is 15190-2 (2002): acetylene pipelines - code of practice ... · premises where acetylene is...

18
Disclosure to Promote the Right To Information Whereas the Parliament of India has set out to provide a practical regime of right to information for citizens to secure access to information under the control of public authorities, in order to promote transparency and accountability in the working of every public authority, and whereas the attached publication of the Bureau of Indian Standards is of particular interest to the public, particularly disadvantaged communities and those engaged in the pursuit of education and knowledge, the attached public safety standard is made available to promote the timely dissemination of this information in an accurate manner to the public. इंटरनेट मानक !ान $ एक न’ भारत का +नम-णSatyanarayan Gangaram Pitroda “Invent a New India Using Knowledge” प0रा1 को छोड न’ 5 तरफJawaharlal Nehru “Step Out From the Old to the New” जान1 का अ+धकार, जी1 का अ+धकारMazdoor Kisan Shakti Sangathan “The Right to Information, The Right to Live” !ान एक ऐसा खजाना > जो कभी च0राया नहB जा सकता ह Bharthari—Nītiśatakam “Knowledge is such a treasure which cannot be stolen” IS 15190-2 (2002): Acetylene Pipelines - Code of Practice, Part 2: For Pressures from 155 kPa (g) to 2550 kPa (g) [MED 16: Gas Cylinders]

Upload: others

Post on 10-Mar-2020

7 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: IS 15190-2 (2002): Acetylene Pipelines - Code of Practice ... · premises where acetylene is discharg~d from dissolved acetylene cylinder banks through discharge manifolds, It is

Disclosure to Promote the Right To Information

Whereas the Parliament of India has set out to provide a practical regime of right to information for citizens to secure access to information under the control of public authorities, in order to promote transparency and accountability in the working of every public authority, and whereas the attached publication of the Bureau of Indian Standards is of particular interest to the public, particularly disadvantaged communities and those engaged in the pursuit of education and knowledge, the attached public safety standard is made available to promote the timely dissemination of this information in an accurate manner to the public.

इंटरनेट मानक

“!ान $ एक न' भारत का +नम-ण”Satyanarayan Gangaram Pitroda

“Invent a New India Using Knowledge”

“प0रा1 को छोड न' 5 तरफ”Jawaharlal Nehru

“Step Out From the Old to the New”

“जान1 का अ+धकार, जी1 का अ+धकार”Mazdoor Kisan Shakti Sangathan

“The Right to Information, The Right to Live”

“!ान एक ऐसा खजाना > जो कभी च0राया नहB जा सकता है”Bhartṛhari—Nītiśatakam

“Knowledge is such a treasure which cannot be stolen”

“Invent a New India Using Knowledge”

है”ह”ह

IS 15190-2 (2002): Acetylene Pipelines - Code of Practice,Part 2: For Pressures from 155 kPa (g) to 2550 kPa (g) [MED16: Gas Cylinders]

Page 2: IS 15190-2 (2002): Acetylene Pipelines - Code of Practice ... · premises where acetylene is discharg~d from dissolved acetylene cylinder banks through discharge manifolds, It is
Page 3: IS 15190-2 (2002): Acetylene Pipelines - Code of Practice ... · premises where acetylene is discharg~d from dissolved acetylene cylinder banks through discharge manifolds, It is
Page 4: IS 15190-2 (2002): Acetylene Pipelines - Code of Practice ... · premises where acetylene is discharg~d from dissolved acetylene cylinder banks through discharge manifolds, It is

IS 15190 (Part 2) :2002

Indian Standard

ACETYLENE PIPELINES — CODE OF PRACTICE

PART 2 FOR PRESSURES FROM 155 kPa (g) TO 2550 kPa (g)

ICS 25,160.20; 77.140.75

[

:“*,

: ~,,~’”h),

,,

.“.“,

,, ‘

@ BIS 2002

BUREAU OF INDIAN STANDARDSMANAK BHAVAN, 9 BAHADUR SHAH ZAFAR MARG

NEW DELHI 110002

September 2002 Price Group 6

Page 5: IS 15190-2 (2002): Acetylene Pipelines - Code of Practice ... · premises where acetylene is discharg~d from dissolved acetylene cylinder banks through discharge manifolds, It is

Gas Cylinders Sectional Committee, ME 16

FOREWORD

‘1’11is Indian Standard (Part 2) was adopted by the Bureau of Indian Standards, after the draft finaIized by theGas Cylinders Sectional Committee had been approved by the Mechanical Engineering Division Council.

Acetylene gas is distributed to consumers from a source such as a generation plant or cylinder discharge manifoldby means of pipelines. In view of the explosive behaviour of acetylene in piping systems, special precautionsneed to be taken in design, fabrication, erection, testing and commissioning of acetylene gas pipelines. ThisCode stipulates engineering requirements for safe design, construction and commissioning of acetylene gaspipelines. It is based on the concept of’ Working Ranges’, which also has been followed by Industrial GasesCommittee (IGC), Paris.

The co,lcept of’ Working Range’ includes a combination of parameters, such as ‘Deflagration Pressure Limit’,‘Deflagration Pressure Limit’, nature and place of ignition.

The guidelines given in this Code are based on published information and observations made by various authoritieson the subject of acetylene gas in pipelines. It is expected that adherence to the guidelines presented in this Codewi II significantly reduce the safety hazard related to acetylene transmission through pipeline systems. Behaviourof acetylene gas transmitted in pipelines is given in Annex A.

This Code is being published in two parts. Part 1 is as under:

Part 1 For pressure up to 155 kPa (g).

Unless otherwise stated, the pressures mentioned in this Code are gauge pressures.

This Code is intended to recommend safety requirements for design and construction of acetylene pipelineshaving a working pressure rating of 155 kPa (g) (1.55 kg/cm2 g) to 2550 kPa (g) (26 kg/cm2 g). This coverspipelines connecting acetylene compressors and high pressure dryers as well as tilling and discharge manifoldsfor acetylene. Unless otherwise stated, the pressures mentioned in this Code are gauge pressures.

In preparation of this Code, assistance has been derived from the following publications:

a) Code of practice for acetylene pipelines based upon working range (IGC Document No. 9/78/E).

b) Standard for acetylene cylinder charging plant, Compressed Gas Associates Inc., New York, U.S.A.,specification No. G. 1.4.

c) National Fire Protection Association Standard for acetylene cylinder charging plant, specification No.NFPA51A.

d) High pressure gas manifolds — Under-Writers Laboratories Inc. U.S.A., specification No. UL-407.

The composition of tbe Committee responsible for formulation of this standard is given in Annex B.

For the purpose of deciding whether a particular requirement of this standard is complied with, the final value,observed or calculated, expressing the result of a test or analysis, shall be rounded off in accordance withIS 2: 1960 ‘Rules for rounding off numerical values (revised)’. The number of significant places retained in therounded off value should be the same as that of the specified value in this standard.

Page 6: IS 15190-2 (2002): Acetylene Pipelines - Code of Practice ... · premises where acetylene is discharg~d from dissolved acetylene cylinder banks through discharge manifolds, It is

1S 15190 (Part 2) :2002

Indian Standard

ACETYLENE PIPELINES — CODE OF PRACTICEPART 2 FOR PRESSURES FROM 155 kpa (g) TO 2550 kPa (g)

1 SCOPE

1.1 This Code (Part 2) applies to new plant andpremises which may be engaged in production andcompression and filling of acetylene in cylinders andpremises where acetylene is discharg~d from dissolvedacetylene cylinder banks through discharge manifolds,

It is applicable to any addition, modification or revam-ping of such plant or system.

1.2 This Code does not cover the following

The existing plant or premises where acetylene isproduced and filled in dissolved acetylene (DA)cylinders or where acetylene is distributed fromcylinder bank through discharge manifolds. Theplant, which only compresses acetylene forchemical process or which only, produces compre-ssed acetylene at less ,tirin. 155 kPa (g) (1.55 kglcm2g). The installations where acetylene is directlyused from one cylinder through hose assembly forwelding, cutting, heating and heat treatmentoperations.

2 REFERENCES

The following Indian Standards contain provisions,which through reference in this text constituteprovision of this standard. At the time of publication,the editions indicated were valid, All standards aresubject to revision, and parties to agreements basedon this standard are encouraged to investigate thepossibility of applying the most recent editions of thestandards indicated below:

IS No.308:1988

554:1999

1040:19871323:1982

2148:1981

2379:1990

3043:1987

Title

Dissolved acetylene gas (third

revision)

Pipe threads where pressure typetight joints are required on thethreads — Dimensions, tolerancesand designation (jourth revision)

Calcium carbide (third revision)

Code of practice for oxy-acetyIenewelding for structural work in mildsteels (second revision)Flameproof enclosures for electricalapparatus (second revision)

Colour code for identification ofpipelines (j%st revision)

Code of practice for earthing

IS No. Titie

3624:1987 Specificationfor pressure and vacuumgauge (second revision)

11006:1984 Specification for flash back arrestor(flame arrestor)

3 TERMINOLOGY

For the purpose of this Code, the following definitionsshall apply,

3.1 Deflagration — A flame produced by decom-position or combustion that travels into the unreactedgas at a velocity, which is less than that of sound. Therate of propagation of a deflagration flame increaseswith the density, the temperature and the turbulenceof unreacted gas. Since these three parameters tend toincrease as a deflagration progresses, the rate of propa-gation is usually not steady but tends to increasecontinuously and sometimes lead to detonation.

3.2 Detonation —A flame produced by decompositionor combustion that travels into the unreacted gas arate above the speed of sound. Unlike a deflagrat ion,

where the pressure ahead or behind the flame frontrises at the same time, a detonation involves a sharpdifference in pressure between the reacted andunreacted gas. The change from the low pressure ofthe unreacted gas to the high pressure of the reactedgas takes place in a shock wave at the front of theflame.

3.3 Flame or Flash Back Arrestor — An equipment,which quenches a flhrne front (flash back or decom-position). It shall be suitable for flame, which mayoccur due to deflagration and/or detonation. Its designand application shall be such that it shall withstandand be effective in stopping aflame coming from eitherone or both directions (see also IS 11006).

3.4 Manifolds — A system in which two or moreindividually valved, dissolved acetylene cylinders areconnected by pipes or hoses to a common inlet headerthrough which all cylinders are charged simul-taneously without dismantling the cylinders or arenormally discharged simultaneously through thecommon outlet header.

3.5 Portable Manifolds — They are basically twotypes:

a) In this, gas passes from connected cylindersthrough individual leads to a single commonlead or block. From there through a single

,1

Page 7: IS 15190-2 (2002): Acetylene Pipelines - Code of Practice ... · premises where acetylene is discharg~d from dissolved acetylene cylinder banks through discharge manifolds, It is

IS 15190 (Part 2) :2002

b)

pressure reducing station (in case of a dis-charge manifold) to the consumption point.

The cylinders are connected through coupler/tees attached to shut off valve of ea~hcyl~der.Gas from each cylinder passes through thecoupler/tees and joins the main streamflowing through a common line.

3.6 Stationary Manifolds — These are essentiallymanifolds supported on wall or floor and provided withfittings for connecting individual cylinders by meansof leads (pigtails). In case of discharge manifolds, oneor more permanently mounted regulators are providedto reduce and regulate the pressure of the gas fromthe cylinders.

28.169

14.084

7.0425.634

4.225

2.817

1.408

0.704

INITIAL PRESSURE CORRECTED

4(+,/

,.

3.7 Nominal Diameter (DN) — Every part of a piping .!+

system manufactured by hot and cold rolling methods ‘,,$andJor by piercing and cold drawing shall be identifiedby its nominal diameter. Nominal diameter is derivedfrom the approximate inside diameter up to 100 mm.

The nominal diameter shall be designated by theabbreviation DN. The typical designation of a pipeline

8

,,,p;.

system where nominal diameter is 50 mm shall be ,.DN 50.

3.8 Predetonation Distance — The distance that adeflagration travels in a Class 3 category pipelinebefore it develops into a detonation. For evaluation ofpredetonation distance, for systems under variousoperating conditions at different pressures shal I betaken from Fig. 1.

To 15“ c (60”F) kg/cm2 (ABSOLUTE)

r 1 I I 1 I I I I I I I I I I 1PREDETONATIONDISTANCE LIESIN THIS AREA 1

MINIMUM R SURq 8

kt%fA#06” I D F RVARIOUS TUBE SIZES

I x I

I I- *12 mm (0.5) —

\ I I\

625 mm (1)

\r

1 I I

I I \ \4s50 mm (2)

I @100 mm (4)

u 7 I I I

I I ‘ % @200 mm (8)I

I 300 mm (12

!11I

I I I II I I I I I I

.-..

1

PREDETONATION DISTANCE, METRES ~

(DISTANCE Transverse BY FUME BEFORE DETONATION DEVELOPS)

NOTE — For acetylene pressure of 2.8 kg/cm2absolute, for example, the predetonation distance lies in the range of 2.4 metres to 16.75lmetresprovided the diameter of the tubes is large enough so that it does not preclude detonation at this pressure. The horizontal Iines 01’IIwabove figure shows the least pressuresrequired for detonation in Wbesof different diameters. It also shows that the 2.4 to 16.5 metres mngcIbr detonation to occur, applies to tubes larger than 35.5 mm internal diameter but not smaller.

The above figure applies to detonations that develop in acetylene gas from deflagrations and which in turn, is initiated tiom non-shockthermal source of initiation.

FIG. 1 EVALUATION OF PREDETONATIONDISTANCE FOR ACETYLENE

PIPELINES UNDER VARIOUS OPERATING CONDITIONS

2

Page 8: IS 15190-2 (2002): Acetylene Pipelines - Code of Practice ... · premises where acetylene is discharg~d from dissolved acetylene cylinder banks through discharge manifolds, It is

3.9 Reflection — If in case of detonation the forwardmoving shock wave hits an obstruction such as theend of a pipe or a closed valve, the pressure increasesconsiderably and the shock wave is reflected, similarto water hammer.

3.10 Working Pressure (Pw) — It is the maximumoperating pressure in kPa of a piping system.

3.11 Acetylene Compression — Compression to apressure of 155 kPa (g) (1.55 kg/cm2g) or above, thepressure rises being achieved by compression eitherin single stage or multiple stages.

3.12 Leads or Pig Tails — Flexible device made ofmetallic reinforced rubber, teflon or steel suitable toconnect the main manifold pipe to the cylinder throughproper connections.

3.13 Unpierced Wall — A wall which may have pipesor conduits passing through it or windows, glazed withsafety glass andlor wired glass set in it, but suchopen ings must be sealed to prevent flow of air betweenthe spaces separated by the wall.

4 LOCATION AND GENERAL ARRANGE-MENT OF PREMISES AND SAFETY

4.1 Location and general arrangement of building shallconform to the Ministry of Industry, Government ofIndia, Notification No, 625 dated 7 August 1983 orany other notifications issued in this regard by theappropriate authority.

4.1,1 The building housing acetylene compressor,filing manifold of discharge manifold of the acetylenemanufacturing and charging plant shall be located atleast 15 meters from public right of way and from lineof adjoining property or building that may be builtupon. Boundary wall or barbed wire fencing shall belaid around the building at a minimbm distance of9 meters to avoid unauthorized entry of any person.Clear sign boards ‘Hazardous area — No smoking inthe premises’ and ‘No trespassing — No smoking oropen flame’ shall be displayed in the premisesprominently.

4.2 The buildings walIs shall be constructed preferablyof non-combustible materials. Any combustiblematerials used shall have a fire resistance rating of atleast one hour.

4.2.1 The compressor station or filling manifold ordischarge manifold shall not be housed in a buildingwhich has a basement or floor below it or of a floorabove it,

4.2.2 The roof of the buildings shall be made of lightmaterial or be provided with explosion venting areaof not less than 0.06 m2/m3of building volume.

‘, 1’$>9 Lik

.

dIS 15190 (Part 2) :2002

1

i.;.S1.f

4.2.3 The building/room housing shall be well

~

. .ventilated both at floor level and roof level. The :,ventilation provided should be such that flow of air isnot less than 3.3 m3/min/m2 of ceiling area. Theventilators should be covered with two layers of11 meshes per linear centimetre stainless steel or any ~,,.non-corroding material wire mesh; brass mesh if used,

/., .:,

shall have not more than 65 percent copper content.‘,,,’,

4.2.4 If any heating is required in the building, it shallbe by steam or hot water.

4.2.5 Boiler, heaters and other heating equipmentemploying flames or capable of creating sparks shallbe housed in a separate building located 15 m awayfrom the building housing the acetylene compressionequipment, charging manifold or discharge manifolds.

4.2.6 Electrical equipment and wiring in roomshousing compressor and equipment for filling anddischarge of acetylene shall have flame proof fittings

conforming to IS 2148 and suitable for at least gasgroup class IIB. All the equipment shall be electrical Iyearthed (see IS 3043).

4.2.7 The acetylene or acetone fire, normally, shallnot be extinguished with hose water or portable fireextinguishers. To avoid any fire, leak free pipelinesand good quality valves shall be used. However, forfweprotection the following precautions shall be taken:

a)

b)

c)

For waste disposal the receptacles should beself-closing metal (non-sparking type).

The area shall be equipped with hose of dia40 mm (nominal bore) station equipmentunless continuous water spraying over fit Iing

or discharge manifold is available. Alterna-tively automatic sprinklers system may beprovided ensuring that the water coverage isnot less than 13 I/m/mz of floor area.

The fire hose and water spray actuation valvesshall be so located that they can be operatedfrom out-door or at an exit.

4.2.8 Each plant shall adopt detailed emergencyprocedure and shall conduct periodic fire drill. Aflameproof alarm shall be provided for summoningfire fighting and to caution people in emergency.

4.2.9 A maximum of 80 cylinders (or 480 cubic meter

of gas) shall be connected to a manifold under oneroof. In case more than 80 cylinders (or 480 cubicmeter of gas) are to be connected under one roof,manifold shall be separated by a concrete wall of 2.5 mhigh and not less than 200 mm thick, so that in anarea isolated by the concrete walls, not more than 80cylinders (or 480 cubic meter of gas) are connected tomanifolds that can be in operation (filling/discharge).

3

Page 9: IS 15190-2 (2002): Acetylene Pipelines - Code of Practice ... · premises where acetylene is discharg~d from dissolved acetylene cylinder banks through discharge manifolds, It is

IS 15190 (Part 2) :2002

5 ACETYLENE COMPRESSOR

5.1 Installation

5.1.1 The inlet and outIet piping of each compressorshall be provided with readily accessible shutoff valvesthat can be closed in an emergency.

5.1.2 Drain lines from high pressure [above 155 kPa (g)(1.55 kg/cm2g)] oil separation condensate traps anddrains shall be manifolded and lead to separators witha safety valve set at 147 kPa (g) (1.5 kg/cm2g) theoutlet of which shall be connected to inlet ofcompressor suction or piped out to vent the gas at aheight of at least 5 m and away from the building.The condensate, liquid, etc, shall be piped outside thebuilding away from any source of ignition andcombustible material or shall be drained to eflluentwater drains.

5.1.3 The compressor shall be fitted with pressurerelief valve (safety valve) of full size on the dischargeof each stage.

5.1.4 The compressor shall be provided at suction anddischarge with pressure switch or a similar fail safedevice capable of shutting down the compressor if thecompressor suction pressure falls below 250 mm ofwater column or if the discharge cross the maximumset pressure, which is no case shall exceed 2744 kPa (g)(28 kg/cm2g). Shut-off valve or by pass valve for thepressure switches shall not be installed.

5.1.5 The flow of acetylene through the inter-connecting piping shall be designed at velocityspecified below:

Pressure Linear Velocity

kgfcmz g mlsUp to 6 106toll 5llto21 321 to26 2.5

5.1.6 Compressor shall be constructed so that theacetylene is co’oled during and after each state ofcompression. When water is used, the flow of waterfrom cooling jacket and inter-coolers shall be visibleto the operator.

5.1.7 Where the compressor is watercooled, valve onwater inlet line shall be provided fbr regulating waterftow.

5.1.8 Transmission belt when used in compressor shallbe anti-static type.

5.2.1 All parts of the compressor coming in contactwith acetylene under pressure shall be tested hydrau-lically at the test pressures given below:

Maximum Working Test Pressure

Pressure, Pw kglcm2 glcgIcm2gup to 0.2 3.750.2 to 1.5 12 to 24Above 1.5 11 XPW+IO

5.2,2 The compressor shall have a connection so thatthe whole unit can be rinsed/purged with nitrogen andlor water.

5.2.3 The compressor shall be pneumatically tested atits operating pressure by holding pressure in the systemfor 24 h without any visible leak. The fall in pressureshall not be more than 0.2 percent per hour of theinitial pressure.

5.2.4 At suction and discharge of the compressor andat”each stage, pressure and temperatures measuringdevices shall be provided.

5.2.5 Where oil lubrication is provided oil pressuregauge to show oil lubrication pressure shall beprovided.

5.2.5.1 Oil used for acetylene compressor should beconrpatible with acetylene.

5.2.5.2 Provision should be made to check oil level.

5.2.6 In case of lubricated compressor having oil pump,a suction filter for lubricating oil shall be provided.Use of porous metallic or ceramic filter element isrecommended. Provisions shall be made so that theycan be cleaned from time-to-time.

5.2.7 If Nitrogen Fails

Safe device is connected directly to the acetylene; itshall have non-return valve and automatic devices toprovide flow of nitrogen in the compressor in case ofemergency.

5.2.8 The compressor shall be provided with a localas well as remote emergency switching off device.

5.2.9 A precooler with condensate trap shall be provi-ded in the suction of the compressor.

5.3 High Pressure Drier

5.3.1 The high pressure drier shall have down-streampressure regulator to regulate the back pressure at1372 to 1666 kPa (g) (14 to 17 kg/cm2g).

, .. ----

.J

5.1.9 The piston speed shall not be more than 0.7 m/s. 5.3.2 The desigp of the high pressure drier shal! be

5.2 The temperature of”acetylene at the discharge valvesuch that the velocity of acetylene ‘shall increase by0.20 to 0.25 mls.

of any stage shall not exceed 140”C.

4

Page 10: IS 15190-2 (2002): Acetylene Pipelines - Code of Practice ... · premises where acetylene is discharg~d from dissolved acetylene cylinder banks through discharge manifolds, It is

5.3.3 Before and after the high pressure drier filtersshall be provided.

5.3.4 Where calcium chloride is used as dryingmedium, the drier shall have arrangements for blowoff with nitrogen or acetylene to remove air after freshcharge or after long stoppage f%omuse.

5.3.5 The drying agent like calcium chloride shall befilled in baskets made of steel sheet having perforationof 5 mm diameter in triangular pitch, or any similardevice, for ease of removal and discharging.

6 PIPING AND SAFETY DEVICES

6.1 High pressure piping are the pipes having aworking pressure above 245 kPa (g) (2.5 kg/cm2 g)for use after first stage of the acetylene compressor upto filling manifold and for discharge manifold up topressure reducing station.

6.2 Piping and fittings shall be made of steel, wroughtiron, malleable iron or copper alloy having less than65 percent copper. Unalloyed free silver or mercuryshall not be used.

6.2.1 Steel is recommended as the material of constru-ction for acetylene transmission systems. In a pipelinesystem, materials for all components like joints, seals,gaskets, diaphragms, hoses shall be so chosen that theyare adequate resistant to the action of commercialgrade acetylene, including its impurities as indicatedin IS 1040 and IS 308 and solvents like acetone (ifpresent), under the system operating conditions (thatis temperature and pressure) and resistant toatmospheric corrosion,

6.3 AII piping and equipments shall be electricallycontinuotis and connected to any grounding electrodeas defined in IS 3043.

6.4 Pipe sizes of more than DN 25 shall be avoided asfar as possible, but in no case pipe size more thanDN 40 shall be used. For higher flow, multiple pipesof DN 25 is recommended.

6.4.1 The diameter of a pipeline shall be finalized sothat the required pressure is available at consumer,with the maximum flow in a given pipe run. It isrecommended that the velocities be maintainedbetween 2 to 4 m/s for sizing of pipelines,

6.5 Pipe material shall preferably have not less thanthe following mechanical properties:

Tensile strength, A4in 3430 kPa (35 kg/cm2)Yield strength, A4in 2352 kPa (24 kg/cm2)Elongation on gauge 28length 5.65dS0,percent, Min

IS 15190 (Part 2) :20024

:1Ci,:’,.

6.6 The working pressure of acetylene pipe lines shall

j

,.,not be more than 2548 kPa (g) (26 kg/cm2 g) absolute.

., $.

6.7 Pipe used shall be seamless having a wall thicknesscalculated as given in 6.7.1”and 6.7.2.

6.7.1 Where pipe materials as specified in 6.2 is usedthe wall thickness shall be:

!

,,f :, ,,;,

a)

b)

,.. ;where the ends of pipe, bends elbow, reducer,

~

~.’:,

enlarger, joints, openings are strengthened by.,. .

a length at least twice the inside diameter ofpipe and to a thickness twice the pipethickness, the thickness shall be 0.16 timesof inside diameter. The strengthening maybe complied by welding the reinforcement orby screwing or by bolting the reinforcement.

where no reinforcement is used the thicknessof the pipe should be 0.30 times of insidediameter.

6.7.2 Where any other material is used other than 6.5the wall thickness (t) shall be:

a) Where reinforcements are used according to6.7.l(a)

20x PWD

*=(200 xf)-(20x Pw)

b) Where reinforcement are not used:

35x PWDt=

(200xf)-(35xPw)

where

Pw = maximum working pressure in kg/cm’absolute,

D = inside diameter in mm, and

f = allowable stress in kg/cm2.

6.7.3 The length of pipe (straight portion) shall besuch that it is less than or exceeds the ‘Predetonat ionDistance’.

6.7.4 The reinforcements of the pipes as recommendedin 6.7.1 a need not be provided if flash back arrestorfitted with non-return valves are provided at each such

point. However, reinforcements at the end of the pipeshall be necessary, as flash back arrestors does notserve any purpose at the ends.

6.7.5 All acetylene gas pipeline system shall be prote-cted .by flashback arrestors and non-return devices ora combination of both. To prevent entry of air oroxygen these should be fitted as near as practical toany outlet point.

6.7.6 The following locations shall be installed withflashback arrestors:

:... -

5

Page 11: IS 15190-2 (2002): Acetylene Pipelines - Code of Practice ... · premises where acetylene is discharg~d from dissolved acetylene cylinder banks through discharge manifolds, It is

a) at the outlet of source of acetylene gas suchas generation plant or discharge manifold.

b) at the entrance and exit of gas holders, ifinstalled, within the acetylene gas conveyingsystems.

c) at the exit of each booster, if any installed onthe acetylene gas pipeline system.

d) at branch point ffom main header to shopsub-header.

e) at the entry to each consuming unit.

6.7.7 Where a single unit of flash back arrestor maynot be adequate to handle required flow rate, multipleunits of flash back arrestors shall be installed forparallel operation and the individual gas inlets, outletsand liquid drain connections shall be interconnectedto respective common headers.

6,8 The provision for expansion and flexibility shalltake into consideration the maximum possibletemperature differential between the design tempe-rature and the ambient temperature in cold season.

6.8.1 All steel pipework shall be of sockethm-weldedconstruction. Use of socket weld joints are however,preferred. Welds on pipelines shall be located at placeswhere the minimum bending stresses occur as farpracticable. Flanges shall be provided on straightlengths as required for easy erection and maintenance.Flanged joints shall also be provided to match theconnecting ends of equipment, valves and fittings, etc.Where screwed connections are permitted shall be ofacceptable standard (see IS 554). Number of flangedand/or screwed joints shall be restricted to a minimumto minimize the possibility of gas leakage.

6.8.2 Joints are recommended to be assembled withthe inside of all pipes and fittings smooth, clean andfree from burns, blisters, scale, welding slag, sand anddirt. The inside edges of pipes and tubings shall bereamed after cutting to remove burrs. Whereverpossible the inside of the weld without backing ringsshall be ground smooth. Flange faces shall be free fromparticles of weld metal.

6.8.3 All jointing by electric arc and gas weldingprocess shall be carried out according to IS 1323.However, provisions of statutory regulations and fireprotection manual of the Insurance Association ofIndia shall be complied with, wherever applicable.

6.8.4 All welding work shall be carried out by qualifiedwelders, All tiller materials, edge preparation, post-weld treatment shall give a good welding. All weldsshall be made in such a manner that complete thsionand penetration are obtained without an excessiveamount of filler metal beyond the root areas. Rein-forcements, wherever required shall be applied in such

a manner that it will have a smooth pipes and weldedfittings. d

. .

6.8.5 Pipe and attachments shall be aligned accuratelyand held fmly prior to welding. If tack weld is used,the tacks shall be either thsed into the first layer ofweld or chipped out. All welds shall be built up by theapplication of multiple beads or passes; the thicknessof metal deposited in each bead or pass shall not exceed3 mm. Each bead shall be cleaned and, if not a workhardening material, shall be lightly preened beforethe next bead is laid. The complete weld and surroun-ding pipe shall be cleaned of slag and metal splatteron all surfaces and the inside beads shall be groundsmooth where practicable.

6.8.6 Welded carbon steel piping need not be stressrelieved except where specified.

6.8.7 Acetylene pipelines shall be clearly identifiedby the word ‘Acetylene gas’ or by colour codingaccording to IS 2379. The identification markingsshall be repeated at regular intervals and visiblelocations to ensure that the pipeline(s) can be clearlyidentified and are not contl.medwith adjacent pipelinescarrying other substances.

6.9 Pipeline or manifold shall be supported as follows:

Pipe Size, DN Maximum DistanceBetween Supports

mm mm

(1] (2)10 2000

---

15 200020 200025 2000

30 2500

40 3000

7 PRESSURE GAUGES/TEMPERATURE GAU-GES AND SAFETY VALVES

7.1 Pressure gauge used in the system shall have safetytype standard with blow (bursting) disc described inrelevant clauses of IS 3624.

7.2 Upstream of every pressure gauge, a throttle shallbe installed to limit the tlow to less than 10 1/s atnormal conditions.

7.3 Pressure gauge and temperature gauges range shallbe such that at the normal working pressure the indica-tor points around the middle of the dial.

7.4 Temperature gauges for measurement of tempera-ture shall have a minimum graduation of 2“C.

7.5 The maximum working pressure and temperatureshall be marked in red on the dial of the gauges.

6

Page 12: IS 15190-2 (2002): Acetylene Pipelines - Code of Practice ... · premises where acetylene is discharg~d from dissolved acetylene cylinder banks through discharge manifolds, It is

7.6 Safety valve shall be full flow type capable ofventing maximum flow for which the pipeline isintended at 10 percent over pressure. The valve shallbe fitted with test lever, so that operation of the safetyvalve can be checked manually.

7.7 The vent of the safety valves or any other ventshall be discharged outside the building at a height of5 m and away from any part of the building orcombustible material and or source of ignition oropenings. The end shall be so constructed, that itcannot be obstructed by rain, snow, ice or birds, Itshouldbe hooded or bent and covered with wire mesh.

7.8 No isolation valve shall be provided on the safetyvalve inlet.

8 ACETYLENE CYLINDER CHARGING ANDDISCHARGING MANIFOLDS

8.1 Each cylinder charging or discharging manifoldshall be provided with a shut off valve, vent valve anda safety valve. The vent valve maybe connected to thelow-pressure system or vented outside the building toatmosphere.

8.2 A flash back arrestor shall be installed in thepipeline at each cylinder charging or dischargingmanifold or in each cylinder charging or discharginglead or pigtail.

8.3 Each outlet or inlet from the manifold shall beprovided with shut off valve.

8.4 The cylinder charging or discharging leads (pig-tails) shall be so arranged that excessive mechanicalstress in the cylinder leads are prevented.

8.5 The cylinder charging or discharging manifoldpipe shall be so arranged they are at least 200 mmabove or below the level of cylinder valves.

8.6 Each cylinder charging or discharging manifoldshall be provided with three flame arrestor with non-retum valve in series,

8.7 The length and size of manifold pipe shall be basedon 1/m3 of acetylene flow per hour per connectedcylinder. The spacing between two connections shallbe not less than 1.25 times the maximum diameter ofacetylene cylinder that will be connected to manifold,with a minimum distance of 300 mm.

8.8 All leads (pigtails) shall have a minimum testpressure of 9800 kPa (g) (100 kg/cm2 g) and have aminimum bursting pressure of 58 800 kPa (g)(600 kg cm’ g).

8,9 The electrical resistance where the leads are joinedto the manifold shall not be more than 10 ki16 ohms.

8.10 To protect the manifold from flame or over-

7

IS 15190 (Part 2) :2002

heating, it is recommended to adopt the followingpractices:

a)

b)

Water sprays on the cylinders and manifoldor provide the manifold inside a channel tilledwith circulating water.

Use of chilled water at a temperature in therange of 4 to 7°C may be used to improve thecooling effect.

8.11 Where rubber hose pipes are used, they shall bereinforced with metallic fibre and shall be compatiblewith acetylene and acetone. The metallic braiding ofthe hoses shall not be used for earthing.

9 VALVES AND FITTINGS

9.1 All fittings shall be seamless socket welded or butt-welded, but socket welding is preferable. Whereverbutt welding is unavoidable, arrangements to cleanthe inside of weld shall be made or ‘Y’ filler or backingstrips used.

9.2 For connecting pressure gauges, transmitter, etc,threaded joints may be used but the thread shall betapered gas threads.

9.3 The valve shall be of a class suitable for theworking pressure of 20580 kPa (g) (210 kg/cm2 g) atambient condition.

9.4 The flanges used, if any, shall be suitable for aworking pressure of 20580 kPa (g) (210 kg/cm2 g)and shall be slip-on type having male female faces.

9.5 The bolts and nuts used shall be high tensile type.

9.6 Gasket material used shall be compressed, graph i-ted asbestos or S-buttons and/or neoprene rubber.

9.7 Packing material shall be graphite impregnatedasbestos or teflon.

9.8 Unions, flanges and threaded joints shall beprovided only to the extent to facilitate maintenance.As far as possible pipe joint shall be done by socketwelding.

9.9 Bends formed with a minimum diameter of fivetimes of inside diameter of the pipe are recommendedin place of elbows, as far as practical.

9.10 Elbows, bends, tees shall preferably be forgedfrom carbon steel and socket weld type suitable forworking pressure of 27440 kPa (g) (280 kg/cm2 g).

10 INSPECTION AND TEST

10.1 Inspection

10.1.1 All components used for the construction ofthe acetylene system (except for site-fabricatedcomponents like bends, tees), shall be supported by

. ..----”

.s

Page 13: IS 15190-2 (2002): Acetylene Pipelines - Code of Practice ... · premises where acetylene is discharg~d from dissolved acetylene cylinder banks through discharge manifolds, It is

IS 15190 (Part 2) :2002

m anufacturer’s test certificate(s). These test certificatesshal1be scrutinized to ensure that all components usedare conforming totherequirements ofthis Code.

10.1.2 The equipment and pipework shall be subjectedto visual inspection. The pipeline, after completion oferection, shall be inspected for its conformity with theconstruction drawings prepared according to thestipulations of this Code.

10.1.3 All welded joints shall be visually examinedeither during manufacture, fabrication and erectionto ensure conformity with the requirements of thisCode.

10.2 Pressure Tests

10.2.1 Prior to acceptance and initial operation, insta-lled piping shall be pressure tested to ensure thesystem’s strength and leakproof.

10.2.2 In the event of repairs or additions are madefollowing the pressure test; the affected piping shallbe retested.

10.2.3 A piping system shall be tested as a completeunit or in sections. For the connecting piping and otherappurtenances for testing, it is not required that thetie-in sections of pipes, be pressure tested.

10.2.4 The test procedure used shall be capable oflocating all leaks in the section and shall be capableof establishing that the section being tested is capableof withstanding the test pressure. The test pressureshall be selected as per stipulations of this code andshal I be done after giving due consideration to thevolumetric content of the section and to its location.

10.2.5 Wherever possible, pipe joints including weldsshall be left uncoated and exposed for examinationduring test.

(2.5 kg/cm2 g), 10 times the maximumworking pressure with m~imum test pressurebeing 2000 kpa (g) (20 kg/cm2g).

c) Pressure above 250 kPa (g) (2.5 kg/cmz g),20 times the maximum working pressure withminimum test pressure of 30 000 kPa (g)(300 kg/cm2 g).

NOTE—Rubberhoses or any part, which can withstand highpressure but can get permanently deformed, may be isolated andpressurereleased after holding the test pressure for a maximum of30 s.

10.3.2 Test Duration

Test duration shall be not less than 30 min for each14 m3of pipe volume or fraction thereof. For pipingsystem having a volume of more that 68 m3, theduration of test shall not be less than 24 h.

11 INSULATION

All overhead yard or exposed acetylene gas pipelinesmay be protected against excessive external heat andpossible formation of ‘liquid acetylene by suitableinsulation. In all cases of insulation provided onacetylene lines, claddings (vapour barriers) shall beof fwe resistant type.

12 DRAINS

Provisions shall be made to drain accumulatedcondensate or testing fluid from acetylene pipelines.To ensure condensate drainage and liquid drainage,pipelines shall be laid with a gradient of about 1 mmper metre run towards the drainage points. Drainagepoints shall be provided at the lowest points ofacetylene gas pipework and special provisions shal I

be made in its design to prevent entry of air into theacetylene line and to prevent fkeezing of any seal liquidused. The size of the drain pipelines s;.all be such

10.2.6 Equipment which is not to be included in the that the entire pipeline between sectionalizing valves

test shall either be disconnected from the piping or can be drained within the desired time period, which

isolated by blank flange$. shall be not more that 30 min.

10.2.7 Prior to testing, the interior of the piping systemshal 1be clear of all foreign material.

10.3 Hydraulic Testing

10.3.1 The following test pressure shall apply forhydraulic testing of systems/components (other thanfor the compressor, which shall be carried out accor-ding to 5.2.1 designed in accordance with thisstandard:

a) For pressure less than 155 kPa (g)(1 .55 kg/cm2g), 1.5 times the maximumworking pressure.

b) For pressure more than 155 kPa (g)(1.55 kg/cm2g) but less than 250 kPa (g)

13 PRE-COMMISSIONING REQUIREMENTS

13.1 It has to be ensured before an acetylene system isput into commission that it has been designed,fabricated and erected in line with the constructiondrawings and with stipulations of this code.

13.2 In case the system is taken up for commissioningafter a considerable time lapse of its erection andtesting and there is a possibility that the system hasdeteriorated, then the system shall be retested beforeits commissioning.

13.3 Commissioning of acetylene system at dark isnot recommended.

13.4 Adequate numbers of fire fighting personnel, fire

------

>;..

8

Page 14: IS 15190-2 (2002): Acetylene Pipelines - Code of Practice ... · premises where acetylene is discharg~d from dissolved acetylene cylinder banks through discharge manifolds, It is

IS 15190 (Part 2) :2002

fighting equipment and appliances are placed inappropriate locations.

13.5 All consumers of acetylene shall be kept in-operative till such time that the commissioning of thesystem is over and the same is certified as being readyto be put into service,

1,3.6 All sources of heat and fire shall be kept at least15 metre away from the acetylene system. Possibilityof sparks from locomotives/automotives, chimneys/stacks, static electricity, and short circuits shall becompletely eliminated.

13.7 Possibility and occurrence of vibration and physi-cal shock to the acetylene pipelines shall be eliminated.

13.8 Unauthorized use of pipeline as electricalconductor or as a support for other items have notbeen made.

13.9 It shall be ensured that the safety devices andinstruments installed are of the correct type andspecifications do not show signs of deterioration ormalfunction or unauthorised usage. Devices againstentry of air and oxygen (that is condensate drainagesystem) shall be checked for proper operation and itshall be ensured that they are not blocked. Wet typeflash back arrestors shall also be checked, formaintenance of correct water level, Filters and drytype flash back arrestors shall be examined for propercondition and has to be ensured that they are notblocked.

13.10 The setting of pressure regulators/reducingstations shall be as per specified parametersldutyconditions.

13.11 All valves at service points, isolation, vent, drainpoints and equipment connections shall be checkedfor complete opening and tight shut-off.

14 CLEANING

14.1 Acetylene system shall be properly cleanedinternally by blowing compressed air or nitrogen gasthrough pipes. Velocity of blowing shall be between15 to 20 m/see and pressure at the air/nitrogen inletshall be 600 kPa (g) to 700 kPa (g) (6 to 7 kg/cm2 g).All vents, drains, service points including flash backarrestors shall be blown by means of blowing medium.

14.2 Wet type flash back arrestors shall be blown afierdraining the water. Atler blowing operation is over,the flash back arrestor shall be refilled with water upto the correct water Iavel.

14.3 Dry type flash back arrestors may be cleanedin-situ by blowing compressed air/nitrogen.

15 PURGING AND COMMISSIONING

15.1 The purpose of process of purging and successfulcommissioning of the acetylene gas systems is toensure that no air and/or oxygen comes in contact withacetylene gas.

15.2 Purging of system shall commence from theacetylene gas source. The isolation valve between thesource and” system shall.. remain closed. Nitrogenadmission to the section/pipeline shall be started byopening the nitrogen inlet valve connection providedat the source end, Nitrogen gas admission shall bedone by connecting the nitrogen supply system withflexible hose, At the same time vent valves located atthe other end of the section/pipeline shall remain open.

15.3 For purging operations, nitrogen gas of Min

97.5 percent purity with a velocity of 15 to 20 m/seeshall be used.

15.4 Introduction of nitrogen gas shall be continuedtill samples taken at selected ventipurge out pointsshow satisfactory oxygen content, The acetylenepipeline may be considered free from air if the outgoingnitrogen contains not more than 2 to 5 percent ofoxygen. Nitrogen supply shall be terminated and al Iisolation/purge-in/drain/vent or purge out valves forthe pipeline/section under consideration shall be keptcompletely shut-off under nitrogen pressure.

15.5 Once the purging operation for the section iscomplete, the nitrogen inlet valve at the source endand the vent valve at the other end shall be closed.The section, which has been purged, shall remainpressurized with nitrogen gas at a pressure of about100 kPa (g) (1 kg/cm2 g),

15.6 Once the entire system has been purged and

pressurized with nitrogen gas, admission of acetylenegas shall be commenced. Acetylene from the sourceshall be admitted by opening the inlet isolation valvea few turns. The valves for purge out point and ordischarge points shall be opened. Gas sample shall becollected for measuring acetylene gas concentration.The section or pipeline vent/purge port points shallbe closed as soon as acetylene concentration of 10 per-cent by volume of nitrogen is reached. The acetylenegas consumption at the outlet or filling then can becommenced.

15.7 Acetylene gas/acetylene gas nitrogen mixturecoming out of the terminal section inside a consumingshop shall be diverted away and out of any shop/workplace to safe distance.

15.8 Any section of the acetylene gas system which isnot in use, after commissioning, shall be purged withnitrogen and remain pressurized with nitrogen gas tiIIit is put on stream.

9

Page 15: IS 15190-2 (2002): Acetylene Pipelines - Code of Practice ... · premises where acetylene is discharg~d from dissolved acetylene cylinder banks through discharge manifolds, It is

* “?aa

‘.,,.

IS 15190 (Part 2) :2002

ANNEX A

( Foreword)

BEHAVIOUR OF ACETYLENE GAS TRANSMITTED IN PIPELINES

Acetylene can burn in the presence of air from a rangeof 2 to 82 percent. In case of occurrence of a source ofignition of any form in an acetylene pipeline system,decomposition of acetylene gas into its constituents,namely carbon and hydrogen, can be initiated even inthe near absence of air or oxygen. Hence the design ofan acetylene conveying system shall include facilitiesto keep airloxygen out of acetylene and to preventacetylene leakage into air, The appearance of a brightflame, rise in temperature and pressure, and sootformation which resembles the explosive conversionof a mixture of fuel gas and oxygen are characteristicsof acetylene decomposition.

Propagation of acetylene gas decomposition from theignition source to the rest of the pipeline dependsmainly on the working pressure of the pipeline andits size.

The ignition energy required initiating the decom-position, its vel~ity and associated pressure rise withinthe pipeline are mainly dependent on the workingpressure qnd size of the pipeline. If decomposition ofacetylene is initiated in atpipeline due to a source ofignition ‘deflagration’ followed by ‘detonation’ mayoccur. The definition of ‘deflagration’ reflects theconditions under which the acetylene decompositionoccurs and procw’ds at a moderate velocity (belowsonic) and at which associated rise in pressure to amaximuiriof11 to 1Ytitnei the initial pressure occurs.The transition from ‘deflagration’ to ‘detotiation’occurs under conditions which are also indicated inthe definition for ‘detonation’. Pipeline conveyingacetylene shall be designed, constructed, tested andmaintained to prevent occurrence of ‘deflagration’ and‘detonation’ and withstand the same in case of theiroccurrence.

._.-----

/

10

Page 16: IS 15190-2 (2002): Acetylene Pipelines - Code of Practice ... · premises where acetylene is discharg~d from dissolved acetylene cylinder banks through discharge manifolds, It is

IS 15190 (Part 2) :2002

ANNEX B

( Foreword)

COMMITTEE COMPOSITION

Gas Cylinders Sectional Committee, ME 16

Organization Representative(s)

SHRIR. H. BHALSXAR(Chairman)Departmentof Explosives,NagpurSHruSHAhraHuPrwsm (Akernate)

DRP.L. BHA_mSmuB. N. QANUNm(Alternate)

All India IndustrialGases Manufacturers’Association,New Delhi

Sau K. GOHNATHANSmuDEBASHISDASS(Alfemafe)

Balmer Lawrie& Co Ltd, MatJrura

Bharat PetroleumCorporation Ltd, Mumbai SHSUGEORGEPAUL

SsrruS. K. DEY (Alternate 1)SHRISURSS.HNAIR(Alternate 11)

BharatPumps&Compressors Ltd, Allahabad

BOC India Ltd, Kolkata

Everest Kanto Cylinder Ltd, Aurangabad

.%uuK. C. JOSHISmaS. K. TEWASU(Alternate)

SHRIP,K. BHATTACIWRYASHRSN. R. PAL(Alternate)

SHIUA.mK. PAREGISSUOP.M. SAMVATSAR(Alternate 1)

SHRIA. G. Kkmmm (Alternate 11)

Hindustan Petroleum Corporation Ltd, Mumbai SHRIK. KXWNANSm D.N. KrUSHNAMORTHY(Alternate)

SsuuR. TANDONSsmuN. K. SAWHNEY(Alternate)

Ilindustan Wires Ltd, Faridabad

Indian Gas Cylinders, Faridabad Smr E. M. PATEL

%ru D. C. JAIN(Alternate)

Indian Oil Corporation Ltd, Mumbai SmuB. L. BANSAL

Smu A. N. KHAFIW(Alternate)

In personal capacity (303, Shantikanj, Athwalines, Surat)

International Industrial Gases Ltd, KolkatR

Mu L. D. THMMR

SHRSDSVSNORAK.GARGSHSUN.K. GARG(Alternate)

SHRIASHWINH.WASrrtuS. SSSHKUMAR(Alternate)

J.R. Fabricators Ltd, Mumbai

KabsonsGas Equipments Ltd, Hyderabad

Kosan IndustriesLtd, Mumbai

SHRISATISHKARRA

SHFUS. SONS(Alternate)

SriruA.T.AZAOEOOSHSUD. R. BHAGALIA(Alternate)

LPG Equipment Research Centre, Bangalore

Maruti Koatsu Cylinders Ltd, Mumbai

Met Lab Services Pvt Ltd, Mumbai

Ministry of Defence (R&D), Pune

Ministryof Defence, Pune

Nagpur Fabriforge Pvt Ltd, Nagpur

MN. Dastur & Co Ltd, Kolkota

Naiional Safety Council, Mumbai

SSUUI.M. BHOLA

Sm S. M. VENOOOPAL(Alternate)

SHRSNmNJ.THARKARSmuA. S. SAXAN(Alternate)

SHRJS.C. PA3UKHSrsroSUDHSRKm_ (Alternate)

SHIGN. K. CHOPRA

SmuA. BASU(Alternate)

SFUUK.PARmrrrMNSmuD. D. BANGAR(Alternafe)

Ma G. L.NaEMASrmrA. M. TmrE(Alternate)

Sr-rraA.K.Ct+wrrMARmSHRSP.K.BANDYOPADHAYAY

SHSUH.N. GWTA

(Continued on page 12)

11

Page 17: IS 15190-2 (2002): Acetylene Pipelines - Code of Practice ... · premises where acetylene is discharg~d from dissolved acetylene cylinder banks through discharge manifolds, It is

IS 15190 (Part 2) :2002

(Continued from page 11)

Organization

Shri Shakti LPG Ltd, Hyderabad

BIS Directorate General

%UJ.P.RAMAPPA

SrmK.V.CHALAPATHVRAO (Alternate)

MUM. L. CHOPRA,Director & Head (MED)~epresenting Director General (E@,71cio)]

Member-Secretary

SW S. B. ROYDkector (MED)

Dissolved Acetylene Gas Cylinders and Gerenators Sub-committee, ME 16:4

International Industrial Gases Ltd, Kolkata SsauD. K. GARG(Convener)

All India Industrial Gases Manufacturers’Association,New Delhi DRP.L. BHATM

Bharat Pumps&Compressors Ltd, Alkrhabad SmUS.K. TOWASU

SrnuK. G. SHUKLA(Alternate)

Bt3C India Ltd, Kolkata SHRIP.K. BH.MTACTMRYA

SHION. R. PAL(Alternate)

Department of Explosives, Nagpur SHSUsHAMaHuPRASADSrouR. H. Bwwmwr (Alternate)

Industrial Gases Ltd, Kolkata SHSUA. GARG

Industrial Oxygen Co Pvt Ltd, Mumbai SHSUR. R. SIGANPORIA

Jai Maruti Gas Cylinders Pvt Ltd, Gwalior SmrrASHOKK. NKMMSsauR. K. NIGAM(Alternate)

M. N. Dastur & Co Ltd, Kolkata SHSOA.K.CwwrurJwwSaruP. K. BAmYOPAOHYAY(Alternate)

“----

12

Page 18: IS 15190-2 (2002): Acetylene Pipelines - Code of Practice ... · premises where acetylene is discharg~d from dissolved acetylene cylinder banks through discharge manifolds, It is

Bureau oflndian Standards

BIS is a statutory institution estdiished under the Bureau of Indian Standards Act, 1986 to promote harmoniousdevelopment of the activities of standardization, marking and quality certification of goods and attending toconnected matters in the country.

Copyright

BIS has the copyright of all its publications. No part of these publications may be reproduced in any formwithout the prior pemlission in writing of BIS. This does not preclude the free use, in the course of implementing{he standard, of necessary de~dils, such as symbols and sizes, type or grade designations. Enquiries relating tocopyright be addressed to the Director (Publication), BIS.

Review of Indian Standards

Amendments are issued to standards as the need arises on the basis of comments. Standards are also reviewedperiodically; a standard along with amendments is reaffkned when such review indicates that no changes areneeded; if the review indicates that changes are needed, it is taken up for revision. Users of Indian Standardsshould ascertain that they are in possession of the latest amendments or edition by referring to the latest issue of‘BIS Catalogue’ and’ Standards: Monthly Additions’.

This Indian Standard has been developed from Dot; No. ME 16 (0388). ,

Amendments Issued Since Publication

Amend No. Date of Issue Text Affected

BUREAU OF INDIAIHeadquarters:

Manak Bhavan, 9 Bahadur Shah Zafar Marg, New Delhi 1Telephones: 3230131,3233375,3239402

Regional Offices:

Central : Manak Bhavan, 9 Bahadur Shah Zafar MargNEW DELHI 110002

STANDARDS

0002 Telegrams: Manaksanstha(Common to all ot%ces)

Telephone

3237617,3233841

Eastern ; 1/14 C.I.T. Scheme VII M, V.I.P. Road, Kankurgachi{

3378499,3378561KOLKATA 700054 3378626, 3379120

Northern : SCO 335-336, Sector 34-A, CHANDIGARH 160022{

603843602025

Southern ; C.I.T, Campus, W Cross Road, CHENNAI 600113{

2541216,25414422542519,2541315

Wcstcm : Mauakalaya, E9 MIDC, Marol, Andheri (East){

8329295,8327858MUMBAI 400093 8327891,8327892

Branches : AHMEDABAD. BANGALORE. BHOPAL. BHUBANESHWAR. COIMBATORE. FAIUDABAD.GHAZIABAD. GUWAHATI. HYDERABAD. JAIPUR. KANPUR. LUCKNOW. NAGPUR.NALAGARH. PATNA. PUNE. RAJKOT, THIRUVANANTHAPURAM. VISAKHAPATNAM.

5,

Printed at Simco Printing Press, Delhi