LSSGB Project Improve on-time deliveries ■ Executive Summary : ABC Manufacturing Co. is a maker of consumer durables that has initiated a project to improve the on-time deliveries from its warehouse to factory from a current level of 87.9% to 98%. On-time delivery at the factory is a critical metric to measure warehouse performance. ■ Business Problem : ABC Manufacturing Co. operates a factory which is supplied various components from its warehouse. On-time deliveries (OTD) at the factory are critical to sustaining mass production and sales to final customers. It is also critical to future growth. Analysis of past one year of deliveries shows that the OTD% is at a level of 87.9% resulting in production and sales losses at the factory. This project has been scoped to increase the OTD% to levels required by the factory. ■ Statistical Problem : Current OTD% is 87.9% based on the past one year’s data. Target is to increase it to 98%. ■ Statistical Solution : The root-causes of the low OTD% are found to be high variability in factory demand, high variability in deliveries from suppliers to warehouse, poor efficiency & inaccurate stock levels at warehouse due to manual processes, lack of standard practices, driver shortage, long lead-times. Improvement actions taken are – Improved S&OP maturity at ABC Manufacturing with joint planning & forecasting, increased efficiency and accurate stock levels through process automation (WMS) & training, process standardization, optimized driver count/best practices to recruit and retain drivers, optimized lead-times by using standard processes & training. ■ Business Solution : OTD% has increased to 98.7% vs. the target of 98%, based on the pilot run. The improvements in the pilot run have been institutionalized at the 1 LSSGB Project_Mahit Ohri 8th Dec 2015

Upload: mahit-ohri

Post on 07-Jan-2017

1.131 views

Category:

Business


2 download

TRANSCRIPT

Page 1: Improve On-time deliveries_ Lean Six Sigma Green Belt Project

LSSGB Project

Improve on-time deliveries

■ Executive Summary : ABC Manufacturing Co. is a maker of consumer durables that has initiated a project to improve the on-time deliveries from its warehouse to factory from a current level of 87.9% to 98%. On-time delivery at the factory is a critical metric to measure warehouse performance.

■ Business Problem : ABC Manufacturing Co. operates a factory which is supplied various components from its warehouse. On-time deliveries (OTD) at the factory are critical to sustaining mass production and sales to final customers. It is also critical to future growth. Analysis of past one year of deliveries shows that the OTD% is at a level of 87.9% resulting in production and sales losses at the factory. This project has been scoped to increase the OTD% to levels required by the factory.

■ Statistical Problem : Current OTD% is 87.9% based on the past one year’s data. Target is to increase it to 98%.

■ Statistical Solution : The root-causes of the low OTD% are found to be high variability in factory demand, high variability in deliveries from suppliers to warehouse, poor efficiency & inaccurate stock levels at warehouse due to manual processes, lack of standard practices, driver shortage, long lead-times.

Improvement actions taken are – Improved S&OP maturity at ABC Manufacturing with joint planning & forecasting, increased efficiency and accurate stock levels through process automation (WMS) & training, process standardization, optimized driver count/best practices to recruit and retain drivers, optimized lead-times by using standard processes & training.

■ Business Solution : OTD% has increased to 98.7% vs. the target of 98%, based on the pilot run. The improvements in the pilot run have been institutionalized at the Control phase.

1LSSGB Project_Mahit Ohri8th Dec 2015

Page 2: Improve On-time deliveries_ Lean Six Sigma Green Belt Project

Improve on-time deliveries : Core Project Team

Project Champion : RV

Master Black Belt : RP

Process Owner : AG

Team Member 2

DEFINE

Team Member 3

Team Member 4

Team Member 5

2

Team Member 1

LSSGB Project_Mahit Ohri8th Dec 2015

Project Leader (Black Belt): SA

Page 3: Improve On-time deliveries_ Lean Six Sigma Green Belt Project

Improve on-time deliveries : SIPOC DiagramDEFINE

S I P O CSUPPLIERS INPUTS PROCESSES OUTPUTS CUSTOMERS

Factory Forecast of demand Production/logistics capacity planning at Suppliers, Warehouse

Adequate capacity to meet demand & on-time deliveries

Suppliers, W/H

Suppliers of components

On-time supply of components

Maintain inventory at specified levels at W/H

Adequate inventory to meet service levels

W/H

Factory Delivery Schedule Sort/pack & dispatch required components from W/H

Payload deliveries Factory

Driver coordinator at W/H

Suitable truck, driver Provide truck & driver to shipping dock

Empty truck ready for loading

Shipping personnel at W/H

Shipping personnel at W/H

Components, Invoice, Excise/Sales Tax documents, Gate pass

Load payload on the truck, provide documents

Full truck ready for dispatch to factory

Drivers at W/H

Drivers Delivery Schedule, payload, documents

Arrive with payload at factory unloading dock

Unloading at factory dock

Factory receiving personnel

Factory receiving personnel

Payload, documents Unloading at factory dock, confirmation of receipt

Receipt confirmation, delivery update by drivers

Driver, driver coordinator at W/H

3LSSGB Project_Mahit Ohri8th Dec 2015

Page 4: Improve On-time deliveries_ Lean Six Sigma Green Belt Project

Improve on-time deliveries : Identify Stakeholders & VOCDEFINE

Stakeholder Who VoiceCustomer Factory Eliminate Production/Sales losses due to

Late Deliveries

Shipping personnel Warehouse Want accurate delivery schedule, on-time receipt of empty trucks/drivers to improve on-time deliveries

Driver coordinators Warehouse Want accurate delivery schedule, on-time dispatch information, correct location of trucks to improve on-time deliveries

Drivers Warehouse Want accurate delivery schedule, correct location of trucks, on-time dispatch from W/H to improve on-time deliveries

Suppliers of components

Suppliers Want accurate forecast and stock-levels at warehouse to improve on-time deliveries

VOC : Improve on-time deliveries

4LSSGB Project_Mahit Ohri8th Dec 2015

Page 5: Improve On-time deliveries_ Lean Six Sigma Green Belt Project

Improve on-time deliveries : CTQ Drill-downDEFINE

Customer Need

Output Characteristic

CTQ

Project ‘Y’ Metric

Target

Specification/Tolerance limits

Defect Definition

5LSSGB Project_Mahit Ohri

Eliminate Production/Sales

losses due to Late Deliveries

On-time Deliveries

On-time Deliveries%

≥ 98%

100%

Late delivery, 1 opportunity

for error

8th Dec 2015

Page 6: Improve On-time deliveries_ Lean Six Sigma Green Belt Project

Improve on-time deliveries : Project CharterDEFINE

6

Project information Process information TeamProject title Improve the Business ABC Manufacturing Co. Project Champion RV

On-time delivery % Process Owner AGProject Leader (BB) SA

Project ID Support function Warehouse MBB RPKey milestones review dates Project delight parameters - Project 'Y' Team members Department % timeDefine 3rd Jan'15 On-time delivery % 1 Factory 25%Measure 10th Jan'15 Efficiency improvement 2 Factory 20%Analyze 25th Jan'15 3 Warehouse 30%Improve 24th Jun'15 4 Warehouse 20%Validate 5th Oct'15 5 Warehouse 20%Control 20th Oct'15

Business case Current OTD performance of the warehouse is average 87.9% based on past 1 year data, which is below the Target of 100%, (expected benefits) leading to customer dissatisfaction due to production & sales losses

Problem statement Average OTD for the past 1 year is at 87.9%, not meeting the Customer target at 100%

Goal statement To increase On-time delivery (OTD) from 87.9% to 98%

Project scope All deliveries from warehouse to ABC Manufacturing Factory

Project plan Start: 3rd Jan'15, End: 20th Oct'15

Resources Warehouse Database, Minitab

Project C,I,A Customer: ABC Manufacturing FactoryInvestor: EFGAssciates: Warehouse team members

Concurrence

Project Champion RV Head Logistics VM MBB RP

Process Owner AG Project Leader (BB) SA

LSSGB Project_Mahit Ohri8th Dec 2015

Page 7: Improve On-time deliveries_ Lean Six Sigma Green Belt Project

Improve on-time deliveries : High-level Process Map

Warehouse(Supply & Inventory

management)

Bi-weekly Schedule

Daily/weekly Deliveries

Supplier 1

Supplier 2

Supplier N

ABC Manufacturing Factory

Monthly forecast

MEASURE

Daily /weekly Deliveries

(VMI)

7LSSGB Project_Mahit Ohri8th Dec 2015

Page 8: Improve On-time deliveries_ Lean Six Sigma Green Belt Project

Improve on-time deliveries : Detailed Process MapMEASURE

Truck available?

Yes

Share schedule with shipping personnelResponsibility: W/H Incharge

Receive Delivery schedule from

factory

▪Locate required components at W/H ▪Pack scheduled quantity▪Prepare Invoice, Tax documents▪Inform driver coordinator about dispatchResponsibility: Shipping Personnel

Wait

No

Check actual availability of the truck at the depotResponsibility: Driver

Take the truck to the loading dockResponsibility: Driver

Request Driver coordinator to locate alternate truckResponsibility: Driver

▪ Take the truck to the Un-loading dock at customer factory▪ Inform receiving personnel 30min before arrivalResponsibility: Driver

▪Unload the payload ▪Check Invoice, Tax documents▪Give receipt confirmation to driverResponsibility: Customer receiving Personnel

Check Backhaul payload with Driver coordinatorResponsibility: Driver/coordinator

Backhaul?

YesNo

Take the empty truck back to W/H depotResponsibility: Driver

▪Load the payload onto the truck▪Handover Invoice, Tax documents, Gate pass to driverResponsibility: Shipping Personnel

▪Locate suitable truck at the depot▪Assign an available driver for the dispatch▪Inform driver about dispatch details▪Record truck request-time, dispatch-time, driver name, loading dock & destination details in W/H DatabaseResponsibility: Driver coordinator

8LSSGB Project_Mahit Ohri8th Dec 2015

Page 9: Improve On-time deliveries_ Lean Six Sigma Green Belt Project

MEASUREImprove on-time deliveries : Data collection plan

Measure/ Metric

X or Y Data type Operational Definition How to measure Data Source

Total deliveries

X Discrete Number of Total deliveries per day

Daily delivery report

On-time deliveries

X Discrete Number of On-time deliveries per day

Daily delivery report

OTD% Y Continuous Calculated % of on-time deliveries per day by total deliveries per day

(Number of on-time deliveries per day / Total number of deliveries per day) x 100

Daily delivery report

■ Data collection purpose: To measure and baseline the Project Xs and Ys

■ What to measure:

■ Sampling Plan: All deliveries from Jan 2014 to Dec 2014

9LSSGB Project_Mahit Ohri8th Dec 2015

Page 10: Improve On-time deliveries_ Lean Six Sigma Green Belt Project

MEASUREImprove on-time deliveries : Baseline Performance

Period of data collection

Total Deliveries On-time Deliveries

OTD% Late deliveries (defects)

Jan 2014 – Dec 2014 4630 4071 87.9% 559

Process Defects UnitsOpportu-

nities per unit

TotalOpportu-

nitiesDPU DPO DPMO Sigma

LTProcess

ShiftSigma

ST

On-time Deliveries 559 4630 1 4630 0.12073 0.12073 120734 1.17 1.5 2.67

■ Base Data:

■ Baseline DPMO & Sigma Level:

10LSSGB Project_Mahit Ohri8th Dec 2015

Page 11: Improve On-time deliveries_ Lean Six Sigma Green Belt Project

Improve on-time deliveries : Pareto Analysis (vital few causes)ANALYZE

11

Late Deliveries 207 157 101 50 28 16Percent 37.0 28.1 18.1 8.9 5.0 2.9Cum % 37.0 65.1 83.2 92.1 97.1 100.0

Cause

600

500400300

200100

0

100

80

60

40

20

0

Late

Deli

verie

s

Perc

ent

Worksheet: Worksheet 4

83% of the late deliveries are caused by 3 causes:▪ Schedule Variation▪ Irregular Replenishment▪ Misplaced Trucks

LSSGB Project_Mahit Ohri8th Dec 2015

Page 12: Improve On-time deliveries_ Lean Six Sigma Green Belt Project

Improve on-time deliveries : Root-cause analysis (Cause & Effect)ANALYZE

12

Low OTD%

High Demand Variability

High Supply Variability

Leadtime

Resource Constraints

schedulevariation/

rush orders

Low forecastaccuracy

Seasonalitynot factored

Market trendsnot factored

W/H Capacity lags market demand

Ill-timed capacity investment

Inefficient cash-to-cash management

DispatchTime

SOP vague

Low efficiency

Too long

Unloading Time/Truck turnaround

No SOP

ImproperlyTrained operators

Too long

Misplacedtrucks

Location notrecorded

Incorrect Location recorded

DriverCount

Shortage

High driverattrition

Manualprocess

Manualprocess

IrregularReplenishment

Low forecastaccuracy

Truck/drivershortage

W/H stock levels inaccurate

Manual stockUpdate in DB

Manualprocess Promotional

offers

LSSGB Project_Mahit Ohri8th Dec 2015

Page 13: Improve On-time deliveries_ Lean Six Sigma Green Belt Project

Improve on-time deliveries : Vital X’s summaryANALYZE

13

No. Vital X

1 Low forecast accuracy

2 Market trends not factored

3 Seasonality

4 W/H stock levels inaccurate

5 Ill-timed investment in W/H capacity

6 Misplaced trucks at W/H

7 Driver shortage

8 W/H dispatch time is long

9 Factory unload time is long

LSSGB Project_Mahit Ohri8th Dec 2015

Page 14: Improve On-time deliveries_ Lean Six Sigma Green Belt Project

Improve on-time deliveries : FMEA (current process)ANALYZE

14

Processfunction

Potential failure mode

Potential effects of failure SEV

Potential cause(s) of

failureOCC

Current process controls

DET RPN Recommended action

Responsibility and Target

date

S&OP Low forecast accuracy

W/H & supplier capacity inadequate

vs. demand10 S&OP process-

maturity low 6 - 6 360 Improve S&OP maturity

Factory management;

20th Feb’15

S&OP Market trends not factored Rush orders 8 S&OP process-

maturity low 6 - 4 192 Improve S&OP maturity

Factory management;

20th Feb’15

S&OP Seasonality Rush orders 6 S&OP process-maturity low 4 - 6 144 Improve S&OP

maturity

Factory management;

20th Feb’15

Inventory recording

W/H stock levels inaccurate

Suppliers can’t know reorder point 10 Manual process 4 - 6 240 W/H Automation

(WMS)

W/H management;

24th Jun’15

Truck dispatch Late dispatch Late Delivery 10

Inefficient process, SOP

vague6 - 6 360 Standardize

process

W/Hmanagement;

8th Feb’15

Investment in capacity

Ill-timed investment

W/H capacity lags market demand 8 Cash-to-cash

cycle long 4 - 8 256 Improve S&OP maturity

Factory management;

20th Feb’15

Truck location

Wrong location recorded

Truck not available for loading 6 Manual process 4 - 6 144 Install GPS in

trucks

W/Hmanagement;

10th Feb’15

Driver retention High attrition Driver shortage 4 Low driver

satisfaction 4 - 6 96Driver

hiring/retention best practices

W/Hmanagement;

15th Feb’15

Factory Unloading

Unloading too long

Late truck turnaround 4

Improper operator

training, No SOP

4 - 2 32 Operator training, Make SOP

Factory management;

20th Feb’15

LSSGB Project_Mahit Ohri8th Dec 2015

Page 15: Improve On-time deliveries_ Lean Six Sigma Green Belt Project

Improve on-time deliveries : Improvement action planIMPROVE

15

No. Cause Improvement Action Responsibility Target date

1 Low forecast accuracy

▪Improve S&OP maturity▪Better segmentation by channel, region & customer▪Review forecasts at aggregate levels▪Regularly monitor forecast accuracy

Factory management

20th May’15

2 Market trends not factored

▪Improve S&OP maturity ▪Better forecast intelligence ▪Involve people with right market & product-line knowledge

Factory management

20th May’15

3 Seasonality ▪Improve S&OP maturity ▪Better forecast intelligence ▪Create dashboard to monitor trends & seasonal effects

Factory management

20th May’15

4 W/H stock levels inaccurate

▪Control inventory through Warehouse Management System (WMS)

W/H management

24thJun’15

5 Ill-timed investment in W/H capacity

▪Improve S&OP maturity▪Better management of cash-to-cash cycle

Factory management

20th May’15

6 Misplaced trucks at W/H

▪Install GPS in trucks, integrate system with WMS W/H management

24th Jun’1510th Mar’15

7 Driver shortage ▪Develop driver hiring & retention best practices▪Optimize driver count

W/H management

15th Apr’15

8 W/H dispatch time is long

▪Control workflow through WMS▪Document precise SOP

W/H management

24th Jun’15

9 Factory unload time is long

▪Provide operator training▪Standardize Unload process

Factory management

20th Apr’15

LSSGB Project_Mahit Ohri8th Dec 2015

Page 16: Improve On-time deliveries_ Lean Six Sigma Green Belt Project

Improve on-time deliveries : Updated Process MapIMPROVE

16

Share schedule with shipping personnel/driver coordinators thru WMS (reduced lead-time & error)Responsibility: W/H Incharge

Receive Delivery schedule from

factory

▪Locate required components thru WMS (reduced time & error)▪Pack scheduled quantity▪Prepare Invoice, Tax documents▪Inform driver coordinator about dispatchResponsibility: Shipping Personnel

Take the truck to the loading dockResponsibility: Driver

▪ Take the truck to the Un-loading dock at customer factory▪ Inform receiving personnel 30min before arrivalResponsibility: Driver

▪Unload the payload ▪Check Invoice, Tax documents▪Give receipt confirmation to driverResponsibility: Customer receiving Personnel

Check Backhaul payload with Driver coordinatorResponsibility: Driver/coordinator

Backhaul?

YesNo

Take the empty truck back to W/H depotResponsibility: Driver

▪Load the payload onto the truck▪Handover Invoice, Tax documents, Gate pass to driverResponsibility: Shipping Personnel

▪Locate suitable truck at the depot thru GPS system (reduced time & error)▪Assign an available driver for the dispatch▪Inform driver about dispatch details▪Record truck request-time, dispatch-time, driver name, loading dock & destination details in WMS (reduced time & error)Responsibility: Driver coordinator

LSSGB Project_Mahit Ohri8th Dec 2015

Page 17: Improve On-time deliveries_ Lean Six Sigma Green Belt Project

Improve on-time deliveries : FMEA (after improvement)

17

Processfunction

Potential failure mode

Potential effects of

failureRecommende

d actionResponsibility and Target date

Action result

Action taken SEV OCC DET RPN

S&OP Low forecast accuracy

W/H & supplier capacity

inadequate vs. demand

Improve S&OP maturity

Factory management;

20th Feb’15

▪Improved S&OP maturity ▪Better segmentation by channel, region & customer

10 3 2 60

S&OP Market trends not factored Rush orders Improve S&OP

maturity

Factory management;

20th Feb’15

▪Improved S&OP maturity ▪Better forecast intelligence 8 3 2 48

S&OP Seasonality Rush orders Improve S&OP maturity

Factory management;

20th Feb’15

▪Improved S&OP maturity ▪Better forecast intelligence ▪Created dashboard to monitor trends & seasonal effects

6 4 2 32

Inventory recording

W/H stock levels

inaccurate

Suppliers can’t know reorder point

W/H Automation (WMS)

W/H management;24th Jun’15 Implemented WMS 10 1 1 10

Truck dispatch Late dispatch Late Delivery Standardize

process

W/Hmanagement;

8th Feb’15

▪Implemented WMS10 2 1 20

Investment in capacity

Ill-timed investment

W/H capacity lags market demand

Improve S&OP maturity

Factory management;

20th Feb’15

▪Improved S&OP maturity ▪Better management of cash-to- cash cycle

8 4 1 32

Truck location

Wrong location recorded

Truck not available for loading

Install GPS in trucks

W/Hmanagement;

10th Feb’15

▪Implemented WMS▪Installed GPS in trucks 6 1 1 6

Driver retention High attrition Driver shortage

Driver hiring/retention best practices

W/Hmanagement;

15th Feb’15

▪Developed driver hiring & retention best practices▪Optimized driver count

4 2 4 32

Factory Unloading

Unloading too long

Late truck turnaround

Operator training, Make SOP

Factory management;

20th Feb’15

▪Provided operator training▪Standardized factory unload process

4 1 2 8

LSSGB Project_Mahit Ohri

IMPROVE

8th Dec 2015

Page 18: Improve On-time deliveries_ Lean Six Sigma Green Belt Project

Improve on-time deliveries : FMEA RPN (Before vs. After improvement)

18LSSGB Project_Mahit Ohri

IMPROVE

0

200

400

600

800

1000

1200

1400

1600

1800

2000

RPN_Before RPN_After

FMEA RPN Before vs. After Improvement

Low forecast accuracy Late dispatch Ill-timed investment

W/H stock levels inaccurate Market trends not factored SeasonalityWrong location recorded High attrition Unloading too long

8th Dec 2015

Page 19: Improve On-time deliveries_ Lean Six Sigma Green Belt Project

Improve on-time deliveries : Cost-benefit analysisIMPROVE

19

■ Project Investment Rs 6 cr (approx.) ▪WMS ▪GPS ▪Training, SOPs, others

■ Project Savings (One year estimate) Rs 30 cr (approx.) ▪Cost-avoidance (sales/production losses) ▪Increased process efficiencies ▪Increased revenues

■ Net Project Savings Rs 24 cr (approx.)

LSSGB Project_Mahit Ohri8th Dec 2015

Page 20: Improve On-time deliveries_ Lean Six Sigma Green Belt Project

Improve on-time deliveries : Measure Pilot Run Results (Hypothesis Test)CONTROL

20

Two-sample T for OTD% Before vs OTD% After

N Mean StDev SE MeanOTD% Before 92 87.65 3.49 0.36OTD% After 92 98.754 0.719 0.075

Difference = μ (OTD% Before) - μ (OTD% After)Estimate for difference: -11.10295% upper bound for difference: -10.485T-Test of difference = 0 (vs <): T-Value = -29.86 P-Value = 0.000 DF = 98

■ H0: There is no difference between OTD% Before and OTD% After ■ H1: OTD% Before < OTD% After

As the P-Value<0.05, we can reject H0 and accept H1 at α=0.05 and conclude that there is a significant increase from OTD% Before to OTD% After.

LSSGB Project_Mahit Ohri

OTD% AfterOTD% Before

100

95

90

85

80

Data

Boxplot of OTD% Before, OTD% After

Worksheet: Worksheet 4

8th Dec 2015

Page 21: Improve On-time deliveries_ Lean Six Sigma Green Belt Project

Improve on-time deliveries : Control Plan

21

CONTROL

Control factor Spec or Tolerance

Measure Technique

Sample size

Sample frequency

Control method

Reaction plan

Forecast accuracy

Per Standard #65

MAD (Mean Absolute Deviation)

100% Monthly Tracking signal ▪Alert user thru exception report ▪Review forecasting model

W/H stock accuracy

Count tolerances

IRA % (Inventory record accuracy)

100% 6 months(one time after deploying WMS, no further need)

Physical count(ABC classification)

Correct records, if required

Truck location at W/H

Per Standard #82

Audit 5% Monthly GPS system Review system

Driver availability Per Standard #65

WMS dashboard

100% Daily WMS dashboard Optimize driver count

W/H dispatch time

Per Standard #83

WMS dashboard

100% Daily WMS dashboard Review process/impart training

Factory unload time

Per Standard #75

Time Study 5% Monthly Unload time report

Review process/impart training

LSSGB Project_Mahit Ohri8th Dec 2015

Page 22: Improve On-time deliveries_ Lean Six Sigma Green Belt Project

Improve on-time deliveries : Performance (after improvement)

22

CONTROL

Period of data collection

Total Deliveries On-time Deliveries

OTD% Late deliveries (defects)

Jan 2014 – Dec 2014 4630 4071 87.9% 559

■ Before Project:

RESULTS

Period of data collection

Total Deliveries On-time Deliveries

OTD% Late deliveries (defects)

Jul 2015 – Sep 2015 1520 1501 98.7% 19

■ After Project:

LSSGB Project_Mahit Ohri8th Dec 2015

Page 23: Improve On-time deliveries_ Lean Six Sigma Green Belt Project

Improve on-time deliveries : Performance (after improvement)

23

CONTROL

Process Defects UnitsOpportu-

nities per unit

TotalOpportu-

nitiesDPU DPO DPMO Sigma

LTProcess

ShiftSigma

ST

On-time Deliveries 559 4630 1 4630 0.12073 0.12073 120734 1.17 1.5 2.67

RESULTS

■ Before Project:

Process Defects UnitsOpportu-

nities per unit

TotalOpportu-

nitiesDPU DPO DPMO Sigma

LTProcess

ShiftSigma

ST

On-time Deliveries 19 1520 1 1520 0.01250 0.012500 12500 2.24 1.5 3.74

■ After Project:

LSSGB Project_Mahit Ohri8th Dec 2015

Page 24: Improve On-time deliveries_ Lean Six Sigma Green Belt Project

Improve on-time deliveries : Conclusion

24

Given the achievement of the Target On-time Delivery (OTD)% and the cost-savings due to cost-avoidance (production & sales losses) and increased operational efficiencies, the Project was declared to be successful by the Customer and the Stakeholders.It was also clear that every effort must be made to sustain the improvements.

LSSGB Project_Mahit Ohri8th Dec 2015