC: 37-2001BM has low binder content and high

    voids and is thus not impervious to water.Effect of high voids is reduced stiffness and

    increased stress concentrations. From fatigueconsiderations, the detrimental effects ofvoids is more a arent at low tem eratures.

    During prolonged hot spells, BM mix willoperate over a very low stiffness range.

    Hence, use of BM may desirably be

    restricted only to roads designed to carrytraffic less than 5 msa. DBM is recommendedfor roads designed to carry higher traffic than

    5 msa

    Methodology for Bituminous Macadam

  • 8/3/2019 Important Aspects in Road Construction

    40/89

    Methodology for Bituminous Macadam1. Prepare the base on which bituminous macadam

    course is to be laid and shape to the specified lines, grade andcross-section.

    2. Apply tack coat over the base preparatory to laying ofthe bituminous macadam.

    3. Bituminous Macadam should be prepared in a Hot MixPlant of adequate capacity Ensure manufacturing and rollingtemperatures for Bituminous Macadam as specified.

    .

    lay by means of an approved self-propelled mechanical paver.5. Commence initial rolling with 80-100 kN rollers (three-

    wheel or tandem type), beginning from the edge and progressing towards the centre longitudinally. On super

    elevated portions, rolling should progress from lower to upperedge parallel to centre line of pavement. Thereafter, do intermediate rolling with vibratory or pneumatic tyred roadrollers. This should be followed by final rolling while the

    material is still workable.

    Methodology for Bituminous Macadam continued

  • 8/3/2019 Important Aspects in Road Construction

    41/89

    Methodology for Bituminous Macadam continued6. Any high spots or depressions noticed after the roller has

    passed over the whole area once should be corrected byremoving or adding premixed material. Rolling shouldrecommence thereafter. Each pass should have an overlap of atleast one-third of the track made in the preceding pass.

    Rolling should be continued till all roller marks have beeneliminated.7. For single lane roads no longitudinal joint is required, while

    -

    depending on the paver width.8. For making longitudinal or transverse joint, cut the edges ofthe bituminous layer laid earlier to their full depth so as toexpose fresh surface and apply a thin coat of binder. Lay

    adjacent new layer and compact flush with the existing layer. 9.Cover the bituminous macadam with the wearing course withina period of 48 hours. If there is any delay in providing wearingcourse the bituminous macadam surface should be covered

    with a seal coat before opening to traffic.

    DOs Donts

  • 8/3/2019 Important Aspects in Road Construction

    42/89

    1.Ensure that stone aggregate

    conforms to the physicalrequirements and gradingrequirements and are dry and clean.2. In case the aggregate has pooraffinity to bitumen use anti strippingagent with the approval of Engineer.3. While transporting the mixture itshould be suitably covered by

    1. Do not undertake the work infoggy, rainy or windy weather orwhen the atmospheric temperaturein the shade is less than 10C.2. Do not allow the difference intemperature of binder and

    aggregate to increase beyond 14OCat any time.3. Do not allow the premix materialto adhere to the roller wheels. (Do

    arpau n.

    4. Rolling operations should becompleted before the mix becomesunworkable5. Maintain strict control on

    temperature while mixing androlling.6. Regulate the rate of delivery ofmaterial to paver to enable it to

    operate continuously.

    no use excess wa er or e

    purpose. Light sprinkling shoulddo.)4. Do not use lubricating oil on thewheels of the roller to prevent mixfrom adhering.

    5. Do not allow traffic until the mixhas been covered with a wearingcourse.6. Do not move roller at a speed

    more than 5 km/h.

  • 8/3/2019 Important Aspects in Road Construction

    43/89

    Mix Design of DBM, SDBC or BC

    1 Proportioning of Coarse aggregate and Fine

    aggregate to satisfy the specified gradation.

    specified values of:a) Marshal Stability Valueb) Flow Value

    c) Voids in Mineral Aggregate (VMA)d) Voids Filled by Bitumen (VFB)e) Air Voids in Mix

    Table 500-10 Composition of Dense Graded Bituminous Macadam Pavement Layers.

  • 8/3/2019 Important Aspects in Road Construction

    44/89

    p y

    Grading 1 2

    Nominal aggregate size 40 mm 25 mm

    Layer Thickness 80-100mm 50-75 mm

    IS Sieve (mm) Cumulative % by weight of total aggregate passing

    45 100

    37.5 95-100 100

    26.5 63-93 90-100

    - -

    13.2 55-75 56-804.75 38-54 38-54

    2.36 28-42 28-42

    0.3 7-21 7-21

    0.075 2-8 2-8

    Bitumen content % bymass of total mix

    Min 4.0 in 4.5

    Bitumen grade (pen) 65 or 90 65 or 90

  • 8/3/2019 Important Aspects in Road Construction

    45/89

    Description Requirements

    Minimum stability (KN at600C)

    9.0

    Minimum flow (mm) 2

    Maximum flow (mm) 4

    Table 500-11, Requirements of DBM layer

    Compaction level (Number ofblows)

    75 blows on each face ofthe specimen

    Percent air voids 3-6

    Percent voids in mineral

    aggregate (VMA) See table 500-12

    Percent voids filled withbitumen (VFB)

    65-75

  • 8/3/2019 Important Aspects in Road Construction

    46/89

    IS Sieve(mm)

    Cumulative per cent passingby weight of total aggregate

    0.6 100

    0.3 95 - 100

    -

    Table 500-9, Grading Requirements of mineral filler

    .

    The filler shall be free from organic impurities and have a Plasticity

    Index not greater than 4. The Plasticity Index requirement shall not apply iffiller is cement or lime. When the coarse aggregate is gravel, 2 per centbyweight of total aggregate, shall be Portland cement or hydrated lime and the

    percentage of fine aggregate reduced accordingly. Cement or hydrated limeis not required when the limestone aggregate is used. Where the aggregates

    fail to meet the requirements of the water sensitivity test in Table 500-8, then2 per cent by total weight of aggregate, of hydrated lime shall be addedwithout additional cost.

    Table 500-12, Minimum per cent voids in mineral aggregate (VMA)

  • 8/3/2019 Important Aspects in Road Construction

    47/89

    NominalMaximum

    particle size

    Minimum VMA, per cent related to design airvoids, per cent

    3.0 4.0 5.0

    9.5 14.0 15.0 16.0

    12.5 13.0 14.0 15.0

    , p gg g ( )

    19.0 12.0 13.0 14.0

    25.0 11.0 12.0 13.0

    37.5 10.0 11.0 12.0

    Notes: 1. The nominal maximum particle size isone size larger thanthe first sieve to retain more than 10%.

    2. Interpolate minimum voids in the mineral (VMA) for design air voids

    values between those listed

    Table 500-15 Composition Of Semi Dense Bituminous Concrete Pavement Layers.

  • 8/3/2019 Important Aspects in Road Construction

    48/89

    Grading 1 2

    Nominal aggregate size 13 mm 10 mm

    Layer Thickness 35-40mm 25-30 mm

    IS Sieve (mm) Cumulative %by weight of total aggregate passing

    19 100

    13.2 90-100 100

    9.5 70-90 90-100

    . - -

    2.36 24-39 24-39

    1.18 15-30 15-30

    0.3 9-19 9-19

    0.075 3-8 3-8Bitumen content % by

    mass of total mixMin 4.5 Min 5.0

    Bitumen grade (pen) 65* 65*

    * Only in exceptional circumstances, 80/100 penetration grade bitumen may be used

  • 8/3/2019 Important Aspects in Road Construction

    49/89

    Description Requirements

    Minimum stability (KN at600C)

    8.2

    Minimum flow (mm) 2

    Maximum flow (mm) 4

    Table 500-16, Requirements of SDBC layer

    Compaction level (Number ofblows)

    75 blows on each face ofthe specimen

    Percent air voids 3-5

    Percent voids in mineral

    aggregate (VMA) See table 500-12

    Percent voids filled withbitumen (VFB)

    65-78

    Table 500-18 Composition of Bituminous Concrete Pavement Layers.

  • 8/3/2019 Important Aspects in Road Construction

    50/89

    Grading 1 2

    Nominal aggregate size 19 mm 13 mm

    Layer Thickness 50-65mm 30-45 mm

    IS Sieve (mm) Cumulative % by weight of total aggregate passing

    26.5 100

    19 79-100 100

    13.2 59-79 79-100

    9.5 52-72 70-88

    4.75 35-55 53-712.36 28-44 42-58

    1.18 20-34 34-48

    0.6 15-27 26-38

    0.3 10-20 18-28

    0.15 5-13 12-20

    0.075 2-8 4-10

    Bitumen content % bymass of total mix

    5.0 - 6.0 5.0 - 7.0

    Bitumen grade (pen) 65 65

    Table 500-19, Requirements of BC layers

  • 8/3/2019 Important Aspects in Road Construction

    51/89

    Minimum stability (kN at60 C)

    9.0

    Minimum flow (mm) 2

    Maximum flow (mm) 4Compaction level(Number of blows)

    75 blows on each of the twofaces of the specimen

    q y

    Percent air voids 3-6

    Percent voids in mineralaggregate (VMA)

    See table 500-12

    Percent voids filled with

    bitumen (VFB) 65-75

    Loss of stability onimmersion in water at

    60C (ASTM D 1075

    Minimum 75 % retainedstrength

    Table 5500-13, Permissible variations from job mix formula for DBM, SDBC, and BC

  • 8/3/2019 Important Aspects in Road Construction

    52/89

    Description Permissible variation

    Base/binder course Wearing course

    Aggregate passing 19mm sieve or

    larger

    8% 7%

    Aggregate passing 13.2mm, 9.5mm 7% 6%

    Aggregate passing 4.75mm 6% 5%

    Aggregate passing 2.36mm, 1.18mm,0.6mm

    5% 4%

    Aggregate passing 0.3mm, 0.15mm 4% 3%

    Aggregate passing 0.075mm 2% 1.5mm

    Binder content 0.3% 0.3%

    Mixing temperature 10C 10C

    Reasons for Poor performance of Asphalt mixes

  • 8/3/2019 Important Aspects in Road Construction

    53/89

    Reasons for Poor performance of Asphalt mixes

    1 Inadequate initial compaction making themix vulnerable to high secondary compaction

    under traffic.2 Relatively high asphalt contents thatpermit the reduction of air voids to less than 3per cent under secondary compaction, leadingto rutting under heavy axle loads whenpavement temperatures rise in summer.

    3 Low asphalt contents and high air voids

    in the mix leading to top- down cracking,raveling and stripping making the mix lesdurable.

  • 8/3/2019 Important Aspects in Road Construction

    54/89

    Modified Penetration Macadam (MPM) 506 Rural Roads Manual

  • 8/3/2019 Important Aspects in Road Construction

    55/89

    Description

    Rate of application for 10sqm area

    75mm 50mm

    Bituminoussurface,

    cum

    On WBMsurface,

    cum

    Bituminoussurface,

    cum

    On WBMsurface,

    cum

    40mm size handbroken metal

    0.9 0.6

    12mm size chi s 0.18 0.18

    Description

    Bitumen rate of application for 10sqm area (kg)

    75mm 50mm

    Bituminoussurface On WBMsurface Bituminoussurface On WBMsurface

    Bitumen for grouting

    Tack coat for existing

    bituminous surface

    20

    5

    20

    -

    17.5

    5

    17.5

    -

    1. Spread coarse aggregate of 40 mm size metal uniformly at the rate of 0.9cum for 75 mm thickness (0.6 cum for 50 mm thickness) per 10 sqm area to

  • 8/3/2019 Important Aspects in Road Construction

    56/89

    ( ) p qproper camber/ super-elevation. Remedy all high spots and depressions by

    removing or adding aggregates.2. Commence rolling with 80-100 kN rollers (three-wheel or tandem type),beginning from the edge and progressing towards the centre longitudinally. Onsuper elevated portions, rolling should progress from lower to upper edge

    parallel to centre line of pavement.3. Correct any irregularities noticed after the roller has passed over the wholearea once by loosening the surface and removing or adding the coarseaggregates followed by rolling. Continue rolling till the entire surface has beenrolled to desired compaction such that there is no crushing of aggregates and al

    roller marks have been eliminated. Each pass of roller should overlap not lessthan one-third of the track made in the preceding pass.4. Heat bitumen (paving grade S-35 to S-90) to a temperature of 160C to180C and spray uniformly on aggregate layer at the rate of 20 kg per 10 m2 for

    75 mm thick layer and 17.5 kg per 10 m2

    for 50 mm thick layer.5. Immediately after application of bitumen, spread 12 mm size key aggregatesat a uniform rate of 0.18 cum for 75 mm thickness (0.12 cum for 50 mmthickness) per 10 m2 so as to cover the surface completely and roll. Rollingshould continue until the key aggregates are firmly embedded in position and

    stop moving under roller

    DOs Donts

  • 8/3/2019 Important Aspects in Road Construction

    57/89

    1. Ensure that aggregatesconform to gradingspecified and are dryand clean at the time of

    laying.

    1. Do not undertake thework in foggy. rainy orwindy weather or whenthe atmospheric

    temperature in theshade is less than l0C.

    .

    temperature of bitumenappropriate tothe grade of bitumen.

    3. Remove excessivedeposits of binder

    during spray operation.

    2. Do not allow anytraffic over Built upspray grout

    without laying wearingcourse or seal coat.

    512 Open Graded Pre Mix Carpet (OGPC)20 mm thick pre mix carpet

  • 8/3/2019 Important Aspects in Road Construction

    58/89

    20 mm thick pre mix carpet

    Aggregate013.2mmchips = 0.18cum11.2mm chips = 0.09cum

    (13.2mm = passing 22.4 & retained on 11.2mm sieves11.2mm chips passing 13.2mm

    AIV < 40%, FIV < 25% and WA < 1% for coarse aggregates.

    reta ne on 5.6mm s eves

    BinderBitumen @ 14.6 kg/ 10sqmEmulsion @ 21.5 kg/ 10sqm

    Appropriate technology and machinery for

  • 8/3/2019 Important Aspects in Road Construction

    59/89

    pp p gy y

    Premix Carpet

    1.Applying Prime Coat : Hand-held lance providedwith sprayer, operated by compressor

    2.Applying Tack Coat : Hand-held lance provided,

    3.Mixing of aggregates and bitumen in : Mini HotMix Plant, capacity of with specified quantities

    around 6 tonnes/hour

    4.Transporting from the mixer to site : Tarpaulin-

    covered tractor-trailer or hand barrows

    Methodology for OGPC1 Mixing should be thorough to ensure that a homogenous mixture is

  • 8/3/2019 Important Aspects in Road Construction

    60/89

    1.Mixing should be thorough to ensure that a homogenous mixture is

    obtained. The temperature of bitumen at the time of mixing should be in therange of 150 C to 163 C and that of aggregates 155C to 163C, providedthat the difference between the temperature of aggregate and the binder shouldnot exceed 14C. If modified bitumen is used, temperature should be asrecommended in Subsection 512. The temperature at the time of discharge of

    the mixture should be between l30C and 160C.2. The premixed material shall be spread on the road surface with rakes.3. Commence rolling with 80-100 kN rollers (three-wheel or tandem type),

    .

    super elevated portions, rolling should progress from lower to upper edgeparallel to centre line of pavement). Continue rolling operations till a smoothuniform surface is achieved and all roller marks are eliminated. Each passshould have an overlap of at least one-third of the track made in the precedingpass.

    4. Correct any high spots or depressions noticed after the roller haspassed over the whole area once by removing or adding premixed material andre-compacting.

    5. Provide a seal coat to the surface immediately after laying the carpet

    as per details in Sub-section

    DOs Donts

    1 Ensure that the 1 Do not allow manual

  • 8/3/2019 Important Aspects in Road Construction

    61/89

    1. Ensure that the

    aggregates and bindersatisfy the specifiedrequirements.

    2. Before opening thebitumen emulsion drum,

    1. Do not allow manual

    mixing.

    2. Do not undertake work

    in foggy, rainy or windyweather or when theminimum air temperature

    ro e rum a s ow

    speed, to and fro at leastfive times for a distance ofabout 10 m to ensure

    proper distribution ofstorage sedimentation.

    3. As far as possible use

    suitable cold mixin lant

    s ess an .

    3. Do not allow any trafficunless the emulsion is

    properly set and thesurface has acquiredadequate stability

  • 8/3/2019 Important Aspects in Road Construction

    62/89

    512 Mix Seal surfacing

  • 8/3/2019 Important Aspects in Road Construction

    63/89

    Table 500-26, aggregate gradationIS sieve

    designation

    (mm)

    Cumulative per cent by weight oftotal aggregate passing

    Type A Type B

    13.2 mm - 100

    11.2 mm 100 88 - 100

    5.6 mm 52 - 88 31 - 52

    2.8 mm 14 - 38 5 - 25

    0.090 mm 0 - 5 0 - 5

    Bitumen 22 kg / 10 sqm 19 kg / 10 sqm

    As per Manual for construction and supervision ofbituminous works Type A grading may be used for 25mm

    thick MSS also, by proportionately increasing bitumen

    content

    Stone Matrix AsphaltA IRC SP 79 2008

  • 8/3/2019 Important Aspects in Road Construction

    64/89

    As per IRC: SP: 79 -2008

    SMA is a gap graded hot mix which contains:a) Coarse aggregate: 70-80%

    b) binder content: 6-7%c) filler: 8-12%

    . .

    e) layer thickness: 40 to 75mm

    Bitumen for SMA shalll be VG-30 grade

    bitumen or PMB-40 grade BitumenFiller shall be stone dust and /or hydrated lime

    passing in 0.3mm sieve by 95 100% and in

    0.075mm sieve by 85 100%

  • 8/3/2019 Important Aspects in Road Construction

    65/89

    Causes of superior performance of SMA

    1) Higher amount of coarse aggregateprovides better stone-to-stone contact,which rovides hi hl rut resistant

    bituminous course.2) Higher binder content adds durability3) Stabilising additive reduces drain

    down of binder

    Physical Requirements of Coarse Aggregates for SMAPhysical Requirements of Coarse Aggregates for SMA

    CodeCode

  • 8/3/2019 Important Aspects in Road Construction

    66/89

    PropertyProperty TestTest SpecificationSpecificationCodeCode

    ReferenceReference

    CleanlinessCleanliness Grain size analysisGrain size analysis% passing 0.075mm sieve% passing 0.075mm sieve

    < 2%< 2%IS: 2386 part 1IS: 2386 part 1

    ParticleParticle

    shapeshape

    Combined FlakinessCombined Flakiness

    and Elongation Indexand Elongation Index

    < 30%< 30% IS: 2386 part 1IS: 2386 part 1

    StrengthStrength

    Los Angeles AbrasionLos Angeles Abrasion

    ValueValue< 25%< 25%

    IS: 2386 part 4IS: 2386 part 4

    ggrega e mpac a ueggrega e mpac a ue 55%> 55%

    durabilitydurability

    Soundness (either Sodium or Magnesium)Soundness (either Sodium or Magnesium) 5 cycles5 cycles

    Sodium SulphateSodium SulphateIS: 2386 part 5IS: 2386 part 5

    < 12%< 12%

    Magnesium SulphateMagnesium Sulphate < 18%< 18%WaterWater

    AbsorptionAbsorptionWater AbsorptionWater Absorption IS: 2386 part 3IS: 2386 part 3 < 2%< 2%

    *Polishing Value does not apply when the coarse aggregate is used in the 19mm

    SMA, which is used as an intermediate (binder) course

    SMA Designation 13mm SMA 19mm SMA

    Composition of Stone Matrix Asphalt

  • 8/3/2019 Important Aspects in Road Construction

    67/89

    SMA Designation 13mm SMA 19mm SMA

    Nominal Aggregate size 13mm 19mm

    Nominal layer thickness 40 50mm 45 75mm

    IS sieveCumulative % passing

    by weight of total

    aggregates

    Cumulative %passing by weightof

    total aggregates

    26.5 - 100

    -

    13.2 mm 90 - 100 45 - 709.5 mm 50 - 75 25 - 60

    4.75 mm 20 - 28 20 - 28

    2.36 mm 16 - 24 16 - 24

    1.18 mm 13 21 13 - 21

    0.6 mm 12 18 12 - 18

    0.3 mm 10 - 20 10 - 20

    0.075 mm 8 - 12 8 - 12

    515.Mastic Asphalt

  • 8/3/2019 Important Aspects in Road Construction

    68/89

    Mastic Asphalt is used as a wearing course for bridgedecks and heavily stressed intersections in urban areas. Thisis a homogeneous mixture of well graded aggregates,limestone powder filler and a hard grade bitumen (10 to 20

    pen) to yield a plastic and void less mass, which whenapplied hot can be trowelled and floated to form a very denseim ermeable surfacin .

    Binder content is 14 to 17%.Normal thickness is 25 to 50mm.

    Hardness number (IS: 1195-1978): Mastic Asphalt shall have ahardness number of 60 to 80 at the time of manufacture at

    25C prior to the addition of coarse aggregate and 10 to 20 at25C at the time of laying after the addition of coarse

    aggregate.

    Table 500 29, Requirements for physicalproperties of binder

  • 8/3/2019 Important Aspects in Road Construction

    69/89

    PropertyTest

    methodRequirements

    Penetration at 25C IS:1203 15 5

    Softening Pont, C IS:1205 65 10

    properties of binder

    C Max

    IS:1212 2.0

    Solubility in trichloroethylene,% by mass Min

    IS:1216 95

    Ash, (mineral matter) by massMax IS:1217 1.0

    Table 500 30, Grade and thickness of Mastic AsphaltPaving and Grading of Coarse aggregate

  • 8/3/2019 Important Aspects in Road Construction

    70/89

    ApplicationThickness range

    (mm)

    Nominal size ofcoarse

    aggregate (mm)

    Coarseaggregate, % by

    mass of totalmass

    Roads andCarriageway

    25 - 50 13 40 10

    Heavily stressed

    g g gg g

    areas .e.

    junctions andtoll plazas

    40 - 50 13

    Nominal size of coarseaggregate

    13mm

    IS Sieve (mm) Cumulative % passing by weight

    19 100

    13.2 88 - 100

    2.36 0 - 5

    Table 500 31, Grading of fine aggregate(inclusive of Filler)

  • 8/3/2019 Important Aspects in Road Construction

    71/89

    IS SievePercentage by

    weight of aggregate

    Passing 2.36mm but retainedon 0.600mm 0 - 25

    Passin 0.600mm but

    ( )

    retained on 0.212mm

    Passing 0.212mm butretained on 0.075mm

    10 - 30

    Passing 0.075mm 30 - 55

    Filler shall be limestone powder passing 0.075mm sieveand shall have a calcium carbonate content of not less than80%by weight when determined in accordance with IS: 1514

  • 8/3/2019 Important Aspects in Road Construction

    72/89

  • 8/3/2019 Important Aspects in Road Construction

    73/89

    501.6 COMPACTION

    Commence From Edges And Progress

    Towards Centre

    Initial Breakdown Rolling 8 To 10 T Smoothee o er

    Intermediate Rolling 8-10 T Dead Wt. OrVibratory Roller, Pneumatic Tyred Roller :12-15 TWt. 5.6 Kg/Sq.Cm Pressure.

    Finished Rolling 6-8 T Smooth WheelTandem Roller

  • 8/3/2019 Important Aspects in Road Construction

    74/89

    Recommended Frequency and Amplitude

    For Vibratory Compaction

    Lift frequency amplitude

    Thin maximum low

    thick minimum high

    The frequency of vibration is the number of complete cycles thatthe eccentrics rotate per minute. The faster the rotation of the eccentrics,the greater the frequency of vibration.

  • 8/3/2019 Important Aspects in Road Construction

    75/89

    Some vibratory rollers can operate at only one frequency or havea very limited selection of frequencies.

    Other vibratory rollers can alter the frequency of the applied loadbetween 1600 and 4000 vibrations per minute.

    Frequencies below 2000 vibrations per minute are not normallyacceptable to compact asphalt mixtures.

    If the width of the roller drum is 2.1 m (7 ft), only two passes ofthe roller are needed to cover the 3.7 meter (12 ft) wide lane, including a150 mm (6 in) overhang at each edge of pavement.

    A roller that is 1.8 m (5.9 ft) wide cannot cover the complete 3.7meter (12 ft) wide lane in only two passes.

    Three passes of the 1.8 m (6 ft) wide roller would be necessary toproperly compact the lane.

    If the roller had drums that were 1.5 m (5 ft) wide, three passes ofthe roller would be required, similar to the roller with the 1.8 m (6 ft) widedrums.

    A 1.4 m (4.5 ft) drum needs four passes for one coverage.For thick lifts, first pass should be about 0.30 m (1 ft) in from edge to

    prevent shoving.

  • 8/3/2019 Important Aspects in Road Construction

    76/89

    AmplitudeAmplitude

    Normal values of nominal amplitude range from 0.25 to 1 mm (1/100 to1/32 in).

    Some rollers can operate at only one fixed amplitude, while others have

    high and low amplitude positions.

    Typically as the layer thickness increases, it is often advantageous toincrease the nominal amplitude applied to the asphalt mix.

    Unless high amplitude is needed to achieve a particular density level,the vibratory roller should be operated in low amplitude.

    Ask: Does changing frequency change the compaction effort? (Yes. 10-12

    vibrations/ft. Never less than 10.)

  • 8/3/2019 Important Aspects in Road Construction

    77/89

    Impact SpacingImpact Spacing

    High FrequencyHigh FrequencyLow FrequencyLow Frequency

    DIRECTION OF TRAVELDIRECTION OF TRAVEL

    FrequencyFrequency

    ONE ROLLER PASS

  • 8/3/2019 Important Aspects in Road Construction

    78/89

    1122

    CROWNCROWN22--lanes @lanes @

    O O SS

    44

    33

    55

    66

    (12 ft)(12 ft)

    Drum WidthDrum Width= 1.8 meters= 1.8 meters

    6 ft6 ft

    The capabilities of each type of roller vary,

  • 8/3/2019 Important Aspects in Road Construction

    79/89

    however, with mat thickness, mix temperature, mixdesign and environmental conditions.In addition, the number of passes required

    depends on the position of the rollers in the roller

    train. A test strip aids us in this decision process.

    ,

    which can tell us whether the designed mix isresistant to rutting. It should be able to proof test themixes and tell us whether a mix satisfies a definitecriteria and passes or fails the torture test. This test

    should be a laboratory test method so that it can beused on designed mixes, and it should be a simpletest method so that it can be used routinely by the

    folks who actually build our pavements.

    Rolling

  • 8/3/2019 Important Aspects in Road Construction

    80/89

    Rolling is a highly technical and skillful operationduring which poor judgment is likely to result in failure toachieve the required compaction. Although various

    guidelines describing sound engineering practices forcompaction procedures are available each case will have itsunique features and there can be no substitute forexper ence n ac ev ng success u compact on.

    Initial or breakdown RollingIntermediate Rolling

    Finish Rolling

    Rolling sequence: Transverse joint, Longitudinal joint,Lower edge rolling, Break-down rolling, Intermediate

    rolling(vibratory) Finished rollin

  • 8/3/2019 Important Aspects in Road Construction

    81/89

    2.25

    2.3

    2.35

    2.4

    Relationship of density with passes

    sity

    PASSINGDENSITY

    Use 3 to 4 passes

    2

    2.05

    2.1

    2.15

    .

    0 2 4 6 8

    Too

    many

    passes

    Den

    No of Passes

  • 8/3/2019 Important Aspects in Road Construction

    82/89

    Table 900 2,Maximum permitted number of irregularities

  • 8/3/2019 Important Aspects in Road Construction

    83/89

    Surfaces ofcarriageways and

    paved shoulders

    Surfaces of laybys,service roads and all

    bituminous courses

    Irregularity 4mm 7mm 4mm 7mm

    Length(m) 300 75 300 75 300 75300

    75

    National highways/

    Expressways 20 9 2 1 40 18 4 2

    Roads of lowercategory

    40 18 4 2 60 27 6 3

    The maximum allowable difference between the roadsurface and underside of a 3m straight edge when

  • 8/3/2019 Important Aspects in Road Construction

    84/89

    For pavement surface (bituminousand cement concrete)

    3mm

    placed parallel with, or at right angles to the center lineof the road at points decided by the Engineer

    For bituminous courses 6mm

    For granular sub-base or basecouses

    8mm

    For sub-base under concrete

    pavements 10mm

    903.2 Tests on Earthwork for embankment, sub-gradeconstruction and cut formation

  • 8/3/2019 Important Aspects in Road Construction

    85/89

    Test type As per codeFrequency of

    testing

    Sand Content IS:2720 part 42 per 3000 cubic

    meters

    Plasticity IS:2720 part 52 per 3000 cubic

    meters

    Density IS:2720 part 8

    2 per 3000 cubic

    meters

    DeleteriousContent

    IS:2720 part 27As and whenrequired by

    engineer

    Moisture Content IS:2720 part 21 test per 50 cubic

    meter

    Soaked/ un-soaked

    CBR

    IS:2720 part 161 per 3000 cubic

    meters

    Important quality Control Tests for sub base andbase

  • 8/3/2019 Important Aspects in Road Construction

    86/89

    Test Type of construction Frequency (min)

    Gradation

    (IS:2386 part1)

    Granular Sub Base

    WBM/ WMM

    1 per 200cum

    1 per 100cum

    Atterbergs limits

    (IS:2720 part 5)

    Granular Sub BaseWMM on aggregates

    WBM(for binding material)

    1 per 200cum1 per 100cum

    1 per 25cum

    Moisture content

    (IS:2720 part 2)

    Granular Sub Base

    (prior to compaction) 1 per 250sqm

    Density (IS: 2720 part28) for compacted layer

    Granular Sub Base 1 per 500sqm

    CBR (IS:2720 part 16) Granular Sub Base As required

    AIV (IS:2386 part 4) WBM/ WMM 1 per 100cum

    FIV and EIV

    (IS:2386 part 1)WBM/ WMM 1 per 200cum

    Important quality Control Tests for Prime Coatand tack coat

  • 8/3/2019 Important Aspects in Road Construction

    87/89

    Test Reference Frequency (min)

    Quality of binder IS:73, IS:217 andIS: 8887

    As applicable in thecodes

    Temperature forapplication - At regular intervals

    Rate of spread of

    binder

    -One test per 500m2

    and not less than 2

    per day

    Tests for Bituminous Macadam

    Test type As per code Frequency of testing

  • 8/3/2019 Important Aspects in Road Construction

    88/89

    Quality of binderIS:73, IS:217 and

    IS: 8887As applicable in the codes

    Aggregate Impact Value LosAngeles Abrasion Value

    IS:2386 part 4 1 test per 50 cubic meter

    Flakiness and ElongationIndex

    IS:2389 part 1 1 test per 50 cubic meter

    Initially 1 set of 3 specimens for each

    tr pp ng a ue :9241 source an su sequent y y c ange nquality of aggregates

    Water Absorption IS:2386 part 3 - DO -

    Water Sensitivity of mix AASHTO T83 In case of failure in stripping test.

    Soundness IS:2386 part 5 1 test by each method for each source

    Binder content and grading - 2 tests per day per plant

    Density - 1 test per 250 M2

    Tests for DBM, SDBC and BCIn addition to the tests on BM

  • 8/3/2019 Important Aspects in Road Construction

    89/89

    Test type As per code Frequency of testing

    Sand Equivalent Test Is:2720 part 37 As required

    Plasticity Index IS:2720 part 5 As required

    Polished Stone value BS:812 part114 As required for SDBC and BC

    Mix grading -

    1 set of tests on individual constituents and

    mixed aggregate from the dryer for each 400T of mix subject to a minimum of 2 per plant

    per day

    Stability of MixMS 2 of Asphaltic

    Institute3 Marshall specimens for 400M3 subject to a

    minimum of 2 per day per plant

    Control of bindercontent and grading

    - 1 test for 400M3 subject to a minimum of 2

    per day per plant

    Rate of spread of mixedmaterial

    -Regular control through checks on the

    weight of mied material and layer thickness.