kent goldthorpe, president paul woods, vice president ...€¦ · 2016. project is part of...
TRANSCRIPT
![Page 1: Kent Goldthorpe, President Paul Woods, Vice President ...€¦ · 2016. Project is part of ITD's Strategic Initiatives request for FY2021. ACHD with ITD on any improvement if funded](https://reader030.vdocuments.net/reader030/viewer/2022041118/5f2f3aeb5603fd337e77e47c/html5/thumbnails/1.jpg)
Kent Goldthorpe, President Paul Woods, Vice President
Rebecca W. Arnold, Commissioner Sara M. Baker, Commissioner Jim D. Hansen, Commissioner
Planning & Programming April 27, 2016
TO: Commissioners, Director, and Deputy Directors
FROM: Ryan Head, AICP, Planning Supervisor
SUBJECT: FY2017‐2021 Integrated Five‐Year Work Plan (IFYWP) ‐ Early Issues Commission Work Session – May 11, 2016
Executive Summary The Integrated Five‐Year Work Plan (IFYWP) is the District’s five‐year plan of projects and activities, which provides common direction internally, and strives to establish stability and consistency for the District and its partners, as ACHD implements its mission. After Commission feedback during the work session, staff will finalize the prioritization ranking (technical scores) and begin programming for the Initial Draft. The Integrated Five‐Year Work Plan is updated annually and its schedule is coordinated with the preparation of the budget to provide a seamless transition between the fiscal years covered by the budget and the subsequent years programmed in the IFYWP. The purpose of this work session is to update the Commission and affirm direction on emerging issues to be addressed during the upcoming IFYWP. Planning Framework ACHD is in the process of developing a Strategic Plan to provide an umbrella framework for all work done by the District. A key focus of this effort is ensuring ACHD is properly managing and maintaining the public’s transportation assets, while investing in additional infrastructure needed to accommodate growth within Ada County and its six cities. This iteration of the IFYWP includes the principles and basic direction provided by the Commission through the Strategic Planning effort to date. Further, the IFYWP is the tool used to implement ACHD’s long‐term plans. This includes the:
Capital Improvement Plan
Transportation Land Use Integration Plan
Bike Master Plan
Pedestrian‐Bicycle Transition Plan
State Street Transit and Traffic Operational Plan
Neighborhood Pedestrian and Bicycle Plans
Downtown Boise Implementation Plan
Kuna Downtown Corridor Plan
Other Sub‐Area and Corridor Plan
![Page 2: Kent Goldthorpe, President Paul Woods, Vice President ...€¦ · 2016. Project is part of ITD's Strategic Initiatives request for FY2021. ACHD with ITD on any improvement if funded](https://reader030.vdocuments.net/reader030/viewer/2022041118/5f2f3aeb5603fd337e77e47c/html5/thumbnails/2.jpg)
2
IFYWP Schedule and Milestones Significant dates for the IFYWP schedule:
April 1: Agency transportation requests due – COMPLETE o Requests received from all agency partners, with the exception of Garden City.
May 11: Early Issues Work Session – CURRENT WORK SESSION
May 20: Send initial feedback to agencies on transportation requests
August 10: Initial Draft IFYWP Work Session
September 9: Public/agency comments due
September 28: Work session on public/agency comments
October 26: 2017‐2021 IFYWP adoption hearing Draft Revenue Assumptions Revenue projections used in the development of the IFYWP included revenue assumptions being used in the development of the FY2017 Budget as well as the assumptions included in the ACHD Strategic Plan. In basic terms, the revenue projections assume the following:
Property tax adjustments (if any) as approved by the Commission for the FY2017 Budget; 3% plus growth FY2019‐FY2023
3.0% annual increase for impact fees and sales tax revenue
2.5% annual increase for the highway user fund. Includes the approved state transportation funding increase (HB312)
2.0% annual increase in labor and operational expenses
1% annual growth for vehicle registration fees
Agency Requests This year, ACHD received a total of 409 transportation requests from Ada County, five cities (no new requests submitted by Garden City), and the Boise, Kuna and West Ada School Districts, including:
263 community programs requests (89 school district requests)
138 road and intersection project requests
8 study requests (6 pathway feasibility requests) Attachments to this memo include a complete summary of the project requests and staff’s proposed response. The original request letter is also provided. These are organized by each individual jurisdiction. Staff makes the proposed responses based on existing policy and practice, with an effort to collaboratively support agency partners wherever possible. Staff seeks Commission confirmation of the proposed responses during the work session. Economic Development Projects In FY2013, the Commission directed staff to set aside up to $2 million per year in funds for the development of an Economic Development program in the IFYWP. During the FY2014‐2018 update to the IFYWP, projects requested by the cities filled the 5 years of the Plan. Staff did not solicit additional economic development projects the last three years (including 2016), in order to allow the projects approved by the Commission in the FY2014 update to move forward and the program to be analyzed for its effectiveness. Many of the first group of projects will be completed by FY2017. Staff anticipates seeking additional requests during the FY2018‐2022 update cycle.
![Page 3: Kent Goldthorpe, President Paul Woods, Vice President ...€¦ · 2016. Project is part of ITD's Strategic Initiatives request for FY2021. ACHD with ITD on any improvement if funded](https://reader030.vdocuments.net/reader030/viewer/2022041118/5f2f3aeb5603fd337e77e47c/html5/thumbnails/3.jpg)
3
Priority Corridor Update During previous IFYWP efforts, the Capital Improvement Citizens Advisory Committee (CICAC) recommended and the Commission approved several priority corridors. Priority corridors are those corridors where significant investment has occurred, and will be a focus of future programming due to high prioritization. These corridors were also recommended to help focus resources and complete all work in a strategic way. The current status of those priority corridors is as follows:
Cloverdale, I‐84/Chinden: All major intersections are complete; improvement of segments is under construction with Franklin/Fairview, followed by Fairview/Ustick in 2018, Ustick/McMillan in 2019, and McMillan/Chinden in 2020.
Fairview Avenue Corridor (Linder/Orchard): The Commission adopted the Fairview Avenue Corridor Management Plan February 2013. On March 25, 2015, this project was put on hold indefinitely by the Commission. That said, ACHD has two intersection projects in the IFYWP: Fairview/Cole in 2017 and Fairview/Locust Grove in preliminary development.
Five Mile (I‐84/Chinden): Fairview/Ustick is slated for construction in 2016. This would complete Five Mile as a priority corridor.
Franklin (Black Cat/Five Mile): Completed to Ten Mile; Black Cat/Ten Mile and the Black Cat intersection slated to begin in 2016. This would complete Franklin as a priority corridor.
Meridian Split Corridor: Complete.
State Street (Glenwood/27th): Veterans Parkway/36th St intersection is in the right‐of‐way phase, with construction currently slated in 2018. Collister intersection is in design, with construction currently programmed for FY2019. The Pierce Park intersection is slated to begin concept design in FY2017. The Glenwood intersection will be put on hold during this IFYWP update due to the inability to obtain financial partnership on the project at this time from ITD. Widening of the roadway segments will not occur until triggers are met as set forth in the State Street TTOP.
Ten Mile (Overland/Ustick): All major intersections are complete from Overland to Chinden; segments are completed from Overland to Cherry, with Cherry/Ustick under construction now. The remaining 2 miles (Ustick/Chinden) are both programmed in preliminary development.
Ustick (Ten Mile/Cole): Completed Cole/Locust Grove. Linder/Locust Grove and the Meridian intersection are slated to begin construction in 2016. These projects are top priorities based on the adopted prioritization system.
With the planned completion of multiple priority corridors, Staff has proposed additional corridors for consideration by the CICAC. The Committee is scheduled to make their official recommendation on these new corridors at their meeting on May 16, 2016. During the work session, staff will review the draft corridors for consideration pending CICAC recommendation. Programming Targets/Considerations Staff recommends continuing the following programming targets/considerations:
A robust shelf strategy will be presented in the IFYWP draft, increasing efforts in design and right‐of‐way phases and allowing construction phases to be “on shelf” as changes occur in revenues or project costs. The goal will be to have a shelf list of projects whose construction phases represent up to 20% of the capital budget in the out years of the IFYWP. Coupled with a robust list of capital maintenance projects, this strategy will allow the District to move more nimble as conditions change.
![Page 4: Kent Goldthorpe, President Paul Woods, Vice President ...€¦ · 2016. Project is part of ITD's Strategic Initiatives request for FY2021. ACHD with ITD on any improvement if funded](https://reader030.vdocuments.net/reader030/viewer/2022041118/5f2f3aeb5603fd337e77e47c/html5/thumbnails/4.jpg)
4
Staff recommends maintaining the target of $7‐$9 million per year for Community Programs. This target includes:
o A minimum of 5% of the capital budget toward Core Community Programs.
o Half of the increase in vehicle registration fee revenues approved in 2008.
o ACHD’s Safe Sidewalk program. (About $1.1 million/year)
o Up to $2 million per year for the Economic Development program.
Staff recommends maintaining the target of $10‐$14 million per year for Capital Maintenance.
Direction Needed
How would the Commission direct staff to respond to the agency requests identified in the attachments?
Does the Commission concur with the continued approach using priority corridors, including the new priorities when recommended by the CICAC?
Does the Commission concur with continued use of the identified programming targets? Next Steps
August 10: Initial Draft IFYWP Work Session
September 9: Public/agency comments due
September 28: Work session on public/agency comments
October 26: 2017‐2021 IFYWP adoption hearing Attachments
1. Ada County Request Summary and Letter 2. Boise Request Summary and Letter 3. Boise School District Request Summary and Letter 4. Eagle Request Summary and Letter 5. Kuna Request Summary and Letter 6. Kuna School District Request Summary and Letter 7. Meridian Request Summary and Letter 8. Star Request Summary and Letter 9. West Ada School District Request Summary and Letter
![Page 5: Kent Goldthorpe, President Paul Woods, Vice President ...€¦ · 2016. Project is part of ITD's Strategic Initiatives request for FY2021. ACHD with ITD on any improvement if funded](https://reader030.vdocuments.net/reader030/viewer/2022041118/5f2f3aeb5603fd337e77e47c/html5/thumbnails/5.jpg)
Attachment 1
Ada County 2016 Requests and ACHD Proposed Response
In IFYWP
(Page)DSN YR ROW YR CN YR
Total Cost
in MillionsProgramming Notes
Road & Intersection
1 1 IN205‐
11
SH 16 and Beacon
Light Rd
Install a signal and add turn lanes as needed. ITD to lead project, with ACHD
participating in the design and cost. Subject to cooperative agreement and
programming with ITD.
Yes (49) 2016 2016 2017 $1.45 Project being led by ITD. To be built in FY2017.
2 2 IN205‐
66
SH 69 (Meridian Rd)
and Hubbard Rd
Widen intersection to 7 lanes on all approaches in accordance with the 2012
CIP.
Yes (50) UF UF UF $5.04 ACHD requested project from ITD in spring
2016. Project is part of ITD's Strategic
Initiatives request for FY2021. ACHD with ITD
on any improvement if funded.
3 3 RC0299 Ten Mile Rd, Victory
Rd / Overland Rd
Widen Ten Mile Rd to 5 lanes with cubr, gutter, sidewalk and bike lanes in
accordance with the 2012 CIP.
Yes (40) PD PD UF $4.38
Project design still in preliminary development,
with construction unfunded. ACHD to evaluate
potential advancement of project phases
during IFYWP update.
4 5 RD207‐
21
Maple Grove Rd, Amity
Rd / Victory Rd
Widen Maple Grove Rd to 5 lanes with curb, gutter, sidewalk, and bike lanes
in accordance with the 2012 CIP. Project includes bridge #269A.
Yes (35) 2020 PD PD $3.47 Programmed to begin design in FY2020. ACHD
to evaluate project construction moving
forward through IFYWP update.
IN215‐
02
Cole Rd and Lake Hazel
Rd
Construct a new signalized intersection in accordance with the 2012 CIP.
Project includes bridge #349.
Yes (48) PD PD PD $6.67
Project design still in preliminary development,
with construction unfunded. ACHD to evaluate
potential advancement of project phases
during IFYWP update.
RD209‐
19
Lake Hazel Rd, Cole Rd
/ Orchard St Extension
Construct a new roadway extension of Lake Hazel Rd, between Cole Rd and
the Orchard St Extension.
No $3.90
Proposed developer cooperative project to be
evaluated for inclusion in the IFYWP update.
RD207‐
01
Orchard St, Gowen Rd
/ I‐84 On‐Ramp
Realign and widen Orchard St to 5 lanes with curb, gutter, sidewalk and bike
lanes.
No $4.76 ACHD to complete an alignment study and
concept design in FY2017.
Orchard St, Lake Hazel
Rd / Gowen Rd
Construct a new roadway extension of Orchard St, between Gowen Rd and
the Lake Hazel Rd Extension.
No $5.89
Proposed developer cooperative project to be
evaluated for inclusion in the IFYWP update.
RD209‐
19
Lake Hazel Rd, Orchard
St Extension / Pleasant
Valley Rd
Construct a new roadway extension of Lake Hazel Rd, between the Orchard
St Extension and Pleasant Valley Rd.
No $5.28 Prioritize and program after completion of the
connection between Lake Hazel and Orchard.
5 NEW
6 NEW
ACHD Proposed Response
2016
County
Priority
Ranking
2015
County
Priority
Ranking
GIS # ACHD Project Name Project Description
Current Programming Status
PD ‐ Preliminary Development
UF ‐ Unfunded
CN ‐ Construction Year Page 1 of 2
![Page 6: Kent Goldthorpe, President Paul Woods, Vice President ...€¦ · 2016. Project is part of ITD's Strategic Initiatives request for FY2021. ACHD with ITD on any improvement if funded](https://reader030.vdocuments.net/reader030/viewer/2022041118/5f2f3aeb5603fd337e77e47c/html5/thumbnails/6.jpg)
Attachment 1
7 8 MA215‐
05
Swan Falls Railroad
Overpass (Kuna
Railroad Overpass)
Install a new bridge over Indian Creek and Union Pacific Railroad on Swan
Falls Rd.
No $18.50 Included on ACHD's Master Street Map.
Project to occur in accordance with the Kuna
Crossing Feasibility and Implementation Plan.
8 4 RC0207 Linder Rd, Overland Rd
/ Franklin Rd
Widen Linder Rd to 5 lanes and construct a new 4‐lane I‐84 overpass,
including curb, gutter, sidewalk, and bike lanes in accordance with the 2012
CIP. Project would be a joint project between ACHD and ITD.
No $3.15 Cost do not include overpass. ACHD requested project from ITD in spring
2016. Project is not on ITD's planned projects
at this time. ACHD will continue to pursue
project with ITD.
9 9 N/A Midway Dr/Glenwood
St
New signal. No N/A ACHD has no right‐of‐way at this location.
ACHD to share request with ITD.
Community Programs
1 1 CM213‐
64
Linder Rd, Main St /
Deer Flat Rd (Linder
Rd, Deer Flat Rd /
Boise St)
Complete curb, gutter, detached sidewalk and bike lanes on both sides of
Linder Rd, between 4th St (Linder/Main/3rd project limits) to Deer Flat Rd.
Project will construct a Rectangular Rapid Flashing Beacon at Porter St.
Yes
(116)
PD PD PD $1.44
Project design still in preliminary development.
ACHD to evaluate potential advancement of
project phases during IFYWP update.
2 2 PPI208‐
91,
CM212‐
05
Lake Hazel Rd, west of
Maple Grove Rd
Two pedestrian projects programmed: 1) Lake Hazel Rd, Cloverdale Rd /
Lowland View Way and 2) Lake Hazel, Pearl Jensen Ave / Acacia Ave.
Yes
(115)
Done 2016 2016‐
2017
$0.62 Projects to be built in FY2016 and FY2017.
3 3 CM212‐
27
Garrett St, Chinden
Blvd / Marigold St
Complete sidewalks and bike lanes on both sides of Garrett Street between
Chinden Blvd and Marigold St for greater pedestrian and bike connectivity
between the west bench and the greenbelt.
Yes
(112)
2017 2018 2019 $0.15 To be built in FY2019.
4 NEW Warm Springs Ave,
Signal Rock Dr / Lysted
Ave
Drainage improvements. No N/A Prioritize and scope.
PD ‐ Preliminary Development
UF ‐ Unfunded
CN ‐ Construction Year Page 2 of 2
![Page 7: Kent Goldthorpe, President Paul Woods, Vice President ...€¦ · 2016. Project is part of ITD's Strategic Initiatives request for FY2021. ACHD with ITD on any improvement if funded](https://reader030.vdocuments.net/reader030/viewer/2022041118/5f2f3aeb5603fd337e77e47c/html5/thumbnails/7.jpg)
![Page 8: Kent Goldthorpe, President Paul Woods, Vice President ...€¦ · 2016. Project is part of ITD's Strategic Initiatives request for FY2021. ACHD with ITD on any improvement if funded](https://reader030.vdocuments.net/reader030/viewer/2022041118/5f2f3aeb5603fd337e77e47c/html5/thumbnails/8.jpg)
![Page 9: Kent Goldthorpe, President Paul Woods, Vice President ...€¦ · 2016. Project is part of ITD's Strategic Initiatives request for FY2021. ACHD with ITD on any improvement if funded](https://reader030.vdocuments.net/reader030/viewer/2022041118/5f2f3aeb5603fd337e77e47c/html5/thumbnails/9.jpg)
Ada County Courthouse 200 West Front Street Boise ID 83702 208.287.7900 Fax 208.287.7909 www.adacounty.id.gov
Department Divisions Building Engineering & Surveying Permitting Planning & Zoning
Ada County Commissioners Jim Tibbs, First District Rick Yzaguirre, Second District David L. Case, Third District
Megan M. Leatherman, MCRP Director
ADA COUNTY
Development Services Department
April 1, 2016 Ryan Head, AICP Planning Supervisor Ada County Highway District 3775 Adams Street Garden City, ID 83714 RE: Ada County FY 2017-2021 IFYWP Narratives Community
Programs #1 – Pedestrian Improvements along Linder Road
Dear Mr. Head: Thank you for the opportunity to describe Ada County’s transportation priorities for the FY17-2021 IFYWP. The County respectfully requests sidewalks be installed along both sides of Linder Road between Deer Flat Road and Boise Street. Both sides of the street have some sidewalk but there are large gaps that should be completed. There are also several schools in the immediate vicinity and the complete sidewalks would benefit the children walking to-and-from school. I appreciate your consideration of the information contained herein as you prepare a draft IFYWP. If you have any questions or need additional detail about the project(s) please do not hesitate to contact me. Sincerely yours,
Megan Basham, AICP Community and Regional Planner
![Page 10: Kent Goldthorpe, President Paul Woods, Vice President ...€¦ · 2016. Project is part of ITD's Strategic Initiatives request for FY2021. ACHD with ITD on any improvement if funded](https://reader030.vdocuments.net/reader030/viewer/2022041118/5f2f3aeb5603fd337e77e47c/html5/thumbnails/10.jpg)
Ada County Courthouse 200 West Front Street Boise ID 83702 208.287.7900 Fax 208.287.7909 www.adacounty.id.gov
Department Divisions Building Engineering & Surveying Permitting Planning & Zoning
Ada County Commissioners Jim Tibbs, First District Rick Yzaguirre, Second District David L. Case, Third District
Megan M. Leatherman, MCRP Director
ADA COUNTY
Development Services Department
April 1, 2016 Ryan Head, AICP Planning Supervisor Ada County Highway District 3775 Adams Street Garden City, ID 83714 RE: Ada County FY 2017-2021 IFYWP Narratives Community
Programs #2 – Lake Hazel Road Bicycle & Pedestrian Improvements
Dear Mr. Head: Thank you for the opportunity to describe Ada County’s transportation priorities for the FY17-2021 IFYWP. There are sections of Lake Hazel Road, west of Maple Grove Road, that lack adequate or safe bicycle and pedestrian facilities. To increase safety for non-motorized users of the identified roadway segment, the County requests that the roadway be improved with sidewalk and that the shoulders be widened. I appreciate your consideration of the information contained herein as you prepare a draft IFYWP. If you have any questions or need additional detail about the project(s) please do not hesitate to contact me. Sincerely yours,
Megan Basham, AICP Community and Regional Planner
![Page 11: Kent Goldthorpe, President Paul Woods, Vice President ...€¦ · 2016. Project is part of ITD's Strategic Initiatives request for FY2021. ACHD with ITD on any improvement if funded](https://reader030.vdocuments.net/reader030/viewer/2022041118/5f2f3aeb5603fd337e77e47c/html5/thumbnails/11.jpg)
Ada County Courthouse 200 West Front Street Boise ID 83702 208.287.7900 Fax 208.287.7909 www.adacounty.id.gov
Department Divisions Building Engineering & Surveying Permitting Planning & Zoning
Ada County Commissioners Jim Tibbs, First District Rick Yzaguirre, Second District David L. Case, Third District
Megan M. Leatherman, MCRP Director
ADA COUNTY
Development Services Department
April 1, 2016 Ryan Head, AICP Planning Supervisor Ada County Highway District 3775 Adams Street Garden City, ID 83714 RE: Ada County FY 2017-2021 IFYWP Narratives Community Programs #3 – Garrett Street Improvements Dear Mr. Head: Thank you for the opportunity to describe Ada County’s transportation priorities for the FY17-2021 IFYWP. The County respectfully requests that sidewalks and bike lanes be constructed on both sides of Garrett Street between Chinden Boulevard and Marigold Street. These improvements would provide greater bicycle and pedestrian connectivity between the west bench and the greenbelt. This request is made in support of the City of Garden City. I appreciate your consideration of the information contained herein as you prepare a draft IFYWP. If you have any questions or need additional detail about the project(s) please do not hesitate to contact me. Sincerely yours,
Megan Basham, AICP Community and Regional Planner
![Page 12: Kent Goldthorpe, President Paul Woods, Vice President ...€¦ · 2016. Project is part of ITD's Strategic Initiatives request for FY2021. ACHD with ITD on any improvement if funded](https://reader030.vdocuments.net/reader030/viewer/2022041118/5f2f3aeb5603fd337e77e47c/html5/thumbnails/12.jpg)
Ada County Courthouse 200 West Front Street Boise ID 83702 208.287.7900 Fax 208.287.7909 www.adacounty.id.gov
Department Divisions Building Engineering & Surveying Permitting Planning & Zoning
Ada County Commissioners Jim Tibbs, First District Rick Yzaguirre, Second District David L. Case, Third District
Megan M. Leatherman, MCRP Director
ADA COUNTY
Development Services Department
April 1, 2016 Ryan Head, AICP Planning Supervisor Ada County Highway District 3775 Adams Street Garden City, ID 83714 RE: Ada County FY 2017-2021 IFYWP Narratives Community
Programs #4 – Drainage Improvements on Warm Springs between Gergerson Property (Signal Rock Drive) and Lysted Avenue
Dear Mr. Head: Thank you for the opportunity to describe Ada County’s transportation priorities for the FY17-2021 IFYWP. The County respectfully requests that drainage improvements be installed along Warm Springs Avenue between Signal Rock Drive and Lysted Avenue. The greenbelt runs parallel to Warm Springs Avenue in this location within the ACHD ROW and is maintained by Ada County Parks and Waterways. The road consistently floods several segments of the greenbelt in this area, creating a hazardous experience for greenbelt users. I appreciate your consideration of the information contained herein as you prepare a draft IFYWP. If you have any questions or need additional detail about the project(s) please do not hesitate to contact me. Sincerely yours,
Megan Basham, AICP Community and Regional Planner
![Page 13: Kent Goldthorpe, President Paul Woods, Vice President ...€¦ · 2016. Project is part of ITD's Strategic Initiatives request for FY2021. ACHD with ITD on any improvement if funded](https://reader030.vdocuments.net/reader030/viewer/2022041118/5f2f3aeb5603fd337e77e47c/html5/thumbnails/13.jpg)
Ada County Courthouse 200 West Front Street Boise ID 83702 208.287.7900 Fax 208.287.7909 www.adacounty.id.gov
Department Divisions Building Engineering & Surveying Permitting Planning & Zoning
Ada County Commissioners Jim Tibbs, First District Rick Yzaguirre, Second District David L. Case, Third District
Megan M. Leatherman, MCRP Director
ADA COUNTY
Development Services Department
April 1, 2016 Ryan Head, AICP Planning Supervisor Ada County Highway District 3775 Adams Street Garden City, ID 83714 RE: Ada County FY 2017-2021 IFYWP Narratives Road & Intersection #1 – Traffic Control Signal at Beacon Light Road & SH-16 Dear Mr. Head: Thank you for the opportunity to describe Ada County’s transportation priorities for the FY17-2021 IFYWP. The County respectfully requests that a traffic control signal be installed at the intersection of SH-16 and Beacon Light Road to increase safety. As traffic flows are influenced by the extension of SH-16 to US-20/26, the need for a controlled intersection appears warranted to ensure safer interaction with east-west flowing traffic. I appreciate your consideration of the information contained herein as you prepare a draft IFYWP. If you have any questions or need additional detail about the project(s) please do not hesitate to contact me. Sincerely yours,
Megan Basham, AICP Community and Regional Planner
![Page 14: Kent Goldthorpe, President Paul Woods, Vice President ...€¦ · 2016. Project is part of ITD's Strategic Initiatives request for FY2021. ACHD with ITD on any improvement if funded](https://reader030.vdocuments.net/reader030/viewer/2022041118/5f2f3aeb5603fd337e77e47c/html5/thumbnails/14.jpg)
Ada County Courthouse 200 West Front Street Boise ID 83702 208.287.7900 Fax 208.287.7909 www.adacounty.id.gov
Department Divisions Building Engineering & Surveying Permitting Planning & Zoning
Ada County Commissioners Jim Tibbs, First District Rick Yzaguirre, Second District David L. Case, Third District
Megan M. Leatherman, MCRP Director
ADA COUNTY
Development Services Department
April 1, 2016 Ryan Head, AICP Planning Supervisor Ada County Highway District 3775 Adams Street Garden City, ID 83714 RE: Ada County FY 2017-2021 IFYWP Narratives
Road & Intersection #2 – Traffic Control Signal at SH-69 and Hubbard Road
Dear Mr. Head: Thank you for the opportunity to describe Ada County’s transportation priorities for the FY17-2021 IFYWP. The County respectfully requests that a traffic control signal be installed at the intersection of SH-69 and Hubbard Road to increase safety. According to ITD’s High Accident Location summary report, the intersection is seeing an increase in traffic accidents and its ranking has gone from 255 to 180.5. The area is growing and as people move in, the pressure at the intersection will continue. I appreciate your consideration of the information contained herein as you prepare a draft IFYWP. If you have any questions or need additional detail about the project(s) please do not hesitate to contact me. Sincerely yours,
Megan Basham, AICP Community and Regional Planner
![Page 15: Kent Goldthorpe, President Paul Woods, Vice President ...€¦ · 2016. Project is part of ITD's Strategic Initiatives request for FY2021. ACHD with ITD on any improvement if funded](https://reader030.vdocuments.net/reader030/viewer/2022041118/5f2f3aeb5603fd337e77e47c/html5/thumbnails/15.jpg)
Ada County Courthouse 200 West Front Street Boise ID 83702 208.287.7900 Fax 208.287.7909 www.adacounty.id.gov
Department Divisions Building Engineering & Surveying Permitting Planning & Zoning
Ada County Commissioners Jim Tibbs, First District Rick Yzaguirre, Second District David L. Case, Third District
Megan M. Leatherman, MCRP Director
ADA COUNTY
Development Services Department
April 1, 2016 Ryan Head, AICP Planning Supervisor Ada County Highway District 3775 Adams Street Garden City, ID 83714 RE: Ada County FY 2017-2021 IFYWP Narratives
Road & Intersection #3 – Ten Mile Road Widening between Overland Road and Victory Road
Dear Mr. Head: Thank you for the opportunity to describe Ada County’s transportation priorities for the FY17-2021 IFYWP. In 2011, Ada County identified Ten Mile Road widening north of Interstate 84 as a top priority. The County is appreciative of all of the improvements that have been completed by the ACHD thus far. Completing remaining improvements between Overland Road and Victory Road will help to move traffic more efficiently south of the I-84. That segment of the road is currently operating at a LOS F. I appreciate your consideration of the information contained herein as you prepare a draft IFYWP. If you have any questions or need additional detail about the project(s) please do not hesitate to contact me. Sincerely yours,
Megan Basham, AICP Community and Regional Planner
![Page 16: Kent Goldthorpe, President Paul Woods, Vice President ...€¦ · 2016. Project is part of ITD's Strategic Initiatives request for FY2021. ACHD with ITD on any improvement if funded](https://reader030.vdocuments.net/reader030/viewer/2022041118/5f2f3aeb5603fd337e77e47c/html5/thumbnails/16.jpg)
Ada County Courthouse 200 West Front Street Boise ID 83702 208.287.7900 Fax 208.287.7909 www.adacounty.id.gov
Department Divisions Building Engineering & Surveying Permitting Planning & Zoning
Ada County Commissioners Jim Tibbs, First District Rick Yzaguirre, Second District David L. Case, Third District
Megan M. Leatherman, MCRP Director
ADA COUNTY
Development Services Department
April 1, 2016 Ryan Head, AICP Planning Supervisor Ada County Highway District 3775 Adams Street Garden City, ID 83714 RE: Ada County FY 2017-2021 IFYWP Narratives Road &
Intersection #4 – Maple Grove Widening between Victory Road and Amity Road
Dear Mr. Head: Thank you for the opportunity to describe Ada County’s transportation priorities for the FY17-2021 IFYWP. The County respectfully requests that Maple Grove Road be widened to 5 lanes with curb, gutter, sidewalk and bike lanes south of Victory Road to improve mobility in the Southwest, to help alleviate congestion, and to increase safety. It is a priority corridor and is functioning at a LOS F. I appreciate your consideration of the information contained herein as you prepare a draft IFYWP. If you have any questions or need additional detail about the project(s) please do not hesitate to contact me. Sincerely yours,
Megan Basham, AICP Community and Regional Planner
![Page 17: Kent Goldthorpe, President Paul Woods, Vice President ...€¦ · 2016. Project is part of ITD's Strategic Initiatives request for FY2021. ACHD with ITD on any improvement if funded](https://reader030.vdocuments.net/reader030/viewer/2022041118/5f2f3aeb5603fd337e77e47c/html5/thumbnails/17.jpg)
Ada County Courthouse 200 West Front Street Boise ID 83702 208.287.7900 Fax 208.287.7909 www.adacounty.id.gov
Department Divisions Building Engineering & Surveying Permitting Planning & Zoning
Ada County Commissioners Jim Tibbs, First District Rick Yzaguirre, Second District David L. Case, Third District
Megan M. Leatherman, MCRP Director
ADA COUNTY
Development Services Department
April 1, 2016 Ryan Head, AICP Planning Supervisor Ada County Highway District 3775 Adams Street Garden City, ID 83714 RE: Ada County FY 2017-2021 IFYWP Narratives Road &
Intersection #5 – Lake Hazel/Cole Road Intersection and Extension to Orchard Street
Dear Mr. Head: Thank you for the opportunity to describe Ada County’s transportation priorities for the FY17-2021 IFYWP. Ada County respectfully requests that the intersection of Lake Hazel and Cole Road be constructed as well as the extension of Lake Hazel Road over the New York Canal to Orchard Street be built prior to the construction of homes in the Syringa Valley proposed development. Residents in this area are very concerned about the impacts the development will have on the efficiency and safety of the transportation network for cars, bikes and pedestrians. Cole Road from Amity to Victory is already operating at LOS F and the intersection of Cole Road and Victory Road is operating at LOS E. I appreciate your consideration of the information contained herein as you prepare a draft IFYWP. If you have any questions or need additional detail about the project(s) please do not hesitate to contact me. Sincerely yours,
Megan Basham, AICP Community and Regional Planner
![Page 18: Kent Goldthorpe, President Paul Woods, Vice President ...€¦ · 2016. Project is part of ITD's Strategic Initiatives request for FY2021. ACHD with ITD on any improvement if funded](https://reader030.vdocuments.net/reader030/viewer/2022041118/5f2f3aeb5603fd337e77e47c/html5/thumbnails/18.jpg)
Ada County Courthouse 200 West Front Street Boise ID 83702 208.287.7900 Fax 208.287.7909 www.adacounty.id.gov
Department Divisions Building Engineering & Surveying Permitting Planning & Zoning
Ada County Commissioners Jim Tibbs, First District Rick Yzaguirre, Second District David L. Case, Third District
Megan M. Leatherman, MCRP Director
ADA COUNTY
Development Services Department
April 1, 2016 Ryan Head, AICP Planning Supervisor Ada County Highway District 3775 Adams Street Garden City, ID 83714 RE: Ada County FY 2017-2021 IFYWP Narratives Road & Intersection #6 – Orchard Street Extension Dear Mr. Head: Thank you for the opportunity to describe Ada County’s transportation priorities for the FY17-2021 IFYWP. Ada County respectfully requests that the both legs of the Orchard Steet extension (Lake Hazel to Orchard Street and Gowen Road to Pleasant Valley) be constructed prior to the construction of homes in the Syringa Valley proposed development. Residents in this area are very concerned about the impacts the development will have on the efficiency and safety of the transportation network for cars, bikes and pedestrians. The extension of Orchard Road will help to alleviate the pressure on Cole Road and its intersections. Cole Road from Amity to Victory is already operating at LOS F and the intersection of Cole Road and Victory Road is operating at LOS E. I appreciate your consideration of the information contained herein as you prepare a draft IFYWP. If you have any questions or need additional detail about the project(s) please do not hesitate to contact me. Sincerely yours,
Megan Basham, AICP Community and Regional Planner
![Page 19: Kent Goldthorpe, President Paul Woods, Vice President ...€¦ · 2016. Project is part of ITD's Strategic Initiatives request for FY2021. ACHD with ITD on any improvement if funded](https://reader030.vdocuments.net/reader030/viewer/2022041118/5f2f3aeb5603fd337e77e47c/html5/thumbnails/19.jpg)
Ada County Courthouse 200 West Front Street Boise ID 83702 208.287.7900 Fax 208.287.7909 www.adacounty.id.gov
Department Divisions Building Engineering & Surveying Permitting Planning & Zoning
Ada County Commissioners Jim Tibbs, First District Rick Yzaguirre, Second District David L. Case, Third District
Megan M. Leatherman, MCRP Director
ADA COUNTY
Development Services Department
April 1, 2016 Ryan Head, AICP Planning Supervisor Ada County Highway District 3775 Adams Street Garden City, ID 83714 RE: Ada County FY 2017-2021 IFYWP Narratives Road & Intersection #7 – Kuna Railroad Overpass Dear Mr. Head: Thank you for the opportunity to describe Ada County’s transportation priorities for the FY17-2021 IFYWP. The County respectfully requests that an overpass be installed above the railroad track that runs through the City of Kuna. An overpass will provide residents and emergency responders with the ability to cross the railroad as trains pass through or stop on the tracks. This request is made in support of the City of Kuna. I appreciate your consideration of the information contained herein as you prepare a draft IFYWP. If you have any questions or need additional detail about the project(s) please do not hesitate to contact me. Sincerely yours,
Megan Basham, AICP Community and Regional Planner
![Page 20: Kent Goldthorpe, President Paul Woods, Vice President ...€¦ · 2016. Project is part of ITD's Strategic Initiatives request for FY2021. ACHD with ITD on any improvement if funded](https://reader030.vdocuments.net/reader030/viewer/2022041118/5f2f3aeb5603fd337e77e47c/html5/thumbnails/20.jpg)
Ada County Courthouse 200 West Front Street Boise ID 83702 208.287.7900 Fax 208.287.7909 www.adacounty.id.gov
Department Divisions Building Engineering & Surveying Permitting Planning & Zoning
Ada County Commissioners Jim Tibbs, First District Rick Yzaguirre, Second District David L. Case, Third District
Megan M. Leatherman, MCRP Director
ADA COUNTY
Development Services Department
April 1, 2016 Ryan Head, AICP Planning Supervisor Ada County Highway District 3775 Adams Street Garden City, ID 83714 RE: Ada County FY 2017-2021 IFYWP Narratives Road &
Intersection #8 – Linder Road Overpass, Overland Road / Franklin Road
Dear Mr. Head: Thank you for the opportunity to describe Ada County’s transportation priorities for the FY17-2021 IFYWP. In 2011, Ada County requested that installation of the Linder Road Overpass be advanced in priority. Moving this project up in priority will help alleviate traffic on north-south corridors as well as east-west corridors such as Chinden Blvd (SH-20/26) and State St (SH-44). This request is made in support of the City of Meridian. I appreciate your consideration of the information contained herein as you prepare a draft IFYWP. If you have any questions or need additional detail about the project(s) please do not hesitate to contact me. Sincerely yours,
Megan Basham, AICP Community and Regional Planner
![Page 21: Kent Goldthorpe, President Paul Woods, Vice President ...€¦ · 2016. Project is part of ITD's Strategic Initiatives request for FY2021. ACHD with ITD on any improvement if funded](https://reader030.vdocuments.net/reader030/viewer/2022041118/5f2f3aeb5603fd337e77e47c/html5/thumbnails/21.jpg)
Ada County Courthouse 200 West Front Street Boise ID 83702 208.287.7900 Fax 208.287.7909 www.adacounty.id.gov
Department Divisions Building Engineering & Surveying Permitting Planning & Zoning
Ada County Commissioners Jim Tibbs, First District Rick Yzaguirre, Second District David L. Case, Third District
Megan M. Leatherman, MCRP Director
ADA COUNTY
Development Services Department
April 1, 2016 Ryan Head, AICP Planning Supervisor Ada County Highway District 3775 Adams Street Garden City, ID 83714 RE: Ada County FY 2017-2021 IFYWP Narratives Road &
Intersection #9 – Traffic Control Signal at Midway Drive and Glenwood Street
Dear Mr. Head: Thank you for the opportunity to describe Ada County’s transportation priorities for the FY17-2021 IFYWP. The County respectfully requests that a traffic control signal be installed at the intersection of Midway Drive and Glenwood Street to increase safety for visitors of Idaho Expo turning left onto Glenwood Street. I appreciate your consideration of the information contained herein as you prepare a draft IFYWP. If you have any questions or need additional detail about the project(s) please do not hesitate to contact me. Sincerely yours,
Megan Basham, AICP Community and Regional Planner
![Page 22: Kent Goldthorpe, President Paul Woods, Vice President ...€¦ · 2016. Project is part of ITD's Strategic Initiatives request for FY2021. ACHD with ITD on any improvement if funded](https://reader030.vdocuments.net/reader030/viewer/2022041118/5f2f3aeb5603fd337e77e47c/html5/thumbnails/22.jpg)
Attachment 2
City of Boise 2016 Requests and ACHD Proposed Response
In IFYWP
(Page)DSN YR ROW YR CN YR
Total Cost
in MillionsProgramming Notes
LTP LTP RD208‐
07
State St, 36th St / 27th
St
Widen State St to 7 lanes with HOV/transit lanes, curb, gutter, sidewalk and
bike lanes, in accordance with the State St TTOP and the 2012 CIP. This
project may include an access management component.
Yes (38) UF UF UF $5.01 Project will advance when land use, transit and
roadway triggers are met as per the State
Street TTOP.
LTP LTP RD208‐
06
State St, Collister Dr /
36th St
Widen State St to 7 lanes with HOV/transit lanes, curb, gutter, sidewalk and
bike lanes, in accordance with the State St TTOP and the 2012 CIP. This
project may include an access management component.
Yes (38) UF UF UF $10.12 Project will advance when land use, transit and
roadway triggers are met as per the State
Street TTOP.
LTP LTP RD208‐
05
State St, Pierce Park Ln
/ Collister Dr
Widen State St to 7 lanes with HOV/transit lanes, curb, gutter, sidewalk and
bike lanes, in accordance with the State St TTOP and the 2012 CIP. This
project may include an access management component.
Yes (39) UF UF UF $6.67 Project will advance when land use, transit and
roadway triggers are met as per the State
Street TTOP.
LTP LTP RD208‐
04
State St, Glenwood St /
Pierce Park Ln
Widen State St to 7 lanes with HOV/transit lanes, curb, gutter, sidewalk and
bike lanes, in accordance with the State St TTOP and the 2012 CIP. This
project may include an access management component.
Yes (38) UF UF UF $1.28 Project will advance when land use, transit and
roadway triggers are met as per the State
Street TTOP.
1 1 IN205‐
112
State St and Veterans
Memorial Pkwy
Widen intersection in accordance with the State St/Veterans Memorial
Pkwy/36th St Intersection Concept Study, including installation of median U‐
turns and installation of two‐phased pedestrian crossings. Project identified
as a key piece of the State St TTOP.
Yes (46) Done 2016‐
2017
2018 $10.08 To be built in FY2018.
2 2 IN203‐
21
State St and Collister
Dr
Federal aid project to improve the intersection of State St and Collister Dr,
including realignment of the Collister Dr leg, curb, gutter, sidewalk, and bike
lanes in accordance with the State St TTOP and the 2012 CIP. Project includes
replacing bridge #090B.
Yes (45) 2015‐
2016
2016 2018 $9.36 Federal CN funding in 2018.
Actual construction to occur in
2019.
To be built in FY2019.
3 3 IN207‐
03
State St and Glenwood
St
Widen and modify intersection in order to improve traffic and transit
operations in accordance with the State St TTOP and the 2012 CIP. Joint
project with ITD.
Yes (46) 2018 2019 PD $3.31 Project to be delayed during IFYWP update.
ACHD requested project from ITD in spring
2016. Project not on ITD's planned projects at
this time. ACHD will continue to pursue project
with ITD and develop concept when
construction funding is more eminent.
4 4 IN210‐
03
State St and Pierce
Park Ln
Widen intersection to 3 lanes on Pierce Park and 7 lanes on State St, including
curb, gutter, sidewalk, and bike lanes in accordance with the State St TTOP
and the 2012 CIP.
Yes (46) 2019 2020 PD $4.08 Concept design to begin in FY2017. ACHD to
evaluate project construction moving forward
through IFYWP update.
ACHD Proposed Response
2016 City
Priority
Ranking
2015 City
Priority
Ranking
GIS # ACHD Project Name Project Description
Current Programming Status
LTP ‐ Long Term Priority
PD ‐ Preliminary Development
CN ‐ Construction Year Page 1 of 10
![Page 23: Kent Goldthorpe, President Paul Woods, Vice President ...€¦ · 2016. Project is part of ITD's Strategic Initiatives request for FY2021. ACHD with ITD on any improvement if funded](https://reader030.vdocuments.net/reader030/viewer/2022041118/5f2f3aeb5603fd337e77e47c/html5/thumbnails/23.jpg)
Attachment 2
In IFYWP
(Page)DSN YR ROW YR CN YR
Total Cost
in MillionsProgramming Notes
ACHD Proposed Response
2016 City
Priority
Ranking
2015 City
Priority
Ranking
GIS # ACHD Project Name Project Description
Current Programming Status
5 6 IN213‐
01
Fairview Ave and Cole
Rd
Widen intersection to 8 lanes on Fairview Ave and 7 lanes on Cole Rd,
including curb, gutter, sidewalk, and bike lanes in accordance with the 2012
CIP. Project includes non‐traversable raised medians.
Yes (44) Done 2016 2017 $4.97 To be built in FY2017.
6 7 SM215 ‐
SM220
Downtown Boise
Implementation Plan
(DBIP)
Perform road rehabilitation and 2‐way conversion of select streets in
downtown Boise in concert with CCDC and other projects in accordance with
the Downtown Boise Implementation Plan.
Yes (83‐
85)
Varies Varies Varies $12.99 Ongoing construction to continue through
FY2020. City's request for bike facilities and 2‐
way 5th and 6th streets under evaluation.
These treatments, if approved, to be installed
with planned maintenance work.
7 8 CM212‐
08
Emerald St and
Americana Blvd,
Orchard St / Ann
Morrison Park
Entrance
Reconfigure Emerald St and Americana Blvd to add continuous bike lanes and
complete the sidewalk on both sides of Emerald St in accordance with the
Central Bench Neighborhood Plan.
Yes
(129)
2016 2016 2017 $1.49 To be built in FY2017.
8 9 1180‐
705
Fairview Ave and Main
St, Whitewater Park
Blvd / 16th St
Restripe to add on‐street parking by removing a travel lane. No TBD Fairview‐Main Local Streets Improvement Plan
is underway. This plan is exploring the
feasibility and future cross section of Fairview
and Main. The adopted study will inform
future programming and construction.
9a 10 1180‐
705
Orchard St, Chinden St
/ Overland Rd
Convert 4 lanes to 3 lanes and add bike lanes. No TBD As per the City's request, during the FY2017
Budget process, ACHD will propose delaying its
planned Orchard Street Operational Analysis
project until after the City completes its
planning work. Lane reconfiguration feasibility
to be explored through Operational Analysis
when completed.
9b 11 1180‐
705
Orchard St, Emerald St
/ Morris Hill Rd
Develop concept plan to construct a complete street. No TBD As per the City's request, during the FY2017
Budget process, ACHD will propose delaying its
planned Orchard Street Operational Analysis
project until after the City completes its
planning work.
10 13 IN205‐
95
Broadway Ave/Avenue
B and Idaho St/Warm
Springs Ave
Widen and/or modify intersection to improve safety and reduce congestion
for all users in accordance with the 2012 CIP. Design, right‐of‐way, and
construction costs are tentative until completion of the concept design.
Project includes bridge #549.
Yes (42) 2017 2018 2019 $1.54 Costs based on
implementation of CIP.
Concept design underway. Adopted concept
will drive what is ultimately implemented.
11 14 IN215‐
14
Fort St / Hays St / 5th
St
Improve intersection for pedestrians, bicyclists, and motorists. (The City
requests ACHD put its current accessible pedestrian signal project on hold
pending completion of the 2‐way conversion evaluation of 5th St.)
Yes
(112)
2016 N/A 2017 $0.14 ACHD to evaluate potential delay of APS
project during budgeting and IFYWP update.
Outcome is dependent on 5th/6th 2‐way
conversion analysis.
LTP ‐ Long Term Priority
PD ‐ Preliminary Development
CN ‐ Construction Year Page 2 of 10
![Page 24: Kent Goldthorpe, President Paul Woods, Vice President ...€¦ · 2016. Project is part of ITD's Strategic Initiatives request for FY2021. ACHD with ITD on any improvement if funded](https://reader030.vdocuments.net/reader030/viewer/2022041118/5f2f3aeb5603fd337e77e47c/html5/thumbnails/24.jpg)
Attachment 2
In IFYWP
(Page)DSN YR ROW YR CN YR
Total Cost
in MillionsProgramming Notes
ACHD Proposed Response
2016 City
Priority
Ranking
2015 City
Priority
Ranking
GIS # ACHD Project Name Project Description
Current Programming Status
12 15 N/A 32nd St, Moore
St/Whitewater Park
Blvd
Extend roadway. No N/A Defer for completion as part of a future
development application.
13 16 N/A 28th St, Main
St/Fairview Ave
Extend roadway. No TBD Defer for completion as part of a future
development application. Future location
being evaluated as part of the Fairview‐Main
Local Streets Improvement Plan.
14 17 CM215‐
27
Beacon St, Boise Ave /
Broadway Ave
Reconfigure travel lanes from 4‐lanes to 3‐lanes with bike lanes. Add refuge
medians and pedestrian crossings.
No TBD Defer pending ongoing discussions with Boise
State and their long range Master Plan.
15 21 RC0087 Cloverdale Rd,
Fairview Ave / Ustick
Rd
Widen Cloverdale Rd to 5 lanes with curb, gutter, sidewalk and bike lanes, in
accordance with the Cloverdale Rd Concept Design and the 2012 CIP. Project
includes bridge #472.
Yes (31) Done 2016 2018 $3.40 To be built in FY2018.
16 22 RC0092 Cloverdale Rd, Ustick
Rd / McMillan Rd
Widen Cloverdale Rd to 5 lanes with curb, gutter, sidewalk and bike lanes, in
accordance with the Cloverdale Rd Concept Design and the 2012 CIP.
Yes (32) 2016 2017 2019 $4.00 To be built in FY2019.
17 23 RD207‐
16,
IN203‐
14
Cole Rd, I‐84 / Franklin
Rd and Cole Rd and
Franklin Rd
Widen Cole Rd to 5 lanes with curb, gutter, sidewalk and bike lanes in
accordance with the Cole Rd Concept Design and the 2012 CIP. Project to be
constructed concurrently with Cole/Franklin and Cole/McMullen
intersections. Project includes bridge #281.
Yes (33,
43)
Done 2016‐
2017
2019 $10.55 To be built in FY2019.
18 24 RD207‐
22
Maple Grove Rd,
Victory Rd / Overland
Rd
Widen Maple Grove Rd to 5 lanes with curb, gutter, sidewalk, and bike lanes
in accordance with the 2012 CIP. Project includes bridges #267P, #268, and
#269P.
Yes (36) 2016 2017 2020 $4.94 To be built in FY2020.
19 25 RD207‐
21
Maple Grove Rd, Amity
Rd / Victory Rd
Widen Maple Grove Rd to 5 lanes with curb, gutter, sidewalk, and bike lanes
in accordance with the 2012 CIP. Project includes bridge #269A.
Yes (35) 2020 PD PD $3.47 Programmed to begin design in FY2020. ACHD
to evaluate project construction moving
forward through IFYWP update.
20 26 RD207‐
13
Cloverdale Rd,
McMillan Rd / Chinden
Blvd (US 20/26)
Widen Cloverdale Rd to 5 lanes with curb, gutter, sidewalk and bike lanes, in
accordance with the Cloverdale Rd Concept Design and the 2012 CIP.
Project includes bridge #137A.
Yes (32) 2018 2019 2020 $4.33 To be built in FY2020.
21 27 RD207‐
11
Cloverdale Rd, Victory
Rd / Overland Rd
Widen to 5 lanes with curb, gutter, sidewalk and bike lanes in accordance
with 2012 CIP.
No $6.51 Prioritized. ACHD to evaluate potential
programming during IFYWP update.
22 28 IN205‐
97
Cole Rd and Victory Rd Widen intersection in accordance with the 2012 CIP and widen Cole Rd south
to McGlochlin St to 5 lanes with bike lanes, sidewalks and/or asphalt
pathways in accordance to the 2012 CIP. Project includes bridge #282.
Yes (43) 2017 2019 2020 $5.59 To be built in FY2020.
23 29 N/A Warm Springs Avenue,
near the Mesa
Rock fall mitigation. No N/A Defer until long‐term effectiveness of spring
2015 improvements can be evaluated.
LTP ‐ Long Term Priority
PD ‐ Preliminary Development
CN ‐ Construction Year Page 3 of 10
![Page 25: Kent Goldthorpe, President Paul Woods, Vice President ...€¦ · 2016. Project is part of ITD's Strategic Initiatives request for FY2021. ACHD with ITD on any improvement if funded](https://reader030.vdocuments.net/reader030/viewer/2022041118/5f2f3aeb5603fd337e77e47c/html5/thumbnails/25.jpg)
Attachment 2
In IFYWP
(Page)DSN YR ROW YR CN YR
Total Cost
in MillionsProgramming Notes
ACHD Proposed Response
2016 City
Priority
Ranking
2015 City
Priority
Ranking
GIS # ACHD Project Name Project Description
Current Programming Status
24 30 1180‐
705
S. Orchard St
Realignment, Gowen
Rd/Victory Rd
New alignment. No TBD Alignment study to be completed in FY2017.
25 31 MI215‐
01
Barber Dr Bridge #366,
1.0 miles NW/O Warm
Springs Blvd
Replace/widen bridge #366 over Warm Springs Creek on Barber Dr as part of
ACHD's Bridge Maintenance Program.
Yes (54) 2019 N/A 2020 $0.38 To be built in FY2020. Based on ACHD
Commission direction, ACHD to evaluate
advacing project construction during IFYWP
update.
Community Programs
1 1 MMP21
4‐02
Capitol Blvd and
Crescent Rim Dr, Yale
Ln/Eastover Ter
Improve bike and pedestrian connection. No TBD Concept evaluation underway. Project to be
programmed once alternative is selected.
2 2 CM210‐
25
Camas St, Orchard St /
Roosevelt St
Construct sidewalk on both sides of Camas Street from Orchard Street to
Roosevelt Street in accordance with the Central Bench Neighborhood Plan.
Project to include roadway reclamation.
Yes
(107)
2016 2016 2017 $1.17 To be built in FY2017.
3 3 CM214‐
18
Orchard St and Alpine
St Pedestrian Crossing
Install an enhanced pedestrian crossing at the intersection. No TBD Location does not currently meet warrants.
ACHD to reevaluate warrants upon completion
of the Alpine sidewalk project in FY2017.
4 4 CM214‐
21
Phillippi St, Overland
Rd / Franklin Rd
(Overland Rd/Phillippi
St Pedestrian Signal)
Rebuild roadway to include 8' detached sidewalk, parking, 5' bike lanes, 2
auto lanes, and a center turn land/island. Full rebuild of roadway required
due to steep cross slope issues. Includes pedestrian signal at Phillippi St /
Overland Rd intersection on west side and replacement of bridge #1366 or
#404.
No TBD Scoped in 2015. Further refinement of scope
underway due to high cost associated with
sidewalk project and roadway crown issues.
5 5 CM212‐
08
Emerald St and
Americana Blvd,
Orchard St / Ann
Morrison Park
Entrance
Reconfigure Emerald St and Americana Blvd to add continuous bike lanes and
complete the sidewalk on both sides of Emerald St in accordance with the
Central Bench Neighborhood Plan.
Yes
(129)
2016 2016 2017 $1.49 To be built in FY2017.
6 6 CM211‐
38
Kootenai St, Vista Ave
/ Federal Way
Construct curb, gutter, sidewalks and bike lanes on both sides of Kootenai St
from Vista Ave to Federal Way in accordance with the Central Bench
Neighborhood Plan. Project includes removal of on‐street parking.
Yes
(115)
Done 2016 2017 $0.84 To be built in FY2017.
7 7 PPI208‐
15
Victory Rd, Virginia
Ave / Federal Way
Construct sidewalk on both sides of Victory Rd, between Virginia Ave and
Federal Way. Improve rail crossing.
No $2.04 Scoped ‐ High cost project. Programming
pending Kootenai and Overland crossings to
improve coordination with Union Pacific.
LTP ‐ Long Term Priority
PD ‐ Preliminary Development
CN ‐ Construction Year Page 4 of 10
![Page 26: Kent Goldthorpe, President Paul Woods, Vice President ...€¦ · 2016. Project is part of ITD's Strategic Initiatives request for FY2021. ACHD with ITD on any improvement if funded](https://reader030.vdocuments.net/reader030/viewer/2022041118/5f2f3aeb5603fd337e77e47c/html5/thumbnails/26.jpg)
Attachment 2
In IFYWP
(Page)DSN YR ROW YR CN YR
Total Cost
in MillionsProgramming Notes
ACHD Proposed Response
2016 City
Priority
Ranking
2015 City
Priority
Ranking
GIS # ACHD Project Name Project Description
Current Programming Status
8 8 CM210‐
70
Overland Rd,
Columbus St / Federal
Way
Complete curb, gutter and sidewalk on both sides of Overland Rd, between
Columbus St and Federal Way in accordance with the Central Bench
Neighborhood Plan. Includes an improved UPRR crossing.
Yes
(118)
2016 2016 2018 $1.11 To be built in FY2018.
9 9 CM214‐
19
McMillan Rd Refuge
Medians, Eagle Rd /
Cloverdale Rd
Install pedestrian refuge islands at locations along McMillan Rd, between
Eagle Rd and Cloverdale at locations to be determined. Design and
construction will be programmed once locations are identified.
Yes
(117)
TBD ACHD Traffic Engineering has determined that
additional crossing treatments are not
warranted at this time. One installed with
Eagle/ McMillan intersection project. Addition
signalized crossing exists.
10 10 CGSP20
7‐02
Collister Dr, Hillside
Ave / Briarhill Dr
Construct curb, gutter and sidewalk on the east side of Collister Dr
connecting with the existing sidewalk south of Hillside Ave and at Briarhill Dr
in order to improve neighborhood connectivity and pedestrian safety.
Yes
(109)
2016 2017 2019 $0.38 Currently to be built in FY2019. ACHD to
investigate advancing project to align with
planned maintenance during IFYWP update.
11 NEW Columbus St Bikeway,
Canal St / Kootenai St
Improve Columbus St as a bikeway to include way finding signs and/or shared
lane markings in accordance with the Central Bench Neighborhood Plan.
Concept design will further clarify project scope.
No TBD Prioritize and scope.
12 NEW Spaulding St, Vista Ave
/ Columbus St
Construct curb, gutter, and sidewalk on both sides of Spaulding St between
Vista Ave and Columbus St in accordance with the City of Boise's Energize
Vista Neighborhood effort.
No TBD Prioritize and scope.
13 NEW Malad St, Kerr St /
Vista Ave
Construct curb, gutter, and sidewalk on the north side of Malad St between
Kerr St and Vista Ave in accordance with the City of Boise's Energize Vista
Neighborhood effort.
No TBD Prioritize and scope.
14 NEW Annett St, Malad St /
Targee St
Construct curb, gutter, and sidewalk on the west side of Annett St between
Malad St and Targee St in accordance with the Central Bench Neighborhood
Plan.
No TBD Prioritize and scope.
15 11 BIK213‐
03
Leadville Ave Bikeway,
Linden St / Greenbelt
Improve Leadville Ave as a bikeway to include enhanced crossing at Boise
Ave, shared lane markings, possible modification of two‐way stop control at
Iowa, Pennsylvania, Warren, Highland, and Rossi, and traffic calming in
accordance with the Southeast Boise Neighborhood Plan.
Yes
(126)
2017 2018 2020 $0.24 To be built in FY2020.
16 12 CM210‐
50
Cole Rd, Kettering Ave
/ Mountain View Dr
Construct curb, gutter, and sidewalk on both sides of Cole Rd between
Kettering Ave and Mountain View Dr in accordance with the West Bench
Neighborhood Plan.
Yes
(109)
2016 2016 2018 $0.72 To be built in FY2018.
17 13 CGS205‐
20
Columbus St, Overland
Rd / Kootenai St
Construct curb, gutter and sidewalk on both sides of Columbus St from
Overland Rd to Kootenai St in accordance with the Central Bench
Neighborhood Plan.
Yes
(110)
2016 2017 2019 $1.40 To be built in FY2019.
18 NEW Latah St Bikeway,
Targee St / Overland
Rd
Improve Latah St as a bikeway to include way finding signs and/or shared
lane markings in accordance with the City of Boise's Energize Vista
Neighborhood effort. Concept design will further clarify project scope.
No TBD Prioritize and scope.
LTP ‐ Long Term Priority
PD ‐ Preliminary Development
CN ‐ Construction Year Page 5 of 10
![Page 27: Kent Goldthorpe, President Paul Woods, Vice President ...€¦ · 2016. Project is part of ITD's Strategic Initiatives request for FY2021. ACHD with ITD on any improvement if funded](https://reader030.vdocuments.net/reader030/viewer/2022041118/5f2f3aeb5603fd337e77e47c/html5/thumbnails/27.jpg)
Attachment 2
In IFYWP
(Page)DSN YR ROW YR CN YR
Total Cost
in MillionsProgramming Notes
ACHD Proposed Response
2016 City
Priority
Ranking
2015 City
Priority
Ranking
GIS # ACHD Project Name Project Description
Current Programming Status
19 14 BK215‐
01
Owyhee St bikeway,
Elder St / Alpine St
(Bikeway parallel to
Vista)
Improve Owyhee St as a bikeway to include way finding signs, shared lane
markings, and enhanced crossing at Rose Hill in accordance with the Central
Bench Neighborhood Plan. Concept design will further clarify project scope.
Yes
(127)
2019 2020 PD $0.12 Concept design to begin in FY2018. ACHD to
evaluate potential opportunities to advance
construction during IFYWP update.
20 14 BK213‐
04
Shoshone St Bikeway,
Linden St / Greenbelt
(Bikeway parallel to
Vista)
Improve Shoshone St as a bikeway to include wayfinding signage, shared lane
markings, signal modification at Overland Rd, and pedestrian ramps in
accordance with the Central Bench Neighborhood Plan. Project includes an
enhanced pedestrian signal to replace existing flashing caution light at Rose
Hill St. Concept design will further clarify project scope.
Yes
(127)
2020 PD PD $0.12 Concept design to begin in FY2018. ACHD to
evaluate potential opportunities to advance
construction during IFYWP update.
21 15 N/A East‐West Bikeway,
Ave B/Whitewater
Park Blvd
Wayfinding signage and arterial crossings. No TBD ACHD to identify route through Downtown
Boise Implementation projects and the
Fairview‐Main Local Streets Improvement Plan
(underway).
22 16 CM211‐
57
Columbia Village
Bikeway to Amity Rd
See description under City priority #18 below. Yes
(113)
2016 2017 2019 $0.25 Project to be completed as part of City priority
#24.
23 17 CM210‐
89
Heron St, 13th St / 9th
St (north side)
Construct curb, gutter, parking and detached concrete pathway on north side
of Heron St. from 13th St. to 9th St. Project includes a full road rebuild due to
poor pavement condition.
Yes
(113)
2016 N/A 2018 $0.54 To be built in FY2018.
24 18 CM211‐
57
Holcomb Rd, Mimosa
Way / Amity Rd
Construct detached 5’ sidewalk on the east side of Holcomb Rd between
Mendota Dr and Amity Rd in accordance with the Southeast Boise
Neighborhood Plan. Stripe bike lane and install wayfinding signage for a bike
facility from Amity to Mimosa Way. Project will provide ped/bike connection
from Oregon Trail Heights/Columbia Village to Holcomb path/bridge and
Southeast Boise.
Yes
(113)
2016 2017 2019 $0.25 To be built in FY2019.
25 19 CM212‐
07
Alpine St, Orchard St /
Randall St
Complete sidewalk on the south side of Alpine St from Orchard St to Randall
St in accordance with the Central Bench Neighborhood Plan.
Yes
(104)
2016 2016 2017 $0.64 To be built in FY2017.
26 20 NE204.0
1
Phillippi St, Malad St /
Targee St
Complete curb, gutter and sidewalk improvements on both sides of Phillippi
St, between Malad St and Targee St in accordance with the Central Bench
Neighborhood Plan.
Yes
(119)
2016 2017 2019 $0.26 To be built in FY2019.
27 21 CM210‐
49
Phillippi St, Targee St /
Overland Rd
Construct curb, gutter and sidewalk on both the sides of Phillippi St, between
Targee St and Overland Rd in accordance with the Central Bench
Neighborhood Plan. Project includes full road rehabilitation.
Yes
(119)
2017 2019 2020 $2.13 To be built in FY2020.
LTP ‐ Long Term Priority
PD ‐ Preliminary Development
CN ‐ Construction Year Page 6 of 10
![Page 28: Kent Goldthorpe, President Paul Woods, Vice President ...€¦ · 2016. Project is part of ITD's Strategic Initiatives request for FY2021. ACHD with ITD on any improvement if funded](https://reader030.vdocuments.net/reader030/viewer/2022041118/5f2f3aeb5603fd337e77e47c/html5/thumbnails/28.jpg)
Attachment 2
In IFYWP
(Page)DSN YR ROW YR CN YR
Total Cost
in MillionsProgramming Notes
ACHD Proposed Response
2016 City
Priority
Ranking
2015 City
Priority
Ranking
GIS # ACHD Project Name Project Description
Current Programming Status
28 22 CM210‐
24
Clark St, Orchard St /
Roosevelt St
Construct sidewalk on both sides of Clark St between Orchard St and
Roosevelt St to provide pedestrian connectivity and reduce the need for
safety busing for Monroe Elementary School.
Yes
(108)
2015‐
2016
2016 2018 $1.00 To be built in FY2018.
29 24 CM213‐
38
Jefferson St,
Whitewater Park Blvd
/ 27th St
Complete curb, gutter, and sidewalk on both sides of Jefferson St east of
Whitewater Park Blvd where gaps currently exist in accordance with Boise'
30th Area Master Plan. Project includes road rehabilitation.
Yes
(114)
2016 2016 2017 $0.17 To be built in FY2017.
30 25 CM213‐
39
Madison Ave,
Whitewater Park Blvd
/ 27th St
Complete curb, gutter, and sidewalk on both sides of Madison St, between
Whitewater Park Blvd and 27th St in accordance with the City of Boise's 30th
St Area Master Plan. Project will create standard parallel parking between
Whitewater Park Blvd and 30th St. Project also includes full road
rehabilitation.
Yes
(117)
2016 2016 2017 $0.13 To be built in FY2017.
31 26 CM215‐
28
Coston St, Bannock St
/ Franklin St
Construct sidewalk on the west side of Coston St between Bannock St and
Franklin St. (City's request was for sidewalk on both sides. Working in
coordination with the City Forester, project will only construct sidewalks on
the west side due to landscape/tree impacts.)
No $0.23 Scoped "Go" in 2015. ACHD to evaluate
potential programming during IFYWP update.
32 27 CM213‐
40
Peasley St / Alpine St
(Railroad Crossing)
Extend railroad crossing planking to the east side for a pedestrian crossing.
Extend detached sidewalk with swales to intersection from existing sidewalk
on the northeast side of the crossing.
No $0.15 Scoped "Go" in 2015. ACHD to evaluate
potential programming during IFYWP update.
33 28 PPI209‐
05
Cherry Ln, Owyhee St /
Vista Ave
Complete sidewalk on the south side of Cherry Ln between Owyhee St and
Vista Ave in accordance with the Central Bench Neighborhood Plan.
Yes
(108)
PD PD PD $0.77 All project phases currently in preliminary
development. ACHD to evaluate project
construction moving forward through IFYWP
update.
34 29 PPI208‐
22
Garden St, Franklin Rd
/ Emerald St
Construct curb, gutter and sidewalk on both sides of Garden Street from
Emerald St to Franklin Road to provide pedestrian connectivity in an
established neighborhood. Fill in the missing sidewalk across 2 lots on the
northwest corner of Emerald.
No $2.57 Scoped in 2011. ACHD to evaluate potential
programming during IFYWP update. Delay in
programming due to high project cost.
35 30 CM210‐
18
Eckert Rd and Arrow
Junction Dr Pedestrian
Crossing (Eckert Rd,
Boise Ave / Arrow
Junction Dr)
Install a striped crosswalk and pedestrian ramps at the intersection. (City's
request was for sidewalks on the east side. Sidewalks already exist on the
west side with only one house on the east side.)
No $0.06 Pedestrian signal scoped "Go" in 2015. ACHD
to evaluate potential programming during
IFYWP update.
LTP ‐ Long Term Priority
PD ‐ Preliminary Development
CN ‐ Construction Year Page 7 of 10
![Page 29: Kent Goldthorpe, President Paul Woods, Vice President ...€¦ · 2016. Project is part of ITD's Strategic Initiatives request for FY2021. ACHD with ITD on any improvement if funded](https://reader030.vdocuments.net/reader030/viewer/2022041118/5f2f3aeb5603fd337e77e47c/html5/thumbnails/29.jpg)
Attachment 2
In IFYWP
(Page)DSN YR ROW YR CN YR
Total Cost
in MillionsProgramming Notes
ACHD Proposed Response
2016 City
Priority
Ranking
2015 City
Priority
Ranking
GIS # ACHD Project Name Project Description
Current Programming Status
36 31 CGSP20
5‐16
Liberty St, Emerald
St/Franklin Rd
Complete sidewalk on the east side of Liberty St in accordance with the
Central Bench Neighborhood Plan. (City request was for sidewalk on both
sides.)
Yes
(116)
2016 2017 2019 $0.54 Project scope originally assumed completion of
bridge and RRX widening to occur with
improvements at Liberty and Franklin
intersection. That project did not move
forward, thus placing much added expense
($2.5 million) to sidewalk project. Project will
be pushed back in IFYWP update until bridge
widening can be completed.
37 32 N/A Vista Neighborhood
Local Streets
Install curb, gutter, and/or innovative storm drainage on local streets. No TBD Energize Vista Transportation Group did not
identify as a priority. Further exploration of
project scope with City is desired.
38 33 CM214‐
47
Vista Ave and
Spaulding St
Pedestrian Signal
Install an enhanced pedestrian crossing on Vista Ave at Spaulding St, including
bike push buttons.
Yes
(122)
2019 2019 2020 $0.26 At City's request, ACHD to place pedestrian
signal at Spaulding St, in lieu of at Nez Perce St.
To be built in FY2020.
39 NEW Vista Ave Traffic
Calming, Elder St /
Rose Hill St
Explore opportunities to reduce vehicle speeds along Vista Ave, between
Elder St and Rose Hill St by narrowing travel lanes, providing bike lanes, or
other traffic calming measures.
No TBD ACHD Traffic Engineering to evaluate potential
opportunities for traffic calming.
40 NEW Cleveland St, Palouse
St / Nez Perce St
Construct curb, gutter, and sidewalk on both sides of Cleveland St between
Palouse St and Nez Perce St in accordance with the City of Boise's Energize
Vista Neighborhood effort.
No TBD Prioritize and scope.
41 NEW Palouse St, Roosevelt
St / Cleveland St
Construct curb, gutter, and sidewalk on both sides of Palouse St between
Roosevelt St and Cleveland St in accordance with the City of Boise's Energize
Vista Neighborhood effort.
No TBD Prioritize and scope.
42 NEW Hervey St, Cherry Ln /
Lemhi St
Construct curb, gutter, and sidewalk on the west side of Hervey St between
Cherry Ln and Lemhi St in accordance with the City of Boise's Energize Vista
Neighborhood effort.
No TBD Prioritize and scope.
43 34 CM215‐
29
State St and Wylie Ln
Pedestrian Crossing
Install an enhanced pedestrian crossing on State St on the east side of Wylie
Ln.
No $0.30 Scoped "Go" in 2015. ACHD to evaluate
potential programming during IFYWP update.
44 35 CM213‐
53
Ash Park St, Northview
Rd / Ustick Rd
Complete sidewalk on both sides of Ash Park Lane between Northview St and
Ustick Rd in accordance with the West Bench Neighborhood Plan. (City
requested sidewalk and bikeway.)
Yes
(104)
2016 2017 2019 $0.56 To be built in FY2019.
45 36 CM214‐
21
Phillippi St, Overland
Rd / Cassia St
Rebuild roadway to include 8' detached sidewalk, parking, 5' bike lanes, 2
auto lanes, and a center turn land/island. Full rebuild of roadway required
due to steep cross slope issues. Includes pedestrian signal at Phillippi St /
Overland Rd intersection on west side and replacement of bridge #1366 or
#404.
No TBD Scoped in 2015. Further refinement of scope
underway due to high cost associated with
sidewalk project and roadway crown issues.
LTP ‐ Long Term Priority
PD ‐ Preliminary Development
CN ‐ Construction Year Page 8 of 10
![Page 30: Kent Goldthorpe, President Paul Woods, Vice President ...€¦ · 2016. Project is part of ITD's Strategic Initiatives request for FY2021. ACHD with ITD on any improvement if funded](https://reader030.vdocuments.net/reader030/viewer/2022041118/5f2f3aeb5603fd337e77e47c/html5/thumbnails/30.jpg)
Attachment 2
In IFYWP
(Page)DSN YR ROW YR CN YR
Total Cost
in MillionsProgramming Notes
ACHD Proposed Response
2016 City
Priority
Ranking
2015 City
Priority
Ranking
GIS # ACHD Project Name Project Description
Current Programming Status
46 37 CM213‐
52
Allumbaugh St,
Fairview
Ave/Northview St
Complete curb, gutter, and sidewalk on the west side of Allumbaugh St,
between Fairview Ave and Northview St. (City requested sidewalk on both
sides. Sidewalk on east side infeasible at this time due to significant land use,
utility, and drainage impacts.)
No $0.98 Scoped "Go" in 2015. ACHD to evaluate
potential programming during IFYWP update.
47 NEW Grand St, Miller St, and
Ash St Pedestrian
Enhancements
Fix hazardous sidewalks, construct ADA compliant pedestrian ramps, and fill
sidewalk gaps where appropriate.
No TBD Prioritize and scope.
48 NEW 10th St and Myrtle St Construct a new intersection at 10th St and Myrtle St. No TBD Requires coordination with
ITD.
Prioritize and scope.
49 38 CM214‐
28
De Meyer St,
Cloverdale Rd / Lena
Ave; Lena Ave, De
Meyer St / Arlen St
Complete sidewalk on the south side of DeMeyer St by narrowing the
roadway and constructing sidewalk on the inside of existing curb. Construct
at‐grade sidewalks through asphalt eyebrows to connect sidewalk segments.
Install bikeway (signage, pavement markings) from Demeyer / Cloverdale to
Lena / Arlen.
No $0.26 Scoped "Go" in 2015. ACHD to evaluate
potential programming during IFYWP update.
50 39 CM214‐
23
Cassia St, Franklin Park
Dr / Troxel Dr
Complete sidewalk on the north side of Cassia St, between Franklin Park Dr
and Troxel Dr. Install bike lanes from Franklin Park Dr to Curtis Rd. Install an
enhanced pedestrian crossing (rectangular rapid flashing beacon) at Cassia St
and Troxel on the west side of the intersection at an existing crosswalk.
No $0.24 Scoped "Go" in 2015. ACHD to evaluate
potential programming during IFYWP update.
51 40 CM215‐
30
Amity Rd, Federal Way
/ Holcomb Rd
Install pathway on the south side of Amity Rd, between Federal Way and
Rimview Way. Install an enhanced pedestrian crossing (pedestrian hybrid
beacon) at Amity and Rimview to access the pathway on the north side of
Amity and the regional pathway system in the area.
No $0.44 Scoped "Go". ACHD to evaluate potential
programming during IFYWP update.
52 41 RD207‐
12
Cloverdale Rd,
Overland Rd / Franklin
Rd (Cloverdale Rd I‐84
Overpass)
Widen Cloverdale Rd and overpass from 2 to 5 lanes with curb, gutter,
sidewalk, and bike lanes. (City request for sidewalk and bikelanes to be
constructed as part of roadway widening project.
No $2.33 ACHD requested project from ITD in spring
2016. Project is not on ITD's planned projects
at this time. ACHD will continue to pursue
project with ITD.
53 42 CM213‐
58
Broadway Ave and
Boise Ave
Improve intersection for bikes and pedestrians in accordance with the
Southeast Boise Neighborhood Plan. Includes accessible pedestrian signal.
Yes
(106)
2019 2019 2020 $0.17 ACHD to coordinate with ITD
maintenance project.
To be built in FY2020.
LTP ‐ Long Term Priority
PD ‐ Preliminary Development
CN ‐ Construction Year Page 9 of 10
![Page 31: Kent Goldthorpe, President Paul Woods, Vice President ...€¦ · 2016. Project is part of ITD's Strategic Initiatives request for FY2021. ACHD with ITD on any improvement if funded](https://reader030.vdocuments.net/reader030/viewer/2022041118/5f2f3aeb5603fd337e77e47c/html5/thumbnails/31.jpg)
Attachment 2
In IFYWP
(Page)DSN YR ROW YR CN YR
Total Cost
in MillionsProgramming Notes
ACHD Proposed Response
2016 City
Priority
Ranking
2015 City
Priority
Ranking
GIS # ACHD Project Name Project Description
Current Programming Status
54 43 CM214‐
26
Horseshoe Bend Rd,
State St / Hill Rd
(Horseshoe Bend Rd
Bikeway, Hill Rd /
Greenbelt)
Complete detached sidewalks, curb & gutter, seepage beds, bike lanes on
both sides of Horseshoe Bend Rd. Widen shoulder on the west side for
parallel parking. Project includes road rehabilitation due to poor pavement
condition. (City request for a bikeway extending to Greenbelt to be
completed in part through this project.)
Yes
(114)
PD PD PD $1.68 All project phases currently in preliminary
development. ACHD to evaluate project
construction moving forward through IFYWP
update.
55 44 RD215‐
20
Emerald St, Curtis Rd /
Orchard St
Widen Emerald St to 5‐lanes with curb, gutter, sidewalk and bike lane in
accordance with the 2012 CIP. (City request is for sidewalk on both sides. Due
to significant cross slope issues, roadway will need to be rebuilt. Roadway will
be widening to CIP lanes at the same time.)
No $3.47 Defer. Currently operating at a LOS D. City
request for sidewalks to be built with the
roadway widening.
56 45 CM209‐
11
Bogus Basin Rd,
Curling Dr / 550' N/O
Curling Dr (Bogus
Basin, east of Curling
Dr)
Widen pavement and install curb, gutter, and atached sidewalk on both sides
of Bogus Basin to fill in a 550' gap north of Curling Dr. Install retaining wall on
east side as necessary.
Yes
(106)
2018 2019 2020 $0.36 To be built in FY2020.
Studies
1 2 1180 State Street Alignment
and Right‐of‐Way
Study
Expedite completion. No TBD ACHD considers the draft plan complete and
formal adoption is not necessary. Draft plan
will be used to inform capital projects as they
move forward.
2 3 1180 Neighborhood Bike
and Pedestrian Plan
for the North End/East
End Planning Area
Complete a neighborhood pedestrian and bicycle plan. No TBD North Boise Bike and Pedestrian Plan is under
way. Portion of North End south of State St to
be evaluated after completion of Jefferson and
Madison sidewalks to be built in FY2017. ACHD
to propose completion the East End Plan
during FY2017 Budget process.
LTP ‐ Long Term Priority
PD ‐ Preliminary Development
CN ‐ Construction Year Page 10 of 10
![Page 32: Kent Goldthorpe, President Paul Woods, Vice President ...€¦ · 2016. Project is part of ITD's Strategic Initiatives request for FY2021. ACHD with ITD on any improvement if funded](https://reader030.vdocuments.net/reader030/viewer/2022041118/5f2f3aeb5603fd337e77e47c/html5/thumbnails/32.jpg)
April 1, 2016 Kent Goldthorpe, President Ada County Highway District 3775 Adams Street Garden City, ID 83714 Re: Annual Transportation Requests ACHD Integrated Five Year Work Plan FY 2017-2021 Dear President Goldthorpe: The Boise City Council recently approved the attached annual, prioritized list of transportation projects for consideration to be included in the Ada County Highway District’s 2017-2021 Integrated Five Year Work Plan. The list of council priorities includes capital improvement projects, community program projects and studies. We are particularly eager to begin working with ACHD on the South Orchard Street Realignment Study. The realignment and extension of this roadway will provide much needed connectivity to Southwest Boise and offer additional mobility choices for residents of that area. Also, as you are aware, the City of Boise is preparing the final version of its Transportation Action Plan (TAP). The TAP includes a prioritization matrix to better align the City’s transportation priorities with its values and vision of a sustainable, modern transportation system that offers choices. We plan to introduce the matrix in next year’s prioritization process. A major component of the TAP’s vision is improving transportation infrastructure that promotes bicycle and pedestrian modes. In the past, bicycle and pedestrian improvement projects on non-arterial streets have been limited to the funds within ACHD’s Community Programs. These projects contribute highly to our residents’ quality of life. As ACHD completes each new Neighborhood Bicycle Pedestrian Plan, the list of potential Community Program Projects greatly increases. The City of Boise finds the current funding level for Community Programs low and disproportionate to the amount of need. The City is dedicated to increasing the amount of funds for complete streets on collectors and local streets to improve bicycle and pedestrian connectivity
![Page 33: Kent Goldthorpe, President Paul Woods, Vice President ...€¦ · 2016. Project is part of ITD's Strategic Initiatives request for FY2021. ACHD with ITD on any improvement if funded](https://reader030.vdocuments.net/reader030/viewer/2022041118/5f2f3aeb5603fd337e77e47c/html5/thumbnails/33.jpg)
throughout the city. We are not making an official request this year to increase funding for Community Programs by shifting funds from Capital Projects. However, we anticipate that future project requests to ACHD will emphasize these values and that additional Community Program funds will be necessary. We look forward to reviewing the draft ACHD IFYWP FY 2017-2021 soon. Please contact Karen Gallagher at 384-3910 with any questions. Sincerely,
Mayor David H. Bieter cc: Rodney Ashby, ACHD
Karen Gallagher, Boise PDS
![Page 34: Kent Goldthorpe, President Paul Woods, Vice President ...€¦ · 2016. Project is part of ITD's Strategic Initiatives request for FY2021. ACHD with ITD on any improvement if funded](https://reader030.vdocuments.net/reader030/viewer/2022041118/5f2f3aeb5603fd337e77e47c/html5/thumbnails/34.jpg)
City of Boise 2016 Annual Priortized Transportation Requests for ACHD's IFYWP FY 2017‐2021
March 29, 2016
In IFYWP
(Page)
DSN
YR
ROW
YRCN YR
Total
Cost in
Millions
ACHD Programming Notes
LTP LTP
State St, 36th St / 27th St Priority east‐west mobility corridor on north side of Boise River.
Current PM LOS E & F. Widen to 7 lanes. Develop transition plan to
achieve 2 lanes dedicated for transit.
Yes (38) UF UF UF $5.01 Project will advance when land use,
transit, and roadway triggers met.
Widen State St to 7 lanes with HOV/transit lanes, curb, gutter, sidewalk and
bike lanes, in accordance with the State St TTOP and the 2012 CIP. This
project may include an access management component.
LTP LTP
State St, Collister Dr / 36th St Priority east‐west mobility corridor on north side of Boise River.
Current PM LOS F. Widen to 7 lanes. Develop transition plan to
achieve 2 lanes dedicated for transit.
Yes (38) UF UF UF $10.12 Project will advance when land use,
transit, and roadway triggers met.
Widen State St to 7 lanes with HOV/transit lanes, curb, gutter, sidewalk and
bike lanes, in accordance with the State St TTOP and the 2012 CIP. This
project may include an access management component.
LTP LTP
State St, Pierce Park Ln /
Collister Dr
Priority east‐west mobility corridor on north side of Boise River.
Current PM LOS E. Widen to 7 lanes. Develop transition plan to
achieve 2 lanes dedicated for transit.
Yes (39) UF UF UF $6.67 Project will advance when land use,
transit, and roadway triggers met.
Widen State St to 7 lanes with HOV/transit lanes, curb, gutter, sidewalk and
bike lanes, in accordance with the State St TTOP and the 2012 CIP. This
project may include an access management component.
LTP LTP
State St, Glenwood St / Pierce
Park Ln
Priority east‐west mobility corridor on north side of Boise River.
Current PM LOS E. Widen to 7 lanes. Develop transition plan to
achieve 2 lanes dedicated for transit.
Yes (38) UF UF UF $1.28 Project will advance when land use,
transit, and roadway triggers met.
Widen State St to 7 lanes with HOV/transit lanes, curb, gutter, sidewalk and
bike lanes, in accordance with the State St TTOP and the 2012 CIP. This
project may include an access management component.
1 1
State St and Veterans Memorial
Pkwy
High volume intersection connecting to a river crossing. Current PM
LOS E.
Yes (46) Done 2016‐
2017
2018 $10.08 Widen intersection in accordance with the State St/Veterans Memorial
Pkwy/36th St Intersection Concept Study, including installation of median U‐
turns and installation of two‐phased pedestrian crossings. Project identified
as a key piece of the State St TTOP.
2 2
State St and Collister Dr Priority east‐west mobility corridor on north side of Boise River. Yes (45) 2015‐
2016
2016 2018 $9.36 Federal CN funding in 2018. Actual
construction to occur in 2019.
Federal aid project to improve the intersection of State St and Collister Dr,
including realignment of the Collister Dr leg, curb, gutter, sidewalk, and bike
lanes in accordance with the State St TTOP and the 2012 CIP. Project
includes replacing bridge #090B.
3 3
State St and Glenwood St High volume intersection connecting to a river crossing. Priority
corridor. Current PM LOS E.
Yes (46) 2018 2019 PD $3.31 Concept design to begin in spring of
2016.
Widen and modify intersection in order to improve traffic and transit
operations in accordance with the State St TTOP and the 2012 CIP. Joint
project with ITD.
4 4
State St and Pierce Park Ln Intersection on priority east‐west mobility corridor on north side of
Boise River.
Yes (46) 2019 2020 PD $4.08 Concept design to begin in 2017. Widen intersection to 3 lanes on Pierce Park and 7 lanes on State St,
including curb, gutter, sidewalk, and bike lanes in accordance with the State
St TTOP and the 2012 CIP.
5 6
Fairview Ave and Cole Rd Priority east‐west corridor. Current PM LOS E. Yes (44) Done 2016 2017 $4.97 Widen intersection to 8 lanes on Fairview Ave and 7 lanes on Cole Rd,
including curb, gutter, sidewalk, and bike lanes in accordance with the 2012
CIP. Project includes non‐traversable raised medians.
6 7
Downtown Boise
Implementation Plan (DBIP)
Add bicycle facilities to major downtown destinations. Convert 5th
and 6th to two‐way streets for multiple benefits. Request moving
signal retiming up to 2017.
Yes (83‐85) Varies Varies Varies $12.99 Perform road rehabilitation and 2‐way conversion of select streets in
downtown Boise in concert with CCDC and other projects in accordance with
the Downtown Boise Implementation Plan.
7 8
Emerald St and Americana Blvd,
Orchard St / Ann Morrison Park
Entrance
Improve safety. Complete street by adding bike lanes. Convert 4
lanes to 3 and add bike lanes. Also restripe Americana, Latah to Ann
Morrision Park with bike lanes.
Yes (129) 2016 2016 2017 $1.49 Reconfigure Emerald St and Americana Blvd to add continuous bike lanes
and complete the sidewalk on both sides of Emerald St in accordance with
the Central Bench Neighborhood Plan.
2016 City
Priority
Ranking
2015 City
Priority
Ranking
ACHD Project Name
(City Project Name)ACHD Project Description
Current Programming Status
Boise's Request
LTP ‐ Long Term Priority
PD ‐ Preliminary Development
CN ‐ Construction Year Page 1 of 8
![Page 35: Kent Goldthorpe, President Paul Woods, Vice President ...€¦ · 2016. Project is part of ITD's Strategic Initiatives request for FY2021. ACHD with ITD on any improvement if funded](https://reader030.vdocuments.net/reader030/viewer/2022041118/5f2f3aeb5603fd337e77e47c/html5/thumbnails/35.jpg)
In IFYWP
(Page)
DSN
YR
ROW
YRCN YR
Total
Cost in
Millions
ACHD Programming Notes
2016 City
Priority
Ranking
2015 City
Priority
Ranking
ACHD Project Name
(City Project Name)ACHD Project Description
Current Programming Status
Boise's Request
8 9
Fairview Ave and Main St,
Whitewater Park Blvd / 16th St
Restripe to add on‐street parking by trading a travel lane. No TBD 2016 Budget Planning Project ‐ Project
to be evaluated in concept as part of
the Fairview‐Main Local Streets Plan
and Bike Facilities project.
Restripe to add on‐street parking by removing a travel lane.
9a 10
Orchard St, Chinden Blvd /
Overland Rd
Improve safety. Complete street by adding bike lanes. Convert 4
lanes to 3 and add bike lanes.
No TBD 2017 Budget Planning Project ‐ Project
to be evaluated in concept as part of
the Orchard Street Operational
Analysis project.
Convert 4 lanes to 3 lanes and add bike lanes.
9b 11
Orchard St, Emerald St / Morris
Hill Rd
Road segment lacks pedestrains facilities. Also included as an
Economic Development Project. Boise to develop a Concept Plan to
construct a complete street in 2017. We request ACHD delaying
their operational analysis to 2018.
No TBD 2017 Budget Planning Project ‐ Project
to be evaluated in concept as part of
the Orchard Street Operational
Analysis project.
Develop concept plan to construct a complete street.
10 13
Broadway Ave/Avenue B and
Idaho St/Warm Springs Ave
Develop innovative solution to improve intersection for pedestrians,
bicyclists, and motorist.
Yes (42) 2017 2018 2019 $1.54 Concept design underway. Widen and/or modify intersection to improve safety and reduce congestion
for all users in accordance with the 2012 CIP. Design, right‐of‐way, and
construction costs are tentative until completion of the concept design.
Project includes bridge #549.
11 14
5th St / Fort St / Hays St Develop innovative solution at 5‐leg intersection to improve
intersection for pedestrians, bicyclists, and motorists. Delay APS
project until after the two‐way conversion of 5th Street.
No TBD Defer until conversion of 5th Street
decided. 5th St evaluation underway.
Improve intersection for pedestrians, bicyclists, and motorists.
12 15
32nd St, Moore St/Whitewater
Park Blvd
Better access to Esther Simplot Park for this neighborhood area.
Extend the local street to provide the neighborhood and an
undeveloped, higher density parcel critical access to Whitewater
Park Blvd. and Esther Simplot Park. Include coordination with CCDC.
No N/A Add to Master Street Map. Defer until
development.
Extend roadway.
13 16
28th St, Main St/Fairview Ave Extend the local street through this superblock to secure the street
network for better circulation and to create a local town center
typology street with buildings fronting the street. Coordinate with
CCDC. Need to create smaller blocks for redevelopment and secure
secondary circulation network.
No TBD Include analysis as part of local roads
plan for the Fairview‐Main sub‐area.
See City of Boise study priority #1.
Extend roadway.
14 17
Beacon St, Boise Ave / Broadway
Ave
Create a complete street by converting Beacon from 4 Lanes to 3
Lanes. Keep two vehicular lanes, dedicate one lane to left‐turns, add
medians, pedestrian crossings and bike lanes. Current configuration
lacks bicycle facilities, and pedestrians find it difficult to cross.
Coordinate with BSU.
No TBD Evaluate after BSU Master Planning
effort is complete.
Reconfigure travel lanes from 4‐lanes to 3‐lanes with bike lanes. Add refuge
medians and pedestrian crossings.
15 21
Cloverdale Rd, Fairview Ave /
Ustick Rd
Improve this north‐south arterial segment before expanding the
Ustick Corridor to Cloverdale. Current PM LOS F.
Yes (31) Done 2016 2018 $3.40 Widen Cloverdale Rd to 5 lanes with curb, gutter, sidewalk and bike lanes, in
accordance with the Cloverdale Rd Concept Design and the 2012 CIP. Project
includes bridge #472.
16 22Cloverdale Rd, Ustick Rd /
McMillan Rd
Current PM LOS F. Complete this priority corridor. Yes (32) 2016 2017 2019 $4.00 Widen Cloverdale Rd to 5 lanes with curb, gutter, sidewalk and bike lanes, in
accordance with the Cloverdale Rd Concept Design and the 2012 CIP.
17 23
Cole Rd, I‐84 / Franklin Rd and
Cole Rd and Franklin Rd
Connects to interstate interchanges at I‐84 and I‐184. Improve
safety. Current PM LOS D & F for segment, LOS E for intersection.
Concept work started in 2011.
Yes (33,
43)
Done 2016‐
2017
2019 $10.55 Widen Cole Rd to 5 lanes with curb, gutter, sidewalk and bike lanes in
accordance with the Cole Rd Concept Design and the 2012 CIP. Project to be
constructed concurrently with Cole/Franklin and Cole/McMullen
intersections. Project includes bridge #281.
LTP ‐ Long Term Priority
PD ‐ Preliminary Development
CN ‐ Construction Year Page 2 of 8
![Page 36: Kent Goldthorpe, President Paul Woods, Vice President ...€¦ · 2016. Project is part of ITD's Strategic Initiatives request for FY2021. ACHD with ITD on any improvement if funded](https://reader030.vdocuments.net/reader030/viewer/2022041118/5f2f3aeb5603fd337e77e47c/html5/thumbnails/36.jpg)
In IFYWP
(Page)
DSN
YR
ROW
YRCN YR
Total
Cost in
Millions
ACHD Programming Notes
2016 City
Priority
Ranking
2015 City
Priority
Ranking
ACHD Project Name
(City Project Name)ACHD Project Description
Current Programming Status
Boise's Request
18 24
Maple Grove Rd, Victory Rd /
Overland Rd
Improve the arterial grid in southwest Boise for pedestrians,
bicycles, and vehicles. Utilizes 4 lane overpass. Current PM LOS F.
Yes (36) 2016 2017 2020 $4.94 Widen Maple Grove Rd to 5 lanes with curb, gutter, sidewalk, and bike lanes
in accordance with the 2012 CIP. Project includes bridges #267P, #268, and
#269P.
19 25Maple Grove Rd, Amity Rd /
Victory Rd
Improve the arterial grid in southwest Boise for pedestrians,
bicycles, and vehicles. Utilizes 4 lane overpass. Current PM LOS F.
Yes (35) 2020 PD PD $3.47 Widen Maple Grove Rd to 5 lanes with curb, gutter, sidewalk, and bike lanes
in accordance with the 2012 CIP. Project includes bridge #269A.
20 26
Cloverdale Rd, McMillan Rd /
Chinden Blvd (US 20/26)
Complete this priority corridor. Current PM LOS F. Yes (32) 2018 2019 2020 $4.33 Widen Cloverdale Rd to 5 lanes with curb, gutter, sidewalk and bike lanes, in
accordance with the Cloverdale Rd Concept Design and the 2012 CIP.
Project includes bridge #137A.
21 27
Cloverdale Rd, Victory Rd /
Overland Rd
Improve the arterial grid in southwest Boise for pedestrians,
bicycles, and vehicles. Current PM LOS F for segment, LOS A for
intersections.
No $6.51 Prioritized (Ranks 50 of 78). Awaits
programming.
Widen to 5 lanes with curb, gutter, sidewalk and bike lanes in accordance
with 2012 CIP.
22 28
Cole Rd and Victory Rd Improve safety. Connects to only interstate interchange for
southwest Boise. PM Peak Hour LOS E. Shifted down in priority,
while shifting Maple Grove up in priority.
Yes (43) 2017 2019 2020 $5.59 Widen intersection in accordance with the 2012 CIP and widen Cole Rd
south to McGlochlin St to 5 lanes with bike lanes, sidewalks and/or asphalt
pathways in accordance to the 2012 CIP. Project includes bridge #282.
23 29
Warm Springs Avenue, near the
Mesa
Provide long‐term safety upgrades for protection from falling rocks. No N/A Defer until long‐term effectiveness of
spring 2015 improvements can be
evaluated.
Rock fall mitigation.
24 30S. Orchard St Realignment,
Gowen Rd/Victory Rd
Improve arterial grid in southwest Boise. PM Peak LOS Map 2015
showed LOS F and 2016 Map shows LOS D.
No TBD 2017 Budget Planning Project ‐
Alignment study.
New alignment.
25 31
Barber Dr Bridge (Bridge #1335),
1000' E/O Old Hickory Way
Widen Bridge with new box culvert. Add signage and striping to give
drivers additional advance notice of narrow bridge until bridge can
be widened.
Yes (54) 2019 N/A 2020 $0.57 Commission directed project be
accelerated if possible. Will investigate
in next IFYWP update.
Replace/widen bridge #366 over Warm Springs Creek on Barber Dr as part of
ACHD's Bridge Maintenance Program.
1 1
Capitol Blvd and Crescent Rim
Dr, Yale Ln/Eastover Ter
Capitol Boulevard and Crescent Rim Drive, Yale (Elmer’s) to Eastover
Terrace (entrance to Depot) or other logical termini. Improved
bicycle and pedestrian connection.
No TBD Concept evaluation underway. Project
to be programmed once alternative
selected.
Improve bike and pedestrian connection.
2 2
Camas St, Orchard St / Roosevelt
St
Camas, Orchard / Roosevelt: s/w on both sides, north at a
minimum: 1,900 ft.
Yes (107) 2016 2016 2017 $1.17 Construct sidewalk on both sides of Camas Street from Orchard Street to
Roosevelt Street in accordance with the Central Bench Neighborhood Plan.
Project to include roadway reclamation.
3 3
Orchard St and Alpine St
Pedestrian Crossing
Orchard / Alpine, signalized pedestrian crossing No TBD Does not meet traffic warrants.
Reevaluate warrants upon completion
of the Alpine sidewalk project.
Install an enhanced pedestrian crossing at the intersection.
4 4
Phillippi St/ Overland Rd Ped
Signal
PHB Enhanced Pedestrian Signal for access to library, shopping, and
park.
No $0.29 Scoped 2015. Final report pending.
(City request for pedestrian signal to be
built with sidewalk project.)
Combine with project to rebuild roadway to include 8' detached sidewalk,
parking, 5' bike lanes, 2 auto lanes, and a center turn land/island. Full
rebuild of roadway required due to steep cross slope issues. Includes
replacement of bridge #1366 or #404.
5 5
Emerald St and Americana Blvd,
Orchard St / Ann Morrison Park
Entrance
Remove a traffic lane, add bike lanes, and fill sidewalk gaps on both
sides.
Yes (129) 2016 2016 2017 $1.49 City request for sidewalk to be build
with lane reconfiguration.
Reconfigure Emerald St and Americana Blvd to add continuous bike lanes
and complete the sidewalk on both sides of Emerald St in accordance with
the Central Bench Neighborhood Plan.
6 6
Kootenai St, Vista Ave / Federal
Way
Kootenai, Vista / Federal Way, sidewalk on both sides, includes
improved rail crossing.
Yes (115) Done 2016 2017 $0.84 Construct curb, gutter, sidewalks and bike lanes on both sides of Kootenai St
from Vista Ave to Federal Way in accordance with the Central Bench
Neighborhood Plan. Project includes removal of on‐street parking.
Community Programs
LTP ‐ Long Term Priority
PD ‐ Preliminary Development
CN ‐ Construction Year Page 3 of 8
![Page 37: Kent Goldthorpe, President Paul Woods, Vice President ...€¦ · 2016. Project is part of ITD's Strategic Initiatives request for FY2021. ACHD with ITD on any improvement if funded](https://reader030.vdocuments.net/reader030/viewer/2022041118/5f2f3aeb5603fd337e77e47c/html5/thumbnails/37.jpg)
In IFYWP
(Page)
DSN
YR
ROW
YRCN YR
Total
Cost in
Millions
ACHD Programming Notes
2016 City
Priority
Ranking
2015 City
Priority
Ranking
ACHD Project Name
(City Project Name)ACHD Project Description
Current Programming Status
Boise's Request
7 7
Victory Rd, Virginia Ave / Federal
Way
Victory, Virginia / Federal Way: 845 ft sidewalk gaps on both sides
(1,690 ft total). Includes railroad crossing.
No $2.04 Scoped ‐ High cost project.
Programming pending Kootenai and
Overland crossings to improve
coordination with Union Pacific.
Construct sidewalk on both sides of Victory Rd, between Virginia Ave and
Federal Way. Improve rail crossing.
8 8
Overland Rd, Columbus St /
Federal Way
Overland, Columbus / Federal Way: fill sidewalk gaps on both sides.
Includes railroad crossing.
Yes (118) 2016 2016 2018 $1.11 Complete curb, gutter and sidewalk on both sides of Overland Rd, between
Columbus St and Federal Way in accordance with the Central Bench
Neighborhood Plan. Includes an improved UPRR crossing.
9 9
McMillan Rd Refuge Medians,
Eagle Rd / Cloverdale Rd
McMillan Road Pedestrian Refuge Medians and Traffic Calming
Medians, Eagle / Cloverdale ‐ Hold input meetings with schools and
parents to identify best locations
Yes (117) TBD ACHD Traffic evaluating potential
location. One installed with Eagle/
McMillan intersection project. Addition
signalized crossing exists.
Install pedestrian refuge islands at locations along McMillan Rd, between
Eagle Rd and Cloverdale at locations to be determined. Design and
construction will be programmed once locations are identified.
10 10
Collister Dr, Hillside Ave /
Briarhill Dr
Fill 420 ft sidewalk gap on east side of Collister, north of Hill Rd Yes (109) 2016 2017 2019 $0.38 ACHD to investigate advancing project
to align with planned maintenance.
Construct curb, gutter and sidewalk on the east side of Collister Dr
connecting with the existing sidewalk south of Hillside Ave and at Briarhill Dr
in order to improve neighborhood connectivity and pedestrian safety.
11
Columbus Bike Way, Canal to
Kootenai.
Provide on‐street bicycle facilities in Vista Neighborhood. No
12
Spaulding Sidewalk, Vista to
Columbus
Add curb, gutter and min 5' wide sidewalk along north and south
sides of Spaulding in Vista Neighborhood.
No
13
Malad Sidewalk, Kerr to Vista Add curb, gutter and min 5' wide sidewalk along the north side of
Malad in Vista Neighborhood.
No
14
Annett Sidewalk, Malad to
Targee
Add curb, gutter and min 5' wide sidewalk along the west side of
Annett in Vista Neighborhood.
No $0.49 This project is #48 on BSD list.
Move curb, remove on‐street parking in order to save mature trees.
15 11
Leadville Ave Bikeway, Linden St
/ Greenbelt
Bikeway on Leadville, Linden to Greenbelt: Signs installed, enhanced
crossing at Linden; crossing at Boise Ave not recommended by
ACHD.
Yes (126) 2017 2018 2020 $0.24 Improve Leadville Ave as a bikeway to include enhanced crossing at Boise
Ave, shared lane markings, possible modification of two‐way stop control at
Iowa, Pennsylvania, Warren, Highland, and Rossi, and traffic calming in
accordance with the Southeast Boise Neighborhood Plan.
16 12
Cole Rd, Kettering Ave /
Mountain View Dr
Continuous sidewalks, both sides Yes (109) 2016 2016 2018 $0.72 Construct curb, gutter, and sidewalk on both sides of Cole Rd between
Kettering Ave and Mountain View Dr in accordance with the West Bench
Neighborhood Plan.
17 13
Columbus St, Overland Rd /
Kootenai St
Sidewalk on both sides Yes (110) 2016 2017 2019 $1.40 Construct curb, gutter and sidewalk on both sides of Columbus St from
Overland Rd to Kootenai St in accordance with the Central Bench
Neighborhood Plan.
18Latah Bike Way, Targee to
Overland
Provide on‐street bicycle facilities to tie into existing bicycle lanes
on Latah, north of Overland in Vista Neighborhood.
No
19 14
Owyhee St bikeway, Elder St /
Alpine St (Bikeway parallel to
Vista)
Bikeway with signalized crossings Yes (127) 2019 2020 PD $0.12 Improve Owyhee St as a bikeway to include way finding signs, shared lane
markings, and enhanced crossing at Rose Hill in accordance with the Central
Bench Neighborhood Plan. Concept design will further clarify project scope.
City request for bikeway parallel to
Vista to be completed by these two
projects. Also evaluating bikeway on
Columbus. Joint concept design will be
completed in FY2018.
LTP ‐ Long Term Priority
PD ‐ Preliminary Development
CN ‐ Construction Year Page 4 of 8
![Page 38: Kent Goldthorpe, President Paul Woods, Vice President ...€¦ · 2016. Project is part of ITD's Strategic Initiatives request for FY2021. ACHD with ITD on any improvement if funded](https://reader030.vdocuments.net/reader030/viewer/2022041118/5f2f3aeb5603fd337e77e47c/html5/thumbnails/38.jpg)
In IFYWP
(Page)
DSN
YR
ROW
YRCN YR
Total
Cost in
Millions
ACHD Programming Notes
2016 City
Priority
Ranking
2015 City
Priority
Ranking
ACHD Project Name
(City Project Name)ACHD Project Description
Current Programming Status
Boise's Request
20 14
Shoshone St Bikeway, Linden St
/ Greenbelt (Bikeway parallel to
Vista)
Bikeway with signalized crossings Yes (127) 2020 PD PD $0.12 Improve Shoshone St as a bikeway to include wayfinding signage, shared
lane markings, signal modification at Overland Rd, and pedestrian ramps in
accordance with the Central Bench Neighborhood Plan. Project includes an
enhanced pedestrian signal to replace existing flashing caution light at Rose
Hill St. Concept design will further clarify project scope.
21 15
East‐West Bikeway, Ave
B/Whitewater Park Blvd
East‐West Bikeway from Ave B to Whitewater Park Blvd No TBD Identify route as part DBIP and local
roads plan for this sub‐area. FY2016
Planning Budget includes sub‐area
plan. See City of Boise study priority #1.
Wayfinding signage and arterial crossings.
22 16Columbia Village Bikeway to
Amity Rd
North‐South bikeway connection to Amity Yes (113) 2016 2017 2019 $0.25 Project to be completed as part of City
priority # 18.
See description under City priority #18 below.
23 17
Heron St, 13th St / 9th St (north
side)
Heron, 13th to 9th: <1/3 mile of sidewalk on north side Yes (113) 2016 N/A 2018 $0.54 Construct curb, gutter, parking and detached concrete pathway on north
side of Heron St. from 13th St. to 9th St. Project includes a full road rebuild
due to poor pavement condition.
24 18
Holcomb Rd, Mimosa Way /
Amity Rd
Holcomb, Eastgate to Amity: 1/3 mile: sidewalk Yes (113) 2016 2017 2019 $0.25 Construct detached 5’ sidewalk on the east side of Holcomb Rd between
Mendota Dr and Amity Rd in accordance with the Southeast Boise
Neighborhood Plan. Stripe bike lane and install wayfinding signage for a bike
facility from Amity to Mimosa Way. Project will provide ped/bike connection
from Oregon Trail Heights/Columbia Village to Holcomb path/bridge and
Southeast Boise.
25 19Alpine St, Orchard St / Randall St Alpine, Orchard / Randall, sidewalk on south side Yes (104) 2016 2016 2017 $0.64 Complete sidewalk on the south side of Alpine St from Orchard St to Randall
St in accordance with the Central Bench Neighborhood Plan.
26 20
Phillippi St, Malad St / Targee St Phillippi, Malad / Targee: sidewalk on east side Yes (119) 2016 2017 2019 $0.26 Complete curb, gutter and sidewalk improvements on both sides of Phillippi
St, between Malad St and Targee St in accordance with the Central Bench
Neighborhood Plan.
27 21
Phillippi St, Targee St / Overland
Rd
Phillippi, Targee / Overland: sidewalk on both sides Yes (119) 2017 2019 2020 $2.13 Construct curb, gutter and sidewalk on both the sides of Phillippi St,
between Targee St and Overland Rd in accordance with the Central Bench
Neighborhood Plan. Project includes full road rehabilitation.
28 22
Clark St, Orchard St / Roosevelt
St
Clark, Orchard / Roosevelt: s/w on both sides, one side at a min.
(2,100 ft on north side)
Yes (108) 2015‐
2016
2016 2018 $1.00 Construct sidewalk on both sides of Clark St between Orchard St and
Roosevelt St to provide pedestrian connectivity and reduce the need for
safety busing for Monroe Elementary School.
29 24
Jefferson St, Whitewater Park
Blvd / 27th St
Jefferson, gaps in sidewalk between 27th St. and Whitewater Park
Blvd.
Yes (114) 2016 2016 2017 $0.17 Complete curb, gutter, and sidewalk on both sides of Jefferson St east of
Whitewater Park Blvd where gaps currently exist in accordance with Boise'
30th Area Master Plan. Project includes road rehabilitation.
LTP ‐ Long Term Priority
PD ‐ Preliminary Development
CN ‐ Construction Year Page 5 of 8
![Page 39: Kent Goldthorpe, President Paul Woods, Vice President ...€¦ · 2016. Project is part of ITD's Strategic Initiatives request for FY2021. ACHD with ITD on any improvement if funded](https://reader030.vdocuments.net/reader030/viewer/2022041118/5f2f3aeb5603fd337e77e47c/html5/thumbnails/39.jpg)
In IFYWP
(Page)
DSN
YR
ROW
YRCN YR
Total
Cost in
Millions
ACHD Programming Notes
2016 City
Priority
Ranking
2015 City
Priority
Ranking
ACHD Project Name
(City Project Name)ACHD Project Description
Current Programming Status
Boise's Request
30 25
Madison Ave, Whitewater Park
Blvd / 27th St
Madison gaps in sidewalk between 27th St. and Whitewater Park
Blvd.
Yes (117) 2016 2016 2017 $0.13 Complete curb, gutter, and sidewalk on both sides of Madison St, between
Whitewater Park Blvd and 27th St in accordance with the City of Boise's 30th
St Area Master Plan. Project will create standard parallel parking between
Whitewater Park Blvd and 30th St. Project also includes full road
rehabilitation.
31 26
Coston St, Bannock/ Franklin St Coston, Warm Springs / north of Franklin, sidewalk on both sides No $0.23 Scoped 2015. Final report pending. Construct 5' attached sidewalk on the west side of Coston St between Warm
Springs Ave and Franklin St. (City's request was for sidewalk on both sides.
Working in coordination with the City Forrester, project will only construct
sidewalks on the west side due to landscape/tree impacts.)
32 27
Peasley St / Alpine St (Railroad
Crossing)
Improved Railroad Crossing at Peasley for Pedestrians (connected
sidewalks) and Bicyclists
No $0.15 Scoped 2015. Final report pending. Extend railroad crossing planking to the east side for a pedestrian crossing.
Extend detached sidewalk with swales to intersection from existing sidewalk
on the northeast side of the crossing.
33 28
Cherry Ln, Owyhee St / Vista Ave Cherry Ln, Owyhee / Vista: 1,550 ft sidewalk gap on south side.
Connects to transit stop. (ACHD: Defer, sidewalk exists on north
side)
Yes (108) PD PD PD $0.77 Complete sidewalk on the south side of Cherry Ln between Owyhee St and
Vista Ave in accordance with the Central Bench Neighborhood Plan.
34 29
Garden St, Franklin Rd / Emerald
St
Garden St, Emerald / Franklin: sidewalk on both sides No $2.57 Scoped 2011. Awaits programming.
High cost project.
Construct curb, gutter and sidewalk on both sides of Garden Street from
Emerald St to Franklin Road to provide pedestrian connectivity in an
established neighborhood. Fill in the missing sidewalk across 2 lots on the
northwest corner of Emerald.
35 30
Eckert Rd and Arrow Junction Dr
Pedestrian Crossing (Eckert Rd,
Boise Ave / Arrow Junction Dr)
Eckert, Boise / Arrow Junction: sidewalk on east side No $0.06 Scoped 2015. Final report pending.
(City request for pedestrian signal to be
built with sidewalk project.)
Install a striped crosswalk and pedestrian ramps at the intersection. (City's
request was for sidewalks on the east side. Sidewalks already exist on the
west side with only house on the east side.)
36 31
Liberty St, Emerald St/Franklin
Rd
Liberty, Emerald / Franklin, sidewalk on both sides Yes (116) 2016 2017 2019 $0.54 Complete sidewalk on the east side of Liberty St in accordance with the
Central Bench Neighborhood Plan. (City request was for sidewalk on both
sides.)
37 32
Vista Neighborhood Local
Streets
Vista Neighborhood, curb, gutter, innovative stormdrainage on local
streets. Work with ACHD to identify candidates.
No TBD Vista LIV transportation group did not
identify as a priority. Further City input
requested.
Install curb, gutter, and/or innovative storm drainage on local streets.
38 33
Vista Ave and Spaulding St
Pedestrian Signal
Vista signalized ped crossing at Spaulding mainly for transit users.
Project is in the Vista Neighborhood.
Yes (122) 2019 2019 2020 $0.26 Scoped signal at Nez Perce. Willing to
consider location at Spaulding at City's
request.
Install an enhanced pedestrian crossing on Vista Ave at Nez Perce St,
including bike push buttons.
39
Vista Traffic Calming, Elder to
Rose Hill
Reduce vehicle speeds along corridor by narrowing travel lanes,
providing bike lanes, or implementing other traffic calming
measures in Vista Neighborhood.
No
40Cleveland Sidewalk, Palouse to
Nez Perce
Construct curb, gutter and minimum 5' wide sidewalks on both
sides of Cleveland in Vista Neighborhood.
No
41Palouse Sidewalk, Roosevelt to
Cleveland
Construct curb, gutter and minimum 5' wide sidewalks on both
sides of Palouse in Vista Neighborhood.
No
42Hervey Sidewalk, Cherry to
Lemhi
Construct curb, gutter and minimum 5' wide sidewalks on west side
of Hervey in Vista Neighborhood.
No
43 34State St and Wylie Ln Pedestrian
Crossing
State St, east of Collister, signalized pedestrian crossing No $0.30 Project to be scoped in 2016. Install an enhanced pedestrian crossing (PHB) on State St on the east side of
Wylie Ln.
LTP ‐ Long Term Priority
PD ‐ Preliminary Development
CN ‐ Construction Year Page 6 of 8
![Page 40: Kent Goldthorpe, President Paul Woods, Vice President ...€¦ · 2016. Project is part of ITD's Strategic Initiatives request for FY2021. ACHD with ITD on any improvement if funded](https://reader030.vdocuments.net/reader030/viewer/2022041118/5f2f3aeb5603fd337e77e47c/html5/thumbnails/40.jpg)
In IFYWP
(Page)
DSN
YR
ROW
YRCN YR
Total
Cost in
Millions
ACHD Programming Notes
2016 City
Priority
Ranking
2015 City
Priority
Ranking
ACHD Project Name
(City Project Name)ACHD Project Description
Current Programming Status
Boise's Request
44 35
Ash Park St, Northview Rd /
Ustick Rd
Ash St, Northview to Ustick, sidewalk & bike way Yes (104) 2016 2017 2019 $0.56 Complete sidewalk on both sides of Ash Park Lane between Northview St
and Ustick Rd in accordance with the West Bench Neighborhood Plan. (City
requested sidewalk and bikeway.)
45 36
Phillippi St, Overland Rd / Cassia
St
Phillippi, Overland to Cassia, less than 1/2 mi. sidewalk gap No TBD Scoped 2015. Rebuild roadway to include 8' detached sidewalk, parking, 5' bike lanes, 2
auto lanes, and a center turn land/island. Full rebuild of roadway required
due to steep cross slope issues. Includes pedestrian signal at Phillippi St /
Overland Rd intersection on west side and replacement of bridge #1366 or
#404.
46 37
Allumbaugh St, Fairview
Ave/Northview St
Allumbaugh, Fairview to Northview, on both sides. No $0.89 Scoped 2015. Final 2016 scoping report
for sidewalk on one side.
Complete curb, gutter, and sidewalk on the west side of Allumbaugh St,
between Fairview Ave and Northview St. (City requested sidewalk on both
sides. Sidewalk on east side infeasible at this time due to significant land use,
utility, and drainage impacts.)
47Grand, Miller, Ash Pedestrian
Enhancements and Upgrades
Fix hazardous sidewalk, construct ADA compliant pedestrian ramps.
Fill in sidewalk gaps.
No
48 10th Street/Myrtle Extend 10th Street to Myrtle for street grid connectivity. No
49 38
De Meyer St, Cloverdale Rd /
Lena Ave; Lena Ave, De Meyer St
/ Arlen St
Sidewalk connection to DeMeyer Park ‐ Lena Ave, DeMeyer to
Hickory 1/4 mi. sidewalk gap on east side. Connect Shamrock
bikeway to signal at Cloverdale & DeMeyer by adding bike way on
DeMeyer & Lena.
No $0.28 Scoped 2015. Final report pending. Complete 5' attached sidewalk on the south side of DeMeyer St by
narrowing the roadway and constructing sidewalk on the inside of existing
curb. Construct at‐grade sidewalks through asphalt eyebrows to connect
sidewalk segments. Install bikeway (signage, pavement markings) from
Demeyer / Cloverdale to Lena / Arlen.
50 39
Cassia St, Franklin Park Dr /
Troxel Dr
Cassia, east of Franklin Park Dr, 0.2 mi. sidewalk gap on north side No $0.40 Scoped 2015. Final report pending. Complete sidewalk on the north side of Cassia St, between Franklin Park Dr
and Troxel Dr. Install bike lanes from Franklin Park Dr to Curtis Rd. Install an
enhanced pedestrian crossing (rectangular rapid flashing beacon) at Cassia
St and Troxel on the west side of the intersection at an existing crosswalk.
Restripe with bike lanes after chipsealing in 2018 (separate project).
51 40
Amity Rd, Federal Way /
Holcomb Rd
Amity, sidewalk gap on north side, Federal Way to Holcomb No $0.44 Scoped. Awaits programming. Install pathway on the south side of Amity Rd, between Federal Way and
Rimview Way. Install an enhanced pedestrian crossing (pedestrian hybrid
beacon) at Amity and Rimview to access the pathway on the north side of
Amity and the regional pathway system in the area.
52 41
Cloverdale Rd, Overland Rd /
Franklin Rd (Cloverdale Rd I‐84
Overpass)
I‐84 Cloverdale Overpass, add sidewalk & bike way No $2.33 ACHD requested project from ITD in fall
2015. Project is not of ITD's bridge
replacement list and will not be
developed at this time. ACHD will
continue to pursue project with ITD.
Widen Cloverdale Rd and overpass from 2 to 5 lanes with curb, gutter,
sidewalk, and bike lanes. (City request for sidewalk and bikelanes to be
constructed as part of roadway widening project.
53 42Broadway Ave and Boise Ave Broadway & Boise Ave Improve bicycle and pedestrian friendliness
at intersection
Yes (106) 2019 2019 2020 $0.17 ACHD to coordinate with ITD. Improve intersection for bikes and pedestrians in accordance with the
Southeast Boise Neighborhood Plan. Includes accessible pedestrian signal.
54 43
Horseshoe Bend Rd, State St /
Hill Rd (Horseshoe Bend Rd
Bikeway, Hill Rd / Greenbelt)
Bike Way on Horseshoe Bend Rd from Hill Road to State Street and
then to Greenbelt
Yes (114) PD PD PD $1.68 Complete detached sidewalks, curb & gutter, seepage beds, bike lanes on
both sides of Horseshoe Bend Rd. Widen shoulder on the west side for
parallel parking. Project includes road rehabilitation due to poor pavement
condition. (City request for a bikeway extending to Greenbelt to be
completed in part through this project.)
LTP ‐ Long Term Priority
PD ‐ Preliminary Development
CN ‐ Construction Year Page 7 of 8
![Page 41: Kent Goldthorpe, President Paul Woods, Vice President ...€¦ · 2016. Project is part of ITD's Strategic Initiatives request for FY2021. ACHD with ITD on any improvement if funded](https://reader030.vdocuments.net/reader030/viewer/2022041118/5f2f3aeb5603fd337e77e47c/html5/thumbnails/41.jpg)
In IFYWP
(Page)
DSN
YR
ROW
YRCN YR
Total
Cost in
Millions
ACHD Programming Notes
2016 City
Priority
Ranking
2015 City
Priority
Ranking
ACHD Project Name
(City Project Name)ACHD Project Description
Current Programming Status
Boise's Request
55 44
Emerald St, Curtis Rd / Orchard
St
Emerald, Curtis to Orchard, sidewalk No $5.37 Defer. Operating at LOS D. (City
request for sidewalks will be built with
the roadway widening.)
Widen Emerald St to 5‐lanes with curb, gutter, sidewalk and bike lane in
accordance with the 2012 CIP. (City request is for sidewalk on both sides.
Due to significant cross slope issues, roadway will need to be rebuilt.
Roadway will be widening to CIP lanes at the same time.)
56 45
Bogus Basin Rd, Curling Dr / 550'
N/O Curling Dr (Bogus Basin,
east of Curling Dr)
Fill sidewalk gaps of approximately 500 feet north of Curling Drive Yes (106) 2018 2019 2020 $0.36 Widen pavement and install curb, gutter, and atached sidewalk on both
sides of Bogus Basin to fill in a 550' gap north of Curling Dr. Install retaining
wall on east side as necessary.
1 2
State Street Alignment and Right‐
of‐Way Study
Expedite completion. No TBD Draft plan is a working document to be
used during design phase of State St
projects.
Expedite completion.
2 3
Neighborhood Bike and
Pedestrian Plan for the North
End/East End Planning Area
Complete a neighborhood pedestrian and bicycle plan. Next area is
the East End and the portion of the North End south of State Street.
No TBD ACHD to complete a North End‐
Highlands Neighborhood Plan in
FY2016. This area covers 28th to
Military Reserve, State to Hill and the
Highlands planning area.
Complete a neighborhood pedestrian and bicycle plan.
Studies
LTP ‐ Long Term Priority
PD ‐ Preliminary Development
CN ‐ Construction Year Page 8 of 8
![Page 42: Kent Goldthorpe, President Paul Woods, Vice President ...€¦ · 2016. Project is part of ITD's Strategic Initiatives request for FY2021. ACHD with ITD on any improvement if funded](https://reader030.vdocuments.net/reader030/viewer/2022041118/5f2f3aeb5603fd337e77e47c/html5/thumbnails/42.jpg)
Attachment 3
Boise School District 2016 Requests and ACHD Proposed Response
In IFYWP
(Page)DSN YR ROW YR CN YR
Total
Cost in
Millions
Programming Notes
Road and Intersection
1 IN205‐
18
Bergeson St and Law
Ave
Signalize intersection to improve safety. No $0.68 Location does not warrant a
traffic signal based on volumes
and crash history. ACHD to
clarify purpose with the School
District.
Community Programs
1 1 CM215‐
03
Bogart Ln, SH 44 (State
St) / Hill Road Pkwy
Widen shoulders on both sides and complete curb, gutter, and detached
sidewalk on the east side of Bogart Ln between Hwy 44 and Hill Rd Pkwy.
Widen bridge #41 over Eagle Drain as necessary. Install an enhanced
pedestrian crossing at Sloan St.
Yes
(106)
2020 PD PD $1.32 Programmed to begin design in FY2020. ACHD
to evaluate project construction moving
forward through IFYWP update.
2 2 CM214‐
24
Caswell St, Bogart Ln /
Roe St
Complete sidewalk on both sides of Caswell between Bogart Ln an Roe St. No $0.29 Scoped "Go" in 2015, but defer until
development. ACHD to review for
programming in 2018.
3 NEW Warm Springs Ave,
Glacier Dr / Glacier Dr
Construct sidewalk on the north side of Warm Springs Ave, between Glacier Dr
E and Glacier Dr W.
No TBD Prioritize and scope.
4 4 CM212‐
07
Alpine St, Orchard St /
Randall St
Complete sidewalk on the south side of Alpine St from Orchard St to Randall St
in accordance with the Central Bench Neighborhood Plan.
Yes
(104)
2016 2016 2017 $0.64 To be built in FY2017.
5 6 CM211‐
14
Owyhee St, Malad St /
Overland Rd (east side)
Complete curb, gutter and sidewalk on the east side of Owyhee St, between
Malad St and Overland Rd in accordance with the Central Bench Neighborhood
Plan.
Yes
(118)
Done Done 2016 $0.46 Construction to start summer 2016.
6 8 3341 Targee St School Zone Install flashing school zone beacons near Hawthorne Elementary. No TBD Traffic analysis complete. ACHD Traffic analysis showed good compliance
with the existing 20 mph speed limit.
Recommend no additional treatment at this
time.
7 9 CM211‐
24
State St and Mercer St
or Arthur St Pedestrian
Signal
See description for priority #11 below. Yes
(121)
Done Done 2016 $0.47 School District request for
pedestrian signal will be
completed as part of sidewalk
project.
Construction to start summer 2016.
8 13 CM215‐
22
15th St and Resseguie
St Pedestrian Crossing
Install an enhanced pedestrian crossing (rectangular rapid flashing beacon) on
the south leg of the intersection. Project will also remove markings for crossing
on the north leg to encourage use of new signal.
No TBD Traffic analysis complete. Prioritize and scope.
9 NEW Ustick Rd and
Milwaukee St
Install flashing school zone beacons at the intersection of Ustick Rd and
Milwaukee St for students at Valley View Elementary School.
No TBD ACHD Traffic Engineering to evaluate location
for warrants.
ACHD Proposed Response
2016 SD
Priority
Ranking
2015 SD
Priority
Ranking
GIS # ACHD Project Name Project Description
Current Programming Status
PD ‐ Preliminary Development
CN ‐ Construction Year Page 1 of 6
![Page 43: Kent Goldthorpe, President Paul Woods, Vice President ...€¦ · 2016. Project is part of ITD's Strategic Initiatives request for FY2021. ACHD with ITD on any improvement if funded](https://reader030.vdocuments.net/reader030/viewer/2022041118/5f2f3aeb5603fd337e77e47c/html5/thumbnails/43.jpg)
Attachment 3
In IFYWP
(Page)DSN YR ROW YR CN YR
Total
Cost in
Millions
Programming NotesACHD Proposed Response
2016 SD
Priority
Ranking
2015 SD
Priority
Ranking
GIS # ACHD Project Name Project Description
Current Programming Status
10 14 CM213‐
05
Christine St, Northview
St / Ustick Rd
Construct sidewalk on both sides of Christine, from Northview to Ustick in
accordance with the West Bench Neighborhood Plan.
Yes
(108)
2017 2018 2019 $0.45 To be built in FY2019.
11 15 CM211‐
24
State St, Willow Ln /
Veterans Pkwy (south
side)
Complete sidewalks on the southside of State St, between Willow Ln and VMP,
and install an enhanced pedestrian corssing at Arthur St in accordance with the
State St TTOP and the State St/VMP/36th St Intersection Concept Design.
Yes
(121)
Done Done 2016 $0.47 Project also completes School
District priority #9.
Construction to start summer 2016.
12 16 CM210‐
70
Overland Rd,
Columbus St / Federal
Way
Complete curb, gutter and sidewalk on both sides of Overland Rd, between
Columbus St and Federal Way in accordance with the Central Bench
Neighborhood Plan. Includes an improved UPRR crossing.
Yes
(118)
2016 2016 2018 $1.11 To be built in FY2018.
13 17 CM215‐
13
13th St and Resseguie
St Pedestrian Signal
Install an enhanced pedestrian crossing at the intersection. No TBD ACHD Traffic Engineering to evaluate location
for warrants.
14 18 CM211‐‐
34
Pierce St, Washington
St / Shenandoah Dr
Complete sidewalks on Pierce Street, between Washington St and Shenandoah
Dr to improve pedestrian safety students walking to Roosevelt Elementary.
Yes
(120)
2018 2019 2020 $0.76 To be built in FY2020.
15 19 CGSP20
5‐16
Liberty St, Franklin Rd
/ Emerald St
Complete sidewalk on the east side of Liberty St in accordance with the Central
Bench Neighborhood Plan.
Yes
(116)
2016 2017 2019 $0.54 Project scope originally assumed completion of
bridge and RRX widening to occur with
improvements at Liberty and Franklin
intersection. That project did not move
forward, thus placing much added expense
($2.5 million) to sidewalk project. Project will
be pushed back in IFYWP update until bridge
widening can be completed.
16 20 CM210‐
25
Camas St, Orchard St /
Roosevelt St
Construct sidewalk on both sides of Camas Street from Orchard Street to
Roosevelt Street in accordance with the Central Bench Neighborhood Plan.
Project to include roadway reclamation.
Yes
(107)
2016 2016 2017 $1.17 To be built in FY2017.
17 NEW Maple Grove Rd, N/O
Victory Rd
Relocate pedestrian crossing and flashing school zone beacons to ensure
proper location with new park and school parking redesign.
No TBD ACHD and Boise School District to coordinate
potential project and cost share as planned
projects move forward.
18 21 PPI208‐
22
Garden St, Franklin Rd
/ Emerald St
Construct curb, gutter and sidewalk on both sides of Garden Street from
Emerald St to Franklin Road to provide pedestrian connectivity in an
established neighborhood. Fill in the missing sidewalk across 2 lots on the
northwest corner of Emerald.
No $2.57 Scoped in 2011. ACHD to evaluate potential
programming during IFYWP update. Delay in
programming due to high project cost.
19 22 CM211‐
22
Poplar St, Cole Rd /
Raymond St (north
side)
Complete curb, gutter, and sidewalk on the north side of Poplar St, between
Cole Rd and Raymond St in accordance with the West Bench Neighborhood
Plan.
Yes
(120)
2016 2017 2019 $0.62 To be built in FY2019.
20 23 CM215‐
24
14th St and Fort St
Pedestrian Signal
Install an enhanced pedestrian crossing (rectangular rapid flashin beacon) on
both sides of the existing crosswalk across Fort St to North JHS.
No $0.20 Scoped "Go" in 2015. ACHD to evaluate
potential programming during IFYWP update.
PD ‐ Preliminary Development
CN ‐ Construction Year Page 2 of 6
![Page 44: Kent Goldthorpe, President Paul Woods, Vice President ...€¦ · 2016. Project is part of ITD's Strategic Initiatives request for FY2021. ACHD with ITD on any improvement if funded](https://reader030.vdocuments.net/reader030/viewer/2022041118/5f2f3aeb5603fd337e77e47c/html5/thumbnails/44.jpg)
Attachment 3
In IFYWP
(Page)DSN YR ROW YR CN YR
Total
Cost in
Millions
Programming NotesACHD Proposed Response
2016 SD
Priority
Ranking
2015 SD
Priority
Ranking
GIS # ACHD Project Name Project Description
Current Programming Status
21 24 CM211‐
21
Aurora Dr, Randolph
Dr, and Cameron St
See description for priority #23 below. Yes
(107)
Done 2016 2019 $0.53 Intersection improvements to be built as part
of sidewalk project on Cameron St.
22 25 CM213‐
12
Cassia St, Latah St /
Edson St
Complete sidewalk on the north side of Cassia St and upgrade pedestrian
ramps on both sides between Latah St and Edson St in accordance with the
Central Bench Neighborhood Plan.
Yes
(107)
2018 2019 2020 $1.04 To be built in FY2020. School District requested
sidewalk on both sides. Sidewalk already exists
on the south side.
23 26 CM211‐
21
Cameron St, Hummel
Dr / Aurora Dr
(Cameron St, Holiday
Dr/Randolph Dr)
Construct sidewalk on Cameron Street from Hummel to Randolph in
accordance with the Central Bench Neighborhood Plan. Includes pedestrian
improvements to the Cameron, Randolph, and Aurora intersection.
Yes
(107)
Done 2016 2019 $0.53 To be built in FY2019.
24 NEW Curling Dr, at
Highlands Elementary
Provide pedestrian safety improvements in front of Highlands Elementary
School.
No TBD Project to move forward pending outcome of
the traffic calming evaluations for the
Highlands neighborhood.
25 27 CM215‐
25
Bogus Basin Rd and
Curling St Pedestrian
Crossing
Install an enhanced pedestrian crossing at the intersection. No TBD Project to move forward pending outcome of
the traffic calming evaluations for the
Highlands neighborhood.
26 10 3341 Sloan St School Zone Install flashing school zone beacons near Shadow Hills Elementary. No TBD Traffic analysis complete. Prioritize and scope.
27 28 CM215‐
26
Troxel Dr and Cassia St
Pedestrian Crossing
Install an enhanced pedestrian crossing (rectangular rapid flashing beacon) at
the intersection.
No TBD Traffic analysis complete. Prioritize and scope.
28 29 CM210‐
24
Clark St, Orchard St /
Roosevelt St
Construct sidewalk on both sides of Clark St between Orchard St and Roosevelt
St to provide pedestrian connectivity and reduce the need for safety busing for
Monroe Elementary School.
Yes
(108)
2016 2016 2018 $1.00 To be built in FY2018.
29 30 CM213‐
09
Linda Vista Ln,
Canterbury Dr / Ustick
Rd (Linda Vista Ln,
Cory Ln / Ustick Rd)
Complete curb, gutter, and sidewalk on west side of Linda Vista Ln, between
Canterbury Dr and Ustick Rd. (School District request was for sidewalk on both
sides)
Yes
(116)
2020 2020 PD $0.69 District request partially
moving forward. Focus on
more developed section.
Remaining section on hold
pending development.
Programmed to begin design in FY2020. ACHD
to evaluate project construction moving
forward through IFYWP update.
30 32 CGSP20
6‐16
Cory Ln, Mitchell St /
Maple Grove Rd
Complete sidewalk on the north side of Cory Ln, between Maple Grove Rd and
Mitchell St for students attending Valley View Elementary.
No $0.29 Scoped "Go" in 2015. ACHD to evaluate
potential programming during IFYWP update.
31 33 CM213‐
15
Franklin St, McKinley
St / Pierce St
Construct sidewalks on the north side of Franklin St, between McKinley St and
Pierce St.
No $0.37 Scoped "Go" in 2015. ACHD to evaluate
potential programming during IFYWP update.
32 NEW Curling Dr and
Braemere Rd
Provide pedestrian enhancements at the intersection of Curling Dr and
Braemere Rd.
No TBD Project to move forward pending outcome of
the traffic calming evaluations for the
Highlands neighborhood.
PD ‐ Preliminary Development
CN ‐ Construction Year Page 3 of 6
![Page 45: Kent Goldthorpe, President Paul Woods, Vice President ...€¦ · 2016. Project is part of ITD's Strategic Initiatives request for FY2021. ACHD with ITD on any improvement if funded](https://reader030.vdocuments.net/reader030/viewer/2022041118/5f2f3aeb5603fd337e77e47c/html5/thumbnails/45.jpg)
Attachment 3
In IFYWP
(Page)DSN YR ROW YR CN YR
Total
Cost in
Millions
Programming NotesACHD Proposed Response
2016 SD
Priority
Ranking
2015 SD
Priority
Ranking
GIS # ACHD Project Name Project Description
Current Programming Status
33 34 CM211‐
25
Roosevelt St, Rose Hill
St / Emerald St (west
side)
Construct sidewalk on the west side of Roosevelt St, between Rose Hill St and
Emerald St in accordance with the Central Bench Neighborhood Plan.
Yes
(121)
2016 2017 2019 $1.00 To be built in FY2019.
34 35 CM213‐
11
Milwaukee St, Marcum
St/Ustick Rd
Install curb, gutter, and sidewalk on the west side of Milwaukee St, between
Marcum St and Ustick Rd. Sidewalk would be placed between the canal and the
roadway.
No $1.00 Scoped "Go" in 2014. ACHD to evaluate
potential programming during IFYWP update.
35 36 CM214‐
21
Phillippi St, Overland
Rd / Franklin Rd
Rebuild roadway to include 8' detached sidewalk, parking, 5' bike lanes, 2 auto
lanes, and a center turn land/island. Full rebuild of roadway required due to
steep cross slope issues. Includes pedestrian signal at Phillippi St / Overland Rd
intersection on west side and replacement of bridge #1366 or #404.
No TBD Scoped in 2015. Further refinement of scope
underway due to high cost associated with
sidewalk project and roadway crown issues.
36 49 CM210‐
19
Braemere Rd, Highland
View Dr / Curling Dr
Construct sidewalk and vertical curb on Braemere Road between Highland
View Drive and Curling Drive to improve safety for students walking to and
from Highlands Elementary School.
No $0.76 Scoped. Project to move forward pending
outcome of traffic calming evaluations for the
Highlands neighborhood.
37 NEW Braemere Rd and
Highland View Dr
Provide pedestrian enhancements at the intersection of Braemere Rd and
Highland View Dr.
No TBD Project to move forward pending outcome of
the traffic calming evaluations for the
Highlands neighborhood.
38 11 3341 Hidden Springs Drive
School Zone
Install flashing school zone beacons near Hidden Springs Elementary. No TBD Traffic analysis complete. Prioritize and scope.
39 NEW E. Braemere Rd Provide pedestrian improvements along E. Braemere Rd above the Crane
Creek Country Club.
No TBD Project to move forward pending outcome of
the traffic calming evaluations for the
Highlands neighborhood. Sidewalks already
exist the full length of E. Braemere Rd.
40 NEW 38th St, Sunset Ave /
Taft St
Connect roadway and complete curb, gutter sidewalk on 38th St, between
Sunset Ave and Taft St.
No $0.44 Scoped "Go" in 2015. ACHD to evaluate
potential programming during IFYWP update.
41 37 CM211‐
30
Targee St, Maple
Grove Rd / Penninger
Dr
Complete sidewalks on the south side of Targee St, between Maple Grove Rd
and Penninger Dr to create a safe walking route to Maple Grove Elementary.
Yes
(122)
Done 2016 2017 $0.44 To be built in FY2017.
42 38 CM211‐
26
Fairfield Ave, Holiday
Dr S / Holiday Dr N
Construct sidewalks on the south side of Fairfield Ave between Holiday Dr
intersections in accordance with the Central Bench Neighborhood Plan.
Yes
(110)
Done 2016 2019 $0.36 To be built in FY2019.
43 39 BK213‐
04
Shoshone St Bikeway,
Linden St / Greenbelt
(Shoshone St and Rose
Hill St Pedestrian
Signal)
Improve Shoshone St as a bikeway to include wayfinding signage, shared lane
markings, signal modification at Overland Rd, and pedestrian ramps in
accordance with the Central Bench Neighborhood Plan. Project includes an
enhanced pedestrian signal to replace existing flashing caution light at Rose Hill
St. (School District requested flashing light be replaced with pedestrian signal)
Yes
(127)
2020 PD PD $0.12 School District request for
pedestrian signal will be
completed as part of bikeway
project.
Concept design to begin in FY2018. ACHD to
evaluate potential opportunities to advance
construction during IFYWP update.
PD ‐ Preliminary Development
CN ‐ Construction Year Page 4 of 6
![Page 46: Kent Goldthorpe, President Paul Woods, Vice President ...€¦ · 2016. Project is part of ITD's Strategic Initiatives request for FY2021. ACHD with ITD on any improvement if funded](https://reader030.vdocuments.net/reader030/viewer/2022041118/5f2f3aeb5603fd337e77e47c/html5/thumbnails/46.jpg)
Attachment 3
In IFYWP
(Page)DSN YR ROW YR CN YR
Total
Cost in
Millions
Programming NotesACHD Proposed Response
2016 SD
Priority
Ranking
2015 SD
Priority
Ranking
GIS # ACHD Project Name Project Description
Current Programming Status
44 40 CGSP20
6‐03
Dalton Ln, Cory Ln /
Ustick Rd
Install sidewalk on both sides of the roadway to match the existing paved
sidewalk sections. (School District requested sidewalk on the east side)
No $0.28 Scoped "Go". ACHD to evaluate potential
programming during IFYWP update.
45 42 CM213‐
14
Kimball St, Cory Ln /
Ustick Rd
Construct sidewalks on west side of Kimball St from Ustick Rd to Cory Ln. No $0.32 Scoped "Go" in 2015, but defer until
development. ACHD to review for
programming in 2018.
46 43 CGSP20
6‐05
Taft St, Sycamore Dr /
36th St
Construct sidewalk on the south side of Taft St, between Sycamore to 36th St,
by relocating curb and narrowing roadway. Parking will be limited to only one
side.
No $1.80 Scoped "Go" in 2015. ACHD to evaluate
potential programming during IFYWP update.
47 45 CM215‐
10
Sunflower Ln, Yonkers
Ln/Maple Grove Rd
Construct sidewalk on the north side of Sunflower Ln, between Yonkers Ln and
Maple Grove Rd.
No $0.32 Scoped "Go" in 2015. ACHD to evaluate
potential programming during IFYWP update.
48 NEW Warm Springs, Parsnip
Peak Dr / Barber Dr
Construct sidewalk on Warm Springs Ave, between Parsnip Peak Dr and Barber
Dr
No TBD Prioritize and scope.
49 48 CM210‐
61
Annett St, Malad
St/Targee St
Construct sidewalk on the west side of Annett St, between Malad St and
Targee St, by moving curb out and removing on‐street parking to avoid
property impacts.
No $0.49 Scoped "Go" in 2015. ACHD to evaluate
potential programming during IFYWP update.
50 NEW Cole Rd and Diamond
St Pedestrian Crossing
Install an enhanced pedestrian crossing on Cole Rd at Diamond St to improve
safety for students attending West Junior High.
No TBD ACHD to consider signal for inclusion in the
Cole Rd and Victory Rd intersection project.
This project will widen Cole Rd, from Victory to
McGlochlin.
Study (Pathway Feasibility)
1 N/A Pathway ‐ Maple
Grove Rd/Bienapfl
Pathway between Maple Grove and West Jr High No N/A ACHD has no unopened right‐of‐way in this
area and cannot acquire additional right‐of‐
way through eminent domain for a pathway.
Recommend the School District work with the
City of Boise to obtain a pathway through
development.
2 N/A Pathway ‐ Targee
between
Milwaukee/Maple
Grove
Pathway between Milwaukee and Maple Grove to access Maple Grove
Elementary
No N/A ACHD has no unopened right‐of‐way in this
area and cannot acquire additional right‐of‐
way through eminent domain for a pathway.
Recommend the School District work with the
City of Boise to obtain a pathway through
development.
PD ‐ Preliminary Development
CN ‐ Construction Year Page 5 of 6
![Page 47: Kent Goldthorpe, President Paul Woods, Vice President ...€¦ · 2016. Project is part of ITD's Strategic Initiatives request for FY2021. ACHD with ITD on any improvement if funded](https://reader030.vdocuments.net/reader030/viewer/2022041118/5f2f3aeb5603fd337e77e47c/html5/thumbnails/47.jpg)
Attachment 3
In IFYWP
(Page)DSN YR ROW YR CN YR
Total
Cost in
Millions
Programming NotesACHD Proposed Response
2016 SD
Priority
Ranking
2015 SD
Priority
Ranking
GIS # ACHD Project Name Project Description
Current Programming Status
3 N/A Pathway ‐ Between
Mossy Cup or
Chinkapin Ave
Pathway between Mossy Cup and Chinkapin to access Maple Grove
Elementary
No N/A ACHD has no unopened right‐of‐way in this
area and cannot acquire additional right‐of‐
way through eminent domain for a pathway
that would connect into the park. Recommend
the School District work with the City of Boise
to obtain a pathway through development of
the park.
4 N/A Pathway ‐ Between
Gary Ln/Pierce Park Ln
Pathway between Gary Ln and Pierce Park Ln and Pierce Park Ln No N/A ACHD has no unopened right‐of‐way in this
area and cannot acquire additional right‐of‐
way through eminent domain for a pathway.
Recommend the School District work with the
City of Boise to obtain a pathway through
development.
5 N/A Pathway ‐ Between
North St/Bloom St
Pathway between North St and Bloom St west of Collister No N/A ACHD has no unopened right‐of‐way in this
area and cannot acquire additional right‐of‐
way through eminent domain for a pathway.
Recommend the School District work with the
City of Boise to obtain a pathway through
development.
6 N/A Pathway ‐ Between
Willow Ln and
Alomosa St
Pathway between Willow and Alomosa No N/A ACHD has unopened right‐of‐way in this area.
On hold due to public opposition. To be
explored again when State St expands to 7
lanes.
PD ‐ Preliminary Development
CN ‐ Construction Year Page 6 of 6
![Page 48: Kent Goldthorpe, President Paul Woods, Vice President ...€¦ · 2016. Project is part of ITD's Strategic Initiatives request for FY2021. ACHD with ITD on any improvement if funded](https://reader030.vdocuments.net/reader030/viewer/2022041118/5f2f3aeb5603fd337e77e47c/html5/thumbnails/48.jpg)
![Page 49: Kent Goldthorpe, President Paul Woods, Vice President ...€¦ · 2016. Project is part of ITD's Strategic Initiatives request for FY2021. ACHD with ITD on any improvement if funded](https://reader030.vdocuments.net/reader030/viewer/2022041118/5f2f3aeb5603fd337e77e47c/html5/thumbnails/49.jpg)
![Page 50: Kent Goldthorpe, President Paul Woods, Vice President ...€¦ · 2016. Project is part of ITD's Strategic Initiatives request for FY2021. ACHD with ITD on any improvement if funded](https://reader030.vdocuments.net/reader030/viewer/2022041118/5f2f3aeb5603fd337e77e47c/html5/thumbnails/50.jpg)
![Page 51: Kent Goldthorpe, President Paul Woods, Vice President ...€¦ · 2016. Project is part of ITD's Strategic Initiatives request for FY2021. ACHD with ITD on any improvement if funded](https://reader030.vdocuments.net/reader030/viewer/2022041118/5f2f3aeb5603fd337e77e47c/html5/thumbnails/51.jpg)
![Page 52: Kent Goldthorpe, President Paul Woods, Vice President ...€¦ · 2016. Project is part of ITD's Strategic Initiatives request for FY2021. ACHD with ITD on any improvement if funded](https://reader030.vdocuments.net/reader030/viewer/2022041118/5f2f3aeb5603fd337e77e47c/html5/thumbnails/52.jpg)
![Page 53: Kent Goldthorpe, President Paul Woods, Vice President ...€¦ · 2016. Project is part of ITD's Strategic Initiatives request for FY2021. ACHD with ITD on any improvement if funded](https://reader030.vdocuments.net/reader030/viewer/2022041118/5f2f3aeb5603fd337e77e47c/html5/thumbnails/53.jpg)
![Page 54: Kent Goldthorpe, President Paul Woods, Vice President ...€¦ · 2016. Project is part of ITD's Strategic Initiatives request for FY2021. ACHD with ITD on any improvement if funded](https://reader030.vdocuments.net/reader030/viewer/2022041118/5f2f3aeb5603fd337e77e47c/html5/thumbnails/54.jpg)
![Page 55: Kent Goldthorpe, President Paul Woods, Vice President ...€¦ · 2016. Project is part of ITD's Strategic Initiatives request for FY2021. ACHD with ITD on any improvement if funded](https://reader030.vdocuments.net/reader030/viewer/2022041118/5f2f3aeb5603fd337e77e47c/html5/thumbnails/55.jpg)
![Page 56: Kent Goldthorpe, President Paul Woods, Vice President ...€¦ · 2016. Project is part of ITD's Strategic Initiatives request for FY2021. ACHD with ITD on any improvement if funded](https://reader030.vdocuments.net/reader030/viewer/2022041118/5f2f3aeb5603fd337e77e47c/html5/thumbnails/56.jpg)
![Page 57: Kent Goldthorpe, President Paul Woods, Vice President ...€¦ · 2016. Project is part of ITD's Strategic Initiatives request for FY2021. ACHD with ITD on any improvement if funded](https://reader030.vdocuments.net/reader030/viewer/2022041118/5f2f3aeb5603fd337e77e47c/html5/thumbnails/57.jpg)
Attachment 4
City of Eagle 2016 Requests and ACHD Proposed Response
In IFYWP
(Page)DSN YR ROW YR CN YR
Total
Cost in
Millions
Programming Notes
Road & Intersection
1 1 IN205‐
11
SH 16 and Beacon
Light Rd
Install a signal and add turn lanes as needed. ITD to lead project, with ACHD
participating in the design and cost. Subject to cooperative agreement and
programming with ITD.
Yes (49) 2016 2016 2017 $1.45 Project being led by ITD. To be built in FY2017 in partnership with ITD.
2 NEW Palmetto Ave, SH 44 /
Plaza Dr
Extend Palmetto Ave from Plaza Dr to SH 44. Install a right‐in/right‐out acces
onto SH‐44.
New TBD New request. Collector roadway to be built by development
or it could be considered as part of a future
economic development request.
3 2 IN211‐
04
Eagle Rd and State St Construct a quadrant intersection, including local system improvements, as per
the Eagle Rd and State St Intersection Concept Study.
No $4.23 Intersection operating at LOS C
or better. Roadway segment at
LOS E.
Prioritize and program. ACHD to complete
currently programmed collector and local road
improvements prior to programming
construction.
4 3 RD209‐
27
Eagle Rd, Floating
Feather Rd / Beacon
Light Rd
Widen shoulders for bike lanes and complete curb, gutter, and sidewalk on
both sides of Eagle Rd, between Floating Feather Rd and Beacon Light Rd.
No $0.87 Project to be prioritized as a
community programs project.
Scoped "Go" in 2015. ACHD to evaluate
potential programming during IFYWP update
as a community programs project.
Floating Feather
Corridor Study
Study to evaluate Floating Feather Rd, between Linder Rd and Eagle Middle
School with emphasis on expansion to 3 lanes, bike lanes, detached sidewalks
and other improvements including the following:
No Based on study description in request, ACHD
can proceed with programming individual
projects without additional study. Corridor
currently operating at an acceptable level of
service. ACHD to seperately evaluate
intersections listed below as follows:
Floating Feather Rd
and Linder Rd
Install signal No ACHD Traffic Engineering to evaluate location
for signal warrants.
Floating Feather and
Ballantyne Rd
Improve intersection including east leg No ACHD Traffic Engineering to evaluate location
for signal warrants.
Floating Feather Rd
and Park Ln
Improve intersection specifically for bike and pedestrian flow. Review school
peak hour congestion
No Prioritize and scope as a Community Programs
project.
6 5 RD209‐
28
Linder Rd, SH 44 /
Floating Feather Rd
Widen Linder Rd to 5‐lanes, with curb, gutter, sidewalk, and bike lanes in
accordance with the 2012 CIP.
No $3.30 Roadway currently operating at a level of
service C or better. Defer until warranted.
7 6 RD207‐
19
Linder Rd, Chinden
Blvd (US 20/26) / SH
44 (State St) (Linder
Rd, Boise River/SH 44)
Widen Linder Rd to 5‐lanes, with curb, gutter, sidewalk, and bike lanes in
accordance with the 2012 CIP.
No $22.95 Project combined with priority
#8.
Prioritized (Ranks 70 of 78). Awaits
programming.
1180 Evaluate and scope individual
projects as warranted.
TBD
ACHD Proposed Response
Current Programming Status2016
City
Priority
Ranking
2015
City
Priority
Ranking
GIS # ACHD Project Name Project Description
5 4
PD ‐ Preliminary Development
CN ‐ Construction Year Page 1 of 3
![Page 58: Kent Goldthorpe, President Paul Woods, Vice President ...€¦ · 2016. Project is part of ITD's Strategic Initiatives request for FY2021. ACHD with ITD on any improvement if funded](https://reader030.vdocuments.net/reader030/viewer/2022041118/5f2f3aeb5603fd337e77e47c/html5/thumbnails/58.jpg)
Attachment 4
In IFYWP
(Page)DSN YR ROW YR CN YR
Total
Cost in
Millions
Programming NotesACHD Proposed Response
Current Programming Status2016
City
Priority
Ranking
2015
City
Priority
Ranking
GIS # ACHD Project Name Project Description
8 7 RD207‐
19
Linder Rd, Chinden
Blvd (US 20/26) / SH
44 (State St) (Linder
Rd, Chinden Blvd/Boise
River)
Widen Linder Rd to 5‐lanes, with curb, gutter, sidewalk, and bike lanes in
accordance with the 2012 CIP.
No $22.95 Project combined with priority
#7.
Prioritized (Ranks 70 of 78). Awaits
programming.
9 8 RD209‐
25
Beacon Light Rd, SH 55
/ SH 16
Preserve right‐of‐way for up to 3 lanes. No N/A Approved by ACHD Commission action on
February 24, 2016.
10 9 RD209‐
29
Floating Feather Rd
Alignment
Realign roadway in accordance with the Floating Feather Realignment Study.
Install curb, gutter, and sidewalk.
No TBD New alignment to be built through
development.
11 10 C202‐01 Three Cities River
Crossing
Construct a new bridge between SH 44 and US 20/26. No $82.50 ACHD Commission selected the "no build"
option on July 21, 2010.
Community Programs
1 1 CM214‐
13
Park Ln and Cardon St
(Eagle High School)
Pedestrian Crossing
Install and enhanced pedestrian crossing and curb ramps for students crossing
Park Ln to access Eagle High School.
Yes
(119)
2016 2016 2017 $0.08 To be built in FY2017.
Horseshoe Bend Rd
and Floating Feather
Rd Pedestrian Crossing
Convert intersection to an all‐way stop and install pedestrian crossing markings
and signage.
New Seperated request into two
projects for scoping and
programming purposes.
Prioritize and scope.
Horseshoe Bend Rd
and Bucktail Dr
Pedestrian Crossing
Install an enhanced pedestrian crossing near the intersection of Horseshoe
Bend Rd and Bucktail Dr.
New Seperated request into two
projects for scoping and
programming purposes.
Prioritize and scope. ACHD Traffic Engineering
to evaluate location for signal warrants.
CM214‐
26
Horseshoe Bend Rd,
State St / Hill Rd
Complete detached sidewalks, curb & gutter, seepage beds, bike lanes on both
sides of Horseshoe Bend Rd. Widen shoulder on the west side for parallel
parking. Project includes road rehabilitation due to poor pavement condition.
(City request is for 3‐lane cross section)
Yes
(114)
PD PD PD $1.68 Project programmed in preliminary
development. Will evaluate opportunities to
move forward through IFYWP update.
Proposed scopes seeks to address the request
for bike and ped facilities while minimizing
right‐of‐way/topography impacts.
PPI208‐
52
Hill Rd, Hwy 55 /
Horseshoe Bend Rd
Install bike lanes and a paved pathway with raised curb on both sides of Hill Rd,
between Hwy 55 and Horseshoe Bend Rd in accordance with the Northwest
Boise Neighborhood Plan. Project includes road rehabilitation due to poor
pavement condition.
No TBD Project to be built when the intersection of Hill
Rd and Horseshoe Bend Rd is widened.
Intersection is currently operating at at a level
of service C or better.
4 4 CM211‐
63
SH 44, Edgewood Ln /
Horseshoe Bend Rd
Install pedestrian improvements. No N/A ACHD has no right‐of‐way at this location.
ACHD to share request with ITD.
2 NEW
3 3
PD ‐ Preliminary Development
CN ‐ Construction Year Page 2 of 3
![Page 59: Kent Goldthorpe, President Paul Woods, Vice President ...€¦ · 2016. Project is part of ITD's Strategic Initiatives request for FY2021. ACHD with ITD on any improvement if funded](https://reader030.vdocuments.net/reader030/viewer/2022041118/5f2f3aeb5603fd337e77e47c/html5/thumbnails/59.jpg)
Attachment 4
In IFYWP
(Page)DSN YR ROW YR CN YR
Total
Cost in
Millions
Programming NotesACHD Proposed Response
Current Programming Status2016
City
Priority
Ranking
2015
City
Priority
Ranking
GIS # ACHD Project Name Project Description
5 5 RD209‐
25
Beacon Light Rd, SH 55
/ SH 16
Install sidewalks and bike lanes on Beacon Light Rd, between SH 55 and SH 16. No TBD ACHD to implement improvements with
development or maintenance where feasible.
6 2 IN205‐
48
Eagle Rd and Ranch Dr
Pedestrian Signal
Install an enhanced pedestrian crossing and curb ramps on Eagle Rd at Ranch
Dr.
No TBD Defer. Traffic evaluation shows minimal
crossings at this location.
7 6 N/A Dry Creek Pedestrian
Underpass
Connect pathway from SH 44 (existing pathway) to Dry Creek Valley. No N/A ACHD will support a City‐led effort.
8 NEW SH 44 Bike/ Pedestrian
Crossing
Install a grade seperated bike and pedestrian crossing of SH 44 between Eagle
Rd and Edgewood Ln.
No TBD ACHD will support a City‐led effort. ACHD will
evaluate partnership opportunities for
improvements made within the ACHD right‐of‐
way.
9 NEW State St and Stierman
Way Pedestrian Signal
Install an enhanced pedestrian signal on State St at Stierman Way. No TBD Prioritize and scope. ACHD Traffic Engineering
to evaluate location for signal warrants.
1 (Econ.
Devel.)
1 (Econ.
Devel.)
RD203‐
08
Plaza Dr, 02nd St / Iron
Eagle Dr
Construct a new 2‐lane roadway alignment with curb, gutter, detached
pathway on the north side, and bike lanes between the existing Plaza
alignments, in accordance with the Eagle Rd and State St Intersection Concept
Study.
Yes
(129)
Done 2016 2017 $1.35 To be built in FY2017 in partnership with the
City of Eagle.
2 (Econ.
Devel.)
2 (Econ.
Devel.)
RD209‐
11
Aikens St, Eagle Rd /
2nd St
Extend Aikens Rd east to 2nd St from its current terminus and complete the
street section with curb, gutter, and sidewalk in accordance with the Eagle Rd
and State St intersection concept study.
Yes
(128)
2017 2018 2019 $1.40 To be built in FY2019.
PD ‐ Preliminary Development
CN ‐ Construction Year Page 3 of 3
![Page 60: Kent Goldthorpe, President Paul Woods, Vice President ...€¦ · 2016. Project is part of ITD's Strategic Initiatives request for FY2021. ACHD with ITD on any improvement if funded](https://reader030.vdocuments.net/reader030/viewer/2022041118/5f2f3aeb5603fd337e77e47c/html5/thumbnails/60.jpg)
![Page 61: Kent Goldthorpe, President Paul Woods, Vice President ...€¦ · 2016. Project is part of ITD's Strategic Initiatives request for FY2021. ACHD with ITD on any improvement if funded](https://reader030.vdocuments.net/reader030/viewer/2022041118/5f2f3aeb5603fd337e77e47c/html5/thumbnails/61.jpg)
![Page 62: Kent Goldthorpe, President Paul Woods, Vice President ...€¦ · 2016. Project is part of ITD's Strategic Initiatives request for FY2021. ACHD with ITD on any improvement if funded](https://reader030.vdocuments.net/reader030/viewer/2022041118/5f2f3aeb5603fd337e77e47c/html5/thumbnails/62.jpg)
![Page 63: Kent Goldthorpe, President Paul Woods, Vice President ...€¦ · 2016. Project is part of ITD's Strategic Initiatives request for FY2021. ACHD with ITD on any improvement if funded](https://reader030.vdocuments.net/reader030/viewer/2022041118/5f2f3aeb5603fd337e77e47c/html5/thumbnails/63.jpg)
![Page 64: Kent Goldthorpe, President Paul Woods, Vice President ...€¦ · 2016. Project is part of ITD's Strategic Initiatives request for FY2021. ACHD with ITD on any improvement if funded](https://reader030.vdocuments.net/reader030/viewer/2022041118/5f2f3aeb5603fd337e77e47c/html5/thumbnails/64.jpg)
![Page 65: Kent Goldthorpe, President Paul Woods, Vice President ...€¦ · 2016. Project is part of ITD's Strategic Initiatives request for FY2021. ACHD with ITD on any improvement if funded](https://reader030.vdocuments.net/reader030/viewer/2022041118/5f2f3aeb5603fd337e77e47c/html5/thumbnails/65.jpg)
![Page 66: Kent Goldthorpe, President Paul Woods, Vice President ...€¦ · 2016. Project is part of ITD's Strategic Initiatives request for FY2021. ACHD with ITD on any improvement if funded](https://reader030.vdocuments.net/reader030/viewer/2022041118/5f2f3aeb5603fd337e77e47c/html5/thumbnails/66.jpg)
![Page 67: Kent Goldthorpe, President Paul Woods, Vice President ...€¦ · 2016. Project is part of ITD's Strategic Initiatives request for FY2021. ACHD with ITD on any improvement if funded](https://reader030.vdocuments.net/reader030/viewer/2022041118/5f2f3aeb5603fd337e77e47c/html5/thumbnails/67.jpg)
Attachment 5
City of Kuna 2016 Requests and ACHD Proposed Response
In IFYWP
(Page)DSN YR ROW YR CN YR
Total Cost
in
Millions
Programming Notes
Road & Intersection
1 2 IN207‐
01
Linder Ave and Main St
and 3rd St Roundabout
Construct a single‐lane roundabout and pedestrian facilities at the intersection
of Main Street/3rd Street/Linder Avenue to improve vehicular mobility and
capacity.
Yes (49) Done Done 2016 $1.18 Under construction. Expected completion in
July 2016.
2 1 IN211‐
01
Linder Rd and Deer
Flat Rd
Federal aid project to improve intersection of Linder Rd and Deer Flat Rd,
including curb, gutter, sidewalk and bike lanes. Right‐of‐way funding will
advance to a year prior to construction as funds become available.
Yes (45) 2016 2020 2020 $3.34 To be built in FY2020.
6 N/A Kay St, Deer Flat Rd /
Boise St
Construct curb, gutter, sidewalk and on‐street parking on the east side of Kay
St, between Deer Flat Rd and Boise St.
No N/A Improvements to the east side of Kay St to be
built through development. Complete sidewalk
currently exists on the west side of Kay St.
NEW N/A Deer Flat Rd and Kay St Install traffic signal or add a left turn lane from Kay onto Deer Flat due to traffic
concerns prior to and after school.
No N/A Location did not meet warrants for additional
traffic control when investigated in 2015.
ACHD Traffic Engineering to review to
determine if conditions have changed.
4 3 CM214‐
10
Deer Flat Rd and Kuna
HS Pedestrian Crossing
(Deer Flat Rd, Kuna
High School/LDS
Church)
Install an enhanced pedestrian crossing on Deer Flat Rd east of the central
driveway of Kuna HS. Project also includes completion of of sidewalk on the
north side of Deer Flat from where it ends near the west school boundary and
the identified signal location. (City request was for a deceleration lane at this
location.)
No $0.42 City request for a deceleration
lane to be evaluated as part of
this project.
Scoped "Go" in 2015. ACHD to evaluate
potential programming during IFYWP update.
5 8
Comm.
Prog.
CM215‐
12
Main St, Ave C / Ave A Streetscape improvements, including road reconstruction, wider sidewalks, on‐
street parking, drainage, and bike markings in accordance with Kuna
Downtown Corridor Plan.
No TBD ACHD to support a City‐led effort upon
clarification of expected partnership and
subsequent Commission approval.
6 9 MA215‐
05
Swan Falls Railroad
Overpass (Swan Falls
Rd and Shortline St)
Install a new bridge over Indian Creek and Union Pacific Railroad on Swan Falls
Rd in accordance with the Kuna Crossing Feasibility and Implementation Plan.
No $18.50 Included on ACHD's Master Street Map.
Project to occur in accordance with the Kuna
Crossing Feasibility and Implementation Plan.
7 NEW Main St, Ave E / Ave C Streetscape improvements, including road reconstruction, wider sidewalks, on‐
street parking, drainage, and bike markings in accordance with Kuna
Downtown Corridor Plan.
No TBD ACHD to support a City‐led effort upon
clarification of expected partnership and
subsequent Commission approval.
8 11 IN209‐
15
Avalon St/Kuna Rd and
Kay Ave
Install a traffic signal (5 x 3 intersection) in accordance with Kuna Downtown
Corridor Plan (Project I‐1).
No N/A Location did not meet warrants for additional
traffic control when investigated in 2015.
ACHD Traffic Engineering to review to
determine if conditions have changed.
3
ACHD Proposed Response
2016
City
Priority
Ranking
2015
City
Priority
Ranking
GIS # ACHD Project Name Project Description
Current Programming Status
PD ‐ Preliminary Development
CN ‐ Construction Year Page 1 of 4
![Page 68: Kent Goldthorpe, President Paul Woods, Vice President ...€¦ · 2016. Project is part of ITD's Strategic Initiatives request for FY2021. ACHD with ITD on any improvement if funded](https://reader030.vdocuments.net/reader030/viewer/2022041118/5f2f3aeb5603fd337e77e47c/html5/thumbnails/68.jpg)
Attachment 5
In IFYWP
(Page)DSN YR ROW YR CN YR
Total Cost
in
Millions
Programming NotesACHD Proposed Response
2016
City
Priority
Ranking
2015
City
Priority
Ranking
GIS # ACHD Project Name Project Description
Current Programming Status
9 8 IN205‐
127
Ten Mile Rd and
Columbia Rd
Install a single‐lane expandable roundabout in accordance with the Ten Mile
Corridor Intersection Analysis.
No $1.34 Defer. Currently operating at a LOS C or better.
10 10 IN214‐
02
Ten Mile Rd and
Hubbard Rd
Install a multilane roundabout in accordance with the Ten Mile Corridor
Intersection Analysis.
No TBD Project is not identified in the 2012 CIP. Will
evaluate project for inclusion during the 2016
CIP update.
11 4 MMP21
3‐01
Kuna Mora Rd and
Cole Rd
Road improvements to sustain truck traffic Yes (88) 2016 2017 2018/
2019
$2.60 Maintenance project. To be built in FY2018/2019.
Community Programs
1 7 CM214‐
10 and
IN211‐
01
Deer Flat Rd, Linder Rd
/ Kay Ave
Install sidewalk. Partial
(45)
2016 2020 2020 $3.34 Costs show full cost of
intersection project. Project to
be complete as part of Road &
Intersection Priorities #2/#4
and Community Programs
Priority #4
To be built in FY2019. ACHD to evaluate
potential programming of sidewalk portion in
front of High School during IFYWP update.
2 1 CM214‐
04
Orchard St Greenbelt
Connection
Provide pedestrian and bicycle access to greenbelt extension via proposed
sidewalk/path in Orchard Street right of way. Install ADA ramps at south side of
Avalon at Orchard. Install 5' attached pathway on the west side of Orchard St.
No Done Done 2016 $0.11 Design modifications to reduce cost underway.
Project will be rebid upon completion.
3 12 CM212‐
11
02nd St, Ave C / Linder
Ave, including
Pedestrian Crossing
Construct curb, gutter, and sidewalk on the south side of 2nd St from Ave C to
Linder Rd, and install an enhanced pedestrian crossing on Linder Rd in
accordance with the Kuna Downtown Corridor Plan. Project includes road
rehabilitation.
Yes
(103)
Done Done 2016 $0.41 To be completed with Linder /
Main / 3rd Roundabout
project.
Under construction. Expected completion in
July 2016.
4 3 CM214‐
10
Deer Flat Rd and Kuna
HS Pedestrian Crossing
(Deer Flat Rd and Kuna
HS)
Install an enhanced pedestrian crossing on Deer Flat Rd east of the central
driveway of Kuna HS. Project also includes completion of of sidewalk on the
north side of Deer Flat from where it ends near the west school boundary and
the identified signal location.
No $0.43 Scoped "Go" in 2015. ACHD to evaluate
potential programming during IFYWP update.
5 NEW Boise St and School St
Pedestrian Crossing
Install an enhanced pedestrian crossing on Boise St at School St. No TBD ACHD Traffic Engineering to evaluate location
for warrants.
6 NEW Ten Mile Rd and
Crenshaw St
Install an enhanced pedestrian crossing on Ten Mile Rd at Crenshaw St. No TBD ACHD Traffic Engineering to evaluate location
for warrants.
7 2 CM213‐
64
Linder Rd, Main St /
Deer Flat Rd (Linder
Rd, south of Porter
St/Art Ct)
Complete curb, gutter, detached sidewalk and bike lanes on both sides of
Linder Rd, between 4th St (Linder/Main/3rd project limits) to Deer Flat Rd.
Project will construct a Rectangular Rapid Flashing Beacon at Porter St.
Yes
(116)
PD PD PD $1.44
Project design still in preliminary development.
ACHD to evaluate potential advancement of
project phases during IFYWP update.
8 5 CM213‐
64
Linder Rd, Main St /
Deer Flat Rd (Linder
Rd, Main St/Boise St)
Complete curb, gutter, detached sidewalk and bike lanes on both sides of
Linder Rd, between 4th St (Linder/Main/3rd project limits) to Deer Flat Rd.
Project will construct a Rectangular Rapid Flashing Beacon at Porter St.
Yes
(116)
PD PD PD $1.44 This request is included in priority #7 above.
PD ‐ Preliminary Development
CN ‐ Construction Year Page 2 of 4
![Page 69: Kent Goldthorpe, President Paul Woods, Vice President ...€¦ · 2016. Project is part of ITD's Strategic Initiatives request for FY2021. ACHD with ITD on any improvement if funded](https://reader030.vdocuments.net/reader030/viewer/2022041118/5f2f3aeb5603fd337e77e47c/html5/thumbnails/69.jpg)
Attachment 5
In IFYWP
(Page)DSN YR ROW YR CN YR
Total Cost
in
Millions
Programming NotesACHD Proposed Response
2016
City
Priority
Ranking
2015
City
Priority
Ranking
GIS # ACHD Project Name Project Description
Current Programming Status
9 NEW 2nd St and Ave D,
Main St / Avalon St
Install bike lanes in accordance with the Kuna Downtown Corridor Plan. No TBD Sidewalks on 2nd St, Ave C / Linder Ave under
construction. ACHD to verify if bike lanes is the
appropriate treatment for this roadway and
consider striping with current project if
feasible.
10 NEW Linder Ave/Avalon St,
2nd St / Orchard St
Construct curb, gutter, sidewalk on both sides of Linder Ave/Avalon St,
between 2nd St and Orchard St.
No TBD Prioritize and scope.
11 NEW Swan Falls Rd and
Indian Creek Pathway
Pedestrian Crossing
Install an enhanced pedestrian crossing on Swan Falls Rd at the Indian Creek
Pathway.
No TBD ACHD Traffic Engineering to evaluate location
for warrants.
NEW Ave A, Main St / 4th St
(North Downtown
Blocks Sidewalk
Addition)
Construct curb, gutter, and sidewalk on both sides of Ave A, between Main St
and 4th St in accordance with the Kuna Downtown Corridor Plan.
No TBD Prioritize and scope.
NEW Ave B, Main St / 4th St
(North Downtown
Blocks Sidewalk
Addition)
Construct curb, gutter, and sidewalk on both sides of Ave B, between Main St
and 4th St in accordance with the Kuna Downtown Corridor Plan.
No TBD Prioritize and scope.
NEW Ave C, Main St / 4th St
(North Downtown
Blocks Sidewalk
Addition)
Construct curb, gutter, and sidewalk on both sides of Ave C, between Main St
and 4th St in accordance with the Kuna Downtown Corridor Plan.
No TBD Prioritize and scope.
NEW Ave D, Main St / 4th St
(North Downtown
Blocks Sidewalk
Addition)
Construct curb, gutter, and sidewalk on both sides of Ave D, between Main St
and 4th St in accordance with the Kuna Downtown Corridor Plan.
No TBD Prioritize and scope.
13 NEW Dear Flat Rd and
School St Pedestrian
Crossing
Install an enhanced pedestrian crossing on Deer Flat Rd at School St. No TBD ACHD Traffic Engineering to evaluate location
for warrants.
NEW Ave A, 2nd St / Main St
(Southeast Downtown
Blocks Sidewalk
Addition)
Construct curb, gutter, and sidewalk on both sides of Ave A, between 2nd St
and Main St in accordance with the Kuna Downtown Corridor Plan.
No TBD Prioritize and scope.
NEW Ave B, 2nd St / Main St
(Southeast Downtown
Blocks Sidewalk
Addition)
Construct curb, gutter, and sidewalk on both sides of Ave B, between 2nd St
and Main St in accordance with the Kuna Downtown Corridor Plan.
No TBD Prioritize and scope.
15 6 CM215‐
13
Swan Falls, Shortline St
/ Initial Point
Sidewalk and bike lane. Done Done Done Done Done Bike facility built in 2015. ACHD to discuss
scope of sidewalk with the City.
12
14
PD ‐ Preliminary Development
CN ‐ Construction Year Page 3 of 4
![Page 70: Kent Goldthorpe, President Paul Woods, Vice President ...€¦ · 2016. Project is part of ITD's Strategic Initiatives request for FY2021. ACHD with ITD on any improvement if funded](https://reader030.vdocuments.net/reader030/viewer/2022041118/5f2f3aeb5603fd337e77e47c/html5/thumbnails/70.jpg)
Attachment 5
In IFYWP
(Page)DSN YR ROW YR CN YR
Total Cost
in
Millions
Programming NotesACHD Proposed Response
2016
City
Priority
Ranking
2015
City
Priority
Ranking
GIS # ACHD Project Name Project Description
Current Programming Status
16 9 RS203‐
07
Park and Ride Lot Park and ride lot. Location to be determined No TBD ACHD will support a City‐led site selection
effort. Project to be prioritized and scoped
after site selected.
17 10 N/A Greenbelt Extension
(West)
Extend greenbelt west to Deer Flat Rd No N/A ACHD will support a City‐led effort.
18 11 N/A Greenbelt Extension
(East)
Extend greenbelt east to Stroebel Rd No N/A ACHD will support a City‐led effort.
PD ‐ Preliminary Development
CN ‐ Construction Year Page 4 of 4
![Page 71: Kent Goldthorpe, President Paul Woods, Vice President ...€¦ · 2016. Project is part of ITD's Strategic Initiatives request for FY2021. ACHD with ITD on any improvement if funded](https://reader030.vdocuments.net/reader030/viewer/2022041118/5f2f3aeb5603fd337e77e47c/html5/thumbnails/71.jpg)
![Page 72: Kent Goldthorpe, President Paul Woods, Vice President ...€¦ · 2016. Project is part of ITD's Strategic Initiatives request for FY2021. ACHD with ITD on any improvement if funded](https://reader030.vdocuments.net/reader030/viewer/2022041118/5f2f3aeb5603fd337e77e47c/html5/thumbnails/72.jpg)
![Page 73: Kent Goldthorpe, President Paul Woods, Vice President ...€¦ · 2016. Project is part of ITD's Strategic Initiatives request for FY2021. ACHD with ITD on any improvement if funded](https://reader030.vdocuments.net/reader030/viewer/2022041118/5f2f3aeb5603fd337e77e47c/html5/thumbnails/73.jpg)
![Page 74: Kent Goldthorpe, President Paul Woods, Vice President ...€¦ · 2016. Project is part of ITD's Strategic Initiatives request for FY2021. ACHD with ITD on any improvement if funded](https://reader030.vdocuments.net/reader030/viewer/2022041118/5f2f3aeb5603fd337e77e47c/html5/thumbnails/74.jpg)
![Page 75: Kent Goldthorpe, President Paul Woods, Vice President ...€¦ · 2016. Project is part of ITD's Strategic Initiatives request for FY2021. ACHD with ITD on any improvement if funded](https://reader030.vdocuments.net/reader030/viewer/2022041118/5f2f3aeb5603fd337e77e47c/html5/thumbnails/75.jpg)
![Page 76: Kent Goldthorpe, President Paul Woods, Vice President ...€¦ · 2016. Project is part of ITD's Strategic Initiatives request for FY2021. ACHD with ITD on any improvement if funded](https://reader030.vdocuments.net/reader030/viewer/2022041118/5f2f3aeb5603fd337e77e47c/html5/thumbnails/76.jpg)
Attachment 6
Kuna School District 2016 Requests and ACHD Proposed Response
In IFYWP
(Page)DSN YR ROW YR CN YR
Total
Cost in
Millions
Programming Notes
Road & Intersection
1 1 IN211‐
01
Linder Rd and Deer
Flat Rd
Federal aid project to improve intersection of Linder Rd and Deer Flat Rd,
including curb, gutter, sidewalk and bike lanes. Right‐of‐way funding will
advance to a year prior to construction as funds become available.
Yes (45) 2016 2020 2020 $3.34 To be built in FY2020.
Community Programs
1 NEW N/A Kay St, Deer Flat Rd /
Boise St
Construct curb, gutter, and sidewalk on the east side of Kay St, between Deer
Flat Rd and Boise St.
No N/A Complete sidewalk exists on the west side
already. Defer addition of sidewalk on the east
side until development occurs.
2 NEW Kay St and Kuna High
School Enterance
Repair deteriorated asphalt in crosswalk. No TBD ACHD Maintenance to investigate and identify
solution.
3 6 N/A Deer Flat Rd and Kay St Install traffic signal due to traffic concerns prior to and after school. No N/A Location did not meet warrants for additional
traffic control when investigated in 2015.
ACHD Traffic Engineering to review to
determine if conditions have changed.
4 4 CM214‐
10
Deer Flat Rd and Kuna
HS Pedestrian Crossing
(Deer Flat Rd and
School Zone
Pedestrian Signal)
Install an enhanced pedestrian crossing on Deer Flat Rd east of the central
driveway of Kuna HS. Project also includes completion of of sidewalk on the
north side of Deer Flat from where it ends near the west school boundary and
the identified signal location.
No $0.42 Scoped "Go" in 2015. ACHD to evaluate
potential project programming during IFYWP
update.
5 NEW Deer Flat Rd, Linder Rd
/ Kay St
Complete sidewalk on the south side of Deer Flat Rd, between Linder Rd and
SH 69.
Yes (45) 2016 2020 2020 $3.34 Costs show full cost of
intersection project.
Sidewalk to be completed with intersection
project to be built in FY2020.
6 NEW Linder Rd and Reed
Elementary School
Enterance
Expand driveway with Linder Rd and Deer Flat intersection project to improve
bus access to Reed Elementary School
Yes (45) 2016 2020 2020 $3.34 Costs show full cost of
intersection project.
ACHD to evaluate improvement in the design
of the intersection project. The School District
will be responsible for any additional
modifications needed on the school property.
7 8 3341‐
00269
Ridgewood Rd,
Columbia Rd/Lake
Hazel Rd
Install speed limit sign No N/A ACHD Traffic Engineering to complete a speed
study and install signage.
ACHD Proposed Response
2016 SD
Priority
Ranking
2015 SD
Priority
Ranking
GIS #ACHD Project Name
(City Project Name)Project Description
Current Programming Status
PD ‐ Preliminary Development
CN ‐ Construction Year Page 1 of 1
![Page 77: Kent Goldthorpe, President Paul Woods, Vice President ...€¦ · 2016. Project is part of ITD's Strategic Initiatives request for FY2021. ACHD with ITD on any improvement if funded](https://reader030.vdocuments.net/reader030/viewer/2022041118/5f2f3aeb5603fd337e77e47c/html5/thumbnails/77.jpg)
Kuna School District 2016 Requests Status and 2016 Prioritization
Community Programs 2016
Ranking Project Name Project Description
1 Kay Street S. Side of Kay St. needs sidewalks, curb and gutter.
2 Kay Street Repair deteriorating asphalt in crosswalk
3 Deer Flat Rd & Kay St.
Install 3 way traffic controls. During school release and at commute times it is very difficult for buses and vehicles to pull out onto Deer flat because of the high volumes of traffic. In addition, making it very difficult for pedestrian to safely cross the street.
4 Deer Flat Rd & Kuna Install enhanced Pedestrian Crossing on Deer Flat Rd East of the central driveway of Kuna HS. Project includes completion of sidewalk on the north side of Deer Flat near the west school boundary and the identified signal location. School advises that the current two crosswalks needs to be dissolved and a sidewalk installed on the north side of Deer Flat. Or move the crosswalks away from the turn lane going into the high school to help mitigate between vehicles and pedestrians.
5 E Deer Flat Rd. Install sidewalks (fill in the gaps) N. Linder Rd to N. Kay Street
6 Linder @ Reed Elementary School
Expand the width of the driveway apron at the entrance of Reed Elementary school, currently buses are having a very difficult time pulling into the entrance and therefore riding on the sidewalk causing safety concern for students walking to school.
7 Ridgewood Rd., Columbia Rd/Lake Hazel Rd.
Install speed limit sign.
Please note: Road and intersection request stay the same.
![Page 78: Kent Goldthorpe, President Paul Woods, Vice President ...€¦ · 2016. Project is part of ITD's Strategic Initiatives request for FY2021. ACHD with ITD on any improvement if funded](https://reader030.vdocuments.net/reader030/viewer/2022041118/5f2f3aeb5603fd337e77e47c/html5/thumbnails/78.jpg)
Attachment 7
City of Meridian 2016 Requests and ACHD Proposed Response
In IFYWP
(Page)DSN YR ROW YR CN YR
Total Cost
in MillionsProgramming Notes
Road & Intersection
1 1 (1
Road)
RD202‐
37
Ustick Rd, Meridian Rd
/ Locust Grove Rd
Widen Ustick Rd to 5 lanes with curb, gutter, sidewalk and bike lanes in
accordance with 2012 CIP. Project to be constructed concurrently with the
Ustick Rd / Meridian Rd intersection and Ustick Rd, Linder Rd / Meridian Rd
widening.
Yes (41) Done Done 2016‐
2018
$2.83 Construction to start summer 2016.
2 2 (2
Road)
RD213‐
16
Linder Rd, Franklin Rd
/ Pine Ave (Linder Rd,
Franklin Rd/Cherry Ln)
Widen Linder Rd to 5 lanes with curb, gutter, sidewalk and bike lanes in
accordance with 2012 CIP. Project includes upgrade of the Union Pacific
Railroad crossing and bridge #131.
Yes (35) 2016 2017‐
2018
2019 $3.43 #1 Community Programs
request from the West Ada
School District.
To be built in FY2019.
3 5 (5
Road)
RD208‐
01
Pine Ave, Meridian Rd
/ Locust Grove Rd
Reconstruct roadway to include widening at intersections, curb, gutter,
sidewalk and bike lanes in partnership with the City of Meridian and the
Meridian Development Corporation. Project includes bridge #134.
Yes (37) 2016 2017 2018 $3.67 Economic Development
Project
To be built in FY2018.
4 6 (1 Int) IN202‐
06
Ustick Rd and
Meridian Rd
Widen intersection to 7 lanes on all approaches in accordance with the 2012
CIP. Project to be constructed concurrently with the Ustick Rd, Meridian Rd /
Locust Grove Rd and Ustick Rd, Linder Rd / Meridian Rd widenings.
Yes (48) Done Done 2016‐
2018
$4.53 Construction to start summer 2016.
5 9 (6
Road)
RD202‐
44
Locust Grove Rd,
Victory Rd / Overland
Rd
Widen Locust Grove Rd to 5 lanes with curb, gutter, sidewalk and bike lanes in
accordance with the 2012 CIP.
No $3.10 Prioritized. ACHD to evaluate potential
programming during IFYWP update.
6 7 (2 Int) IN211‐
05
Fairview Ave and
Locust Grove Rd
Widen intersection to 9 lanes on Fairview Ave and 7 lanes on Locust Grove Rd,
including curb, gutter, sidewalk, and bike lanes in accordance with the 2012
CIP.
Yes (45) 2020 PD PD $6.23 Programmed to begin design in FY2020. ACHD
to evaluate project construction moving
forward through IFYWP update.
7 10 ( 7
Road)
RD202‐
35
Ustick Rd, Linder Rd /
Meridian Rd
Widen Ustick Rd to 5 lanes with curb, gutter, sidewalk and bike lanes in
accordance with 2012 CIP. Project to be constructed concurrently with the
Ustick Rd / Meridian Rd intersection and Ustick Rd, Meridian Rd / Locust Grove
Rd widening.
Yes (40) Done Done 2016‐
2018
$2.56 Construction to start summer 2016.
8 18 Road RD215‐
03
McMillan Rd, Linder
Rd / Meridian Rd
Widen McMillan Rd to 3 lanes with curb, gutter, sidewalk, and bike lanes. No TBD Project is not identified in the
2012 CIP. Will evaluate project
for inclusion during the 2016
CIP update.
Not a 2012 ACHD CIP project. ACHD is
evaluating this project for potential inclusion
in the 2016 CIP.
9 12 (9
Road)
RD207‐
33
Eagle Rd, Amity Rd /
Victory Rd
Widen Eagle Rd to 5 lanes with curb, gutter, sidewalk and bike lanes in
accordance with the 2012 CIP.
Yes (33) 2019 2020 PD $3.35 Programmed to begin design in FY2019. ACHD
to evaluate project construction moving
forward through IFYWP update.
2015 City
Priority
Ranking
2016 City
Priority
Ranking
ACHD Proposed Response
Current Programming Status
Project DescriptionACHD Project Name
(City Project Name)GIS #
PD ‐ Preliminary Development
UF ‐ Unfunded
CN ‐ Construction Year
LOS ‐ Level of Service Page 1 of 10
![Page 79: Kent Goldthorpe, President Paul Woods, Vice President ...€¦ · 2016. Project is part of ITD's Strategic Initiatives request for FY2021. ACHD with ITD on any improvement if funded](https://reader030.vdocuments.net/reader030/viewer/2022041118/5f2f3aeb5603fd337e77e47c/html5/thumbnails/79.jpg)
Attachment 7
In IFYWP
(Page)DSN YR ROW YR CN YR
Total Cost
in MillionsProgramming Notes
2015 City
Priority
Ranking
2016 City
Priority
Ranking
ACHD Proposed Response
Current Programming Status
Project DescriptionACHD Project Name
(City Project Name)GIS #
10 10 Road RD207‐
23
Meridian Rd, Cherry Ln
/ Ustick Rd
Widen Meridian Rd to 5 lanes with curb, gutter, sidewalk, and bike lanes in
accordance with the 2012 CIP. Project includes bridge #124 and #126X.
Yes (36) 2016 2018 2020 $4.39 To be built in FY2020.
11 11 Road RC0299 Ten Mile Rd, Victory
Rd / Overland Rd
Widen Ten Mile Rd to 5 lanes with curb, gutter, sidewalk, and bike lanes in
accordance with the 2012 CIP.
Yes (40) PD PD UF $4.38 ACHD to evaluate project construction
moving forward through IFYWP update.
12 23 Road RD202‐
27
McMillan Rd, Meridian
Rd / Locust Grove Rd
Widen McMillan Rd to 3 lanes with curb, gutter, sidewalk, and bike lanes. No TBD Not a 2012 ACHD CIP project. ACHD is
evaluating this project for potential inclusion
in the 2016 CIP. May be opportunities to
address sidewalk concerns in this developing
area with a temporarily solution ahead of the
future widening.
13 12 Road RD215‐
02
Victory Rd, Locust
Grove Rd / Eagle Rd
Widen Victory Rd to 3 lanes with curb, gutter, sidewalk, and bike lanes in
accordance with the 2012 CIP.
No $3.77 Prioritized. ACHD to evaluate potential
programming during IFYWP update.
14 16 Road RD210‐
02
Locust Grove Rd,
Fairview Ave / Ustick
Rd
Widen Locust Grove Rd to 5 lanes with curb, gutter, sidewalk, and bike lanes in
accordance with the 2012 CIP.
No $3.08 Fairview and Locust Grove
intersection should occur prior
to project.
Prioritized. ACHD to evaluate potential
programming during IFYWP update.
15 17 Road RD202‐
20
Locust Grove Rd,
Ustick Rd / McMillan
Rd
Widen Locust Grove Rd to 3 lanes with curb, gutter, sidewalk, and bike lanes in
accordance with the 2012 CIP.
No $2.45 Prioritized. ACHD to evaluate potential
programming during IFYWP update.
16 11 (8
Road)
RC0152 Franklin Rd, Black Cat
Rd/Ten Mile Rd
Federal aid project to widen Franklin Rd to 5 lanes with curb, gutter, and
sidewalks in accordance with the 2012 CIP. Drainage will include green
stormwater infrastructure strategies. Project includes bridge #170CX. Project
to be constructed concurrently with the Franklin Rd and Black Cat Rd
intersection widening.
Yes (48) Done Done 2016‐
2017
$9.54 Federal project. Cost is
combined cost with IN203‐01.
Construction to start summer/fall 2016.
17 3 (3
Road)
RD188 Ten Mile Rd, McMillan
Rd / Chinden Blvd (US
20/26)
Widen Ten Mile Rd to 5 lanes with curb, gutter, sidewalk and bike lanes in
accordance with 2012 CIP. Project includes bridge #113P over Nine Mile Creek.
Yes (39) 2020 PD PD $3.31 Programmed to begin design in FY2020. ACHD
to evaluate project construction moving
forward through IFYWP update.
18 4 (4
Road)
RD202‐
32
Ten Mile Rd, Ustick Rd
/ McMillan Rd
Widen Ten Mile Rd to 5 lanes with curb, gutter, sidewalk and bike lanes in
accordance with 2012 CIP. Project includes bridges #114 and #115P.
Yes (40) 2019 2020 PD $3.85 Programmed to begin design in FY2019. ACHD
to evaluate project construction moving
forward through IFYWP update.
19 15 (6 Int) IN215‐
06
Locust Grove Rd and
Victory Rd
Roundabout
Construct a dual‐lane roundabout with a southbound right turn bypass lane in
accordance with the 2012 CIP.
No $1.78 Defer. Interim signal installed in 2013.
Operating at a LOS C or better.
20 21 Road RD207‐
34
Locust Grove Rd,
Amity Rd / Victory Rd
Widen Locust Grove Rd to 3 lanes with curb, gutter, sidewalk, and bike lanes. No $2.75 Defer. Operating at a LOS C or better.
21 15 Road RD202‐
17
Linder Rd, McMillan
Rd / Chinden Blvd (US
20/26)
Widen Linder Rd to 5 lanes with curb, gutter, sidewalk, and bike lanes in
accordance with 2012 CIP.
No $1.42 Prioritized. ACHD to evaluate potential
programming during IFYWP update.
PD ‐ Preliminary Development
UF ‐ Unfunded
CN ‐ Construction Year
LOS ‐ Level of Service Page 2 of 10
![Page 80: Kent Goldthorpe, President Paul Woods, Vice President ...€¦ · 2016. Project is part of ITD's Strategic Initiatives request for FY2021. ACHD with ITD on any improvement if funded](https://reader030.vdocuments.net/reader030/viewer/2022041118/5f2f3aeb5603fd337e77e47c/html5/thumbnails/80.jpg)
Attachment 7
In IFYWP
(Page)DSN YR ROW YR CN YR
Total Cost
in MillionsProgramming Notes
2015 City
Priority
Ranking
2016 City
Priority
Ranking
ACHD Proposed Response
Current Programming Status
Project DescriptionACHD Project Name
(City Project Name)GIS #
22 14 Road RD202‐
18
Linder Rd, Ustick Rd /
McMillan Rd
Widen Linder Rd to 5 lanes with curb, gutter, sidewalk, and bike lanes in
accordance with 2012 CIP.
No $2.73 Prioritized. ACHD to evaluate potential
programming during IFYWP update.
23 13 Road RD209‐
15
Linder Rd, Cherry Ln /
Ustick Rd
Widen Linder Rd to 5 lanes with curb, gutter, sidewalk, and bike lanes in
accordance with 2012 CIP.
No $5.97 Prioritized. ACHD to evaluate potential
programming during IFYWP update.
24 19 Road RC0207 Linder Rd, Overland Rd
/ Franklin Rd
Widen Linder Rd to 5 lanes and construct a new 4‐lane I‐84 overpass, including
curb, gutter, sidewalk, and bike lanes in accordance with the 2012 CIP. Project
would be a joint project between ACHD and ITD.
No $3.15 Cost do not include overpass. ACHD requested project from ITD in spring
2016. Project not on ITD's planned projects at
this time. ACHD will continue to pursue
project with ITD.
25 8 (3 Int) IN203‐
01
Franklin Rd and Black
Cat Rd
Federal aid project to widen and signalize the intersection to 7 lanes on all
approaches in accordance with the 2012 CIP. Project to be constructed
concurrently with the Franklin Rd, Black Cat Rd / Ten Mile Rd widening.
Yes (48) Done Done 2016‐
2017
$9.54 Federal project. Cost is
combined cost with RC0152.
Construction to start summer/fall 2016.
26 14 (5 Int) IN206‐
02
Overland Rd and
Linder Rd
Widen and signalize intersection to 7 lanes on Linder Rd and 8 lanes on
Overland Rd in accordance with the 2012 CIP.
No $4.69 Defer until further development in area or
overpass built. Operating at a LOS C or better.
27 13 (4 Int) IN202‐
09
Ustick Rd and Black
Cat Rd
Widen and signalize intersection to 7 lanes on all approaches in accordance
with the 2012 CIP.
No $3.43 Defer. Operating at a LOS C or better.
28 20 Road RD207‐
24
Ustick Rd, Ten Mile Rd
/ Linder Rd
Widen Ustick Rd to 5 lanes with curb, gutter, sidewalk, and bike lanes in
accordance with the 2012 CIP.
No $2.77 Prioritized. ACHD to evaluate potential
programming during IFYWP update.
29 22 Road RD202‐
30
Meridian Rd, Ustick Rd
/ McMillan Rd
Widen Meridian Rd to 3 lanes with curb, gutter, sidewalk, and bike lanes in
accordance with the 2012 CIP.
No $2.09 Defer. Operating at a LOS D.
30 24 Road RD202‐
29
Meridian Rd, McMillan
Rd / Chinden Blvd
Widen Meridian Rd to 3 lanes with curb, gutter, sidewalk, and bike lanes in
accordance with the 2012 CIP.
No $3.07 Defer. Operating at a LOS D.
31 25 Road RC0161 Franklin Rd,
McDermott Rd / Black
Cat Rd
Widen Franklin Rd to 5 lanes with curb, gutter, sidewalk, and bike lanes in
accordance with the 2012 CIP.
No $2.91 Defer. Operating at a LOS D. Implementation
will be coordinated with Franklin Rd
improvements in Canyon County and SH16
Extension.
32 7 Int IN205‐
03
Ten Mile Rd and Amity
Rd
Construct a roundabout. Project includes bridge #205AX. Yes (50) 2017 2018 2019 $1.33 To be built in FY2019.
33 8 Int IN209‐
06
US 20/26 (Chinden
Blvd) and Locust Grove
Rd
Widen Locust Grove Rd intersection legs in coordination with ITD. Yes (47) UF UF UF TBD ACHD requested project from ITD in spring
2016. Project is part of ITD's Strategic
Initiatives request for FY2021. ACHD with ITD
on any improvement if funded.
34 9 Int IN209‐
05
US 20/26 (Chinden
Blvd) and Meridian Rd
Widen Meridian Rd intersection legs in coordination with ITD. Yes (47) UF UF UF TBD ACHD requested project from ITD in spring
2016. Project is not part of ITD's planned
projects. ACHD will continue to pursue project
with ITD.
PD ‐ Preliminary Development
UF ‐ Unfunded
CN ‐ Construction Year
LOS ‐ Level of Service Page 3 of 10
![Page 81: Kent Goldthorpe, President Paul Woods, Vice President ...€¦ · 2016. Project is part of ITD's Strategic Initiatives request for FY2021. ACHD with ITD on any improvement if funded](https://reader030.vdocuments.net/reader030/viewer/2022041118/5f2f3aeb5603fd337e77e47c/html5/thumbnails/81.jpg)
Attachment 7
In IFYWP
(Page)DSN YR ROW YR CN YR
Total Cost
in MillionsProgramming Notes
2015 City
Priority
Ranking
2016 City
Priority
Ranking
ACHD Proposed Response
Current Programming Status
Project DescriptionACHD Project Name
(City Project Name)GIS #
35 10 Int IN205‐
20
US 20/26 (Chinden
Blvd) and Black Cat Rd
Widen intersection in accordance with the 2012 CIP in coordination with ITD. No $1.21 ACHD requested project from ITD in spring
2016. Project is not part of ITD's planned
projects. ACHD will continue to pursue project
with ITD.
36 11 Int IN205‐
32
US 20/26 (Chinden
Blvd) and Ten Mile Rd
Widen intersection in accordance with the 2012 CIP in coordination with ITD. No $1.23 ACHD legs built out in accordance with the
2012 CIP by development in 2014. ACHD to
coordinate with ITD on improvements to
Chinden legs.
37 12 Int IN215‐
05
Eagle Rd and Amity Rd
Roundabout (Dual
Lane)
Widen roundabout to a dual lane roundabout, with curb, gutter, sidewalk, and
bike lanes. Project to be constructed concurrently with Eagle Rd, Amity Rd /
Victory Rd.
Yes (44) 2020 N/A PD $0.77 Programmed to begin design in FY2020. ACHD
to evaluate project construction moving
forward through IFYWP update.
38 16 Int IN205‐
70
SH 69 (Meridian Rd)
and Lake Hazel Rd
Install an interim signal in cooperation with ITD maintenance project. Project
also includes installation of an interim signal at SH 69 (Meridian Rd) and
Hubbard Rd. All costs for both signals included with this project.
Yes (50) UF UF UF $0.68 ACHD requested project from ITD in spring
2016. Project is part of ITD's Strategic
Initiatives request for FY2021. ACHD with ITD
on any improvement if funded.
39 13 Int IN211‐
06
Cherry Ln and Linder
Rd
Widen intersection to 7 lanes on all approaches in accordance with the 2012
CIP.
No $4.30 Defer. Operating at a LOS C or better.
40 14 Int IN215‐
07
Cherry Ln and Black
Cat Rd
Widen intersection to 6/7 lanes on all approaches in accordance with the 2012
CIP.
No $4.34 Defer. Interim signal installed in 2013.
Operating at a LOS C or better.
41 15 Int IN214‐
03
Victory Rd and Ten
Mile Rd
Widen intersection to 6 lanes on Ten Mile and 5 lanes on Victory in accordance
with the 2012 CIP.
No $2.53 Defer. Interim signal installed in 2013.
Operating at a LOS C or better.
42 26 Road RC0130 Fairview Ave, SH 55
(Eagle Rd) / Cloverdale
Rd
Widen Fairview Ave to 7 lanes with curb, gutter, sidewalk, and bike lanes in
accordance with the 2012 CIP.
No $3.31 Defer. Operating at a LOS D. ACHD to
coordinate with the City of Meridian
regarding implementing the Fairview Ave
Corridor Management Plan through
development.
43 27 Road RD207‐
19
Linder Rd, Chinden
Blvd (US 20/26) / SH
44 (State St)
Widen Linder Rd to 7 lanes with curb, gutter, sidewalk, and bike lanes in
accordance with the 2012 CIP. Project includes bridges #80, #81, and #82.
Part
(102)
$20.66 Linder Rd, 1/4 mile to 2/3 mile
N/O Chinden programmed.
Prioritized. ACHD to evaluate potential
programming during IFYWP update.
44 28 Road RC0133 Fairview Ave, Locust
Grove Rd / SH 55
(Eagle Rd)
Widen Fairview Ave to 7 lanes with curb, gutter, sidewalk, and bike lanes in
accordance with the 2012 CIP.
No $3.65 Defer. Operating at a LOS D. ACHD to
coordinate with the City of Meridian
regarding scope of widening.
45 29 Road RC0135 Fairview Ave, Meridian
Rd / Locust Grove Rd
Widen Fairview Ave to 7 lanes with curb, gutter, sidewalk, and bike lanes. No $4.01 Defer. Operating at a LOS D. ACHD to
coordinate with the City of Meridian
regarding scope of widening.
PD ‐ Preliminary Development
UF ‐ Unfunded
CN ‐ Construction Year
LOS ‐ Level of Service Page 4 of 10
![Page 82: Kent Goldthorpe, President Paul Woods, Vice President ...€¦ · 2016. Project is part of ITD's Strategic Initiatives request for FY2021. ACHD with ITD on any improvement if funded](https://reader030.vdocuments.net/reader030/viewer/2022041118/5f2f3aeb5603fd337e77e47c/html5/thumbnails/82.jpg)
Attachment 7
In IFYWP
(Page)DSN YR ROW YR CN YR
Total Cost
in MillionsProgramming Notes
2015 City
Priority
Ranking
2016 City
Priority
Ranking
ACHD Proposed Response
Current Programming Status
Project DescriptionACHD Project Name
(City Project Name)GIS #
46 30 Road RD215‐
17
Cherry Ln, Linder Rd /
Meridian Rd
Widen Cherry Ln to 5 lanes with curb, gutter, sidewalk, and bike lanes. No TBD Not a 2012 ACHD CIP project. ACHD to
evaluate project for potential inclusion in the
2016 CIP. Previous statement that roadway
would be widened to 7 lanes in error. See
corrected project description.
47 31 Road RD208‐
10
Fairview Ave Corridor
Management, Linder
Rd / Orchard St
Improve safety and traffic operations along Fairview Ave in accordance with
the Fairview Avenue Corridor Management Strategy. Project may include
bicycle and pedestrian facilities and other access management treatments.
No TBD Project to be implemented through
development. ACHD and Meridian to
coordinate on implementation with
appropriate development applications.
48 32 Road RD209‐
03
Ten Mile Rd, Amity Rd
/ Victory Rd
Widen Ten Mile Rd to 5 lanes with curb, gutter, sidewalk, and bike lanes in
accordance with the 2012 CIP.
No $3.03 Defer. Operating at a LOS D.
49 33 Road RD215‐
18
East 03rd St Extension,
Carlton St / Fairview
Ave (Phase 2)
Extend roadway and construct streetscape improvements, including curb,
gutter, sidewalk, and improved UPRR crossing, from Carlton Ave to Fairview
Ave in accordance with the Downtown Meridian Neighborhood Plan.
No TBD Defer until after completion of Phase 1
(Franklin Rd / Carlton St)
50 34 Road RD209‐
04
Broadway Ave / Idaho
Ave Extension, East
06th St / Locust Grove
Rd
Extend roadway and construct streetscape improvements, including curb,
gutter, sidewalk, and improved UPRR crossing, from Carlton Ave to Fairview
Ave.
No TBD Defer. Potential future economic
development request or to be built by
development.
51 17 Int IN205‐
21
McMillan Rd and Black
Cat Rd
Widen intersection to 6 lanes on Black Cat and 4 lanes on McMillan in
accordance with the 2012 CIP.
No $2.34 Defer. Operating at a LOS C or better.
52 18 Int IN208‐
02
Amity Rd and Black Cat
Rd
Widen intersection to 4 lanes on Amity and 6 lanes on McMillan in accordance
with the 2012 CIP.
No $2.21 Defer. Operating at a LOS C or better.
53 19 Int IN203‐
25
McMillan Rd and Star
Rd
Widen intersection to 6 lanes on Star and 4 lanes on McMillan in accordance
with the 2012 CIP.
No $2.47 Defer. Operating at a LOS C or better.
54 20 Int IN215‐
08
Amity Rd and Linder
Rd
Widen intersection to 6 lanes on Linder and 5 lanes on Amity in accordance
with the 2012 CIP.
No $3.04 Defer. Operating at a LOS C or better.
55 21 Int IN215‐
09
Cherry Ln and
McDermott Rd
Widen intersection to 3 lanes on McDermott and 5 lanes on Cherry in
accordance with the 2012 CIP.
No $1.18 Defer. Operating at a LOS C or better.
56 22 Int IN215‐
10
Franklin Rd and
McDermott Rd
Widen intersection to 3 lanes on McDermott and 5/6 lanes on Franklin in
accordance with the 2012 CIP.
No $1.19 Defer. Operating at a LOS C or better.
57 23 Int IN202‐
20
Ustick Rd and
McDermott Rd
Widen and signalize intersection to 5 lanes on McDermott and 6 lanes on
Ustick in accordance with the 2012 CIP.
No $1.96 Defer. Operating at a LOS C or better.
58 24 Int IN215‐
11
McMillan Rd and
McDermott Rd
Intersection improvement. No TBD Project is not identified in the 2012 CIP. Will
evaluate project for inclusion during the 2016
CIP update.
59 25 Int IN205‐
88
Ustick Rd and Star Rd Widen and signalize intersection to 5 lanes on Star and 7 lanes on Ustick in
accordance with the 2012 CIP.
No $1.70 Defer. Operating at a LOS C or better.
60 NEW Ten Mile Rd and
Chateau Dr
Signalize intersection. No TBD ACHD Traffic Engineering to evaluate location
for signal warrants.
PD ‐ Preliminary Development
UF ‐ Unfunded
CN ‐ Construction Year
LOS ‐ Level of Service Page 5 of 10
![Page 83: Kent Goldthorpe, President Paul Woods, Vice President ...€¦ · 2016. Project is part of ITD's Strategic Initiatives request for FY2021. ACHD with ITD on any improvement if funded](https://reader030.vdocuments.net/reader030/viewer/2022041118/5f2f3aeb5603fd337e77e47c/html5/thumbnails/83.jpg)
Attachment 7
In IFYWP
(Page)DSN YR ROW YR CN YR
Total Cost
in MillionsProgramming Notes
2015 City
Priority
Ranking
2016 City
Priority
Ranking
ACHD Proposed Response
Current Programming Status
Project DescriptionACHD Project Name
(City Project Name)GIS #
61 NEW Lake Hazel Rd and
Eagle Rd
Widen and signalize intersection to 6 lanes on Eagle and 7 lanes on Lake Hazel
in accordance with the 2012 CIP.
No $4.27 Defer. Operating at a LOS C or better.
62 NEW Lake Hazel Rd and
Locust Grove Rd
Widen and signalize intersection to 5 lanes on Locust Grove and 6 lanes on
Lake Hazel in accordance with the 2012 CIP.
No $3.32 Defer. Operating at a LOS C or better.
63 NEW Amity Rd and Locust
Grove Rd
Construct a dual‐lane roundabout with westbound and eastbound right turn
bypass lanes in accordance with the 2012 CIP.
No $1.95 Defer. Operating at a LOS C or better.
64 NEW Victory Rd and Linder
Rd
Widen and signalize intersection to 5/6 lanes on Linder and 3/4 lanes on
Victory in accordance with the 2012 CIP.
No $2.40 Defer. Operating at a LOS C or better.
65 NEW Locust Grove Rd,
McMillan Rd / Chinden
Blvd (US 20/26)
Widen Locust Grove Rd to 3 lanes with curb, gutter, sidewalk, and bike lanes in
accordance with the Master Street Map.
No TBD Project is not identified in the 2012 CIP. Will
evaluate project for inclusion during the 2016
CIP update. Agency staffs to discuss lane
designation as requested.
66 NEW Ustick Rd, McDermott
Rd / Black Cat Rd
Widen Ustick Rd to 6 lanes with curb, gutter, sidewalk, and bike lanes in
accordance with the 2012 CIP.
No $3.06 Prioritize and evaluate potential programming
during IFYWP update.
Community Programs
1 1 CM212‐
09
West 04th St,
Broadway Ave / Maple
Ave
Construct curb, gutter and sidewalk on the east side of West 4th St, between
Broadway Ave and Maple Ave and a pathway between Maple Ave and Cherry
Ln in accordance with the Downtown Meridian Neighborhood Plan. Project will
provide pedestrian connectivity and a safer walking route for students
attending Meridian Elementary.
Yes
(123)
Done 2016 2017 $0.45 To be built in FY2017.
2 2 CM209‐
31
West 01st St,
Broadway Ave / Pine
Ave
Construct sidewalk on both sides of West 01st St, between Broadway Ave and
Pine Ave, including replacing existing substandard sidewalks and pedestrian
ramps in accordance with the Downtown Meridian Neighborhood Plan. Project
to be completed in partnership with the Meridian Development Corporation.
Project will improve pedestrian connectivity and safety for children walking to
Meridian Elementary School.
Yes
(123)
2016 2016 2017 $0.46 To be built in FY2017.
3 4 RD208‐
01
Pine Ave, Meridian Rd
/ Locust Grove Rd
Reconstruct roadway to include widening at intersections, curb, gutter,
sidewalk and bike lanes in partnership with the City of Meridian and the
Meridian Development Corporation. Project includes bridge #134.
Yes (37) 2016 2017 2018 $3.67 Economic Development
Project
To be built in FY2018.
4 5 N/A Meridian Rail‐with‐
Trail
Improve arterial crossing with pathway. No TBD ACHD to prioritize and scope arterial crossing
improvements when pathway moves forward.
5 6 CM213‐
43
McMillan Rd, Locust
Grove Rd / Red Horse
Way
Complete sidewalk on the north side of McMillan Rd, between Locust Grove Rd
and Red Horse Way.
No TBD Project is in a developing area. ACHD to scope
interim pedestrian facilities until a permanent
solution completed through development or
road widening.
PD ‐ Preliminary Development
UF ‐ Unfunded
CN ‐ Construction Year
LOS ‐ Level of Service Page 6 of 10
![Page 84: Kent Goldthorpe, President Paul Woods, Vice President ...€¦ · 2016. Project is part of ITD's Strategic Initiatives request for FY2021. ACHD with ITD on any improvement if funded](https://reader030.vdocuments.net/reader030/viewer/2022041118/5f2f3aeb5603fd337e77e47c/html5/thumbnails/84.jpg)
Attachment 7
In IFYWP
(Page)DSN YR ROW YR CN YR
Total Cost
in MillionsProgramming Notes
2015 City
Priority
Ranking
2016 City
Priority
Ranking
ACHD Proposed Response
Current Programming Status
Project DescriptionACHD Project Name
(City Project Name)GIS #
6 7 CM214‐
31
West 02nd St, UPRR /
Broadway Ave
Complete sidewalk on both sides of West 02nd, between the Union Pacific
Railroad and Broadway Ave to address parking concerns in this area.
No $0.15 Scoped No Go in 2015. ACHD to coordinate
with the City of Meridian on alternative
treatments to address parking concerns.
7 8 CM210‐
55
Black Cat Rd,
Moonlake Dr / Ustick
Rd (Black Cat Rd and
Moon Lake Dr
Pedestrian Signal)
Construct an asphalt pathway from the north west corner of Ustick and Black
Cat on the west side south to Moon Lake. Install an enhanced pedestrian signal
at or near Moon Lake Dr.
Yes
(105)
Done 2016 2016 $0.21 Under construction.
8 9 5345 Eagle Rd and
Ridenbaugh Canal
Pedestrian Signal
Install an enhanced pedestrian signal on Eagle at Ridenbaugh Canal. No Done TBD Construction to be built in coordination with
adjacent development.
9 10 PPI208‐
99
Locust Grove Rd and
Palermo Dr Pedestrian
Signal
Install an enhanced pedestrian signal and lighting on the north side of Palermo
at Locust Grove.
No $0.36 Scoped "Go" in 2015. ACHD to evaluate
potential programming during IFYWP update.
10 11 CM212‐
28
Locust Grove Rd,
Overland Rd/Puffin St
Detached asphalt or concrete pathway on east side of Locust Grove between
Puffin and Overland.
No $0.16 Scoped "Go" in 2014. ACHD to evaluate
potential programming during IFYWP update.
11 12 N/A Meridian Rd and
Railroad Pedestrian
Signal
Signalized pedestrian crossing. Part of Rails‐with‐Trails project. No TBD ACHD to prioritize and scope arterial crossing
improvements when pathway moves forward.
12 13 N/A Main St and Railroad
Pedestrian Signal
Signalized pedestrian crossing. Part of Rails‐with‐Trails project. No TBD ACHD to prioritize and scope arterial crossing
improvements when pathway moves forward.
13 14 PPI208‐
96
Locust Grove Rd,
Paradise Ln/Grand
Canyon Dr
Asphalt path on the east side of Locust Grove Rd to connect with an existing
path to the school.
No N/A This project is complete. An interim treatment
was built in 2010.
14 15 N/A Five Mile Creek Path,
Badley Ave/Fairview
Ave
Off‐system pathway. No N/A ACHD will support a city‐led effort.
15 18 Stoddard Rd, Victory
Rd / Kodiak Dr
Sidewalk on the west side of Stoddard Rd, between Victory and Kodiak. No TBD Scoped "Go" in 2015. ACHD to evaluate
potential programming during IFYWP update.
16 19 CM211‐
54
Duane Dr, Granger Dr
/ Ustick Rd
Sidewalk on east side of Duane Dr, between Granger and Ustick. No TBD Prioritize and scope.
PD ‐ Preliminary Development
UF ‐ Unfunded
CN ‐ Construction Year
LOS ‐ Level of Service Page 7 of 10
![Page 85: Kent Goldthorpe, President Paul Woods, Vice President ...€¦ · 2016. Project is part of ITD's Strategic Initiatives request for FY2021. ACHD with ITD on any improvement if funded](https://reader030.vdocuments.net/reader030/viewer/2022041118/5f2f3aeb5603fd337e77e47c/html5/thumbnails/85.jpg)
Attachment 7
In IFYWP
(Page)DSN YR ROW YR CN YR
Total Cost
in MillionsProgramming Notes
2015 City
Priority
Ranking
2016 City
Priority
Ranking
ACHD Proposed Response
Current Programming Status
Project DescriptionACHD Project Name
(City Project Name)GIS #
17 21 RD207‐
33
Eagle Rd, Amity Rd /
Victory Rd (Eagle Rd,
Falcon Dr / Victory Rd)
Widen Eagle Rd to 5 lanes with curb, gutter, sidewalk and bike lanes in
accordance with the 2012 CIP.
Yes (33) 2019 2020 PD $3.35 City request is for sidewalk. This will be
completed with the roadway widening project
to start design in FY2019.
18 22 RD202‐
35
Ustick Rd, Linder Rd /
Meridian Rd (Ustick
and West 03rd
Pedestrian Signal)
Widen Ustick Rd to 5 lanes with curb, gutter, sidewalk and bike lanes in
accordance with 2012 CIP. Project to be constructed concurrently with the
Ustick Rd / Meridian Rd intersection and Ustick Rd, Meridian Rd / Locust Grove
Rd widening.
Yes (40) Done 2016 2016‐
2018
$2.56 City request is for a pedestrian signal at Ustick
and W. 03rd St. This will be completed with
the roadway widening project. Construction
to start summer 2016.
19 23 CM213‐
45
McMillan Rd, Linder
Rd / Meridian Rd
Complete sidewalk on the north side of McMillan Rd, between Linder Rd and
Meridian Rd.
No TBD Developing area. ACHD to coordinate with the
City on the scope and timing of
improvements.
20 24 CM210‐
68
Broadway Ave, West
07th St / West 04th St
Complete sidewalks on the south side of Broadway Ave, between West 07th St
and West 04th St.
No TBD Scoped "Go" in 2015. ACHD to evaluate
potential programming during IFYWP update.
21 25 CM215‐
19
Victory Rd and
Standing Timber Ave
Pedestrian Crossing
(Victory Rd, west of
Mesa)
Install an enhanced pedestrian crossing and curb ramps on Victory Rd at
Standing Timber Ave.
No TBD ACHD Traffic to review location for warrants.
Prioritize and scope in 2016.
22 27 CM214‐
37
McMillan Rd, Ten Mile
Rd/Linder Rd
Install extruded curb pathway on north side of McMillan Rd between Cortona
Way and Goddard Creek Way and detached concrete sidewalk with curbing
between Goddard Creek Way and Wild Goose Way.
No $0.47 Developing area. ACHD to coordinate with the
City on the scope and timing of
improvements.
23 28 RD207‐
33
Eagle Rd, Amity Rd /
Victory Rd (Eagle Rd,
Zaldia Dr / Victory Rd)
Widen Eagle Rd to 5 lanes with curb, gutter, sidewalk and bike lanes in
accordance with the 2012 CIP.
Yes (33) 2019 2020 PD $3.35 City request is for sidewalk. This will be
completed with the roadway widening project
to start design in FY2019.
24 29 RD213‐
16
Linder Rd, Franklin Rd
/ Pine Ave
Widen Linder Rd to 5 lanes with curb, gutter, sidewalk, and bike lanes in
accordance with the 2012 CIP. Project includes upgrade of the Union Pacific
Railroad crossing and bridge #131.
Yes (35) 2016 2017‐
2018
2019 $3.43 City request is for sidewalk. This will be
completed with the roadway widening project
to be built in FY2019.
25 30 RD209‐
02
East 03rd St, Franklin
Rd / Carlton Ave
(Phase 1)
Construct streetscape improvements, including curb, gutter, sidewalk, and
improved UPRR crossing, from Franklin Rd to Carlton Ave in accordance with
the Downtown Meridian Neighborhood Plan.
Yes
(128)
2019 2020 PD $2.05 Economic Development
Project.
Programmed to begin design in FY2019. ACHD
to evaluate project construction moving
forward through IFYWP update.
PD ‐ Preliminary Development
UF ‐ Unfunded
CN ‐ Construction Year
LOS ‐ Level of Service Page 8 of 10
![Page 86: Kent Goldthorpe, President Paul Woods, Vice President ...€¦ · 2016. Project is part of ITD's Strategic Initiatives request for FY2021. ACHD with ITD on any improvement if funded](https://reader030.vdocuments.net/reader030/viewer/2022041118/5f2f3aeb5603fd337e77e47c/html5/thumbnails/86.jpg)
Attachment 7
In IFYWP
(Page)DSN YR ROW YR CN YR
Total Cost
in MillionsProgramming Notes
2015 City
Priority
Ranking
2016 City
Priority
Ranking
ACHD Proposed Response
Current Programming Status
Project DescriptionACHD Project Name
(City Project Name)GIS #
26 16 CM214‐
43
State Ave, East 2nd St
/ Cathy Ln
Sidewalk repair. Requested by land owner in this area. No $0.50 Scoped "No Go" in 2015. This section has
connectivity already on the south side and the
original requestor no longer owns the
property.
27 17 Kentucky Ridge Way,
Riodosa Dr / Victory
Rd
Sidewalk on the west side of Kentucky Ridge Way, between Victory and
Riodosa.
No TBD Scoped "Go ‐ Defer" in 2015. New sidewalk
recently built on the east side.
28 31 CM214‐
37
McMillan Rd and
Palantine Way
Pedestrian Crossing
Install an enhanced pedestrian crossing and curb ramps on McMillan Rd at
Palantine Way.
No TBD Developing area. ACHD to coordinate with the
City on the scope and timing of
improvements.
29 32 N/A Eagle Rd, River Valley
St / Ustick Rd
Complete sidewalks on Eagle Rd, between River Valley St and Ustick Rd. No N/A ACHD has no right‐of‐way at this location.
ACHD to share request with ITD.
30 33 N/A Chinden Blvd, east of
Ten Mile Rd
Complete sidewalks on Chinden Blvd, east of Ten Mile Rd. No N/A ACHD has no right‐of‐way at this location.
ACHD to share request with ITD.
31 34 CM214‐
44
Cherry Ln and
Meridian Library
Pedestrian Crossing
Install an enhanced pedestrian crossing on Cherry Lane approximately midway
between the existing signalized intersections at West 8th and Linder. This will
require relocation of the existing school zone beacon to the west.
No $0.25 Scoped "Go" 2014. ACHD to evaluate
potential programming during IFYWP update.
32 36 3341‐
00269
W. 8th St and
Meridian Middle
School
School Crossing Ahead signage on W. 8th St. Project is the #12 request from
the West Ada School District (2015).
No TBD ACHD Traffic Engineering to coordinate
improvement.
33 NEW N/A Amity and Mary
McPherson
Elementary School
Pedestrian Signal
Signalized pedestrian crossing No N/A ACHD Traffic evaluation shows good vehicle
compliance with existing crossing. ACHD to
reevaluate at a later date.
34 NEW Pine Ave and W. 1st St
Pedestrian Crossing
Signalized pedestrian crossing (RRFB) No TBD Conduit is being placed for a future crossing
with the W. 1st sidewalk project. ACHD Traffic
Engineering to evaluate for signal warrants.
35 NEW Washington St and W.
1st St Pedestrian
Crossing
Pedestrian crossing near Meridian Elementary School No TBD ACHD Traffic Engineering to evaluate location
for enhanced pedestrian crossing
opportunities.
36 NEW Bower St, Meridian Rd
/ E. 03rd St
Complete sidewalks and add wayfinding signage on Bower St, between
Meridian Rd and E. 03rd St
No TBD Prioritize and scope.
37 NEW Linder Rd, I‐84 /
Franklin Rd
Complete sidewalks on Linder Rd, between I‐84 and Franklin Rd No TBD Prioritize and scope.
PD ‐ Preliminary Development
UF ‐ Unfunded
CN ‐ Construction Year
LOS ‐ Level of Service Page 9 of 10
![Page 87: Kent Goldthorpe, President Paul Woods, Vice President ...€¦ · 2016. Project is part of ITD's Strategic Initiatives request for FY2021. ACHD with ITD on any improvement if funded](https://reader030.vdocuments.net/reader030/viewer/2022041118/5f2f3aeb5603fd337e77e47c/html5/thumbnails/87.jpg)
Attachment 7
In IFYWP
(Page)DSN YR ROW YR CN YR
Total Cost
in MillionsProgramming Notes
2015 City
Priority
Ranking
2016 City
Priority
Ranking
ACHD Proposed Response
Current Programming Status
Project DescriptionACHD Project Name
(City Project Name)GIS #
38 NEW Linder Rd, Washington
St / Maple St
Complete sidewalk on the west side of Linder Rd, between Washington St and
Maple St.
No TBD Complete pedestrian facilities exist in this
section. There is one parcel where sidewalk
does not exist, however, there is a paved
pathway with extruded curb.
39 NEW Victory Rd, Glacier Bay
Way / Mesa Way
Complete sidewalk on the south side adjacent to county parcel. No TBD Developing area. ACHD to coordinate with the
City on the scope and timing of
improvements.
40 NEW Main St and Williams
St Pedestrian Crossing
Install an enhanced pedestrian crossing of Main St at Williams St. No TBD ACHD Traffic Engineering to evaluate location
for enhanced pedestrian crossing
opportunities.
41 NEW Washington St, W.
07th St / Main St
Complete sidewalk on Washington St, between W. 07th St and Main St. No TBD Prioritize and scope.
42 NEW Gordon Harris
Pathway Lighting
Pedestrian lighting on pathway between Mountain View HS and Eagle Rd. No N/A ACHD to support a city‐led effort.
43 NEW Locust Grove Rd and
Time Zone Dr
Pedestrian Crossing
Install an enhanced pedestrian crossing of Locust Grove Rd at Time Zone Dr. No TBD Prioritize and scope.
44 NEW Locust Grove Rd and
Woodbridge Dr
/Watertower St
Pedestrian Crossing
Install an enhanced pedestrian crossing of Locust Grove Rd at Woodbridge Dr
or Watertower St.
No TBD Prioritize and scope.
PD ‐ Preliminary Development
UF ‐ Unfunded
CN ‐ Construction Year
LOS ‐ Level of Service Page 10 of 10
![Page 88: Kent Goldthorpe, President Paul Woods, Vice President ...€¦ · 2016. Project is part of ITD's Strategic Initiatives request for FY2021. ACHD with ITD on any improvement if funded](https://reader030.vdocuments.net/reader030/viewer/2022041118/5f2f3aeb5603fd337e77e47c/html5/thumbnails/88.jpg)
![Page 89: Kent Goldthorpe, President Paul Woods, Vice President ...€¦ · 2016. Project is part of ITD's Strategic Initiatives request for FY2021. ACHD with ITD on any improvement if funded](https://reader030.vdocuments.net/reader030/viewer/2022041118/5f2f3aeb5603fd337e77e47c/html5/thumbnails/89.jpg)
![Page 90: Kent Goldthorpe, President Paul Woods, Vice President ...€¦ · 2016. Project is part of ITD's Strategic Initiatives request for FY2021. ACHD with ITD on any improvement if funded](https://reader030.vdocuments.net/reader030/viewer/2022041118/5f2f3aeb5603fd337e77e47c/html5/thumbnails/90.jpg)
![Page 91: Kent Goldthorpe, President Paul Woods, Vice President ...€¦ · 2016. Project is part of ITD's Strategic Initiatives request for FY2021. ACHD with ITD on any improvement if funded](https://reader030.vdocuments.net/reader030/viewer/2022041118/5f2f3aeb5603fd337e77e47c/html5/thumbnails/91.jpg)
![Page 92: Kent Goldthorpe, President Paul Woods, Vice President ...€¦ · 2016. Project is part of ITD's Strategic Initiatives request for FY2021. ACHD with ITD on any improvement if funded](https://reader030.vdocuments.net/reader030/viewer/2022041118/5f2f3aeb5603fd337e77e47c/html5/thumbnails/92.jpg)
![Page 93: Kent Goldthorpe, President Paul Woods, Vice President ...€¦ · 2016. Project is part of ITD's Strategic Initiatives request for FY2021. ACHD with ITD on any improvement if funded](https://reader030.vdocuments.net/reader030/viewer/2022041118/5f2f3aeb5603fd337e77e47c/html5/thumbnails/93.jpg)
![Page 94: Kent Goldthorpe, President Paul Woods, Vice President ...€¦ · 2016. Project is part of ITD's Strategic Initiatives request for FY2021. ACHD with ITD on any improvement if funded](https://reader030.vdocuments.net/reader030/viewer/2022041118/5f2f3aeb5603fd337e77e47c/html5/thumbnails/94.jpg)
![Page 95: Kent Goldthorpe, President Paul Woods, Vice President ...€¦ · 2016. Project is part of ITD's Strategic Initiatives request for FY2021. ACHD with ITD on any improvement if funded](https://reader030.vdocuments.net/reader030/viewer/2022041118/5f2f3aeb5603fd337e77e47c/html5/thumbnails/95.jpg)
![Page 96: Kent Goldthorpe, President Paul Woods, Vice President ...€¦ · 2016. Project is part of ITD's Strategic Initiatives request for FY2021. ACHD with ITD on any improvement if funded](https://reader030.vdocuments.net/reader030/viewer/2022041118/5f2f3aeb5603fd337e77e47c/html5/thumbnails/96.jpg)
![Page 97: Kent Goldthorpe, President Paul Woods, Vice President ...€¦ · 2016. Project is part of ITD's Strategic Initiatives request for FY2021. ACHD with ITD on any improvement if funded](https://reader030.vdocuments.net/reader030/viewer/2022041118/5f2f3aeb5603fd337e77e47c/html5/thumbnails/97.jpg)
![Page 98: Kent Goldthorpe, President Paul Woods, Vice President ...€¦ · 2016. Project is part of ITD's Strategic Initiatives request for FY2021. ACHD with ITD on any improvement if funded](https://reader030.vdocuments.net/reader030/viewer/2022041118/5f2f3aeb5603fd337e77e47c/html5/thumbnails/98.jpg)
![Page 99: Kent Goldthorpe, President Paul Woods, Vice President ...€¦ · 2016. Project is part of ITD's Strategic Initiatives request for FY2021. ACHD with ITD on any improvement if funded](https://reader030.vdocuments.net/reader030/viewer/2022041118/5f2f3aeb5603fd337e77e47c/html5/thumbnails/99.jpg)
![Page 100: Kent Goldthorpe, President Paul Woods, Vice President ...€¦ · 2016. Project is part of ITD's Strategic Initiatives request for FY2021. ACHD with ITD on any improvement if funded](https://reader030.vdocuments.net/reader030/viewer/2022041118/5f2f3aeb5603fd337e77e47c/html5/thumbnails/100.jpg)
![Page 101: Kent Goldthorpe, President Paul Woods, Vice President ...€¦ · 2016. Project is part of ITD's Strategic Initiatives request for FY2021. ACHD with ITD on any improvement if funded](https://reader030.vdocuments.net/reader030/viewer/2022041118/5f2f3aeb5603fd337e77e47c/html5/thumbnails/101.jpg)
Attachment 8
City of Star 2016 Requests and ACHD Proposed Response
In IFYWP
(Page)DSN YR ROW YR CN YR
Total
Cost in
Millions
Programming Notes
Community Programs
1 1 CM‐215‐
04
Floating Feather Rd,
Munger Rd / Star Rd
Complete Floating Feather Rd with bike lanes, curb, gutter, borrow ditches,
and detached sidewalk on both sides between Munger Rd and Star Rd. Project
includes bridge #068.
Yes
(111)
PD PD PD $1.85
Project design still in preliminary development.
ACHD to evaluate potential advancement of
project phases during IFYWP update.
2 2 CM211‐
61
Plummer Rd Bridge
#16, 1700' N/O State
St (Plummer Rd, State
St / Pembridge Dr)
Replace/widen bridge #16 over Middleton Canal including sidewalk and bike
facility as part of ACHD's Bridge Maintenance Program.
No $0.53 Scoped "Go" in 2015. ACHD to evaluate
potential programming during IFYWP update.
Sidewalk exists the full length of the City
request with the exception of the bridge.
Sidewalk on the east side will be built through
development.
3 NEW Floating Feather Rd,
Brandon Rd /
Hornback Ave
Construct curb, gutter, and sidewalk on north side of Floating Feather Rd,
between Brandon Rd and Hornback Ave.
No TBD Prioritize and scope.
4 NEW Floating Feather Rd,
Hornback Ave /
Plummer Rd
Construct curb, gutter, and sidewalk on both sides of Floating Feather Rd,
between Hornback Ave and Plummer Rd.
No TBD Developing area. ACHD to coordinate with the
City on the scope and timing of improvements.
5 NEW Plummer Rd,
Streamfield St /
Floating Feather Rd
Construct curb, gutter, and sidewalk on the west side of Plummer Rd, between
Streamfield St and Floating Feather Rd.
No TBD Developing area. ACHD to coordinate with the
City on the scope and timing of improvements.
2016
City
Priority
Ranking
Current Programming Status
ACHD Proposed ResponseProject DescriptionACHD Project Name GIS #
2015
City
Priority
Ranking
PD ‐ Preliminary Development
CN ‐ Construction Year Page 1 of 1
![Page 102: Kent Goldthorpe, President Paul Woods, Vice President ...€¦ · 2016. Project is part of ITD's Strategic Initiatives request for FY2021. ACHD with ITD on any improvement if funded](https://reader030.vdocuments.net/reader030/viewer/2022041118/5f2f3aeb5603fd337e77e47c/html5/thumbnails/102.jpg)
1
Ryan Head
Subject: FW: Star transportation extra projects
From: Cathy Ward [mailto:[email protected]] Sent: Tuesday, March 29, 2016 6:12 PM To: Mitch Skiles Subject: Star transportation extra projects Hi Mitch, I can’t seem to find Brooks phone number to ask if we can add the four sidewalk projects to our transportation projects and I am leaving town tomorrow and won’t be back until next Tuesday – a little after the April 1st deadline. The list I have to add is: Floating Feather Road, Brandon Rd/Hornback Ave. Floating Feather Rd, Hornback Ave./Plummer Rd. Plummer Rd, State Street / Pembridge Drive Plummer Road, Streamfield Street/Floating Feather Road I wish I had more time, but would you forward these four to her please. I promise to do better next year! Thanks, Cathy
![Page 103: Kent Goldthorpe, President Paul Woods, Vice President ...€¦ · 2016. Project is part of ITD's Strategic Initiatives request for FY2021. ACHD with ITD on any improvement if funded](https://reader030.vdocuments.net/reader030/viewer/2022041118/5f2f3aeb5603fd337e77e47c/html5/thumbnails/103.jpg)
Attachment 9
West Ada School District 2016 Requests and ACHD Proposed Response
In IFYWP
(Page)DSN YR ROW YR CN YR
Total
Cost in
Millions
Programming Notes
Road & Intersection
1 2 IN215‐
13
Linder Rd and Saguaro
Dr
Signalize intersection. No TBD Defer. Location does not meet
traffic warrants for
signalization.
Location does not currently meet signal
warrants. ACHD Traffic Engineering to
reevaluate as conditions change in the area.
2 1 IN215‐
12
Linder Rd and Chateau
Dr
Install dedicated left turn lanes. No Done Done Done N/A Project is complete.
Community Programs
1 NEW W. 1st St at
Washington and
Carlton Ave at
Meridian Rd
Post school zone (20 MPH) speed limit signage. No TBD ACHD Traffic Engineering to evaluate potential
sign placement.
2 14 3341‐
00269
Moon Lake St and Inlet
Way
Painted crosswalk No N/A Traffic review in 2015 indicated that current
markings meet standards. ACHD Traffic to
review again to determine if conditions have
changed.
3 15 3341‐
00269
Braddock Dr at
Spalding STEM
Repaint faded crosswalks No N/A Traffic review in 2015 indicated that current
markings meet standards. ACHD Traffic to
review again to determine if conditions have
changed.
4 12 3341‐
00269
W 8th St and Meridian
Middle School
School Crossing Ahead signage on W. 8th St No TBD ACHD to coordinate with Meridian Police and
School District regarding parents parking in
bike lane.
5 16 3341‐
00269
Valley St and Lake
Hazel Middle School
Install pedestrian ramps and paint crosswalk at Lake Hazel Middle School
entrance on Valley St.
No TBD ACHD to coordinate improvement in 2016 with
in‐house resources.
6 17 3341‐
00269
Chateau Dr and
Barbara Morgan STEM
Repaint faded crosswalks No N/A Traffic review in 2015 indicated that current
markings meet standards. ACHD Traffic to
review again to determine if conditions have
changed.
7 NEW Pine St and W 1st St Repaint faded crosswalks No TBD ACHD Traffic Engineering to evaluate location
for repainting.
8 NEW Valley Heights Dr
Pedestrian Crossing
Painted crosswalk on Valley Heights Dr at the pedestrian pathway about 400
feet south of Lake Hazel Rd.
No TBD ACHD Traffic Engineering to evaluate location
for crossing.
9 18 3341‐
00269
McMillan Rd and
Lowell Scott Middle
School Parking Lot
"Do Not Block Intersection" signage and paint No TBD ACHD Traffic to monitor new intersection to
determine if warranted.
ACHD Proposed Response
2016 SD
Priority
Ranking
2015 SD
Priority
Ranking
GIS #ACHD Project Name
(City Project Name)Project Description
Current Programming Status
PD ‐ Preliminary Development
UF ‐ Unfunded
CN ‐ Construction Year Page 1 of 4
![Page 104: Kent Goldthorpe, President Paul Woods, Vice President ...€¦ · 2016. Project is part of ITD's Strategic Initiatives request for FY2021. ACHD with ITD on any improvement if funded](https://reader030.vdocuments.net/reader030/viewer/2022041118/5f2f3aeb5603fd337e77e47c/html5/thumbnails/104.jpg)
Attachment 9
In IFYWP
(Page)DSN YR ROW YR CN YR
Total
Cost in
Millions
Programming NotesACHD Proposed Response
2016 SD
Priority
Ranking
2015 SD
Priority
Ranking
GIS #ACHD Project Name
(City Project Name)Project Description
Current Programming Status
10 NEW Alley of Pine St,
between West 1st and
W 2nd
Install gate at the north end to restrict alley access to emergency vehicles and
pedestrians only.
No TBD ACHD to explore feasibility.
11 20 3341 Cloverdale Rd and
Spalding STEM
Additional speed limit signage due to cars speeding on overpass and do not
slow in school zone
No TBD ACHD Traffic Engineering to evaluate potential
improvement.
12 21 3341 Linder Rd, Chateau Dr
/ Barbara Morgan
STEM
Way finding signage on Linder. Renamed school has caused confusion. Signage
on Chateau installed in 2014
No TBD ACHD Traffic Engineering to coordinate with
School District on improvement.
13 NEW CM210‐
55
Black Cat Rd,
Moonlake Dr / Ustick
Rd (Black Cat Rd and
Moon Lake Dr
Pedestrian Signal)
Construct an asphalt pathway from the north west corner of Ustick and Black
Cat on the west side south to Moon Lake. Install an enhanced pedestrian signal
at or near Moon Lake Dr.
Yes
(105)
Done 2016 2016 $0.21 Under construction.
14 2 CM215‐
20
Floating Feather Rd
and Pimlico Dr
Pedestrian Crossing
Signalized pedestrian crossing. No $0.33 Scoped "Go" in 2015. ACHD to evaluate
potential programming during IFYWP update.
15 4 CM214‐
34
Hollandale Dr and
Pepper Ridge
Elementary Pedestrian
Signal
Install an enhanced pedestrian signal at Hollandale Dr and the entrance to
Pepper Ridge Elementary.
Yes
(113)
2018 2018 2019 $0.13 To be built in FY2019.
16 5 CM212‐
28
Locust Grove Rd,
Overland Rd / Puffin St
Detached asphalt or concrete pathway on east side of Locust Grove between
Puffin and Overland.
No $0.17 Scoped "Go" in 2014. ACHD to evaluate
potential programming during IFYWP update.
17 6 PPI208‐
91
Lake Hazel Rd,
Cloverdale Rd /
Lowland View Way
(Lake Hazel Rd,
Cloverdale Rd/Fruithill
Pl)
Construct asphalt pathway and extruded curb on both sides of Lake Hazel Rd,
between Cloverdale Rd and Lowland View Way. In‐house design.
Yes
(115)
Done 2016 2016 $0.23 To be built summer 2016.
18 NEW Linder Rd, Escalante Dr
/ Maricopa Dr
Construct curb, gutter, and sidewalk on Linder Rd, between Escalante Dr and
Maricopa Dr. Project requires the widening of Linder Rd Bridge #1022. (See
project request #30)
No TBD Prioritize and scope.
19 13 CM214‐
38
Musket Dr / Frontier
Elementary Crossing
Install painted crosswalk with ADA curbs on Musket Drive and the entrance to
Frontier School.
No N/A Per email from WASD dated
10/24/14, project no longer
needed.
Please confirm if request is still desired as this
request conflicts with previous direction from
the School District.
20 19 N/A Amity and Mary
McPherson
Elementary School
Pedestrian Signal
Signalized pedestrian crossing No N/A ACHD Traffic evaluation shows good vehicle
compliance with existing crossing. ACHD to
reevaluate if location meets warrants for
additional crossing treatments.
PD ‐ Preliminary Development
UF ‐ Unfunded
CN ‐ Construction Year Page 2 of 4
![Page 105: Kent Goldthorpe, President Paul Woods, Vice President ...€¦ · 2016. Project is part of ITD's Strategic Initiatives request for FY2021. ACHD with ITD on any improvement if funded](https://reader030.vdocuments.net/reader030/viewer/2022041118/5f2f3aeb5603fd337e77e47c/html5/thumbnails/105.jpg)
Attachment 9
In IFYWP
(Page)DSN YR ROW YR CN YR
Total
Cost in
Millions
Programming NotesACHD Proposed Response
2016 SD
Priority
Ranking
2015 SD
Priority
Ranking
GIS #ACHD Project Name
(City Project Name)Project Description
Current Programming Status
21 NEW W. 1st St and Carlton
Ave
Complete missing sidewalk gap at the corner of W. 1st St and Carlton Ave. No TBD Prioritize and scope.
22 NEW Locust Grove Rd,
Amity Rd /
Wrightwood Dr
Construct curb, gutter, and sidewalk on the west side of Locust Grove Rd,
between Amity Rd and Wrightwood Dr.
No TBD Prioritize and scope.
23 NEW Amity Rd, Margaret Ln
/ Locust Grove Rd
Construct curb, gutter, and sidewalk on both sides of Amity Rd, between
Margaret Ln and Locust Grove Rd
No TBD Prioritize and scope.
24 NEW McMillan Rd and
Leather Way
Pedestrian Crossing
Install an enhanced pedestrian signal at McMillan Rd and Leather Way. No TBD ACHD Traffic Engineering to determine if
location meets warrants.
25 NEW McMillan Elementary
School Zone
Modify existing flashing school zone beacons to relocate them on mastarms
over roadway to increase compliance.
No TBD ACHD Traffic Engineering to evaluate request.
School District should work with the Police
Department to enforce compliance of existing
school zone.
26 1 RD213‐
16
Linder Rd, Franklin Rd
/ Pine Ave (Linder Rd,
Railroad / Franklin Rd)
Widen Linder Road to 5 lanes with curb, gutter, sidewalk, and bike lanes in
accordance with the 2012 CIP. Project includes upgrade of the Union Pacific
Railroad crossing and bridge #131.
Yes (35) 2016 2017‐
2018
2019 $3.43 School District request for
sidewalk to be completed with
the road widening.
To be built in FY2019.
27 7 RD202‐
34
Ustick Rd, McDermott
Rd / Black Cat Rd
Widen Ustick Rd to 5 lanes with curb, gutter, sidewalk and bike lanes in
accordance with the 2012 CIP.
No $3.06 School district request for sidewalk will be
completed as part of the roadway widening
project. Pedestrian connectivity exists through
existing neighborhoods. Black Cat Rd,
Ustick/Moon Lake programmed.
28 8 RD207‐
33
Eagle Rd, Amity Rd /
Victory Rd
Widen Eagle Rd to 5 lanes with curb, gutter, sidewalk and bike lanes in
accordance with the 2012 CIP.
Yes (33) 2019 2020 PD $3.35 Programmed to begin design in FY2019. ACHD
to evaluate project construction moving
forward through IFYWP update. School district
request for sidewalk and a crosswalk at Eagle
and Rome will be considered as part of the
road widening project.
29 9 RD202‐
14
Cloverdale Rd, Franklin
Rd / Fairview Ave
Widen Cloverdale Rd to 5 lanes with curb, gutter, sidewalk and bike lanes, in
accordance with the Cloverdale Rd Concept Design and the 2012 CIP. Project
includes the Cloverdale/ Executive intersection.
Yes (31) Done Done 2016 $3.33 Under construction. School district request for
sidewalk will be completed as part of the road
widening project.
30 10 MA214‐
03
Linder Rd Bridge #1021
and #1022, 0.3 miles
N/O Hwy 44
Replace/widen bridge #1021 over the Middleton Mill Canal and bridge #1022
over the Foothills Ditch to accommodate pedestrian facilities and the future
widening of Linder Rd.
Yes (61) UF UF UF $1.05 Prioritize and scope.
31 11 RD207‐
12
Cloverdale Rd,
Overland Rd / Franklin
Rd
Widen road and overpass from 2 to 5 lanes with curb, gutter, sidewalk, and
bike lanes.
No $2.33 ACHD requested project from ITD in spring
2016. Project is not of ITD's bridge
replacement list and will not be developed at
this time. ACHD will continue to pursue project
with ITD.
PD ‐ Preliminary Development
UF ‐ Unfunded
CN ‐ Construction Year Page 3 of 4
![Page 106: Kent Goldthorpe, President Paul Woods, Vice President ...€¦ · 2016. Project is part of ITD's Strategic Initiatives request for FY2021. ACHD with ITD on any improvement if funded](https://reader030.vdocuments.net/reader030/viewer/2022041118/5f2f3aeb5603fd337e77e47c/html5/thumbnails/106.jpg)
Attachment 9
In IFYWP
(Page)DSN YR ROW YR CN YR
Total
Cost in
Millions
Programming NotesACHD Proposed Response
2016 SD
Priority
Ranking
2015 SD
Priority
Ranking
GIS #ACHD Project Name
(City Project Name)Project Description
Current Programming Status
32 NEW Lake Hazel Rd and Star
Struck Ave Pedestrian
Crossing
Painted crosswalk. No N/A To be built by in‐house forces in 2016.
PD ‐ Preliminary Development
UF ‐ Unfunded
CN ‐ Construction Year Page 4 of 4
![Page 107: Kent Goldthorpe, President Paul Woods, Vice President ...€¦ · 2016. Project is part of ITD's Strategic Initiatives request for FY2021. ACHD with ITD on any improvement if funded](https://reader030.vdocuments.net/reader030/viewer/2022041118/5f2f3aeb5603fd337e77e47c/html5/thumbnails/107.jpg)
West Ada School District Request Status and 2016 Prioritization
In IFYWP
(Page)DSN YR ROW YR CN YR
Total
Cost in
Millions
Programming Notes
Road & Intersection
1 2 IN215-
13
Linder Rd and Saguaro
Dr
Signalize intersection. No TBD Defer. Location does not meet
traffic warrants for
signalization.
WASD is requesting a traffic light at Linder Rd and Saguaro Dr. The request is in
response to increased traffic on Linder Road with the addition of North Star
Charter school we need a 4 way stop light for the traffic control during pick up
and drop off times (aproximately 8:15-8:45 AM; 12:00-12:15 PM; 12:45-1:00
PM; and 3:40-4:00PM). The crosswalk at this intersection will be used more as
the subdivisions are developed on the West side of Linder Road. For students
to be able to walk to Galileo there will need to be a light to stop traffic so the
students can cross safely at this intersection.
2 1 IN215-
12
Linder Rd and Chateau
Dr
Install dedicated left turn lanes. No Done Done Part Part Pavement widening complete.
Pavement striping to occur in
spring 2016.
WASD is requesting a turn signal installed at the current traffic light on Linder
Rd & W. Chateau Dr. As is, traffic turning from Linder onto W. Chateau must
yield to oncoming Linder traffic. During pick up and drop off times
(aproximately 8:15-8:45 AM; 12:00-12:15 PM; 12:45-1:00 PM; and 3:40-
4:00PM) traffic waiting to turn onto W. Chateau significantly backs up traffic
on Linder Rd. (both North bound and South bound).
Community Programs
1 New NW 1st St at W
Washington St and W
Carlton Ave at N
Meridian Rd
WASD is requesting 20mph speed limit signs be posted for Meridian
Elementary School.
2 14 3341-
00269
Moon Lake St and Inlet
Way
Painted crosswalk No N/A Traffic review in 2015
indicated that current
markings meet standards.
WASD is requesting to have the crosswalk repainted on N Moon Lake Street
and Inlet Way
3 15 3341-
00269
Braddock Dr at
Spalding STEM
Repaint faded crosswalks No N/A Traffic review in December
2015 indicated that current
markings meet standards.
WASD is requesting the crosswalk on W Braddock be repainted. It is faded and
difficult for cars to see on the road.
4 12 3341-
00269
W. 8th St and Meridian
Middle School
School Crossing Ahead signage on
W. 8th St
No TBD ACHD to coordinate with
Meridian Police and School
District regarding parents
parking in bike lane.
WASD is requesting a School Crossing Ahead sign be added for northbound
traffic on W 8th St prior to the crosswalk.
5 16 3341-
00269
Valley St and Lake
Hazel Middle School
Install pedestrian ramps and paint
crosswalk at Lake Hazel Middle
School entrance on Valley St.
No TBD ACHD to coordinate
improvement in 2016 with in-
house resources. WASD is requesting a crosswalk for students to cross Valley St at the school
entrance.
6 17 3341-
00269
Chateau Dr and
Barbara Morgan STEM
Repaint faded crosswalks No N/A Traffic review in December
2015 indicated that current
markings meet standards.
WASD is requesting the crosswalk be repainted for students to cross W
Chateau Dr at the school entrance.
7 New W Pine St at NW 1st St Painted crosswalk WASD is requesting the crosswalk be repainted for students to cross. The
current paint is no longer easily visible or reflective.
Instructions - Please insert your agency's ranking for each project in the column "2016 City Priority Ranking". Please add any additional comments or information in the last column. The remaining columns are for your information to
Additional Project Specific City Input
2016
City
Priority
Ranking
2015
City
Priority
Ranking
GIS #
ACHD Project Name
(School District
Project Name)
Project Description
Current Programming Status
PD - Preliminary Development
UF - Unfunded
CN - Construction Year Page 1 of 5
![Page 108: Kent Goldthorpe, President Paul Woods, Vice President ...€¦ · 2016. Project is part of ITD's Strategic Initiatives request for FY2021. ACHD with ITD on any improvement if funded](https://reader030.vdocuments.net/reader030/viewer/2022041118/5f2f3aeb5603fd337e77e47c/html5/thumbnails/108.jpg)
In IFYWP
(Page)DSN YR ROW YR CN YR
Total
Cost in
Millions
Programming NotesAdditional Project Specific City Input
2016
City
Priority
Ranking
2015
City
Priority
Ranking
GIS #
ACHD Project Name
(School District
Project Name)
Project Description
Current Programming Status
8 New S Valley Heights Dr
about 400ft south of
W Lake Hazel Rd
Painted crosswalk WASD is requesting to have a crosswalk added on S Valley Heights Dr adjacent
to the neighborhood walkway at the corner of Portola and Red Shine (walkway
is parcel # R3526470080) for Lake Hazel ES. There is currently a crosswalk at W
Napia St that is unsafe due to the curve in Valley Heights and inattentive
drivers.
9 18 3341-
00269
McMillan Rd and
Lowell Scott Middle
School Parking Lot
"Do Not Block Intersection" signage
and paint
No TBD ACHD Traffic to monitor new
intersection to determine if
warranted.
WASD is requesting “Do not block the intersection” signage and road paint at
the McMillan Rd and the new LSMS parking lot, so traffic can safely get out of
the parking lot and onto McMillian. It is difficult to turn right to get across to
the shared turned lane. Turning left can be dangerous for students who use
the crosswalk.
10 New Alley off Pine Ave
between W 2nd St and
NW 1st St
WASD is requesting this alley be gated south of parcel R6066000130 and only
made accessible to pedestrian and emergency vehichles. The alley has low
visibility on the corner of Pine due to the trees on either side (on private
property). The alley has no signage warning cars to look for children and other
pedestrians walking down Pine Ave sidewalks.
11 20 3341 Cloverdale Rd and
Spalding STEM
Additional speed limit signage due
to cars speeding on overpass and do
not slow in school zone
No TBD ACHD Traffic Engineering to
evaluate potential
improvement.
WASD is requesting more speed limit signs. Cars speed over the overpass
through the school zone, and not all cars stop at the
flashing light/crosswalk.
12 21 3341 Linder Rd, Chateau Dr
/ Barbara Morgan
STEM
Way finding signage on Linder.
Renamed school has caused
confusion. Signage on Chateau
installed in 2014
No TBD ACHD Traffic Engineering to
coordinate with School District
on improvement.
WASD is requesting signage on Linder and Chateau directing traffic to or
identifying the location of Barbara Morgan Stem Academy Elementary. The
school used to be Linder Elementary and was recently renamed when it
became a magnet school. The address is 1825 W Chateau Drive, Meridian, ID
13 New Black Cat and Moon
Lake St
Painted crosswalk WASD is requesting to have a crosswalk with HAWK light added on Black Cat at
Moon Lake St. There is a large development on the west side of Black Cat that
could be added to the walk zone and potenially eliminate 1 bus at Pondersosa
ES.
14 2 CM215-
20
Floating Feather Rd
and Pimlico Dr
Pedestrian Crossing
Signalized pedestrian crossing. No TBD Scoped Fall 2015. Final report
pending. WASD is requesting a HAWK light be installed in front of Eagle Middle School
at the cross walk of W Floating Feather Rd and N Pimlico Dr. There are
approximately 140 students in the walk zone that could utilize the cross walk
around approximately 8:00 AM and 3:15 PM.
15 4 CM214-
34
Hollandale Dr and
Pepper Ridge
Elementary Pedestrian
Signal
Install an enhanced pedestrian
signal at Hollandale Dr and the
entrance to Pepper Ridge
Elementary.
Yes
(113)
2018 2018 2019 $0.13 WASD is requesting a HAWK light at West Hollandale Drive and the entrance to
Pepper Ridge Elementary or a 20 MPH zone with flashing school traffic lights.
Literally hundreds of student cross at the crosswalk at school start and end
times (aproximately 8:15-8:45 AM; 12:00-12:15 PM; 12:45-1:00 PM; and 3:40-
4:00PM). Congestion will increase because of new building within the
immediate area.
16 5 CM212-
28
Locust Grove Rd,
Overland Rd / Puffin St
Detached asphalt or concrete
pathway on east side of Locust
Grove between Puffin and
Overland.
No $0.17 Scoped "Go" 2014. Awaits
programming. WASD is requesting a concrete sidewalk or an asphalt temporary path to
connect the missing section on Locust Grove just south of Overland to Puffin.
There is about a 200 foot gap in the sidewalk.
PD - Preliminary Development
UF - Unfunded
CN - Construction Year Page 2 of 5
![Page 109: Kent Goldthorpe, President Paul Woods, Vice President ...€¦ · 2016. Project is part of ITD's Strategic Initiatives request for FY2021. ACHD with ITD on any improvement if funded](https://reader030.vdocuments.net/reader030/viewer/2022041118/5f2f3aeb5603fd337e77e47c/html5/thumbnails/109.jpg)
In IFYWP
(Page)DSN YR ROW YR CN YR
Total
Cost in
Millions
Programming NotesAdditional Project Specific City Input
2016
City
Priority
Ranking
2015
City
Priority
Ranking
GIS #
ACHD Project Name
(School District
Project Name)
Project Description
Current Programming Status
17 6 PPI208-
91
Lake Hazel Rd,
Cloverdale Rd /
Lowland View Way
(Lake Hazel Rd,
Cloverdale Rd/Fruithill
Pl)
Construct asphalt pathway and
extruded curb on both sides of Lake
Hazel Rd, between Cloverdale Rd
and Lowland View Way. In-house
design.
Yes
(115)
Done 2016 2016 $0.23
WASD is requesting a portion of sidewalk completed between Cloverdale and
Lowland View Way on Lake Hazel Road. We could eliminate approximately 2
busses by increasing the Lake Hazel ES walk zone.
18 New Linder Road between
W Maricopa Dr and W
Escalante Dr
WASD is requesting contiguos sidewalks. This bridge does not have a walk path
for students to cross the bridge safely without walking in the narrow street.
There is a large new development on the west side of Linder. If the canal is
closed off and the road has sidewalks, we can potentially reduce 1 bus.
19 13 CM214-
38
Musket Dr / Frontier
Elementary Crossing
Install painted crosswalk with ADA
curbs on Musket Drive and the
entrance to Frontier School.
No N/A Per email from WASD dated
10/24/14, project no longer
needed.
WASD is requesting a painted crosswalk with ADA curbs on Musket Drive and
the entrance to Frontier Elementary School. remove?
20 19 N/A Amity and Mary
McPherson
Elementary School
Pedestrian Signal
Signalized pedestrian crossing No N/A ACHD Traffic evaluation shows
good vehicle compliance with
existing crossing. ACHD to
reevaluate at a later date.
WASD is requesting an Hawk crossing light at the existing school crosswalk.
Traffic is increasing and the road is 45 mph. Student attendance will be
increasing with two new subdivisions and a new apartment complex feeding
into our school.
21 New NW 1st St at W Carlton
Ave
WASD is requesting the sidewalk be finished at the corner on NW 1st St. The
sidewalk was demolished during a costruction project, and then never
replaced.
22 New S Locust Grove
between E
Wrightwood Dr and E
Amity Rd
WASD is requesting sidewalks be added to the west side of Locust Grove. The
new devlopement at S Locust Grove and E Wrightwood Dr as well as the
existing Pitkin and S Ramona neighborhood would benefit from contiguous
sidewalks to Mary McPherson.
23 New Amity Rd. between
Locust Grove and
Margaret Lane
WASD is requesting sidewalks be added to both sides of Amity Rd between
Locust Grove and Margaret Ln. The new devlopement at S Locust Grove and E
Wrightwood Dr as well as the existing Pitkin and S Ramona neighborhood
would benefit from contiguous sidewalks to Mary McPherson.
24 New McMillan Rd. and
Leather Way.
Signalized pedestrian crossing WASD is requesting to have a HAWK light added to the crosswalk on McMillan
Rd at Leather Way. Traffic on McMillan moves very quickly despite the 20mph
speed limit and poses a great danger to the crossing guard and students. There
are approximately 90 Gateway ES students who could be utilizing that
crosswalk.
25 New McMillan Rd between
N Farrow St and N Five
Mile Rd
WASD is requesting an enhanced flashing speed limit system at the two ends
of the school zone that hangs out over the street. The current lights are on the
sides of the street and trafic tends to ignore them. There are potentially
hundreds of students walking down McMillan to get to Gateway ES each
morning, midday, and afternoon. These students are in danger if traffic does
not notice the speed limit signs.
PD - Preliminary Development
UF - Unfunded
CN - Construction Year Page 3 of 5
![Page 110: Kent Goldthorpe, President Paul Woods, Vice President ...€¦ · 2016. Project is part of ITD's Strategic Initiatives request for FY2021. ACHD with ITD on any improvement if funded](https://reader030.vdocuments.net/reader030/viewer/2022041118/5f2f3aeb5603fd337e77e47c/html5/thumbnails/110.jpg)
In IFYWP
(Page)DSN YR ROW YR CN YR
Total
Cost in
Millions
Programming NotesAdditional Project Specific City Input
2016
City
Priority
Ranking
2015
City
Priority
Ranking
GIS #
ACHD Project Name
(School District
Project Name)
Project Description
Current Programming Status
26 1 RD213-
16
Linder Rd, Franklin Rd
/ Pine Ave (Linder Rd,
Railroad / Franklin Rd)
Widen Linder Road to 5 lanes with
curb, gutter, sidewalk, and bike
lanes in accordance with the 2012
CIP. Project includes upgrade of the
Union Pacific Railroad crossing and
bridge #131.
Yes (35) 2016 2017-
2018
2019 $3.43 School District request for
sidewalk to be completed with
the road widening.
WASD is asking for the sidewalks to be connected on either side of the road
and a better crossing for pedestrians on the railroad tracks
27 7 RD202-
34
Ustick Rd, McDermott
Rd / Black Cat Rd
(Ustick Rd, West of
Black Cat Rd)
Widen Ustick Rd to 5 lanes with
curb, gutter, sidewalk and bike lanes
in accordance with the 2012 CIP.
No $3.06 School district request for
sidewalk will be completed as
part of the roadway widening
project. Pedestrian
connectivity exists through
existing neighborhoods. Black
Cat Rd, Ustick/Moon Lake
programmed.
To the west on Ustick Road at Black Cat Road sidewalks and crosswalks need
to be completed, along with ditch and canal safeguards. If the area to the
west was completed, this would accommodate approximately 193 students.
This could eliminate approximately five buses.
28 8 RD207-
33
Eagle Rd, Amity Rd /
Victory Rd (Eagle Rd,
Victory Rd /
Kingsbridge Dr)
Widen Eagle Rd to 5 lanes with curb,
gutter, sidewalk and bike lanes in
accordance with the 2012 CIP.
Yes (33) 2019 2020 PD $3.35 School district request for
sidewalk and a crosswalk at
Eagle and Rome will be
considered as part of the road
widening project.
WASD is requesting continuous sidewalk on the east side of S Eagle Rd
between E Victory Rd and the canal (north of Kingsbridge), a crosswalk from
east side of S Eagle Rd to the north side of E Rome Dr, and continuous sidewalk
on the west side of S Eagle Rd from S Milan Ave to E Rome Dr.
29 9 RD202-
14
Cloverdale Rd, Franklin
Rd / Fairview Ave
(Cloverdale Rd,
Fairview Ave/Pine Ave)
Widen Cloverdale Rd to 5 lanes with
curb, gutter, sidewalk and bike
lanes, in accordance with the
Cloverdale Rd Concept Design and
the 2012 CIP. Project includes the
Cloverdale/ Executive intersection.
Yes (31) Done Done 2016 $3.33 School district request for
sidewalk will be completed as
part of the road widening
project.
WASD is requesting a continuous sidewalk on the east side of N. Cloverdale
Road, along with fixing the northeast corner of N. Cloverdale Road and
Executive Drive with a sidewalk, and a continuous sidewalk on N. Dawn Drive
from Sunnydale Lane to W. Irving St. would increase the walk zone for the
students traveling from the north and east. This would eliminate two buses
for approximately 127 students for Lewis and Clark Middle School. Continuing
the sidewalk on the north side of E. Executive Drive east of E. Cloverdale Road
to Meadowland would extend the walk zone further for students.
30 10 MA214-
03
Linder Rd Bridge #025
and #026, 0.3 miles
N/O Hwy 44 (Linder Rd
and State St)
Replace/widen bridge #025 over the
Middleton Mill Canal and bridge
#026 over the Foothills Ditch to
accommodate future widening of
Linder Rd.
Yes (61) UF UF UF $1.05 School district request for
sidewalk will be completed as
part of the bridge project. WASD is requesting improvements to the bridge over the canal on Linder road
just north of State Street and just south of Galileo Elementary. This bridge is
narrow and does not have a sidewalk or good path on which to cross.
31 11 RD207-
12
Cloverdale Rd,
Overland Rd / Franklin
Rd (Cloverdale Rd I-84
Overpass)
Widen road and overpass from 2 to
5 lanes with curb, gutter, sidewalk,
and bike lanes.
No $2.33 ACHD requested project from
ITD in fall 2015. Project is not
of ITD's bridge replacement list
and will not be developed at
this time. ACHD will continue
to pursue project with ITD.
WASD is requesting a sidewalk or bike walk over the Cloverdale Overpass
PD - Preliminary Development
UF - Unfunded
CN - Construction Year Page 4 of 5
![Page 111: Kent Goldthorpe, President Paul Woods, Vice President ...€¦ · 2016. Project is part of ITD's Strategic Initiatives request for FY2021. ACHD with ITD on any improvement if funded](https://reader030.vdocuments.net/reader030/viewer/2022041118/5f2f3aeb5603fd337e77e47c/html5/thumbnails/111.jpg)
In IFYWP
(Page)DSN YR ROW YR CN YR
Total
Cost in
Millions
Programming NotesAdditional Project Specific City Input
2016
City
Priority
Ranking
2015
City
Priority
Ranking
GIS #
ACHD Project Name
(School District
Project Name)
Project Description
Current Programming Status
32 NEW Lake Hazel Rd an S Star
Struck Ave
Painted crosswalk
WASD is requesting a painted crosswalk at the intersection. This would allow
elementary, middle, and high school age students to cross the street more
safely to access bus stops. The crosswalk would be in use for students between
the hours of 6:00 am and 8:30am and 3:00pm to 5:00pm.
PD - Preliminary Development
UF - Unfunded
CN - Construction Year Page 5 of 5