integrating wind resources: siting decisions in the midwest

34
Integrating wind resources: siting decisions in the Midwest Julian Lamy (speaker) Ines Azevedo Paulina Jaramillo

Upload: zaynah

Post on 25-Feb-2016

34 views

Category:

Documents


0 download

DESCRIPTION

Integrating wind resources: siting decisions in the Midwest. Julian Lamy (speaker) Ines Azevedo Paulina Jaramillo. The Midwest has ambitious renewable targets. Illinois RPS: 25% by 2025, 60 to 75% from wind 30 TWh (10 GW) of wind needed for this target - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Integrating wind resources: siting decisions in the Midwest

Integrating wind resources: siting decisions in the MidwestJulian Lamy (speaker)Ines AzevedoPaulina Jaramillo

Page 2: Integrating wind resources: siting decisions in the Midwest

2

The Midwest has ambitious renewable targets• Illinois RPS: 25% by 2025, 60 to 75% from wind

• 30 TWh (10 GW) of wind needed for this target • RPSs in MN, MO, WI, and MI add another 30

TWh (10 GW)• Currently MISO has about 10 GW

• Research question: in an ideal world, if we could choose to build the farms anywhere in MISO, where would we build them?

• What metrics to consider?

Page 3: Integrating wind resources: siting decisions in the Midwest

3

Cap

acity

Fac

tor

30%

32%

34%

36%

38%

40%

42%

44%

46%

Annual average capacity factor

EWITS (2012), 2006

Page 4: Integrating wind resources: siting decisions in the Midwest

4

Variability is also a big concern, even for the highest capacity resources

1 8 15 22 29 36 43 50 57 64 71 78 85 92 990%

10%20%30%40%50%60%70%80%90%

100%

First 100 hours of 2006

Hou

rly

Cap

acity

Fac

tor

Illinois farm (293 MW)CF 44%COV: 0.52

Page 5: Integrating wind resources: siting decisions in the Midwest

5

Coe

ffici

ent o

f var

iatio

n (C

OV

)

0.65

0.7

0.75

0.8

0.85

0.9

Coefficient of Variation (CoV) in hourly output

EWITS (2012), 2006

𝐶𝑂𝑉=𝜎𝜇

Page 6: Integrating wind resources: siting decisions in the Midwest

6

Transmission: hard to say…

MTEP 2012, pg. 49

Page 7: Integrating wind resources: siting decisions in the Midwest

7

Data on available existing transmission capacity is limited, what about generation?

17%

61%

22%

(eGRID, 2012), % of generation in 2009 by area

26%

Page 8: Integrating wind resources: siting decisions in the Midwest

8

Past research suggests that building around Illinois is best

• Hoppock and Patiño-Echeverri (2010) • Evaluated wind farms using capacity factors for

hypothetical sites using EWITS data (2008)• Remote wind farms were required to build transmission

lines for delivery to Illinois (with sensitivities)

• This paper add to the literature by:

1. In addition to capacity factors, we include a metric to account for the temporal variability of each farm using a simple dispatch model

2. Delivery must be to some node cluster within MISO, not necessarily to Illinois

Page 9: Integrating wind resources: siting decisions in the Midwest

9

Generation cost for each non-wind generator (i)

ramp cost for each non-wind generator (i)

Capital costs incurred for each wind farm

marginal gen cost for non-wind generator i

Generation in hour t by non-wind generator i

Change in generation from hour (t-1) to t

Binary variable : b=1: build farm kb=0: don’t build farm k

Annualized wind capital cost + annualized transmission capital cost

Ramp cost ($/MWh) incurred by non-wind generator i

Modeling Approach

Page 10: Integrating wind resources: siting decisions in the Midwest

10

Modeling Approach

Market Clearing (wind “must-run”)

Annual wind generation target

Generator capacity and ramp limits

ramp cost for each non-wind generator (i)

Capital costs incurred for each wind farm

Generation cost for each non-wind generator (i)

Page 11: Integrating wind resources: siting decisions in the Midwest

11

Assumptions: Ramping Cost• DeCarolis and Keith (2006)

• Increasing wind power to serve 50% of demand adds about $10-20/MWh due to intermittency + transmission costs

• Lueken et al. (2012) • Analyzed the variability of 20 wind farms in ERCOT over one year and

concluded that costs due to variability are on average $4/MWh • Hirst (2001)

• 100 MW wind farm in MN for delivery to PJM• Intra-hour balance cost: $7 to 28/MWh • regulation costs: $5 to $30/MWh

• Very uncertain so we used a parametric analysis and tested the sensitivity to the results:

• $0, $5, $10, $30, and $100/MWh • Incurred during hourly changes in dispatchable generation

Page 12: Integrating wind resources: siting decisions in the Midwest

12

Transmission Assumptions

$/MW-km Year $$ Source 

$200-900 $2001 Fertig and Apt (2011)

$100 – 1,300 Parameterized Denholm (2009)

$1,200-4,200 $2009 Hoppock & Patino (2010)

Case $/MW-km

Base $1,000

High $2,000

Costs

Distance required per site

x

To account for additional transmission needed along the grid:100%, 200%, 300%, 400%

Page 13: Integrating wind resources: siting decisions in the Midwest

13

MISO LMP map, accessed July 3, 2013https://www.misoenergy.org/MarketsOperations/RealTimeMarketData/Pages/LMPContourMap.aspx

Selection of transmission node clusters

Page 14: Integrating wind resources: siting decisions in the Midwest

14

MISO Delivery $1,000/ MW-km - 200% - $10/MWh

Cap

acity

Fac

tor

44%

44%

45%

45%

46%

Page 15: Integrating wind resources: siting decisions in the Midwest

15

Cap

acity

Fac

tor

44%

44%

45%

45%

46%

MISO Delivery $1,000/ MW-km - 200% - $10/MWh

~ 50 km each from node cluster

~ 10 km from node cluster

How does the answer change under different ramping cost assumptions?

Page 16: Integrating wind resources: siting decisions in the Midwest

16

0 5 10 30 1000%

10%

20%

30%

40%

50%

60%

70%

80%

90%

100%

82% 76% 72%56%

45%

18% 24%24%

29%

29%

4%15%

26%

Ramping Cost Assumption ($/MWh)

MISO Delivery - $1,000/ MW-km – 200%

~8 GW built in MISO

% of totalMW built

Page 17: Integrating wind resources: siting decisions in the Midwest

17

Summary of Scenarios Considered

Distance Scenario Transmission needed (% of distance)

Transmission Costs ($/MW-km)

Ramp Costs($/MWh)

Illinois delivery 50%, 100%$1,000, $2,000

$0, $5, $10, $30, $100MISO delivery

100%, 200%, 300%, 400%

Page 18: Integrating wind resources: siting decisions in the Midwest

18

Conclusions• In most scenarios, remote wind is optimal

even when not accounting for variability ($0/MWh)

• When ramping costs ≥$10/MWh, the optimal portfolio of wind farm locations changes

Page 19: Integrating wind resources: siting decisions in the Midwest

19

Next Steps• Refine scenario to better represent the necessary

transmission capacity to connect farms to MISO’s grid• MISO’s historical Impact Studies• Find someone with a detailed dispatch/ power flow model

…unlikely but I’m hopeful…• Other ideas??

• Better represent transmission capacity needs within Illinois. Currently, assume that 0 km need to be built

Page 20: Integrating wind resources: siting decisions in the Midwest

20

Acknowledgements

This work was supported by the center for Climate and Energy Decision Making (SES-

0949710), through a cooperative agreement between the National Science Foundation and

Carnegie Mellon University, and by the RenewElec project.

Page 21: Integrating wind resources: siting decisions in the Midwest

21

Appendix

Page 22: Integrating wind resources: siting decisions in the Midwest

22

MISO Delivery - $1,000/ MW-km – 100%

0 5 10 30 1000%

10%

20%

30%

40%

50%

60%

70%

80%

90%

100%

32% 32% 31% 25% 19%

55% 55% 55%55%

54%

13% 13% 14% 20%22%

6%

Ramping Cost Assumption ($/MWh)~8 GW built in MISO

Page 23: Integrating wind resources: siting decisions in the Midwest

23

MISO Delivery - $1,000/ MW-km – 300%

0 5 10 30 1000%

10%

20%

30%

40%

50%

60%

70%

80%

90%

100%

100% 99% 99%

75%

53%

1% 1%17% 22%

8%

24%

Ramping Cost Assumption ($/MWh)~8 GW built in MISO

Page 24: Integrating wind resources: siting decisions in the Midwest

24

MISO Delivery - $1,000/ MW-km – 400%

0 5 10 30 1000%

10%

20%

30%

40%

50%

60%

70%

80%

90%

100%

100% 100% 100%84%

61%

16%23%

14%

2%

Ramping Cost Assumption ($/MWh)~8 GW built in MISO

Page 25: Integrating wind resources: siting decisions in the Midwest

25

Illinois Delivery - $1,000/ MW-km – 100%

~8 GW built in MISO

0 5 10 30 1000%

10%

20%

30%

40%

50%

60%

70%

80%

90%

100%

100% 100% 100% 100% 100%

Ramping Cost Assumption ($/MWh)

Page 26: Integrating wind resources: siting decisions in the Midwest

26

Illinois Delivery - $1,000/ MW-km – 50%

~8 GW built in MISO

0 5 10 30 1000%

10%

20%

30%

40%

50%

60%

70%

80%

90%

100%

99% 99% 99% 92%76%

1% 1% 1% 4%20%

4% 4%

Ramping Cost Assumption ($/MWh)

Page 27: Integrating wind resources: siting decisions in the Midwest

27

Different sites within Illinois are chosen!Ramping Cost Assumption ($/MWh)

Site ID CF COV 0 5 10 30 1004022 45% 0.68 IL IL IL IL IL4208 44% 0.72 IL IL IL IL IL4327 44% 0.70 IL IL IL IL IL4214 44% 0.73 IL IL IL IL IL4397 44% 0.71 IL IL IL IL IL4640 44% 0.71 IL IL IL IL IL4140 44% 0.72 IL IL IL IL IL4474 44% 0.69 IL IL IL IL IL4659 43% 0.72 IL IL IL IL IL4242 43% 0.71 IL IL IL IL IL4431 44% 0.71 IL IL IL IL IL4662 43% 0.72 IL IL IL IL IL4241 43% 0.72 IL IL IL IL IL4667 43% 0.70 IL IL IL IL4519 43% 0.69 IL IL IL IL4603 43% 0.70 IL IL IL IL4554 43% 0.71 IL IL4435 43% 0.73 IL IL4635 43% 0.70 IL4636 43% 0.72 IL4605 43% 0.73 IL4606 43% 0.73 IL

Strange pattern likely because of optimal “grouping” of farms to decrease variability

Red represent < 100% capacity of the wind farm was built (i.e., 0 < bk <1)

Page 28: Integrating wind resources: siting decisions in the Midwest

28

Assumptions: Dispatchable Generators• Nuclear, hydro, and existing wind are “must-run”• Gas + Coal are aggregated into one representative

dispatchable unit• Model has to dispatch 1 generator to support the new wind

Tech Type GW $/MWhv Capacity Factor Ramp limit per hour(% of max MW)

Must-run Nuclear 8.5 $12 90% -Wind_existii 8.1 $0 ‘Varied’ -

  Wind_newiv ‘Varied’ $0 ‘Varied’ -Hydro 3.5 $0 95% -Otheri 7.1 $50 90% 60%

Dispatchiii Coal 70 $25 90% 60%Gas 35 $37 90% 100%

  Coal + Gas 105 $30 90% 100%

i: includes residual fuel oil, biomass, and other generationii: wind data from MISO ( 2012a)iii: total load data is from MISO (201b)

iv: not currently included, scenarios to be included in final reportv: Computed using $/mmbtu from AEO (2013), and mmbtu/kwh from EGrid (2009)

Page 29: Integrating wind resources: siting decisions in the Midwest

29

Conclusions• MISO delivery scenarios

• In most scenarios, remote wind is optimal even when not accounting for variability ($0/MWh)

• When ramping costs ≥$10/MWh, the optimal portfolio of wind farm locations changes

• Illinois delivery scenarios• Probably too pessimistic for remote wind• For 100% transmission case, Illinois is always optimal• For the 50% transmission case, adjoining states such as MO

and IA are competitive when ramping costs ≥ $30/MWh• Even with Illinois only wind development, accounting for

ramping costs ≥ $30/MWh affects siting within Illinois

Page 30: Integrating wind resources: siting decisions in the Midwest

30

Xcel Energy RFP

Page 31: Integrating wind resources: siting decisions in the Midwest

31

Impact Study Assessment for ND

Page 32: Integrating wind resources: siting decisions in the Midwest

32

30%

32%

34%

36%

38%

40%

42%

44%

46%

remote local + adj lakes

capa

city

fact

or

0.65

0.7

0.75

0.8

0.85

0.9

remote local + adj lakesco

effic

ient

of v

aria

tion

RemoteND, SD, MN, NE

LocalIL, IN, IA,

MO

LakesMI, WI

RemoteND, SD, MN, NE

LocalIL, IN, IA,

MO

LakesMI, WI

Box Plots of CF and COV by region

Page 33: Integrating wind resources: siting decisions in the Midwest

33

MW

h

0

2

4

6

8

10

12

14

16

18

x 106

State TWhs Perc.remote ND 35 5%  SD 12 2%  MN 53 8%  NE 36 6%local IL 199 31%  IN 122 19%  IA 56 9%  MO 95 15%lakes WI 63 10%  MI 109 17%

Existing Generators in MISO (eGRID, 2012)

Page 34: Integrating wind resources: siting decisions in the Midwest

34

100% 99% 99%

75%

53%

8%

24%

1% 1%17% 22%

0%

10%

20%

30%

40%

50%

60%

70%

80%

90%

100%

0 5 10 30 100Ramping Cost Assumption ($/MWh)

32% 32% 31% 25% 19%

55% 55% 55%55%

54%

13% 13% 14% 20%22%

6%

0%

10%

20%

30%

40%

50%

60%

70%

80%

90%

100%

0 5 10 30 100Ramping Cost Assumption ($/MWh)

100%

200%

100%

400%

300%

82% 76% 72%56%

45%

18% 24%24%

29%

29%

4%15%

26%

0%

10%

20%

30%

40%

50%

60%

70%

80%

90%

100%

0 5 10 30 100Ramping Cost Assumption ($/MWh)

100% 100% 100%84%

61%

14%

16%23%

2%

0%

10%

20%

30%

40%

50%

60%

70%

80%

90%

100%

0 5 10 30 100Ramping Cost Assumption ($/MWh)Ramping Cost Assumptions ($/MWh)