details have been given on the development of a successful cleaning chemical for hydrocarbon...
TRANSCRIPT
-
7/27/2019 Details have been given on the development of a successful cleaning chemical for hydrocarbon transport pipeline
1/11
5 PiPelines international digest | august 2011
technical
Development of a common
CCS infrastructure in the UKBy James Watt, Technical Manager, CCS, AMEC, Darlington, UK
The future deployment of CCS transport infrastructure is likely to be via common carrier networks rather than multiplesinge point to point solutions. This article discusses some of the issues around development of common infrastructure.The results from a number of studies in the UK are presented, including Teesside, Humber, Scotland, and the Mersey andDee clusters, as well as considerations for the East, South West, and South East of the UK. Discussed are the commonissues to all developments, critical assumptions, development of cluster scenarios, screening of emitters, modelling andcosting of pipeline networks and compression, and some of the other challenges facing implementation in the UK. Inparticular, the results from a study on Teesside will be used to illustrate the issues and costs facing some emitters, the
impact and potential of shipping, the failure to develop CCS projects and realities facing network development.
UK common infrastructure studiesThere are a number o common inrastructure studies o global
signifcance as highlighted by the GCCSI [1]. 14 storage-only
projects were identifed and 17 associated with enhanced oil
recovery (EOR). Four o the storage-only common inrastructure
projects are in the UK, more than any other nation. The our
identifed are Thames [2], Humber [3], Scotland [4], and Teesside
[5], but urther common inrastructure studies have been
completed. All are at various levels o detail rom simple studies
to the most advanced in the Humber, which is at pre-ront-end
engineering and design (FEED) level. What they show is a high
potential or common inrastructure in the UK. These our regions
are joined by the Mersey and Dee basin which was frst studied
in 2006 [6], while other studies have consider the North West
[7], and Greater South East [8] (Thames estuary, south eastern
counties, London and southern counties) looking at the potential
o clusters. Overall, the geography and density o emitters i the
UK promotes the ormation o common inrastructure. The studies
conducted have also led to the resolution o key considerations
or uture developments:
Figure 1: Humber regional high level network options.
http://-/?- -
7/27/2019 Details have been given on the development of a successful cleaning chemical for hydrocarbon transport pipeline
2/11
6 PiPelines international digest | august 2011
technical
Who is included in the study emitters types, size,
industry sector, geography
Cluster defnitions geography, emission density,
policy driven
Scenario developments
Timelines or roll-out
Storage and capture issues and options need to be
considered
Flexibility requirements o network
Comparison methods or optimisation Consideration o anchor projects
Right sizing or uture development
Compression/pumping strategy and costs
Environmental and social impacts/considerations
Inuence o shipping.
Denition of potential common infrastructureThe most important considerations are or the development
o clusters are the selection or storage sites and the inclusion o
emitters. Location o potential storage sites and emitters dictates
the practical shape o pipeline systems. There are a number o
studies in this area varying in detail. Currently common are GISenabled source/sink matching and optimisation which match
sources to sinks under a timeline scenario [9]. These studies show
time based progression o potential inrastructure, generally on a
large scale. Other reports are more practical in defnition looking
at smaller areas or specifc onshore developments, these latter
studies consider the issues at more detail.
The areas that may be considered clusters vary, no clear
technical defnition is yet proposed. How defnition o a cluster
occurs can be looked at in a number o ways:
Committed anchor projects numerous projects with
CCS ambitions
Density o emissions Regional policy
Proximity o emitters
High potential o accessible storage volumes.
Groups or single projects that can act as a solid base or
scenario defnitions can also enable inrastructure clusters.
These anchor projects are generally frst movers with capture,
storage, or EOR ambitions. For example the desire to utilise the
Hewitt ormation [10] as a storage site with an operator willing to
support CCS development should enable and encourage emitters
with CCS plans to utilise that acility and locate accordingly, such
as in the East o England. Similarly the East Irish Sea [11] has
signifcant storage potential and could enable CCS on the UKs
east coast. The Longannet project in Scotland, Don Valley IGCCproject in Humber, and Progressive Energys Eston Grange project
in Teesside all provide the same ocus rom which scenarios can
be derived. The critical elements remain; where do you store and
which emitters will deploy capture in the uture.
Inuence of storage locationThe location and development o storage sites is potentially
the frst area that must be looked at when considering common
inrastructure studies. The storage sites availability provides two
key actors: how much can be stored, and where. Other actors
included the type o storage site, the timeline through which
it may be made available, and the potential re-use o existinginrastructure. The location and the development o storage over
time sets the shape o the inrastructure, whereas the volumes
over time defne part o the systems capacity and pressure
Food and
Drink
1%
Downstream
Gas
2%
Chemicals
5%
Cement
2%Ceramics
0% Services
0%
Offshore
48%
Other
0%Pulp & Paper
1% Refineries7%
Glass
1%
Power
33%
Figure 2: Emitter screening factors.
Figure 3: Scotland: emitters by sector.
http://-/?- -
7/27/2019 Details have been given on the development of a successful cleaning chemical for hydrocarbon transport pipeline
3/11
7 PiPelines international digest | august 2011
technical
profles. The type o storage also causes issues regarding pressure
and ow: or example, a low-pressure reservoir on a common
network will require de-pressuring, while some stores may need
additional pressure. An optimum design approach needs to be
considered or uture plans, balanced against the risk o earlyinvestment in large systems.
A simple example is the decisions taken in the Humber studies.
Here the options or a common pipeline system drive the overall
shape. Early discussions on the potential storage options see the
Humber connect to the Southern North Sea targeting depleted
hydrocarbon felds (DHF) and potential deep saline ormations
(DSF). This was over the potential o the central North Sea
ormations or EOR. Picking a southern target orientates the
pipeline route south o Hull, while a northern target, central
North Sea, would drive a pipeline route north o Hull. This
changes the shape and inevitable operation o a network. The
purpose is to enable as many emitters as possible and, as shown
in Figure 1, orientation north and south has distinct dierences.The southern routeing is an optimal routeing where the network
alls to a single pipeline along a common route, minimising the
number o stranded assets. The northern route requires a major
river crossing to enable the acilities on the south bank o the
Humber, but essentially the network is much more branched,
connecting to a common pipeline just prior to going oshore.
The inuence o storage site location can be clearly seen.
Inuence of emittersEmitters are the other major driver; their size, type, deployment
timeline, and location all have inuenced inrastructure plans.
The optimum network considers all the emitters in a cluster, buthas to impose screening to ensure that the scenario is sound.
The inuence o size was frst explored in the study o the
Mersey and Dee basin [6] in North West UK. This study, providing
a modelling tool or common inrastructure, considers the
region as a test example. The inrastructure here considered
the use o high- and medium-pressure pipelines, with low-
pressure pipelines transporting CO2 gas in standard polyethylene
pipelines or low-ow, small, emitters. The cost o a networkvaries with the size o emitters and, as the emitters join an
optimised network, there is a marked increase in the marginal
network costs or emitters. This led to the introduction o tiers
0, 1, and 2, a coarse way o indicating the size o an emitter and
screening them.
The early study clearly showed marginal costs or small
emitters,
-
7/27/2019 Details have been given on the development of a successful cleaning chemical for hydrocarbon transport pipeline
4/11
8 PiPelines international digest | august 2011
technical
The completion o the emitters profle or a cluster is a simple
survey o the current and uture emitters. Current emitter data
can be located rom government databases and rom various
international databases or generated rom generic emissions/
capacity metrics. Future emitters need to be considered so that
any common inrastructure is o the right size to accommodate
them. In addition there is the possibility that an installed
common inrastructure may attract CCS-enabled projects to a
region. Early studies considered only installed emitters, but later
studies have considered potential emitters to enable right sizing
to occur.Emitter type is considered as the frst screening mechanism.
The most common screening is emitters that are oshore:
whilst the technology exists to capture the CO2 emitted rom
gas processing or power generation oshore it is viewed as a
medium-, i not long-term, target. In Scotland, when considering
a single inrastructure model, 48 per cent o the emissions or that
region are rom oshore acilities (Figure 3). Other emitter types
may not be suitable or capture, although urther study o this
is required. For some emitters, particularly the smaller emitters,
an evaluation has to be made as to whether a acility can host a
capture plant or would be suitable to do so.
The most common screen applied in studies should be size.Size classifcation typically uses three tiers splitting emitters into
large, medium, and small. The classifcation is based on marginal
connection costs, typically on onshore pipeline costs. In the
recent Teesside study the small emitters marginal cost, in terms
o overnight CAPEX, was 73/tonne, medium emitters
22/tonne, and or the large emitters 8/tonne. The impact o
adding medium emitters reduces the overall costs slightly, and
urther adding the small emitters increases the cost. Similar
results were expressed in the Mersey and Dee. The inclusion o
small emitters
-
7/27/2019 Details have been given on the development of a successful cleaning chemical for hydrocarbon transport pipeline
5/11
9 PiPelines international digest | august 2011
technical
all obstructions identifed. Guidance in the UK at least is explicit:
any CO2 pipeline is to be considered as conveying a dangerous
substance, and this ensures that the most stringent rules are
applied. Issues around the impact o CO2 pipeline dispersion
modelling and consequence analysis need to be resolved to
enable more-accurate routeing studies to be made. As guidance,
the minimum requirements o an appropriate standard such as BS
PD 8010:1 should be applied. The band o interest or a pipeline
then allows access to be assessed. Where a pipeline cannot gain
access to a site, alternatives should be considered; intermediatetransmission as a gas may be applicable or short distances
through crowded areas, or example. However some sites are not
accessible by pipeline due to the urban density, site congestion,
or environmental constraints. These sites can then be excluded
rom a cluster, or placed later into the deployment scenario.
The requirement or access to storage is undamental and, in
considering a common inrastructure, should have already been
considered. For individual sites, the actor inorms screening
capture technology or economic studies. In a recent assessment
o the potential or capture technology roll-out to gas-fred
generators, this element was used to screen remote sites, where
storage access is remote, beore consideration or inclusion intoa pipeline system. In the UK it is rare that an installation does
not have access, however expensive, but or acilities deep inland
with only oshore storage it becomes an economic determination
between the cost o pipeline and storage, simple release to
atmosphere, plant technology change, or closure.
The age o an emitter also inorms the design o common
inrastructure. The simple question is whether the plant is viable
to receive carbon capture or will be continuing long enough to
warrant it. One o the critical assumptions that have to be made
about uture projects also relates to existing emitters and their
end-o-service date. For the most part the consideration has to
be given that existing emitters will continue, i not as-installed
then replaced in the uture. There is a beneft rom re-plantingexisting sites and as such common inrastructure would enable
current and uture plant. But there will be scenarios where over
the lietime o a network plants will close. The reasoning is
complex economically and socially, but an assessment should
be made. The loss o a plant can have a considerable eect on an
inrastructure in term both CAPEX and OPEX.
Scenario developmentScreened emitters then orm the basis o the design o a
scenario or deployment. Whilst this may evolve during the
design o inrastructure, it is benefcial to defne a baseline at an
early stage. In addition, the baseline should include developmento storage sites. Development o clusters is highly dependent
on timing, both or emitters and storage. For storage, the timing
o availability drives the oshore development as well as the
Figure 7: Deployment to storage scenario.
http://-/?- -
7/27/2019 Details have been given on the development of a successful cleaning chemical for hydrocarbon transport pipeline
6/11
10 PiPelines international digest | august 2011
technical
Figure 8: Comparative cost for Tees Valley infrastructure options:
(a top) full-scale: note high marginal costs for 11c and 12;
(b bottom) expanded scale for network options.
http://-/?- -
7/27/2019 Details have been given on the development of a successful cleaning chemical for hydrocarbon transport pipeline
7/11
11 PiPelines international digest | august 2011
technical
expectations o use. Some depleted gas felds may not be
suitable or CCS or may be more suitable as commercial gas
storage sites. Oshore inrastructure age is also a consideration,
as is the lag time rom depleted hydrocarbon feld (DHF) closure
to uptake o CCS. Idle acilities incur ongoing costs when not
in production. Determination o storage availability thereore
shapes oshore common inrastructure in terms o location and
pipeline-operating parameters.
For example, consider three storage sites two DHFs andone deep saline ormation (DSF). I the frst store online is a
small DHF in 2015, typically used or a demonstration plant,
Figure 7. The frst pipeline will run to that feld. In 2020 a
nearby DHF storage site opens or CCS and urther along a
DSF opens in 2025. Enabling these rom the existing 2015
pipeline requires the installation to be expandable and the
initial pipeline to be right-sized, in order to accommodate
uture demand. Optimisation needs to be considered and also
reliability and risks to common inrastructure. Overall, more or
higher-capacity pipelines need to be installed to accommodate
2017 and 2025. By considering the whole scenario, the initial
investment may be higher but benefcial in the uture, This kind
o cost beneft, along with realistic costs o roll-out and oshoreoptions, is yet to be ully considered, particularly examining
the needs or oshore installations, compression and pumping,
and other common acilities.
For emitters timing, size, and type are the critical
scenario actors. When considering type this relates to entry
specifcation o the gas as well as the type actors used in
screening, and care has to be taken to ensure that new entrants
to common inrastructure do not push the content out o the
design conditions. To protect against this, the inrastructure
owner will need to tightly control entry specifcations. A typical
entry specifcation is commonly applied: one derived rom the
Dynamis [14] recommendations includes the ranges rom mostprocesses. There remain issues to address with the specifcation
predominantly the water content requirements still need to be
examined to avoid potential corrosion.
Costs to emitters are typically ignored during current
studies, but they do inuence deployment scenarios. The
ability o an emitter to enable CCS is dependent on cost, both
o the emission and the technology. For medium to small
emitters, or even non-power generation large emitters, capture
technology and high-pressure compression may at current
costs prove economically unviable. This consideration is policy
driven as policy is driving deployment rates, particularly the
demonstrator projects which are heavily publicly unded.
As experience at scale, or with lower-cost new technologies,
cost will decrease and deployment will accelerate. In reality,
medium and small emitters are usually shown to lag large-scale
emitters, a lag also dependent on emitter sector in terms o
deployment timescale.
Slow starts to common inrastructure with signifcant lead
times requires early periods where initial investment is not
being recovered at low utilisation o pipelines. The other eect
is that investments may become delayed or negated by policy,
deleting uture projects rom network scenarios.
Pipeline, compression and pumping
considerations and cost modelsThe costs associated with compression or pumping are
not easily derived, and there are a number o suggested
models (Table 1). Common compressor systems in natural gas
transmission are the natural correlation; however the ormat o
the compression stage is variable, Figure 4. Unlike natural gas,
change o phase is expected to be required rom gas to dense-
phase liquid and is not easily constructed. Direct correlation
with natural gas transmission compressors is not readily
possible as CO2 compressors require ancillary cooling systems
to achieve the phase change and inter-stage cooling is typically
required to improve eciency, Figure 5. The additional option
o pumps in series with the compression step also deviates romthe natural gas model, Figure 6, in which a compressor and
cooler arrangement can be used to produce medium pressures
and liquid carbon dioxide which can then be pumped.
Study Cost Metric/Formula Year
1
The Economics o CO2 Transport by Pipeline and
Storage in Saline Aquiers and Oil Reservoirs, DoE,
USA, 2004
C = 8.35P + 0.49
$8,346 per kW
P =Power, MW
2004
2
Techno-Economic Models or Carbon Dioxide
Compression, Transport, and Storage, McCollum et al,
University o Caliornia, 2005
2005
3
Cost and Perormance Baseline or
Fossil Energy Plants
DOE/NETL-2007/1281 Volume 1: Bituminous Coal and
Natural Gas to Electricity
Final Report (Original Issue Date, May 2007)Revision 1, August 2007
$24,860,000, 183 tonnes/hour, NGCC, 136$/kg/h
$46,363,000, 312 tonnes/hour, s/c CF, 148 $/kg/h
$49,059,000, 628 tonnes/hour, sub/c CF, 78 $/kg/h
2006
Table 1: Compressor/pump cost models.
http://-/?- -
7/27/2019 Details have been given on the development of a successful cleaning chemical for hydrocarbon transport pipeline
8/11
12 PiPelines international digest | august 2011
technical
O course some studies only consider the pipeline cost or thepressurisation to network pressure, and this ignores the initial
compression stage post capture. With limited experience in the
feld, and the demonstration projects at scale yet to come on line,
the actual costs are unknown. Analysis rom results o completed
scale engineering studies, with vendor cost inormation show a
marked dierential. The expectation is that rom Table 1, Equn
1 produces high estimates, whilst Equns 2 and 3 typically show
100 per cent low yields, against costs generated by vendors and
detailed engineering studies; or systems in the range 15 MMt/a
transported.
Critically it becomes important to defne where in any study
the compression stage lies. Whilst not currently addressed,
consideration needs to be given to the act that heat recoveryrom the coolers may be benefcial. In common inrastructure,
the exibility o the systems also becomes a major driver, and
again more work is needed to examine the issues o exibility
and utilisation. Pipeline costs themselves can be transposed rom
existing data; however, the costs associated with above-ground
installations, block valves, and metering remain to be confrmed.
Repeatedly, through dierent economic analyses, UK clusters
have indicated a 23 times cost saving or networks, although this
is higher in Scotland with its lower CO2 density/sq km in the study
area when compared to Humber and Tees.
Common infrastructure for the Tees ValleyThe recent study on Teesside considered scenarios where anetwork was created or transport in the region and into a single
common carrier pipeline in the North Sea. The overall scenario
was tested against other scenarios, three o which were the ailureo predicted projects to arrive. Figure 8 summarises the results
rom the 14 scenarios comparing the minimum cost in each
oshore deployment scenario to the others giving an indication
o the cost variances. The costs here are shown as indicative
overnight costs with no time weighting or economic assessment.
The striking scenarios are those that show the dierential
between single emitter to storage solutions (scenario 11). Large
emitters 11a, 11b, and 11d clearly show the 23 actor multiple
between these costs and those o a network. In scenario 11c
a medium-sized power plant the cost is signifcantly higher at
40115 times, depending on scenario (oshore pipeline distance)
so the beneft o a network is considerable.
Scenario 12 also shows the marginal connection cost ora remote emitter, and the cost o connecting to the existing
network. That this pipeline costs at 12 times that o a network
pipeline illustrates the additional actors that aect remote
assets, typical to cement, orestry-associated biomass, ceramics,
or potash processing plants. This marginal connection cost also
aects emitters spread over large geographic areas.
What is clear is the trend that greater volumes through the
system reduce the liecycle cost per tonne transported. The
Teesside study also considers the addition o a large remote
source (scenario 13) and the inuence o ship-based imports
(scenario 14) on cost. In the case o scenario 13, the remote emitter
contributed a urther 5 MMt/a to the oshore carrier pipeline,reducing the costs to the network. The additional volume
outweighs the cost o the additional pipeline and connection.
Similarly the addition o shipping to a network showed a
ComponentPost
CombustionIGCC Oxyfuel Weyburn Dynamis
CO2 >95% >95%
N2/Ar
0.01 0.030.06% 4.1%
-
7/27/2019 Details have been given on the development of a successful cleaning chemical for hydrocarbon transport pipeline
9/11
13 PiPelines international digest | august 2011
technical
beneft, depending on how the cost o the associated terminal
was assigned. The volume imported reduces the cost, but could
also add valuable buer storage to a network. I the cost o the
terminal acility is shared by networked emitters, then the cost
per tonne marginally increases. For export the costs are
34 times higher, but these exclude oshore cost or unloading
and injection, and this thereore needs urther consideration.
Another element tested in this study was the loss o projects,
something not tested beore in other studies. Three test scenarios
were used based on the arrival o two uture projects a 1000MWCCGT north o the Tees and an 850 MW IGCC south o the
river. In addition the loss o a steelworks, one o the regions
largest emitters was also modelled. These three large projects,
particularly the current steelworks, represent anchor projects,
large-volume emitters that are signifcant percentages o the
regions emissions. The ailure to develop either new project
(scenarios 9 and 10) increases network costs by 6 per cent (north)
and 45 per cent (south). The loss o the existing steelworks, or
ailure to capture CO2, results in 20 per cent higher network costs.
The importance thereore o mapping uture projects, current
emitter plans, and technology roll-outs is important in optimising
and understanding common inrastructure.
Development of UK infrastructureThe development o CCS inrastructure in the UK is dicult to
predict. The major blocker is a clear view o how UK projects will
Figure 9. Example deployment of commoninfrastructure in the UK to 2050.
http://-/?- -
7/27/2019 Details have been given on the development of a successful cleaning chemical for hydrocarbon transport pipeline
10/11
14 PiPelines international digest | august 2011
technical
come to market. By 2015 the frst demonstration project will be
online, potentially closely ollowed by three or our more with
the aid o EPR, NER, and urther DECC unding. Post-2020, when
the technology may be considered mature, the roll-out becomes
driven by investment based on the avoided ETS or oor price cost
o carbon. The mechanism to drive CCS is currently not in place.
Large roll-out as predicted in the IEA roadmap [15] will require
the commercial incentive to develop CCS. This will require clear
regulation, higher carbon prices and a technology less expensive
and more developed than it is now.
Transport inrastructure has its part to play, and reductions
anywhere in the chain o technology are valuable. The rate at
which a technology matures and cost decreases due to experience
and optimisation cannot yet be determined or capture and
storage. For capture technology, several comparative studies
such as Rubin [16] and IEA [17] (2006/6) compare capture plant
to the evolution o ue-gas-desulphurisation (FGD) technology.
The learning rate or FGD o 1113 per cent or each doubling o
capacity may be applied, but or FGDs but this is only a trend.In reality, the cost o wet FGD remained constant or almost six
doublings o installed capacity. From initial deployment to the
downswing in costs rom maturing technology was over a decade;
this included signifcant increases in cost or early projects. In
terms o demonstration projects o 300 MW equivalent, this would
require 9.6 GW equivalent o deployed CCS beore signifcant cost
reductions occur.
With the deployment required to achieve major savings in
capture, savings or at least reductions in CAPEX can come
rom pipelines. Common inrastructure oers signifcant cost
reductions, but with an upront investment based on a frst-
mover project. To examine the most recent study in the Humber
[18] considered the economics o developing networks. The
study showed clearly that deployed projects in a region, even
in small networks oered major savings. Economic analysis
urther showed that investment in right-sizing pipelines to uture
capacity was benefcial, with a no-regrets period o 16 years.
Investment early thereore would deliver low-cost transport
solutions at the point that comparative learning rates indicate
capture technology will start to deliver at lower costs.
There are other drivers that can aect the deployment rates
and thereore the need to develop inrastructure. Political, social,
and energy issues will drive CCS to deployment. Socially the
climate change agenda is driving opinion and in turn this drives
policy. Critically the energy-security issue will drive the UK andother European countries to consider the need to deploy gas
and coal-fred generation should nuclear and renewable energy
deployment not meet the required capacity targets. I carbon-
reduction targets are to be met, then CCS will have to be deployed
as will new gas- and coal-fred generation.
Other actors that will play a part in the deployment rate
include the ability to gain fnance/unding or early projects,
storage identifcation/qualifcation, technology deployment rates,
and social issues such as planning. The critical issue is that o
storage identifcation and access: some studies, such as those
by Kjarstad [19], EU [8], and CO2 Europipe [20] identiy storage
capacity and provide high level indicative inrastructure routesand costs. But the proving o the geological inormation needs to
be progressed. In the short term, consideration needs to be given
to the oshore inrastructure requirements and the enabling o
existing inrastructure to be maintained and preserved until CCS
deployment can include it.
Social issues will aect inrastructure development in terms
o location and planning. Recent experience in both natural gas
and CCS projects has seen major plans deerred or cancelled. The
impact on permitting can be considerable. Simple assumptions
in scenarios can take a lower-risk approach when considering the
use o brown-feld sites to co-locate CCS aculties such as booster
stations or the onshore/oshore transition terminals.
In terms o development, scenarios can be built rom the
programme o unding and current projects. One scenario or
deployment is shown in Figure 9, showing potential network
shapes in line with the DECC-unded competitions and a swing
in power generation to CCS post-2025. In this scenario it can
clearly be seen by examining the project emitter deployment that
common inrastructure installed in early projects can be used to
enable uture expansion.
ConclusionsCommon inrastructure development is clearly justifed,
benefcial, and economic. The studies or UK regions, EU-wide
inrastructure, and other regional work clearly indicate broad
themes and generate common inuences. There is also a case or
common inrastructure planning or even single-emitter projects,
and it should be included at the demonstration phase. The
success o common inrastructure not only requires commitment
in terms o projects and fnance, but also a strong technical basis
in industry and academia, supportive policy and, ultimately, an
inormed and supportive populace.
Should common inrastructure be deployed, co-ordinated
planning, exchange o inormation between projects, and supporto initial pipeline design enabling uture volumes and right sizing
is not only desirable but warranted.
References1. GCCSI, 2011. The global status o CCS: 2010.
2. EON, 2009. Capturing carbon, tackling climate change: a
vision or a CCS cluster in the South East.
3. Yorkshire Forward, 2008. A carbon capture and storage
network or Yorkshire and Humber.
4. SCCS, 2009. Opportunities or CO2 storage around
Scotland: an integrated strategic research study.
5. AMEC / One North East, 2010. Engineering design and
capture technologies or carbon capture and storage in theTees Valley.
6. IEA GHG R&D Programme, 2007. Distributed collection o
CO2. Report 2007/12.
7. DECC, 2009. Technical analysis o carbon capture &
storage (CCS) transportation inrastructure.
8. EON, 2009. Capturing carbon, tackling climate change: a
vision or a CCS cluster in the South East.
9. CO2 Europipe, 2011. Development o a large-scale CO2
transport inrastructure in Europe: matching captured
volumes and storage availability. www.co2europipe.eu/,
2011-06-13.
10. S.Grewcock, 2008. CO2 storage: an oil industry perspective.Oil & Gas UK Breakast 11th December, Tullow Oil, www.
oilandgasuk.co.uk/downloadabledocs/372/Simon%20
Grewcock.pd
http://-/?- -
7/27/2019 Details have been given on the development of a successful cleaning chemical for hydrocarbon transport pipeline
11/11
15 PiPelines international digest | august 2011
technical
11. A.Baddeley, 2011. The East Irish Sea CCS cluster: a
conceptual design technical report. Eunomia Consulting
(www.eunomia.co.uk), Bristol.
12. IEA GHG R&D Programme, 2007. CO2 capture ready power
plants. Report (2007/2), UK.
13. DECC, 2009. Carbon capture readiness (CCR): a
guidance note or Section 36 Electricity Act 1989 consent
applications. UK HMG.
14. Dynamis, 2008. CO2 quality recommendations.Int. J. of
Greenhouse Gas Control,2, pp 478-484.
15. IEA, 2009. Technology roadmap: carbon capture and
storage. www.iea.org/papers/2009/CCS_Roadmap.pd
16. E.S.Rubin, 2007. Cost and perormance o ossil uel power
plants with CO2 capture and storage.Energy Policy, 35, pp
4444-4453.
17. IEA GHG R&D Programme, 2006. Estimating the uture
trends in the cost o CO2 capture technologies. Report
2006/6.
18. J.Watt et al., 2010. CO2 transport inrastructure or
Yorkshire and Humber: pre-FEED study report. AMEC, CO2
Sense.
19. J.Kjarstad, 2009. Ramp up o large scale CCS inrastructure
in Europe, GHGT-9.
20. F.Neele et al., 2010. Development o large scale CO2
transport inrastructure in Europe: matching captured
volumes and storage availability. CO2 Europipe Project.
http://-/?-