  • January-March 2006

  • IN THIS ISSUE

    Overall view of NHT/CRU Plant for CPCL at Manali near Chennai

    Focus

    Editor

    Editorial Team

    Photography

    Cover Design & Layout

    L&T has extensive experience and expertise to execute all types of hydrocarbon projects, such as Refineries, Petrochemical plants, Oil & Gas installations including LNG plants. It is the only Indian EPC company pre-qualified for executing large, process-intensive projects, and offers single-point responsibility for execution of these p r o j e c t s . I t h a s e n g i n e e r e d , manufactured and delivered world-class p l a n t a n d e q u i p m e n t ; o f f e r s comprehensive construction services and provides the complete range of eng ineer ing serv ices inc lud ing procurement and commissioning assistance to refinery, petrochemical, oil & gas projects.

    In the following pages, we bring out some of the projects recently executed by ECC, L&T's Construction Division, which has made a s ign i f icant contribution to the development of country's hydrocarbon industry.

    V.S. Ramana

    K. Sridharan Alex BenjaminV.D.S. Prasad V. Ramesh Kumar Ashwin Chand V. Eswar

    Subha Anand

    V.S. Natanavelu

    Romaa Communications

    L&T Fuels the Nation's Progress 2Panipat Refinery Expanded 9Anand-Rajkot Gas Pipeline 19Mora Vapi Pipeline 21Songo Songo Gas Pipeline 22Cryogenic Storage Tanks 26LPG Underground Storage 28Magadi Soda Project 30HDS Reactor-HPCL, Vizag 33 Projects Commissioned 34New Orders 39Papers Presented 40 Awards/Rewards 43 Exhibitions 48Functions 50Inaugurations 53

    January -March 2006Vol.28,No.4

    L&T Fuels the Nation's Progress

    Hydrocarbons are organic molecules that capacity of the country stood at 127.4 million consist exclusively, or primarily, of carbon metric tonnes for the year 2004-05. To meet and hydrogen atoms. While many of the the ever increasing demand for oil products, hydrocarbon compounds occur free state in existing refineries are rapidly expanding their nature (under the earth's crust), some are capacities and new refineries are slated to artificial in origin. Crude oil and natural gas come up in the near future with the Ministry are mixtures of hydrocarbons of natural of Petroleum & Natural Gas (MoP&NG) origin formed by the decomposition of living contemplating to ramp up the countrys organisms, under the earth. Natural gas refining capacity. The additional refining contains hydrocarbons in gaseous state while capacity for exports will help India offset its crude oil contains hydrocarbons in liquid huge crude oil import bill and take up exports state, either saturated or unsaturated, at room so as to compete with refineries in Singapore temperature. and West Asia. According to Hydrocarbon

    Vision 2025, the demand for oil products is estimated at 155million tonnes for 2006-07, The origin of the oil industry in India can 195 million tonnes for 2011-12 and 368 be traced back to the last part of the 19th million tonnes by 2024-25. century when petroleum was discovered in

    Digboi in nor th -eas t India . Af ter independence, the industry - with Burmah With the increasing environmental Shell, ESSO and Caltex as major players, was concerns, Indian refineries recently nationalised. Every activity - exploration, upgraded their operations to meet Euro III development, production, refining, norms.marketing, distribution - was controlled by the various public sector companies in the Natural Gasfield.

    Known as the fuel of the twenty-first India is currently the fourth largest oil century, natural gas has emerged as the most

    consumer in the Asia-Pacific region after preferred fuel due to its inherent Japan, China and South Korea. Estimated to environmental advantages, greater efficiency grow at the rate of 7% a year, the demand for and cost effectiveness. The demand for petroleum products, in absolute terms is natural gas globally has gone up sharply in expected to be 155 and 195 million tonnes the last two decades. In India too, the natural respectively for the years 2006-07 and gas sector has gained importance, 2011-12. particularly over the last decade.

    Refining Production of natural gas at the present level is around 87 million standard cubic

    As of March 2005, there are 18 refineries meters per day (MSCMD). The main in the country (including one in the private producers of natural gas are Oil & Natural sector). The downstream refining through put Gas Corporation Ltd. (ONGC), Oil India

    2

  • CRU Heaters for Chennai Petroleum Corporation Ltd (CPCL), Manali

    Limited (OIL) and JVs of Tapti, Panna-Mukta L&T's cutting edge technology coupled While the E&C Division of L&T has and Ravva. Under the Production Sharing with business processes and systems has engineered, manufactured and delivered Contracts, private parties are also producing enabled the company to sustain its world-class plant and equipment to gas from some of the fields. Government leadership in the domestic market as well as hydrocarbon related projects, ECC, L&T's have also offered selected blocks under New unfurl its flag in project sites in the Middle C o n s t r u c t i o n D i v i s i o n , o f f e r s Exploration Licensing Policy (NELP) to East, Russia, CIS countries, Asia Pacific and comprehensive construction services for private and public sector companies with the Africa. hydrocarbon related projects. This apart, right to market gas at market determined L&T's joint venture company, L&T Chiyoda

    L&T's core strength lies in its ability to prices. Out of the total production of around Limited, provides the complete range of o f fe r in teg ra ted eng ineer ing and 87 MSCMD, after internal consumption, engineering services including proposal, construction services for critical projects extraction of LPG and unavoidable flaring, front-end engineering and design (FEED), involving process design, basic and detailed around 74 MSCMD is available for sale to procurement and commissioning assistance engineering, project management, consumers. to refinery and petrochemical projects.equipment fabrication, procurement, construction and commissioning all types of L&T has executed several refinery Liquefied Natural Gas (LNG)plant & equipment for the core sector packages including the fast-track Diesel industry including infrastructure projects, Hydro de sulphurisation (DHDS) projects on The first LNG receiving terminal of the with single-point responsibility. Strategic a Lump sum Turnkey (LSTK) basis for country was set up by Petronet LNG, at alliances with world leaders enable L&T to reducing the sulphur content in diesel to Dahej in Gujarat. The plant was designedto access advanced know-how and deliver meet the Bharat / Euro norms as required by handle 5 MMTPA (20 MSCMD) of LNG and projects that meet stringent quality the country's statutory bodies. is doubling its capacity to 10 MMTPA (40 requirements and time frames.MSCMD). To date, there are 2 LNG

    It has fabricated and supplied critical terminals operational in India while four equipment and systems for refineries and gas EPC ProjectsLNG receiving terminals are proposed to be cracker plants. The range includes high set up in the country.pressure, high temperature reactors like L&T, as builders to the Nation with its hydrocrackers, DHDT & DHDS reactors for we l l known commi tmen t t o t he Larsen & Toubro Limited'clean fuel' projects. An area of development of India's core sector Oil & Gas specialization includes fabrication and industry, has a major presence in Larsen & Toubro Limited (L&T) is India's supply of critical equipment like FCC hydrocarbon related projects. L&T is the largest engineering and construction reactors and regenerators to international only Indian EPC company pre-qualified for organization. With a sales turnover standards & specifications of well-known exceeding US $3.5 billion, L&T has an executing large, process-intensive projects, process licensors (reactors as large as16.3 international presence with a global spread and offers single-point responsibility for metres in diameter and 1200 tonnes in of operations. execution of these projects. weight).

    3

  • Over the years L&T has acquired vast experience in design, engineering, procurement, fabrication and construction of other packages like Sulphur Recovery Units (SRU), Mini refineries, Skid mounted Sulphur Recovery units, Skid mounted Mini refineries and Skid mounted Gas Processing Plants. L&T's E&C Division has been certified for conformity to ISO-9001, ISO-14001 and OHSAS-18001 standards and accreditations.

    Oil & Natural Gas

    Apart from its involvement in the construction of downstream projects, L&T is also actively involved in the execution of critical projects for the upstream oil and gas sector including construction of offshore oil platforms, cross country pipelines and oil & gas terminals. A number of repeat orders and challenging assignments won against stiff compet i t ion through internat ional competitive bidding from Oil & Natural Gas Corporation (ONGC) as well as the cross-country pipeline projects executed by ECC

    involved in the construction of the Assam Oil ECC undertakes turnkey construction of for Oil & Gas Public Sector Companies bear Refinery way back in the 1950s, when it Refinery & Petrochemical, Chemical, testimony to its growing presence in executed the piping and equipment erection Fertilizer, Cross-country pipelines and Oil & developing this core sector industry in India.works. Since then there has been no looking Gas projects involving comprehensive back and ECC has been associated with services, civil construction works, structural ECC's Constructive Contributiona lmos t a l l the re f ine ry p ro jec t s , fabrication and erection, piping fabrication petrochemical and oil & gas related projects and erection, fabrication and erection of Many of the major refinery projects in including the cross country oil & gas pipeline equipment, erection of heavy lifts, electrical India have benefitted from L&T's engineering projects. system design and project electrification and construction expertise. ECC, was

    including instrumentation works.

    Floating roof tank for HPCL Vizag

    Pipe laying for Jamnagar - Loni Gas Pipeline Project

    4

  • their gas cracker plant at Nagothane and of the World's largest refinery at Jamnagar for Reliance Petroleum including their units at Patalgana and Hazira.

    Refineries and Petrochemicals

    The range of services offered by ECC includes:

    ! Design and construction of all civil works for cooling towers, equipment & pipe-rack foundations, electrical sub station and control buildings including geo-technical investigations and solutions.

    ! Design, procurement and construction of plant structures and non-plant buildings

    ! Design, procurement and construction of storage tanks with floating and fixed roof tanks

    ! Electrical system design including Its track record includes turnkey Corporation Ltd (HPCL); Mangalore procurement and project electrification construction of major refinery, petrochemical Refineries and Petrochemicals Ltd (MRPL), aswell as installation of equipment, and oil & natural gas projects involving Gas Authority of India Ltd (GAIL), Gujarat control and automation systems.multiple challenges, such as technical State Petronet Ltd (GSPL). In addition, ECC

    complexities, faster construction periods; was actively involved in the construction of logistics, high risks, safety and environmental the project for Indian Petrochemicals issues etc. Corporation Limited (IPCL) at Baroda and

    ECC has built a vast reservoir of in-house capabilities and expertise in design and construction of cross-country oil & gas pipelines, terminals, offsite facilities, storage tanks with floating / fixed roofing systems, cooling towers and cooling water systems, electrical & instrumentation including fire protection system.

    A specialised team of erection engineers provide erection schemes for lifting all types of heavy and odd size equipment, towers, columns, reactors, regenerators, absorbers, converters etc. with precision arrangements using heavy lift cranes as well as the strand jack lifting systems. It will not be out of place to mention that L&T is the only organization in India, which has executed the maximum number of fast track shut-down assignments in virtually every refinery, under operating conditions, close to highly hazardous and congested areas prone to high risks, meeting the complete safety requirements and stringent time schedules.

    ECC's clientele includes Indian Oil Corporation (IOC) and its subsidiary, Chennai Petroleum Corporation Limited (CPCL); Bharath Petroleum Corporation Limited (BPCL) and its subsidiaries Numaligarh (Assam) Refinery Ltd, and Kochi Refineries Ltd, Kerala; Hindustan Petroleum

    Reformer, PSA Vessels and heaters for CPCL, Manali

    Piping works executed for BPCL at Mahul

    ...Contd on page 8

    5

  • E&C Division has successfully executed Infrastructure at MFF: projects for international clients such as Kuwait National Petroleum Company Area

    L & T h a s s t a t e - o f - t h e a r t (Shuaiba Refinery), Songas-Tanzania ! Total developed manufacturing facilities which are (onshore and offshore pipeline), Qatar area : 180,000 Sqm capable of meeting the challenges of Petroleum, and Gasco Bu Hasa, Abu Dhabi. ! Fabrication and technology, quality conformance and Load-out : 173,000 Sqm de l i ve ry , wh i le ensu r ing cos t ! Piping shops : 1,900 Sqm competitiveness. L&T's manufacturing ! Covered stores : 1,500 Sqmunits are located at: ! Offices : 3,600 Sqm

    ! Jetty/Wharf L&T's Modular Fabrication Facility (MFF) ! Powai (Mumbai) Main Jetty : 100 m x 18 m meets exacting quality standards with

    ! Heavy load-out compressed delivery schedules. Located at ! Hazira (Surat) - with its own water facility : 80 m x 42 m Hazira, 295 km north of Mumbai and 21 km

    front and a Ro-Ro (roll-on/ roll-off) ! Roll-on-roll-off jetty : 60 m x 40 mfrom Surat, on the banks of the river Tapi, the jetty facility has unimpeded passage to the

    Range Arabian Sea, 8 km away. ! Ranoli (Vadodara) dedicated to ! Offshore platforms

    handling stainless steel, non-ferrous ! Process modules and skid-mounted One of the largest of its kind in South and exotic materials equipmentAsia, the MFF is capable of manufacturing

    ! Fired heaters several large modules simultaneously. L&T has been associated with leading ! Modular process plants like Fabricated modules are tested and pre-

    EPC contractors and engineering Continuous Catalyst Regeneration commissioned onshore to ensure rapid and consultants in this sector. Large numbers (CCR) unit, trouble-free hook-up at site. The MFF of critical equipment have been exported Sulphur recovery unit conforms to international standards of safety to every continent including North ! Heat recovery steam generators and quality and has ISO 9001-2000, ISO America, South America, Europe, the ! Desalination plant and equipment 14001 and OHSAS 18001 accreditations and Middle East, South Africa, the former ! Barge-mounted plant a certificate of authority to use the API Soviet Union, Australia and the Asia- ! Modular and marine structures monogram for products manufactured as per Pacific region. ! Pipe reelsspecifications API 5L and API 2B.

    Engineering & Manufacturing Capabilities

    A view of L&Ts Hazira works on the banks of the river Tapi

    Modular Fabrication Facility

    Heavy Engineering

    6

  • ! Technology eva lua t ion/ l icensor To ensure smooth and timely selection execution of its projects, LTC has state-of-

    ! Basic engineering the-art IT facilities and a rich talent pool of ! Front-end engineering design experienced and highly competitive ! Detailed engineering Knowing t he po t en t i a l f o r engineering manpower. The quality of ! Procurement assistance hydrocarbon projects in the country, in LTC's engineering deliverables is ! Inspection and expediting services 1994 L&T went in for a technical maintained through implementation of ! Start-up and commissioning assistance collaboration and set up a joint venture ISO 9000:2001 quality system into the ! Total project management engineering company with Chiyoda project execution.consultancy ServicesCorporation of Japan, a world renowned ! Revamp and modernisationEPC organisation for undertaking the LTC has executed more than 60 major Studies construction of large hydrocarbon projects with the latest engineering

    projects specifically in the area of grass technologies to the complete satisfaction LTC has developed high-end engineering root petroleum refineries, oil and gas (on of domestic clients such as IOCL, BPCL, capabilities such as process simulation, shore and off shore) processing, CPCL, KRL, IPCL, ONGC, GAIL, Cairn intelligent P&IDs, intelligent 3D plant petrochemicals, liquefied natural gas Energy, etc as well as international clients modeling, composite analysis, finite element plants and terminals on EPC basis. such as TOC (Thailand), Sipchem (Saudi analysis, piping stress analysis, etc. in a short Arabia), QAFAC (Qatar), FERTIL (Abu period of time.

    L&T-Chiyoda Limited (LTC) is a joint Dhabi), etc.venture engineering company of L&T (holding 50% of equity) and Chiyoda Corporation, Japan, international integrated engineering and construction contractor with five decades of experience in hydrocarbon and related fields.

    LTC offers total engineering solutions to process industries such as:

    ! Petroleum refineries ! Chemical & Petrochemical units ! Oil and gas processing facilities ! LNG & LPG terminals ! Fertilizer plants

    The engineering and consultancy services provided by LTC include:

    ! Techno-economic feasibility reports 71m high, 210t Demethaniser (left), 83m, 395t Ethylene Rectifier being erected for the petrochemical complex of Reliance Industries (Phase II) at Hazira

    Well head platforms ready for load out from L&Ts Hazira Works for Oil & Natural Gas Corporation

    L&T-Chiyoda Limited

    7

  • ! Construction of LNG terminals and LPG ...contd. from page 5 construction of civil, mechanical, storage facilities.electrical and instrumentation for

    ! Procurement and construction of fired composite station works, cathodic heaters involving massive structural ! Engineering, procurement, construction protection system for pipelines/stations.fabrication and process plant piping and commissioning of storage facilities

    inc lud ing spec ia l i zed we ld ing for LPG underground caverns.techniques using inconel, hastalloy,

    ! L&T entered into laying of onshore titanium, etc., ! Erection of high capacity gas compressors cross country pipelines in1992 and so far

    and associated facilities.has laid about 3300 Km of pipelines ! Procurement and construction of M. Ramkumarranging from 12 to 30 in diameter and

    mounted bullets and horton-spheres General Managernow is in a position to manage 5 spreads (Hydrocarbon Construction & Pipelines)simultaneously.

    ! Erection of static and rotary equipment including heavy lift erection of tall columns, reactors, re-generators, etc.,

    ! Complete shutdown maintenance and revamping works.

    Cross-country Pipelines and Oil & Gas Terminals

    ECC offers a wide range of services like:

    ! Execution of cross-country pipeline projects involving pipe-laying (including OFC), horizontal directional drilling (HDD), testing, pre-commissioning and commissioning of pipelines including design, engineering, procurement and

    Illuminated view of the Reliance Patalganga project

    Naptha cracker plant for Reliance Industries, Hazira

    8

  • Panipat Refinery is the seventh refinery turpentine oil, bitumen, sulphur, etc. highly challenging as well as satisfying as all of Indian Oil Corporation Limited (IOCL), a Besides, about 2.4 lakh tonnes of cooking the packages had very stringent completion Global Fortune 500 company with a vision gas per annum is being supplied from the schedules and the progress was monitored to become a major , d ivers i f ied , Refinery. by IOCL at the highest levels with their transnational, integrated energy company. Director (Projects) attending all the monthly Backed by state-of-the-art technologies from Currently the Refinery's capacity is review meetings and reporting to the global majors, Panipat Refinery is being expanded to 12 MMTPA and L&T has Chairman, said Mr. S.K. Sampath, ECC's considered a technically advanced refinery. played a major role in the construction of the Project Manager (since posted as Chief Built in an area of around 2,200 acres of land same through five packages as follows: Manager, Larsen & Toubro [Qatar] LLC). In at a project cost of Rs. 3868 crore (including the initial stages the clients had serious marketing and pipeline installations), the ! Diesel Hydro Treater Unit (DHDT) & reservations about timely completion of the Refinery has an installed capacity of 6 Hydrogen Generation Unit (HGU) various packages but in course of time L&T million metric tones per annum (MMTPA). ! Reformer Packages within Hydrogen was able to remove all these apprehensions. Designed for processing both indigenous Generation Plantand imported crude oil, since its ! Purified Terephthalic Acid (PTA) On seeing the speedy progress, IOCL commissioning in 1998, the Refinery has ! Coke Drum System Package (CDSP) developed so much confidence that they processed about twenty-five types of ! Raw Water Treatment Plant (RWTP). even contemplated offloading to L&T some imported crude oil from different countries. of CDU/VDU works which were entrusted

    While the first four packages were to other contractors, said Mr. Sampath. The Refinery is capable of producing bagged by L&T's E&C Division as EPCC Further, he said that the close interaction of

    about 8 lakh tonnes of petrol, 3 lakh tonnes contracts, with ECC taking responsibility for ECC with IOCL and their Consultants of jet fuel, 12 lakh tonnes of kerosene and 26 the construction part, the fifth package for Kvaerner Powergas helped them to address lakh tonnes of diesel annually. Other RWTP was awarded as a direct EPC contract a number constructability issues at the products include naphtha, mineral to ECC. Execution of Panipat Project was design stage itself.

    Panipat Refinery Expanded To 12 MMTPA

    PTA Plant at IOCLs refinery, Panipat

    9

  • construction work, initially valued at Rs.75 mobile tower crane of 45 meters height was DHDT and HGU Plants -crore, on September 23, 2002 with soil placed in the passage between the hydrogen Worlds Largestinvestigation. Piling was taken up on plants to lift various structures and December 4, 2002 and mechanical mechanical equipment as part of the

    IOCL awarded the DHDT/HGU package completion achieved on July 28, 2005. The mechanical erection work. This tower crane to E&C Division of L&T on August 27, 2002 scope included piling, civil works, was used round the clock for civil and through International Competitive Bidding. fabrication & erection of structures, mechanical erection and electrical work as The scope of work included residual process underground and aboveground piping, well and substantially quickened the design, detailed engineering, procurement, erection of static/rotary equipment, grit progress of construction. supply, transportation, fabrication, storage, blasting & painting, design/engineering, construction, installation, testing, pre- procurement and construction of fire fighting Critcal Wall Pipingcommissioning, commissioning and system, installation, testing & commissioning performance guarantee test run of DHDT & of electrical & instrumentation work for the For welding of heavy wall piping joints, a Hydrogen Generation Unit. The completion entire DHDT/ HGU and Reformer Package. fully automatic welding machine was time for the package, valued at Rs.581 crore, This involved fabrication and erection of imported from Luberdi Diametric of USA was pegged at 27 months. complex and heavy structures using state-of- because of its cutting edge technology and

    the-art P&M. Execution of this unique project high productivity. The machine was used to IOCL subsequently awarded to M/s involved several challenges and ECC with its weld about 100 joints of diameter ranging

    Haldor Topsoe A/S and L&T, the 2 x 70,000 meticulous planning and systems approach from 12 to 24 and thickness varying TPA Reformer packages, to be constructed faced every obstacle with ease and between 16 mm and 40 mm. It is capable of within the Hydrogen Generation Plant. successfully completed the project to the welding 16 dia and 32 mm thick joints in a

    entire satisfaction of the client. Following are matter of thirty minutes whereas, if done ECC played a major role in the some of the construction highlights of our conventionally, the same work would take

    construction of the 3.50 MMTPA capacity work: one full day. The machine greatly helped in DHDT Unit (world's largest) and the 2 x completing critical heavy wall piping in 70,000 MTPA capacity hydrogen plants reaction area with a high level of quality and Tower crane for mechanical erection(Asia's largest), valued at Rs.109 crore and accuracy and in saving considerable Rs. 18.3 crore well ahead of the given execution time.Since the two hydrogen plants, had to be schedule of 35 months and 24 months. constructed in a congested and restricted

    Radiant Chambersarea of 153 m x 125 m with intricate The DHDT/HGU project at Panipat, a structures already in place, it was not feasible The reformer fabricated for IOCL at

    first of its kind in the world, proved to be a to use cranes for erection work as originally Panipat has two streams and is Asia's biggest challenging task. ECC commenced the envisaged. After a lot of brainstorming, a in terms of its size and capacity. Radiant

    A View of DHDT/HGU Plant at IOCL, Panipat

    10

  • chambers for reformers are normally fabricated in panel Form. However, due to excessive heat generated during welding it was very difficult to achieve the stipulated tolerances. Further, this method was found to be time-consuming and posed safety and quality problems. In view of this and the tight construction schedule, ECC adopted the modular concept for the radiant chamber. In all 40 modules of size 13.10 m x 3 m x 3 m, weighing 18 tonnes, were fabricated in a record time of 106 days and pre-assembled in the fabrication shop and later erected at site. By this method the site could achieve the required tolerances and save on time and cost.

    Bobcats

    Bobcats are compact lifting machines, made of longer wheelbase and skid-streer, used for various activities during construction where working space is a constraint. At Panipat, these compact and agile machines were used for multi-tier working due to limited workspace amidst heavy structures, thereby ensuring that the movement of men and materials were made easy and kept to the minimum and also meeting standards.

    Safety Record

    Challenging as the task on hand was, the site team did not lose sight of the equally important aspects of quality and safety and achieved 24 million safe man-hours without any lost time or accident. In recognition of

    This performance L&T won the following co n v e n t i o n a l man ag e me n t s t y l e , awards: participative style of management was

    brought in. By this method, every staff was ! Silver Award for Occupational Safety allocated a definite area of operation, and he from Royal Society for the Prevention of was empowered to carry out his assignment Accidents (RoSPA) for the period 2003-2004. without waiting for instructions from the

    seniors. He asserts, Our engineers were ! Best Safety Conscious Project (Above given the freedom to interact directly with Rs.500 crore Contract) Category by IOCL the clients whenever required. This brought Panipat Refinery Award February 2005. down considerably the time for any

    communication or instructions to percolate ! Safest Trophy for Major Job site in ECC for down the line.the period April 2004 to March 2005.

    The Hydrogen Generation Unit was ! ISO 9001-2000 Certificate for Quality commissioned on November 18, 2005 and Management System in IPU Sector. DHDT Plant went on stream on December

    21, 2005 smoothly and flawlessly much to Mr. Sharad Kumar (SK), Project Manager, the delight of all associated with this mega

    attributes the success of the DHDT/HGU project. Significantly, IOCL's commissioning project to certain measures introduced at site team members commented this has for better results. In place of the never happened before

    HGU Plant at IOCL Panipat

    Technological Structures of DHDT Unit

    11

  • ! Driven Cast In Situ Piles(450 mm dia,18.5 m long) : 4107 nos.! RCC/PCC Concrete : 25000 Cum! Structural fabrication

    & Erection : 7300 t! RCC pavement &

    Ironite flooring : 45000 Sqm! Fire proofing of

    structures : 60600 Sqm! Under ground : 49737 IM

    Piping /20000ID ! Above ground : 491772 ID

    Piping /576241 IM! Fire fighting system : 50180 IM! Static Equipment

    Erection : 3000 t! Heavy Lift Equipment

    Erection : 2000 t! Rotary Equipment

    Erection : 1006 t! Painting of

    Structures & Piping : 175000 SqmKVA- 12 nos., Batching plant 20 cubic /Hrs- ! Impulse Piping : 2225 Tags Major resources employed1 no., Transit Mixture 4 cubic/ 6 cubic- 5 (43200joints)nos., Weld Generator / Rectifier- 6 nos., ! Electrical &

    Following are the major resources Hydrolic Test Pump- 6 nos., Gantry Crane- 2 Instrumentation Cabling : 950 km

    deployed during peak for DHDT / HGU & nos! Cable Tray & Duct

    Reformer project including E&I.Installation : 135 km ! Equipment & panel Hydrogen Reformer & Heaters

    Installation : 478 nos. Plant & Machinery :! Fabrication & Erection

    This 2 x 70000MTPA capacity hydrogen of Duct/Cable Supports : 1000 t Link belt Crane 700 t Capacity-1no., reformer (the biggest reformer in Asia) ! Calibration of American Crane 225 t Capacity- 1 no., Tower converts hydrocarbons and methane into Instruments : 6138 nos. Crane G3/33B T2 60 m 12 t Capacity- 1 no., hydrogen, carbon monoxide and carbon-di-! Installation of Fully Automatic Orbital Welding M/c- 1 no., oxide. Valued at Rs.18.30 crore, this Instruments : 6301 nos. Crawler Crane 75 t Capacity- 5 nos., Crawler involved three main process features ! Impulse Tubing : 13161 nos Crane 20 t Capacity- 4 nos., Hydra Crane hydrocarbon reaction section, furnace ! Installation of Lighting 20/30/40 Mt Capacity- 10 nos., Trailer heating section and waste heat recovery Poles & Fixture : 6961 nos. 20/40t / TRUCK- 11+1 nos., Hydra Crane section and the entire work was executed in

    10 t- 9 nos., DG Set - 380 KVA /250 KVA/125 24 months

    Each of the two reformers having a capacity of 70,000 MTPA, has the following identical features:

    ! 360 burners in 6 horizontal rows installed on the two side walls of the duplex fire box

    ! 240 nos. of catalyst tubes - 120 in each box

    ! 240 nos. of hair pin tubes - 120 in each box

    Gas is used as the main fuel for burners, but Naptha is also used as an alternate fuel.

    Diesel Hydro Treater (DHDT) unit of IOCLs refinery at Panipat

    2 x 70000MTPA capacity hydrogen reformer (the biggest reformer in Asia)

    Major quantities

    12

  • A View of Silos at the PTA Plant of IOCL Panipat

    During the process, the fuel gas flows Major Quantities Appreciation from the client upward through the outlet provided at the top of the chamber whereas the process gas Following are major items of work flows downwards through the catalyst tube executed for Reformers & Heaters:(provided inside) and gets collected in cold collector at the bottom of the furnace. The ! Radiant Section : 1329 tprocess gas leaving the tubular reformer ! Structural : 822 tpasses through a waste heat boiler (RG ! Ducting (CS) : 406 tBoiler), where saturated HP steam is ! Ducting (AS) : 335 tproduced. This process gas is again cooled ! Stack : 862 tin a BFW pre-heater. ! CS Piping : 33245 ID

    ! Jacket Piping : 65434 IDThereafter, the process gas enters ! S.S Piping

    Hydrogen generation unit (HGU) for further (Heavy) : 1981 IDheat recovery and finally it is sent to PSA ! A.S. Piping : 2251 IDsystem for purification to produce 99.99% ! Piping supports : 34 tpure Hydrogen. ! Inlet distributor : 224 ID

    ! Inlet hairpin tubes : 960 IDThe waste heat generated by the fuel gas ! Catalyst tube : 2400 ID

    and let out from the reformer furnace, has a ! Cold collector : 984 IDtemperature of around 1060C. This heat is ! Static Equipment recovered and used for: erection : 1602 t

    ! Rotary Equipment ! Pre heating of Reformer feed ! erection : 174 t! Pre heating of Pre-reformer feed ! Grit Blasting ! Superheating of steam & Painting : 75335 Sqm! Heating of combustion air! Generation of superheated HP steam! Preheating of Combustion air

    13

    To: [email protected]: [email protected]: 11/21/2005 03:16PM

    Subject: Safe and successful commissioning of Hydrogen Unit

    November 21, 2005Dear Shri Moorthy,

    It gives me immense pleasure to convey my heartiest congratulations to you and your team associated with Panipat Refinery Expansion Project for the safe and successful commissioning of the largest capacity Hydrogen Plant in the country on 18th November, 2005. This is a major landmark achieved in the ongoing commissioning activities of PREP.

    As you are aware, this is the largest capacity Hydrogen Unit in the country and also the largest Haldor-Topsoe (HTAS) licensed Plant in the world. The construction / commissioning of such mega Hydrogen Plant has been the most challenging task in the total PREP. Successful accomplishment of this task is definitely going to boost up the pace of the construction / commissioning activities of other units / facilities in PREP and PX-PTA.

    You can be proud of the fact that the first chain of this mega plant could be commissioned and stabilized in the first attempt itself. I know that this could be made possible due to your excellent leadership and also with the hard work, dedication and teamwork by all the concerned personnel of L&T, IOCL and other agencies.

    With regards,C. ManoharanGeneral Manager(T)Panipat Refinery

  • October 2003 and were completed on granite, tiles and Burma teak for doors, is PTA PlantNovember 16, 2005. Construction of such a bound to become a benchmark for process Plant was not an easy task considering the plants in the future. One has to see it to The PTA Plant of 5,53,000 MTPA magnitude as well as the intricacies involved. believe it for, it is a different world by itself. capacity constructed by L&T for IOCL at Moreover, the harsh climatic condition of Panipat is Asia's biggest. It is the largest Panipat also proved a hurdle to speedy Major Parameters of PTA Plant turnkey project awarded in India and also the completion of the project. Summer biggest EPC contract for L&T so far, valued at temperature was as high as 49 C and winter Rs.1,242 crore. This project marked IOCL's ! EPC Value of PTA drops were as low as 10 C. Mobilisation of entry into petrochemical sector and is also Package (EPCC III) : 1242 Crore3,800 workmen and extended working L&T's largest EPC contract to date. The

    ! Constructionhours in such weather itself is a great success of the project is due to the synergy Value : 200 Croreachievement. This was achieved with pro-and seamless working brought in by E&C and ! RC Driven Cast in active support from site management such as ECC Divisions of L&T. Mr. S.N. Roy, Project

    Situ Piles : 3400 nos.free warm clothing to workmen in winter, Manager, E&C, echoes the sentiment and ! Excavation -A : 60000 Cumrest sheds during summer, free refreshments says that for the first time in projects involving

    during peak period. PTA Plant comprised ! Earth Filling : 140000 CumE&C and ECC, it was jointly decided to have construction of Plant buildings, Process Plant ! Concreting (Exclthe Resident Construction Manager (RCM) and Warehouse. Every building has some from ECC instead of E&C as in the past, and Piling & Pavement) : 42000 Cumunique components not seen in other the change has yielded good results. He ! Pavement : 67000 Cumconventional process plants.believes this arrangement should continue in ! Fire Proofing : 12000 Sqm

    future as well. This coming together had also ! Formwork : 130000 Sqm

    helped in bringing down the staff Electrical Control Room! Reinforcement : 7150 t

    requirement by 100. There was no ! Bitumastic Flooring : 45000 Sqm

    supervision over supervision and the two Though buildings such as control room, ! Pre-coated Sheets : 55000 SqmDivisions worked hand in hand as one substation, D.G. room and operators cabin ! Structural unified L&T team so much so that Mr. P.R. are common in any process plant, at IOCL-

    Fabrication, ErectionDas, Executive Director (Projects), IOCL, had Panipat they had special requirements. The & Painting : 9500 tthis to say to Mr. A.M. Naik: The PTA team is control room had blast-proof concrete outer

    a totally dedicated and seamless team. ! Under Ground Piping : 112000 IMwalls while the console room was made ! Above Ground Piping : 500000 IMsoundproof using lightweight concrete

    blocks and the doors were made of fireproof Though the contractual commencement ! Non-destructive steel. The control room, with its world-class date was March 31, 2005, site mobilisation Testing : 70000 IDarchitectural finishes and electrical fixtures & was started in February 2003. Actual ! Equipment Erection : 4650 tfittings and clad with superior quality marble, construction activities stabilised from

    State-of- the-art control room for IOCLs PTA Plant at Panipat

    14

  • Compliments from IOCL

    I am happy to see a very high level of motivation in the entire PTA team. Considering our maiden venture, we have done very well in project execution. I look forward to a very successful commissioning of the plant."

    - Mr. S. Behuria. Chairman

    "Visiting the control room of PTA Plant and the plant itself today was a fantastic experience, the quality of construction as seen today is of highest order. The three teams of L&T, IOCL & EIL have worked shoulder to shoulder for the last over two years to bring the plant to a stage of near readiness for commissioning without a single LTA. This is a marvelous achievement. I wish the three teams all the best in remaining activities of construction and of course in smooth commissioning of the plant." - Mr Jaspal Singh, Director (Refineries)

    Process Plant The heavy-duty pavements in the plant DEGUSSA regarded worldwide as the ideal

    above the process area pavement (31,000 anti-corrosive lining material. PTA is a product derived from paraxylene Sqm) were made of steel fibre reinforced passing through various oxidation processes. concrete with a 50 mm thick carpet to make As the spillages and effluents arising out of Asia's Largest Warehouse the floor and pavement abrasion-resistant. It the processes are highly corrosive in nature, was a totally mechanised operation - special technologies and materials were used The PTA Warehouse at IOCL-Panipat is cleaning the broomed surface, application of to make the floors and drains highly anti- Asia's largest warehouse with an area of bonding agent, immediate spreading of corrosive. All chemical trenches and effluent 44,363 Sqm (109 m x 407 m) and has four concrete by a spreader and final trowelling tanks were constructed with stainless steel rows of 22.43 m high concrete columns and involving time-bound activities which, if (SS304) lining. This was highly demanding a structural steel roof with precoated delayed, could have impacted the carpet work since even a minor defect would mean galvolume sheets. The structural steel roof quality. In line with the recommendation of dismantling the trench and doing the work all weighs 2,750 t. To withstand the corrosive the process licenser DuPont, specific areas over again. However, the task was nature of PTA, the floor was made of 250 mm were covered with acid resistant tiles and accomplished by ECC's highly skilled thick VDF (Vacuum Dewatering Floor) UCRETE, a patented product of MBT / workmen and well-motivated supervisors. concrete over 200 mm thick sand layer used

    as sub-base floor. VDF offers the advantage of minimal moisture content and lends very high compressive strength to concrete. Over the VDF, 30 mm thick Bitumastic flooring (Prodorphalt-W) was applied to make it acid-and corrosion-resistant. The Bitumastic flooring of 44,500 Sqm was done in a record time of five months, deploying five boilers for bitumen cake melting.

    After completion of civil & structural works, the fire fighting system design was changed to accommodate large quantities of spray nozzles including header lines. All purlins were strengthened at erected condition and support structures were provided on civil columns through anchor fasteners. It was a unique experience to accommodate 176 nos. of 20 mm dia anchor fasteners in an area of 1.5 Sqm per column without touching rebar. High precision rebar detectors were used to detect the rebar and a specilalist agency from Chennai was requisitioned to fix the anchor fasteners.

    Electrical Panels installed in the control room

    Interior view of the warehouse at PTA plant

    15

  • Erection of Process Air Compressor (PAC)

    It was a pre-requisite from the Manufacturer M/s. Mann Turbo of Germany that the Assembled Compressor be erected in roofed shed at foundation level at 6 m. Total Weight of PAC being 212 t with a volume of 742 Cum (23.31 m Long x 5.96 m Wide x 5.34 m High), it was a tough proposition to lift and slide inside the shed. But construction Engineers were made to achieve such difficult propositions.

    After careful study of all arrangement, Sliding Strand Jack System was as found the only suitable arrangement for such a job. A

    The contract for theCoke Drum System Coke Drum System core team of Heavy lift experts from site was Package (CDSP), considered to be the heart of deputed to execute the erection of PAC. Basic DCU, was awarded to ECC on September 18, The Delayed Coker Unit (DCU) at design parameters were obtained from 2003 at Rs.22.41 crore (later revised to Rs. Panipat Refinery is designed to process 2.4 Heavy lift wing at ECC-HQ, Chennai. And all 31.15 crore). Coke drum systems of similar million tonnes per annum of Vacuum preparatory arrangements were commenced capacity have so far been completed in thirty-Res idue (VR) and o ther res idua l at site.three months. However, true to its reputation products/materials from various units of the ECC completed the job in the month of June Refinery.Supporting structures of strand jack 2005 (i.e. in twenty-two months), pending system: incorporation of free issue materials from the The products are Green Petroleum Coke, client.Coker Fuel Oil (produced optionally), Heavy Supporting structures are made of 191 t of

    and Light Gas Oils, Light and Heavy built up beams and ISMB 600 and 65 t of pipe A major highlight in this package is the Naphtha, mixed C3-C4 LPG and Fuel Gas, trestles. Height of supporting structures was

    coke drum foundation structure with 2.4 m etc. It works normally on a 48-hour cycle i.e. 17 m load test on erected structure was thick foundation slab, which is the tallest 24 hours of on-line Coke Drum filling and 24 carried prior to lifting.

    hours of off-line Decoking.

    Night view of DHDT Unit at IOCL Panipat

    Eerection Package Wt. (mt) Installation Size sequence elevation* l (m) x b (m) x w (m)

    1 Coolers with base frame -1 58.6 100.3 13.48x5.96x3.2

    2 Base frame - 2 14 100.3 9.83x5.96x13 Turbine skid 87.1 105.016 13.29x6x4.734 Base frame 3 for

    generator 37.6 105.016 11.97x6x5.345 Compressor skid 122.5 105.016 8.11x5.21x5.316 Generator 48.8 105.016 ~4x~4x~4.757 Expander & gear 33.05 105.016 ~5.5X~4X~4.75

    Basic methodology / sequence of erection

    With ref to ground lvl.*

    16

  • foundation in India at a height of 27.353 m from ground level. A total of 1,419 tonnes of reinforcement went into the work. Using three concrete pumps, a massive quantity of 1,360 Cum of M25 concrete was poured into the dense reinforcement (weighing 315 t) of 4 layers of 36 mm Torsteel each at top and bottom, with 16 mm Torsteel as stirrups at a height of 27 m. 5,000 tonnes of heavy duty towers and L&T formwork were used extensively for the top foundation slab alone. This type of mass concrete foundation slab was carried out for the first time in India. The timely completion of the structure was possible with the tower crane, which was used to lift heavy-duty towers of 24 m length. The entire load of reinforcement and wet concrete of the foundation slab was transferred to the H-Beam placed over ISMC 125, which in turn was transferred to the HD Tower.

    For the coke drum structures, weighing The CDSP project has another first to its of working at heights, increased the quality of 2,800 tonnes, the modular concept was credit - the highest capacity bridge crane ever workmanship and saved considerable time. adopted for the first time in India. Universal used in India, with a self weight of 250 The site used CO2 welding machine and columns and beams were used to raise the tonnes, a travel speed of 95 metres per achieved a productivity of 24 Kg per day structures from the ground level to a height of minute and a loading capacity of 44 tons, was compared to 6 Kg per day with SMAW.103 m around four coke drums over the 2.4 erected at this site. The crane has a span of 23 m thick slab at 27 m level. The Coke Drum m excluding a cantilever portion of 10 m Total piping scope was 50,000 inch-dia Structures consisted of eight modules of 2 span with level difference of 8 m between out of which 23,500 inch-dia piping was of nos each weighing 160 t, 190 t, 80 t and 84 t both ends supporting carriage. high alloy steel (P5 and P9). High alloy steel respectively. All eight modules were pipe welding needs preheating, post-heating, fabricated and assembled at ground level and post-weld heat treatment and 100% The heavy lift operation was done with were lifted by Link Belt FMC crane of 750 t radiography. The work was completed with the help of FMC Link Belt Crane having a capacity (On Ringer). The modules were a high degree of accuracy and quality, lifting capacity of 750 t mounted on ringer placed one over the other to a height of 103 requiring only 1.3% re-work. The critical foundation. It was for the first time in India m from ground level within 15 days. The part of the work was vertical pipe (diameter that we used full boom length of the FMC. All critical part of the structure was the slope of ranging from 0.5 to 42 dia) erections at a modules and four Coke Drums were lifted in 5.24 degrees, which gradually tapers from 64 height of 77 m from ground level. The a single operation. One Fractionator m to 103 m towards top. The modular highest hydro test pressure in the project was Column, an elevator structure of 67 m (in 2 concept helped in overcoming the criticality 444 Kg/Sqcm. parts) and the Bridge Crane were also lifted at

    one go. Altogether the FMC crane was used for lifting and erection of 2,822 t of structures/equipment.

    The site won the Best Safety Performance Award for the year 2005 from IOCL after clocking 4 million safe manhours with 'zero' Accident. It also received Certificate of Merit for achieving 2 million Lost Time Injury Free Manhours, Certificate of Merit for achieving 3 million Lost Time Injury Free Manhours and Certificate of Merit for Zero Accident rate.

    Automated Heading and Unheading system is a fully automatic hydraulic system for opening and closing of Coke Drum. This is an imported system and has been installed for the first time in India. The hydraulic system consists of pneumatic SS tubes varying from 0.5 to 1.5 (total 8 Km) connected with double compressed fitting.

    Coke Drum System Package Unit

    A view of the PTA Process plant

    17

  • Inside view of the Filter house of 120 MLD RWTP at IOCL Panipat

    Mr. V. Ravichandran, Project In-Charge construction, installation, testing, pre- commissioning of phase-I of the plant as per for CDSP from E&C Division, says that the commissioning and commissioning of client's requirement.modular concept we used for fabrication of RWTP. This is the first 120 MLD raw water structural items in this package greatly treatment plant ever executed by ECC. The helped in timely completion of the project. work was awarded on September 15, 2003 This would pave the way for out securing and the plant was commissioned on May 5, similar packages in IOCLs future projects at 2005 while the mechanical completion was ! Excavation : 115080 Cumother locations. For design/engineering of achieved on September 30, 2005. ! RCC & PCC : 27480 Cumstructural items L&T-Chiyoda, EDRC and an ! Steel : 1750 texternal agency were engaged. IOCL awarded the site the best safety ! Shuttering : 80000 Sqm

    performance trophy for achieving 4 million ! Waterproofing : 6015 SqmMr. Anil Kumar Bansal (AKB), lost time, injury-free manhours. ! Piping Fabrication : 58011 ID

    Construction Manager, says that almost 70% ! Piping erection : 38075 IMof the work involved working at heights, The raw water treatment plant treats ! Pumps : 60 nos.maximum being 103 m, and this required water upto 5,000 Cum/hr capacity and has ! Electrical cable trays : 4000 Rmeven greater attention to safety aspects. special equipments like sludge thickener and ! Electrical cabling : 29950 RmHowever, by fabricating and assembling the belt filter press. One of the special features of ! Instrumentationentire coke drum structures in modular form, the plant is that it has zero discharge of waste cabling : 19875Rmthe quantum of work at heights was kept to liquid. All the sludge from clarified the minium and construction cost brought water/dirty back wash water is extracted by down by almost 30%. The site achieved 3 means of belt filter press and dry sludge cakes Mr. S.K. Banerjee, Construction million lost time injury free manhours and are transported to a designated dumping Manager, says that one major problem faced won Best Safety Performance Award for the place. The water thus re-cycled is used in during execution was the complete year 2005 from IOCL. Thanks to good various refinery processes, thereby submergence of filter water sump and pump construction planning, 1080 tonnes of conserving water. house area during rainy season. However, fabricated steel structures in modular form additional resources equipment, men and were erected in a matter of 15 days. AKB During the execution of the project, ECC materials were immediately deployed to adds that in terms of quality as well, the faced several hurdles, such as - the complete successfully overcome the situation and we clients were highly satisfied with our work, submergence of filter water sump and pump could hand over the pump house for Phase-I particularly in piping joints where welding house area during rainy season, because the commissioning of the plant as required by repair percentage was as low as 1.3%. entire area was excavated 10 m deep from the client.

    ground level for the foundation and piling work (72 nos. driven cast in situ piles). The clients were very happy with the quality 120 MLD Raw Water Treatment PlantHowever, ECC surmounted this by of our work as well as water supplied from the immediately deploying additional resources plant. Mr. Banerjee adds that with the The package inc luded pro jec t and managing the situation efficiently. Thus, successful execution of this project, ECC will managemen t , de s i gn /eng inee r ing , ECC completed the project and handed over be well placed to secure similar project procurement, manufacture, supply, t h e p u m p h o u s e f o r i m m e d i a t e orders in future. transportation, storage, fabrication,

    Major quantities

    18

  • Welding in progress

    Trenching and laying of pipes

    The Anand-Rajkot Pipeline Project123 km long 24 dia line for transmission of Natural Gas

    Gujarat State Petronet Ltd. (GSPL) is currently implementing a high-pressure pipeline project covering various industrial belts and cities of Gujarat. Considering the importance of such a pipeline network and realizing Gujarat's aim of emerging as the 'Petro Capital' of the Country, the State Government has accorded 'Infrastructure Project' status to GSPL's project.

    In a bid to establish a systematic, integrated and seamless infrastructure for gas transmission from supply points to various demand centers in the state, GSPL has been laying underground gas transmission network across Gujarat. At present around 742 Km of gas pipeline is under construction. The EPC contract for the 123 Km long 24 Natural Gas Pipeline from Anand (Gana) to Chuda, awarded to L&T, is the first section (Section A)of the Anand-Rajkot pipeline laying programme of GSPL.

    Project overview

    The project envisages setting up of a ! The Pipeline will transport natural gas launching facilities at Gana, six nos. of high-pressure natural gas pipeline system.

    from Anand to Rajkot for domestic, intermediate sectionalized valve stations and The pipeline system broadly consists of the automobile, commercial and industrial an intermediate pigging station at Chuda.following:consumers.

    ! ARPL is originating from the existing Peep holeL&T's scope as an EPC contractor in this Sectionalizing Valve Station No. 2 of

    project includes design and detailed Baroda-Ahmedabad-Kalol Pipeline The Anand Rajkot Gas Pipeline Project Engineering, supply and laying of 123 Km (BAKPL) situated at Gana Village of Section A (ARPL-A) was awarded on 7th July pipeline, construction and installation of Anand District in Gujarat. 2005 with a tight completion target of 13

    months including commissioning and one-month operational acceptance. This being a full-fledged high-pressure pipeline, all parameters right from procurement of all specialized materials and equipment to delivery, execution including pipeline laying and HDD at Sabarmati river, testing and commissioning of the pipeline needed to be meticulously planned and executed. With excellent coordination between site management, HCP BU at HQ, North Zonal and Ahmedabad Regional Office, the project has seen smooth and steady progress till date, which has earned profound appreciation of the client.

    This project had set tough challenges for the Site Management which rose to the occasion by evolving effective strategies and implementing the same. Following are some of the strategies the site adopted. This not only yielded the desired result but also resulted in achieving the targets as per schedule.

    19

  • ! The th i rd and most impor tant line team and pipe delivery coordinator. This Strategies adoptedachievement was welder selection and helped everyone concerned to clearly their qualification at site. The sub- understand their role in the activity and ! The contract required approved work contractors were called and instructed to facilitated smooth delivery of pipes at site. procedures for almost all activities. mobilize welders immediately. On The whole exercise was so well-planned that Hence the first thing the site did was to arrival of welders, they were interviewed the actual mainline welding started the very draw up procedures and submit them to and screened. The welder qualification next morning on receipt of the first pipe with client for approval. This helped in activity followed immediately and the zero loss of time.obtaining approved procedures much site was ready with welders before the before the actual start of job, which gave mainline pipes arrived.the frontline engineers enough time to Effective resource management

    study and understand the procedures. ! Similarly it was ensured that welding This in turn guaranteed execution with A project of this magnitude with an asking

    machines and other equipment were absolute conformity with contract rate of 120 joints per day would generally received, inspected and made ready specifications and saved time and cost of require mobilisation of ample resources. before the mainline pipes were received rework and repairs. Keeping in view the limited resources at site. All efforts were made for early allocated to this project, a detailed and import of electrodes. Electrode ! The approved procedures required effective resource allocation was worked out qualification tests were also successfully 'procedure qualification'. This meant the at site. Low-priced and easily available completed before the mainline pipes sequence of activities for pre- and post- alternatives (12t Hydras) to unavailable arrived.welding are performed on actual resources (Pipelayers / Tata320) were

    mainline pipes and tested for viability of mobilised at site for stringing activities. Unloading and stringing of pipesthe procedure. However, the pipes were Similarly resources in other activities were

    to reach site three months later. So, allocated in such a manner that the waiting till then meant a delay of at least It was decided that pipes be directly availability of equipment would help and one week in start of production because unloaded at site and stringing be done complement the smooth progress of work. actual job could be started only after simultaneously during unloading. Keeping in This resulted in achieving 120 to 150 welded Procedure Qualification. view the hundreds of trailer loads of pipes to joints per day.

    be received, this task needed close and To overcome this situation, the clients meticuolous coordination between pipe Quality assurancewere persuaded to arrange for a small manufacturer and the frontline team. To quantity of pipes immediately, on which ensure accurate delivery at desired locations, The site management made it a policy to we could carry out procedure it was decided to depute one of our senior keep weld joint repair percentage below 2%. qualification and return them at a later personnel at the manufacturer's works to To achieve this target, a strategy was stage. Thus a lot of time was saved and coordinate with site and the transporter, to established to analyse and find out the root procedure qualification obtained much monitor progress and expedite third party causes of repair. Once the root cause was before arrival of mainline pipes. inspection. As part of this effort, a meeting found out, the frontline engineers, sub-

    was held between the manufacturer, the front contractor supervisors and welders were given feedback and advised of the preventive action to be taken to stop further recurrence of repair. This was quite educative for the front line team and helped them achieve a repair percentage of as low as 1.2%, which is one of the most commendable achievements of the project.

    ECC's success in the project proves that a strategy can work only when it is worked out with a vision at the back of everyone's mind. The site team worked with diligence in turning the strategies into concrete results. The relentless efforts of the whole team with firm commitment to achieve targets both quantitatively and qualitatively have been commendable.

    V. ThirumalaisamyProject Manager

    Dev Nandan DasPlanning Engineer

    Pipe laying work in progress

    20

  • Horizontal directional drilling for one of the major crossings

    Pipe Lowering under progress

    Mora Vapi Pipeline

    Gujarat State Petronet Limited (GSPL) is which involved installation of 30 carrier one of the emerging players in the pipe inside 36 casing pipe.transportation of gas through pipelines connecting various supply and demand Present statuscenters in Gujarat and is playing a key role in the development of Gujarat. GSPL aims to At the outset of the eleventh month of the complete approximately 600km pipeline project, 70% of the work has been across the state of Gujarat as part of Phase 1 completed. The major works competed are-of the Gas Grid Project as a service provider (link between supplier and user) to quench ! 100 Km of mainline welding.the thirst of the Industries in this region ! 65 Km of Lowering.(Diversified area coverage). The 128 Km ! Completion of all station civil works.Mora Vapi Pipeline Project is currently in ! Completion of 22 nos. of cased installation stage as part of Phase I. crossing.

    ! Completion of 5 nos. of HDDProject features

    Constraints facedMora Vapi Pipeline project is 30 OD,

    128 km long pipeline project which runs ! Due to heavy torrential rains during the from Mora to Vapi and is considered the initial phase of the project, the pipeline most prestigious project in view of the installation works were affected badly. industrial development and the presence of The whole area was flooded with water mega industries along its course. The project and the work was at a standstill for caters to the needs of major industrial areas around 3 months. at Sachin GIDC, Navsari, Vapi, Valsad and

    highly committed team and available Silvassa. ! HDD works, the most important activity resources, ECC is confident of completingof the project, were getting delayed due

    The project, valued at Rs.351.9 crore to unforeseen problems. was awarded to ECC on an EPC basis with a

    the project in time in tune with its reputation. project duration of 15 months. This involved Challengesretain the glory created in the past projects. design, procurement, installation, testing

    and commissioning of pipeline including As the completion date is drawing to a Mukesh Kumarconstruction of 2 receiving stations, close, ECC has the daunting task of catching Asst. Manager, HCP - BUlaunching station, intermediate pigging with up the progress. With the efforts of a Ahmedabad Regional Office

    station and 5 sectionalized stations and one tap off station.

    Project highlights

    ! This is the first higher dia (30 OD) EPC Gas pipeline project in the History of L&T and the entire pipeline route passes through cultivated land wherein main crops are mango, sapota, sugarcane etc.

    ! The scope of work includes design, procurement & supply, fabrication, installation, inspection, testing, pre-commissioning, commissioning and performance testing along with associated works.

    ! Horizontal Directional Drilling (HDD) methodology was used for the 12 major river crossings. HDD works were done indigenously for the first time in the pipeline history by 250 t rig specially procured for this project.

    ! 33 nos. of cased crossings across canals, roads, railways were done by boring

    21

  • Aerial view of the Songo Songo Gas Pipeline, Tanzania

    Songo Songo Gas Pipeline, Tanzania

    The United Republic of Tanzania, Development Corporation (TPDC) and Pan Scope of Worklocated in East Africa, is bounded on the African Energy. The World Bank and north by Kenya and Uganda, on the east by European Investment Bank (EIB) are the Work under LOT-1 comprised detailed the Indian Ocean, on the south by lenders to the project through the design engineering, procurement, supply, Mozambique, Malawi and Zambia and on Government of Tanzania. The Total Project transportation, installation, testing, pre-the west by the Democratic Republic of cost was US$ 350 Million. commissioning and commissioning of:- Congo, Burundi and Rwanda.

    Songas developed Songo Songo gas field ! One 70 MSCFD (million standard cubic The country's territory includes the in Kilwa District, Lindi Region and invited feet per day) processing plant (2 trains,

    islands of Zanzibar and Pemba and other bids for constructing the gas processing each of 35 MSCFD)Islands including the Songo Songo Island (25 facilities on Songo Songo island and the km off the country's southern coast) in the pipeline network to transport natural gas to ! Three offshore wellhead structuresIndian Ocean. Dar es Salaam where it will be used as the

    principal fuel supply for five gas turbine ! 5 Km of 168.3 mm flowlines from the When natural gas was discovered in electricity generators. three offshore gas wells to the gas

    Songo Songo Island in 1974 the Government processing facility in Songo Songo Islandof Tanzania decided to implement a Gas-to- The pipeline will then continue to supply Electricity Project for producing power to power to the Wazo Hill Cement Plant. The ! 1.3 Km of 114.3 mm flowlines from the feed the existing 110 MW gas turbine power project will produce reliable electricity for the two onshore gas wells to the gas plant. The project implementation was national grid and also bring gas to other processing facility on Songo Songo Islandentrusted to Songas Limited, Tanzania, a industrial users in Dar es Salaam. local joint venture company formed by ! 25 Km of 12 marine pipeline from Gas Globeleq (majority stockholder), Tanzania The project was divided into 6 Lots and Processing facility on Song Songo island Electr ic Supply Company Limited L&T were the successful bidders for two lots to the landfall point (LFP) near Somanga ( T A N E S O ) , T a n z a n i a P e t r o l e u m Lot 1 and Lot 2. Funga in Lindi Region

    22

  • LOT-2 involved of final engineering, detailed design, procurement supply, transportation, installation, testing, pre-commissioning and commissioning of:-

    ! 204 Km 16 dia. Mainline from LFP tie-in to Ubungo Power Plant in Dar-es-Salaam including 15 Km flood plain crossing at the Rufiji River

    ! 15.7 Km 8 dia. Lateral Spurline from Ubungo to Wazo Hill Cement Plant

    ! Metering facilities and Pressure Reduction Station (PRS) at the Ubungo Power Station including supply line and turbine pressure control equipment

    ! PRS and metering facilities at the Wazo Hill Cement Plan

    ! On-Wayleave Restoration and Erosion Control works

    M/s. Granherne of UK carried out the ! 2.45 Km - 12 diameter mainline from ! 440 mtrs. of pipeline section across Rufiji basic engineering for Songas Limited

    LFP to Somanga river was laid by Horizontal Directional Drilling (HDD) Method

    The onshore route selected by Songas ! 15.7 Km - 8 diameter Spurline to Twiga Limited had minimized the impact on the

    (Wazo) Cement Plant at Wazo Hill ! The terrain in upstream of Ubungo physical and social environment of the Station and the spur line was highly coastal area that it passed through.undulated. More than 1500 cold bends ! One intermediate Pigging Station at were installed in this 25 Km sectionSomanga Funga

    Salient Features

    ! 6 major crossings were completed, of ! 66 Km of Flood Plain designed for Anti-! 204 Km - 16 diameter main pipeline which two were railway crossings and bouyancy measures like 13000 saddle

    from IP Station at Somanga to Ubungo four were road crossings which were weights and 15 Km of coated concrete Power Plant in Dar-es-Salaam executed by Horizontal Thrust Boring pipes in the Rufiji Flood Plain

    Method

    ! 2 crossings, each 100 mtr wide, at trunk roads with heavy traffic, were executed by HDD method

    ! 9 Main Line Block Valve stations along the pipeline way leave were built

    ! Girth Weld Joints were coated with Heat Shrink Sleeves (HDD portion was done by DIRAX Sleeves)

    ! Laying of 223 Km of FOC (Fibre Optic Cable) along with the pipeline for SCADA

    ! Cathodic protection of pipeline: both temporary (during execution) and permanent (for 20 years)

    ! Pressure Reducing Station at Ubungo and Wazo Cement plants

    Pipe line passing through steep area at channel 158

    Holiday check being done before lowering of pipeline

    23

  • ! Caliper Pigging of 15.7 Km of 8, 2.45 ! A s a c o s t s a v i n g m e t h o d , ! The project was exempted from various Km of 12 and 203 Km of 16 Lines. documents were exchanged with clients, duties and VAT. Proper planning and

    HQ and associates over electronic documentation in the initial stages of media, viz. e-mail, etc. procurement minimized the difficulties

    ! Swabbing, Drying, Pre-commissioning & in clearing the consignments. This also Commissioning

    ! In Tanzania, convincing the authorities to helped in our taking full advantage of issue work permits for the expatriates was exemptions of duties and VAT. VAT paid

    ! Intelligent Pigging 15.7 Km of 8, 27.45 a major problem. Matter was taken up at for small items, tools & tackles, etc. Km of 12 (Including Offshore line) and all levels in the government including the purchased locally during execution was 203 Km of 16 Line Labour department and immigration subsequently refunded by TRA.

    through Tanzania Investment Center. Songo Songo Gas-to-Electricity project ! Kiswahili, the local language, has a few Experiences was one of the biggest projects words similar to Hindi/ Urdu. Picking completed recently in Tanzania and these words and with the help of local

    ! This was the first overseas cross-country hence this was seen as a dream project to drivers who knew a little bit of English, pipeline project executed by ECC on overcome the unemployment problems our staff could establish communication E n g i n e e r i n g , P r o c u r e m e n t & to a large extent. As specialist workmen, and manage the day-to-day works. Construction (EPC) basis. This is also the downhill welders, pipeline equipment Training was also given to local workmen first project for ECC in Africa. As the operators, radiographers etc. were not in spoken English as well as Kiswahili pro jec t was in a to ta l ly new locally available, we could employ the English and Kiswahili.environment, it posed challenges right locals in the semi-skilled and unskilled from the conceptual planning stage to categories only. However, this point ! Advance Planning and identification of project management and execution. needed to be substantiated to the plant and machinery and staff with cross-

    Government authorities with the country pipeline experience in India, lukewarm response received to coupled with timely completion of ! The project schedule prepared on recruitment ads in the local media. formalities with Reserve Bank of India primavera helped in reading out the Finally, 400 expatriate workmen and 40 (RBI) and other authorities augured well critical path from time to time and taking staff were mobilized for this project. for the project. corrective actions as and when required.

    Golden tie-in welding in progress

    24

  • ! The terrain was quite difficult and the The fo l lowing ma jo r i t em o f work involved advance planning for construction equipments were mobilized fabrication of cold bends to avoid from India for the execution of this interruption of work during mainline prestigious project.welding.

    ! Pipe Layers / Side Booms - 18 nos.! The work in flood plain of 50 Km stretch

    ! Excavators - 16 nos. was taken up on top priority and was ! Motor Grader - 2 nos. completed before the onset of monsoon

    during November 2003. A mini crew ! Dozer - 5 nos.was formed to accomplish the task on

    ! Diesel Weldingtime.

    Generators - 25 nos.! Compressor 1100 Cfm - 1 no. ! There were frequent thefts, threats and ! Compressor 600 Cfm - 1 no. dacoities during the execution of this

    project on the pipeline route and also in ! Bending Machine - 3 nos.the camp. The staff and workmen

    ! Boring Machine - 1 no.showed courage in facing the situation

    ! Water Filling Pump - 2 nos. and kept up their morale.! Hydro test Pump - 2 nos.

    ! Laying of Pipeline across the river Rufiji was crit ical for the successful

    ! Clearing of right-of-way involved cutting completion of the project. This activity down some trees through the dense suffered a setback several times but went forests. Local workmen and heavy th rough succes s fu l l y w i th the construction equipment such as ! 1.5 Km- Intertidal Zone from Land Fall mobilization of a suitable rig from France. excavator, dozers, etc. were deployed Point was filled up by the scooping The work was carried out by HDI, a for this work which was carried out in method.specialist agency from France, and was line with the Environmental Social appreciated by our client.Management Plan.

    ! As an erosion control measure, slope breakers were provided during lowering and backfilling.

    ! The construction work was completed in time in spite of all the difficulties encountered. Swabbing, drying and-commissioning were done in a phased manner. The mainline, spur line and pressure reducing station at Ubungo Power Plant as well as Wazo Hill Cement plant were commissioned in July 2004. Commercial production commenced from July 21, 2004.

    ! Songas commended the safety standards maintained by L&T to achieve one million safe man-hours and issued a ce r t i f i c a t e acknowledg ing t he performance.

    ! Financially too the project has done well. The final contract value was US$ 41,269,789.

    ! Finally, it is worth mentioning that M/s Songas Limited, owners of the project, were highly appreciative of L&T's performance in making their dream project a reality.

    S.N EachampatiProject Manager

    Pradumna TripathyPlanning Engineer

    Pipe floating in bentonite filled trench

    Saddle weight installed for anti bouyancy measure

    25

  • Cryogenic Storage Tanks

    L&T has acquired a leadership position in India for turnkey construction of cryogenic storage tanks and terminals for a variety of products such as, ethylene, propylene, LNG and LPG. Cryogenics deals with very low temperature operations, in the region of -40 C.

    Creating History

    L&T has come a long way since its entry into this new technology arena, way back in 1989 with an award of the first order from Reliance Industries Limited for turnkey execution of cryogenic ethylene storage tanks and terminal facilities at its Hazira Complex in Gujarat. The project involved construction of cryogenic storage tanks for storage of liquid ethylene at -104 C under atmospheric pressure in 2 x 10000 tonne capacity double wall tanks along with unloading facilities, boil-off gas refrigeration system and send out facility. This project was executed for Reliance's Vinyl Chloride-Monomer (VCM) plant on the banks of river

    The jetty was designed for unloading operated through hydraulic power system Tapi in Hazira. L&T's scope of work included ethylene from ocean-going vessels at a flow and electric panel. PUF insulated cross-detailed engineering, procurement, rate of 600 Cum/hr. The marine unloading country pipelines were used to transport fabrication and erection at site, civil works, system comprised three unloading arms ethylene from the jetty to tanks.testing and commissioning.

    Reliance Petrochemical Complex at Hazira

    A propylene storage tank at Hazira

    26

  • L&T completed this project in 1995. It Subsequently, it executed a maiden Building A Track Recordinvolved cryogenic ethylene receiving, contract for cryogenic propylene storage unloading, storage and truck loading tank of 10000 tonnes capacity from Reliance Following the successful completion of facilities. Indus t r ies L imi ted for i t s Hazi ra the Ethylene Terminal Facility at Hazira, L&T

    petrochemical complex. The storage secured a contract from Finolex Industries temperature in case of propylene was It also included design and construction Limited for setting up cryogenic ethylene -47.7C. The project was successfully of import jetty in the open sea, unloading storage tanks and receiving terminal facility completed in 1996.facility for ethylene from ships into the cross at Ratnagiri in Maharashtra. The project

    country pipelines which carry it to the two involved 2 x 5700 tonne capacity double ethylene storage tanks, in the first phase for The complete Process engineering wall storage tanks. The jetty was designed for the requirement for Finolex's PVC Complex activities comprising conceptualization, unloading liquid ethylene from ocean going at Ratnagiri in Maharashtra. process simulation, process flow diagrams tankers at the flow rate of 280 t/hr.

    (PFDs), process control philosophy, P&l diagrams, thermal design and equipment sizing were carried out by L&T's Chemical Plant team of engineers.

    This is a landmark project for L&T in cryogenic storage systems and with the successful completion of various projects for cryogenic storage and handling, L&T is now fully geared up to take up projects on Lumpsum Turnkey (LSTK) basis in the areas of ethylene, propylene, LPG and LNG receiving terminals and storage tanks.

    L&T is also proud of successful completion of Indias first LNG Project at Dahej with execution of equipment and piping works at Jetty and terminal area for Toyo Engineering India Ltd.

    Cryogenic ethylene storage tanks built by ECC for Reliance Industries at Hazira

    170 m long Open sea jetty for Finolex Pipes Limited, Ratnagiri

    27

  • Panoramic view of underground cavern under construction for SALPG Visakhapatnam

    ECC, the Construction Division of L&T is Water Curtain Gallery 15m above the cavern added support of a water curtain gallery.executing an engineering marvel, deep will maintain the hydrostatic pressure to down the earth's crust, under a 13-acre ensure leak-proof LPG containment within Construction of underground LPG greenfield site at the foot of a hillock, named the cavern. caverns calls for an avant-garde technology Dolphin's Nose, that juts out into the sea at that is gaining worldwide currency as man Vizag port. Valued at Rs.208 crore ECC seeks to capture and subjugate more territory Above Ground Packagebagged this order in the teeth of stiff for use under land and undersea. The competition from major domestic and successful completion of this rock cavern will Under this package ECC will construct international players. patently propel L&T-ECC into the vanguard of all process facilities for unloading bulk

    a new business line in India, considering that shipments of propane and butane, blending South Asia LPG (SALPG) Company a in the near future the creation of more caverns them into LPG prior to transfer into the

    50:50 joint venture between Hindustan are envisaged for storage of LPG and crude cavern through the Access Shaft and Petroleum Corporation Ltd. (HPCL) and oil, the production of which is on the rise. The evacuating it whenever required from the Total Gas and Power India (TGPI), subsidiary project is thus the cynosure of all eyes in the cavern through the Operating Shaft for of French oil major Total are the clients for industry.commercial distribution/export.the project. As a special purpose vehicle .SALPG will develop, own and operate this Sunken bulk storage of LPG offers many India's firstfacility. M/s Geostock of France, a world advantages such as safety from natural leader in underground cavern design, is calamities and various forms of sabotage The mined bedrock cavern will be providing the geological and design including bombings during war not to India's first underground storage facility and consultancy for the project. The Technical mention the hazards of leakage of the the world's deepest LPG cavern. The design Advisor to the project is M/s IDEA-Chennai. inflammable gas besides tremendous spatial for sub-surface gas storage relies on the

    economy when compared to conventional principle of water pressure in surrounding ECC is executing this EPC contract, in pressurised spheres and refrigerated tanks rock being more than the 'escape' pressure

    two packages as follows: used for surface storage of the gas.of the stored gas.Though there are a few such scattered caverns, they cache either butane

    Underground Package Vizag was chosen as the location for the or propane gas, for which the depth needed project because of the ideal sub-soil stratum is 100m to 160m.The SALPG cavern would

    This involves construction of a 60,000 t (with highly water saturated hard rock layer of be storing either butane or/and propane capacity Underground Rock Cavern -200m minimal joints) for cavern construction that blended as LPG, which exerts much greater below sea level for storing LPG together with the chosen site offers in addition to the escape pressure. Because of this the cavern attendant Access and Operating Shafts. A advantages of existing port infrastructure for depth has been extended to 200m, with the

    LPG Underground Storage Cavern, VizagIndia's First and the World's Deepest

    28

  • receiving large tankers, high demand in the shafts would also allow access for building P r o c u r e m e n t , C o n s t r u c t i o n , P r e -region and along the east coast for LPG and its the ramp and inclined cavern connector Commissioning and Commissioning of the re-exporting potential to South-East Asia. shafts at three levels: Header, Bench-1 and entire unloading, storage and loading

    Bench-2 system, plus various utilities including 33kV Once the project is operational, LPG transmission line.

    distribution will be significantly streamlined A diaphragm wall is constructed in the and enhanced in the region, especially as overburden section of the soil strata through This also included construction of plant Vizag Port has an exclusive LPG berth. which the vertical shafts, OS and AS, have buildings, such as DG Room, Electrical Sub-Imported bulk LPG sourced from refrigerated been sunk. station, Compressor House, 33kV Supply ships would be piped to the cavern and Station, Maintenance Workshop, Control evacuation through HPCLs pipeline network Room & Administration building and Water Curtain as also through the Vizag-Hyderabad Analyser Laboratory as well as seawater pipeline of Gas Authority of India Ltd. for intake pump house. This also included two This wide curtain of water created 15m commercial distribution. blast proof buildings. above the Main Cavern with the aid of a

    water tunnel having horizontal boreholes, ECC's scope of supply comprises Process facilitiesdrilled laterally from both sides, is charged

    underground and aboveground civil, with bacteria free water to prevent microbial structural and mechanical works with clogging in the rock cracks. The seepage of This involved procurement and erection attendant engineering services, which water from these boreholes create over the of imported and indigenous equipment like include electrical works and instrumentation. cavern a curtain of water that saturates the LPG Unloading Arms, Cavern LPG and

    underlying rock, preventing escape of LPG. seepage water pumps, 1.2mV HTDG set, The Underground (UG) Package LPG Booster Pumps and Sea Water Heat

    Exchanger for enhancing temperature of LPG Main Cavern This involves hard rock excavation, shaft from (-) 21C upto 3C prior to letting it into

    sinking, construction of the main cavern and the cavern. The LPG process facilities This has a overall dimension of 352m in providing the water curtain which calls for involved erection of marine loading and length and 20m in width and 20m in height l,30,000 cu.m of hard rock excavation, unloading arms as also LPG receiving (equivalent to 6-storeys). The 135168cu.m 34,000sq.m of shotcreting, 115t of rock facilities. Two refrigerated pipelines will cavern will be hewn out of hard garnet gneiss bolting and 175t of grouting and comprises connect the jetty area to the heating and bedrock, 200m below ground. Drilling and the following salient features: radio control installation to unload butane blasting methodology is adopted for carving

    and propane. It also covers setting up of out the cavern.Seawater Heat Exchanger System to heat the Shaft Sinking flow, in shaft equipment for LPG pump line, Plugging the Water Curtain Gallery and seepage water pumps, level measurement This involves construction of two major the Access/Operating Shafts will be the final lines, level alarm line, temperature sensors, vertical shafts - 4m dia Operation Shaft (OS) act that will provide the safety seal after vent/safety valves etc. and connection to and 6.5m dia Access Shaft (AS). They provide completion of underground operations.existing facilities.shaft-only approach not just for construction

    of Cavern and Water Curtain Gallery but Chittarajan Sahoowould also serve as conduit for piping in the The Aboveground (AG) Package Construction Managerpropane/butane shipments after blending as

    LPG through the AS, and piping out of stored This EPC contract package involved LPG from the cavern via'the OS. These main Project Management, Engineering Studies,

    Tunnel for SALPG at Visakhapatnam

    29

  • L&T secured an EPC Contract for 365,000 TPA Pure Soda Ash Plant of The Magadi Soda Company Limited (MSCL), Kenya against stiff international competitive bidding. MSCL is a wholly owned subsidiary of Brunner Mond, UK who are the second largest producer of Soda ash in Europe and sixth in the World.

    The exiting plant of MSCL in Kenya has a capacity of 300,000 TPA and exports 90 % of Soda Ash to South East Asia, India, Middle East and Republic of South Asia.

    This project is funded by International Finance Corporation (IFC), EIP and Dutch FMO. Bosch Projects Pty Limited, South Africa is the Project Management Consultant appointed by MSCL. Akzo Nobel Engineering b.v, Netherlands is the Process Consultant and Jacobs H&G, India is the Detail Engineering Consultant appointed by L&T for execution of this job. Contract Value for L&T is USD 58.56 Mn and Project Duration is 27 months.

    Major Quantities/Scope of Work

    Mechanical! Refractory works : 280 t ! LT PCC : 2 Verticals! Insulation works : 14,000 Sqm ! LT MCCs : 11 nos.

    ! Excavation : 20,348 Cum! Triple circuit overhead

    ! Concrete (all grades) : 10,025 Cum line : 250 m Electrical! Shuttering : 22,098 Sqm

    ! Electrical switchgear ! Structural steel & tank rooms : 3 nos.Power distribution for the plant from 5.5kv erection : 2,140 t

    ! Variable speed drives : 28 nos.level! Piping works : 58,718 IM

    ! Lighting, earthing and ! 5.5kv Switchboard : 11 Verticals! Equipments erection : 2,625 t lightning protection : 1 Lot! 5/3.5 MVA transformers : 2 nos.

    ! Cabling : 110 Km (approx.)

    Instrumentation

    ! DCS : 1 Lot! Field transmitters : 227 nos.! Mag. flow transmitters : 25 nos.! Control valves : 141 nos.! Dust monitoring system : 3 Sets! Flue Gas Analyser System : 1 Set

    General Flow of Engineering

    The Magadi Project Cell coordinated the complete Design & Engg Activities from HQ. The flow of engineering information between Engineering Consultants and Magadi Project Cell is depicted above: (See Chart)

    Magadi Pure Ash Soda Project, Kenya

    Flash Calciner area of Magadi Soda project, Kenya

    Jacobs H&G Mumbai, IndiaUtilities Consultant,

    Mech. Design & Detailed engg

    L&T EDRC Civil, E&IDesign & Detailed Engg

    HPD Systems [Veolia] USACrystallization

    Package

    Akzo Nobel Engg NetherlandsProcess Consultant

    L&T-ECCMagadi Project Cell

    FFE MineralsUSA

    GEA Process (L&T Niro) Baroda, India

    Fluid Bed Dryer

    Other Vendors for Equipment supplies

    Magadi Soda Compa